Travel Plans Supplementary Planning Document | XA guide for developers in Swindon
Travel Plans Supplementary Planning DocumentA guide for developers in SwindonFebruary 2020
X | Travel Plans SPD A guide for developers in Swindon
Travel Plans Supplementary Planning Document | 3A guide for developers in Swindon
Contents Page
1 What is a Travel Plan? 4 1.1Benefitsofatravelplan 4
2 The purpose of this guidance 5 2.1 Travel Plan Policy landscape 5
3 Do I need to produce a travel plan? 6 3.1 Guidance Thresholds 6
4 Types of travel plan 8 4.1 Securing the travel plan 8
5 Optionsforproducingthetravelplan 9 5.1OptionOne–SBCimplementthetravelplan 9 5.2OptionTwo–Thedeveloperimplementsthetravelplan 10 5.3IntroducingSTARSBusinessandSTARSCommunity 10 5.4IntroducingSTARSeducationforschools 11
6 Employment travel plans 12 Requirements 12 Evaluationcriteria 18
7 Residentialtravelplans 19 Requirements 21 TravelPlanStatements(20–59dwellings) 23 Evaluationcriteria 24
8 School travel plans 26
9 Contacts and links 27
Appendices
� Exampleofcontributioncosts 28
B SampleS106agreementsandmodelconditions 32
X | Travel Plans SPD A guide for developers in Swindon
1. What is a Travel Plan? Atravelplanisdefinedasalong-termmanagementstrategyforanorganisationorsitethatseekstodeliversustainabletransportobjectivesandisregularlyreviewed.
SwindonBoroughCouncilrequiresdeveloperstoproduceandimplementtravelplanstoaconsistentstandardtohelpmitigatethetransportimpactsoftheirdevelopment.
1.1 Benefitsofatravelplan
A Travel Plan will assist in bringing about a wide range of benefits to the wider community such as:
• Reducingpeaktimecongestion• Reducingharmfultransportemissionsandreducingenergyuse• Improvingaccessibilityandtacklingsocialexclusion• Improvedpublictransport• Reductioninvehiculartripspotentiallyreducingthecostofoff-sitehighwayworks• Creatingadditionalsitecapacitybyreducingtheneedforcarparkingspacesandtheir on-goingmaintenancecosts• Enhancingtheimageofthecompany/organisationinquestioninenvironmentalterms whichsupportsCorporateSocialResponsibility• Promotionofhealthylifestylesthroughmorephysicalactivityanduseofactive travelmodes
TadpoleGardenVillageinSwindonisanewcommunitywhichhassustainabilitybuiltintoitscore.Byitslocationandtherealattentiontodetailinplanningthelayoutandinfrastructureofthesite,sustainabletravelwillbetheobviouschoicefornewresidents.Hardinfrastructureandsupportingsoftmeasuresfurtherencouragetheuptakeofsustainablemodesbyresidents,visitors,pupilsandemployeesofthedevelopment.
CRESTNICHOLSON
Travel Plans Supplementary Planning Document | 5A guide for developers in Swindon
2. PurposeofthisguidanceTravelPlanshaveanimportantroleinreducingtrafficandincreasingaccessibilityforall,whichwillcontributetolocalandregionaltargetsalignedwithnationalpolicy.
SwindonBoroughCouncilisseekingtoensurethatalltravelplansproducedintheBoroughareconsistentintermsofstructure,contentandapproach.Thisguidancehasbeenwrittentoprovideaframeworktoensuretheconsistencyofquality,butaimstoallowflexibilitytoadapttravelplanstositespecificconditions.
Itisacknowledgedthatbestpracticeandrequirementschangeovertime,andthisguidancewillbereviewedeverythreeyears.
2.1 Travel Plan Policy Landscape
Theeffectsoftheunsustainablewaywefrequentlytravelcanbeclearlyseenontheenvironment,ourhealthandonourqualityoflife.Ourtownsarebecomingmoreandmorecongestedwithincreasedlevelsofcartraffic.
TravelplansareanintegralpartoftheGovernment’spoliciesonsustainabletransport.TheprimarynationalplanningpolicyimpetusfortravelplansisthroughChapter9oftheNationalPlanningPolicyFramework(NPPF)(2018):
“All developments that will generate significant amounts of movement should be required to provide a travel plan, and the application should be supported by a transport statement or transport assessment so that the likely impacts of the proposal can be assessed.”
Swindon Borough Local Plan 2026 (adopted March 2015)
TheLocalPlanprovidesadevelopmentstrategytodeliversustainablegrowthinSwindontotheyear2026.Inrelationtothedeliveryofthetravel,thekeyplanningpoliciestorealisetheseobjectivesare:
• PolicyTR1(SustainableTransportNetworks)seekstodeliverahighqualitytransportnetwork throughouttheBorough,whichsupportseconomicgrowth,regenerationandhousinggrowth.
• PolicyTR2(TransportandDevelopment)seekstoensurenewdevelopmentprovides appropriateaccessarrangements,isdesignedtoreducetheneedtotraveland encouragestheuseofsustainabletransport.Inparticular,toassessandmitigatetheimpactof developmentandtopromotesustainabletravelchoices,proposalsarerequired tosubmitatravelplanalongsideatransportassessmentandtransportstatement.This isinaccordancewithDepartmentforTransportguidanceandwhereproposeddevelopmentis likelytohavesignificanttransportandrelatedenvironmentalimpact.
Attimeofwriting,theemergingLocalPlan2036iscurrentlybeingpreparedforadoptionmid-2021.WhilstpoliciesTR1andTR2arelikelytobereplaced,therequirementtopromotesustainabletravelchoiceswillremaininanyfuturerevisions.
TheTravelPlanSupplementaryPlanningDocumentneedstobereadinconjunctionwithallotherSwindonpoliciesandguidance.
X | Travel Plans SPD A guide for developers in Swindon
3. Do I need to produce a travel plan? ATravelPlanwillbenegotiatedforallnewdevelopmentsasdefinedinTable1belowandforotherplanningapplications,suchasextensionsandchangeofuse,thatarelikelytohavenegativeimplicationsforthehighwaynetwork.
These include;
• Developmentscomprisingjobs,shopping,leisureandserviceswhichwouldgenerate significantamountsoftravelin,orwithin100metresof, Air Quality Management Areas.
• All schools and nurseries,andextensionstoschoolslikelytohaveamaterialimpactontrafficmovements.AllstateschoolsareobligedtohaveaSchoolTravelPlan.
• Comprisingorinvolvingamaterialincreaseinexistingcarparkingprovision (tobedeterminedonacasebycasebasis)atemployment,retail,orleisuresites,schools,colleges,hospitalsorhealthcentres.
• Wherethetravelplanwillhelpaddressaparticulartrafficproblemassociatedwithaplanningapplication,whichotherwisewouldbelikelytoberefusedonlocaltrafficgrounds.(Thiscategorymayincludesmallerresidential,commercial,serviceoreducationaldevelopmentsbelowtherelevantthresholds)orwherethereisinadequate transport infrastructureinthearea.
3.1 Guideline thresholds
ThethresholdsinTable1oppositearebasedonthosesetoutinAppendixBoftheDepartmentforTransportGuidanceonTransportAssessmentMarch2007,adaptedtolocalneedinSwindoninrespectofuseclassC3,wherethelowerthresholdissetat60dwellingsforatravelplanand20dwellingsforaTravelPlanStatement.
Travel Plans Supplementary Planning Document | 7A guide for developers in Swindon
Land Use Thresholdatorabovewhicha Travel Plan is required
Threshold at which a Travel Plan Statement is required
A1Retail-Food 800m2 250m2
A1Retail–Nonfood 1500m2 800m2
A2FinancialandProfessional 2500m2 1000m2
A3/A4/A5FoodandDrink 2500/600/500m2 300m2
B1includingOffices 2500m2 1500m2
B2 Industrial 4000m2 2500m2
B8WarehousingandDistribution 5000m2 3000m2
C1 Hotels 100bedrooms 60bedrooms
C2ResidentialInstitutions• Hospitals and nursing homes• Residentialeducation• Hostels
50beds2500m2
2500m2
30beds1500m2
1500m2
C3Residential 60+dwellings 20dwellings
D1Non-residentialinstitutions 1000m2 500m2
D1 Schools
State schools: All are already required to have a School Travel Plan.
