Tony [email protected]
“GridPP – Year 2 to Year 3”, Collaboration Meeting, Bristol, 22 September 2003
Tony Doyle - University of Glasgow
OutlineOutline
• Challenges • Management• The Project Map• GridPP Status:
two years on..• UK Grid Users• Deployment – LCG
and UK perspective• Current Resources• EDG 2.0/LCG 1.0
Deployment Status
• Accounting
• Today’s Operations
• Future Operations Planning
• Middleware Status
• Middleware Evolution
• GridPP2 Planning Status
• Dissemination
• Summary
Tony Doyle - University of Glasgow
The Challenges Ahead: The Challenges Ahead: Event SelectionEvent Selection
LEVEL-1 Trigger Hardwired processors (ASIC, FPGA) Pipelined massive parallel
HIGH LEVEL Triggers Farms of
processors
10-9 10-6 10-3 10-0 103
25ns 3µs hour yearms
Reconstruction&ANALYSIS TIER0/1/2
Centers
ON-lineOFF-line
sec
Giga Tera Petabit
9 or
ders
of
mag
nitu
de
The HIGGS
All interactions
Tony Doyle - University of Glasgow
The Challenges Ahead: The Challenges Ahead: ComplexityComplexity
Understand/interpret data via numerically intensive simulations:• e.g. ATLAS Monte Carlo (gg H bb)
182 sec/3.5 MB event on 1 GHz linux box
• Many events– ~109 events/experiment/year– >~1 MB/event raw data– several passes required
Worldwide Grid computing requirement (2007):
~300 TeraIPS (100,000 of today’s fastest processors
connected via a Grid)
16 Million channels
100 kHzLEVEL-1 TRIGGER
1 MegaByte EVENT DATA
200 GigaByte BUFFERS500 Readout memories
3 Gigacell buffers
500 Gigabit/s
Gigabit/s SERVICE LAN PetaByte ARCHIVE
Energy Tracks
Networks
1 Terabit/s(50000 DATA CHANNELS)
20 TeraIPS
EVENT BUILDER
EVENT FILTER
40 MHzCOLLISION RATE
Charge Time Pattern
Detectors
Grid Computing Service 300 TeraIPS
Tony Doyle - University of Glasgow
The Challenges Ahead: The Challenges Ahead: Experiment Requirements: UK onlyExperiment Requirements: UK only
CPU
0
2000
4000
6000
8000
10000
12000
2004 2005 2006 2007
Year
kS
I20
00
ye
ar
ATLAS
CMS
LHCb
ALICE
Phenomenology
ZEUS
UKQCD
UKDMC
MINOS
MICE
LISA
D0
CDF
BaBar
ANTARES
LHC
NonLHC
Disk
0
500
1000
1500
2000
2500
2004 2005 2006 2007
Year
TB
ATLASCMSLHCbALICEPhenomenologyUKQCDUKDMCMINOSMICED0CRESSTCDFBaBarANTARES
LHC
NonLHC
Tape
0
500
1000
1500
2000
2500
3000
2004 2005 2006 2007
Year
TB
ATLASCMS
LHCb
ALICEUKDMC
MINOS
MICED0
ANTARES
LHC
NonLHC
Total Requirement:
Year 2004 2005 2006 2007
CPU [kSI2000] 2395 4066 6380 9965
Disk [TB] 369 735 1424 2285
Tape [TB] 376 752 1542 2623
Tony Doyle - University of Glasgow
GridPP ManagementGridPP Management
CB (20 members) meets half-yearly to provide Institute overview
PMB (12 members) meets weekly [via VC] to provide management of project
TB (10 members) meet as required in response to technical needs and regularly via phone
EB (14 members) meet quarterly to provide experiments input
Tony Doyle - University of Glasgow
GridPP Project OverviewGridPP Project Overview
1. 1 2. 1 3. 1 4. 1 5. 1 6. 1 7. 1
1. 2 2. 2 3. 2 4. 2 5. 2 6. 2 7. 2
1. 3 2. 3 3. 3 4. 3 5. 3 6. 3 7. 3
1. 4 2. 4 3. 4 4. 4 5. 4
1. 5 2. 5 3. 5 4. 5
Navigate down
External link 2. 6 3. 6 4. 6 Link to goals
2. 7 3. 7
2. 8 3. 8
System
UK Grid Rollout
Data Challenges
Dissemination
Tier-1 Centre
Tier-A Centre
Applications
CERN DataGrid Applications
LCG Creation WP1
WP2
ResourcesInfrastructure
Presentation Deployment of
related areasGANGA/GaudiATLAS/LHCb
resources
Participation in
of GridPP
Monitoring of
UK e-Science
Computing Fabric
Grid Technology
Tier-2 Centres
CMSMonte Carlo
WP3
WP4
LHCb
Standards
Open SourceImplementation
Grid Deployment
resourcesEngagementof UK groups
Attract newParticle Physics
UK Testbed
resources
WP6
WP7
WP5
SAM Framework
UKQCD
BaBar
Integration
Integration
Applications
QCD Application
Other
Data Analysis
CDF/D0
GridPP Goal
ATLAS
in the UK for the use of the Particle Physics communityTo develop and deploy a large scale science Grid
5Interoperability
International
WP8
6 71 2 3 4
Worldwide
Tony Doyle - University of Glasgow
GridPP Status: The Project MapGridPP Status: The Project Map
1 . 1 2 . 1 3 . 1 4 . 1 5 . 1 6 . 1 7 . 1
1 . 1 . 1 1 . 1 . 2 1 . 1 . 3 1 . 1 . 4 2 . 1 . 1 2 . 1 . 2 2 . 1 . 3 2 . 1 . 4 3 . 1 . 1 3 . 1 . 2 3 . 1 . 3 3 . 1 . 4 4 . 1 . 1 4 . 1 . 2 4 . 1 . 3 4 . 1 . 4 5 . 1 . 1 5 . 1 . 2 5 . 1 . 3 6 . 1 . 1 6 . 1 . 2 6 . 1 . 3 6 . 1 . 4 7 . 1 . 1 7 . 1 . 2 7 . 1 . 3 7 . 1 . 41 . 1 . 5 2 . 1 . 5 2 . 1 . 6 2 . 1 . 7 2 . 1 . 8 3 . 1 . 5 3 . 1 . 6 3 . 1 . 7 3 . 1 . 8 4 . 1 . 5 4 . 1 . 6 4 . 1 . 7 4 . 1 . 8 6 . 1 . 5
