Neoferma Australia Pty Ltd BPT&IM V4 June 2018 Page 1 of 53 TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL & INSTALLATION MANUAL REF: CODEMARK BPTIM Doc V4, issued date: June 2018 For New Zealand NZ Distributor Contact details: Neptune Pacific LTD, PO Box 185, Albany Village, NZ B2, 39 Arrenway Drive, Rosedale 0632 New Zealand Ph: 09 415 4469 [email protected] Australian Supplier and Distributor Contact details: Web Site: www.neoferma.com Ph.: +61 7 5576 4922 e-mail: [email protected] PO Address: P.O. Box 324, West Burleigh, QLD 4219 HO Street Address: Unit 9, 4 Flagstone Drive, Burleigh, QLD, Australia 4220
Transcript
Page 1: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 1 of 53

TotalSeal MS ™ System

BUILDING PRODUCT TECHNICAL & INSTALLATION MANUAL REF: CODEMARK

BPTIM Doc V4, issued date: June 2018

For New Zealand

NZ Distributor Contact details:

Neptune Pacific LTD, PO Box 185, Albany Village, NZ

B2, 39 Arrenway Drive, Rosedale 0632 New Zealand

Ph: 09 415 4469

[email protected]

Australian Supplier and Distributor Contact details:

Web Site: www.neoferma.com

Ph.: +61 7 5576 4922

e-mail: [email protected]

PO Address: P.O. Box 324, West Burleigh, QLD 4219

HO Street Address: Unit 9, 4 Flagstone Drive, Burleigh, QLD, Australia 4220

Page 2: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 2 of 53

This page intentionally left blank

Page 3: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 3 of 53

Table of Contents:

1. General description of the product ……………………………………………….…… P5

a. Product description ……………………………………………………………….… P5

b. Purpose / Use ………………………………………………………………………….. P5

2. Scope of use & limitations ……………………………………………………………….… P6

a. Scope of use ………………………………………………………………………….… P6

b. Limitations …………………………………………………………………………….… P6

3. Compliance with the Building Code ……………………………………………….. P6-7

a. NZBC compliance …………………………………………………………………….. P6

b. B2 Durability ………………………………………………………………………….… P6

c. E2 Weather tightness / External moisture ……………………………. P6-7

d. F2 Hazardous building materials …………………………………………….…P7

4. List of specified components and SDS information ………………………….… P7

a. Membranes …………………………………………………………………………….. P7

b. Ancillary products …………………………………………………………………… P7

c. Features and Benefits …………………………………………………………..… P7

5. Construction Details and Drawings …………………………………………………... P8

a. General installation requirements ………………………………………..… P8

b. Substrate and Backfill …………………………………………………………..… P9

Limitation: Ref Expansion Joints …………………………………………….. P9

c. Construction guidance …………………………………………………………... P10

i. Installation – Soldier Piles ……………………………………………. P10

ii. Installation – Under slab / Horizontal ……………………… P10-11

iii. Installation – Vertical surfaces ………………………………..…… P11

iv. Backfilled Poured in place concrete walls ……………………. P11

v. Metal sheet Piling retention walls ………………………….….… P12

vi. Auger cast concrete retention walls ……………………….….… P12

vii. Pipe penetrations ………………………………………………………… P12

viii. Pile caps ………………………………………………………………………. P13

ix. Wall Floor junctions ………………………………………………….…. P13

x. Shotcrete walls ……………………………………………………….…… P13

xi. Waterstops ……………………………………………………………….…. P13

xii. Construction Joints / Non-movement joints ………………... P13

xiii. Clean up …………………………………………………………………….… P13

6. Maintenance and warranty ……………………………………………………………… P14

Page 4: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 4 of 53

a. Maintenance …………………………………………………………………………. P14

b. Warranty ..……………………………………………………………………………… P14

7. Quality Management System …………………………………………………………… P14

a. Applicator / Installer Training ………………………………………………… P14

b. Project Checklists and Site Inspections ………………………………….. P15

8. Appendix A: TotalSeal MS™ Technical Data Sheets

a. TotalSeal MS ™ HP…………………..………………………………………….…. P16

b. SwellSeal Bentonite Granules …………………….………………………..… P17

c. Neoferma Seaming Paste …………………………….………………………… P18

d. Neoferma Detail Paste …………………………………..………………………. P19

Appendix B: Sample Warranty Documents for NZ

a. NZ warranty document example ………………………………………. P20-21

Appendix C: Examples of Generic Detail drawings ………………………. P22-39

i. DT001 – Standard Pit Detail (Below water)

ii. DT003 – Standard Pit Detail (Above water)

iii. DT005 – Standard Capping Beam detail (Above Water)

iv. DT006 – Standard Pipe Penetration (Below water)

v. DT007 – Typical Pile Cap Detail

vi. DT008 – Step Down Pile Cap Detail

vii. DT009 – Screw Pile Detail

viii. DT010 – CSM Wall Detail

ix. DT012 – Steel pile Concrete Wall Detail Below Water

x. DT013 – Secant Wall Detail

xi. DT014 – Construction joint Detail (Non moving Above Water)

xii. DT015 – Construction joint Detail (Non moving Below Water)

xiii. DT016 – Construction joint Detail (Non moving Below Water, High pressure)

xiv. DT021 – Pour Strip Detail

xv. DT022 - Masonry Block Foundation Wall Above Water Table

xvi. DT023 - Masonry Block Wall Horizontal Lap Above Water Table

xvii. DT024 - Masonry Block Wall Vertical Lap Above Water Table

xviii. DT025 - Termination Detail

Appendix D: Project checklists / Site Inspection documents

a. Pre-Project start up – IPP008 ……………………………..………………………..….. P40-41

b. Pre-Steel Placement – ITPC 030 V2 …………………..……………………………… P42-45

c. Pre-Concrete Pour – ITPC 031 V1 …………………………………………………….. P46-P47

Appendix E: Safety Data Sheets (SDS) …………………………………………. P48-53

Page 5: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 5 of 53

1. General description

a. Product description

The TotalSeal MS ™ system is a highly effective, bentonite based, basement

tanking (vertical and horizontal foundation surfaces) waterproofing membrane

system. The membrane is comprised of a geosynthetic clay liner composite

made from high quality polypropylene geotextiles and premium grade sodium

bentonite granules. As part of the system approach the ancillary products;

SwellSeal seaming paste and Detail paste, used with the membrane are also

sodium bentonite based.

