+ All Categories
Home > Documents > Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... ·...

Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... ·...

Date post: 26-Apr-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
45
17 th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete Pavements Shiraz Tayabji Fugro Consultants, Inc., Columbia, MD FHWA ACPT Program Team
Transcript
Page 1: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013

Top 10 Considerations for Designing, Constructing & Maintaining Long-Life

Concrete Pavements

Shiraz Tayabji Fugro Consultants, Inc., Columbia, MD FHWA ACPT Program Team

Page 2: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

Ø Introductory Ø Top 3 Design Considerations

o  Focus on Design Features o  Joint Load Transfer o PCCP Support Condition/Drainage

Ø Top 5 Construction Considerations o Construction Quality

§  Poor Design/Quality Construction vs. Good Design/Poor Construction

o Concrete Management – from Plant to Curing o Well-developed Specs/End Product Emphasis o Contractor Process Control o Agency Acceptance Testing

Presentation Outline

Page 3: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

Ø Top 2 M&R Considerations o  Timely M&R o Accelerated M&R (to Minimize Traffic

Congestion & Improve Work Zone Safety

Presentation Outline (Cont.)

Page 4: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top
Page 5: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top
Page 6: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

Simply by Achieving Consistently What We Know is Attainable

& Continue Making Concrete

Pavements Cheaper & Sustainable (in terms of overall LCA) by Taking Advantage of

New Developments

HOW CAN WE GET THERE?

Page 7: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

Ø  Original PCC surface service life – 40+ years Ø  Pavement will not exhibit premature failures

and materials related distress o  Pavement failure=> Result of traffic loading

Ø  Pavement will have reduced potential for cracking, faulting & spalling, and

Ø  Pavement will maintain desirable ride and surface texture characteristics with minimal intervention activities to correct for ride & texture, for joint resealing, and minor repairs

US Expanded Definition of Long-Life Concrete

Pavements

Page 8: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

Current PCCP Hot Topics Ø Design o  MEPDG implementation o  Optimizing design features o  Composite pavement (PCC(+)/PCC(-) for new) o  Precast pavement (rapid rehab/reconstruction) o  In with the old – CRCP getting more attention

Ø Materials (major focus: durability & sustainability) o  Dense (well) graded aggregates (3+ sizes) o  Less cement use, more SCM (flyash & slag) o  Two-lift paving (PCC(+)/PCC(-) ) o  Joint concrete durability (joint rot issue)

Page 9: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

Current PCCP Hot Topics Ø Construction

o  Jointing §  Single vs. double cut; sealing vs. no-sealing §  Dowel bar alignment testing & specification

o  Two-lift paving o  Stringless paving o  End product specification/PRS o  Pro-active contractor process control

§  Concrete testing; profile testing

Ø Repair/Rehabilitation o  Rapid/Accelerated

§  Full closures vs. night/weekend closures o  Thin concrete overlay use o  Precast pavement use

Page 10: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

Current PCCP Hot Topics Ø Surface characteristics/user benefits o  Reduce wet weather accidents o  Improve ride o  Reduce pavement/tire noise

Ø Construction management o  Minimize extended lane closures o  Reduce congestion o  Reduce work zone accidents

Ø US FHWA national focus areas o  Recycling

Page 11: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top
Page 12: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top
Page 13: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

Top 3 Design Considerations

•  Focus on Design Features •  Load Transfer at joints •  PCCP Support Condition/Drainage

Page 14: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

1 - Comprehensive Long-Life Concrete Pavement Design

Ø More than just slab thickness Ø Incorporation of appropriate design features

to enhance performance (e.g., improved base, dowel bars, etc.)

Ø Must design pavement as a system o Consider interactive effects of all design

elements o Consider overall cost effectiveness o Consider use of locally available & recycled

materials

Page 15: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top
Page 16: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

1 - Comprehensive Long-Life Concrete Pavement Design

Ø Some simple changes in approach to reduce concrete volume & amount of other materials without compromising performance o Reduce slab thickness

§  Improve foundation/base (European approach) § Use widened lane & shorter joint spacing

o Reduce materials § Reduce no. of dowel bars (9 or 10 vs.12 per lane) § Reduce joint sealant material (single cut sawing)

Ø Other changes o Consider two-lift design & construction to allow use of

local/marginal & recycled materials in the lower lift.