Independentschools:Allnewschools and extensions to schoolsthatarelikelytohaveamaterialimpactontrafficmovements.
Nurseriesthatcaterfor60+children daily are required to have a travel plan.
n/a
D1HigherandFurtherEducation 1000m2 n/a
D2AssemblyandLeisure 1500m2 500m2
Mixed-usedevelopments
Whereaplanningapplicationcoversmixedlanduses,asingle or overarching travel planwillberequiredcoveringthe complete development.
n/a
Table1
X | Travel Plans SPD A guide for developers in Swindon
4. TypesoftravelplanATravelPlanwillbenegotiatedforalldevelopmentsasdefinedinTable1onpage7andforplanningapplicationswhicharelikelytohavesignificanttransportimplications.
4.1 Securing the Travel Plan
TravelplanswillbesecuredthroughaSection106obligation,whichrequiresthelegalbindingofaSection106agreement.Section106agreementsaremoreeffectiveinsecuringtravelplansgiventherangeofelementsrequiredwithinthem.
Insomecircumstances,SwindonBoroughCouncilmayuseaplanningconditiontosecurethetravelplanorTravelPlanStatement.YoucanfindourmodelconditionsinAppendixB
INTERIM Travel PlanPreparedwhentheexact scale and splitofusescannotbeidentifiedattheplanningapplicationstage.
FRAMEWORK Travel PlanTheFrameworkisanumbrellaplanusedtodevisesubsequentindividualplansforeachelementofthedevelopment.Itsetsoutbasicprinciplesforthesiteasawhole.
FULL Travel PlanPreparedwheretheproposeduseandaccessibilityneedsareknown.Willbetailoredtotheend occupier(s) – egresidential/school/workplace
Travel Plan STATEMENTForsmallerdevelopments.Cantaketheformofan‘ActionPlan’promotedbythedeveloperoroccupierofthesite
Travel Plans Supplementary Planning Document | 9A guide for developers in Swindon
5. OptionsforproducingthetravelplanDevelopersfindthatimplementingatravelplanoveralengthyperiodcanbeachallenge,andSwindonBoroughCouncilareabletotakeenforcementactionagainstdeveloperswhofailtoimplementtheirtravelplanobligations.
For this reason, Swindon Borough Council offers two options.
5.1 OptionOne-SwindonBoroughCounciltakesresponsibilityformanagingandimplementingthetravelplanonbehalfofthedeveloperinreturnforasetcontribution.
SwindonBoroughCouncilwouldberesponsiblefortheimplementationofthetravelplan,incentives,andtheappointmentofadesignatedtravelplancoordinator.Thetravelplancoordinator(TPC)takesresponsibilityforimplementingthetravelplan,andprovidesacontactpointfortheplan.
Thisoptionrequiresa“perdwelling”(forresidential)or“persquaremetre”(foremployment)contribution.
Thisoptionremovesanyresponsibilityfromthedeveloperfortheimplementationoftheplan(otherthanprovidinghardinfrastructuremeasuressuchaselectriccharginginfrastructure,signage,lighting,walking/cyclingpaths,cycleparkingetc,whicharesecuredseparatelytothetravelplan).
Toensurethetravelplandutiesareundertakeninatimelyfashion,contributionsviaaSection106agreementwillberequestedinlinewiththesuggestedtriggerpointsoutlinedinTable1.1below.Thetriggerpointsaresubjecttothesizeandnatureofthedevelopmentandcanbeagreedwithin thelegalagreement.
Table1.1–SuggestedphasingofSection106contributions
Phaseofdevelopment %ofcontributiondue
Commencementofdevelopment 25%
1stoccupation 20%
50%occupationofsite 40%
Priorto100%occupationofsite 15%
AlthoughitisnotcompulsorytochooseOptionOneandpaythetravelplancontribution,SBCconsiderthisisaeffectiveoptionforallconcerned.ThealternativeisOptionTwo.
10 | Travel Plans Supplementary Planning Document A guide for developers in Swindon
5.2 OptionTwo -Theowner/developerretainsresponsibilityformanagingandimplementingthetravelplan,andalsopaysabond/monitoringfee.Thisbondwouldberepayableonsuccessfulcompletionofthetravelplan,minusthemonitoringfee(deposit).
Underthisoption,thedeveloper/ownerretainsresponsibilityforfundingandimplementingthetravelplan,itsincentivesandmeasures,theappointmentandretentionofatravelplancoordinator,monitoringforaperiodcoveringfullbuildoutandoccupation,andidentifyingremedialmeasures.
Inadditiontofundingthetravelplan,thisoptionalsorequiresabondtobepaidtoSwindonBoroughCouncil,repayableonsuccessfulcompletionofthetravelplan.Atravelplanmonitoringfeeisalsorequired,whichisnon-refundable.SwindonBoroughCouncilwouldretainthebondinordertoimplementremedialmeasuresifthedeveloper/ownerdoesnotmeettheagreedsettargetsand/orcomplywiththeagreement.
Atravelplansubmittedbyadeveloperwouldneedtomeettherequiredspecificationssetoutinthisguidance,detailedatChapter6(Employment)andChapter7(Residential).
Thecostsofeachoption,andtheirjustificationsareoutlinedinmoredetailinAppendixA.
5.3IntroducingSTARSBusinessandSTARSCommunity(formerlyStarsfor)(https://www.modeshiftstars.org)
STARSBusinessandSTARSCommunity(formerlyknownasSTARSfor)isthenationaltravelplanratingschemethathasbeenestablishedtorecogniseexcellenceinsupportingwalking,cyclingandotherformsofsustainabletransport.Itisanonlineplatformwhereresidentialorbusinesstravelplanscanbestored,developed,managedandmonitoredovertime.TheplatformisfreeforallSwindonbasedorganisationsanddeveloperstouse,andissuitableforworkplaces,retail,leisure,residentialsitesandcolleges/universities.Schoolsandnurseriesarecoveredseparately.
STARSBusinessandSTARSCommunityallowsuserstocollectdataandinformationlinkedtoasiteoracollectionofsitesandtoinputintothesystem.ThisprocessismoreefficientthanpaperandPDFtravelplans.Usersofthesystemwillsavetimewhenputtingtogetheratravelplanandtheywillbeabletoaccessandupdatetheirsite’sinformationonlineatanytime.
ThreestepstogettingstartedwithSTARS
123
Visithttps://www.modeshiftstars.org/
SelecttheContact/Registerdropdownfromthetopofthepage
Completetheappropriateformandclicksend
Once registered, the Local Authority will approve your access and you can then work on the travel plan.Afulluserguideisavailableatwww.swindontravelchoices.co.uk/resources
Travel Plans SPD | XA guide for developers in Swindon
Creatingyourtravelplan
Fordeveloperschoosing OptionOneabove,pleasecompletethesitedetailswithintheSiteAuditsectionofthesystem.Thisisallthatisrequired,asSwindonBoroughCouncilwilltakeresponsibilityfortheremainderoftheplananditsimplementation.
FordeveloperschoosingOptionTwoabove,pleasecompletethefulltravelplanwithintheStarssystem,detailedatChapter6(Employment)andChapter7(Residential).Youwillneedtoliaisewiththetravelplanofficertoassignasurveythroughthesystem,andtosettargets.Forconsistency,aminimumsetofactionsarerequiredinthesustainabletravelactionplan.ThesearesetoutinChapter6(Employment)andChapter7(Residential).Planswillnotbeapprovedwithouttheminimumactionsinplace.
Thelifeofatravelplanstartsoncommencementofthedevelopment,andlastsfor5yearspost fulloccupation.
5.4IntroducingSTARSEducationforschools
ModeshiftSTARSEducationisthenationaltravelplanratingschemeforschoolsthathasbeenestablishedtorecogniseexcellenceinsupportingwalking,cyclingandotherformsofsustainabletransport.Itisanonlineplatformwheretravelplanscanbestored,developed,managedandmonitoredovertime.STARSisfreeforallSwindonbasedschools(primaryandsecondary)touse.
