173020.00 ● Env. Assessment Registration Document ● April 2017
Town of Gander Wastewater Treatment Plant
Environmental Assessment Registration Document
Prepared by: Prepared for:
Town of Gander
Issued for Review G. Sheppard 04/11/17 M. Rutherford
Issue or Revision Reviewed By: Date Issued By:
This document was prepared for the party indicated herein. The material and
information in the document reflects CBCL Limited’s opinion and best
judgment based on the information available at the time of preparation. Any
use of this document or reliance on its content by third parties is the
responsibility of the third party. CBCL Limited accepts no responsibility for
any damages suffered as a result of third party use of this document.
Project No: 173020.00
173020.00 EA REGISTRATION DOCUMENT/hb ED: 19/04/2017 15:22:00/PD: 19/04/2017 15:22:00
April 11, 2017 Dept. of Municipal Affairs and Environment PO Box 8700 St. John’s, NL A1B 4J6 Attention: Ms. Susan Squires, Ph.D. Director of Environmental Assessment RE: Town of Gander – Wastewater Treatment Plant (WWTP) Environmental Assessment (EA) Registration Document CBCL Project # 173020.00 Dear Ms. Squires: Enclosed is our application and associated materials required for your review of the Environmental Assessment Registration Document for the above noted project. If you have any questions or require clarification, please contact me. Yours very truly, CBCL Limited Greg Sheppard Senior Civil Engineer Direct: 709-364-8623 E-Mail: [email protected]
Project No: 173020.00
CBCL Limited Gander WWTP -Environmental Assessment Registration Document i
Contents
CHAPTER 1 Name of Undertaking ............................................................................................ 1
CHAPTER 2 Proponent ............................................................................................................. 2
2.1 Name of Corporate Body .............................................................................................. 2
2.2 Address ......................................................................................................................... 2
2.3 Proponent ..................................................................................................................... 2
2.3.1 Director of Engineering ..................................................................................... 2
2.3.2 Mayor ................................................................................................................ 2
2.3.3 Chief Administrative Officer ............................................................................. 2
2.4 Principal Contact for Purpose of Environmental Assessment ...................................... 3
2.4.1 CBCL Limited Project Manager ......................................................................... 3
2.4.2 CBCL Limited Environmental Lead .................................................................... 3
CHAPTER 3 The Undertaking .................................................................................................... 4
3.1 Name of the Undertaking ............................................................................................. 4
3.2 Purpose/Rationale/Need for the Undertaking ............................................................. 4
CHAPTER 4 Description of the Undertaking.............................................................................. 6
4.1 Geographic Location ..................................................................................................... 6
4.2 Physical Features of the Undertaking ........................................................................... 6
4.2.1 Description of the Project ................................................................................. 6
4.2.2 Physical and Biological Setting .......................................................................... 9
4.3 Construction................................................................................................................ 12
4.3.1 Environmental Impacts during Construction .................................................. 13
4.3.2 Potential Source of Pollutants during Construction ....................................... 13
4.3.3 Mitigation Measures ....................................................................................... 14
4.3.4 Potential Causes of Resource Conflict ............................................................ 15
4.4 Operations .................................................................................................................. 16
4.4.1 Environmental Impacts during Operation ...................................................... 16
4.4.2 Potential Source of Pollutants during Operations .......................................... 16
4.4.3 Mitigation Measures during Operations ........................................................ 17
4.4.4 Potential Causes of Resource Conflict ............................................................ 18
4.5 Occupations ................................................................................................................ 19
4.5.1 Construction Phase ......................................................................................... 19
4.5.2 Operations Phase ............................................................................................ 19
CBCL Limited Gander WWTP -Environmental Assessment Registration Document ii
4.6 Project Related Documents ........................................................................................ 20
4.6.1 Public Meeting ................................................................................................ 20
4.6.2 Reference Documents .................................................................................... 20
CHAPTER 5 Approval of Undertaking ..................................................................................... 22
CHAPTER 6 Schedule ............................................................................................................. 24
CHAPTER 7 Funding ............................................................................................................... 25
Appendices
A Figures
B Geotechnical Investigation, Proposed New Wastewater Treatment Facilities
C Town of Gander, Open House / Public Meeting
CBCL Limited Gander WWTP - Environmental Assessment Registration Document 1
CHAPTER 1 NAME OF UNDERTAKING
Town of Gander Wastewater Treatment Plant
CBCL Limited Gander WWTP - Environmental Assessment Registration Document 2
CHAPTER 2 PROPONENT
2.1 Name of Corporate Body Town of Gander
2.2 Address 100 Elizabeth Drive
Gander, NL
A1V 1G7
2.3 Proponent 2.3.1 Director of Engineering
Name: James Blackwood
Official Title: Director of Engineering
Address: 100 Elizabeth Drive, Gander, NL, A1V 1G7
Telephone No: 709-651-5915
Email: [email protected]
2.3.2 Mayor
Name: Claude Elliott
Official Title: Major, Town of Gander
Address: 100 Elizabeth Drive, Gander, NL, A1V 1G7
Telephone No: 709-651-2930
Email: [email protected]
2.3.3 Chief Administrative Officer
Name: Dermot Chafe
Official Title: Chief Administrative Officer, Town of Gander
Address: 100 Elizabeth Drive, Gander, NL, A1V 1G7
Telephone No: 709-651-5920
Email: [email protected]
CBCL Limited Gander WWTP - Environmental Assessment Registration Document 3
2.4 Principal Contact for Purpose of Environmental Assessment 2.4.1 CBCL Limited Project Manager
Name: Greg Sheppard
Official Title: Senior Civil Engineer, CBCL Limited
Address: 187 Kenmount Rd, St. John's, NL A1B 3P9
Telephone No: 709-364-8623
Email: [email protected]
2.4.2 CBCL Limited Environmental Lead
Name: Melissa Rutherford
Official Title: Environmental Scientist, CBCL Limited
Address: 1489 Hollis Street PO Box 606, Halifax, NS, B3J 2R7
Telephone No: 902-421-7241 x2574
Email: [email protected]
CBCL Limited Gander WWTP - Environmental Assessment Registration Document 4
CHAPTER 3 THE UNDERTAKING
3.1 Name of the Undertaking Town of Gander Wastewater Treatment Plant
3.2 Purpose/Rationale/Need for the Undertaking The proposed project is a new Wastewater Treatment Plant (WWTP) located in Gander, NL. The purpose of the Project is to replace existing wastewater treatment facilities that do not meet the current Federal Wastewater Systems Effluent Regulations (WSER). The new WWTP will be designed to meet future wastewater treatment demands for the Town of Gander (herein referred to as the ‘Town’). The Town is currently serviced by two (2) WWTPs. The Beaverwood WWTP, a hydrodynamic separation plant, services the Southeast part of the Town. The Magee Road WWTP, an extended aeration plant, services the Northeast portion of the Town. The Beaverwood WWTP discharges to a stream that is tributary to Gander Lake, while the Magee Road WWTP discharges to Whitman’s Pond and, ultimately, to the Gander River. Current effluent sampling results indicate that neither treatment system meets WSER requirements. The Beaverwood WWTP sewershed contains areas serviced with combined sewers. This plant was designed to accommodate large volumes of flow, but is still reported to overflow during extreme rainfall events. The overflow is located upstream of the headworks; therefore, wastewater that discharges via the overflow is not treated. The Magee Road WWTP is located in an area of Town experiencing significant growth. This facility is currently operating at approximately 95% capacity and cannot accommodate future growth. Land in this area is becoming increasing valuable for development. Further, the Town has received odour complaints from nearby residents. The design population has been projected to be 17,500 in 2040. This reflects the fact that the Town is growing rapidly, and that continued rapid growth is expected, although at a somewhat lower rate (8% per 5 years) than the last few years (11% per 5 years). Future growth is assumed to expand the current built-up area at a similar density to the current Magee Road WWTP catchment. The 2015 population is approximately 12,000, as projected from 2011 census data, and 5,500 more people are projected to join the Town in the next 25 years (Statistics Canada 2017).
CBCL Limited Gander WWTP - Environmental Assessment Registration Document 5
The new WWTP will include preliminary, primary, and secondary levels of treatment as well as effluent disinfection to mitigate the effect of the effluent discharge on the receiving water. The facility design will consider residuals handling procedures in order to safely and effectively handle wastewater treatment residuals such as screenings, grit, and sludge. Further details of the project are described in section 4.2.1. The project delivery method for the new WWTP is the Design-Build method. By this method, a short-listed group of contractor-engineer teams will respond to a Request for Proposals which outlines the performance requirements for the WWTP. The successful proponent becomes the Design-Build contractor.
CBCL Limited Gander WWTP - Environmental Assessment Registration Document 6
CHAPTER 4 DESCRIPTION OF THE UNDERTAKING
4.1 Geographic Location The proposed location of the wastewater treatment system is approximately 3 km East of Cooper Boulevard in Gander, NL (Figure 4.1 and Figure 4.2 in Appendix A). Located South of Whitman’s Pond, treated effluent would be discharged to Whitman’s Pond, which flows to Jonathan’s Pond, which is outside of the Gander Lake watershed. There are no marked water bodies identified on the proposed site. The project site will be accessed via newly constructed roads constructed from Cooper Boulevard. The proposed project would be located on Crown Lands and land controlled by the Gander International Airport Authority (GIAA); the property area, including the site, access road and sewer easements, is approximately 44 hectares. The proposed lot property boundaries for the WWTP are:
Northwest boundary – N 5428347.04, E 408669.50
Northeast boundary – N 5428510.67, E 409039.34
Southwest boundary – N 54 27809.24, E 408907.44
Southeast boundary – N 5427972.87, E 409277.28. The Town is in discussions with the Crown and the GIAA for the procurement/lease of these properties. The site is situated in a rural area removed from future development. This proposed WWTP location is currently forested, and as such some areas of the site will be cleared and grubbed during site preparation. This location was selected as the preferred option of several sites under consideration, as adequate separation distances from the Town are easily achieved at this location. Accordingly, the risk of exposure to odours is minimized.
4.2 Physical Features of the Undertaking 4.2.1 Description of the Project The Town intends to design and construct the WWTP to treat wastewater at variable rates. A 60-year life span for structural components and a 15-25 year life span for mechanical, electrical and instrumentation components are anticipated. Project components will include the WWTP proper,
new access roadways, new trunk sewers and an outfall. Major features are described below.
CBCL Limited Gander WWTP - Environmental Assessment Registration Document 7
4.2.1.1 WASTEWATER TREATMENT FACILITY The new WWTP will include a number of major features, which are described, in general terms, below. The exact number of these features, materials of construction, and configuration will be determined by the Design-Build contractor.
Process building(s): These will contain preliminary treatment equipment, offices, control room, electrical room, and process equipment that must be sheltered, such as blowers and UV disinfection units. It is anticipated that 1-3 process buildings will be required.
Large basins for solids removal: These basins are unaerated to promote effective settling of solids from the wastewater. These may be constructed of earthen berms lined with an impervious liner, or of concrete or fibreglass-reinforced plastic.
Large basins for biological organics removal: These basins are typically aerated actively or passively to foster the growth of microorganisms to metabolize and remove the organic matter in the wastewater. These may be constructed of earthen berms lined with an impervious liner, or of concrete or fibreglass-reinforced plastic.
The design of the WWTP processes and equipment, including the major features, will comply with the more stringent requirements from the following list of design guidelines, which cover all aspects of the design of wastewater treatment facilities:
Atlantic Canada Wastewater Guidelines Manual for Collection, Treatment, and Disposal (Environment Canada, 2006).
Guidelines for the Design, Construction and Operation of Water and Sewerage Systems (NL Department of Environment and Conservation, Water Resources Management Division, 2005).
Recommended Standards for Wastewater Facilities, “Ten State Standards” (Great Lakes – Upper Mississippi River Board of State and Provincial Public Health and Environmental Managers, 2014).
The WWTP will include the following levels of treatment, as a minimum, as shown in Figure 4.3:
Figure 4.3: Proposed WWTP treatment unit operations The exact equipment and configuration will be determined by the Design-Build contractor, but a typical process train is described below:
Preliminary Treatment uses automated screens and/or grit removal equipment to remove large, non-biodegradable solids. This produces a “screenings” waste stream and possibly a “grit” waste stream, both of which must be removed from site and disposed of in an approved waste-disposal facility such as a landfill. The total annual volume of screenings projected to be produced under 2040 design flow conditions is 73 m³.
Primary Treatment uses large, quiescent tanks to provide conditions for settling out of fine solids. This produces a “sludge” waste stream which is typically dewatered, and may be partly biodegraded on site to stabilize it before eventual removal from site and disposal in an approved waste-disposal facility such as a landfill.