2 . 1 . 9 3 . 1 . 9 3 . 1 . 1 0 4 . 1 . 9
1 . 2 2 . 2 3 . 2 4 . 2 5 . 2 6 . 2 7 . 2
1 . 2 . 1 1 . 2 . 2 1 . 2 . 3 1 . 2 . 4 2 . 2 . 1 2 . 2 . 2 2 . 2 . 3 2 . 2 . 4 3 . 2 . 1 3 . 2 . 2 3 . 2 . 3 3 . 2 . 4 4 . 2 . 1 4 . 2 . 2 4 . 2 . 3 4 . 2 . 4 5 . 2 . 1 5 . 2 . 2 5 . 2 . 3 6 . 2 . 1 6 . 2 . 2 6 . 2 . 3 7 . 2 . 1 7 . 2 . 2 7 . 2 . 31 . 2 . 5 1 . 2 . 6 2 . 2 . 5 2 . 2 . 6 2 . 2 . 7 3 . 2 . 5 3 . 2 . 6 3 . 2 . 7 3 . 2 . 8 4 . 2 . 5 4 . 2 . 6 4 . 2 . 7
3 . 2 . 9
1 . 3 2 . 3 3 . 3 4 . 3 5 . 3 6 . 3 7 . 3
1 . 3 . 1 1 . 3 . 2 1 . 3 . 3 1 . 3 . 4 2 . 3 . 1 2 . 3 . 2 2 . 3 . 3 2 . 3 . 4 3 . 3 . 1 3 . 3 . 2 3 . 3 . 3 3 . 3 . 4 4 . 3 . 1 4 . 3 . 2 4 . 3 . 3 4 . 3 . 4 5 . 3 . 1 5 . 3 . 2 5 . 3 . 3 6 . 3 . 1 6 . 3 . 2 6 . 3 . 3 6 . 3 . 4 7 . 3 . 1 7 . 3 . 2 7 . 3 . 3 7 . 3 . 41 . 3 . 5 1 . 3 . 6 2 . 3 . 5 2 . 3 . 6 2 . 3 . 7 3 . 3 . 5 3 . 3 . 6 4 . 3 . 5
1 . 4 2 . 4 3 . 4 4 . 4 5 . 4
1 . 4 . 1 1 . 4 . 2 1 . 4 . 3 1 . 4 . 4 2 . 4 . 1 2 . 4 . 2 2 . 4 . 3 2 . 4 . 4 3 . 4 . 1 3 . 4 . 2 3 . 4 . 3 3 . 4 . 4 4 . 4 . 1 4 . 4 . 2 4 . 4 . 3 4 . 4 . 4 5 . 4 . 1 5 . 4 . 2 5 . 4 . 3 5 . 4 . 41 . 4 . 5 1 . 4 . 6 1 . 4 . 7 1 . 4 . 8 2 . 4 . 5 2 . 4 . 6 2 . 4 . 7 3 . 4 . 5 3 . 4 . 6 3 . 4 . 7 3 . 4 . 8 4 . 4 . 5 4 . 4 . 6 5 . 4 . 51 . 4 . 9 3 . 4 . 9 3 . 4 . 1 0 M e t r ic O K 1 . 1 . 1
M e t r ic n o t O K 1 . 1 . 1 1 . 5 2 . 5 3 . 5 4 . 5 T a s k c o m p le t e 1 . 1 . 1
1 . 5 . 1 1 . 5 . 2 1 . 5 . 3 1 . 5 . 4 2 . 5 . 1 2 . 5 . 2 2 . 5 . 3 2 . 5 . 4 3 . 5 . 1 3 . 5 . 2 3 . 5 . 3 3 . 5 . 4 4 . 5 . 1 4 . 5 . 2 4 . 5 . 3 4 . 5 . 4 T a s k o v e r d u e 1 . 1 . 11 . 5 . 5 1 . 5 . 6 1 . 5 . 7 1 . 5 . 8 2 . 5 . 5 2 . 5 . 6 2 . 5 . 7 3 . 5 . 5 3 . 5 . 6 3 . 5 . 7 6 0 d a y s 1 . 1 . 11 . 5 . 9 1 . 5 . 1 0 T a s k n o t d u e s o o n 1 . 1 . 1
N o l o n g e r a c t i v e 1 . 1 . 1 2 . 6 3 . 6 4 . 6 N o T a s k o r m e t r i c
2 . 6 . 1 2 . 6 . 2 2 . 6 . 3 2 . 6 . 4 3 . 6 . 1 3 . 6 . 2 3 . 6 . 3 3 . 6 . 4 4 . 6 . 1 4 . 6 . 2 4 . 6 . 32 . 6 . 5 2 . 6 . 6 2 . 6 . 7 2 . 6 . 8 3 . 6 . 5 3 . 6 . 6 3 . 6 . 7 3 . 6 . 8 N a v i g a t e u p
2 . 6 . 9 3 . 6 . 9 3 . 6 . 1 0 3 . 6 . 1 1 3 . 6 . 1 2 N a v i g a t e d o w n
E x t e r n a l li n k 2 . 7 3 . 7 L i n k t o g o a l s
2 . 7 . 1 2 . 7 . 2 2 . 7 . 3 2 . 7 . 4 3 . 7 . 1 3 . 7 . 2 3 . 7 . 3 3 . 7 . 42 . 7 . 5 2 . 7 . 6 2 . 7 . 7 2 . 7 . 8 3 . 7 . 5 3 . 7 . 6
2 . 8 3 . 8
2 . 8 . 1 2 . 8 . 2 2 . 8 . 3 2 . 8 . 4 3 . 8 . 1 3 . 8 . 2 3 . 8 . 32 . 8 . 5
T o d e v e l o p a n d d e p l o y a l a r g e s c a l e s c i e n c e G r i di n t h e U K f o r t h e u s e o f t h e P a r t i c l e P h y s i c s c o m m u n i t y
P r e s e n t a t i o n D e p lo y m e n t
5 6 74
1 1 - S e p - 0 3S t a t u s D a t e
I n t . S t a n d a r d s
O p e n S o u r c e
W o r l d w i d e I n t e g r a t i o n
U K I n t e g r a t i o n
M o n i t o r i n g
D e v e lo p in gE n g a g e m e n t
P a r t i c i p a t i o n
O t h e r
D a t a C h a l l e n g e s
R o l l o u t
T e s t b e d
W P 7
A T L A S / L H C b
C M S
B a B a r
C D F / D O
U K Q C D
W P 1
W P 2
W P 3
L C G C r e a t i o n
A p p li c a t io n s
C E R N D a t a G r i d A p p l i c a t i o n s I n f r a s t r u c t u r e
D u e w it h in
A T L A S
G r i d P P G o a l
R e s o u r c e sI n t e r o p e r a b i l i t y D i s s e m i n a t i o n
T i e r - 1
T i e r - A
L H C b T i e r - 2
W P 8
1 2 3
D e p lo y m e n t
W P 4
W P 5
F a b r i c
T e c h n o lo g y
W P 6
U p d a t e
C l e a r
Tony Doyle - University of Glasgow
Quarterly ReportingQuarterly Reporting
Q9 Q10 Q11 Q12
Actual Planned Actual Planned Actual Planned Actual Planned
1.50 0.60 1.30 0.60 0.60 0.60
2.25 1.50 2.50 1.50 1.50 1.50
0.75 1.50 0.50 1.50 1.50 1.50
3.00 3.00 3.00 3.00 3.00 3.00
1.50 0.54 1.60 2.40 2.40 2.40
0.38 1.20 0.60 0.00 0.00 0.00
1.28 0.99 1.00 0.90 0.90 0.90
0.39 0.00 0.00 0.00 0.00
2.40 2.40 2.40 2.40 2.40 2.40
0.90 1.20 0.00 1.20 1.20 1.20
3.00 3.00 3.00 3.00 3.00 3.00
3.00 3.00 3.00 3.00 3.00 3.00
1.80 0.00 2.00 1.50 1.50 1.50
3.00 3.00 3.00 3.00 3.00 3.00
3.00 3.00 3.00 3.00
0.00 3.00 3.00 2.00 0.00
1.50 1.50 1.00 1.50 1.50 1.50
1.50 1.50 1.50 1.50 1.50 1.50
3.00 3.00 2.00 3.00 3.00 1.00
3.00 3.00 3.00 3.00 3.00 3.00
3.00 3.00 3.00 3.00 3.00 3.00
3.00 3.00 3.00 3.00 3.00 3.00
3.00 3.00 3.00 3.00 3.00 3.00
3.00 3.00 3.00 3.00 3.00 3.00
