+ All Categories
Home > Documents > TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report...

TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report...

Date post: 04-Apr-2020
Category:
Upload: others
View: 3 times
Download: 0 times
Share this document with a friend
207
NSL TIDONG POWER GENERATION (P) LTD. NSL TIDONG POWER GENERATION (P) LTD. TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – 1x50MW) District Kinnaur, Himachal Pradesh (India) DETAILED PROJECT REPORT (VOLUME I: MAIN REPORT) (VOLUME I: MAIN REPORT) NSL Tidong Power Generation Pvt Ltd. NSL ICON, 4 th Floor, 8-2-684/2/A Road No:12, Banjara Hills Hyderabad 500034 February 2015 Indo Canadian Consultancy Services Limited Bhilwara Towers, A-12, Sector-1, Noida – 201301 Website : www.iccspower.com Consultant : Hyderabad - 500034
Transcript
Page 1: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

NSL TIDONG POWER GENERATION (P) LTD.NSL TIDONG POWER GENERATION (P) LTD.

TIDONG-I HYDRO ELECTRIC PROJECT

(PHASE II – 1x50MW)District Kinnaur, Himachal Pradesh (India)

DETAILED PROJECT REPORT(VOLUME I: MAIN REPORT)(VOLUME I: MAIN REPORT)

NSL Tidong Power Generation Pvt Ltd.NSL ICON, 4th Floor, 8-2-684/2/ARoad No:12, Banjara HillsHyderabad 500034

February 2015

Indo Canadian Consultancy Services Limited

Bhilwara Towers, A-12, Sector-1, Noida – 201301

Website : www.iccspower.com

Consultant :

Hyderabad - 500034

Page 2: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

NSL TIDONG POWER GENERATION (P) LTD.NSL TIDONG POWER GENERATION (P) LTD.

TIDONG-I HYDRO ELECTRIC PROJECT

(PHASE II – 1x50MW)(PHASE II 1x50MW)District Kinnaur, Himachal Pradesh (India)

DETAILED PROJECT REPORT(VOLUME I MAIN REPORT)(VOLUME I: MAIN REPORT)

NSL Tidong Power Generation Pvt Ltd.NSL ICON, 4th Floor, 8-2-684/2/ARoad No:12, Banjara HillsHyderabad 500034

February 2015

Indo Canadian Consultancy Services Limited

Bhilwara Towers, A-12, Sector-1, Noida – 201301

Website : www.iccspower.com

Consultant :

Hyderabad - 500034

Page 3: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd.

TIDONG-I PHASE-II HYDRO ELECTRIC PROJECT

DETAILED PROJECT REPORT

VOLUME I

: MAIN REPORT

VOLUME II

: DRAWINGS

Page 4: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents

Indo Canadian Consultancy Services Ltd. 1 P-1143

Table of Contents

BIBLIOGRAPHY OF ABBREVIATIONS ................................................................................................ 6

CHECK LIST ........................................................................................................................................... 8

SALIENT FEATURES ........................................................................................................................... 16

1 INTRODUCTION ........................................................................................................................ 22 1.1 General ............................................................................................................................... 22 1.2 Present Study For Additional Unit of 50 MW of Tidong –I, Phase - II ............................... 24 1.3 Proposed scheme ............................................................................................................... 24

2 PROJECT SUMMARY ................................................................................................................ 26 2.1 General ............................................................................................................................... 26 2.2 Main Components ............................................................................................................... 26

2.2.1 Diversion works ........................................................................................................... 26 2.2.2 Head Regulator ........................................................................................................... 27 2.2.3 Desilting Basin ............................................................................................................. 27 2.2.4 Reservoir ..................................................................................................................... 27 2.2.5 Head Race Tunnel ...................................................................................................... 27 2.2.6 Surge Shaft ................................................................................................................. 28 2.2.7 Valve House ................................................................................................................ 28 2.2.8 Pressure Shaft ............................................................................................................. 28 2.2.9 Power House Complex ................................................................................................ 29 2.2.10 Tail Race Channel ....................................................................................................... 29

2.3 Transmission System .......................................................................................................... 29 2.3.1 Power Benefits ............................................................................................................ 30

2.4 Project Cost ........................................................................................................................ 30 2.5 Financial Aspects ................................................................................................................ 30

3 SOCIO-ECONOMIC SCENE OF HIMACHAL PRADESH .......................................................... 31 3.1 General ............................................................................................................................... 31 3.2 People, Culture And Religion Of Himachal Pradesh .......................................................... 32

3.2.1 The People .................................................................................................................. 32 3.2.2 The Dress .................................................................................................................... 33 3.2.3 Houses and Equipment ............................................................................................... 34 3.2.4 Cuisine of Himachal Pradesh ...................................................................................... 35 3.2.5 Religion ....................................................................................................................... 36 3.2.6 Monasticism ................................................................................................................ 36 3.2.7 Festivals ...................................................................................................................... 37 3.2.8 Music and Dance ......................................................................................................... 37 3.2.9 Language .................................................................................................................... 38

3.3 Geographical Features Of Himachal Pradesh .................................................................... 38 3.3.1 Location ....................................................................................................................... 38 3.3.2 Climate ........................................................................................................................ 38 3.3.3 Hills .............................................................................................................................. 39 3.3.4 Valleys ......................................................................................................................... 39 3.3.5 Glaciers, Rivers & Lakes ............................................................................................. 39 3.3.6 Flora & Fauna .............................................................................................................. 40 3.3.7 Mineral Resources ...................................................................................................... 42 3.3.8 Soils ............................................................................................................................. 42

3.4 Demographic Profile of Himachal Pradesh ......................................................................... 42 3.5 Infrastructure Development Of Himachal Pradesh ............................................................. 43

3.5.1 Social Infrastructure .................................................................................................... 43 3.5.2 Access Infrastructure ................................................................................................... 45 3.5.3 Communications Infrastructure ................................................................................... 46

Page 5: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents

Indo Canadian Consultancy Services Ltd. 2 P-1143

3.5.4 Financial Infrastructure ................................................................................................ 46 3.5.5 Industrial Infrastructure ................................................................................................ 47

3.6 Status Of Industry In Himachal Pradesh ............................................................................. 47 3.6.1 Agriculture ................................................................................................................... 49 3.6.2 Animal Husbandary ..................................................................................................... 50 3.6.3 Livestock ..................................................................................................................... 51 3.6.4 Handicraft .................................................................................................................... 51 3.6.5 Textiles ........................................................................................................................ 52 3.6.6 Mineral-Based ............................................................................................................. 52 3.6.7 Power .......................................................................................................................... 52 3.6.8 Tourism ....................................................................................................................... 53 3.6.9 Pharmaceuticals .......................................................................................................... 53 3.6.10 Business Opportunities ............................................................................................... 54

3.7 Fact File For Kinnaur District .............................................................................................. 54 4 POWER SCENARIO .................................................................................................................. 58

4.1 General ............................................................................................................................... 58 4.2 Power Scenario ................................................................................................................... 61

4.2.1 Power Development in India ....................................................................................... 61 4.2.2 Power Planning Concept ............................................................................................. 61 4.2.3 Central Sector Participation ........................................................................................ 62 4.2.4 Power Sector Reforms in India ................................................................................... 62

4.3 Installed Capacity In The Country ....................................................................................... 62 4.4 Power Scenerio For Northern Region And Himachal Pradesh........................................... 63

4.4.1 Hydro Power Potentail in Northern Region ................................................................. 63 4.4.2 Status of Hydro and Thermal Power Projects in the Region ....................................... 64 4.4.3 Power Generation and Sales in Himachal Pradesh .................................................... 64 4.4.4 Power Consumption .................................................................................................... 67 4.4.5 Sector - Wise Energy Utilization For Himachal Pradesh ............................................. 67 4.4.6 Power Shortage in Northern India and Himachal Pradesh ......................................... 69

4.5 Status Of Rural Electrification In Himachal Pradesh .......................................................... 70 4.6 Requirement of Capacity Additions .................................................................................... 71

4.6.1 Resources for Power Development In Northern Region ............................................. 71 4.6.2 Power potential in the state of Himachal Pradesh – exploited and available ............. 72 4.6.3 Existing and under investigation hydro projects. ......................................................... 72

4.7 Participation By Private Sector In Development Of Hydro Projects ................................... 73 4.8 Clean Development Mechanism (CDM) ............................................................................. 74 4.9 Necessity Of The Project And Related Aspects ................................................................. 74

5 TOPOGRAPHICAL SURVEY AND INVESTIGATIONS ............................................................. 76 5.1 Introduction ......................................................................................................................... 76 5.2 Topographical Survey ......................................................................................................... 76

5.2.1 General layout ............................................................................................................. 76 5.2.2 Intake Area .................................................................................................................. 76 5.2.3 Head Race Tunnel ...................................................................................................... 76 5.2.4 Surge shaft and Pressure Shaft .................................................................................. 77 5.2.5 Powerhouse Site ......................................................................................................... 77 5.2.6 Approach roads ........................................................................................................... 77 5.2.7 Cross- Sections of Tidong khad .................................................................................. 77 5.2.8 Cross- Sections of Sutlej River ................................................................................... 77 5.2.9 Plan and L- Sections ................................................................................................... 77

6 HYDROLOGY ............................................................................................................................. 79 6.1 General ............................................................................................................................... 79

6.1.1 Introduction .................................................................................................................. 79 6.1.2 Project Location ........................................................................................................... 79

6.2 Basin Characteristics .......................................................................................................... 79 6.2.1 Major river Basin: Sutlej River Basin ........................................................................... 79 6.2.2 Tidong khad basin ....................................................................................................... 80

6.3 Climate ................................................................................................................................ 80

Page 6: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents

Indo Canadian Consultancy Services Ltd. 3 P-1143

6.4 Precipitation ........................................................................................................................ 81 6.5 Source Of Runoff ................................................................................................................ 83 6.6 Sediment Load .................................................................................................................... 83 6.7 Water Quality ...................................................................................................................... 84 6.8 Gauge & Discharge (G&D) Site .......................................................................................... 84 6.9 Discharge Measurements ................................................................................................... 84

6.9.1 Methodology ................................................................................................................ 84 6.10 Design Flood Discharge...................................................................................................... 85

6.10.1 Dicken’s Empirical Formula ......................................................................................... 85 6.10.2 Unit Hydrograph Method ............................................................................................. 86 6.10.3 Ryve’s Formula ........................................................................................................... 88 6.10.4 Design flood proposed to be adopted ......................................................................... 88

6.11 Discharge Data ................................................................................................................... 89 6.11.1 Available Discharge Data ............................................................................................ 89 6.11.2 Analysis of available data ............................................................................................ 89

6.12 Flow Duration Curve ........................................................................................................... 92 6.13 Further Study ...................................................................................................................... 93

7 GEOLOGY AND GEOTECHNICAL ASPECTS ........................................................................ 105 7.1 Introduction ....................................................................................................................... 105 7.2 Upstream Works ............................................................................................................... 105 7.3 Surge Shaft ....................................................................................................................... 106 7.4 T-Junction ......................................................................................................................... 106 7.5 Pressure Shaft (Adit-4) ..................................................................................................... 106 7.6 Powerhouse ...................................................................................................................... 106

8 POWER POTENTIAL STUDIES ............................................................................................... 111 8.1 General ............................................................................................................................. 111 8.2 Hydrological Data .............................................................................................................. 111 8.3 Head .................................................................................................................................. 113 8.4 Combined Turbine Generator Efficiencies of The Unit ..................................................... 113 8.5 Methodology For Power Potential Analysis ...................................................................... 113 8.6 Power Potential Analysis .................................................................................................. 114 8.7 Number Of Generating Units ............................................................................................ 115 8.8 Conclusion ........................................................................................................................ 116

9 CIVIL STRUCTURES & HYDRO-MECHANICAL EQUIPMENT ............................................... 118 9.1 General ............................................................................................................................. 118 9.2 Headworks At Upstream ................................................................................................... 118

9.2.1 Location ..................................................................................................................... 118 9.2.2 Design Flood ............................................................................................................. 118 9.2.3 Waterway .................................................................................................................. 119 9.2.4 Pond Level ................................................................................................................ 119 9.2.5 Undersluice Bay ........................................................................................................ 119 9.2.6 Spillway ..................................................................................................................... 119 9.2.7 Energy Dissipation .................................................................................................... 119 9.2.8 Protection Works ....................................................................................................... 120 9.2.9 Diversion channel ...................................................................................................... 120 9.2.10 Raft, Pier and Abutment ............................................................................................ 120 9.2.11 Vertical Lift Gates and Stoplogs ................................................................................ 121

9.3 Head Regulator ................................................................................................................. 122 9.4 Desilting Basin .................................................................................................................. 123 9.5 Storage Reservoir ............................................................................................................. 124 9.6 Head race tunnel (HRT) .................................................................................................... 124

9.6.1 Tunnel support system .............................................................................................. 125 9.6.2 Tunnel reach in very good rock ................................................................................. 125 9.6.3 Tunnel reach in Good rock ........................................................................................ 125 9.6.4 Tunnel reach in Fair rock........................................................................................... 125 9.6.5 Tunnel reach in Poor rock/Shear zone ...................................................................... 125 9.6.6 Tunnel Concrete Lining ............................................................................................. 126

Page 7: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents

Indo Canadian Consultancy Services Ltd. 4 P-1143

9.6.7 Grouting ..................................................................................................................... 126 9.7 Surge Shaft ....................................................................................................................... 126

9.7.1 Type........................................................................................................................... 126 9.7.2 Surge Shaft Supporting System ................................................................................ 126 9.7.3 Steel Lining ................................................................................................................ 127

9.8 Pressure Shaft .................................................................................................................. 127 9.9 Power house complex ....................................................................................................... 128 9.10 Tail Race Ducts And Channel ........................................................................................... 129 9.11 Transformer Hall, GIS And Control Room ........................................................................ 129 9.12 Additional Works Required For The 3rd Unit (Phase-II) ................................................... 129

10 POWER PLANT-ELECTRICAL & MECHANICAL WORKS .................................................. 131 10.1 General ............................................................................................................................. 131 10.2 Turbine -Capacity And Type ............................................................................................. 131 10.3 Main Turbine Parameters ................................................................................................. 134 10.4 Description Of Electromechanical Equipment .................................................................. 134

10.4.1 Turbine ...................................................................................................................... 134 10.4.2 Governor ................................................................................................................... 137 10.4.3 Main Inlet Valve (MIV) ............................................................................................... 138 10.4.4 Generator and excitation system .............................................................................. 138 10.4.5 Automation control, metering and protection ............................................................ 139 10.4.6 Station switching scheme and type of 220kV switching equipment .......................... 140 10.4.7 Transformers ............................................................................................................. 140 10.4.8 Electrical Auxiliaries .................................................................................................. 140 10.4.9 Mechanical auxiliaries ............................................................................................... 142

11 POWER EVACUATION ARRANGEMENTS ......................................................................... 144 11.1 Introduction ....................................................................................................................... 144 11.2 Load Demand ................................................................................................................... 144 11.3 Transmission Lines ........................................................................................................... 144 11.4 Identification Of Transmission System ............................................................................. 146 11.5 Power Evacuation From Tidong-I Phase-II HEP .............................................................. 147 11.6 Status Of Open Access/ Connectivity ............................................................................... 147

12 INFRASTRUCTURE FACILITIES ......................................................................................... 159 12.1 General ............................................................................................................................. 159 12.2 Access Roads And Strengthning Of Exesting Roads ....................................................... 159 12.3 Tele-Communication ......................................................................................................... 160 12.4 Construction Power ........................................................................................................... 161 12.5 Explosive Magazine .......................................................................................................... 161 12.6 Infrastructure For Phase – II Works .................................................................................. 161

13 CONSTRUCTION METHODOLOGY & EQUIPMENT PLANNING ....................................... 162 13.1 General ............................................................................................................................. 162

13.1.1 Surge Shaft ............................................................................................................... 163 13.1.2 Unit-3 Pressure Shaft ................................................................................................ 163 13.1.3 Power House and other outlet structures .................................................................. 163

14 CONSTRUCTION SCHEDULE ............................................................................................ 164 14.1 General ............................................................................................................................. 164

15 PROJECT ORGANIZATION ................................................................................................. 166 15.1 General ............................................................................................................................. 166 15.2 Project Organisation ......................................................................................................... 166 15.3 Functions And Responsibilities Of Project Team Members ............................................. 167

15.3.1 Senior Manager (Civil) ............................................................................................... 167 15.3.2 Senior Manager (Quality control) .............................................................................. 168 15.3.3 Senior Manager (Electrical and Mechanical Works) ................................................. 168

15.4 Need Based Units ............................................................................................................. 168 15.5 Project Planning And Monitoring ...................................................................................... 169 15.6 Finance & Accounts .......................................................................................................... 169 15.7 Project Administration ....................................................................................................... 169 15.8 Technical Advisory Committee ......................................................................................... 170

Page 8: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents

Indo Canadian Consultancy Services Ltd. 5 P-1143

15.9 Consultants ....................................................................................................................... 170 15.10 Reporting / Reviews ...................................................................................................... 170

16 ENVIRONMENTAL & ECOLOGICAL ASPECTS .............................................................................. 173 16.1 General ............................................................................................................................. 173 16.2 Submergence .................................................................................................................... 173 16.3 Effect on Climate ............................................................................................................... 174 16.4 Catchment area Treatment ............................................................................................... 174 16.5 Seismicity .......................................................................................................................... 174 16.6 Rehabilitation .................................................................................................................... 174 16.7 Other Preventative Measures ........................................................................................... 174

16.7.1 Restoration of construction areas and disposal of muck .......................................... 174 16.7.2 Anti Poaching Measures ........................................................................................... 174 16.7.3 Environmental Impact and Mitigation Measures ....................................................... 174

16.8 Benefits ............................................................................................................................. 175 16.9 Conclusion ........................................................................................................................ 176

17 COST ESTIMATE ................................................................................................................. 182 17.1 General ............................................................................................................................. 182 17.2 Basis of Cost Estimate ...................................................................................................... 182 17.3 Escalation in Cost ............................................................................................................. 182 17.4 Details of Cost Estimates .................................................................................................. 182 17.5 Estimated Cost Of The Project ........................................................................................ 184

18 FINANCIAL AND ECONOMIC EVALUATION ................................................................................... 200 18.1 General ............................................................................................................................. 200 18.2 Analysis Of The Major Assumptions ................................................................................. 200

18.2.1 Project Cost in Rs. Crores ......................................................................................... 201 18.2.2 Capital Structure in Rs Crores .................................................................................. 201 18.2.3 Debt Financing Terms ............................................................................................... 201 18.2.4 Plant Details .............................................................................................................. 201 18.2.5 Generation Details ..................................................................................................... 202 18.2.6 O & M ........................................................................................................................ 202 18.2.7 Working Capital ......................................................................................................... 202 18.2.8 Depreciation .............................................................................................................. 202 18.2.9 Tariff (Calculated as per CERC Norms) .................................................................... 202 18.2.10 Conclusion ............................................................................................................. 202

19 RECOMMENDATIONS ........................................................................................................ 203 19.1 General ............................................................................................................................. 203 19.2 Preliminary And Pre-Construction Works ......................................................................... 203 19.3 Recommendations ............................................................................................................ 204

Page 9: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Bibliography of Abbreviations

Indo Canadian Consultancy Services Ltd. 6 P-1143

BIBLIOGRAPHY OF ABBREVIATIONS

Amp - Ampere

BIL - Basic Insulation Level

CEA - Central Electricity Authority

cfm - Cubic feet per minute

Cts - Current Transformers

Cumecs - Cubic metre per second

cum - Cubic metre

d/s - Downstream

DEM - Digital Elevation Model

DPR - Detailed Project Report

DVC - Damodar Valley Corporation

El - Elevation

EOT - Electric Overhead Travelling

FRL - Full Reservoir Level

GIS - Geographical Information System

GSI - Geological Survey of India

Ha-m - Hectare metre

HFL - Highest Flood Level

HPSEB - Himachal Pradesh State Electricity Board

HPPWD Himachal Pradesh Public Work Department

HRT - Head Race Tunnel

HT - High Tension

Hz - Hertz

ID - Internal Diameter

IDC - Interest During Construction

IRR - Internal Rate of Return

Km - Kilometre

LAVT - Lightning Arrestor and Voltage Transformers

LT - Low Tension

m - Metre

Page 10: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Bibliography of Abbreviations

Indo Canadian Consultancy Services Ltd. 7 P-1143

MDDL - Minimum Draw Down Level

mkw - Metric Kilowatt

MVA - Mega Volt Ampere

MVAR - Mega Volt Ampere Reactive

MW - Mega Watt

MWL - Maximum Water Level

NJPC - Nathpa Jhakri Power Corporation

NLC - Neyvelli Lignite Corporation

NSL - Natural Surface Level

NTPC - National Thermal Power Corporation

OD - Outer Diameter

OPU - Oil Pressure Unit

PCC - Plain Cement Concrete

PCD - Pitch Circle Diameter

PFR - Pre-Feasibility Report

PLCC - Power Line Carrier Communication

PTs - Potential Transformers

Pu - Per Unit

RD - Reduced Distance

RITES - Rail India Technical & Engineering Services Ltd

RPM - Revolution per Minutes

sqm - Square metre

TWL - Tail Water Level

u/s - Upstream

UCB - Unit Control Board

XLPE - Cross Linked Polyethylene

Page 11: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Check List

Indo Canadian Consultancy Services Ltd. 8 P-1143

CHECK LIST SECTION-1 GENERAL AND HYDROLOGICAL

Remarks

1 Attach an index map (in the case of flood control scheme, the index map should show the flooded area for normal floods and the depth of flooding)

NA

2 Have hydrological meteorological and other data been collected in respect of following:

a) Map showing sub-divisions of catchment by tributaries, watersheds, rain gauge and temperature recording stations, gauge and discharge site, contour and isohyets.

Yes

b) Monthly and annual rain fall and temperature data for the catchment.

Yes

c) Average, maximum and minimum rainfall and temperatures.

Yes

d) Gauge and discharge data of tributaries and the main river.

Yes

e) Hydrographs of the river.

No

f) Maximum historical flood with hydrographs and designed maximum flood and its frequency.

No

g) Maximum, minimum and average annual run-off.

Yes

h) Hydrological studies to establish generally the availability of water for the benefits envisaged in the project.

Yes

i)

Suitability of water for irrigation, drinking etc. and treatment contemplated, where required.

N.A

j) Silt discharge, showing maximum, minimum and average silt intensities.

Enclose

k) The magnitude of the problem of soil erosion in the catchment area and the programme proposed for soil conservation measures.

Yes

l) Depth of sub soil water table in the command area and its seasonal variation.

N.A

m) Seismicity of the area.

Considered

3 Has basin wise development of the river been considered and the following information furnished?

a) A map showing the overall proposals for valley Yes

Page 12: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Check List

Indo Canadian Consultancy Services Ltd. 9 P-1143

development. b) Alternative proposals, discussing their merits and

demerits. Yes

c) Stages of development of the project and their salient features.

Yes

d) Extent to which the existing project will be assisted or affected.

N.A

e) Particulars of minor irrigation projects. N.A 4 Has reservoir data been collected completely and

the following information furnished?

a) Reservoir topography and area capacity curves.

N.A (Dam is not provided)

b) Probable rate of silting in the reservoir in comparison with silting of any existing reservoir.

N.A

c) Live storage, the numbers of years in that the reservoir completely fills, average annual utilization, evaporation losses, extra storage provided for carry from the year-to-year, if any.

Only Peaking Storage Contemplated

d) Working tables for the reservoir. N.A e) Flood absorption and flood routing. N.A f) Back water (tail water curves with bank levels). N.A g) Fetch of reservoir direction and velocity of winds

and free board. N.A

h) Malaria control. N.A i) Area to be submerged and its classification,

acquisition and compensation for land and properties.

18270sq-m (Artificial reservoir with all side closed boundaries)

j) Programme of resettlement of population displaced from the reservoir area

No displacement of Population

5 Head works (Weir)

Have the following aspects been discussed and shown on map.

a) Weir site and considerations leading to its preference over other sites.

Yes

b) Reservoir topography and area capacity curves. N.A c) Borrow area and quarries. Yes

d) Road and Railways existing and proposed. Yes e) Colonies, workshops and offices. Yes 6. Has a detailed survey map of the Weir site been

prepared showing the following?

a) All the natural features e.g. out-crops of rocks, springs etc.

Yes

b) Dam and appurtenant works Yes c) Site for construction plant e.g. crushing and

concreting plant, construction power plant, compressed air station etc.

Yes

7. Have geological investigations been made and a report showing the following submitted?

a) A brief account of regional geology, major rock types, effect of faulting etc. description of other structural features and their relation of water tightness and grouting proposals.

Yes

Page 13: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Check List

Indo Canadian Consultancy Services Ltd. 10 P-1143

b) Laboratory tests of samples of foundation materials and their interpretation.

Yes

c) Levels of ground water tables and discussions of percolation tests.

N.A

d) Reference to any special conditions affecting the preliminary designs.

Nil

8. Have the following Maps been included?

a) Combined topographical and geological map.

Yes

b)

Map showing bed map contours.

Yes

c) Logs of drill holes test pit exploratory tunnel etc.

Yes

d) Map profiles and station showing results of geophysical work or any other special methods.

Yes

e) Ground and aerial photographs, if available.

Ground Photographs

9. Have investigations of construction materials been made and report showing the following attached?

a) Various types of embankment materials e.g. pervious with quantities in various borrow areas.

Yes

b) Stone for riprap and rock fill. Yes c) Materials for stone masonry and concrete, fine and

coarse aggregates, with quantities and physical properties.

River borne material is to be used

d) Source of supply of cement. Yes e) Laboratory tests performed on item (a) to (d)

above. Yes

f) Haul roads for transport of construction material Yes g) Plan of borrows areas and quarries with trial pit

data.

Yes

10. Have the main structures and appurtenant works e.g. dam, spillway outlets, coffer dam etc been designed and the following appended?

a) General plan, upstream and downstream elevations showing natural ground levels, final excavation levels etc.

Yes

b) Foundation treatment and drainage.

Yes

c) Spillway and outlets with energy dissipation arrangements.

Yes

d) Maximum sections of overflow, non- overflow and earth dams.

Yes

e) Retaining and training walls.

Yes

Page 14: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Check List

Indo Canadian Consultancy Services Ltd. 11 P-1143

f) Galleries and other openings.

N.A

g) Gates, hoists and other control equipments.

Yes

h) Diversion works during construction etc.

Yes

i) Design calculation with list of assumptions made and factors of safety adopted, together with justification of the types of structures adopted.

Yes

SETION-II IRRIGATION

N.A

SECTION-III. POWER DEVELOPMENT

11. Have investigations been made and the following furnished?

a) Present position of power supply in the region, system load factor etc.

Yes

b)

Extent of firm power available from the scheme and also from the grid after commissioning of the plant (working tables and the basis of estimation of firm power should be supplied) .

Yes

c)

Load survey-giving details of major loads to be served, future peak and energy demands, anticipated system load factor.

Yes

d)

Proposed initial and ultimate installed capacities, number and size of generating units, numbers and capacity of turbines, power factor, efficiency etc. transformer capacity added at power station and sub-stations.

Yes

e)

Map showing the general layout of the schemes, including the dam, water conductor system, power house step up sub-stations and out-going transmission lines.

Yes

f) General map showing the transmission system, the location of the present /future principal loads.

Yes

g) Route miles of trunk and main line and distribution line with voltages under the scheme.

N.A

h) A note on the development of power in stages, if any.

N.A

i)

Proposed sources of coal, fuel etc and technical characteristic of fuel, costs per tonne and distance from location of power station to source of fuel.

N.A

Page 15: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Check List

Indo Canadian Consultancy Services Ltd. 12 P-1143

j) Have the coal commissioner and Railway been consulted in regard to supply to coal?

N.A

k) Proposed sources of cooling water

NA

l) Details of construction materials for hydro installations.

Yes

m)

In respect of distribution and rural electrification schemes, a list of small towns and villages (as per latest census) to be electrified.

N.A

SECTION-IV FLOOD CONTROL, DRAINAGE, ANTI WATER LOGGING

N.A

SECTION-V NAVIGATION, FISH CULTURE ETC.

N.A

SECTION-VI CONSTRUCTION PROGRAMME EQUIPMENT & MANPOWER

12. Has a construction programme been drawn up for the execution of the various components of the project with the following details?

a) Machinery and equipment available together with the proposed requirements.

Yes

b) The quantities or material involved together with the daily out-turn proposed for major items like masonry, concrete or earthwork.

Yes

c) Yearly requirement of cement, steel and other essential materials.

Yes

d) Synchronization in the construction of head works canal system including distributaries, minors and water course, field channels (by the beneficiaries) and implementation activities to ensure phase realization of maximum benefits

N.A

e) Synchronization of generation facilities with completion of transmission system.

Yes

f) Justification of the construction programme adopted.

Yes

g) Have charts been furnished showing the construction programme and targets diagrammatically for the various components of the projects?

Yes

Page 16: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Check List

Indo Canadian Consultancy Services Ltd. 13 P-1143

SECTION-VII ESTIMATE AND ANALYSIS OF RATES

Yes

13. Have project estimates of cost together with abstract of quantities and costs for various components of the project been made and following details furnished?

a) Estimated cost of the various stages of the project and the foreign exchange components thereof.

Yes

b) The year to which the rates adopted in the estimate pertain.

December 2014

c) Allocated costs of irrigation, power, flood control, navigation and other purpose served by the project, as considered equitable by the state Govt.

N.A

14. Have analysis of rates been made and following details furnished?

a) Labour out turns for various items

Yes

b) Material required for unit quantities of items of work.

Yes

c) The current schedule of rates in the area and rates proposed, comparison with rates obtained on similar works.

Item rates analyzed from first principle

SECTION-VIII FINANCIAL RETURNS AND BENEFITS

15. Has the financial aspect of the project been discussed and the following details furnished?

a) The phased or year wise programme of expenditure on the various units of the project, in foreign exchange and in rupees.

Yes

b) The phased or year wise programme of development of irrigation, power, navigation etc.

Yes

c) Present and proposed power tariff rates for different categories of consumers.

Yes

d) Compulsory irrigation cess proposed.

N.A

e) Scale of water rates proposed for the various N.A

Page 17: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Check List

Indo Canadian Consultancy Services Ltd. 14 P-1143

crops, comparison with rates prevailing on existing projects in the region/states.

f) Betterment levy proposed.

N.A

g) Comparison of above rates with the rates proposed for other projects in the state.

N.A

h) Comments of the state Revenue Department in regard to the rates of betterment levy, water rates compulsory irrigation cess, flood cess etc.

N.A

i) Statement of gross revenue from the different functions of the project.

Yes

J) Statement showing maintenance and establishment cost interest charges and net revenue.

Yes

k) Cost per Kwh of generation giving details of interest charges, depreciation and working expenses on which the estimate is based.

Yes

l) Capital cost per acre of annual gross irrigated area.

N.A

m) Productiveness of the project in terms of percentage of financial return.

Yes

i. At the end of the 10th year after completion.

Yes

ii. On full development.

Yes

iii. When the entire revenue from betterment levy anticipated has been realized.

Yes

n) Special grounds for undertaking an unproductive project and specific concurrence of the state finance department thereof.

N.A.

16. Have total direct and indirect benefits of the project been started in respect of the following?

a) Irrigation N.A

b) Power Yes

c) Flood control N.A

d) Navigation N.A

e) Employment Yes

Page 18: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Check List

Indo Canadian Consultancy Services Ltd. 15 P-1143

f) Other facilities N.A

SECTION-IX PUBLIC CO-OPERATION AND PARTICIPATION

17. Have the following aspects been discussed and information furnished?

a) The degree of public co-operation and participation expected for the project.

N.A

b) View and attitude of the beneficiaries about the advantage from the project and in respect of water rates betterment levy, irrigation cess etc.

N.A

SECTION-X INTERSTATE ASPECTS

a) Are the inter-state aspects involved? If so, the details about the same may be mentioned together with the latest views of the state concerned.

N.A

SECTION-XI EMPLOYMENT AND TRAINING

18 Have the following aspects been discussed and information furnished?

a) Yearly employment during construction (approx) by categories

Yes

b) Personnel required to be retained under above categories after completion of the project (approx)

Yes

Page 19: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Salient Features

Indo Canadian Consultancy Services Ltd. 16 P-1143

SALIENT FEATURES 1. LOCATION

State : Himachal Pradesh

District : Kinnaur

Stream : Tidong, a tributary of Sutlej river

Vicinity : Near Reckong Peo town.

Longitude : 78 22’ 10”E to 78 47’ 50”E

Latitude : 31 20’ 30” N to 31 33’ 30” N

2. HYDROLOGY

Catchment area at diversion : 497.86 km2

Design Flood (50 year Return period) : 405 cumec.

3. RIVER DIVERSION (During Construction)

Type : Diversion Channel

Length : 210.00m

Size & shape : 9m (W)x 2 (D), Rectangular

4. DIVERSION BARRAGE

A. Spillway

Type : Non Gated

Maximum Water level : 2889.40 m

Average river bed level at barrage axis : 2880.00m

Crest level of Spillway bays : 2881.75 m

Bridge deck level : 2890.40 m

No. of Spillway bays : 1

Width of bay : 20.0 m

Energy Dissipation System : Stilling Basin

B. Undersluice

Type : 2 Nos, Vertical Lift Gate(5m x 3 m size)

Maximum Water level : 2889.40 m

Average river bed level : 2880.00 m

Crest level of undersluice : 2875.50 m

Bridge deck level : 2890.40 m

Width of undersluice portion : 12.00 m

No. of undersluice bays : 2

Width of each bay : 5.0 m

Page 20: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Salient Features

Indo Canadian Consultancy Services Ltd. 17 P-1143

Energy Dissipation System : Stilling Basin.

C. Head regulator

Type : 2Nos.Vertical lift gates, 3.6 m x 4.35m

Maximum Water level : 2889.40 m

Average river bed level : 2880.00 m

Crest level of Head Regulator : 2877.40 m

Bridge deck level : 2890.40 m

No. of bays : 2

Width of bay : 3.6 m

Energy Dissipation System : Stilling Basin.

D. Tunnel Intake Structure

Type : Rectangular bell mouth entrance, Non

gated

Sill level : 2853.00m

Trash rack : Vertical (3 panels)

Design Discharge : 28.65 Cumecs

5. DESILTING BASINS

Type : Surface desilting basins

No. & Size of desilting trough : 2 Nos., 80.5 m x 9.50 m x 9.15 m

Particle size to be excluded : 0.20 mm and above

Design discharge : 35 cumec

Flow through velocity : 0.2 m/s

Flushing velocity : 6 m/sec.

Gates opening for flushing conduit : 2 Nos.Vertical lift gates, 2.5 m x 1.5 m

6. RESERVOIR

Capacity : 3 Hours peaking (265000m3)

FRL : 2873.75 m

MDDL : 2860.75m

Reservoir bed level : 2860.00m

Page 21: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Salient Features

Indo Canadian Consultancy Services Ltd. 18 P-1143

7. HEAD RACE TUNNEL

Type and Size

RD 0 to RD 2130

RD 2130 to RD 8409

RD 8409 to RD 8504

3.5m x 3.5m, Concrete Lined, D-shaped

3.5m x 3.9m, Concrete Lined, D-shaped

2.5m dia Circular steel lined

Velocity : 2.62 m/s & 2.32 m/s

Length : 8504 m

Design discharge : 28.65 cumec.

Slope : 1 in 162

8. ADITS

Type and Size : D – Shaped

To HRT (RD-2140) : Adit-1: 245 m long, 5.5m x 5.5m

To HRT, Surge Shaft & Valve house(At

junction of Surge shaft & Valve house)

: Adit-2: 180 m long, 5.5m x 5.5m

To Pressure Shaft (Intermediate Adit At El

2530)

: Adit-3: 186 m long, 4.5m x 4.5m

To Pressure shaft (upstream of

pressureshaft bifurcation.

:

Adit-4: 85 m long. 4.1m x 4.1m

To HRT (RD-242) :

Adit-5: 116 m long. 4.1m x 4.1m

9. SURGE SHAFT

Type : Underground, 2.5m dia riser. Concrete

lined with steel liner upto 2910 m.

Size: : 10.0m Dia., 110 m high.

Maximum Upsurge Level : 2903.00 m

Minimum Downsurge Level : 2825.00 m

Bottom Level : 2800.00 m

Top Level : 2910.00 m

10. PRESSURE SHAFT

Type : Underground

Size Main : 1 No., 2.5 m dia, 1145m long.

Page 22: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Salient Features

Indo Canadian Consultancy Services Ltd. 19 P-1143

Branches 3 nos.

For Branch-1 &2 : 2.5m dia 33m long,

1.75 m dia 23 m each, 1.2m dia 12m

each,

For Branch-3 : 2.5m dia 33m long, 1.75

m dia 40m long, 1.2m dia 12m long

Velocity : 5.8 m/s

Type & thickness of steel liner : Sumitten 610 F Grade, 18 mm to 54

mm thk.

Valve gallery : 13.0 m (H) x 10.0 m (W) x 10.0 m (L)

11. POWER HOUSE

Type : Surface

Installed Capacity : 150 MW (3 x 50 MW)

Size

: 80.3 m x 19.1 m

Maximum gross head : 615.31 m

Max Net head : 593.25 m

Min Net Head : 580.25 m

Rated Net head : 588.92 m

C/L of Turbine : 2258.44 m

Erection bay floor level : 2268.30 m

Crane beam level : 2278.65 m

Maximum TWL : 2252.00 m

HFL : 2250.00 m

Capacity of E.O.T crane : 120 tones

12. TAIL RACE CHANNEL

Type : Surface

Size : 5 m wide closed box channel, 100 m

long

Velocity : 1.90m/s

13. TURBINES

No. & Type : 3, Vertical Shaft Pelton.

Rated Power (at generator terminal) : 50 MW

Rated net Head : 588.92m

Max/Min net Head : 593.25 /580.25 m

Rated discharge : 9.55 cumec.

Speed : 500 RPM

Page 23: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Salient Features

Indo Canadian Consultancy Services Ltd. 20 P-1143

Specific Speed (wrt 10% overload) : 18.29 (m. kw)

14. MAIN INLET VALVE

Type : Spherical valve

Diameter : 1.2m

Location : In the power house

15. GENERATOR

Type : Vertical shaft synchronous generator

Number : 3

Rated Capacity : 55.55 MVA

Nominal Active Power : 50 MW

16. MAIN GENERATOR STEP UP TRANSFORMER

Location : Side wall of Powerhouse

No. of Single Phase Transformer : 10

Rated Output of Each Transformer : 22.5 MVA

Rated Voltage : 11 KV/220V

Frequency : 50Hz

Type of cooling : OFWF

17. GIS Hall

Size : 71.5 m x 14 m

Transformer Floor level : 2268.30m

GIS bay Floor level : 2277.30

Pothead Yard level : 2286.80

18. TRANSMISSION SYSTEM

Switchyard of Tidong-I Phase-II shall be located adjacent to Tidong-I HEP switchyard. Power of

Tidong-I Phase-II HEP shall be injected into Tidong-I HEP transmission system at Tidong-I HEP

switchyard.

19. ESTIMATED COST FOR PHASE-II DEVELOPMENT

Pre Operative and Civil Works : Rs. 39.89 Cr

Page 24: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Salient Features

Indo Canadian Consultancy Services Ltd. 21 P-1143

Electrical /Mechanical Works : Rs. 65.76 Cr

20. ESTIMATED COST- FOR TARIFF CALCULATIONs

Pre-operative Expenses : Rs. 15.80 Cr

Civil works : Rs. 24.09 Cr

Elect./Mech. Works : Rs. 65.76 Cr

Total Basic cost : Rs. 105.65 Cr

Escalations : Rs. 8.78 Cr

Interest During Construction & Financial charges

: Rs. 15.39 Cr

Total (Generation Works) : Rs. 135.01 Cr

21. POWER BENEFITS

Energy generation at 95% availability in

90% dependable year.

