TO: Kalamazoo Area Transportation Study Technical Committee FROM: Jonathan Start, Executive Director DATE: March 5, 2019 SUBJECT: TECHNICAL COMMITTEE MEETING THURSDAY, March 14, 2019 - 9:00 A.M. METRO 530 N. ROSE STREET, KALAMAZOO The Kalamazoo Area Transportation Study Technical Committee will be meeting on Thursday, March 14, 2019 at 9:00 a.m. at Metro. The following materials are included in your meeting packet: 1. Agenda for the March 14, 2019 Meeting 2. Draft Minutes of the February 7, 2019 Meeting 3. FY 2017-2020 Transportation Improvement Program Amendments 4. Draft FY 2020-2023 Transportation Improvement Program Project List 5. Adoption of Air Quality Conformity Analysis for Kalamazoo and Battle Creek Areas 6. Letter of Support for FY 2022 Bridge Program, Village of Augusta 7. Resolution of Support for Stadium Drive TAP Grant in Oshtemo DDA Area Please remember that time sheets are due by the 15 th of each month. Meeting Materials Page 1 of 83
Transcript
Page 1: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

TO: Kalamazoo Area Transportation Study Technical Committee

FROM: Jonathan Start, Executive Director

DATE: March 5, 2019

SUBJECT: TECHNICAL COMMITTEE MEETING THURSDAY, March 14, 2019 - 9:00 A.M.

METRO 530 N. ROSE STREET, KALAMAZOO The Kalamazoo Area Transportation Study Technical Committee will be meeting on Thursday, March 14, 2019 at 9:00 a.m. at Metro. The following materials are included in your meeting packet:

1. Agenda for the March 14, 2019 Meeting 2. Draft Minutes of the February 7, 2019 Meeting 3. FY 2017-2020 Transportation Improvement Program Amendments 4. Draft FY 2020-2023 Transportation Improvement Program Project List 5. Adoption of Air Quality Conformity Analysis for Kalamazoo and Battle Creek Areas 6. Letter of Support for FY 2022 Bridge Program, Village of Augusta 7. Resolution of Support for Stadium Drive TAP Grant in Oshtemo DDA Area

Please remember that time sheets are due by the 15th of each month.

Meeting Materials Page 1 of 83

Page 2: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

KALAMAZOO AREA TRANSPORTATION STUDY

TECHNICAL COMMITTEE MEETING MARCH 14, 2019 - 9:00 A.M.

METRO

AGENDA

Please limit public comments to 4 minutes.

1. CALL TO ORDER

2. ROLL CALL (Sign-in Sheet Circulated)

3. CHANGES OR ADDITIONS TO THE AGENDA

4. APPROVAL OF THE AGENDA (ACTION)

5. MINUTES FROM THE FEBRUARY 7, 2019 MEETING (ENCLOSURE) (ACTION)

6. POLICY COMMITTEE REPORT

7. CITIZENS’ COMMENTS (Non-agenda Items)

8. FY 2017-2020 TRANSPORTATION IMPROVEMENT PROGRAM AMENDMENTS (ENCLOSURE) (ACTION)

9. DRAFT FY 2020-2023 TRANSPORTATION IMPROVEMENT PROGRAM PROJECT LIST (ENCLOSURE) (ACTION)

10. ADOPTION OF AIR QUALITY CONFORMITY ANALYSIS FOR KALAMAZOO AND BATTLE CREEK AREAS (ENCLOSURE) (ACTION)

11. LETTER OF SUPPORT FOR 2022 BRIDGE PROGRAM, VILLAGE OF AUGUSTA (ENCLOSURE) (ACTION)

12. RESOLUTION OF SUPPORT FOR STADIUM DRIVE TAP GRANT IN OSHTEMO DDA AREA (ENCLOSURE) (ACTION)

13. PUBLIC TRANSPORTATION UPDATES

14. STATUS REPORTS

a. ROADS - Questions on written status reports. Verbal reports will be limited to 4 minutes per agency.

b. LAND USE/PLANNING AND ZONING - Questions on written status reports. Verbal reports will be limited to 4 minutes per agency.

15. NEW BUSINESS

16. ADJOURNMENT

The next meeting of the Kalamazoo Area Transportation Study Technical Committee will be held on Thursday, April 11, 2019 at 9:00 a.m. Metro, 530 N. Rose Street.

Meeting Materials Page 2 of 83

Page 3: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

KALAMAZOO AREA TRANSPORTATION STUDY

TECHNICAL COMMITTEE MEETING MINUTES FEBRUARY 7, 2019

CALL TO ORDER

The February 7, 2019 Technical Committee Meeting was called to order at 9:00 am by Chair Forth.

ROLL CALL

Meeting attendance was recorded on the sign-in sheet. MEMBERS PRESENT Eric Arnsman City of Kalamazoo Jamie Baker Oshtemo Township Mickey Bittner Village of Paw Paw Steve Deisler Texas Township Orrin Dorr City of Kalamazoo David Fairchild MDOT, Statewide Planning Chris Forth, Chair City of Portage Kendra Gwin City of Portage Jeff Heppler Village of Augusta Joel Hoort Van Buren County Road Commission Lotta Jarnefelt Kalamazoo County Debbie Jung Road Commission of Kalamazoo County Jenny McCowen Kalamazoo County Transportation Authority Michelle O'Neil MDOT, TSC Ryan Russell Village of Schoolcraft Brian Sanada MDOT, Region Kathy Schultz, Vice-Chair Central County Transportation Authority Jodi Stefforia Comstock Township Mark Worden Road Commission of Kalamazoo County MEMBERS ABSENT Tom Anthony Village of Mattawan Muhammad Arif City of Portage Bill Bresson City of Galesburg Todd Hackenberg Village of Lawton Robert Henderson Van Buren Public Transit Jim Mallery Village of Vicksburg Dexter Mitchel Kalamazoo Township Abhishek Prodduturi City of Kalamazoo Katie Reilly City of Kalamazoo John Small Village of Paw Paw Nancy Stoddard City of Parchment

Meeting Materials Page 3 of 83

Page 4: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

OTHERS PRESENT Jamie Harmon City of Portage Grace Guan KATS Megan Mickelson KATS Fred Nagler KATS Jon Start KATS Steve Stepek KATS

CHANGES OR ADDITIONS TO THE AGENDA

Remove number 11 from the agenda due to technical difficulties.

APPROVAL OF THE AGENDA

MOTION by Heppler, SECOND by Baker, “to approve the agenda for the February 7, 2019 Technical Committee Meeting as amended.” MOTION APPROVED.

MINUTES FROM THE JANUARY 10, 2019 MEETING

It was noted that the road report for the City of Portage should reference Romence Road. Chair Fort noted the change for the land use report to read “small cell networks.”

MOTION by Heppler, SECOND by Stefforia, “to approved the Minutes of the January 10, 2019 Technical Committee Meeting with amendments.” MOTION APPROVED.

POLICY COMMITTEE REPORT

Stepek noted the Policy Committee met on February 6 and approved all action items.

CITIZENS’ COMMENTS

No citizens’ comments were made.

FY 2017-2020 TRANSPORTATION IMPROVEMENT PROGRAM AMENDMENTS

Stepek noted one additional change of $80,000 flex transit job had the wrong year, it has been corrected. Additional money was added to the Westnedge job with the job number approved. The Stadium TAP award will be in next months amendments.

MOTION by Schultz, SECOND by Bittner, “to approve the FY 2017-2020 Transportation Improvement Program Amendments.” MOTION APPROVED. FY 2020-2023 TRANSPORTATION IMPROVEMENT PROGRAM MASTER PROJECT LIST

Stepek reported that the master list has been shared online and KATS needs to adopt the master program list to move forward with the full Transportation Improvement Program (TIP) document. Projects have been scored and ranked with illustrative projects listed for potential influx of TIP dollars.

MOTION by Schultz, SECOND by Heppler, “to approve the FY 2020-2023 Transportation Improvement Program Master Project List.” MOTION APPROVED.

FY 2020-2023 TRANSPORTATION IMPROVEMENT PROGRAM DRAFT FUNDING DISTRIBUTION

Stepek noted that the KATS committees will take action on the full TIP in May. Funded projects for the FY 2020-2023 TIP cycle are locked in place at this point. Consultation letters will go out following today’s meeting with an open house to follow in March for public participation. The TIP funding distribution will be included with the full TIP in April with adoptions set for May.

Meeting Materials Page 4 of 83

Page 5: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

PUBLIC TRANSPORTATION UPDATES

Schultz gave the update for Metro transit. Metro is partnering with the Foundation of Excellence, Kalamazoo Public Schools and library in the City of Kalamazoo to provide bus service as part of the Youth Mobility in Kalamazoo initiative. New bus stop sign design in process.

STATUS REPORTS

ROADS

Status reports concerning road projects were given by the City of Portage, Michigan Department of Transportation, Village of Augusta, and the Road Commission of Kalamazoo County.

Stepek reported that a PDF of programming information will be sent out via email to verify projects.

LAND USE/PLANNING AND ZONING

Texas Township is working on a Comprehensive Plan.

Kalamazoo County Planning has new GIS mapping website using ArcGIS Online. United Way in Kalamazoo is working on a census 2020 count committee and is looking for volunteers.

NEW BUSINESS Start mentioned the Transportation Asset Management Council Michigan Framework is currently version

17 with great uncertainty that version 19 would be available before spring data collection. For those

collecting data early, they can still use version 17 and when version 19 comes out, the data can be

moved to version 19.

Stepek reminded the committee that changes to FY19 or FY20 TIP need to be in by February 25 for the

March amendment. The February 25th meeting at 9:00 a.m. at KATS office will be the last meeting for the

FY 2017-2020 TIP.

Ribbon cutting for new Prein and Newhof office is February 19, a formal invitation will go out the

Technical Committee shortly.

ADJOURNMENT There being no other business, Chair Forth adjourned the February 7, 2019 Technical Committee Meeting at 9:39 a.m.

The next meeting of the Kalamazoo Area Transportation Study Technical Committee will be held on Thursday, March 14, 2019 at 9:00 a.m. Metro, 530 N. Rose Street.

Meeting Materials Page 5 of 83

Page 6: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

KALAMAZOO AREA TRANSPORTATION STUDY FY 2017-2020 TRANSPORTATION IMPROVEMENT PROGRAM MARCH 2019 AMENDMENTS

What is the TIP? The Transportation Improvement Program (TIP) is an outline of transportation projects programmed in the Kalamazoo Area Transportation Study (KATS) Planning Area for Fiscal Year (FY) 2017-2020. This area includes all of Kalamazoo County and Almena Township, Antwerp Township, Paw Paw Township, Waverly Township, and the Villages of Paw Paw, Lawton, and Mattawan in Van Buren County.

The Metropolitan Planning Area

Figure 1: Map of KATS MPO and Urbanized Area

The TIP, as required by federal regulations, addresses all projects proposed to use federal transportation funding within the KATS area. Everyone who lives, works, attends school, visits, or travels through our region is affected by these projects. The TIP responds to the everchanging needs of all users and includes maintenance, public transit, bikeway, sidewalk, bridge, traffic signal, and other projects.

Development of the TIP The TIP covers a four-year period but is updated every three years to ensure an efficient transition between programs.

The program is developed using the continuing, cooperative, and comprehensive planning process with state and federal transportation agencies (the Michigan Department of Transportation, the Federal Highway Administration and the Federal Transit Administration), public transit agencies, local governments, and residents. To be included in the TIP, projects must have committed funding and provide project details.

Amending the TIP KATS regularly amends the TIP to reflect new and changing projects. The KATS staff may approve minor changes, but certain modifications are more significant and require KATS to approve a formal amendment to the TIP. These modifications include:

• Cost changes that exceed percentagethresholds

• Major changes that affect project scope• Additions• Deletions• Schedule changes that move projects into the

TIP’s time period

The TIP Process

Figure 2: KATS Transportation Improvement Process

The Metropolitan Transportation Plan The Kalamazoo Area Transportation Study also develops the region’s long-term Metropolitan Transportation Plan (MTP). The MTP covers more than 20 years of planning efforts and must be updated every four years. The short-range projects included in the TIP must be consistent with the long-range planning efforts included in the MTP.

Kalamazoo Area Transportation Study 5220 Lovers Lane, Suite 110 Portage, MI 49002 Phone: 269-343-0766 Email: [email protected]

For more information on the Transportation Improvement Program visit

www.KATSmpo.org.

Public notice of public involvement activities and time established for public review and comments on the Transportation Improvement Program (TIP) will satisfy the Program of Projects (POP) requirements for the following grantees: The Kalamazoo County Transportation Authority, the Central County Transportation Authority and Van Buren Public Transit.

FY 2017-2020 TIP Fiscal Constraint 2017 Total Commitments

2018 Total Commitments

2019 Total Commitments

2020 Commitments

Figure 3: FY 2017-2020 Fiscal Constraint by Year

Call for Projects Every Three Years

Project Prioritization

Committee Approval

MDOT and FHWA Approval

Amen

dmen

ts

Publ

ic P

artic

ipat

ion

Meeting Materials Page 6 of 83

Page 7: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Fiscal Year

Job no. Phase Responsible Agency Project Name Limits Primary Work Type Project Description Federal Budget State Budget Local Budget Total Phase Cost

Type Total Project Cost

FiscalYear

JobNumber

Phase Responsible Agency

Project Name Limits Primary Work Type

Project Description FederalCost

State Cost Local Cost Total Phase Cost

AmendmentType

Total Project Cost

2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility

Construct 5ft shoulders for non-motorized use

$277,239 $0 $76,137 $353,376 Addition $353,376

2019 124035 CON MDOT I-94 I-94 WB from Exit 46 to Exit 56

Traffic Safety Install Trees $240,085 $26,677 $0 $266,761 Scope Construction

Length Change

$289,958

2019 206566 PE MDOT I-94 W East of Lovers Lane to west of Sprinkle Road

Major Widening Road and Bridge Reconstruction

$415,962 $92,238 $0 $508,200 Addition $6,200,040

2019 206782 NI Kalamazoo Central County Transportation Authority

N Rose St Areawide/Kalamazoo County

P004-Operating Assistance

FY16 Section 5311 operating reconciliation.

$1,996 $0 $0 $1,996 Addition $1,996

2019 206782 NI Kalamazoo Central County Transportation Authority

N Rose St Areawide/Kalamazoo County

P004-Operating Assistance

FY16 Section 5311 operating reconciliation.

$1,996 $0 $0 $1,996 Addition $1,996

2019 207308 NI Kalamazoo Central County Transportation Authority

N Rose St Metro Transit SP3000-operating except JARC and New Freedom

5311 Rural Operating $30,000 $7,500 $0 $37,500 Addition $37,500

2019 207308 NI Kalamazoo Central County Transportation Authority

N Rose St Metro Transit 3000-Operating Assistance

5311 Rural Operating $18,454 $4,613 $0 $23,067 Budget over 24%

$23,067

2019 203132 NI Central County Transportation Authority

Transit Operating Areawide SP3000-operating except JARC and New Freedom

Operating $1,700,000 $5,200,000 $8,000,000 $14,900,000 Budget over 24%

$14,900,000

2020 206262 CON Parchment Commerce Ln City of Parchment- Commerce Lane

Road Rehabilitation

Roadway Rehabilitation- Mill and Resurface

$130,141 $0 $28,859 $159,000 Addition $159,000

March 2019 Amendments (3/27/19)FY 2017-2020 Transportation Improvement Program

Kalamazoo Area Transportation StudyMeeting Materials Page 7 of 83

Page 8: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Fiscal Year

Job no. Phase Responsible Agency Project Name Limits Primary Work Type Project Description Federal Budget State Budget Local Budget Total Phase Cost

Type Total Project Cost

FiscalYear

JobNumber

Phase Responsible Agency

Project Name Limits Primary Work Type

Project Description FederalCost

State Cost Local Cost Total Phase Cost

AmendmentType

Total Project Cost

March 2019 Amendments (3/27/19)FY 2017-2020 Transportation Improvement Program

2020 207249 CON Kalamazoo County G Avenue G Avenue from 2nd Street to 6th Street, Kalamazoo County

Traffic Safety Construct paved shoulder, remove trees, upgrade guardrail, edgeline marking

$299,700 $0 $33,300 $333,000 Addition $333,000

2020 206566 CON MDOT I-94 W East of Lovers Lane to west of Sprinkle Road

Major Widening Road and Bridge Reconstruction

$4,658,771 $1,033,069 $0 $5,691,840 Addition $6,200,040

2020 132617 CON MDOT I-94BL between 11th Street and Seneca, Kalamazoo

Traffic Safety Install Traffic Responsive Signal Technology

$625,000 $0 $0 $625,000 Budget over 24%

$935,000

2020 203698 CON MDOT M-139 Various Crack Seal Locations

Road Capital Preventive Maintenance

Overband Crack Fill $177,273 $38,913 $0 $495,000 Budget over 24%

$527,000

2020 207188 CON Kalamazoo County Multiple Routes, Kalamazoo County

Multiple Routes, Various Locations, Kalamazoo County

Traffic Safety Upgrade Stop and Stop Ahead signs

$247,500 $0 $27,500 $275,000 Addition $275,000

2020 206263 CON Mattawan N Main St Main Street in Mattawan: Payne Creek Crossing

Reconstruction Remove box culvert, resurface

$170,248 $0 $37,752 $208,000 Addition $208,000

2020 207304 NI Kalamazoo Central County Transportation Authority

N Rose St Metro Transit SP3000-operating except JARC and New Freedom

5311 Rural Operating $30,000 $7,500 $0 $37,500 Addition $37,500

2020 205102 NI Kalamazoo Central County Transportation Authority

N Rose St Metro Transit SP1103-35-39 foot replacement bus with or without lift

5307 Capital $1,399,602 $349,901 $0 $1,749,503 Addition $1,749,503

2020 205175 NI Kalamazoo Central County Transportation Authority

N Rose St Metro Transit SP1103-35-39 foot replacement bus with or without lift

5339 Capital $313,398 $78,349 $0 $391,747 Addition $391,747

Meeting Materials Page 8 of 83

Page 9: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Fiscal Year

Job no. Phase Responsible Agency Project Name Limits Primary Work Type Project Description Federal Budget State Budget Local Budget Total Phase Cost

Type Total Project Cost

FiscalYear

JobNumber

Phase Responsible Agency

Project Name Limits Primary Work Type

Project Description FederalCost

State Cost Local Cost Total Phase Cost

AmendmentType

Total Project Cost

March 2019 Amendments (3/27/19)FY 2017-2020 Transportation Improvement Program

2020 205195 NI Kalamazoo Central County Transportation Authority

N Rose St Metro Transit SP1105-van replacement, any size with or without lift

5310 Capital $196,026 $49,006 $0 $245,032 Addition $245,032

2020 207248 CON Kalamazoo County S Avenue S Avenue from west of 34th Street to 36th Street, Kalamazoo County

Traffic Safety Construct center left turn lane, vertical curve modification, pave shoulder

$495,000 $0 $55,000 $550,000 Addition $550,000

2020 206546 CON MDOT Southwest Regionwide Longitudinal Pavement Marking

All of KATS MPO Traffic Safety Longitudinal pavement marking application on trunklines in Southwest Region

$311,220 $34,580 $0 $1,820,000 Addition $1,825,000

2020 206546 PE MDOT Southwest Regionwide Longitudinal Pavement Marking

All of KATS MPO Traffic Safety Longitudinal pavement marking application on trunklines in Southwest Region

$855 $95 $0 $5,000 Addition $1,825,000

2020 206006 CON MDOT Southwest Regionwide Pvmt Mrkg Retro Readings

All of KATS MPO Traffic Safety Pvmt mrkg retroreflectivity readings on trunklines in Southwest Region

$2,052 $228 $0 $12,000 Addition $12,000

2020 206547 CON MDOT Southwest Regionwide Special Pavement Markings

All of KATS MPO Traffic Safety Special pavement marking application on trunklines in Southwest Region

$76,950 $8,550 $0 $450,000 Addition $455,000

2020 206547 PE MDOT Southwest Regionwide Special Pavement Markings

All of KATS MPO Traffic Safety Special pavement marking application on trunklines in Southwest Region

$855 $95 $0 $5,000 Addition $455,000

Meeting Materials Page 9 of 83

Page 10: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Fiscal Year

Job no. Phase Responsible Agency Project Name Limits Primary Work Type Project Description Federal Budget State Budget Local Budget Total Phase Cost

Type Total Project Cost

FiscalYear

JobNumber

Phase Responsible Agency

Project Name Limits Primary Work Type

Project Description FederalCost

State Cost Local Cost Total Phase Cost

AmendmentType

Total Project Cost

March 2019 Amendments (3/27/19)FY 2017-2020 Transportation Improvement Program

2020 206301 CON Kalamazoo County Stadium Ave Stadium Drive- Non Motorized

New Facilities Roadside Facility $259,913 $0 $358,522 $618,435 Addition $618,435

2020 203137 NI Central County Transportation Authority

Transit Operating Areawide SP10-State Match urban Agency

Operating $1,700,000 $5,200,000 $8,000,000 $14,900,000 Addition $14,900,000

2023 122664 CON MDOT US-131 SB & NB Over Amtrak & KL Avenue

Bridge Replacement

Bridge Replacement $9,249,051 $2,050,951 $0 $11,300,000 Moved out of Current TIP

$12,215,000

Meeting Materials Page 10 of 83

Page 11: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Total Estimated

Amount

Fed Estimated

Amount

State Estimated

Amount

03/06/2019

1 of 9

105885 1.248 $41,741,733 $50,997,840 12/04/202010/09/20202021 $9,125,497 $130,612 53,647,840

105886 1.182 $27,878,171 $34,060,074 12/04/202010/09/20202021 $6,181,903 $0 36,735,074

122664 0.000 $9,249,051 $11,300,000 12/02/202210/07/20222023 $2,050,951 $0 12,215,000

129068 0.688 $2,533,258 $3,095,000 12/04/202011/04/20202021 $561,743 $0 4,075,000

129071 0.957 $963,099 $1,070,110 12/04/202010/20/20202021 $107,011 $0 1,320,692

129837 1.274 $556,887 $556,887 01/29/2016 06/07/201904/12/20192020 950,000

129887 0.000 $1,059,300 $1,177,000 02/05/202112/15/20202021 $117,700 $0 1,358,000

130143 1.505 $549,243 $1,700,000 09/26/2018 06/05/202010/01/20192020 $0 $1,150,757 1,700,000

130803 0.181 $300,000 $468,000 06/29/2016 12/06/201910/01/20192020 $0 $168,000 468,000

130804 0.729 $900,000 $1,425,000 06/29/2016 12/06/201910/01/20192020 $0 $525,000 1,425,000

130824 1.253 $457,000 $650,000 03/23/2017 02/07/202002/07/20202020 $0 $193,000 1,500,000

130824 1.253 $543,000 $850,000 03/23/2017 02/07/202002/07/20202020 $0 $307,000 1,500,000

131000 2.005 $433,947 $1,271,000 05/22/2017 12/06/201910/01/20192020 $0 $837,053 1,271,000

131001 1.129 $860,000 $1,060,000 06/29/2016 12/06/201910/01/20192020 $0 $200,000 1,060,000

131004 0.001 $51,408 $51,408 07/11/2018 12/06/201910/01/20192020 $0 $0 51,408

131018 0.932 $924,477 $1,089,000 05/22/2017 12/06/201910/01/20192020 $0 $164,523 1,089,000

132617 0.763 $625,000 $625,000 12/06/201910/11/20192020 $0 $0 935,000

132931 0.458 $417,435 $510,000 07/11/2018 10/04/201910/01/20192020 $0 $92,565 510,000

200366 0.000 $428,080 $428,080 08/31/2017 06/05/202004/10/20202020 $0 $0 2,618,400

200641 3.402 $170,174 $207,910 02/03/202311/01/20212022 $37,736 $0 11,241,145

200641 3.402 $8,042,970 $9,826,475 02/03/202312/09/20222023 $555,822 $1,227,683 11,241,145

DRAFT KATS Transportation Improvement Program ProjectsFiscal Year(s) : 2020, 2021, 2022, 2023

Page:

Date:

S/TIP Cycle

Job Type PhaseStatus

MPO/RuralApproval

Date

ProjectName

Job # ActualLet Date

Schedule Let Date

ActualObligation

Date

ScheduleObligation

Date

FederalAmendment

Type

County Length Fund Source

FiscalYear

ProjectDescription

Total Job Cost

FTAApproval

Date

S/TIP Status

S/TIP Line items

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Road Reconstruction and Widen

CON 20-23 NH Phase Added

I-94 Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Road and Bridge Reconstruction

CON 20-23 NH Phase Added

I-94 Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Bridge Replacement

CON 20-23 NHUS-131 Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Construct Roundabout

CON 20-23 CM Phase Added

M-43 Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Add Left turn Lanes and Intersection Realignment

CON 20-23 HSIP Phase Budget

over 24%

M-43 Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Van Buren Mill of existing HMA 2 inches, install fabric, rep

CON 17-20 STLRed Arrow Highway

2020 Programmed Approved02/10/2016

Trunkline Kalamazoo Area Transportation Study (KATS)

Van Buren Shallow Overlay, substructure repairs

CON 20-23 BOII-94 Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Resurface CON 17-20 STLU Avenue Programmed Approved10/10/2018

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo HMA mill and resurface

CON 17-20 STUShaver Rd Programmed Approved07/20/2017

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Mill and resurface, ADA upgrades

CON 17-20 STUWestnedge Ave

Programmed Approved09/30/2016

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Resurface CON 17-20 NHDrake Rd Programmed Approved03/23/2017

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Resurface CON 17-20 STUDrake Rd Programmed Approved03/23/2017

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo HMA mill and resurface

CON 17-20 STUCentre Ave Programmed Approved07/10/2017

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Cold mill and resurface

CON 17-20 STU Funding changes to Federal and Local funding amounts.

