Date post: | 06-Aug-2015 |
Category: |
Documents |
Upload: | venutatipathi |
View: | 42 times |
Download: | 1 times |
A
PROJECT REPORT
ON
Transmission Management by Determining
ATC between Different Zones
By
Venutathipathi
Under the guidance of
Prof. D. M. Vinod KumarDept. of Electrical Engg.
NIT Warangal,Warangal.
DEPARTMENT OF ELECTRICAL ENGINEERING
NATIONAL INSTITUTE OF TECHNOLOGY
WARANGAL – 506 004
ANDHRA PRADESH
INDIA
2011
i
DEPARTMENT OF ELECTRICAL ENGINEERING
NATIONAL INSTITUTE OF TECHNOLOGY
WARANGAL-506004
Certificate
This is to certify that the mini project entitled “Transmission Management
by Determining ATC between Different Zones” which is submitted by
murali kandakatla in the partial fulfillment of the requirement for the award of
degree of M.Tech in Power Systems at NIT Warangal has been carried out by
him under my supervision and guidance. The matter embodied in this work has
not been submitted for the award of any other degree
Professor & Head Prof. D. M. Vinod Kumar
Dept. of Electrical Engineering, Dept. of Electrical Engineering,
National Institute of Technology, National Institute of Technology,
Warangal. Warangal.
ii
iii
Acknowledgement
Success of any work depends upon the dedication, sincerity and hard work. It also
requires some ingredients such as motivation, guidance, encouragement and time.
Whole hearted effort altogether makes the project useful and meaningful.
I am highly grateful to Prof. D. M. Vinod Kumar, NIT Warangal for his continuous
guidance and inspiration in the successful completion of my work.
Finally, I would like to thank all the members, for their continuous motivation in the
success of my mini project work.
(venu thathipathi)
iv
Abstract
The goal of deregulation in power industry is to enhance competition and to bring new
choices and economical benefits to consumer. The process has necessitated reformulation
of established models of power system operation and control activities. As a consequence
several issues such as system control, security, transmission management, optimal
bidding has came up.
Congestion management is one of the most challenging aspects in a multi buyer / multi-
seller system. For managing congestion, three different methods of accomplishing the
task a) Optimal Power Flow (OPF) model b) price area congestion model and c) US
transaction based Availability Transfer Capability (ATC) model are incorporated. Each
maintains power system security but differ in its impact on the economics of energy
market.
In a competitive power market the task of an Independent System Operator (ISO) is to
ensure full dispatch of the contracted power. However, if it causes the line flows
exceeding their limits, thus treating the system security, the ISO makes decision on the
curtailment of the contracted power.
With the further development of power markets, large amount of electric power wheeling
and frequent transmission transaction emerging, accurately determining ATC and
broadcasting this information in time are very important to prevent and relieve
transmission congestion effectively. In practical power markets, there are large amount of
uncertainties involved in Transmission Reliability Margin (TRM) and Capacity Benefit
Margin (CBM) of ATC. In this work the ATC is calculated and compared using three
different methods, dc distribution factors, ac distribution factor and ac load flow.
The mini project work is intended to demonstrate the aforementioned models on the
IEEE-24 bus (RTS). The simulation studies were conducted with the help of MATLAB
coding.
v
Table of Contents
Acknowledgement..............................................................................................................iv
Abstract................................................................................................................................v
1. Power System Deregulation.......................................................................................1
1.1 Introduction.............................................................................................................1
1.2 Vertically Integrated Electrical Utility (VIEU)......................................................1
1.2.1 Need for regulation...........................................................................................1
1.2.2 Features of VIEU.............................................................................................2
1.2.3 Demerits of VIEU............................................................................................2
1.3 Deregulated electrical power industry....................................................................3
1.3.1 Need for Deregulation......................................................................................5
1.3.2 Benefits of deregulated power system.............................................................5
1.3.3 The Market place mechanisms.........................................................................5
1.3.4 Market models..................................................................................................6
1.3.5 ISO activities in Bilateral Market.....................................................................6
1.3.6 Pool operator activities in Pool market............................................................7
1.3.7 Issues involved in Deregulation.......................................................................7
1.4 Conclusion..............................................................................................................7
2. Transmission Congestion management......................................................................8
2.1 Introduction.............................................................................................................8
2.1.1 Definition of congestion...................................................................................8
2.1.2 Importance of congestion management in deregulated structure.....................9
2.1.3 Effects of congestion........................................................................................9
2.2 Congestion management methods........................................................................11
2.3 Conclusion............................................................................................................11
3. Available Transfer Capability (ATC) Based Congestion Management...................12
3.1 Introduction...........................................................................................................12
3.1.1 How the transfer capability is limited............................................................13
3.1.2 ATC definitions..............................................................................................14
3.1.3 ATC principles...............................................................................................15
3.2 Methods of calculation of ATC............................................................................16
3.3 ATC calculation using PTDF...............................................................................16
3.3.1 Power Transfer Distribution Factor (PTDF)..................................................16
1
3.3.2 Calculation of PTDF using DC power flow model........................................17
3.3.3 Calculation of PTDF using AC power flow model........................................18
3.3.4 Algorithm for ATC Determination using DC PTDF.....................................18
3.3.5 Algorithm for ATC determination using AC PTDF......................................19
3.5 ATC calculation using Continuation Power Flow method...................................22
3.7 Case studies...........................................................................................................23
3.7.1 IEEE Reliability Test System (RTS)..............................................................25
3.8 conclusions………………………………………………………………………..26
3.9 references…………………………………………………………………………...27
Appendix- test systems…………………………………………………………………..28
2
1. Power System Deregulation
1.1 Introduction
Electrical power industry has been dominated by large utilities that have overall
authorities overall activities in generation, transmission and distribution of power refer to
as vertically integrated utilities. During the nineties many electrical utilities and power
network companies world wide have been forced to changed their ways of doing business
from vertically integrated mechanism to open market system. This kind of process is
called as deregulation or restructuring.
