Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 Visit the website: www.danc.org/operations/engineering/clifton-fine-efficiencyconsolidation-study 1
Transcript
Page 2: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Water & Sewer Districts

• Municipal consolidation doesn’t affect special benefit district boundaries, charges, etc.

• Only customers within a water/sewer district pay for and receive service.

• As part of the Efficiency/Consolidation Study we consider water/sewer operations to identify potential opportunities to improve efficiencies, delivery of services, etc.

2

Page 3: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Town Water Districts & Sewer Districts

Town of Fine Water Districts Town of Clifton Water Districts

Star Lake Water District Newton Falls Water District

Wanakena Sewer District

Star Lake Water District (formerly Woodhaven Water District)

Newton Falls Sewer District

3

Note: Wanakena Water is supplied by a private water company and not under the jurisdiction of the town; as such this Study will not impact the operation/delivery of

services for this district.

Page 4: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Town of Fine: Star Lake Water District System Overview

4

System Elements Description

Source Supply (PWS ID# NY4404398)

Star Lake – Surface Water Treatment Plant; Diatomaceous Earth Filtration and Sodium hypochlorite disinfection

Permitted Capacity (WSA 2132)

150,000 gallons per day

Installation Year 1951

Fire Protection? Yes

Meters Commercial customers only

Gallons & Type of Water Storage

200,000 gallons steel painted ground storage tank

Number of EDUs Served 466.9 debt EDUs, 398.2 O&M EDUs (existing); +24 debt EDUs & 19 O&M EDUs with Phase 1 capital project

Number of Fire Hydrants 46

Feet of Mainline Piping 35,000’

Page 5: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Map of Fine Star Lake Water District

5 Not all water infrastructure is shown due to map scale.

Page 6: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Town of Fine: Star Lake Water District Financial Overview

• On 2014 AUD Star Lake Water

– Fund Balance $157,035

• 2015 Star Lake residential customer rates

– Pay $350/year*; billed annually with option to pay full amount or $35/month from January to October

– Pay ad valorem charge of $1.264/$1,000 of assessed value; billed in January with property taxes

6 NOTE: * User cost increased to $250 in 2012.

Page 7: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Town of Fine: Star Lake Water District Revenue

Description 2014 AUD

Real Property Taxes $42,061

Other Payments in Lieu of Taxes $109

Water Sales $129,085

Interest & Earnings $48

TOTAL $171,303

7

Page 8: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Town of Fine: Star Lake Water District Expenses

Description 2014 AUD

Water Administration & Operation - Salaries $55,363 - Equipment & Capital Outlay $169 - Contractual $91,157*

$146,689

Debt - EFC Principle Payment (30 year 0% financing, projected debt retired in 2045)

$0

Employee Benefits (for Water Admin) - State Retirement, Social Security, Medicare

$23,758

Repair Reserve $0

Interfund Transfer for Highway Services (Collection System Issues) $0

TOTAL $170,447

8

NOTE: * Expenditures include $30,839 in engineering costs for PER and MPR which will be reimbursed to the Town from EFC by the project.

Page 9: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Town of Fine: Star Lake Water District Expenses & Revenue Charts

Salaries 32%

Equipment& Capital

Outlay 0%

Contractual 54%

Employee Benefits

14%

Expenses

9

Property Taxes 25% PILOTs

0%

Water Sales 75%

Interest 0%

Revenue

Page 10: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Town of Clifton: Woodhaven WD* System Overview

10

System Elements Description

Source Supply PWS ID# NY4405673

8” groundwater well, 40 GPM well pump

Permitted Capacity WSA 1664, 5673

Unknown

Installation Year 1945

Fire Protection? No

Meters? No customers are metered

Gallons & Type of Water Storage

No elevated storage; 3,000 gallon hydro pneumatic tank

Number of EDUs Served 32.5 debt EDUs & 30 O&M EDUs (existing); +30 debt EDUs & 25 O&M EDUs with Phase 1 project

Number of Fire Hydrants 0

Feet of Mainline Piping 1,800’

* Woodhaven Water District became Star Lake WD in 6/2015 as a result of district formation proceedings related to the impending Capital Improvement Project.