: 632.63 MU

22. FINANCIAL ASPECTS

Cost of generation in first year : 1.48

Average DSCR : 1.18

23. CONSTRUCTION PERIOD

For Phase-II development

: 2.0 years

Page 25: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 1. Introduction

Indo Canadian Consultancy Services Ltd. 22 P-1143

1 INTRODUCTION

1.1 GENERAL

Himachal Pradesh State Electricity Board (HPSEB) floated a Global Tender in 2004 for

allotment of Tidong -1 HEP in Kinnaur district of Himachal Pradesh and HPSEB allotted

Tidong-1 Hydro Electric Project to M/s Nuziveedu Seeds Limited, for investigation and

implementation of the project. The memorandum of understanding (MOU) for

development of this project has been signed between Nuziveedu Seeds Limited and the

Govt. of Himachal Pradesh on 23 September 2004. The MOU lays down the broad terms

to allow investigations and implementation of the project.

Prior to NSL’s takeover of the Tidong-1 Hydro Electric Project, Himachal Pradesh State

Electricity Board has carried out the initial field investigations of Tidong-1 Hydro Electric

Project as a part of Prime Minister’s initiative to develop 50,000 MW of Hydropower in the

country on a fast track. The preliminary project layout is prepared by HPSEB and is

indicated in the pre-feasibility report made available to the developer. As per this report, a

gross head of 608m and a rated discharge of 19.2m3/s are utilized to generate 100 (2x50)

MW of power and 414.15 MU of energy in a 90% dependable year.

In order to finalize the layout of various project components, Nuziveedu Seeds Ltd (NSL)

had started the work of detailed geological investigations and appointed RITES Ltd for

carrying out site investigations. The geological exploration has been carried out by RITES

included drilling, testing and logging at penstock alignment and power house area,

geophysical investigation by seismic refraction and resistivity survey; photo-geological

remote sensing studies, rock mechanic tests & Petrographic analysis, construction

material survey and testing to assess alkali-silica reactivity; property survey for storage

reservoir, submergence and communication surveys. The socio-economic studies for

Environmental Impact Assessment studies have also been entrusted to M/s RITES Ltd, a

government of India undertaking.

Partial Hydrological observations at diversion site have been done by HPSEB from 1995

to 2004. Discharge is being measured by NSL at the proposed intake from Dec 2004

onwards and the data is available up to date.

Based on a conceptual layout of development, topographical maps of the project area

were prepared and geological mapping done. The project layout is prepared based on

detailed topographical surveys. The survey for diversion barrage, desilting basin, storage

reservoir, intake, colonies, plant areas has been done to the scale of 1:500. The survey

for Head Race Tunnel covered a strip of 75m on either side of tunnel alignment. The

Pressure Shaft alignment was surveyed to the scale of 1:500 with a contour interval of 2 m

in a strip of 75 m on either side of the entire length of the penstock. The Powerhouse,

Page 26: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 1. Introduction

Indo Canadian Consultancy Services Ltd. 23 P-1143

Switchyard, TailRace and access tunnel areas have been surveyed to a scale of 1:500

with a contour interval of 2 m.

After studying various proposals, it was decided to locate the barrage with crest at EL

2881.75m downstream of confluence of Tidong Khad and Lamber Khad. The water shall

be conveyed through a head race tunnel of about 8.5 km long, surge shaft,

inclined/horizontal pressure shaft and a surface power house on the left bank of Tidong

river.

The project features were optimized based on the comprehensive analysis of

topographical, geological, hydrological data and alternative studies of project layout,

preliminary design features, broad parameters of cost and financial analysis etc. The

construction planning and cost studies have been carried out as per the final layout

adopted in this report.

The DPR (for two units of 50 MW each) was prepared accordingly and has been approved

by HSPEL vide letter no: HPSEB: (Sectt) 401 – TEC/Tidong-I/50 42034-47 dtd

23/07/2007. Nuziveedu Seeds Limited has formed a special purpose vehicle ”NSL Tidong

Power Generation (P) Ltd.” for implementation of this project. The implementation of

Tidong -1 project with an installed capacity of 100MW (2x50MW) has been taken up and

the work is in the final stage of completion and project commissioning. The present status

of the project work is mentioned below.

Excavations for Spillway, sluiceway and diversion channel and slope protection

works are completed, and Concreting works are partly completed.

Excavations for Head Regulator & Desilting Basin are almost completed, and

Concreting works for head regulator is under progress.

Excavation works at Storage Reservoir area and gravity wall location is completed

and concreting of gravity wall is under progress.

Underground excavations of all construction adits are completed.

Excavation of 95 % of Head Race Tunnel is completed and 10 % of concrete lining

is completed. Mud mat concreting is under progress in different faces.

Underground excavation of pilot shaft for surge shaft is completed, and widening of

the surge shaft is to be commenced.

Excavation of Valve house is under progress.

Excavation of underground pressure shaft is completed and fabrication and

transportation of pressure shaft ferrules is under progress.

Excavation for Power house & service bay area and slope protection behind power

house area are completed. Concreting of Service bay area is completed and super

structure like columns and beams upto roof level has been completed. In machine

Page 27: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 1. Introduction

Indo Canadian Consultancy Services Ltd. 24 P-1143

hall area, concreting of raft at turbine floor has been completed and concreting of

walls on either side of powerhouse area upto generator floor has been completed.

In view of significantly higher river flows in monsoon period, the possibility of increasing

the installed capacity of Tidong-I HEP has been explored by the Project Developer. NSL

Tidong Power Generation (P) Ltd has carried out discharge measurements in Tidong

River from Dec, 2004 to Dec, 2014 and based on detailed hydrological studies including

study of discharge pattern in adjacent Baspa basin. It is seen from the results of this study

that one additional unit of 50 MW capacity can be added to existing power house based

on techno economic consideration. The details of this study are presented in this report.

1.2 PRESENT STUDY FOR ADDITIONAL UNIT OF 50 MW OF TIDONG –I, PHASE - II

During implementation of the project, NSL started various other activities like acquisition of

land, clearance from the forest department, preparation of tender document etc. Most of

these activities were completed by 2008, and the development of infrastructure work

commenced in 2009. All these activities took almost 3 years to complete.

Simultaneously discharge measurements have been also carried out at diversion site

since December, 2004. Presently, about 10 years of actual measured flow data of Tidong

khad available for hydrological study. However, in DPR for Tidong -1 HEP having installed

capacity of 100 MW, the power potential study was done based on hydrological flow

series developed from Baspa river flow and one year measured river discharge data of

Tidong.

While analyzing the ten years of measured discharge data, it is observed that significantly

higher monsoon period flows are available in the river as compared to river flow estimated

at the time of DPR preparation. In view of the higher values of actual flow measurement,

the feasibility of increasing the installed capacity, with an additional unit of 50 MW, has

been studied. It is observed that adequate space for placing the new unit of 50 MW is

available in the land already acquired for existing surface power house.

1.3 PROPOSED SCHEME

The Phase - I project layout involves the construction of a diversion barrage with river bed

El 2880m, under sluice, reservoir to store 265000m3 of water to provide peaking

generation of 4 hour during lean season, head works, desilting basin to remove silt

particles above 0.2 mm in size, 8.5 km long head race tunnel, 10m diameter surge shaft

with a height of 110m, 1145 m long and 2.5 m diameter steel lined pressure shaft (partly

inclined and partly horizontal), surface power house having installation of two high head

Pelton type generating units each of 50 MW capacity with compatible generator and other

auxiliary equipment, and tail race channel. The project proposes to utilize about 610.977

m of maximum gross head and a rated discharge of 19.2 m3/s for power generation. The

energy benefits were assessed at 414.15 Gwh in 90% dependable year.

Page 28: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 1. Introduction

Indo Canadian Consultancy Services Ltd. 25 P-1143

For Phase –II, existing civil works at barrage, head regulator, desilting tank, storage

reservoir, HRT, pressure shaft are proposed to be utilized. Existing surge shaft will require

increase in finished diameter from 8m to 10 m. For installing the third unit in phase – II of

project, a new machine hall bay will be required adjacent to Unit 2 of existing power

house. Control room building of existing units will be used for the new unit also. The net

energy generation considering 95 % plant availability in 90% dependable year is

estimated as 632.63 MU.

Power evacuation arrangement as finalized with HPPTCL involves construction of

16.50km long 220 kV D/C transmission line from Tidong to Kashang. This arrangement

has been confirmed by HPPTCL vide their letter No.: HPPTCL//Tidong-I/CORR/09/1229

dated 06/09/2009 and later modified vide their letter no MPP-F(2) -9/2007-IV dated

11.10.2013. The same power evacuation arrangement is considered adequate to carry

the additional unit of 50 MW of power in phase – II.

The project cost for Phase – II works is estimated as Rs. 135 Cr. and the project shall be

completed in a period of 24 months, after obtaining all clearances and financial closure.

Power shall be sold to HPSEB or any of the utilities in Delhi, Chandigarh, Haryana, Punjab

or other states in Northern India.

Page 29: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 2. Project Summary

Indo Canadian Consultancy Services Ltd. 26 P-1143

2 PROJECT SUMMARY

2.1 GENERAL

The Tidong Hydro-Electric Project has been envisaged with the purpose of exploiting the

potential in the lower reach of Tidong khad. The project involves the construction of an

Ungated spillway, Gated undersluice, Head Regulator, Desilting Basins, Storage

Reservoir and a 8.504 km long Head Race Tunnel culminating in under ground Surge

Shaft. A pressure shaft partly inclined and partly horizontal will convey the water to the

surface powerhouse. The power house will accommodate two nos. Pelton Turbines 50

MW each in phase – I, and one additional unit of 50 MW is proposed to be added in phase

II of project development.

In Detailed Project Report, submitted in 2006, the project was anticipated to generate

414.15 Gwh with 100 MW installed capacity in a 90% dependable year (2004). With the

updated hydrological series, the project is expected to provide annual energy generation

of about 539.43 Gwh in phase – I with 100 MW, and about 632.63 GWh in phase – II with

150 MW in a 90% dependable year (2004-05) with 95% plant availability. During lean

seasons, the project shall also provide peaking capacity benefits of 100 MW for about 4

hours per day in phase – I, and 150 MW for about 3 hours per day in phase – II of project

development.

The project works for phase – I are in advanced stage of completion of construction and

commissioning. The project development in phase – II is expected to be completed in a

period of 24 months from zero date. The infrastructure facilities available in phase - I will

be used and are mostly found to be adequate for construction of the phase II. Tidong-1 in

Phase – II is techno-economically viable and its early execution is planned for reducing

the gap between availability and demand of power in the Northern Region of the country.

The phase – II of the project development is likely to be commissioned by February, 2019.

2.2 MAIN COMPONENTS

The project envisages construction of following structures in phase-I and phase II

development:

2.2.1 Diversion works

A barrage comprising of two sluice bays of 5.00 m width each and an ungated spillway of

20.00 m width is constructed. The barrage is designed to pass design flood of 405 cumecs

in Tidong Khad at High Flood Level (HFL) of 2889.4m. The crest levels of undersluice

and spillway bays are kept at El 2875.50 m and El 2881.75 m respectively. All works are

completed in phase - I development, and no modification is required during phase II of

project development.

Page 30: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 2. Project Summary

Indo Canadian Consultancy Services Ltd. 27 P-1143

2.2.2 Head Regulator

The Head Regulator is located on the left bank of the Tidong Khad, just upstream of the

diversion barrage, and is designed to draw a maximum flow of 35.00 m3/s. Two bays of

3.60 m clear width each having crest at El. 2877.40 m are provided in the head regulator.

Two regulating gates are provided to control the flow to the desilting chamber. All works

will be completed in phase - I development, and no further change is required during

phase II of project development.

2.2.3 Desilting Basin

The desilting basin comprises of two longitudinal chambers, each chamber having a

length of 80.50 m and width of 9.50 m, with a 2.50 m wide longitudinal flushing trench at

the bottom. A 1500mm dia silt flushing pipe is provided at the end of the flushing gallery

to convey the silt from desilting basin, back into river. The desilting basin is designed to

remove silt particles of size to 0.2 mm and above for the discharge corresponding to the

phase II of project development. All works will be completed in phase - I development, and

no modification is required during phase II of project development.

2.2.4 Reservoir

The reservoir is designed to meet the storage requirement for peaking demand of four

hours in phase – I of the project development in the lean season. The total storage

capacity provided in the reservoir is about 265000 m3. The available storage is sufficient

for peaking demand of three hours in phase – II of the project development. The bed level

of reservoir is kept at El 2860.00m, and MDDL is provided at 2860.75m considering

sufficient submergence depth to the tunnel intake. FRL of the reservoir is kept at El

2873.75m and top of the reservoir walls at El 2875.00 m by giving free board of 1.25m. An

overflow section is provided in the reservoir to spill water above FRL. The desilted water

from desilting chambers will be impounded in the reservoir. Silt particles of size below 0.2

mm are likely to get silted in reservoir, thus reducing the reservoir capacity over a period

of time. For efficient functioning of reservoir, suitable desilting arrangements are provided

in the form of sediment flushing pipe with a butterfly valve type control gate. No

modification in reservoir arrangement is proposed in the phase – II of the project

development.

2.2.5 Head Race Tunnel

From the reservoir, the water would be conveyed through 8.504 km long Headrace tunnel

drawn from intake structure located at the downstream end of the reservoir. At the entry,

the intake has been provided with a smooth transition to a D-shaped Headrace tunnel. A

trash rack structure is provided in front of the intake to avoid the passage of floating debris

into the tunnel along with an intake gate. The size of the D shaped tunnel between RD

0.00 m to RD 2130.00 m is of 3.50 m, and the size from RD 2130.00 m to RD 8409m is of

Page 31: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 2. Project Summary

Indo Canadian Consultancy Services Ltd. 28 P-1143

3.5 (W) x 3.9 (H). The stretch from RD 8409 to 8504 m will be provided with 2.5 m circular

shaped.

The tunnel invert level at the HRT intake is El. 2853.0, m and that at the the surge shaft

junction is EL. 2800 m. The tunnel is provided with a bed slope of 1 in 162. Three

intermediate adits are provided to facilitate construction of HRT. These adits meet the

main HRT at RD 242.00m, RD 2140.00 m and RD 8474.00m respectively. All works of

HRT will be completed in phase - I development, and no modification is required during

phase II of project development.

2.2.6 Surge Shaft

At the end of the HRT, a vertical circular surge shaft is provided to absorb the transient

pressure variations due to changes in power load. The surge shaft is at offset of about

11.00 m from the junction of HRT and Pressure Shaft. This offset acts as a restricted

orifice for the surge shaft to minimize the water fluctuations in addition to the initial 2.50m

vertical opening in surge shaft at the time of load rejection and sudden load acceptance.

With increase in design discharge in phase – II of project development, the finished

diameter of the existing surge shaft will require increase in diameter from 8.00m to 10.00

m. The surge shaft has a total height of 110.00 m from top to bottom with a provision of

riser of 2.50 m diameter between EL 2800.00 m to 2820.00 m.

2.2.7 Valve House

Downstream of the Surge Shaft, a pressure shaft protection Butterfly Valve of 2.50 m

diameter is provided. The valve will be housed in an underground cavern having a width

of 10.00 m and a length of about 10.00 m. A 180.00 m long adit is provided at El.2800.00

m to approach the valve house. The adit is being used for excavation of HRT during

construction for phase-I of the project. All works related to valve house are nearly

completed in phase - I development, and no modification is required during phase II of

project development.

2.2.8 Pressure Shaft

A steel lined Pressure Shaft of 2.50 m inner diameter is provided downstream of the

Surge Shaft. The excavated sizes of pressure shaft at inclined portion and horizontal

portion are 3.10 m dia circular and 3.40 m dia D-shaped respectively. The pressure shaft

has a inclined length of 326.00 m at 55º inclination to horizontal line between El 2801.75

and El 2534.51, followed by a horizontal length of 187.00m. Thereafter, length of 294.00

m is provided at an inclination of 55o between El 2525.14 and El 2284.40, and then a

horizontal length of 310.00 m is provided upto powerhouse. For construction of Pressure

shaft, an intermediate Adit-3 of 186.00m long at El 2530.00 m is provided. Another access

is provided to the bottom of Pressure Shaft through adit - 4 of 85.00 m long at El. 2257.00

m.

Page 32: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 2. Project Summary

Indo Canadian Consultancy Services Ltd. 29 P-1143

In phase I of project development, the single 2.50 m diameter pressure shaft bifurcates

into two unit penstocks of 1.76 m diameter each to feed the two Pelton Turbines of 50

MW. The length of the 2.50 m dia main pressure shaft upto the bifurcation is about

1145.0m and the length of unit penstock for machine 1 and 2 is 70.00m. Under phase II of

project development, it is proposed to provide T branching of about 33.00m upstream of

earlier bifurcation point, to feed the third unit. The alignment of pressure shaft for third unit

will follow the alignment of adit- 4 to bottom of pressure shaft. This arrangement will thus

eliminate the necessity of any excavation for pressure shaft for unit - 3. The length of

pressure shaft for unit 3 from bifurcation point to power house will be about 85.00 m.

2.2.9 Power House Complex

The power house is located on the left bank of Tidong khad about 150.00m upstream of

its confluence with Sutlej River. The overall dimension of the powerhouse, including the

space requirement of additional bay proposed in the phase – II of the project

development, is 80.30 meters long and 19.10 meters wide. Units 1&2 will be installed in

phase – I, and unit – 3 is proposed to be installed in phase – II of the project development.

The units 1 & 2 are spaced at 15.00 meters C/C, while units 2 & 3 are spaced at 27.00

meters.

A Transformer cum GIS hall is proposed upstream of the Power house building and it shall

house 10 nos of 26MVA single phase Transformers and Gas Insulated Switch yard (GIS).

The size of the Transformer cum GIS hall is proposed as 14m (W) x 71.5m (L) x 18.5m

(H) and shall be located at EL 2868.30m. A 300mm thick concrete fire wall is proposed to

separate each Transformer. GIS hall has been proposed at EL 2277.30m along with

control room building. The control room building shall accommodate Electrical Room,

Battery Room, Mechanical Workshop, Control Room, and HVAC unit Room.

2.2.10 Tail Race Channel

The tail water from Unit – 1 & 2 in phase – I of project development passes through two

tailrace ducts and merges into a common tailrace channel. The tail water from unit-3 is

planned to merge the common tailrace channel separately. The common tailrace channel

of 5.00 m wide rectangular shaped, having a length of about 100.00 m, conveys the tail

water back into Sutlej River.

2.3 TRANSMISSION SYSTEM

Switchyard of Tidong-I Phase-II shall be located adjacent to Tidong-I HEP switchyard.

Power of Tidong-I Phase-II HEP shall be injected into Tidong-I HEP transmission system

at Tidong-I HEP switchyard.

Page 33: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 2. Project Summary

Indo Canadian Consultancy Services Ltd. 30 P-1143

2.3.1 Power Benefits

The gross energy benefits from the project have been assessed as about 632.63 Gwh per

annum in 90% dependable year after ecological release as per requirement viz. 15% of

minimum flow. The project would afford peaking capacity benefits of 150 MW for about

three hours per day during lean season.

2.4 PROJECT COST

The project is estimated to cost Rs. 135 Crore at December, 2014 price level including Rs.

15.39 Crore as interest during construction & financial charges. It is proposed to finance

the project on a 70:30 debt: equity basis.

2.5 FINANCIAL ASPECTS

As per GOI norms the average cost of unit generation (for first five years) with 15.5%

return on equity (ROE) works out to Rs. 1.48 and average DSCR as 1.18 (Rs./kwh).

Assumptions for carrying out financial analysis are summarized in chapter-18, Financial

and Economic Evaluation.

Page 34: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 31 P-1143

3 SOCIO-ECONOMIC SCENE OF HIMACHAL PRADESH

3.1 GENERAL

Himachal Pradesh is a small hilly state, geographically located in the north-western part of

the country. It is surrounded by four states, namely, Uttarakhand, Punjab, Haryana and

Jammu & Kashmir with Tibet on the eastern side. Himachal Pradesh is among the most

advanced socio-economic states and has shown promising growth over the years. Over

the last decade the strong agro-based economy has shifted towards services, particularly

Tourism. The state is sparsely populated and endowed with natural attractions, Tourism is

one of the key contributors to the state’s income. Some of the tourist attractions include

Tribal areas, Mountaineering, Winter sports like skiing, besides a large number of pilgrim

centres. It is a hub for domestic and foreign tourists.

The state is largely an agro-based economy with about 71 per cent of its population

dependent on farming, horticulture and livestock for their livelihood. The main crops are

wheat, corn (maize), barley, rice and potatoes revenue from Apple crops in the main

resource for the people and Government . It is one of the leading fruit and vegetable

producing states in the country. The State Government has steadily been focusing on

improvement of industrial infrastructure.

A slew of industrial parks and estates including export-oriented parks for agro-processing

units have been set up, thus, strengthening the agriculture sector in the state. Several fruit

and food processing units and other allied industries like warehousing and packaging

have come up in various parts of the state. The state’s agro-processing units have highest

per capita output and value addition in the country.

Himachal Pradesh has one of the highest levels of telecom penetration in the country. The

state has a well-developed banking sector with a high density branches. It has the highest

Hydel power generation potential in the Northern region of the country and has fostered

private sector participation in the sector.

The Government of Himachal Pradesh has formulated its policies with an objective to

improve the industrial sector in the state. It has initiated many welfare programmes to

improve the economic well being of its people. The state provides special package of

incentives to the investors and ranks highest on the incentives index. The state enjoys a

healthy investment climate with the presence of several domestic and multinational

corporations.

Page 35: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 32 P-1143

3.2 PEOPLE, CULTURE AND RELIGION OF HIMACHAL PRADESH

3.2.1 The People

The population of HP consists of a medley of tribes, all speaking their own language.

Some of them are the Gaddis, Gujjars, Kinnauris, Lahulis and Pangwalis. The majority of

the people are of Aryan stock, with exceptions like the inhabitants of Lahaul and Spiti who

are distinctly of Mongol origin. Perhaps the most exotic among them are the Kinnauris,

known for their extraordinary beauty and ornate jewellery.

The Earliest Inhabitants

Before the coming of the Khasha Aryans were the Kols and Mundas. These people are

represented by the various scheduled castes like the Kolis, Halis, Chamars, Darains,

Rehars, Chanals, Lohars, Baris, Dagis, Dhakis or Turis, and form a considerable part of

the population.

The great social fusion over the centuries, a process which is still going on, has resulted in

many changes in the appearance and characteristics of these people. As such, like the

rest of Northern India, they are ascribed to Aryan blood by mainstream historians.

The present day the Kinnauras do not constitute a homogenous group and display

significant territorial and ethnic diversity. For a better understanding of ethnic and cultural

distribution, the Kinnaur District may be classified into three territorial units.

Lower Kinnaur comprises area between Chora at the boundary of the Kinnaur District with

Rampur Bushahr and Kalpa including Nichar and Sangla valleys. The people of lower

Kinnaur are mostly Hindus though the ethno-historical factors have resulted in some

Buddhist influence.

The middle Kinnaur is the area between Kalpa and Kanam including Moorang tehsil. The

people of middle Kinnaur are of mixed racial strain. The inhabitants are Buddhist as well

as Hindus. Many people have faith in both the religions.

Page 36: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 33 P-1143

The upper Kinnaur comprises of remaining north-eastern part of the district i.e. the area

between Pooh and Hangrang valley extending upto international border with Tibet.

However the people of Hangrang valley are almost universally Mongoloids. They mostly

follow Mahayana Buddhist religion. The project site falls under this zone.

HP is the least urbanized of states in India, and so there’s an ‘untouched’ simplicity about

its inhabitants. Living in a world of their own, the people are sometimes quite unaware of

what’s happening in the rest of the country. Their whole life seems to revolve around high

peaks, near-accessible passes, rivers and deep valleys. All this makes for people who are

essentially simple, honest, god-fearing and firmly rooted in the bedrock of the past. Ninety

percent of the people live in distant ‘fairy tale’ villages and small towns, and depend on

agriculture for their livelihood. Many also rear sheep, goats, and other cattle.

3.2.2 The Dress

The people of distinct dress in mostly woolen clothes. Their clothing is well suited to the

climate and is artistic too in its own distinctive way.

Head dress of men and women is a round woolen cap called thepang in the local dialect.

It is generally of light grey or of white colour with a colour velvet band on the outer fold.

Band of green colour is most liked. Crimson blue, yellow etc. may also be worn.

Men wear woolen shirts called chamn Kurti made of woolen cloth and tailored in the

village. Another type of dress which the men wear is Chhuba. It is long woolen coat

somewhat resembling an Achkan. A sleeveless woolen jacket worn outside the Chhuba.

Men wear woolen churidhar pajama.

Women wrap up a woolen shawl like garment called dohru. The first wrap of dohru is on

the back with embridered border displayed throughout its length up to the heels. Darker

shades of colours are preferred for dohru. Besides beautiful coloured shawls are also

worn by them over their shoulders. Choli a sort of full sleeves blouse is worn by the

women. Some of them have decorative lining also.

However, now a days wearing of cotton/synthetic salwar, kammez, pants and shirts have

become popular among the young Kinnauras. The traditional footwear worn by the

Kinnauras were made of wool and goat hair with sole of goat hide. However, with the

Page 37: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 34 P-1143

passage of the time the indigenous shoes have almost disappeared and wearing of

readymade shoes is in vogue.

3.2.3 Houses and Equipment

The traditional village house of Himachal has a rather interesting structure. The lowest

storey is for household cattle, the middle for storing grain (also doubles as sleeping room

for the family in winter) and the top floor or dafi forms the living area.

The housing pattern of upper Kinnaur is different from that of lower Kinnaur.

In the lower Kinnaur the houses are two storied and built of stone and wood. These are

either slated roofs or having flat roofs made of layers of bhojpatra (tree bark) covered with

earth. The door is often folding and opens inwards.

In upper Kinnaur the houses are usually built of stone. These are flat roofed and covered

with earth. They are ill-built on account of the scarcity of wood. The houses are two storied

and doors are small. The ground floor is used as cattle shed and upper storey for living

purposes. The size and plinth area of the house depends upon the site available for

construction. The houses are white washed in lower as well as upper Kinnaur. Besides

these traditional houses, now RCC houses built in modern designs are also coming up.

Usually the households have some wooden chest for keeping grain and dried fruits. In

addition most of the houses have separate wooden grain storage structures locally called

'Kathar'. Khayarcha is a mat used for sitting purposes, which is made of goats hair. Pakpa

which is skin of sheep or goat or some wild animal as often placed on khayarcha for

sitting. Traditionally the people used to use utensils made of brass, bronze and aluminum.

However, nowadays with the increased outside contact they are fast adopting the china

crockery and utensils made of stainless steel.

Page 38: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 35 P-1143

3.2.4 Cuisine of Himachal Pradesh

No discussion about people and culture is complete without giving due mentioning of its

cuisine. The preferred taste in Himachal varies from region to region. Non-vegetarian

food, with a generous dose of spices like cardamom, cinnamon, cloves and red chillies, is

very much the norm. The average Himachal kitchen churns out all sorts of meat, lentil and

cereal preparations.

Simple Eating Habits

However there may be local variations. For instance, in the barren regions of Kinnaur and

Lahaul-Spiti, there is more emphasis on locally-grown coarse grains like buckwheat, millet

and barley. In areas with a pastoral tradition, milk and its products are liberally used in

cooking. Himachalis are not particularly fond of vegetarian fare and till recently tubers like

potatoes and turnips were all they ate in the name of vegetables. Green vegetables,

however, are increasingly finding their way into Himachali kitchens. While the everyday

meal is the usual dal-chawal-subzi-roti (the common north Indian meal of rice, lentil broth,

dish of vegetables and bread), special dishes are cooked during festive occasions.

Famous Sidu is a kind of bread made from wheat flour. It is kneaded with yeast and the

dough is allowed to rise for 4-5 hours. With a stuffing of fat it is first browned over a slow

fire and then steamed. Sidu is normally eaten with ghee (clarified butter), dal (lentil broth)

or mutton. In many parts of the state, ankalos made of rice flour are a festive dish. In the

dry Lahaul-Spiti valley, the leaves of buckwheat are mixed with wheat flour and made into

cakes called aktori. Patande (a sort of pancake) is a specialty in the Sirmaur area.

Page 39: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 36 P-1143

3.2.5 Religion

More than 95% of the population of HP is Hindu but Buddhism has also made inroads in

to the state thanks to the nearness to Tibet and presence of the Dalai Lama at

Dharamsala.

The ashen valleys of Lahaul, Spiti and Kinnaur are made brilliant by the Buddhist way of

life.

At times the demarcation between Hinduism and Buddhism is very faint in these hill

regions. For example, the rituals of the Kinnauris are a mix Buddhist and Hindu practices.

The hundreds of gompas and monasteries here serve as a veritable library for the student

of Buddhism. No wonder HP is said to be God’s Own Country.

There are also several notable churches and Sikh gurudwaras in the state. Christianity

came in with the British, of course, who dashed to these mountains whenever the heat of

the plains got to them. Shimla, Kasauli and Dalhousie served as the most important British

retreats, and so have the most well known churches of the state. St-John-in-the-

Wilderness in Dharamsala is also quite an attraction.Sikhism, too, is practiced in a few

places in Himachal. Paonta Sahib in Sirmaur district is a major pilgrimage for Sikhs, and

so is beautiful Manikaran in the Kullu Valley. The Sikhs played an important role in the

history of Himachal and Guru Govind Singh, one of the ten founders of the religion, began

his career on this very land.

3.2.6 Monasticism

Kanet boys, who learn the Tibetan scriptures and are well versed in Buddhist doctrines,

are called Lamas. Similarly the Kanet girls, who do not marry, but devote their time to the

study of Tibetan scriptures are called Zomos or Jomos. They live in nunneries. The two

principal nunneries are at Kanam and Sunnam and in these a great numbers of Zomos

Page 40: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 37 P-1143

live. Besides this, almost every village had few Zomos. The Lamas live in the monasteries

and are looked upon as very holy. In fact they are the priests of all the Kanets. There are

several monasteries of these Lamas in Kanam, Sunnam and other villages. Lamas are

either Gyolong or Celibate like the Brahmchari or Dugpu, who marry but never shave. The

head Lama is consulted with regard to important undertaking.

3.2.7 Festivals

Festivals and fairs form an integral part of the culture of Himachal Pradesh. These

festivals are full of religious rites and cultural practices that the Himachalis assert in the

best of their abilities. It is the time of fun and frolic; people wear colorful dresses and

engross themselves in dancing and singing. Apart from celebrating all other Indian

festivals , few local festivals too are observed with the same vividness and festivity. Some

heralds the arrival of seasons. Sikh festivals namely Baisakhi and Lohri and few festivals

of tribal communities are celebrated here.

The culture of Himachal Pradesh incorporates zestful festivals and fairs. The tourists from

all over the world participate in the festivities. In the second week of December, the

International Himalayan festival is held in Dharamshala. Diwali is feted throughout the

state. The Lavi fair is famous in Himachal and it is observed for three days on the Sutlej

riverbanks. At Sirmaur, the effigies of Parasuram are plunged in the Renuka Lake. The

people of Himachal Pradesh, especially Shimlaites are celebrating Christmas since the

British domination. Lahaul observes a special festival called Cheeshu. The Lahaul Festival

is also held near Keylong. Haryali is a famous festival observed in Kangra region of

Himachal Pradesh and Sirmaur. Shravan Sankranti takes place in Nahan in July. The

renowned Naina Devi fair, in Bilaspur also occurs during the month of August.

3.2.8 Music and Dance

The Himachalis are fond of dance and music and these are key elements of culture of

Himachal Pradesh. The songs and performing dances are spiritual in nature and mainly

used to invoke gods and goddesses during festive seasons. Himachal is racy in folk music

and till date no classical music has initiated. However, special kind of songs namely

Samskara song are grounded on ragas which belong to the genre of Indian classical

music. The war songs sung by the Himachalis Jhanjhotis too have the similar originations.

Page 41: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 38 P-1143

Ainchaliyan are the famous religious songs, buzzed at the bride`s house. All the females

present at the residence of an unmarried girl sing it with the completion of wedding

ceremony. The dancer is called jhoomar. In the Kullu region of Himachal, Laman songs

are quite famous.

The musicians carry various instruments like Flute, karna, Ranasingha, Turhi, Ektara,

Kindari, Jhanjh, Manjara, Chimta, Ghunghru and Ghariyal during their gala musical

performance.

Famous dance styles are Naati, Kharait, Ujagjama and Chadhgebrikar (Kullu), Shunto

(Lahaul & Spiti) and Dangi (Chamba). In Sirmaur and Mahusa regions a woman dances in

high spirits and the whole lot of audience are totally enthralled by her vivacious

performance.

3.2.9 Language

Thanks to the many tribes – each with its own language and dialect – Himachal boasts of

more than 60 dialects. These are Chambyali, Pangwali, Lahauli, Kinnauri and so on. In

places with a Buddhist population, Tibetan is the language.

But the state’s main language is Pahari, a derivation from Sanskrit and Prakrit, which is

largely unintelligible to plain dwellers. Hindi is also spoken widely and is the language of

instruction in schools. With Himachal’s close proximity to Punjab, Punjabi is the medium of

communication in some places.

3.3 GEOGRAPHICAL FEATURES OF HIMACHAL PRADESH

3.3.1 Location

Himachal Pradesh is situated between 300 22' 40” to 330 12’ 20” north latitudes and 750

45' 55" to 790 04’ 20” east longitudes. The altitude in the Pradesh, a wholly mountainous

region in the lap of Himalayas, ranges from +350.00 metres to+ 6975.00 metres above

mean sea level. It is surrounded by Jammu and Kashmir in the north, Tibet on north east,

Uttarakhand in the east/south east; Haryana in south and Punjab in south west/west.

3.3.2 Climate

Himachal Pradesh can be divided into three regions: - (i) The Shivalik ranges (the height

from plain upto 915 metres); (ii) Colder Zone (the height is 915 m to about 4500 metres);

and (iii) the Axis and Crystalline core of the whole system (the height above 4500 metres

but below 5500 metres).

The climatic conditions, therefore, vary from the semi- tropical to semi-artic.

Physiographically, the state can be divided into five zones based on altitudes and

Page 42: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 39 P-1143

moisture regime conditions. These vary from wet humid sub-temperate situation to dry

temperate alpine high lands.

Besides the seasonal variations, the climate of Himachal Pradesh varies at different

altitudes. The average rainfall is 152 cms (60 inches). The highest rainfall occurs in

Kangra district followed by Shimla district.Temperature varies from -40C to 310C.

3.3.3 Hills

Himachal Pradesh (HP) ‘the Mountain State’ is a complex mosaic of hills, lush valleys and

snow-clad peaks. It straddles the Himalayas from the foothills, over peaks, to the valleys

of Lahaul and Spiti. The prominent ranges which curve across the state are the Shiwaliks,

Pir Panjal, Pangi, Zaskar and Dhauladhar. The highest peaks are Shilla (7,026m),

Manerang (6,597m) and Shipki (6,608m). The hills rise gradually from the south to the

north of the state – the outer Himalaya or Shiwaliks, the Lower or Lesser Himalaya, the

Main or Great Himalaya and Trans or Tibetan Himalaya.

3.3.4 Valleys

Much of HP can be easily divided according to its many lovely valleys. Lahaul and Spiti

stretch from the Chandra Valley in the northwest to the Lingti Valley along the Spiti River.

The Chamba and Kangra valleys lie on either side of the mighty Dhauladhars, while the

remote Pattan Valley is separated from Chamba by the Pir Panjal. Kullu Valley stretches

from Mandi to Manali, and the Parbati Valley obviously follows the Parbati River. The

Malana Valley is quite an interesting place, supposed to be the oldest democracy in the

world.

3.3.5 Glaciers, Rivers & Lakes

The many glaciers above the snow line feed the fast flowing rivers of Himachal Pradesh.

In fact, the whole of the Himalayas is like one mammoth reservoir of snow. The Beas

Kund glacier near the famous Rohtang pass in Kullu is the mother of the Beas. The other

biggies are the Bara Shigri, the largest glacier in Lahaul valley, the Bhadal Glacier, the

Bhaga Glacier and the Chandra Glacier. Alpine pastures spring up around them in

summer turning the place into a picnic spot for migratory graziers.

Life moves at a gentle pace in Himachal, but not the rivers; they are always in great hurry.

In the furrows between the many ranges rush the perennial rivers that drain the snow

slopes off the crests. The major rivers, criss-crossing the roughly square Himachal, are

Beas, Chenab, Spiti, Sutlej, Ravi and Yamuna.

The Beas originates in the Pir Panjal range near the Rohtang Pass and flows some 256

km in Himachal. The river is formed by a number of tributaries, the important being the

Parbati, the Hurla, the Sainj, the Uhl, the Suheti, the Luni, the Banganga and the Chaki.

The Chandrabhaga or Chenab is the largest river (in volume of water) formed after the

Page 43: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 40 P-1143

meeting of 2 streams, Chandra and Bhaga at Tundi, in Lahul. The river flows a distance of

122 kms and has a catchment area of 7500 sq. km in Himachal, before entering Kashmir.

The Ravi originates from Bara Banghal (Kangra district) as a joint stream formed by the

glacier fed Bhadal and Tantgari. The river flows a distance of about 158km and has a

catchments area of about 5451sq. km.

The Satluj is unique, the only river in HP to rise from beyond the Himalayas. It begins as

the outflow from the sacred lake of Rakas Tal in southern Tibet, and enters Himachal

through a notch in the Zaskar Range at Shipkila. Passing through precipitous gorges and

narrow valleys it emerges from the mountains at Bhakra. The catchment area of Sutlej in

Himachal is 20000 sq.km.

The river Yamuna originates from Yamunotri in Uttar Kashi (Uttar Pradesh). Its total

catchment area in Himachal is 2320 sq.km. Its main tributaries are the Tons, the Giri and

the Bata.

Most of these rivers join the Indus River system which flows into the Arabian Sea. Dams

have been constructed over them at many places to exploit their enormous hydel power

potential. The Bhakra Dam on the Sutlej has created Govind Sagar, the largest lake in the

region. Come monsoon and numerous waterfalls and gurgling streams gush out from

every nook and corner of the land. Apart from these dancing brooks, there are hot water

sulphur springs at Manikaran and Vashist which are a balm for tired limbs.

The major lakes of Himachal Pradesh include Renuka, Rewalsar, Khajjiar, Dal, Beas

Kund, Dasaur, Brighu, Prashar, Mani Mahesh, Chander Tal, Suraj Tal, Kareri, Sreolsar,

Gobind Sagar and Nako.

3.3.6 Flora & Fauna

Himachal is a land of jade forests and fresh air. As much as 68% of the land area is

covered with jungles. While the foothills and valleys are a refreshing green, the areas

above the snow line are almost bare. The southernmost tracts are dominated by sal

(Shorea robusta), sisham, chir pine, dry deciduous and moist broad-leafed forests. The

temperate region above this grows oaks, deodar, blue pine, fir and spruce. In the

uppermost climes, trees are sturdy with a vast network of roots (to help them tide over the

weeks of burial under heavy snow). One can mostly find alders, birches, rhododendrons

and moist alpine scrubs in the name of vegetation. The tough rhododendron, is an

amazing plant and of terrific importance in the ecological chain. By attracting insects,

which in turn attract birds, it forms a major link in high altitude ecosystems.

Himachal is the fruit bowl of the country with orchards scattered all over the place.

Meadows and pastures are often seen clinging to the dangerously steep slopes. After the

winter snow thaws, the hillsides and orchards bloom with wild flowers, while gladiolas,

Page 44: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 41 P-1143

carnations, marigolds, roses, chrysanthemums, tulips, lilies and other flowers are carefully

cultivated.

Agriculture is the prime mover of economic growth in Himachal Pradesh and the state has

also carved a niche as a horticulture state and is also known as the “Fruit Bowl of Nation”

Dry temperate areas are suitable for apple cultivation. The fruits produced in these areas

are of high quality and long shelf life. In the horticulture crops, apple is a major crop

cultivated over about 8800 ha of land. The yield of this crop is approximately 5200 kg/ha

producing between 40,000 to 50,000 tonnes annually. In addition dry fruits like almonds ,

walnuts etc.