STARSallowsuserstocollectdataandinformationlinkedtoaschoolsiteandtoinputintothesystem.ThisprocessismoreefficientthanpaperandPDFtravelplans.Usersofthesystemwillsavetimewhenputtingtogetheratravelplanandtheywillbeabletoaccesstheirsitesinformationonlineatanytime.Schoolscanalsoaimforbronze,silverandgoldaccreditation.
MoredetailonproducingschooltravelplansisgiveninChapter8.
12 | Travel Plans Supplementary Planning Document A guide for developers in Swindon
6. Employment travel plans Table2belowrelatestoheadingsrequiredforanemployertravelplanproducedinStarsBusiness.FrameworkandInterimtravelplanscanbeinputtedintothesystem,butthefulltravelplanoftheendoccupierwillalsoberequiredasthemainevidenceofimplementation.
UnderOptionOne,SwindonBoroughCouncilwillfollowthisstructure,andunderOptionTwo,thedeveloperwillberesponsibleforensuringthatallheadingsarecompletedandupdatedforthedurationofthetravelplanobligation.
Table2–SectionandRequirements
1.Aboutthesite
Basicsarerequiredabouttheemploymentsite,suchas• Sitename,address,introductiontotheorganisation• Detailsofoccupationandbuildout• Maincontacts,includingseniormanagement• DetailsofTravelPlanCoordinator(Ifnotyetappointed,the
authorsofthetravelplanwillbeheldaccountableastheTravelPlanCoordinatoruntilthisfieldisupdated).ATPCneedstobeappointedpriortofirstoccupationandemployedforaminimumof5years,oruntilcompletionoftheplan,whicheverislater.
• Aimsandobjectivesoftravelplan
2.WorkingGroup
• Addworkinggroupcontactsinthissection,onceknown.(Thismayincludedeveloper,othersectionsoftheorganisation(egHR/Facilities),publictransportoperator,neighbouringbusinesscontacts,andresidentgroup.)
3. Site Audit
Site AuditThissectiondealswiththeoperationalsideofthedevelopment,suchas• Locationdetails,siteplans,layouts• Detailsofstaff,visitorsanddeliveries,suchasnumbers,working
patterns,openinghours,sicknesslevels(onceknown)• Travelandtransportinfrastructure(egcyclestands,storage,facilities,
busroutesandstops,accessarrangements)• ArrangementsforcartravelandparkingThesiteauditshouldbereviewedandresubmittedannually.
Travel Plans Supplementary Planning Documen | 13A guide for developers in Swindon
4. Travel Surveys
• SwindonBoroughCouncil’stravelplanofficerwillassignastafftravelsurveythroughthesystem–thiscanbecompletedelectronicallyoronpaper(andinputtedintothesystem),oramixtureofboth.
• Priortodevelopment,baselinedatacanbeascertainedusingcensusdatafortherelevantward(availablefromtheOfficeforNationalStatistics),ordatafromasimilarorganisation,orthesameorganisationinadifferenttown.ThisdatacanbeuploadedasPDForimagefilefromthe“AdditionalSurveys”tab.Triprates–ifyouhavethem-canbestoredheretoo.
• WerequireabaselinestaffsurveytobeundertakenonStarsBusinesswithin3monthsoffirstoccupation,andannuallythereafterforthelifeofthetravelplan.
• AutomaticTrafficCountsmayalsobeappropriateoverthesametimescales.
• Aresponserateof30%andhigherisacceptablefortravelsurveys.
Targets
• Fromthebaselinesurvey,werequireatargettobesettoreducesingleoccupancyvehicletriprates.Asaguidewesuggestatargetof8-10percentagepointreductionoverthelifeofthetravelplan,tobeagreedwithSBC.Thesetargetscanbenegotiable,dependingonthenatureandlocationofthedevelopment.Withthedecreaseofcarrates,anincreaseinactivetravel,publictransportuseandreducingtheneedtotravel(i.e.byworkingfromhome/videoconferencing)shouldbeevidenced.
5. Travel and transport issues
• Thissectionistorecordissuesassociatedwiththedevelopmentsiteas they develop
6.SustainableTravelActionPlan
Thisisakeysectiontoadd,createandreportonactionsthatsupport,encourageandpromotesustainabletravelatyoursite.Seetable3below.DeveloperschoosingOptionTwowillneedtoincludetheminimumrequirementofeachsectionfortheirplanstobeapproved.
Forlargerormorecomplexsites,wewillbelookingforrecommendedrequirementstobemet,whereappropriate.Thelistbelowisnotexhaustiveandadditionalmeasuresarewelcomed.
14 | Travel Plans Supplementary Planning Document A guide for developers in Swindon
Table3belowoutlinesitemsforaSustainableTravelActionplan.FordeveloperschoosingOptionTwo,wewillrequirecommitmenttotheminimalrequirementstobemetinordertoapproveyourplan.
TheminimalrequirementsmatchthelevelofprovisiongivenbySBCfordeveloperschoosingOptionOne.
Table3–SustainableTravelActionPlan
CarTravelDisincentives
Minimal Requirementforall sites
• Providedirectionstothesite(onlineandembedintomarketingmaterials)thatpromoteactivetravel,publictransportandcarsharing over solo car travel.
• Regularmonitoringofcarparkcapacityandtakestepstoaddressanyissuesaroundexcessdemandforspaces.
Recommended Requirement
• Considerationofhowparkingwillbemanaged.Thismayincludepermits,barriers,carshareareas,charging.
• Developbusinessmileagepolicythatencourageslocaljourneystobeundertakenbysustainabletravel.
• Enforcementactionforunauthorisedparking• Incentivesforcommutingbysustainablemeans
Promotionofwalking
Minimal Requirementforall sites
• Provisionofwalkingmaps/magazines/websitesforusersofthesite• Provisionofpersonalisedroutemapsforcommutingtoworkonfoot
aspartofaPersonalisedtravelplanningoffer• Providepoolumbrellasatreceptiontoaidtripsonfoot• Holdannualpedometerchallengesforstaff• Holdpromotionaleventsforusersofthesiteaspartof“Walkto
Workweek”
Travel Plans Supplementary Planning Document | 15A guide for developers in Swindon
Promotionofcycling
Minimal Requirementforall sites
• Provisionofcyclingmaps/magazines/informationforusersofthesite• Cyclemapsprovidedwithinnewstarterwelcomepackandonthe
company intranet.• Borrowabikescheme–Freeuseofabicycleforupto4weeksto“try
cycling”.Employeestakinguptheoffershouldbehelpedtopurchaseabikeafterwardsthrough(forexample)abikediscountvoucher,cy-cletoworkschemeandinformationaboutlocalbikeshops.
• PromoteActiveSwindonChallengetostaffandencourageaworkteam,ordepartmentalteamsforlargerorganisations.
• Regular(atleast2annually)eventsforusersofthesite-suchasbikebreakfastsanddoctorbikesessions,securitybikemarking,ledbikeride,cycleskillstraining
Recommended Requirement
• Cyclingcluband/orBikeUserGroupsetupforstaff• Poolbikescheme• CCTVinstalledinthebikesheds• Lockersandshowersavailable• Cycletoworkschemeforstaff
Publictransportactions
Minimal Requirementforall sites
• Activedisseminationofpublictransportinformation.Informationonpublictransportoptionsshouldbeactivelydisseminatedinnewstarterwelcomepacksandontheemployer’swebsite.
• Currentbustimetablesshouldbemadeavailableonnoticeboards,onlineandatreception
• Employeesofferedaweek’spasstotrythebusforfree.• Eventtopromote“CatchtheBusweek”eachyear
Recommended Requirement
• Mechanismtoprovidebusseasontickets/loansforstaff• Realtimebusinformationintheoffice• Promotebus/railtravelforbusinessjourneys
16 | Travel Plans SPD A guide for developers in Swindon
MonitoringActions
Minimal Requirementforall sites
• Baselinestafftravelsurveywithin3monthsoffirstoccupation,followedbyannualstafftravelsurveyforatleast5yearssubsequently.