Page 11: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Map of Clifton Woodhaven Water District

11 Not all water infrastructure is shown due to map scale.

Page 12: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Town of Clifton: Newton Falls WD System Overview

12

System Elements Description

Source Supply Oswegatchie River with Surface Water Treatment Plant with Filtration and Sodium Hypochlorite Disinfection

Permitted Capacity 95,000 gallons per day

Installation Year 1997

Fire Protection? Yes

Meters? No customers are metered

Gallons & Type of Water Storage 272,000 gallon painted steel ground water storage tank

Number of EDUs Served 125

Number of Fire Hydrants 16

Feet of Mainline Piping 12,000’

Page 13: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Map of Clifton Newton Falls Water District

13 Not all water infrastructure is shown due to map scale.

Page 14: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Town of Clifton: Newton Falls & Woodhaven WDs Financial Overview

• On 2014 AUD Woodhaven and Newton Falls Water are reported combined – Combined Fund Balance $77,471

• Newton Falls WD has no debt and Woodhaven owes the General Fund $2,500

• 2015 Customer Rates – Woodhaven customers pay $550/year; billed monthly from

January to October – Newton Falls customers pay $519/year; billed monthly

from January to October

• All revenue from customer billings

14

Page 15: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Town of Clifton: Woodhaven WD Expenses

Description 2015 Budget*

Water Administration (billing, accountants receivable and payable) $1,500

Source of Supply (Power & Pumping) - Personal Services $1,365 - Contractual $2,600

$3,965

Purification - Contractual $700

$700

Transmission & Distribution - Contractual $300

$300

Employee Benefits (for Water Admin) - State Retirement, Social Security, Medicare

$625

Repair Reserve $0

Interfund Transfer for Highway Services $3,060

TOTAL $12,650

15 * 2015 Budget used since AUD included combined financials for Newton Falls and Woodhaven WDs.

Page 16: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Town of Clifton: Woodhaven WD Expenses & Revenue Charts

15%

13%

36%

6%

30%

Expenses

Administration

Salaries

Contractual

Employee Benefits

Interfund Transfer to Highway Dept.

16

100%

Revenue

Customer Billings

Page 17: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Town of Clifton: Newton Falls WD Expenses

Description 2015 Budget

Water Administration (billing, accountants receivable and payable) $2,500

Source of Supply (Power & Pumping) - Personal Services $6,365 - Contractual $22,370

$28,735

Purification - Contractual $7,000

$7,000

Transmission & Distribution - Contractual $5,000

$5,000

Employee Benefits (for Water Admin) - State Retirement, Social Security, Medicare

$1,640

Repair Reserve $10,000

Interfund Transfer for Highway Services $10,000

TOTAL $64,875

17

Page 18: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Town of Clifton: Newton Falls WD Expenses & Revenue Charts

4% 10%

53% 3%

15%

15%

Expenses

Administration

Salaries

Contracutal

Employee Benefits

Repair Reserve

Interfund Transfer to Highway Dept.

18

100%

Revenue

Customer Billings

Page 19: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Clifton-Fine Water Improvement Project Phase 1

• Scope: – $7.408M total project cost – Replacement of Star Lake Surface Water Treatment Plant

with groundwater supply – Replacement of Star Lake storage tank. – Decommissioning of Woodhaven system – Mainline piping improvements – Interconnection of 2 systems along RT3 and completion of

loop around Star Lake

• Funding: $2M grant, $5.408M 0% 30 yr. loan • User cost will be $538/EDU • Schedule: Design 2015, Construction 2016-2017

19

Page 20: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Clifton-Fine Water Improvement Project Phase 2

• Newton Falls Interconnect

– ~$3.3M (Costs/Scope still being fine-tuned)

– Decommissioning of Newton Falls treatment plant and storage tank

– Mainline piping improvements

– Interconnection of Star Lake system to Newton Falls

• Funding: TBD

• Schedule: Preliminary Engineering to be completed 7/2015

20

Page 21: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Town of Fine: Wanakena Sewer District System Overview

21

System Elements Description

Type of Wastewater Treatment Plant 2-4,000 gallon septic tanks & 2-6,600 sf. sand filter beds, UV disinfection

Permitted Capacity SPDES #NY0034533

0.050 MGD; excess capacity is available for additional development/connections

Installation Year 1999

Number of EDUs Served 43

Number & Type of Pump Stations 1

Feet of Collection Main 3,694’

Number of Manholes 26

Page 22: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Map of Wanakena Sewer District

22 Not all sewer infrastructure is shown due to map scale.

Page 23: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Town of Fine: Wanakena Sewer Financial Overview

• Fund Balance 12/31/14: $76,581

• Customers are billed

– $770 annually for residential (37 EDUs)

– $1,300 annually for commercial (1 EDU)

– $100 annually for vacant lots in district (5 EDUs)

23

Page 24: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Town of Fine: Wanakena Sewer Budgeted Expenses

