Before you begin If a yellow security bar appears at the top of the screen in PowerPoint, click Enable Editing. You need PowerPoint 2010 to view this presentation. If you don’t have PowerPoint 2010, download the PowerPoint Viewer (see the URL in the notes pane).
Transcript
Before you begin If a yellow security bar appears at the top of
the screen in PowerPoint, click Enable Editing. You need PowerPoint
2010 to view this presentation. If you dont have PowerPoint 2010,
download the PowerPoint Viewer (see the URL in the notes
pane).
Microsoft Project 2010 Training Getting started with Project
2010
Course contents Overview: Learn Project basics Lesson: Includes
four instructional movies Suggested practice tasks Test Quick
Reference Card Getting started with Project 2010
Course goals Create a new project quickly and efficiently.
Create a new task and change task from manual to automatic
scheduling. Create relationships, or links, between tasks. Outline
tasks to add structure to your project. Getting started with
Project 2010
Create a new project Point to the bottom of the video to see
the video controls. Drag or point along the progress bar to move
forward or go back. Getting started with Project 2010
Add tasks to your project Point to the bottom of the video to
see the video controls. Drag or point along the progress bar to
move forward or go back. Getting started with Project 2010
Add links between tasks in your project Point to the bottom of
the video to see the video controls. Drag or point along the
progress bar to move forward or go back. Getting started with
Project 2010
Create an outline for tasks in your project Point to the bottom
of the video to see the video controls. Drag or point along the
progress bar to move forward or go back. Getting started with
Project 2010
Suggestions for practice 1. Create a few tasks. 2. Create
relationships by linking tasks. 3. Outline tasks. Online practice
(requires Project 2010) Getting started with Project 2010
Test question 1 If you enter durations for manually scheduled
tasks, start and end dates are automatically created by Project.
(Pick one answer.) 1. True. 2. False. Getting started with Project
2010
Test question 1 If you enter durations for manually scheduled
tasks, start and end dates are automatically created by Project.
Answer: 2. False. Entering durations for manually scheduled tasks
does not automatically create start and finish dates for tasks.
Getting started with Project 2010
Test question 2 Manually scheduled tasks have durations as well
as start dates and finish dates. (Pick one answer.) 1. True. 2.
False. Getting started with Project 2010
Test question 2 Manually scheduled tasks have durations as well
as start dates and finish dates. Answer: 2. False. Manually
scheduled tasks dont require durations or dates. They can exist as
tasks without any scheduling information. Getting started with
Project 2010
Test question 3 Summary tasks always roll up the total duration
lengths of their subtasks. (Pick one answer.) 1. False. 2. True.
Getting started with Project 2010
Test question 3 Summary tasks always roll up the total duration
lengths of their subtasks. Answer: 1. False. Only summary tasks
that are set to automatically scheduled will roll up the total
durations of their subtasks. Getting started with Project 2010
Test question 4 Which of the following duration values are
allowed automatically scheduled tasks? (Pick one answer.) 1. 4. 2.
Four days. 3. Soon. Getting started with Project 2010
Test question 4 Which of the following duration values are
allowed automatically scheduled tasks? Answer: 1. 4. Automatically
scheduled tasks use numeric values. In this case, you can type
either 4d or 4. Getting started with Project 2010
Test question 5 Manually scheduled tasks can have a start date
of Soon. (Pick one answer.) 1. True. 2. False. Getting started with
Project 2010
Test question 5 Manually scheduled tasks can have a start date
of Soon. Answer: 1. True. Manually scheduled tasks can have a date
values of words, dates, or numbers. Getting started with Project
2010
Quick Reference Card For a summary of the tasks covered in this
course, view the Quick Reference Card. Getting started with Project
2010