Oakland Dr Programmed Approved07/18/2017

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Community Rideshare Marketing

PE 17-20 CMG Already determined eligible, March 2015

Rose St Programmed Approved07/11/2018

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Traffic Signal Optimization

CON 17-20 CM Determined eligible March, 2015.

Drake Rd Programmed Approved05/22/2017

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Install Traffic Responsive Signal Technology

CON 17-20 CMG Phase Budget

over 24%,Rollup

Changes,Scope

Construction Length

Change

I-94BL Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Van Buren Resurfacing CON 17-20 STULCR 653 Programmed Approved07/11/2018

Trunkline Kalamazoo Area Transportation Study (KATS)

Cass Traffic Signal Modernizations; connected vehicle installations.

CON 17-20 STGM-60 E Programmed Approved08/31/2017

Trunkline Kalamazoo Area Transportation Study (KATS)

Van Buren Mill and Two Course Hot Mix Asphalt Overlay

ROW 20-23 STM-40 Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Van Buren Mill and Two Course Hot Mix Asphalt Overlay

CON 20-23 STM-40 Programmed PendingN/A

Local Estimated

Amount

PrimaryWork Type

PhaseMPO ResponsibleAgency

FHWAApproval

Date

CommentsLimits

MDOT Major WideningEast of Lovers Lane to East of Portage Road

MDOT Major WideningPortage Road to Sprinkle Road

MDOT Bridge Replacement

Over Amtrak and KL Avenue

MDOT Traffic SafetyM-43 at G Avenue, Comstock Township, Kalamazoo Co.

MDOT Traffic SafetyM-43 at 28th St, Richland Township, Kalamazoo Co.

Van Buren County

Road Rehabilitation

26th Street to 28th Street

ACC N/A

MDOT Bridge Rehabilitation

under 32nd Street (CR 653)

Kalamazoo County

Road Rehabilitation

29th St to 32nd St

N/A

Portage Road Rehabilitation

W. Centre to S. Westnedge

N/A

Portage Road Rehabilitation

Shaver to Romence Rd

N/A

Kalamazoo County

Road Capital Preventive Maintenance

KL to M-43 N/A

Kalamazoo County

Road Capital Preventive Maintenance

KL to M-43 N/A

Portage Road Rehabilitation

Portage Rd to Sprinkle Rd

N/A

Kalamazoo Road Rehabilitation

Parkview Ave to Howard St

N/A

Central County Transportation Authority

Operation Improvements

Areawide Rideshare

N/A

Kalamazoo County

Traffic SafetyW. Main St. to Parkview- 9 Signals

N/A

MDOT Traffic Safetybetween 11th Street and Seneca, Kalamazoo

Van Buren County

Road Rehabilitation

Red Arrow Highway South to I - 94

N/A

MDOT Traffic SafetyUS131 @ U AVE (6 pole)US131BR (PARK) @ PATERSON

N/A

MDOT Road Rehabilitation

72nd Street to south of Lagrave Street

MDOT Road Rehabilitation

72nd Street to south of Lagrave Street

ACCYear(s)

AC/ACC

Meeting Materials Page 11 of 83

Page 12: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Total Estimated

Amount

Fed Estimated

Amount

State Estimated

Amount

03/06/2019

2 of 9

200693 0.000 $110,571 $122,857 12/03/202110/08/20212022 $12,286 $0 500,000

201119 0.340 $147,330 $180,000 12/02/202210/01/20202021 $32,670 $0 1,855,000

201119 0.340 $32,740 $40,000 12/02/202212/01/20202021 $7,260 $0 1,855,000

201119 0.340 $1,338,248 $1,635,000 12/02/202210/07/20222023 $296,753 $0 1,855,000

201967 6.812 $47,552 $52,835 12/02/202210/01/20212022 $5,284 $0 477,050

201967 6.812 $381,794 $424,215 12/02/202210/07/20222023 $42,421 $0 477,050

0.050 $69,573 $85,000 12/04/202010/09/20202021 $15,428 $0

201985 2.792 $7,740,000 $8,600,000 01/07/202211/12/20212022 $860,000 $0 9,300,000

201994 0.000 $69,300 $77,000 11/04/202204/01/20212021 $7,700 $0 796,100

201994 0.000 $647,190 $719,100 11/04/202210/03/20222023 $71,910 $0 796,100

202433 0.000 $87,200 $109,000 12/27/2017 01/10/202011/15/20192020 $16,350 $5,450 109,000

202434 0.000 $80,000 $100,000 01/24/2018 02/07/202012/13/20192020 $15,000 $5,000 227,000

202434 0.000 $42,400 $53,000 01/24/2018 02/07/202012/13/20192020 $7,950 $2,650 227,000

202434 0.000 $59,200 $74,000 01/24/2018 02/07/202012/13/20192020 $11,100 $3,700 227,000

202651 68.189 $250,000 $250,000 08/29/2018 12/04/202010/01/20192020 $0 $0 1,207,005

202651 68.189 $957,005 $957,005 12/04/202010/09/20202021 $0 $0 1,207,005

203137 0.000 $1,700,000 $14,900,000 09/30/20202020 $5,200,000 $8,000,000 14,900,000

203643 5.869 $4,634,068 $5,148,965 09/26/2018 02/07/202012/13/20192020 $514,897 $0 5,336,200

203698 33.301 $177,273 $216,186 02/07/202012/13/20192020 $38,913 $0 527,000

201979

Fiscal Year(s) : 2020, 2021, 2022, 2023 Page:

Date:

S/TIP Cycle

Job Type PhaseStatus

MPO/RuralApproval

Date

ProjectName

Job # ActualLet Date

Schedule Let Date

ActualObligation

Date

ScheduleObligation

Date

FederalAmendment

Type

County Length Fund Source

FiscalYear

ProjectDescription

Total Job Cost

FTAApproval

Date

S/TIP Status

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Installation of detection for actuation

CON 20-23 HSIPE Kilgore Rd Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Construct Dual Left Turn Lanes

PE 20-23 CM Phase Added

M-43 Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Construct Dual Left Turn Lanes

ROW 20-23 CM Phase Added

M-43 Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Construct Dual Left Turn Lanes

CON 20-23 CM Phase Added

M-43 Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Roadside Fixed Object Removal

PE 20-23 HSIP Phase Added

I-94 W Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Roadside Fixed Object Removal

CON 20-23 HSIP Phase Added

I-94 W Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Construct new carpool lot.

CON 20-23 ST Phase Abandone

d

M-43 Abandoned PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Van Buren Hot Mix Asphalt Overlay

CON 20-23 IMI-94 E Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Rural intersection warning system

PE 20-23 HSIP Phase Added

E Kilgore Rd Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Rural intersection warning system

CON 20-23 HSIP Phase Added

E Kilgore Rd Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Miscellaneous Bridge Capital Preventative Maintenance

CON 17-20 BOS 29th St Programmed Approved02/14/2018

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Miscellaneous Bridge Capital Preventative Maintenance

CON 17-20 BHTCountywide Programmed Approved02/14/2018

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Miscellaneous Bridge Capital Preventative Maintenance

CON 17-20 BHTCountywide Programmed Approved02/14/2018

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Miscellaneous Bridge Capital Preventative Maintenance

CON 17-20 BHTCountywide Programmed Approved02/14/2018

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Non-freeway Signing

PE 17-20 STGUS-131 N Programmed Approved09/11/2018

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Non-freeway Signing

CON 20-23 STGUS-131 N Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo Operating NI 17-20 5307 Phase Added

Transit Operating

Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Mill and One Course Hot Mix Asphalt Overlay

CON 17-20 IMI-94 W Programmed Approved10/10/2018

Trunkline Kalamazoo Area Transportation Study (KATS)

Berrien Overband Crack Fill

CON 17-20 ST Phase Budget

over 24%,Rollup

Changes,Scope

Construction Length

Change

M-139 Programmed PendingN/A

Local Estimated

Amount

PrimaryWork Type

PhaseMPO ResponsibleAgency

FHWAApproval

Date

CommentsLimits

MDOT Traffic SafetyUS131 @ U AVEM43 (W MAIN) @ KENDALLM96 @ 35TH (SHAFTER RD)US131 NB @ SHAVER RD

MDOT Minor WideningM-43 at Sprinkle Road in Kalamazoo County

MDOT Minor WideningM-43 at Sprinkle Road in Kalamazoo County

MDOT Minor WideningM-43 at Sprinkle Road in Kalamazoo County

MDOT Traffic SafetyI-94 between I-94 Business Route and 40th Street

MDOT Traffic SafetyI-94 between I-94 Business Route and 40th Street

MDOT New FacilitiesAt G Avenue.

MDOT Road Rehabilitation

West of M-51 to 40th Street

MDOT Traffic SafetyIntersections located in Cass, Branch and Calhoun Counties

MDOT Traffic SafetyIntersections located in Cass, Branch and Calhoun Counties

Kalamazoo County

Bridge CPM29th Street over Portage River, Str# 4625, Kalamazoo County

N/A

Kalamazoo County

Bridge CPMCountywide, Kalamazoo County

N/A

Kalamazoo County

Bridge CPMCountywide, Kalamazoo County

N/A

Kalamazoo County

Bridge CPMCountywide, Kalamazoo County

N/A

MDOT Traffic SafetyVarious in Kalmazoo County

N/A

MDOT Traffic SafetyVarious in Kalmazoo County

Central County Transportation Authority

SP10-State Match urban Agency

Areawide

MDOT Road Capital Preventive Maintenance

Van Buren/Kalamazoo County Line to Ninth Street

N/A

MDOT Road Capital Preventive Maintenance

Various Crack Seal Locations

ACCYear(s)

AC/ACC

DRAFT KATS Transportation Improvement Program Projects

Meeting Materials Page 12 of 83

Page 13: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Total Estimated

Amount

Fed Estimated

Amount

State Estimated

Amount

03/06/2019

3 of 9

204423 0.357 $270,538 $270,538 02/20/2019 12/06/201910/11/20192020 $0 $0 880,538

204668 1.450 $135,000 $135,000 12/03/202110/08/20212022 $0 $0 1,414,968

204791 3.012 $96,188 $106,876 12/01/202301/03/20222022 $10,688 $0 930,214

204954 0.589 $199,999 $199,999 02/20/2019 07/10/202007/10/20202020 $0 $0 199,999

205077 38.481 $1,426,493 $1,739,625 02/05/202112/11/20202021 $313,133 $0 4,701,078

205102 0.000 $160,000 $200,000 07/01/20202020 $40,000 $0 1,749,503

205102 0.000 $32,000 $40,000 07/01/20202020 $8,000 $0 1,749,503

205102 0.000 $53,000 $66,250 07/01/20202020 $13,250 $0 1,749,503

205102 0.000 $268,000 $335,000 07/01/20202020 $67,000 $0 1,749,503

205102 0.000 $886,602 $1,108,253 07/01/20202020 $221,651 $0 1,749,503

205175 0.000 $313,398 $391,747 07/01/20202020 $78,349 $0 391,747

205195 0.000 $196,026 $245,032 07/01/20202020 $49,006 $0 245,032

205408 6.003 $0 $236,967 01/08/202111/13/20202021 $236,967 $0 900,000

205408 6.003 $541,000 $663,033 01/08/202111/13/20202021 $0 $122,033 900,000

205409 0.000 $103,000 $128,750 07/01/20212021 $25,750 $0 128,750

205411 2.534 $552,000 $1,040,000 01/07/202211/12/20212022 $0 $488,000 1,040,000

205412 0.000 $105,000 $131,250 07/01/20222022 $26,250 $0 131,250

205414 3.497 $0 $157,978 01/06/202311/10/20222023 $157,978 $0 682,978

205414 3.497 $525,000 $525,000 01/06/202311/10/20222023 $0 $0 682,978

Fiscal Year(s) : 2020, 2021, 2022, 2023 Page:

Date:

S/TIP Cycle

Job Type PhaseStatus

MPO/RuralApproval

Date

ProjectName

Job # ActualLet Date

Schedule Let Date

ActualObligation

Date

ScheduleObligation

Date

FederalAmendment

Type

County Length Fund Source

FiscalYear

ProjectDescription

Total Job Cost

FTAApproval

Date

S/TIP Status

Trunkline Kalamazoo Area Transportation Study (KATS)

Berrien Cantilevers Replacement Project

CON 17-20 STG Phase Added

Various Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Signing Replacement

CON 20-23 STGVarious Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Diamond Grinding Concrete Pavement

PE 20-23 HSIP Phase Added

I-94 W Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Van Buren Replace Traffic Signal

OPS 17-20 CMG Phase Budget

over 24%,Rollup

Changes

W North St Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Van Buren Variable Advisory Speed Limit System along I-94 in VanBuren Co.

CON 20-23 NH Phase Added

I-94 Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5307 Capital NI 17-20 5307 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5307 Capital NI 17-20 5307 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5307 Capital NI 17-20 5307 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5307 Capital NI 17-20 5307 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5307 Capital NI 17-20 5307 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5339 Capital NI 17-20 5339 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5310 Capital NI 17-20 5310 Phase Added

N Rose St Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Cold Milling & HMA Overlay (<2 inches)

CON 20-23 EDDE R Ave Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Cold Milling & HMA Overlay (<2 inches)

CON 20-23 STLE R Ave Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo van purchase NI 20-23 STL Phase Added

N Rose St Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Reconstruction CON 20-23 STL Phase Added

E S Ave Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo van purchase NI 20-23 STL Phase Added

N Rose St Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Crush and Shape and Asphalt Resurfacing

CON 20-23 EDDS 36th St Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Crush and Shape and Asphalt Resurfacing

CON 20-23 STLS 36th St Programmed PendingN/A

Local Estimated

Amount

PrimaryWork Type

PhaseMPO ResponsibleAgency

FHWAApproval

Date

CommentsLimits

MDOT Traffic SafetySigning Update, Signing Updates

MDOT Traffic SafetySigning Update

MDOT Road Capital Preventive Maintenance

I-94 Westbound between Westnedge and 12th Street in Kalamazoo County

Paw Paw Traffic SafetyIntersection of North St. and Hazen St.

MDOT ITS Applications

I-94 VanBuren County east, I-94 eastern limits of VanBuren County

Kalamazoo Central County Transportation Authority

SP1404-computers (hardware and software)

Metro Transit

Kalamazoo Central County Transportation Authority

SP1409-administrative vehicle

Metro Transit

Kalamazoo Central County Transportation Authority

SP1105-van replacement, any size with or without lift

Metro Transit

Kalamazoo Central County Transportation Authority

SP1203-admin/maintenance facility improvements

Metro Transit

Kalamazoo Central County Transportation Authority

SP1103-35-39 foot replacement bus with or without lift

Metro Transit

Kalamazoo Central County Transportation Authority

SP1103-35-39 foot replacement bus with or without lift

Metro Transit

Kalamazoo Central County Transportation Authority

SP1105-van replacement, any size with or without lift

Metro Transit

Kalamazoo County

Road Rehabilitation

36th Street to East County Line

Kalamazoo County

Road Rehabilitation

36th Street to East County Line

Kalamazoo Central County Transportation Authority

SP10-State Match urban Agency

Areawide

Kalamazoo County

Reconstruction 29th Street to 34th Street

Kalamazoo Central County Transportation Authority

SP10-State Match urban Agency

Metro Transit

Kalamazoo County

Road Rehabilitation

36th Street T Avenue to PQ Avenue

Kalamazoo County

Road Rehabilitation

36th Street T Avenue to PQ Avenue

ACCYear(s)

AC/ACC

DRAFT KATS Transportation Improvement Program Projects

Meeting Materials Page 13 of 83

Page 14: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Total Estimated

Amount

Fed Estimated

Amount

State Estimated

Amount

03/06/2019

4 of 9

205416 0.000 $145,000 $181,250 09/29/20232023 $36,250 $0 181,250

206006 3.199 $2,052 $2,280 10/01/20192020 $228 $0 12,000

206256 1.061 $920,000 $1,150,000 03/03/202301/06/20232023 $0 $230,000 1,150,000

206257 1.048 $750,000 $1,085,000 03/03/202301/06/20232023 $0 $335,000 1,085,000

206258 2.002 $1,200,000 $2,530,000 03/03/202301/06/20232023 $0 $1,330,000 2,530,000

206259 0.958 $371,000 $463,750 03/03/202301/06/20232023 $0 $92,750 1,575,299

206259 0.958 $485,000 $606,250 03/03/202301/06/20232023 $0 $121,250 1,575,299

206259 0.958 $505,299 $505,299 03/03/202301/06/20232023 $0 $0 1,575,299

206261 1.577 $245,000 $306,250 03/03/202301/06/20232023 $0 $61,250 306,250

206262 0.377 $130,141 $159,000 03/06/202001/10/20202020 $0 $28,859 159,000

206263 0.065 $170,248 $208,000 03/06/202001/10/20202020 $0 $37,752 208,000

206264 2.905 $450,000 $744,701 03/05/202101/08/20212021 $0 $294,701 3,620,000

206264 2.905 $1,455,299 $2,875,299 03/05/202101/08/20212021 $0 $1,420,000 3,620,000

206265 1.234 $466,000 $582,500 03/05/202101/08/20212021 $0 $116,500 1,500,000

206265 1.234 $534,000 $917,500 03/05/202101/08/20212021 $0 $383,500 1,500,000

206266 1.757 $720,000 $900,000 03/05/202101/08/20212021 $0 $180,000 900,000

206267 0.509 $144,000 $180,000 03/05/202101/08/20212021 $0 $36,000 180,000

206269 2.483 $1,600,000 $2,000,000 03/04/202201/07/20222022 $0 $400,000 2,000,000

206271 1.206 $448,000 $560,000 03/05/202101/08/20212021 $0 $112,000 560,000

206273 2.181 $153,000 $195,000 03/04/202201/07/20222022 $0 $42,000 785,000

206273 2.181 $475,000 $590,000 03/04/202201/07/20222022 $0 $115,000 785,000

206275 0.938 $200,000 $250,000 03/04/202201/07/20222022 $0 $50,000 250,000

Fiscal Year(s) : 2020, 2021, 2022, 2023 Page:

Date:

S/TIP Cycle

Job Type PhaseStatus

MPO/RuralApproval

Date

ProjectName

Job # ActualLet Date

Schedule Let Date

ActualObligation

Date

ScheduleObligation

Date

FederalAmendment

Type

County Length Fund Source

FiscalYear

ProjectDescription

Total Job Cost

FTAApproval

Date

S/TIP Status

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo Bus Purchase NI 20-23 STL Phase Added

N Rose St Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Pvmt mrkg retroreflectivity readings on trunklines in Southwest Region

CON 17-20 HSIP Phase Added

Southwest Regionwide Pvmt Mrkg Retro Readings

Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Resurface and Road Diet

CON 20-23 STU Phase Added

Whites Rd Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Roadway Rehabilitation- Mill and resurface

CON 20-23 STU Phase Added

Portage Rd Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Roadway Rehabilitation- Mill and Resurface

CON 20-23 STU Phase Added

Shaver Rd Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Roadway Rehabilitation- Mill and Resurface

CON 20-23 STU Phase Added

S Westnedge Ave

Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Roadway Rehabilitation- Mill and Resurface

CON 20-23 NH Phase Added

S Westnedge Ave

Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Roadway Rehabilitation- Mill and Resurface

CON 20-23 CMG Phase Added

S Westnedge Ave

Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo HMA Mill and resurface

CON 20-23 STU Phase Added

Douglas Ave Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Roadway Rehabilitation- Mill and Resurface

CON 17-20 HIPU Phase Added

Commerce Ln Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Van Buren Remove box culvert, resurface

CON 17-20 HIPU Phase Added

N Main St Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Roadway Rehabilitation and Signal Interconnect

CON 20-23 CMG Phase Added

W Milham Ave Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Roadway Rehabilitation and Signal Interconnect

CON 20-23 STU Phase Added

W Milham Ave Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo HMA Mill and resurface

CON 20-23 NH Phase Added

Sprinkle Rd Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo HMA Mill and resurface

CON 20-23 STU Phase Added

Sprinkle Rd Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Roadway Rehabilitation- Mill and Resurface

CON 20-23 STU Phase Added

Parkview Ave Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo HMA Mill and resurface

CON 20-23 STU Phase Added

Solon St Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Roadway Rehabilitation- Mill and Resurface

CON 20-23 STU Phase Added

Stadium Dr Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Roadway Rehabilitation- Mill and Resurface

CON 20-23 STU Phase Added

N Nichols Rd Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Roadway Rehabilitation- Mill and Resurface

CON 20-23 STU Phase Added

Sprinkle Rd Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Roadway Rehabilitation- Mill and Resurface

CON 20-23 NH Phase Added

Sprinkle Rd Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Microsurface CON 20-23 STU Phase Added

S Westnedge Ave

Programmed PendingN/A

Local Estimated

Amount

PrimaryWork Type

PhaseMPO ResponsibleAgency

FHWAApproval

Date

CommentsLimits

Kalamazoo Central County Transportation Authority

SP10-State Match urban Agency

Kalamazoo Metro

MDOT Traffic SafetyAll of KATS MPO

Kalamazoo Road Rehabilitation

Whites Rd- City of Kalamazoo

Portage Road Rehabilitation

Portage Rd in City of Portage

Portage Road Rehabilitation

Shaver Rd- City of Portage

Kalamazoo Road Rehabilitation

Westnedge Ave-

Kalamazoo Road Rehabilitation

Westnedge Ave-

Kalamazoo Road Rehabilitation

Westnedge Ave-

Kalamazoo County

Road Rehabilitation

Douglas Avenue- City of Kalamazoo Limits to G Avenue

Parchment Road Rehabilitation

City of Parchment- Commerce Lane

Mattawan ReconstructionMain Street in Mattawan: Payne Creek Crossing

Portage Road Rehabilitation

Milham Ave in City of Portage

Portage Road Rehabilitation

Milham Ave in City of Portage

Kalamazoo County

Road Rehabilitation

Sprinkle Rd: Milham Ave to N Ave

Kalamazoo County

Road Rehabilitation

Sprinkle Rd: Milham Ave to N Ave

Kalamazoo Road Rehabilitation

City of Kalamazoo: Parkview Ave

Kalamazoo County

Road Rehabilitation

Solon Ave

Kalamazoo Road Rehabilitation

Stadium Drive, City of Kalamazoo

Kalamazoo County

Road Rehabilitation

Nichols Rd

Kalamazoo County

Road Rehabilitation

Sprinkle Rd

Kalamazoo County

Road Rehabilitation

Sprinkle Rd

Portage Road Capital Preventive Maintenance

City of Portage: Westnedge Ave

ACCYear(s)

AC/ACC

DRAFT KATS Transportation Improvement Program Projects

Meeting Materials Page 14 of 83

Page 15: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Total Estimated

Amount

Fed Estimated

Amount

State Estimated

Amount

03/06/2019

5 of 9

206294 0.779 $368,000 $460,000 03/04/202201/07/20222022 $0 $92,000 460,000

206297 1.626 $60,000 $80,000 03/04/202201/07/20222022 $0 $20,000 850,000

206297 1.626 $445,000 $770,000 03/04/202201/07/20222022 $0 $325,000 850,000

206298 1.320 $200,000 $252,000 01/07/202211/12/20212022 $0 $52,000 252,000

206299 2.038 $750,000 $1,075,000 02/04/202212/10/20212022 $0 $325,000 1,075,000

206301 0.423 $259,913 $618,435 03/06/202001/10/20202020 $0 $358,522 618,435

206304 0.000 $87,000 $108,750 09/30/20222022 $21,750 $0 108,750

206305 0.440 $0 $514,934 02/20/2019 03/06/202001/10/20202020 $375,000 $139,934 725,000

206305 0.440 $168,053 $210,066 02/20/2019 03/06/202001/10/20202020 $0 $42,013 725,000

206546 2.372 $855 $950 02/07/202010/01/20192020 $95 $0 1,825,000

206546 2.372 $311,220 $345,800 02/07/202001/06/20202020 $34,580 $0 1,825,000

206547 3.756 $855 $950 04/03/202010/01/20192020 $95 $0 455,000

206547 3.756 $76,950 $85,500 04/03/202003/02/20202020 $8,550 $0 455,000

206566 2.495 $4,658,771 $5,691,840 02/07/202012/13/20192020 $1,033,069 $0 6,200,040

206648 0.000 $340,000 $425,000 07/02/20212021 $85,000 $0 1,250,000

206648 0.000 $660,000 $825,000 07/02/20212021 $165,000 $0 1,250,000

206651 0.000 $1,700,000 $14,900,000 07/02/20212021 $5,200,000 $8,000,000 14,900,000

206652 0.000 $119,000 $148,750 07/02/20212021 $29,750 $0 437,500

206652 0.000 $231,000 $288,750 07/02/20212021 $57,750 $0 437,500

Fiscal Year(s) : 2020, 2021, 2022, 2023 Page:

Date:

S/TIP Cycle

Job Type PhaseStatus

MPO/RuralApproval

Date

ProjectName

Job # ActualLet Date

Schedule Let Date

ActualObligation

Date

ScheduleObligation

Date

FederalAmendment

Type

County Length Fund Source

FiscalYear

ProjectDescription

Total Job Cost

FTAApproval

Date

S/TIP Status

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo HMA Mill and Resurface

CON 20-23 STU Phase Added

Sprinkle Rd Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Traffic Signal Interconnect

CON 20-23 STU Phase Added

W Mosel Ave Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Traffic Signal Interconnect

CON 20-23 CMG Phase Added

W Mosel Ave Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo HMA Mill and Resurface

CON 20-23 STU Phase Added

Barney Rd Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo HMA Mill and Resurface

CON 20-23 STU Phase Added

Lovers Ln Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Roadside Facility

CON 17-20 TAU Phase Added

Stadium Ave Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo Van Replacement

NI 20-23 STUTransit capital Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo HMA Mill and Resurface

