Date post: | 04-Jan-2016 |
Category: |
Documents |
Upload: | brianna-page |
View: | 214 times |
Download: | 0 times |
Title – xxxx 1
LARP & US-HiLumi Contribution to the Inner Triplet Quadrupoles
G. Ambrosio
Cost and Schedule ReviewCERN, March 9th-11th 2015
Title – xxxx 2
LARP & US-HiLumi
• LARP (LHC Accelerator Research Program) — A collaboration among BNL, FNAL, LBNL & SLAC— Goals:
• make more luminosity, earlier• collaborate in interaction region upgrades, to make even
more luminosity, later• use, develop, and preserve unique U.S. resources and
capabilities.
— May not deliver deliverables
• US-HiLumi will be a Project— LARP has been charged to prepare the path for this
future project
Title – xxxx 3
SQSM TQS
LR
LQS
HQTQC
LARP Magnets (2003-now)
Title – xxxx 4
90 mm Aperture QuadsShort & Long
Short models (1 m):
• Understanding stress vs degradation safe preload
• 1000 power cycles with no degradation
Long models (3.4 m):
• Demonstration of scale-up• Demonstration of excellent
training memory
Title – xxxx 5
• Goal: demonstrate all performance requirements for Nb3Sn IR Quads in the range of interest for HL-LHC (magnetic, mechanical, quench protection etc.)
• Main design parameters and features in the latest models tested (HQ02a/b):
Conductor and cable
Strand diam. (mm) 0.778
Cu/Sc 1.2
No. strands 35
Cable width (mm) 14.8
Cable thickness (mm) 1.375
Keystone angle (deg.) 0.75
HQ02 Short Sample Performance
Param. 4.5K 1.9K
Iss [kA] 16.4 18.2
Bpk [T] 12.9 14.2
Gss [T/m] 186 205
Al shell
Coil
Bladder locations Alignment key
Iron yoke
Al collar
120 mm Aperture HQ
Title – xxxx 6
Accelerator Quality
• Order of magnitude reduction of dynamic effects (ramp rate, field quality) with cable core
Quench performance
• HQ02b: fast training to 95% level with 200 MPa pre-load
• HQ03: 1st quench at 81.5 SSL
Quench protection
• 380K quench temperature without degradation
• Successful first test of the CLIQ system in Nb3Sn
250K
320K
380K
HQ02/03 Test Results
Title – xxxx 7
LARP Development of QXF Short Models & Prototypes
• The LARP plan has been presented by P. Ferracin
• LARP & CERN short model plans are tightly correlated, and support and strengthen each other
• By working together LARP & CERN achieve optimization of resources, maximization of return and back-up
Title – xxxx 8
US-HiLumi Project Plan
• US-HiLumi Magnets Preliminary:— Scope— Top-Level Schedule— Fabrication Plan— Early US Project Milestones— Summary
Based on presentation by R. Carcagnoat HiLumi-LARP Collaboration MeetingNovember 19, 2014Note: assuming 8.0 m magnetic length
Title – xxxx 9
Preliminary US-HiLumi Magnet Scope
MQXFA
MQXFA
LMQXFA (Q1)LMQXFB (Q3)
• Five Q1 Cold Masses (LMQXFA) and Five Q3 Cold Masses (LMQXFB)
— Each cold mass includes two ~ 4.8m Nb3Sn magnets (MQXFA) installed in a SS helium vessel with end domes, ready for insertion into a cryostat by CERN
— Option: deliver magnets (MQXFA) after vertical test
Title – xxxx 10
US-HiLumi Magnets Timeline Tentative plan:
— Assumes Q1 and Q3 tunnel installation in CY-2024— Provides 3.5 years for CERN Q1 and Q3 scope (cryostating, test, etc)— Production Coil winding must start in January 2018 (US Critical Decision 3 DOE approval, CD-3)— Two years of preparations needed for strand and series production tooling procurements, start cable
fabrication, etc.— Production throughput based on June 2013 MQXF fabrication plan
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4CY-2025CY-2021 CY-2022 CY-2023 CY-2024
US-HiLumi Magnet Preliminary Timeline - November 2014CY-2015 CY-2016 CY-2017 CY-2018 CY-2019 CY-2020
#8
CERN Long Shutdown 3 (LS3)
Ends
MQXFA 1/2
LMQXF #1 Delivered #8 Delivered #10 Delivered (#9 and #10 Spares)
19/20
Production: Two Production LinesMultiple Coil Fabrication Tooling
CD-3
Pre-Production: Strand, Cable, Tooling, Parts, etc
Coil Fab Starts
CERN Scope: Cryostating, Tunnel Installation, Commissioning
Q1, Q3 Tunnel installation Starts
15/16
LQXF #1
Title – xxxx 11
US-HiLumi Preliminary Top Level Schedule
• Assumes Q1 and Q3 tunnel installation in CY2024
• First LMQXFA/B cold mass delivered to CERN summer 2020
• Last LMQXFA/B cold mass for tunnel installation delivered to CERN summer 2022
• Last LMQXFA/B cold mass spare delivered to CERN summer 2023
Title – xxxx 12
Preliminary Fabrication Plan
Plan is based on the production plan presented by M. Anerella during the June 2013 DOE review of LARP plus additional information
• Nb3Sn:
— First strand delivery one year after placing purchase order. Last
delivery 2 years later. A total of 9,400 Kg will be needed for 90 coils
• Cable and Insulation (LBNL):
— Starts three months after first strand delivery
— Throughput starts at 2 UL/month, ramping to a peak rate of 3
UL/month
— A total of 90 ULs are needed for 90 coils
— Insulation by vendor
— Total duration ~ 3 years
CERN is back-up for cabling, and LARP is for CERN
Title – xxxx 13
Preliminary Fabrication Plan (Cont.)
