+ All Categories
Home > Documents > Trinity County Collaborative Group - From Fire Kill to...

Trinity County Collaborative Group - From Fire Kill to...

Date post: 20-Jul-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
14
1 Trinity County Collaborative Group - From Fire Kill to Fuelbreaks - Mad River Complex Fire Salvage Project Geology Summary - prepared by: Fred S. Levitan, Six Rivers National Forest Geologist May 20, 2016 Mad River Complex Fires The fires of the Mad River Complex were ignited by lightning storms on July 30-31, 2015, and burned until contained in late August and early September, 2015. In general, the most intense burning occurred during the first few days of the fires, largely on ridgetops, with lower fire intensities occurring as the fires spread downslope, with some exceptions in later active burning periods. Fire spread from the crest of South Fork Mountain (Pickett Fire), Mad River Ridge (Gobbler Fire), and the Lassics (Lassic Fire), making up in the Mad River Complex fires. The fires as they spread affected watersheds including the South Fork Trinity River, the Mad River and Ruth Lake, and the Van Duzen River and many tributary streams. The Pickett Fire burned portions of both the Six Rivers and Shasta-Trinity National Forests and adjacent private lands; the other fires in the complexes were restricted to the Six Rivers National Forest and adjacent private lands. The current project addresses portions of the burned areas of the Pickett and Lassics Fires on the Six Rivers National Forest (SRNF). Project Background and Proposed Action The project described and analyzed here is a collaborative project between the SRNF and a group of stakeholders known as the Trinity County Collaborative Group (TCCG). Its objective is cost-effective removal of roadside, post-fire standing dead tree fuel concentrations that impede roadside safety corridor objectives, as a first step toward a larger network of roadside fuelbreaks creating safety corridors for community and resource protection. It has been agreed that the present project will avoid sensitive resource areas prone to additional post-fire damage. Specific to geologic resources and potential impacts to water quality, this includes avoidance of project activities on unstable and potentially unstable hillslopes. The proposed project addresses salvage of dead timber only, on up to 205 acres adjacent to roads in the Pickett Fire on the crest of South Fork Mountain and the Lassics Fire east of the Mount Lassic Wilderness and south of the high Lassics peaks. Dead trees would be felled and yarded by ground-based means within a maximum 300-foot wide roadside corridor, as described in the Decision Memo (DM). No new roads would be constructed, and any new temporary roads and landings would be rehabilitated post- project. A robust suite of design features, best management practices and monitoring provisions would be followed to ensure erosion control and to prevent on- and off-site effects to sensitive resources, including geologically unstable areas and water quality, as detailed below. Geologic and Geomorphic Setting The burned area includes bedrock of a variety of lithologies of the Coast Range geologic and geomorphic province of northern California. The Pickett Fire burned area is underlain by the South Fork Mountain Schist and Franciscan assemblage rocks, while the Lassics Fire area consists of Franciscan rocks and an outlier of the Coast Range ophiolite associated with the Great Valley Formation, the bulk of which is located in the easternmost Coast Ranges and westernmost Sacramento Valley (McLaughlin et al, 2000). All of these formations are susceptible to slope instability, with a variety of dormant and active deep-
Transcript
Page 1: Trinity County Collaborative Group - From Fire Kill to ...a123.g.akamai.net/.../11558/www/nepa/103383_FSPLT3_3083713.pdf · Geology Summary - prepared by: Fred S. Levitan, Six Rivers

1

Trinity County Collaborative Group - From Fire Kill to Fuelbreaks - Mad River Complex Fire Salvage Project

Geology Summary - prepared by: Fred S. Levitan, Six Rivers National Forest Geologist

May 20, 2016

Mad River Complex Fires

The fires of the Mad River Complex were ignited by lightning storms on July 30-31, 2015, and burned

until contained in late August and early September, 2015. In general, the most intense burning occurred

during the first few days of the fires, largely on ridgetops, with lower fire intensities occurring as the

fires spread downslope, with some exceptions in later active burning periods. Fire spread from the crest

of South Fork Mountain (Pickett Fire), Mad River Ridge (Gobbler Fire), and the Lassics (Lassic Fire),

making up in the Mad River Complex fires. The fires as they spread affected watersheds including the

South Fork Trinity River, the Mad River and Ruth Lake, and the Van Duzen River and many tributary

streams. The Pickett Fire burned portions of both the Six Rivers and Shasta-Trinity National Forests and

adjacent private lands; the other fires in the complexes were restricted to the Six Rivers National Forest

and adjacent private lands. The current project addresses portions of the burned areas of the Pickett

and Lassics Fires on the Six Rivers National Forest (SRNF).