Preliminary Treatment: Large solids
removal
Primary Treatment: Fine solids removal
Secondary Treatment:
Organic matter removal
Disinfection: Pathogen
deactivation
CBCL Limited Gander WWTP - Environmental Assessment Registration Document 8
Secondary Treatment uses large, usually aerated tanks to provide conditions for microbes to metabolize and remove organic matter. This produces a “sludge” waste stream which is typically dewatered, and may be partly biodegraded on site to stabilize it before eventual removal from site and disposal in an approved waste-disposal facility such as a landfill. The total annual volume of sludge (primary and secondary combined) projected to be produced under 2040 design flow conditions is 3,000 m³/year, assuming 15% solids.
Disinfection uses banks of ultraviolet (UV) lights to deactivate pathogens so that they cannot reproduce. This produces no waste streams. Chlorination and dechlorination will not be used for disinfection because of the risk of unacceptable chlorine release into the receiving water.
The WWTP will produce effluent of a quality that meets or exceeds the values presented below in Table 4.1, in accordance with WSER and Provincial requirements.
Table 4.1: Treated Effluent Quality Objectives
Parameter Units Measurement
Method
Monitoring
Location Value
Carbonaceous Biochemical
Oxygen Demand - CBOD5 mg/L Composite Final Effluent 25
Total Suspended Solids -TSS mg/L Composite Final Effluent 25
Un-ionized ammonia mg/L Composite Final Effluent 1.25
Total Residual Chlorine (TRC) mg/L Grab Final Effluent 0.00
Total Coliforms MPN/mL Grab Final Effluent 5,000
E.Coli MPN/mL Grab Final Effluent 1,000
pH Composite Final Effluent 6.5–9.0
The site will be equipped with security perimeter fencing system around the perimeter of WWTP and a gated entry at the access road to the WWTP. The fencing and gate shall deter and delay unauthorized entry or access by animals or humans, control the exit and entry through designated openings. A security system will be developed to monitor boundaries of the facilities and detect attempts at unauthorized entry and exit. The site layout will be designed so that surface water does not drain into treatment process units. All surface storm water will be piped underground to a natural drainage course. Adequate drainage slopes and pipes shall be provided to accommodate run off along any earthworks or structures constructed. Drainage from access roads and parking lots shall be captured and discharged to a common location, as approved by the Town and authorities having jurisdiction.
The WWTP will rely on electricity to operate most of the equipment required for operations. An emergency generator will be located on site to provide power to all the equipment in the case of a power outage so that releases of inadequately treated effluent and excessive odours do not occur due to loss of power. 4.2.1.2 LINEAR INFRASTRUCTURE Sewers and force mains will connect the existing Town sewers at the locations of the current WWTPs to the proposed WWTP. The proposed linear infrastructure will include approximately 4.3
CBCL Limited Gander WWTP - Environmental Assessment Registration Document 9
km of new sewers and sewage force mains, and one sewage lift station (Figure 4.2). Much of the proposed locations are currently forested, and will need to be cleared in order to construct the pipelines. Sewer pipes and water mains shall be installed in separate trenches with a minimum of 3 m of undisturbed soil in between. Sewer pipes shall have a minimum cover of 1.8 m to prevent freezing. 4.2.1.3 ACCESS ROAD The access road will be 2.2 km long and will connect Cooper Boulevard in Gander to the proposed WWTP site (Figure 4.2). A new entrance will be established off of this new roadway to give direct access to the site. The roadway will run adjacent to the proposed new trunk sewer alignment to the WWTP, and power will be brought to site along the access road. The road will have a minimum width of 6 m. The proposed cleared road alignment is 15 m in width. The new access road and onsite parking lots shall be serviceable and free draining under all weather conditions. 4.2.1.4 OUTFALL DITCH AND EFFLUENT DISCHARGE The outfall ditch will connect the WWTP to in Whitman’s Pond (Figure 4.2). The WWTP shall produce water of quality that meets or exceeds the values presented below in Table 4.2. Table 4.2 Treated Effluent Quality Objective
4.2.2 Physical and Biological Setting Setting & Major Vegetation: The project is located in the Northcentral Subregion of the Central Newfoundland Forest Ecoregion. The Ecoregion is characterized by the Hylocomium-Balsam Fir (Hylocomium splendens and Abies balsamea respectively) forest type. As result of fire occurrences, much of the Hylocomium-Balsam Fir forest type has been converted to a black spruce (Picea mariana) forest type with white birch (Betula papyrifera) and aspen (Populus tremuloides and P. grandidentata) hardwood forests noted at richer sites. Aspen within the Central Newfoundland forest is more abundant than in other regions. Other species that are abundant in other regions, but absent within the Central Newfoundland Forest, include yellow birch (Betula alleghaniensis) due to the short frost-free period. Unique to this subregion, the high summer temperatures may stimulate aspen root suckering and contribute to the local success of aspen (Damman 1983). This subregion can be susceptible to regeneration failure due to low moisture, coarse soils and the prevalence of black spruce cover types. Succession to dwarf shrub heath dominated by sheep laurel
Parameter Units Measurement
Method Value
Carbonaceous Biochemical Oxygen Demand -
CBOD5 mg/L Composite 25
Total Suspended Solids -TSS mg/L Composite 25
Un-ionized Ammonia mg/L Composite 1.25
Total Residual Chlorine (TRC) mg/L Grab 0.00
Total Coliforms MPN/mL Grab 5,000
E.Coli MPN/mL Grab 1,000
pH Composite 6.5–9.0
CBCL Limited Gander WWTP - Environmental Assessment Registration Document 10
(Kalmia angustifolia) may occur where tree regeneration is lacking, and nutrient-poor, coarse textured till is present. The Project site itself is relatively flat, heavily forested, and falling slightly in elevation from west to east. The Ecoregion is generally characterized with rolling to undulating topography below 200 m. Forestry: The Project is located in Forest Management District 5 of the Eastern Region of Newfoundland. There are no known Corner Brook Pulp and Paper Limited (CBPPL) Timber Harvest Rights on the property. Soils: Soils within the region are generally medium quality till that is shallow, lighter in colour, and has lower organic matter content compared to other ecoregions. The soil texture ranges from sandy loam to loam. Soils in the northern part of this ecoregion can display moisture deficiency, because of seasonal warm summer temperatures and high evapo-transpiration losses (Government of Newfoundland and Labrador 2017). Shallow groundwater is present in the project area ranging from 0.2 to 3.7 m (Englobe 2016; Appendix B). Climate: The Central Newfoundland Ecoregion has the highest summer and lowest winter temperatures of the Newfoundland ecoregions (Government of Newfoundland and Labrador 2017). The coldest day on average is recorded in January and February (daily average -7.1 °C), with peak summer temperature observed in July (16.3 °C, Environmental Canada 2017). Despite an average summer temperature above 0°C, night frost can occur in any summer month (Government of Newfoundland and Labrador 2017). Average annual precipitation is 1,270.2 mm, with most precipitation falling as rain. The highest precipitation is recorded in December with an average of 126.7 mm (Environment Canada 2017). The Northcentral sub region is known to higher summer maximum temperatures, lower rainfall and higher frequency of fires than the other regions of Newfoundland (Government of Newfoundland and Labrador 2017). Prevailing winds at this location are to the west, and will generally be in the direction of populated areas (Environment Canada 2017). Hydrology: Whitman’s Pond is located approximately 200 m north of the proposed WWTP. Whitman’s Pond is within the Jonathan’s Brook watershed and flows to Jonathan’s Pond, which is outside of the Gander Lake watershed. The Jonathan’s Pond series of lakes is used for recreational activities (camping, swimming, canoeing, etc.). Surface water generally flows northward from the site toward Whitman’s Pond or east toward a wetland located south of Whitman’s Pond. Whitman’s Pond is a shallow lake, with an average depth of 1.2 m and a maximum depth of 2.2 m (D Keefe, pers. comm. March 21, 2017). Whitman’s Pond currently receives effluent from the Magee Road WWTP. Sampling by NL ECC Aquatic Research Program found that the background conditions of the Pond exceeded the CCME guideline for iron (2004 and 2005), and Chlorophyll A (2004). The othro-phosphate concentration range from 30 to 40 µg/L in 2004 and 2005. Wildlife and Species of Concern: Common mammal wildlife that may be present within the Project area include moose, snowshoe hare, Arctic hare, fox, muskrat, otter, mink, black bear, beaver, lynx, and other small fur bearing mammals (Government of Newfoundland and Labrador 2016). Bird species that may be present in the forest vegetated areas include raptors species (Bald Eagle, Osprey, Merlin, Boreal Owl, Great Horned Owl and Sharp-shinned Hawk), and grouse species (Ruffed Grouse and Spruce Grouse). The Project is located in close proximity to the Whitman’s Pond area
CBCL Limited Gander WWTP - Environmental Assessment Registration Document 11
identified in the Gander – Benton Stewardship Agreement, which provides productive waterfowl wetlands, with abundant aquatic vegetation providing important cover for protection from predators (Government of Newfoundland and Labrador 2007). Waterfowl species that may be observed include Green-winged Teal, Ring-necked Duck and Canada Goose. Within the Gander region, the Gander River is located approximately 12 km north of the Project and is designated as Scheduled Salmon Rivers (DFO 2017a, b). Species present within Whitman’s Pond include brook trout, Atlantic salmon, three spined stickleback, and nine spined stickleback (D Keefe, pers. comm. March 21, 2017). Both Atlantic salmon and brook trout have special harvesting management plans for this area (DFO 2017b). Also within the watershed (Jonathans Pond), American eel can be present (D Keefe, pers comm. March 21, 2017). The Atlantic Canada Conservation Data Centre (AC CDC) documented 2 rare plant observations and 80 rare animal observations within 5km of the Project. Of the 80 rare animal records, the following species of conservation concern were observed: Rusty Blackbird, Gray-Cheeked Thrush, Barn Swallow, Olive-sided Flycatcher and Red Crossbill. The remaining species observed where not provincially or nationally listed, but are considered rare on the island and include American Tree Sparrow, Brown Creeper, Bufflehead, Mourning Dove, Northern Goshawk, Northern Harrier and insects. The 2 rare plant records included species that are not provincially or federally listed, and outside of Newfoundland & Labrador are not considered globally rare (A. Durocher, AC CDC, pers comm. March 21, 2017). Based on AC CDC Expert opinion maps of provincially and federally listed species, no species have been identified within 5 km of the project location; however, the Expert Opinion Maps suggest that banded killifish presence is possible, while boreal felt lichen, Newfoundland marten and Short-eared Owl are possible, but unlikely (A. Durocher, AC CDC, pers comm. March 21, 2017). Species of conservation concern are species that are protected by provincial and/or federal legislation. Species that are or may be found in the project area include the following (Table 4.3): Table 4.3 Species of Conservation Concern
Species NL Endangered
Species Act Status
Canadian Species at Risk Act (SARA)
Committee on the Status of
Endangered Wildlife in Canada
(COSEWIC)
Bird
Barrow's Goldeneye
Bucephala islandica
Vulnerable Schedule 1 – Special
Concern
Special Concern
Bobolink
Dolichonyx oryzivorus
Vulnerable No Status Threatened
Chimney Swift
Chaetura pelagica
Threatened Schedule 1 –
Threatened
Threatened
Common Nighthawk
Chordeiles minor
Threatened Schedule 1 –
Threatened
Threatened
CBCL Limited Gander WWTP - Environmental Assessment Registration Document 12
Species NL Endangered
Species Act Status
Canadian Species at Risk Act (SARA)
Committee on the Status of
Endangered Wildlife in Canada
(COSEWIC)
Eskimo Curlew
Numenius borealis
Endangered Schedule 1 –
Endangered
Endangered
Gray-cheeked Thrush
Catharus minimus
Vulnerable No Status
Harlequin Duck
Histrionicus
Vulnerable Schedule 1 – Special
Concern
Special Concern
Newfoundland Gray-cheeked Thrush
Catharus minimus
Threatened No Status
Olive-sided Flycatcher
Contopus cooperi
Threatened Schedule 1 –
Threatened
Threatened
Red Crossbill
Loxia curvirostra percna
Endangered Schedule 1 –
Endangered
Endangered
Red Knot
Calidris canutus rufa
Endangered Schedule 1 –
Endangered
Endangered
Rusty Blackbird
Euphagus carolinus
Vulnerable Schedule 1 – Special
Concern
Special Concern
Short-eared Owl
Asio flammeus
Vulnerable Schedule 1 – Special
Concern
Special Concern
Fish
American eel
Anguilla rostrata
Vulnerable No Status Threatened
Banded Killifish
Fundulus diaphanous
Vulnerable Schedule 1 – Special
Concern
Special Concern
Protected Areas: There are no existing Provincial protected areas or Federal parks/reserves on the property; however, the Project is located upstream of the Jonathan's Pond Provincial Park reserve. The Town of Gander signed a Municipal Wetland Stewardship Agreement with the Province of Newfoundland in 1993 and recommitted to this initiative in 2007 for another 30-year period. Several wetlands and waterbodies were identified as part of this agreement, including the area around Whitman’s Pond and a 100 m area from the high water mark, and associated marsh south of Whitman’s Pond (Government of Newfoundland and Labrador, 2007). The construction and operation of this proposed WWTP will align with the initiative as stated in the Stewardship Agreement.