• Coil Fabrication:— Two production lines (FNAL and BNL)— Peak rate: 1 coil every 15 working days
• First two coils in each facility assumed to take twice as long• First 4 coils: 8 months after coil production starts
— Total duration for 90 coils ~ 3.5 years— Additional tooling needed at each production line to
sustain throughput:• One additional winding mandrel assembly• Two additional reaction fixtures• One additional impregnation fixture Looking at optimizing
parts procurement between LARP & CERN
Title – xxxx 14
Preliminary Fabrication Plan (Cont.)
• Magnet Assembly (LBNL):— Starts ~ 8 months after coil fabrication starts
• As soon as a set of four coils are delivered
— Includes Yoke/Shell structure assembly, coil pack insert assembly, and magnet assembly
— Two production lines. In each line, peak rate:• 1 coil pack insert every 60 working days• 1 yoke/shell assembly every 75 working days
(concurrent)• 1 magnet assembly every 34 working days
— Peak overall rate: 1 magnet every ~ 2.2 months• First magnet assumed to take twice as long
— Total duration for 20 magnets is ~ 4 years
Title – xxxx 15
Preliminary Fabrication Plan (Cont.)
• Magnet Test (BNL):— Test and train each magnet in BNL vertical test stand prior to
cold mass assembly• Needed quantity under consideration• It takes ~ 38 working days for a production vertical test
• Cold Mass Assembly (FNAL):— Connection of two magnets, installation of stainless steel skin
and end domes, heat exchanger, bore tube, etc.— Peak rate: 1 cold mass every ~2 months
• First assembly assumed to take 3 months
• Cold Mass Test (FNAL):— Insert cold mass in re-usable cryostat and test cold mass in
Fermilab’s Horizontal test stand— Peak rate 1 cold mass test every ~3.5 months
• First test assumed to take 1.5 times longer, second test 1.25 times longer• Assumes no prior magnet training• Assumes 30 training quenches per magnet
Title – xxxx 16
US-HiLumi Early Milestones
Frozen Baseline:— Definitive
scope— Detailed
resource loaded schedule
— Time-phased budget
— EVMS-ready
Baseline must be frozen before March 2016
• Earned Value Management System (EVMS) monthly reporting is required six months prior to the independent Director’s CD-2 review, which is required before a DOE CD-2 review
• EVMS requires a frozen baseline– Changes after baseline freezing require going through a change control and approval process– Monthly Cost/Schedule variances must be explained and corrective actions put in place
Title – xxxx 17
Summary
• Plan is based on Q1 and Q3 tunnel installation in 2024• Q1 and Q3 cold masses delivered to CERN starting in summer 2020
— Last cold mass for tunnel installation delivered summer 2022— Last spare delivered summer 2023
• Plan requires start coil production (DOE CD-3 approval) in January 2018
• DOE CD-2 approval needed by ~April 2017— EVMS monthly reporting must start by March 2016 to support
Director’s CD-2 review prior to DOE CD-2 review• US-HiLumi project baseline must be frozen before March 2016
— Definitive scope, detailed resource-loaded schedule, time-phased budget, EVMS-ready
• This is a preliminary plan, more details and analysis needed (e.g., incorporate rework/re-test activities)
Title – xxxx 18
Risks & Opportunities
Nb3Sn superconducting strand 2 strand producers
Cable fabrication 2 cabling machines (LARP & CERN)
Coil fabrication Complete lines at 2 US labs
Coil parts Share procurement with CERN
Magnet assembly Baseline is one lab, but could set up 2nd line at another lab
Structure parts Stamped laminations
Magnet performance Vertical test of each magnet allows for fast coil substitution