TotalSeal MS ™ uses the high swelling and self-sealing properties of Sodium

Bentonite to form a monolithic, low permeability membrane to protect the

structure from water.

Installation is fast and easy, requiring no primers or special tools.

TotalSeal MS ™ can be installed in virtually any weather, including freezing

temperatures and damp conditions.

b. Purpose / Use

Designed for use in below grade / below water table vertical and structural

foundation surfaces. Applications may include structures under continuous or

intermittent hydrostatic pressure. A strong mechanical bond is formed when

concrete is poured against the membrane as the membrane fibres “lock” into

the wet concrete. Upon hydration and when confined under pressure the

sodium bentonite granules swell forming a dense, impervious waterproofing

membrane.

Typical applications include backfilled concrete walls, under structural slabs,

tunnels, earth-covered roofs, and property line construction. Property line

construction applications include metal sheet piling, soldier pile and lagging, and

concrete caisson construction. TotalSeal MS ™ can be installed directly over a

properly prepared soil substrate without a working mud slab. Additionally,

Page 6: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 6 of 53

TotalSeal MS ™ can be installed on freshly poured concrete walls as soon as the

forms are removed.

Use of TotalSeal MS ™ in areas not specified in the TotalSeal MS ™ Technical

manual (BPTIM Doc V4, issued date: June 2018) are outside the scope of this

certificate.

2. Scope of Use & Limitations

a. Scope of Use

The TotalSeal MS ™ waterproofing system is designed and engineered for use

under reinforced structural concrete slabs of 150mm thick or greater and where

the substrate has been compacted to 85% modified proctor density.

For external waterproof tanking membrane to in-situ concrete, precast

concrete and concrete masonry basement constructions subject to hydrostatic

pressures of up to 2 bar (20 metres); and a damp-proof membrane (DPM) to

slab-on-ground and basement constructions.

b. Limitations

The effectiveness of TotalSeal MS ™ is dependent upon the membrane being

both compacted and confined.

TotalSeal MS ™ is not designed for un-confined, above ground waterproofing

applications or over lightweight insulating concrete or “Besser” type blocks.

TotalSeal MS ™ is not designed for being fully immersed in excessively ponding

water before the geotextile membrane is covered with concrete.

TotalSeal MS ™ is not an expansion joint filler or sealant.

For warranty requirements a manufacturer’s representative should approve

the wall surface(s) prior to installing TotalSeal MS ™.

3. Compliance with the Building Code

A. The TotalSeal MS ™ basement tanking system complies with the following

clauses in the NZ Building Code:

B. B2 Durability: The TotalSeal MS ™ membrane system applied in

accordance with this manual will meet the requirements of NZBC Clause

B2.3.1(a) in terms of 50year longevity.

C. E2 Weather tightness: The TotalSeal MS ™ membrane system applied in

accordance with this manual will meet the requirements of NZBC Clause

E2.3.2 relating to the resistance of water penetration (hydrostatic water

Page 7: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 7 of 53

resistance, susceptibility to leakage), provided the integrity of the

specified system is maintained.

D. F2 Hazardous building materials: Reference NZBC Clause F2.3.1

regarding Hazardous Building Materials, TotalSeal MS ™ membrane is

non-hazardous. All safety precautions to be adhered to are provided in

this technical manual.

4. List of products within the TotalSeal MS ™ system

Reference: Safety Data Sheet (SDS) provision:

Although all the materials in the basement tanking system mentioned below

are classified as non-hazardous, normal construction industry protocols

regarding the provision of SDS are followed. Current copies of all SDS are kept

on file (both hard copy and electronic) and are provided to customers when

product is shipped, when product is collected from Neoferma facilities and/or

when requested by any relevant site personnel.

a. Membranes

1. TotalSeal MS ™ HP – 1.65mt x 15mt rolls

b. Ancillary Products

1. SwellSeal Granulated Bentonite – 25kg bags

2. Neoferma Seaming Paste – 10kg pails

3. Neoferma Detail Paste -15kg pails

c. Features and Benefits of TotalSeal MS ™ membrane:

1. Purpose made for the construction industry and construction friendly

2. Self-heals if damaged preventing tracking water

3. Has an indefinite life-cycle

4. Can be installed in any weather and as soon as the forms are removed

5. Is easy to handle and install

6. Reinforcing steel can be installed directly on to the membrane

Page 8: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 8 of 53

5. Construction Details and Drawings

For examples of generic Detail drawings please refer to Appendix C.

a. General Installation Requirements

• Ensure the substrate meets the minimum 85% modified proctor density.

• Install the membrane with the woven side (dark grey) of the geotextile liner facing

the concrete to be waterproofed, in both horizontal and vertical applications.

• Prevent bentonite waterproofing products from being fully immersed in excessively

ponding water before the geotextile membrane is covered with concrete.

• Diagrammatic example of the membrane lapping:

Page 9: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 9 of 53

b. Substrate and Backfill Requirements:

• Backfill and substrate must be compacted to a minimum 85% Modified Proctor density.

• Substrate materials should be; mud slab, concrete, compacted sand, earth, crushed rock (no larger than 15mm in size.), blue metal or gravel.

• Materials and methodology to be approved in writing by Neoferma Australia prior to commencement.

