Tier 2 Public Meeting I-10 West Alternatives Analysis November 6, 2008 November 13, 2008
Transcript
Page 1: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

Tier 2 Public MeetingI-10 West Alternatives Analysis

November 6, 2008November 13, 2008

Page 2: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

Project Status and Overview

I-10 Mainline Tier 2 EvaluationEvaluation CriteriaStation LocationsEnd of Line configuration

I-10 Downtown Tier 2 EvaluationEvaluation CriteriaTier 2 AlignmentsLRT Connections to CP/EV Starter Line

Next Steps

Agenda

Page 3: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

Future Extension Corridors

Page 4: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

I-10 West Study Area

Page 5: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

I-10 West High Capacity Transit StudyProject Goals

Improve regional mobility

Enhance transit system connectivity

Provide access to corridor destinations and employment (State Capitol) and support economic development

Provide cost-effective transit improvements

Minimize environmental impacts

Page 6: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

Alternative Analysis Process

Page 7: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

Study Recommendations

Alignment/Route

Transit OptionsLight Rail TransitBus Rapid TransitLocal Bus

Preliminary Station Locations

Page 8: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

Decision-Making Process

Page 9: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

Stakeholder InputPublic Meetings

State, County, and City Departments

Neighborhood Groups

Special Interest Groups

One-on-one Meetings

Community Working Groups

Page 10: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

Purpose and Role of the Community Working Group

Provide input and feedback to the Project Team during the Tier 2 Process.

Page 11: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

Light Rail Transit (LRT) Features

Electrified overhead wireDedicated right-of-way3 Car Train = 525 Passengers

Completed section of Washington St. - Phoenix

Page 12: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

Bus Rapid Transit (BRT) Features

Exclusive lanes or roadway (50% minimum during peak periods)1 Bus = 60-80 Passengers

AND / ORTraffic signal prioritySpecial design (low floor)Substantial stationsSpecial branding/identityFrequent service

10-minute peak, 15-minute off-peak

Page 13: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

Comparison of LRT and BRT

Lower, if demand is moderate

Lower, if demand is high

Long Term Costs

1,000 passengers5,000 passengersHourly Capacity in One Direction

Can use guideway or share lanes with cars

Restricted to guideway

Operational Flexibility

Limited opportunitySignificant opportunity

Economic Development

LowerHigherConstruction Cost

Bus Rapid Transit(BRT)

Light Rail Transit(LRT)

Page 14: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

I-10 West: Approvals to Date

Recommendation for High Capacity Transit Improvements Recommendation for High Capacity Transit Improvements in the Iin the I--10 Right10 Right--ofof--Way west of IWay west of I--17:17:

Phoenix City Council Phoenix City Council –– April 2008April 2008METRO Board METRO Board –– June 2008June 2008MAG Regional Council MAG Regional Council –– July 2008July 2008

Page 15: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

Mass Transit Median in I-10

50-foot median preserved for future mass transit as part of I-10 completion

Page 16: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

I-10 Potential Station Area Locations

Page 17: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

Tier 2 Downtown Alternatives

Page 18: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

I-10 West Mainline

Page 19: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

This process is highly interactive and seeks to determine:

Station Planning Process

Where stations should be located along the alignment

What functions each station will serve (regional park-and-ride, neighborhood serving, destination, special generator, etc…)

Page 20: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

Mainline Station Evaluation Criteria

MOBILITYProjected daily station boardingsProximity to regional N/S arterialsBus routes serving the stationsNumber of deviated bus routesProximity to existing pedestrian routes

TRAFFICEase of traffic ingress/egressExisting traffic congestion in the station area

COMMUNITYCompatibility of loading areas with surrounding land useVacant land availability to meet parking requirements, bus facilities, etc.