Deregulation word refers to un-bundling of electrical utility or restructuring of
electrical utility and allowing private companies to participate. The aim of deregulation is
to introduce an element of competition into electrical energy delivery and thereby allow
market forces to price energy at low rates for the customer and higher efficiency for the
suppliers.
1.2 Vertically Integrated Electrical Utility (VIEU)
VIEU is referred as Regulated Electrical Power Industry.
Regulation means that the Government has set down laws and rules that put limits on and
define how a particular industry or company can operate.
1.2.1 Need for regulation
1. Risk free way to finance the creation of electric industry
2. Recognition and support from local government to utilities
3. Assured return on investments
4. Establishment of local monopoly
In Figure 1-1 shows the basic structure of regulated power system, in which one
controlling authority-the utility-operated the generation, transmission and distribution
systems located in a fixed geographic area.
3
Figure 1-1: Basic structure of VIEU
1.2.2 Features of VIEU
1. Overall authority, overall activities in generation transmission distribution of
power utility lie within its domain of operation.
2. VIEU will be the only electricity provider ion the region and it has obligation to
provide electricity to every one in the region.
3. Information flow is a bilateral one between generation and transmission system
but money flow was unidirectional.
1.2.3 Demerits of VIEU
1. It was often difficult to regulate the cost incurred in generation transmission and
losses occurred in distribution.
2. Losses occurred in distribution is accounted by spreading the cost over all three
components. Hence utilities often charged their customers at an average tariff
depending upon their aggregated cost during the particular period.
3. The prices setting is done by an external regulator agency often involved
considerations other than economics. (Political party interferences or government
policies on new issues etc.)
4. The main objective of VIEU is to minimize the total cost while satisfying all the
associated problems and constraints, but this leads to complex operation issues
because of the big size VIEU. Further VIEU needs centralized planning for long-
4
Competitive
Generation
Market
Multiple sellers
Competitive
Retail market
Multiple Buyers
Transco & Disco
term generation, transmission expansion, midterm planning activities such as
maintenance, production scheduling, fuel scheduling for optimal cost.
In spite of all the above demerits VIEU have performed satisfactorily over the long years
with respect to operation, control and planning. But after 1990 there has been very big
mismatch between the growth of the load and the generation expansion. This has led to
ineffective operation of the system. Hence the concept of deregulation has been mooted.
When the generation, transmission and distribution system control are separated in terms
of management and ownership, the power system is said to be deregulated.
1.3 Deregulated electrical power industry
Deregulation in power industry is a restructuring of the rules and economic incentives
that governments set up to control and drive the electric power industry.
Figure 1-2: Unbundling the system
Figure 1-3: Typical configuration of restructured or deregulated power system
5
Competition Regulated monopoly Competition
Figure 1-4: The competition
ISO
ISO was appointed for the whole system and its main responsibility is to keep the system
in balance. i.e.,
Imports + productions = Exports + Consumption + losses.
Thus ISO must be an independent authority without any involvement in market
competition. But it validates all the transactions before the actual operation takes place
from the point of view of security of the systems, congestion management, real time
operation etc.
Responsibilities of Independent System Operator
1. System security and reliability
2. Power delivery
3. Transmission pricing
4. Service quality assurance
5. Promotion of economic efficiency and equity
6. Fair market
Market trader/Market operator (Retailer)
Market operator is an entity in the de-regulated environment and is responsible for the
operation of market trading of electricity. He receives the bid offers from various market
participants and determines the markets price based on certain criteria in accordance with
the market structure.
1.3.1 Need for Deregulation
1. To provide cheaper electricity.
2. To offer greater choice to the customer in purchasing the economic energy.
3. To give more choice of generation.
6
4. To offer better services w.r.t power quality i.e. Constant voltage, constant freq.
and uninterrupted power supply.
1.3.2 Benefits of deregulated power system
1. Cheaper electricity.
2. Efficient capacity expansion planning at GENCO level, TRANSCO level and
DISCO level.
3. Pricing is cost effective rather than a set tariff.
4. More choice of generation.
5. Better service is possible.
1.3.3 The Market place mechanisms
Table 1-1: Comparison Between different Mechanisms
Type of system No. of buyers Buyers know sellers? All buyers pay same price?
Pool co One Yes Yes
Bilateral exchange Many Yes No
Power exchange Many No Yes
1.3.4 Market models
Two types of market models in deregulated market
1. Pool model
7
Market place
Mechanisms
* only one buyer *Multi seller/Multi buyer *Operates like stock exchange
Bilateral
exchange
Power
exchangePool Co
2. Open access model
Table 1-2: Comparison between market models
Open Access Pool
Bulk of the energy transactions are carried
out as bilateral trades while there may also
exist a day ahead spot market
All energy transactions are carried out
through the pool, which may be organized
through a day ahead trading mechanism.
