Timetable and Room Allocation System Project
Stage 1 – Preparation of Reports
Stage Plan
Version 1.0
Prepared By
Robert Treadgold
Manager, Student Information
TARA System Project Stage Plan 1
Page i
Table of Contents 1 INTRODUCTION ..................................................................................................1
1.1 Purpose of the Document...............................................................................1 2 STAGE DEFINITION ............................................................................................1
2.1 Objectives ......................................................................................................1 2.2 Scope .............................................................................................................1 2.3 Exclusions ......................................................................................................2 2.4 Constraints .....................................................................................................2 2.5 Assumptions...................................................................................................2
3 APPROACH .........................................................................................................2 3.1 Methodology...................................................................................................2 3.2 Project Products .............................................................................................3
4 STAGE PLAN DETAILS ......................................................................................4 4.1 Gantt Chart.....................................................................................................4 4.2 Resource Matrix .............................................................................................4 4.3 Milestones and Dates.....................................................................................4
APPENDICES APPENDIX A –PRODUCT DESCRIPTIONS
APPENDIX B – GANTT CHART
TARA System Project Stage Plan 1
Page ii
DOCUMENT APPROVAL
DOCUMENT CONTROL
Document Title Timetable and Room Allocation System Stage 1 Plan
Version No 1.0
File Name TARA Stage 1 Plan
Date: 23 March 2005
Distribution Project Management Group, Timetable and Room Allocation Reference Group, Project Working Parties.
Note: This is the only controlled copy of this document. All others are uncontrolled
DOCUMENT MODIFICATION HISTORY
Version Number
Primary Author(s)
Description of Version Date Completed
0.1 Robert Treadgold Draft 18 February 05
0.2 Robert Treadgold Updated Draft 25 February 05
0.3 Robert Treadgold Updated Draft 02 March 05
1.0 Robert Treadgold Final 23 March 2005
RELATED MATERIAL
Document Name Description
Project Execution Plan (PEP)
Project Execution Plan for the Timetable and Room Allocation System Project
Project Sponsor – John Wood Project Manager – Robert Treadgold
Signed
Date
Signed
Date
TARA System Project Stage Plan 1
Page 1
1 INTRODUCTION
1.1 Purpose of the Document
This document is the Stage 1 Plan for the Timetable and Room Allocation System Project. It provides relevant information for the day-to-day management of the stage and is used as the basis for project management control throughout this stage. Specifically, it
• Identifies details of all work activities, products and resource requirements to deliver the stage objectives
• Identifies all the products which the stage must produce
• Provides a baseline against which the stage progress will be measured
• Specifies the quality controls for the stage products and identifies the resources needed for them.
2 STAGE DEFINITION
2.1 Objectives
Determine what Edith Cowan University requires from a Teaching and Room Allocation (TARA) System. A requirements specification document to be prepared and focus on a system that
• reduces data duplication and consolidates systems with the potential for a single system for timetabling and room allocation of both teaching and non teaching spaces
• streamlines room bookings and optimizes the use of space
• provides ability for staff/students to request room bookings via the web
• provides a seamless means for collecting teaching activity requirements from schools preferably via the web
• integrates with other ECU systems, particularly Callista Student Management System and Archibus
• has technical support either via a supplier or internal support from KITSC
Prepare a report outlining what Timetable and Room Allocation Systems are currently available for purchase and which systems are Australian universities using.
2.2 Scope
The specifications document to describe the requirements from a teaching timetable, room booking, event management and space management perspective. To also include interface and other technical requirements.
TARA System Project Stage Plan 1
Page 2
2.3 Exclusions
Changes to business processes identified in specifications document.
2.4 Constraints
The following constraints have been identified in developing this Stage Plan:
• Timescale – deadlines for the various reports
• Budget
• Resources with appropriate skills
• Dependency on interfaces with Callista and Archibus
2.5 Assumptions
The following assumptions have been made in developing this Stage Plan:
• Budget and Resources (with appropriate skills) will be available
• Timescale will be adequate
• Required Interfaces will be identified by stakeholders and approved by Project Management Group
3 APPROACH
3.1 Methodology
Stage One has the following outcomes:
• Completion of a Timetable and Room Allocation System specifications document.