4.3 Construction Regular Project hours for construction are to be Monday to Friday from 07:00 to 18:00 hours and on Saturdays, Sundays and statutory holidays from 08:00 to 17:00. Approval is required to work
CBCL Limited Gander WWTP - Environmental Assessment Registration Document 13
outside of regular hours or days of the Project. Request approval from the Owner’s Engineer at least 72 hours in advance if work is scheduled outside these times. The site will be prepped, backfilled, graded, and compacted for the purposes of construction. All surfaces within the boundary of the WWTP will be either newly paved, top soil and seeded, sodded, planted, undisturbed or low maintenance river stone around tankage. Buildings, hardscape, roads and parking areas will not be developed within 30.5 m of any natural wetlands or watercourses. Excluding buried infrastructure, power sourcing and road access, no component of the treatment facility shall be constructed within a 25 m buffer around the entire site perimeter. The following construction activities will be required for site preparation activities:
Site clearing (road and site);
Site excavation and backfilling;
Site compaction;
Roadway construction;
Construction of onsite infrastructure;
Paving;
Use of temporary facilities;
Security perimeter fencing installation;
Storm water management; and
Sodding and seeding.
4.3.1 Environmental Impacts during Construction The Project will be designed and constructed so as to minimize risk and potential environmental impacts. Potential environmental impacts that have been identified include:
Removal of vegetation;
Disruption of wildlife, including fish;
Silt and sedimentation runoff;
In-water works (outfall placement);
Smoke from brush burning;
Dust;
Construction debris;
Risk of fuel, lubricant and hydraulic fluid release;
Airborne emissions from construction equipment;
Noise pollution from construction activities; and
Temporary disruption of traffic.
4.3.2 Potential Source of Pollutants during Construction Potential sources of pollutants that may occur as a result of construction include the following:
Spills and releases (sewage from temporary toilets, fuel, lubricant and hydraulic fluid
release);
Silt and sedimentation runoff;
Airborne exhaust emissions from construction equipment;
Noise from construction activities;
Dust; and
Construction debris.
CBCL Limited Gander WWTP - Environmental Assessment Registration Document 14
4.3.3 Mitigation Measures The Town and their contractors will follow all specified permit conditions and construction best management practices during construction. The following project specific mitigation measures will be implemented during construction so as to mitigate potential sources of pollutants from entering the environment:
A site specific Environmental Management Plan (EMP) will be developed and followed.
All debris and waste materials will be disposed of in accordance with the latest regulations respecting Solid Waste Resource Management issued by the Newfoundland and Labrador
Department of Municipal Affairs and Environment (MAE). Non-hazardous construction and demolition debris will be either recycled or salvaged; items may include cardboard, metal, brick, mineral fibre panel, concrete, plastic, clean wood, glass, gypsum wallboard, carpet and insulation. A construction waste management plan will be developed and will include designated specific area(s) on the construction site for segregated or comingled collection of recyclable materials.
On completion of the Project, all construction equipment, surplus materials and temporary works will be cleared away and removed from the site.
Temporary weather tight enclosures and protection for exterior openings will be used until permanently enclosed.
Only new or reused, clean materials will be used for the purposes of backfill, and grading.
Surface soil stripping will be minimized where possible; material will be stockpiled and reused where possible.
Dust mitigation measures will be implemented. Specific measures might include dust suppression activities such as wetting of the construction areas and sweeping and washing of paved road surfaces.
All equipment used on site will be in good working order to reduce effects of noise.
All construction activities will occur during working hours as defined in the permit.
As required, traffic control will be provided by certified traffic control persons, in accordance with the Traffic Control Manual issued by the Newfoundland and Labrador Department of Transportation and Works. Access will be maintained for all emergency vehicles in construction areas.
The Project will be designed to minimize disruption to existing natural areas. All removal and disposal of trees, brush, stumps, surface litter, boulders and grubbings will follow applicable permits and best management practices.
An Erosion and Sediment Control Plan will be implemented prior to construction and will describe the measures implemented to prevent loss of soil during construction by stormwater run-off and wind erosion. The Plan will include protecting topsoil by stockpiling for reuse; preventing sedimentation of storm sewer or receiving streams; and preventing air pollution by dust and particulate matter. Temporary erosion and pollution control devices such as silt fences will be used to mitigate possible sources of pollutants.
Dewatering plans and associated measures will be implemented to control the inflow of groundwater into excavations. Measures may include use of earthworks such as perimeter ditches and sump pumps. Any discharge of water from the site will be conducted in accordance with applicable environmental guidelines.
All soils and surface water impacted via spills and releases will be disposed of off-site in accordance with all applicable environmental regulations and legislation.
Any liners will be tested for leakage during commissioning.
CBCL Limited Gander WWTP - Environmental Assessment Registration Document 15
It is proposed that the outfall will be installed by a means to reduce impact to the environment. If possible, it will be installed in a dry environment, i.e. cofferdams, to isolate the sediment and erosion during outfall installation.
The proposed location of the WWTP will be fenced to minimize unauthorized access and wildlife conflicts.
4.3.4 Potential Causes of Resource Conflict Mitigation measures and best management procedures will be established and monitored to minimize all potential resource conflicts. Land Disturbance: Construction equipment will not be permitted to operate outside the construction zone to prevent damaging adjacent areas. Where possible, surface soil will be reused. Standard safety and environmental practices will be enforced to reduce and prevent potential conflicts caused by construction equipment and tasks. The project is located in a rural and undeveloped area; disturbance to surrounding properties is not anticipated. Surface Water and Surface Water Management: An Erosion and Sediment Control Plan will be implemented prior to construction and will describe the measures implemented to prevent loss of soil during construction by stormwater run-off or wind erosion, including protecting topsoil by stockpiling for reuse; prevent sedimentation of storm sewer or receiving streams; prevent pollution of the air with dust and particulate matter. Temporary erosion and pollution control devices such as silt fences will be used to mitigate the possible sources of pollutants. Following these requirements, minimal conflicts are expected. Groundwater: During excavation activities or removal of existing soil materials, there is a potential for interactions with groundwater. Dewatering plans and associated measures will be implemented to control the inflow of groundwater. Discharge of water from the site will be conducted in accordance with applicable environmental guidelines. All liners will be tested for leakage during commissioning. Following these requirements, no conflicts are expected. Fish and Fish Habitat: Construction activities will be designed and executed so as to minimize impacts to any body of water and, therefore, minimize effects on any fish or fish habitat areas. As such, all activities related to the outfall construction will be coordinated with the regulatory agencies at both Provincial and Federal levels. It is proposed that the outfall will be installed by a means that would reduce impact to the environment. If possible, the outfall will be installed in-the-dry with measures such as silt fencing and cofferdams installed to isolate the sediment and erosion during installation. Any culvert installations will follow best management practices and guidelines to reduce impacts to watercourses and fisheries. Following these requirements, minimal conflicts are expected. Wildlife: Short-term effects to wildlife are expected during the construction period. Operation of machinery, equipment, human presence, and noise may result in temporary avoidance behaviours by animals in the vicinity of the WWTP and associated Project components. Best management practices will be implemented for the handling of domestic refuse generated during construction in order to reduce potential for wildlife (i.e. bears) to opportunistically forage on these materials, hence becoming a nuisance. If problem wildlife/nuisance animals are encountered, the appropriate authorities will be contacted. Following these requirements, minimal conflicts are expected.
CBCL Limited Gander WWTP - Environmental Assessment Registration Document 16
Vegetation and Forestry: The project area consists of forested areas. All equipment used on site will be clean and clear to prevent the spread of invasive weeds. Where practical, vegetation removal should be completed outside of the bird breeding period (typically April 1st to August 31st). If clearing is required within the bird breeding period, pre-clearing bird nest surveys will be required to be completed by a qualified biologist to ensure no active nests are destroyed or impacted by clearing. Following these requirements, no conflicts are expected.
Air Emissions and Quality: Air emissions and air quality measures will be implemented into the Environmental Management Plan to prevent pollution of the air with dust and particulate matter. All equipment and construction activities on site will occur during approved working hours and all equipment used on site will be in good working order to reduce effects of noise. Following these requirements, no conflicts are expected. Human Activities: The access road will be aligned from the existing roadway (Cooper Blvd.) to the WWTP site. This private road will be gated in order to restrict any unauthorized access to the WWTP area. If required, temporary traffic management will be implemented at the connection to Cooper Blvd. There are no registered homes or cabins in the vicinity of the proposed project. Though snowmobile and ATV trails in the area may intersect with the proposed access road, there is no expectation of any significant level of human conflicts.
4.4 Operations The WWTP will operate year round following construction, and will be sized to treat the future design flows shown in Table 4.4 for the year 2040. Flows were monitored at the existing treatment plants to establish current flows, and census data was used for 2016 populations. A program of sewer separation and rehabilitation is underway to reduce wet weather flows and bring average and peak flows per capita down to more typical ranges. Table 4.4 Proposed WWTP Flows
4.4.1 Environmental Impacts during Operation The Project will be operated so as to minimize risk and potential environmental impacts. Potential environmental impacts that have been identified include:
Controlled release of treated effluent (liquid or odour);
Uncontrolled release of treated effluent (liquid or odour);
Noise pollution from operation activities; and
Silt and sedimentation runoff.
4.4.2 Potential Source of Pollutants during Operations Potential sources of pollutants that may occur as a result of operation include the following:
Treated effluent;
Dewatered and biodegraded solids;
Parameter Units 2016 (Measured) 2040 (Design)
Connected Population capita 11,688 17,500
Average Day Flow (ADF) m³/day 8,994 10,500
Peak Day Flow (PDF) m³/day 20,346 23,800
CBCL Limited Gander WWTP - Environmental Assessment Registration Document 17
Treatment chemicals;
Airborne exhaust emissions from operational equipment;
Odours;
Noise pollution from operational equipment; and
Storm water runoff from site.
4.4.3 Mitigation Measures during Operations The Town will follow all specified permit conditions and best management practices during operation. The following project specific mitigation measures will be implemented during operations to mitigate potential sources of pollutants from entering the environment:
All chemical systems shall be contained with separate drainage systems for each chemical dosing system.
Each chemical storage tank will be corrosion proof and shall have at least 110% the storage capacity of the largest tank.
Sumps will be located in the containment areas such that they can be pumped out with a small portable pump.
Unloading of tankers shall be carried out within a shallow containment or sloping area draining to an isolated sump (road tanker containment area). This sump shall be capable of being pumped out using the same pump as that provided to pump out the chemical tank containment areas. The drains adjacent to the sumps shall be connected to the sanitary sewerage system.
The treatment plant and related infrastructure shall be designed to minimize the production of odours. Specific engineered measures shall be in place to mitigate the propagation of odours, such as aeration, ventilation, and odour removal through bio-filters or chemical scrubbers. The proposed treatment plant location is in a rural area in order to avoid the risk of odour nuisance to neighbouring properties.
Noise from the WWTP when operating at full capacity with all systems operating normally, not including the emergency generator, shall not exceed 65 dBA at the plant boundary. Noise generation will be limited using the following design practices:
o Design equipment for normal operation at lower rotational speeds; o Locate noise generating equipment away from points of compliance; o Orient discharge stacks directly upwards; and o Use features such as sound traps, silencers, enclosures and sound walls.
Odour monitoring shall occur four times throughout the first year with a minimum of two months between samples. During each sampling event, six air samples, taken at two-hour intervals, will be taken at four sampling sites at the plant perimeter using a flux chamber. At least one sample shall be taken during worst-case odour dispersion scenarios (high temperatures, low wind speed) during a period of low flow. Samples shall be tested offsite using independent testing staff for odour units.
Provide adequate dust control and ventilation to any areas where dry powders are batched or stored.
Effluent quality will be monitored for compliance with applicable permits (Table 4.5).
CBCL Limited Gander WWTP - Environmental Assessment Registration Document 18
Table 4.5 Compliance Sampling Requirements (WSER)
1 Effluent samples for compliance determination shall be based on the collection of a 24-hour composite sample every two weeks, separated by at least 7 days. Each composite sample shall include a minimum of 2 discrete samples, with samples evenly distributed throughout the 24-hour period. 2 Quarterly average compliance shall be based on composite sample results from each Quarter as defined in the WSER regulations. 4.4.4 Potential Causes of Resource Conflict Surface Water and Surface Water Management: The effluent from the proposed WWTP will meet or surpass the WSER and Provincial requirements. An effluent sampling program will be implemented to confirm that the effluent meets or exceeds the requirements for discharge into the environment. Following these requirements, no conflicts are expected. Groundwater: All liners will be tested for leakage during operations. Following these requirements, no conflicts are expected. Fish and Fish Habitat: The outfall will be both designed and scheduled for installation to reduce and minimize the impact on fish and fish habitat. All of the outfall work will be coordinated with the MAE and the Department of Fisheries and Oceans. The effluent to be discharged to Whitman’s Pond from the WWTP will be of better quality than the effluent from the current WWTP. Following these requirements, no conflicts are expected. Wildlife: There are no additional resource conflicts expected for wildlife during operation. Vegetation and Forestry: There are no additional resource conflicts expected for vegetation and forestry during operations. Air Emissions and Quality: Operations will be implemented so as to reduce effects from noise and odour. The WWTP is over 1,000 m from the nearest residential area; therefore, the undertaking is not expected to impact everyday human activity given the secluded location of the site. As such, no additional conflict is expected. Human Activities: The private road will be gated to restrict unauthorized access to the WWTP area. Though snowmobile and ATV trails in the area may intersect with the proposed Trunk sewer and access road, there is no expectation of any significant level of human conflicts.
