TPC Commissioning ALICE Technical Forum, CERN, 8 th March 2007 L. Musa

Date post: 15-Jan-2016
Category:
Upload: marlee
View: 22 times
Download: 0 times
Share this document with a friend
Description:
TPC Commissioning ALICE Technical Forum, CERN, 8 th March 2007 L. Musa. Outline Pre-commissioning above ground (2006) Preparing for the commissioning in the cavern (2007). TPC pre-commissioning above ground (2006). - PowerPoint PPT Presentation
11
1 08 Mar 2007 L. Musa TPC Commissioning ALICE Technical Forum, CERN, 8 th March 2007 L. Musa Outline Pre-commissioning above ground (2006) • Preparing for the commissioning in the cavern (2007)
Transcript
Page 1: TPC Commissioning ALICE Technical Forum, CERN, 8 th  March 2007 L. Musa

108 Mar 2007 L. Musa

TPC CommissioningALICE Technical Forum, CERN, 8th March 2007

L. Musa

Outline

• Pre-commissioning above ground (2006)

• Preparing for the commissioning in the cavern (2007)

Page 2: TPC Commissioning ALICE Technical Forum, CERN, 8 th  March 2007 L. Musa

208 Mar 2007 L. Musa

A first phase of TPC Commissioning was carried out above ground in the course of 2006

• Jan-Mar installation of SSW and FEE

• April start of gas system

• May HV (100KV) applied to FC

• Jun–Dec test of all sectors (in pairs)

Each sector was operated continuously over a period of 40 hours and verified with

• calibration pulser, • cosmic-muon trigger detector ACORDE • UV laser system for the generation of tracks in the detector

Many TPC and ALICE sub-systems (e.g. cooling, gating grid pulser, temperature sensors, DCS, Trigger, DAQ, HLT and Offline) have been part of this commissioning programme

TPC pre-commissioning above ground (2006)

~300 man shift, 3588 runs, ~24 TB in CASTOR

Page 3: TPC Commissioning ALICE Technical Forum, CERN, 8 th  March 2007 L. Musa

308 Mar 2007 L. Musa

Only two sectors can be instrumented at a time with – Low Voltage Power Supplies– Cooling

Commissioning objectives– Test functionality of all components – gas stability, noise, signal tails, gain homogeneity, space

resolution, etc.

Cosmic tests

Laser testsALICE COSMIC Trigger (ACORDE)

Each pair of sectors continuously operated over 40 hours

TPC pre-commissioning above ground (2006)

Page 4: TPC Commissioning ALICE Technical Forum, CERN, 8 th  March 2007 L. Musa

408 Mar 2007 L. Musa

TPC pre-commissioning (2006); some results – Noise measurements

r.m.s. of the pedestals (sNOISE) is below 1 ADC count

as required in the Technical Design Report

(PASAnoise2 + ADCnoise

2) = 0.70 ADC counts

Page 5: TPC Commissioning ALICE Technical Forum, CERN, 8 th  March 2007 L. Musa

508 Mar 2007 L. Musa

space point resolution as function of z position (cut on inclination angle tan(f) <0.05)

TDR value: 210m / cm

A

A

Q total (total charge in the cluster) as function of z position

relative decrease over the full TPC length: ~7% decrease due to electron capture and threshold effect

TDR value 1% / m per ppm of O2

3 ppm of O2 measured with gas chromatograph

B

B

TPC pre-commissioning (2006); some results – Cosmic tracks

Page 6: TPC Commissioning ALICE Technical Forum, CERN, 8 th  March 2007 L. Musa

608 Mar 2007 L. Musa

DesignDesign MeasuredMeasured

TPC pre-commissioning (2006); some results – Laser tracks

Drift velocity = 2.73 cm/m agreement with drift monitor detector (Goofie)

Page 7: TPC Commissioning ALICE Technical Forum, CERN, 8 th  March 2007 L. Musa

708 Mar 2007 L. Musa

Moving the TPC into the ALICE magnet

Jan ‘07 TPC has been lowered in UX25

After the alignment with respect to the beam line, the TPC has been put in parking position.

Feruary, alignment of SSW with respect to endplate, and test of the connection of FEE to the endplate (calibration pulser)

All 4356 FECs and 216 RCUs are working

All 26136 kapton cables are properly connected to the pad plane

Page 8: TPC Commissioning ALICE Technical Forum, CERN, 8 th  March 2007 L. Musa

808 Mar 2007 L. Musa

Alignment of SSW wrt endplate within mmR

eado

ut C

ham

ber

~7 mm

X

Z

Y

Displacements of SSW wrt endplate should not exceed 3mm

Fro

nt

En

d C

ard

kapton cable

Page 9: TPC Commissioning ALICE Technical Forum, CERN, 8 th  March 2007 L. Musa

908 Mar 2007 L. Musa

Preparing for Commissioning in UX25

Still some hardware components to be finalized and/or constructed. Two examples:

• Trigger Busy Box (being finalized and tested)

• Trigger&DCS Interface Unit for Laser, GG Pulser and

Calibration Pulser (starting design)

Many software components to be finalized and commissioned Some examples:

• Software for the configuration and monitoring of the

FEE

• Interface to the FERO database

• Interface to ECS

• DCS for some of the sub-systems and TPC FSM

(Supervisory Layer)

• Data Quality Monitoring

In 2006 all efforts mostly devoted to pre-commissioning in SXL2

Page 10: TPC Commissioning ALICE Technical Forum, CERN, 8 th  March 2007 L. Musa

1008 Mar 2007 L. Musa

Cables and cooling pipes (before connecting to the TPC all cables and cooling lines will be tested)

cables from crates to backframe (C side): April

test of cables @ backframe (C side): May

Connection of TPC C side June

TPC wil be moved to final position (interaction point) and connected to the gas system in June

(~about 1 month before reaching nominal conditions)

Preparing for Commissioning in UX25

Connection of TPC A side Aug

Page 11: TPC Commissioning ALICE Technical Forum, CERN, 8 th  March 2007 L. Musa

1108 Mar 2007 L. Musa

TPC commissioning - Milestones

Test of FEE & ROC (C-side)

Test of FEE, Trigger, DAQ, DCS and all servicesJuly Test of ROCs July -

Aug Test of FEE & ROC (A-side)

Test of FEE, Trigger, DAQ, DCS and all serviceSep

Turn on FEE July

Turn on FEE Sep

TPC Commissioning with cosmic tracks, laser Sep - Oct and Kr (under study)

ALICE Commissioning Oct -Nov