1.50 1.50 1.50 1.50 1.50 1.50
1.75 1.50 1.50 1.50 1.50 1.50
1.75 1.50 1.50 1.50 1.50 1.50
1.50 1.50 1.50 1.50 1.50 1.50
1.50 1.50 1.50 1.50 1.50 1.50
3.00 3.00 3.00 3.00 3.00 3.00
3.00 3.00 2.00 3.00 3.00 3.00
3.00 3.00 3.00 3.00 3.00 3.00
3.00 3.00 3.00 3.00 3.00 3.00
3.00 3.00 3.00 3.00 3.00 3.00
3.00 3.00 3.00 3.00 3.00 3.00
3.00 3.00 3.00 3.00 3.00 3.00
1.50 1.50 1.50 1.50 1.50 1.50
1.90 1.50 1.40 1.50 1.50 1.50
1.50 1.50 1.50 1.50 1.50 1.50
1.50 1.50 1.50 1.50 1.50 1.50
3.00 3.00 3.00 3.00 3.00 3.00
3.00 3.00 3.00 3.00 3.00 3.00
3.00 3.00 3.00 3.00 3.00 3.00
3.00 3.00 3.00 3.00
3.00 3.00 3.00 3.00 3.00 3.00
3.00 3.00 3.00 3.00 3.00 3.00
3.00 3.00 3.00 3.00 3.00 3.00
0.00 0.00 1.50 1.50
1-Jul-031-Jan-03 1-Apr-03 1-Oct-03Q Start Date
Initial Surname WG ExptPost/DescriptionInstituteRoute
J Gordon WP5 eSC RALL Cornwall WP3 PPD RALL Cornwall WP7 PPD RALS Fisher WP3 PPD RALD Kelsey WP7 PPD RALD Kelsey WP6 PPD RALB Saunders WP6 PPD RALT Folkes WP5 eSC RALA Sansum WP6 eSC RALR Tasker WP7 BITD RALR Tam WP5 PPD RALS Traylen WP6 PPD RALJ Jensen WP5 eSC RALG Kuznetsov LHCb PPD RALS Burke WP8 EUDG - WP8 topupRALT Shah WP5 PPD RALD Colling WP1 DGPP: WP6/WP1ImperialD Colling WP6 DGPP: WP6/WP1ImperialW Bell WP2 DGPP: WP2GlasgowR Cordenonsi WP3 DGPP: WP3QMULA McNab WP6 DGPP: WP6ManchesterC Cioffi WP8 LHCb DGPP: WP8OxfordM Gardner WP8 Atlas DGPP: WP8RHULH Talini WP8 CMS DGPP: WP8ImperialF Brochu WP8 Atlas DGPP: WP8CambridgeA Washbrook WP4 DGPP: WP5/WP4LiverpoolA Washbrook WP5 DGPP: WP5/WP4LiverpoolO Moroney WP6 DGPP: WP6BristolO Moroney WP8 CMS DGPP: WP8BristolP Mealor WP7 DGPP: WP7UCLG Fairey WP7 DGPP: WP7 + spptManchesterG McCance WP2 DGPP: WP2GlasgowA Holt WP4 DGPP: WP4EdinburghA Soroko ATLAS GANGA1OxfordK Harrison LHCb GANGA2CambridgeA Tan ATLAS ATLAS BirminghamB MacEvoy CMS CMS ImperialJ Nebrensky CMS CMS BrunelT Barrass CMS CMS BristolT Barrass BaBar Babar DBBristolJ Martyniak BaBar Babar JSImperialA Forti BaBar Babar MDManchesterR Walker D0 SAM 1 ImperialA Flavell CDF SAM 2 GlasgowS Stonjek CDF SAM 3 OxfordD Evans D0 D0 LancasterJ Perry UKQCD UKQCD EdinburghM Egbert UKQCD UKQCD Edinburgh
Quarterly reporting allows comparison of delivered effort with expected effort
Feedback loop as issues arise
Tony Doyle - University of Glasgow
Funded Effort Breakdown Funded Effort Breakdown (Snapshot 2003Q3)(Snapshot 2003Q3)
Applications18%
LCG35%
EDG30%
Tier-1/A11%
Management6%
LCG effort is largest single area of GridPP
Future project priorities focussed on LCG and EGEE
Tony Doyle - University of Glasgow
GridPP Status: SummaryGridPP Status: Summary
• GridPP1 has now completed 2 ex 3 years
• All metrics are currently satisfied
• 103 of 182 tasks are complete
• 70 tasks not yet complete or overdue
• 9 tasks are overdue:– 6 are associated with LCG
• 2 of these are trivial (definition of future milestones)• 4 of these are related to the delay in LCG-1
– 2 are associated with applications (CMS and D0)– 1 is associated with the UK infrastructure (test of a
heterogeneous testbed)
Tony Doyle - University of Glasgow
Risk Register (Status April 03)Risk Register (Status April 03)
ID NameLi Im Risk Li Im Risk Li Im Risk Li Im Risk Li Im Risk Li Im Risk
R1 Recruitment/retention difficulties 1 2 2 2 2 4 2 2 4 2 2 4R2 Sudden loss of key staff 1 4 4 1 3 3 1 3 3 1 3 3R3 Minimal Contingency 1 2 2 2 2 4 1 2 2R4 GridPP deliverables late 1 3 3 4 2 8R5 Sub-components not delivered to project 2 4 8 2 3 6 2 3 6 2 3 6R6 Non take-up of project results 2 1 2 1 4 4 1 4 4R7 Change in project scope 1 1 1 2 2 4 1 1 1R8 Bad publicity 2 2 4 1 3 3 1 3 3R9 No publicity 2 1 2
R10 External software dependence 2 4 8 1 4 4 2 3 6R11 Lack of monitoring of staff 1 2 2 2 2 4 1 3 3 1 2 2R12 Withdrawal of an experiment 1 4 4 1 4 4 1 2 2R13 Lack of cooperation between Tier centres 1 4 4 1 2 2R14 Scalablity problems 3 3 9 2 3 6 1 3 3R15 Software maintainability problems 3 2 6 1 3 3R16 Technology shifts 1 3 3 1 4 4 1 3 3R17 Repitition of research 3 2 6R18 Lack of funding to meet LCG PH-1 goals 1 3 3R19 Adequate persistency solution not ready 1 3 3R20 Conflicting software requirements 4 1 4 2 2 4R21 Tier-A hardware fails to meet requirements 1 3 3R22 Other Hardware fails to meet requirements 1 1 1R23 Hardware physical risk (large scale) 1 4 4R24 Hardware physical risk (small scale) 2 2 4R25 Hardware