Parameter Units Sampling Frequency1 Monitoring
Location
Quarterly
Average2
CBOD5 mg/L Composite Every 2 weeks Final Effluent 25
TSS mg/L Composite Every 2 weeks Final Effluent 25
pH - Composite Every 2 weeks Final Effluent 6.5 to 9.0
Un-Ionized
Ammonia
mg/L Composite Every 2 weeks Final Effluent 1.25
Total Coliforms MPN/ 100 mL Grab Every 2 weeks Final Effluent 5,000
Fecal Coliforms MPN/ 100 mL Grab Every 2 weeks Final Effluent 1,000
CBCL Limited Gander WWTP - Environmental Assessment Registration Document 19
4.5 Occupations Design and construction will be the responsibility of the Build contractor with input from the Town, the Town’s Project Manager, and the Town’s Engineer. The Design-Build contractor will ultimately decide on the numbers and types of employees working on the project following final design. Anticipated project estimates have been provided below for evaluation; however, final estimates will be dependent on the successful contractor. Employment equity will be the responsibility of the successful contractors during the design and construction. The Town of Gander has already developed employment equity policies that will be followed in any employment opportunities. 4.5.1 Construction Phase It is projected that the following occupations will be required for employment during the construction phase of the project. Table 4.6 displays the approximate anticipated number of positions during construction and their associated National Occupational Classification (NOC) codes. Table 4.6 Anticipated Positions / Occupations Required during Construction Phase
Position
National
Occupational
Classification Group
Title Code
Number Positions
Anticipated
Duration of
Employment
(months)
Construction Manager 0711 1 18
Construction Trades Helpers &
Laborers
7611 4 18
Land Surveyors 2154 2 6
Contractors & Supervisors, Heavy
Construction Equipment Crews
7217 6 18
Contractors and Supervisors,
Other Construction Trades,
Installers, Repairs and Services
7219 6 18
Construction Inspectors 2264 2 18
Electricians 7241 4 6
Heavy Equipment Operators 7412 4 12
Carpenters 7271 8 6
Bricklayers 7281 4 6
Truck Drivers 7411 4 12
Landscape Architects 2185 0 0
Other Trades Helpers and Laborers 7612 6 18
4.5.2 Operations Phase The Town already employs staff to handle daily operations and maintenance at the active WWTPs; however, new positions may be required. It is projected that the following occupations will required for employment during the operations phase of the project. Table 4.7 displays the approximate anticipated number of positions during operations and their NOC code.
CBCL Limited Gander WWTP - Environmental Assessment Registration Document 20
Table 4.7 Anticipated Positions / Occupations Required during Operation Phase
Position National Occupational
Classification Group Title Code
Number Positions Anticipated
Duration of Employment
(months)
Utilities Manager 0912 0.5 Indefinite
4.6 Project Related Documents 4.6.1 Public Meeting The Town of Gander held an Open House and Public Meeting on March 28, 2017 to present information on the project and to outline the process for the registration of the undertaking according to the Environmental Protection Act and Environmental Assessment Regulations. The public was able to ask questions and present areas of concerns during this session. A summary of the topics covered and concerns raised are presented in Appendix C. 4.6.2 Reference Documents The following resources were used to form this document Damman, A.W.H. 1983. An Ecological Subdivision of the Island of Newfoundland, pp. 163-206. South, G.R. (ed.), Biogeography and Ecology of the Island of Newfoundland. Dr. W. Junk Publ., The Hague. Durocher, Adam. Data Manager, Atlantic Canada Conservation Data Centre, Corner Brook, Newfoundland and Labrador. March 21, 2017. Fisheries and Oceans Canada. 2017a. Newfoundland and Labrador Angler’s Guide 2016-2017. Available: http://www.nfl.dfo-mpo.gc.ca/NL/AG/MWatershedManagementPlans. Accessed March 16, 2017. Fisheries and Oceans Canada. 2017b. Newfoundland and Labrador Angler’s Guide 2016-2017. Available: http://www.nfl.dfo-mpo.gc.ca/folios/01019/docs/anglersguide-guidedepecheur-2016-17-eng.pdf Accessed March 16, 2017. Government of Canada. 2017. Canadian Climate Normals 1981 – 2010 Station Data – Gander Int’L A – Climate ID: 8401700 Available: http://climate.weather.gc.ca/climate_normals/results_1981_2010_e.html?stnID=6633&autofwd=1. Accessed: March 10, 2017. Government of Newfoundland and Labrador. Department of Fisheries, Forestry, and Agrifoods – Ecoregions of Newfoundland. Available http://www.faa.gov.nl.ca/forestry/maps/central_eco.html. Accessed: March 10, 2017. Government of Newfoundland and Labrador, Department of Environment and Climate Change. 2016. Hunting & Trapping Guide 2016-2017. Available: http://www.ecc.gov.nl.ca/wildlife/pdf/Hunting_Trapping_Guide.pdf. Accessed: March 17, 2017.
CBCL Limited Gander WWTP - Environmental Assessment Registration Document 21
Government of Newfoundland and Labrador. 2007. Stewardship Agreement between Her Majesty the Queen in Right of Newfoundland and Labrador and the Town Council of Gander dated March 14, 2007. Available: http://www.ecc.gov.nl.ca/wildlife/stewardship/community_profiles/pdf/Gander.pdf. Accessed March 16, 2017. Keefe, Donald. Ecosystem Management Ecologist, Aquatic, Wildlife Division, Newfoundland and Labrador, Department of Municipal Affairs and Environment, Corner Brook, Newfoundland and Labrador. March 21, 2017. Statistics Canada. 2017. Census Profile – Gander, Newfoundland. Available http://www12.statcan.gc.ca/census-recensement/2011/dp-pd/prof/details/page.cfm?Lang=E&Geo1=POPC&Code1=0311&Geo2=PR&Code2=12&Data=Count&SearchText=&SearchType=Begins&SearchPR=01&B1=All&Custom=&TABID=1. Accessed March 30, 2017. The following Project related documents have been provided for further information: Englobe. 2016. Geotechnical Investigation - Proposed New Wastewater Treatment Facilities, Ref. N°: 20784. Report Prepared for Town of Gander, c/o MHPM Project Managers Inc. by Englobe, Mount Pearl, NL, Canada dated June 2016.
CBCL Limited Gander WWTP - Environmental Assessment Registration Document 22
CHAPTER 5 APPROVAL OF UNDERTAKING
Additional permits, approvals and authorizations may be required for the construction and operation of the Gander WWTP. The following permits, approvals, and authorizations from various issuing agencies that may be required include, but are not limited to, the items listed in Table 5.1. Table 5.1 List of Permits, approvals and authorization for the Undertaking
Permit, Approval or Authorization Applicable Legislation Issuing Body
Approval for the Undertaking Environmental Protection Act /
Environmental Assessment
Regulation
Minister of Municipal Affairs and
Environment
Certificate of Approval
Certificate of Approval –
Sewage Treatment Plant
Certificate of Approval –
Water and Sewer Distribution
System (update)
Water Resources Act Water Resources Division,
Department of Environment and
Climate Change
Alterations to a Body of Water –
Schedule A - Culvert
Water Resources Act Water Resources Division,
Department of Environment and
Climate Change
Crown Lands
Applications/Licenses
Lands Act Customer Services, Department of
Municipal Affairs
Permit to Cut Crown Timber Forestry Act /
Cutting of Timber Regulations
Department of Fisheries, Forestry
and Agrifoods
Burn Permit
Operating Permit
Forestry Act /
Forest Fire Regulations
Department of Fisheries, Forestry
and Agrifoods
Approval under the National
Building Code of Canada
Service NL,
Department of Government
Services
Storage and Handling of Gasoline
and Associated Products
Application
Environmental Protection Act/
Gasoline and Associated Products
Regulations
Department of Municipal Affairs
and Environment
CBCL Limited Gander WWTP - Environmental Assessment Registration Document 23
Access agreements with neighbouring properties may be required for right-of-way and access allowances during construction and operations. These will be negotiated by the Town of Gander and other parties such as the GIAA.
CBCL Limited Gander WWTP - Environmental Assessment Registration Document 24
CHAPTER 6 SCHEDULE
The project design is scheduled to commence in July, 2017. Upon receipt of all required approvals and authorizations, the estimated start date for construction is October, 2017. Project operations are estimated to commence in April, 2019.
CBCL Limited Gander WWTP - Environmental Assessment Registration Document 25
CHAPTER 7 FUNDING
The estimated capital cost for the design, construction and commissioning of the Gander WWTP is $35M. The annual operation and maintenance costs will be estimated when the final technology has been selected. For the purpose of evaluation, annual operation and maintenance costs could range from $50,000 to $500,000 annually. Funding will be obtained from Federal, Provincial and Municipal sources. The breakdown is as follows:
Federal: $11.7M
Provincial: $10.3M
Municipal: $13M Upon successful award of government funding, the Town will contribute the remainder of the funding.
This document was prepared for the party indicated herein. The material and information in the document reflects CBCL Limited’s opinion and
best judgment based on the information available at the time of preparation. Any use of this document or reliance on its content by third parties
is the responsibility of the third party. CBCL Limited accepts no responsibility for any damages suffered as a result of third party use of this
document.
CBCL Limited Appendices
APPENDIX A
Figures
FIG-4.2-REV 0 SITE PLAN
CBCL Limited Appendices
APPENDIX B
Geotechnical Investigation Proposed New Wastewater Treatment Facilities
Town of Gander c/o MHPM Project Managers Inc.
Geotechnical Investigation Proposed New Wastewater Treatment Facilities
Report
Date: June 2016 Ref. N°: 20784
39 Sagona Avenue, Mount Pearl (Newfoundland and Labrador) Canada A1N 4P9 – 709.576-8148 | F 709.576.3713 – [email protected]
Town of Gander c/o MHPM Project Managers Inc.
Geotechnical Investigation Proposed New Wastewater Treatment Facilities
Report | 20784
Prepared by:
Janet Williams, P.Eng.
Geotechnical Engineer
28-June-2016
TABLE OF CONTENTS
P20784
GEOTECHNIC AL INVESTIG ATION – PROPOSED NEW WAST EWA TER TREAT MENT FAC IL I T IES, JUNE 2016
i
1 INTRODUCTION............................................................................................................1
2 PROJECT DESCRIPTION.............................................................................................1
3 INVESTIGATION PROCEDURE ...................................................................................1
4 SUBSURFACE CONDITIONS.......................................................................................2
4.1 Soil Conditions .....................................................................................................2 4.2 Laboratory Testing ...............................................................................................4 4.3 Groundwater Conditions ......................................................................................6
5 CLOSURE ......................................................................................................................6
Tables
Table 1. Summary of Test Pit Locations, Termination Depths and Groundwater Depths ..... 2 Table 2. Summary of Laboratory Results .............................................................................. 5 Table 3. Summary of Monitoring Well Locations and Levels................................................. 6
Figures
Figure 1. Test Pit Location Plan- Pipelines
Figure 2. Test Pit Location Plan - WWTP
Figure 3. Monitoring Well Location Plan - WWTP
Appendices
Appendix 1 Explanataion of Terms and Symbols Appendix 2 Test Pit and Monitoring Well Logs Appendix 3 Laboratory Test Results
P20784
GEOTECHNIC AL INVESTIG ATION – PROPOSED NEW WAST EWA TER TREAT MENT FAC IL I T IES, JUNE 2016
ii
Property and Confidentiality
“This engineering document is the property of Englobe Corp. and, as such, is protected under Copyright Law. It can only be used for the purposes mentioned herein. Any reproduction or adaptation, whether partial or total, is strictly prohibited without having obtained Englobe’s and its client’s prior written authorization to do so.
Test results mentioned herein are only valid for the sample(s) stated in this report.
Englobe’s subcontractors who may have accomplished work either on site or in laboratory are duly qualified as stated in our Quality Manual’s procurement procedure. Should you require any further information, please contact your Project Manager.”