• Backfill and surfaces should be level, without sharp objects or indentations have a smooth finish, free of debris, oil, grease, laitance, dirt, dust, or other foreign matter which will impair the performance of the waterproofing and drainage system and which do not comply with manufacturer's warranty requirements. TotalSeal MS™ can be installed on green structural concrete as soon as the forms are removed. There is no product limitation regarding a minimum concrete curing time requirement for TotalSeal MS™ to be installed over structural concrete. The Manufacturer recommends obtaining instructions from the project structural engineer regarding any site specific concrete curing time requirement. Do not apply TotalSeal MS™ waterproofing over lightweight insulating concrete or “Besser” type blocks.

• Horizontal deck or roof concrete surfaces should be sloped for proper drainage.

• Remove fins, ridges, and other protrusions to provide a level, smooth finish to match monolithic concrete surface. Completely fill honeycomb, aggregate pockets, holes or other voids with proprietary non-shrink cementitious repair mortar, levelled and smoothly finished to match monolithic concrete surface.

• Closely coordinate TotalSeal MS™ installation with the Backfill operation conducted under Division 2 work. Care should be used during Backfill operation to avoid damage to the waterproofing system. Follow generally accepted practices for backfilling and compaction. Backfill should be added in 150 - 300 mm lifts and compacted to a minimum 85% Modified Proctor density. At grade line and other areas that cannot be fully compacted.

• FLASHING is recommended across the top termination of the membrane.

• Failure to provide substrates to specification will void warranty.

Limitation: Ref Expansion Joints

TotalSeal MS™ waterproofing is not an expansion joint filler or sealant but may be used as

an expansion joint cover over properly installed expansion joint material placed during

substrate preparation.

To use TotalSeal MS™ as a cover for an expansion joint:

• All expansion joints should be cleaned, primed, fitted with the relevant expansion joint product – refer to Expansion joint material manufacturer for details.

• Install a 500 mm wide strip of TotalSeal MS™ centred over the expansion joint. Then place the main course of TotalSeal MS™.

• If movement is expected contact Neoferma for recommendation(s).

Page 10: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 10 of 53

c. Construction Guidance

Typical generic Detail drawings are provided in Appendix C to assist.

i. Soldier Piles

For warranty requirements, a manufacturer’s representative should approve the wall

surface prior to installing TotalSeal MS™.

• Cut and attach a minimum 200mm strip of TotalSeal MS™ centred over all soldier piles. Prepare surface. Sharp offsets must be filled with Cementitious Repair Mortar. Large projections must be removed and made flush with surface. TotalSeal MS™ will conform to large gradual change in planes (e.g. around caisson column). Wall should be sufficiently planar to provide adequately smooth surface to apply TotalSeal MS™.

• TotalSeal MS™ should extend a minimum 100 mm on both sides of soldier pile.

• Attach TotalSeal MS™ horizontally (dark grey woven geotextile outward facing installer) with washer-head mechanical fasteners 600 mm on centre around the edge. Overlap all seams a minimum of 100 mm. Stagger all vertical overlap seams a minimum of 600 mm.

• Detail around all penetrations and tie-backs with 18 mm cant of Neoferma DETAIL paste. Extend 6 mm Neoferma DETAIL paste over substrate a minimum radius of 50

mm around penetration and tie-backs. Cut TotalSeal MS™ to fit snugly around penetrations and tie-backs.

• Terminate at grade with FLASHING fastened 300 mm on centre. Cover top edge of TotalSeal MS™ with 12 mm thick, 50 mm wide layer of Neoferma DETAIL paste.

• Inspect finished TotalSeal MS™ installation and repair any damaged material prior to concrete placement. Assure that TotalSeal MS™ is not displaced during concrete placement.

ii. Under Slab / Horizontal Installation

• Reinforced structural foundation slabs should be a minimum of 200 mm thick when placed on a working blinding slab. Reinforced concrete slab(s) on compacted grade shall be a minimum of 100 mm thick. When hydrostatic conditions exist, install TotalSeal MS™ under all footings, elevator pits and grade beams.

• No laps are to be directly under a construction or movement joint.

• All construction or movement joints are to have a 500mm wide secondary layer of TotalSeal MS™ membrane located centrally on the construction joint under the main course of membrane.

• Place TotalSeal MS™ directly on properly prepared substrate (dark grey woven geotextile side up facing installer) with adjoining edges overlapped a minimum of 100

mm.

• Stagger sheet end seams a minimum of 600 mm.

• All horizontal laps to be reinforced with a 20mm thick bead of Neoferma Seaming paste.

• All laps are to be staggered a minimum of 300mm to the next adjacent lap.

• When the slab is poured in sections, extend TotalSeal MS™ a minimum 300 mm beyond the slab edge to enable proper overlapping.

• Cut TotalSeal MS™ to fit snugly around penetrations and pile caps. (Do not extend TotalSeal MS™ over pile cap.)

• Around base of penetrations trowel 18 mm thick fillet of Neoferma DETAIL paste and extend the Neoferma DETAIL paste onto TotalSeal MS™.

Page 11: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 11 of 53

• Around base of pile caps trowel 50 mm thick fillet of Neoferma DETAIL paste and extend the Neoferma DETAIL paste onto TotalSeal MS™.

• Provide a minimum of 300 mm overlap between underslab and vertical wall waterproofing by either extending the TotalSeal MS™ beyond the form or turning it up in the form and reinforcing with Neoferma DETAIL paste.

• When laying membrane in trenches, make sure the laps are positioned "outside the trench" (There should be no horizontal lap on the trench wall).

• Any TotalSeal MS™ application in salt or contaminated water MUST BE PRE-HYDRATED with fresh water within a maximum of 24 hours prior to concrete placement.

• In sites with high salt levels refer to Neoferma Australia Pty Ltd.

• Inspect finished TotalSeal MS™ installation and repair any damaged material prior to concrete placement.