• Reviewactionsannuallyandupdateaccordingtosurveyresults• Physical trip counts annually across all modes at the development
entry and exit points• Annualreporttomonitorprogresstowardstargets,andreporton
activityoverthepast12months.Submittodeveloper(OptionOne)orSBC(OptionTwo)
Recommended Requirement
• Countsofbikesonbikestands• Increasebikestandsifdemandexceedscapacity
SmarterDrivingActions(inccarsharing)
Minimal Requirementforall sites
• Promotionofacar-sharematchingserviceThereisalreadyarecognisedcarsharematchingserviceinSwindonthatmaybepromoted(www.carshareswindon.com)
• Corporatemembershipofthecarclub,ifapplicable• Annualevent(egcoffeemorning)forstafftomeeteachotherwitha
viewtosettingupcarsharearrangements.
Recommended Requirement
• Promote eco driving• Installationofelectricchargingpoints• Providepoolcarsforstaff(orcorporatemembershipofthecarclubif
applicable)• Offerdrivertrainingtoimprovesafetyandskills
Travel Plans Supplementary Planning Document | 17A guide for developers in Swindon
Promotion,CommunicationsandEventsActions
Minimal Requirementforall sites
• Sustainabletransportinformationonthecompanywebsiteandin-tranet
• Welcomepacksfornewstarterstocontain:-Detailsofonlinejourneyplanning-Localbespoketravelmap-SwindonCycleMap-LocalGetWalkingmagazine-SwindonCyclingmagazine-Adviceleaflets(range)-DetailsoftheActiveSwindonChallenge-Carshareinformation-DetailsofSwindonCyclecampaign-Detailsofdevelopmentwebsite/journeyplanner-CarClubinformation/membershipvoucher(ifrelevant)-Bustimetables,detailsofticketingoptions,smartcarddetailsandvoucherforaweek’spass
• Companytravelpolicies/benefits• Promotionalevents• TheTravelPlanCoordinatorshouldconducttwopromotionalevents
eachyear,itisoftenappropriatetousenational’eventssuchasbiketoworkday,catchthebusweekorliftshareweek.
Recommended Requirement
• CommitmentforthetravelplanCoordinatortoundertakefreetravelplantraining,courtesyofwww.travelplans365.com
• TravelplanCoordinatortojoinSWIFT–thefreetravelplannetworkforSwindonbusinesses.
Failsafe Mechanisms
For developers choosing Option Two, mechanisms need to be in place to ensure that best endeavors are made to meet the travel plan targets. Funds from the bond will need to be retained to allow Swindon Borough Council to implement additional measures if the targets set are not met.
Examples of remedial measures could include – but is not limited to:
• Intensified Personalised Travel Planning with staff • Additional promotional events • Creation of walking groups for commuters • Cycle training for individuals or teams• Use of video to promote infrastructure, or highlight routes, incentives and interventions• Traffic Regulation Orders (TROs)• Implementation of “real time” information boards
18 |Travel Plans Supplementary Planning DocumentA guide for developers in Swindon
EvaluationCriteria
For developers choosing Option Two, we will evaluate the initial travel plan using the following criteria:
1. Toapprovethetravelplan,allsectionsinStarsBusiness (outlinedinTable2above)needtobecompletedandkeptuptodate.
2. Werequirea named Travel Plan co-ordinator. WheretheTPChasyettobeappointed,an interimnamedcontact(suchastheauthorofthetravelplan)willneedtoberetainedandheldresponsiblefortheplanuntiltheTPCisappointedB
3. Baseline survey data isrequiredtosettargetsfrom
4. Targetsneedtobeset. WehavesuggestedaminimumasaguideinTable2,buttheseare negotiabledependingonbaselinedataandlevelofinfrastructureinstalled.
5. Acommitmentto annual monitoring isrequiredforaperiodofthelifeofthetravelplan;thiscanbeincludedasanactionintheSustainableTravelActionPlan.
6. AlltheminimumrequirementsintheSustainableTravelActionPlan(outlinedinTable3above)needtobeincludedwitharealistictargetdateforcompletion.
7. Forlargerormorecomplexsites,recommendedrequirementsfromTable3willneedtobeincluded.
Travel Plans Supplementary Planning Document | 19A guide for developers in Swindon
7. ResidentialtravelplansTable4belowrelatestoheadingsrequiredforaresidentialtravelplanproducedinStarsCommunity.
UnderOptionOne,SwindonBoroughCouncilwillfollowthisstructure,andunderOptionTwo,thedeveloperwillberesponsibleforensuringthatallheadingsarecompletedandupdatedforthedurationofthetravelplanobligation.
Table4
1.Aboutthesite
Basicsarerequiredabouttheemploymentsite,suchas• Sitename,address• Detailsofoccupationandbuildout• Maincontacts,includingseniormanagement• DetailsofTravelPlanCoordinator(Ifnotyetappointed,theauthors
ofthetravelplanwillbeheldaccountableastheTravelPlanCoordinatoruntilthisfieldisupdated).ATPCneedstobeappointedpriortofirstoccupationandemployedforaminimumof5years,oruntilcompletionoftheplan,whicheverislater.
• Aimsandobjectivesoftravelplan
2. Working Group• Addworkinggroupcontactsinthissectiononceknown.(Thismay
includedeveloper,publictransportoperator,neighbouringbusinesscontacts,andresidentgroup.)
3. Site Audit
Thissectiondealswiththeoperationalsideofthedevelopment,suchas• Locationdetails,siteplans,layouts• Travelandtransportinfrastructure(egcyclestands,storage,facilities,
busroutesandstops,accessarrangements)• Arrangementsforcartravelandparking
Werequirethesiteaudittobereviewedandresubmittedannually.
Continuedoverleaf
20 | Travel Plans Supplementary Planning DocumentA guide for developers in Swindon
4. Travel Surveys
• Thetravelplanofficerwillassignaresidenttravelsurveythroughthesystem–thiscanbecompletedelectronicallyoronpaper(andinputtedintothesystem),oramixtureofboth.
• Priortodevelopment,baselinedatacanbeascertainedusingcensusdatafortheward,ordatafromasimilardevelopment.ThisdatacanbeuploadedasPDForimagefilefromthe“AdditionalSurveys”tab.Tripratescanbestoredheretoo.
• Werequireabaselineresidentsurveytobeundertakenupon30thOccupation,or1yearfrom1stoccupation,whicheverissooner, thenannuallythereafterforthelifeofthetravelplan
• AutomaticTrafficCountsmayalsobeappropriateoverthesametimescales.
• Aresponserateof30%andhigherisacceptableforresidenttravelsurveys,whichneedtobecompletedwithin6weeksofsurveylaunch date.
Targets
• Fromthebaselinesurvey,werequireatargettobesettoreducesingleoccupancyvehicletriprates.Asaguidewesuggestatargetof8-10percentagepointreductionoverthelifeofthetravelplan,tobeagreedwithSBC.Thesetargetscanbenegotiable,dependingonthenatureandlocationofthedevelopment.Withthedecreaseofcarrates,anincreaseinactivetravel,publictransportuseandreducingtheneedtotravel(i.e.byworkingfromhome/videoconferencing)shouldbeevidenced.
5. Travel and transport issues • Thissectionistorecordissuesatthedevelopmentsiteastheydevelop
6.SustainableTravelActionPlan
• Thisisakeysectiontoadd,createandreportonactionsthatsupportsustainabletravelatyoursite.Seetable3below.DeveloperschoosingOptionTwowillneedtoincludetheminimumrequirementofeachsectionfortheirplanstobeapproved.
• Forlargerormorecomplexsites,wewillbelookingforrecommendedrequirementstobemet,whereappropriate.Thelistbelowisnotexhaustiveandadditionalmeasuresarewelcomed.
Travel Plans Supplementary Planning Document | 21A guide for developers in Swindon
Table5–SectionandRequirements
CarTravelDisincentives
Minimal Requirement
• Providedirectionstothesite(onlineandembedintomarketingmaterials)thatpromoteactivetravel,publictransportandcarsharing over solo car travel.
• Regularmonitoringofonstreetparkingandtakestepstoaddressanyissuesaroundproblemparking.
Promotionofwalking
Minimal Requirement
• Provisionofwalkingmaps/magazinesforresidents• Provisionofpersonalisedroutemapsforregularjourneysonfootas
partofaPersonalisedtravelplanningoffer• Holdannualpedometerchallengesforresidents(aspartofActive
SwindonChallenge)• Holdpromotionaleventsaspartof“WalktoWorkweek”
Promotionofcycling
Minimal Requirement
• Provisionofcyclingmaps/magazines/informationforusersofthesite• Cyclemapsprovidedwithinresidenthouseholdwelcomepack.• Borrowabikescheme–Freeuseofabicycleforupto4weeksto“try
cycling”.Employeestakinguptheoffershouldbehelpedtopurchaseabikeafterwardsthrough(forexample)abikediscountvoucher,cy-cletoworkschemeandinformationaboutlocalbikeshops.
