+ All Categories
Home > Documents > Transportation Supporting Dulles Airport · County of Fairfax, Virginia Silver Line Phase 2 Garages...

Transportation Supporting Dulles Airport · County of Fairfax, Virginia Silver Line Phase 2 Garages...

Date post: 10-Jul-2020
Category:
Upload: others
View: 3 times
Download: 0 times
Share this document with a friend
20
County of Fairfax, Virginia Department of Transportation Transportation Supporting Dulles Airport Committee for Dulles Economic Development and Transportation Committee July 12, 2018 Tom Biesiadny, Director Fairfax County Department of Transportation
Transcript

County of Fairfax, Virginia

Department of Transportation

Transportation Supporting Dulles Airport

Committee for DullesEconomic Development and Transportation Committee

July 12, 2018

Tom Biesiadny, DirectorFairfax County Department of Transportation

County of Fairfax, Virginia

Department of Transportation 2

Multiple Transportation Improvements• Silver Line Status Report

– Herndon and Innovation Center Garage– Adjacent Roadway Improvements– Pedestrian and Bicycle Connections

• Reston Metrorail Assess Group• Herndon Metrorail Station Access and Mobility Study

– Transit Service Adjustments

• Improvements to Route 28• Reston Area Transportation Projects• Innovation Area Transportation Project• I-66 Express Lanes • I-66 Construction Mitigation• Future I-66 Transit Service

County of Fairfax, Virginia

• Phase 1• Punchlist – Ongoing

• Old Meadow Road Realignment at Route 123 – completion: End of 2018

• Remaining VDOT items being addressed• Work underway at Tysons stations

• Phase 2• Overall Project Status ~ 83% complete• Highlights

• All stations under construction • Mechanical/electrical/plumbing• Stormwater facilities• Pavilions; pedestrian bridges

• Aerial Guideway at Dulles Airport nearly finished• Traction Power Substations in progress• Sections of third rail have been energized• Rail yard at Dulles Airport ~ 84% complete• Herndon and Innovation Center garages under

construction • Budget - $2.778B

• Total Contingency - $551 M (Remaining ~$350 M)

County of Fairfax, Virginia

Silver Line Phase 2 Garages• Herndon Station

– 2,006 parking spaces; Cost: $44.5 M; 87% Complete– Pedestrian and vehicular connections to the existing parking garage– Pedestrian and bicycle amenities, including a bike room – Road widening and improvements on site and on Sunrise Valley Drive– New access road from Sunrise Valley Drive to the existing garage– Existing garage modifications to accommodate the bridge connections

from the new garage, new pedestrian path to Metro elevator, accessible parking spaces, and addition of revenue collection system

– Future Transit Oriented Development (TOD) on the west side

4

County of Fairfax, Virginia

Herndon Station Garage• Bridge erection and precast work completed• Ongoing coordination with MWAA for construction interface on

garage, Metrorail facilities, road improvements, bus and vehicular operations during construction

• Completion in Spring 2019• Upgrades to the existing garage follow

5

County of Fairfax, Virginia

Silver Line Phase 2 GaragesInnovation Center• 2,070 spaces; Cost: $52 M; 62% complete• Pedestrian and bicycle amenities • Real estate exchange and development

agreement with Rocks Engineering• Integration with the overall site with the private development• Shared infrastructure design and construction for the garage, retail,

residential and office development• The overall partnership project includes the design and construction

of roads, stormwater management, plaza, and other amenities for the 15-acre Transit Oriented Development

6

County of Fairfax, Virginia

Innovation Center Station Garage• Precast erection underway• Completion in Spring 2019• Onsite coordination and cooperation continues as MWAA is working on

County parcel and Nugget is neighboring parcels and roads

7

County of Fairfax, Virginia

Adjacent Roadway Improvements• As part of the Silver Line project numerous intersections and

roadways will be improved:– Reston Town Center Station

• Sunrise Valley Drive and Reston Parkway • Sunrise Valley Drive and Edmund Halley Drive • Sunset Hills Road and the future Reston Town Center Station,

– Herndon Station• Sunrise Valley Drive and Fairfax County Parkway, and• Sunrise Valley Drive and the Herndon-Monroe Park-and-Ride Lot/Herndon

Metrorail Station– Innovation Center Station

• Innovation Avenue• Sunrise Valley Drive• Carta Way Extension

Department of Transportation 8

County of Fairfax, Virginia

Pedestrian and Bicycle ConnectionsReston Metrorail Access Group• Recommendation Prepared in 2 Phases• Phase I (Wiehle-Reston East Station) - $20 M allocated

25 Phase I recommendations:– 19 complete– 1 in utility relocation and construction – 1 in design – 1 will be completed with Phase II – 3 under discussion with developers

– Includes W&OD Bridge over Wiehle

Department of Transportation 9

County of Fairfax, Virginia

Pedestrian and Bicycle ConnectionsReston Metrorail Access Group• Phase II (Reston Town Center Station) - $25 M allocated

22 Phase II recommendations, – 1 in utility relocation and construction, – 5 in land acquisition, – 9 in design, and – 7 in project initiation or on hold,

due to adjacent land development activity.