The ISO is responsible for market
administration, generation scheduling or
dispatch functions.
The pool co operator is responsible for the
market settlements, unit commitment (UC)
and determination of pool price.
Participation in the market by gencos is not
mandatory
Participation by gencos is mandatory
The ISO is responsible for system security
and control, procuring necessary ancillary
services.
The pool co operator is responsible for
system security and control, procuring
necessary ancillary services.
Example: Nordic Markets Example :UK Market
1.3.5 ISO activities in Bilateral Market
24 Hours Ahead
1. ISO is informed of all hour-by-hour transactions that are to take place the next
day. The transaction can either be decided by independent market operator based
on bidding mechanism, or through bilateral contract. ISO is not involved in these
processes.
2. ISO then carries out load flow studies and other simulations based on load
forecast, availability of transmission capacity to check system security level.
In real time
1. Monitors system power flows, frequency and voltage and trades interact with
regional networks.
2. Power imbalances are corrected.
After real-time
1. Settlement of accounts and payments for ancillary service providers like reactive
power supporters.
8
1.3.6 Pool operator activities in Pool market
24 Hours ahead
1. Carry out load forecast to determine aggregate hourly load demand for the next
day.
2. Receive bids from GENCOs. Based on this information, simulate hourly dispatch
and evaluate system price for each hour of next day.
3. Formulate nodal marginal costs and congestion transmission prices.
In real-time
1. Dispatch generation and load.
2. Procure and provide for system services such as reactive power support, frequency
regulation etc.
3. Do OPF calculation in case of probable congestion situation.
After real-time
1. Calculate the settlements, nodal prices of energy and transmission congestion
surcharges.
1.3.7 Issues involved in Deregulation
Network congestion
Optimal bidding for GENCO
Transmission pricing
Ancillary services management
1.4 Conclusion
This chapter gives an overview of the conventional VIEU and the modern deregulated
power system and contrasts them. Different market models of the deregulated power
system and various issues involved with it are discussed.
9
2. Transmission Congestion management
2.1 Introduction
The objective of deregulation in power industry is to enhance competition and
bring new choice and economic benefits to consumers. The process has necessitated
reformulation of established models of power system operation and control activities. As
a consequence several such as system control, security, transmission management and
optimal bidding has come up.
Congestion management [1] is one of the most challenging aspects in a multi-
buyer/multi-seller system. In the vertically integrated utility structure, all the entities such
as generation, transmission and distribution are with in the domain of central energy
management system. Generation is dispatched in order to achieve the system least cost
operation. In such systems, congestion management is usually taken care of by
determining optimal dispatch solution using a model similar to the optimal power flow or
the security constrained economic dispatch problem. This effectively means that a
generation pattern is determined such that the power flow limits on the transmission
system are not exceeded.
This is not so simple in case of deregulated environment. Suppose under
deregulation, every buyer want to purchase cheap hydropower which is available in
northern region of state, buyer we want to lower their cost purchase all the can get even if
they are to far south. If too many sales of such types are made, the transmission system of
a state would overload.
2.1.1 Definition of congestion
Congestion [1] means, “When the producer and consumer of the electrical energy desire
to produce and consume in amounts that would cause the transmission system to operate
at or beyond one or more transfer limit, the system is said to be congested”
Whenever the physical or operational constraints in a transmission network
become active, the system is said to be in a state of congestion. The possible limits that
may be hit in a case of congestion are: line thermal limits, transformer emergency ratings,
bus voltage limits, transient or oscillatory stability limits. These limits constrain the
amount of electric power that can be transmitted between two locations through a
transmission network. Flows should not be allowed to increase to levels where a
10
contingency would cause the network to collapse because of voltage instability etc. in a
deregulated structure, the market/s must be modeled so that the market participants
(buyers and sellers of energy) engage freely in transaction and play as per market forces,
but in a manner that does not threaten the integrity of the power system. Thus irrespective
of the market structure in place, congestion management is has universally become an
important activity of power system operators. Universally the dual objectives of
congestion management have been to minimize the interference of the transmission
network in the market for electrical energy and to simultaneously ensure secure operation
of the power system.
In the deregulated power system, the challenge of congestion management for the
transmission system operator is to create a set of rules that ensure sufficient control over
producers and consumers to maintain an acceptable level of power system security and
reliability in both the short term (real time operation) and the long term (transmission and
generation construction) while maximizing market efficiency.
2.1.2 Importance of congestion management in deregulated structure
Kirchoffs’ law combined with the magnitude and the location of the generation
and loads, the line impedances and network topology determine the flow on each line.
The power system security constraints may therefore necessitate a change in the generator
schedule away from the most efficient dispatch. In the traditional vertically integrated
utility environment, the generation patterns are fairly stable and the transmission network
expansion could be planned along with the construction of new generation facilities.
Congestion is usually in frequent in such scenarios and the flow patterns are quite
predictable too. However, in deregulated structures, with generating companies
(GENCOs) competing in an open transmission access environment, the generation / flow
patterns can change drastically over small time periods with the market forces. In such
situations, it becomes necessary to have a congestion management scheme in place to
ensure that the system stay secure.
