Systems Analysis & Design
7th Edition
Systems Analysis & Design
7th Edition
Toolkit 4
22
Toolkit Objectives
Describe project management tools and how they are used
Describe the steps used in project planning, scheduling, monitoring and controlling, and reporting
Explain techniques for estimating task completion times and costs
Describe various scheduling tools, including Gantt charts and PERT/CPM charts
33
Toolkit Objectives
Calculate completion times, start dates, and end dates for a project
Identify examples of project management software and explain how these programs can assist you in project planning, estimating, scheduling, monitoring, and reporting
Explain the steps involved in software change control
Understand the reasons why projects sometimes fail
44
Introduction
You will learn about project planning, estimating, scheduling, monitoring, reporting, and the use of project management software
You also will learn how to control and manage project changes that typically occur
55
Project Management Overview
Project managers typically perform four main tasks:
– Project planning
– Project scheduling
– Project monitoring and controlling
– Project reporting
66
Project Planning
77
Project Planning
Identifying Tasks– One of the most important variables is the
size of the project, because the amount of work does not relate directly to the size of the project
– If one project is twice the size of another project, the larger project will take more than twice as many resources to develop
88
Project Planning
Identifying Tasks
– The capabilities of project team members also affect time requirements
– Brooke’s Law
99
Project Planning
Estimating Task Completion Time and Cost
– Person-days
– Some tasks can be divided evenly so it is possible to use different combinations of time and people, up to a point
– In most systems analysis tasks, however, time and people are not interchangeable
1010
Project Planning
Estimating Task Completion Time and Cost
– Best-case estimate (B)
– Probable-case estimate (P)
– Worst-case estimate (W)
– Weight
– Expected task duration:(B+4P+W)
6
1111
Project Planning
Factors Affecting Time and Cost Estimates
– Project size and scope
– IT resources
– Prior experience with similar projects or systems
– Applicable constraints
1212
Overview of Project Scheduling
Project scheduling involves the creation of a specific timetable
Dependent task Must balance task time estimates, sequences,
and personnel assignments Several graphical planning aids can help
1313
Project Scheduling with Gantt Charts
Gantt Chart Task groups Are not an ideal tool
for controlling a complex project
1414
Project Scheduling with PERT/CPM Charts
The Program Evaluation Review Technique (PERT)
Critical Path Method (CPM) The important distinctions between the two
methods have disappeared over time, and today the technique is called either PERT, or CPM, or PERT/CPM
1515
Project Scheduling with PERT/CPM Charts
Overview of PERT/CPM
– PERT/CPM is called a bottom-up technique
– Once you know the tasks, their duration, and the order in which they must be performed, you can calculate the time that it will take to complete the project
1616
Project Scheduling with PERT/CPM Charts
PERT/CPM Chart Format
– Task box
– T (task duration, or time)
– ES (earliest start)
– EF (earliest finish) – expected project duration
– LF (latest finish)
– LS (latest start)
1717
Project Scheduling with PERT/CPM Charts
Task Patterns
– Sequential tasks
– Multiple successor tasks• Concurrent task
• Predecessor task
• Successor task
– Multiple Predecessor Tasks
1818
Project Scheduling with PERT/CPM Charts
Task Patterns
1919
Project Scheduling with PERT/CPM Charts
Complex Task Patterns
– When various task patterns combine, you must study the facts carefully in order to understand the logical sequence of tasks
– A systems analyst must understand that project calculations will not be accurate unless the underlying task pattern is logically correct
2020
Project Scheduling with PERT/CPM Charts
A PERT/CPM Example with Five Tasks
2121
Project Scheduling with PERT/CPM Charts
A PERT/CPM Example with Five Tasks
2222
Project Scheduling with PERT/CPM Charts
Critical Path
– Is a series of tasks with no slack time.