CON 17-20 EDF Phase Added

S Westnedge Ave

Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo HMA Mill and Resurface

CON 17-20 STU Phase Added

S Westnedge Ave

Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Longitudinal pavement marking application on trunklines in Southwest Region

PE 17-20 HSIP Phase Added

Southwest Regionwide Longitudinal Pavement Marking

Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Longitudinal pavement marking application on trunklines in Southwest Region

CON 17-20 HSIP Phase Added

Southwest Regionwide Longitudinal Pavement Marking

Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Special pavement marking application on trunklines in Southwest Region

PE 17-20 HSIP Phase Added

Southwest Regionwide Special Pavement Markings

Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Special pavement marking application on trunklines in Southwest Region

CON 17-20 HSIP Phase Added

Southwest Regionwide Special Pavement Markings

Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Road and Bridge Reconstruction

CON 17-20 NH Phase Added

I-94 W Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5307 Capital NI 20-23 5307 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5307 Capital NI 20-23 5307 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5307 Operating NI 20-23 5307 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5339 Capital NI 20-23 5339 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5339 Capital NI 20-23 5339 Phase Added

N Rose St Programmed PendingN/A

Local Estimated

Amount

PrimaryWork Type

PhaseMPO ResponsibleAgency

FHWAApproval

Date

CommentsLimits

Kalamazoo County

Road Rehabilitation

Sprinkle Rd

Kalamazoo County

Traffic SafetyMosel Avenue

Kalamazoo County

Traffic SafetyMosel Avenue

Kalamazoo County

Road Rehabilitation

Barney Rd

Portage Road Rehabilitation

Lovers Lane

Kalamazoo County

New FacilitiesStadium Drive- Non Motorized

Kalamazoo Central County Transportation Authority

SP1105-van replacement, any size with or without lift

Kalamazoo Metro Transit

Portage Road Rehabilitation

South Westnedge Avenue

Portage Road Rehabilitation

South Westnedge Avenue

MDOT Traffic SafetyAll of KATS MPO

MDOT Traffic SafetyAll of KATS MPO

MDOT Traffic SafetyAll of KATS MPO

MDOT Traffic SafetyAll of KATS MPO

MDOT Major WideningEast of Lovers Lane to west of Sprinkle Road

Kalamazoo Central County Transportation Authority

SP1203-admin/maintenance facility improvements

Metro Transit

Kalamazoo Central County Transportation Authority

SP1103-35-39 foot replacement bus with or without lift

Metro Transit

Kalamazoo Central County Transportation Authority

SP3000-operating except JARC and New Freedom

Metro Transit

Kalamazoo Central County Transportation Authority

SP1203-admin/maintenance facility improvements

Metro Transit

Kalamazoo Central County Transportation Authority

SP1103-35-39 foot replacement bus with or without lift

Metro Transit

ACCYear(s)

AC/ACC

DRAFT KATS Transportation Improvement Program Projects

Meeting Materials Page 15 of 83

Page 16: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Total Estimated

Amount

Fed Estimated

Amount

State Estimated

Amount

03/06/2019

6 of 9

206653 0.000 $39,200 $49,000 07/02/20212021 $9,800 $0 245,000

206653 0.000 $156,800 $196,000 07/02/20212021 $39,200 $0 245,000

206654 0.000 $30,400 $38,000 07/02/20212021 $7,600 $0 38,000

206656 0.000 $1,700,000 $14,900,000 07/01/20222022 $5,200,000 $8,000,000 14,900,000

206657 0.000 $1,700,000 $14,900,000 07/03/20232023 $5,200,000 $8,000,000 14,900,000

206662 0.000 $340,000 $425,000 07/01/20222022 $85,000 $0 1,250,000

206662 0.000 $660,000 $825,000 07/01/20222022 $165,000 $0 1,250,000

206663 0.000 $340,000 $425,000 07/03/20232023 $85,000 $0 1,250,000

206663 0.000 $660,000 $825,000 07/03/20232023 $165,000 $0 1,250,000

206665 0.000 $121,312 $151,640 07/01/20222022 $30,328 $0 446,000

206665 0.000 $235,488 $294,360 07/01/20222022 $58,872 $0 446,000

206666 0.000 $123,760 $154,700 07/03/20232023 $30,940 $0 455,000

206666 0.000 $240,240 $300,300 07/03/20232023 $60,060 $0 455,000

206669 0.000 $40,000 $50,000 07/01/20222022 $10,000 $0 250,000

206669 0.000 $160,000 $200,000 07/01/20222022 $40,000 $0 250,000

206672 0.000 $30,400 $38,000 07/01/20222022 $7,600 $0 38,000

206673 0.000 $160,000 $200,000 07/03/20232023 $40,000 $0 255,000

206673 0.000 $44,000 $55,000 07/03/20232023 $11,000 $0 255,000

Fiscal Year(s) : 2020, 2021, 2022, 2023 Page:

Date:

S/TIP Cycle

Job Type PhaseStatus

MPO/RuralApproval

Date

ProjectName

Job # ActualLet Date

Schedule Let Date

ActualObligation

Date

ScheduleObligation

Date

FederalAmendment

Type

County Length Fund Source

FiscalYear

ProjectDescription

Total Job Cost

FTAApproval

Date

S/TIP Status

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5310 Capital NI 20-23 5310 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5310 Capital NI 20-23 5310 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5311 Operating NI 20-23 5311 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5307 Operating NI 20-23 5307 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5307 Operating NI 20-23 5307 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5307 Capital NI 20-23 5307 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5307 Capital NI 20-23 5307 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5307 Capital NI 20-23 5307 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5307 Capital NI 20-23 5307 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5339 Capital NI 20-23 5339 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5339 Capital NI 20-23 5339 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5339 Capital NI 20-23 5339 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5339 Capital NI 20-23 5339 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5310 Capital NI 20-23 5310 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5310 Capital NI 20-23 5310 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5311 Operating NI 20-23 5311 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5310 Capital NI 20-23 5310 Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5310 Capital NI 20-23 5310 Phase Added

N Rose St Programmed PendingN/A

Local Estimated

Amount

PrimaryWork Type

PhaseMPO ResponsibleAgency

FHWAApproval

Date

CommentsLimits

Kalamazoo Central County Transportation Authority

SP1502-JARC mobility management

Metro Transit

Kalamazoo Central County Transportation Authority

SP1105-van replacement, any size with or without lift

Metro Transit

Kalamazoo Central County Transportation Authority

SP3000-operating except JARC and New Freedom

Metro Transit

Kalamazoo Central County Transportation Authority

SP3000-operating except JARC and New Freedom

Metro Transit

Kalamazoo Central County Transportation Authority

SP3000-operating except JARC and New Freedom

Metro Transit

Kalamazoo Central County Transportation Authority

SP1203-admin/maintenance facility improvements

Metro Transit

Kalamazoo Central County Transportation Authority

SP1103-35-39 foot replacement bus with or without lift

Metro Transit

Kalamazoo Central County Transportation Authority

SP1203-admin/maintenance facility improvements

Metro Transit

Kalamazoo Central County Transportation Authority

SP1103-35-39 foot replacement bus with or without lift

Metro Transit

Kalamazoo Central County Transportation Authority

SP1203-admin/maintenance facility improvements

Metro Transit

Kalamazoo Central County Transportation Authority

SP1103-35-39 foot replacement bus with or without lift

Metro Transit

Kalamazoo Central County Transportation Authority

SP1203-admin/maintenance facility improvements

Metro Transit

Kalamazoo Central County Transportation Authority

SP1103-35-39 foot replacement bus with or without lift

Metro Transit

Kalamazoo Central County Transportation Authority

SP1502-JARC mobility management

Metro Transit

Kalamazoo Central County Transportation Authority

SP1105-van replacement, any size with or without lift

Metro Transit

Kalamazoo Central County Transportation Authority

SP3000-operating except JARC and New Freedom

Metro Transit

Kalamazoo Central County Transportation Authority

SP1105-van replacement, any size with or without lift

Metro Transit

Kalamazoo Central County Transportation Authority

SP1502-JARC mobility management

Metro Transit

ACCYear(s)

AC/ACC

DRAFT KATS Transportation Improvement Program Projects

Meeting Materials Page 16 of 83

Page 17: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Total Estimated

Amount

Fed Estimated

Amount

State Estimated

Amount

03/06/2019

7 of 9

206675 0.000 $30,400 $38,000 07/03/20232023 $7,600 $0 38,000

207188 0.000 $247,500 $275,000 03/06/202001/10/20202020 $0 $27,500 275,000

207248 1.103 $495,000 $550,000 03/06/202001/10/20202020 $0 $55,000 550,000

207249 1.989 $299,700 $333,000 03/06/202001/10/20202020 $0 $33,300 333,000

207269 0.000 $55,299 $55,299 07/02/20212021 $0 $0 55,299

207271 0.000 $60,299 $60,299 07/01/20222022 $0 $0 60,299

207293 2.372 $1,710 $1,900 04/02/202110/01/20202021 $190 $0 2,090,000

207293 2.372 $355,680 $395,200 04/02/202103/05/20212021 $39,520 $0 2,090,000

207295 2.747 $1,710 $1,900 03/05/202110/01/20202021 $190 $0 370,000

207295 2.747 $61,560 $68,400 03/05/202102/05/20212021 $6,840 $0 370,000

207304 0.000 $30,000 $37,500 07/01/20202020 $7,500 $0 37,500

207313 1.389 $1,881 $2,090 12/01/20202021 $209 $0 11,000

207328 1.309 $1,710 $1,900 02/04/202210/01/20212022 $190 $0 2,140,000

207328 1.309 $364,230 $404,700 02/04/202201/07/20222022 $40,470 $0 2,140,000

Fiscal Year(s) : 2020, 2021, 2022, 2023 Page:

Date:

S/TIP Cycle

Job Type PhaseStatus

MPO/RuralApproval

Date

ProjectName

Job # ActualLet Date

Schedule Let Date

ActualObligation

Date

ScheduleObligation

Date

FederalAmendment

Type

County Length Fund Source

FiscalYear

ProjectDescription

Total Job Cost

FTAApproval

Date

S/TIP Status

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5311 Operating NI 20-23 5311 Phase Added

N Rose St Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Upgrade Stop and Stop Ahead signs

CON 17-20 HSIP Phase Added

Multiple Routes, Kalamazoo County

Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Construct center left turn lane, vertical curve modification, pave shoulder

CON 17-20 HRRR Phase Added

S Avenue Programmed PendingN/A

Local Kalamazoo Area Transportation Study (KATS)

Kalamazoo Construct paved shoulder, remove trees, upgrade guardrail, edgeline marking

CON 17-20 HRRR Phase Added

G Avenue Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo Vanpool Program

NI 20-23 CMG Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo Vanpool Program

NI 20-23 CMG Phase Added

N Rose St Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Longitudinal pavement marking application on trunklines in Southwest Region

PE 20-23 HSIP Phase Added

Southwest Regionwide Longitudinal Pavement Marking

Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Longitudinal pavement marking application on trunklines in Southwest Region

CON 20-23 HSIP Phase Added

Southwest Regionwide Longitudinal Pavement Marking

Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Special pavement marking application on trunklines in Southwest Region

PE 20-23 HSIP Phase Added

Southwest Regionwide Special Pavement Markings

Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Special pavement marking application on trunklines in Southwest Region

CON 20-23 HSIP Phase Added

Southwest Regionwide Special Pavement Markings

Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo 5311 Rural Operating

NI 17-20 5311 Phase Added

N Rose St Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Pvmt Marking Retroreflectivity Readings on trunklines in Southwest Region

CON 20-23 HSIP Phase Added

Southwest Regionwide Retroreflectivity Readings

Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Longitudinal pavement marking application on trunklines in Southwest Region

PE 20-23 HSIP Phase Added

Southwest Regionwide Longitudinal Pavement Marking

Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Longitudinal pavement marking application on trunklines in Southwest Region

CON 20-23 HSIP Phase Added

Southwest Regionwide Longitudinal Pavement Marking

Programmed PendingN/A

Local Estimated

Amount

PrimaryWork Type

PhaseMPO ResponsibleAgency

FHWAApproval

Date

CommentsLimits

Kalamazoo Central County Transportation Authority

SP3000-operating except JARC and New Freedom

Metro Transit

Kalamazoo County

Traffic SafetyMultiple Routes, Various Locations, Kalamazoo County

Kalamazoo County

Traffic SafetyS Avenue from west of 34th Street to 36th Street, Kalamazoo County

Kalamazoo County

Traffic SafetyG Avenue from 2nd Street to 6th Street, Kalamazoo County

Kalamazoo Central County Transportation Authority

SP1110-van expansion, any size with or without lift

Metro Transit

Kalamazoo Central County Transportation Authority

SP1110-van expansion, any size with or without lift

Metro Transit

MDOT Traffic SafetyAll of KATS MPO

MDOT Traffic SafetyAll of KATS MPO

MDOT Traffic SafetyAll of KATS MPO

MDOT Traffic SafetyAll of KATS MPO

Kalamazoo Central County Transportation Authority

SP3000-operating except JARC and New Freedom

Metro Transit

MDOT Traffic SafetyAll of KATS MPO

MDOT Traffic SafetyAll of KATS MPO

MDOT Traffic SafetyAll of KATS MPO

ACCYear(s)

AC/ACC

DRAFT KATS Transportation Improvement Program Projects

Meeting Materials Page 17 of 83

Page 18: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Total Estimated

Amount

Fed Estimated

Amount

State Estimated

Amount

03/06/2019

8 of 9

207329 2.829 $1,710 $1,900 04/01/202210/01/20212022 $190 $0 470,000

207329 2.829 $78,660 $87,400 04/01/202203/04/20222022 $8,740 $0 470,000

207341 1.645 $1,881 $2,090 12/01/20212022 $209 $0 11,000

207365 0.978 $1,710 $1,900 03/03/202310/03/20222023 $190 $0 2,140,000

207365 0.978 $364,230 $404,700 03/03/202302/03/20232023 $40,470 $0 2,140,000

207367 1.191 $1,710 $1,900 02/03/202310/03/20222023 $190 $0 570,000

207367 1.191 $95,760 $106,400 02/03/202301/06/20232023 $10,640 $0 570,000

207378 1.721 $1,881 $2,090 12/01/20222023 $209 $0 11,000

207433 0.000 $20,325 $24,786 12/02/202210/01/20212022 $4,461 $0 411,723

207433 0.000 $98,833 $120,528 12/02/202210/07/20222023 $21,695 $0 411,723

207497 0.000 $49,700 $62,125 10/01/20202021 $12,425 $0 62,125

207498 0.000 $87,000 $108,750 09/30/20212021 $21,750 $0 108,750

0.075 $389,964 $476,437 12/03/202110/08/20212022 $86,473 $0

0.459 $152,648 $169,609 02/03/202310/01/20202021 $14,841 $2,120

201111

201968

$154,716,256 $244,854,806$45,658,702

Fiscal Year(s) : 2020, 2021, 2022, 2023 Page:

Date:

S/TIP Cycle

Job Type PhaseStatus

MPO/RuralApproval

Date

ProjectName

Job # ActualLet Date

Schedule Let Date

ActualObligation

Date

ScheduleObligation

Date

FederalAmendment

Type

County Length Fund Source

FiscalYear

ProjectDescription

Total Job Cost

FTAApproval

Date

S/TIP Status

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Special pavement marking application on trunklines in Southwest Region

PE 20-23 HSIP Phase Added

Southwest Regionwide Special Pavement Markings

Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Special pavement marking application on trunklines in Southwest Region

CON 20-23 HSIP Phase Added

Southwest Regionwide Special Pavement Markings

Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Pavement mrkg retroreflectivity readings on trunklines in Southwest Region

CON 20-23 HSIP Phase Added

Southwest Regionwide Retroreflectivity Readings

Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Longitudinal pavement marking application on trunklines in Southwest Region

PE 20-23 HSIP Phase Added

Southwest Regionwide Longitudinal Pavement Mrkgs

Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Longitudinal pavement marking application on trunklines in Southwest Region

CON 20-23 HSIP Phase Added

Southwest Regionwide Longitudinal Pavement Mrkgs

Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Special pavement marking application on trunklines in Southwest Region

PE 20-23 HSIP Phase Added

Southwest Regionwide Special Pavement Markings

Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Special pavement marking application on trunklines in Southwest Region

CON 20-23 HSIP Phase Added

Southwest Regionwide Special Pavement Markings

Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Pvmt marking retroreflectivity readings on trunklines in Southwest Region

CON 20-23 HSIP Phase Added

Southwest Regionwide Retroreflectivity Readings

Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Install seventeen (17) CCTV cameras on existing DMS.

PE 20-23 NH Phase Added

I-94 E Programmed PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Install seventeen (17) CCTV cameras on existing DMS.

CON 20-23 NH Phase Added

I-94 E Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo Van Replacement

NI 20-23 STU Phase Added

N Rose St Programmed PendingN/A

Multi-Modal

Kalamazoo Area Transportation Study (KATS)

Kalamazoo Van Replacement

NI 20-23 STU Phase Added

Transit Capital Programmed PendingN/A

S/TIP Line items

Trunkline Traffic Operations And Safety

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Intersection Improvement, Add Center and right turn lanes

CON 20-23 CMM-331 Abandoned PendingN/A

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Intersection Improvements

PE 20-23 HSIPI-94BL W Abandoned PendingN/A

Local Estimated

Amount

$44,479,857

PrimaryWork Type

PhaseMPO ResponsibleAgency

FHWAApproval

Date

CommentsLimits

MDOT Traffic SafetyAll of KATS MPO

MDOT Traffic SafetyAll of KATS MPO

MDOT Traffic SafetyAll of KATS MPO

MDOT Traffic SafetyAll of KATS MPO

MDOT Traffic SafetyAll of KATS MPO

MDOT Traffic SafetyAll of KATS MPO

MDOT Traffic SafetyAll of KATS MPO

MDOT Traffic SafetyAll of KATS MPO

MDOT ITS Applications

I-94, US-131 Existing DMS

MDOT ITS Applications

I-94, US-131 Existing DMS

Kalamazoo Central County Transportation Authority

SP1105-van replacement, any size with or without lift

Metro Transit

Kalamazoo Central County Transportation Authority

SP1105-van replacement, any size with or without lift

Metro Transit

GPA Type Subtotals:

MDOT Traffic SafetyM-331 at the intersection of Whites Road

MDOT Traffic SafetyI-94BL, Michigan and Kalamazoo Avenue

ACCYear(s)

AC/ACC

DRAFT KATS Transportation Improvement Program Projects

Meeting Materials Page 18 of 83

Page 19: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Total Estimated

Amount

Fed Estimated

Amount

State Estimated

Amount

Total Jobs Reported:

Preferences:

TemplatesFinance System

Standard

2020, 2021, 2022, 2023

122

Approved, Pending

Trunkline - ALL, , Local - ALL, , Multi-Modal - ALL

03/06/2019

9 of 9

0.459 $666,389 $740,432 02/03/202312/09/20222023 $64,787 $9,256201968

$1,209,001 $1,386,478$166,101

$155,925,257 $246,241,284$45,824,803

ALL PROJECT SEARCH - STANDARD REPORT

Fiscal Year(s) : 2020, 2021, 2022, 2023 Page:

Date:

S/TIP Cycle

Job Type PhaseStatus

MPO/RuralApproval

Date

ProjectName

Job # ActualLet Date

Schedule Let Date

ActualObligation

Date

ScheduleObligation

Date

FederalAmendment

Type

County Length Fund Source

FiscalYear

ProjectDescription

Total Job Cost

FTAApproval

Date

S/TIP Status

Trunkline Kalamazoo Area Transportation Study (KATS)

Kalamazoo Intersection Improvements

CON 20-23 HSIPI-94BL W Abandoned PendingN/A

Trunkline Traffic Operations And Safety

Grand Total:

Report Format:

FISCAL Year(s):

MPO/Non-MPO: Kalamazoo Area Transportation Study (Kalamazoo)

County: ALL

Prosperity Region: ALL

MDOT Region: ALL

STIP Cycle: ALL

STIP Status:(A - Approved, P - Pending)

Job Type: Trunkline, Local, Multi-Modal

Phase Type: ALL

Phase Status ALL(AP - Programmed, AC - Active, CP - Completed)

(Active - Obligated)

Amendment Type ALLTrunkline - ALL, Local - ALL, Multi-Modal - ALL

Local Estimated

Amount

$11,376

$44,491,233

PrimaryWork Type

PhaseMPO ResponsibleAgency

FHWAApproval

Date

CommentsLimits

MDOT Traffic SafetyI-94BL, Michigan and Kalamazoo Avenue

GPA Type Subtotals:

ACCYear(s)

AC/ACC

Meeting Materials Page 19 of 83

Page 20: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Draft for Public Comment

Air Quality Conformity Analysis for

Kalamazoo – Battle Creek MI Conformity Area (Calhoun, Kalamazoo, Van Buren Counties)

January 22, 2019

Prepared by: Michigan Department of Transportation Statewide and Urban Travel Analysis Section Van Wagoner Transportation Building Lansing, MI 48909 [email protected] 517-335-4620 in cooperation with Battle Creek Area Transportation Study (BCATS) 601 Ave. A Springfield, MI 49037 269-963-1158 www.bcatsmpo.org and Kalamazoo Area Transportation Study (KATS) 5220 Lovers lane # 110 Portage, MI 49002 269-343-0766 www.katsmpo.org

Meeting Materials Page 20 of 83

Page 21: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

2 | P a g e Draft for public comment

Table of Contents 1.0 Conformity .......................................................................................................................... 4

1.1 Introduction ..................................................................................................................... 4

1.2 Conformity Area and Conformity .................................................................................... 4

1.3 Conformity Finding .......................................................................................................... 5

1.4 Results of Conformity Analysis ........................................................................................ 5

2.0 Background and Attainment Status .................................................................................... 6

2.1 Background ...................................................................................................................... 6

2.2 Attainment Status ........................................................................................................... 6

2.3 SIP Budgets ...................................................................................................................... 7

3.0 Interagency Consultation .................................................................................................... 7

4.0 Public Participation ............................................................................................................. 8

5.0 Modeled Project in Conformity Analysis ............................................................................ 8

6.0 Transportation Modeling .................................................................................................... 8

6.1 Travel Demand Forecasting Model ................................................................................. 8

6.1.2 BCATS Model ............................................................................................................ 8

6.1.3 KATS Model ............................................................................................................... 8

6.1.4 Statewide Model ....................................................................................................... 9

6.1.5 Coding Travel Demand Model Links for NFC by Urban and Rural ............................ 9

6.1.6 Highway Performance Monitoring System (HPMS) ................................................. 9

6.2 Analysis Years .................................................................................................................. 9

7.0 Latest Planning Assumptions ............................................................................................ 10

7.1 Demographic Data ......................................................................................................... 10

7.2 Vehicle Miles of Travel .................................................................................................. 10

7.3 Vehicle Hours of Travel ................................................................................................. 11

7.4 Transportation Control Measures ................................................................................. 12

8.0 Emission Modeling ............................................................................................................ 12

8.1 MOVES Specifications.................................................................................................... 12

8.2 Road Type Distribution .................................................................................................. 12

8.3 Average Speed ............................................................................................................... 12

8.4 Ramp Fraction ............................................................................................................... 12

8.5 Average Weekday VMT to Annual VMT ........................................................................ 12

Meeting Materials Page 21 of 83

Page 22: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

3 | P a g e Draft for public comment

8.6 Vehicle Population ........................................................................................................ 12

8.7 Vehicle Age Distribution ................................................................................................ 13

8.8 Other Local Data ............................................................................................................ 13

9.0 Conclusion ......................................................................................................................... 13

Appendix A: Meeting Summary of the Interagency Workgroups .......................................... 15

Appendix B: Public Comments and Responses ...................................................................... 32

Appendix C: Projects Included in Conformity Analysis ........................................................... 33

List of Tables: Table 1: Results of 1997 Ozone Standard Conformity Analysis .............................................. 5 Table 2: Base and Future Year Population and Employment by County .............................. 10 Table 3: Vehicle Miles of Travel and Growth Rate by County ............................................... 11 Table 4: Vehicle Hours of Travel by County ........................................................................... 11 Table 5: MOVES Source Types from SOS Body Style, Plate Type, and Company Code ......... 14

Meeting Materials Page 22 of 83

Page 23: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

4 | P a g e Draft for public comment

1.0 Conformity

1.1 Introduction

Transportation conformity provisions of the Clean Air Act Amendments require metropolitan planning organizations (MPOs) make a determination that the Long-Range Transportation Plan (LRTP), Transportation Improvement Program (TIP), and projects conform to the State Implementation Plan (SIP) and regional emissions will not negatively impact the region’s ability to meet the National Ambient Air Quality Standards (NAAQS).

Conformity to the SIP means that the region’s LRTPs and TIPs 1) will not cause any new violations of the NAAQS; 2) will not increase the frequency or severity of existing violation; and 3) will not delay attaining the NAAQS. A demonstration is conducted by comparing emissions estimates generated from implementation of LRTPs and TIPs for analysis years to the motor vehicle emissions budgets (MVEBs) contained in the maintenance SIP.

The purpose of this report is to document the process and findings of the transportation conformity analysis for the conformity area.

1.2 Conformity Area and Conformity

The conformity area consists of the three counties of Calhoun, Kalamazoo, and Van Buren. Within the boundary are the MPOs of the Battle Creek Area Transportation Study (BCATS) and the Kalamazoo Area Transportation Study (KATS), as well as, the rural projects contained in the State Transportation Improvement Program (STIP).

Findings of the transportation conformity analysis are for projects contained within:

• BCATS 2040 LRTP, • BCATS 2017-20 TIP, • KATS 2045 LRTP, • KATS 2017-20 TIP, and • STIP.

