Work from DaysIf A can do a piece of work in n days,then A's 1 day's work = 1 .

n

• Days from Work:• If A's 1 day's work = 1 , then A can finish

the n

work in n days.

Page 3: Time and work

Ratio• If A is thrice as good a workman as B,

then:Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

Page 4: Time and work

Question• Worker A takes 8 hours to do a job.

Worker B takes 10 hours to do the same job. How long should it take both A and B, working together but independently, to do the same job?

• A. 4 2/9 days • B. 4 4/9 days• C. 4 5/9 days• D. 4 7/9 days

Page 5: Time and work

• Answer: Option B• Explanation:• A’s 1 hour’s work = 1/8• B’s 1 hour’s work = 1/10• (A+B)’s 1 hour’s work = (1/8+1/10) = 9/40• Both A and B will finish the work in 40/9= 4 4/9

days

Page 6: Time and work

Question

• Rohan can do a piece of work in 36 days but with the help of Mohan he can complete the work in 24 days. Find the no of days in which Mohan alone can complete the work?

• A 80 days• B 84 days• C 72 days• D 74 days

Page 7: Time and work

C 72 days

• Total work done by Rohan and Mohan=L.C.M of 36 & 24= 72 days

• Work rate of Rohan= 72/36=2• Combine work rate(R+M)=72/24=3• Work rate of Mohan=3-2=1• No.of days required by Mohan=72/1=72 days

Page 8: Time and work

Question

• A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work?

• A. 6 days • B. 4 days• C. 8 days• D. 9 days

Page 9: Time and work

• Answer: Option A• Explanation:• (A+B)’s 1 day’s work = ¼• A’s 1 day’s work = 1/12• B’s 1 day’s work = ¼ - 1/12 = 1/6 • B alone can complete the work in 6 days.

Page 10: Time and work

Question

• A and B can do a work in 25 days and 20 days. Both together work for 5 days and then A leaves off. How many days B take to finish the remaining work?

• A 16 days• B 11 days• C 12 days• D 14 days

Page 11: Time and work

B 11 days• A can finish work in 25 days & B can finish

the work in 20 days• Total work done=100(L.C.M of 25&20)• A’s Contribution=100/25=4• B’s Contribution =100/20=5• First we need to calculate 5 days

work=9x5=45• Remaining work=100-45=55• B require No.of days=55/5=11 days

Page 12: Time and work

Question

• A is twice as good a workman as B and together they finish a piece of work in 18 days. In how many days will A alone finish the work?

• A. 27 days • B. 24 days• C. 28 days• D. 29 days

Page 13: Time and work

• Answer: Option A• Explanation:• (A’s 1 day’s work) : (B’s 1 day’s work) = 2 : 1• (A+B)’s 1 day’s work = 1/18• Divide 1/18 in the ratio 2 : 1• A’s 1 days work = 1/18 x 2/3 = 1/27• So, A alone can finish the work in 27 days.

Page 14: Time and work

Question

• A can finish a work in 24 days. B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in

• A 9 days• B 10 days• C 11 days• D 12 days

Page 15: Time and work

B 10 days

• Total work done= L.C.M of 24,9,8=72 • Work rate of A =72/24=8• Work rate of B= 72/9=8• Work rate of C=72/12=6• In 3 days B & C can complete

work=14x3=42 part• Remaining work= 72-42=30(A’s Work)• No of days required by A= 30/3= 10 days

Page 16: Time and work

Question• A and B working separately can do a piece

of work in 9 and 12 days respectively. If they work for a day alternately, A beginning, in how many days, the work will be completed?

• A. 10 ¼ days • B. 10 ½ days• C. 8 ¼ days• D. 8 ½ days

Page 17: Time and work

• Answer: Option A• Explanation:• (A+B)’s 2 day’s work = 1/9+1/12 = 7/36• Work done in 5 pairs of days = 5x7/36=35/36• Remaining work = 1 – 35/36 = 1/36• On 11th day, it is A’s turn.• 1/9 work done by him in 1 day.• 1/36 work done by him in (9x1/36) = ¼ days.• Total time taken = 10 + ¼ = 10 ¼ days.

Page 18: Time and work

Question

• A and B can do a piece of work in 20 days and 12 days resp. A alone started the work and then after 4 days B joined him till the completion of work. How long did the work last?

• A 10 days• B 12 days• C 13 days• D 11 days

Page 19: Time and work

A 10 days• Total Work Done by A & B =L.C.M OF

20&12 =60• Work done by A=60/20=3 part• Work done by B =60/12=5 part• In 4 days work done= 4x3=12 • Remaining work=60-12=48• Combine work rate=A+B=3+5=8• No.of days both A&B work=48/8=6• Total no.of days work last=6+4=10 days

Page 20: Time and work

Question• 45 men can complete a work in 16 days.

Six days after they started working, 30 more men joined them. How many days will they now take to complete the remaining work?

• A. 6 days • B. 4 days• C. 8 days• D. 9 days

Page 21: Time and work

• Answer: Option A• Explanation:• 45 men can complete the work in 16 days.• (45x16) men can complete the work in 1 day.• 1 man’s 1 day’s work = 1/720• 45 men’s 6 day’s work = 45/720 x 6 = 3/8• Remaining work = 1 – 3/8 = 5/8• 75 men’s 1 day’s work = 75/720 = 5/48.• Now, 5/48 work is done by them in 1 day.• So, 5/8 work is done by them in 48/5 x 5/8 = 6 days

Page 22: Time and work

QUESTION

• IF 5 MEN OR 19 WOMEN CAN DO A PIECE OF WORK IN 19 DAYS. IN HOW MANY DAYS CAN 3 MEN AND 6 WOMEN WILL DO THE SAME WORK?

• A 10• B 15• C 18• D 20

Page 23: Time and work

B-15 DAYS

• 5M/9W Can do work in 19 days.3M & 6W =d2(find)

• 5MX 19=(3M+6W)d2• 1W=5/9M, 6W=5/9X6=10/3M• 5MX19=(3M+6W)d2• 5MX19=(3M+10/3M)d2• 5X19=(3+10/3)d2• d2= 15 days

Page 24: Time and work

Question• Sachin can do a piece of work in 10 days

while Rahul can do it in 15 days. They work together for 5 days and the rest work is done by Virat in 2 days. If they get Rs 4500 for the whole work what is the share of Virat?

• A 700 Rs• B 780 Rs• C 800 Rs• D 750 Rs

Page 25: Time and work

D 750 Rs• Sachin Work= 10 , Rahul Work=15• Total work done by both= 30• Work rate of Sachin= 30/10=3• Work rate of Rahul=30/15=2• One day Sachin & Rahul can complete

3+2=5 piece of work• In 5 days work complete=5(sachin & rahul

work)x 5(no.of days)=25• S & R: V=25:5=5:1• Virat Share=4500/6x 1=750 Rs