Description 2014 AUD

Sewer Administration (billing, accountants receivable and payable) $110

Sanitary Sewers - Salary $5,860 - Contractual $7,468

$13,328

Debt - Principal Payment 2014: $6,300 - Interest Payment 2014: $8,245 - Balance 2015: $186,700 - Expires: 2044

$14,245

Employee Benefits (for Sewer Admin) - State Retirement, Social Security, Medicare

$2,199

Repair Reserve $0

Interfund Transfer for Highway Services $0

TOTAL $29,882

24

Page 25: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Town of Fine: Wanakena SD Expenses & Revenue Charts

0.37%

20%

25% 48%

7%

Expenses

Administration

Salaries

Contracutal

Debt

EmployeeBenefits

25

98.5%

1.5% 0.1%

Revenue

Sewer Rents Interest & Penalties

Interest & Earnings

Page 26: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Town of Fine: Newton Falls Sewer District System Overview

26

System Elements Description

Type of Wastewater Treatment Plant Rotating Biological Contactors (2)

Permitted Capacity SPDES #NY0270211

0.0366 MGD

Installation Year 2014

Number of EDUs Served 125.5

Number & Type of Pump Stations 1 Main Pump Station; 71 grinder pumps

Feet of Collection Main TBD – Will be determined after as-built records are complete Number of Manholes

Page 27: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Map of Newton Falls Sewer District

27 Note: New Sewer Construction drawn using preliminary construction prints.

Not all sewer infrastructure is shown due to map scale.

Page 28: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Town of Clifton: Newton Falls Sewer Financial Overview

• Fund Balance 12/31/14: $6,957

• Since facility went online in 2014, 1st full year of operation will occur in 2015, so 2015 budget is used for financial summary instead of 2014 actuals as reported in AUD

• Customers are billed $577.41 in January on their Town taxes; parcels with homes in the district that aren’t connected are assessed a charge of 0.5 EDUs; vacant parcels at assessed 0.18 EDUs

28

Page 29: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Town of Clifton: Newton Falls Sewer Budgeted Expenses

Description 2015 Budget

Sewer Administration (billing, accountants receivable and payable) $1,700

Sewage Collection System (contractual) $1,000

Sewage Treatment & Disposal Wastewater Treatment Plant - Contractual (lab fees, etc. ) $3,000 - Contractual Operation (DANC) $21,100 - Contractual Electricity $15,778

$39,878

Debt - EFC Principle Payment (30 year 0% financing, projected debt retired in 2045)

$13,320

Employee Benefits (for Sewer Admin) - State Retirement, Social Security, Medicare

$422

Repair Reserve $10,850

Interfund Transfer for Highway Services (Collection System Issues) $3,000

TOTAL $70,170 29

Page 30: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Town of Clifton: Newton Falls SD Expenses & Revenue Charts

3%

2%

37%

5%

28%

24%

1%

Expenses Administration

Sewer Collection(Contractual)

Sewage Treatment-Contr. Operator

Sewage TreatmentExpenses (lab fees,etc.)Sewage TreatmentUtilities

Debt

Employee Benefits

30

100%

Revenue

Taxes

Page 31: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Clifton-Fine Lighting Areas

31

Town Area

Clifton Cranberry Lake

Clifton Newton Falls

Clifton Star Lake/Benson Mines

Fine Fine

Fine Oswegatchie

Fine Star Lake

Fine Wanakena

Town Paid for By 2014 Actual Expense

Fund Balance

Clifton General Fund – Real Property Taxes from all Tax Payers in Town

$27,409 Part of General Fund; not separated

Fine Special Assessment – Real Property Taxes from all Tax Payers in Town

$29,956 $464

Page 32: Towns of Clifton and Fine Consolidation Study · Towns of Clifton and Fine Consolidation Study Water, Sewer & Lighting 7/22/15 ... •Schedule: Design 2015, Construction 2016-2017

Operations

System Operator NYS Operator License Required

Clifton – Newton Falls Water

DANC contract starting in 2015

Grade IIA*

Clifton – Newton Falls Sewer

DANC contract starting in 2014

Grade 1

Clifton – Star Lake Water (formerly Woodhaven)

DANC contract starting in 2014

Grade C

Fine – Star Lake Water Town employees Grade IIA*

Fine – Wanakena Water Private System – not Town owned

Grade C

Fine – Wanakena Sewer Town employee; plans to retire in upcoming 1-2 years; no backup

Grade 1

32 NOTE: * NYSDOH also requires IIA Assistant Operator.