Meeting Materials Page 23 of 83

Page 24: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

5 | P a g e Draft for public comment

1.3 Conformity Finding

The staff of BCATS and KATS finds that the LRTPs and TIPs conform to the SIP for the 1997 ozone standard based on the results of this conformity analysis. This report makes the determination that the region’s transportation plan and programs satisfy all applicable criteria and procedures in the conformity regulations.

This conformity analysis document is subject to public comment period, for BCATS from Feb. 7 through Feb. 27, 2019 and for KATS from Feb. 5 through March 27, 2019. Comments received will be recognized, considered, and a response provided.

The MPOs policy committee will make a formal conformity determination, through a resolution, at the:

• BCATS Policy Committee on Feb. 27, 2019 • KATS Policy Committee on March 27, 2019.

1.4 Results of Conformity Analysis

Conformity is demonstrated when the analysis-year emissions are equal to or less than the SIP budget. For the 1997 ozone standard, as shown in Table 1, the emission results for the analysis years show that the volatile organic compounds (VOC) and nitrogen oxides (NOx) emissions are lower than the SIP budgets; thus, conformity for the ozone standard is demonstrated.

Table 1: Results of 1997 Ozone Standard Conformity Analysis

Analysis Year Emissions (tons/day)

VOC NOx SIP Budget 29.67 54.36

2020 6.99 10.75 2030 4.20 4.95 2040 2.95 3.19 2045 2.84 3.09

Meeting Materials Page 24 of 83

Page 25: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

6 | P a g e Draft for public comment

2.0 Background and Attainment Status

2.1 Background

The Federal Clean Air Act Amendments of 1990 (CAAA) established rules to improve the air, protect public health, and protect the environment. The act requires the U.S. Environmental Protection Agency (EPA) to set, review, and revise the National Ambient Air Quality Standards (NAAQS) periodically.

The Clean Air Act links together air quality planning and transportation planning through the transportation conformity process. Air quality planning is controlled by Michigan’s SIP, which includes the state’s plans for attaining or maintaining the NAAQS. The main transportation planning tools are the metropolitan LRTP and the metropolitan TIP. Transportation conformity ensures that federal funding and approval are given to highway and transit activities that are consistent with the SIP and that these activities will not affect Michigan’s ability to achieve the NAAQS.

Transportation activities that are subject to conformity are LRTPs, TIPs, and all non-exempt federal projects that receive Federal Highway Administration (FHWA) or Federal Transit Administration (FTA) funding or approval. The conformity process ensures emissions from LRTP, TIP, or projects are within acceptable levels specified within the SIP and meet the goals of the SIP.

Transportation conformity only applies to on-road sources and transportation-related pollutants: ozone, particulate matter (particulate sizes 2.5 and 10), nitrogen dioxide, and carbon monoxide.

In addition to emissions that are directly emitted, regulations specifically require certain precursor pollutants to be addressed. Precursor pollutants are those pollutants that contribute to the formation of other pollutants. For example, ozone is not directly emitted but created when NOx and VOC react with sunlight.

When the EPA revises a NAAQS, all areas of the country are evaluated to determine if monitored levels of the pollutant are at or below the standard; these areas are classified as attainment. If the pollutant level is above the standard, these areas are classified as nonattainment. MPOs in areas classified as nonattainment or maintenance must conduct conformity analysis on their transportation programs.

2.2 Attainment Status

On April 15, 2004, the EPA issued final designations of areas not attaining the 1997 ozone NAAQS (also referred to as 1997 ozone standard). The three counties Calhoun, Kalamazoo, and Van Buren were designated a nonattainment area. On May 16, 2007, the EPA redesignated the area attainment/maintenance, approving and finding adequate motor vehicle emissions budgets for VOC and NOx for the year 2018.

Meeting Materials Page 25 of 83

Page 26: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

7 | P a g e Draft for public comment

Placing the area into maintenance, this requires conformity emission to be compared to the motor vehicle emission budgets contained in the SIP, referred to as SIP budgets. On July 20, 2012, the EPA designated all of Michigan as attainment for the strengthened 2008 ozone NAAQS. On July 20, 2013, the EPA partially revoked the 1997 ozone standard, revoking the requirement to do transportation conformity for areas that were in maintenance. On April 6, 2015, the EPA completely revoked the 1997 ozone standard, which resulted in removal of all transportation conformity requirements. On Jan. 16, 2018, the EPA designated Calhoun County attainment for the strengthened 2015 ozone NAAQS (also referred to as 2015 ozone standard). Then on Aug. 3, 2018, Kalamazoo and Van Buren Counties were also designated. On April 23, 2018, the FHWA, complying with the court’s decision in South Coast Air Quality Management District v. EPA, started requiring areas in the country that were maintenance for the 1997 ozone standard and attainment for the 2008 ozone standard to conduct conformity. Later, this was amended to give MPOs until Feb. 16, 2019, to make conformity determinations.

2.3 SIP Budgets

The Kalamazoo – Battle Creek conformity area has existing maintenance budgets from the 1997 ozone standard maintenance SIP. Regulations require use of these budgets to test against for ozone standard. Emissions generated must be equal to or less than the SIP budgets, also referred to as the MVEB. MVEB is the portion of the total allowable emissions allocated to highway and transit vehicle use in the maintenance or nonattainment area. By showing emissions are below the MVEB, the LRTPs and TIP are conforming to the SIP.

3.0 Interagency Consultation

Consultation with federal, state, and local transportation authorities is conducted through the Michigan Transportation Conformity Interagency Workgroup (MITC-IAWG). Issues discussed include evaluating and choosing emission models and methods, determining regionally significant project definition, procedures for future MITC-IAWG meetings, and rules for reviewing projects.

An initial MITC-IAWG was held on Oct. 25, 2018, with a meeting to review projects held Dec. 17, 2018. Individuals attended in person or by conference call. Summaries of the meetings and all interagency consultation correspondence related to this conformity are in Appendix A. Copies of this conformity analysis were sent to each MITC-IAWG member to review and comment.

Meeting Materials Page 26 of 83

Page 27: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

8 | P a g e Draft for public comment

4.0 Public Participation

The Public Participation Plan adopted by the MPO Policy Committee establishes the procedures by which the MPOs reach affected public agencies and the public. The same procedures were followed for this document, ensuring the public has an opportunity to review and comment before the MPOs make a determination.

Formal public comment periods for the draft Air Quality Conformity Analysis will be held for BCATS from Feb. 7 through Feb. 27, 2019 and KATS from Feb. 5 through March 27, 2019. Public comments received and responses to those comments will be in Appendix B.

5.0 Modeled Project in Conformity Analysis

All projects in the LRTPs, TIP, and amendments were evaluated for inclusion in the analysis. Projects classified as non-exempt must be analyzed. Projects with exempt classification that can be modeled with the travel demand model were modeled. Appendix C includes a complete list of the projects evaluated for, and included, in this analysis.

6.0 Transportation Modeling

6.1 Travel Demand Forecasting Model

Nonattainment areas are established independent of MPO boundaries. The conformity area is covered by three travel demand forecasting models: the BCATS model, the KATS model, and the statewide model covering the rural areas. Each of these models were developed in TransCAD modeling software and using the latest demographic and employment data available to generate estimates of travel, vehicle miles of travel (VMT), and speeds. Detailed documentation on each of these models is contained in separate documents available upon request.

6.1.2 BCATS Model

The BCATS model covers the greater Battle Creek and Springfield area. It was developed by MDOT and is a standard four-step model with a base year of 2010 and horizon year of 2040. Each of the four steps - trip generation, trip distribution, mode choice, and traffic assignment - are checked for reasonableness against national standards. Final model validation verifies that the assigned volumes replicate actual traffic counts. The decennial 2010 census and American Community Survey are the sources of population and household base data. Employment data is developed from a private business database verified with local knowledge. Future data is based on the Regional Economic Models, Inc. (REMI) economic and demographic forecasts. The University of Michigan and MDOT jointly develop county-specific forecast data.

6.1.3 KATS Model

This model is a regional model developed by a consultant and covers all of Kalamazoo County and four townships in Van Buren County. It is a standard four-step model with time of day, a base year of 2010, and horizon year of 2045. Each of the four steps - trip generation, trip distribution, mode choice, and traffic assignment - are checked for reasonableness against

Meeting Materials Page 27 of 83

Page 28: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

9 | P a g e Draft for public comment

national standards. Final model validation verifies that the assigned volumes replicate actual traffic counts. The decennial 2010 census and American Community Survey are the sources of population and household base data. Employment data is developed from a private business database verified with local knowledge. Future data is based on the Regional Economic Models, Inc. (REMI) economic and demographic forecasts. The University of Michigan and MDOT jointly develop county-specific forecast data.

6.1.4 Statewide Model

The statewide model developed by MDOT covers all counties in the state and was used for the non-urban parts of Calhoun and Van Buren counties. The model is a standard three-step trip generation, trip distribution, and assignment model, with a base year 2010 and a 2045 future year. Trip assignment uses an equilibrium method and was validated against traffic counts using MDOT standards and those suggested by FHWA.

6.1.5 Coding Travel Demand Model Links for NFC by Urban and Rural

For emission modeling, the National Functional Classification (NFC) system is used to determine the function of roads; however, NFCs after 2010 do not distinguish roads by urban and rural. The emission model, Motor Vehicle Emission Simulator (MOVES), requires roads to be classified as urban or rural. MOVES requires roads to be grouped into one of four road types: rural restricted, rural unrestricted, urban restricted, and urban unrestricted. To determine a road’s urban or rural status, roads within the adjusted census urban boundary were considered urban and those outside as rural. NFCs designated as interstate and other freeways are considered restricted while all others are considered unrestricted. The Michigan Geographic Framework (GIS digital base map) was used to combine NFC with adjusted census urban boundary to generate MOVES road types for the network.

6.1.6 Highway Performance Monitoring System (HPMS)

The EPA and FHWA endorse HPMS as the source of VMT estimates. The travel demand modeling VMT is aggregated by NFC road types for the county then normalized to HPMS data for the base year/validation year of the travel demand model. Normalization factors were applied to all analysis years.

6.2 Analysis Years

Analysis years were determined by the MITC-IAWG. Projects requiring modeling are grouped into an analysis year based on the project’s open to traffic date. Emissions are generated for each analysis year.

Analysis Year Reason 2020 Interim year (so analysis years not more than 10 years apart) 2030 Interim year (so analysis years not more than 10 years apart) 2040 Last year of BCATS long-range transportation plan 2045 Last year of KATS long-range transportation plan

Meeting Materials Page 28 of 83

Page 29: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

10 | P a g e Draft for public comment

7.0 Latest Planning Assumptions

7.1 Demographic Data

The most current and future assumptions developed or approved by the MPO were used in the development of the travel demand models. Table 2 shows base and future year population and employment by county from the travel demand models.

Table 2: Base and Future Year Population and Employment by County

County Population

Employment

2010 2045 2010 2045

Calhoun County 136,146 139,112 71,209 79,977

Kalamazoo County 250,31 287,703 140,638 164,778

Van Buren County 76,258 80,600 27,162 32,865

7.2 Vehicle Miles of Travel

Vehicle miles of travel (VMT) is one measure of the travel. Current and future levels of travel and growth rates are provided in Table 3.

Meeting Materials Page 29 of 83

Page 30: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

11 | P a g e Draft for public comment

Table 3: Vehicle Miles of Travel and Growth Rate by County

Analysis year

Calhoun County Base Year 2010 2020 2030 2040 2045

VMT 4,461,576 4,593,118 4,715,936 4,822,116 4,835,786

Growth Rate 1.000 1.029 1.057 1.081 1.084

Analysis year

Kalamazoo County Base Year 2010 2020 2030 2040 2045

VMT 6,512,223 7,148,254 7,624,681 7,863,566 7,944,368

Growth Rate 1.000 1.098 1.171 1.208 1.220

Analysis year

Van Buren County Base Year 2010 2020 2030 2040 2045

VMT 2,714,319 2,936,468 3,057,865 3,097,750 3,112,388

Growth Rate 1.000 1.082 1.127 1.141 1.147

7.3 Vehicle Hours of Travel

Vehicle hours of travel (VHT) is an indicator of congestion. Current and future levels are provided in Table 4.

Table 4: Vehicle Hours of Travel by County

Analysis year

Calhoun County Base Year 2010 2020 2030 2040 2045

VHT 97,523 100,338 102,925 105,180 105,571 Analysis year

Kalamazoo County Base Year 2010 2020 2030 2040 2045

VHT 176,614 199,399 216,568 225,951 229,703 Analysis year

Van Buren County Base Year 2010 2020 2030 2040 2045

VHT 55,152 60,079 63,351 64,530 65,034

Meeting Materials Page 30 of 83

Page 31: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

12 | P a g e Draft for public comment

7.4 Transportation Control Measures

There are no transportation control measures (TCMs) identified in the applicable state implementation plan. Thus, no measures are included at this time.

8.0 Emission Modeling

8.1 MOVES Specifications

The EPA’s MOVES version MOVES2014b was used to generate emissions. Ozone is formed in the presence of heat and sunlight, so the highest ozone concentrations are monitored during the summer. This conformity analysis involves generating a summer (July) weekday emissions to simulate the meteorology of a high-ozone summer day.

8.2 Road Type Distribution

HPMS data is used to create MOVES road-type distribution fractions. County-level HPMS passenger data is used for motorcycle and passenger vehicles, and commercial HPMS is used for trucks and buses. HPMS VMT is aggregated to MOVES road types then converted to a fraction, generating a road-type distribution.

8.3 Average Speed

Speed distributions are created using a method developed by EPA for taking a single average speed and creating a distribution. The method generates an average speed fraction by MOVES road type, by day, by hour, and speed bin from speeds generated by the travel demand forecasting models. The same distribution is used for each vehicle type.

8.4 Ramp Fraction

The default vehicle hours traveled ramp fraction of 8 percent was used.

8.5 Average Weekday VMT to Annual VMT

Monthly VMT adjustment factors were obtained from MDOT’s data collection area. The EPA's AADVT Converter-Tool MOVES 2014 was used to convert annual average daily VMT to annual VMT, monthly VMT fractions, and daily VMT fractions. Hourly fractions use MOVES default data. For motorcycles, the monthly fractions use MOVES defaults since local data is limited. Future analysis years utilize the same fractions.

8.6 Vehicle Population

The source of the vehicle population is the Michigan Secretary of State (SOS) vehicle registration database of 2012. The database was supplemented with school bus data from the Michigan Department of Education and MDOT public transit bus data. The EPA's default

Meeting Materials Page 31 of 83

Page 32: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

13 | P a g e Draft for public comment

distributions were used to determine intercity bus, refuse truck, single-unit truck, and combination truck categories. The SOS data must be converted to MOVES source (vehicle) types. Table 5 shows how vehicle body style combined with plate type and company code is used to obtain MOVES vehicle types.

Future year vehicle population is based on growth in VMT from base year to analysis year. Growth rate is applied to all MOVES vehicle types. Table 3 shows the VMT for each analysis year and growth rate.

8.7 Vehicle Age Distribution

MOVES requires vehicle age as one of the local data inputs. The Michigan SOS vehicle registration database of 2012 was the source of vehicle ages. Vehicles are assigned to an age group, from 0 to 30-plus, based on model year indicated in the SOS database, with 0 being the newest vehicles (2012 or newer) and each year is its own group until vehicles are 30 years and older, which are aggregated into the 30-plus group. The SOS database is sorted by MOVES vehicle types and age. For intercity buses, refuse trucks, single-unit trucks, and combination trucks, the EPA’s default age distribution are used to calculate splits in population because of limited numbers. Base-year age distribution fractions were used for all future years.

8.8 Other Local Data

The MOVES model allows input for other types of local data, if available. This conformity demonstration used default meteorology data since the budgets were developed using default data; thus, analysis should also. Lacking local data, defaults were used for hoteling (truck parking) and starts. The default fuel data is correct for Michigan.

9.0 Conclusion

Conformity has a two-step approval process. The MPOs must make a formal conformity determination through a resolution that the findings of this conformity analysis conform to the SIP; thus, emissions are at or below the budgets found in the SIP. Then FHWA, jointly with the FTA, after consultation with the EPA, issues a letter of concurrence with the determination.

The conformity analysis described here and conducted by MDOT, with support of BCATS and KATS, concludes that the BCATS 2040 LRTP and 2017-20 TIP, KATS 2045 LRTP and 2017-20 TIP, and the rural projects meet all applicable requirements for conformity for the 1997 ozone standard; thus, it is recommended for approval by FHWA.

Meeting Materials Page 32 of 83

Page 33: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

14 | P a g e Draft for public comment

Table 5: MOVES Source Types from SOS Body Style, Plate Type, and Company Code MOVES Source Type SOS Body Style, Plate Type, and Company code

11 – Motorcycles Motorcycles 21 – Passenger Cars Two-Door

Four-Door Convertible Roadster Low-Speed

31 – Passenger Trucks Station Wagon Pickup Van Hearse with Plate Type, Personal Ambulance with Plate Type, Personal Panel Van with Plate Type, Personal

32 – Light Commercial Trucks 40 – Buses (MOVES: 41*, 42, 43) 50 – Single-Unit Trucks* (MOVES: 51, 52, 53) 54 – Motorhomes

60 – Combination Trucks* (MOVES: 61, 62)

Pickup Commercial or Company Van Commercial or Company Hearse Commercial or Company Ambulance Commercial or Company Panel Van Commercial or Company Utility Truck Wrecker Bus; Supplemented with Other Data Sources Dump Truck Mixer Truck Stake Truck Motorhome Tractor Trailer Tanker

* The EPA default age distribution is applied to calculate individual MOVES Source Type categories.

Meeting Materials Page 33 of 83

Page 34: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

15 | P a g e Draft for public comment

Appendix A: Meeting Summary of the Interagency WorkgroupsSummary of Meeting

Michigan Transportation Conformity Interagency Workgroup (MITC- IAWG) Kalamazoo- Battle Creek Conformity Area

10 a.m. - Noon (EDT), Thursday, Oct. 25, 2018 MDOT Kalamazoo Transportation Service Center, 5372 S 9th St., Kalamazoo, MI 49009

Conference number and web link information provided in e-mail

Name Agency In attendance: Andrea Dewey Federal Highway Administration (FHWA) Breanna Bukowski Michigan Department of Environmental Quality (MDEQ) Kaitlyn Leffert MDEQ Michael Leslie US Environmental Protection Agency (EPA) Susan Weber Federal Transit Administration (FTA) Pat Karr Battle Creek MPO Andy Tilma Battle Creek MPO Jon Start Kalamazoo MPO Steve Stepek Kalamazoo MPO Megan Mickelson Kalamazoo MPO Donna Wittl Michigan Department of Transportation (MDOT) Jeff Franklin MDOT David Fairchild MDOT Ryan Gladding MDOT Amy Lipset MDOT Brian Sanada MDOT Absent: Angelica Salgado FTA Eric Mullen MDOT

Attendance at the meeting was in person or teleconferencing with web linking.

Materials distributed before the meeting:

1) Agenda 2) Exempt Project Excerpt from EPA Transportation Conformity Regulations – April 2012 3) 2016 Memorandum of Agreement Regarding Determination of Conformity of Transportation

Plans, Programs, and Projects to State Implementation Plans 4) PM Hot-spot Analyses: FAQs 5) Link to information on Road Diets (agenda topic): https://safety.fhwa.dot.gov/road_diets/

Meeting Materials Page 34 of 83

Page 35: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

16 | P a g e Draft for public comment

6) Link to conformity training: https://www.fhwa.dot.gov/Environment/air_quality/conformity/training/sdtrain.cfm

The interagency work group meeting was facilitated by slides. The slides are provided with a summary of discussion related to slide below it. Some slides had no discussion.

It was emphasized this is a collaborative process and the group was encouraged to ask questions and have a discussion. The group is here to discuss the rules (maybe set them up), to evaluate the road projects in the LRTPs and TIPs and those projects in the rural area (outside the MPOs), to ensure emissions from on-road travel are consistent with the goals of the SIP. The question was asked if the name “Kalamazoo – Battle Creek” was the correct name for the conformity area. The federal register was checked when the area was designated as a 1997 ozone nonattainment area in 2004 and it is correct.

Meeting Materials Page 35 of 83

Page 36: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

17 | P a g e Draft for public comment

The Kalamazoo – Battle Creek conformity area is comprised of three counties; Calhoun, Kalamazoo, and Van Buren.

The group discussed the court case decisions. Status of the area is attainment but must do conformity for the reminder of the maintenance period which will be until 2027. It was stated that a conformity finding needs to be in place on Feb. 16, 2019 - that means an approval letter from FHWA. Next year’s new TIP will need to conform, too. It was offered to the Kalamazoo TMA, if they wanted, that MDOT would run the emission model for conformity until Sept. 30, 2019, to assist the MPOs in meeting the February 2019 date and getting through the new TIP development. Kalamazoo TMA said they would accept MDOT’s offer. It was stated that even though it is required to do conformity, the area is only considered a maintenance area for anti-backsliding. The status of the area is attainment, so the LRTP update cycle will stay five years. Discussed briefly was the travel demand model base and horizon year and the need for the MPOs to have the same years. Emissions are generated in the MOVES model at the county level. MPOs in the same county need to have the same base year. It is better to have the same base year in case the MPOs boundary expands into the next county and to limit the interim years required. MPOs in different counties, within the same conformity area, can have different base years but need to have the same interim years and horizon year.

Meeting Materials Page 36 of 83

Page 37: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

18 | P a g e Draft for public comment

Everyone indicated they had received a copy of the Transportations Conformity SIP MOA. It was asked why SEMCOG was the only MPO that signed. The answer was because SEMCOG was the only nonattainment or maintenance area at the time the document was signed. Since Battle Creek and Kalamazoo MPOs are in an attainment area, technically they don’t have to sign the document. But these are the rules we use in Michigan, so all IAWGs are following the same format and rules, and the majority are included in Transportation Conformity Rule. The Transportation Conformity SIP provides an easier way to understand the rules and process.

There was discussion on what is being conformed. The LTRP with all the projects from the TIP are conformed together. This gives a base, so moving forward it will need to be seen if projects would change the conformity emissions. Any amendments after conformity analysis projects are assembled will need to be reviewed by the IAWG. The question was asked whether the changes to the TIP could potentially change the conformity analysis. If all projects are exempt, then conformity analysis is still valid. Conformity will need to be done on existing LRTP and TIP, so conformity analysis will need to be in place for Feb. 16, 2019.

Meeting Materials Page 37 of 83

Page 38: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

19 | P a g e Draft for public comment

It was asked even though TMAs are generally responsible for running the travel demand model and emission model if MDOT would do it. MDOT will run the emission model through Sept. 30, 2019. The TMA will provide the travel demand model inputs needed for MOVES and MDOT will run MOVES.

Meeting Materials Page 38 of 83

Page 39: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

20 | P a g e Draft for public comment

One of the main functions of the IAWG is to evaluate projects for conformity analysis. The projects that form the LRTP and TIP are evaluated for conformity. We are doing regional conformity – conformity must be determined every four years. Conformity must be determined before federal approval or acceptance.

Non-federal projects only need to be included in regional conformity if determined to be regionally significant for air quality.

Meeting Materials Page 39 of 83

Page 40: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

21 | P a g e Draft for public comment

Projects that are 100 percent state or locally funded and do not require any federal approval are not required to be included in the conformity analysis unless determined to be regionally significant for air quality. The IAWG can make the definition more restrictive but not less. The group was not ready to decide the definition at this meeting. Regionally significant projects need to be modeled in a conformity analysis but won’t trigger a conformity analysis.

All projects need to be evaluated to determine if they need to be included in a conformity analysis. The evaluation is to determine if the project is exempt or nonexempt. If a project is classified as exempt it does not need to be included in the conformity analysis. One of the main tasks of the IAWG is to determine if a project is exempt; thus, the project does not need to be included in the conformity analysis. Table 2 shows projects that have a minor or limited impact on air quality. It is important to understand why a project is exempt.

Meeting Materials Page 40 of 83

Page 41: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

22 | P a g e Draft for public comment

There was a question on why transportation enhancement activities are exempt but rehabilitation is not. This will be clarified; it’s not an issue now but an MPO had a project like this in the past.

Meeting Materials Page 41 of 83

Page 42: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

23 | P a g e Draft for public comment

Table 3 includes projects that are exempt from regional conformity but not project-level, which is a more detailed analysis. We are doing regional analysis. These types of projects have local impacts on air quality and we are doing regional conformity.

Meeting Materials Page 42 of 83

Page 43: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

24 | P a g e Draft for public comment

As a project moves from design to build, its status as exempt can change.

Meeting Materials Page 43 of 83

Page 44: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

25 | P a g e Draft for public comment

The emissions generated from the conformity analysis must be equal or less than the budget or otherwise known as the MVEB. The MVEB is the portion of the total allowable emissions in the area allocated to highway and transit vehicles. By being below the SIP budget, the LRTP and TIP are conforming to the SIP. The budget is the combined emissions for all three counties; emissions are generated at the county level. The emission budget will stay the same until a second maintenance plan is developed. It was emphasized the conformity needs to be done on the current LRTPs and TIPs.

The question was asked if this administrative modification was based on the federal definition. FHWA was going to determine an answer to this. Because we are starting the process with some projects having already been determined to be part of an administrative modification list, all projects on that list should be evaluated for exempt or nonexempt status. Then, if an amendment is an administrative modification, it would be exempt. There was discussion about moving a project

Meeting Materials Page 44 of 83

Page 45: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

26 | P a g e Draft for public comment

within an analysis year group. If a project’s open-to-traffic date was 2032 and moved to 2034, this would not cause a new conformity analysis. But moving the project from 2034 to an open-to-traffic date of 2022 would cause a new conformity analysis because it is moving the project to a new analysis year group. The timeframe to do a conformity analysis was discussed, estimating it will take 60 days from IAWG meeting to start of public comment period. Once the process has been completed a few times it could be less but right now that is what MDOT is estimating.