procurement problems 2 2 4R26 LAN Bottlenecks 2 1 2R27 Tier-2 organisation fails 1 2 2R28 Tier-2 hardware not used as planned 2 1 2R29 SYSMAN effort inadequate 3 3 9R30 Firewalls interfere with Grid 1 3 3R31 Inablility to establish trust relationships 2 2 4R32 Security inadequate to operate Grid 1 3 3R33 GGF does not establish standards 1 3 3R34 Minimal open source code development 2 2 4R35 Failure of international cooperation 1 4 4 1 4 4R36 e-Science and GridPP divergence 2 2 4R37 Institutes do not embrace Grid 1 3 3R38 Grid is not stable enough for use 4 2 8R39 Delay of the LHC 2 2 4R40 Lack of future funding 2 4 8 2 2 4R41 Network backbone failure 0 4 0R42 Network backbone bottleneck 1 2 2
Alt-i-r
Interop.GridPP LCG EDG Apps Infrast.
Scaling up to aproduction system(LCG-1 deployment)
System managementeffort at UK Tier-2 sites(being addressed as part of GridPP2)
Tony Doyle - University of Glasgow
UK Certificates andUK Certificates andVO membership VO membership
1. UK e-Science CA now used in production EDG testbed
2. PP “users” engaged from many institutes
3. UK participating in 6 ex 9 EDG VOs
0 20 40 60 80 100 120
BaBar
Eobs
Iteam
LHCb
Alice
BioMe
CMS
Atlas
WP6
Members
UK Members
1.
2. 3.
Tony Doyle - University of Glasgow
• Certification and distribution process established • Middleware package – components from
– European DataGrid (EDG2.0)
– US (Globus, Condor, PPDG, GriPhyN) Virtual Data Toolkit, VDT 1.1
• Agreement reached on principles for registration and security• RAL to provide the initial grid operations centre• FZK to operate the call centre
• Initial service being deployednow to 10 centres US, Europe, Asia
• Expand to other centres assoon as the service is stable
LCG
Academia Sinica Taipei, BNL, CERN, CNAF, FNAL,FZK, IN2P3 Lyon, Moscow State Univ., RAL, Univ. Tokyo
LHC Computing Grid ServiceLHC Computing Grid Service
Tony Doyle - University of Glasgow
UK Deployment OverviewUK Deployment Overview
• Significant resources within EDG. Currently being upgraded to EDG2.
• Integrating EDG on farms has been repeated many times but it is difficult.
• Sites are keen to take part within EDG2 currently, with LCG1 deployment after this.
• By the end of the year many HEP farms plan to be contributing to LCG1 resources.
• Basis of Deployment Input to LCG Plan.
• Input from Tier-1 (~50%) initially and four distributed Tier-2’s (50%) on ~Q1 2004 timescale.
CPU(kSI2K)
Disk TB
Support FTE
Tape TB
CERN 700 160 10.0 1000
Czech Repub 60 5 2.5 5
France 420 81 10.2 540
Germany 207 40 9.0 62
Holland 124 3 4.0 12
Italy 507 60 16.0 100
Japan 220 45 5.0 100
Poland 86 9 5.0 28
Russia 120 30 10.0 40
Taiwan 220 30 4.0 120
Spain 150 30 4.0 100
Sweden 179 40 2.0 40
Switzerland 26 5 2.0 40
UK 1656 226 17.3 295USA 801 176 15.5 1741
Total 5600 1169 120.0 4223
LCG
Resources committed for 1Q04
Tony Doyle - University of Glasgow
EDG 2.0 Deployment Status EDG 2.0 Deployment Status 12/9/0312/9/03
• RAL (Tier1A): Up and running with 2.0.1. UI gppui04 available (as part of CSF) and offer to give access to LCFGng node to help people compare with their own LCFGng setup.
• IC: Existing WP3 testbed site is at 2.0.0. Standard 2.0 RB available• UCL: Trying to go to 2.0: SE up so far.• QMUL: 2.0 installation ongoing.• RAL (PPD): 2.0.0 site up and running.• Oxford: wait until October for 2.0. • Birmingham: Working on getting a 2.0 site up next week• Bristol: WP3 testbed site at 2.0.0. Also doing a new 2.0 site install.
UI and MON up, still doing CE, SE and WN.• Cambridge to follow.• Manchester: Trying to get 2.0.1 set up.• Glasgow: Concentrating on commissioning new hardware during
the next month. Wait until then before going to 2.0.• Edinburgh to follow.
Tony Doyle - University of Glasgow
Tier-1 @ RALTier-1 @ RAL
CE SE
LCG 1.0/EDG 2.0
5xWN
LCG Testbed
CE
LCG 1.0/EDG 2.0
230xWN
Tier-1/A
CE SE
EDG 2.0
WP3 Testbed
MON
CE SE
EDG 2.0
1xWN
EDG Dev Testbed
MON SE
ADS
•UI within CSF.
•NM for EDG2.
•Top level MDS for EDG.
•Various WP3 and WP5 dev nodes.
•VOMS for DEV TB.
•http://ganglia.gridpp.rl.ac.uk/
SE
LCG0 Testbed
CE 1xWN
Tony Doyle - University of Glasgow
London Grid:London Grid:Imperial CollegeImperial College
CE SE
EDG 2.0
EDG Testbed
WNs
CE
EDG 2.0
WNs
BaBar Farm
CE SE
CMS-LCG0
CMS-LCG0
WN
CE SE
EDG 2.0
1xWN
WP3 Testbed
MON
•RB for EDG 2.0.
•Plan to be in LCG1 and other testbeds.