Out of total 45,000 species of plants found in the country as many as 3,295 species

(7.32%) are found in the State. More than 95% of species are endemic to Himachal and

characteristic of Western Himalayan flora, while about 5% (150 species) are exotic

introduced over the last 150 years.

From thick sub-tropical forests to the dry alpine vegetation, Himachal is home to a wide

variety of animals. This includes the leopard, which is the most widely distributed mammal

in the entire state, the snow leopard, ghoral (goat-like stout animal), musk deer which is

the state animal and monal (a pretty bird in nine iridescent colours), the state bird. HP has

11 major national parks and sanctuaries – the largest number in the Himalayan region.

The Great Himalayan National Park in Kullu – the first in the state – was created to

conserve the flora and fauna of the main Himalayan range, while the Pin Valley National

Park to conserve the flora and fauna of the cold desert.

Legal Classification of Forest

Table 3.1 Category Area (Km²) Percentage

1. Reserved Forests 1896 5.12

2. Demarcated Protected Forests 11387 30.75

3. Un-demarcated Protected Forests 21656 58.48

4. Unclassed Forests 976 2.63

5. Others (managed by ForestDept.) 370 1

6. Not managed by Forest Department. 748 2.02

Total 37033 100

Forest Types in Himachal Pradesh

Moist Tropical Forests

Dry Tropical Forests

Montane Sub-Tropical Forests

Page 45: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 42 P-1143

Montane Temperate Forests

Sub-Alpine Forests

Alpine Scrub

Source: H. P. Forest Department

3.3.7 Mineral Resources

Mineral Resources of Himachal Pradesh has a huge possibility of turning into a profitable

economic sector of the state. Himachal Pradesh is blessed with mineral wealth. As per

investigation of Geological Survey of India, the minerals available in Himachal Pradesh

include limestone, byrytes, clays, mica, iron pyrites, salt, gypsum, slate, antimony and

lead. The distribution of these minerals is scattered all over the State and includes lime

stone in Bilaspur, Sirmaur and Kangra districts; salt and slates in Mandi District; gypsum in

Rajban, Bharli Sirmour distt.; Lahaul & Spiti and Sapatu in Solan distt.; byryte in Sirmour,

iron ore in Mandi and Kangra; and uranium in Kullu and Hamirpur districts.

3.3.8 Soils

The soils of the State can broadly be divided into nine groups on the basis of their

development and physico-chemical properties. These are: (i) alluvial soils, (ii) brown hill

soil, (iii) brown earth, (iv) brown forests soils, (v) grey wooded or podzolic soils, (vi) grey

brown podzolic soils, (vii) planosolic soils, (viii) humus and iron podzols (ix) alpine humus

mountain speletal soils. The soil found in the districts of Mandi, Kangra, Bilaspur, Una,

Solan, Hamirpur and Sirmaur is generally brown, alluvial and grey brown podzolic, Kullu

and Shimla have greywooded podzolic soils, while Kinnaur, Lahaul and Spiti and some

parts of Chamba district have humus mountain speletal soils.

3.4 DEMOGRAPHIC PROFILE OF HIMACHAL PRADESH

Table 3.2

i) Number of Districts 12

ii) Area in Sq.Km. 55,673.00

iii) Total Population

Persons 6,077,248

Males 3,085,256

Females 2,991,992

iv) Population Density per Sq.Km. 109

v) Sex-Ratio per thousand Males 970

vi) Percentage of Rural Population 90.21

vii) Percentage of Urban Population 9.79

viii) Literacy Absolute 4,029,097

Page 46: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 43 P-1143

Rate 77.13

Absolute 2,266,103

Rate 86.02

Absolute 1,762,994

Rate 68.08

ix) No. of Villages 20,118

x) No. of Tahsils 75

xi) No. of Sub-Tahsils 34

xii) No. of Towns 57

xiii) Labor Force Main Workers 1,963,882

Marginal Workers 1,028,579

3.5 INFRASTRUCTURE DEVELOPMENT OF HIMACHAL PRADESH

3.5.1 Social Infrastructure

Health

The health infrastructure includes 50 civil hospitals, 60 community health centres, 449

primary health centres and 2,067 sub-centres. The state ranks second on the health

index.

Table 3.3 Medical and Public health

Item 2005-06 2006-07 2007-08 2008-09 2009-10

(upto Dec

2009)

1. 2. 3. 4. 5. 6.

Allopathic institutions

No. of Institutions

Hospitals* 90 92 93 93 93

P.H.Cs. 439 443 449 452 449

C.H.Cs. 66 71 73 73 73

Dispensaries* 40 40 40 41 41

TOTAL 635 646 655 659 656

Beds Available* 10060 9687 10197 10197 10197

Ayurvedic institutions

No. of Institutions

Page 47: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 44 P-1143

Item 2005-06 2006-07 2007-08 2008-09 2009-10

(upto Dec

2009)

Hospitals 24 24 25 25 27

Nature Cure Hospital. 1 1 1 1 1

Dispensaries/ Health

Centres

1105 1105 1109 1109 1104

Ayurvedic Pharmacies 3 3 3 3 3

Research Institution 1 1 1 1 1

TOTAL 1134 1134 1139 1139 1136

Beds Available 726 726 786 786 747

No. of Unani Dispensaries 3 3 3 3 3

No. of Homeopathy

Dispensaries

14 14 14 14 14

Source: - Directorate of Health & Family Welfare and Ayurveda, Himachal Pradesh.

* It also includes Private; State Special, Cantonment Board and Missionary. Education

The literacy percentage in Himachal Pradesh has increased from 31.96 percent in 1971 to

42.48 percent in 1981, 63.86% in 1991 and has now reached 76.50% as per 2001

census. This literacy rate in Himachal Pradesh is higher than the national average. The

march of education continued ahead through concerted efforts of spread of educational

institutions, providing incentives for retention especially of SCs/STs and OBCs category

children and enlarged enrolment.

Table 3.4 2008-09 2009-10 (Upto 31.12.2009)

1. 2. 3.

No. of educational

Institutions Notified:

Primary 10,738 10,748

Middle 2,291 2,338

High Schools 835 849

Senior Secondary Schools 1,223 1,251

Degree Colleges 67 67

Total 15,154 15,253

Source: - Education Department, Himachal Pradesh

Page 48: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 45 P-1143

3.5.2 Access Infrastructure

Himachal Pradesh ranked second on the infrastructure index in the country. Himachal

Pradesh is approchable by air, rail and road. It has a road network of 32,926 Kms as

depicted in table below and connects all district headquarters, sub divisions and blocks.

Table 3.5

Type of Road

As on 31st March (in Kilometers)

2005 2006 2007 2008 2009 2009-10

Upto

31.12.2009

1. 2. 3. 4. 5. 6. 7.

1. Motorable

Double lane

2,355 2,369 2,374 2,374 2,377 2,380

2. Motorable Single

lane

22,567 23,599 25,210 26,783 27,925 28,533

3. Jeepable 442 390 381 365 345 325

4. Less than

Jeepable

3,103 2,653 2,299 1,990 1,803 1,688

Total 28,467 29,011 30,264 31,512 32,450 32,926

Source:-Public works Department, Himachal Pradesh

Note: - Figures include National Highways also.

At present there are Eleven National Highways having length of 1471 Kms pass through

the State. These National Highways are NH-1A,NH- 20,NH-21, NH-21A, NH- 22, NH-70,

NH-72, NH-88, 73-A,72-B and 20-A. Other five approved national highways are Hamirpur-

Sujanpur-Palampur (59 km), Brahmpukhar-Bilaspur-Ghumarwin-Baijnath (11 km),

Bharmour-Chamba-Dalhousie-Pathankot (133 km), Taradevi-Jubbarhatti-Kunihar-

Ramshehar-Nalagarh-Ghanauli (106 km) and Chandigarh-Baddi-Nalagarh-Arki-Shalaghat

(83 km).

The state has three domestic airports at Shimla, Kullu and Kangra while two are coming

up at Spiti and Banikhet (Chamba). Airways operate regular flights to Himachal Pradesh.

Rail Heads in Himachal Pradesh

Kalka

Pathankot

Una

Kalka – Shimla. Pathankot- Joginder Nagar (Narrow Gauge)

Page 49: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 46 P-1143

Major Rail Heads in Surrounding States

Kiratpur

Jagadhri

Dehradun

Pathankot

3.5.3 Communications Infrastructure

The state has a high tele-density (no. of telephones per 1,000 people) of 8.4 against 5 at

the national level. All telephone exchanges in the state are 900 digitalised and are

interconnected to each other by Optical Fibre Cables (OFCs). It has the highest density of

OFC penetration per unit area with a 6,000 km network.

The Government of India has set up a Software Technology Park and High Speed Data

Connectivity facility in Shimla. The state recorded a growth of 84 per cent in the Internet

subscriber base and appeared in the top quartile in the country in 2002-03.

About 98.5 per cent of the villages in the state have been provided with telecom facility*.

Up to 2004, there were 936 telephone exchanges in the state with net switching capacity

of 650,694. The state recorded the highest growth of mobile users at 175 per cent in

2002-03.

STD and ISD facilities are available in most places, even small. The Internet too is making

its presence felt at an amazing speed. There are cybercafés in Shimla, Manali and

McLeodganj. Surprisingly, notwithstanding the hilly terrain, radio has penetrated to the

remotest corners of the state (100% as against the national average of 96.89%).

3.5.4 Financial Infrastructure

Banks in the State are playing predominate role to accelerating economic growth in the

State economy and sharing the responsibility to enhance the flow of Institutional credit in

all sectors in accordance with the national priorities.

The total number of bank branches in the State was 1,373 as on September, 2009. There

are 20 Commercial Banks operating in Himachal Pradesh through a network of 776

branches of which 558 are located in rural areas and 218 in urban/semi-urban areas. UCO

Bank has been entrusted the responsibility of Convenor Bank in the State by RBI having

135 network of branches in the State. Other major banks are PNB with 234 branches, SBI

with 177 branches, SBOP with 81 branches and Central Bank of India with 40 branches in

Himachal Pradesh. In addition State having a strong network of 4 Cooperative banks with

407 branches and 2 Regional Rural Banks having 152 branches. There are 8 Private

Sector Banks functioning in the State with 38 branches as on September, 2009.

Page 50: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 47 P-1143

3.5.5 Industrial Infrastructure

Due to the persistent effort of the state government, a broad-based industrial structure has

slowly developed in the state.

Himachal Pradesh is a hilly region; hence the scope of agriculture is very limited in the

state. Yet there are many places in the state where people earn their livelihood through

farming, which reflects on the industry and enterprise of its people. Agriculture is the

fulcrum of the business and economy of Himachal Pradesh. Agriculture accounts for 45

percent of the net domestic product of Himachal Pradesh and 71 percent of the state's

labour force are employed in agriculture. Wheat, rice, maize and barley are the main

cereals being produced in the state. Seed-potato, mushrooms, ginger, chicory seeds,

olives and fig are the important sources of revenue to the Himachal farmers. Apple is

another major income generator for Himachal Pradesh. Fruit cultivation in Himachal

Pradesh is presently yielding an annual income to the tune of Rs.30 million.

Woollen garments and handicrafts make up the main small-scale industry. In fact, the

annual turnover from the shawl industry alone is estimated at around six crores rupees.

Spinning and weaving of wool (which is locally produced) is mainly a winter occupation

when there is time to spare from the fields.

The State Government has established 16 industrial Areas at Pauranoo, Barotiwala,

Baddi, Paonta Sahib, Mehatpur, Shamshi, Nagrotu Bagwan, Bilaspur, Reckong-Peo and

Sansar Pur Tera, 11 export promotion parks and 11 industrial estates with basic amenities

such as roads, power, sewerage, water, communications and power supply.

As the dust free and cool climate of Himachal is extremely suitable for the establishment

of electronic and precision industries, many electronic complexes have been set up at

Solan, Mandi, Hanurpur, Shogi, Raga-Ka-Bagh, Chamba, Ambi, Taliwala and Keylong,

like watch manufacturing units, thermometers, microscopes, hospital and laboratory

equipment. The state has established three agro export zones, including the one at

Parwanoo, which is one of the largest in Asia.

Furniture making, rope making, bamboo products, manufacturing and specialized wood

based industrial units have also been set up. Two vanaspati ghee plants have been set up

where limestone exists in plenty, cement factories have come up in public and private

sectors. Sericulture, handloom and tea are other industries that have lately been given

particular attention. Silk industry is providing employment to a lot of people.

3.6 STATUS OF INDUSTRY IN HIMACHAL PRADESH

During the last few years, the industrialization in the State of H.P. has made significant

progress. As on 31/03/2010 there are 36845 Micro, Small, Medium & Large Enterprises of

which 444 are in Medium & Large Scale registered with the Department of Industries with

Page 51: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 48 P-1143

an investment of Rs. 10408.41 Crore and employment to about 2.42 lac persons. The

District wise details of the registered industrial units are as under:-

Table 3.6- District wise details of the registered industrial units (Micro, Small, Medium &

Large Enterprises) upto 31-3-2010.

Sr. No. District No of units

Investment

( Rs. in Lacs)

Employment

1 Bilaspur 2239 52760.68 9771

2 Chamba 1733 2850.13 6015

3 Hamirpur 2718 6102.65 9832

4 Kangra 8761 29615.18 39372

5 Kullu 2438 7066.55 12822

6 Kinnaur 562 490.23 1762

7 Lahaul& Spiti 572 318.77 1575

8 Mandi 3727 9904.81 15386

9 Shimla 3317 23597.42 12819

10 Solan 4574 694118.75 88610

11 Sirmour 3065 136676.99 25695

12 Una 3139 77339.57 18004

Total 36845 1040841.73 241663

Table 3.7- Year wise details of registered industrial units (Micro, Small, Medium & Large Enterprises) upto 31-03-2010

Sr. No. Year No of units

set up

Investment

( Rs. in Lacs)

Employment

generated

1 Upto 2002-03 30372 308783.48 159694

2 2003-04 678 7202.48 4531

3 2004-05 948 39178.44 9885

4 2005-06 978 62376.54 11217

5. 2006-07 998 106798.68 15233

6. 2007-08 861 118900.94 13225

7. 2008-09 955 187898.74 15164

8. 2009-10 1055 209702.43 12714

Total 36845 1040841.73 241663

Page 52: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 49 P-1143

3.6.1 Agriculture

Himachal Pradesh agriculture is a very crucial part of the state's economy as agriculture is

the chief occupation of people in Himachal Pradesh. The agricultural sector of the

Himachal Pradesh has more than 45 percent contribution in its economy in terms of the

state's domestic product.

The entire population of the state more or less depends directly upon the agriculture of

Himachal Pradesh. The major portion of the revenue earning in the state's economy is

carried out by the cash crops in the Himachal Pradesh agriculture. The chief food crops

cultivated in Himachal Pradesh agriculture include wheat, maize, rice, barley, seed-potato,

ginger, vegetables, vegetable seeds, mushrooms, chicory seeds, hops, olives, and fig.

Himachal Pradesh is also known as the 'Apple State of India' for its large-scale production

of fruits. Farmers have engaged themselves highly in the fruit cultivation and it is also a

great blessing to the economy of the state. Some very important factors that have led to

the outstanding development in the agriculture of Himachal Pradesh are an efficient

irrigation system, accessibility of low-cost cargo, and marketing facilities structured in an

organized form.

Himachal Pradesh agriculture provides employment to around 71 percent of the working

population in the state. The agricultural sector and the allied sector generate revenue of

nearly 22.5 percent of the gross State Domestic Product. The farming community of the

state holds an area of 9.99 lakh hectares which is run by 8.63 lakh farmers out of the total

geographical area of 55.673 lakh hectares. Around 84.5 percent of the total land held by

the farming community of Himachal Pradesh is owned by the small and marginal farmers.

Only 10.4 percent of the area of the state is cultivated and about 80 percent of the area

experiences rainfall.

The agricultural sector of Himachal Pradesh has adopted a diversification approach that

demands for a focus on the production of off-season vegetables that include potato,

ginger, soyabean, oilseeds, and pulses. At present, about 41,500 hectare area constitutes

vegetable production and the production level of those vegetables is 7.85 lakh tonne. The

farmers focus more upon generating the cash crops for more revenue earning as it suits

the agro-climactic conditions in Himachal Pradesh.

The main cereals cultivated in Himachal Pradesh agriculture are wheat, maize, rice, and

barley. Kangra, Mandi district and to some extent Paonta valley of Sirmur district are the

major producers of wheat, maize, and rice. Barley is cultivated largely in Shimla district of

Himachal Pradesh. The main sources of irrigation in Himachal Pradesh are small water

channels that are filled from the perennial and seasonal springs, well irrigation in few

areas, and lift irrigation. All these development witnessed by the agricultural sector of

Himachal Pradesh have stepped-up the productivity of the crops to a large extent.

.

Page 53: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 50 P-1143

Table 3.8- Production of Principal Crops (In ‘000 Tonnes)

Crops 2006-07 2007-08 2008-09

(Likely)

2009-10

(Anti. Ach)

2010-11

(Target)

1. 2. 3. 4. 5. 6.

Food Grains:

A. Cereals

1. Rice 123.49 121.45 118.28 50.98 130.00

2. Maize 695.38 682.61 676.64 331.67 785.00

3. Ragi 3.16 2.49 3.10 1.48 4.50

4. Small Millets 5.08 5.46 5.09 1.90 6.60

5. Wheat 596.49 562.01 531.49 523.85 687.00

6. Barley 33.87 30.68 26.40 27.11 37.00

Total- Cereals 1457.47 1404.70 1361.00 936.99 1650.10

B. Pulses

7. Gram 1.02 1.37 1.60 0.62 4.00

8. Other pulses 17.98 34.59 36.96 18.77 16.50

Total Pulses 19.00 35.96 38.56 19.39 20.50

Total Food Grains 1476.47 1440.66 1399.56 956.38 1670.60

Potato 163.21 155.26 145.60 61.08 185.00

Vegetables 991.44 1040.49 1090.33 1130.00 1250.00

Ginger(Dry) 2.06 2.55 4.16 2.00 5.20

Source: - Directorate of Agriculture Himachal Pradesh

3.6.2 Animal Husbandary

Animal husbandry plays a vital role in the development of agriculture, especially in

Himachal where cattle are the main instruments for ploughing and other agricultural

operations. Indigenous breeds of cows, buffaloes and sheep are of poor quality.

A number of schemes for cattle development, cattle health and disease improvement in

wood production, poultry development, feed and fodder development, dairy improvement,

milk supply schemes and veterinary education have been undertaken to improve the

livestock in the state. The many veterinary hospitals, dispensaries and outlaying

dispensaries in the state provide veterinary aids and also take measures against various

contagious diseases. A number of mobile dispensaries are also in operation. Thus the

state has remained free from animal scourge.

Recently, Angora rabbits imported from West Germany were introduced in the Pradesh.

Now seven units for their propagation have been set up in Kangra district.

Page 54: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 51 P-1143

Milk production has increased due to these measures. Milk chilling plants with a capacity

of about 55 thousand liters have been set up at about 2 dozens places and departmental

milk supply schemes are operational in half a dozen towns.

3.6.3 Livestock

During the last 7 years 2001-02 to 2008-09, it has shown an increase of 15.88 percent

which shows that animal health care services have paid dividend. The table also shows

that egg production also increased at a considerable pace upto 2002-03 but thereafter it

declined slightly but again picked up in the year 2007-08 & 2008-09. The critical feature of

this table is that wool production has remained almost static. This strengthens the belief

that younger generation of the migrating gaddis has not come forward to adopt sheep

rearing as their main occupation.

.

Table-3.9-Livestock Production

Sr.

No.

Pro

duct

Uni

t

1997

-98

1999

-00

2001

-02

2002

-03

2004

-05

2005

-06

2006

-07

2007

-08

2008

-09

1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12.

1. Milk 000’

Tonnes 713.96 741.26 762.86 772.49 869.51 869.01 872.40 873.47 884.00

2. Eggs Lakh

Number 750.38 800.53 822.41 827.74 811.38 752.67 771.98 842.84 977.30

3. Wool Lakh

Kg. 15.65 15.76 15.86 15.94 16.00 16.03 16.05 16.07 16.18

3.6.4 Handicraft

Himachal Pradesh produces some of the wonderful handicrafts, which reflect on the

impeccable craftsmanship of its crafts persons or artists. They have been making these

flawless art pieces for generations together. Himachal Pradesh has a whole range of

different handicrafts like shawls, wood crafts, paintings, embroidery, textiles, rugs and

carpets, etc. Often they are products of months of meticulous precision.

Wood Crafts is perhaps the oldest type of handicrafts in Himachal Pradesh. The most

popular wood crafts of Himachal Pradesh are fruit baskets, trays, serving bowls, photo

frames, candle stands and carved idols, which a tourist can treasure as momentos. Metal

Crafts is another of the ancient skills developed and evolved in the hilly climes of Himachal

Pradesh. The traditional metals of copper and silver are still used to make jewelry and

utensils in some parts of the state.

Page 55: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 52 P-1143

Majority of the shawls are woven according to the old traditions, that is the shawls are

made up of fleece i.e. hair that are shed by a goat. The artisans have also mastered the

art of weaving imaginative but extraordinary designs on them. The shawls are also

available in a number of different colours and shades. The Pashmina shawl, the most

sought after shawl around the world, is also made in the state.

Khangra and Chamba schools of miniature paintings are part of the wonderful tradition of

handicrafts of Himachal Pradesh. Even after more than two hundred years since they

were introduced, these painting styles still have their presence in the cultural firmament of

Himachal Pradesh. Most of these paintings depict the court and the romantic scenes, and

can create a wonderful aesthetic contrast in today's modern homes. The state government

has setup schools to preserve the miniature art of painting. The state is also imparting

professional training to the students about modern painting.

3.6.5 Textiles

In addition to handloom and handicrafts, sericulture is one of the key cottage industries in

the state. In 2003-04, 114,000 kg reeling cocoons were produced. There are about 50,000

handloom units primarily based on wool. The main products of the textile industry in the

state are shawls, tweeds & blankets, woollen carpets, traditional dresses and other

handicrafts.

The Baddi-Barotiwala-Nalagrah belt in Solan district near Chandigarh is fast emerging as

a textile belt. The valley has a dozen units with a total capacity of about 600,000 spindles.

Another five units with an additional capacity of 200,000 spindles are in the pipeline.

3.6.6 Mineral-Based

Minerals constitute a fundamental component of the state’s economic base. The state has

considerable mineral resources including rock salt, limestone, gypsum, silica-sand and

baryte. The high availability of quality limestone, a key raw material has made the cement

industry flourish. Many domestic companies and MNCs have established their

manufacturing facilities in the state. The cement plants of ACC and Ambuja Cements have

a total capacity of over 4 million tonnes with plans of future expansion. Jai Prakash

Associates plans to set up a unit with an investment of US$ 110 million. Besides these,

there are many other mineral-based units like stone crushing, calcium carbonate units,

hydrated lime units etc.

3.6.7 Power

Himachal is extremely rich in hydel resources. The state has about 25% of the national

potential in this respect. It has been estimated that about 20,300MW of hydel power can

be generated in the State by constructing various major, medium, small and mini/micro

hydel projects on the five river basins. The state government has been giving the highest

priority for its development, as hydel generation can not only meet the growing need of

Page 56: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 53 P-1143

power for industry, agriculture and rural electrification, but can also be the biggest source

of income to the state by way of sale of electricity to the neighboring states.

The most prestigious and major project on river Sutlej in the state is the Nathpa Jhakri

(1500M.W). It is constructed in collaboration with the central government. The project is

funded by the World Bank.

The major completed and ongoing projects include 300MW Chamera II Hydel Project, 800

MW Parbati Hydel Power Project and 800 MW Kol Dam project. Other major projects by

Government of Himachal Pardesh and NHPC are: Bhaba Augmentation Scheme, Ghanvi

Hydro Electric Project (22.5 MW), Chamera III HEP (231 MW), Larji Hydel Project

(126MW) and Khauli Hydro Electric Project (12MW). The state government has given

many hydel projects for private sector participation. These include Baspa Hydro Electric

Project (300MW), Bajoli Holi Hydro Electric Project (180 MW), Kutehr HEP (220 MW),

Dhamwari Sunda Hydro Electric Project (70MW), Project (15MW), Allian Duhangan Hydro

Electric Project (192 MW), Malana HEP (86 MW), Karcham Wangtoo HEP (1000 MW)

and Budhil (70MW).

The state has electrified each one of its 16,807 inhabited villages. It is very impressive,

looking at the location of its villages in far off areas and their isolation.

3.6.8 Tourism

HP is far, far ahead of other states in India in this sector. Its great natural splendor

explains why tourists should make a trip to this destination. Apart from good hotels and

transportation, there are excellent facilities for adventure sports like trekking, rock

climbing, skiing, heli-skiing, river rafting and kayaking which attract enthusiasts from all

over the globe. Some of the important tourist centres are Shimla, Solan, Chail, Renuka,

Kalpa, Nako, Sangla, Kullu, Manali, Baijnath, Dharamsala, Kangra, Palampur, Dalhousie,

Khajjiar and Chamba.

The state ranks second in total tourism projects sanctioned during 2001-2004 in the

country. The state ranks fifth in domestic tourist visits. It enjoyed a 14 per cent growth in

tourist visits against the national average of 6 per cent in 2001.

3.6.9 Pharmaceuticals

Pharmaceutical units set up in the state enjoy an income tax holiday for five years till 2007

and a concessional rate of income tax for the next five years. The cost of production is

also considerably lower. It is becoming a hub for pharmaceuticals manufacturing, with

over 300 pharmaceutical firms. With a proactive policy of the Government, the state has

managed to attract significant investment in the recent past. The investment, particularly

from the pharmaceuticals sector has been impressive, clearly vindicating the special

Page 57: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 54 P-1143

incentives policy pursued by the Government. The Government plans to introduce a

special package of incentives exclusively for the pharmaceuticals sector by 2007.

Ranbaxy, Torrent, Indoco Pharma, Nectar Life Sciences, Indo-Swift Pharma, Dr Reddy’s

Laboratories and Cipla are some of the pharmaceutical companies that have

manufacturing facilities in the state. UniChem plans to invest over US$ 8.7 million in its

third formulation manufacturing facility. Indoco plans a formulation facility and Pulse

Pharma plans its second plant for therapeutic nutrition in Baddi. Torrent and Zydus Cadila

are also planning to set up formulation facilities in Baddi.

3.6.10 Business Opportunities

There are several factors that affect evolution of an industry in a region. Some of the major

factors are:

Policy proactiveness: The policy that a state government adopts towards a sector

directly affects its attractiveness for further investment. For example, the State

Government has given many concessions for the establishment of industries. This

has prompted many industry players to establish their manufacturing facilities in

the state.

Availability of natural resources: Certain industries like agro-based industries have

a high dependence on the availability of natural resources. The availability of high

quality limestone spurred the growth of the cement industry in the state.

Capability: Availability of good quality manpower is essential for industries to

flourish. High literacy rates and good quality workforce are added assets for the

state.

3.7 FACT FILE FOR KINNAUR DISTRICT

Population - As per 2001 Census

Male 42,173

Female 36,161

Rural 78,334

Urban NIL

Sex Ratio 857 (No. of females per 1000 males)

Density of Population 12 per sq. km.

Page 58: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 55 P-1143

Climate

Temperature [With respect to Kalpa for the year 2003]

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Min(in deg cent) -

04.7-07.2

-

04.2

-

00.202.5 08.2 10.2 10.2 04.5 01.5

-

02.8

-

06.5

Max(in deg cent) 16.1 13.1 20.1 23.1 25.2 25.7 25.3 24.4 24.6 21.4 20.0 15.9

Total Rainfall(mm) 0.00 0.00 23.9 83.5 59.6 28.2 78.2 32.5 26.8 04.9 0.00 0.00

Total Snowfall(cms) 45.5 139.9 85.6 16.0 0.00 0.00 0.00 0.00 0.00 0.00 06.4 75.1

Literacy Rate of Rural Population- As Per 2001 Census

Male Literacy 84.3 %

Female Literacy 64.4%

Geographical Area Sq. Kms.

Forest Land 458297.47 Hect.

Cultivated Land 9355 Hect

NonCultivable 614387 Hect.

Altitude Between 2350m to 6816m above sea level.

Longitude Between 77° 45' and 79° 00' 35'' East Longitude

Latitude Between 31° 05' 50'' and 32° 05' 15'' North Latitude

Major Rivers Satluj, Spiti & Baspa

Distances

Nearest Railway Station Shimla - 235 Kms

Nearest Airport Shimla - 235 Kms

Administrative Setup

No. of Sub Divisions 3 - Pooh,Kalpa,Nichar

No. of Tehsils 5 - Sangla,Pooh,Nichar,Moorang,Kalpa.

Development Blocks 3 - Nichar,Kalpa,Pooh

Panchayats 64

Villages 660

Page 59: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 56 P-1143

Education

Primary Schools 190

Middle Schools 37

High Schools 25

Sr. Sec. Schools 15

Colleges 1-Govt. College R/Peo.

Medical/Engineering Colleges NIL

Others ITI R/Peo, DIET R/Peo.

University NIL

Animal Husbandry

Hospitals 18 (17 providing AI Facilities)

Dispensaries 39 (30 equiped with AI Facilities)

AI Centres No special AI Centre.

Poultry Farms 2

Sheep Breeding Farm 1

Mobile Vetnary Dispensaries 1

Cattle Population As per Cattle Census

Caprine 35919

Ovine 73208

Poultry 5964

Swine 30

Canine 3447

Bovine 24685

Equine 4133

Page 60: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 3. Socio-Economic Scene of Himachal Pradesh

Indo Canadian Consultancy Services Ltd. 57 P-1143

General

Number of Post Offices Head Post Office Reckong Peo.

Sub Post Offices

Bhavanagar,Kalpa,Leo,Moorang,

Nichar

Pooh,Sangla,Ribba,Spillo,Tapri,K

atgaon

Branch Post Offices 56

Nationalized Bank

Branches

Punjab National Bank R/Peo,Karcham,Nigulsari,Kalpa

UCO Bank Skibba,Yangthang,Katgaon,Sungr

a,Sangla Tapri,Spillo

State Bank of India Bhawanagar,Pooh,Moorang,Lipp,

Giabong,Chango,R/Peo.

Union Bank Nichar

Land Development Bank R/Peo,Pooh

Name of the Lead Bank Punjab National Bank

Cooperative Bank

Branches

Kalpa,R/Peo,Moorang,Nichar,Pooh,Sangla,Tapri,Pangi

Katgaon,Sungra

Major Crops Kharif

Cereals Maize

Pulses Rajmash,Mash

Others Olga,Fafra,Koda,Cholai

Cereals Wheat,Barley

Vegetables Tomato,Brinjal,Cabbage,Cauliflower,Onion, Chilies, Capsicum, Peas,

Reddish, Turnip

Health Setup

Regional Hospitals 1

Block Hospitals 4

PHCs/Sub-Centres 50

Ayurvedic Hospitals 1

Ayurvedic Health Centres 41

Industrial Units

Large Industries NIL

Handicraft Units 3

Handloom Units 59

Page 61: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 4. Power Scenario

Indo Canadian Consultancy Services Ltd. 58 P-1143

4 POWER SCENARIO

4.1 GENERAL

India is a vast country having borders with most of the SAARC member countries. It has a

population of above 1.20 billion people. It is also one of the fastest growing economies,

with very good GDP growth rate

India‘s per capita power consumption is rather low, as compared to developed economies,

being under 400 kWh per year. With the economy growing at about 8% the rate of growth

of electricity demand will rise substantially over the next two decades. The rise of demand

has consistently exceeded the installed capacity addition, thus there has been chronic

shortage of both the peaking power as well as energy.

Electricity is essential for socio-economic development of any country. The standard of

living of people and status of industrialization of any country largely depend upon the

extent of the usage of electricity and can be judged by the per capita electricity

consumption. In India, concerted efforts have been made to increase the availability of

power to give a fillip to Indian economy. The power system planning in the country has

been done on the basis of five regions comprising of Northern, Western, Southern,

Eastern and North Eastern regions.

India’s hydro-power potential has been assessed at about 150,000 MW installed capacity

to provide about 600 billion units. Most of the hydro potential lies in the north-eastern and

northern region of the country in the Himalayan range of mountains. About 20% of the

hydro resources have been developed so far. Ideal thermal-hydro mix in the power system

has been established at 60:40, but the present mix is about 75:25 which is creating

operational problems in the power system including backing down of large thermal power

units.

The total installed capacity of thermal, Hydel, nuclear and gas based power projects in

India, as on 30th June 2013 is about 225793.10 MW as shown in table 4.1 depicted

below. The Northern Region, comprising of Chandigarh, Delhi, Haryana, Himachal

Pradesh, Jammu & Kashmir, Uttarakhand, Punjab, Rajasthan and Uttar Pradesh,

accounts for about 60794.75 MW of this capacity. Being a developing country with

growing power and energy requirements, the country experienced energy shortfall of

about 8.5% during the period April 2011 – March 2012. The shortfall in peak power was

10.6% during the same period.

Page 62: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 4. Power Scenario

Indo Canadian Consultancy Services Ltd. 59 P-1143

Table 4.1 ALL INDIA REGION WISE GENERATING INSTALLED CAPACITY (MW) OF POWER UTILITIES

INCLUDING ALLOCATED SHARES IN JOINT AND CENTRALSECTOR UTILITIES As on 30.09.2014

Captive Generation Capacity in Industries having demand of 1 MW or above, Grid

interactive (as on 31-03-2011) =34444.12 MW

RES- Renewable Energy Sources includes Small Hydro projects (SHP), Biomass Gas

(BG), Biomass Power (BP), Urban & Industrial waste Power (U&I) and wind energy.

ALL INDIA GENERATING INSTALLED CAPACITY (MW) (As on 30.06.2013)

S.No. Region Thermal

Nuclear Hydro R.E.S

@(MNRE) Total

Coal Gas Deisel Total

1. Northern 39431.00 5331.26 12.99 44775.25 1620.00 16598.11 5935.77 68929.13

2. Western 60169.51 10915.41 17.48 71102.40 1840.00 7447.50 1127107 91660.97

3. Southern 27382.50 4962.78 939.32 32284.60 1320.00 11398.03 13784.67 59787.30

4. Eastern 26527.88 190.00 17.20 26735.08 0.00 4113.12 432.86 31281.06

5. N.Eastern 60.00 1571.80 142.74 1774.54 0.00 1242.00 256.67 3273.21

6. Islands 0.00 0.00 70.02 70.02 0.00 0.00 11.10 81.12

7. All India 153570.89 22971.25 1199.75 177741.89 4780.00 40798.76 31692.14 255012.78

Page 63: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 4. Power Scenario

Indo Canadian Consultancy Services Ltd. 60 P-1143

The Government of India (GOI) has adopted a national hydro-power policy to accelerate

the development of hydro-power resources. Under this policy, GOI has undertaken a

number of actions which include rationalization of the process of project clearances,

providing committed funds for the ongoing schemes, creation of a new fund for survey &

investigation of hydro schemes by levying a surcharge on the electricity sold, multistage

clearance from the environment & forest angles to facilitate undertaking feasibility study

and pre-construction activities at the proposed project site, rationalizing the formulation of

tariff, promoting private sector participates in hydro-power development, special

concession for mega power projects, creation of electricity regulatory authorities at central

and state government levels, setting up Power Trading Corporation to facilitate sale of

power across the country.

The GoI aims to develop the entire hydro-power potential of the country by the year 2025-

26.However there are many barriers and hurdles in achieving the above goal. The

principal barriers are lack of financial resources, complicated and multi- agency

involvement in project clearances procedure, inadequate hydrological & geological

investigations, inter-state disputes, limitation of managerial capabilities & contract

management skills, lack of competent construction agencies, lack of adoption of the latest

construction methodologies and technologies etc.

As a part of Power Generation Strategy, Govt. of India has sought active participation of

private sector in power generation. The Electricity Act has been amended to facilitate entry

of private sector in power generation & distribution. Various incentives have been offered

to attract private investors, both domestic and overseas to enter in the field of power

generation. The untapped hydroelectric potential of Northern region provides excellent

opportunities for fulfilling this initiative and to bridge the gap between demand and supply

of power.

In line with the policy guidelines of the Govt. of India, the Himachal Pradesh Govt. has

since 1992 allowed development of small, medium and large capacity hydroelectric power

projects in the State by the private sector on Build, Own, Operate and Transfer (BOOT)

basis. Pursuant to this policy, Himachal Pradesh State Electricity Board (HPSEB) floated a

Global Tender in 2004 for allocation of medium and large hydroelectric projects in

Himachal Pradesh to private developers. Based on the assessment of technical and

financial capabilities of the bidders, HPSEB allotted Tidong - 1 hydroelectric project with

an installed capacity of 100MW in Kinnaur district to M/S NSL Tidong Power Generation

(P) Limited.

Page 64: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 4. Power Scenario

Indo Canadian Consultancy Services Ltd. 61 P-1143

4.2 POWER SCENARIO

The installed generating capacity, planned additions to generating capacity, existing and

anticipated energy demand patterns for Himachal Pradesh in the northern region of India

are discussed in this chapter.

4.2.1 Power Development in India

The power sector since independence has undergone a tremendous change and grown

from 1712 MW at the beginning of First Five Year Plan (1951-52) to 225793 MW as on

31.07.2012. The share of Northern Regional Grid is about 60794.75 MW, accounting for

26.92% of the total installed capacity in the country. Development of the large hydro

electric potential of India is being presently favoured due to its renewable, non-polluting

and low generating cost characteristics.

4.2.2 Power Planning Concept

The country has been divided into 5 power regions for the purpose of planning and

development of electric power. The concept of regional planning has been adopted as

energy resources are not evenly distributed amongst the various states. The approach in

various Five Year Plans has been found extremely useful for exploitation of available

resources and to achieve proper mix of hydro and thermal energy in the region, which is

essential to achieve cost economy in power production.

Central Electricity Authority (CEA) formulates National Power Policy, coordinates the

planning for power development in the country and draws long-term perspective plans. In

drawing up such a plan, CEA identifies the projects, which could be considered for

implementation during the successive Five Year Plan periods to achieve a proper mix of

hydro and thermal in a particular region. Such identification helps the executing agencies

to proceed with further detailed investigations and preparation of detailed project reports.

The names of the constituent States and Union Territories in the various regions are given

below:

Northern Region- Haryana, Himachal Pradesh, Jammu and Kashmir, Punjab,

Rajasthan, Uttar Pradesh, Chandigarh and Delhi (U.T.).

Western Region- Gujarat, Madhya Pradesh, Maharashtra, Goa, Dadra &

Nagar Haveli (UT) and Daman and Diu.

Southern Region Andhra Pradesh, Karnataka, Kerala, Tamil Nadu and

Pondicherry (UT)

Eastern Region Bihar, DVC (System), Orissa, West Bengal, Sikkim and

Andaman & Nicobar Islands

North Eastern- Assam, Manipur, Meghalaya, Nagaland, Tripura, Region

Arunachal Pradesh, Mizoram.

Page 65: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 4. Power Scenario

Indo Canadian Consultancy Services Ltd. 62 P-1143

Various State Govts/ State Electricity Boards are doing power development work in

various states of the regions.

4.2.3 Central Sector Participation

Central government is also setting up a number of hydro and thermal power projects in the

various regions to supplement the efforts of the State Governments/State Electricity

Boards in order to remove the imbalance of power development among several states and

for optimum utilization of energy resources through agencies like NTPC, NHPC, DVC,

NLC, NEEPCO etc. Some projects such as NJPC, THDC etc. are being executed jointly

by the State and Central Governments.

4.2.4 Power Sector Reforms in India

The State Electricity Boards, responsible for providing electricity to people are found to

incur perpetual losses and owe large sums to central power generating companies

because of their deteriorating financial performance. So the Govt. has taken steps in the

power sector to gradually eliminate losses. This process in India was initiated in 1991.The

govt. has amended Electricity Supply Act, 1948 and the Indian Electricity Act, 1910 in

order to attract private sector participation.

The Govt. enacted Electricity Act 2003. The objective is to introduce competition, to

protect consumers’ interests and provide power for all. This aims at commercial growth of

power sector and to enable center and states to move in harmony and co-ordination.