2.1.3 Effects of congestion
In multi-seller / multi-buyer the operator faces additional problems with congestion.
Some of these can be enlisted as follows:
11
1. Forces change generating schedules so that some GENCOs raise and others
reduce output until congestion is eliminated. In pool structure, where central
dispatch is done, Pool co operator has to look after this.
2. Operator compensates the parties who were asked to generate more, paying them
for additional power production and giving lost opportunity payments to parties
who were ordered to cut back.
3. Raising transmission prices during congestion, by collecting congestion fees to
compensate affected GENCO in above point.
Example problem [1]
Effect of network congestion is explained by using simple two-zone system
connected by an interface, shown in Fig. 1.
$10/MWh $20/MWh
200MW 0 MW
100 MW
100 MW 100 MW
Figure 2-5: Two Zone system (No Congestion)
$10/MWh $20/MWh
150MW 50 MW
100 MW 100 MW
50 MW
Figure 2-6: Two Zone system (with 50MW Transfer limit)
Let each zone have a 100 MW constant load. Zone A has a 200 MW generator
with an incremental cost of $10/MWh. Zone B has a 200 MW generator with an
incremental cost of $20/MWh. Assume both generators bid their incremental costs. If
there is no transfer limit between zones, all 200 MW of load will be bought from
12
A B
A B
generator A at $10/MWh, at a cost of $2000/h, as shown in Fig. 1(a). If there is a
50MWtransfer limit, then 150MW Will be bought from A at $10/MWh and the remaining
50 MWh must be bought from generator B at $20/MWh, a total cost of $2500/h.
Congestion has created a market inefficiency of 25% of the optimal costs, even without
strategic behavior by the generators. Congestion has also created unlimited market power
for Generator B. B can increase its bid as much as it wants, because the loads must still
buy 50 MW from it. Generator B’s market power would be limited if there was an
additional generator in zone B with a higher incremental cost, or if the loads had nonzero
price elasticity and reduced their energy purchase as prices increased. In the real power
system, cases of both limited and unlimited market power due to congestion can occur.
Unlimited market power is probably not socially tolerable.
2.2 Congestion management methods
Tackling the congestion problem takes different forms in different countries. It
really depends on what type of deregulated model is being employed in a particular
region. Three main forms are identified all over the world to solve the congestion
problem, although details vary widely among specific implementations. Optimal power
flow model is used in United Kingdom, Australia, New Zealand and some parts of United
States of America. The price area congestion control model is used in Norway, Sweden
and Finland and Transaction based model (ATC model) is used in some parts of United
States of America.
Each method has strengths and flaws, and also interrelationships to some extent.
Each maintains power system security but differs in its impact on the economics of
energy market. The following chapters give the details of the above methods.
2.3 Conclusion
This chapter gives the importance of congestion management. The effects of congestion
on the operational and economic aspects of the power system are discussed. Various
methods for handling the congestion problem are addressed.
13
3. Available Transfer Capability (ATC) Based Congestion
Management
3.1 Introduction
Congestion management is a vital issue in the power system operator under
deregulated environment and can be a major hurdle to trade of electricity if not properly
implemented. Congestion management ensures the non-violation of operating limits.
Congestion management has direct effect on bidding strategies since the bids under
congestion differ from the normal condition. So, for managing the congestion on the
transmission network efficient power transaction between different zones is required.
Efficient power transfers are necessary in competitive market for reliable supply.
Thus, in this context, Available Transfer Capability (ATC) indicating how much inter
area power transfer can be increased without compromising system security must be
evaluated. Accurate identification of this capability provides vital information for both
planning and operation of bulk power markets. A system which can accommodate large
inter area transfers, is generally more robust and flexible than a system with limited
capability to transfer inter area power. Thus ATC can be used as a rough indicator of
relative system security. In an inter area system the loss of generation of one area can be
replaced generation from other areas. ATC calculations are useful for evaluating the
ability of inter connected system to secure following generation and transmission outages
and also to determine the amount of lost generation that can be replaced by potential
reserves and limiting constraints in each circumstance. ATC information can help
independent system operator (ISO) to determine the validity of bidding results in an open
access deregulated market when timely ATC information is very important. It can also
help the power market participants to place bids strategically when congestion happens.
There is a very strong economic incentive to improve the accuracy and
effectiveness of transfer capability computations for use by system operators, planners
and power markets. The practical computations of transfer capability are evolving.
Without a fast computation algorithm the central computer of the ISO would not calculate
at a faster speed, as the market would appreciate.
14
3.1.1 How the transfer capability is limited
The ability of interconnected transmission network to reliably transfer electric
power may be limited by the physical and electrical characteristics of the systems
including any or more of the following [2].
Thermal Limits
Thermal limits establish the maximum amount of electrical current that a
transmission line or electrical facility can conduct over a specified time period before it
sustain permanent damage by overheating or before it violates public safety requirements.
Voltage limits
System voltages and change in voltages must be maintained within the range of
acceptable minimum and maximum limits. For example, minimum voltage limits can
establish the maximum amount of electrical power that can be transferred without causing
damage to the electric system or customer facilities. A widespread collapse of system
voltage can result in a blackout of portion or entire interconnected network.