All projects need to be presented to the IAWG. The question was asked if projects need to be sent to IAWG for review every time the MPO does an amendment. Yes, even if they are on the exempt list. It is the job of IAWG to determine a project’s status.

There was discussion on use of the public participation plan. Since they do not have conformity analysis specifically listed, the MPOs should use the requirements for the TIP and or LRTP.

IAWG designated contact:

Meeting Materials Page 45 of 83

Page 46: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

27 | P a g e Draft for public comment

DEQ contact: Breanna Bukowski Alternate contact: Kaitlyn Leffert FHWA contact: Andrea Dewey Alternate contact: If needed, Andrea will delegate EPA contact: Michael Leslie Alternate contact: None MDOT contact: Donna Wittl Alternate contact: to be determined FTA contact: Susan Weber Alternate contact: To be determined Battle Creek MPO: Andy Tilma Alternate contact: Pat Karr Kalamazoo MPO contact: To be determined Alternate contact: To be determined

It was discussed that Mark K. could send the STIP list or MPO could ask for the list; exact details to be determined. It was suggested that at least, at first, a response to the e-mail meeting would be required; this way we know people are receiving the e-mails.

Meeting Materials Page 46 of 83

Page 47: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

28 | P a g e Draft for public comment

Donna Wittl will send out an example of the conformity document.

Meeting Materials Page 47 of 83

Page 48: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

29 | P a g e Draft for public comment

Summary of Meeting Michigan Transportation Conformity Interagency Workgroup (MITC- IAWG)

Kalamazoo-Battle Creek Conformity Area

10:30 – 11 a.m. (EST), Monday, Dec. 17, 2018 TPS 3rd floor, Van Wagoner Transportation Building, Lansing, MI

Conference number and web link information provided in email Name Agency In attendance: Aaron Dawson Federal Highway Administration (FHWA) Breanna Bukowski Michigan Department of Environmental Quality (MDEQ) Michael Leslie Environmental Protection Agency (EPA) Susan Weber Federal Transit Administration (FTA) Pat Karr Battle Creek MPO Andy Tilma Battle Creek MPO Steve Stepek Kalamazoo MPO Jon Start Kalamazoo MPO Donna Wittl Michigan Department of Transportation (MDOT) Jeff Franklin MDOT David Fairchild MDOT Tyler Kent MDOT Rob Maffeo MDOT Ryan Gladding MDOT Brian Sanada MDOT

Attendance at the meeting was in person or teleconferencing with web linking. Agenda:

Meeting Materials Page 48 of 83

Page 49: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

30 | P a g e Draft for public comment

1) Review analysis years and model information. 2) Review project lists.

Project lists are color coded, with yellow being non-exempt projects, orange being exempt but might want to discuss, and blue are project that need more information for a decision to be made. Workbooks may have more than one worksheet.

3) Update on South Coast II court decision. Kalamazoo-Battle Creek MITC-IAWG reviewed and agreed with the analysis years. The group decided that since 2018 would be past once the analysis was conducted it would be not be used as an analysis year. Base year 2010 with analysis years of 2020, 2030, 2040 and 2045 would be used. The group discussed the project list. All the projects in the Battle Creek MPO area were determined to be exempt. The same was true for those projects in the STIP in Calhoun County. The project list from Kalamazoo MPO was discussed, including projects in Kalamazoo and Van Buren counties. Duplicate projects in the list were discussed and projects noted. It was stated that since a conformity analysis is being conducted, any project exempt or non-exempt that can be modeled with the travel demand model would be modeled. It was discussed that complete project descriptions would assist in determining project status of exempt versus non-exempt. Road diets were discussed. If a road diet is less than a mile could it be considered exempt? It could be but it would still need to be discussed by the IAWG, not an automatic exempt. FHWA would like further consideration of this and is waiting for more guidance from their headquarters on this topic. FHWA said that, with the prevalence of road diets in Michigan, they are concerned with not having more specific criteria. Michigan will have a statewide IAWG meeting on road diets to discuss these issues. The list of road projects from the STIP in Van Buren County was discussed. All projects are exempt. An update on the South Coast II court decision was provided and discussed. It was stated the EPA has released guidance on the requirements for the 1997 ozone areas. The guidance states what does not need to be done; areas do not need to run the emission model (MOVES) but need to do everything else, which includes IAWG to review projects, create a conformity document, and have a policy committee resolution. FHWA is coming out with a template on what a conformity document would be without analysis. As part of the court decision, areas need to have in place a second maintenance plan. DEQ is currently working on these plans. Most 1997 areas in Michigan, it appears, will qualify for a “limited maintenance plan.” Once these second maintenance plans are in place, the conformity process will significantly diminish. Based on the unstable environment of the court case, and that doing the emission analysis is not much more work given the stability it will provide, we are going to continue to do a traditional conformity analysis to meet the Feb. 16, 2019, due date from the court. The conformity process was discussed. Once the conformity analysis document is completed, it will

Meeting Materials Page 49 of 83

Page 50: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

31 | P a g e Draft for public comment

need to go out for public comment and then each of the MPO policy committees will need to make a formal resolution supporting the findings. The public comment process should be what the MPO has in their public involvement plan. If they don’t have a specific mention of air quality conformity analysis, they should use what is most appropriate. Future TIP amendments were discussed. All future TIP amendments need to be reviewed by the IAWG. IAWG meetings can be conducted by e-mail if all the projects are exempt. If an amendment contains a non-exempt project, a conference call IAWG will need to be held. A conference call can also be held even if all projects are exempt. It was asked for a list of IAWG contacts. The appointment for this meeting contains the list of contacts. One of the reasons a group list or blind copying is not used is so participants know the group.

Meeting Materials Page 50 of 83

Page 51: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

32 | P a g e Draft for public comment

Appendix B: Public Comments and Responses No comments received to date.

Meeting Materials Page 51 of 83

Page 52: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

33 | P a g e Draft for public comment

Appendix C: Projects Included in Conformity Analysis

The list of projects included in this analysis can be found here https://goo.gl/Ht5ooZ

Meeting Materials Page 52 of 83

Page 53: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined TIP/STIP Project Listing for Conformity

Fiscal Job # County Responsible Project Name Limits Length Primary Work Type Project Description Phas Total Budget Air Quality AQ comments 2018 133114 Kalamazoo Cass County

Transportation Authority

Transit CCTA service area 0.000 1140-Bus Support Equip / Facilities Facility improvements NI $19,000 Exempt

2018 133116 Kalamazoo Cass County Transportation

Authority

Transit CCTA service area 0.000 1140-Bus Support Equip / Facilities Maintenance equipment NI $7,000 Exempt

2018 204215 Kalamazoo Kalamazoo Area Transportation

Study

N Rose St Areawide 0.000 Operation Improvements FY2018 Areawide Rideshare NI $48,457 Exempt

2018 129068 Kalamazoo MDOT M-43 M-43 at G Avenue, Comstock Township, Kalamazoo Co.

0.688 Traffic Safety Construct Roundabout ROW $500,000 Exempt

2018 129071 Kalamazoo MDOT M-43 M-43 at 28th St, Comstock Township, Kalamazoo Co.

0.957 Traffic Safety Add Left turn Lanes and Intersection Realignment

ROW $120,000 Exempt

2018 130045 Van Buren MDOT I-94 I-94 EB and WB from MM44 to MM57. 14.556 Traffic Safety Tree clearing and wind screening CON $716,462 Exempt2018 130844 Kalamazoo Central County

Transportation Authority

Transit Capital Central County Transportation Authority 0.000 SP10-State Match urban Agency Vehicle Replacement NI $100,000 Exempt

2018 130847 Kalamazoo Central County Transportation

Authority

Rose St Central County Transportation Authority 0.000 SP10-State Match urban Agency ADA and bus shelter improvements NI $62,500 Exempt

2018 201444 Kalamazoo Central County Transportation

Authority

N Rose St Central County Transportation Authority/Kalamazoo County

0.000 SP05-Local Bus Operating Formula Budget NI $5,766,895 Exempt

2018 201444 Kalamazoo Central County Transportation

Authority

N Rose St Central County Transportation Authority/Kalamazoo County

0.000 SP05-Local Bus Operating Formula Budget NI $0 Exempt

2018 201518 Kalamazoo Central County Transportation

Authority

N Rose St Central County Transportation Authority/Kalamazoo County

0.000 SP05-Local Bus Operating Formula Budget NI $0 Exempt

2018 201518 Kalamazoo Central County Transportation

Authority

N Rose St Central County Transportation Authority/Kalamazoo County

0.000 SP05-Local Bus Operating Formula Budget NI $42,374 Exempt

2018 201596 Kalamazoo Central County Transportation

Authority

N Rose St Central County Transportation Authority/Kalamazoo County

0.000 SP09-Specialized Service Services for the elderly and individuals with disabilities.

NI $0 Exempt

2018 201596 Kalamazoo Central County Transportation

Authority

N Rose St Central County Transportation Authority/Kalamazoo County

0.000 SP09-Specialized Service Services for the elderly and individuals with disabilities.

NI $30,000 Exempt

2018 201764 Kalamazoo Central County Transportation

Authority

N Rose St Central County Transportation Authority/Kalamazoo County

0.000 3000-Operating Assistance Provide additional operating funds for public transportation services.

NI $13,211 Exempt

2018 202319 Kalamazoo Central County Transportation

Authority

N Rose St Central County Transportation Authority/Kalamazoo County

0.000 3000-Operating Assistance Operating assistance. NI $19,999 Exempt

2018 202728 Kalamazoo Central County Transportation

Authority

N Rose St Central County Transportation Authority 0.000 SP10-State Match urban Agency Buss purchase NI $114,000 Exempt

2018 202729 Kalamazoo Central County Transportation

Authority

N Rose St Central County Transportation Authority 0.000 SP10-State Match urban Agency Van Purchase NI $42,358 Exempt

Page 1 of 12

Meeting Materials Page 53 of 83

Page 54: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined TIP/STIP Project Listing for Conformity

Fiscal Job # County Responsible Project Name Limits Length Primary Work Type Project Description Phas Total Budget Air Quality AQ comments 2018 202933 Kalamazoo Central County

Transportation Authority

N Rose St Central County Transportation Authority/Kalamazoo County

0.000 SP10-State Match urban Agency Purchase vehicles and mobility management under the Section

5310 program.

NI $58,030 Exempt

2018 202935 Kalamazoo Central County Transportation

Authority

N Rose St Central County Transportation Authority/Kalamazoo County

0.000 SP10-State Match urban Agency Purchase vehicles under the FY14/15 Section 5307 local

program.

NI $19,405 Exempt

2018 202936 Kalamazoo Central County Transportation

Authority

N Rose St Central County Transportation Authority/Kalamazoo County

0.000 SP10-State Match urban Agency Purchase vehicles and security equip. and facility improvements.

NI $451,281 Exempt

2018 202938 Kalamazoo Central County Transportation

Authority

N Rose St Central County Transportation Authority/Kalamazoo County

0.000 SP10-State Match urban Agency Purchase vehicles, facility and office equipment under the Section

5307.

NI $166,560 Exempt

2018 202941 Kalamazoo Central County Transportation

Authority

N Rose St Central County Transportation Authority/Kalamazoo County

0.000 SP10-State Match urban Agency Purchase vehicles under the fY14/15 Section 5339 program.

NI $77,344 Exempt

2018 203851 Kalamazoo Central County Transportation

Authority

Transit operating Areawide 0.000 3000-Operating Assistance FY15 5311 Operating underpaid NI $3,444 Exempt

2018 204122 Kalamazoo Central County Transportation

Authority

Transit Operating areawide 0.000 3000-Operating Assistance FY 2018 Transit Operating NI $27,626 Exempt

2018 204152 Kalamazoo Central County Transportation

Authority

N Rose St Areawide/Central County Transp., Kalamazoo County

0.000 SP10-State Match urban Agency Purchase vehicles, bus and terminal/office equipment, and

facility rehab.

NI $2,432,799 Exempt

2018 204153 Kalamazoo Central County Transportation

Authority

Transit Capital Areawide/Central County Transp./Kalamazoo County

0.000 SP10-State Match urban Agency Purchase replacement buses. NI $298,451 Exempt

2018 202044 Kalamazoo Grand Trunk Western RR

E N Ave At Grand Trunk Western Railroad in Comstock Township, Kalamazoo County

0.000 Railroad install gates and interconnect with adjacent track

CON $462,488 Exempt

2018 123958 Kalamazoo Kalamazoo Howard St West Michigan and Howard, multiple intersections

5.281 Traffic Safety Signal interconnect CON $1,175,000 Exempt

2018 130825 Kalamazoo Kalamazoo Pitcher St E. Michigan Ave to E. Kalamazoo Ave 0.120 Road Rehabilitation Resurface CON $600,000 Exempt2018 131002 Kalamazoo Kalamazoo Howard Street Stadium Dr. to Oakland Dr. 0.490 Road Rehabilitation Cold Mill and resurface 3" CON $406,000 Exempt2018 204212 Kalamazoo Kalamazoo Central

County Transportation

Authority

Transit Capital Systemwide 0.000 SP10-State Match urban Agency Transit Capital NI $325,000

Exempt

2018 130822 Kalamazoo Kalamazoo County K L Ave 0.45 Mile West of Drake to Drake Road 0.499 Minor Widening Widen to three lanes/HMA overlay CON $750,000 Exempt

2018 200239 Kalamazoo Kalamazoo County W Q Avenue Q Avenue at 10th Street 0.108 Traffic Safety Signal modernization CON $250,000 Exempt2018 200262 Kalamazoo Kalamazoo County W KL Avenue KL Avenue between 1st Street and Almena

Drive0.359 Traffic Safety Intersection realignment CON $550,125 Exempt

2018 200457 Kalamazoo Kalamazoo County S 9th Street 9th Street at KL Avenue and at Quail Run Drive

0.291 Traffic Safety Signal modernization CON $187,254 Exempt

2018 200481 Kalamazoo Kalamazoo County S 42nd St 42nd Street from Z avenue to Y Avenue 1.005 Road Rehabilitation resurface CON $99,174 Exempt2018 200481 Kalamazoo Kalamazoo County S 42nd St 42nd Street from Z avenue to Y Avenue 1.005 Road Rehabilitation resurface CON $800,826 Exempt2018 202047 Kalamazoo Kalamazoo County S Drake Rd S. Drake Road, Green Meadow Rd. to West

Main Street (M-43), Oshtemo Twp0.833 Traffic Safety Construct S. Drake Road Sidewalk CON $585,807 Exempt

2018 202047 Kalamazoo Kalamazoo County S Drake Rd S. Drake Road, Green Meadow Rd. to West Main Street (M-43), Oshtemo Twp

0.833 Traffic Safety Construct S. Drake Road Sidewalk CON $109,957 Exempt

Page 2 of 12

Meeting Materials Page 54 of 83

Page 55: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined TIP/STIP Project Listing for Conformity

Fiscal Job # County Responsible Project Name Limits Length Primary Work Type Project Description Phas Total Budget Air Quality AQ comments 2018 120545 Kalamazoo MDOT M-96 at G avenue 0.220 Traffic Safety intersection improvements CON $185,000 Exempt2018 127443 Kalamazoo MDOT I-94 under 9th Street 0.000 Bridge Rehabilitation Railing Replacement CON $1,228,851 Exempt2018 127501 Kalamazoo MDOT I-94 EB at MM 83 and WB at MM 82, Comstock

Township1.198 Roadside Facilities - Improve Construct Emergency/Crash

Investigation SitesPE $111,800 Exempt

2018 129068 Kalamazoo MDOT M-43 M-43 at G Avenue, Comstock Township, Kalamazoo Co.

0.688 Traffic Safety Construct Roundabout PE $480,000 Exempt

2018 129576 Kalamazoo MDOT I-94 under ML Ave (Miller), I-94 BL EB, 35th St, and 38th St

0.000 Bridge CPM Full Pt, Bm Repr, Jt. Replc, Epoxy, Substr Repr, Dk Patching

CON $2,618,000 Exempt

2018 131571 Kalamazoo MDOT M-43 Kalamazoo County Line to US-131; M-40 in Gobles.

5.948 Road Capital Preventive Maintenance

Micro-Surfacing on M-43; Chip Seal & Fog Seal on M-40.

CON $1,093,409 Exempt

2018 132993 Kalamazoo MDOT M-96 West of 33rd Street, Comstock Township 0.411 Minor Widening Add turn lane, relocate non-motorized path

ROW $50,000 Exempt

2018 201157 Kalamazoo MDOT E Kilgore Rd Region-wide 0.000 Traffic Safety Pavement marking retroreflectivity readings and condition assessment

CON $7,750 Exempt

2018 201479 Kalamazoo MDOT E Kilgore Rd Region-wide 1.115 Traffic Safety Longitudinal pavement marking application

CON $367,135 Exempt

2018 201482 Kalamazoo MDOT E Kilgore Rd Region-wide 1.762 Traffic Safety Special pavement marking application

CON $412,870 Exempt

2018 202615 Kalamazoo MDOT Norfolk Southern Railway

At CP 140 and CP 142 on the Michigan Line 0.322 R000-Rail Turnout replacement NI $1,040,111 Exempt

2018 203101 Kalamazoo MDOT Freeway Interchange

Lighting Upgrades

I-94 @ Westnedge Interchange; I-194 @ Dickman Road Interchange

0.025 Operation Improvements Upgrade to LED Lights PE $3,928

Exempt

2018 130810 Kalamazoo Portage Westnedge Ave Mall Dr to Romence Rd 0.636 Road Capital Preventive Maintenance

Resurface CON $1,380,000 Exempt

2018 130811 Kalamazoo Portage Centre Avenue 12th Street to Oakland Drive 3.490 Reconstruction Mill and resurface CON $721,335 Exempt2018 130811 Kalamazoo Portage Centre Avenue 12th Street to Oakland Drive 3.490 Reconstruction Mill and resurface CON $1,278,665 Exempt2018 200461 Kalamazoo Portage Lakeview Drive Lakeview Drive at Portage Road 0.339 Traffic Safety Intersection relocation CON $413,410 Exempt2018 200462 Kalamazoo Portage Oakland Drive Oakland Drive at Vanderbilt Avenue 0.105 Traffic Safety Signal installation CON $40,000 Exempt2018 200709 St. Joseph MDOT M-60 Southwest Region 99.948 Road Capital Preventive

Maintenance2019 Calendar Year Crack Seal CON $625,404 Exempt

2018 132351 Van Buren Van Buren County 72nd Ave M40 to Nursery St. 0.338 Road Rehabilitation Resurfacing. CON $248,100 Exempt2018 132352 Van Buren Van Buren County CR 665 M40 south to 60th Ave. 0.163 Road Rehabilitation Mill and fill, trench and widen. CON $235,000 Exempt2018 133143 Van Buren Van Buren County County Road 653 CR 653 3.258 Road Capital Preventive

MaintenanceChip Seal and Fog Seal CON $99,823 Exempt

2018 132993 Kalamazoo MDOT M-96 West of 33rd Street, Comstock Township 0.411 Minor Widening Add turn lane, relocate non-motorized path

CON $614,372 Exempt

2018 201479 Kalamazoo MDOT E Kilgore Rd Region-wide 1.115 Traffic Safety Longitudinal pavement marking application

PE $1,000 Exempt

2018 201482 Kalamazoo MDOT E Kilgore Rd Region-wide 1.762 Traffic Safety Special pavement marking application

PE $4,085 Exempt

2018 202753 Kalamazoo Central County Transportation

Authority

N Rose St Kalamazoo Metro 0.000 1110-Bus Rolling Stock Bus Purchase NI $114,000 Exempt

2018 202754 Kalamazoo Central County Transportation

Authority

N Rose St kalmazoo metro transit 0.000 1110-Bus Rolling Stock van purchase NI $42,358 Exempt

Page 3 of 12

Meeting Materials Page 55 of 83

Page 56: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined TIP/STIP Project Listing for Conformity

Fiscal Job # County Responsible Project Name Limits Length Primary Work Type Project Description Phas Total Budget Air Quality AQ comments 2018 130069 Kalamazoo Central County

Transportation Authority

Transit Kalamazoo Metro Transit area 0.000 1110-Bus Rolling Stock Van Purchase NI $90,000 Exempt

2018 123955 Kalamazoo Kalamazoo Area Transportation

Study

Areawide Areawide 0.001 Operation Improvements Rideshare EPE $48,457 Exempt

2018 130071 Kalamazoo Kalamazoo County 38th Street O Ave to MN Ave 1.527 Road Rehabilitation Resurface CON $476,600 Exempt2018 119959 Kalamazoo MDOT Calhoun County Calhoun County 25.109 Traffic Safety Non-Freeway Signing Upgrade CON $325,000 Exempt2019 200366 Cass MDOT M-60 E Signal Corridors in Berrien, Cass, and

Kalamazoo Counties0.000 Traffic Safety Traffic Signal Modernizations;

connected vehicle installations.ROW $5,000 Exempt

2019 121685 Kalamazoo Central County Transportation

Authority

Rose St Travel Trainer - Kalamazoo Metro Transit 0.000 1170-Other Capital Items (Bus) Travel Trainer - Kalamazoo Metro Transit

NI $100,000 Exempt

2019 130079 Kalamazoo Central County Transportation

Authority

Transit Kalamazoo Metro Transit area 0.000 1110-Bus Rolling Stock Bus Replacement NI $105,000 Exempt

2019 130845 Kalamazoo Central County Transportation

Authority

Rose St Kalamazoo Metro Transit 0.000 1110-Bus Rolling Stock Vehicle Replacement NI $100,000 Exempt

2019 203132 Kalamazoo Central County Transportation

Authority

Transit Operating Areawide 0.000 SP10-State Match urban Agency Operating NI $4,768,000 Exempt

2019 127385 Kalamazoo Kalamazoo S Drake Road Drake Road from West Michigan to Greenmeadow

0.614 New Facilities Construction of a shared use path CON $785,000 Exempt

2019 130823 Kalamazoo Kalamazoo Portage St Stockbridge to Porter/Pitcher Con 0.764 Road Rehabilitation Resurface CON $850,000 Exempt2019 130823 Kalamazoo Kalamazoo Portage St Stockbridge to Porter/Pitcher Con 0.764 Road Rehabilitation Resurface CON $1,000,000 Exempt2019 131003 Kalamazoo Kalamazoo Cork St 500 west of Lovers Lane to Sprinkle Rd 1.925 Road Rehabilitation Cold mill and resurface, road diet,

ADACON $3,400,000 Exempt made one lane in

each direction2019 202248 Kalamazoo Kalamazoo Howard St Howard Street from Stadium Drive to W.

Michigan Avenue0.586 Roadside Facilities - Improve Roadside Facility CON $493,000 Exempt

2019 123956 Kalamazoo Kalamazoo Central County

Transportation Authority

Areawide Areawide 0.001 Operation Improvements Rideshare EPE $49,911

Exempt

2019 120246 Kalamazoo Kalamazoo County W D Ave Rolling Meadow Drive to Douglas Ave 1.716 Road Rehabilitation Resurface CON $644,303 Exempt2019 120246 Kalamazoo Kalamazoo County W D Ave Rolling Meadow Drive to Douglas Ave 1.716 Road Rehabilitation Resurface CON $85,697 Exempt2019 200393 Kalamazoo Kalamazoo County S 42nd St Z Ave to Y Ave 1.005 Road Rehabilitation Road Rehabilitation CON $900,000 Exempt2019 200865 Kalamazoo Kalamazoo County W D Avenue W D Avenue from 17th Street to Riverview

Drive2.448 Traffic Safety Widen paved shoulders and HMA

resurfacingCON $533,200 Exempt

2019 202037 Kalamazoo Kalamazoo County S Drake Rd S Drake Rd, Stadium Dr (I-94BL) to Michigan Ave, Oshtemo Township

0.388 New Facilities Construct S. Drake Road Shared-Use Pathway

CON $226,286 Exempt

2019 202857 Kalamazoo Kalamazoo County S 8th Street 8th Street from south of S Avenue to north of R Avenue, Kalamazoo County

0.639 Traffic Safety Construct center left turn lane CON $668,948 Exempt

2019 101089 Kalamazoo MDOT I-94 BL at Howard Street intersection 0.500 Minor Widening Reconstruct to install dual left turn lanes at the

CON $8,750,000 Exempt suspend

2019 113129 Kalamazoo MDOT I-94 BL East of Seneca to Howard 1.232 Road Rehabilitation Resurface roadway CON $1,904,000 Exempt2019 122664 Kalamazoo MDOT US-131 SB & NB Over Amtrak & KL Avenue 0.000 Bridge Replacement Bridge Replacement CON $11,300,000 Exempt

2019 201111 Kalamazoo MDOT M-331 M-331 at the intersection of Whites Road 0.075 Traffic Safety Intersection Improvement, Add Center and right turn lanes

PE $135,033 Exempt

Page 4 of 12

Meeting Materials Page 56 of 83

Page 57: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined TIP/STIP Project Listing for Conformity

Fiscal Job # County Responsible Project Name Limits Length Primary Work Type Project Description Phas Total Budget Air Quality AQ comments 2019 201111 Kalamazoo MDOT M-331 M-331 at the intersection of Whites Road 0.075 Traffic Safety Intersection Improvement, Add

Center and right turn lanesROW $100,000 Exempt

2019 202022 Kalamazoo MDOT E Kilgore Rd Various locations in the Southwest Region 0.000 Traffic Safety Delineator Job PE $10,000 Exempt2019 203025 Kalamazoo MDOT Southwest

Regionwide Special

Pavement Markings

Regionwide 0.000 Traffic Safety Application of special pavement markings

PE $2,500

Exempt

2019 203101 Kalamazoo MDOT Freeway Interchange

Lighting Upgrades

I-94 @ Westnedge Interchange; I-194 @ Dickman Road Interchange

0.025 Operation Improvements Upgrade to LED Lights CON $57,327

Exempt

2019 204725 Kalamazoo MDOT I-94 W/Westnedge

Ramp

I-94 @ Westnedge Interchange 0.622 Operation Improvements Install Ramp Lights CON $40,250 Exempt

2019 204725 Kalamazoo MDOT I-94 W/Westnedge

Ramp

I-94 @ Westnedge Interchange 0.622 Operation Improvements Install Ramp Lights PE $3,500 Exempt

2019 123959 Kalamazoo Portage S Westnedge Ave Multiple intersections, S. Westnedge and Shaver

0.729 Traffic Safety Signal interconnect, detection, modernization

CON $950,000 Exempt

2019 130809 Kalamazoo Portage Milham Ave Oakland Dr to S. Westnedge Ave 0.617 Road Rehabilitation Resurface CON $2,700,000 Exempt2019 130999 Kalamazoo Portage Romence Rd Oakland Dr. to Constitution Blvd 0.551 Road Rehabilitation HMA mill and resurface CON $522,000 Exempt2019 123961 Kalamazoo Van Buren County Countywide Van Buren County 0.000 Air Quality Improvement Purchase of new clean diesel plow

truckEPE $259,999 Exempt

2019 203754 Kalamazoo Vicksburg Vicksburg Trail - Phase 1 North

E. TU Ave and North St. 3.119 New Facilities New Non-Motorized Path CON $316,707 Exempt

2019 124035 Van Buren MDOT I-94 I-94 WB from Exit 46 to Exit 56 9.020 Traffic Safety Install Trees CON $266,761 Exempt2019 200632 Van Buren MDOT M-43 WCL of Bangor to M-40. 13.926 Road Capital Preventive

MaintenancePaver Placed Surface Seal with

spot HMA repairsCON $1,283,150 Exempt

2019 133222 Van Buren Van Buren County County Road 653 over West Branch Paw Paw River, Van Buren County

0.000 Bridge CPM Preventative Maintenance CON $93,000 Exempt

2019 133222 Van Buren Van Buren County County Road 653 over West Branch Paw Paw River, Van Buren County

0.000 Bridge CPM Preventative Maintenance CON $66,725 Exempt

2019 133222 Van Buren Van Buren County County Road 653 over West Branch Paw Paw River, Van Buren County

0.000 Bridge CPM Preventative Maintenance CON $50,000 Exempt

2019 133222 Van Buren Van Buren County County Road 653 over West Branch Paw Paw River, Van Buren County

0.000 Bridge CPM Preventative Maintenance CON $65,730 Exempt

2019 202934 Kalamazoo Central County Transportation

Authority

N Rose St Central County Transportation Authority/Kalamazoo County

0.000 SP10-State Match urban Agency Purchase vehicles and mobility management under the Section

5310 program.