• Assure that TotalSeal MS™ is not displaced during concrete placement.

iii. Vertical Surfaces

• All vertical laps to be reinforced with Neoferma Seaming paste (note: the paste is to be placed in the middle of the lap at a bead size of approx 20mm) If the TotalSeal MS™ membrane has a rear PE layer, remove approximately 100 of the PE layer to allow pasting of laps.

• TotalSeal MS™ membrane is to be terminated a minimum 300 mm below grade and is to be secured with an Neoferma approved termination bar.

iv. Vertical / Backfilled Poured-In-Place Concrete Walls

• Place Neoferma DETAIL paste along the wall/footing intersection to form a continuous installation.

• Trowel 18 mm thick Neoferma DETAIL paste fillet at all inside corner transitions.

• Starting at the base of the wall, install TotalSeal MS™ sheet horizontally (dark grey woven geotextile against the wall) covering the Neoferma DETAIL paste and extending onto the footing a minimum of 150 mm.

• For hydrostatic conditions, cover the entire footing and overlap under slab waterproofing a minimum of 150 mm. Attach TotalSeal MS™ using washer-headed mechanical fasteners centred 600 mm around the edge. Stagger all vertical overlap seams a minimum of 600 mm.

• Detail around all penetrations with 18 mm cant of Neoferma DETAIL paste. Extend Neoferma DETAIL paste 60 mm thick over substrate a minimum radius of 150 mm around penetration. Cut TotalSeal MS™ to fit snugly around penetrations (See Detail 5).

• Terminate at grade with FLASHING fastened 300 mm on centre. Cover top edge of TotalSeal MS™ with 12 mm thick, 50 mm wide layer of Neoferma DETAIL paste (See Detail 6).

• Inspect finished TotalSeal MS™ installation and repair any damaged material prior to backfill placement. Assure that TotalSeal MS™ is not displaced during backfill placement or soil compaction.

Page 12: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 12 of 53

v. Vertical / Metal Sheet Piling Retention Walls

• Trowel 18 mm thick layer of Neoferma DETAIL paste along all sheet piling interlocks and over all tie-back plates.

• Attach TotalSeal MS™ directly to sheet piling horizontally (dark grey woven geotextile outward facing installer) with washer-head mechanical fasteners 600 mm on centre around the edge. Overlap all seams a minimum of 100 mm. Stagger all vertical overlap seams a minimum of 600 mm.

• Detail around all penetrations and tie-backs with 18 mm cant of Neoferma DETAIL paste. Extend 6 mm Neoferma DETAIL paste over substrate a minimum radius of 150

mm around penetration and tie-backs. Cut TotalSeal MS™ to fit snugly around penetrations and tie-backs.

• Terminate at grade with FLASHING fastened 300 mm on centre. Cover top edge of TotalSeal MS™ with 12 mm thick, 50 mm wide layer of Neoferma DETAIL paste.

• Inspect finished TotalSeal MS™ installation and repair any damaged material prior to concrete placement. Assure that TotalSeal MS™ is not displaced during concrete placement.

vi. Vertical / Auger Cast and Concrete Retention Walls

• Prepare surface. Sharp offsets must be filled with Cementitious Repair Mortar. Large projections must be removed and made flush with surface. TotalSeal MS™ will conform to large gradual change in planes (e.g. around caisson column). Wall should be sufficiently planar to provide adequately smooth surface to apply TotalSeal MS™. For warranty requirements, a manufacturer’s representative should approve the wall surface prior to installing TotalSeal MS™.

• Attach TotalSeal MS™ horizontally (dark grey woven geotextile outward facing installer) to prepared surface with mechanical fasteners 600 mm on centre around the edge. Overlap all seams a minimum of 100 mm. Stagger all vertical overlap seams a minimum 24" (600 mm).

• Cut TotalSeal MS™ to closely contour caissons and fit snugly around penetrations and tie-back plates. Detail around all penetrations and tie-backs with 18 mm cant of Neoferma DETAIL paste. Extend 6 mm Neoferma DETAIL paste over TotalSeal MS™ a minimum radius of 150 mm around penetration and tie-backs.

• Terminate at grade with FLASHING fastened 300 mm on centre. Cover top edge of TotalSeal MS™ with 12 mm thick, 50 mm wide layer of Neoferma DETAIL paste.

• Inspect finished TotalSeal MS™ installation and repair any damaged material prior to concrete placement.

• Assure that TotalSeal MS™ is not displaced during concrete placement.

vii. Penetrations

• All pipe penetrations to have a 50mm fillet of Neoferma Detail Paste around the base of the pipe in addition to a 300 mm flashing of TotalSeal MS™ membrane, with a 150 mm turn up.

• A single waterstop or equivalent bead of Neoferma XSeal 600 Mastic to be installed around the pipe just prior to the concrete placement. Ensuring that there is sufficient cover as per material manufacturers specification.

Page 13: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 13 of 53

viii. Pile Caps

• At the pile slab junction, lap the TotalSeal MS™ a minimum of 75mm onto the top or side face. Install a minimum of 50mm Neoferma Seaming paste fillet under the TotalSeal MS™ against the pile side or on top of the pile beneath the 75mm lap.

• A minimum of one row of hydrophilic waterstop / Bentonite waterstop or equivalent bead of XSeal 600 Mastic installed strictly as per manufacturers specification.

ix. Wall / Floor Junctions

• At all wall floor junctions, a minimum of 50mm fillet of bentonite powder, granules, Neoferma seaming paste or SwellSeal Hydrobar Tubes is to be placed under the corner junction.

x. Waterstops

• All waterstops are to be placed in a manner that ensures that the bond to the concrete is "firm and continuous". Any void areas beneath the waterstop are to be levelled prior to application.

xi. Construction Joints / Non-Movement Joints.

• All construction joints require a minimum of one row of Neoferma specified hydrophilic or Bentonite based waterstop, installed strictly as per manufacturers specification and must have a minimum of 70 mm concrete cover. On high pressure areas two rows of waterstop are required.