• PromoteActiveSwindonChallengetoresidentsandencourageacommunity team.
• Regular(atleast2annually)eventsforusersofthesite-suchasbikebreakfastsanddoctorbikesessions,securitybikemarking,ledbikeride,cycleskillstraining
Recommended Requirement
• Cyclingcluband/orBikeUserGroupsetupforresidents
Publictransportactions
Minimal Requirement
• Activedisseminationofpublictransportinformation.Informationonpublictransportoptions,includingrail,shouldbeactivelydisseminatedinhouseholderwelcomepacksandonthedevelopmentwebsite.
• Residentsofferedaweek’spasstotrythebusforfree• Eventtopromote“CatchtheBusweek”eachyear
Recommended Requirement
• Realtimebusinformationatthedevelopment’sbusstops
MonitoringActions
Minimal Requirement
• Baselineresidenttravelsurveywithin3monthsoffirstoccupation,followedbyannualtravelsurveysforthelifeofthetravelplan
• Reviewactionsannuallyandupdateaccordingtosurveyresults• Physical trip counts annually across all modes at the development
entry and exit points• Annualreporttomonitorprogresstowardstargets,andreporton
activityoverthepast12months.Submittodeveloper(OptionOne)orSBC(OptionTwo)
Recommended Requirement
• Countsofbikesonbikestandsincommunityspaces(ifapplicable)• Increasebikestandsifdemandexceedscapacity
SmarterDrivingActions(inccarsharing)
Minimal Requirement
• Promotionofacar-sharematchingserviceThereisalreadyarecognisedcarsharematchingserviceinSwindonthatmaybepromoted(www.carshareswindon.com)
• Freemembershiptothecarclub(whereprovided)• Annualevent(egcoffeemorning)forresidentstomeeteachother
withaviewtosettingupcarsharearrangements.
Recommended Requirement
• Promote eco driving• Installationofelectricchargingpoints• Provideonecarclubvehicleandspaceforevery500dwellings
22 | Travel Plans Supplementary Planning Document A guide for developers in Swindon
Travel Plans Supplementary Planning Document | 23A guide for developers in Swindon
Promotion,CommunicationsandEventsActions
Minimal Requirement
• Sustainabletransportinformationforresidentsonthedevelopmentwebsite
• Sustainabletransportinformationforresidentsonthedevelopmentwebsite
•Householderwelcomepackstocontain:-Detailsofonlinejourneyplanning-Localbespoketravelmap-SwindonCycleMap-LocalGetWalkingmagazine-Adviceleaflets(range)-DetailsoftheActiveSwindonChallenge-Carshareinformation-DetailsofSwindonCyclecampaign-DetailsofBorrowaBikescheme-CarClubinformation/membershipvoucher(ifrelevant)-Bustimetables,detailsofticketingoptions,smartcarddetailsandvoucherforaweek’spass.
• Promotionalevents• TheTravelPlanCoordinatorshouldconducttwopromotionalevents
eachyear,itisoftenappropriatetousenational’eventssuchasbiketoworkday,catchthebusweekorliftshareweek.
Recommended Requirement
• CommitmentforthetravelplanCoordinatortoundertakefreetravelplantraining,courtesyofwww.travelplans365.com
Failsafe Mechanisms
FordeveloperschoosingOptionTwo,mechanismsneedtobeinplacetoensurethatbestendeavorsaremadetomeetthetravelplantargets.FundsfromthebondwillneedtoberetainedtoallowSwindonBoroughCounciltoimplementadditionalmeasuresifthetargetssetarenotmet.
Examples of remedial measures could include – but is not limited to:
• IntensifiedPersonalisedTravelPlanningwithresidents
• Additionalpromotionalevents
• Cycletrainingforindividualsorfamilies
• Useofvideotopromoteinfrastructure,orhighlightroutes, incentivesandinterventions
• TrafficRegulationOrders(TROs)
24 | Travel Plans Supplementary Planning DocumentA guide for developers in Swindon
EvaluationCriteria
For developers choosing Option Two, we will evaluate the initial travel plan using the following criteria:
1. Toapprovethetravelplan,allsectionsinStarsCommunity (outlinedinTable4above)needto becompletedandkeptuptodate.
2. Werequirea named Travel Plan co-ordinator. WheretheTPChasyettobeappointed, aninterimnamedcontact(suchastheauthorofthetravelplan)willneedtoberetained andheldresponsiblefortheplanuntiltheTPCisappointed.TheTPCwillneedtobeappointed priortooccupationandberetainedforthelifeofthetravelplan.
3. Baseline survey dataisrequiredtosettargetsfrom
4. Targetsneedtobeset. WehavesuggestedaminimumasaguideinTable4,buttheseare negotiabledependingonbaselinedataandlevelofinfrastructureinstalled.
5. Acommitmenttoannual monitoringisrequired;thiscanbeincludedasanactioninthe SustainableTravelActionPlan.
6. AlltheminimumrequirementsintheSustainableTravelActionPlan (outlinedinTable3 above)needtobeincludedwitharealistictargetdateforcompletion.
7. Forlargerormorecomplexsites,recommendedrequirementsfromTable3willneedto beincluded.
Smaller residential developments
Developmentsbetween20and60dwellings
OptionOneisnotappropriatefordevelopmentsofbetween20and60dwellings,sodevelopersareresponsiblefortheserequirements.However,nobondwillbetakenandthetravelplanningrequirementcanbesecuredbycondition.
A shorter travel statement will be required within Stars Community, along with commitment to providing the following;
• CyclestorageforresidentsandvisitorsasperSwindonBoroughCouncil’scycleparkingguidelines.
• Householdtravelinformationpacksalongwiththeoptionofchoosingeitheramonthlybuspass(valueapprox£50)oracyclediscountvoucherofequivalentvalue.Thepacksshouldincludedetailsaboutthelocalwalking,cyclingandbusroutesandtime,thecarsharescheme,localisedmaps,contactdetailsofwheretofindoutmoreinformationandthefacilitiesandincentivesavailable.
• Telecommunicationpointstoallowon-lineshoppingandhomeworking,reducingtheneedfortravel
• Travelinformationprovisionandpromotionofsustainabletransportinestateagents/showrooms etc.
Travel Plans SPD | XA guide for developers in Swindon
Developmentsofflatsandapartments
Cycleparkingwillberequiredforallflats/apartmentsregardlessofthesizeofdevelopment.Thiswilldependonthedensityofflatsandlocationbutasageneralrule,thereshouldbeonespaceprovidedperflat.Visitorcycleparkingisalsorequired;thenumberofstandswilldependonthesizeofdevelopment,numberofblocksetc.
Cycle parking for residential developments should be as per Swindon Borough Council’s Cycle Parking Guidelines.
Developmentswithlessthan1:1carparkingratios
Giventhatthiswillmeansomehouseholdswillhavenoaccesstoacar,provisionforothermodesoftransportareessential.Additionaltravelplanmeasures,suchasacarclub,arelikelytoberequestedforsuchdevelopments.Wherethemajorityofhouseshaveparkingbutsomedon’t,additionalincentivesshouldbeprovidedtothesehouseholds(e.g.freecarclubmembership,cyclevouchersinadditiontobuspassesforthehousehold,taxidiscountsetc).
These should be discussed with Swindon Borough Council prior to the submission of a planning application.
26 | Travel Plans Supplementary Planning Document A guide for developers in Swindon
8. School travel plans AllnewschoolsinSwindonarerequiredtosubmitandimplementatravelplan.Wedefineaschoolasanyeducationalfacilityforchildrenuptotheageof16,including(butnotlimitedto)nurseries,primary,secondary,academy,independent,VoluntaryAidedandSEN.
ASchoolTravelPlan(STP)isadocumentwhichsetsouthowaschoolwillpromotesafer,activeandsustainabletraveltoschool,withthemainemphasisbeingonreducingthenumberofchildrenbeingdriventoandfromschool.AgoodSTPshouldbebasedonconsultationwithteachers,parents,pupilsandgovernorsandthelocalcommunity.
