MARCH 2016
Tower A | Tower B | Tower C | Tower D | Tower E | Tower F | Tower G
Tower H | Tower I | Tower J | Tower K | Tower L | Tower M | Tower N
TOWER A Level 12 roof completed
TOWER B Level 4 flooring work in Progress
TOWER C Terrace and internal Plastering work in progress
TOWER D • Level 12 flooring work in progress • Level 7 dado work in progress
TOWER E • Level 4 base molding work in progress
• Level 8 flooring work in progress
TOWER F• Common flooring works of level 10 and 4 are in progress
• Level 11 flooring work in progress • Terrace work in progress
TOWER G Terrace work in progress
TOWER H Level 1 work in progress
TOWER J Level 1 roof completed
TOWER K Level 20 roof completed
TOWER L • Upper basement floor completed• Level 1 column work in progress
TOWER M Level 1 roof completed
TOWER NUpper basement roof reinforcement work in progress