• When installing waterstop to vertical slab construction joints, install a small waterstop or equivalent size bead of XSeal 600 Mastic as per manufacturers specification at five metre intervals running top to bottom of the slab. This is to provide "segmented cells" along the joint. (This is to prevent horizontal tracking of water between installed waterstops that may result from lateral cracks.)

• Waterstops are not recommended in expansion joints unless part of and in conjunction with approved systems for use in expansion or movement joints. Consult Neoferma Australia Pty Ltd for information.

Clean Up

• In areas where adjacent finished surfaces are soiled by work of this Section, consult manufacturer of surfaces for cleaning advice and conform to their recommendations and instructions. Remove all tools, equipment and remaining product on-site. Dispose of section work debris and damaged product following all applicable regulations.

Page 14: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 14 of 53

6. Maintenance & Warranty

a. There is no requirement for on-going maintenance of the membrane

once it has been confined by the concrete pour.

b. Warranty: Neoferma Australia Pty Ltd offers a range of warranty

periods up to 50 years dependent upon levels of certified inspection;

country and client’s requirements.

For examples of the NZ Basement Tanking warranty documents refer to

Appendix B.

To qualify for the TotalSeal MS™ warranty the following steps are required:

1. Warranty request with all relevant information provided, see Appendix B

warranty document for detail of information.

2. Independent Inspection, Distributor or Neoferma Inspection, minimum of 3

site visits during the installation process. See Appendix D for example

documents to be provided.

3. Job photos in conjunction with the site inspections to be on record in the

electronic project folder held by Neoferma Australia Pty Ltd.

7. Quality Management system elements

Key risks related to substrate condition, satisfactory installation and concrete

pour requirements are managed via a Quality Management documentation

system (BPQP manual). See Appendix D for relevant TotalSeal MS™ Technical

Support documents related to Site Inspections.

a. Applicator / Installer Training

Required for entities that have had no experience with the installation of

bentonite membranes.

Neoferma in Australia and Neptune Pacific in New Zealand provide a “hands

on” approach to training with a Product Familiarisation PowerPoint

presentation including required standard procedures. Followed by practical

demonstrations.

A Neoferma Technical Support representative will be present on site to provide

Installation training at the start-up of the project, and during the project life

until satisfied that the Applicator is fully conversant with the products.

Page 15: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 15 of 53

b. Project Checklists & Site Inspections (See Appendix D.)

Notice period required to arrange independent inspections or for a Neoferma or Neptune Technical Support person to visit site:

Minimum notice required: 2 days. At Contractors cost.

Give sufficient notice so that inspections can be made at the following stages:

1. All substrate surfaces prior to the application of the waterproofing system. 2. At completion of installed products, pre-steel placement. 3. Prior to concrete pours to inspect laps and terminations, Pre Hydration of

the membrane. Dependent upon the size of project and number of concrete pours this may entail several visits.

Non approved applicators must disclose to the Head Contractor in writing and

receive an acknowledgement that CodeMark Warranty / QA does not apply,

failure to do so is a prosecutable offence under Australian and New Zealand

law.

Page 16: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 16 of 53

APPENDIX: A

TotalSeal MS™ and Ancillary Products - Technical Data Sheets

Page 17: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 17 of 53

APPENDIX: A

TotalSeal MS™ and Ancillary Products - Technical Data Sheets

SwellSeal Granular Bentonite

TECHNICAL DATA SHEET

PRODUCT CODE: A15 ISSUE DATE: AUGUST 2017 V1

SWELLSEAL BENTONITE GRANULES

GENERAL Description:

A standard viscosity sodium bentonite with average particle size ranging from

between 0.850 and 0.212mm.

APPLICATIONS:

SwellSeal Bentonite Granules are a general purpose filler and extender for use when

mild thixotropic properties are desirable.

INSTALLATION:

• Neoferma SwellSeal Seaming Paste should be trowel (or hand) applied to approx 50-

75mm width of the top lap edge of the membrane and allowed to “ooze” out from the

lap.

• Smooth off the excess over the lap joint.

Typical Chemical composition (moisture free):

SiO2 31.02% MgO 1.35% Al2O3 11.04% Na2O 1.25%

Fe2O3 1.12% CaO 0.37% FeO 0.13% H2O 53.36%

Trace elements: 0.36%

Purity:

Hydrous aluminium silicate comprised principally of the clay mineral montmorillonite.

Montmorillonite content 90% minimum. Contains small percentage of feldspar,

biotite, selenite, etc.

Moisture Content: Maximum 13% shipped.

Dry particle size: Maximum 20% retained on a 1.18mm sieve.

Maximum 15% passing a 0.212mm sieve.

Page 18: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 18 of 53

APPENDIX: A

TotalSeal MS™ and Ancillary Products - Technical Data Sheets

TECHNICAL DATA SHEET

PRODUCT CODE: A36 ISSUE DATE: JUNE 2018 V2

NEOFERMA SEAMING PASTE

GENERAL Description:

Neoferma Seaming paste is a detailing accessory product for use with TotalSeal MS &

SwellSeal MS bentonite membranes to provide additional waterproofing protection. When

used on all horizontal and vertical membrane laps the seaming paste provides lap integrity

until the concrete pour is completed as the Neoferma Seaming Paste prevents movement

from construction operations or concrete placement.

APPLICATIONS:

Neoferma Seaming Paste is designed to work in conjunction with TotalSeal MS & SwellSeal

MS waterproofing membranes at the horizontal and vertical laps by providing a consistent

application of pre-hydrated sodium bentonite to secure the laps.

Neoferma Seaming Paste can also be used as a fillet for the footing/wall junction of

foundation walls providing additional waterproofing protection at this critical junction.

INSTALLATION:

Neoferma Seaming Paste should be trowel (or hand) applied to approx 50-75mm width of

the top lap edge of the membrane and allowed to “ooze” out from the lap.