https://www.fairfaxcounty.gov/transportation/projects/silver-line/restonimp

Department of Transportation 10

County of Fairfax, Virginia

Pedestrian and Bicycle ConnectionsHerndon Metrorail Station Access Management Study• Area around Herndon and Innovation Center Metrorail Stations• Multimodal challenges and possibilities around stations identified• Missing links and needed pedestrian and bicycle connections• $21 M allocated• 14 priority projects approved• 6 projects in design• 2 projects being studied• 6 project being initiated

• https://www.fairfaxcounty.gov/transportation/projects/silver-line/herndonimp

Department of Transportation 11

County of Fairfax, Virginia

Transit Service Adjustments• Fairfax Connector service reconfigured as part the Silver Phase 1

implementation.– Tysons Circulator service implemented; RIBS revised– Service reoriented to feed Wiehle-Reston East Station– $4 million in new service (annually) added

• Increased frequencies• Service to new areas• Additional late night and weekend service

• Additional service changes will be implemented with Phase 2– Outreach efforts beginning in Fall 2018– Service concepts to be refined during 2019– Herndon bus garage renovation nearly complete– Anticipate new service and more frequent service to all three new Fairfax County

stations

Department of Transportation 12

County of Fairfax, Virginia

Improvements to Route 28• Northern Virginia Transportation Authority allocated funding to

multiple projects in the Route 28 corridor with HB 2313 revenues• FY 2014 priorities included two construction projects on Route 28

– Widen from 6 to 8 Lanes SB (Dulles Toll Road to Route 50) –completed

– Widen from 6 to 8 Lanes NB (McLearen Road to Dulles Toll Road) – completed

• FY 2015-16 priorities included design funds for widening Route 28 from the Prince William line to New Braddock Road.– Design, environmental and traffic work underway– Additional funding approved on 6/14– Design–build procurement to begin in late 2018

• Other projects in Loudoun and Prince William Cos.

Department of Transportation 13

County of Fairfax, Virginia

Improvements to Route 28• Remaining segment in Fairfax County north of Route 50.

– NVTA did not allocate funding to this project in their FY 2018 to FY 2023 program

– County staff will be submitting the project to the Commonwealth’s SmartScale funding competition on August 1, 2018

Department of Transportation 14

County of Fairfax, Virginia

Reston Transportation Projects• Since February 2014:

– Network analysis/prioritization completed– Board adopted Funding Plan– Board adopted a Comprehensive Plan

realignment of Sunset Hills Road– Route 7 widening (Reston to Tysons) –

design-build contract scheduled to be awarded on July 17

– Soapstone Connector (Sunset Hills to Sunrise Valley Drive)

• Preliminary engineering underway• Environment document nearly

complete• Historical assessment underway

– Board approved $500,000 for Sunrise Valley/Fairfax County Parkway intersection improvements

- W&OD Bridge over Wiehle advancing to land acquisition by end of 2018

Department of Transportation 15

County of Fairfax, Virginia

Innovation Transportation Project• Davis Drive/Rock Hill Road Extension

– New crossing of the Dulles Toll Road from Center for Innovative Technology to Sunrise Valley Drive

– 4 lanes + bike and pedestrian facilities– Estimated cost: $100 M– Fairfax and Loudoun have each

approved $500,000 for preliminary engineering

– VDOT advancing preliminary engineering

– NVTA approved an additional $20 M for this project on June 14

– Fairfax County requesting an additional $30 M through Smart Scale

Department of Transportation 16

County of Fairfax, Virginia

I-66 Express Lanes• VDOT awarded a design-build contract to Express Mobility Partners

– Two express lanes in each direction (Gainesville to Beltway)• Construction Underway• Early Deliverable:

– I-66/Route 28 Interchange– Eliminate four traffic signals on Route 28 north of Route 29– Significantly enhance access to Dulles Airport from the south– Target Date: 2020

• Remainder of the project due to be completed in 2022.

Department of Transportation 17

County of Fairfax, Virginia

I-66 Construction Mitigation• Inside the Beltway and Outside the Beltway• Route 699 (Government Center to Foggy Bottom)

– Implemented in December 2017– Ridership has grown from 130 per day to 305 per day, continues to increase

• NVTC has approved funding for Route 698 (Vienna Metrorail Station to Pentagon)

– Implementation plan and timing being developed

• Outside the Beltway– Fairfax Connector Bus Fare Buy Down began May 5, 2018– All feeder routes to the Vienna Metrorail Station now $1– VDOT offering vanpool and telework incentives; County providing commuter

assistance.

Department of Transportation 18

County of Fairfax, Virginia

Future I-66 Transit Service• A portion of tolls collected will support future transit service in the I-

66 corridor.– Funding for additional transit service during construction– Upfront capital funding for on-going service: $36.5 million– On-going annual operating funding beginning in 2023– Inflationary increases; Funding continuing through 2046

• Both PRTC and Fairfax Connector will be adding service• Fairfax Connector service additions planned:

Department of Transportation 19

Centreville - TysonsCentreville - Wahington DCFairfax Center - Washington DCWestfields - ViennaStringfellow - ViennaStringfellow - Mark Center via Pentagon

County of Fairfax, Virginia

Questions?

Department of Transportation


Recommended