Project Background and Proposed Action

The project described and analyzed here is a collaborative project between the SRNF and a group of

stakeholders known as the Trinity County Collaborative Group (TCCG). Its objective is cost-effective

removal of roadside, post-fire standing dead tree fuel concentrations that impede roadside safety

corridor objectives, as a first step toward a larger network of roadside fuelbreaks creating safety

corridors for community and resource protection. It has been agreed that the present project will avoid

sensitive resource areas prone to additional post-fire damage. Specific to geologic resources and

potential impacts to water quality, this includes avoidance of project activities on unstable and

potentially unstable hillslopes.

The proposed project addresses salvage of dead timber only, on up to 205 acres adjacent to roads in the

Pickett Fire on the crest of South Fork Mountain and the Lassics Fire east of the Mount Lassic Wilderness

and south of the high Lassics peaks. Dead trees would be felled and yarded by ground-based means

within a maximum 300-foot wide roadside corridor, as described in the Decision Memo (DM). No new

roads would be constructed, and any new temporary roads and landings would be rehabilitated post-

project. A robust suite of design features, best management practices and monitoring provisions would

be followed to ensure erosion control and to prevent on- and off-site effects to sensitive resources,

including geologically unstable areas and water quality, as detailed below.

Geologic and Geomorphic Setting

The burned area includes bedrock of a variety of lithologies of the Coast Range geologic and geomorphic

province of northern California. The Pickett Fire burned area is underlain by the South Fork Mountain

Schist and Franciscan assemblage rocks, while the Lassics Fire area consists of Franciscan rocks and an

outlier of the Coast Range ophiolite associated with the Great Valley Formation, the bulk of which is

located in the easternmost Coast Ranges and westernmost Sacramento Valley (McLaughlin et al, 2000).

All of these formations are susceptible to slope instability, with a variety of dormant and active deep-

Page 2: Trinity County Collaborative Group - From Fire Kill to ...a123.g.akamai.net/.../11558/www/nepa/103383_FSPLT3_3083713.pdf · Geology Summary - prepared by: Fred S. Levitan, Six Rivers

2

seated and shallow landslide features present. The Franciscan formation is pervasively sheared and

stratigraphically incoherent; with basic lithologies of sandstone and argillaceous materials

predominating. The South Fork Mountain Schist is highly foliated quartz mica schist, with structure

dipping parallel to the eastern slope of the mountain, supporting ubiquitous deep-seated landslide

complexes and perched groundwater. The schist is the tectonic sole of the Farallon Plate that was

subducted and sutured to North America in an accretionary event that began in the late Jurassic; the

Franciscan represents the subduction complex associated with that event (Dumitru et al, 2010). The

Lassics contain numerous outcrops of ultramafic rocks of the ophiolite sequence, and support unique

and rare plant communities adapted to harsh serpentine environments.

A number of large landslide features as well as many smaller features are present on the landscape.

Notably, the Mule Slide is a very large debris slide complex that occupies the eastern slope of the ridge

crest traversed by Roads 1S07 and 1S11, in the immediate vicinity of the proposed Lassics units.

Numerous smaller debris slides are present below the crest slope breaks of the major Lassics ridgelines

as well. Large deep-seated landslide complexes are prevalent in the Pickett Fire area and occupy much

of the western slope downslope of the proposed Pickett units. These and other features are discussed

further in the Field Observations section below.