Tony Doyle - University of Glasgow
London Grid:London Grid:Queen Mary and UCLQueen Mary and UCL
CE SE
EDG 1.4
1xWN
EDG Testbed
32xWN
• Queen Mary CE also feeds EDG jobs to 32 node e-Science farm.
•Plan to have LCG1/EDG2 running for the end of the year.•Expansion with SRIF grants.(64WN+2TB in Jan 2004, 100WN + 8TB in Dec 2004.)
•http://194.36.10.1/ganglia-webfrontend
CE SE
EDG 1.4
1xWN
EDG Testbed
•UCL Network Monitors for WP7 development.
•SRIF bid in place for 200 CPUs for the end of the year to join LCG1.
Tony Doyle - University of Glasgow
Southern Grid:Southern Grid:BristolBristol
CE SE
EDG 2.0
1xWN
EDG Testbed
CE SE
EDG 2.0
1xWN
WP3 Testbed
MON
CE SE
CMS-LCG0
CMS/LHCb Farm
24xWN
CE SE
EDG 1.4
BaBar Farm
78xWN
•GridPP RC.
•Plan to join LCG1
Tony Doyle - University of Glasgow
Southern Grid:Southern Grid:Cambridge and OxfordCambridge and Oxford
CE SE
EDG 1.4
15xWN
EDG Testbed •Cambridge farm shared with local NA-48, GANGA users.
•Some RH73 WNs for ongoing ATLAS challenge.
•3TB GridFTP-SE.
•Plan to join LCG1/EDG2 later in the year with an extra 50 CPUs.
•EDG jobs will be fed into local e-Science farm.
•http://farm002.hep.phy.cam.ac.uk/cavendish/
CE SE
EDG 1.4
2xWN
EDG Testbed•Oxford: Plan to join EDG2/LCG1.
•Nagios monitoring has been set up.
•(RAL is also evaluating Nagios)
•Planning to send EDG jobs into 10 WN CDF farm.
•128 node cluster being ordered now.
Tony Doyle - University of Glasgow
Southern Grid:Southern Grid:RAL PPD and BirminghamRAL PPD and Birmingham
CE SE
EDG 2.0
9xWN
EDG Testbed
CE SE
EDG 2.0
1xWN
WP3 Testbed
MON
•PPD User Interface
•Part of Southern Tier2 Centre within LCG1.
•50 CPUs and 5TB of disk expected for the end of year.
CE SE
EDG 1.4
1xWN
EDG Testbed•Birmingham: Expansion to 60 CPUs and 4TBs.
•Expect to participate within LCG1/EDG2
Tony Doyle - University of Glasgow
NorthGrid: NorthGrid: Manchester and LiverpoolManchester and Liverpool
CE SE(1.5TB)
EDG 1.4
80xWN
CE SE(5TB)
EDG 1.4
60xWN
CE SE
EDG 1.4
9xWN
EDG Testbed BaBar Farm DZero Farm
•GridPP and BaBar VO Servers.
•User Interface
•Plan that DZero farm will join LCG.
•SRIF bid in place for significant HEP resources.
CE SE
EDG 1.4
1xWN
EDG Testbed
•Liverpool plan to follow EDG 2, possibly integrating newly installed Dell (funded by NW Development Agency) and BaBar farm. Largest single Tier-2 resource.
Tony Doyle - University of Glasgow
ScotGrid: Glasgow, Edinburgh ScotGrid: Glasgow, Edinburgh and Durhamand Durham
CE SE
EDG 1.4
ScotGRID
59xWN
• WNs on a private network with outbound NAT in place.
• Various WP2 development boxes.
• 34 dual blade servers just arrived. 5TB FastT500 expected soon.
• Shared resources (CDF and Bioinformatics)
CE SE
EDG 2.0
WP3 Testbed
MON
• Edinburgh: 24TB FastT700 and 8-way server just arrived.
• Durham: existing farm available.
• Plan to be part of LCG.
CDF
LHC BIO
Tony Doyle - University of Glasgow
Testbed StatusTestbed StatusSummer 2003Summer 2003
UK-wide developmentusing EU-DataGrid tools (v1.47).Deployed during Sept 02-03. Currently being upgraded to v2.0.See http://www.gridpp.ac.uk/map/
Tony Doyle - University of Glasgow
Meeting Current LHC Requirements: Meeting Current LHC Requirements: Experiment AccountingExperiment Accounting
Number of Normalised Processors per country48
9
765
900
0
136
105
332
15
154
297
218
326
0
256
348
127
1156
758
1 2 3 4 5 6 7 8 9 10 11 12 13
14 15 16 17 18 19
Regional Centre Simulation Hits No Pile Up 2x1033 2x1044 NassIDBristol/RAL 0.55 0.33 0.04 0.06 0.02 20Caltech 0.17 0.15 0.00 0.15 0.00 6CERN 0.89 2.20 1.40 2.66 2.25 300Fermilab 0.35 0.41 0.00 0.25 0.33 70ICST&M 0.88 0.59 0.50 0.15 0.12 84IN2P3 0.20 0.00 0.00 0.00 0.00 1INFN 1.55 1.18 0.40 0.72 0.71 99Moscow 0.43 0.14 0.14 0.00 0.00 41UCSD 0.34 0.30 0.00 0.29 0.30 80UFL 0.54 0.04 0.00 0.04 0.04 11USMOP 0.00 0.00 0.00 0.00 0.00 1Wisconsin 0.07 0.08 0.00 0.06 0.00 12
TOTAL 5.94 5.40 2.47 4.36 3.77
Experiment-driven project.Priorities determined by Experiments Board.
Tony Doyle - University of Glasgow
Tier-1/A AccountingTier-1/A Accounting
LHCb
ATLAS
CMS
CMS
Monthly accounting:Online Ganglia-based monitoring, see:http://www.gridpp.ac.uk/tier1a/Last month: CMS and BaBar jobs.
Annual accounting:ATLAS, CMS and LHCb jobs. Generally dominated by BaBar since January.
BaBar
BaBar
Tony Doyle - University of Glasgow
Today’s OperationsToday’s Operations
1. Support Team • built from sysadmins. 4 funded by
GridPP to work on EDG WP6, the rest are site sysadmins.