The Govt. of India has kept a target to provide availability of over 1000 units of per capita

electricity by year 2012 by need based capacity addition of more than 100000 MW during

2002-2012. The Govt. of India has created favourable environment for adding power

generation by attracting the private sector. Section 63 of the Act provides for participation

of suppliers on competitive basis in different segments which will further encourage private

sector for investment.

4.3 INSTALLED CAPACITY IN THE COUNTRY

The total installed generating capacity in the country as on 30.06.2013 is 225793 MW

distributed as below:

Thermal (including Coal, gas & diesel) 153848 MW

Hydro 39623 MW

Nuclear 4780 MW

Renewable Energy Sources* 27542 MW

The region-wise distribution of the total power supply and demand position in the country

during April 2009– March 2010 is given below in table 4.2:

Page 66: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 4. Power Scenario

Indo Canadian Consultancy Services Ltd. 63 P-1143

TABLE-4.2

ACTUAL POWER SUPPLY POSITION DURING APR 2011–MAR 2012

PERIO

D

PEAK

DEMAND

(MW)

PEAK

MET

(MW)

PEAK

DEFICIT/

SURPLU

S (MW)

PEAK

DEFICIT/

SURPLU

S (%)

ENERGY

REQUIR

EMENT

(MU)

ENERGY

AVAILABILI

TY (MU)

ENERGY

DEFICIT/

SURPLUS

(MU)

ENERGY

DEFICIT/

SURPLU

S (%)

NORTHERN

APR-

11-

MAR 12

40248 37117 -3131 -7.8 276121 258382 -17739 -6.4

WESTERN

APR-

11-

MAR 12

42352 36509 -5843 -13.8 290421 257403 -33018 -11.4

SOUTHERN

APR-

11-

MAR 12

37599 32188 -5411 -14.4 260302 237480 -22822 -8.8

EASTERN

APR-

11-

MAR 12

14707 13999 -708 -4.8 99344 94657 -4687 -4.7

N.EASTERN

APR-

11-

MAR 12

1920 1782 -138 -7.2 11011 9964 -1047 -9.5

4.4 POWER SCENERIO FOR NORTHERN REGION AND HIMACHAL PRADESH

4.4.1 Hydro Power Potentail in Northern Region

The Hydro Power Potential in the Northern Region is assessed as 53405 MW at 60% PLF

as indicated below in Table 4.3.

Page 67: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 4. Power Scenario

Indo Canadian Consultancy Services Ltd. 64 P-1143

Table 4.3

Particulars Potential Assessed

based on CEA

Principal Hydro Potential at 60 % Load Factor 30155

Feasible Installed Capacity in MW 53405

Potential in billion kWh per year 225

Pumped Storage Feasible Installed Capacity in MW 13065

Small Hydro (up to 15 MW) Potential in MW 3180

4.4.2 Status of Hydro and Thermal Power Projects in the Region

The installed capacity of hydro and thermal power projects and gross energy generation

as on 31.03.2012 in Northern Region is given in following table.

Table 4.4

States Hydro Thermal Nuclear R.E.S Total

Coal Gas Diesel Total

1 Chandigarh 50.74 27.09 15.32 0.00 42.41 8.84 0.00 101.99

2 Delhi 637.12 4193.46 1616.01 0.00 5809.47 122.08 18.53 6587.20

3 Haryana 1351.18 4734.99 560.29 3.92 5299.20 109.16 122.70 6882.54

4 H.P. 2842.94 118.30 61.88 0.13 180.31 34.08 527.66 3584.99

5 J&K 1523.03 263.70 304.14 8.94 576.78 77.00 130.59 2307.40

6 Punjab 2996.89 3208.19 288.92 0.00 3497.11 208.04 353.58 7055.62

7 Rajasthan 1502.80 5054.48 665.03 0.00 5719.51 573.00 2365.55 10160.86

8 U.P. 1774.42 9706.84 549.97 0.00 10256.81 335.72 686.98 13053.93

9 Uttarakhand 1988.18 261.26 69.35 0.00 330.61 22.28 185.87 2526.94

4.4.3 Power Generation and Sales in Himachal Pradesh

The year wise data on power generation and power purchase by the HPSEB from outside

w.e.f. 1980-81 has been depicted in the following table:

Page 68: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 4. Power Scenario

Indo Canadian Consultancy Services Ltd. 65 P-1143

Table 4.5 - Power Generated/Purchased

Generation Year Generation MU Electricity Purchased MU

1. 2. 3.

1980-81 245.07 265.41

1985-86 596.83 392.12

1989-90 935.51 887.58

1990-91 1262.40 1058.69

1991-92 1050.37 1200.72

1992-93 1087.38 1256.16

1993-94 976.60 1338.98

1994-95 1131.69 1685.43

1995-96 1285.42 1926.35

1996-97 1251.93 2065.58

1997-98 1306.008 2287.61

1998-99 1484.493 2333.831

1999-2k 1201.319 2520.149

2000-01 1153.321 2539.338

2001-02 1149.501 2588.836

2002-03 1277.929 2882.881

2003-04 1356.953 3936.958

2004-05 1295.410 4296.838

2005-06 1332.375 4918.951

2006-07 1432.375 5056.951

2007-08 1864.943 5433.371

2008-09 2075.138 6047.497

It would be seen that power generation, which was 245.07 MU in 1980-81, touched the

level of 1262.40 MU in 1990-91. The electricity generation process got a setback in the

year 1993-94, when it dipped to a level of 976.60 MU due to the blockage in the Satluj

river at Bhaba which brought the generation process to a halt. Thereafter, the generation

went up so rapidly that it touched the highest level in the year 2008-09. The shortfall in

over-all generation during 1999-2000 to 2006-07 is mainly due to less water availability at

power stations. During the year 2008-09, total electricity generation from own projects was

2075.138 MU.

Page 69: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 4. Power Scenario

Indo Canadian Consultancy Services Ltd. 66 P-1143

Table 4.6 – Sale of Power (Million KWH)

Year Sale within the state Sale outside the State Total

1. 2. 3. 4.

1980-81 264.73 147.13 411.86

1984-85 470.02 217.28 687.30

1985-86 563.32 223.93 787.25

1989-90 897.10 359.487 1256.587

1990-91 1008.74 717.715 1726.455

1991-92 1022.02 581.866 1603.886

1992-93 1083.28 581.749 1665.029

1993-94 1155.63 511.047 1666.677

1994-95 1339.68 752.721 2092.401

1995-96 1597.68 802.400 2400.08

1996-97 1757.61 732.453 2490.063

1997-98 1946.52 721.458 2667.978

1998-99 2083.42 713.289 2796.709

1999-2k 2181.741 681.985 2863.726

2000-01 2205.866 615.618 2821.484

2001-02 2331.860 548.837 2880.697

2002-03 2519.002 688.026 3207.028

2003-04 2726.324 1692.889 4419.213

2004-05 2954.156 1658.997 4613.153

2005-06 3568.689 1722.532 5291.221

2006-07 4300.439 1255.280 5555.719

2007-08 5028.655 1198.620 6227.275

2008-09 5460.507 1498.210 6958.717

It would be seen that sale of power within the State is on an increase and registered an

increase of 77.55 percent during 1984-85 over 1980-81 period. During 1989-90, the sale

within the State was 897.10 Million kwh and registered an increase of 90.86 percent over

1984-85 period. During 1994-95 the sale within the State was 1339.68 Million kwh and

registered an increase of 49.33% over 1989-90 period. During 1999-2000, the sale within

the State was 2181.741 Million kwh and registered an increase of 62.86% over 1994-95

period and during the last financial year 2007-08 the sale within the State was 5028.655

Million kwh and registered an increase of 16.93% over previous financial year 2006-07.

The power sale within and outside the State during 2008-09 was of the order of 6958.717

Million kwh. The aggregate availability being 8014.502 Million units, the transmission and

Page 70: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 4. Power Scenario

Indo Canadian Consultancy Services Ltd. 67 P-1143

distribution losses come to 1055.785 Million units, which accounted for 13.17% of the total

energy availability. However, it needs to be underlined that the aggregate figures of T&D

losses do not reflect the reality since a large volume of energy is also wheeled through the

system.

4.4.4 Power Consumption

The rate of electricity consumption is growing every year not only in Northern Region but

also throughout the country. Due to limited availability, the growth rate of electricity

consumption which averaged 12-19 % per annum compounded during the decade (1960-

61 to 1979-80) declined sharply to 6.54% during the decade (1970-71 to 1979-80). The

energy consumption has, however, increased to 5460.50 Million kWh in 2008-09 from

5028.656 Million kWh in 2007-08.

4.4.5 Sector - Wise Energy Utilization For Himachal Pradesh

The following are the main categories of electricity consumers.

Domestic

Commercial

Industrial

Government, Irrigation and WSS

Agriculture

Public lighting

Non Domestic/ Non Commercial

Temporary

Bulk/ miscellaneous

The trend in power consumption in the state among different categories is given below:-

Page 71: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 4. Power Scenario

Indo Canadian Consultancy Services Ltd. 68 P-1143

Table 4.7 – Power Consumption (Million KWH)

S.No. End Users Year

1991-92

At the

end of

8th plan

1996-97

At the

end of

9th plan

1997-02

At the

end of

10th plan

2002-07

Year

2007-08

Year

2008-09

1. 2. 3. 4. 5. 6. 7. 8.

1. Domestic 253.1

(24.7)

426.771

(24.28)

664.419

(28.49)

948.307

(22.05)

1058.812

(21.06)

1089.118

(19.95)

2. Commercial 83.7

98.2)

120.549

(6.86)

174.963

(7.52)

225.776

(5.25)

248.252

(4.94)

274.663

(5.03)

3. Industrial 467.7

(47.2)

910.622

(51.81)

1122.544

(48.14)

2553.520

(59.38)

3100.095

(61.65)

3385.303

(62.00)

4. Government

Irrigation &

WSS

94.8

(9.3)

149.334

(8.50)

202.258

(8.67)

324.881

(7.56)

334.973

(6.66)

389.331

(7.13)

5. Agriculture 29.8

(2.92)

11.375

(0.65)

18.048

(0.77)

26.404

(0.61)

26.653

(0.53)

28.738

(0.53)

6. Public

Lighting

3.2

(0.31)

6.158

(0.35)

9.135

(6.39)

11.355

(0.26)

12.609

(0.25)

13.013

(0.24)

7. Non

Domestic/

Non

Commercial*

63.386

(1.47)

77.349

(1.54)

80.585

(1.48)

8. Temporary * 19.370

(0.45)

23.407

(0.47)

22.705

(0.42)

9. Bulk/Misc. 70.2

(6.87)

132.797

(7.55)

140.493

(6.02)

127.461

(2.96)

146.505

(2.90)

177.050

(3.24)

Total 1002.00 1757.606 2331.860 4300.439 5028.656 5460.50

Note: Figures in parentheses are present shares of various end uses of energy for each year.

* Commercial category consumption upto FY 2001-02 is including Non Domestic Non Commercial/

temporary category consumption

The above data indicates that industrial consumption has increased to 3385.303 Million

Kwh at the end of the year 2008-09, which is 9.20% more than the consumption recorded

during the year 2007-08, which is the first year of the 11th Plan. It is interesting to note

Page 72: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 4. Power Scenario

Indo Canadian Consultancy Services Ltd. 69 P-1143

down that industrial consumption alone account for about 62% of the total consumption

which signifies the high rate of industrialization in the State.

The other interesting feature to note is that as compared to the year 2007-08 to 2008-09

there is slight increase in commercial consumption whereas marginal decrease in

domestic consumption of power. In agriculture the power consumption remained same

during the year 2007-08 & 2008-09, while in Govt. irrigation and water supply percentage

consumption has slightly increased as compared to the year 2007-08 to 2008-09.

4.4.6 Power Shortage in Northern India and Himachal Pradesh

It is seen from table 4.8, the requirement and availability of power for northern India during

2009-10 is 253803 MU and 224447 MU respectively, which amounts to a deficit of 29356

MU or 11.6%. The deficit of power is clearly evident almost all the years in Northern

Region and the availability/requirement of energy and peak power during last decade is

summarized in table 4.8.

TABLE-4.8

ACTUAL POWER SUPPLY POSITION IN NORTHERN REGION

Note: Peak Demand- 38021 MW, Energy Requirement – 239807 MU for the year 2008-09 (As per 17th

EPS Report), Occurrence of peak as per actual Power supply position in the month(s)- June, July & August

PERIOD PEAK

DEMAN

D (mw)

PEAK

MET

(mw)

PEAK

DEFICIT/

SURPLU

S (mw)

PEAK

DEFICIT/

SURPLUS

(%)

ENERGY

REQUIREM

ENT (mu)

ENERGY

AVAILAB

ILITY

(mu)

ENERG

Y

DEFICIT

/

SURPL

US (mu)

ENERGY

DEFICIT/

SURPLU

S (%)

9th plan end 23200 21346 -1854 -8 150383 142410 -7973 -5.3

2002-03 24092 21889 -2203 -9.1 156610 144218 -12392 -7.9

2003-04 23817 22271 -1546 -6.5 161595 152743 -8852 -5.5

2004-05 26834 24125 -2709 -10.1 175498 159358 -16140 -9.2

2005-06 28154 25200 -2954 -10.5 188794 168611 -20183 -10.7

2006-07 31516 26644 -4872 -15.5 202125 179986 -22139 -11

2007-08 32462 29495 -2967 -9.1 219797 196147 -23650 -10.8

2008-09 33034 29204 -3530 -10.7 224218 199928 -24290 -10.8

apr,09- mar

10

37159 31439 -5720 -15.4 253803 224447 -29356 -11.6

march 2010 31253 26843 -4410 -14.1 20956 18734 -2222 -10.6

Page 73: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 4. Power Scenario

Indo Canadian Consultancy Services Ltd. 70 P-1143

TABLE-4.9 ACTUAL POWER SUPPLY POSITION IN HIMACHAL PRADESH

Note: Peak Demand- 1176 MW, Energy Requirement – 6909 MU for the year 2008-09 (As per

17th EPS Report), Occurrence of peak as per actual Power supply position in the month(s)- July

4.5 STATUS OF RURAL ELECTRIFICATION IN HIMACHAL PRADESH

As per Census 2001, there were 17495 census villages in Himachal Pradesh. Of these,

110 census villages were un-electrified. Under RGGVY schemes, 108 villages of seven

districts namely Chamba, Kangra, Shimla, Mandi, Kinnaur, Lahaul & Spiti and Sirmour

have been covered and one village (Vari Koksar) of Lahaul Block has been covered for

electrification under R.V.E. plan by Director (Himurja). Only one village Chandori Dhar of

Mehla Block of District Chamba having migratory population still remains to be covered.

In addition to above, 4036 hamlets (out of total of 4182 as per 1988 survey) also stand

electrified upto September, 2009. Besides, 587 un-identified hamlets have also been

electrified.

In order to provide electricity in every household in the State, scheme for all the 12

districts has been sanctioned by the Ministry of Power, Govt. of India within a provision of

Rs. 341.80 crore.

Schemes for 11 districts namely Kangra, Hamirpur, Bilaspur, Una, Mandi, Sirmour,

Shimla, Solan, Kullu, Kinnaur and Lahaul & Spiti have been sanctioned during 11th Plan

amounting to Rs. 275.53 crore and Rs. 82.81 crore have been released as Ist installment.

The awards for these 11 districts have been placed and work is in progress. These

schemes are proposed to be completed within 18 months.

PERIOD PEAK

DEMAND

(mw)

PEAK

MET

(mw)

PEAK

DEFICIT/

SURPLUS

(mw)

PEAK

DEFICIT/

SURPLUS

(%)

ENERGY

REQUIREMENT

(mu)

ENERGY

AVAILABILITY

(mu)

ENERGY

DEFICIT/

SURPLUS

(mu)

ENERGY

DEFICIT/

SURPLUS

(%)

9th plan end 562 562 0 0.0 3293 3206 -87 -2.6

2002-03 770 770 0 0.0 3427 3341 -86 -2.5

2003-04 670 670 0 0.0 3439 3424 -15 -0.4

2004-05 678 671 -7 -1.0 4000 3917 -83 -2.1

2005-06 788 749 -39 -4.9 4302 4258 -44 -1.0

2006-07 873 873 0 0.0 5136 4996 -140 -2.7

2007-08 1061 1010 -51 -4.8 5992 5814 -178 -3.0

2008-09 1055 1014 -41 -3.9 6261 6246 -15 -0.2

apr,09- mar

10

1118 1158 40 3.6 7009 6762 -247 -3.5

march 2010 852 827 -25 -2.9 612 608 -4 -0.7

Page 74: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 4. Power Scenario

Indo Canadian Consultancy Services Ltd. 71 P-1143

4.6 REQUIREMENT OF CAPACITY ADDITIONS

As there is a persistent deficit in power supply, it is imperative to add new power projects

in Northern Region and Himachal Pradesh in particular to meet the energy demand in

different sectors. The Govt. of Himachal Pradesh is taking steps for accelerating the

growth in power sector. The Table below shows the details of month wise Power cuts

imposed on HPSEB system over the various years. The Table emphasizes on the need

for quick or accelerated growth in Hydro power development to meet the needs of ever

rising demand in electricity in Himachal Pradesh.

TABLE-4.10

Month wise detail of Power Cuts imposed on HPSEB System

S. No. Month 2004-05 2005-06 2006-07* 2007-08 2008-09 2009-10

1 April - - 46.53 3.08 15.97 24.95

2 May - 15.26 0.30 16.25 13.30 35.17

3 June - - 91.60 3.20 25.92 187.62

4 July - 0.52 40.30 7.48 33.80 31.8

5 August - 3.04 8.08 41.43 42.77 363.78

6 September - 3.95 12.46 19.62 17.21 278.68

7 October - 33.04 383.76 91.89 10.89 280.44

8 November 13.72 40.68 7.71 120.78 26.59 294.15

9 December 178.13 61.51 81.48 424.70 3.36 289.67

10 January 418.93 233.12 402.51 443.72 17.50 -

11 February 161 91.36 231.20 323.01 16.18 -

12 March 0 77.86 14.30 22.35 46.63 -

Total 771.78 560.34 1320.23 1517.51 270.12 1786.26

During 2004-05 Power cuts were imposed up till 14th Feb, 2005

During 2005-06 Power cuts were imposed up till 14th March, 2006

During 2006-07 Power cuts were imposed up till 14th Feb, 2007

* Including 100 MW relief during peak Load hours is from 07.12.2006 to 14.02.2007

4.6.1 Resources for Power Development In Northern Region

The Northern Region has insignificant coal resources and fossil fuels for power

development. On the other hand the region is endowed with large hydroelectric

resources, which account for 36% of the country’s total hydroelectric resources.

Exploitation of nuclear resources for the purpose of power development remains an

uneconomic and unreliable proposition due to inherent problems of operation and

maintenance and disposal of nuclear waste. The unfavourable location of the coal mines

with respect to the Northern Region and the extremely congested railway system make

Page 75: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 4. Power Scenario

Indo Canadian Consultancy Services Ltd. 72 P-1143

regular supply of coal to power plants in the Northern Region a difficult proposition besides

increasing the operation and maintenance costs. The most important and economical

source of power in the Northern Region, therefore, is the hydro resources located in

Uttarakhand, Himachal Pradesh and Jammu & Kashmir.

4.6.2 Power potential in the state of Himachal Pradesh – exploited and available

Himachal Pradesh is endowed with approximately 20,376 MW of hydroelectric potential in

its five river basins. Basin-wise distribution of the potential in H.P. is indicated in the Table

– 4.11 below:

TABLE- 4.11 S. No Basin Potential (MW)

1 Beas 4501

2 Ravi 2361

3 Satluj 8634

4 Yamuna 1049

5 Chenab 3267

6 Mini Micro Projects 564

Total 20376

The Northern Region is blessed with vast hydel potential, but is presently facing under

severe power shortage and the situation is likely to deteriorate further during the 11th and

12th plan periods unless additional schemes are taken up immediately and implemented

to derive timely benefits.

The Govt. of Himachal Pradesh is aware of the need for accelerated exploitation of its

resources and the responsibility it shares in meeting the power needs of the region. In this

context, the Himachal Pradesh State Electricity Board has a significant role to play in

mitigating power shortage in the northern region because of easy accessibility of potential

sites in the state besides being located close to the load centres. Accordingly, a good no.

of major and medium hydroelectric projects has been identified by the State

Government/Himachal Pradesh State Electricity Board for implementation to yield benefits

during 11th and 12th Five Year Plan Periods.

4.6.3 Existing and under investigation hydro projects.

Himachal Pradesh has total estimated harnessed potential of 20415 MW. Out of which

around 6370 MW is already under operation and remaining around 13321.48 MW is under

various stages of execution as detailed below:

Page 76: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 4. Power Scenario

Indo Canadian Consultancy Services Ltd. 73 P-1143

TABLE- 4.12: Hydro Power Status in H.P. (in MW)

Projects under Operation (i/c Himurja

Projects)

6370.12

Projects which are under execution/allotted

and planned for 11th Plan Period

5744.10

Projects which have been allotted/under

process of allotment and expected to yield

benefit during the 12th Plan period

5615.50

Projects which would have to be re

advertised

1481.00

Projects which have been abandoned due to

environmental considerations

435.00

Projects under investigation for preparation

of DPR

46.50

Himurja Projects proposed/under execution)

{750-26.60} [Under Operation - 26.60 MW]

723.40

TOTAL POTENTIAL 20415.00

4.7 PARTICIPATION BY PRIVATE SECTOR IN DEVELOPMENT OF HYDRO PROJECTS

Due to limited resources available with the Central and State Government, the Govt. of

India has approved the participation of private sector in the generation, supply and

distribution of electricity in the country in order to overcome existing and anticipated power

shortage. The Government of India has issued broad guidelines for allotment and

development of hydro power projects to private sector. The details of New Hydro Policy of

Himachal Pradesh on Privatisation are indicated below:

Selection of Developer on MOU Route allowed for projects up to 100 MW

Selection of Developer on ICB route for Projects above 100 MW.

No Clearances necessary from CEA for projects selected on competitive bidding

route for projects costing upto Rs. 2500 crores.

Secondary energy rate to be at par with primary energy. Premium on peak power

proposed.

Process of Transferring clearances to IPP’s simplified.

100% Foreign Equity permitted on the automatic approval route provided it does

exceed Rs. 1500 Crores.

Limit of 40% financing from Indian Financial Institutions waived off.

Page 77: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 4. Power Scenario

Indo Canadian Consultancy Services Ltd. 74 P-1143

Tariff determination by SERC/CERC.

Projects upto 25 MW to be transferred to MNES.

Moratorium of 5 years for payment of Electricity duty by companies which consume

electricity produced by them.

Government of Himachal Pradesh has actively promoted private sector participation in

development of hydro power sector and has issued separate policies for small projects up

to 25 MW, medium projects between 25MW and 100 MW, and large projects above 100

MW. The policy details are available on HPSEB web site - www.hpseb.com.

4.8 CLEAN DEVELOPMENT MECHANISM (CDM)

The Kyoto Protocol sets legally binding targets and timetables for cutting the greenhouse-

gas (GHG) emissions of industrialized countries. The limits on greenhouse-gas emissions

set by the Kyoto Protocol are a way of assigning monetary value to the earth's shared

atmosphere.

The Kyoto Protocol sets limits on total emissions by the world's major economies, a

prescribed number of "emission units." Countries not meeting their commitments will be

able to "buy" carbon credits from developing countries like India that have emission units

to spare.

Hydro power project does not lead to emission of GHG (CO2), whereas the fossil fuel

based power plants leads to emission of GHG (CO2). Thus the Tidong Hydroelectric

Project will result in mitigation in the emission of GHG and addressing the issue of global

warming and is hence eligible for benefits under the Clean Development Mechanism

(CDM) of Kyoto protocol. The project is proposed to be registered as a CDM Project.

4.9 NECESSITY OF THE PROJECT AND RELATED ASPECTS

From the growth of peak demand and anticipated installed generation capacity on the

basis of schemes proposed for benefits under construction / consideration during 10th and

early 11th Five Year Plan period, it is observed that power supply position in the Northern

region would become all the more acute from the start of 11th Five Year Plan and power

region shortages would have to be faced unless additional schemes are taken up

immediately and implemented to derive timely benefits. The most important source of

power development in the Northern region is its abundant hydro resources located in

Himachal Pradesh, Uttar Pradesh, Uttarakhand and Jammu & Kashmir. Priority would

have to be given to the development of these untapped resources because of the

following distinguishing features of the hydro stations.

Page 78: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 4. Power Scenario

Indo Canadian Consultancy Services Ltd. 75 P-1143

They exploit the most economic source of power development.

They provide the cheapest source of peaking capacity.

They enable improvement in the utilization of thermal/nuclear power stations in the

region.

They provide much needed operational flexibility to the system.

The need for the Tidong-1 Hydroelectric project has been considered in the context of

increasing demand of power in the northern region of India. It has been assumed in the

16th power survey that energy requirement increases @ 10% per annum each year. This

project will generate about 643 MU of energy during 90% dependable year and 100%

availability and shall partly meet the increase in energy requirement.

Thus, there is an urgent need of rapid hydro potential exploration for providing additional

generation capacity in the Northern region. Among the various sites, available for hydro

development, Tidong –I HEP is considered very attractive from point of view of deriving

benefits during 11th Five Year Plan.

Page 79: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 5. Topographical Survey & Investigations

Indo Canadian Consultancy Services Ltd. 76 P-1143

5 TOPOGRAPHICAL SURVEY AND INVESTIGATIONS

5.1 INTRODUCTION

M/s NSL Tidong Power Generation (P) Ltd has carried out detailed field

investigations/surveys for the Tidong – I Hydroelectric project for the purpose of design,

construction planning, preparation of layout plans, optimization of various parameters,

components of the project, cost estimate etc .

This chapter deals with topographic survey carried out to establish relative disposition of

various project components with respect to each other and with respect to the defined

benchmarks.

5.2 TOPOGRAPHICAL SURVEY

5.2.1 General layout

The topographical survey conducted for preparing the general layout extends to about 400

m on the upstream of the diversion works location and about 100 m downstream of power

house location on a scale of 1: 1000 with 10 m contour interval. Different alternatives

were studied and general layout has been finalised duly fixing the location of the diversion

barrage, intake structure, desilting basins , head race tunnel, surge shaft, pressure shaft

alignment and power house etc. In addition, surveys along alignment of approach road

required for project implementation has also been carried out. The major components of

project shown in general layout plan vide drawing no 1143-CC-103 and details are

discussed below:

5.2.2 Intake Area

An area covering 400 m upstream and 600m downstream of the diversion

barrage/desilting basin has been surveyed. Cross-Section of Tidong khad has been taken

along axis of diversion site at a regular interval of 50m. Profile of the river has also been

surveyed along 5 locations upstream of barrage axis and 16 locations downstream of

barrage axis. Survey plan of various components for Tidong-1 HEP are indicated in

drawing no. 1143-CD-202.

5.2.3 Head Race Tunnel

The water conductor system consists of 8504 m long Head Race Tunnel. The survey for

head race tunnel covered a strip of 75m on either side of tunnel alignment. The details of

survey for water conductor system are indicated in drawing no. 1143-CD-103.

Page 80: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 5. Topographical Survey & Investigations

Indo Canadian Consultancy Services Ltd. 77 P-1143

5.2.4 Surge shaft and Pressure Shaft

The area covering Surge Shaft extending up to a width of 50m on both side and Pressure

Shaft extending up to a width of 20m on either side of pressure shaft alignment has been

surveyed to a scale of 1:500 with contour interval of 5m.

The L-section of the Pressure Shaft has been prepared on scale of 1:1000. Details of

Surge Shaft area and Pressure Shaft alignment are given in drawing no. 1143-CD-501.

The L-section of pressure shaft alignment has been shown in drawing no 1143-CD-502.

5.2.5 Powerhouse Site

An area covering the locations of Power House, Transformer cum GIS hall and Tailrace

channel has been surveyed to a scale of 1:500 and plotted with contour interval of 5.00 m.

A cross-section of power house along the pressure shaft alignment has been prepared

and shown in 1143-CD-603. Details of the powerhouse location are given in drawing no.

1143-CD-601.

5.2.6 Approach roads

Approach road is made from Rispa Village to Surge Shaft, Powerhouse and Adit-2.

Survey with 10m contour interval has been carried out for the alignment of this road

network.

Survey was also carried out for road alignment on left bank of Tidong Khad for the

approach road to muck dumping yard as well as Adit-1 to Head Race Tunnel with 5.00m

contour interval. These approach roads have been indicated in drawing no 1143-CD-103.

5.2.7 Cross- Sections of Tidong khad

20 Nos of Cross-sections for Tidong khad have been prepared at the interval of 50.00 m.

These cross-sections were required for the area elevation curve and for calculating the

reservoir area and volume for the requisite storage.

5.2.8 Cross- Sections of Sutlej River

Three cross-sections of Sutlej River, near its confluence with Tidong khad have been

prepared for the selection of suitable location for the power house.

5.2.9 Plan and L- Sections

Plan and L-sections of Tidong khad as well as its tributaries have been prepared for the

planning of Head Race Tunnel and Adits to tunnel. Following are the plans and cross-

sections:

Page 81: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 5. Topographical Survey & Investigations

Indo Canadian Consultancy Services Ltd. 78 P-1143

Gara khad, Shicky khad, Rovang khad and Duba khad from bed level of Tidong

khad Junction up to EL 3000.00 m.

Tidong khad from the confluence of Lamber khad with Tidong khad up to the

confluence of Tidong khad with Sutlej river.

The implementation of Tidong - I HEP Phase – I with an installation of 2 x 50MW has been

taken up based on the above survey and investigations conducted. No fresh surveys and

investigations are required for the phase – II of project development.

Page 82: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 79 P-1143

6 HYDROLOGY

6.1 GENERAL

6.1.1 Introduction

Tidong-1 HEP proposes to utilize the hydropower potential available in lower reach of

Tidong khad, a tributary of Sutlej River in Kinnaur District of Himachal Pradesh. The

project proposes to utilize a gross head of about 610.977 m for generation of power. The

detailed project report for Tidong-1 having an installed capacity of 100 (2x50) MW was

prepared in 2006 and the power potential study was done based on hydrological flow

series developed from Baspa river flow and one year measured river discharge data of

Tidong. It was recommended in DPR that discharge series shall be updated upon

availability of further measured discharge values of Tidong khad to confirm the data series

obtained by regression analysis.

A gauge site was installed for discharge measurement on Tidong khad in December 2004.

The Gauge site is located near the proposed Intake, downstream of the confluence of

Lambar khad and Tidong khad. Presently, about ten years of measured discharge data is

available at intake site of Tidong 1 HEP. From this data, it is observed that significantly

higher monsoon period flows are available in the river as compared to river flow estimated

at the time of DPR preparation. In view of the higher value of actual flow measurement,

the feasibility of increasing the installed capacity has been studied and the details on

hydrological study are indicated in this chapter.

6.1.2 Project Location

The project has been contemplated as a run-of-the river scheme. The river bed level at

diversion site is EL 2880.00m. The catchment area of Tidong khad up to intake point and

the project components are located between the latitude 31 20’ 30” N to 31 33’ 30” N

and longitude 78 22’ 10”E to 78 47’ 50”E.

6.2 BASIN CHARACTERISTICS

6.2.1 Major river Basin: Sutlej River Basin

Sutlej rises from beyond Indian borders in the Southern slopes of the Kailash mountain

near Mansarover lake from Rakas lake, as Longcchen Khabab river (in Tibet). It is the

largest among the five rivers of Himachal Pradesh. It enters Himachal at Shipki (EL 6,608

metres) and flows in the South-Westerly direction through Kinnaur, Shimla, Kullu, Solan,

Mandi and Bilaspur districts. Its course in Himachal Pradesh is 320 km long from

Rakastal, with famous tributaries viz. Spiti, Ropa, Taiti, Kashang, Mulgaon, Yula, Wanger,

Throng and Rupi as right bank tributaries, whereas the Tirung, the Gayathing, the Baspa,

Page 83: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 80 P-1143

the Duling and the Soldang khad are left bank tributaries. Its total catchment area in

Himachal Pradesh is 20,000 sq. km.

6.2.2 Tidong khad basin

The Tidong khad is a left bank tributary of Sutlej river. It originates in the North Western

slopes of Great Himalayas ranges at an altitude of 6740 m. It mostly flows in South-

Easterly to North-Westerly direction. A number of Nallas join Tidong khad up to its

confluence with Sutlej river, just upstream of Tirung village in District Kinnaur of Himachal

Pradesh.

The total catchment area of Tidong khad at diversion site is 497.86 km2 out of which

418.36 km2 lies under permanent snow line (EL 4200m).

6.3 CLIMATE

In general, Tidong catchment is cold desert and being a dry zone, the precipitation during

monsoon is low. In winter, the temperature can drop below freezing point and in summer,

the weather remains pleasant.

The study region is upstream of the dividing line between climatic zone-I and III of

northern India. Zone-I, the tropical Monsoon climate, extends from the Indian ocean north

as far as Wangtoo, with its effects modified by the elevation and topography. The tropical

monsoon climate involves an annual rainfall in excess of 1000mm, occurring mostly in the

month of June to October. The study region, however, experience little rainfall as the

mountains between plains and the study region captures most of the precipitation.

Climatic zone III, the arid mountain climate affects the Tibetan and western China Plateau.

Due to effect of Tibetan and western China plateau, the winters are cold and dry where as

summers are hot and dry. From November to May, the region experiences a generally

north-easterly flow of cold continental air moving out from across the Tibetan plateau. The

effect of this flow is somewhat modified by the mountains but it can result in high winds.

There is no temperature recording station inside the catchment. Measurements of

maximum daily temperature are being made by different agencies at following sites. Also

the temperature observations have been recently started at Kalpa and Jeori from 1984.

Available significant data of the temperature is given in table 6.1 (a):

Page 84: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 81 P-1143

Table 6.1 (a)

Station Maximum

Temperature (oc)

Minimum

Temperature (oc)

Period

Shimla 30 -7.2 1956-70

Bilaspur 45.5 -2.0 1956-70

Kalpa 27 -9.5 1984-85

Jeori 40 -3.0 1984-85

Monthly mean temperature (maximum and minimum) and relative humidity at 8:30 AM

and 5:30 PM for Kalpa metrological station have been given in table 6.1 (b)

Table 6.1 (b)

Station

MONTHLY MEAN

TEMPERATURE (oC)

MONTHLY MEAN RELATIVE

HUMIDITY

Maximum

Temperature

Minimum

Temperature

8:30 AM 5:30 PM

January 6.1 -2.9 61 56

February 9.2 -1.6 50 44

Mach 17.5 3.5 32 23

April 19.6 5.3 47 40

May 21.4 7.2 45 38

June 22.7 9.2 61 50

July 24.5 12.1 72 52

August 22.0 11.8 85 75

September 22.9 9.6 69 55

October 16.3 2.9 59 56

November 15.2 0.7 38 41

December 11.5 -0.7 44 31

6.4 PRECIPITATION

Precipitation in the Tidong khad catchment area occurs mostly in the form of snow, which

can be described as moderate to heavy depending upon the altitude.

Average annual precipitation is of the order of 630 to 700 mm, most of which is received in

the form of snow during winter months. Though snow measurement has not been done

however some records are available for rainfall and water equivalent of snow.

There are at present five rain gauge stations in the catchments around the project site.

Long term records are available at these stations and are being regularly published by

Indian Meteorological department. The relevant details of these stations are given in the

following table:

Page 85: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 82 P-1143

Table 6.2 (a)

Station District Altitude (in metre) Year of

Commencement

Purbani Kinnaur 2285 1951

Kalpa Kinnaur 2530 1951

Sangla Kinnaur 2590 1951

Kilba Kinnaur 2200 1882

Nichar Kinnaur 1830 1930

There is no regular and systematic record of snowfall at any station in the catchment.

Although snow observations have been started at some stations i.e. Purbani, Kalpa, Kilba

and Nichar from 1984.

The Rainfall and snowfall observations are being conducted in a conventional manner.

There is no self recording rain gauge/snow gauge station in the catchment up to weir site.

Rainfall recorded at Morang Tehsil for 2001 to 2004 and at Kalpa metrological station for

year 2004 are given in Table 6.2 (b)

Table 6.2 (b)

Months

Station

Morang Kalpa

2001 2002 2003 2004 2004

January 3.60 35.20 33.3 149.7 117.50

February 34.10 149.10 209.9 16.3 53.90

Mach 69.40 22.60 38.2 0.00 5.70

April 7.10 108.60 126.7 46.9 46.00

May 10.10 24.34 33.7 18.3 40.10

June 12.50 0.00 13.7 1.4 4.80

July 6.50 0.00 25.3 14.2 25.90

August 33.50 23.60 11.2 28.4 53.00

September 2.40 34.40 0 0.00 5.90

October 0.00 2.40 0 32.3 185.50

November 8.80 0.00 0 0.00 0.00

December 34.6 0.00 60.1 7.80 31.80

Total 222.6 400.24 552.1 315.3 570.10

Snowfall data for the years 2000-2005 recorded at Kalpa, which is the nearest

observatory, is given in the following table.

Page 86: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 83 P-1143

Table 6.2 (c)

Sl No. Months Snowfall in mm

2000 2001 2002 2003 2004 2005

1. January 49.1 20.6 87.2 45.5 115 140

2. February 90.4 28.0 165.6 139.9 52.3 155.2

3. March 82.0 24.2 140.4 85.6 0.0 46.6

4. April 0.0 0.0 10.0 16.0 0.0 3.3

5. May 0.0 0.0 0.0 0.0 0.0 0.0

6. June 0.0 0.0 0.0 0.0 0.0 0.0

7. July 0.0 0.0 0.0 0.0 0.0 0.0

8. August 0.0 0.0 0.0 0.0 0.0 0.0

9. September 0.0 0.0 0.0 0.0 0.0 0.0

10. October 0.0 0.0 0.0 0.0 18.0 0.0

11. November 0.0 4.0 0.0 6.4 0.0 0.0

12. December 30.8 48.5 1.8 75.1 16.2 2.2

Total 252.3 125.3 405.0 368.5 201.5 347.3

6.5 SOURCE OF RUNOFF

The flow regime of the stream in this region is complex. Mostly runoff is contributed by

rainfall/snowfall melting, ground water and springs. However, contribution from snowmelt

is significant.

The discharge of Tidong khad is lowest in winter months of November to February and

starts increasing from March due to melting of snow. The snowmelt generally occurs in the

period from March to June. The rainfall occurs during the monsoon period, from July to

September. The bulk of discharge is contributed in months from May to August.

6.6 SEDIMENT LOAD

Major catchment area contributing discharge in tidong khad is snow fed and hence the

river water has very less silt during most of the time in year. But in monsoon season, water

contains a small quantity of silt. Silt analysis is done for the samples collected in the month

of July and August 06. Results of silt analysis are appended in annexure-6.a. During

winter, water is quite clear and free from all kind of impurities. The streambed is

characterized by accumulation of boulders of different sizes along the course of the

stream. The sizes of such boulders vary from small pebbles to big boulders of size up to

3m in diameter.

Page 87: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 84 P-1143

6.7 WATER QUALITY

The water in the stream is free from any kind of pollution during winter. It is also suitable

for drinking purposes as well as for construction activities in this period. However, it is

muddy during monsoon months.

6.8 GAUGE & DISCHARGE (G&D) SITE

A discharge measurement site has been installed in December 2004 near the proposed

diversion site. A straight reach of Tidong khad is available at this location with uniform flow

conditions. The waterway width is kept as 12 m for discharge measurements guided by

Gabion wall on both the banks.

At site, following arrangements have been set up for establishing G&D site:

The total width of 12m at gauging site is divided into 6 sections of equal width.

The depth is being measured in each section at 7AM, 12 noon and 5 PM on daily

basis.

For velocity measurement, Float method is used.

Ropeway of adequate capacity along with pulley, Wire & Cradle arrangement for

movement across the River for facilitating measurement of depth of flow by

sounding and velocity by float method.