Inordertoensurethattheplanremainsrelevantandappropriatetochangingcircumstancesitisessentialthattheplanisreviewedandupdatedregularly.
UsingModeshiftSTARSEducationtosupportyourplanningapplication
SwindonBoroughCouncilarenowincorporatingModeshiftSTARSintotheplanningprocesstomakeiteasierforschoolstoimplementandmaintaintheirSTPoncethedevelopmenthasbeencompleted.
TheinformationrequiredtosupportaplanningapplicationshouldbesubmittedviaanInterimSchoolTravelPlanform–Seehttp://www.swindontravelchoices.co.uk/business/travel-plans-guidance/.
TheInterimSchoolTravelPlanformisdesignedinsuchawayastoallowtheinformationtobetransferredeasilytotheSchool’sSTARSapplicationoncethedevelopmentiscomplete.TheSTARSapplicationwillthenbecometheSchool’slivetravelplanandshouldcontinuetobemaintained.
In particular, as a minimum standard we will be looking for
• A designated STP champion/co-ordinator
• Establishmentofa working group
• Clearidentificationofthe travel and transport issues (thattheplanwillseektomitigate)
• Travel surveys andconsultationexercisesundertakenatleastyearly
• Arangeofinitiativestoincreaseactiveandsustainabletraveltothesitethatwillbe implementedbeforeandafteroccupation–WeadviseusingModeshiftStarslistofinitiatives
• Monitoring schedule
• A commitment to achieve accreditation: bronzeaccreditationwithin1yearofopening,and silveraccreditation(orhigher)within5years.
ThereisnoOptionOneforschools,astheschoolcommunityneedtotakeresponsibilityforitsowntravelplan,andembedthisintotheschoolcultureforfuturegenerations.SwindonBoroughCouncilwillnotbeseekingabondnormonitoringfeeforSchoolTravelPlans.
Travel Plans SPD | 27A guide for developers in Swindon
9. ContactsandlinksForfurtherinformationandadviceontravelplanscontact:
TravelPlanOfficerSwindonBoroughCouncilWatTylerHouseBeckhamptonStreetSwindonWiltshireSN12JH
Email:[email protected]
Transport Development Management TeamSwindonBoroughCouncilWatTylerHouseBeckhamptonStreetSwindonWiltshireSN12JH
Email:[email protected]
28 | Travel Plans Supplementary Planning Document A guide for developers in Swindon
Appendices
APPENDIX A
Example of contribution costs under Option One and Option Two
1. Employment Travel Plan
The Employment Travel Plan package(OptionOne)wouldrequirea‘persquaremetre’(GFA)contributionfromeachdevelopertoSwindonBoroughCouncil,whowouldtheneffectivelyadoptthemanagement,implementationandmonitoringofthetravelplanforthedevelopment.
BenefitsoftheEmploymentTravelPlanPackage
BycommittingtotheEmployment Travel Plan package,thedeveloperisbenefittingfromthescaleandstrategicnatureofSwindonBoroughCouncil’sresources,ratherthanrelyingonthefinaloccupierscreatingtheirownindividualtravelplan.ASwindonwideapproachtoemploymenttravelplanningallowsforstrongerconnectionstobemadebetweenthenewdevelopmentsandexistingcommunities,aswellbenefittingfromeconomiesofscalewithtownwideschemes,suchasonlinetravelsurveys,acarcluband“borrowabike”scheme.
What measures are included in the Employment Travel Plan Package?
ThebreakdownofwhatwillbeprovidedunderOptionOnefortheEmployment Travel Plan package,hasalreadybeenoutlinedinChapterSix. WhatleveloffundingaredevelopersrequiredtocontributetojointheEmploymentTravelPlan package?
TheleveloffundingrequiredtojointheEmployment Travel Plan packageisoutlinedinTable6onpage29.ThisamounthasbeencalculatedusingcostsforthemeasuresoutlinedinChapterSixmultipliedupoveraproposed5yeardeliveryperiod.Wecanthenconvertthisperemployeecosttoasquaremetre1(GFA)cost-perlanduse-usingtheHCAemploymentdensitiestable1.Thisamountisindexlinked(basedateJuly2019.
Is it a compulsory charge?
ItisnotcompulsorytopaytheEmployerTravelPlancontribution,butSBCconsideritamorecosteffectiveoptionforallconcerned.Furthermore,thedeveloperwouldbereleasedfromcertainobligationssuchasmonitoringtheirdevelopmentafterconstructioncommences.
1https://www.gov.uk/government/publications/employment-densities-guide-3rd-edition
Travel Plans Supplementary Planning Document | 29A guide for developers in Swindon
Table6belowdemonstratesthecontributioncostpersquaremetreGFAbasedontheplanning land use.
Land Use Cost per square metre (GFA)A1Retail-Food £28.10A1Retail–Nonfood £28.10A2FinancialandProfessional £35.13A3/A4/A5FoodandDrink £28.10B1includingOffices £46.84
B2 Industrial £15.61B8WarehousingandDistribution £8.03C1 Hotels £281.07perbedroomC2ResidentialInstitutions• Hospitals and nursing homes• Residentialeducation• Hostels
£281.07perbed
D1Non-residentialinstitutionsDiscusswithSwindonBoroughCouncil:Basedonpredictedstaffinganduserlevels
D1 Schools Nocontributionsought
D1HigherandFurtherEducationDiscusswithSwindonBoroughCouncil:Basedonpredictedstaffingandstudentlevels
D2AssemblyandLeisureDiscusswithSwindonBoroughCouncil:Basedonpredictedstaffingandcustomerlevels
WhatifIdecidetodoOptionTwoinstead?
Developerscanchoosetoberesponsibleforfundingandimplementingtheirowntravelplan,includingprovidingincentives,theappointmentofatravelplancoordinator,conductingmonitoringandimplementingremedialmeasuresshouldtargetsnotbemet.Thisoptionalsorequiresabond,repayableonsuccessfulcompletionofthetravelplan,orretainedtoimplementremedialmeasuresifthedeveloper/ownerdoesnotmeetthesettargetsand/orcomplywiththeS106agreement.
ThebondforOptionTwo(inadditiontofundingthetravelplan)willfollowthesamecostasthe“persquaremetre”costsoutlinedinTable6above.Wealsorequireanon-refundablemonitoringdeposit of£5000foratravelplancovering5years.Fordevelopmentsphasedbeyondafiveyearperiod,furthermonitoringdepositswouldberequired.
Forillustrationpurposes,thecontributionsforthefollowingsizeddevelopmentswouldbeasfollows;
Employment Land OptionOne OptionTwo2
1000SqmetreA1foodstore £28,100 £28,100+£50005000SqmetreB8distributionwarehouse £40,150 £40,150+£5000200bedroomhotel £56,214 £56,214+£5000
2 This bond / deposit is on top of the costs to implement your own travel plan. The bond is refundable on successful completion and achieving targets, but the £5000 monitoring contribution is not.
30 | Travel Plans Supplementary Planning Document A guide for developers in Swindon
2.ResidentialTravelPlanTheresidentialtravelplanpackagewouldrequirea‘perdwelling’contributionfromeachdevelopertoSwindonBoroughCouncil,whowouldtheneffectivelyadoptthemanagement,implementationandmonitoringofthetravelplanforthedevelopment.
BenefitsoftheResidentialTravelPlanPackageBycommittingtotheResidentialTravelPlanpackage,thedeveloperisbenefittingfromthescaleandstrategicnatureofSwindonBoroughCouncil’sresources,ratherthancreatingtheirownindividualtravelplan.ASwindonwideapproachtoresidentialtravelplanningallowsforstrongerconnectionstobemadebetweenthenewdevelopmentsandexistingcommunities,aswellbenefittingfromeconomiesofscalewithtownwideschemes,suchasacarcluband“borrowabike”.
WhatmeasuresareincludedintheResidentialTravelPlanPackage?ThebreakdownofwhatwillbeprovidedunderOptionOnefortheResidentialtravelplanhasalreadybeenoutlinedinChapterSeven.