• Smooth off the excess over the lap joint.

Typical Analysis:

SiO2 31.02% MgO 1.35%

Al2O3 11.04% Na2O 1.25%

Fe2O3 1.12% CaO 0.37%

FeO 0.13% H2O 53.36%

Trace elements: 0.36%

Packaging: 10kgs plastic pails.

Storage and shelf life: Maximum 12 months in sealed containers stored in a cool dry and

ventilated space.

Once open use immediately, will dry out if lid not replaced after each use.

Page 19: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 19 of 53

APPENDIX: A

TotalSeal MS™ and Ancillary Products - Technical Data Sheets

TECHNICAL DATA SHEET

PRODUCT CODE: A30 ISSUE DATE: JUNE 2018 V2

NEOFERMA DETAIL PASTE

GENERAL Description:

Neoferma Detail paste is a trowel grade, sodium bentonite based, detailing accessory

product for use with TotalSeal MS & Swellseal MS bentonite membranes, gasket and a

variety of surfaces. When used on all horizontal and vertical membrane laps the Detail paste

provides lap integrity until the concrete pour is completed as the DETAIL PASTE prevents

water ingress in the event of movement from construction operations or concrete placement.

APPLICATIONS:

Neoferma Detail paste is designed to work;

- Bonding waterstops to uneven surfaces

- At the horizontal and vertical laps by providing a consistent application of pre-

hydrated sodium bentonite to secure the TotalSeal bentonite membrane laps.

- Around drains and penetrations

- Sealing waterproofing terminations

- As a fillet for the footing/wall junction of foundation walls providing additional

waterproofing protection at this critical junction.

- Pre-cast manhole covers, cable ducts and pipes

- Sealing around precast segments

- Sealing rubber, and / or pvc waterstops

INSTALLATION for basement tanking specifically:

• Neoferma Detail Paste should be trowel (or hand) applied to approx 50-75mm width

of the top lap edge of the membrane and allowed to “ooze” out from the lap. Smooth

off the excess over the lap joint.

Packaging:

15kgs, plastic pails.

Storage and shelf life:

Maximum 12 months in sealed containers stored in a cool dry and ventilated space.