6.9 DISCHARGE MEASUREMENTS

6.9.1 Methodology

The flow in the mountainous river changes seasonally and from year to year, due to

temporal and spatial variation in precipitation. The flow pattern of Tidong khad is no

exception to this and it follows the trend of Himalayan rivers in which most of the runoff is

available during monsoon months of July to September. Winter rains swell the river flow to

some extent for a short duration during the months of December to February. During

these winter months, the river runoff is usually minimum. Tidong khad receives perennial

flow.

Discharges of Tidong khad at Lumber village gauging sites is measured by surface float

method. Surface floats are made up of well seasoned heavier type wood available locally.

Heavier floats are generally preferred so that its greater part would be submerged in water

thus reducing influence of the wind. Cableways have been installed across the river for the

purpose of taking observations. Two wire ropes have been stretched across the river

section, one at the beginning and other at the end of the selected river reach for

conducting observations. The distance between two ropes known as float run has been

kept as 12 m at Lumber village discharge sites. The ropes have been marked at 2 m

intervals to divide the river cross-section into different segments. The centerline of the

Page 88: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 85 P-1143

segment defines the path or track of the float. A third rope has been stretched 12 m

upstream of test reach. The gauge reader rides in a jhulla attached with the cable with a

pulley arrangement and drops floats in different segments 12m upstream of the float race

so that floats acquires uniform velocity by the time they reach float race. Three floats are

dropped in each segments and mean of the time taken to traverse the float race is

considered. The time of travel of test reach of only those floats which follows there correct

track is recorded.

The cross section area has been divided into segments, each of 2m width. Cross-section

is checked before and after monsoon and after every major flood in the river.

Discharge in each vertical is arrived at after multiplying corresponding average velocity

and cross-sectional area of each vertical. Total discharge is calculated by adding

discharge values of each vertical. Discharge is being measured three times a day the

discharge calculations at 7:00 AM, 12:00 PM and 5:00 PM from 1st December, 04

onwards.

Measurement of velocity = (Float Run / Time taken by float to cover float run.)

Mean velocity is generally determined by taking average of the velocities measured at

depths, 0.2 and 0.8 times the total depth from the surface. Float measurements represent

surface velocity, thus velocities measured by float are multiplied by 0.89 to determine

mean velocity of flow.

Mean velocity of flow= 0.89 X Surface velocity.

Mean velocity V1,V2,-------- in each segment is obtained after multiplying the surface

velocities by 0.89. The velocities are multiplied by area of cross-section of corresponding

segment to obtain discharges in each segment. Summation of discharges in each

segment gives discharges in the river.

Q = A1V1 +A2V2+A3V3+--------

Q= Q1+Q2+Q3-------------

6.10 DESIGN FLOOD DISCHARGE

Flood discharge is calculated using the Dicken’s empirical formula as well as by method

based on unit hydrograph principle in Central Water Commission Report no-1/73.

The total catchment area at gauging site is worked out as 497.86 km2. This is further

bifurcated as rain fed area of 79.50 km2 and snow fed area of 418.36 km2.

6.10.1 Dicken’s Empirical Formula

The flood estimation has been done by the use of Dicken’s empirical formula

Page 89: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 86 P-1143

QF = C x A3/4

Where C is the constant = 12 and

A is the rain fed Catchment area.

At diversion site A= 79.50 km2

QF = 12 x (79.50)3/4

= 319.49 m3/sec

6.10.2 Unit Hydrograph Method

CWC Report No. WH/22/1994 & 1/73

In this approach, the design storm after converting it into effective rainfall is applied to the

unit hydrograph to obtain the design flood. Detail steps have been followed referring report

no. WH/22/1994.

Total area of catchment (C.A) = =

497.86 sq km

192.2 sq mile

Area of catchment below contour 4200m (A = =

79.5 sq km

30.687 Sq mile

Length of the longest stream (L) = =

24.975 km

14.4845 mile

Length of the longest stream from a point opposite

to C.G of the catchment to the pt. of study (Lc)

= =

10.2 km

6.32 mile

Weighted mean slope (SLc)= =

RL(m) RL(ft) Li(Km) Li(ft) Di (ft) Si Li/sqrt(Si

) 4200 13482 4000 12840 1.04 3338.4 642 19.23 0.24 3900 12519 9.35 30013.5 321 1.07 9.04 3700 11877 0.32 1027.2 642 62.50 0.04 3500 11235 2.35 7543.5 642 8.51 0.81 3300 10593 7.625 24476.25 642 2.62 4.71 3100 9951 4.05 13000.5 642 4.94 1.82 3000 9630 0.24 770.4 321 41.67 0.04

24.975 Total 16.69 SLc= 0.14% = 0.0014 Since SLc is less than 0.0028

Peak value (QTp=16000A3/4Slc2/3) = 10508.40Cusec

Duration of rainfall excess (tc=255/(Qtp/A)0.9) = 6.96 hrs

Page 90: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 87 P-1143

The point rainfall values corresponding to a 50-yr return period storm and for various durations

have been read from the isopulvial maps of India Meteorological departments, Aerial to point

reduction factor is taken from table-A chapter-6 of report 1/73 of CWC and the aerial rainfall

corresponding to different durations as below:-

Duration

Point rainfall vol (mm) of 50 yr return period

Areal to point R/fall ratio (%)

Areal R/fall

Hourly areal

R/fall of Design storm

Read from IMD mapsRead depth duration curve Fig-3.10

0.25 hr 30 29 - - 0.5 hr 40 49 57.53 28.17 -

0.75 hr 58 61 - - 1 hr 70 69 67.63 46.79 46.79 2 hr 89 75.84 67.79 21.00 3 hr 60 101 79.79 80.75 12.96 4 hr 110 82.24 90.13 9.38 5 hr 116 83.95 97.46 7.33 6 hr 80 121 85.25 103.50 6.04 7 hr 126 86.09 108.39 4.89 8 hr 130 86.94 112.84 4.45 9 hr 100 133 87.78 116.95 4.11

10 hr 136 88.29 120.34 3.40 11 hr 139 88.81 123.51 3.17 12 hr 100 142 89.32 126.49 2.98 13 hr 144 89.68 129.09 2.60 14 hr 146 90.04 131.55 2.46 15 hr 100 148 90.40 133.89 2.34 16 hr 150 90.66 135.99 2.10 17 hr 152 90.93 137.99 2.00 18 hr 153 91.19 139.92 1.92 19 hr 155 91.40 141.67 1.76 20 hr 156 91.61 143.37 1.69 21 hr 158 91.82 145.00 1.63 22 hr 159 91.99 146.52 1.52 23 hr 161 92.16 147.98 1.47 24 hr 115 162 92.33 149.40 1.42

Runoff for a long duration storm ( 24 hrs) for hilly region is given by R=0.6H1.2 where, R= Runoff in inches H= Aerial rainfall in inches

Page 91: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 88 P-1143

For aerial rainfall of 24 hr duration and 50 year return period, H=149.40 mm

=5.89 inches R=5.03 inches

=127.88 mm Average loss rate per hour = 0.897mm per hr Aerial rainfall of 50-yr return period and 6.96hr duration= 30.03 mm = 1.18 inches Maximum runoff excess of 6.96hr duration is given by Qtc= 10508.40 Cusec

Peak flood hydrograph due to rainfall excess of 1.18 inches and duration of 6.96 hrs= 12433.3

Cusec Taking adjustment factor for the effect of temporal distribution of rainfall excess of 1.075 Peak flood hydrograph excluding base flow = 13365.9 cusec = 378.21cumec Adding base flow @ 5.0 cusecs per sq mile with entire catchment contributing,

Design peak flood = 14326.72694cusec = 405.40cumec = 405.00cumec

6.10.3 Ryve’s Formula

Ryve's Formula :-

QP = C1A2/3

where,

QP, C1 and A have the same meaning as in Dicken's formula.

C1 for areas near hills = 10.1

QP = 186.738 cumecs

Flood estimation was also worked out based on Gumble’s and Ven-Te-Chow method also

but the same found to give very low values which are not comparable with the actual

expected flood in Tidong khad. Therefore, these values have been discarded.

6.10.4 Design flood proposed to be adopted

On the basis of above methods following results are obtained:-

Page 92: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 89 P-1143

Table 6.3

S.No Method Flood Discharge

1 Dicken’s formula 319.49 m3/sec

2 CWC ReportNo.H/2/1994 & 1/73 405.00 m3/sec

3 Ryve’s Formula 186.74 m3/sec

To be on safer side, it is proposed to adopt design flood of 405 m3/sec computed by unit

hydrograph approach which is based on physical as well as climatic parameters of the

Tidong catchment.

6.11 DISCHARGE DATA

6.11.1 Available Discharge Data

The available data for carrying out the Hydrological analysis are listed below.

i. Measured ten daily discharge data for Baspa River at Sangla from 1965 to 1972

and then from 1977 to 2001. The gap in the data is filled by developing

correlations between ten daily flow at Sangla and ten daily flow at Wangtoo on

river Sutlej.

ii. Discharge data of Baspa at Sangla from Jan 2002 to Dec 2014, excluding the

period of Jan 2003 to May 2003 collected from Baspa HEP.

The data of (i) & (ii) is presented in Annexure-6.1.

iii. Discharge data of Tidong khad near Lamber from 23rd June 95 to Dec 95, Feb 96

to Mar 96, March 1997 to December 1998 and January 2003 to November 2004

(Measured by HPSEB). This data is given in Annexure-6.2.

iv. Discharge data measured by NSL Tidong Power Generation (P) Ltd near

diversion site of Tidong-1 HEP from December 2004 to December 2014. (This

data is given in Annexure-6.3).

6.11.2 Analysis of available data

Discharge data at serial no 6.11.1 (i) and (iii) was mainly used along with 1 year measured

flow data of Tidong khad for development of long term flow series at intake site of Tidong

1 HEP in DPR finalized in 2006. The long term flow series has been updated based on

measured flow data of Tidong Khad and measured flow of Baspa khad from 2004 to 2014.

From the above available data set, long term data of Tidong khad derived from the Long

term measured discharge data of Baspa at Sangla and discharge data of Tidong near

Page 93: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 90 P-1143

Lamber. The following alternative studies have been made to estimate long term flow

series at intake site of Tidong – I HEP:

Method-I : Regression analysis between 10 daily concurrent period discharge of

Baspa at Sangla and Tidong at diversion site from Dec 04 to March 14.

Method-II :Seasonal regression analysis for concurrent period 10 daily discharge

of Baspa at Sangla with Tidong discharge (two regression equations, first for June

to September and second for November to May).

Method-III :Long term discharge data generated by catchment area proportionate

method using the following equation.

Tidong discharge = Baspa discharge at Sangla X [(catchment area of Tidong khad/

catchment area of Baspa at Sangla site)]

Annual flow volume derived from above methods is compared with the actual measured

annual flow volume for the period between 2005-06 and 2013-14 and depicted in the

following curve.

It is seen that the annual inflow estimated from the three alternative methods follows the

same pattern as the annual inflow computed from measured flow at Tidong intake

location.

Discharge series derived by annual regression analysis between discharges of Baspa

river (at Sanlga) and Tidong discharge gives realistic results for development of long term

discharge series. It is observed that results obtained by use of Method –1 are comparable

Page 94: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 91 P-1143

with the actual discharge measurement, therefore long term discharge series as obtained

by Method-1 have been adopted for further power potential studies.

Based on annual regression analysis between Baspa discharge and Tidong khad

discharge measured, coefficient of correlation works out as 0.785. The coefficient of

correlation is within acceptable range and hence the long term discharge data of Tidong –

I HEP (Phase – II) at intake location has been generated using annual regression analysis

between Baspa discharge data at Sangla and NSL discharge data at Lamber village site.

This data has been utilized to compute 50%, 75% and 90% dependable year discharge.

Fig-6.1 (Regression Curve)

The Adopted linear regression equation for deriving the long term discharge data is:

y = 0.3862 X + 5.3163

R = 0.886

Where y is the discharge value for Tidong at Lamber and X is the Baspa River discharge

at Sangla.

Long term discharge data for Tidong-1, derived from Baspa Long Term discharge data by

different method is listed in Annexure- 6.4, 6.6 and 6.8.

By considering the annual inflows and applying Weibul's distribution formula, the 90%,

75% and 50% dependable years have been worked out, the computations are indicated in

Annexure 6.5, 6.7 and 6.9.

Page 95: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 92 P-1143

6.12 FLOW DURATION CURVE

Variability of stream flow is studied using flow duration curves. Discharge is plotted against

the % of time the flow exceeded.

Fig-6.2

Flow duration curve for Tidong khad shows the following results:

Design Discharge of 19.2 cumecs for 100 MW installed capacity is available for

35.5 % of time i.e. 130 days.

For 50% of time i.e. 183 days, minimum discharge of 11.73 cumecs is available.

For 75% of time i.e. 274 days, minimum discharge of 8.71 cumecs is available.

For 90% of time i.e. 329 days, minimum discharge of 7.60 cumecs is available.

In the lower reach of flow duration curve, major discharge is contributed by base flow,

which is available throughout the year and hence, the curve in this portion is almost flat.

The middle reach of flow duration curve has mild slope. Discharge in this portion is

contributed by snowmelt having low variations compared to rainfall.

The upper reach of flow duration curve has steep slope compared to middle portion

because major discharge is contributed by rainfall.

Flow duration curve of Baspa River and Tidong River are compared and the result is

shown in figure 6.3.

Page 96: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 93 P-1143

Fig-6.3

The above flow duration curve indicates that:

For 50% of time i.e. 183 days, minimum discharge of 17.49 cumecs is available in

Baspa river as against 11.73 cumecs in Tidong River.

For 75% of time i.e. 274 days, minimum discharge of 9.40 cumecs is available in

Baspa river as against 8.71 cumecs in Tidong River.

For 90% of time i.e. 329 days, minimum discharge of 7.50 cumecs is available in

Baspa river as against 7.60 cumecs in Tidong River.

The flow duration curve of Tidong khad and Baspa River shows similar trend.

Corresponding to power output of 100 MW, the design flow for Tidong I HEP is estimated

as 19.2 cumecs. With increase in installed capacity proposed in Phase II of the project, the

design flow for 150 MW capacity is estimated as 28.65 cumecs. Flow duration curve of

Tidong River shows that design discharge of 28.65 cumecs is available for 26.29% of the

time i.e. for 96 days a year. Hence plant will run at 150MW generation capacity for 96

days in a year.

6.13 FURTHER STUDY

Hydrology for the Tidong-1 HEP shall be updated based on further availability of discharge

measurements at intake location and for Baspa khad. These measurements will continue

till the completion of the project construction

Baspa Data

Tidong

Page 97: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 94 P-1143

ANNEXURE-6 a

Silt analysis data and results

Silt data:

Date of sampling

Silt content PPM (mg/l) Size > 0.212 mm

0.075mm <Size < 0.212 mm Size < 0.075 mm

13.07.05 3 6 1158

20.07.05 24 78 377

27.07.05 128 104 625

01.08.05 21 61 249

08.08.05 110 449 1535

16.08.05 55 293 1356

Results:

Size > 0.212 mm

0.075mm <Size < 0.212 mm Size < 0.075 mm

Maximum 128 449 1535

Minimum 3 6 249

Average 56.83 165.17 883.33

Page 98: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 95 P-1143

ANNEXURE – 6.1

Discharge Data of Baspa River at Sangla (1978-79 to 2014-15)

Page 99: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 96 P-1143

ANNEXURE – 6.1

Discharge Data of Baspa River at Sangla (1978-79 to 2014-15)

Page 100: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 97 P-1143

10 Daily discharge measured by HPSEB Annexure-6.2

MONTH PERIOD 1995 1996 1997 1998 2003 2004

JAN

I NA NA NA 3.25 4.35 3.58

II NA NA NA 3.09 4.25 3.56

III NA NA NA 3.09 3.99 3.77

FE

B

I NA 2.51 NA 2.75 3.40 3.51

II NA 2.47 NA 2.60 3.47 3.45

III NA 2.30 NA 2.67 3.51 3.55

MA

R

I NA 2.32 2.03 2.70 3.76 3.58

II NA 2.48 2.34 2.85 4.19 3.84

III NA 2.95 2.66 2.80 5.28 3.63

AP

R

I NA NA 2.95 2.87 5.22 4.70

II NA NA 2.86 3.19 9.06 4.62

III NA NA 3.06 3.80 16.65 6.21

MA

Y

I NA NA 3.50 9.37 20.11 5.02

II NA NA 3.57 15.17 30.73 10.67

III NA NA 5.09 28.29 53.01 9.04

JUN

I NA NA 6.39 26.49 40.33 10.70

II NA NA 10.65 18.86 31.32 18.56

III NA NA 16.88 34.39 36.89 17.03

JUL

I 15.90 NA 26.53 36.03 51.72 13.16

II 18.05 NA 33.33 37.83 42.17 8.42

III 21.91 NA 36.45 30.95 42.05 9.59

AU

G

I 19.18 NA 31.67 30.80 39.61 10.90

II 16.42 NA 22.89 29.55 25.51 11.25

III 15.30 NA 19.05 24.82 16.70 7.80

SE

P

I 14.73 NA 16.41 24.47 14.19 4.97

II 8.30 NA 15.92 14.53 10.54 5.04

III 5.70 NA 11.93 12.85 7.60 3.74

OC

T

I 5.22 NA 8.82 7.56 6.88 3.64

II 4.19 NA 7.07 5.44 6.59 3.43

III 3.39 NA 6.11 5.51 5.64 3.24

NO

V

I 2.95 NA 5.35 4.55 5.20 3.17

II 2.69 NA 4.30 4.29 4.91 3.08

III 2.35 NA 3.69 4.04 4.61 3.26

DE

C

I 2.72 NA 3.46 3.78 4.30

II 2.74 NA 3.60 3.50 3.90

III 2.55 NA 3.31 NA 3.70

Page 101: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 98 P-1143

ANNEXURE-6.3

DISCHARGE DATA MEASURED BY NSL ( 2004-05 TO 2013-14 )

Month 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12 2012-13 2013-14 2014-15

JUN

12.15 17.20 12.90 14.60 18.20 24.90 26.70 37.10 36.09 23.71

23.12 20.00 25.80 25.70 15.70 26.30 35.90 40.30 40.73 37.31

43.22 37.00 36.40 41.40 35.10 49.40 45.30 49.40 52.32 30.36

Jul

58.08 64.90 46.90 59.90 43.30 52.30 54.30 41.60 37.76 35.80

62.20 69.10 51.50 69.10 47.70 53.60 59.80 35.10 31.56 39.82

60.97 67.10 56.90 67.10 51.40 54.70 68.80 34.60 34.62 41.35

AUG

58.10 67.30 54.70 65.80 52.10 56.20 73.50 34.20 31.11 40.26

52.49 54.40 49.80 57.20 49.40 49.70 78.20 32.30 30.05 36.27

46.73 48.40 47.00 50.60 43.80 42.20 78.20 32.70 31.19 28.98

SEP

31.45 36.50 35.80 36.00 30.90 34.50 59.80 31.50 31.83 20.08

20.54 27.10 27.80 26.50 22.60 23.70 78.20 29.90 30.08 14.18

18.37 21.40 21.90 20.00 19.40 20.22 43.30 25.70 25.89 11.87

OCT

12.90 14.20 14.50 12.60 17.60 16.10 36.40 21.80 22.55 8.76

8.60 9.10 9.10 11.00 12.20 12.30 31.60 14.10 14.15 6.46

7.50 7.40 7.70 8.30 8.70 10.80 22.70 12.00 12.24 5.55

NOV

6.90 7.20 7.30 7.40 7.90 8.40 15.14 9.50 9.84 4.90

7.00 6.60 7.00 6.90 7.40 7.70 15.20 7.90 10.66 4.31

6.00 5.80 5.90 6.10 6.80 7.40 13.40 6.80 13.53 3.94

DEC

5.33 5.80 5.90 6.10 6.10 6.40 7.80 10.80 5.70 10.72 3.76

5.48 6.30 6.40 6.40 6.40 6.60 8.10 8.60 5.10 8.57 3.69

5.49 6.90 6.80 6.90 6.80 6.90 7.70 7.80 5.10 7.84 3.67

JAN

4.53 6.90 6.70 6.90 6.90 6.80 7.50 6.20 6.60 7.48

5.41 6.40 6.20 6.70 6.70 6.20 7.80 7.00 7.00 7.84

4.61 6.30 6.30 6.30 6.30 6.30 7.90 7.20 7.20 7.85

FEB

4.79 6.40 6.60 6.60 5.80 6.20 8.20 7.00 7.00 8.21

4.93 6.50 6.70 6.70 6.00 6.30 8.50 6.50 6.50 8.49

4.75 6.80 6.50 6.80 6.20 7.20 8.90 6.80 7.60 8.92

MAR

4.82 6.60 6.60 6.50 7.00 7.50 8.50 8.10 8.10 8.54

5.67 7.10 7.00 7.00 7.10 8.50 10.10 7.90 7.90 10.09

5.29 6.70 8.00 6.70 7.40 8.90 11.70 8.20 8.20 11.67

APR

5.21 7.50 7.30 6.30 6.20 8.20 8.90 8.80 8.90 8.72

5.95 7.90 7.60 7.30 7.10 10.30 9.50 10.50 9.90 9.37

7.94 8.70 9.00 9.30 8.40 13.70 11.50 12.50 16.00 11.34

MAY

10.73 9.40 11.60 10.60 9.90 17.30 13.60 13.30 18.00 15.52

10.88 11.10 11.60 11.00 13.00 22.80 18.30 16.00 26.50 14.13

10.71 14.60 10.00 12.60 17.60 29.80 24.30 28.70 37.60 14.91

Page 102: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 99 P-1143

Page 103: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 100 P-1143

ANNEXURE - 6.5

DEPENDABLE YEAR CALCULATION : REGRESSION METHOD

Rank Annual Flow

(MCM) Year

Probability of Exceedance

1 1099.31 1999-00 2.7%

2 1016.70 2000-01 5.4%

3 997.99 2001-02 8.1%

4 965.45 2002-03 10.8%

5 925.93 1998-99 13.5%

6 898.40 2011-12 16.2%

7 888.30 1978-79 18.9%

8 844.18 1995-96 21.6%

9 801.65 1997-98 24.3%

10 725.25 1994-95 27.0%

11 723.16 1996-97 29.7%

12 695.18 2003-04 32.4%

13 677.29 1983-84 35.1%

14 667.62 1985-86 37.8%

15 650.91 2010-11 40.5%

16 649.36 1990-91 43.2%

17 641.32 2008-09 45.9%

18 632.10 2006-07 48.6%

19 625.23 1992-93 51.4%

20 620.04 1984-85 54.1%

21 611.38 2012-13 56.8%

22 604.57 1982-83 59.5%

23 596.37 2009-10 62.2%

24 594.36 1979-80 64.9%

25 594.29 2005-06 67.6%

26 593.28 2013-14 70.3%

27 589.88 1980-81 73.0%

28 584.91 1989-90 75.7%

29 578.30 2007-08 78.4%

30 555.36 1987-88 81.1%

31 550.67 1981-82 83.8%

32 531.48 1986-87 86.5%

33 511.17 1988-89 89.2%

34 493.37 2004-05 91.9%

35 489.50 1991-92 94.6%

36 419.01 1993-94 97.3%

Page 104: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 101 P-1143

Page 105: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 102 P-1143

ANNEXURE - 6.7

DEPENDABLE YEAR CALCULATION : SEASONAL REGRESSION METHOD

Rank Annual Flow

(MCM) Year

Probability of Exceedance

1 1042.41 1999-00 2.7%

2 975.33 2000-01 5.4%

3 956.73 2001-02 8.1%

4 947.08 2002-03 10.8%

5 898.40 2011-12 13.5%

6 897.52 1998-99 16.2%

7 867.32 1978-79 18.9%

8 830.18 1995-96 21.6%

9 793.92 1997-98 24.3%

10 728.84 1994-95 27.0%

11 728.40 1996-97 29.7%

12 706.43 2003-04 32.4%

13 688.87 1983-84 35.1%

14 682.81 1985-86 37.8%

15 667.76 1990-91 40.5%

16 650.91 2010-11 43.2%

17 644.23 1992-93 45.9%

18 642.10 1984-85 48.6%

19 641.32 2008-09 51.4%

20 632.10 2006-07 54.1%

21 629.13 1982-83 56.8%

22 620.66 1979-80 59.5%

23 616.42 1980-81 62.2%

24 612.94 1989-90 64.9%

25 611.38 2012-13 67.6%

26 596.37 2009-10 70.3%

27 594.29 2005-06 73.0%

28 593.28 2013-14 75.7%

29 587.19 1987-88 78.4%

30 583.79 1981-82 81.1%

31 578.30 2007-08 83.8%

32 568.41 1986-87 86.5%

33 551.65 1988-89 89.2%

34 535.58 2004-05 91.9%

35 533.62 1991-92 94.6%

36 473.31 1993-94 97.3%

Page 106: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 103 P-1143

Page 107: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 6. Hydrology

Indo Canadian Consultancy Services Ltd. 104 P-1143

ANNEXURE - 6.9

DEPENDABLE YEAR CALCULATION : CATCHMENT AREA PROPORTIONATE METHOD

Rank Annual Flow

(MCM) Year

Probability of Exceedance

1 1235.95 1999-00 2.70%

2 1131.03 2000-01 5.41%

3 1106.11 2001-02 8.11%

4 1104.51 2002-03 10.81%

5 1010.11 1998-99 13.51%

6 959.99 1978-79 16.22%

7 900.14 1995-96 18.92%

8 897.82 2011-12 21.62%

9 844.57 1997-98 24.32%

10 742.78 1994-95 27.03%

11 740.00 1996-97 29.73%

12 701.77 2003-04 32.43%

13 677.90 1983-84 35.14%

14 666.02 1985-86 37.84%

15 650.91 2010-11 40.54%

16 641.69 1990-91 43.24%

17 641.32 2008-09 45.95%

18 632.10 2006-07 48.65%

19 611.38 2012-13 51.35%

20 609.55 1992-93 54.05%

21 602.63 1984-85 56.76%

22 596.37 2009-10 59.46%

23 594.29 2005-06 62.16%

24 593.28 2013-14 64.86%

25 582.02 1982-83 67.57%

26 577.71 2007-08 70.27%

27 567.41 1979-80 72.97%

28 562.46 1980-81 75.68%

29 555.84 1989-90 78.38%

30 515.48 1987-88 81.08%

31 510.22 1981-82 83.78%

32 484.66 1986-87 86.49%

33 457.60 1988-89 89.19%

34 433.89 2004-05 91.89%

35 427.81 1991-92 94.59%

36 334.83 1993-94 97.30%

Page 108: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 7. Geology & Geotechnical Aspects

Indo Canadian Consultancy Services Ltd. 105 P-1143

7 GEOLOGY AND GEOTECHNICAL ASPECTS

7.1 INTRODUCTION

The project layout for phase II development involving installation of 50 MW necessitates

modifications in part of Pressure shaft in (Y-Piece), Surge Shaft and Powerhouse. The

already excavated Adit-4 would serve as the additional pressure shaft by providing T-

Junction . Engineering carried out for Phase-I (100MW ) for Barrage and appurtenant

structures and head race tunnel remain unchanged. The updated geological assessment

has been done for the project components that require modification due to phase II

development, viz. surge shaft, Y-Junction, additional Pressure Shaft (Adit-4) and

Powerhouse. All required geological studies for these components have been completed

and their construction is in progress. The progress of construction at the site as of 31

January 2015 is as given in Table.1. The geological details of components to be modified /

constructed due to phase II development are discussed in following paragraph.

Table.1: The progress of construction of project components

S.No. Components Progress Remarks

1. Barrage 50-60% Under progress 2. Desilting Tank Nil To be done 3. Intake Nil To be done 4. Adit-1 to 5 & Valve House

Adit 100% Completed

5. HRT 95% Only 190.00m length out of 8.5km long HRT is remaining for excavation

6. Surge Shaft 15% Pilot shaft completed 7. Pressure Shaft Excavations 100% Completed

8. Powerhouse 40% Under progress

7.2 UPSTREAM WORKS

No modification is required in upstream works due to proposed enhancement in installed

capacity from 100 MW to 150 MW. The structure is founded on gentle overburden slope

comprising river borne material. This material consists of grey sandy- gravelly matrix with

rounded to sub rounded boulders of granite, gneiss and quartzite. At downstream side,

granitic gneiss/granite is found exposed up to the river bed level.

The intake structure is located in exposed coarse grained, white to off-white to pinkish

granitic gneiss. Foliation is not prominent but dipping north-easterly from 40o-58o. Granitic

gneiss is hard and compact and slightly weathered at surface. Three sets of main joint

sets dissect the strata and include N140-170/78o-85o, N115-130/25o-35o and N195-

210/25o-40o.

Page 109: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 7. Geology & Geotechnical Aspects

Indo Canadian Consultancy Services Ltd. 106 P-1143

The Rock Mass Quality (‘Q’) is considered Fair to Good.

7.3 SURGE SHAFT

The surge shaft modification involves increase in diameter from 8.00m to 10.00m. The

structure lies in off white to yellowish white, medium to coarse grained and slightly

weathered granitic gneiss. At the surface, the joints are open up to 5cm and filled with silty

sand and vegetation. These are expected to be tight at shallow depth. The depth of

overburden varies from 1 to 5 m at this location. The rock is dipping N30oE/58o. Three joint

sets dissect the strata resulting in large wedges due to higher spacing. The granitic gneiss

has Good to Fair Rock Mass Quality (‘Q’).

7.4 T-JUNCTION

The already excavated T-Junction at the intersection of Adit-4 and Pressure Shaft would

serve as the location for placement of T-piece of the additional penstock pipe. In the

vicinity, both the pressure shaft and the adit have been excavated in Fair Quality (‘Q’)

quartzite and phyllitic schist. The marginal enlargement of the junction for accommodating

the T-piece is not expected to pose any problem. However, the already erected steel

supports at this location would be removed and reinstalled to suit the larger dimension of

the opening. The geological map covering the site is appended as Plate.1 with this report.

7.5 PRESSURE SHAFT (ADIT-4)

The additional penstock pipe would be laid along the already excavated Adit-4. The adit

has been excavated in quartzite and phyllitic schist. The rock quality is found to be Fair

(‘Q’). The adit remains excavated and unsupported for over 36 months and corroborates

the rock mass classification. The adit, however, has been provided steel supports at its

inlet and exit at pressure shaft. No additional work in this adit is involved with the

modifications in the layout proposal.

7.6 POWERHOUSE

The modification in the powerhouse structure for accommodating additional unit involves

its extension on conventional left side. The powerhouse area is located within quartzite

and phyllitic schist dipping N200/30, i.e. into the hill (Photo.1, Plate.1). Large variations in

dip directions may be expected due to the possibility of the dips being rolling type. Besides

bedding joints, viz N200/30 (J1), three sets of joints are recognized at the site. These

include J2: N300/75, J3: N040/20 and J4: N030/70. Thick colluvium deposits occur at the

base of the rock cliffs forming the valley face. The rock is very well exposed in the hill face

above the colluvium deposit. By virtue of its proximity to the Tidong-Satluj confluence, the

site is dominated by alluvial deposits close to the river.

Page 110: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 7. Geology & Geotechnical Aspects

Indo Canadian Consultancy Services Ltd. 107 P-1143

No fresh or further Geological studies are required to be conducted for Phase II installation

of additional 50 MW unit than what studies are conducted for phase I of 100 MW Tidong- I

HEP

Photo.1: Site photograph illustrating major geological features.

At the selected powerhouse location, the bedrock is found exposed on the left side and

lies below shallow overburden immediately to its right (Plates 2&3). Immediately away

from the powerhouse location on right side, the overburden of colluvium assumes greater

thickness, but, is of no consequence to the structure. The extended portion of the

powerhouse would rest over exposed bedrock and, hence, is considered free from any

geotechnical problem.

The geology of the powerhouse site is illustrated in the detailed geological map of the site

on 1:1000 scale and two geological sections along the pressure shaft alignment and

across the extended portion of the powerhouse structure. These are appended as Plates

2&3.

Page 111: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 7. Geology & Geotechnical Aspects

Indo Canadian Consultancy Services Ltd. 108 P-1143

Page 112: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 7. Geology & Geotechnical Aspects

Indo Canadian Consultancy Services Ltd. 109 P-1143

Page 113: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 7. Geology & Geotechnical Aspects

Indo Canadian Consultancy Services Ltd. 110 P-1143

Page 114: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 8. Power Potential Studies

Indo Canadian Consultancy Services Ltd. 111 P-1143

8 POWER POTENTIAL STUDIES

8.1 GENERAL

Tidong HEP envisages utilization of discharges in Tidong khad, a tributary to Satluj River.

It is intended to run the power plant during lean season as peaking station which will be

based on the reservoir operation, and provide peaking capacity benefits of 100 MW for

about 4 hours per day in phase I and 150 MW for 3 hours in Phase II of project

development. The power generated at this project is intended to supplement and partly

meet the growing power requirements of Himachal Pradesh as well as Northern regional

grid of Indian Power supply system. Due to improved water availability series, NSL

proposes to increase the installed capacity of the project. The present study comprises the

analysis of energy generation with power plant capacity ranging from 100MW to 200 MW

so as to arrive at the optimum project capacity in Phase II development due to improved

hydrological series.

8.2 HYDROLOGICAL DATA

A detailed analytical study of hydrological data as prescribed for the project has been

presented in Chapter VI ‘Hydrology’. On the basis of this study, the ten daily discharge

series has been developed with 90% dependability for intake site. Further, it is considered

that a discharge corresponding to 15% of minimum discharge in the lean period ( Dec to

Feb ) arrived at by taking the weighted average of the above 3 months from measured

data for 10 years by NSLTPGPL shall be released in the natural path of the Tidong

stream to meet the D/s ecological flow considerations. It can be observed from the

discharge data in Annexure 6.3 that the minimum discharge works out to 6.7 Cumecs

and 15% of this works out to be 1.0 cumec. Thus, ecological flow release of 1.0 cumec

has been considered from every ten daily discharge data of the 90 % dependable year

flow series for carrying out power potential study. The 90% dependable year discharge

series after deducting the sacrificial discharge is tabulated below in Table 8.1 and shall be

used to carry out power potential of the project:

Page 115: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 8. Power Potential Studies

Indo Canadian Consultancy Services Ltd. 112 P-1143

Table 8.1

90% Dependable year : 2004 – 2005

Month Days River

Discharge (Cumecs)

Discharge after ecological

release (Cumecs)

June 10 18.18 17.18 10 29.48 28.48 10 27.23 26.23

July 10 34.83 33.83 10 32.68 31.68 11 31.04 30.04

August 10 36.15 35.15 10 35.64 34.64 11 26.58 25.58

September 10 19.86 18.86 10 21.07 20.07 10 13.41 12.41

October 10 12.25 11.25 10 11.09 10.09 11 10.30 9.30

November 10 9.88 8.88 10 9.52 8.52 10 9.00 8.00

December 10 9.03 8.03 10 8.88 7.88 11 8.64 7.64

January 10 7.86 6.86 10 7.52 6.52 11 7.53 6.53

February 10 7.43 6.43 10 7.54 6.54 8 7.37 6.37

March 10 8.00 7.00 10 8.22 7.22 11 8.18 7.18

April 10 8.34 7.34 10 9.54 8.54 10 12.71 11.71

May 10 16.46 15.46 10 16.28 15.28 11 14.14 13.14

Page 116: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 8. Power Potential Studies

Indo Canadian Consultancy Services Ltd. 113 P-1143

8.3 HEAD

The net operating head, which is expected to be available for the turbines, have been

estimated from the data tabulated below as Table 8.2:

Table 8.2

8.4 COMBINED TURBINE GENERATOR EFFICIENCIES OF THE UNIT

Corresponding to the rated head of 588.92 m, Pelton turbine has been considered for the

project. The power plant shall run as peaking station which will be based on the reservoir

operation i.e running the machines within the operating head range w.r.t. FRL & MDDL

levels of the reservoir and at rated load.

During monsoon when the water is in abundance, the machines can operate continuously

on rated load/overload upto 20%.

The weighted average efficiency of TG unit considered for power potential study is

90.551%.

8.5 METHODOLOGY FOR POWER POTENTIAL ANALYSIS

The methodology adopted for Power potential analysis comprises of calculating the

generation pattern for the power plant at various capacities ranging from 100MW to

200MW at rated net head and weighted TG efficiency of 90.551%, and considering the

plant availability of 95% when all the three machines are in operation

Further, calculation and analysis of the various parameters such as unrestricted energy

available from the discharge, restricted energy generated from the plant, plant load factor,

power potential exploitation for various power plant capacities is also done.

Maximum (full reservoir) level at Reservoir EL 2873.75 m

Minimum draw down level EL 2860.75 m

Runner Centerline EL 2258.44 m

Maximum tail water level EL 2252.00 m

Rated Gross head 610.977 m

Maximum gross head 615.31 m

Minimum gross head 602.31 m

Head loss in water conductor system 22.06 m

Rated Net head 588.92m

Page 117: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 8. Power Potential Studies

Indo Canadian Consultancy Services Ltd. 114 P-1143

The unrestricted energy for the project has been assessed 671.12 million units in a 90%

dependable year and considering the ecological flow of 1 cumecs. Without considering

ecological flow, the unrestricted energy is computed as 716.94 million units.

8.6 POWER POTENTIAL ANALYSIS

For the purpose of optimization of the installed capacity of the project, an analysis on the

energy extracted throughout the year for 90% dependable year discharge, considering

ecological flow is indicated in Annexure 8.1. A brief comparison of parameters considered

for optimum installed capacity is shown below in the Table 8.3.

Table 8.3

Comparison of various parameters for 90% dependable year discharge series

Sl. No.

Plant cap.

Net Generation

PLF Incr.

Energy

Incr. Capacity

Utilization Potential Exploited

(MW) (MU) (%) (KWh/KW) (%) (%)

1 100 539.43 61.58% Base Base 80.38%

2 110 561.29 58.25% 2186.00 24.95% 83.64%

3 120 580.11 55.19% 1882.00 21.48% 86.44%

4 130 598.79 52.58% 1868.00 21.32% 89.22%

5 140 617.49 50.35% 1870.00 21.35% 92.01%

6 150 632.63 48.15% 1514.00 17.28% 94.27%

7 160 645.82 46.08% 1319.00 15.06% 96.23%

8 170 656.30 44.07% 1048.00 11.96% 97.79%

9 180 664.15 42.12% 785.00 8.96% 98.96%

10 190 670.14 40.26% 599.00 6.84% 99.85%

11 200 671.13 38.31% 99.00 1.13% 100.00%

Note: “Net generation “is calculated considering plant availability of 95%

The incremental energy per kW of installed capacity (kWh/kW), corresponding to different

installed capacities in a 90% dependable year is presented in fig 8.1.

Page 118: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 8. Power Potential Studies

Indo Canadian Consultancy Services Ltd. 115 P-1143

Fig. 8.1

From Table 8.3 and Fig 8.1, it is analyzed that there is no appreciable increase in the

generation and capacity utilization by increasing the capacity any further from 150 MW.

The plant load factor at this installed capacity is at the optimum value of 48.15% which is

well acceptable for a hydropower project of this size. Besides, it can also be observed that

the potential has been exploited to the extent of 94.27% as against the unrestricted

energy of 671.12 MU by the plant capacity of 150MW. Additional capacity utilization up to

180 MW can be harnessed due to extra discharge available during the monsoon &

summer season with the inherent continuous overloading capacity of 10% to 20% in the

TG unit.

8.7 NUMBER OF GENERATING UNITS

The number of Generating units in the power station are fixed primarily with consideration

of harnessing the potential power to the maximum extent i.e with increase in the number

of generating units it is intended that even the lean discharges could also be exploited

efficiently, however, with the increase in the nos. of units the power house size, cost of the

electromechanical works and cost of the operation & maintenance of the generating units

increases thus increasing the overall project cost. Since, Tidong HEP is envisaged as

peaking power station based on the reservoir operation having sufficient storage for

peaking, the Generating units shall not run at lesser load conditions with respect to less

discharge during lean season, as during the lean season the stream discharges shall be

accumulated in the reservoir and upon filling of the reservoir the machines shall run at full

load. As the existing phase I development of the project envisages installation of 2 units of

50 MW each, it is recommended to provide an additional 50 MW in phase II of project

development leading to total installed capacity of 150 MW for the project.