2. Methods• Email list, phone meetings,
personal visits, job submission monitoring
• RB, VO, RC for UK use to support non-EDG use
3. Rollout• Experience from RAL in EDG dev
testbeds and IC and Bristol in CMS testbeds
• 10 sites have been part of EDG app testbed at one time
Tony Doyle - University of Glasgow
0
1
2
3
4
5
6
7
8
9
10
FT
EOperations Manager
Tier-2 Expert
Tier-2 Expert
Tier-2 Expert
Tier-2 Expert
Tier-1 Expert
Tier-1 Expert
Applications Expert
University WP6 Posts
RAL WP6 Post
WP8 Post
Testbed Team Production Team
GridPP1 GridPP2
GridPP2 OperationsGridPP2 Operations
• To move from testbed to production, GridPP plans a bigger team with a full-time Operations Manager
• Manpower will be from the Tier-1 and Tier-2 Centres who will contribute to the Production Team
• The team will run a UK Grid which will belong to various grids (EDG, LCG,..) and also support other experiments
Ta
gged
re
leas
e s
elec
ted
for
cert
ifica
tion
Ce
rtifi
ed r
ele
ase
sele
cte
d fo
r d
eplo
yme
nt
Ta
gged
p
acka
ge
Problem reports
add unittested code to
repository
Run nightly build
& auto. tests
Grid certification
Fix problemsApplication Certification
BuildSystem
CertificationTestbed ~40CPU
ProductionTestbed ~1000CPU
Certified publicrelease
for use by apps.
24x7
Build system
Test Group
WPs
Unit Test Build
Certification
Production
Users
DevelopmentTestbed ~15CPU
Individual WP tests
Integration
Team
Integration
Overall release tests
Releases candidate
Tagged Releases
Releases candidate
Certified Releases
Apps. Representative
s
Tony Doyle - University of Glasgow
LCG OperationsLCG Operations
• RAL has led project to develop an Operations Centre for LCG1– Applied GridPP and MapCenter monitoring to LCG1– Dashboard combining several types of monitoring – Set up a web site with contact information– Developing Security Plan– Accounting (the current priority, building upon
resource centre and experiment accounting)• RAL is also leading the LCG Security Group
– written 4 documents setting out procedures and User Rules
– working with GOC task force on Security Policy
– Risk Analysis and further planning for LCG in 2004
Tony Doyle - University of Glasgow
EGEE Technical Annex:EGEE Technical Annex:nearing completionnearing completion
Tony Doyle - University of Glasgow
EGEEEGEE
Tier1 (16.5 FTE)
UK Team (8 FTE)
UK GSC (2 FTE)
(2FTE)
EGEE ROC(5 FTE)
EGEE CIC(4.5 FTE)
• The UK Production Team will be expanded as part of EGEE ROC and CIC posts to meet EGEE requirements
• To deliver an EGEE grid infrastructure that must also deliver to other communities and projects
• Could do this just within PP (matching funding available) but also want to engage fully with UK Core programme
• Ongoing discussions…
Tony Doyle - University of Glasgow
Possibility for future ~ 1 year timescalePossibility for future ~ 1 year timescale(10/7/03, PC)(10/7/03, PC)
GT2
L2 Grid
Application
GT2
PP Grid
PP Application
EGEE-0 (GT2)
If UK is backing
EGEE (which it is)..
..then it probably
makes sense to
embrace EGEE-0
which will be based upon GT2
… this way we would influence development,
and reap benefit of leverage
Tony Doyle - University of Glasgow
““The Italian Job”The Italian Job”Management structure for the production GridManagement structure for the production Grid
~36 people~36 people
Experiments GRID Projects
Coordination Committee
Management Operations
•Planning/Deployment
• resource Policy usage•Management tools
Central TeamMonitoringAuthorization
Site-man
GridServicesupport
VO support
Usersupport
Application
Grid ResourceCoordination
Experimemt or research org. support
releaseConfigurationmanagement
4p
6p
8p 4p 4p
2pRelease distribution, documentation and porting
EGEE, LCG coord
2p
Tony Doyle - University of Glasgow
Tier-1/A Services [FTE]Tier-1/A Services [FTE]
• High quality data services
• National and International Role• UK Focus for International Grid development
• Highest single priority within GridPP2
Current Planning
CPU 2.0
Disk 1.5
AFS 0.0
Tape 2.5
Core Services 2.0
Operations 2.5
Networking 0.5
Security 0.0
Deployment 2.0
Experiments 2.0
Management 1.5
Total 16.5
Tony Doyle - University of Glasgow
Tier-2 Services [FTE]Tier-2 Services [FTE]
• Four Regional Tier-2 Centres • London: Brunel, Imperial College, QMUL, RHUL, UCL.• SouthGrid: Birmingham, Bristol, Cambridge, Oxford, RAL PPD.• NorthGrid: CLRC Daresbury, Lancaster, Liverpool, Manchester, Sheffield.• ScotGrid: Durham, Edinburgh, Glasgow.
• Hardware provided by Institutes
• GridPP provides added manpower
Role FTE
Tier Centre Experts 4 (taken from those below)
Hardware Support 8
Core Services 4
User Support 2
Specialist Support 6
Total 20
Current Planning
Y 1 Y 2 Y 3
Hardware Support 4.0 8.0 8.0
Core Services 4.0 4.0 4.0
User Support 1.0 2.0 2.0
Specialist Services
Security 1.0 1.0 1.0
Resource Broker 1.0 1.0 1.0
Network 0.5 0.5 0.5
Data Management 2.0 2.0 2.0
VO Management 0.5 0.5 0.5
14.0 19.0 19.0
Existing Staff -4.0 -4.0 -4.0
GridPP2 10.0 15.0 15.0
Total SY 40.0
Tony Doyle - University of Glasgow
Operational RolesOperational Roles
• Core Infrastructure Services (CIC) – Grid information services
– Monitoring services
– Resource brokering
– Allocation and scheduling services
– Replica data catalogues
– Authorisation services
– Accounting services
• Still to be defined fully in EGEE
• Core Operational Tasks (ROC)– Monitor infrastructure, components
and services
– Troubleshooting
– Verification of new sites joining Grid
– Acceptance tests of new middleware releases
– Verify suppliers are meeting SLA
– Performance tuning and optimisation
– Publishing use figures and accounts
Tony Doyle - University of Glasgow
LCG Level 1 MilestonesLCG Level 1 Milestonesproposed to LHCCproposed to LHCC
M1.1 - June 03 First Global Grid Service (LCG-1) available-- this milestone and M1.3 defined in detail by end 2002
M1.2 - June 03 Hybrid Event Store (Persistency Framework) available for general users
M1.3a - November 03 LCG-1 reliability and performance targets achieved
M1.3b - November 03 Distributed batch production using grid services
M1.4 - May 04 Distributed end-user interactive analysis-- detailed definition of this milestone by November 03
M1.5 - December 04 “50% prototype” (LCG-3) available-- detailed definition of this milestone by June 04
M1.6 - March 05 Full Persistency Framework
M1.7 - June 05 LHC Global Grid TDR
Tony Doyle - University of Glasgow
RB Stress Tests (9/9/03): RB Stress Tests (9/9/03): Benchmark for LCG DeploymentBenchmark for LCG Deployment
• Status (LCG report by Ian Bird):
• RB never crashed
• ran without problems at a load of 8.0 for several days in a row 20 streams with 100 jobs each ( typical error rate ~ 2 % still present )
• RB stress test in a job storm of 50 streams , 20 jobs each :– 50% of the streams ran out of connections between UI and