REVISION AND PUBLICATION REGISTER
Revision N° Date Modification And/Or Publication Details
A 2016-03-21 Draft Report Issued for Information and Review
1 2016-06-28 Final Report Issued
P20784
GEOTECHNIC AL INVESTIG ATION – PROPOSED NEW WAST EWATER TREAT MENT FAC IL I T IES, JUNE 2016
1
1 INTRODUCTION
Englobe Corp (Englobe), at the request of MHPM Project Managers Inc., on behalf of the Town
of Gander, has carried out a geotechnical investigation at the locations of a proposed new
wastewater treatment plant (WWTP) and the associated new pipeline corridors. The purpose of
the work was to assess the subsurface and groundwater conditions in these areas.
This report presents the observations of the geotechnical investigation of the proposed locations.
Included herein are the factual results of the field investigation including discussion of field
procedures, subsurface conditions, and laboratory analysis.
It is understood that the Owner’s Technical Consultant (OTC) for the wastewater treatment
facility project is CBCL Limited (CBCL).
2 PROJECT DESCRIPTION
It is understood that the Town of Gander is planning for the replacement of their two existing
wastewater treatment plants, namely the Magee Road Sewage Treatment Plant and the
Beaverwood Sewage Treatment Plant, with a new wastewater treatment plant. The new facility
will be capable of treating all of Gander’s current needs as well as having the built-in capacity to
handle future growth of the municipality. The scope of work associated with this project includes
the construction of new trunk sewers, construction of a new wastewater treatment facility, and
decommissioning of one or both of the two existing sewage treatment plants or possible
refurbishment of the Beaverwood plant to serve as a combined sewage and storm water
treatment facility during high flow events.
The planned location of the new WWTP is northeast of Town of Gander and south of Whitman’s Pond. Site reconnaissance with the CBCL, found that the original proposed location of the
WWTP, just south of Whitman’s Pond, was a marsh. The proposed location was moved by
CBCL to along the northeastern boundary of the Bowater property. The new proposed location
generally slopes down gently to the northwest to Whitman’s Pond.
3 INVESTIGATION PROCEDURE
The fieldwork for the test pit investigation was carried out between November 27, 2015 and April
8, 2016. Sixty-two (62) test pits were excavated using an excavator supplied by ANW
Construction Limited. The locations of all test pits were provided by CBCL. Due to accessibility
issues, primarily boggy areas, some locations had to be altered. The approximate as-built test
pit locations are indicated on the enclosed site plans, Figure 1 and Figure 2. Test pit locations
were referenced in the field to UTM-NAD-83 Zone 22 Grid system using a held-held GPS unit.
The co-ordinates for each test pit location are shown in Table 1.
P20784
GEOTECHNIC AL INVESTIG ATION – PROPOSED NEW WAST EWATER TREAT MENT FAC IL I T IES, JUNE 2016
2
The site investigation was carried out by qualified geotechnical engineering personnel who
located the test pits in the field and logged the subsurface conditions. Grab samples were
obtained from the test pits and placed in waterproof bags and transported to our Mount Pearl
laboratory for further examination and testing.
The fieldwork for the monitoring well installation was carried out between June 21, 2016 and
June, 2016. Eight (8) boreholes were drilled using a truck-mounted drill rig supplied to the project
by Logan Geotech Inc. and were advanced through the overburden using standard solid stem
augers. Standard Penetration Testing and soil sampling were performed (where possible) in the
overburden using a 50-mm diameter split-spoon sampler. A 50 mm diameter PVC monitoring
well was installed in each borehole. Well details are shown on the Borehole Logs in Appendix
2. The approximate as-built test pit locations are indicated on the enclosed site plan, Figure 3.
Borehole locations were referenced in the field to UTM-NAD-83 Zone 22 Grid system using a
held-held GPS unit. The co-ordinates for each monitoring well location are shown in Table 3.
4 SUBSURFACE CONDITIONS
4.1 Soil Conditions
An explanation of terms and symbols used in the report is provided in Appendix 1. A summary
of the encountered geologic conditions is provided in the Test Pit Logs in Appendix 2. Laboratory
test results are provided in Appendix 3.
It should be noted that the stratigraphic boundaries on the Test Pit Logs typically represent a
transition of one soil type to another and do not necessarily indicate an exact plane of geologic
change. Subsurface conditions may vary between and beyond the test pit locations.
Groundwater observations were made during the field investigation through open-hole
measurement at the test pit locations. A summary of the accumulated groundwater information
is provided on the Test Pit Logs in Appendix 2 and in Table 1.
Table 1. Summary of Test Pit Locations, Termination Depths and Groundwater Depths
Test Pit Northing Easting Depth (m) Water Seepage
Location Termination Groundwater
TP-01 5426329 676195 3.0 0.9 Rootmat/till surface
TP-02 5426526 676262 3.0 0.3 Rootmat/till surface
TP-03 5426751 676153 3.4 ne -
TP-04 5426958 676063 3.0 0.3 Rootmat/till surface
TP-05 5427202 675936 2.7 0.3 Rootmat/till surface
TP-06 5427427 675827 2.7 0.8 Peat/till surface
TP-07 5427652 675718 3.0 2.9 Within till
P20784
GEOTECHNIC AL INVESTIG ATION – PROPOSED NEW WAST EWATER TREAT MENT FAC IL I T IES, JUNE 2016
3
Test Pit Northing Easting Depth (m) Water Seepage
Location Termination Groundwater
TP-08 5427877 675607 3.0 ne
TP-09 5427545 674848 2.9 0.0 Through peat
TP-10 5427508 675095 3.4 1.2 Rootmat/till surface
TP-11 5427471 675311 3.0 2.7 Within till
TP-12 5427513 675544 3.2 0.5 Rootmat/till surface
TP-13 5428131 675649 3.0 0.9 Peat/till surface
TP-14 5427475 676055 2.1 1.2 Peat/till surface
TP-15 5427478 676305 3.0 0.6 Peat/till surface
TP-16 5427565 676519 4.6 ne -
TP-17 5427747 676684 2.7 0.9 Within till
TP-18 5427899 676883 2.4 ne -
TP-19 5428015 677111 3.0 0.9 Within till
TP-A0 5428443 676940 4.0 3.7 Within bedrock
TP-A1 5428486 677031 3.7 ne -
TP-A2 5428529 677121 4.3 ne -
TP-A3 5428570 677213 4.3 2.7 Within till
TP-A4 5428606 677312 4.3 3.0 Within till
TP-A5 5428401 676848 2.7 2.4 Within till
TP-A6 5428359 676757 1.5 0.6 Rootmat/till surface
TP-A7 5428318 676666 4.0 1.5 Within till
TP-B0 5428355 676976 3.4 ne -
TP-B1 5428379 677069 3.4 1.5 Peat/till surface
TP-B2 5428437 677163 4.9 0.3 Rootmat/till surface
TP-B3 5428479 677254 2.4 1.5 Within till
TP-B4 5428521 677345 3.0 0.9 Peat/till surface
TP-B5 5428310 676890 2.3 0.6 Peat/till surface
TP-B6 5428268 676799 2.7 1.5 Within till
TP-B7 5428227 676708 3.0 0.9 Peat/till surface
TP-C0 5428263 677031 3.7 0.9 Within till
TP-C1 5428305 677114 3.4 1.5 Within till
TP-C2 5428347 677205 4.3 0.5 Peat/till surface
TP-C3 5428388 677296 2.7 0.6 Peat/till surface
TP-C4 5428436 677398 2.7 1.4 Peat/till surface
P20784
GEOTECHNIC AL INVESTIG ATION – PROPOSED NEW WAST EWATER TREAT MENT FAC IL I T IES, JUNE 2016
4
Test Pit Northing Easting Depth (m) Water Seepage
Location Termination Groundwater
TP-C5 5428219 676931 3.7 ne -
TP-C6 5428178 676841 4.0 0.6 Peat/till surface
TP-C7 5428136 676750 3.4 0.5 Peat/till surface
TP-D0 5428170 677064 4.6 ne -
TP-D1 5428214 677155 3.0 1.2 Peat/till surface
TP-D2 5428261 677236 3.7 0.5 Peat/till surface
TP-D3 5428297 677337 2.7 0.9 Peat/till surface
TP-D4 5428339 677428 2.7 0.8 Peat/till surface
TP-D5 5428128 676973 3.4 2.7 Within till
TP-D6 5428087 676882 4.0 0.3 Peat/till surface
TP-D7 5428045 676791 3.4 0.3 Peat/till surface
TP-E0 5428086 677111 4.3 0.5 Peat/till surface
TP-E1 5428118 677201 3.0 0.9 Within till
TP-E2 5428165 677288 3.7 ne -
TP-E3 5428220 677381 4.6 0.9 Peat/till surface
TP-E4 5428239 677455 4.6 0.9 Peat/till surface
TP-E5 5428037 677015 2.7 0.5 Peat/till surface
TP-E6 5427996 676924 3.4 0.5 Peat/till surface
TP-E7 5427954 676833 2.7 1.8 Within till
TP-F1 5428033 677242 4.6 0.9 Within till
TP-F2 5428074 677329 4.6 1.2 Within till
TP-F3 5428116 677421 4.6 0.9 Within till
TP-F4 5428157 677511 4.0 0.8 Within till
TP-F5 5428199 677603 4.6 ne -
4.2 Laboratory Testing
Grab samples were obtained from each test pit during the geotechnical investigation. 29
samples were submitted to our Mount Pearl laboratory for moisture content and grain size
analysis. . A summary of the laboratory testing results is provided on the Test Pit Logs in
Appendix 2 and in Table 1. The laboratory results are provided in Appendix 3.
P20784
GEOTECHNIC AL INVESTIG ATION – PROPOSED NEW WAST EWATER TREAT MENT FAC IL I T IES, JUNE 2016
5
Table 2. Summary of Laboratory Results
Test Pit Depth (m) Gravel (%) Sand
(%) Fines (%)
Moisture Content
(%)
Liquid Limit
Plastic Limit
TP-01 2.7 24 33 43 10.2 Non-plastic
TP-02 2.4 15 41 44 - 18 12
TP-03 3.0 34 36 30 11.2 Non-plastic
TP-04 2.4 26 46 28 - Non-plastic
TP-05 2.4 33 35 32 10.3 Non-plastic
TP-06 2.4 36 30 34 - 19 13
TP-07 2.7 19 39 42 10.1 Non-plastic
TP-10 3.0 26 41 32 9.7 Non-plastic
TP-11 3.0 27 39 34 - Non-plastic
TP-12 2.7 32 42 27 10.1 Non-plastic
TP-16 3.0 29 39 32 12.7 Non-plastic
TP-A0 2.7 30 36 34 10.1 19 14
TP-A2 3.0 38 33 29 8.7 Non-plastic
TP-A3 3.0 29 35 36 12.5 Non-plastic
TP-A7 3.7 30 36 34 8.8 Non-plastic
TP-B1 2.4 31 29 39 9.2 Non-plastic
TP-B3 1.2 52 26 22 7.9 Non-plastic
TP-B6 2.4 31 34 35 9.9 18 14
TP-C0 3.0 17 54 29 12.6 Non-plastic
TP-C2 3.0 39 31 30 10.3 Non-plastic
TP-C4 1.8 40 34 26 8.1 21 15
TP-C5 3.4 29 39 32 10.4 Non-plastic
TP-D1 3.0 19 42 40 13.3 Non-plastic
TP-D3 2.4 21 38 41 11.9 20 13
TP-E0 2.4 39 32 29 10.5 19 12
TP-E7 2.4 23 34 43 12.7 19 14
TP-F3 1.5 18 34 48 13.0 17 12
TP-F4 2.4 28 33 39 10.5 Non-plastic
TP-F4 3.7 25 45 30 8.6 Non-plastic
P20784
GEOTECHNIC AL INVESTIG ATION – PROPOSED NEW WAST EWATER TREAT MENT FAC IL I T IES, JUNE 2016
6
4.3 Groundwater Conditions
Each monitoring well was drilled adjacent to previous excavated test pit and the monitoring well
soil profile shown on the borehole logs is based on each corresponding test pit. The
approximate elevations shown in Table 3 are based on current available topographical
mapping of the site area. Note that for MW-B3 and MW-E3 elevation could not be determined
since available mapping did not cover these locations. For MW-C0 and MW-E0, the water
level in the wells had not stabilized when groundwater level was taken.
Table 3. Summary of Monitoring Well Locations and Levels
Monitoring Well Northing Easting
Approximate Surface
Elevation (m)
Groundwater
Depth (m)
Approximate Elevation (m)
MW-A0 5428443 676940 104.5 2.2 102.3
MW-A7 5428318 676666 103 1.7 101.3
MW-B3 5428479 677254 Na1 1.2 -
MW-C0 5428263 677031 106 3.22 102.8
MW-C7 5428136 676750 105 0.2 104.8
MW-E0 5428086 677111 109.5 3.22 106.3
MW-E3 5428220 677381 Na1 0.2 -
MW-E7 5427954 676833 108 0.5 107.5 Notes: 1. Elevation not available
2. Water level not stabilized.
Based on observations during both field investigations, intermittent bog areas were
encountered in the proposed WWTP location. Therefore during excavation and removal of
existing peat/rootmat materials soils, control of inflow of groundwater into excavations will be
required. Where appropriate, the flow of water should be controlled by the earthworks
contractor by using perimeter ditches and sump pumps. Control of groundwater during site
preparation is a critical factor and dewatering plans should be reviewed by designers prior to
start of any construction activities. Discharge of water from the site must be conducted in
accordance with applicable environmental guidelines for sediment and any potential
environmental contamination concentrations.
