Track Trigger Meeting 3/23/10
• Chip Schedule:– 2D wafers complete fab~ April 30 – available for single –tier
functional testing– 3D wafers complete fab ~ May 28– Diced parts and full wafers June – Sent to Ziptronix for oxide
bonding of a handle wafer, then back to Tezzaron for exposure of bottom TSVs.
– Sensor wafers available early July• Topography and flatness checked at Ziptronix• Backside protection• Test of topside tungsten deposition and CMP
• Phone conference next week with Ziptronix to discuss plans• Volunteers for chip testing work?
Short Strip TierLong Strip Tier
VICTR Chip
Can be used to estimate areas needed on final chip
Pad Structure
Kapton-based Interposer
• A preliminary project description has been written and sent to one vendor
• The goals include:– Develop a low-mass layup which is
sufficiently planar (<100 microns bow) to allow bump bonding on both sides over the full area.
– Minimum mass, either using low mass materials or by removing unneeded material.
– Contains embedded capacitance.– Provides a flex circuit “tail” for connection
to optical drivers about 5 cm away. – Provides through vias to measure load
capacitance and crosstalk.
Approach Endicott, Compunetics Cyrexx
Interposer Strategy
1. Development of a full-size technology demonstration board which would be used for mounting dummy chips and developing bump-bonding techniques. This board would provide a platform to demonstrate a low-mass interposer with the appropriate interconnectivity.– We probably need to develop a full candidate layout
of either a full or VICTR 2 interposer including bussing for vendors
– Guess at pinout and numbers of bus lines 2. Production of a direct interconnection interposer for
the VIP-1 chip. 3. Production of a direct interconnection interposer for
the VIP-2 chip.4. Final product – full sized fully functional
Proposed On-chip Logic Diagram
Proposal for VICTR II
2nd Submission Plan
Dec 2010 ?
Meetings• Upgrade Week (April 26-30) Presentations
– Simulation– Mass Budget– Module Design– Interposer?– Trigger Architecture– Mechanics and cooling
• US CMS (May 6-8)• Workshop in Elba (May 24-28) – detailed discussions of
CMS upgrade plans in light of revised machine plans.• Address issues and objections:
– Detector mass– Yield and chip size– Functionality
• Increase breadth of the collaboration