Page 20: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 20 of 53

APPENDIX: B

TotalSeal MS™ – Warranty Document examples

Example: NZ Warranty Template – Page 1

Page 21: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 21 of 53

APPENDIX: B

TotalSeal MS™ – Warranty Document examples

Example: NZ Warranty Template – Page 2

Page 22: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 22 of 53

APPENDIX: C

EXAMPLES OF GENERIC DETAIL DRAWINGS

Page 23: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 23 of 53

APPENDIX: C

EXAMPLES OF GENERIC DETAIL DRAWINGS

Page 24: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 24 of 53

APPENDIX: C

EXAMPLES OF GENERIC DETAIL DRAWINGS

Page 25: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 25 of 53

APPENDIX: C

EXAMPLES OF GENERIC DETAIL DRAWINGS

Page 26: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 26 of 53

APPENDIX: C

EXAMPLES OF GENERIC DETAIL DRAWINGS

Page 27: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 27 of 53

APPENDIX: C

EXAMPLES OF GENERIC DETAIL DRAWINGS

Page 28: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 28 of 53

APPENDIX: C

EXAMPLES OF GENERIC DETAIL DRAWINGS

Page 29: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 29 of 53

APPENDIX: C

EXAMPLES OF GENERIC DETAIL DRAWINGS

Page 30: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 30 of 53

APPENDIX: C

EXAMPLES OF GENERIC DETAIL DRAWINGS

Page 31: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 31 of 53

APPENDIX: C

EXAMPLES OF GENERIC DETAIL DRAWINGS

Page 32: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 32 of 53

APPENDIX: C

EXAMPLES OF GENERIC DETAIL DRAWINGS

Page 33: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 33 of 53

APPENDIX: C

EXAMPLES OF GENERIC DETAIL DRAWINGS

Page 34: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 34 of 53

APPENDIX: C

EXAMPLES OF GENERIC DETAIL DRAWINGS

Page 35: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 35 of 53

APPENDIX: C

EXAMPLES OF GENERIC DETAIL DRAWINGS

Page 36: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 36 of 53

APPENDIX: C

EXAMPLES OF GENERIC DETAIL DRAWINGS

Page 37: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 37 of 53

APPENDIX: C

EXAMPLES OF GENERIC DETAIL DRAWINGS

Page 38: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 38 of 53

APPENDIX: C

EXAMPLES OF GENERIC DETAIL DRAWINGS

Page 39: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 39 of 53

APPENDIX: C

EXAMPLES OF GENERIC DETAIL DRAWINGS

Page 40: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 40 of 53

APPENDIX: D

PROJECT CHECKLISTS / SITE INSPECTION DOCUMENTS

IPP 008 – Pre Project Start Up Checklist – Page 1

Page 41: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 41 of 53

APPENDIX: D

PROJECT CHECKLISTS / SITE INSPECTION DOCUMENTSIPP 008 – Pre Project

Start Up Checklist – Page 2

Page 42: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 42 of 53

APPENDIX: D

PROJECT CHECKLISTS / SITE INSPECTION DOCUMENTS

ITPC 030 V2 – Inspection Pre-Steel Placement – Installed products - Page 1

Page 43: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 43 of 53

APPENDIX: D

PROJECT CHECKLISTS / SITE INSPECTION DOCUMENTS

ITPC 030 V2 – Inspection Pre- Steel Placement – Installed products - Page 2

Page 44: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 44 of 53

APPENDIX: D

PROJECT CHECKLISTS / SITE INSPECTION DOCUMENTS

ITPC 030 V2 – Inspection Pre Steel Placement – Installed products - Page 3

Page 45: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 45 of 53

APPENDIX: D

PROJECT CHECKLISTS / SITE INSPECTION DOCUMENTS

ITPC 030 V2 – Inspection Pre Steel Placement – Installed products - Page 4

Page 46: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 46 of 53

APPENDIX: D

PROJECT CHECKLISTS / SITE INSPECTION DOCUMENTS

ITPC 031 V1 – Inspection Pre-Concrete Pour - Page 1

Page 47: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 47 of 53

APPENDIX: D

PROJECT CHECKLISTS / SITE INSPECTION DOCUMENTS

ITPC 031 V1 – Inspection Pre-Concrete Pour - Page 2

Page 48: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 48 of 53

APPENDIX: E

TotalSeal MS™ and Ancillary Products - Safety Data Sheets

Date of Issue: June 2018

Product Name: Neoferma TotalSeal MS™

Geosynthetic Bentonite Membrane Liner PRODUCT CODE: M12 MS5500 HP PLUS

Issued By: Neoferma Australia Pty Ltd.

Not Classified As Hazardous According to Criteria of Worksafe Australia.

This SDS summarizes to the best of our knowledge the health and safety hazard

information of the product and how to safely handle and use the product in the

workplace.

COMPANY DETAILS

Company Name: Neoferma Australia Pty Ltd

Address: PO Box 324, West Burleigh. QLD Australia 4219

Telephone Number: + 61 7 5576 4922

Emergency Number: (M) +61 419 773005 - 24 Hr.

Fax Number: +61 7 5576 4933

Poisons Information Centre: 13 11 26

Identification

Product Name: Neoferma TotalSeal MS™

Product Code: M12 MS5500 HP PLUS

UN Number: None Allocated

Dangerous Goods Class: None Allocated

Hazchem Code: None Allocated

Poisons Schedule: None Allocated

Packaging Group: None Allocated

USE:

Product Use: The Neoferma TotalSeal MS™ bentonite membrane is suitable for waterproofing.

Method of Application: By hand, rolling out prior to concrete pour.

PHYSICAL DESCRIPTION / PROPERTIES

The following information relates to the bentonite layer.

Appearance: odourless, off white to light tan powder

Temperature Working Range: Not applicable

Specific Gravity Not applicable

Flashpoint: Not applicable

Flammability Limits: Not applicable

Solubility in Water: Insoluble, however forms colloidal suspensions

INGREDIENTS:

Typically, bentonite is composed predominantly of the clay mineral Montmorillonite.

Page 49: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 49 of 53

CAS No: 1302-78-9 80 - 85%

HEALTH HAZARD INFORMATION

HEALTH EFFECTS:

Acute: Bentonite is physiologically inert.

Swallowed: Amounts swallowed during normal handling are not likely to cause

harm. Ingestion of bentonite may cause swelling of a homogenous mass up to 12 times the volume

of the bentonite powder. This may produce intestinal and bowel obstruction.

No serious poisoning hazard expected.

Eye: Mild irritant

Skin: May cause drying and minor irritation.

Inhaled: May cause irritation to the upper respiratory tract.

Chronic: Inhalation of crystalline silica over a long period of time may cause

silicosis

FIRST AID

Swallowed: Wash out mouth with water. Do not induce vomiting. Drink plenty

of water, Keep warm and at rest. Obtain medical attention immediately.

Eye: Wash continuously with water.

Skin: Wash continuously with water.

Inhaled: Remove from exposure. If upper respiratory tract irritation persists

seek medical advice. Show this SDS to the medical practioner.

First Aid Facilities: Provide ready access to running water and first aid kit.

ADVICE TO DOCTOR

Treat symptomatically.

PRECAUTIONS FOR USE

Exposure Limits: N/A

Where natural ventilation is inadequate use local mechanical exhaust ventilation at the point of dust

generation.

PERSONAL PROTECTION

Respiratory Protection: N/A

In confined spaces use air filter dust respirators

complying with AS 1716, or an approved equivalent.

Hand Protection: N/A.

Eye Protection: N/A.

Body Protection: N/A

This information may not be relevant for emergency service situations.

FLAMMABILITY - NOT FLAMMABLE

Page 50: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 50 of 53

SAFETY SAFE HANDLING INFORMATION

Storage and Transport:

Storage: Not classified as Dangerous Goods for storage.

Avoid contact with water.

Transport: Not classified as Dangerous Goods for transport.

Spills and Disposal:

Spills: Collect spills by vacuum or sweeping. Care should be taken to avoid

slippery surfaces which will occur when bentonite comes into contact with water.

Disposal: Dispose of product in accordance with Local State and Federal

regulations.

Environmental: N/A

Fire/Explosion Hazard:

Dangerous Decomposition: No hazardous decomposition products.

CONTACT POINT

Paul Lyden

Director, Neoferma Australia Pty Ltd

PO Box 324, West Burleigh. Qld. Australia 4219

Tel: (Bus. Hrs) +61 7 5576 4922 24Hr Tel: (M) +61 419 773 005

This data sheet and health, safety and the environmental information it contains is considered to be

accurate at the specified Issue Date. We have reviewed any information contained herein, which we

received from sources outside Neoferma Australia Pty Ltd. However, no warranty or

recommendation, expressed or implied, is made as to the accuracy or completeness of the data and

information contained in this data sheet. Health and safety precautions and environmental advice

noted in this data sheet may not be accurate for all individuals and / or situations. It is the user’s

obligation to evaluate and use this product safely and to comply with all applicable laws and

regulations. No statement made in this data sheet shall be construed as a permission,

recommendation or authorisation given or implied to practise any patented invention without a valid

licence. Neoferma Australia Pty Ltd shall not be responsible for any damage or injury from abnormal

use of the material, for any failure to adhere to recommendations, or from any hazards inherent in

the nature of the material.

Safety Data Sheet updated frequently. Please ensure you have a current copy.