5 CLOSURE
The geotechnical investigation undertaken has involved random sampling of site conditions.
Should any conditions be encountered during constructions that are contrary to those reported
herein, we request immediate notification so that reassessment can be undertaken.
Pro
ject:
Date
:S
cale
:D
raw
n b
y:
Checked b
y:Job N
um
ber:
Tow
n o
f G
ander
TE
ST
PIT
LO
CA
TIO
N P
LA
N -
PIP
ELIN
E
Fig
ure
1June 2
016
N/A
JLW
SS
20784
Pro
posed N
ew
Waste
wate
r T
reatm
ent
Facili
ties
TP-02
BH-05
BH-02
TP-03
BH-01
TP-04
TP-06
BH-04
BH-03
TP-05
TP-02
Pro
ject:
Date
:S
cale
:D
raw
n b
y:
Checked b
y:Job N
um
ber:
Tow
n o
f G
ander
Pro
posed N
ew
Waste
wate
r T
reatm
ent
Facili
ties
TE
ST
PIT
LO
CA
TIO
N P
LA
N -
WW
TP
SIT
E
Fig
ure
2June 2
016
N/A
JLW
SS
20784
TP-02
BH-05
BH-02
TP-03
BH-01
TP-04
TP-06
BH-04
BH-03
TP-05
TP-02
Pro
ject:
Date
:S
cale
:D
raw
n b
y:
Checked b
y:Job N
um
ber:
Tow
n o
f G
ander
Pro
posed N
ew
Waste
wate
r T
reatm
ent
Facili
ties
MO
NIT
OR
ING
WE
LL L
OC
AT
ION
PLA
N -
WW
TP
SIT
E
Fig
ure
3June 2
016
N/A
JLW
SS
20784
TP-02
BH-05
BH-02
TP-03
BH-01
TP-04
TP-06
BH-04
BH-03
TP-05
TP-02
Appendix 1 Explanation of Terms and
Symbols
SYMBOLS AND TERMS USED ON THE BOREHOLE AND TEST PIT RECORDS
SOIL DESCRIPTION
Behavioural properties (i.e. plasticity, permeability) take precedence over particle gradation in describing soils.
Terminology describing soil structure:
Desiccated - having visible signs of weathering by oxidationof clay minerals, shrinkage cracks etc.
Fissured - having cracks, and hence a blocky structureVarved -composed of regular alternating layers of silt
and clayStratified - composed of alternating layers or different soil
types, e.g. silt and sand or silt and clayWell Graded - having wide range in grain sizes and substantial
amounts of all intermediate particle sizesUniformly Graded - predominantly of one grain size.
Terminology used for describing soil strata based upon the proportion of individual particle size present:
Trace, or occasional Less than 10%Some 10-20%Adjective (e.g. silty or sandy) 20-35%And (e.g. silt and sand) 35-50%
The standard terminology to describe cohesionless soils includes the relative density, as determined bylaboratory test or by the Standard Penetration Test ‘N’ - value: the number of blows of 140 pound (64 kg)hammer falling 30 inches (760 mm), required to drive a 2 inch (50.8 mm) O.D. split spoon sampler one foot(305 mm) into the soil.
Relative Density ‘N’ Value Relative Density %
Very loose <4 <15Loose 4-10 15-35Compact 10-30 35-65Dense 30-50 65-85Very Dense >50 >85
The standard terminology to describe cohesive soils includes the consistency, which is based on undrained shearstrength as measured by insitu vane tests, penetrometer tests, unconfined compression test, or occasionally bystandard penetration tests.
Consistency Undrained Shear Strength ‘N’ ValueKips/sq.ft. kPa
Very Soft <0.25 <12.5 <2Soft 0.25-0.5 12.5-25 2-4Firm 0.5-1.0 25-50 4-8Stiff 1.0-2.0 50-100 8-15Very Stiff 2.0-4.0 100-200 15-30Hard >4.0 >200 >30
SOIL SAMPLES
CONDITION – This column graphically indicates the depth and condition of the sample:
TYPE – The type of sample is indicated in this column as follows:
A auger sampleB block sampleC rock core, or frozen soil coreD drive sampleG grab sampleSS split spoonP Pitcher tube sampleU tube sample (usually thin-walled)W wash or air return sampleO other (see report text)
PENETRATION RESISTANCE – Unless otherwise noted this column refers to the number ofblows (N) of a 140 pound (63.5 kg) hammer freely dropping 30 inches (0.76 m) required to drive a2 inch (50.8 mm) O.D. open-end sampler 0.5 feet (0.15 m) to 1.5 feet (0.45 m) into the soil, oruntil 100 blows have been applied, in which case, the penetration is stated. This is the standardpenetration test referred to in ASTM D 1586.
OTHER TESTS
In this column are tabulated results of other laboratory tests as indicated by the followingsymbols:
*C Consolidation testFines Percentage by weight smaller than #200 sieveDR Relative density (formerly specific gravity)k Permeability coefficient*MA Mechanical grain size analysis and hydrometer test (if appropiate)pp Pocket pentrometer strength*q Triaxial compression testqU Unconfined compressive strength*SB Shearbox testSO4 Concentration of water-soluble sulphate*ST Swelling testTV Torvane shear strengthVS Vane Shear Strength (undistrubed-remolded)
f Unit strain at failureUnit weight of soil or rock
d Dry unit weight of soil or rockDensity of soil or rock
d Dry density of soil or rock
* The results of these tests usually are reported separately
undisturbed disturbed not recovered
Appendix 2 Test Pit and Monitoring Well
Logs
Appendix 3 Laboratory Test Results
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Fax: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 10025.4 9719.1 9312.7 869.53 834.76 761.20 64
0.600 590.300 550.150 500.075 43.5
Moisture Content, %: 10.2
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
3343
MHPM Project Managers Inc.1559 Brunswick Street, Suite 501Halifax, Nova ScotiaB3J 2G1
TP01 Grab Sample
Gander WWTP
20784
SIEVEANALYSISREPORT
MTPL-0130
J. Williams of Englobe7/Dec/157/Dec/15
Steve Matthews
2.7m1
NANANA
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
PHYSICAL PROPERTY TESTSGrab Sample
24
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Fax: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 10025.4 9819.1 9612.7 939.53 924.76 851.20 72
0.600 650.300 590.150 530.075 44.5
Moisture Content, %: 0.3
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
PHYSICAL PROPERTY TESTSGrab Sample
1518126
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
20784
SIEVEANALYSISREPORT
MTPL-0131
J. Williams of Englobe7/Dec/1518/Jan/16
Steve Matthews
2.4m1
NANANA
4144
MHPM Project Managers Inc.1559 Brunswick Street, Suite 501Halifax, Nova ScotiaB3J 2G1
TP02 Grab Sample
Gander WWTP
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Fax: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 10025.4 9419.1 8912.7 799.53 754.76 661.20 51
0.600 460.300 420.150 360.075 30.1
Moisture Content, %: 11.2
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
3630
MHPM Project Managers Inc.1559 Brunswick Street, Suite 501Halifax, Nova ScotiaB3J 2G1
TP03 Grab Sample
Gander WWTP
20784
SIEVEANALYSISREPORT
MTPL-0132
J. Williams of Englobe7/Dec/157/Dec/15
Steve Matthews
3.0m2
NANANA
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
PHYSICAL PROPERTY TESTSGrab Sample
34
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Fax: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 9225.4 9119.1 8812.7 849.53 834.76 741.20 60
0.600 540.300 480.150 400.075 28.0
Moisture Content, %: 0.1
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
4628
MHPM Project Managers Inc.1559 Brunswick Street, Suite 501Halifax, Nova ScotiaB3J 2G1
TP04 Grab Sample
Gander WWTP
20784
SIEVEANALYSISREPORT
MTPL-0133
J. Williams of Englobe7/Dec/1518/Jan/16
Steve Matthews
2.4m1
NANANA
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
PHYSICAL PROPERTY TESTSGrab Sample
26
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Fax: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 9725.4 9019.1 8512.7 809.53 764.76 671.20 52
0.600 470.300 420.150 360.075 31.7
Moisture Content, %: 10.3
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
3532
MHPM Project Managers Inc.1559 Brunswick Street, Suite 501Halifax, Nova ScotiaB3J 2G1
TP05 Grab Sample
Gander WWTP
20784
SIEVEANALYSISREPORT
MTPL-0134
J. Williams of Englobe7/Dec/157/Dec/15
Steve Matthews
2.7m3
NANANA
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
PHYSICAL PROPERTY TESTSGrab Sample
33
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Fax: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 9125.4 8319.1 7912.7 749.53 714.76 641.20 53
0.600 480.300 440.150 400.075 33.7
Moisture Content, %: 0.1
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
3034
MHPM Project Managers Inc.1559 Brunswick Street, Suite 501Halifax, Nova ScotiaB3J 2G1
TP06 Grab Sample
Gander WWTP
20784
SIEVEANALYSISREPORT
MTPL-0135
J. Williams of Englobe7/Dec/1518/Jan/16
Steve Matthews
2.4m1
NANANA
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
PHYSICAL PROPERTY TESTSGrab Sample
3619136
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Fax: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 10025.4 10019.1 9712.7 919.53 884.76 811.20 68
0.600 620.300 570.150 510.075 42.4
Moisture Content, %: 10.1
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
3942
MHPM Project Managers Inc.1559 Brunswick Street, Suite 501Halifax, Nova ScotiaB3J 2G1
TP07 Grab Sample
Gander WWTP
20784
SIEVEANALYSISREPORT
MTPL-0136
J. Williams of Englobe7/Dec/157/Dec/15
Steve Matthews
2.7m4
NANANA
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
PHYSICAL PROPERTY TESTSGrab Sample
19
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Fax: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 10025.4 9719.1 9312.7 879.53 834.76 741.20 59
0.600 530.300 470.150 400.075 32.2
Moisture Content, %: 9.7
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
4132
MHPM Project Managers Inc.1559 Brunswick Street, Suite 501Halifax, Nova ScotiaB3J 2G1
TP10 Grab Sample
Gander WWTP
20784
SIEVEANALYSISREPORT
MTPL-0138
J. Williams of Englobe7/Dec/157/Dec/15
Steve Matthews
3.0m5
NANANA
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
PHYSICAL PROPERTY TESTSGrab Sample
26
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Fax: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 10025.4 9919.1 9612.7 899.53 844.76 731.20 57
0.600 510.300 460.150 410.075 34.3
Moisture Content, %: 0.3
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
PHYSICAL PROPERTY TESTSGrab Sample
27
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
20784
SIEVEANALYSISREPORT
MTPL-0139
J. Williams of Englobe7/Dec/1518/Jan/16
Steve Matthews
3.0m1
NANANA
3934
MHPM Project Managers Inc.1559 Brunswick Street, Suite 501Halifax, Nova ScotiaB3J 2G1
TP11 Grab Sample
Gander WWTP
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Fax: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 10025.4 9419.1 9012.7 839.53 804.76 681.20 51
0.600 450.300 390.150 330.075 26.8
Moisture Content, %: 10.1
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
4227
MHPM Project Managers Inc.1559 Brunswick Street, Suite 501Halifax, Nova ScotiaB3J 2G1
TP12 Grab Sample
Gander WWTP
20784
SIEVEANALYSISREPORT
MTPL-0140
J. Williams of Englobe7/Dec/157/Dec/15
Steve Matthews
2.7m6
NANANA
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
PHYSICAL PROPERTY TESTSGrab Sample
32
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Fax: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 10025.4 9219.1 8912.7 839.53 804.76 711.20 57
0.600 510.300 450.150 400.075 32.5
Moisture Content, %: 12.7
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
3932
MHPM Project Managers Inc.1559 Brunswick Street, Suite 501Halifax, Nova ScotiaB3J 2G1
TP 16 Grab Sample
Gander WWTP
20784
SIEVEANALYSISREPORT
MTPL-0203
J. Williams of Englobe16/Feb/1622/Feb/16
Steve Matthews
3.0m1
NANANA
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
PHYSICAL PROPERTY TESTSGrab Sample
29
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Fax: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 9425.4 9219.1 8712.7 819.53 784.76 701.20 56
0.600 510.300 450.150 400.075 34.3
Moisture Content, %: 10.1
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
3634
MHPM Project Managers Inc.1559 Brunswick Street, Suite 501Halifax, Nova ScotiaB3J 2G1
TP A0 Grab Sample
Gander WWTP
20784
SIEVEANALYSISREPORT
MTPL-0185
J. Williams of Englobe26/Jan/161/Feb/16
Steve Matthews
2.7m1
NANANA
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
PHYSICAL PROPERTY TESTSGrab Sample
3019145
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Fax: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 10025.4 9119.1 9012.7 789.53 734.76 621.20 47