Page 17: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

2 - Joint Load Transfer —

Ø Joint spacing – Typical practice o 15 ft (4.6 m) max for most

highway applications o Uniform spacing & perpendicular

joints Ø Load transfer (40+ year design)

o Corrosion protection a must § Epoxy-coated (?) § Clad bars (steel/zinc) § Microcomposite steel (MMFX) § Fiber-reinforced polymer (FRP)

Page 18: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

2 - Joint Load Transfer

Ø Dowels for truck-loaded highways, typically for § Slab t > 8 in or ESALs > 5 million § Minimum 1.25 in (32 mm) diameter

Ø Round dowels meet needs & are economical Ø Need to maintain LTE at joints - > 70% Ø NO NEED FOR MIDDLE 2 to 3 BARS IN

EACH LANE

Page 19: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top
Page 20: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

3 – Support Condition/Drainage Ø US Approach – Do the best we can? Ø European approach – Start with a good (standard)

foundation Ø We must construct better support – cannot undo

poor support in future R&R Ø Non-erodible base - prevention of pumping Ø Stiffer support - reduction in slab stresses &

deflections; less rolling resistance (MIT study) Ø Provide stable and uniform construction platform

– achieve better concrete surface finish Mentality switch – Refer to a base as a base

& not as a subbase

Page 21: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

3 – Support Condition/Drainage Base Type Selection

Ø Provide for needed base-slab friction Ø Provide for needed frost heave protection Ø Provide for needed subsurface drainage Ø Untreated granular (aggregate) bases should be

reserved for low traffic Ø Stabilized (treated) bases for LLCP (40+ years)

o Asphalt-treated/Cement-treated o Lean concrete bases (Caltrans use) o Permeable bases – treated

Page 22: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

3 – Support Condition/Drainage Pavement Subsurface Drainage

Ø Need to pay more attention Ø Rapidly remove water from

beneath pavement structure o  Stability vs. porosity: use lower

permeability material <300 - 500 ft/day (90 - 150 m/day)

Ø Drainable Pavement System o Daylighted permeable base o Permeable base with edge

drainage system

Page 23: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

Top 5 Construction Considerations

•  Construction Quality •  Poor Design/Quality Construction vs. Good

Design/Poor Construction •  Concrete Management – from plant to joint

sawing •  Well-developed Specs/End Product

Emphasis •  Contractor Process Control •  Agency Acceptance Testing

Page 24: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

24

Ø  For construction projects, achieving quality equates to conformance to requirements o Requirements need to be well defined, can

be measured, and are not arbitrary Ø Quality must be built into a project. It is

not a hit or miss proposition.

4 - Construction Quality?

• Owner should not expect more than what

is specified

• Contractor may not deliver more than what is specified

Page 25: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

Poor Design/Quality Construction vs. Good Design/Poor Construction

A poorly designed pavement but well constructed will outlast a well designed pavement but

poorly constructed Ray Rollings

Retired, Corps of Engineers

4 - Construction Quality?

Page 26: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top
Page 27: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

5 – Concrete Management Ideal Paving Concrete Mixture

Ø US vs. European approach (Freeways) o US: ~650 psi MR & slab t = 12 to 14 in. o European: 750+ psi & slab t = 10 in.

Ø Design for low paste - most concrete durability concerns are due to paste issues o Results in better slipform paving & better finishing

Ø 2-lift paving – Top: PCC(+); Bottom: PCC(-)

Page 28: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top
Page 29: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

5 – Concrete Management The Joint Rot Issue

Ø Some joints are deteriorating faster than we would like (Peter Taylor)

Ø Some key findings o Paste saturation is a main culprit (f(freeze/thaw)) o Need better quality concrete – w/cm < 0.40 & good in-

situ air system & dense concrete & well-draining pavement, especially at the joint

Page 30: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

5 – Concrete Management From Placement to Curing

Ø Proper consolidation o Use of smart vibrator system o Check cores for proper consolidation

