+ All Categories
Home > Documents > TransWest Express and Gateway South WECC Planning Coordination Committee David Smith, National Grid...

TransWest Express and Gateway South WECC Planning Coordination Committee David Smith, National Grid...

Date post: 31-Mar-2015
Category:
Upload: shamar-hibbett
View: 216 times
Download: 0 times
Share this document with a friend
Popular Tags:
15
TransWest Express and Gateway South WECC Planning Coordination Committee David Smith, National Grid October 25-26, 2007 Vancouver, B.C.
Transcript
Page 1: TransWest Express and Gateway South WECC Planning Coordination Committee David Smith, National Grid October 25-26, 2007 Vancouver, B.C.

TransWest Express and Gateway South

WECC Planning Coordination CommitteeDavid Smith, National GridOctober 25-26, 2007Vancouver, B.C.

Page 2: TransWest Express and Gateway South WECC Planning Coordination Committee David Smith, National Grid October 25-26, 2007 Vancouver, B.C.

2

APS National Grid PacifiCorp Wyoming Infrastructure Authority

Overview

Page 3: TransWest Express and Gateway South WECC Planning Coordination Committee David Smith, National Grid October 25-26, 2007 Vancouver, B.C.

3

APS National Grid PacifiCorp Wyoming Infrastructure Authority

Co-Development Agreement

Purpose Take initial development steps Allows time to canvas load serving entities and stakeholders Provides time to define the two projects Provides time to structure more complex, longer term agreements Allows opportunity to develop regulatory plan

Agreement Executed August 2007 $3m budget; costs shared by APS, National Grid, PacifiCorp & WIA Longer term business agreements targeted for 2008

National Grid Lead developer of both projects Cost based billing (as if the partners were a regulated subsidiary) Compensated by partners facilitating an equity position across both projects

Page 4: TransWest Express and Gateway South WECC Planning Coordination Committee David Smith, National Grid October 25-26, 2007 Vancouver, B.C.

4

APS National Grid PacifiCorp Wyoming Infrastructure Authority

What is Co-Development?

Activities undertaken jointly Common project team implementation strategy and deployment Coordinated understanding of the needs of customers Coordinate permitting and stakeholder outreach More efficient regional planning and rating review processes

Each project to maintain a degree of independence

Activities undertaken separately ROW filings - purpose and need case, approvals WECC Rating Process Regulatory filings, approvals

Page 5: TransWest Express and Gateway South WECC Planning Coordination Committee David Smith, National Grid October 25-26, 2007 Vancouver, B.C.

5

APS National Grid PacifiCorp Wyoming Infrastructure Authority

Meeting Regional Needs

Consistent with WGA, RMATS, and CDEAC recommendations for transmission expansion

Improve overall electric reliability for the West Reinforces east side of Western Interconnection Adds import capability into the Desert Southwest Wasatch Front reinforced from North and South AC and DC combination

Provides increased access for 3rd party transmission users

Improves regional resource diversity, reliability and economics Access to renewables (primarily wind) Enhance wholesale market vitality

Page 6: TransWest Express and Gateway South WECC Planning Coordination Committee David Smith, National Grid October 25-26, 2007 Vancouver, B.C.

6

APS National Grid PacifiCorp Wyoming Infrastructure Authority

Benefits of Co-Development

Meet regional needs

Better use of transmission corridors

Opportunities to coordinate permitting

Economies of scale and cost savings in the development and construction activities

Page 7: TransWest Express and Gateway South WECC Planning Coordination Committee David Smith, National Grid October 25-26, 2007 Vancouver, B.C.

7

APS National Grid PacifiCorp Wyoming Infrastructure Authority

APS’ summer resource capacity requirement expected to increase 8000MW by 2025

APS’ annual energy sales expected to increase by 70% by 2025

Other Arizona utilities are growing at comparable rates

Arizona RPS requires 15% of retail energy sales from renewable resources by 2025

TransWest Express is viewed as a viable alternative to local resource development

Transwest Express – Need for the Project

Page 8: TransWest Express and Gateway South WECC Planning Coordination Committee David Smith, National Grid October 25-26, 2007 Vancouver, B.C.