Fire Effects and Slope Stability Concerns

The unstable geomorphology of the area is susceptible to accelerated slope instability, erosion and

sediment delivery as a consequence of fire effects to soil and vegetation. Possible mechanisms of

increased erosion and landsliding include: 1) increased surface erosion and delivery of sediment as well

as increased channel scour due to loss of soil strength and increased post-fire peak flows from burned

watersheds; 2) increased probability of shallow debris sliding along channels and inner gorges where

banks and toe slopes are susceptible to erosion from higher flood flows; 3) channelized debris flows

from burned areas with loss of soil cover and structure, reduced root strength and increased sediment

delivery to channels; and 4) reactivation of deep-seated landslides, potentially related to loss of

evapotranspiration and associated elevated groundwater following tree mortality from fire (Mikulovsky

et al, 2012; Levitan 2014).

During the Burned Area Emergency Response (BAER) assessment of the Mad River Complex (USDA

Forest Service BAER Team, 2015), a distributed debris flow model developed (Cannon et al 2010) and

run by the USGS was used to help evaluate the risk of post-fire debris flows. Debris flows are shallow

rapid failures that occur when sediment or unconsolidated geologic materials become saturated and fail

in a channelized system, presenting threats of impact and inundation to downstream resources. Debris

flows often initiate in denuded post-fire landscapes, although their prevalence in post-fire environments

of the Pacific Northwest is less evident than in more arid areas of the Intermountain West where intense

summer thunderstorms often initiate debris flow events. Notwithstanding that, the model was run to

assess whether there was increased debris flow potential in fire-affected drainages within the Mad River

Complex. A number of watersheds and channel segments with potentially elevated debris flow risk were

identified and described in the BAER reports. To date, despite the wet winter of 2015-2016, no debris

flows have been reported in the burned areas. There has been considerable small-scale erosion and

sedimentation in the burned areas, including slumping and sliding of road cutslopes and rilling of

hydrophobic soils. Significant landsliding has not been observed to date, but remains a concern as

burned areas and vegetation slowly recover from fire effects.

Page 3: Trinity County Collaborative Group - From Fire Kill to ...a123.g.akamai.net/.../11558/www/nepa/103383_FSPLT3_3083713.pdf · Geology Summary - prepared by: Fred S. Levitan, Six Rivers

3

Field Observations

Geologic reconnaissance of the project area was conducted several times between November 2015 and

April 2016 as the project was developed. The focus of the field effort was to identify active and

potentially unstable areas and exclude them from the units. As described below in the Regulatory

Framework section, unstable and potentially unstable areas area are defined as Riparian Reserves under

the Northwest Forest Plan (NWFP) and the SRNF Land and Resource Management Plan (LRMP). Among

the collaborative zones of agreement underlying the project, as outlined in the DM, is avoidance of

Riparian Reserves and geologically unstable areas. Furthermore, as described below in the Project

Design Features and Monitoring sections, project planning and implementation are focused on

minimizing to the greatest extent possible damaging effects to fire-affected resources including soil and

water quality. Consequently, field identification of unstable areas included assessment of potential

offsite effects to adjacent landslide-prone hillslopes, and suggestions to project planners to adjust unit

boundaries and prescriptions to avoid promoting slope failures. Following is a unit-by-unit description of

field observations, concerns, and any adjustments made pursuant to field review.

Lassics Units (counterclockwise, east to west) The Lassics units are located in ridgetop positions

in a roughly circular arc encompassing the headwaters of the West Fork Van Duzen River,

following roads 1S11, 1S07, and 2S08 and spur roads that intersect those arterial roads. Bedrock

geology is Franciscan Formation (Central Belt and Yolla Bolly terrane), with a mix of sedimentary

rock types dominated by graywacke sandstone and lesser proportions of argillite and shale. Few

areas of highly sheared mélange are present, and no areas of serpentinite or other ultramafic

lithologies occur within the project units.