Page 119: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 8. Power Potential Studies

Indo Canadian Consultancy Services Ltd. 116 P-1143

8.8 CONCLUSION

Based on the above analysis, the total plant capacity of 150MW with three numbers of

generating units of 50 MW each is recommended, with 2 units being installed in phase I

and one unit of 50 MW being installed in phase 2 of project development.

Page 120: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 8. Power Potential Studies

Indo Canadian Consultancy Services Ltd. 117 P-1143

Page 121: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 9. Civil Structures & HM Equipment

Indo Canadian Consultancy Services Ltd. 118 P-1143

9 CIVIL STRUCTURES & HYDRO-MECHANICAL EQUIPMENT

9.1 GENERAL

The civil structures for Tidong – I under Phase I of project development have been

planned to divert and convey water from Tidong khad for generating power in a surface

power house by utilising a maximum gross head of 615 m. The main components of

Phase – I are being executed and under final stage of construction. The main works of the

project comprise a barrage, a head regulator, two desilting basins for removing the silt

particles down to 0.2 mm size and a headrace tunnel, a surge shaft, a pressure shaft, a

surface power house to accommodate 2 generating units of 50 MW each, a tailrace

channel for carrying the tail water back to Tidong khad. The general layout of the project

features under phase I development and one additional bay in power house for phase II

development are shown in drawing no 1143-CD-103. The design features and provisions

of the different components of the scheme are discussed in the following paragraphs. The

provisions are based on detailed designs and dimensioning, taking into account all

essential design parameters. Before implementation of the project, necessary

investigations were carried out to obtain all necessary design parameters and detailed

designs were done for each component, considering the fresh input parameters.

9.2 HEADWORKS AT UPSTREAM

The head works on Tidong khad comprise of a conventional non-gated Barrage,

Diversion channel, Head regulator, Desilting basins, a Storage Reservoir and Intake for

Head Race Tunnel. The general arrangement is shown in drawing no1143-CD-201.

9.2.1 Location

Barrage structure is located across Tidong khad at El 2880.00m downstream of

confluence of Lamber khad with Tidong khad. Based on the topography of the area and

requirement of space for locating the head regulator, desilting basin structure, and

reservoir, the barrage structure has been located downstream of confluence of Tidong

khad with Lamber khad. The orientation of the barrage axis has been so fixed that the

design flood discharge is guided smoothly.

9.2.2 Design Flood

The barrage structure has been dimensioned for passing a discharge of 50 year return

period flood computed as 405 m3/sec. The high flood level for this flood discharge using

Manning’s formula works out to El 2889.00 m for the given khad reach for a bed gradient

of 1 in 13 and value of rugosity coefficient as 0.6.

Page 122: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 9. Civil Structures & HM Equipment

Indo Canadian Consultancy Services Ltd. 119 P-1143

9.2.3 Waterway

The average bed level of the khad at barrage site is at about El 2880.00 m. The crest

level of the undersluice is kept at El 2875.50 m. The crest level of the spillway is kept at El

2881.75m, i.e., 6.25m higher than the crest level of the undersluice bays. With the above

crest levels of undersluice and spillway bays and keeping the afflux of 1.00 m, the clear

water-way requirement works out to be 20.00 m and the same has been provided for the

barrage. One un-gated bay of 20 m width and two bays of 5.00 m width each have been

provided for Spillway & under sluice portions respectively. Total width between abutments

including piers works out to 39.50m. No modification in waterway width is required for

phase II development, as there is no change in flood discharge.

9.2.4 Pond Level

The pond level at upstream of the barrage has been fixed at El 2881.75m from the

topographical and hydraulic considerations. Upstream HFL considering afflux of 1.00 m

works out to El 2889.40 m.

9.2.5 Undersluice Bay

Two bays of 5.0 m width each have been provided to pass gravels & debris collected in

gravel trap. Total floor length of 117.00 m, including sloping glacis, has been provided. At

upstream and downstream end of concrete floors, cut-offs to required depth have been

provided to reduce uplift and safe exit gradient. Plan and section of undersluice bays have

been shown in Drawing no. 1143-CD-202 and 1143-CD-203 respectively. No change in

undersluice bay is required for phase II development.

9.2.6 Spillway

An ungated spillway of 20.00m width has been provided to pass 405 m3/s flood. Total

floor length of 117.00m has been provided comprising upstream floor, sloping glacis and

downstream floor. A cut-off extending up to El 2871.00 m on upstream floor and El

2865.00m on downstream floor has been provided to protect the floor from scour action.

Plan and section of barrage bays have been shown in Drawing no. 1143-CD-202 and

1143-CD-203 respectively. No change in spillway arrangement is required for phase II

development.

9.2.7 Energy Dissipation

The energy is dissipated with a hydraulic jump by providing a suitable stilling basin

downstream of the glacis. The stilling basin level and length have been computed for

various flood discharge. On the basis of this study, the lengths worked out to about 68.00

m and 66.00m for the undersluice and spillway respectively.

Page 123: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 9. Civil Structures & HM Equipment

Indo Canadian Consultancy Services Ltd. 120 P-1143

9.2.8 Protection Works

On upstream and downstream ends of the impervious floor, a bed protection comprising of

concrete blocks has been provided. Beyond the concrete blocks on both upstream and

downstream. loose boulder protection is also provided.

Downstream block protection

Pervious concrete block protection of size 1500x1500x900 mm arranged in four rows has

been provided beyond the downstream end of the impervious floor over 600 mm thick

graded inverted filter. The length of downstream block protection has been provided as

1.5 times the design scour depth below the floor.

Loose Stone Protection

Beyond the cement concrete block protection on the downstream end, launching apron of

loose boulders/stone has also been provided to spread uniformly over the scoured slopes

upto the design depth of scour below the floor level.

9.2.9 Diversion channel

Construction of undersluice and spillway bays has been completed and no further river

diversion works are required for phase II development.

9.2.10 Raft, Pier and Abutment

The barrage impervious floor is of R.C.C. raft founded on bouldery strata. Deep R.C.C.

cut-offs are provided all around the periphery of undersluice & spillway structures.

R.C.C. piers monolithic with raft are provided for the barrage structure. The height of the

piers is provided from the consideration of free board and the stability of structure against

sliding.

Divide wall between the undersluice and spillway is provided for creating smooth flow

conditions in front of head regulator and to check the cross flows upstream & downstream

of the barrage floor.

The length of the abutment is kept the same as the length of the barrage floor. The top

levels of the abutments are fixed with adequate freeboard over the computed upstream

and downstream H.F.L. and from consideration of bridge requirements.

Page 124: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 9. Civil Structures & HM Equipment

Indo Canadian Consultancy Services Ltd. 121 P-1143

9.2.11 Vertical Lift Gates and Stoplogs

Vertical Lift Gates

Two numbers Vertical lift gates for clear opening of size 5.00 m x 3.00 m are provided for

the undersluice. These gates are meant for flushing the silt and boulders deposited in the

upstream of the barrage, and are designed for closing under self weight.

Each Vertical lift gate shall consist of an upstream skin plate supported by vertical

stiffeners and horizontal girders, which in turn transfer the water pressure through the end

vertical girders, wheels and embedded wheel tracks to the concrete. The wheels shall be

equipped with anti-friction roller bearings of the self-aligning type with a ‘Line contact’

between the wheel and the track. To prevent leakage, hollow bulb music note type side

rubber seals shall be attached with the skin plate on the upstream side, and flat wedge

type rubber seals at the bottom. The material of the rubber seals conforms to IS:11855.

In order to limit the longitudinal and transverse movements of the gate in either direction, a

minimum of two guide shoes shall be provided on each side of the gate. The structural

design of the gate embedded parts including selection of materials for various

components of the gate shall be in accordance with provisions of IS:4622.

The Undersluice gates shall be operated by means of independent electrically operated

hoists of 10 tonnes capacity. Undersluice gates shall also be provided with a facility of

manual operation in the event of electric supply failure, in accordance with IS:6938. The

equipment shall be supported on hoist bridges located on steel overhead structures

designed in accordance with IS:800.

Stoplog

Provision of one set each of stoplogs along with two sets of embedded parts for

underluices has been kept for the purpose of maintenance and inspection of the main

gates. Each set shall consist of 2 equal interchangeable sliding type units for the

undersluices.

Each unit shall consist of an upstream skin plate supported by vertical stiffeners and

horizontal girders, which in turn transfer the water pressure through the end vertical

girders, slide blocks and embedded bearing plates to the concrete. To prevent leakage,

hollow bulb music note type side rubber seals shall be attached with the skin plate on the

upstream side and flat wedge type rubber seals at the bottom. In order to limit the

longitudinal and transverse movements of each unit in either direction, a minimum of two

guide shoes shall be provided on each side of the unit. The structural design of the

stoplogs, embedded parts including selection of materials for various components of

stoplogs shall be in accordance with provisions of IS:5620. The stoplogs shall be

operated under balanced head conditions, except the raising of top unit, which shall be

done under unbalanced conditions against a head equal to its height. The stoplogs of

Page 125: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 9. Civil Structures & HM Equipment

Indo Canadian Consultancy Services Ltd. 122 P-1143

undersluice shall be operated by means of a common electrically operated mono rail

crane hoist of 10 tonne capacity through an automatic lifting beam, as per IS:13591,

which shall engage and disengage automatically with stoplogs in required position. The

crane shall be equipped with pendant type push button switch capable of operating from

El 2894.00 m. When not in use, two units of undersluice stoplogs shall be dogged.

9.3 HEAD REGULATOR

The head regulator has been located on the left bank of Tidong khad. Its orientation is to

suit topography of the site as well as orientation of the desilting basin.

The sizing of head regulator structure has been verified to draw maximum flow of 35.00

cumecs to the desilting basin under phase II of project development. Two bays of 3.6 m

each have been provided to give clear waterway of 7.20 m. Two bays have been provided

to feed the two separate bays of the desilting basin independently to facilitate functioning

of the other row when one of the desilting rows is isolated for maintenance. The crest of

the structure has been provided at El 2877.40m which is about 2.0 m higher than the

undersluice floor to prevent the rolling bed load from entering the head regulator. A

trashrack comprising a steel framed structure with bar spacing of 75 mm centres has been

provided at the upstream end to prevent entry of any floating/suspended matter. The

hydraulic design of head regulator has been checked for satisfactory operation under both

phase - I and phase – II of project development. The required discharge can be tapped

with the upstream water level at about 2881.75 m. The requirement of maximum

discharge, when the three units are running at overload, can also be met when the

upstream water levels are at or higher than 2881.75 m.

Service and Emergency Gates

2 numbers vertical lift fixed-wheel type Head Regulator Service gates of size 3.6 m x

4.35m have been provided for regulating the discharge in the water conductor system and

these shall be designed to close under self weight, with or without the addition of ballast.

The gate shall consist of an upstream skin plate supported by horizontal beams and

vertical stiffeners which in turn transfer the water pressure through the end vertical girders,

wheels and embedded wheel tracks to the concrete. The cantilever mounted wheels shall

be equipped with sleeve type bronze bushings with a ‘Point contact’ between the wheel

and the track. To prevent leakage, hollow bulb music note type side rubber seals shall be

attached with skin plate on the upstream side and flat wedge type rubber seals at the

bottom. In order to limit the transverse movement of the gate, the wheels have been

flanged on one side whereas for limiting longitudinal movements a guide plate with

rounded face shall be fixed on to the end vertical girders on the upstream side. The

structural design of the gate embedded parts including selection of materials for various

components of the gate shall be in accordance with provisions of IS: 4622.

Page 126: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 9. Civil Structures & HM Equipment

Indo Canadian Consultancy Services Ltd. 123 P-1143

The gates shall be operated by means of independent electrically operated rope drum

hoists with a facility of manual operation in the event of electric supply failure, in

accordance with IS:6938. The equipment shall be supported on hoist bridges located on

steel overhead structures designed in accordance with IS: 800.

Provision of one number vertical lift fixed-wheel type Emergency gate of size 3.6 m x

4.35m along with two sets of embedded parts has been made for maintenance, inspection

and reports of service gates of the head regulator. The layout of the Emergency gate has

been made identical to the service gates. The gate shall be capable of being lowered

under flowing water conditions under its own weight with addition of ballast, if required.

The gate shall be operated by means of an electrically operated mono rail crane hoist

through an automatic lifting beam as per IS : 13591 which shall engage and disengage

automatically with gate in required position. The crane shall be equipped with pendant

type push button switch capable of operating from El 2895.0 m. The mono rail support

frame shall be integrated with the hoist supporting structure of the main gates. When not

in use, the emergency gate shall be stored by dogging at the top of any one of the gate

slots. However, an idle bay shall be planned beyond the left abutment of the head

regulator for maintenance purposes.

9.4 FEEDER CHANNEL

The end of the head regulator structure has been connected to desilting basins by feeder

channels with a provision of a suitable transition to ensure smooth flow conditions. The

width of feeder channel throughout the length is 3.60 m. In Feeder Channel, the bed level

varies from El 2877.40 m to El 2874.26m. The structure is divided into two separate

channels by providing a divide wall in continuation of the head regulator pier for isolating

any of the two hoppers of desilting basin for maintenance.

9.5 DESILTING BASIN

The desilting basin is located on the left bank, downstream of the head regulator, and

comprises two longitudinal chambers. A short transition channel, between each bay of the

desilting basin, is proposed of which the width varies from 3.60 m at the end of feeding

channel from each bay of head regulator to 9.50 m at the entry to the desilting basin.

Desilting basin is designed to remove particles of size 0.2 mm or above. The maximum

flow through velocity is 0.25 m/s when the water level is at El 2881.25 m.

Each chamber of the desilting basin is 80.50 m long including transition of 5.00m, 9.50m

wide and 9.15m deep with 2.5m wide central longitudinal flushing trench. Its bed level

lowers from El 2872.6 m to 2871.40m. At the end of each chamber, a weir at El.

2880.00m keeps the water level in desilting basin at 2881.25m at full discharge. No gate is

provided at the outlet of desilting basin for maintenance purposes due to 6.50m level

difference between weir level in desilting and maximum water level in reservoir (El

Page 127: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 9. Civil Structures & HM Equipment

Indo Canadian Consultancy Services Ltd. 124 P-1143

2873.50m). Both the longitudinal flushing trenches are connected to a common flushing

pipe, 1.5 m dia discharging into diversion channel by gravity action.

A silt flushing gate located at the end of the desilting basin will allow for conveying the silt

back into the diversion channel. The gate, a Vertical lift type unit, 2.5m wide by 1.5 m high

is operated using an electrical screw hoist. Plan and section of Desilting basin has been

shown in Drawing No. 1143-CD-202 and 1143-CD-204 respectively. Hydraulic design of

desilting basin is verified for higher design flow of 28.65 cumecs under phase II of project

development. It is seen that the provision of desilting basin shall facilitate about 93%

against a permissible 90% removal of sediments of size greater than or equal to 0.2 mm.

Thus no change in desilting basin is required for phase II development.

9.6 STORAGE RESERVOIR

Storage Reservoir is provided for peaking arrangement during lean season. It caters for

peaking capacity benefits of 100 MW for about 4 hours per day in phase I, and 150 MW

for 3 hours in phase II of project development. The reservoir floor is kept at EL.2860.00m,

and MDDL is kept at EL. 2860.75m by providing sufficient submergence for Tunnel Intake.

A low level water channel is provided to feed tunnel intake directly during cleaning and

maintenance of storage reserovoir. The FRL is kept at EL 2873.75m. To ensure that the

top level in the reservoir does not exceed the top level of wall, a 42.00m wide surplus weir

has been provided at the RCC gravity wall of the reservoir. The crest level of the weir has

been proposed at the El. 2873.75m. In case of rise in water level in reservoir above the

crest of weir, excess water shall spill over the weir into the Diversion channel. The top

level of gravity wall is kept at EL.2875.00 with a freeboard of 1.25m.

The layout plan and section of storage reservoir are shown in Dwg No. 1143-CD-301 &

1143-CD-302 respectively.

9.7 HEAD RACE TUNNEL (HRT)

The 8504 m long headrace tunnel is designed to convey water from reservoir to surge

shaft Turbine through Pressure shaft under pressure with an upstream water level in the

reservoir varying between El 2860.75 and EL 2873.75 m. The size of the D shaped tunnel

between RD 0 and RD 2130.00 m is of 3.50 m, and the size from RD 2130.00 m to

8409.00m is of 3.5 (W) x 3.9 m (H). The entire HRT stretch from RD 0 to RD 8409m will

be lined with 200 mm thick M:20 grade concrete, and the stretch from RD 8409.00m to RD

8504.00 will be provided with 2.50 m dia circular shape, and will be steel lined.

Head losses are calculated by Manning’s formula with coefficient of rugosity of 0.014 for

concrete lined stretch and with a coefficient of 0.01 in steel lined stretch. The flowing water

in the concrete lined stretch will have a maximum velocity of about 3.0 m/sec

corresponding to discharge, when three machines are running at 10% to 20% overload

capacity. The velocity is well within the limit for concrete lined tunnel.

Page 128: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 9. Civil Structures & HM Equipment

Indo Canadian Consultancy Services Ltd. 125 P-1143

The tunnel invert level at the HRT intake is El 2853.0 m, and that at the surge shaft

junction is El 2800.00 m. Three intermediate construction adits are provided to facilitate

the construction activities with five working faces, and they meet the HRT at RD 242 m,

RD 2140 m and RD 8474 m respectively. Keeping in view of length of the tunnel, provision

of access in the adit plugs has been proposed in Adit -2 to facilitate the future inspection of

the HRT. Plan and L-section of head race tunnel have been shown in Drawing no. 1143-

CD-402. Plan and L-section of Intermediate adits have been shown in Drawing no. 1143-

CD-406, 407 & 409 respectively.

The hydraulic design of HRT is verified for carrying higher design flow under phase – II of

project development. All hydraulic design parameters are found to be within permissible

limit and accordingly no change in HRT is proposed in phase II of project development.

9.7.1 Tunnel support system

Based on the geological condition encountered along the tunnel alignment, reaches have

been classified into four types of tunneling media rocks, each requiring a different

supporting system.

9.7.2 Tunnel reach in very good rock

The length of tunnel that passes through very good rock has given following support. After

excavation local shotcrete is applied in the tunnel as required to fill up over breaks in the

form of shotcrete etc. Provision for rock bolts 25 mm dia, 2.50 m long has also been made

for this reach. Details have been shown in Drawing no. 1143-CD-403 & 404 respectively.

9.7.3 Tunnel reach in Good rock

After excavation in good rock, 50 mm thick shotcrete is placed in the tunnel for rock

support. Provision for rock bolts 25 mm dia, 3.0 m long & 2 m c/c has also been made for

this reach. Details have been shown in Drawing no. 1143-CD-403 & 404 respectively.

9.7.4 Tunnel reach in Fair rock

Wherever fair rock corresponding to very blocky and seamy rock is encountered, 100 mm

thick shotcrete is applied in the tunnel after excavation. Provision for rock bolts 25 mm dia,

3.0 m long & 1.75 m c/c has also been made for this reach. In addition to this provision of

wire mesh has been provided between, 2 layers of 50 mm shotcrete with wire mesh

installed after the first layer. Details have been shown in Drawing no. 1143-CD-403 & 404

respectively.

9.7.5 Tunnel reach in Poor rock/Shear zone

Wherever shear zone is encountered in tunnel reach, after excavation, 150 mm thick

shotcrete is applied in the tunnel over breaks in the form of shortcrete etc. Provision for

Page 129: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 9. Civil Structures & HM Equipment

Indo Canadian Consultancy Services Ltd. 126 P-1143

rock bolts 25 mm dia, 3.0 m long & 1.5 m c/c has also been made for this reach. In

addition to this provision of wire mesh has been provided, 3 layers of 50 mm each with

wire mesh installed after the first layer. Another alternative has also been provided which

comprises of steel rib ISMB 150 at spacing of 1000 mm c/c with concrete backfill between

steel ribs and rock surface, with precast sleepers 100 mm x 125 mm x 900 mm as

required has been proposed. Details have been shown in Drawing no. 1143-CD-403 &

404 respectively.

9.7.6 Tunnel Concrete Lining

Head race tunnel is proposed to be lined throughout its length with 200 mm thick lining of

M20 concrete.

9.7.7 Grouting

A low/high pressure contact/consolidation grouting will be done in the tunnel, wherever

required. Details have been shown in Drawing no. 1143-CD-405.

9.8 SURGE SHAFT

At the end of head race tunnel, surge shaft with its top level at El 2910.00m and bottom

level at El 2800.0 m. With increase in design discharge in phase II of project development,

the finished diameter of existing surge shaft will require increase from 8.00m to 10.00 m.

Surge shaft is located at about 11.00m offset to alignment of HRT. The maximum upsurge

level has been worked out at El 2903.00 m and minimum down surge level at El 2825.00

m. Hydraulic design of surge shaft is verified for both phase I and phase II of project

development and is found to be within permissible limits with increase in diameter from

8.00 m to 10.00m. Sections of surge shaft have been shown in Drawing no. 1143-CD-411.

9.8.1 Type

A simple circular surge shaft is provided with a provision of orifice type riser from El

2800.00 to 2820.00 m. The 11 m offset from HRT acts as a restricted orifice for the surge

shaft to minimize the water fluctuations at the time of load rejection and sudden load

acceptance.

9.8.2 Surge Shaft Supporting System

Surge shaft is located in fine to medium grained granitic gneiss rock. The surge shaft has

been proposed to be anchored with rock bolts of 3 m long, 25 mm dia & 2.5 m c/c spacing

(both ways) and to be finished with 100 mm thick shotcrete with welded wire mesh.

Page 130: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 9. Civil Structures & HM Equipment

Indo Canadian Consultancy Services Ltd. 127 P-1143

9.8.3 Steel Lining

It has been proposed to provide steel lining in surge shaft, with a backfill concrete of 500

mm thickness, along periphery from bottom up to the top of surge shaft. It is assumed that

upsurge being of very short duration will not cause any saturation in the surrounding rock

mass. Lining has been designed for maximum internal pressure and design is verified for

external loading also.

9.9 PRESSURE SHAFT

A 2.50 m dia steel lined pressure shaft takes-off beyond surge shaft to carry water to the

Turbines . The general arrangement of the pressure shaft is shown in drawing no 1143-

CD-501, 502 & 503 respectively.

To optimize the diameter of Pressure shaft studies were carried out in phase II

development. The results show that a 2.5 m diameter conduit, steel lined, back filled with

concrete is required. Optimisation studies included evaluation of parameters such as

cost of excavation of inclined tunnel, concrete backfill, cement grouting, steel liner

procurement, fabrication and erection, head loss and power loss.

In phase I of project development, the 2.5 m diameter pressure shaft bifurcates into two Y-

piece unit penstocks of 1.76 m diameter each to feed the two pelton turbine of 50 MW.

The length of the 2.5 m dia main pressure shaft upto the bifurcation is about 1145.0m.

Under phase II of project development, it is proposed to provide a new bifurcation about

33m upstream of earlier bifurcation point, to feed the third unit. taking advantage of follow

the alignment of adit- 4 to bottom of pressure shaft. This arrangement will thus eliminate

the necessity of any excavation for pressure shaft for unit - 3.

The 2.50 m dia penstock takes off as T junction at the junction of Adit 4 to pressure shaft,

which feeds the unit no -3 proposed in phase – II of the project development. The

Pressure shaft continues little further bifurcates into two 1.76m dia pressure shaft, feeding

two Pelton turbines of 50 MW each.

An inclination of 55 to the horizontal has been provided for the pressure shaft. The

pressure shaft tunnel in the inclined portions has been excavated by raise climber. Two

such machines were deployed at El 2284.00m and El 2534.00m.

Diameter of the inclined tunnel has been kept as 3.1 m circular. Since the dia of steel-liner

has been adopted as 2.5 m, minimum space of 300 mm between the liner and excavated

rock surface has been made available for ease in erection and welding of steel liner and

placement of backfill concrete. Circular shape for the inclined tunnel has been proposed

as this would give wider working space at the invert.

Page 131: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 9. Civil Structures & HM Equipment

Indo Canadian Consultancy Services Ltd. 128 P-1143

Horizontal tunnel at El 2530 m has been provided with a 3.4m D-shaped section as this

would facilitate transportation of raise climber upto the inclination point leaving enough

space for mucking and independent erection of horizontal portion of the steel liner without

interfering with the excavation/erection of inclined pressure shaft.

Depending upon the head to be resisted, steel-liner of different thicknesses has been

used. Thickness of the plates varies from 18mm to 54mm. Maximum plate thickness has

been restricted to 54mm to exclude requirement of stress relieving and for ease in

handling. Sumiton 610 F grade steel plates have been proposed.

Length of each ferrule has been restricted to 2.5 m for ease in handling. All field-welded

circumferential joints shall be radiographed at the contractor’s workshop whereas 10% of

the field joints shall be radiographed. All field joints shall also be subjected to ultrasonic

examination.

The ferrules shall be lowered from top downwards from EL 2801.75m for the first inclined

stretch, and from EL 2525.14m for the second inclined stretch. Ferrules shall be provided

with backing steel strip for proper alignment and fitting.

Procurement of steel plates for phase I development has been completed and fabrication

of ferrules is in progress. About 350 MT of steel will have to be purchased for fabrication

and erection of bifurcation and unit pressure shaft for unit-3.

9.10 POWER HOUSE COMPLEX

The Power House has been located on a moderately flat terrace on the left bank of Tidong

khad. The overall dimension of the powerhouse, including the space requirement of

additional bay proposed in the phase – II of the project development, is 80.1meters long

and 19.1meters wide. The units 1 & 2 are spaced at 15 meters, c/c while units 2 & 3 are

spaced at 27 meters c/c. The levels of different floors in Power House Complex are

mentioned below.

Turbine Floor at EL. 2257.71 m

Generator Floor at EL. 2263.80 m

Service bay, Machine hall & Transformer bay at El. 2268.30 m

GIS bay & Control room are at EL. 2277.30 m

Pot head yard at EL 2286.80 m

The total height of Power house above bottom of the tailrace channel is about 33 meters.

The powerhouse machine hall has dimensions of 59.85 x 19.1. The control panels will be

located near upstream wall. It is proposed to construct the powerhouse. Concrete slab

supported over plate girder section spacing between B and D line column is provided to

cover the powerhouse. The service bay will have slanting transgress covered with

Page 132: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 9. Civil Structures & HM Equipment

Indo Canadian Consultancy Services Ltd. 129 P-1143

corrugated sheet with RCC columns of size 800 mm x 1200 mm shall be provided to

support the roof and crane beam. All columns are connected with tie beams of size

600mm x 600mm. A RCC beam is constructed at EL 2278.65m for carrying operation load

of EOT crane of 120 / 25 T carrying capacity. A 230mm thick brick wall / RCC wall is

provided all the sides above Service bay Floor. Proper drainage arrangement is provided

all along the powerhouse.

The powerhouse is protected from floods by Gabion wall, which will be constructed along

the left bank of the Tidong khad.

The Plan at different elevations, Unit cross section and longitudinal section are given in

the Dwg No’s 1143-CD-602, 603 & 604.

9.11 TAIL RACE DUCTS AND CHANNEL

From the power house, water is conveyed through independent tail race RCC ducts

joining a tail race channel. Length of the tail race channel is about 100 m. The maximum

water level in the channel corresponds to the highest flood level in Tidong khad (i.e, El

2250m). This channel joins Sutlej River smoothly to convey the tail water. Drawing no.

1143-CD-605 shows details of tail race.

9.12 TRANSFORMER HALL, GIS AND CONTROL ROOM

A Transformer cum GIS hall is proposed on the upstream of the Power house building and

it shall house 10 nos of 26MVA single phase Transformers and Gas Insulated Switch yard

(GIS). The size of the Transformer cum GIS hall is proposed as 14m (W) x 71.5.m (L) x

18.5m (H) and shall be located at EL 2268.30m. A 300mm thick concrete fire wall is

proposed to separate each Transformer. Under each Transformer a soak pit has been

provided to collect oil and fire water from there, and both oil and water will be sent to Oil

separator tank. Oil will be separated from water in oil separator tank, and water will be

thrown to Tail race channel. GIS hall has been proposed at EL 2277.30m along with

control room building. This control room building shall accommodate Electrical Room,

Battery Room, Mechanical Workshop, Control Room, and HVAC unit Room.

9.13 ADDITIONAL WORKS REQUIRED FOR THE 3RD UNIT (PHASE-II)

Existing surge shaft shall require increase in finished diameter from 8 m to 10 m.

The space available in the power house has been examined in detail and it is

found that the third unit can be accommodated, without necessitating any

additional land acquisition. A new bay of size 16.8 m x 19.1m will be constructed to

have the third unit.

The power transformer will be accommodated in the transformer hall of size 14.00

m wide x 18.5 m height x 71.50m long at elevation 2268.3 m.

Page 133: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 9. Civil Structures & HM Equipment

Indo Canadian Consultancy Services Ltd. 130 P-1143

The tail race channel from the 3rd unit shall be joined to the tail race channel of the

2 units with a transition.

Provision for addition of new GIS to cater 3rd unit will be made in the existing

arrangement of phase I development. No additional works are necessary in the pot

head yard.

Page 134: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 10. Power Plant – E&M Works

Indo Canadian Consultancy Services Ltd. 131 P-1143

10 POWER PLANT-ELECTRICAL & MECHANICAL WORKS

10.1 GENERAL

The Tidong I Hydroelectric Project with installed capacity of 2x50 MW for Phase-1 has

been already approved by government of Himachal Pradesh. Based on updated

hydrological studies, it is proposed to install 3rd Unit of 50 MW in the same surface Power

House as Phase-II development.

The Electro-Mechanical equipment for the power plant shall primarily consist of Turbine,

Generator, Governor, Oil Pumping Units, Main Inlet Valves, Excitation System, Battery &

Battery Charger, Generator Transformers, Station Service Transformer, Unit Auxiliary

Transformers, D.G set, Cooling Water System, AC & Ventilation System, Fire Detection &

Fire Fighting System etc., The description of above has been given in detail in relevant

paragraphs below.

The power evacuation shall be through 220kV D/C transmission line and has been

discussed in detail in a separate chapter.

10.2 TURBINE -CAPACITY AND TYPE

The Tidong HEP is a run of the river type development with pondage facility to enable the

power station to work as the peaking power station and to cater the daily variations .

The Power potential studies incorporated in the report clearly lead us for utilization of as

much of the stream flows as possible for power generation followed by the economic

evaluation of various possible project capacities. The in depth analysis has resulted in

optimizing the project capacity by extending the capacity to 150 MW from the existing

capacity of 100(2x50) MW under Tidong I, HEP Phase I. Hence, an additional unit of 50

MW is envisaged to be installed for the Tidong I HEP, Phase II.

As discussed in the Power Potential chapter, in view of the

machines already being installed

requisite operation conditions

maintenance aspects of generating units of the two units of 50 MW, it is felt that it

would be of 50 MW in advantageous to install similar type and capacity machine,

phase II development. Further, an inherent overloading capacity of 10% to 20% is

considered for the generating units to harness the extra discharge available during

the summer & monsoon period.

Page 135: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 10. Power Plant – E&M Works

Indo Canadian Consultancy Services Ltd. 132 P-1143

Total head loss in the entire water conductor system i.e from the intake at the reservoir to

Powerhouse corresponding to the unit design discharge of 9.55 cumecs for each of the

three units works out to 22.06 m. The rated net head works out to 588.92 m and the

Turbine is expected to operate within maximum and minimum net head of 593.25m and

580.25m, respectively. For this range of operating heads, Pelton Turbines are considered

suitable for installation. However, various aspects pertinent to the selection criteria based

on specific speed have been looked in to, as follows:

The specific speed (m.kW) as suggested for various Turbines are:

Ns Type of M/c

4- 35 per jet Pelton Turbine

60 – 400 Francis Turbine

> 300 Kaplan Turbine

Specific speeds calculated for the Tidong HEP with a Turbine to generate 55 MW at

Generator terminals (i.e rated capacity of 50MW and overloading of 10%) for different

parameters is indicated in Table 10.1, below.

Table 10.1

S. No.

Speed (N) Specific Speed (Ns)

(rpm) Machine (m. kW) Per jet (m. kW)

4jets 5jets 6jets

1 750 61.35 30.68 27.74 25.05

2 600 49.08 24.54 21.95 20.04

3 500 40.90 20.45 18.29 16.70

4 428.57 35.09 17.55 15.69 14.33

5 375 30.68 15.35 13.72 12.52

6 333 27.24 13.62 12.18 11.12

It is observed form the above table that all the values pertinent to specific speed per jet

with 4, 5 and 6 jets option falls within the suggested range for the Pelton type Turbine.

The basic parameters required to be determined in order to optimize the specification of

the Pelton Turbine are:

Specific speed per jet (Ns)

Number of jets

Turbine runner pitch circle diameter (D)

Jet diameter (d)

Wheel ratio (D/d)

Page 136: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 10. Power Plant – E&M Works

Indo Canadian Consultancy Services Ltd. 133 P-1143

Buckets number

Jet interference

The computations are tabulated in the following Table 10.2

Table 10.2

S.

No.

Total

jets

Jet

diameter

(d) (mm)

speed

(rpm)

PCD (D)

(mm)

wheel

ratio

(D/d)

Ns per jet

(m. kW)

No. of

buckets

1 4 178.21 428.57 2149.29 12.06 17.55 21

2 4 178.21 500 1844.09 10.35 20.45 20

3 4 178.21 600 1536.74 8.62 24.54 19

4 4 178.21 750 1229.40 6.90 30.68 18

5 5 159.39 428.57 2149.29 13.48 15.69 22

6 5 159.39 500 1844.09 11.57 18.29 21

7 5 159.39 600 1536.74 9.64 21.95 20

8 5 159.39 750 1229.40 7.71 27.44 19

9 6 145.51 428.57 2149.29 14.77 14.33 22

10 6 145.51 500 1844.09 12.67 16.70 21

11 6 145.51 600 1536.74 10.56 20.04 20

12 6 145.51 750 1229.40 8.45 25.05 19

As per the prevailing best modern practices, the optimum range of specific speed per jet

is 15 to 19 with a preference of specific speed per jet on the lower side; the optimum

range of wheel ratio is 10 to 14 with the preference of the wheel ratio on the higher side.

In view of the above criteria the options available with respect to the Turbine speed and

number of jets narrows down and are show in the table 10.3 below:

Table 10.3

S.

No.

Total

jets

Jet

diameter

(d) (mm)

speed

(rpm)

PCD (D)

(mm)

wheel

ratio

(D/d)

Ns per jet

(m. kW)

No. of

buckets

1 4 178.21 428.57 2149.29 12.06 17.55 21

2 4 178.21 500 1844.09 10.35 20.45 20

3 5 159.39 500 1844.09 11.57 18.29 21

4 5 159.39 600 1536.74 9.64 21.95 20

Page 137: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 10. Power Plant – E&M Works

Indo Canadian Consultancy Services Ltd. 134 P-1143

Among the options available in the table 10.3 above it is observed that the option with 5

jets and 600 rpm has specific speed of 21.95 which is very high for such a high head

installation, hence should be ruled out.

The option with 4 nos. of jets and 500 rpm has high specific speed of 20.45 and for such a

high head machine it is preferred to opt for a lower specific speed.

Among the remaining options of 4 jet with 428.57 rpm and 5 jet of 500 rpm, it is observed

that the 4 jet 428.57 rpm has a higher wheel ratio but has a larger Turbine runner and

shall have a heavier Generator thus increasing the overall cost of the Electromechanical

works.

Thus, a 5 jet 500 rpm vertical arrangement Pelton Turbine installation is recommended for

the Tidong – I, Phase II HEP. The selected turbine is similar to the turbines already under

installation in Phase-I development.

10.3 MAIN TURBINE PARAMETERS

10.4 DESCRIPTION OF ELECTROMECHANICAL EQUIPMENT

10.4.1 Turbine

The Turbine shall be 5 jet 500 rpm vertical installation type capable to generate 50 MW at

Generator terminal at rated head and discharge. An inherent overloading capacity of 10%

shall be provided in the Turbine to generate higher output.

S. No. Parameter Value

1 Rated output at Generator terminals 50 MW

2 Rated output a Turbine shaft 50.7 MW (approx.)

3 Rated Head 588.92 m

4 Rated Discharge 9.55 cumecs

5 Rated Speed 500 rpm

6 Number of Jets 05

7 Specific speed per jet (w r t 10% overload) 18.29 (m. kw)

8 Maximum Net Head 593.25 m

9 Minimum Net Head 580.25 m

10 Pitch circle Diameter (approx.) 2000 mm

11 Runner centerline elevation El 2258.44 m

Page 138: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 10. Power Plant – E&M Works

Indo Canadian Consultancy Services Ltd. 135 P-1143

10.4.1.1 Runner

The runner shall be single piece forged. The material composition of runner shall be 13%

Cr and 4% Ni stainless steel, in accordance with ASTM A 743, Grade CA-6N. Its

composition shall be follows:

C 0.05%, Si = 0.4 – 0.6%, Mn = 0.5 –0.8 %, P 0.025%, Si 0.015%,

Cr = 12.5 – 13.5%, Ni = 3.5- 4.5%, Mo 0.7 %, P + S 0.03%

The buckets shall be accurately ground and polished to templates. The runner shall be

provided with machined spigot flange and fitted with friction bolts. The runner shall be

statically balanced, designed and manufactured to withstand safely the stresses at the

runway speed under the conditions of maximum head. In addition the runner shall be

provided coating of tungsten carbide (or better material) with 300 microns of thickness to

prevent buckets from silt erosion and hence to prolong the runner life.

10.4.1.2 Shaft

The Turbine shaft shall be of forged carbon steel, properly heat-treated with integral

flanges for bolting to the runner and the generator shaft on either side. It shall be hollow

bored and of ample size to transmit torque at any speed up to the full runaway speed

without detrimental vibration or distortion.

10.4.1.3 Turbine Guide Bearing

The Turbine guide bearing shall be of the Babbitt-lined, oil self-lubricating type, shall be

located above the runner, and easily removable; shall be capable of being insulated from

ground, and shall be complete with oil sump having removable cover plates. It shall

permit axial movement of the shaft to facilitate adjustment and dismantling of the

generator thrust bearing and clearing of the male and female portions of the

Turbine/generator shaft couplings. The bearing shall be designed to withstand safely and

without damage natural retardation from maximum runaway speed without the use of the

generator brakes. The bearing shall also be designed for eccentric loading in any

direction and shall be capable of withstanding the side thrust caused by the use of only

one nozzle, or any combination of nozzles whereby one nozzle is shut off while the

opposite is operating normally.

10.4.1.4 Nozzle assembly

Nozzles for supplying water to the Turbine runner shall be designed to produce the most

uniform jet possible, shall be equipped with governor operated needles and shall be

placed as near as possible to the runner.

Page 139: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 10. Power Plant – E&M Works

Indo Canadian Consultancy Services Ltd. 136 P-1143

The nozzle body shall be of Cast steel construction, flanged for bolting to the distributor

piping and to the nozzle tip. Each nozzle shall have a bronze guide bearing (self-

lubricated type or equivalent) for supporting the needle stem. Each nozzle shall be

provided with a replaceable nozzle tip.

The needle stems shall be of forged Stainless Steel and shall be fitted with renewable

sleeves where they pass through the guide bearings and packing boxes. The Nozzle tip,

and Nozzle spear shall be made of forged stainless steel of 13 Cr 4 Ni same as of runner.

The needle stems shall be protected in the water passage area by suitable Stainless Steel

sleeves to prevent sand or grit from entering the bearings and stuffing boxes. The nozzle

servomotor shall be self closing type and provided with spring at the upstream side of

piston

10.4.1.5 Deflector

The deflector shall be of cast steel with weld deposit cutting edge of stainless steel of 13

Cr 4 Ni, complete with operating shaft carried in bearings mounted on the nozzle body.

The deflector rod is keyed to the deflector lever and operated through deflector operating

mechanism.