RB. (configuration parameter – but machine constraints)– Remaining 50% streams finished normal ( 2% error rate)– Time between job-submit and return of the command
(acceptance by the RB) is 3.5 seconds. ( independent of number of streams )
• NOTE:RB interrogates all suitable CE's : wide area delay-killer
Tony Doyle - University of Glasgow
Next m/w steps (9/9/03)Next m/w steps (9/9/03)
• Status (LCG report by Ian Bird):Next LCG-1 upgrades:• The same software recompiled with gcc 3.2• New VDT? Based on Globus 2.4? LCG will work on this issue.• Add VOMS• Add RLI? – see discussion of RLS• R-GMA now seems to be off the table *Corrective Action 16/9/03*• Working group to resolve data access issues:
– Components exist: SRM, GFAL, RLS, gridFTP; – need to make coherent based on use-cases and integrate with MSS’s
For more features we would like to apply the simple rule:Add it if and only if
– it is proven to work (by EDG, LCG, together)– it adds some desirable feature or feature requested by users– it makes the user’s application setup significantly simpler or practical– it is required by new user applications
Bug fixing will always have the highest priority.Target release date for 2004 system: November
Tony Doyle - University of Glasgow
RGMA – Status (16/9/03)RGMA – Status (16/9/03)
• Running on WP3, EDG-development and EDG-application testbeds• Application Deployment: 29 CEs, 11 SEs, 10 sites in 6 countries
– RGMA browser access in < 1sec
• Monitoring scripts being run on the testbeds and results linked from the WP3 web page– http://hepunx.rl.ac.uk/edg/wp3/
• Registry replication is being tested on WP3 testbed– Better performance & higher reliability required
• Authentication successfully tested on WP3 testbed• Two known bugs remain
– Excessive threads requiring GOUT machine restart• New code has been developed with extensive unit tests. Now
being tested on WP3 testbed• This new code will support at least 90 sites
– Latest Producer choosing algorithm failing to reject bad LPs – shows up intermittent absence of information
• Revised algorithm needs coding (localised change)
Tony Doyle - University of Glasgow
RGMA - UsersRGMA - Users
• Users and Interfaces to other systems: – Resource Broker– CMS (Boss)– Service and Service Status for all EDG services – Network Monitoring & Network Cost Function– MapCenter– Logging & Bookkeeping– UK e-Science, CrossGrid and BaBar evaluating– Replica Manager– MDS (GIN/GOUT) – Nagios – Ganglia (Ranglia)
• Future: RB direct use of RGMA (no GOUT)– Better performance and reliability
Tony Doyle - University of Glasgow
SRB for CMSSRB for CMS
• UK eScience has been interested in SRB for several years.
• CCLRC has gained expertise for other projects and is collaborating with SDSC
• Now hosting MCAT for worldwide CMS pre-DC04
• Interfaced to RAL Datastore– Service Started 1 July 2003
• 183,000 files registered
• 10 TB of data stored in system
• Used across 13 sites worldwide including CERN and Fermilab
• 30 Storage resources managed across the sites
MCATDatabase
MCATServer
SRB AServer
SRB BServer
SRBClient
a
b
c d
e
f
g
Tony Doyle - University of Glasgow
EDG StorageElementEDG StorageElement
• Not initially adopted by LCG1
• Since then limited SRM functionality has been added to support GFAL – available for test by LCG
• Full SRMv1 functionality has been developed and is currently being integrated on internal testbed
• GACLs being integrated
Tony Doyle - University of Glasgow
OptorSim: OptorSim: File Replication SimulationFile Replication Simulation
Test P2P file replication strategies: e.g. economic models
1. Optimisation principles applied to GridPP 2004 testbed with realistic PP use patterns/policies
2. Job scheduling: Queue access cost takes into account queue length and network connectivity. Anticipate replicas needed at “close” sites using three replication algorithms.
3. Build in realistic JANET background traffic
4. Replication algorithms optimise CPU use/job time as replicas are built up
on the Grid.
Tony Doyle - University of Glasgow
Middleware, Security and Network Middleware, Security and Network Service EvolutionService Evolution
0
5
10
15
20
25
30
FT
E
GridPP1 GridPP2
Security
Networking
Data Management
Information Services
Workload ManagementWP1
WP2
WP3
WP4
WP5
WP70
5
1 0
1 5
1 2 3 4
GridPP
Non GridPP
• Information Services [5+5 FTE] and Networking [3.0+1.5+1.5 FTE]: strategic roles within EGEE• Security expands to meet reqts.• Data and Workload Management continue• No further configuration management development
• programme defined by – mission criticality (experiment
requirements driven) – International/UK-wide lead – leverage of EGEE, UK core and
LCG developments
• Redefine (EDG-based) UK Work Packages into five Development Groups
Activity Current Planning
Security 3.5
Info-Mon. 4.0
Data & Storage 4.0
Workload 1.5
Networking 3.0
TOTAL 16.0
SecurityMiddleware
Networking
Tony Doyle - University of Glasgow
Application InterfacesApplication Interfaces - Service Evolution- Service Evolution
Experiment Present Grid Activities Present Posts Proposed New Grid Activities
ATLAS MC production EDG integration
2.5
MC production Metadata LCG integration Persistency and data management
CMS MC production Persistency and data management Workload management Monitoring
3
MC production Persistency and data management Workload management Monitoring
LHCb MC production Metadata Persistency
2
MC production Metadata LCG integration Persistency and data management
GANGA (ATLAS+LHCb) Common Grid user interface
2
Common Grid user interface LCG integration Monitoring
BaBar Job submission Replica catalogue Persistency
2.5
Job submission Replica catalogue Persistency MC production
DØ MC production SAM development
2 MC production SAM deployment
CDF MC production SAM development
2 MC production SAM deployment
UKQCD Data access Job submission
1 Data federation Data binding
WP8 Applications integration 1 Applications integration UKDMC MC production
Analysis ZEUS MC production PhenoGrid Metadata MICE MC production
Data handling ANTARES Data handling CALICE MC production LC-ABD Metadata Total 18
• Applications– 18 FTEs: ongoing programme
of work can continue– Difficult to involve experiment
activity not already engaged within GridPP
• Project would need to build on cross-experiment collaboration – GridPP1 already has experience
– GANGA: ATLAS & LHCb– SAM: CDF & D0– Persistency: CMS &
BaBar• Encourage new joint
developments across experiments
Tony Doyle - University of Glasgow
£0.24m
£2.21m
£2.41m
£4.01m
£3.05m
£3.14m
£4.82m
£2.25m
£3.16m
£m £1m
£2m
£3m
£4m
£5m
£6m
£7m
Tier-0 Hardware
Tier-0 Staff
Tier-1 Hardware
Tier-1 Staff
Tier-2 Hardware
Tier-2 Staff
App. Integration
LHC Application Dev.