Stability limits
The transmission network must be capable of surviving disturbances through the
transient and dynamic time periods (from milliseconds to several minutes, respectively)
following the disturbance. All generators connected to ac interconnected transmission
systems operate in synchronism with each other at the same frequency (nominal
frequency is 50 Hertz in India). Immediately following a system disturbance, generators
begin to oscillate relative to each other, causing fluctuations in system frequency, line
loadings, and system voltages. For the system to be stable, the oscillations must diminish
as the electric system attains a new, stable operating point. If a new, stable operating point
is not quickly established, the generators will likely lose synchronism with one another,
and all or a portion of the interconnected electric systems may become unstable. The
results of generator instability may damage equipment and cause uncontrolled,
widespread interruption of electric supply to customers.
15
3.1.2 ATC definitions
Available Transfer Capability (ATC) is a measure of the transfer capability remaining
in the physical transmission network for further commercial activity over and above
already committed uses. Mathematically, ATC is defined as the Total Transfer Capability
(TTC) less the Transmission Reliability Margin (TRM), less the sum of existing
transmission commitments (which includes retail customer service) and the Capacity
Benefit Margin (CBM), shown in Figure 3-7
Transmission Reliability Margin (TRM)
Capacity Benefit Margin (CBM)
Available Transfer Capability (ATC)
Total Transfer Capability (TTC) Existing
Transfer Commitments (ETC)
Figure 3-7: Basic Definition of ATC
Total Transfer Capability (TTC) is defined as the amount of electric power that can be
transferred over the interconnected transmission network in a reliable manner while
meeting all of a specific set of defined pre- and post-contingency system conditions.
Transmission Reliability Margin (TRM) is defined as that amount of transmission
transfer capability necessary to ensure that the interconnected transmission network is
secure under a reasonable range of uncertainties in system conditions.
Capacity Benefit Margin (CBM) is defined as that amount of transmission transfer
capability reserved by load serving entities to ensure access to generation from
interconnected systems to meet generation reliability requirements.
16
3.1.3 ATC principles
ATC is a measure of the transfer capability remaining in the physical transmission
network for further commercial activity over and above already committed uses. As a
measure bridging the technical characteristics of how interconnected network perform to
the commercial requirements associated with transmission service requests, ATC must
satisfy certain principles balancing both technical and commercial issues. ATC must
accurately reflect the physical realities of the transmission network. The following
principles identify the requirements of the calculation and application of ATC.
1. ATC calculations must produce commercially viable results. ATC produced by
the calculation must give reasonable and dependable indication of transfer
capabilities available to the electrical power market. The frequency and details of
individual ATC calculation must be consistent with the level of commercial
activity and congestion.
2. ATC calculation must recognize time-variant power flow conditions on the entire
inter connected transmission network. In addition, the effect of simultaneous
transfers and parallel path flows throughout the network must be addressed from a
reliability viewpoint. Regardless of the desire for commercial simplification, the
laws of physics govern how the transmission network will react to customer
demand and generation supply. Electrical demand and supply cannot, in general,
be independently of one another. All system conditions, uses, and limits must be
considered to accurately access the capabilities of transmission network.
3. ATC calculation must recognize the dependency of ATC on the points of electric
power injection, the direction of transfer across the interconnected transmission
network, and the points of power extraction. All entities must provide sufficient
information necessary for calculation of the ATC. Electric power flows resulting
from each power transfer use the entire network and not governed by the
commercial terms of the transfer.
4. Regional or wide area interconnection is necessary to develop and post
information that reasonably reflects the ATCs of the interconnected transmission
network. ATC calculation must use a regional or wide-area approach to capture
the interactions of electrical power flows among individual, sub-regional, and
multiregional systems.
17
5. ATC calculation must confirm to NERC, regional, sub-regional, power pool, and
individual system reliability planning and operating policies, criteria or guides.
Appropriate system contingencies must be considered.
6. The determination of ATC must accommodate reasonable uncertainties in system
conditions and provide operating flexibility to ensure the secure operation of the
interconnected network. A TRM may be necessary to apply this principle.
Additionally transmission capability (defined as CBM) may need to reserve to
meet generation reliability requirements.
3.2 Methods of calculation of ATC
The transfer margin computation can be implemented with a range of power system
models and computation technique. Here, following four ATC calculation methods are
presented [1].
1. ATC calculation using Power Transfer Distribution Factor (PTDF).
2. ATC calculation using Continuation Power Flow (CPF) method under Base case
and contingency case.
3.3 ATC calculation using PTDF
For ATC determination the MW flows must be allocated to each line or group of lines
in proportion to the MWs being transmitted by each transaction. This is accomplished
through the use of the PTDF.
3.3.1 Power Transfer Distribution Factor (PTDF)
From the power flows point of view, a transaction is specific amount of power
that is injected in to the system and at one bus by a generator and removed at another bus
by a load. The coefficient of linear relationship between the amount of transaction and
flow on a line is called the PTDF [1]. PTDF is also called sensitivity because it relates the
amount of one change – transaction amount – to another change – line power flow.
PTDF is the fraction of the amount of transaction from one bus to another that
flows over a transmission line. PTDFij,mn is the fraction of the amount of transaction from
bus m to bus n that flows over a transmission line connecting bus i and j.
