+ All Categories
Home > Documents > Timbering Week 5

Timbering Week 5

Date post: 14-Apr-2018
Category:
Upload: fikadukitessa
View: 213 times
Download: 0 times
Share this document with a friend

of 22

Transcript
  • 7/30/2019 Timbering Week 5

    1/22

  • 7/30/2019 Timbering Week 5

    2/22

    By- Kokebe Yifru -Adama University Department of Civil Engineering & Arc- 20010/2011

  • 7/30/2019 Timbering Week 5

    3/22

    3. TIMBERING & EXCAVATIONS

    3.1 IntroductionExcavation & Earth work IncludesSite clearance

    Removal of trees, bushes and Vegetations

    Removal of termite hills

    Removal of structures

    Excavation

    Topsoil Excavation

    Excavation to reduce levelsExcavation for foundation

    Backfilling

    Disposal of excavated material

  • 7/30/2019 Timbering Week 5

    4/22

    3. TIMBERING & EXCAVATIONS

    3.1 Introduction cont The earth work of foundation of a building involves the

    following operations:-

    1.

    Preparing Foundation plan

    2.

    Setting out of foundation trenches

    3.

    Excavation of foundation

  • 7/30/2019 Timbering Week 5

    5/22

    3.2 Setting out

  • 7/30/2019 Timbering Week 5

    6/22

    3. TIMBERING & EXCAVATIONS

    3.2 Setting out foundation trenches

    Setting out or ground tracing is the process of laying down

    the excavation lines and center lines etc. on the ground,

    before excavation is started.` 'Setting out', as practiced on civil engineering and

    building sites, is the locating of the works to beconstructed, ensuring that they are dimensionally within

    permissible tolerances and correctly constructed.

  • 7/30/2019 Timbering Week 5

    7/22

    3. TIMBERING & EXCAVATIONS

    3.2 Setting out.` Setting out is essentially an aid to the labour force

    and must necessarily be provided in a form that is

    easy for them to use and understand; the information

    must be reliable and must be available as and when

    required.

  • 7/30/2019 Timbering Week 5

    8/22

    3. TIMBERING & EXCAVATIONS

    3.2 Setting out.

    ` Errors in setting out will in most cases result inremedial works which will be expensive. Whatever lines

    or levels are provided should be checked to be sure of

    their accuracy, and they should be provided to the

    foreman efficiently so that he can have the necessary

    confidence in them.

  • 7/30/2019 Timbering Week 5

    9/22

    3. TIMBERING & EXCAVATIONS

    3.2 Setting out foundation

    trenches cont..Steps in marking points-

    1.

    Establish reference points

    2.

    Fix wooden pegs and batten boards (poling boards) around

    the site to excavated. Each peg may be projected about 25-50mm above ground

    level and may be driven at a distance of

    about 2m from the edges

    of excavation;

  • 7/30/2019 Timbering Week 5

    10/22

    3. TIMBERING & EXCAVATIONS

    Steps in marking points-

    3.

    Mark the center line of the walls;

    4. Mark the plinth lines:-these are

    lines making the inside and the outside of walls;

    5. Check the right angles ( by stretching strings and formingtriangles with sides 3, 4 and 5 units, and for big projects

    using surveying equipments)

  • 7/30/2019 Timbering Week 5

    11/22

    3. TIMBERING & EXCAVATIONS cont.

    3.2 Setting out foundation trenches c0nt..

    Steps in marking points-

    6. If all dimensions are correct and all corners are at their

    angles, mark the cutting lines on the ground (using lime)

    NB-

    It is essential to have permanent reference marks, which should

    not get disturbed as the excavation proceeds.

  • 7/30/2019 Timbering Week 5

    12/22

    3.3 Excavation of foundation

    trenches

  • 7/30/2019 Timbering Week 5

    13/22

    3. TIMBERING & EXCAVATIONS cont.

    3.3 Excavation of foundation trenches

    Excavation of foundation trenches can be done either

    manually with the help of conventional implements (spade,

    pick axe, etc) or with the help of special mechanical

    equipments. (Read)

    Working safely in excavations

    The most important rule is to make sure that the sides ofthe excavation are always supported or safe from collapsing.

  • 7/30/2019 Timbering Week 5

    14/22

    3.4 Timbering of foundation

    trench

  • 7/30/2019 Timbering Week 5

    15/22

    3. TIMBERING & EXCAVATIONS cont.

    3.4 Timbering of foundation trench

    The process of supporting the sides of foundation trenches

    by means of wooden members is called timbering of

    foundation trench.

    When the depth of foundation trench is large, or when the

    sub soil is loose, the side of foundation trench may

    irregularly form a cave like hollow (concave). The problem

    can be solved by timbering.

  • 7/30/2019 Timbering Week 5

    16/22

    3. TIMBERING & EXCAVATIONS cont.

    3.5 Methods of Timbering of foundation trench

    1.Stay bracing

    Used in fairly firm soil.

    When the depth of

    excavation is

  • 7/30/2019 Timbering Week 5

    17/22

    3. TIMBERING & EXCAVATIONS cont.

    3.5 Methods of Timbering

    2. Box Sheeting

    Is adopted in loose soil.

    When the depth of

    excavation is

  • 7/30/2019 Timbering Week 5

    18/22

    3. TIMBERING & EXCAVATIONS cont.

    3.5 Methods of Timbering

    3. Vertical Sheeting

    Is adopted for soft ground. When the depth of

    excavation is

  • 7/30/2019 Timbering Week 5

    19/22

    3. TIMBERING & EXCAVATIONS cont.

    3.5 Methods of Timbering

    4. Runner system

    Used in extremely loose and soft ground, which needs

    immediate support as excavation progresses.

    Similar to vertical sheeting or box sheeting, except that in the

    place of vertical sheeting, runners, made of long thick wooden

    sheets or planks are provided.

    The runners are driven about 30cm in advance of the progress

    of the work, by hammering.

  • 7/30/2019 Timbering Week 5

    20/22

    3. TIMBERING & EXCAVATIONS cont.

    3.5 Methods of Timbering

    5. Sheet piling

    This method is adopted when-1.

    The soil is soft or loose

    2.

    The depth of excavation is large

    3.

    The width of the trench is large

    4.

    There is sub-soil water

    Sheet piles are designed to resist lateral earth pressure. Are driven in the ground by mechanical means (pile driving

    equipment).

    They can be used for excavating to a very large depth.By - Kokebe Yifru -Adama University Department of Civil Engineering & Arc- 2009/2010

  • 7/30/2019 Timbering Week 5

    21/22

    3. TIMBERING & EXCAVATIONS

    Assignment

    1.

    Discuss the methods of improving safe bearing

    capacity of soils.

    2.

    Explain the problems of foundations on black cotton

    soil briefly.(max

    10 pages)

    Summary

    By Group 4

  • 7/30/2019 Timbering Week 5

    22/22

    Thank You!!


Recommended