8

APS National Grid PacifiCorp Wyoming Infrastructure Authority

TransWest Express Feasibility Study Summary

LegendHVDC/ShortestRoute

AC Co-LocationRoute(Routes are Illustrative)

Analyzed:5 route options500 & 765 kV AC500 kV DC

Economic analysis supports DC or AC/DC hybrid alternatives

Cost $2.3B – $3.2B

Multiple permitting opportunities identified

Page 9: TransWest Express and Gateway South WECC Planning Coordination Committee David Smith, National Grid October 25-26, 2007 Vancouver, B.C.

9

APS National Grid PacifiCorp Wyoming Infrastructure Authority

TransWest ExpressReference Case

3,000 MW

500kV bi-pole HVDC

2015 in-service date

Route to preserve option of Las Vegas area terminal

LegendTransWest Express

Substation(Routes are Illustrative)

Page 10: TransWest Express and Gateway South WECC Planning Coordination Committee David Smith, National Grid October 25-26, 2007 Vancouver, B.C.

10

APS National Grid PacifiCorp Wyoming Infrastructure Authority

Gateway SouthNeed for the Project

Wasatch Front annual peak load to increase 2500MW by 2022

Southern Utah annual peak load to increase by 500MW by 2022*

PacifiCorp IRP targets 8.5% renewables by 2016

Over 5000MW in point to point Transmission Service Requests

*including Transmission Network Service customers

Third Party Point to Point Requests on PacifiCorp System

Page 11: TransWest Express and Gateway South WECC Planning Coordination Committee David Smith, National Grid October 25-26, 2007 Vancouver, B.C.

11

APS National Grid PacifiCorp Wyoming Infrastructure Authority

Gateway SouthReference Case

Legend

Gateway South

Gateway West

Substation(Routes are Illustrative)

Wyoming - Utah 3,000 MW 2 - 500kV AC 2014 in-service date

Utah - Nevada 800 - 1500 MW 345 kV or 500 kV AC 2014 in-service Date

Page 12: TransWest Express and Gateway South WECC Planning Coordination Committee David Smith, National Grid October 25-26, 2007 Vancouver, B.C.

12

APS National Grid PacifiCorp Wyoming Infrastructure Authority

Size of combined projects dependent on regional and customer needs

Capacity options are under review from 4,500 to 7,500 MW export from WY

DC circuit options include 3rd terminal or termination in southern Nevada

LegendTransWest Express

Gateway South

Gateway West

Substation(Routes are Illustrative)

TransWest Express and Gateway South Potential Design Solutions

Page 13: TransWest Express and Gateway South WECC Planning Coordination Committee David Smith, National Grid October 25-26, 2007 Vancouver, B.C.

13

APS National Grid PacifiCorp Wyoming Infrastructure Authority

TransWest Express and Gateway SouthComplementary Projects

Palo Verde - Devers #2 - 500kV line EOR 9300 Project Palo Verde - North Gila #2 - 500kV line

Gateway West – 2-500kV line Mona – Terminal – 2-500kV line Populus – Terminal – 2-345kV line Path 27 (IPP HVDC Intertie) Upgrade

Page 14: TransWest Express and Gateway South WECC Planning Coordination Committee David Smith, National Grid October 25-26, 2007 Vancouver, B.C.

14

APS National Grid PacifiCorp Wyoming Infrastructure Authority

WECC Review Timeline for Projects

6/1/2007 & 9/21/2007 – 1/31/2008Regional Planning Project Review

12/15/2007 – 7/31/2008Phase 1 Rating Process

7/17/2007 – 7/31/2009Phase 2 Rating Process

Regional Planning Project Review

Stake Holder Meetings Salt Lake City – October 17, 2007 Cheyenne - November 7, 2007 Phoenix - December 5, 2007

Page 15: TransWest Express and Gateway South WECC Planning Coordination Committee David Smith, National Grid October 25-26, 2007 Vancouver, B.C.

15

APS National Grid PacifiCorp Wyoming Infrastructure Authority

Questions…

David Smith, National [email protected]


Recommended