Unit 3 - Roads 1S11, 1S11G - 8 acres - The unit is located on either side of Road 1S11 and

extends east across Road 1S11G at its southeast corner. It occupies a broad, gentle ridge crest

with rocky, apparently colluvial soils dominant. The margins of the units are steeper and show

signs of soil creep (pistol-butted trees). A minor landslide area was excluded on the northeast

side of the unit – interpretation is based on a <2 foot high active scarp and an apparent deposit

lobe in a swale. The northwest portion of the unit west of Road 1S11 sits above a large grassy

earthflow, and the unit boundary appears to cross the uppermost portion of the earthflow

scarp. There are is no evidence of recent activity on the scarp, so it was not designated as active

or unstable. The unit appears to present no threats to slope stability, but should be monitored

post-treatment, and any unfavorable project-created drainage issues corrected at that time.

Unit 91A - Road 1S11 - 39 acres - The unit is located on either side of Road 1S11, just north of

Unit 3, on the eastern slopes of Green Mountain. Steep slopes at the head of landslide

complexes are present east (downslope) of the road. The unit is dissected by a number of

drainages descending the east slopes of Green Mountain.

An area at the head of a landslide, with nested benches and scarps, was flagged out at the

northeast corner of the unit. This unit is for future (2017) harvest, following additional post-

fire tree mortality. Consequently, it was not fully evaluated in 2016. Prior to future entry and

unit designation, the unit will be assessed for slope stability concerns, and any unstable areas

will be excluded.

Page 4: Trinity County Collaborative Group - From Fire Kill to ...a123.g.akamai.net/.../11558/www/nepa/103383_FSPLT3_3083713.pdf · Geology Summary - prepared by: Fred S. Levitan, Six Rivers

4

Unit 91 - Road 1S11 - 1 acre - This small unit is located immediately northeast of Road 1S11 on

the northeast slopes of Green Mountain. It occupies mostly gentle topography, with a steeper

pitch toward the northeast corner. No immediate slope stability concerns were noted. This unit

is for future (2017) harvest, following additional post-fire tree mortality. Consequently, it was

not fully evaluated in 2016. Prior to future entry and unit designation, the unit will be

assessed for slope stability concerns, and any unstable areas will be excluded.

Unit 92 - Road 1S11 - 10 acres - This unit is mostly below (north of) Road 1S11 on the northern

slopes of Green Mountain, west of Unit 91. It is similar to Unit 91a in that it is dissected by a

number of stream channels. Portions below the road are steep, but no immediate slope stability

concerns were noted. This unit is for future (2017) harvest, following additional post-fire tree

mortality. Consequently, it was not fully evaluated in 2016. Prior to future entry and unit

designation, the unit will be assessed for slope stability concerns, and any unstable areas will

be excluded.

Unit 2A - Road 1S11 - 3 acres – This unit is mostly above (south of) Road 1S11, straddling the

ridgeline, with a smaller area north of (below) the road. Colluvial slopes are prevalent, with

steep road-cuts and through-cuts subject to ravel and rilling. Landslide hazard is low, but care

will need to be taken not to destabilize cutslopes during yarding.

Unit 2 - Road 1S11 -12 acres - This unit is on both sides of Road 1S11, north of the Mule Slide

and immediately east of the junction with Road 1S07. The southern portion of the unit, above

the road, approached the ridge that defines the drainage divide at the head of the Mule Slide,

but does not cross the ridgeline to the landslide area. A portion of the unit that had been

proposed on benched slopes above the slide was eliminated based on the geologist’s

recommendation. The head of an unstable area in a swale downslope (north) of the road at the

west end of the unit was also flagged by the geologist and excluded from the unit. The

remaining unit area occupies colluvial slopes, which are moderate above the road and very

steep (70-80%) below the road (to the north). These steep slopes are very rocky, and show no

signs of instability. Steep road-cuts and through-cuts are subject to ravel and rilling. Landslide

hazard is low, but care will need to be taken not to destabilize cutslopes during yarding.