PTDF ij, mn = ( Pijnew / Pmn
new ) (3.1)
18
3.3.2 Calculation of PTDF using DC power flow model
The linearity property of dc power flow model can be used to find the transaction amount
that would give rise to a specific power flow, such as interface limits. The following
approximations are made for dc power flow model.
i) Transmission lines have no resistance and therefore no losses.
ii) Voltage magnitudes are constant.
iii) The variation in angles of complex bus voltages is small.
These approximations create a model that is a reasonable approximation of real power
system, which is only slightly nonlinear in normal steady state operation. The model has
advantages for speed of computation and also has some useful properties.
i) Linearity: If the MW in a transaction from one bus to another is doubled, the
flows that are directly attributable to this transaction will also double.
ii) Superposition: The flows on the interfaces can be broken down into a sum of
components each directly attributable to transaction on the system.
With the assumptions listed above, the power flow on a transmission line connecting bus i
to bus j, Pij, is given by
)(10
jiij
ij xP (3.2)
where xi, j line inductive reactance in per unit
θi phase angle at bus i
θj phase angle at bus j
Now, PTDFij, mn is the fraction of a transaction from bus m to bus n that flows over a
transmission line connecting between buses i and j.
ij
jninjmimmnij x
XXXXPTDF
, (3.3)
where
xij - reactance of the transmission line connecting zone i and zone j;
Xim - entry in the ith row and the mth column of the bus reactance
matrix X.
The change in line flow associated with new transaction is then
Pijnew = PTDF ij, mn * Pmn
new (3.4)
where
19
Pmnnew = new transaction in MW.
3.3.3 Calculation of PTDF using AC power flow model
In the previous section we have seen PTDF calculation using DC power flow
model. But this involves many assumptions, which lead to inaccurate results. More
accurate PTDFs can be calculated using AC power flow model. Line power flows are
simply function of voltage and angle at its terminal buses. So PTDF is function of these
voltage and angle sensitivities [3].
Consider a bilateral transaction tp between a seller bus, m and buyer bus, n.
Further consider a line, l carrying a part of the transaction power. Let the line be
connected between a bus-i and a bus-j. For a change in real power transaction between the
above seller and buyer say by tp MW, if the change in transmission line quantity q l is
ql, the AC power transfer distribution factors can be defined as:
(ACPTDF) ql-tp = p
l
t
q
(3.5)
where
q l = change in power flow in line l
tp = change in transaction between bus m and n.
3.3.4 Algorithm for ATC Determination using DC PTDF
1) Evaluate the bus injections Pi at each bus i as the algebraic sum of all
generation into the bus minus the sum of all loads on the bus.
2) Multiply the vector of bus injections Pi by the reactance matrix X of the
network to get the vector of bus phase angles.
3) Find the base case line flows Pij for each line as
)(10
jiij
ij xP
4) Read the source bus (m) and sink bus (n) in which the ATC is to be calculated.
Calculate the DC PTDF for each line connecting between bus i and bus j for a
transaction from zone m to zone n using eq. (3.3)
5) Calculate the maximum allowable transaction amount from source bus (m) to sink
bus (n) for each line as
20
}{min ,Max
lmnl
mn PATC
where
Pijmax = line flow limit
Pij0 = Base case line flow
6) The ATC between zone m to zone n is the minimum of the maximum allowable
transaction over all lines
}{min ,Max
ijmnij
mn PATC
3.3.5 Algorithm for ATC determination using AC PTDF
1) Run a base case NR load flow to find the transmission line flows (P l0) for each
line.
2) Read the sending bus (seller bus) m and the receiving bus (buyer bus) n.
3) Assume some positive real power injection change ∆tp (=0.1) at seller bus-m and
negative injection ∆tp at the buyer bus-n and form mismatch vector ( P).
4) Compute the change in voltage magnitude and its angle ( V and ), and
voltages at each bus.
5) Calculate the new values of transmission line flows (Pl) and then calculate the
change in power flow from base case is ( 0lll PPq ) for each line l.
6) Compute AC PTDF for each line by using eq (3.5)
7) Calculate the maximum allowable transaction amount from zone m to zone n for
each line as
tpql
lllmn PTDF
PPP
0maxmax
,
8) The ATC between zone m to zone n is the minimum of maximum allowable
transaction over all lines
21
3.4 ATC calculation using Continuation Power Flow method
In previous sections we have seen the ATC calculations by using PTDF and
LODF, these methods are taking less computational time. But, in accuracy wise it shows
wrong results because the distribution factors are works on the principle of linearity.
Actually the load flow equations are non linear in nature so, the line flows are not
distributed linearly. In previous case we are taking line limit has taken as an active power
limit. But in reality the line limit is taken as a MVA rating. In case of MW limit the
power flow from bus p to bus q is more or less same as bus q to bus p (the difference is
because of losses), but in case of MVA rating there is a big difference between power
flow from p to q and q to p, it is because of reactive power flow on the line.
ATC calculation using NR load flow continuation power flow method gives the
accurate results. But the computational effort and time requirements are large because of
incorporating limits of reactive power flows, voltage limits as well as voltage collapse
and line flow limits [4].