Non LHC Application Dev.
Middleware/Security/Network
Operations/Management/Dissem.
23% Institutes
27% EGEE + Others
Experiment Collaboration Bids
98% non-PPARC
?50% of £5mSRIF-1 SRIF-2
18% CLRC
Current planning based uponCurrent planning based upon£19.6m Funding Scenario£19.6m Funding Scenario
£0m
£2m
£4m
£6m
£8m
£10m
£12m
£14m
2003 2004 2005 2006 2007 2008
Application Development
Tier-1 and 2 staff
Middleware/Security/Network
Tier-2 Hardware
Tier-2 Staff
Tier-1 Hardware
Tier-1 Staff
Tier-0 Hardware
Tier-0 Staff
Application Integration
Middleware/Security/Network
Dissemination
Travel and Operations
Management
GridPP2Proposal
ExternallyFunded
PPARC Review Timeline:
Projects Peer Review Panel(14-15/7/03)
Grid Steering Committee(28-29/7/03)
Science Committee(October 03)
Tony Doyle - University of Glasgow
Dissemination:Dissemination: e-Science and Web e-Science and Web
e-Science ‘All Hands’ Meeting held at Nottingham, 2-4 September 2003
– ~ 500 people in total
– ~ 20 GridPP People attended
– ~ 17 GridPP Abstracts accepted
– ~ 10 GridPP Papers published + posters displayed
– 6 GridPP Invited talks
– 3 GridPP Demonstrations
• Next step: SC2003 (DC et al.)• and a dissemination officer…
GridPP Web Page Requests:
Currently ~35,000 per month
month: reqs: pages: --------: ------: -----: Nov 2001: 29918: 4374: Dec 2001: 29315: 5576: Jan 2002: 50892: 7594: Feb 2002: 66166: 7724: Mar 2002: 135683: 8180: Apr 2002: 222939: 12008: May 2002: 249830: 11879: Jun 2002: 205480: 12679: Jul 2002: 148604: 14125: Aug 2002: 186690: 21449: Sep 2002: 266853: 24318: Oct 2002: 237031: 26893: Nov 2002: 243710: 29796: Dec 2002: 204119: 27101: Jan 2003: 251185: 27291: Feb 2003: 295381: 30002: Mar 2003: 419985: 35650: Apr 2003: 316816: 34548:
Tony Doyle - University of Glasgow
LCG Press Release…LCG Press Release…
• LHC Computing Grid goes Online
• CERN, Geneva, 29 September 2003.
• The world's particle physics community today announces the launch of the first phase of the LHC computing Grid (LCG-1). Designed to handle the unprecedented quantities of data that will be produced at CERN's Large Hadron Collider (LHC) from 2007 onwards, the LCG will provide a vital test-bed for new Grid computing technologies. These are set to revolutionise the way we use the world's computing resources in areas ranging from fundamental research to medical diagnosis.
• "The Grid enables us to harness the power of scientific computing centres wherever they may be to provide the most powerful computing resource the world has to offer" Les Robertson
Tony Doyle - University of Glasgow
ConclusionsConclusions
• Visible progress this year in GridPP1
• Management via the Project Map and Project Plan
• High level tasks and metrics: under control
• Major component is LCG– We contribute significantly to
LCG and our success depends critically on LCG
• Middleware components on critical path w.r.t. LCG adoption
• Deployment – high and low level perspectives merge via monitoring/accounting
• Resource centre and experiment accounting are both important
• Today’s operations in the UK are built around a small team
• Future operations planning expands this team: Production Manager being appointed
• Middleware deployment focus on Information Service performance
• Security (deployment and policy) is emphasised
• “Production Grid” will be difficult to realise: need to start GridPP2 planning now (already underway)
• GridPP2 proposal: formal feedback in November
• Transition period for:– Middleware/Security/Networking
Groups– Experiments Phase II– Production Grid Planning
Tony Doyle - University of Glasgow
GridPP8 - WelcomeGridPP8 - Welcome• Monday September 22nd
• 10:30-11:00 Arrive - Coffee • Opening Session (Chair: Nick Brook) • 11:00-11:30 Welcome and Introduction - Steve Lloyd • 11:30-12:00 GridPP2 Next Stages - Tony Doyle • 12:00-12:30 LCG Overview - Tony Cass • 12:30-13:30 Lunch • Application Developments I: Grid User Interfaces
(Chair: Roger Barlow) • 13:30-14:00 The GANGA Interface for ATLAS/LHCb -
Alexander Soroko • 14:00-14:30 GANGA for BaBar - Janusz Martyniak • 14:30-15:00 UKQCD interfaces - James Perry • 15:00-15:30 CMS analysis framework - Hugh Talini • 15:30-16:00 Coffee • Application Developments II (Chair: Roger Jones) • 16:00-16:25 Control/Monitoring for LHCb Production -
Gennady Kuznetsov • 16:25-16:50 BaBar Grid status - Alessandra Forti • 16:50-17:10 JIM and the Gridification of SAM - Morag
Burgon-Lyon • 17:10-17:30 UKQCD progress - Lorna Smith • 17:30-17:50 CMS Status - Peter Hobson • 17:50-18:10 D0 Status - Rod Walker • 18:10-18:30 ATLAS Status - Alvin Tan • 18:30-18:35 Logistics - Dave Newbold • 19:00 Collaboration Dinner at Goldney Hall
• Tuesday 23rd September
• Bristol e-Science, GSC Operation and Tier Centre Reports (Chair: David Britton)
• 09:00-09:15 Bristol e-Science - Tim Phillips, Deputy Director of Information Services
• 09:15-09:30 HP Grid Strategy - Paul Vickers • 09:30-10:00 Grid Support and Operations Centre -
John Gordon • 10:00-10:30 Tier-1 report - Andrew Sansum • 10:30-10:45 London Tier-2 Report - Dave Colling • 10:45-11:00 Southern Tier-2 Report - Jeff Tseng • 11:00-11:30 Coffee • Tier-2 Centre Reports and Planning (Chair: John
Gordon) • 11:30-11:45 Northern Tier-2 Report - Andrew McNab • 11:45-12:00 ScotGrid Tier-2 Report - Akram Khan • 12:00-12:30 Tier-2 Centre Development Plans - Steve
Lloyd • 12:30-13:30 Lunch • Middleware Development (Chair: Steve Lloyd) • 13:30-14:00 UK e-Science BOF session summary -
Robin Middleton • 14:00-14:20 Workload Management - Dave Colling • 14:20-14:40 Data Management - Paul Millar • 14:40-15:00 Information & Monitoring - Steve Fisher • 15:00-15:20 Security - Dave Kelsey / Andrew McNab • 15:20-15:40 Networking - Peter Clarke • 15:40-16:00 Fabric Management - Lex Holt