– Slack time is the difference between a task’s EF and LF
– If any task along the critical path falls behind schedule, the entire project is delayed
– A critical path includes all tasks that are vital to the project schedule
2323
Project Scheduling with PERT/CPM Charts
Transforming a Task List into a PERT/CPM Chart
– You must develop three versions:• Version 1: Basic Structure
• Version 2: Enter ES and EF Values
• Version 3: Add LF and LS Values
– After you enter the LS and LS figures, you will be able to identify the critical path
2424
Project Scheduling with PERT/CPM Charts
Transforming a Task List into a PERT/CPM Chart
2525
Project Scheduling with PERT/CPM Charts
Transforming a Task List into a PERT/CPM Chart
2626
Project Scheduling with PERT/CPM Charts
Transforming a Task List into a PERT/CPM Chart
2727
Project Scheduling with PERT/CPM Charts
Transforming a Task List into a PERT/CPM Chart
2828
Project Scheduling with PERT/CPM Charts
Comparing Gantt Charts and PERT/CPM– One significant advantage of PERT/CPM
charts is that all individual tasks and dependencies are shown
– A PERT/CPM chart displays the critical path for the overall project and the slack time
– A Gantt chart offers a rapid overview – PERT/CPM and Gantt charts are not
mutually exclusive techniques
2929
Project Monitoring and Controlling
Monitoring and Control Techniques– The project manager must keep track of
tasks and progress of team members, compare actual progress to the project plan, verify the completion of project milestones, and set standards and ensure that they are followed
– Structured walkthrough is a review of a project team members based on design reviews, code reviews, or testing reviews
3030
Project Monitoring and Controlling
Maintaining a Schedule– Maintaining a project schedule can be a
challenging task– The better the original plan, the easier it will
be to control the project– If enough milestones and frequent
checkpoints exist, problems will be detected rapidly
– It is mathematically possible for a project to have more than one critical path
3131
Project Reporting
Project Status Meetings– Most project managers schedule regular
status meetings with the entire project team– Each team member updates the group and
identifies any problems or delays– The meetings also give the project manager
an opportunity to update the entire group, seek input, and conduct brainstorming sessions
3232
Project Reporting
Project Status Reports– A project manager must report regularly to
his or her immediate supervisor, upper management, and users
– Should explain what you are doing to handle and monitor the problem
– Most managers recognize that problems do occur on most projects; it is better to alert management sooner rather than later
3333
Project Management Software
Project Management Software
– can assist you with project planning, estimating, scheduling, monitoring, and reporting.
Project Management Examples
– Microsoft Project
– Open Workbench
– Open-source software
3434
Project Management Software
Project Management Examples
– The first step in project management is to identify the tasks, task duration, and task dependencies
– Network diagram
– Project planning is a dynamic task and involves constant change
3535
Project Management Software
Project Management Examples
3636
Software Change Control
Software Change Control A procedure for processing requests for
changes to an information system’s requirements consists of four steps:
1. Complete a change request form
2. Take initial action on the request
3. Analyze the impact of the requested change
4. Determine the disposition of the requested change
3737
Keys to Project Success
Business Issues
– The major objective of every system is to provide a solution to a business problem or opportunity
– A system that falls short of business needs also produces problems for users and reduces morale and productivity
3838
Keys to Project Success
Budget Issues
– Cost overruns typically result from one or more of the following:
• Unrealistic estimates
• Failure to develop an accurate TCO forecast
• Poor monitoring of progress and inadequate reaction to early signs of problems
• Schedule delays due to unanticipated factors
• Human resource factors
3939
Keys to Project Success
Schedule Issues
– Problems with timetables and project milestones can indicate a failure to recognize task dependencies, confusing effort with progress, poor monitoring and control methods, personality conflicts among team members, or turnover of project personnel
4040
Keys to Project Success
Successful Project Management
– When problems occur, the project manager’s ability to handle the situation becomes the critical factor
– Sometimes, when a project experiences delays or cost overruns, the system still can be delivered on time and within budget if several less critical requirements are trimmed
4141
Keys to Project Success
Successful Project Management– If a project is in trouble because of a lack of
resources or organizational support, management might be willing to give the project more commitment and higher priority
– A typical response is to push back the completion date
– Option only if the original target date is flexible and the extension will not create excessive costs or other problems
4242
Toolkit Summary
Project management is the process of planning, scheduling, monitoring and controlling, and reporting upon the development of an information system
Begins with identifying and planning all specific tasks or activities
Can use graphical tools such as Gantt charts and PERT/CPM charts to assist in the scheduling process
4343
Toolkit Summary
A project manager uses a variety of techniques to monitor, control, and report project tasks
Software change control is concerned with change requests that arise
Every successful information system must support business requirements, stay within budget, and be available on time
Toolkit 4 complete