End of SDS Report : July 2013 Reviewed and amended June 2018

Page 51: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 51 of 53

APPENDIX: E

TotalSeal MS™ and Ancillary Products - Safety Data Sheets

Date of Issue: March 25 2015,

Review date: June 2018 V1

Neoferma Australia Pty Ltd, ABN: 72 094 042

Unit 10, 4 Flagstone Drive, QLD 4220

Tel: +61 7 5576 4922 Email: [email protected]

IDENTIFICATION of the Substance/Preparation and Company name

Product Name: Neoferma Detail Paste

Product Code: A29

Product Use: Waterproofing material.

HAZARDS IDENTIFICATION

Main Hazards: Not classified as hazardous according to Work-safe criteria and NOHSC, but these are

naturally occurring bentonite clays and contain a small amount of crystalline quartz as an impurity.

UN Number: NONE ALLOCATED

Dangerous Goods Class & Subsidiary Risk: NONE ALLOCATED

Hazchem Code: NONE ALLOCATED

Poisons Schedule Number: NONE ALLOCATED

COMPOSITION/INFORMATION on Ingredients

Hazardous ingredients: Mono propylene glycol (CAS number 57–55–7)

Bentonite Clay - Natural Mineral, Montmorillonite (CAS number 1302-78-9)

Non hazardous substances 99 - 100%

FIRST AID MEASURES

INGESTION / Swallowed: No adverse effects expected for normal, incidental ingestion. If large

amounts are swallowed get immediate medical attention.

Skin Contact: No first aid should be needed since this product does not affect the skin. Wash

exposed skin with soap and water before breaks and at the end of the shift.

Eye Content: flush the eyes immediately with large amounts of water, lifting the upper and lower

lids occasionally. If irritation persists or for imbedded foreign body, get immediate medical

attention.

Inhalation: Move immediately to fresh air. If breathing has stopped. Perform artificial respiration. If

breathing is difficult have qualified personnel administer oxygen. Get prompt medical attention.

First Aid facilities: Must ensure eyewash and safety showers area available in close proximity to any

workplace.

FIRE FIGHTING MEASURES

Page 52: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 52 of 53

Fire Explosion hazard:

Product is combustible if in contact with naked flame.

Thermal decomposition in open flames can generate toxic gases (such as CO, CO2 and possibly

propionaldehyde vapours) as well as hazardous smoke and dust.

Normal extinguishing media is water spray, carbon dioxide, dry chemical or appropriate foam.

When fighting fires ensure use of SCBA units and full protective equipment.

ACCIDENTAL RELEASE MEASURES

Spills and Disposal:

After spills/accidents ensure Australian Standards approved chemical resistant PVC gloves and

protective clothing are worn.

Care must be taken as spillage may be slippery.

Shovel into suitably labelled containers for storage until disposed of via approved landfill. Avoid

contamination of drains and waterways.

Thoroughly wash area with water after spill collected.

HANDLING AND STORAGE

HAZCHEM: Not Applicable

STORAGE AND TRANSPORT

No special precautions required. Ensure containers tightly closed when not in use. Keep dry and

away from heat and open flames. Exercise good housekeeping.

EXPOSURE CONTROLS / PERSONAL PROTECTION

EXPOSURE STANDARDS: None applied by Worksafe Australia

ENGINEERING CONTROLS: Ensure ventilation at the immediate workplace is adequate to avoid

vapours in the immediate vicinity.

PERSONAL PROTECTION: Wear gloves, safety boots and glasses. Avoid skin, eye contact as well as

inhalation of the product. Always wash hands before eating, drinking, smoking or using the toilet.

Wash contaminated clothing and other protective equipment before re-use or storage. Gloves,

safety glasses and boots should comply with the appropriate Australian Standard.

FLAMMABILITY: This product is combustible.

PHYSICAL AND CHEMICAL PROPERTIES

Physical Description/Properties

Appearance: ODOURLESS, BEIGE PASTE

Page 53: TotalSeal MS ™ System BUILDING PRODUCT TECHNICAL ...€¦ · an expansion joint cover over properly installed expansion joint material placed during substrate preparation. To use

Neoferma Australia Pty Ltd BPT&IM V4 June 2018

Page 53 of 53

Boiling Point/Melting Point: NOT APPLICABLE

Vapour Pressure: (mm Hg.) NOT APPLICABLE

Specific Gravity: (H2o=1) 1.5 approx

Flashpoint: 103 deg C PMCC

Flammability Limits: COMBUSTIBLE-LEL = 2.6% and UEL = 12.5%

Solubility in Water: NEGLIGIBLE

STABILITY AND REACTIVITY

Stability: Stable – hazardous polymerisation will not occur.

TOXICITY

Toxicity: LD 50 (oral) = 21-33 g/kg (Rat)

IARC, NTP or OSHA does not list this product as a carcinogen, mutagen, teratogen or neurotoxin.

HEALTH EFFECTS

Acute Ingestion: No adverse health effects expected however diarrhoea may occur if large

quantities ingested.

Acute Eye: Slight to mild irritation.

Acute skin: May cause drying of skin (dermatitis) and may cause irritation.

Acute Inhalation:

Remove to fresh air. If breathing has stopped. Perform artificial respiration.

If breathing is difficult have qualified personnel administer oxygen.

Get prompt medical attention.

Facilities: No special requirements

Advice to Doctor: Treat symptomatically.

CONTACT POINT

Contact: +61 7 5576 4922 Director: Neoferma Australia Pty Ltd

This SDS summarises to our best knowledge at the date of issue, the chemical health and safety hazards of the material

and general guidance on how to safely handle the material in the workplace, however it shall not constitute a guarantee

for any specific product features and shall not establish a legally valid contractual relationship. Although some hazards are

described herein, we cannot predict that these are the only hazards because we have no knowledge or control over the

user’s working conditions. The user is responsible for the observance of all required statutory provisions. Each user should

read this SDS and consider the information in the context of how the product will be handled and used in the workplace,

including in conjunction with other products.


Recommended