Unit 1c - Road 1S07 - 6 acres - This unit is mostly west of Road 1S07, south of the junction with

Road 1S11. It occupies a gently rolling ridgetop knoll. The ground is hummocky but shows no

signs of slope instability. A portion of the unit that had been proposed east of the road was

judged unstable and eliminated during early project planning based on the geologist’s

recommendation. A few hundred feet west of the unit, below a steep slope break, there is a

substantial debris slide complex. Unit treatments should have no effect on this feature;

however, it may experience increased activity related to post-fire conditions.

Unit 6 - Road 2S34 - 9 acres – This unit is on either side of Road 2S34, just southeast of Road

1S07 and south of Unit 1c. It is similar to Unit 1C in occupying a gentle rolling ridge crest, with no

slope stability concerns. A gate near the north end of the unit marks a transition to steeper,

concave slopes with debris slide potential – these were excluded from the unit. Steep road-cuts

are subject to ravel and rilling. Landslide hazard is low, but care will need to be taken not to

destabilize cutslopes during yarding.

Page 5: Trinity County Collaborative Group - From Fire Kill to ...a123.g.akamai.net/.../11558/www/nepa/103383_FSPLT3_3083713.pdf · Geology Summary - prepared by: Fred S. Levitan, Six Rivers

5

Unit 4 - Road 1S07 - 5 acres - This unit is east of Road 1S07 and about 0.5 miles south of Unit 6.

It mostly occupies a flat to gently convex ridge crest area with no slope stability concerns,

although there is a small steeper area in the axis of a swale at the southeast corner of the unit.

This is the only area of concern with this unit. The unit boundary at the southeast corner is

immediately upslope of an active slide scarp, associated with a landslide feature that occupies

the swale downslope of the unit. Care will need to be exercised in assuring that log skidding

does not create additional drainage onto the slide. Recontouring of any gouges or trenches

created by yarding will be necessary to mitigate this concern.

Unit F80 - Road 1S07 - 12 acres - This unit is located east (downslope) of Road 1S07, north of the

junction with Road 2S08. This unit is designated a commercial firewood unit (not saw logs). The

firewood purchaser would be bound to the same project design features and mitigations that

the timber sale contractor would be, including avoiding operations in Riparian Reserves,

following all BMPs, and mitigating/repairing damage that might contribute to slope instability.

The unit is very steep. The northern portion appears colluvial but stable. The southern portion,

south of the junction with Road 2S33 and due north of the junction with Road 2S08, includes

concave slopes in stream headwaters that appear to have some risk of instability. As the stream

corridor Riparian Reserves are excluded from harvest per the project guidelines, these concerns

should be mitigated.

Unit 1B - Road 2S36 - 11 acres – This unit is located above southeast) of Road 2S36, immediately

southeast of Unit F80 and the junction of Road 1S07 and 2S08. The western portion of the unit is

gently convex, while the eastern portion occupies moderately steep, very rocky slopes. No

landslide activity is evident.

Unit 1A – Road 2S36 – 5 acres – This unit is located approximately 1,000 feet northeast of Unit

1B on Road 2S36, above (south of) the road. The unit occupies a convex, moderately sloping

ridge spur. No landslide activity was observed.

Unit 5 - Road 2S20 - 22 acres - This unit is located on both sides of Road 2S20 where it descends

a series of switchbacks traversing a broad ridge spur to the northeast. Near the gate on 2S20,

approximately 400 feet north of the junction with Road 2S08, colluvium from the fill slope has

blocked the inboard ditch and diverted spring flow onto the road surface in two locations,

saturating the road surface. Immediately downslope of fill slope, an approximately two-foot

high active scarp is present, above a hummocky hillslope that appears unstable. Because of this

unstable slope, it is NOT recommended to dip and drain the spring at the road onto the hillslope

at this location. Rather, because this site needs repair prior to project implementation to

provide a stable road surface, ditch cleaning and spot rock is recommended. This location should

be monitored and evaluated for a long-term solution (Decommissioning? Road reconstruction

with drainage and stabilization measures incorporated into the design?)

The unit itself is generally moderately steep, with slightly hummocky ground in a mix of convex

and concave slopes. Some colluvial activity was observed (pistol-butted trees), but no signs of

more pervasive landsliding or slope instability were observed within the unit. North of the unit is

a steep concave headwall that descends into a drainage – this is outside the unit and below the

road, which is the unit boundary. Proposed activities should not negatively affect slope stability.