Ø Minimize tendency to over-finish surface o Brings more paste to the surface o Surface does not have to be super-smooth

Ø Timely curing o A concern on many projects during hot weather

Ø Timely & proper joint sawing o Not an issue for transverse sawing, but delay in

longitudinal sawing can result in premature cracking

Page 31: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

6 – Well-Developed Specs Construction Specification Objective

Ø To identify and accommodate or minimize variability in the concrete pavement construction process o  To deliver an end product that is durable o  To minimize risk of premature failures o  To minimize owner’s risk of accepting a marginal

product o  To minimize contractor’s risk of rejection of an

acceptable product

Good Specs lead to Good Construction!

Page 32: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top
Page 33: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top
Page 34: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

Ø  Ideal contractor process control (QC) limits or eliminates placement of marginal concrete & use of marginal construction processes o  Do not produce concrete if aggregate grad. not met o  Reject concrete loads if requirements not met o  Stop paving process if placement (edge slump) or

consolidation issues Ø  Process control tests

o  Aggregate gradation & concrete mixture o  Slab thickness o  Concrete “slump” & air & density/consolidation o  Profile (behind paver) & texture o  Dowel bar alignment

7 – Contractor Process Control

Page 35: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top
Page 36: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

Ø  Perform sufficient testing to verify marginal materials & construction techniques are not being used o  Statistically based sample testing best o  Preferably rapid nondestructive testing

Ø  Test for end product metrics (PWL) o  Slab thickness o  Concrete strength o  Concrete durability – air/denseness o  Smoothness & texture o  Dowel bar alignment (?) o  Early age distress

8 – Agency Acceptance Testing Determine the Degree of Compliance

Ideal Testing Behind paver, not in front of paver

Page 37: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

Top 2 M&R Considerations

•  Timely Maintenance & CPR •  Accelerated M&R

•  Minimize Lane Closures & Traffic Congestion

•  Improve Work Zone Safety

Page 38: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

Ø  We expect that current & future new concrete pavements will provide a low maintenance service life

Ø  However, we still have to manage concrete pavements constructed more than 20 years ago & designed for ~20+ years. Many of these pavements have been in place for 40+ years.

Ø  With timely M&R strategies, we can continue to extend the service life of many of these older concrete pavements without resorting to “fracturing” & reconstruction o  Economical & sustainability benefits

M&R Overview

Page 39: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

Ø  With minimal effort and lower costs, we can extend service life of most concrete pavements without fracturing, resurfacing & reconstruction

Ø  Well-performing CPR techniques are available – to maintain ride/texture/structural capacity

o  FDR, DBR, grinding, concrete shoulder retrofit o  Joint resealing ? – topic of debate

Ø  But, M&CPR must be done in a timely manner & done well (NO MORE FIXING THE FIX)

9 – Timely M&CPR Extend service Life of Existing Pavements

Page 40: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

Ø  Take advantage of advances in repair materials o  Rapid set concretes (cementitious binder) o  Polymer-based materials o  Other

Ø  Consider precast pavement for full-depth repairs & rehabilitation o  Production use by NYSDOT, NJDOT, Illinois Tollway,

Caltrans o  Cost effective & longer-lasting

10 – Accelerated M&R Technologies Minimize Lane Closures & Traffic Congestion

& Improve Work Zone Safety

Page 41: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top
Page 42: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top
Page 43: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

CA I-680 Precast Prestressed System Up to 36 ft long panels over new RSLCB, 2011

Page 44: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

Achieving LLCP (40+ years) Many Small Steps => Big Gains (LLCPs)

One Small Misstep => Premature Failure (PPCPs)

Ø Optimizing long-life pavement designs o Thickness reduction; fewer dowel bars o Single cut joints; better bases/foundation

Ø Managing the construction processes & materials

Ø Effectively extending service life of existing pavements by timely M&CPR

Page 45: Top 10 Considerations for Designing, Constructing & Maintaining Long-Life Concrete ... · 2015-11-19 · 17th Annual Terra Conference St. Paul, Minnesota – February 14, 2013 Top

Recommended