3.4.1 Algorithm for ATC determination under base case and Contingency
case
1. Run the load flow by using NR load flow method
2. Calculate the base case voltages and base case power flow.
Note: power flow is the maximum (Spq , Sqp)
Spq = MVA flow from bus p to bus q
Sqp = MVA flow from bus q to bus p
3. Read the source bus (seller) m and sink bus (buyer) n.
4. Read the number of line outage; if there is no outage goes to next step else simulate
the outage by general technique (put the infinite impedance to corresponding line).
5. Assume some positive real power injection change ∆tp (=0.1) at seller bus m and
negative injection of same amount at the buyer bus n and then form the mismatch
vector.
6. Repeat the load flow and form the new line flows.
7. Check the line flows with maximum MVA rating of the line, if any line flows are
crossing the limit then go to next step, else go to step 4.
8. The maximum possible increment achieved above base- case load at the sink bus is
the ATC.
22
3.5 Case studies
3.5.1 IEEE Reliability Test System (RTS)
The transmission network [1] consists of 24 bus locations connected by 38 lines
and transformers, as shown in Figure A-0-1. The line data and generator data are
tabulated in appendix table.
Number of buses = 24
Number of lines = 38
The simulation studies are conducted on IEEE RTS and calculate the ATC with the
help of PTDF by using DC and AC load flow method. The effectiveness of those methods
is compared with AC NR-Load Flow continuous power flow method. Those three
methods are compared for ATC between different buses under normal conditions. The
results are shown in . The ATC values are calculated by taking active power flow line
limits (instead of MVA) as a constraint.
Table 3-3: Comparison of various methods
S.NO
TRANSACTION
ATC from DCPTDF
ATC from ACPTDF ATC from NRLF
1 14_8 0.48815 0.6579 0.7
2 22-5 2.845 2.5926 2.7
3 10_6 1.1493 1.0137 0.9
4 19_ 5 2.8656 2.628 2.7
5 20_8 0.49191 0.66471 0.7
6 18_5 2.849 2.5998 2.7
7 21_6 1.2262 1.0894 1
8 22_9 3.5654 3.6301 3.7
9 10_3 2.9949 2.99 3.1
10 23_15 6.1479 6.0066 6
23
Observations
1. The distribution factor methods takes less computational time as compare to
continuous power flow method
2. In distribution factor method for different transactions and outages, first we have
to pre-calculate the sensitivity factors, and then we can directly use those factors
for ATC calculations.
3. DC distribution factor method takes less time as compared to remaining methods,
but it shows wrong results because of approximations.
4. AC distribution factor method results are approximately equal to actual case, and
it case less computation time. But, because of linearity is applied to non linear
load flow equation it can give higher ATC values as compared to actual case.
5. AC NRLF continuous power flow method gives exact results, but computational
time is very high.
6. In real time studies the ATC information is necessary for every hour. So, AC
distribution factor method is well suited for real time studies.
24
4. Conclusions
Each of the ATC based congestion management methods discussed in this thesis has
its strengths and its flaws. ATC method directly gives the maximum possible transaction
amount before accepting any transaction and this information is displayed on OASIS
WebPages and uses the information available there to determine if the transmission
system could accommodate transaction, and to reserve the necessary service. Though, this
method is very effective, dynamic online calculation of ATC is difficult, as every single
transaction will have its effect on each and every component in the system. Hence
accurate ATC calculation needs to have fast and accurate computing algorithms, with less
and less assumptions.
The distribution factor methods takes less computational time as compare to continuous
power flow method. In distribution factor method for different transactions and outages,
first we have to pre-calculate the sensitivity factors, and then we can directly use those
factors for ATC calculations. DC distribution factor method takes less time as compared
to remaining methods, but it shows wrong results because of approximations.
AC distribution factor method results are approximately equal to actual case and it takes
less computation time. But, because of linearity applied to non linear load flow equation it
can give higher ATC values as compared to actual case. AC NRLF continuous power
flow method gives exact results, but computational time is very high.
In real time studies the ATC information is necessary for every hour. So, AC distribution
factor method is well suited for real time studies.
Presently congestion management is a challenging aspect in the deregulated market.
Whatever be the method followed to alleviate the congestion, it is very difficult to ensure
100% security.
25
References
[1] Richard D. Christen, Bruce F. Wollenberg and Ivar Wangensteen, “Transmission
Management in the Deregulated Environment”, Proceedings of the IEEE, Vol.88,
No.2, pp. 170-195, February 2000.
[2] “Available Transfer Capability Definitions and Determination”, NERC Report,
United States.
[3] Ashwani Kumar, S.C.Srivastava and S.N.Singh, Available Transfer Capability
Determination in a Competitive Electricity Market using A.C. Distribution Factors,
pp. 99 to 112
[4] Yan Ou, Chanan Singh, “Assesment of Available Transfer Capability and Margins”,
IEEE Trans. Power Syst., Vol. 17, pp. 463-468, May 2002
[5] G. Hamoud, “Feasibility Assessment of Simultaneous Bilateral Transaction in a
Deregulated Environment”, IEEE Trans. Power Syst., Vol. 15, pp. 22-26, Feb 2000
[6] G. Hamoud, “Assessment of Available Transfer Capability of Transmission Systems”,
IEEE Trans. Power Syst., Vol. 15, pp. 27-32, Feb 2000
[7] G.C. Ejebe, J. Tong, J.G. Waight, J.G. Frame, X. Wang, W.F. Tinney, ”Available
Transfer Capability Calculations”, IEEE Trans. Power syst., Vol. 13, pp. 1521-1527,
Nov 1998
[8] G. Sombuttiwilailert, B. Eua-Arporn, “A Novel Sensitivity Analysis For Total
Transfer Capability Evaluation”, 2001 IEEE pp. 342-347
[9] George J. Anders, ”Probability Concepts in Electric Power Systems”, A Wiley-
Interscience Publication.