0.600 420.300 370.150 330.075 29.2
Moisture Content, %: 8.7
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
PHYSICAL PROPERTY TESTSGrab Sample
38
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
20784
SIEVEANALYSISREPORT
MTPL-0180
J. Williams of Englobe26/Jan/161/Feb/16
Steve Matthews
3.0m1
NANANA
3329
MHPM Project Managers Inc.1559 Brunswick Street, Suite 501Halifax, Nova ScotiaB3J 2G1
TP A2 Grab Sample
Gander WWTP
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Fax: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 10025.4 9119.1 8812.7 839.53 794.76 711.20 58
0.600 520.300 470.150 420.075 35.9
Moisture Content, %: 12.5
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
PHYSICAL PROPERTY TESTSGrab Sample
29
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
20784
SIEVEANALYSISREPORT
MTPL-0160
J. Williams of Englobe20/Jan/1628/Jan/16
Steve Matthews
10ft1
NANANA
3536
MHPM Project Managers Inc.1559 Brunswick Street, Suite 501Halifax, Nova ScotiaB3J 2G1
TP A3 Grab Sample
Gander WWTP
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Cell: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING76.2 10050.8 9038.1 9025.4 8719.1 8512.7 809.53 774.76 701.20 57
0.600 510.300 460.150 400.075 33.9
Moisture Content, %: 8.8
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
3634
Colliers Project LeadersSuite 306 Terrace on the Square, 8-10 Rowan Street St. John’s, NewfoundlandA1B 2X1
TP A7 Grab Sample
Gander WWTP
709-699-9729 [email protected]
20784
SIEVEANALYSISREPORT
MTPL-0213
J. Williams of Englobe8-Apr-168-Apr-16
Steve Matthews
3.7m27
NANANA
709-237-8700 ext. 203
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
PHYSICAL PROPERTY TESTSGrab Sample
30
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Fax: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 10025.4 8719.1 8312.7 799.53 764.76 691.20 57
0.600 520.300 480.150 440.075 39.3
Moisture Content, %: 9.2
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
PHYSICAL PROPERTY TESTSGrab Sample
31
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
20784
SIEVEANALYSISREPORT
MTPL-0189
J. Williams of Englobe26/Jan/161/Feb/16
Steve Matthews
2.4m1
NANANA
2939
MHPM Project Managers Inc.1559 Brunswick Street, Suite 501Halifax, Nova ScotiaB3J 2G1
TP B1 Grab Sample
Gander WWTP
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Fax: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 7425.4 6519.1 6212.7 589.53 554.76 481.20 36
0.600 320.300 290.150 250.075 21.7
Moisture Content, %: 7.9
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
PHYSICAL PROPERTY TESTSGrab Sample
52
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
20784
SIEVEANALYSISREPORT
MTPL-0202
J. Williams of Englobe16/Feb/1622/Feb/16
Steve Matthews
1.2m1
NANANA
2622
MHPM Project Managers Inc.1559 Brunswick Street, Suite 501Halifax, Nova ScotiaB3J 2G1
TP B3 Grab Sample
Gander WWTP
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Cell: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 10025.4 9019.1 8612.7 809.53 774.76 681.20 55
0.600 500.300 450.150 400.075 34.5
Moisture Content, %: 9.9
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
PHYSICAL PROPERTY TESTSGrab Sample
3118144
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
20784
SIEVEANALYSISREPORT
MTPL-0220
J. Williams of Englobe8-Apr-168-Apr-16
Steve Matthews
2.4m26
NANANA
709-237-8700 ext. 203
3435
Colliers Project LeadersSuite 306 Terrace on the Square, 8-10 Rowan Street St. John’s, NewfoundlandA1B 2X1
TP B6 Grab Sample
Gander WWTP
709-699-9729 [email protected]
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Fax: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 10025.4 10019.1 9912.7 959.53 944.76 831.20 57
0.600 480.300 410.150 350.075 29.0
Moisture Content, %: 12.6
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
5429
MHPM Project Managers Inc.1559 Brunswick Street, Suite 501Halifax, Nova ScotiaB3J 2G1
TP C0 Grab Sample
Gander WWTP
20784
SIEVEANALYSISREPORT
MTPL-0187
J. Williams of Englobe26/Jan/161/Feb/16
Steve Matthews
3.0m1
NANANA
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
PHYSICAL PROPERTY TESTSGrab Sample
17
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Fax: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 9025.4 8519.1 7812.7 729.53 704.76 611.20 49
0.600 440.300 400.150 350.075 30.5
Moisture Content, %: 10.3
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
PHYSICAL PROPERTY TESTSGrab Sample
39
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
20784
SIEVEANALYSISREPORT
MTPL-0186
J. Williams of Englobe26/Jan/161/Feb/16
Steve Matthews
3.0m1
NANANA
3130
MHPM Project Managers Inc.1559 Brunswick Street, Suite 501Halifax, Nova ScotiaB3J 2G1
TP C2 Grab Sample
Gander WWTP
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Fax: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 9525.4 9219.1 8712.7 769.53 714.76 601.20 44
0.600 380.300 340.150 300.075 25.6
Moisture Content, %: 8.1
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
PHYSICAL PROPERTY TESTSGrab Sample
4021156
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
20784
SIEVEANALYSISREPORT
MTPL-0161
J. Williams of Englobe20/Jan/1628/Jan/16
Steve Matthews
1.8m1
NANANA
3426
MHPM Project Managers Inc.1559 Brunswick Street, Suite 501Halifax, Nova ScotiaB3J 2G1
TP C4 Grab Sample
Gander WWTP
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Cell: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING76.2 10050.8 10038.1 9825.4 9119.1 8912.7 839.53 804.76 711.20 57
0.600 510.300 450.150 380.075 31.9
Moisture Content, %: 10.4
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
3932
Colliers Project LeadersSuite 306 Terrace on the Square, 8-10 Rowan Street St. John’s, NewfoundlandA1B 2X1
TP C5 Grab Sample
Gander WWTP
709-699-9729 [email protected]
20784
SIEVEANALYSISREPORT
MTPL-0215
J. Williams of Englobe8-Apr-168-Apr-16
Steve Matthews
3.4m28
NANANA
709-237-8700 ext. 203
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
PHYSICAL PROPERTY TESTSGrab Sample
29
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Fax: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 10025.4 9519.1 9512.7 909.53 884.76 811.20 67
0.600 610.300 550.150 470.075 39.6
Moisture Content, %: 13.3
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
4240
MHPM Project Managers Inc.1559 Brunswick Street, Suite 501Halifax, Nova ScotiaB3J 2G1
TP D1 Grab Sample
Gander WWTP
20784
SIEVEANALYSISREPORT
MTPL-0174
J. Williams of Englobe20/Jan/1628/Jan/16
Steve Matthews
3.0m1
NANANA
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
PHYSICAL PROPERTY TESTSGrab Sample
19
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Fax: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 10025.4 9919.1 9712.7 929.53 884.76 791.20 63
0.600 580.300 530.150 470.075 41.0
Moisture Content, %: 11.9
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
3841
MHPM Project Managers Inc.1559 Brunswick Street, Suite 501Halifax, Nova ScotiaB3J 2G1
TP D3 Grab Sample
Gander WWTP
20784
SIEVEANALYSISREPORT
MTPL-0181
J. Williams of Englobe26/Jan/161/Feb/16
Steve Matthews
2.4m1
NANANA
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
PHYSICAL PROPERTY TESTSGrab Sample
2120137
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Fax: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 8325.4 7819.1 7412.7 709.53 694.76 611.20 51
0.600 460.300 410.150 350.075 29.0
Moisture Content, %: 10.5
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
3229
MHPM Project Managers Inc.1559 Brunswick Street, Suite 501Halifax, Nova ScotiaB3J 2G1
TP E0 Grab Sample
Gander WWTP
20784
SIEVEANALYSISREPORT
MTPL-0188
J. Williams of Englobe26/Jan/161/Feb/16
Steve Matthews
2.4m1
NANANA
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
PHYSICAL PROPERTY TESTSGrab Sample
3919127
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Cell: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING76.2 10050.8 10038.1 9225.4 9219.1 9112.7 879.53 844.76 771.20 65
0.600 600.300 550.150 500.075 43.4
Moisture Content, %: 12.7
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
PHYSICAL PROPERTY TESTSGrab Sample
2319145
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
20784
SIEVEANALYSISREPORT
MTPL-0216
J. Williams of Englobe8-Apr-168-Apr-16
Steve Matthews
2.4m29
NANANA
709-237-8700 ext. 203
3443
Colliers Project LeadersSuite 306 Terrace on the Square, 8-10 Rowan Street St. John’s, NewfoundlandA1B 2X1
TP E7 Grab Sample
Gander WWTP
709-699-9729 [email protected]
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Fax: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 10025.4 9719.1 9512.7 929.53 904.76 821.20 70
0.600 650.300 600.150 540.075 47.9
Moisture Content, %: 13.0
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
3448
MHPM Project Managers Inc.1559 Brunswick Street, Suite 501Halifax, Nova ScotiaB3J 2G1
TP F3 Grab Sample
Gander WWTP
20784
SIEVEANALYSISREPORT
MTPL-0159
J. Williams of Englobe20/Jan/1628/Jan/16
Steve Matthews
1.5m1
NANANA
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
PHYSICAL PROPERTY TESTSGrab Sample
1817125
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Fax: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 9225.4 8719.1 8512.7 809.53 774.76 721.20 59
0.600 550.300 500.150 450.075 39.0
Moisture Content, %: 10.5
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
3339
MHPM Project Managers Inc.1559 Brunswick Street, Suite 501Halifax, Nova ScotiaB3J 2G1
TP F4 Grab Sample
Gander WWTP
20784
SIEVEANALYSISREPORT
MTPL-0167
J. Williams of Englobe20/Jan/1628/Jan/16
Steve Matthews
2.4m1
NANANA
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
PHYSICAL PROPERTY TESTSGrab Sample
28
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
39 Sagona Ave, Mount Pearl, NL, A1N 4P9 - TEL (709)576-8148 FAX (709)576-3713Client: Our Project No:
Client Contract No:Client PO:CC:
Attn:Phone: Fax: E-Mail:
Project:Source: Sampled By:Sample No: Date Received:Lab ID: Date Tested:Location: Soil Description:
Soil Type Liquid Limit Flat & Elongated Particles, %Gravel % Plastic Limit Coarse Specific GravitySand % Plasticity Index Fractured Faces, %Silt and Clay % Coarse Absorption, % Soundness Loss, %Petrographic No. Fine Absorption, % Max. Dry Density, (kg/m³)Abrasion Loss, % Micro-Deval Loss, % Optimum Moisture, %
SIEVE SIZE PERCENT(mm) PASSING50.8 10038.1 9225.4 9219.1 8912.7 859.53 834.76 751.20 55
0.600 470.300 400.150 350.075 29.9
Moisture Content, %: 8.6
Comments:
Record No: Englobe Tech: Per: CCIL Certified Laboratory For Testing Concrete
4530
MHPM Project Managers Inc.1559 Brunswick Street, Suite 501Halifax, Nova ScotiaB3J 2G1
TP F4 Grab Sample
Gander WWTP
20784
SIEVEANALYSISREPORT
MTPL-0165
J. Williams of Englobe20/Jan/1628/Jan/16
Steve Matthews
3.7m1
NANANA
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on request.
J. Hill
PHYSICAL PROPERTY TESTSGrab Sample
25
0
10
20
30
40
50
60
70
80
90
100
0.10.55.0
% P
ASSI
NG
Grain Sizes (mm)
CBCL Limited Appendices
APPENDIX C
Town of Gander Open House / Public Meeting
Home Residents Public Notices +
QUICK LINKS
Calendar of Events
Publications & Forms
Public Notices
Job Opportunities
Complaints | Comments
Business Directory
GIS Map | Getting Here
Cool Stuff
Contact Us
ENVIRONMENT CANADA
Current Public NoticesCurrent Public NoticesCurrent Public NoticesCurrent Public Notices
DISCRETIONARY NOTICE - 131 ROE AVENUE
Notice of Open House / Public Meeting
VARIANCE FROM REGULATIONS - 176 ROE AVENUE
SNOW CLEARING NOTICE
SUMMARY OF CHANGES – GARBAGE AND REFUSE REGULATIONS
BOARDWALK OPEN
WASTE TRANSFER STATION
TREE & PARK BENCH MEMORIAL PROGRAM
GARBAGE REGULATIONS & SCHEDULE
DISCRETIONARY NOTICE - 131 ROE AVENUE
Posted: March 27, 2017
Notice is hereby given that the Town Council of Gander has received an application to operate a taproom,
retail beer sales and on-site brewing company at the above noted property.