• Completion of an analysis outlining what Timetable and Room Allocation Systems are currently available and which systems are Australian universities using.
• An analysis of the current Timetable and Room Allocation System (Admin) against the specifications document is completed.
• The Project Management Group decides if the University continues with Admin initiating improvements or seek to buy/build a new system.
• The above outcomes would require the following steps:
o Establishment of a Working Party chaired by the Timetable Officer (Caryn Bate) to prepare the teaching timetable component of the Specifications document.
o Establishment of a Working Party chaired by a Campus Services representative (Karen Knowles) to prepare the ad hoc room bookings component of the Specifications document
TARA System Project Stage Plan 1
Page 3
taking into consideration the requirements of Security and how the system could be used for events management.
o Establishment of a Working Party chaired by a Facilities Services representative (Sonja Woodwell) to prepare the space management and reporting component of the Specifications document.
o The Timetable Officer to undertake an analysis outlining what Timetable and Room Allocation Systems are currently available and which systems are Australian universities using. Recommend using the CAUDIT survey on Timetabling/Scheduling Software undertaken by Murdoch University in 2004 as a starting point.
o Information Delivery Systems (IDS) support compiles the Specifications document from the components prepared by each Working Party. Project Manager to prepare Specification document in a format suitable for the analysis/tender process.
o The specification document and two reports on current systems in use and on the market are provided to the Timetable and Room Allocation Reference Group (TARARG) for consideration and endorsement. The membership of TARARG is
A representative from each Faculty A representative from Student Services A representative from Systems Support (Alan Dent) The Chair of each Working Party, Project Manager and IDS support would attend in an advisory capacity
o Timetable Officer and IDS representative (Rukmini Edirisinghe or Stephen Edwards) to conduct an analysis of the current Timetable and Room Allocation System (Admin) against the Specifications document. The analysis would also provide an indication of the amount of enhancement required for Admin to meet the new ECU TARA system requirements.
o TARARG would consider the analysis and make a recommendation to the PMG
o PMG decide if we go with an improved version of Admin or buy/build a new system.
3.2 Project Products
This is a matrix showing responsibility for production of the project’s products. It cross-references back to the product descriptions (see Appendix A).
ID Product Name Product Type
Primary Responsibility
Due Date
1 Timetable and Room Allocation System specifications document
Report Project Manager 20 April 2005
2 Report on Timetable and Room Allocation System packages currently in use by other universities
Report Timetable Officer 8 April 2005
3 Report on Timetable and Room Allocation System packages currently on the market
Report Timetable Officer 15 April 2005
5 Request for Tender Document Analysis document
Project Manager 11 May 2005
6 Admin comparison against TARA system requirements
Report Timetable Officer 1 June 2005
The full list of the products to be produced by this stage of the project, together with their quality assurance status, will be maintained in the Quality Log.
TARA System Project Stage Plan 1
Page 4
4 STAGE PLAN DETAILS
4.1 Gantt Chart
Appendix B
4.2 Resource Matrix
Timetable and Room Allocation Reference Group (TARARG)
• Review of Specification document and reports on available TARA systems and TARA systems currently being used by other universities
IDS Support (Stephen Edwards)
• Compile component of each WP into final Specifications document Project Manager (Robert Treadgold)
• Determine tender process
• Format Specifications document into analysis format Working Party Chairs (Caryn Bate, Steve Butcher, Stephen Edwards, Karen Knowles)
• Preparation of TARA System Specifications document Timetable Officer (Caryn Bate)
• Prepare report on what TARA systems are available
• Prepare report on what TARA systems used by other universities
4.3 Milestones and Dates
Key Milestone Target Date
Timetable and Room Allocation System specifications document 20 April 2005
Report on Timetable and Room Allocation System packages currently in use by other universities
8 April 2005
Report on Timetable and Room Allocation System packages currently on the market
15 April 2005
Request for Tender Document 11 May 2005
Admin comparison against TARA system requirements 1 June 2005
TARA System Project Stage Plan 1
TARA Stage 1 Plan v1.0
Appendix A - Product Descriptions
Product number 1 PRODUCT NAME
Timetable and Room Allocation System Specifications
PURPOSE OF THE PRODUCT
The specification document to describe the requirements for a Timetable and Room Allocation system from a teaching timetable, room booking, event management and space management perspective.