NI $176,250 Exempt

2019 200633 Kalamazoo MDOT US-131 Milham Avenue to M-43. 5.724 Road Capital Preventive Maintenance

Mill and One Course Hot Mix Asphalt Overlay

CON $6,626,000 Exempt

2019 201974 Kalamazoo MDOT US-131 Exit 44, SW quadrant of interchange. 0.000 Roadside Facilities - Preserve Resurface existing carpool lot. CON $70,000 Exempt2019 201991 Kalamazoo MDOT E Kilgore Rd Various signalized intersections in the

Southwest Region0.000 Traffic Safety Dilemma zone detection at

signalized intersectionsPE $8,000 Exempt

2019 202704 Kalamazoo MDOT M-43 M-43 over Kalamazoo River, Kalamazoo County

0.000 Bridge CPM Joint Repl, Crack Sealer, Silane Waterproof Deck, Sidewalk, Railing

surface

CON $432,000 Exempt

Page 5 of 12

Meeting Materials Page 57 of 83

Page 58: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined TIP/STIP Project Listing for Conformity

Fiscal Job # County Responsible Project Name Limits Length Primary Work Type Project Description Phas Total Budget Air Quality AQ comments 2019 203131 Kalamazoo Central County

Transportation Authority

Transit Operating Areawide 0.000 SP10-State Match urban Agency Operating NI $4,768,000 Exempt

2019 130081 Kalamazoo Kalamazoo County Ravine Road F Ave to D Ave 2.319 Road Rehabilitation Resurface CON $464,600 Exempt2019 200391 Kalamazoo Kalamazoo County E D Ave Westnedge to Riverview 3.002 Road Rehabilitation Resurfacing CON $730,000 Exempt2020 200366 Cass MDOT M-60 E Signal Corridors in Berrien, Cass, and

Kalamazoo Counties0.000 Traffic Safety Traffic Signal Modernizations;

connected vehicle installations.CON $428,080 Exempt

2020 130102 Kalamazoo Central County Transportation

Authority

Transit Kalamazoo Metro Transit area 0.000 1110-Bus Rolling Stock Van purchase NI $90,000 Exempt

2020 130846 Kalamazoo Central County Transportation

Authority

Rose St Kalamazoo Metro Transit 0.000 1110-Bus Rolling Stock Vehicle Replacement NI $100,000 Exempt

2020 131004 Kalamazoo Central County Transportation

Authority

Rose St Areawide Rideshare 0.001 Operation Improvements Community Rideshare Marketing PE $51,408 Exempt

2020 203137 Kalamazoo Central County Transportation

Authority

Transit Operating Areawide 0.000 SP10-State Match urban Agency Operating NI $4,768,000 Exempt

2020 131001 Kalamazoo Kalamazoo Oakland Dr Parkview Ave to Howard St 1.129 Road Rehabilitation Cold mill and resurface CON $1,060,000 Exempt2020 130143 Kalamazoo Kalamazoo County U Avenue 29th St to 32nd St 1.505 Road Rehabilitation Resurface CON $1,685,697 Exempt2020 130824 Kalamazoo Kalamazoo County Drake Rd KL to M-43 1.253 Road Capital Preventive

MaintenanceResurface CON $650,000 Exempt

2020 130824 Kalamazoo Kalamazoo County Drake Rd KL to M-43 1.253 Road Capital Preventive Maintenance

Resurface CON $850,000 Exempt

2020 131018 Kalamazoo Kalamazoo County Drake Rd W. Main St. to Parkview- 9 Signals 0.932 Traffic Safety Traffic Signal Optimization CON $1,089,000 Exempt2020 202433 Kalamazoo Kalamazoo County S 29th St 29th Street over Portage River, Str# 4625 0.000 Bridge CPM Capital Preventative Maintenance CON $109,000 Exempt2020 202434 Kalamazoo Kalamazoo County S 9th St Various Bridges, Capital Preventative

Maintenance0.000 Bridge CPM Capital Preventative Maintenance CON $100,000 Exempt

2020 202434 Kalamazoo Kalamazoo County S 9th St Various Bridges, Capital Preventative Maintenance

0.000 Bridge CPM Capital Preventative Maintenance CON $74,000 Exempt

2020 202434 Kalamazoo Kalamazoo County S 9th St Various Bridges, Capital Preventative Maintenance

0.000 Bridge CPM Capital Preventative Maintenance CON $53,000 Exempt

2020 105885 Kalamazoo MDOT I-94 East of Lovers Lane to East of Portage Road 1.248 Major Widening Road Reconstruction and Widen CON $50,997,840 nonexpmpt

2020 105886 Kalamazoo MDOT I-94 Portage Road to Sprinkle Road 1.182 Major Widening Road and Bridge Reconstruction CON $34,060,074 nonexempt2020 127501 Kalamazoo MDOT I-94 EB at MM 83 and WB at MM 82, Comstock

Township1.198 Roadside Facilities - Improve Construct Emergency/Crash

Investigation SitesCON $581,291 Exempt

2020 132617 Kalamazoo MDOT Stadium Dr between 11th Street and Academy Street, Kalamazoo

3.701 Traffic Safety Install Traffic Responsive Signal Technology

CON $1,600,000 Exempt

2020 202022 Kalamazoo MDOT E Kilgore Rd Various locations in the Southwest Region 0.000 Traffic Safety Delineator Job CON $403,479 Exempt2020 202651 Kalamazoo MDOT US-131 N Various in Kalmazoo County 68.189 Traffic Safety Non-freeway Signing PE $250,000 Exempt2020 203643 Kalamazoo MDOT I-94 W Van Buren/Kalamazoo County Line to Ninth

Street5.869 Road Capital Preventive

MaintenanceMill and One Course Hot Mix

Asphalt OverlayCON $5,148,965 Exempt

2020 130803 Kalamazoo Portage Shaver Rd W. Centre to S. Westnedge 0.181 Road Rehabilitation HMA mill and resurface CON $468,000 Exempt2020 130804 Kalamazoo Portage Westnedge Ave Shaver to Romence Rd 0.729 Road Rehabilitation Mill and resurface, ADA upgrades CON $1,425,000 Exempt2020 131000 Kalamazoo Portage Centre Ave Portage Rd to Sprinkle Rd 2.005 Road Rehabilitation HMA mill and resurface CON $1,271,000 Exempt2020 129837 Van Buren Van Buren County Red Arrow

Highway26th Street to 28th Street 1.274 Road Rehabilitation Mill of existing HMA 2 inches,

install fabric, repCON $841,887 Exempt

Page 6 of 12

Meeting Materials Page 58 of 83

Page 59: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined TIP/STIP Project Listing for Conformity

Fiscal Job # County Responsible Project Name Limits Length Primary Work Type Project Description Phas Total Budget Air Quality AQ comments 2020 129837 Van Buren Van Buren County Red Arrow

Highway26th Street to 28th Street 1.274 Road Rehabilitation Mill of existing HMA 2 inches,

install fabric, repCON $108,113 Exempt

2020 132931 Van Buren Van Buren County CR 653 Red Arrow Highway South to I - 94 0.458 Road Rehabilitation Resurfacing CON $510,000 Exempt

2018 203898 Calhoun Battle Creek 2018 City BC Crackfilling

Selected Fed-aid eligible roadways in City of Battle Creek 0.000 Road Capital Preventive

Maintenance Asphalt crackfilling CON $489 Exempt

2018 130178 Calhoun Battle Creek

2018 City BC Major

Resurfacings - Helmer,Kendall,+

Helmer Rd, Kendall St, Hamblin Ave, 24th St, & Gethings Rd 3.675 Road Rehabilitation Resurfacing CON $796,440 Exempt

2018 124463 Calhoun Battle Creek2018 City BC

Propane Conversions

BCATS MPO area 0.150 Air Quality Improvement Vehicle conversion to propane EPE $159,246 Exempt

2018 130179 Calhoun Battle Creek Capital Avenue Capital Avenue SW @ Jackson Street 0.001 Traffic Safety Intersection Signal Modernization CON $325,000 Exempt2018 122879 Calhoun Battle Creek Main St Mary St. to SCL and M-66 to Hamblin Ave. 0.606 Road Rehabilitation Resurface CON $194,000 Exempt2018 130180 Calhoun Battle Creek McCamly St VanBuren to North Ave 0.138 Road Rehabilitation Resurfacing CON $49,600 Exempt2018 200296 Calhoun Battle Creek River Road W River Road at Clark Road 0.039 Traffic Safety Signal installation CON $12,040 Exempt

2018 130181 Calhoun Battle Creek Roosevelt Ave East Ave to Garrison 0.377 Road Capital Preventive Maintenance Resurfacing CON $139,720 Exempt

2018 203298 CalhounBattle Creek Area

Transportation Study

Traffic Counting Equipment for Battle Crk MPO

Battle Crk MPO 0.000 Planning, Research & Design purchase traffic counting equipment for Battle Crk MPO NI $9,796 Exempt

2018 130038 Calhoun Calhoun County East Ave Roosevelt to Morgan 1.168 Road Rehabilitation Resurfacing CON $247,115 Exempt

2018 202745 Calhoun Calhoun County F Dr N F Dr N, 4315' W. of M-311 to M-311, Emmett Township, Calhoun County 0.817 Road Rehabilitation HMA Crush & Shape & Resurfacing CON $416,604 Exempt

2018 130177 Calhoun Calhoun County McAllister Rd Verona to N Dr N 1.348 Road Rehabilitation Resurfacing CON $357,500 Exempt

2018 202529 Calhoun Grand Trunk Western RR Capital Ave SW At Grand Trunk Western Railroad in the City

of Battle Creek, Calhoun County 0.000 Railroad install new crossing surface CON $300,895 Exempt

2018 202542 Calhoun Grand Trunk Western RR Elm St At Grand Trunk Western Railroad in the City

of Battle Creek, Calhoun County 0.000 Railroad install new crossing surface CON $241,649 Exempt

2018 202526 Calhoun Grand Trunk Western RR McAllister Rd At Grand Trunk Western Railroad in Pennfield

Township, Calhoun County 0.000 Railroad install new crossing surface CON $232,915 Exempt

2019 124463 Calhoun Battle Creek2018 City BC

Propane Conversions

BCATS MPO area 0.150 Air Quality Improvement Vehicle conversion to propane CON $159,246 Exempt

2019 130187 Calhoun Battle Creek

2019 City BC Major

Resurfacings - Elm,GlennCross,+

Elm,GlennCross,NorthAve,JacksonStringham,EmmettSt,Goodale,Lafayette,RiverRd 6.387 Road Rehabilitation Resurfacing CON $768,617 Exempt

2019 121059 Calhoun Battle Creek

Capital @ Michigan Intrsctn

Signal Modernization

Capital Ave @ Michigan Ave intersection in downtown Battle Creek 0.000 Traffic Safety Traffic signal modernization CON $325,000 Exempt

2019 130188 Calhoun Battle Creek Glenn Cross Rd Capital to M-66 0.832 Road Rehabilitation Resurfacing CON $260,580 Exempt

2019 202475 Calhoun Battle Creek Hill Brady Rd Hill Brady Rd, Skyline Dr. to M-96 (W. Dickman Rd), City of Battle Creek 2.128 Roadside Facilities - Improve Construct Hill Brady Shared Use

Trail CON $694,670 Exempt

2019 130189 Calhoun Battle Creek North Ave, City of BC Roosevelt to Coolidge 0.608 Road Capital Preventive

Maintenance Resurfacing CON $240,000 Exempt

Page 7 of 12

Meeting Materials Page 59 of 83

Page 60: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined TIP/STIP Project Listing for Conformity

Fiscal Job # County Responsible Project Name Limits Length Primary Work Type Project Description Phas Total Budget Air Quality AQ comments

2019 202889 Calhoun Calhoun County

Flashing Beacons (sign-mounted) at 3 Intersections

3 intersections 0.256 Traffic Safety Install sign-mounted flashing beacons on existing stop signs CON $45,581 Exempt

2019 130186 Calhoun Calhoun County North Ave, Pennfield Twp Halbert to county line 2.652 Road Rehabilitation Resurfacing CON $674,039 Exempt

2020 130194 Calhoun Battle Creek Capital Ave south city limits to Beckley 1.000 Road Rehabilitation Resurfacing CON $372,050 Exempt2020 120752 Calhoun Battle Creek Capital Ave NE at Van Buren St, city of Battle Creek 0.001 Traffic Safety Signal Modernization CON $0 Exempt2020 130195 Calhoun Battle Creek Kendall St Dickman to Michigan 0.434 Road Rehabilitation Resurfacing CON $168,600 Exempt2020 130196 Calhoun Battle Creek Union St Michigan to VanBuren 0.477 Road Rehabilitation Resurfacing CON $150,630 Exempt2020 130192 Calhoun Calhoun County N Dr Bellevue Rd to 12 Mile Rd 3.549 Road Rehabilitation Resurfacing CON $760,000 Exempt2020 131042 Calhoun Calhoun County Raymond Rd Cliff St @ Raymond Rd 0.006 Traffic Safety Intersection Signal Modernization CON $200,000 Exempt2020 130193 Calhoun Calhoun County Waubascon Rd Morgan to Halbert 2.009 Road Rehabilitation Resurfacing CON $490,000 Exempt

2018 124461 Calhoun Battle Creek Transit Areawide Battle Creek transit fixed-routes in Battle Creek 0.000 1110-Bus Rolling Stock Propane conversion/retrofit NI $15,000 Exempt

2018 203089 Calhoun Battle Creek Transit Battle Creek Transit BCT service area 0.000 3000-Operating Assistance Operating Assistance NI $3,447,048 Exempt

2018 201458 Calhoun Battle Creek Transit M-89 City of Battle Creek/Calhoun County 0.000 SP05-Local Bus Operating Formula Budget NI $1,452,141 Exempt

2018 201458 Calhoun Battle Creek Transit M-89 City of Battle Creek/Calhoun County 0.000 SP05-Local Bus Operating Formula Budget NI $0 Exempt

2018 201593 Calhoun Battle Creek Transit M-89 City of Battle Creek/Calhoun County 0.000 SP09-Specialized Service Services for the elderly and individuals with disabilities. NI $0 Exempt

2018 201593 Calhoun Battle Creek Transit M-89 City of Battle Creek/Calhoun County 0.000 SP09-Specialized Service Services for the elderly and individuals with disabilities. NI $92,624 Exempt

2018 204024 Calhoun Battle Creek Transit Transit Capital Areawide 0.000 SP02-Bus Capital Bus replacement NI $400,000 Exempt

2018 203985 Calhoun Battle Creek Transit

TRANSIT CAPITAL - BCT

Large Bus - FY18 100% State$

Large bus for use on BCT fixed-routes in Battle Crk urban area 0.000 1110-Bus Rolling Stock Purchase & acquisition of one large

bus for use on BCT fixed-routes NI $401,738 Exempt

2018 203077 Calhoun Battle Creek Transit Transit Capital Improvement Areawide 0.000 SP10-State Match urban Agency Bus purchase NI $120,000 Exempt

2018 203712 CalhounCommunity Action Agency of South Central MI, Inc

Transit Capital Areawide/Community Action Agency/Calhoun County 0.000 6410-5310 Projects Purchase replacement vans. NI $119,572 Exempt

2018 203079 CalhounCommunity Action Agency of South Central MI, Inc

Transit Capital Improvements Areawide 0.000 1110-Bus Rolling Stock Bus purchases NI $102,000 Exempt

2018 203086 CalhounCommunity

Inclusive Recreation, Inc.

Transit Capital Improvement Areawide 0.000 1110-Bus Rolling Stock Bus purchase NI $59,160 Exempt

2018 203728 Calhoun

Marian E. Burch Adult Care & Rehabilitation

Center

Transit Capital Areawide/Marian Burch Adult Day Care/Calhoun County 0.000 6410-5310 Projects Purchase one replacement van. NI $36,632 Exempt

Page 8 of 12

Meeting Materials Page 60 of 83

Page 61: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined TIP/STIP Project Listing for Conformity

Fiscal Job # County Responsible Project Name Limits Length Primary Work Type Project Description Phas Total Budget Air Quality AQ comments

2018 203087 Calhoun

Marian E. Burch Adult Care & Rehabilitation

Center

Transit Capital Improvement Areawide 0.000 1110-Bus Rolling Stock Bus purchase NI $44,001 Exempt

2019 124462 Calhoun Battle Creek Transit Areawide Battle Creek transit fixed-routes in Battle Creek 0.000 1110-Bus Rolling Stock Bus Replacement NI $272,346 Exempt

2019 204428 Calhoun Battle Creek Transit M-89 Areawide/Battle Creek/Calhoun County 0.000 SP09-Specialized Service Services for the elderly and individuals with disabilities. NI $92,624 Exempt

2019 203103 Calhoun Battle Creek Transit Transit Capital Improvements Areawide 0.000 SP10-State Match urban Agency FTA Sec 5339(a) Capital Project(s) NI $120,000 Exempt

2019 203093 Calhoun Battle Creek Transit Transit Operating Areawide 0.000 3000-Operating Assistance Operating NI $2,115,162 Exempt

2019 203104 CalhounCommunity

Inclusive Recreation, Inc.

Transit Capital Improvements Areawide 0.000 1170-Other Capital Items (Bus) Community Inclusive Recreation

(CIR) Capital Assistance NI $44,800 Exempt

2019 203105 Calhoun

Marian E. Burch Adult Care & Rehabilitation

Center

Transit Capital Improvements Areawide 0.000 1110-Bus Rolling Stock Marian Burch Adult Daycare Center

(MBADC) Capital Assistance NI $175,000 Exempt

2020 205179 Calhoun Battle Creek Transit

Specialized Services Transit

Operating Assistance

Areawide/Battle Creek/Calhoun County 0.000 SP09-Specialized Service Services for the elderly & individuals with disabilities NI $92,624 Exempt

2020 203108 Calhoun Battle Creek Transit Transit Capital Improvements Areawide 0.000 1110-Bus Rolling Stock FTA Sec 5339(a) Capital Projects NI $120,000 Exempt

2020 203096 Calhoun Battle Creek Transit Transit Operating Areawide 0.000 3000-Operating Assistance Operating NI $2,115,162 Exempt

2020 203106 CalhounCommunity Action Agency of South Central MI, Inc

Transit Capital Improvements Areawide 0.000 1110-Bus Rolling Stock Community Action Capital

Assistance NI $212,241 Exempt

2020 203107 CalhounCommunity

Inclusive Recreation, Inc.

Transit Capital Improvements Areawide 0.000 1110-Bus Rolling Stock Community Inclusive Recreation

(CIR) Capital Assistance NI $61,550 Exempt

2020 203109 Calhoun

Marian E. Burch Adult Care & Rehabilitation

Center

Transit Capital Improvements Areawide 0.000 1110-Bus Rolling Stock Capital Assistance NI $126,000 Exempt

2018 119959 Kalamazoo MDOT Calhoun County Calhoun County 25.109 Traffic Safety Non-Freeway Signing Upgrade CON $325,000 Exempt

2018 201479 Kalamazoo MDOT E Kilgore Rd Region-wide 1.115 Traffic Safety Longitudinal pavement marking application PE $400 Exempt

2018 201479 Kalamazoo MDOT E Kilgore Rd Region-wide 1.115 Traffic Safety Longitudinal pavement marking application CON $171,365 Exempt

2018 201482 Kalamazoo MDOT E Kilgore Rd Region-wide 1.762 Traffic Safety Special pavement marking application PE $100 Exempt

2018 201482 Kalamazoo MDOT E Kilgore Rd Region-wide 1.762 Traffic Safety Special pavement marking application CON $1,250 Exempt

Page 9 of 12

Meeting Materials Page 61 of 83

Page 62: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined TIP/STIP Project Listing for Conformity

Fiscal Job # County Responsible Project Name Limits Length Primary Work Type Project Description Phas Total Budget Air Quality AQ comments

2018 203101 Kalamazoo MDOTFreeway

Interchange Lighting Upgrades

I-94 @ Westnedge Interchange; I-194 @ Dickman Road Interchange 0.025 Operation Improvements Upgrade to LED Lights PE $2,722 Exempt

2018 129575 Calhoun MDOT I-194 & M-66 over I-94 0.000 Bridge Rehabilitation Railing Replacement, Epoxy Overlay CON $1,778,000 Exempt

2018 202931 Calhoun MDOT I-194 N/Dickman Ramp NB I-194 Exit to I-94BR (Dickman) 0.198 Traffic Safety Install Wrong Way Traffic Detection

System CON $33,500 Exempt

2018 202709 Branch MDOT I-69BL Signal modernizations for 12 locations. 0.000 Traffic Safety 2018 Marshall TSC Signal Modernization Project PE $0 Exempt

2018 125865 Calhoun MDOT I-94 6 1/2 to 11 Mile Roads 4.807 Road Rehabilitation HMA overlay, partial reconst, drainage & ramp impr CON $19,000,000 Exempt

2018 125646 Branch MDOT I-BL-69 Signal modernizations for 12 locations. 1.101 Traffic Safety 2018 Marshall TSC signal modernization projects ROW $95,000 Exempt

2018 125646 Branch MDOT I-BL-69 Signal modernizations for 12 locations. 1.101 Traffic Safety 2018 Marshall TSC signal modernization projects CON $402,338 Exempt

2018 200709 St. Joseph MDOT M-60 Southwest Region 99.948 Road Capital Preventive Maintenance 2019 Calendar Year Crack Seal CON $26,528 Exempt

2018 129143 Calhoun MDOT M-66 Division Street north to Frey Drive 2.535 Road Capital Preventive Maintenance

Mill and One Course Hot Mix Asphalt Overlay CON $1,884,407 Exempt

2018 202943 Calhoun MDOT M-96 I-94 BL/M-37/M-96 (Helmer Road) from Columbia Avenue to Dickman Road 1.671 Road Capital Preventive

Maintenance Cold milling, 2 HMA Overlay CON $995,000 Exempt

2019 201991 Kalamazoo MDOT E Kilgore Rd Various signalized intersections in the Southwest Region 0.000 Traffic Safety Dilemma zone detection at

signalized intersections PE $16,000 Exempt

2019 203101 Kalamazoo MDOTFreeway

Interchange Lighting Upgrades

I-94 @ Westnedge Interchange; I-194 @ Dickman Road Interchange 0.025 Operation Improvements Upgrade to LED Lights CON $44,323 Exempt

2019 202017 Calhoun MDOT I-194 N I-94 to Hamblin Avenue 3.374 Road Rehabilitation Concrete Pavement Repairs CON $2,345,000 Exempt

2019 204457 Calhoun MDOT I-194 S/Columbia Ramp Various @ Marshall TSC 0.764 Traffic Safety