WhatleveloffundingaredevelopersrequiredtocontributetojointheResidentialTravelPlan?TheleveloffundingrequiredtojointheResidentialTravelPlanpackageis£288.00perdwelling.Thisamountisindexlinked(basedateJuly2019)ThishasbeencalculatedbydeterminingcostsforthemeasuresoutlinedinChapterSevenovertheproposeddeliveryperiod.ThisapproachisconsideredtooffergreaterbenefitstoSBC,developersandprospectiveresidents,ratherthanthroughthedeliveryofpiecemealtravelplans.
Is it a compulsory charge?ItisnotcompulsorytopaytheResidentialTravelPlancontribution,butSBCconsiderthisisamorecosteffectiveoptionforallconcerned.Furthermore,thedeveloperwouldbereleasedfromcertainobligationssuchasmonitoringtheirdevelopmentforyearsafterconstructioncommences.
WhatifIdecidetodoOptionTwoinstead?Developerscanchoosetoberesponsibleforfundingandimplementingtheirowntravelplan,includingprovidingincentives,theappointmentofatravelplancoordinator,conductingmonitoringandimplementingremedialmeasuresshouldtargetsnotbemet.
Thisoptionrequiresanadditionalbond,repayableonsuccessfulcompletionofthetravelplan,orkepttoimplementremedialmeasuresifthedeveloper/ownerdoesnotmeetthesettargetsand/orcomplywiththeS106agreement.
Wealsorequireanon-refundablemonitoringdepositof£5000foratravelplancovering5years.Fordevelopmentsphasedbeyondafiveyearperiod,furthermonitoringdepositswouldberequired.
For illustration, the contributions for the following sized developments are as follows;
ResidentialUnits OptionOne OptionTwo2
60 £17,280 17,280+£5000
90 £25,920 £25,920+£5000
150 £43,200 £43,200+£5000
250 £72,000 £72,000+£5000
500 £144,000 £144,000+£5000
1000 £288,000 £288,000+£5000
32 | Travel Plans Supplementary Planning DocumentA guide for developers in Swindon
APPENDIX B
Example S106 agreements
Condition
Aconditionisonlysuitableforphysicalinfrastructurerequiredasameansofaidingthemeasuresofthetravelplan.Forexample:Apedestrianand/orcyclewaythatcouldbepromotedandwouldofferimprovedaccessand/oralinktolocalservices.
Somesmallerdevelopmentscouldalsohavetheirtravelplanortravelplanstatementsecuredbycondition.
Contribution
Contributionswillbeagreedonadevelopmentspecificbasis,pleaserefertoAppendixAaboveforlevelsofcontribution.
LegalAgreement(Section106)
Travelplansshouldbesecuredthroughlegalagreementstoensureampleflexibilityandtheabilitytoincluderelatedcostsandcontributions.
Example clauses
WehaveprovidedsomeexampleSection106templatesbelow.Theseareforguidanceonlyandagreementswillbeagreedonadevelopmentspecificbasis.
Thereare5templateagreements;
Template1-ResidentialTravelPlanOptionOne-contributiononly(forSBCtodeliverthetravelplan)Template2-EmploymentTravelPlanOptionOne-contributiononly(forSBCtodeliverthetravelplan)Template3-ResidentialTravelPlanOptionTwo-ImplementedbyDeveloperTemplate4-EmploymentTravelPlanOptionTwo-ImplementedbyDeveloperTemplate5-PlanningconditionfortravelplanTemplate6-Planningconditionfortravelplanstatement
Travel Plans Supplementary Planning Document | 33A guide for developers in Swindon
Template 1 ResidentialTravelPlanOptionOne-contributiononly(forSBCtodeliverthetravelplan)
‘theTravelPlan’ meansaplanonModeshiftStarstodeliveramodalshiftaway fromtheprivatecarinfavourofsustainabletransport.
‘theTravelPlanContribution’ meansthesumofXXXpounds(£XX)tobeusedtowards:-
(a)theproductionandimplementationoftheTravelPlan;and
(b)theemploymentofapersonororganisation(atthediscretion oftheDirector)toco-ordinatetheTravelPlan
and (c)monitoringtheTravelPlan
TheTravelPlanContributionThepartiesherebyagreeandcovenantwitheachotherthat:-
(a) theOwnerwillpaytheTravelPlanContributiontotheCouncilonthefollowingtriggerpoints;
Phase of development %ofcontributiondueCommencementofdevelopment 25%1stoccupation 20%50%occupationofsite 40%Priorto100%occupationofsite 15%
(b) theCouncilwillimplementtheTravelPlaninaccordancewithScheduleA
(c) intheeventthetargetsinScheduleAarenotmet,theCouncilwillcontinuetravelplanning activityattheDevelopmentforafurther2yearsatitsowncost.
SCHEDULE AThecouncilwillundertakethefollowinguponreceiptoftheTravelPlanContribution
Travel Plan
ThecouncilwillproducetheTravelPlanonModeshiftStarsandmakethisavailabletoallrelevantparties.
Travel Plan Coordinator
ThecouncilwillemployanamedpersontoactasTravelPlanCoordinatorforaminimumperiodof5andahalfyears.TheTravelPlanCoordinatorwillberecruitednolaterthan3monthspriortofirstoccupation.
34 | Travel Plans Supplementary Planning DocumentA guide for developers in Swindon
Targets
OveralltripreductionratesbyprivatecarwillbesetatX%afterXyearsfrombaselinedatagatheredat30thoccupation.TherewillbeaninterimtargetreductionofX%Xyearsfrombaselinesurvey.
Monitoring
Thecouncilwillundertakesurveysupon30thoccupationandannuallythereafterforaperiodofXyears.Thesurveyswillinclude,butnotbelimitedto,residentsurveysandtrafficcounts.
Thecouncilwillproduceanannualmonitoringreportoutliningactivityandsurveyresults.Thereportwillbemadepublicallyavailabletoallrelevantparties.
SustainableTravelActionplan
Thecouncilwillundertakethefollowingactivitytoachievetheoutcomesofthetravelplan;
• Localsustainabletravelinformationwillbeprovidedtosalesofficestafffordistributiontoprospectiveresidents
• Householderwelcomepackswillbedistributedwhenresidentsfirstoccupytheirnewproperty.
Thepackswillincludetravelmapsforthelocalarea,bustimetables,detailsofthecarshareschemeandanoutlineofspecialoffersforthehousehold.
• Specialofferswillbeofferedtoeachhousehold.Theseincludeafree“borrowabike”scheme,andweek’spasstotrythebusforfree.
• ThetravelplanCoordinatorwillplanandholdpromotionalactivitiesonthesite–suchasledbikeridesorlocalwalks,inadditiontocarsharecoffeemorningsoreventstiedintonationalevents(e.g.catchthebusweek/bikeweek).Therewillbeaminimumoftwoactivitiesperyear,increasedinyears3-5iftargetsarenotontracktobemet.
Remedial measures
Iftargetsoutlinedabovearenotmetafter5years,thecouncilwillextendtheemploymentofthetravelplancoordinatorforafurthertwoyearstocontinuetravelplanningactivityoutlinedaboveatitsowncost.
Travel Plans Supplementary Planning Document | 35A guide for developers in Swindon
Template 2 EmploymentTravelPlanOptionOne-contributiononly(forSBCtodeliverthetravelplan)
‘theTravelPlan’ meansaplanonModeshiftStarstodeliveramodalshiftaway fromtheprivatecarinfavourofsustainabletransport.
‘theTravelPlanContribution’ meansthesumofXXXpounds(£XX)tobeusedtowards:-
(a)theproductionandimplementationoftheTravelPlan;and
(b)theemploymentofapersonororganisation(atthediscretion oftheDirector)toco-ordinatetheTravelPlan
and (c)monitoringtheTravelPlan
TheTravelPlanContributionThepartiesherebyagreeandcovenantwitheachotherthat:-
(a) theOwnerwillpaytheTravelPlanContributiontotheCouncilonthefollowingtriggerpoints;
Phase of development %ofcontributiondueCommencementofdevelopment 25%1stoccupation 20%50%occupationofsite 40%Priorto100%occupationofsite 15%
(b) theCouncilwillimplementtheTravelPlaninaccordancewithScheduleA
(c) intheeventthetargetsinScheduleAarenotmet,theCouncilwillcontinuetravelplanning activityattheDevelopmentforafurther2yearsatitsowncost.