It is noted that this area is zoned Commercial General and the use is permitted as a Discretionary Use under
the Town of Gander Development Regulations.
Anyone wishing to make representation on this matter must do so in writing and the representation must be
received by the Engineering Department, Town of Gander, no later than 12:00 noon on Monday, April 3, 2017.
Further information on this matter may be obtained by contacting the Engineering Department at 651-5915.
looking for...
Online Services Home Town Hall Residents Doing Business Explore Gander Moving to Gander
Page 1 of 6Public Notices +
30/03/2017http://www.gandercanada.com/index.php/residents/public-notices
-1°C Wind: NE 16 km/hWind Chill: -6
Today
0°C
Tonight
-1°C
Fri
0°C
Alerts in EffectGander, NL John Boland
Planning & Control Technician
Town of Gander
100 Elizabeth Drive
Gander, NL
A1V 1G7
Notice of Open House / Public Meeting
Posted: March 17, 2017
The Town of Gander invites residents and concerned stakeholders to an Open House / Project Introduction
Meeting for the Proposed New Wastewater Treatment Facility in Gander, Newfoundland, as part of the pre-
submission of an Environmental Assessment Registration to Newfoundland and Labrador Department of
Environment and Climate Change.
Prepared materials will provide a project concept, and project personnel will be available to document /
answer questions and share information.
The event details are as follows:
Nature of Meeting: Information Session for the New Proposed Wastewater Treatment Facility
Date: Tuesday, March 28, 2017
Time: 7:00 p.m. to 9:00 p.m.
Location: Council Chambers, 100 Elizabeth Drive, Gander, NL
Anyone wishing to understand more about this project or provide comments or concerns on this matter may
do so in person during the meeting or provide written comments to the Engineering Department, Town of
Gander, no later than 12:00 p.m., Friday, April 28, 2017.
Further information on this matter may be obtained by contacting the Engineering Department at 709-651-
5915.
James Blackwood
Director of Engineering
Town of Gander
100 Elizabeth Drive
Gander, NL
A1V 1G7
VARIANCE FROM REGULATIONS - 176 ROE AVENUE
Posted: March 14, 2017
Notice is hereby given that the Town Council of Gander has received an application to construct an addition to
the rear of the existing building at the above noted address which will extend to within 4.78 metres of the side
property line.
It is noted that this area is zoned Commercial General (CG) and requires a minimum sideyard of 5.0 meters.
The addition will encroach into this sideyard.
Page 2 of 6Public Notices +
30/03/2017http://www.gandercanada.com/index.php/residents/public-notices
Anyone wishing to make representation on this matter must do so in writing and the representation must be
received by the Engineering Department, Town of Gander, no later than 12:00 noon, Tuesday, March 21,
2017.
Further information on this matter may be obtained by contacting the Engineering Department at 651-5915.
John Boland
Planning & Control Technician
Town of Gander
100 Elizabeth Drive
Gander, NL
A1V 1G7
SNOW CLEARING NOTICE
Posted: November 14, 2016
The Town of Gander advises that winter parking restrictions are in effect from Nov. 1, 2016, up to and
including April 30, 2017.
During this time, no vehicle shall be parked on any street between midnight and 8 a.m., regardless of
weather conditions, nor may any vehicle be
parked such as to impede or interfere with snow clearing operations at any time of the day or night, at any
time of the year.
Citizens are also reminded that it is illegal to throw, sweep, shovel or place snow or ice from any private
property upon any Town street or sidewalk, or such that it obstructs access to fire hydrants.
Snow clearing regulations include Sections 23-26 of Town of Gander Traffic Regulations, which are available
for inspection at Town Hall or in PDF format
on the Town’s official website at www.gandercanada.com, in the ‘Residents’ section under ‘Protection
Services’
The Town thanks residents for their patience and cooperation in keeping our streets and sidewalks clear and
safe throughout the year.
Additional links: http://www.gandercanada.com/index.php/residents/public-works/snow-clearing.
SUMMARY OF CHANGES – GARBAGE AND REFUSE REGULATIONS
Posted: November 10, 2016
Residents are advised that the following changes to the Garbage and Refuse Regulations are now in effect:
• Garbage shall be covered at all times throughout the year to prevent birds accessing garbage.
• There will no longer be a collection of garden waste (leaves & grass) during special clean-up week.
Residents may access the compost facility at 34 McCurdy Drive for the disposal of garden waste at any time.
• C & D material must have nails removed or bent into wood when placed for collection during spring clean-
up.
Page 3 of 6Public Notices +
30/03/2017http://www.gandercanada.com/index.php/residents/public-notices
• Material must be sorted when placed for collection during special clean-up week
BOARDWALK OPEN
Updated: September 16, 2016
The Town of Gander is advising the public that the Cobb's Pond Rotary Park boardwalk has been reopened.
Thank you for your patience while this work was being completed.
Please use caution when using the Boardwalk.
For more information please contact the Recreation Dept at 709-651-5927.
WASTE TRANSFER STATION
Updated: December 22, 2016
The Town of Gander waste transfer station on McCurdy Drive will be accepting refuse on selected
Saturdays only, year-round, from 8 a.m. to 4 p.m.
Residents are encouraged to use this facility for all household debris and surplus items that cannot
otherwise be reused, re-purposed or recycled. Click here for transfer station drop-off fees in PDF
format.
The next dates the waste transfer station will accept materials during 2017 are:
January 7
February 4
March 4
April 1, 15 & 29
May 27
June 10 & 24
July 8 &22
August 12 & 26
September 9 & 23
October 14 & 28
November 4 & 25
December 16
TREE & PARK BENCH MEMORIAL PROGRAM
Updated: August 2016
Page 4 of 6Public Notices +
30/03/2017http://www.gandercanada.com/index.php/residents/public-notices
0 Tweet
The Town of Gander, in conjunction with the Civic Enhancement Committee, has adopted a Memorial Park
Bench and Tree Placement Program for public and business participation.
The program provides the opportunity to purchase a tree and/or bench for many occasions, i.e., in memory of
a loved one, in honour of a dedicated service member, family celebrations, etc. This program is tax deductible.
For more information, please contact the Town of Gander at 651-5927 or email
[email protected] . The program will serve as a remembrance to many people for years to
come.
GARBAGE REGULATIONS & SCHEDULES
Updated: August 2016
The Town of Gander reminds residents that Garbage and Refuse Regulations require that household garbage
be placed at the concrete curb no earlier than 6 a.m. and no later than 8 a.m. on your scheduled collection
day. Household waste must be separated into two streams, with all recyclables placed in transparent blue
bags and non-recyclable waste in transparent clear bags.
Note: All garbage placed for collection shall be covered by metal or plastic container, netting or
blanket from April 1st to November 30th every year.
A limit of six (6) bags per household will be accepted on each scheduled collection day. Empty containers and
any garbage/refuse not collected under these regulations must be removed from the curb before 8:30 p.m. the
same day.
Please heed the following guidelines for safe disposal of hazardous items:
• Needles must be in a container such as steel or heavy plastic that will prevent accidental puncture to those
collecting it.
• Broken glass should be placed in a separate container and marked as such.
• Hot coals/ashes must not be put out for collection.
Complete Garbage and Refuse Regulations, along with the regular collection schedule, may be found by
clicking here, or by calling the Public Works Depot at 709-651-5938.
For questions on proper sorting of household waste, contact Central Newfoundland Waste Management by
telephone at 709-653-2900 or by emailing [email protected] .
61 people like this. Be the first of your friends.Like
Page 5 of 6Public Notices +
30/03/2017http://www.gandercanada.com/index.php/residents/public-notices
Thursday, March 30th 2017 | 9:19:am
Terms of Reference | Getting Here | Contact Us | Links | Site Map © Town of Gander. All rights reserved.
Page 6 of 6Public Notices +
30/03/2017http://www.gandercanada.com/index.php/residents/public-notices
173020.00 MEETING MINUTES (PUBLIC MEETING MARCH 28 2017) /RM ED: 31/03/2017 3:37:00 PM/PD: 05/04/2017 5:14:00 PM
MINUTES TAKEN BY M Rutherford PROJECT NO: 173020.00 DATE 03/28/2017
MINUTES OF Town of Gander ‐ Wastewater Treatment Plant (WWTP) Environmental
Assessment Open House / Public Meeting: 7:00pm ‐ 9:00 pm
PROJECT NAME Gander WWTF SUBJECT #01
ATTENDING James Blackwood, Director of Engineering, Town of Gander
Stephen Mathews, Project Manager, Colliers
Greg Sheppard, Project Manager, CBCL Limited
Melissa Rutherford, Environmental Scientist, CBCL Limited
Also see list of Attendees
ABSENT N/A
COPIES TO Town of Gander
7:00 – Introductions by Town Council (Cyril Abbott, Deputy Mayor)
James Blackwood, Director of Engineering, Town of Gander
Stephen Mathews, Project Manager, Colliers
Greg Sheppard, Project Manager, CBCL Limited
Melissa Rutherford, Environmental Scientist, CBCL Limited
7:02 – Introduction of Project (Greg Sheppard)
CBCL started with the project in 2014.
Project delivery methodology is Design‐Build.
Preliminary engineering was completed in early 2015.
Eight design‐build teams responded to a Request for Quotations (similar to an
Expression of Interest) which was issued in 2015. Four teams were short‐listed and will
be invited to respond to a Request for Proposals. Teams will be evaluated using various
criteria; parameters may include: technology, price, and schedule.
7:05 – Introduction to the Environmental Assessment Process (Melissa Rutherford)
Project is required to be registered as an undertaking under Environmental Protection
Act and the Environmental Assessment Regulations.
The Registration Document will be submitted to Newfoundland and Labrador
Department of Municipal Affairs and Environment (MAE).
The Minister will have 45 days to review and provide comment on the Registration
Document. MAE will post notice of their decision within 10 days of the 45 after
registration.
After submission, MAE will have 7 days to publish the notice and the public will have 35
days to provide comment after the notice is published.
The Registration Document will include the information as required by the
Environmental Assessment Regulations and includes information such as the description
of the project, environmental background, employment , schedule, and funding.
187 Kenmount Road
ICON Building
St. John’s, NL
Canada A1B 3P9
Telephone: 709 364 8623
Fax: 709 364 8627
E-mail: [email protected]
URL: http://www.cbcl.ca
173020.00 MEETING MINUTES (PUBLIC MEETING MARCH 28 2017) /RM ED: 31/03/2017 3:37:00 PM/PD: 05/04/2017 5:14:00 PM
The Registration Document will include information for that important to the
community, for example environmental components and human activities. This forum
allows for us to include specific things that are important to the community that cannot
be completed via desktop reviews.
7:15 – Questions
The floor was open for question: Specific Question were not recorded. Question themes and
summarized responses are presented in Table 1.
8:10 – Meeting closed by Council Table 1 Question Themes and Responses
Theme Topic Response
Environmental Assessment Process
Environmental Assessment Timeline How will the Registration Document be submitted in absence of the final process technology?
The Minister has 45 days to review the registration document and 10 days to post the decision after the 45 days. CBCL has been in discussions with MAE regarding this issue; the Registration Document will be submitted outlining the potential technology processes at a high level.
Project Process Detail How does the Environmental Assessment impact the overall project schedule? How was the location selected? What buffer will be around the proposed WWTP? How far is the project from the development areas? Has the location been selected based on allowing adequate space for future development?
The WWTP will use either land‐based or mechanical processes. The technology will be decided on during the design‐build contractor selection process. Construction activities will not be able to occur until after the undertaking is released from the Environmental Assessment process and other permits have been obtained. Site selection was based on the need to be outside of the Gander Lake watershed, the need to be close to existing treatment plants, and the need to reserve adequate space for future land development. The buffer is 100 metres. The proposed site is located ~ 2 km East of Cooper Blvd. Yes, this was considered in consultation with the town.
173020.00 MEETING MINUTES (PUBLIC MEETING MARCH 28 2017) /RM ED: 31/03/2017 3:37:00 PM/PD: 05/04/2017 5:14:00 PM
Theme Topic Response
How will the location of the trunk sewer be selected?
The trunk sewer alignment will be selected as to minimize effects to potential development areas and current rights‐of‐way.
Environmental Concerns
Have studies been complete to determine how the project will affect Jonathon’s Pond? Will snowmobile trails be impacted; one trail might intersect the trunk sewer and road alignment? There may be an unregistered winter cabin on Whitman’s pond.
Specific studies have not been completed on Jonathon’s Pond. The effluent to be discharged to Whitman’s pond will be improved over the current discharged effluent from the Magee Road WWTP. Access along the access road may be restricted. Snowmobile crossings can be marked along the road alignment. Impacts are not expected. The comment was noted by CBCL; no impacts expected for cabin use if present.