Cantilevers Rep for W068-C,W071-C,W072-C,W081-C,W084-C,W085-

C,W-153-C,W-154PE $50,000 Exempt

2019 201976 Calhoun MDOT I-94 Exit 100 on M-294. 0.000 Roadside Facilities - Preserve Resurface existing carpool lot. CON $49,999 Exempt2019 123301 Calhoun MDOT M-311 At the Kalamazoo River 0.692 Road Rehabilitation Multi-course HMA overlay CON $1,132,500 Exempt2019 124061 Calhoun MDOT M-311 M-60 to B Drive S 8.940 Traffic Safety fixed object removal CON $560,100 Exempt2019 124062 Calhoun MDOT M-311 B Drive S to I-94 BL 4.492 Traffic Safety fixed object removal CON $135,500 Exempt2019 125818 Calhoun MDOT M-311 over Kalamazoo River 0.000 Bridge Replacement Bridge Replacement CON $3,507,500 Exempt

2019 132618 Calhoun MDOT M-66 Calhoun County 12.630 Traffic Safety Signal modernizations, upgrades, and optimization. ROW $175,000 Exempt

2019 132618 Calhoun MDOT M-66 Calhoun County 12.630 Traffic Safety Signal modernizations, upgrades, and optimization. CON $2,041,000 Exempt

2019 202999 Barry MDOT M-78 & M-89 M-78: M-66 to Pease Rd; M-89: Doster Rd to Barry S Co Line 6.984 Road Capital Preventive

MaintenanceMilling & One Course Asphalt

Overlay CON $641,000 Exempt

2019 203667 Calhoun MDOT M-96 (Columbia Ave) Helmer Road to east of Riverside Drive 2.797 Road Capital Preventive

Maintenance Milling & one course asphalt overlay PE $177,000 Exempt

2020 204348 Calhoun MDOT I-94 over Riverside Drive, City of Battle Creek, Calhoun County 0.000 Bridge CPM

Thin Epoxy Ovly, Sleeper Slab Repl, Approach Repl, Expansion

Joint ReplPE-S $68,950 Exempt

Page 10 of 12

Meeting Materials Page 62 of 83

Page 63: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined TIP/STIP Project Listing for Conformity

Fiscal Job # County Responsible Project Name Limits Length Primary Work Type Project Description Phas Total Budget Air Quality AQ comments

2020 204348 Calhoun MDOT I-94 over Riverside Drive, City of Battle Creek, Calhoun County 0.000 Bridge CPM

Thin Epoxy Ovly, Sleeper Slab Repl, Approach Repl, Expansion

Joint ReplPE $72,890 Exempt

2020 204349 Calhoun MDOT I-94 under I-194 & M-66 NB & SB, City Of Battle Creek, Calhoun County 0.000 Bridge CPM

Full Paint, Substr Horizontal Surf Coating, Elas Bearing Repl, Joint

ResealPE-S $218,599 Exempt

2020 204349 Calhoun MDOT I-94 under I-194 & M-66 NB & SB, City Of Battle Creek, Calhoun County 0.000 Bridge CPM

Full Paint, Substr Horizontal Surf Coating, Elas Bearing Repl, Joint

ResealPE $147,701 Exempt

2020 201957 Calhoun MDOT I-94 E I-94 BL (Michigan Ave) over I-94, Emmett Township, Calhoun County 0.000 Bridge Rehabilitation

Barrier Repl, Deck Patching, H/S, Latex Bm Repr, Substr Patching,

CSCPE-S $83,000 Exempt

2020 201957 Calhoun MDOT I-94 E I-94 BL (Michigan Ave) over I-94, Emmett Township, Calhoun County 0.000 Bridge Rehabilitation

Barrier Repl, Deck Patching, H/S, Latex Bm Repr, Substr Patching,

CSCPE $60,000 Exempt

2020 202655 Calhoun MDOT M-60 Various Routes in Calhoun County 137.366 Traffic Safety Non-freeway signing PE $150,000 Exempt

2020 203675 Branch MDOT M-60 I-69 Jonesville Road Ramps, M-60, M-66 11.459 Road Capital Preventive Maintenance Asphalt Crack Treatment CON $49,500 Exempt

2020 203667 Calhoun MDOT M-96 (Columbia Ave) Helmer Road to east of Riverside Drive 2.797 Road Capital Preventive

Maintenance Milling & one course asphalt overlay CON $1,654,000 Exempt

2020 127639 Calhoun MDOT Wheatfield/W I 94 RAMP I-94 WB entrance ramp from I-94 BL / M-311 0.178 Traffic Safety Reconstruction of the loop entrance

ramp CON $1,123,000 Exempt

2019 130078 Calhoun Calhoun County Various CCRD Locations

Various CCRD Locations 0.001 Road Rehabilitation Resurface CON $744,719 Exempt

2020 130101 Calhoun Calhoun County Various CCRD Routes

Various CCRD Routes 0.001 Road Rehabilitation Resurface CON $744,719 Exempt

2022 117729 Calhoun MDOT I-69 N Drive North (Exit 42) to Eaton County Line 5.004 Reconstruction Reconstruction CON $31,200,000 Exempt

2019 124061 Calhoun MDOT M-311 M-60 to south Newton Township line 8.940 Traffic Safety fixed object removal CON $373,400 Exempt2021 129886 Calhoun MDOT I-69 under N Drive North and Garfield Road 0.000 Bridge Rehabilitation Deep Overlay, Full Paint, Pin and

HangersCON $5,006,002 Exempt

2019 133087 Calhoun Marshall Monroe St over Rice Creek 0.000 Bridge Replacement replacement CON $2,181,000 Exempt2022 200914 Calhoun MDOT I-69 S over St. Joseph River and Jackson Road 0.000 Bridge Rehabilitation Deep Overlay, Barrier

Replacement, PCI Beam and Substructure Repair

CON $3,602,001 Exempt

2020 201992 Calhoun MDOT I-94 C-Drive N, Albion Facility Lot No. 713006. 0.000 Roadside Facilities - Preserve Resurface existing carpool lot. CON $88,000 Exempt2020 202655 Calhoun MDOT M-60 Signing Upgrade 137.366 Traffic Safety Non-freeway signing PE $250,000 Exempt2022 202655 Calhoun MDOT M-60 Signing Upgrade 137.366 Traffic Safety Non-freeway signing CON $922,973 Exempt2024 203387 Calhoun MDOT I-94 E 17 Mile Road over I-94, Marshall Township,

Calhoun County0.000 Bridge Rehabilitation Deck Patch, Epoxy Ovly, Full Paint,

Joint Repl, Pier Repl and RoadworkCON $5,820,000

Exempt

2019 203497 Calhoun Calhoun County 4 segments tree removal

13 Mile Rd in Convis Twp, 13 Mile Rd in Fredonia Twp, 29 Mile Rd, Condit Rd

12.829 Traffic Safety Tree removal CON $218,624 Exempt

2022 204457 Calhoun MDOT I-194 S/Columbia Ramp

Signing Update 0.764 Traffic Safety Cantilevers Rep for W068-C,W071-C,W072-C,W081-C,W084-C,W085-

C,W-153-C,W-154

CON $580,000

Exempt

2019 204636 Calhoun Albion W North St E. North Street 0.661 Reconstruction Reconstruction CON $900,000 Exempt2020 127025 Calhoun MDOT M-199 27 Mile Road to I-94 2.938 Road Rehabilitation Cold mill, two course overlay, and

widen shouldersCON $1,450,002 Exempt

Page 11 of 12

Meeting Materials Page 63 of 83

Page 64: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined TIP/STIP Project Listing for Conformity

Fiscal Job # County Responsible Project Name Limits Length Primary Work Type Project Description Phas Total Budget Air Quality AQ comments 2019 204205 Calhoun MDOT I-94BL I-94BL from west of Sycamore Street to west

of Marshall Street0.565 Road Rehabilitation Milling and two course asphalt

resurfacingROW $20,000 Exempt

2019 204205 Calhoun MDOT I-94BL I-94BL from west of Sycamore Street to west of Marshall Street

0.565 Road Rehabilitation Milling and two course asphalt resurfacing

CON $1,049,266 Exempt

2022 201977 Calhoun MDOT I-69 Exit 42, SW quadrant of interchange. 0.000 Roadside Facilities - Preserve Resurface existing carpool lot. CON $56,000 Exempt2019 133076 Van Buren Van Buren County 70th St various 0.000 Bridge CPM preventative maintenance CON $25,000 Exempt2019 133076 Van Buren Van Buren County 70th St various 0.000 Bridge CPM preventative maintenance CON $25,000 Exempt2019 133076 Van Buren Van Buren County 70th St various 0.000 Bridge CPM preventative maintenance CON $57,000 Exempt2019 133076 Van Buren Van Buren County 70th St various 0.000 Bridge CPM preventative maintenance CON $65,000 Exempt2019 133076 Van Buren Van Buren County 70th St various 0.000 Bridge CPM preventative maintenance CON $93,480 Exempt2019 133076 Van Buren Van Buren County 70th St various 0.000 Bridge CPM preventative maintenance CON $118,070 Exempt2019 133077 Van Buren Van Buren County 55 1/5 St over Paw Paw River, over Mentha Drain 0.000 Bridge CPM preventative maintenance CON $0 Exempt2019 133077 Van Buren Van Buren County 55 1/5 St over Paw Paw River, over Mentha Drain 0.000 Bridge CPM preventative maintenance CON $75,000 Exempt2019 129853 Van Buren Decatur S. Williams Street Delaware Street (M-51) to the south Village

Limits0.870 Road Rehabilitation Resurface CON $401,000 Exempt

2019 129854 Van Buren Breedsville W. Main Street From the west villlage limits to Pine Street 0.499 Road Rehabilitation Resurface CON $373,200 Exempt2019 133005 Van Buren Van Buren County 8th Ave. Blue Star Hwy. East to 1-196 0.099 Road Rehabilitation Pavement restoration. CON $325,000 Exempt2019 133207 Van Buren South Haven 8th Avenue Blue Star Hwy. East to 1-196 0.099 Road Rehabilitation Resurfacing CON $325,000 Exempt2021 129859 Van Buren Bloomingdale W. Kalamazoo

StreetOak Street to west Village Limits 0.720 Reconstruction Reconstruct CON $651,200 Exempt

2020 132932 Van Buren South Haven Area Wide Van Buren Transit 0.000 1110-Bus Rolling Stock Replace bus. NI $92,000 Exempt2019 133001 Van Buren Van Buren County Area Wide Van Buren County Public Transit 0.000 1110-Bus Rolling Stock Bus purchase. NI $180,000 Exempt2019 200632 Van Buren MDOT M-43 WCL of Bangor to 46th Street 13.926 Road Capital Preventive

MaintenancePaver Placed Surface Seal with

spot HMA repairsCON $1,283,150 Exempt

2019 200635 Van Buren MDOT I-94 WB M-140 to County Road 687 5.113 Road Capital Preventive Maintenance

Pavement Grind, Groove, Joint Sealing, pavement undersealing.

CON $2,893,000 Exempt

2019 131563 Van Buren MDOT M-43 I-196 BL to Blue Star Highway 0.762 Road Capital Preventive Maintenance

Full Depth Concrete Pavement Repairs

CON $422,663 Exempt

Page 12 of 12

Meeting Materials Page 64 of 83

Page 65: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined MTP Project Listing for Conformity

Year Agency Limits Length Road Location/Agency Work Type Estimated Cost Description Air Quality Air quality comments

2016 City of Kalamazoo

Kilgore Service Road to Sprinkle 1.17 Kilgore Road City of Kalamazoo Resurface $911,000

Road resurfacing, road diet to connect future non-motorized facilities, new sidewalk

constructionnonexempt modeled

2016

Road Commission of

Kalamazoo County

Wallace to Nazareth 1.1 E. Main Street Kalamazoo Township Resurface $1,005,000 Signal Safety Improvements with City of

Kalamazoo exempt

2018

Road Commission of

Kalamazoo County

N/ E of 8th Street to 12th Street 2.7 Texas Drive Texas Resurface $750,000 Mill/ HMA Overlay/ Left Turn Lane exempt intersections only

2020Michigan

Department of Transportation

east of Lovers Lane to east of Portage Road

1.16 I-94 City of Kalamazoo, City of Portage Reconstruct $33,097,837 JN 105885 - Roadway reconstruction and

widening and interchange reconstruction nonexempt modeled

2020Michigan

Department of Transportation

east of Portage Road to west of

Sprinkle1.2 I-94 City of Kalamazoo Reconstruct $34,660,074

JN 105886 - Road reconstruction and widening and reconstruction and widening of 2 railroad

bridges and a large culvertnonexempt modeled

2021-2025 City of Kalamazoo

Cross Town to Oakland 0.797 Howard Street City of Kalamazoo Resurface $625,000

Road diet to convert 4 lanes to 3 lanes with the addition if a center median island to provide safe passage across Howard for Kalamazoo

Magnet School

removed project suppended

2021-2025 City of Kalamazoo

Ampersee to North 0.672 Gull Road City of Kalamazoo Resurface $425,000 Road diet to convert 4 lanes to 3 lanes and add

bike lanes nonexempt modeled

2021-2025 City of Kalamazoo

Gar Lane TO W. Michigan 0.713 Howard Street City of Kalamazoo Roadside Facility $400,000

Installation of a non-motorized pathway/sidewalk from Gar Ln to W. Michigan

Ave to be completed in conjunction with MDOT's construction of Stadium Drive.

exempt

2021-2025 City of Kalamazoo

Parkview to Westnedge 1.006 Whites Road City of Kalamazoo Resurface $650,000 Road diet to convert 4 lanes to 3 lanes and add

bike lanes nonexempt modeled

2021-2025 City of Kalamazoo

Westnedge to West Main 1.19 Douglas and

Kalamazoo City of Kalamazoo Traffic Operations $5,000,000 Convert Kalamazoo avenue and Douglass Ave to two way removed project removed

2021-2025Kalamazoo

County Parks Department

D Ave. in Cooper Township north

to Allegan County Line

3.5 Kalamazoo River Valley Trail Cooper Township New Route/Structure $2,100,000

A 3.5-mile addition to the Kalamazoo River Valley Trail that will extend north with plans to

link to existing and future trail systems. exempt

2021-2025Kalamazoo

County Parks Department

M-89/Gull Lake in Ross Township

to Barry County/Kalamazo

o County Line

5 Kalamazoo River Valley Trail

Gull Lake/M-89 north to Kalamazoo County/Barry

County LineNew Route/Structure $2,200,000

A 5-mile addition to the Kalamazoo River Valley Trail that will connect the eventual Gull Lake/M-89 trail north to the Barry County/Kalamazoo

County line.

exempt

2026-2030 City of Kalamazoo

Pitcher to Michigan 0.411 Portage Street City of Kalamazoo Resurface $260,000 Road diet to convert 4 lanes to 3 lanes and add

bike lanes nonexempt modeled

2026-2030 City of Kalamazoo

Riverview to Porter 0.452 Paterson Street City of Kalamazoo Resurface $300,000 Road diet to convert 4 lanes to 3 lanes and add

bike lanes nonexempt modeled

Page 1 of 16

Meeting Materials Page 65 of 83

Page 66: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined MTP Project Listing for Conformity

Year Agency Limits Length Road Location/Agency Work Type Estimated Cost Description Air Quality Air quality comments

2026-2030 Portage I-94 to Kilgore Road 0.43 Oakland Drive City of Portage Widen - Major $2,150,000

Widen Oakland Drive from 4 lanes to 5 lanes from I-94 to Kilgore Road for the additions of

dedicated left turn lane and bike lanes. As part of this project, the bridge over the west fork of Portage Creek will need to be reconstructed to

accommodate the wider road section.

nonexempt modeled

2026-2030 PortageLakeview Drive

to East Osterhout Avenue

1.2 Portage Road City of Portage Widen - Major $1,820,000

Widen Portage Road from 4 lanes to 5 lanes to accommodate bike lanes on both sides of the

roadway from Lakeview Drive to East Osterhout Avenue. This project will

accommodate increase capacity needs in this area.

nonexempt modeled

2026-2030 Portage Portage Road to Sprinkle Road 1 Romence Road City of Portage Widen - Major $1,820,000

Widen Romence Road from 2 and 3 lanes to 4 lane boulevard from Portage Road to Sprinkle Road. The project will include bike lanes and accommodate increased industrial and airport

traffic demands.

nonexempt modeled

2026-2030 Portage Milham Avenue to Romence Road 1

South Westnedge

AvenueCity of Portage Widen - Major $3,475,000

Widen northbound lanes on South Westnedge Avenue from 2 lanes to 3 lanes from Milham Avenue to Romence Road. The project will increase capacity for northbound traffic and

provide bus stop areas for Metro Transit. This project includes milling and resurfacing of all

existing lanes from Milham Avenue to Romence Road, and replacement of sidewalks on east side of road to accommodate widening

the northbound lane from 2 to 3 lanes.

nonexempt modeled

2026-2030 Portage Shaver Road to Portage Road 2.47 Osterhout Avenue City of Portage Widen - Major $2,500,000

Widen Osterhout Avenue from 2 lanes to 3 lanes to widen existing bike lanes on both sides of the roadway and install sidewalk on the north

side, from Shaver Road to Portage Road. As part of this project, the culvert crossing for

Sugarloaf Drain will be replaced to accommodate a wider roadway.

nonexempt modeled

2026-2030 PortageRomence Road to West Centre

Avenue1

South Westnedge Ave /

Shaver RoadCity of Portage Widen - Major $4,808,000

Widen South Westnedge Avenue & Shaver Road from 5 lanes to 7 lanes from Romence Road to West Centre Avenue. Widening the road will provide additional capacity for the

project area. Upgrades to sidewalks will also be included in this project.

nonexempt modeled

Page 2 of 16

Meeting Materials Page 66 of 83

Page 67: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined MTP Project Listing for Conformity

Year Agency Limits Length Road Location/Agency Work Type Estimated Cost Description Air Quality Air quality comments

2026-2030 PortageVanderbilt

Avenue to South City Limits

2 Shaver Road City of Portage Widen - Major $3,600,000

Widen Shaver Road from 2 and 3 lanes to a 4 lane boulevard or 5 lanes from Vanderbilt

Avenue to south city limits. This project will include bike trails and sidewalks to

accommodate non-motorist traffic. The project will provide additional capacity for traffic to/from

US-131.

nonexempt modleded

2026-2030 Portage Oakland Drive to Shaver Road 0.41 Vanderbilt

Avenue City of Portage Widen - Minor (Less than 1 mile) $440,000

Widen Vanderbilt Avenue from 2 lanes to 3 lanes to accommodate bikes lanes on both sides of the roadway from Oakland Drive to

Shaver Road. The project will improve capacity and provide dedicated left turn lane into

adjacent properties and intersections.

nonexempt modeled

2026-2030 Village of Mattawan

Main Street to east village limits 1.031 East McGillen Village of Matawan Reconstruct $2,410,000

Add roughly 700 feet of 3rd lane add 200 feet of right turn lane, 4400 feet of bike path, grind

existing pavement and repave.exempt

2036-2040 City of Kalamazoo Cork to Kilgore 0.996 Burkdick Street City of Kalamazoo Widen - Minor (Less

than 1 mile) $1,200,000 Construct Bike lanes by widening roadway. exempt

2041-2045 Portage Dawnlee Avenue to Milham Avenue 0.3

South Westnedge

AvenueCity of Portage Widen - Minor (Less

than 1 mile) $1,500,000

Widen northbound lanes on South Westnedge Avenue from 2 lanes to 3 lane boulevard from

Dawnlee Avenue to Milham Avenue. This project will include mill and resurface

southbound lanes and replace sidewalk on the west side to accommodate widening of

northbound lanes.

nonexempt modeled

2041-2045 Portage Old Kilgore Road to Lovers Lane 0.6 Kilgore Road City of Portage Widen - Minor (Less

than 1 mile) $1,290,000

Widen Kilgore Road from 4 lanes to 5 lanes (addition of one lane for eastbound traffic) from Old Kilgore Road to Lovers Lane. This project will include the removal and replacement of

sidewalk to accommodate widening.

nonexempt modeled

2041-2045 PortageOsterhout

Avenue to Centre Avenue

2.56 Portage Road City of Portage Reconstruct $2,160,000

Reduce Portage Road from 4-5 lanes to 3 lanes from Osterhout Avenue to Centre

Avenue. This project would include upgrading/extending sidewalks, adding bike

lanes on both sides of the roadway, and constructing a dedicated left turn lane.

nonexempt modeled

2041-2045 PortageCentre Avenue to Romence Road

Parkway1 Lovers Lane City of Portage Reconstruct $1,060,000

Reduce Lovers Lane from 4 lanes to 3 lanes from Centre Avenue to Romence Road

Parkway. This project will include bicycle trail improvements/replacement, new landscaping, sidewalk extensions, and a dedicated center

left turn lane.

nonexempt modeled

2041-2045 Portage Portage Road to Sprinkle Road 1.06 Zylman Avenue City of Portage Widen - Major $1,680,000

Widen Zylman Avenue from 2/3 lanes to 5 lanes to accommodate for dedicated left turn lane and bike lanes on both sides of the road.

nonexempt modeled

Page 3 of 16

Meeting Materials Page 67 of 83

Page 68: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined MTP Project Listing for Conformity

Year Agency Limits Length Road Location/Agency Work Type Estimated Cost Description Air Quality Air quality comments

2041-2045 Portage

South Westnedge Avenue to

Portage Road

1.06 Bacon Avenue City of Portage Widen - Major $1,000,000

Widen Bacon Avenue from 2 lanes to 3 lanes to accommodate left turns and for bike lanes on both sides of the road from South Westnedge

Avenue to Portage Road.

nonexempt modeled

2041-2045 PortageGladys Street to Romence Road

Parkway0.59 Newport Avenue City of Portage New Route/Structure $5,500,000

Construct new 4 lane boulevard to extend Newport Avenue from Gladys Street to

Romence Road Parkway. This project will include bike lanes on both sides of the road

and adding sidewalks along the east side. The purpose of this project is to improve the traffic

carrying capacity and safety on Newport Avenue and Gladys Street.

nonexempt modeled

2041-2045 Portage Shaver Road to Centre Avenue 1.97 Oakland Drive City of Portage Widen - Major $5,000,000

Widen Oakland Drive from 2 lanes to 4 lane boulevard to accommodate dedicated left turn lane, bike lanes on both sides of the road, and extending sidewalks where needed. As part of this project, the culvert crossing for Portage

Creek will be replaced to accommodate a wider roadway.

nonexempt modeled

2041-2045 Portage

Oakland Drive to South

Westnedge Avenue

1.26 Schuring Road City of Portage Widen - Major $1,128,800

Widen Schuring Road from 2 lanes to 3 lanes to accommodate for dedicated left turn lane

and bike lanes on both sides of the road from Oakland Drive to South Westnedge Avenue.

nonexempt modeled

2018 within Calhoun County

1 (one) Clean Diesel Dump

Truck (replacement), double-axle,

cab+chassis only Fed-aid eligible

CCRD Replace one dump truck in existing fleet 243,820$ Air Quality exempt

2018from Roosevelt

Ave northward to Morgan Rd

1.17 East Ave CCRD Resurfacing 325,000$ Preservation exempt

2018from Verona Rd northward to N

Dr N1.35 McAllister Rd CCRD Resurfacing 335,000$ Preservation exempt

2018

Intersection of Clark Rd/Custer Dr N @ River Rd

W, & all four approaches

0.40 Clark Rd @ River Rd City of Battle Creek

installation of intersection control

beacon & supports for span wire mount

24,080$ Traffic Safety/Operations exempt

2018from Gethings

Rd northward to Columbia Ave

1.00 Helmer Rd City of Battle CreekResurfacing with spot

sidewalk & ramp replacement

368,900$ Preservation & Non-Motorized exempt

Page 4 of 16

Meeting Materials Page 68 of 83

Page 69: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined MTP Project Listing for Conformity

Year Agency Limits Length Road Location/Agency Work Type Estimated Cost Description Air Quality Air quality comments

2018 Capital Ave @ Jackson St 0.40

Intersection Signal

Modernization - Capital @ Jackson

City of Battle Creek

Upgrade/modernize signal &

interconnection to nearby signals and

City's Traffic Management Center

325,000$ Traffic Safety/Operations & Air Quality exempt

2018

from Mary St southward to

south city limits (~200' south of Kingman Ave),

~0.5 mi; and from M-66 (Division

St) southward to Hamblin Ave,

~0.1 mi.

0.57 Main St City of Battle Creek Resurfacing (2" mill & overlay) 194,090$ Preservation exempt

2018

M-66 from Capital

Ave/Division St intersection

northward to Frey Dr

2.54 M-66 (Capital Ave NE) MDOT 1.5" mill & 1.5" overlay

with ADA ramps 1,452,123$ Preservation exempt

2018Battle Creek Transit (BCT) fixed-routes

1 (one) Heavy-Duty - Low Floor

Bus, for fixed-route service

Transit - City of Battle Creek Replace one bus used in fixed-route service 433,500$ Transit Capital exempt

2018

BCT facilities, 339 W Michigan

Ave, in southwest

quadrant of M-89 (Michigan Ave) /

Cass St intersection, and on-board vehicles

Ancillary Equipment -

TransitTransit - City of Battle Creek Computers and vehicle

technology 120,000$ Transit Capital exempt

2018 within Calhoun County

Community Action (formerly

Community Action Agency)

Capital Assistance -

Planned 2018 Application

Transit - City of Battle Creek

Acquisition of one (1) new small light-duty cutaway bus, 138"

wheelbase, w/lift, gas engine, to REPLACE one vehicle in existing

fleet.

58,000$ Transit Capital exempt

Page 5 of 16

Meeting Materials Page 69 of 83

Page 70: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined MTP Project Listing for Conformity

Year Agency Limits Length Road Location/Agency Work Type Estimated Cost Description Air Quality Air quality comments

2018 within Calhoun County

Community Action (formerly

Community Action Agency)

Capital Assistance -

Planned 2018 Application

Transit - City of Battle Creek

Acquisition of one (1) new 15-psngr van, to

REPLACE one vehicle in existing fleet.