[10] IEEE Reliability Test System, A report prepared by the Reliability Test System
task force of the applications of probability methods subcommittee, IEEE
Transactions on Power Apparatus and Systems, Vol. PAS-98, No.6, pp. 2047-2054,
Nov/Dec. 1979.
26
Appendix – Test Systems
4
8
1920
5
6
16
18
9
13
103
72
17
24 1211
2122
1
15 14
23
Area 1 Area 2
Area 3
Figure A-0-1: IEEE 24 BUS SYSTEM.
27
IEEE 24 BUS SYSTEM
Number of buses = 24
Number of line = 38
Slack Bus = 13
Line Data
LineFrom bus
To bus R X Max.powerLine
charging susceptance
Tap rattio
1 1 2 0.0026 0.0139 1.75 0.4611 1
2 1 3 0.0546 0.2112 1.75 0.0572 1
3 1 5 0.0218 0.0845 1.75 0.0229 1
4 2 4 0.0328 0.1267 1.75 0.0343 1
5 2 6 0.0497 0.192 1.75 0.052 1
6 3 9 0.0308 0.119 1.75 0.0322 1
7 3 24 0.0023 0.0839 4 0 1.015
8 4 9 0.0268 0.1037 1.75 0.0281 1
9 5 10 0.0228 0.0883 1.75 0.0239 1
10 6 10 0.0139 0.0605 1.75 2.459 1
11 7 8 0.0159 0.0614 1.75 0.0166 1
12 8 9 0.0427 0.1651 1.75 0.0447 1
13 8 10 0.0427 0.1651 1.75 0.0447 1
14 9 11 0.0023 0.0839 4 0 1.03
15 9 12 0.0023 0.0839 4 0 1.03
16 10 11 0.0023 0.0839 4 0 1.015
17 10 12 0.0023 0.0839 4 0 1.015
18 11 13 0.0061 0.0476 5 0.0999 1
19 11 14 0.0054 0.0418 5 0.0879 1
20 12 13 0.0061 0.0476 5 0.0999 1
21 12 23 0.0124 0.0966 5 0.203 1
22 13 23 0.0111 0.0865 5 0.1818 1
23 14 16 0.005 0.0389 5 0.0818 1
24 15 16 0.0022 0.0173 5 0.0364 1
28
25 15 21 0.0063 0.049 5 0.103 1
26 15 21 0.0063 0.049 5 0.103 1
27 15 24 0.0067 0.0519 5 0.1091 1
28 16 17 0.0033 0.0259 5 0.0545 1
29 16 19 0.0003 0.0231 5 0.0485 1
30 17 18 0.0018 0.0144 5 0.0303 1
31 17 22 0.0135 0.1053 5 0.2212 1
32 18 21 0.0033 0.0259 5 0.0545 1
33 18 21 0.0033 0.0259 5 0.0545 1
34 19 20 0.0051 0.0396 5 0.0833 1
35 19 20 0.0051 0.0396 5 0.0833 1
36 20 23 0.0028 0.0216 5 0.0455 1
37 20 23 0.0028 0.0216 5 0.0455 1
38 21 22 0.0087 0.0678 5 0.1424 1
Bus Data
Bus Type Pgen Pload Pgmax Qgen Qload Vspecified
1 P-V 1.52 1.08 1.92 0 0.22 1.035
2 P-V 1.52 0.97 1.92 0 0.2 1.035
3 P-Q 0 1.8 0 0 0.37 1
4 P-Q 0 0.74 0 0 0.15 1
5 P-Q 0 0.71 0 0 0.14 1
6 P-Q 0 1.36 0 0 0.28 1
7 P-V 1.39273 1.25 3 0 0.25 1.025
8 P-Q 0 1.71 0 0 0.35 1
9 P-Q 0 1.75 0 0 0.36 1
10 P-Q 0 1.95 0 0 0.4 1
11 P-Q 0 0 0 0 0 1
12 P-Q 0 0 0 0 0 1
13 Slack 0 265 5.91 0 54 1.02
14 P-V 0 0.94 0 0 1.39 1
15 P-V 1.55 3.17 2.15 0 0.64 1.014
29
16 P-V 1.55 1 1.55 0 0.2 1.017
17 P-Q 0 0 0 0 0 1
18 P-V 4 3.33 4 0 0.68 1.05
19 P-Q 0 1.81 0 0 0.37 1
20 P-Q 0 1.28 0 0 0.26 1
21 P-V 4 0 4 0 0 1.05
22 P-V 3 0 3 0 0 1.05
23 P-V 6.6 0 6.6 0 0 1.05
24 P-Q 0 0 0 0 0 1
30