Page 6: Trinity County Collaborative Group - From Fire Kill to ...a123.g.akamai.net/.../11558/www/nepa/103383_FSPLT3_3083713.pdf · Geology Summary - prepared by: Fred S. Levitan, Six Rivers

6

Unit 90 - Road 2S24 - 8 acres - This unit is located above (on the north side of) Road 2S24, in the

Summit Flats area about 0.5 miles northeast of the junction with Road 2S08. The unit occupies

gentle to moderate sideslopes with no signs of slope instability.

Unit 90a - Road 2S24 - 18 acres – This unit overlaps Unit 90, but is on both sides of the road and

extends roughly 1,500 feet further to the northeast. It is located on moderate, slightly concave

sideslopes undissected by drainages. No signs of slope instability were seen. This unit is for

future (2017) harvest, following additional post-fire tree mortality. Consequently, it was not

fully evaluated in 2016. Prior to future entry and unit designation, the unit will be re-assessed

for slope stability concerns, and any unstable areas will be excluded.

Pickett Units - The Pickett units are located on and near the ridgetop of South Fork Mountain off

Road 1S23 south of its junction with Highway 36, and on Road 1S41 on the west slope of South

Fork Mountain. Bedrock is South Fork Mountain Schist, with some massive metavolcanic

outcrops present near the ridgetop. The contact with Franciscan rocks (metasandstone and

metashale) is at the base of unit 37.

Unit 32 - Roads 1S23 and 1S41 - 9 acres - This unit is located on the downslope side (southwest)

of Road 1S23, approximately 2.5 road miles south of the junction with Highway 36. Road 1S41

joins Road 1S23 in the southern half of the unit. The upper portion of the unit occupies the

convex ridge crest of South Fork Mountain, and no slope stability concerns were observed there.

The western portions of the unit quickly drop off to steep, rocky slopes above concave

headwalls. These slopes were evaluated in the field, and suspected landslide-prone portions of

concave headwalls were excluded as the unit was laid out on the geologist’s recommendation.

The remaining steep slopes within the unit are subject to post-fire rill and sheet erosion and dry

ravel on denuded, hydrophobic soils. An especially sensitive area between Roads 1S23 and

1S41, within the unit, will require careful post-project monitoring and erosion control

implementation to reduce the risk of sediment delivery and drainage diversion on Road 1S41.

Immediately downslope of Unit 32, an old non-system road crosses a steep headwall slope and

two swales. The northern of the two sites is immediately upslope of a channel head. Both

crossings are eroding and failing, and are in need of repair (fill removal). If sale area

improvement (K-V) funds are available, this would be a good application for those.

Unit 33 - Road 1S23 - 6 acres - This unit is located on the downslope side (southwest) of Road

1S23, approximately 2,000 south of Unit 32. It also occupies gently convex ridgetop slopes and

steeper slopes on the west side of South Fork Mountain. These steeper slopes are generally very

rocky, with no evident slope stability concerns. Some areas of unconsolidated colluvial soils are

present, and may require care to prevent and control erosion from skid trails, log skidding paths,

etc. Landing access may require disturbing steep cutslopes on road 1S23, which will likewise

require monitoring and erosion control to prevent sediment delivery and progressive cutslope

failure.

Unit 34 - Road 1S23 - 10 acres - This unit is located on the downslope side (southwest) of Road

1S23, immediately south of Unit 33. It also occupies gently convex ridgetop slopes and steeper

slopes on the west side of South Fork Mountain. In the southern portion of the unit, these

slopes are moderately steep (20-30%) and may be tractor harvestable. The northern portion of

Page 7: Trinity County Collaborative Group - From Fire Kill to ...a123.g.akamai.net/.../11558/www/nepa/103383_FSPLT3_3083713.pdf · Geology Summary - prepared by: Fred S. Levitan, Six Rivers

7

the unit is located in a steep, rocky concave headwall, with numerous rock outcrops and cliff

bands. No landslide concerns were observed, but colluvial sliding of rock and soil in the steep

headwall is likely. Erosion control will need to be implemented where log skidding occurs on

unconsolidated colluvial slopes.

