TQM Study in Royal Commission of Jubail CEM 515
Transcript
Page 1: TQM Study in Royal Commission of Jubail CEM 515. Purpose of the royal commission Is to develop, construct and maintain the infrastructure of Jubail-2:

TQM Study in Royal Commission

of Jubail CEM 515

Page 2: TQM Study in Royal Commission of Jubail CEM 515. Purpose of the royal commission Is to develop, construct and maintain the infrastructure of Jubail-2:

Purpose of the royal commission

Is to develop, construct and maintain the infrastructure of Jubail-2:

Earth Work, Concrete channels & bridges roads Substations 230/34.5 kV & 115/34.5 kV (SEC) Telecom (STC) pipelines: - Seawater cooling (Marafiq) - Water in/out (Marafiq) - Industrial gas Methane/ Ethane (ARAMCO) - Industrial waste (Marafiq)

Page 3: TQM Study in Royal Commission of Jubail CEM 515. Purpose of the royal commission Is to develop, construct and maintain the infrastructure of Jubail-2:

Sea water cooling pipeline

Page 4: TQM Study in Royal Commission of Jubail CEM 515. Purpose of the royal commission Is to develop, construct and maintain the infrastructure of Jubail-2:

Problem statement

Lack of Coordination between Royal Commission and Marafiq for the final acceptance of construction works of Jubail-2 Projects

Page 5: TQM Study in Royal Commission of Jubail CEM 515. Purpose of the royal commission Is to develop, construct and maintain the infrastructure of Jubail-2:

Effects

Delay on close-out date of the project

Excessive submittal review work Punch list items not in the scope of

contract Unfamiliarity with construction

problems Rework of finished work Specifications correspondence

between entities Reject of work already paid/accepted

Page 6: TQM Study in Royal Commission of Jubail CEM 515. Purpose of the royal commission Is to develop, construct and maintain the infrastructure of Jubail-2:

Pareto

Note: Based on feedback from RC staff involved in the project

Pareto Chart

0

5

10

15

20

25

30

35

Delay

Excess ive subm ittals

Unclear scope

Unfam iliar with cons truction

Rework

Specs correspondance

Reject work

Page 7: TQM Study in Royal Commission of Jubail CEM 515. Purpose of the royal commission Is to develop, construct and maintain the infrastructure of Jubail-2:

As-planned

Award

Initial Acceptance

Close-out

Project Timeline

Final

acceptanceA

ppro

val o

f pr

ojec

t

Area of concern

Page 8: TQM Study in Royal Commission of Jubail CEM 515. Purpose of the royal commission Is to develop, construct and maintain the infrastructure of Jubail-2:

As-built

Award

Initial Acceptance

Close-out

Project Timeline Commissioning

Delay

Final

acceptanceA

ppro

val o

f pr

ojec

t

Page 9: TQM Study in Royal Commission of Jubail CEM 515. Purpose of the royal commission Is to develop, construct and maintain the infrastructure of Jubail-2:

RC flow chartStart

Plan the project

Prepare budget

Start design

Marafiq involvement

Start construction

Handle-over to Marafiq IAMarafiq involvement

Close-out

End

YES

NO

Area where problem is noticed

Problem discussion

Page 10: TQM Study in Royal Commission of Jubail CEM 515. Purpose of the royal commission Is to develop, construct and maintain the infrastructure of Jubail-2:

START

Contractor complete Milestone &ready for Initial Acceptance (I/A)

FCS &his group

determine if milestoneis complete and

contractor requestis ok

Contractor send letter request for I/A

If the above is acceptedFCS prepare I/A inspection package

A

RC Acceptance teamwill designate team for inspection

RC Acceptance teamwill issue I/A Deficiency List

for the complete scopeFCS will review items and

issue letter to Contractor to completeall I/A deficiencies

When I/A Deficiency completedto the satisfaction of FCS,

a request for re-inspection of thecompleted items is sent

The RC acceptance team will issuethe Initial Acceptance Exception List

(Exception for remaining deficiencies)

A

FCS will recommendInitial Acceptance Certificate

with the exceptions to RC

Contractor to complete allexception items during the

warranty period

If all I/A exception items aresatisfactory completed and the one

year warranty finish, the FCS/Contract Administrator will

recommend and issueFinal Acceptance Certificate

to RC approval

All performance bond and releaseof financial issues will be done upon

issuance of Final AcceptanceCertificate

INITIAL ACCEPTANCE FLOWCHART

END

Yes

No

RC Acceptance team will contactinvolved future Owner Utility Co.

MARAFIQ

SCECO

POWER& TELECOM

ROADS

Page 11: TQM Study in Royal Commission of Jubail CEM 515. Purpose of the royal commission Is to develop, construct and maintain the infrastructure of Jubail-2:

Process mapping

Marafiq

RC Construction

RC Engineering

RC IA Team

Contractor

Plan

Review

Review

Design

A/E Design

Review

Award

Construct

Supervise Inspect

Inspect

Inspect

Inspect

Review

Accept

Accept

Page 12: TQM Study in Royal Commission of Jubail CEM 515. Purpose of the royal commission Is to develop, construct and maintain the infrastructure of Jubail-2:

Initial acceptance requirements

AS-BUILT O&M Manuals Spare parts Encroachment Permit

Warranty Performance bond – cant be 3rd party beneficiary

Change orders Claims

Page 13: TQM Study in Royal Commission of Jubail CEM 515. Purpose of the royal commission Is to develop, construct and maintain the infrastructure of Jubail-2:

Close-out requirements Technical submittals-who should review

them QC documentation Spare parts O&M Manuals As-built drawings Testing and commissioning-wittiness Final quantities Change orders and claims In-House inspection

Page 14: TQM Study in Royal Commission of Jubail CEM 515. Purpose of the royal commission Is to develop, construct and maintain the infrastructure of Jubail-2:

Force field analysis

• Contractor wants to finish work

• Finance department stress to close-out the project

• Jubail-2 schedule time

• Upper management monthly reviews

• Staff accomplishment records

• Reputation of the Royal commission

• Old procedures JMP-1975

• NO custodian contractual liabilities

• specification correspondence

• Motivation of staff

• Overload on Marafiq

• Mutual scope clarification

• Warranty/Bond expiry

Page 15: TQM Study in Royal Commission of Jubail CEM 515. Purpose of the royal commission Is to develop, construct and maintain the infrastructure of Jubail-2:

Cause and effect diagram

Lack of coordination between RC and Marafiq

Contractor procedure RC procedure Marafiq procedure

Contractor people RC people Marafiq people

No tracking system

New staff

No technology involved

No mutual procedureUn familiar to RC

No Motivation

Overload

Lack of knowledge

Contractual obligation s

When to review submittals

No Mutual procedure

No quality check

No reporting system

New staff

No Motivation

Overload

Lack of knowledge

No Motivation

Lack of knowledge

Not familiar with procedures

Page 16: TQM Study in Royal Commission of Jubail CEM 515. Purpose of the royal commission Is to develop, construct and maintain the infrastructure of Jubail-2:

Solution

Review IA procedure and requirements Involve custodian in analysis design and

all construction phases Recruit more people Assign a contractual obligation to

custodian in order to meet demands Establish Mutual procedure Online mutual courses with Mutual

procedure Motivate people