44,000$ Transit Capital exempt

2018 within Calhoun County

Community Inclusive

Recreation (CIR) Capital

Assistance - Planned 2018

Application

Transit - City of Battle Creek

Acquisition of one (1) new small (15-psngr)

light-duty cutaway buses, 138"

wheelbase, w/lift, gas engine, to REPLACE one vehicle in existing

fleet.

59,160$ Transit Capital exempt

2018 within Calhoun County

Marian Burch Adult Daycare

Center (MBADC) Capital

Assistance - Planned 2018

Application

Transit - City of Battle Creek Replacement of one mini-van 23,800$ Transit Capital exempt

2019

from Halbert Rd northward to

Calhoun County limits

2.65 North Ave, Pennfield Twp CCRD Resurfacing 650,000$ Preservation exempt

2019from Mary St northward to Michigan Ave

0.33 Elm St City of Battle CreekResurfacing with spot

sidewalk & ramp replacement

102,420$ Preservation & Non-Motorized exempt

2019 from Capital Ave eastward to M-66 0.82 Glenn Cross Rd City of Battle Creek Resurfacing 260,580$ Preservation exempt

2019 Capital Ave @ Michigan Ave

Intersection Signal

Modernization - Capital @ Michigan

City of Battle Creek

Upgrade/modernize signal &

interconnection to nearby signals and

City's Traffic Management Center

325,000$ Traffic Safety/Operations & Air Quality exempt

2019

from Roosevelt Ave northward to

Coolidge Ave (city limits)

0.61 North Ave, City of BC City of Battle Creek

Resurfacing with spot sidewalk & ramp

replacement240,000$ Preservation & Non-Motorized exempt

Page 6 of 16

Meeting Materials Page 70 of 83

Page 71: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined MTP Project Listing for Conformity

Year Agency Limits Length Road Location/Agency Work Type Estimated Cost Description Air Quality Air quality comments

2019

from BCATS southern

Metropolitan Planning Area

(MPA) boundary line btwn Newton

& Burlington Twps northward

to I-94 BL (Michigan Ave)

9.50M-311 (11

Mile/Wheatfield Rd) - CON

MDOT Multi-course HMA overlay 4,347,668$ Preservation exempt

2019

1/4 mile N+S of Kalamazoo River

at M-311 (11 Mile/Wheatfield Rd), just north of D Dr N, including

bridge.

0.50

M-311 (11 Mile/Wheatfield Rd) Bridge over

Kalamazoo River - CON

MDOTConstruction to replace bridge &

rehabilitate approaches3,407,000$ Bridges exempt

2019

from BCATS southern

Metropolitan Planning Area

(MPA) boundary line btwn Newton

& Burlington Twps northward

to B Drive S

5.00M-311 (11

Mile/Wheatfield Rd) CON/1

MDOTfixed object removal -

tree removal and culvert replacement

522,760$ Traffic Safety/Operations exempt

2019

from B Drive S northward to I-94

BL (Michigan Avenue)

4.50M-311 (11

Mile/Wheatfield Rd) CON/2

MDOT fixed object removal - tree removal 135,500$ Traffic Safety/Operations exempt

2019

within BCATS metropolitan

planning area in Calhoun County

1 (one) Heavy-Duty - Low Floor

Bus, for fixed-route service

Transit - City of Battle Creek Replace one large bus in existing fleet 442,170$ Transit Capital & Air Quality exempt

2019 within Calhoun County

Community Inclusive

Recreation (CIR) Capital

Assistance - Planned 2019

Application

Transit - City of Battle Creek

Acquisition of one (1) new pickup truck to REPLACE one 2006

Chevy Silverado, used to transport program

participants & equipment.

42,000$ Transit Capital exempt

Page 7 of 16

Meeting Materials Page 71 of 83

Page 72: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined MTP Project Listing for Conformity

Year Agency Limits Length Road Location/Agency Work Type Estimated Cost Description Air Quality Air quality comments

2019 within Calhoun County

Community Inclusive

Recreation (CIR) Capital

Assistance - Planned 2019

Application

Transit - City of Battle Creek

Acquisition & installation of

"Viamente" route planning software,

replacement

2,800$ Transit Capital exempt

2019 within Calhoun County

Marian Burch Adult Daycare

Center (MBADC) Capital

Assistance - Planned 2019 Application 1

Transit - City of Battle Creek Replacement of one cutaway small bus 66,800$ Transit Capital exempt

2019 within Calhoun County

Marian Burch Adult Daycare

Center (MBADC) Capital

Assistance - Planned 2019 Application 2

Transit - City of Battle Creek Replacement of one medium-duty large bus 121,800$ Transit Capital exempt

2020Cliff St @

Raymond Rd, Emmett Twp

Intersection Signal

Modernization - Cliff @ Raymond

CCRDModernization & upgrade of traffic

signal(s) at intersection200,000$ Traffic Safety/Operations & Air Quality exempt

2020from Bellevue Rd

eastward to 12 Mile Rd

3.55 N Dr N (Gorsline Rd) CCRD Resurfacing 760,000$ Preservation exempt

2020from Morgan Rd

northward to Halbert Rd

2.01 Waubascon Rd CCRD Resurfacing 490,000$ Preservation exempt

2020from south city limits northward to Beckley Rd

1.01 Capital Ave SW City of Battle CreekResurfacing with spot

sidewalk & ramp replacement

372,050$ Preservation & Non-Motorized exempt

2020 Capital Ave @ VanBuren St

Intersection Signal

Modernization - Capital @ VanBuren

City of Battle Creek

Upgrade/modernize signal &

interconnection to nearby signals and

City's Traffic Management Center

325,000$ Traffic Safety/Operations & Air Quality exempt

2020from Dickman Rd

northward to Michigan Ave

0.43 Kendall St City of Battle CreekResurfacing with spot

sidewalk & ramp replacement

168,600$ Preservation & Non-Motorized exempt

Page 8 of 16

Meeting Materials Page 72 of 83

Page 73: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined MTP Project Listing for Conformity

Year Agency Limits Length Road Location/Agency Work Type Estimated Cost Description Air Quality Air quality comments

2020from Michigan

Ave northward to VanBuren St

0.48 Union St City of Battle CreekResurfacing with spot

sidewalk & ramp replacement

176,120$ Preservation & Non-Motorized exempt

2020

within City of Springfield &

adjoining areas as necessary in Calhoun County

1 (one) Clean Diesel Dump

Truck (replacement),

single-axle, only cab+chassis Fed-

aid eligible

City of Springfield Replace one dump truck in existing fleet 152,230$ Air Quality exempt

2020

I-94 WB entrance ramp from I-

94BL/M-311 (11 Mile/Wheatfield Rd) east-south-westward to I-94

0.17I-94 WB entrance ramp at Exit 104 interchange CON

MDOT Reconstruction of the loop entrance ramp 1,123,000$ Preservation, & Traffic Safety/Operations exempt

2020

Battle Creek Transit demand-

response service area, generally within City of

Battle Creek & limited service into adjoining

townships

1 (one) Propane-Fueled Small Bus/Van for

demand-response service

Transit - City of Battle Creek

1 (one) Propane-Fueled 10-Passenger

Lift-Equipped Light-Duty 20' Cutaway Bus,

replacement, for demand-response

service

80,000$ Transit Capital & Air Quality exempt

2020 within Calhoun County

Community Action (formerly

Community Action Agency)

Capital Assistance -

Planned 2020 Application

Transit - City of Battle Creek

Acquisition of two (2) new small light-duty cutaway buses, 138" wheelbase, w/lift, gas engine, to REPLACE

two vehicles in existing fleet.

120,686$ Transit Capital exempt

2020 within Calhoun County

Community Action (formerly

Community Action Agency)

Capital Assistance -

Planned 2020 Application

Transit - City of Battle Creek

Acquisition of two (2) new 15-psngr van, to

REPLACE two vehicles in existing

fleet.

91,555$ Transit Capital exempt

Page 9 of 16

Meeting Materials Page 73 of 83

Page 74: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined MTP Project Listing for Conformity

Year Agency Limits Length Road Location/Agency Work Type Estimated Cost Description Air Quality Air quality comments

2020 within Calhoun County

Community Inclusive

Recreation (CIR) Capital

Assistance - Planned 2020

Application

Transit - City of Battle Creek

Acquisition of one (1) new small (15-psngr)

light-duty cutaway buses, 138"

wheelbase, w/lift, gas engine, to REPLACE one vehicle in existing

fleet.

61,550$ Transit Capital exempt

2020 within Calhoun County

Marian Burch Adult Daycare

Center (MBADC) Capital

Assistance - Planned 2020

Application

Transit - City of Battle Creek Replacement of one cutaway small bus 69,936$ Transit Capital exempt

2021I-194 / M-66

north+southbound bridges over I-94

0.06 I-194/M-66 over I-94 MDOT

Bridge railing replacement, Epoxy

overlay, Concrete deck patching, Zone Paint,

Reseal Joints, Concrete surface

coating

1,778,000$ Bridges exempt

2021

I-94 east+westbound

bridges over CN/GTW

railroad, ~0.5 mi east of I-94BL

exit 92

I-94 over CN/GTW railroad MDOT minor widening and

rehabilitation 3,668,000$ Bridges exempt

2022

Battle Creek Transit demand-

response service area, generally within City of

Battle Creek & limited service into adjoining

townships

2 (two) Small Buses/Vans for

demand-response service

Transit - City of Battle Creek

2 (two) 10-Passenger Lift-Equipped Light-Duty 20' Cutaway

Buses, replacement, for demand-response

service

167,000$ Transit Capital exempt

2023

I-94 east+westbound bridges over 6

1/2 Mile Rd, ~0.6 mi east of I-

194/M-66 exit 98

I-94 over 6 1/2 Mile Rd MDOT minor widening and

rehabilitation 4,618,000$ Bridges exempt

Page 10 of 16

Meeting Materials Page 74 of 83

Page 75: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined MTP Project Listing for Conformity

Year Agency Limits Length Road Location/Agency Work Type Estimated Cost Description Air Quality Air quality comments

2023

within BCATS metropolitan

planning area in Calhoun County

1 (one) Heavy-Duty - Low Floor

Bus, for fixed-route service

Transit - City of Battle Creek Replace one large bus in existing fleet 476,000$ Transit Capital exempt

2024

Battle Creek Transit demand-

response service area, generally within City of

Battle Creek & limited service into adjoining

townships

1 (one) Small Bus/Van for

demand-response service

Transit - City of Battle Creek

1 (one) 10-Passenger Lift-Equipped Light-

Duty 20' Cutaway Bus, replacement, for

demand-response service

87,000$ Transit Capital exempt

2024 for Battle Creek Transit

Fare System Upgrade Transit - City of Battle Creek update and upgrade

fare system 517,000$ Transit Capital exempt

2025

I-94 east+westbound bridges over M-

294 (Beadle Lake Rd), at exit 100

I-94 over M-294 (Beadle Lake Rd) MDOT

minor widening and rehabilitation of bridge,

with allowances for future widening of M-

294 under bridge

3,884,000$ Bridges exempt

2025 for Battle Creek Transit

Transit Computer System Upgrade Transit - City of Battle Creek

upgrade/replacement of transit computer

system150,000$ Transit Capital exempt

2026

Battle Creek Transit demand-

response service area, generally within City of

Battle Creek & limited service into adjoining

townships

4 (four) Small Buses/Vans for

demand-response service

Transit - City of Battle Creek

4 (four) 10-Passenger Lift-Equipped Light-Duty 20' Cutaway

Buses, replacement, for demand-response

service

361,000$ Transit Capital exempt

2026 for Battle Creek Transit

Transit Passenger

SheltersTransit - City of Battle Creek purchase 10

replacement shelters 67,000$ Transit Capital exempt

2027

I-94 east+westbound bridges over 9

Mile Rd, ~2.1 mi west of M-311/11 Mile Rd exit 104

I-94 over 9 Mile Rd MDOT minor widening and

rehabilitation 4,162,000$ Bridges exempt

Page 11 of 16

Meeting Materials Page 75 of 83

Page 76: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined MTP Project Listing for Conformity

Year Agency Limits Length Road Location/Agency Work Type Estimated Cost Description Air Quality Air quality comments

2027

Battle Creek Transit demand-

response service area, generally within City of

Battle Creek & limited service into adjoining

townships

3 (three) Small Buses/Vans for

demand-response service

Transit - City of Battle Creek

3 (three) 10-Passenger Lift-

Equipped Light-Duty 20' Cutaway Buses,

replacement, for demand-response

service

276,000$ Transit Capital exempt

2027 for Battle Creek Transit

Automatic Vehicle

Locator/Computer-Aided Dispatch

(AVL/CAD) System Upgrade

Transit - City of Battle Creek upgrade AVL/CAD system 175,000$ Transit Capital exempt

2029

within BCATS metropolitan

planning area in Calhoun County

1 (one) Heavy-Duty - Low Floor

Bus, for fixed-route service

Transit - City of Battle Creek Replace one large bus in existing fleet 500,000$ Transit Capital exempt

2030

I-94 east+westbound

bridges over Kalamazoo

River, ~1.8 mi west of M-311/11 Mile Rd exit 104

I-94 over Kalamazoo River MDOT replacement of bridges 15,764,000$ Bridges exempt

2030

within BCATS metropolitan

planning area in Calhoun County

6 (six) Heavy-Duty - Low Floor Buses, for fixed-

route service

Transit - City of Battle Creek Replace six large buses in existing fleet 3,232,000$ Transit Capital exempt

2030

for Battle Creek Transit, at location of project #22

Transit facility renovation Transit - City of Battle Creek renovation of facilities 1,457,000$ Transit Capital exempt

2031

Battle Creek Transit demand-

response service area, generally within City of

Battle Creek & limited service into adjoining

townships

1 (one) Small Bus/Van for

demand-response service

Transit - City of Battle Creek

1 (one) 10-Passenger Lift-Equipped Light-

Duty 20' Cutaway Bus, replacement, for

demand-response service

100,000$ Transit Capital exempt

Page 12 of 16

Meeting Materials Page 76 of 83

Page 77: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined MTP Project Listing for Conformity

Year Agency Limits Length Road Location/Agency Work Type Estimated Cost Description Air Quality Air quality comments

2032

within BCATS metropolitan

planning area in Calhoun County

4 (four) Heavy-Duty - Low Floor Buses, for fixed-

route service

Transit - City of Battle Creek Replace four large buses in existing fleet 2,274,000$ Transit Capital exempt

2033

Battle Creek Transit demand-

response service area, generally within City of

Battle Creek & limited service into adjoining

townships

4 (four) Small Buses/Vans for

demand-response service

Transit - City of Battle Creek

4 (four) 10-Passenger Lift-Equipped Light-Duty 20' Cutaway

Buses, replacement, for demand-response

service

440,000$ Transit Capital exempt

2033

for Battle Creek Transit, at location of project #22

Transit Computer System Upgrade Transit - City of Battle Creek

upgrade/replacement of transit computer

system250,000$ Transit Capital exempt

2034

Battle Creek Transit demand-

response service area, generally within City of

Battle Creek & limited service into adjoining

townships

3 (three) Small Buses/Vans for

demand-response service

Transit - City of Battle Creek

3 (three) 10-Passenger Lift-

Equipped Light-Duty 20' Cutaway Buses,

replacement, for demand-response

service

330,000$ Transit Capital exempt

2035

within BCATS metropolitan

planning area in Calhoun County

1 (one) Heavy-Duty - Low Floor

Bus, for fixed-route service

Transit - City of Battle Creek Replace one large bus in existing fleet 550,000$ Transit Capital exempt

2035

BCT facilities, 339 W Michigan

Ave, in southwest

quadrant of M-89 (Michigan Ave) /

Cass St intersection, and

on-board vehicles, at location of project #22

Ancillary Equipment -

TransitTransit - City of Battle Creek

Computers, vehicle technology, & furniture

(replacement)250,000$ Transit Capital exempt

Page 13 of 16

Meeting Materials Page 77 of 83

Page 78: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined MTP Project Listing for Conformity

Year Agency Limits Length Road Location/Agency Work Type Estimated Cost Description Air Quality Air quality comments

2035

for Battle Creek Transit, at location of project #22

Automatic Vehicle

Locator/Computer-Aided Dispatch

(AVL/CAD) System Upgrade

Transit - City of Battle Creek upgrade AVL/CAD system 161,000$ Transit Capital exempt

2035 for Battle Creek Transit

Fare System Upgrade Transit - City of Battle Creek update and upgrade

fare system 643,000$ Transit Capital exempt

2035 for Battle Creek Transit

Transit Passenger

SheltersTransit - City of Battle Creek purchase 10

replacement shelters 80,000$ Transit Capital exempt

2035 for Battle Creek Transit

Transit Radio System Transit - City of Battle Creek replace transit radio

system 350,000$ Transit Capital exempt

2038

Battle Creek Transit demand-

response service area, generally within City of

Battle Creek & limited service into adjoining

townships

1 (one) Small Bus/Van for

demand-response service

Transit - City of Battle Creek

1 (one) 10-Passenger Lift-Equipped Light-

Duty 20' Cutaway Bus, replacement, for

demand-response service

120,000$ Transit Capital exempt

2039

within BCATS metropolitan

planning area in Calhoun County

1 (one) Heavy-Duty - Low Floor

Bus, for fixed-route service

Transit - City of Battle Creek Replace one large bus in existing fleet 600,000$ Transit Capital exempt

2039

BCT facilities, 339 W Michigan

Ave, in southwest

quadrant of M-89 (Michigan Ave) /

Cass St intersection, and

on-board vehicles, at location of project #22

Ancillary Equipment -

TransitTransit - City of Battle Creek Computers and vehicle

technology 250,000$ Transit Capital exempt

Page 14 of 16

Meeting Materials Page 78 of 83

Page 79: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined MTP Project Listing for Conformity

Year Agency Limits Length Road Location/Agency Work Type Estimated Cost Description Air Quality Air quality comments

2040

Battle Creek Transit demand-

response service area, generally within City of

Battle Creek & limited service into adjoining

townships

4 (four) Small Buses/Vans for

demand-response service

Transit - City of Battle Creek

4 (four) 10-Passenger Lift-Equipped Light-Duty 20' Cutaway

Buses, replacement, for demand-response

service

560,000$ Transit Capital exempt

2040

within BCATS metropolitan

planning area in Calhoun County

6 (six) Heavy-Duty - Low Floor Buses, for fixed-

route service

Transit - City of Battle Creek Replace six large buses in existing fleet 3,600,000$ Transit Capital exempt

2040

BCT facilities, 339 W Michigan

Ave, in southwest

quadrant of M-89 (Michigan Ave) /

Cass St intersection, at

location of project #22

Transit facility renovation Transit - City of Battle Creek renovation of facilities 1,700,000$ Transit Capital exempt

2017-2040 for local human services agencies

Annual Specialized

Services Transit OPERATING

Assistance (total expected over

2017-40, $92,624/year.

Transit - City of Battle Creek

State transit operating assistance "passed thru" Battle Creek

Transit to local human services agencies

2,222,976$ Transit Operating exempt

2017-2040 for Battle Creek Transit

Annual Transit Operating

Assistance (total expected over

2017-40, average $4.7M/year)

Transit - City of Battle Creek

Federal, State, & Local Operating Assistance.

Local $ includes "farebox revenue" from fares, tokens/tickets, passes, misc transp contracts, Auxiliary Trans Revenues (i.e.advertising),

NonTrans Revenues, and contribution from City of Battle Creek

general fund.

113,304,000$ Transit Operating exempt

Page 15 of 16

Meeting Materials Page 79 of 83

Page 80: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

Combined MTP Project Listing for Conformity

Year Agency Limits Length Road Location/Agency Work Type Estimated Cost Description Air Quality Air quality comments

2017-2040 for Battle Creek Transit

Annual Transit Security (total expected over

2017-2040, average

$15,970/year)

Transit - City of Battle Creek

Security related improvements (1% of

Federal operating assistance annually)

383,280$ Security exempt

2021-2040

Capital Preventive

Maintenance (CPM) on

Federal-aid eligible roadways

Annual Pavement

Preservation Strategy Local Agencies (75% of STP Urban

Local Allocation) (total planned over 2021-40,

average $1.4M/year)

Local Road Agencies (Cities of BC & Springfield, &

CCRD)

resurfacing and reconstruction 27,517,433$ Preservation exempt

2021-2040

Capital Preventive

Maintenance (CPM) on State system roadways

Annual Pavement

Preservation Strategy MDOT (total planned over 2021-40,

average $6.2M/year)

MDOT resurfacing and reconstruction 124,701,102$ Preservation exempt

2021-2040 for local human services agencies

Annual Specialized

Services Transit CAPITAL

Assistance (total expected over

2021-40, $135,150/year.

Transit - City of Battle Creek

Fed Sec 5310 (with match from State)

transit capital assistance "passed thru" Battle Creek

Transit to local human services agencies

2,703,000$ Transit Capital exempt

Page 16 of 16

Meeting Materials Page 80 of 83

Page 81: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

RESOLUTION

Supporting Application for FY 2022 Local Bridge Program Funds For

Village of Augusta Bridge # STR 4666

WHEREAS, the Washington Street Bridge over the canal of Augusta Creek in the Village of Augusta, Kalamazoo County, Michigan, was constructed in 1921 as a steel I-beam structure and is in poor condition; and

WHEREAS, the current deterioration places a risk on the longevity of the bridge, the service it provides and its value as an important transportation system asset with a current load rating of 5 tons; and

WHEREAS, the investment in the complete bridge replacement will improve the condition of the bridge, avoiding more costly repairs in the future; and

WHEREAS, the Village of Augusta has prepared an application for Local Bridge Program Funds to replace this structure; and

WHEREAS, the Village Council will consider the application for Local Bridge Program Funds and authorize the submission of the application for Local Bridge Program Funds for FY 2022.

NOW, THEREFORE, BE IT RESOLVED that the Kalamazoo Area Transportation Study Technical Committee supports the consideration of the Village of Augusta application for Local Bridge Program Funds.

By _______________________________ Dated: March 14, 2018 Chair

Meeting Materials Page 81 of 83

Page 82: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

RESOLUTION OF SUPPORT

FOR TRANSPORTATION ALTERNATIVES PROJECT

FOR

STADIUM DRIVE SHARED-USE NON-MOTORIZED FACILITY WITHIN THE OSHTEMO DOWNTOWN DEVELOPMENT AUTHORITY AREA (8TH STREET TO 617

FEET WEST OF QUAIL RUN DRIVE)

WHEREAS, the Federal Transportation Act provides funding towards transportation alternatives for pedestrian and bicycle facilities, access to public transportation, enhanced mobility and safety, and the Michigan Department of Transportation is soliciting new candidate projects for Transportation Alternatives Program (TAP) grants; and

WHEREAS, Oshtemo Township has identified an improvement project on Stadium Drive, a public road that is within the municipal jurisdiction of Oshtemo Township; and

WHEREAS, the Kalamazoo Area Transportation Study (KATS) awarded Oshtemo Township a local TAP grant for 2020 to construct a six-foot wide shared-use pathway on both sides of Stadium Drive from 11th Street to 617 feet west of Quail Run Drive and constructing both segments of the non-motorized facility at the same time would be a cost-effective use of Township funds; and

WHEREAS, Oshtemo Township created the Go! Green Oshtemo Master Plan and Non-motorized update wherein the construction of a non-motorized facility along Stadium Drive is a highest priority non-motorized facility for Oshtemo Township; and

WHEREAS, Oshtemo Township approved and submitted an application to the Road Commission of Kalamazoo County to build a non-motorized facility within the public right-of-way, and provided preliminary design plans as a basis to initiate negotiations with the Road Commission of Kalamazoo County for Oshtemo to be responsible for the grant’s required local matching funds plus all non-eligible project costs estimated to be $400,000; and

WHEREAS, the Road Commission of Kalamazoo County has accepted said application for a non-motorized facility improvement in the form of a six-foot wide shared-use pathway, along both sides of Stadium Drive, providing barrier-free non-motorized access, a connector to commercial centers adjacent to Stadium Drive, plus necessary pedestrian access to single and multi-family housing within this well-traveled corridor; and

WHEREAS, Oshtemo Township caused to be created a Downtown Development Authority along Stadium Drive and 9th Street whose principal purpose is tax increment financing to revitalize and preserve the economic and social vitality of the corridor, and whose initial plan has adopted as its principle effort the provision of non-motorized facilities; and

WHEREAS, upon ratification of the award of the funding and execution by the respective local authorities (Road Commission of Kalamazoo and Oshtemo Township) of necessary inter-

Meeting Materials Page 82 of 83

Page 83: TO: Kalamazoo Area Transportation Study Technical ......2019/03/03  · 2019 206204 CON Van Buren County E Red Arrow Hwy 26th St. to 28th St. Bike/Pedestrian Facility Construct 5ft

local agreements for the Transportation Alternatives Projects, the parties will proceed toward construction letting by summer of 2020; and

WHEREAS, Oshtemo Township, within its Non-Motorized Facility Agreement with the Road Commission of Kalamazoo County approved by unanimous vote of the Oshtemo Township Board on March 13, 2018, will provide engineering documents for the non-motorized facility, obtain all permits, and fund potential cost overruns and non-participating items, and maintain the Stadium Drive non-motorized facility in perpetuity.

NOW, THEREFORE, BE IT RESOLVED that the Kalamazoo Area Transportation Study Technical Committee recognizes the importance of a non-motorized facility on this heavily trafficked corridor and supports Oshtemo Township’s application for TAP grant funding.

___________________________________ ____________ Christopher Forth, Chairperson Date Kalamazoo Area Transportation Study Technical Committee

Meeting Materials Page 83 of 83