The deflectors shall be inter-connected to move in unison and shall be controlled by a

servomotor operated by governor oil pressure. A restoring mechanism and

interconnecting controls shall be provided to ensure proper relative movement between

the needles and deflectors with change of load. Under normal speed control, the needles

shall do the governing so that water will not be wasted. The deflectors shall enter the jets

when the rate of load reduction is faster than that which can be controlled by the needles

alone.

The deflectors shall be actuated by a counter force supplied by a spring, in case of oil

pressure failure. Each deflector shall be constructed to withstand safely the maximum

continuous discharge from its associated nozzle.

10.4.1.6 Needle and Deflector servomotors

The servomotors shall be oil pressure actuated, double-acting type, having sufficient

capacity to supply the maximum forces necessary to operate the jet deflectors and

needles with the oil in the governor oil tank at 60 % of the rated governor oil pressure. The

arrangement shall be such that with a loss of governor oil pressure, the needles shall

close automatically by means of a spring. Control orifices shall be installed in the closing

end of the servomotors to limit the maximum rate of needle movement to the minimum

closing time. Each servomotor shall be equipped with a pointer and scale to indicate the

needle position.

Page 140: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 10. Power Plant – E&M Works

Indo Canadian Consultancy Services Ltd. 137 P-1143

The servomotor cylinders shall be of plate steel or cast steel construction and shall be

provided with a drain connection at each end of the cylinder. The pistons shall be fitted

with not less than three oil piston rings. Pistons shall be locked to the operating shafts to

prevent rotation, and piston rings shall also be designed to prevent their rotation on the

pistons. The cylinders shall be of such design as to provide cushioning at the end of the

piston stroke from a point slightly below speed-no-load position to the fully closed position.

Provision shall be made for collection of leakage water and oil from the needle stem

packing

10.4.1.7 Spiral distributor

The spiral distributor shall be of welded plate steel fabricated only confirming to ASTM 517

Gr A steel plates. The distributor shall be designed for maximum internal working pressure

including the effect of water hammer. The stresses in the material shall not exceed those

permitted by the ASME Code.

The spiral distributor shall be connected to MIV through dismantling cum expansion joint

through welding.

10.4.1.8 Turbine Housing

The discharge pit liner shall consist of a lower cylindrical part and an upper conical part.

The top of the liner shall be provided with a curb ring to support the discharge pit cover

and guide bearing assembly. The curb ring shall have sufficient strength and rigidity to

support the bearing while the Turbine is operating under the most adverse conditions.

10.4.1.9 Brake Nozzle

A braking nozzle or nozzles impinging on the back of the runner buckets, of sufficient

power to bring the unit rapidly to a reasonable minimum speed before the generator

brakes shall be supplied for bringing the unit to rest. The supply of water for braking

nozzle operation shall be taken from upstream of main inlet valve. The braking jet system

shall be complete with necessary piping, brake nozzle, isolating valve and control

equipment, both for manual and automatic operation

10.4.2 Governor

The governor shall be microprocessor based Electro-hydraulic governor (EHG) of PID

type (Proportional Integral Derivation). The governor shall be possible to sense the speed

of rotation, determine an error signal and there from, with suitable feedback and

stabilization, develop a hydraulic control signal of sufficient power to regulate the

deflectors and nozzles via the servomotors. The governor shall be complete with all

necessary devices for completely automatic and local manual control and shutdown. The

governor shall primarily have two parts- The Hydraulic control assemble and governor

electronic cubicle.

Page 141: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 10. Power Plant – E&M Works

Indo Canadian Consultancy Services Ltd. 138 P-1143

The hydraulic control assembly of the Governor shall be enclosed in a free-standing sheet

steel enclosure competes with sump tank and pumps. The control block, oil filters and

deflector relay valve shall be mounted on one side of the cabinet, facing the front, with the

needle relay valves and the pump set equipment on another side. The cabinet shall be of

rigid construction and neat appearance, dustproof and properly ventilated.

The governor electronic cubicle, containing all wiring, instrumentation, controls and

electrical devices

10.4.3 Main Inlet Valve (MIV)

The main Inlet Valve shall be of spherical valve type one for each Turbine and shall be

housed in the Powerhouse. The MIV shall be of 1200 mm nominal size and nominal

Turbine flow of 9.55 cumecs. The valve shall be of dual seal type i.e. one main or service

seal and one repair or maintenance seal for repairing the service seal without the need for

dewatering the penstock header/pressure shaft.

The valve would be designed to withstand the maximum pressure inclusive of water

hammer. It will be operated by the same oil supply from the governor Oil pressure unit to

open and the closing shall be with the dead weight. The valve shall be provided with

emergency closure function also i.e. capable of closing against full flows.

10.4.4 Generator and excitation system

10.4.4.1 Type & description

The generator will be, vertical shaft synchronous machine with rated continuous output of

55.55 MVA having rotational speed of 500 rpm to match with that of the Turbine. Each

generator will have the following parameters

Rated Speed 500 rpm

Rated capacity 55.55 MVA

Power factor 0.9

Nominal Active Power 50 MW

Maximum Active Power 55 MW (One Unit operation)

Rated Voltage 11 KV

Rated Frequency 50 Hz

Qty 02 Nos (Phase-I), 01 No (Phase-II).

Approx. rotor weight 100 T

The generators are envisaged to have overload rating of 110% of the name plate rating.

Provision of this overload capacity is as per convention and would be useful during

Page 142: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 10. Power Plant – E&M Works

Indo Canadian Consultancy Services Ltd. 139 P-1143

planned and forced outage of the other unit, as the capacity loss due to outage could be

partially compensated and to harness more energy from the excess discharge during the

monsoon season.

The generator stator and rotor windings will be provided with epoxy insulation of class F

type. The generator ventilation system would be of re-circulation type with air (the primary

coolant) cooled by water. The generator shall be designed to withstand the runaway

speed which shall be co-ordinated with the Turbine supplier. The reactances short circuit

ratio and GD2 shall be consistent with optimal and stable operation of the units both

under steady state and dynamic conditions

For the rated and 110% overload generator output within the permissible operating

conditions, the temperature rise limits of the stator and rotor windings would be restricted

to class B insulation temperature rise and the limits would be as per latest Bureau of

Indian Standards (BIS)/IEC over the ambient air temperature of 40C.

The bearing arrangement will comprise a combined thrust and guide bearing above the

rotor and a guide bearing below the rotor.

The generator will be provided with the static excitation system complete with excitation-

transformer, thyristor cubicle, field flashing system, field suppression system, digital

(electronic) voltage regulator. It will have features like rotor current limiter, stator current

limiter, follow up circuits etc. for the entire function. Auxiliary Excitation shall be provided

for switching on during dynamic braking.

10.4.5 Automation control, metering and protection

PLC based Unit Control board shall be provided, which shall control all functions of the

generating units, transformers and lines etc., both in auto & manual mode. A separate Unit

Control Board shall be provided for each unit and shall comprise of ammeter, voltmeter,

power factor meter, kWH meter, kVAR meter, frequency meter, recorder, push buttons,

indicators etc., as per the system requirement. The energy meter shall be provided of 0.2

accuracy class for measurement of import & export of energy from the system.

The protection equipment will comprise instantaneous time delay over current relay, over

voltage relay, reverse power relay, negative phase sequence relay, loss of excitation

relay, and differential protection relay. In addition suitable alarm/trip circuits shall be

provided for indicating abnormal conditions like high bearing temperature, low oil pressure,

low high oil level etc. For power transformer, Bucholz protection and temperature

alarm/trip circuit shall be provided. The protection system is designed for 110V DC

operation

Page 143: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 10. Power Plant – E&M Works

Indo Canadian Consultancy Services Ltd. 140 P-1143

10.4.6 Station switching scheme and type of 220kV switching equipment

Considering the site terrain and space constraint, it has been decided to install 220 kV GIS

Bays, for interfacing with the evacuation line instead of 220 kV outdoor switchyard

envisaged in the earlier DPR (Phase-I). Accordingly 5 GIS bays consisting of Two (2)

Generator bays, Two (2) Line bays and One (1) Bus coupler bays are being installed as

part of Phase-I execution of project. Under Phase-II, one (1) additional 220 kV GIS Bay is

proposed to be installed by extending the 220 kV buses of existing switchgear. The double

bus scheme has been adopted as per prevailing practices as well as approved for Phase-I

DPR for the Project. The GIS bays for Phase-I are already under execution.

The double bus switching scheme shall be consistent with established sub-station

practices in India which has been evolved to give reliable service. The outgoing 220 KV

circuits shall be provided with lightning arrestors, CVT, Wave trap, Line Isolator as well as

revenue metering CT & VT on line side.

10.4.7 Transformers

10.4.7.1 Power Transformers

Seven number (including One Spare), single phase, 22.5 MVA, 11/220 kV Delta/Star step

up transformer of OFWF type with normal protective devices such as restricted earth fault,

etc. will be installed in the Phase-I. Additionally 3 Nos, single phase, 22.5 MVA, 11/220 kV

step-up transformers will installed in the Phase-II to cater to the requirement of 3rd unit.

10.4.7.2 Station Transformer and unit Auxiliary Transformers

Two number of 11kV/433 V, 630kVA capacity ONAN type Unit Auxiliary Transformers are

being provided in the Phase-I to meet the requirement of unit auxiliary loads such as rotor

jacking, governor OPU motor, brake dust collector etc. One number of 22 kV/433 V,

630kVA capacity ONAN type Station Service Transformer is being provided to meet the

requirement of station loads such as cooling water pump, compressor, general lighting,

switchyard auxiliary supply, EOT crane and other misc. loads. Additional One (1) No.

11kV/433V, 630 kVA capacity ONAN type Unit Auxiliary Transformer (UAT) will be

provided in the Phase-II for feeding auxiliary loads of 3rd Unit (Similar to Unit-1 & Unit-2).

10.4.8 Electrical Auxiliaries

10.4.8.1 Generator Main Bus ducts and tap off bus ducts

The generator will be connected to main step-up transformer by 11 KV, isolated phase

main bus ducts of rating 4000A. There would be auxiliary ducts tapped off from the main

bus duct for connection to unit auxiliary transformer, excitation transformer, LAVT cubicle

etc. The connection between generator neutral terminal and neutral grounds equipment

Page 144: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 10. Power Plant – E&M Works

Indo Canadian Consultancy Services Ltd. 141 P-1143

would also be by bus ducts. The main bus ducts would be laid as shown in the layout

drawings. The bus duct shall be complete with shorting isolators for Dynamic Braking.

10.4.8.2 Generator terminal and Neutral equipment

The terminal equipment would comprise of potential transformers, CTs, lightning arrestors

and neutral grounding cubicles. The neutral of the generator shall be connected to the

grounding system of the Powerhouse through neutral grounding distribution transformer

loaded with a resistor in the secondary winding

10.4.8.3 Auxiliary LT power supply

LT auxiliary power supply for units would be tapped from respective unit buses at 11 KV

through 11KV/433 V - 3 phase 630kVA (each) dry type transformers. Station service

supply would be taken through a 630kVA, 11 KV/433 V station service transformer

(installed in Phase-I). For emergency supply, 500 KVA, DG set is being provided in

Phase-I.

10.4.8.4 DC supply system

This shall be110 volts DC system and consists of two sets of 680 AH, 110 V DC batteries

with main and standby chargers, other control equipment and independent DC distribution

boards under Phase-I. These two batteries shall be used for control/protection function

and field flashing/emergency functions respectively. The same batteries shall meet the DC

requirement of 3rd unit being installed under Phase-II. However a separate DC Board will

be provided for DC distribution for Phase-II loads.

10.4.8.5 Grounding mat

Two grounding mats of steel having suitable cross section have been provided, one

embedded under Powerhouse and the other embedded under transformer/GIS Area. All

mats have been inter-connected by grounding strips. Grounding electrodes of suitable

size have been be installed and connected to grounding mats. Suitable number of

grounding connections would be provided on each power house floor for earthing of

various electrical equipment under Phase-I & Phase-II. The grounding system shall be

designed to keep the step and touch potential within safe limits. The embedded grounding

mat for area covered by 3rd unit (Phase-II) is proposed to be laid as provided for Phase-I

before completion of Phase-I schedule.

10.4.8.6 Illumination of the Plant

Fluorescent tubes with appropriate fitting for diffused light would be used inside the

Powerhouse. High bay type mercury/sodium vapour lamps would be used to illuminate the

machine hall. Outdoor switchyard would be illuminated by mercury/ sodium vapour lamps.

Page 145: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 10. Power Plant – E&M Works

Indo Canadian Consultancy Services Ltd. 142 P-1143

DC emergency lighting at suitable location would also be provided. Area/street lighting

would be provided by suitable mercury/sodium vapour lamps.

10.4.8.7 PLCC equipment

PLCC equipment for this Powerhouse will be installed for providing line protection,

communication, telemetry and remote control. Independent carrier channels would be

provided for relaying, communication and telemetry functions. The PLCC equipment will

be installed and commissioned at Phase-I. The system/equipment will be used for

communicating 3rd unit operating parameters as well to load dispatch in the Phase-II.

10.4.9 Mechanical auxiliaries

10.4.9.1 EOT Crane

The heaviest assembly required to be lifted by the EOT crane will be the assembled rotor.

For the 50 MW, 500 rpm generating unit, the assembled rotor weight is expected to be of

the order of 100 tonnes. One Cabin operated EOT crane with 120 tonnes Main Hook for

handling the rotor and 25 tonnes Auxiliary Hook has been provided at Phase I.

Appropriate hook limits to enable handling of Turbine Inlet Valve etc. have been provided.

The existing crane provided at Phase I will be used for assembly & execution of Turbine &

Generator of third unit in Phase II.

10.4.9.2 Cooling water system

Cooling water for generating unit and transformers and other purposes will be tapped from

the Turbine discharge water. Two (2) sets of pumps (1W + 1SB) for the third unit under

Phase II will be provided. These are located in the downstream side. The cooling water

supply pumps will be of vertical type. It will feed water through a common header to the

third unit. Cooling water requirement during initial start-up of a unit is met by a sump with

adequate capacity.

10.4.9.3 Compressed Air System

Compressed Air requirements have been envisaged for governor pressure oil system, the

Turbine inlet valve pressure oil system, generator brakes and station service. Two high

pressure (60 bar) compressors with an air receiver tank meeting the requirements of both

the units have been provided. Low pressure air (at 7 Kg/Cm2) required for Generator

Brakes and Station Service is tapped off from the main high pressure air header with a

pressure reducing valve and a low pressure air receiver. The high pressure (HP) and low

pressure (LP) compressed air requirements will be met from the existing equipment in

Phase I.

Page 146: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 10. Power Plant – E&M Works

Indo Canadian Consultancy Services Ltd. 143 P-1143

10.4.9.4 Station Drainage System

No station drainage equipment is required for the station with Pelton Turbine installation

as all station drain water will be led by gravity to the free flow unit discharge duct/tailrace.

10.4.9.5 Ventilation and Air Conditioning System

Forced ventilation for Powerhouse MIV, Turbine and Generator floors is envisaged. Two

nos. Air Handling Units with air filters will be installed for forcing air to various floors.

During winter when outside temperature will be low, recirculation of air mixed with fresh air

will be provided, to maintain desired temperature level. Manually controlled heaters will be

provided in the ventilation system to maintain warm temperature, whenever necessitated

during very cold season. Control Room, Shift Engineer and Officers rooms will be air

conditioned with suitable Windows / Split type air conditioning units.

10.4.9.6 Fire protection system

Water for fire protection covering emulsifier systems for Generator Transformers, OPU

and other areas have been taken from an overhead tank located outside the Powerhouse

at an elevation. Suitable capacity submersible water sump pumps have been provided for

filling of overhead Fire Protection Tank under Phase I. Fire protection system comprises of

Pipe Systems with Valves, Hydrant Valves, Deluge Valves and hose cabinets at number

of strategic points. Portable Fire Extinguishers have been provided at strategic points at

all the floors of the Powerhouse/ Transformer area for protection in case of small

fire/emergencies. In addition, fire alarm system is provided in the Powerhouse and

Transformer area etc.

For the third unit, an automatic CO2 fire protection system will be provided for Generator.

10.4.9.7 Potable Water System

Potable and Sanitation Service Water have been provided for the Powerhouse which

draws water from the Fire Water Tank. The system comprises of distribution piping and

water purifying units.

10.4.9.8 Vibration Monitoring System

One set of Vibration measurement system for third generating unit is proposed to measure

at the vibrations in the shaft near the Turbine & generator bearings

Page 147: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 11. Power Evacuation Arrangements

Indo Canadian Consultancy Services Ltd. 144 P-1143

11 POWER EVACUATION ARRANGEMENTS

11.1 INTRODUCTION

The Tidong-I Phase-II Hydro Electric Project (50 MW) is located on Tidong Rivualet which

is a tributary of Satluj River near Reckong Peo Town in Kinnaur District of Himachal

Pradesh. The Project consists of One No. vertical Pelton Turbine driven Generating Unit

of 50 MW. It is expected that bulk of the power generated at this Project would be

available to serve the Northern Region of India. This chapter details the power evacuation

arrangement from the Project to the injection point.

11.2 LOAD DEMAND

As per projections (including Ultra Mega Projects) for the year 2013-14 given by CEA in

the National Electricity Plan 2007, the Northern Region shall be power deficit region (with

a power deficit of - 6890 MW during Winter Off Peak, - 11772 MW during Winter Peak, -

4368 MW during Summer off Peak & - 5535 MW during Summer Peak conditions.

As per Annual Report 2012-13 of NRLDC there was a minimum deficit of 1093 MW in

September, 2012 and a maximum deficit of 4343 MW during January, 2013 (copy of

relevant abstract is enclosed as Ann. 11.1). During Evening Peak hour this deficit was

1939 MW on 18.01.2015 (Power Supply Position in Northern Region for 18.01.2015 as

available on NRLDC website and copy enclosed as Ann. 11.2).

Thus, the power deficiency in Northern Region still remains. The commissioning of the

proposed Tidong-I Phase-II HEP shall partly meet power deficiency in Northern Region.

11.3 TRANSMISSION LINES

There is an existing 400 kV D/C Transmission Line from Baspa-II HEP (300 MW) to

Nathpa Jhakri HEP (1500 MW) which is also looped in and looped out at Karcham

Wangtoo HEP (1000 MW). Further, Nathpa Jhakri HEP (1500 MW) is connected to

Abdullapur sub – station through 400 kV D/C Transmission Line and to Nalagarh sub –

station through another 400 kV D/C Transmission Line.

Karcham Wangtoo HEP is also connected to Abdullapur sub- station through 400 kV D/C

Transmission Line. HPSEB has also constructed 220 kV D/C Transmission Line from

Bogtu sub – station to Bhava HEP (120 MW) which is further connected to Kunihar sub –

station (via Kotla sub – station) through 220 kV D/C Transmission Line.

As per Master Plan prepared by CEA (downloaded from CEA website and enclosed as

Ann. 11.3) for Satluj Basin, proposed 400/220 kV station at Ka-Dogri is to be developed as

Interstate Pooling Station. Power from different Projects to be established across Spiti

River i.e. Killing - Lara HEP (40 MW), Lara HEP (60 MW), Mane - Nadang HEP (70 MW),

Page 148: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 11. Power Evacuation Arrangements

Indo Canadian Consultancy Services Ltd. 145 P-1143

Lara - Sumta HEP (104 MW), Sumte - Khatang HEP (130 MW), Chango - Yangthang

HEP (140 MW), will be fed to proposed 400/220 kV Ka-Dogri Pooling Station being

constructed by HPPTCL. One more 400/220 kV Pooling Station at Jangi is proposed to be

constructed by HPPTCL. The 400/220 kV Pooling S/stn. at Ka- Dogri shall be connected

to this 400/220 kV S/stn. at Jangi through 400 kV Twin Moose D/C Transmission Line.

Power from Tidong-I HEP (100 MW), Tidong-II HEP (90 MW) and Kashang HEP (243

MW) shall be injected into Jangi Pooling station. One 400 kV D/C Transmission Line with

HTLS Quad Conductor has been proposed between 400/220 kV Jangi Pooling Station

and proposed 400/220 kV Wangtoo Pooling Station. One circuit of this proposed 400 kV

D/C Transmission Line shall be looped in & looped out at Jangi Thopan – Thopan Powari

(480 + 480 MW) HEP and other circuit of this proposed 400 kV D/C Transmission Line

shall be looped in & looped out at Shongton – Karcham HEP (450 MW) as shown in

Master Plan prepared by CEA (Ann. 11.3).

Subsequently, a Task Force having representatives from Govt. of HP, HPPTCL, CEA and

POWERGRID visited site of Satluj Basin Projects in Sept, 2011 & the matter came up for

discussion in the 30th meeting of the Standing Committee on Power System Planning of

Northern Region. Relevant portion from Annex. II of Minutes of 30th SCM dated 19.12.11

(enclosed as Ann. 11.4) is reproduced below:

“• SHPs: Establishment of 66/220/400 kV GIS Pooling Station at Wangtoo by Mid

2014 to match commissioning of SHPs in Bhaba Khad (57 MW) and Sangla Valley

(40 MW) + LILO of 220 kV Kashang – Bhaba D/c Line and LILO of both circuits of

400 kV Karcham Wangtoo - Abdullapur D/c line at Wangtoo. – Proposed

Implementation through STU.

HPPTCL proposed to implement this substation by Mid 2014 and they have tied up

the funds from ADB. The switchgear rating and bus capacity etc. at Wangtoo

substation should be equivalent to 4000 Amps.

• Kashang-I (65 MW), Kashang-II (65 MW) and Tidong-I (100 MW): During the

meeting HPPTCL stated that Kashang-I is likely to be commissioned by 2013. For

evacuation of power from Kashang-I, HP is constructing a 220 kV D/c line from

Bogtu to Kashang. Accordingly, power can be evacuated through Bogtu – Bhabha

220 kV D/c line. HPPTCL stated that Tidong-I is under construction and is likely to be

commissioned by December, 2014. Since, Tidong-I (100 MW) is due for

commissioning by December, 2014 and Jangi Pooling station may not come up by

that time, Tidong-I power shall be temporarily evacuated by LILO of one circuit of

220 kV D/C Kashang- Bhaba line at Tidong-I HEP. These works shall be carried out

by HPPTCL. Later on when Jangi P.S. is commissioned, Tidong-I – Jangi line shall

be constructed and also Kashang – Jangi 220 kV D/c line with single HTLS

Page 149: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 11. Power Evacuation Arrangements

Indo Canadian Consultancy Services Ltd. 146 P-1143

conductor shall be established. These works are proposed to be carried out by

HPPTCL.

HPPTCL further informed that works for Kashang-II (65 MW) has also been awarded

and commissioning is expected by 2015. It was suggested that Kashang-II is also

evacuated through 220 kV system as Jangi pooling station may not be available in

that time frame, however some constraints may be faced during contingency of

outage of one circuit. POWERGRID stated that establishment of Jangi Pooling

station may be taken up with further stages of Kashang.

…………………………………………………………………………………………………

…………………………………………………………………………………

• Kashang-III (65 MW) & Kashang-IV (48 MW) and Tidong-II (90 MW) HEP:

Evacuation of power from Kashang-I (65 MW), Kashang-II (65 MW) and Tidong-I

(100 MW) is discussed above. With the commissioning of other stages of Kashang

and Tidong, the power shall be injected at Jangi pooling station. The Jangi Pooling

station shall be established by this time frame. Transmission scheme for Kashang &

Tidong shall be as given as below:

° Kashang-Jangi Pooling Station 220 kv D/c line (Single HTLS- Equivalent to

300 MW capacity) – Proposed Implementation as STU network

° 2x315 MVA (7X105 MVA units) 220/400 kV GIS Pooling Station at Jangi (with

4000 Amps. Switchgear) (with space provision for 3rd ICT) - Proposed

Implementation as ISTS

° LILO of one ckt. of Shongtong – Wangtoo 400 kV Line at Jangi - Proposed

Implementation as ISTS

° Tidong – Jangi Pooling Station 220 kV D/C line - Proposed Implementation

as STU network

Note: After coming up of Kashang III & Tidong-II and its inter-connection with Jangi

Pooling Station, the Kashang-Bogtu 220 kV Line has to be kept in open condition.”

11.4 IDENTIFICATION OF TRANSMISSION SYSTEM

As per CEA Master Plan and Minutes of 30th SCM dated 19.12.11 the evacuation from

Tidong-I HEP in temporary and final evacuation arrangement is at 220 kV level.

Accordingly, the Switchyard at Tidong-I HEP is designed for Power Evacuation at 220 kV

voltage level.

Since the Tidong-I Phase-II HEP (50 MW) shall be located adjacent to Tidong-I HEP (100

MW), switchyard of Tidong-I Phase-II HEP can also be located adjacent to Tidong-I HEP

switchyard to facilitate injection of power from Tidong-I Phase-II HEP (50 MW) into

Tidong-I HEP switchyard.

Page 150: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 11. Power Evacuation Arrangements

Indo Canadian Consultancy Services Ltd. 147 P-1143

11.5 POWER EVACUATION FROM TIDONG-I PHASE-II HEP

The facility that is being created by laying the 16.5 Kms of 220 D/c line from Tidong-I HEP

to Kashang Bhaba through LILO is adequate to carry the power generated through

Phase-II installation of 50MW .As such no other facility need be created.

11.6 STATUS OF OPEN ACCESS/ CONNECTIVITY

Approval for Grid connectivity and Long Term Open Access from STU & CTU for Tidong-I

phase II HEP (50 MW) will be sorted out for after getting Techno Economic Clearance

(TEC) for the Project.

Page 151: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 11. Power Evacuation Arrangements

Indo Canadian Consultancy Services Ltd. 148 P-1143

Page 152: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 11. Power Evacuation Arrangements

Indo Canadian Consultancy Services Ltd. 149 P-1143

Page 153: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 11. Power Evacuation Arrangements

Indo Canadian Consultancy Services Ltd. 150 P-1143

Page 154: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 11. Power Evacuation Arrangements

Indo Canadian Consultancy Services Ltd. 151 P-1143

Page 155: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 11. Power Evacuation Arrangements

Indo Canadian Consultancy Services Ltd. 152 P-1143

Page 156: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 11. Power Evacuation Arrangements

Indo Canadian Consultancy Services Ltd. 153 P-1143

Page 157: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 11. Power Evacuation Arrangements

Indo Canadian Consultancy Services Ltd. 154 P-1143

Page 158: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 11. Power Evacuation Arrangements

Indo Canadian Consultancy Services Ltd. 155 P-1143

Page 159: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 11. Power Evacuation Arrangements

Indo Canadian Consultancy Services Ltd. 156 P-1143

Page 160: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 11. Power Evacuation Arrangements

Indo Canadian Consultancy Services Ltd. 157 P-1143

Page 161: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 11. Power Evacuation Arrangements

Indo Canadian Consultancy Services Ltd. 158 P-1143

Page 162: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 12. Infrasturcutre Facilities

Indo Canadian Consultancy Services Ltd. 159 P-1143

12 INFRASTRUCTURE FACILITIES

12.1 GENERAL

Tidong khad joins Sutlej river near village Rispa/Morang at an elevation of about 2244m.

Morang is located about 325 km from Shimla and is accessible through National Highway-

22. The Powerhouse site is located near village Rispa. An approach road to Rispa village

is available on the left bank of Sutlej. The nearest broad gauge railway station, is Kalka

on the Northern Railway which is about 400 km from the project site.

The project is located on the left bank of Tidong khad. The diversion site is located at an

elevation of 2880.00 m, downstream of the confluence of the Lambar khad with Tidong

khad. The barrage site is located in a steep valley with exposed bed rock available on left

bank of Tidong khad. Right bank is covered with the overburden and rock is exposed at

higher elevation only.

An approach road is constructed by HPPWD for connecting Moorang with Lambar village

on the right bank of Tidong khad. This road passes through the diversion site. Permanent

approach to diversion barrage is planned by constructing about 100 meters long branch

road from PWD road. This road is extended by 2900m to inlet face of Adit-1 to Head

Race Tunnel via Plant area cum muck dump yards.

Powerhouse is just located upstream of the confluence of the Tidong khad with Sutlej

river. Permanent approach roads to powerhouse, surge shaft, construction adits and

muck dumping yards are made.

For the efficient & economical execution of the project, adequate construction facilities like

project roads, colonies & construction power etc. are already in position for project

execution in Phase – I which would be sufficient for phase II also.

12.2 ACCESS ROADS AND STRENGTHNING OF EXESTING ROADS

To approach the various major components and construction sites, The following project

roads and bridges are constructed.

A 6.00 m wide and 2.46 km long approach road to power house which takesoff

from PWD road.

A bridge across Tidong khad at power house site.

An approach road of 6.22 km long to reach Surge shaft and Adit- 2 and Adit-3.

Two temporary bridges across Tidong khad at barrage site.

Approximately 100 m long approach road to connect Barrage site from HPPWD

road.

Page 163: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 12. Infrasturcutre Facilities

Indo Canadian Consultancy Services Ltd. 160 P-1143

A 2.9 km long approach road to provide access to adit-1.

Strengthening of bridges on Sutlej river wherever required.

Besides the above main roads, access roads/paths/mule paths are also be provided as

per the requirements of construction. These include:

Approach path to explosive magazines, road to crusher and aggregate processing

plants, batching and mixing plants, contractor’s staff and labour camps, stores,

sheds, workshops, plants etc.

Colony roads.

Haulage roads for removal of excavated muck to fill plant cum dumping areas.

Temporary residential colony near the power house site and at village Lambar for

the staff deployed for the construction supervision of power house, auxiliary works

and diversion works respectively.

The approach roads to reach permanent colony are constructed as permanent roads

while other roads are temporary roads

The permanent colony near Power house has a well equipped medical center as also a

recreation center, telephone exchange etc. Colony is built with Prefab structures using puff

panels which are thermal resistant. This colony has following facilities:

Potable Water Supply arrangements.

Sanitation and sewage disposal arrangements

Drainage arrangements

Internal roads and cross-drainage works

Electrical supply

Fencing and Security

Medical facility

All above facilities are proposed to be used for project development under phase – II

without any need for additional infrastructure.

12.3 TELE-COMMUNICATION

Telecommunication link between powerhouse, barrage and the project is provided by

connecting these places by extending the existing telephone network of Post and

Telegraph Department, through the nearest P&T exchange.

Page 164: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 12. Infrasturcutre Facilities

Indo Canadian Consultancy Services Ltd. 161 P-1143

An internal automatic telephone exchange (EPABX) with 50 lines capacity for the project

is provided. All important sites of work, offices and residences of senior officers are

connected by telephone.

The powerhouse and permanent colony near Power house is also provided with VHF

wireless link to keep contact with other power stations and substations in the grid. The

powerhouse shall ultimately be connected by carrier communication system.

12.4 CONSTRUCTION POWER

The construction power for execution of phase – I works is taken from available HPSEB

supply lines at the powerhouse, surge shaft and barrage sites. The power distribution

lines from these sites are laid by the Project Authorities. The contractors, engaged on the

construction of various project components, are supplied power at one point where it can

be metered. The power distribution lines for carrying power to various places of work are

installed by the contractors themselves.

In addition to power from HPSEB grid, One DG set of 1010 kVA at Powerhouse site and

Two 1010 kVA capacities at Diversion site are installed and distribution is laid for

supplying at all the working sites.

12.5 EXPLOSIVE MAGAZINE

The arrangement for storage and transportation of explosives required for the drilling and

blasting operations is made by the contractors themselves.

12.6 INFRASTRUCTURE FOR PHASE – II WORKS

All infrastructure works developed for executing project works under Phase – I

development for 2 x 50 MW power house are considered adequate for phase – II

development also. No additional cost is likely to be incurred for infrastructure works under

phase II of the project.

Page 165: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 13. Construction Methodology & Equipment Planning

Indo Canadian Consultancy Services Ltd. 162 P-1143

13 CONSTRUCTION METHODOLOGY & EQUIPMENT PLANNING

13.1 GENERAL

Construction work on various components of civil works in Phase-I development is under

progress. It is proposed to utilize the same methodology for working at site for small

quantum of work required for the installation of third unit.

Status of Phase-I civil works:

Excavations for Spillway, sluiceway and diversion channel and slope protection works are completed, and Concreting works are substantially completed.

Excavations for Head Regulator & Desilting Basin are almost completed, and Concreting works for head regulator is under progress.

Excavation works at Storage Reservoir area and gravity wall location are almost completed and concreting of gravity wall is under progress.

Underground excavations of all construction adits are completed.

Excavation of 95 % of Head Race Tunnel is completed and 10 % of concrete lining is completed. Mud mat concreting is under progress in different faces.

Underground excavation of pilot shaft for surge shaft is completed, and widening of the surge shaft is to be commenced.

Excavation of Valve house is under progress.

Excavation of underground pressure shaft is completed and fabrication of pressure shaft ferrules is under progress and erection will commence shortly

Excavation for Power house & service bay area and slope protection behind power house area are completed. Concreting of Service bay area is completed and super structure like columns and beams upto roof level has been completed. In machine hall area, concreting of raft at turbine floor has been completed and concreting of wall in powerhouse area upto generator floor has been completed.

The civil engineering works required for the installation of additional 3rd unit to be carried

out in Phase I

Surge shaft of required diameter is planned to be constructed in Phase-I works.

The excavation and rock support in unit pressure shaft-3 is planned to be

completed under Phase-I works.

The other works associated to unit-3 and planned to be completed in phase-II are

Civil Works associated with fabrication and erection of unit pressure shaft for the 3rd unit.

Excavation at Power House Building. Minor Civil works in Tail Race.

Page 166: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 13. Construction Methodology & Equipment Planning

Indo Canadian Consultancy Services Ltd. 163 P-1143

It is estimated that the additional works required for the commissioning of 3rd unit will take

about 24 months from the zero date.

13.1.1 Surge Shaft

The additional works required in surge shaft for the 3rd unit are planned to be completed

under Phase-I. The excavation of surge shaft is in progress at site and the methodology

planned under Phase-I works shall be adopted for the construction of surge shaft.

13.1.2 Unit-3 Pressure Shaft

The excavation and rock support in unit pressure shaft-3 is planned to be completed

under Phase-I works and the methodology planned under Phase-I works shall be adopted

for the excavation & rock support of unit-3 pressure shaft. Civil Works associated with

fabrication and erection of unit pressure shaft for the 3rd unit is planned to be taken under

Phase-II. The methodology adopted for fabrication and erection of ferrules under Phase-I

work shall be adopted for Phase-II works.

13.1.3 Power House and other outlet structures

13.1.3.1 Construction Methods

Main activities to be undertaken for the addition of 3rd unit of power house complex are

surface excavation, concreting along with erection of Electro-Mechanical and Hydro-

mechanical equipments. Surface excavation will comprise of common excavation in

overburden and rock excavation.

The sequence of operations for power house complex is based on the following

construction methods and equipments:

Excavation and loading of the soft material by 1.5 Cum Hydraulic excavators

assisted by 180 hp bulldozer.

The unit 3 area of Power House pit rock excavation may have to be carried out by

Rock breakers to avoid any disturbance to the concreting and equipment already

erected for unit I & II. The area excavated may have to be filled up with the same

muck

The E&M works in Power House will be taken up in parallel to civil works after the first

stage concrete in Power House is completed. The civil contractor will co-ordinate with the

agencies supplying E&M equipments and provide them all necessary support at site.

Block outs and first stage embedment shall be provided in various structures during first

stage concreting. The supply and installation of all E&M equipments required at different

fronts shall be ensured to be completed in time so that the Power House works can be

completed in scheduled time.

Page 167: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 14. Construction Schedule

Indo Canadian Consultancy Services Ltd. 164 P-1143

14 CONSTRUCTION SCHEDULE

14.1 GENERAL

It is proposed to utilize the same methodology of Phase-I work for working at site for small

quantum of work required for phase II installation of the third unit. The project area is

situated in extreme winter conditions therefore the working season is limited to 9 months,

beginning from March to November. It is estimated that the additional works required for

the commissioning of 3rd unit will take about 24 months from the zero date.

The civil engineering works involved for the additional 3rd unit are:

Surge shaft of required diameter is planned to be constructed in Phase-I works

only.

The excavation and rock support in unit pressure shaft-3 is planned to be

completed under Phase-I works.

The other works associated to unit-3 and planned to be completed in phase-II are

Civil Works associated with fabrication and erection of unit pressure

shaft for the 3rd unit.

Excavation at Power House Building.

Minor Civil works in Tail Race.

In order to achieve the benefits from the scheme at the earliest possible time, a suitable

phasing of expenditure of various component works consistent with the resources

expected to be available, is made. It is expected that it will be possible to complete the

additional works in a period of 24 months from day of the commencement of work (zero

date). A bar chart showing the approximate schedule of construction is given in

Appendix -14.1. It is proposed to mechanize all construction activities by deployment of

appropriate equipments for the timely completion of the works associated to 3rd unit.

The delivery schedule of the various generating equipment and their accessories and

other related equipments, their erection and commissioning has been planned to

synchronize with the construction schedule of civil works, so that the TG set will be put

into operation as per the programme chalked out.

The scheduled time for commissioning of 3rd unit is February 2019

Page 168: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 14. Construction Schedule

Indo Canadian Consultancy Services Ltd. 165 P-1143

APPENDIX – 14.1

Page 169: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 15. Project Organization

Indo Canadian Consultancy Services Ltd. 166 P-1143

15 PROJECT ORGANIZATION

15.1 GENERAL

The project spreads over a length of about 10 km along the left bank of Tidong khad

starting from Lambar village to Rispa village.

The construction in phase – I of project development has been supported by relevant

infrastructure works such as permanent and temporary colonies, offices, roads and

bridges, workshops etc., all situated within the project area, and the same infrastructure

facilities will be used to complete the phase –II of project development.

The phase – II of project development is planned to be completed in a period of 24

months.

The construction of the phase II of project development is proposed to be carried out

through contracting agencies entrusted with suitable contract packages. Following

packages have been envisaged for the civil and E&M works:

Powerhouse complex and its associated works including pressure shaft and tail

race channel.

Hydro-mechanical works including fabrication and erection of steel liner for

pressure shaft.

Turbine, Generator, Spherical valve and other associated auxiliary equipment.

It is also proposed that works related to preparation of detailed designs, technical

specifications and construction drawings for various components of the project would be

executed through a separate contract package by a competent consultant.

Keeping in view of the difficult hilly terrain in which the project is located and the quantum

of design and construction work involved, very close coordination would have to be

maintained to avoid time and cost over-runs. The organization of the project has,

therefore, been planned keeping the above in view and is presented in the Organization

Chart. Broad features of this organization structure are described in the following

paragraphs.

15.2 PROJECT ORGANISATION

The works would be looked after by a specific unit sets up for the purpose under the

overall control of a Project Manager for the overall management of the project. All

engineering disciplines and project services would be accountable to the Project Manager

stationed at Rispa, the Project Headquarter. The Project Manager would be assisted by

separate wings to look after the planning, material procurement, construction

management, quality control, Public relation, financial and accounts aspects of the project.

Page 170: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 15. Project Organization

Indo Canadian Consultancy Services Ltd. 167 P-1143

Organisation chart showing seven wings to be handled by Project Manager (Head

Quarter) is indicated in Figure-15.1. The organizational set up outlined above will be

supported by the necessary support staff.

Organization for Peak Construction Period

The proposed organization for peak construction period will comprise of the following:

Project Manager, responsible for overall execution of the project.

Four DGM/AGM level Senior Managers, for Quality Control, civil, planning &

monitoring, Geology and Electrical/Mechanical works. One Asst .General Manager

will take care of each of the major civil construction components of surface works ,

tunnel and power house complex. One Manager (Electrical) and One Manager (

Mechanical) for the Power house works of the E&M equipment including stores

are proposed. Required number of supporting staff (Assistant manager, Engineer,

Assistant Engineer and junior engineer) will work under the supervision of each

Manager in-charge.

One Financial Adviser along with necessary complimentary staff for ensuring

proper financial control.

One Senior Manager with necessary complementary staff to look after personnel &

administration, public health, liaison work, security, medical etc.

One Public Relations officer

The above mentioned officers shall be overall in-charge of their respective wings and shall

function as an integrated team, every member of which will not only be conversant with his

duties and responsibilities, but will also get necessary report/feed back regularly from his

respective Division for taking timely corrective measures wherever required, for achieving

targeted completion of the project. Each Division will have technical and secretarial

supporting staff as per requirement.