SCHEDULE AThecouncilwillundertakethefollowinguponreceiptoftheTravelPlanContribution
Travel Plan
ThecouncilwillproducetheTravelPlanonModeshiftStarsandmakethisavailabletoallrelevantparties.
Travel Plan Coordinator
ThecouncilwillemployanamedpersontoactasTravelPlanCoordinatorforaminimumperiodofXyears.TheTravelPlanCoordinatorwillberecruitednolaterthan3monthspriortofirstoccupation.
36 | Travel Plans Supplementary Planning Document A guide for developers in Swindon
Targets
OveralltripreductionratesbyprivatecarwillbesetatX%after5yearsfrombaselinedatagatheredat30%occupation.TherewillbeaninterimtargetreductionofX%Xyearsfrombaselinesurvey.
Monitoring
Thecouncilwillundertakesurveysuponminimum30%occupationandannuallythereafterforaperiodofXyears.Thesurveyswillinclude,butnotbelimitedto,staffsurveysandtrafficcounts.
Thecouncilwillproduceanannualmonitoringreportoutliningactivityandsurveyresults.Thereportwillbemadepublicallyavailabletoallrelevantparties
SustainableTravelActionplan
Thecouncilwillundertakethefollowingactivitytoachievetheoutcomesofthetravelplan;
• Localsustainabletravelinformationwillbeprovidedtostaffuponinduction. Thepackswillincludetravelmapsforthelocalarea,bustimetables,anddetailsofthecarshare schemeandanoutlineofspecialoffersattheworkplace.
• Specialofferswillbeofferedtotheworkplace.Theseincludeafree“borrowabike”scheme, andweek’spasstotrythebusforfree.
• ThetravelplanCoordinatorwillplanandholdpromotionalactivitiesonthesite–suchas ledbikeridesorlocalwalks,inadditiontocarsharecoffeemorningsoreventstiedinto nationalevents(e.g.catchthebusweek/bikeweek).Thewillbeaminimumoftwoactivities peryear,increasedinyears3-5iftargetsarenotontracktobemet.
Remedial measures
IftargetsoutlinedabovearenotmetafterXyears,thecouncilwillextendtheemploymentofthetravelplancoordinatorforafurthertwoyearstocontinuetravelplanningactivityoutlinedaboveatitsowncost.
Travel Plans Supplementary Planning Document | 37A guide for developers in Swindon
Template 3 ResidentialTravelPlanOptionTwo-ImplementedbyDeveloper
‘theTravelPlan’ meansaplansubmittedonModeshiftStarsCommunityto deliveramodalshiftawayfromtheprivatecarinfavour ofsustainabletransport.
The Travel Plan Thepartiesherebyagreeandcovenantwiththeotherthat:
(a) priortoFirstOccupationtheOwner/DeveloperwillsubmittotheDirectortheTravelPlanon ModeshiftStarsCommunityforhiswrittenapproval.
(b) theDirectorshallprovidehiswrittencommentsonthedocumentssubmittedinaccordance withsub-clause(a)ofthisClausewithin28daysofreceiptofthesameandconfirminsodoing thatitisapproved(withorwithoutamendment)ornotapprovedandintheabsenceofa responseinthatperiodthedocumentinquestionshallbedeemedapproved
(c) theOwner/Developershallimplement,monitorandreviewtheTravelPlanatitsowncostin accordancewiththemonitoringstrategyasapproved
Bond
TheOwnerherebyagreeswiththeCouncilthatitwillupontheexecutionhereofpay
(b) abondinthesumofXXXpounds(£XXX)
(c) amonitoringcontributionof£5000
Bond repayment
X%ofthebondwillberepaidifTravelPlantargetsaremetfollowingmonitoringatyearX.TheremainderofthebondwillberepaidifTravelPlantargetsaremetatyearX.
Failuretomeettargetsby{date}willresultinSwindonBoroughCouncilusingthebondtoimplementfailsafemeasuresasoutlinedintheapprovedTravelPlan.
38 | Travel Plans Supplementary Planning DocumentA guide for developers in Swindon
Template 4 EmploymentTravelPlanOptionTwo-ImplementedbyDeveloper
‘theTravelPlan’ meansaplansubmittedonModeshiftStarsBusinesstodelivera modalshiftawayfromtheprivatecarinfavourofsustainable transport.
The Travel Plan Thepartiesherebyagreeandcovenantwiththeotherthat:
(a) priortoFirstOccupationtheOwner/DeveloperwillsubmittotheDirectortheTravelPlanon ModeshiftStarsBusinessforhiswrittenapproval.
(b) theDirectorshallprovidehiswrittencommentsonthedocumentssubmittedinaccordance withsub-clause(a)ofthisClausewithin28daysofreceiptofthesameandconfirminsodoing thatitisapproved(withorwithoutamendment)ornotapprovedandintheabsenceofa responseinthatperiodthedocumentinquestionshallbedeemedapproved
(c) theOwner/Developershallimplement,monitorandreviewtheTravelPlanatitsowncostin accordancewiththemonitoringstrategyasapproved
Bond
TheOwnerherebyagreeswiththeCouncilthatitwillupontheexecutionhereofpay
(a) abondinthesumofXXXpounds(£XXX)
(b) amonitoringcontributionof£5000
Bond repayment
X%ofthebondwillberepaidifTravelPlantargetsaremetfollowingmonitoringatyearX.TheremainderofthebondwillberepaidifTravelPlantargetsaremetatyearX.
Failuretomeettargetsby{date}willresultinSwindonBoroughCouncilusingthebondtoimplementfailsafemeasuresasoutlinedintheapprovedTravelPlan.
Travel Plans SPD | 39A guide for developers in Swindon
Template 5 TravelPlanningcondition
ThedevelopmentshallnotbeoccupieduntilatravelplanhasbeensubmittedthroughModeshiftStarsCommunity/ModeshiftStarsBusinessandagreedinwritingbytheLocalPlanningAuthority.
Thetravelplanshouldsetout:
i. objectivesandtargetsforpromotingsustainabletravel,
ii. appointment,contactdetailsandfundingofatravelplancoordinator,
iii. detailsofanannualmonitoringandreviewprocess,
iv. detailsofannualreportingtoSBC,
v. meansoffundingofthetravelplan,and;
vi. animplementationtimetable,lastingatleast5yearsand6months,includingtheresponsible bodyforeachaction.
Theapprovedtravelplanshallbeimplementedpriortooccupationofanypartofthedevelopmentandshallbecontinuedthereafterinaccordancewiththedetailstherein.
Reason:ToreducesingleoccupancycartravelandtoencourageandpromotesustainabletransportandtravelinaccordancewithPolicyTR1ofSwindonBoroughLocalPlan2026.
X | Travel Plans SPD A guide for developers in Swindon
Template 6 TravelPlanningStatementcondition
ThedevelopmentshallnotbeoccupieduntilaTravelPlanStatementhasbeensubmittedthroughModeshiftStarsCommunity/ModeshiftStarsBusinessandagreedinwritingbytheLocalPlanningAuthority.
TheTravelPlanStatementshouldsetout:
i. objectivesforpromotingsustainabletravel,
ii. contactdetailsofatravelplancoordinatorresponsibleforimplementingtheactionsfromthe travelplanstatement,
iii. anactionplan,and;
iv. animplementationtimetable,includingtheresponsiblebodyforeachaction.
Theapprovedtravelplanshallbeimplementedpriortooccupationofanypartofthedevelopmentandshallbecontinuedthereafterinaccordancewiththedetailstherein.
Reason:ToreducesingleoccupancycartravelandtoencourageandpromotesustainabletransportandtravelinaccordancewithPolicyTR1ofSwindonBoroughLocalPlan2026.
40 | Travel Plans Supplementary Planning DocumentA guide for developers in Swindon
Travel Plans Supplementary Planning Document | 41A guide for developers in Swindon
41 | Travel Plans Supplementary Planning DocumentA guide for developers in Swindon
Notes
Travel Plans Supplementary Planning Document | 42A guide for developers in Swindon
Notes
X | Travel Plans Supplementary Planning DocumentA guide for developers in Swindon
TravelPlansSPD–AguidefordevelopersinSwindon-version2–03/22FOI4177/19