COMPONENTS
• executive summary • current configuration • key issues • functional requirements • information requirements • reporting requirements • interface requirements • the warnings and help facilities required • system administration requirements with regards to archiving, auditing, disaster recovery, storage,
service level, performance and security • system requirements with regard to hardware, software, network, web and servers • implementation considerations.
DERIVATION
Working parties will be established that will consult with relevant stakeholders so as to determine the functional requirements of a timetable and room allocation system. The TARA system functional specification document prepared by Robert Treadgold in April 2004 will be used as reference material in preparing the specifications document.
FORMAT AND PRESENTATION
Must conform to requirements template agreed upon by the Project Management Group.
ALLOCATED TO
The Chair of each relevant Working Party is responsible for their component of the specifications document. The Project Manager is responsible for compiling the components into the final document.
QUALITY CRITERIA
TYPE OF QUALITY CHECK REQUIRED
Each working party is to ensure adequate consultation takes place that ensures all key clients of a TARA system have input into the construction of the specifications document.
The Timetable and Room Allocation Reference Group to assess the specifications document.
PEOPLE OR SKILLS REQUIRED FOR QA
TARA System Project Stage Plan 1
TARA Stage 1 Plan v1.0
Reviewing the Product
The teaching timetable component of the specifications document should be reviewed by the Project Manager, Heads of School, School Timetable Coordinators, Timetable Office staff and the TARARG.
The room booking and events management component of the specifications document should be reviewed by the Project Manager, Campus Services, Marketing and Timetable Office staff and the TARARG.
The space management component of the specifications document should be reviewed by the Project Manager, Planning and Development staff, Faculty Managers and the TARARG.
The completed specifications document would be reviewed by the TARARG.
Approving the Product
The Project Management Group is responsible for approving the document for the analysis of Admin and in stage two.
TARA System Project Stage Plan 1
TARA Stage 1 Plan v1.0
Product Number 2 PRODUCT NAME
Report on Timetable and Room Allocation System packages currently in use by other universities
PURPOSE OF THE PRODUCT
This report will let the PMG know which universities to contact should it require an external assessment of a particular TARA system package. It also provides knowledge of which TARA systems are being used in conjunction with Callista and Archibus and how many universities may be using a particular product. This would allow the PMG to gauge the level of satisfaction other universities have for a particular product.
COMPONENTS
• name of university and contact person • what timetable and room allocation system they are using and for how long they have been using
it • whether they are using a different system for timetabling to what they use for room bookings and
the name of the systems being used • what student information system are they using • what space management system are they using • does their timetable system also allow for students to enrol in units and unit activities on line • of the above systems, which have a direct or indirect interface • level of satisfaction with the systems they are using
DERIVATION
The CAUDIT survey on Timetabling/Scheduling Software undertaken by Murdoch University in 2004 and consultation with universities in Australia.
FORMAT AND PRESENTATION
Must conform to standard reports template agreed upon by the Project Management Group.
ALLOCATED TO
Timetable Officer
QUALITY CRITERIA
TYPE OF QUALITY CHECK REQUIRED
The Timetable and Room Allocation Reference Group to assess the report ensuring at least 50% of Australian universities have replied.
PEOPLE OR SKILLS REQUIRED FOR QA
Reviewing the Product
The report would be reviewed by the Project Manager and assessed by the TARARG.
Approving the Product
The Project Management Group is responsible for approving the document for use in stage two.