Project organization chart proposed for peak construction period is given in Figure-15.2

15.3 FUNCTIONS AND RESPONSIBILITIES OF PROJECT TEAM MEMBERS

15.3.1 Senior Manager (Civil)

He will be responsible for the construction of additional bay in powerhouse required for

Unit – 3 proposed in the phase – II of the project development. He will be assisted by one

manager (Civil) in execution of these works.

Manager (Civil): The manager in-charge will take care of the construction of pressure

shaft, Surge shaft and additional bay for unit – 3 in power house and its associated works

including tail race channel.

Page 171: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 15. Project Organization

Indo Canadian Consultancy Services Ltd. 168 P-1143

15.3.2 Senior Manager (Quality control)

He will be responsible for organizing all testing of materials and quality control for the

entire civil works and would also be in charge of upkeep and maintenance of all

laboratories. For this purpose, he will be assisted by a team of assistant manager,

engineers, assistant engineers and junior engineers

15.3.3 Senior Manager (Electrical and Mechanical Works)

One manager (Electrical) and one manager (Mechanical) will assist the senior manager

along with the required number of assistant manager, engineers, assistant engineers and

junior engineers for executing the following works for Electrical/Mechanical Works:

Power house electrical and mechanical works.

Switchyard and Transmission lines,

Procurement of Stores and equipment

Material management

Construction and running of workshops

Communication and Transport

Inspection and maintenance of field machinery and

Construction power.

Stores

Manager (Electrical): He will be responsible for execution of all electrical and mechanical

works pertaining to the powerhouse complex as well as construction power requirement.

Manager (Mechanical): He will be responsible for procurement of material equipment,

material management, maintenance of stores, construction and running of workshops,

communication and transport, inspection and maintenance of field machinery etc.

These managers will assisted by a team of assistant manager, engineer, assistant

engineer and junior engineers for performance of their duties.

Geology: Any and all the excavations, protection works for underground and surface

works will be taken by DGM level specialist in Geology

15.4 NEED BASED UNITS

The number of units headed by the senior managers as proposed above, are based on

the functional and physical requirements of works. The works have been so distributed

that appropriate progress is achieved for critical items of works without affecting progress

on other works.

Page 172: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 15. Project Organization

Indo Canadian Consultancy Services Ltd. 169 P-1143

Senior Managers shall execute works in a manner that all items including critical items of

work are completed on schedule to ensure timely commissioning of the project.

15.5 PROJECT PLANNING AND MONITORING

Senior Manager will be assisted at Project Headquarters directly by a Project manager

along with one manager in carrying out the functions of monitoring the progress of works,

co-ordination and liaison with various agencies, safety aspects etc.

15.6 FINANCE & ACCOUNTS

The Project Manager will have a Financial incharge (F.A.) supported by two Accounts

Officer (AO) attached to his office to support the work of accounts , costing regular and

work-charged staff establishment etc.

15.7 PROJECT ADMINISTRATION

Regarding project administration including maintenance of colonies, running of schools

and dispensaries, public relations, welfare , security etc., the Project Manager will be

assisted directly by a Senior Manager (Administration) posted in his office. The Senior

Manager (Administration) will be assisted by a Security officer along with supporting staff

to look after the vigilance and security aspects of the project areas.

The organization structure will be reviewed and firmed up as part of the detailed planning

in the pre-construction stage.

M/s NSL Tidong Power Generation (P) Ltd. will ensure adequate review of project

activities, give financial and administrative approvals and render policy guidance to the

Project Manager of the project. Support from M/s NSL will help the Project Manager in

taking expeditious decisions regarding award of contracts to competent contractors,

procurement of materials and posting of staff etc.

The project management shall function as a fully integrated team dedicated to the

implementation of the project. Every member of the team shall report regularly to his

officer-in-charge and shall be subject to review of his performance.

While the Project Manager assumes responsibility for all aspects of the project, his

deputies have to ensure that their reports etc. reflect up to date status of the project at that

point of time. They would periodically review the progress of works, identify the problem

areas suggest remedial measures, see through the implementation of such measures,

and have a realistic forecast of the status of the project in the intermediate time frame.

Page 173: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 15. Project Organization

Indo Canadian Consultancy Services Ltd. 170 P-1143

To achieve the above objective the Engineers shall ensure that they and their personnel

are interacting regularly on a day-to-day basis with all the concerned personnel of the

project whose work has a direct impact on the progress of their own work, and take

corrective actions, wherever called for, to adhere to work schedule.

15.8 TECHNICAL ADVISORY COMMITTEE

A technical advisory committee comprising of renowned international experts shall be

constituted by M/s NSL. This committee will advise the project team through Project

Manager on all critical aspects of project planning, design and construction activities.

15.9 CONSULTANTS

The Project Manager may utilize the services of Technical Consultants who will assist and

advice the project authorities on all aspects of the project implementation including

engineering design, logistics, costs and schedules, planning, construction and quality

control. The consultants will submit a monthly report indicating the work programme,

progress to date, status of drawings, problem areas and ways and means for solving the

same.

15.10 REPORTING / REVIEWS

The project will be subject to monthly reviews so that all concerned are aware of progress

to date. The monthly report will give details of manpower, productivity, materials ,logistics,

schedule and costs. The purpose of these reviews will be to highlight the problem areas

and provide the required additional supervision and action to resolve the problem. The

reports will be prepared using inputs from consultants, contractors, construction

supervisors, procurement officers etc., so that a realistic picture of the project is available

for review and report.

Page 174: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 15. Project Organization

Indo Canadian Consultancy Services Ltd. 171 P-1143

Page 175: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 15. Project Organization

Indo Canadian Consultancy Services Ltd. 172 P-1143

Page 176: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 16. Environmental & Ecological Aspects

Indo Canadian Consultancy Services Ltd. 173 P-1143

16 ENVIRONMENTAL & ECOLOGICAL ASPECTS

16.1 GENERAL

NSL Tidong Power Generation Pvt. Ltd. (TGPL) is constructing the run-off the river Hydro

Power Project of 2 X 50 MW on Tidong Khad a tributary of Satluj river AS Phase-I. The

project has obtained Environmental Clearance from MoEF vide letter no. J-

12011/35/2007-IA-I dated 7/9/2007. (Copy of the environmental clearance letter is

enclosed as Annexure-XIV-1).

The detailed hydrological study conducted recently indicates that the flow condition of the

Tidong Khad has a potential to generate more power. The required water flow of 28.60

cusecs with 90% dependability is available which can generate 50 MW more power. NSL

TPGPL is proposing to expand the existing power generating capacity from 100 MW to

150 MW by installing third unit of 50 MW. The excess water which is available in the khad

will be utilized for expansion project. The 15% of the lean flow will always be maintained

in the khad to comply with the condition of Environmental Clearance.

The design components of the existing project like spillway, under sluice, desilting

chamber, Head Race Tunnel, Surge shaft, Pressure shaft etc. have adequate capacity to

generate additional 50 MW capacity. Therefore this additional 50 MW power generation

can be achieved without any change/modification in the existing design. Only one Turbine

and Generator of 50 MW capacity shall be installed in the area adjacent to the existing

units in the power house. This will improve the cost per MW of power and benefit the

nation.

The installation of Unit 3 will be located within the project area and no additional land is

required.

NSL TPGPL will adhere to the environmental conditions as approved in TEC and maintain

15% of the lean flow in the river downstream of the intake during operation of the project.

The observations made in the earlier EIA studies indicate that there are no aquatic life in

the Tidong Khad.

16.2 SUBMERGENCE

As only diurnal storage is envisaged, no submergence is involved. The water will be

diverted through the spillway and no land will be submerged.

No habitation will be affected due to the implementation of the expansion project and there

will not be any displacement of any population and loss of cultivated land.

Page 177: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 16. Environmental & Ecological Aspects

Indo Canadian Consultancy Services Ltd. 174 P-1143

16.3 EFFECT ON CLIMATE

The project layout and planning ensure no submergence and impoundment of water that

could influence the microclimate of the region, there will be no effect of the project on the

climate.

16.4 CATCHMENT AREA TREATMENT

There is no change in the catchment area to the spillway site. Therefore the Catchment

Area Treatment (CAT) plan prepared earlier stands good. CAT plan was prepared and

approved by the Forest Department. Subsequently, NSL TPGPL has deposited Rs.

7,24,00,000/- to Forest Department for implementation of CAT plan.

16.5 SEISMICITY

The project area lies in the Himalayan Region and is susceptible to earthquakes. The area

as per ISI classification falls in seismic zone V. Proper seismic co-efficients have already

been taken into consideration during design stage of the project.

16.6 REHABILITATION

The installation of 3rd unit is located within the area of project under construction and no

additional land is required. Therefore the land acquisition and displacement of the

habitation is not envisaged.

16.7 OTHER PREVENTATIVE MEASURES

16.7.1 Restoration of construction areas and disposal of muck

All the construction areas are properly planned so as to merge the project in the natural

surroundings after completion of the construction work. There will not be any additional

muck generation in the proposed expansion project since all the components of the

project under construction are adequate and no more extra excavation/construction work

is needed. The muck is being stacked systematically at the muck dump area approved by

HPPCB.

16.7.2 Anti Poaching Measures

Proper training is being given to all the construction labour and project staffs and educated

in terms of environmental concerns and relevant anti poaching laws.

16.7.3 Environmental Impact and Mitigation Measures

The environmental impact which occur as a result of construction activity of spillway,

intake structure, desilting tank, head race tunnel, pressure shaft, power house, road

construction, housing and dumping of excavated material etc., are already considered in

Page 178: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 16. Environmental & Ecological Aspects

Indo Canadian Consultancy Services Ltd. 175 P-1143

the existing project under construction and necessary mitigation measures are being

implemented. Since there is no additional construction work with very little excavation

involved for the expansion project, no additional impacts are envisaged. The mitigation

measures, which are being implemented, are adequate.

Further, there is no additional land requirement for the expansion project and

consequently there will be no adverse social impact on the nearby habitation.

NSL TPGPL is committed to release 15% of the lean flow at any given time in the Tidong

Khad to preserve the aquatic life.

A summary of environment management plan, which is under implementation, is given as

under:-

The EIA study has established the fact that the Tidong Khad is not a biologically

rich area and no fishe were observed. However, we have already deposited Rs.

1.11 crore to Fishery Department, Bilaspur to improve and conserve the biological

life of the Tidong kahd.

Catchment Area Treatment plan has been prepared and approved by the Forest

Department. The amount of Rs. 7,24,00,000/- have been deposited to forest

department for the implementation of CAT plan.

Compensatory afforestation scheme has been prepared by the Forest Department

and Rs. 2,66,76,610/- are deposited for the implementation of the same.

Environmental Monitoring Plan has been prepared and monitored by HPPCB. The

amount of Rs. 25.02 Lakh is already paid to HPPCB for the same.

Local Area Development Fund of Rs. 6,41,40,000/- has been paid to LADA for

development of infrastructural facilities in the affected villages.

16.8 BENEFITS

One of the main reasons for promoting hydroelectric schemes is their environmentally

friendly character. This form of energy, unlike the energy from other conventional sources,

entails no discharge of wastes or emission of toxic gases. It is virtually free from pollution

and is therefore looked as “technology of the future” for the rural and remote areas. The

generation of energy at low cost will help in reducing the demand for fuel wood and will

help in reducing the global warming impacts. This is renewable energy and Eco-friendly.

The expansion of the project by adding 50 MW will help to reduce the overall cost of

power generation resulting in the lower tariff, which would benefit the people, state and the

country at large.

Page 179: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 16. Environmental & Ecological Aspects

Indo Canadian Consultancy Services Ltd. 176 P-1143

NSL TPGPL has implemented CSR activities in surrounding villages like Lamber, Thangi,

Rispa and Moorang etc. in addition to funds deposited to LADA. Further, many local

persons have got the employment in the project. NSL TPGPL has awarded many petty

contracts to local people. This has benefited the local population in improving the socio-

economic condition.

16.9 CONCLUSION

The Phase-II of the Tidong I HEP is being taken up without acquiring any further land nor

raising any further structures either in the surface or sub-surface works, not affecting any

habitation, no displacement of population, no submergence, cause no pollution etc.

Phase-I of the project was accorded the Environmental Clearance by MoEF based on the

detailed environmental assessment study. Further Environment Impact Assessment for

the Phase-II project is not required since there is no land acquisition.

ECOLOGICAL ASPECTS OF HYDRO-ELECTRIC PROJECT

1.01 Detailed basic information affecting the environment.

The project consists of a spillway, desilting tank, head race tunnel, surge shaft, pressure shaft, power house etc. All these components are being constructed for the project under construction and the design of these components are capable to accommodate additional 50 MW expansion project. No additional construction is required for the expansion project.

Thus the expansion project does not have any adverse effect on the environment.

02 Break up of submerged area total submerged area of the reservoir.

The capacity of all the components of the project under construction are adequate for the installation of 3rd unit of 50 MW. Therefore, the question of submergence does not arise. There is no requirement of additional land.

Forest land Nil

Cultivated land Nil

Shrubs & fellow Rocky Output Nil

Wetland Nil

Open water other use Nil

03 Forest type in catchments and submerged areas.

Nil

Extent and nature of forest to be cut for construction of roads, colony and other appurtenant

Nil

Page 180: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 16. Environmental & Ecological Aspects

Indo Canadian Consultancy Services Ltd. 177 P-1143

works.

04 Duration of Project construction

24 months

05 Estimated peak labour strength

Skilled / Technical 200

Unskilled / Non-Technical 600

Labour to be recruited from affected population.

No population would be affected by the expansion project. Local labour is being recruited as per the requirement. However, local population has been given the employment in the existing project under construction.

Skilled

Unskilled

.06 Population density in the area per sq. km.

60 persons per sq. km. (Dist. Kinnaur)

07 Number of villages and population to be displaced.

No displacement of population of the village.

No. of villages. Nil

Size of village. Not applicable

Affected families in each villages Not applicable

Occupation of the affected people.

Not applicable

Agriculture Nil

Industrial labour Nil

Forest based Nil

Owner cultivators by size of land holdings.

Marginal (1.0-2 hect.) Not applicable

Small (1.0 –2 hect.) Not applicable

Medium (2-5.0 hect.) Not applicable

Big (Over 5.0 hect.) Not applicable

08 Resettlement

Is a rehabilitation committee being constituted.

Resettlement is not involved.

Existing guidelines, if any for compensation in cash and kind.

Nil

Number of ousted families likely to be settled in new settlement.

Nil

Size of the proposed new settlement.

Nil

Page 181: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 16. Environmental & Ecological Aspects

Indo Canadian Consultancy Services Ltd. 178 P-1143

09 Layout plans/master plans for new settlements.

Nil

Distance of new settlements from the present habitat.

Nil

Number and type of facilities Approach road and paths (e.g. school, post offices, for the project area bank, approach road drainage and water supply etc., proposed to be provided).

Nil

10 Is the affected area covered by development programmes like IED, SED, Drought prone area, tribal development etc.?

No

11 Any proposal to provide or create employment for oustees; nature and quantum of employment to be provided.

No oustees under expansion project. However, land oustees under the project under construction have been given the employment.

12 Wind at Dam site (diagram giving statistical information concerning the direction and speed of the wind at the site.

Predominant wind direction in the morning and evening are NE and SW respectively.

Hurricane, tornadoes, cyclones. : Nil

13 The depth of ground water table : Potable

Maximum : Not applicable

Minimum : Not applicable

Quality of ground water potable/non potable/fit for irrigation/industry.

: Potable

14 Present ground water use pattern in the command area under irrigation.

: Not applicable.

15 Based on the experience of similar project in the area, specify the interaction between the altered surface water patterns and underground aquifers and their recharge.

: Not applicable

00 ENVIRONMENTAL STATUS

01 Indicate known pollution sources in the region (indicate the Industrial like chemicals, textiles and other thermal power units, mining operations etc.).

: None

02 Indicate the industrial and other development project likely to be

: None

Page 182: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 16. Environmental & Ecological Aspects

Indo Canadian Consultancy Services Ltd. 179 P-1143

taken up in the area during the next five to ten years.

03 Does the area support economically viable aquatic life, fish and crocodiles?

: No

Are there any fish/crocodiles breeding ground in the river tributaries in the submergence?

: No

04 Does the site contain a wild life (including birds) habitat, breeding area, feeding area, migration route including the number of wild life available in the area.

: No

05 Is the site potential wild life sanctuary?

: No

06 Specify any rare or end-angered species of flora and fauna in the affected area along with their approximate number and measures to salvage/rehabilitate them.

: No

07 Is the area a tourist resort? : No

08 Are any monuments/sites of cultural, historical, religious, recreational importance including wild life sanctuaries, national park etc. likely to be affected by the proposed project. If so, details thereof.

: No

09 Does the proposed area suffer from endemic health problems due to water/soil borne diseases.

: No

00 ENVIRONMENTAL IMPACTS

01 What measures are planned to develop the site to enhance its aesthetic aspects (i.e. recreation and water sport facilities and picnic sites etc.)

: Not proposed,

02 Will the project help in flood control, reduction for even eradication of flood havoc downstream?

: No

03 Are any changes in water salinity expected? If yes, give details of proposed measures to counter act this.

: No

Page 183: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 16. Environmental & Ecological Aspects

Indo Canadian Consultancy Services Ltd. 180 P-1143

04 Are problems of water logging envisaged in the command area? If so give details of proposed steps to combat the problem.

: No

05 Will the reservoir be used for fisheries development, fish culture as well as fish breeding, crocodile, farming etc? if yes, give details thereof.

: No

06 Will fish ladder/lift and like arrangements be provided to allow movements of import-ant migratory fish population?

: Not applicable

07 Measures proposed to prevent grazing the cultivation on reservoir slopes to avoid erosion and premature silting up the impoundment

: Not applicable

08 Will any important natural resources (minerals, coal, timber etc.) be lost or their use precluded because of the presence or operation of the project? If yes, specify the resources estimated loss.

: No

09 What is potential loss in aquatic production on site up and down stream, fish and other useful animals and plants.

: Nil

10 Will the formation and use of the water body result in the introduction of enhancement of water borne diseases?

: No

11 Will the impounded reservoir lead to:-

Noxious aquatic weeds like salina, water Hyacinth etc.

: No

Intermittent host (vector) like snails, mosquitoes etc.

: No

12 How will aquatic weeds be controlled in submerged areas so as to provide an improved habitat as for fishery exploitations.

: Not applicable

13 Will the project induce ad-verse climatological changes (regarding temperature, humidity, wind and precipitation

: No

Page 184: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 16. Environmental & Ecological Aspects

Indo Canadian Consultancy Services Ltd. 181 P-1143

including modifications to macro and micro climate)?

14 What impact is expected on geological factors (e.g. seismic impact or reservoir loading)?

: No impact

15 Indicate the magnitude of impact due to population pressure on:-

Felling of trees for firewood. : Nil

Forest fires : Nil

Overgrazing leading to depletion of the pastures.

: Nil

Visual pollution and damage to scenic values.

: Nil

16 What arrangements are being made:-

i) to meet fuel requirements of the labour force during construction period to prevent indiscriminate felling of trees for firewood?

:

LPG gas is provided by the contractors to labours. In case of emergency, fire wood is purchased from the authorized vendors.

For compensatory a forestation? : Not applicable

To enforce anticipating laws? : Not applicable

To control flow to sediments and pollutants due to fertilizer and pesticide run-off for cultivated area.

: Not applicable

For restoration of land in construction areas (filling, grading and reforesting etc. to prevent erosion).

: The muck dumps will be re-vegetated after the muck generation is stopped to control the erosion

For soil conservation in the catchment?

: Plantation

00 COST OF ENVIRONMENTAL STUDIES AND PROJECT MANAGEMENT

01 Provision for Environmental studies/ surveys need for this project.

: Not required

02 Cost of proposed remedial and mitigative measures, if any, to protect the environment.

: Not required

03 Has the cost of environmental studies/protection measures been considered in the cost benefit analysis of the project?

: Not applicable

Page 185: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 17. Cost Estimate

Indo Canadian Consultancy Services Ltd. 182 P-1143

17 COST ESTIMATE

17.1 GENERAL

The estimate of cost has been prepared in detail to arrive at the total capital cost of the

project. The estimate is based on the actual rates as being executed and updated to year

2014-15 level.

17.2 BASIS OF COST ESTIMATE

The Phase-II estimates are prepared as per Central Water Commission guidelines

contained in the Publication entitled Broad Guidelines for the preparation of Project

Estimates for Major Irrigation and Multipurpose Projects. The guidelines contained in the

Indian Renewal Energy Development Agency Limited (IREDA) publication titled Best

Practices Manual on Small Hydro have also been followed.

The quantities of various items have been worked out from the drawings

prepared on the basis of preliminary planning and design of various components of

works after review of site conditions. At some places lump sum cost has been

considered where detailed breakup is not possible at present.

The estimate for the Generating Equipment - Electrical and mechanical works are

based on actual purchase orders placed for E & M equipment for the first 2 units

and adding possible escalations upto the completion of the project.

A provision of 1 % for building construction workers welfare cess

A provision of 4.944% of the cost has been made towards Service Tax in the

estimate of civil works.

Contractor overhead and profit @ 20% has been considered.

17.3 ESCALATION IN COST

It is estimated that with the adoption of the available technology for construction of the

various component works and considering the present status of works, the Project can be

completed in a period of 24 months. Therefore, it is appropriate that the estimated cost of

the Project as in the current year 2014-2015 is updated to the date of completion by

adopting suitable rates of average annual escalation of prices, at 7%.

17.4 DETAILS OF COST ESTIMATES

The provisions made under the various heads of cost estimate are briefly explained in the

following paragraphs.

Page 186: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 17. Cost Estimate

Indo Canadian Consultancy Services Ltd. 183 P-1143

I-WORKS

A Preliminary (Rs. 10.80 Crores)

Under this sub-head, provision has been made for topographical surveys, field and

laboratory tests on rocks, construction material investigations and testing, collection

of hydrological and meteorological data, etc. Provision has also been made for

consultant's fees for preparation of the project report and other reports.

J Power plant civil works (Rs. 22.04 Crores)

Under this sub-head, provision has been made for the following works:

Civil Works associated with fabrication and erection of unit pressure shaft

for the 3rd unit.

Excavation at Power House and Building.

Minor Civil works in Tail Race.

O Miscellaneous (Rs. 0.50 Crores)

Under this sub-head provision has been made for the following items:

Capital cost of electrification, water supply, sewerage disposal and drainage.

Fire fighting equipment, telephone and other communication facilities.

Maintenance services for electrification, water supply etc. and other

Services including security arrangement and fire fighting arrangement.

Running of inspection vehicles, transport of staff and ambulances.

Other items such as visits of dignitaries, technical record of works, power

supply, compensation to workmen, writing of completion and history of

project etc.

P Maintenance (Rs. 0.10 Crores)

The provision has been made under this sub-head for maintenance of buildings,

roads and main civil works during construction period of the project.

Q Special Tool and Plants (Rs. 0.15 Crores)

Cost provided under this sub-head for general purpose equipments to meet

exigencies, inspection vehicle and ambulance. Provision for construction equipment

for civil works has not been made under this sub-head, as its cost shall be

recovered from the works, as per norms.

Page 187: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 17. Cost Estimate

Indo Canadian Consultancy Services Ltd. 184 P-1143

X Environment and Ecology (Rs. 0.20 Crores)

The provision under this sub head covers the cost of landscaping, Public Health

Measures, etc. The cost is based on the current estimates and may vary with the

actual plans prepared by the various govt. Bodies. Provision for Catchment Area

Treatment (2.5% of Final Cost) and Local Area Development Fund (1.5% of Final

cost of Project) is included separately.

II-Establishment (Rs. 2.00 Crores)

A provision of Rs 2.00 Crores has been made towards establishment cost during

construction of Phase-II works.

2 b) Audits and Accounts (Rs. 0.99 Crore)

Provision of Rs 0.99 Crore has been made for Audit and Accounts.

2 c) Design Engineering Services (Rs. 2.00 Crores)

A provision of Rs 2.00 Crores has been made towards Detailed Design Engineering

services cost during construction of Phase-II works.

Cost of Electromechanical Works (Rs. 65.76 Crores)

The cost of the turbine, generator and the related electrical and mechanical

equipment for setting up of Unit-3 has been worked out as Rs. 65.76 Crores. The

cost under this head also covers transportation, insurance, erection &

commissioning charges. Major component of the electro-mechanical equipment are:

Turbine, Generator Set, Main Inlet Valve;

All Balance of plant (BOP) Electrical Equipments;

All BOP Mechanical Equipments;

Main Power Transformers;

Switchyard equipment and interconnection.

17.5 ESTIMATED COST OF THE PROJECT

The total cost of the project at December, 2014 price level works out as under:

Page 188: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 17. Cost Estimate

Indo Canadian Consultancy Services Ltd. 185 P-1143

ABSTRACT OF COST OF CIVIL WORKS Sl. No.

Description Amount in

lakhs

A CIVIL WORKS

1 DIRECT CHARGES

I - Works

A- Preliminary

1,080.00

B- Land -

C - Works -

J. Power Plant civil works

1. Pressure Shaft

693.17

2. Power House

1,387.52

Total for J-Works

2,080.69

Add @1% on J-Works for Construction Workers Cess 1.00%

20.81

Add @4.944% on J-Works for Service Tax 4.944%

102.87

Total for J- Works with Taxes

2,204.37

K - Buildings -

M - Plantation -

O - Miscellaneous

50.00

P - Maintenance

10.00

Q - Special Tools & Plants

15.00

R. communication -

S - Power Plant & Electro-Mechanical System

6,576.44

X - Environment & Ecology

20.00

Y - Utilities and other Services

10.00

Total of I - Works

9,965.81

II Establishment

200.00

III - Tools and Plants @ 1% of cost of I - Works

99.66

IV - Suspense -

V - a)Receipt & Recoveries -

b) Resale value of Temporary buildings -

TOTAL DIRECT CHARGES 10,265.47

Page 189: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 17. Cost Estimate

Indo Canadian Consultancy Services Ltd. 186 P-1143

ABSTRACT OF COST OF CIVIL WORKS Sl. No.

Description Amount in

lakhs

2 INDIRECT CHARGES

a) Capitalised Value of abatement of Land Revenue -

b) Audit and Account charges @ 1% of Cost of I - works

99.66

c)Design engineering services

200.00

TOTAL INDIRECT CHARGES

299.66

TOTAL DIRECT AND INDIRECT CHARGES

10,565.12

3 Escalation 878.00

4 IDC & Financing Charges 1,539.00

5 CAT 324.55

6 LADA 194.73

7 Total Cost

13,501.41

Page 190: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 17. Cost Estimate

Indo Canadian Consultancy Services Ltd. 187 P-1143

TIDONG - I (PHASE-II) HEP

A - PRELIMINARY

It.No. Description of Item Unit QuantityRate in

Rs. Amount

1 Expenditure towards the Survey and

Investigation works, discharge measurement LS

10.00 2 Topographical surveys, preparing block levels

of the various components of the Project. LS

10.00 3 Printing project reports, estimates and Design

reports and completion reports LS

10.00 4 Charges payable to GoHP @ Rs 20 Lakh per

MW LS

1,000.00 5

Consultancy for DPR+ DPR Clearance LS

50.00

Total Estimated

Cost

1,080.00

Page 191: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 17. Cost Estimate

Indo Canadian Consultancy Services Ltd. 188 P-1143

J1‐Pressure Shaft 

Abstract of Quantities 

S.No.  Description of Items  Unit  Quantity  Rate (Rs) Amount (Rs in

Lakhs)

1 Supply and placing of M15 concrete backfill behind steel ribs/steel liner 

m³                                 1,000.00  

          5,349.00  

                              53.49  

2 Steel Liner including horizontal shafts 

MT                                 350.00  

     173,335.20  

                            606.67  

    Sub Total                                       660.16  

3  Contingencies @ 3 % of Sub Total cost excluding LS Items  

   3%                                    20  

4  Work Charged Establishment @ 2 % of Sub Total cost excluding LS Items  

   2%                                    13  

    Total Cost                                   693  

Page 192: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 17. Cost Estimate

Indo Canadian Consultancy Services Ltd. 189 P-1143

J2‐Power House 

Abstract of Quantities 

S. No.

Description Unit Quantity Rate (Rs) Amount (Rs

in Lakhs)

1 Site clearance LS    10 

2 Excavation      

2.1 Common excavation m³

5,000.00                251  

                     12.55  

2.2 Rock excavation m³

15,000.00                537  

                     80.55  

3 Rock stabilization and supports

3.1 Rock bolts including accessories and testing of bolts 32 mm

m

500.00             1,571  

                       7.86  

3.2 Welded wire mesh reinforcement (4mm thick, 100 mm*100 mm opening)

500.00                316  

                       1.58  

4 Shot crete m³

50.00             8,792  

                       4.40  

5 Supply and installation of PVC pipe 70mm dia

m

200.00                669  

                       1.34  

6 Concrete      

6.1 PCC (M10) m³

150.00             5,349  

                       8.02  

6.2 Reinforced concrete M25/A40 (Second stage)

5,000.00             6,551  

                  327.55  

7 Reinforced steel      

7.1 Deformed reinforcing bars Grade Fe500

MT

300.00          74,284  

                  222.85  

8 Structural Steel MT

500.00          91,869  

                  459.35  

9 Brickwork m³ 150.00  7,116   10.67  

    Sub Total            1,147  

10  Miscellaneous and Architectural, Building works etc @ 10 % of Sub Total cost excluding LS Items  

 LS   10%                      114.67  

11  Instrumentation works @ 1 % of Sub Total cost excluding LS Items  

   1%                             11  

12  Dewatering works @ 3 % of Sub Total cost excluding LS Items  

   3%                             34  

13  Contingencies @ 5 % of Sub Total cost excluding LS Items  

   5%                             57  

14  Work Charged Establishment @ 2 % of Sub Total cost excluding LS Items  

   2%                              23  

    Total Cost               1,388  

Page 193: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 17. Cost Estimate

Indo Canadian Consultancy Services Ltd. 190 P-1143

TIDONG - I (PHASE-II) HEP O - MISCELLANEOUS

It.No. Description of Item Unit Amount

(Rs. in Lacs) 1.00 Capital Cost

1.01 Electrification at work sites, colony etc. LS 2.00

1.02 Water supply, purification and distribution arrangements including

purchase of water tankers, cost of tanks and chlorination LS 2.00

1.03 Providing sewage disposal and storm water drains at various colonies sites LS 1.00

1.04 Furnishing and equipping rest houses, field hostels, hospitals,

schools etc. LS 1.00 2.00 Maintenance and Service charges during execution period 2.01 Maintenance of Power arrangements LS 1.00

2.02 R & M of water supply facilities LS 1.00

2.03 R & M of sanitation and drainage facilities LS 1.00

2.04 R & M of Telecommunication system and post office LS 1.00

2.05 R & M of Hospitals LS 2.00

2.06 R & M of Rest houses and field hostel LS 1.00

2.07 R & M of Research and Quality control laboratories LS 1.00

2.08 Labour welfare compensation and retrenchment benefits LS 2.00

2.09 Providing Security Police including R & M of posts LS 2.00

2.10 R & M of inspection vehicles and staff cars LS 2.00

2.11 R & M of school buss and staff buses LS 2.00

2.12 R & M of Ambulance LS 2.00

2.13 R & M of field workshops LS 1.00

2.14 Maintenance and running of school LS 2.00

3.00 Miscellaneous

3.01 Group Insurance LS 10.00

3.02 Compensation for accidents LS 10.00

3.03 Training personnel abroad including study courses and visits LS 3.00

TOTAL 50.00

Page 194: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 17. Cost Estimate

Indo Canadian Consultancy Services Ltd. 191 P-1143

TIDONG - I (PHASE-II) HEP P - MAINTENANCE

Amount in Rs. Lakhs

It.No. Description of Item Unit Quantity Rate Amount

1 Maintanance LS 10.00 Total 10.00

Page 195: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 17. Cost Estimate

Indo Canadian Consultancy Services Ltd. 192 P-1143

TIDONG - I (PHASE-II) HEP

Q - SPECIAL TOOLS AND PLANTS

It.No. Description of Item Unit Quantity Rate Amount

1 Ambulance 1

8.00

2 Jeep 1

7.00

Total for 'Q- Special tools and Plants' 15.00

Page 196: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 17. Cost Estimate

Indo Canadian Consultancy Services Ltd. 193 P-1143

Page 197: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 17. Cost Estimate

Indo Canadian Consultancy Services Ltd. 194 P-1143

Page 198: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 17. Cost Estimate

Indo Canadian Consultancy Services Ltd. 195 P-1143

Page 199: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 17. Cost Estimate

Indo Canadian Consultancy Services Ltd. 196 P-1143

Page 200: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 17. Cost Estimate

Indo Canadian Consultancy Services Ltd. 197 P-1143

Page 201: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 17. Cost Estimate

Indo Canadian Consultancy Services Ltd. 198 P-1143

Page 202: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 17. Cost Estimate

Indo Canadian Consultancy Services Ltd. 199 P-1143

TIDONG - I (PHASE-II) HEP

X - ENVIRONMENT & ECOLOGY& SOCIAL DEVELOPMENT

It.No. Description of Item Unit Qty Rate Amount

1 Miscellaneous LS 20

Total 20.00

Page 203: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 18. Financial & Economic Evaluation

Indo Canadian Consultancy Services Ltd. 200 P-1143

18 FINANCIAL AND ECONOMIC EVALUATION

18.1 GENERAL

Tidong-I Phase-II HE Project (50 MW), at December 2014 price level is estimated to cost

Rs. 129.83 Crores excluding IDC, Escalation and Financial Charges. Assuming an annual

escalation of 7% & 3.05% per annum in respect of the civil works and electro-mechanical

works, the completed cost is estimated to be around Rs. 135.01 Crore including IDC and

Financial Charges.

Pre-construction activities and infrastructure development works would be carried out prior

to start of the main civil works. A total construction period of 24 months has been

considered for completion of the project.

The project is estimated to be financed in a Debt: Equity ratio of 70:30, with the financing

terms including;

Interest of 14% per annum on loan.

Loan repayment of 10 years post construction.

The Design Energy of Tidong-I Phase-II Hydro Electric Power Project is assessed to be

218.48 MUs at the generator terminals after considering mandatory ecological releases

equivalent to 10% of the minimum inflows in 90% dependable year. After considering

auxiliary consumption, transformation losses and free Power to the Government of

Himachal Pradesh @ 12% for the lease period, the net saleable energy is 190.34 MUs.

The financial analysis was carried out following the applicable CERC tariff norms, which

inter-alia allows 15.5 % post-tax return on the equity. The 40 years levelised tariff as per

the CERC norms works out to Rs. 1.31 per KWh. Major base case assumptions/ key

results in the financial analysis conducted for the project are summarized below:

18.2 ANALYSIS OF THE MAJOR ASSUMPTIONS

The major assumptions and findings of the analysis are given below followed by the tariff

& cash flow statements:

Page 204: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 18. Financial & Economic Evaluation

Indo Canadian Consultancy Services Ltd. 201 P-1143

18.2.1 Project Cost in Rs. Crores

Description Amount (Rs)

Total Hard Cost of the Project 105.65

Up front Lenders’ Financing fees 3.88

Interest During Construction (IDC) 11.52

Escalation 8.78

TOTAL PROJECT COST 135.01

Margin money for working capital -

GRAND TOTAL (At December’14 Price Level)

135.01

18.2.2 Capital Structure in Rs Crores

Description Amount (Rs)

Equity (30%) 40.51

Debt (70%) 94.51

TOTAL

18.2.3 Debt Financing Terms

Term of Loan (Post construction) 10 years

Interest Rate on loan 14%

Interest on working capital 14 %

18.2.4 Plant Details

Unit Capacity 50 MW

No of Units 1

Plant Gross Capacity 150 MW

Auxiliary Consumption & Transformation Losses 1.00 %

Page 205: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 18. Financial & Economic Evaluation

Indo Canadian Consultancy Services Ltd. 202 P-1143

18.2.5 Generation Details

Primary Generation (90% Dependable year) in MUs 218.48

Less: Auxiliary & Transformation Consumption (@ 1.00%) in MUs 2.18

Total Energy Metered in Million Units 216.30

- Royalty payable to GoHP 12% 25.96

- Total Energy Billed in Million Units before 12 years in MU 190.34

18.2.6 O & M

Annual O&M as a % of Project Cost 2.00 %

Annual O&M Escalation 5.72%

18.2.7 Working Capital

Interest on Working Capital 14%

18.2.8 Depreciation

Depreciable Value 90 %

18.2.9 Tariff (Calculated as per CERC Norms)

Description Rs / KWh

First Year Tariff Rs./KWh 1.48

Levelised Tariff of 1st Thirty Forty years

Rs./KWh 1.31

18.2.10 Conclusion

The levelised tariff of 1st 40 years as Rs. 1.31/ kWh calculated with financial parameters

mentioned above suggests that Tidong-I Phase-II Hydro Electric Project is techno-

economically viable for implementation. With easy accessibility to the project, it can be

taken up for active construction immediately.

Page 206: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 19. Recommendations

Indo Canadian Consultancy Services Ltd. 203 P-1143

19 RECOMMENDATIONS

19.1 GENERAL

The Phase-I of Tidong-1 Hydro electric project comprising of an installation of Pelton

turbines with rated capacity of 2x50 MW each is under advanced stage of completion.

Based on updated hydrological study of flow in Tidong River, it is observed that installed

capacity of Tidong-I HEP Phase I can be enhanced from 100 MW of project development

to 150 MW in phase II with provision of one additional TG unit of 50 MW capacity. The

project involves construction of conventional civil structures with the availability of

Reservoir the project is ideally suited for providing peaking power. The project would

afford a peaking benefit of 100 MW for 4 hours per day in phase I, and 150 MW for 3

hours per day in phase II of project development during lean seasons.

Shown in the detailed project report, prepared in 2006, anticipated the annual energy

generation is 414.15 MU with 100 MW installed capacity in a 90 % dependable year

(2004). With the improved hydrological series, the annual energy generation after

completion of phase I with 100 MW and phase II with 150 MW is estimated to be about

539.43 MU and 632.63 MU respectively in a 90% dependable year (2004-05) with 95 %

plant availability.

The power generated would be transmitted to the Northern regional power grid. The

additional capital cost, including the escalation, financial charges and interest charges

during construction period, for 50 MW additional installed capacity in phase II has been

estimated to be about Rs. 135 crore, which is considered very attractive as compared to

other projects of similar magnitude in the region. Addition of one unit of 50 MW capacity in

phase – II will also improve techno-economical feasibility of the ongoing Tidong -1 Phase I

HEP having installed capacity of 2 x 50 MW. The project implementation period is

anticipated as 24 months including winter / monsoon months after obtaining all required

project clearance and achieving financial closure.

19.2 PRELIMINARY AND PRE-CONSTRUCTION WORKS

In order to ensure the commissioning of third unit, as proposed in the phase –II of project

development by the end of February 2019, the already available infrastructure

development at site will be used. The following activities have already been completed

under phase – I development.

Acquisition of land and completion of main infrastructure facilities.

Completion of detailed designs and specifications.

Firm financial arrangements for taking up the construction, and

Award of work for major components and substantial completion of Civil and E&M

works.

Page 207: TIDONG-I HYDRO ELECTRIC PROJECT (PHASE II – …...Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. Table of Contents Indo Canadian Consultancy

Tidong-I Phase-II HEP Detailed Project Report NSL Tidong Power Generation Pvt. Ltd. 19. Recommendations

Indo Canadian Consultancy Services Ltd. 204 P-1143

19.3 RECOMMENDATIONS

Tidong – I HEP Phase – II is expected to provide additional 50 MW power at very

reasonable capital cost and is recommended for implementation at the earliest. The

following sequential activities are recommended for early project commission.

Obtaining Techno Economic Clearance for additional 50 MW installation under

phase II development

Obtaining all clearance for phase II development

Achieving Financial closure

Conducting detailed Engineering designs and preparation of tender documents

and award of works and speedy implementation of installation of third unit of 50

MW under phase II.


Recommended