NOTE: Station decisions along I-10 are important to coordinate based on proposed ADOT plans

Page 21: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

DEMOGRAPHICSFuture population within ½ mile of station Future employment within ½ mile of station Percentage of households that are transit dependent within ½ mile of station

STATION COSTSStation development/property acquisition costsEnvironmental impactsImpacts to historic structures/buildings

PUBLIC INPUTProximity to sensitive land usesSupport of station concept received at stakeholder meetings

Mainline Station Evaluation Criteria

Page 22: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

35th/39th Ave. Station Options35thAve

Page 23: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

39thAve35th/39th Ave. Station Options

Page 24: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

43rd/51st/59th Station Options43rd Ave

Page 25: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

43rd/51st/59th Station Options51st Ave

Page 26: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

43rd/51st/59th Station Options59th Ave

Page 27: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

63rd/67th Station Options

63rd Ave

Page 28: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

63rd/67th Station Options 67th Ave

Page 29: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

79th Ave. Station Options

Page 30: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

End of Line – I-10 Extension

Possible future high-capacity transit extension west along I-10

Page 31: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

End of Line – North Extension

Possible future high-capacity transit north to Desert Sky Mall

Page 32: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

End of Line – North Extension

Conceptual Station at

Desert Sky Mall

Page 33: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

I-10 Mainline Next Steps

Present preliminary findings at upcoming public meetings

Further refine station concept plansMultiple park-and-ride locations Determine appropriate park-and-ride capacity based on potential ridershipDetermine appropriate number of stations and select locations

Page 34: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

I-10 West Downtown

Page 35: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

Tier 2 Downtown Alternatives

Page 36: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

Tier 2 LRT Conceptual Alternatives

Page 37: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

Tier 2 Conceptual LRT Evaluation Results

Remove: Madison and Jackson- Not as close to major employment- Limited space, Veterans Memorial CemeteryRemove: 17th Avenue- Very limited space- Heavy truck traffic- Neighborhood and elementary school impactsModify: Van Buren (turn South on 7th Ave)- Unable to make direct connection to Starter Line- Substantial width constraints 7th Ave to Central

Page 38: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

Refined Tier 2 LRT Alternatives

Page 39: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

Tier 2 Conceptual BRT Alternatives

Page 40: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

Tier 2 Conceptual BRT Evaluation Results

Remove: I-10 BRT to Hance Park- Does not serve Capitol directly- Physical constraintsRemove: 17th Avenue- Very limited space and heavy truck trafficRemove: 15th Avenue, Van Buren, and Madison/Jackson- Does not serve Capitol as well as other alternativesRemove: Adams Street- Moves current bus routes off Washington/Jefferson

Page 41: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

Refined Tier 2 BRT Alternatives

Page 42: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

Downtown Key Issues – CWG

Location of Grand Avenue StationAvoid Elementary SchoolsMinimize Impacts to Historic NeighborhoodsHow to Best Serve Employment CentersTransit Technology (BRT vs. LRT)Economic Development PotentialCirculator Service Connection Integration with Capitol Mall Centennial Plan

Page 43: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

Downtown Key Issues - Technical

Direct Connection to CP/EV Line at 1st/CentralUtility Relocation Concerns on 15th AvenueRight of Way ConstraintsReduction in Traffic LanesADOT I-17 Widening ProjectSeparation from Rail Yard and Tracks West of 19th AvenueTransit Technology (BRT vs. LRT)

Page 44: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

I-10 West Downtown Next Steps

Document public meeting commentsIdentify preferred downtown alignments for LRT and BRTIdentify station locations along the preferred alignmentsExamine physical north/south connections to I-10Analyze LRT vs. BRT

Page 45: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if

Tier 2 Public MeetingsNovember 6th and 13th 2008

Complete Technical AnalysisStaff Recommendation for Locally Preferred Alternative (Early 2009)

Additional input from VPC and StakeholdersPublic Meetings (Spring 2009)

Present LPAFormal Adoption of LPA (Summer 2009)

I-10 West AA/EIS Next Steps

Page 46: Tier 2 Public Meeting - Valley Metro · Agenda. Future Extension Corridors. ... 10-minute peak, 15-minute off-peak. Comparison of LRT and BRT Lower, if demand is moderate Lower, if