TARA System Project Stage Plan 1
TARA Stage 1 Plan v1.0
Product Number 3 PRODUCT NAME
Report on Timetable and Room Allocation System packages currently on the market
PURPOSE OF THE PRODUCT
This report will assist the TARARG and PMG in deciding which suppliers to approach for the tender process or whether an open tender may be required. The report will confirm what systems are on the market, the costs and support service available.
COMPONENTS
• name of system and how long it has been on the market • name and location of supplier • how many other universities use it and if possible the name of the Australian universities using it. • summary of what the system can do • what is the purchase and maintenance costs • what after sales service is available including implementation and training • is their evidence of it being used with either Callista or Archibus
DERIVATION
Report on Timetable and Room Allocation System packages currently in use by other universities will give an indication of products on the market. A search on the internet should advise of other systems available.
FORMAT AND PRESENTATION
Must conform to standard reports template agreed upon by the Project Management Group.
ALLOCATED TO
Timetable Officer
QUALITY CRITERIA
TYPE OF QUALITY CHECK REQUIRED
The Timetable and Room Allocation Reference Group to assess the report ensuring systems available for purchase mentioned in the report on systems in other universities has been included.
PEOPLE OR SKILLS REQUIRED FOR QA
Reviewing the Product
The report would be reviewed by the Project Manager and assessed by the TARARG.
Approving the Product
The Project Management Group is responsible for approving the document for use in stage two.
TARA System Project Stage Plan 1
TARA Stage 1 Plan v1.0
Product Number 4 PRODUCT NAME
The Request for Tender document.
PURPOSE OF THE PRODUCT
This report will allow suppliers to make an assessment of whether their product matches the University’s requirements of a TARA system. The report will also be used in assessing Admin.
COMPONENTS
The document would comprise the information from the specifications document. It will include a prioritising of the functionality and technical requirements.
DERIVATION
The TARA system specifications document.
FORMAT AND PRESENTATION
This document will be in a table format listing the requirements as outlined in the Specifications document. The supplier would also receive the specifications document for referencing. The table format would be as below.
System Requirement
Yes our system can fulfil this requirement
No our system can not meet this requirement
Future enhancement planned to allow for this requirement (give date when available)
Comment
ALLOCATED TO
Project Manager
QUALITY CRITERIA
TYPE OF QUALITY CHECK REQUIRED
The Timetable and Room Allocation Reference Group to assess the report ensuring all functional and technical requirements of a TARA system have been included.
PEOPLE OR SKILLS REQUIRED FOR QA
Reviewing the Product
The report would be reviewed by the TARARG.
Approving the Product
The Project Management Group is responsible for approving the document for use in stage two.
TARA System Project Stage Plan 1
TARA Stage 1 Plan v1.0
Product number 6 PRODUCT NAME
Admin comparison against TARA system requirements
PURPOSE OF THE PRODUCT
To determine if Admin meets the current and future TARA system requirements as determined in the specifications document. Also to determine the level of enhancement required to have all the desired features of ECU’s preferred TARA system.
COMPONENTS
The document would comprise the information from the specifications document.
DERIVATION
The TARA system specifications document.
FORMAT AND PRESENTATION
Must conform to standard template agreed upon by the Project Management Group.
This document will be in a table format listing the broad requirements as outlined in the specification document. The table format would be as below.
System Requirement
Yes Admin can fulfil this requirement
No Admin can not meet this requirement
Level of enhancement necessary to allow for this requirement
Comment
ALLOCATED TO
Timetable Officer and IDS Representative
QUALITY CRITERIA
TYPE OF QUALITY CHECK REQUIRED
The Timetable and Room Allocation Reference Group to assess the report ensuring all functional and technical requirements of a TARA system have been assessed.
PEOPLE OR SKILLS REQUIRED FOR QA
Reviewing the Product
The report would be reviewed by the TARARG.
Approving the Product
The Project Management Group is responsible for deciding whether the University continues with Admin.