Unit 37 - Road 1S41 - 11 acres – This unit is located on Road 1S41, between descending

switchbacks, on the west slope of South Fork Mountain, approximately one road mile southwest

of Unit 32. Slopes are moderately steep, with no landslide concerns observed within the unit.

There are some areas of concern for slope stability and sediment delivery immediately adjacent

to the unit, however. At the southeast corner of the unit, there is an unstable swale immediately

upslope of the road which has been designated as a legacy sediment source for repair. The

swale incorporates the toe of an earthflow that appears to be associated with a shear zone.

Unstable drainage, which is not captured in the existing channel and culvert, has eroded a gully

across the road. Due the unpredictable instability of the drainage and the hillslope feature, the

best repair solution would appear to be to disperse drainage with coarse rock across the

roadbed and through the switchback below.

Spur road 1S41A, due north of the diverted swale, is experiencing fill failure directly into a

stream channel. Repair would consist of pulling back the roadfill and disposing of it in a stable

location, either against the cutslope or in a berm to block the road entrance. This would be a

good application of sale area improvement funds (K-V), if they are available.

Regulatory Framework

As described in the DM, the following regulatory authorities apply to the project, specific to slope

stability and geologic concerns:

Six Rivers National Forest Land and Resource Management Plan (LRMP):

Direction from the LRMP will be followed regarding geology and unstable areas, including standards and

guides for 1) Riparian Reserves – through avoidance of all unstable riparian reserves and mitigation of

off-site effects, as described above; 2) General Forest – through design features to maintain site

productivity and to implement all relevant BMPs as agreed to in the Management Agency Agreement

and the Waiver of Waste Discharge with the North Coast Water Board.; and 3) forest-wide standards

and guides as listed below:

1-6 The potential for increased mass movement and soil erosion will be addressed for proposed

timber harvest and road building. Landslide hazard maps and a risk assessment should be

developed for timber harvest planning. Alternate road specifications or road locations should be

evaluated where proposed management would increase the potential for mass movement and

soil erosion. (LRMP IV-71).

1-7 Roads, landings, and timber harvest units will be located and designed to avoid triggering or

accelerating mass movements that would adversely affect a stream or degrade a commercial

growing site by removing a substantial volume of topsoil. (LRMP IV-71).

Aquatic Conservation Strategy (Northwest Forest Plan and Six Rivers NF LRMP): The action was designed

to meet the Aquatic Conservation Strategy including: all activities staying outside the riparian reserves,

Page 8: Trinity County Collaborative Group - From Fire Kill to ...a123.g.akamai.net/.../11558/www/nepa/103383_FSPLT3_3083713.pdf · Geology Summary - prepared by: Fred S. Levitan, Six Rivers

8

project design features to minimize erosion and best management practices for protecting water

quality. The project meets the aquatic conservation strategy.

Clean Water Act. The project will be conducted in accordance with requirements of the Regional Water

Quality Control Board, North Coast Region, to ensure compliance with the California Water Code and

the Federal Clean Water Act and Porter-Cologne Water Quality Control Act. All streams will be managed

in full compliance with the Aquatic Conservation Strategy and Basin Plan to achieve water quality goals

and objectives. The Forest Service will comply with this Act through the use of BMPs to ensure

protection of soil and water resources, as well as an approved monitoring plan under the terms of the

North Coast Regional Water Quality Control Board (NCRWQCB) the Categorical Waiver for Discharges

Related to Timber Harvest Activities on Federal Lands Managed by the United States Department of

Agriculture, Forest Service (Order No. R1-2015-0021), as described in the DM.

Effects Analysis, No Extraordinary Circumstances

The project was designed to eliminate or minimize to the greatest degree possible, negative effects to

resources, including water quality and erosion concerns associated with slope instability. Units were

reviewed ensure that unstable areas were excluded; project areas that might contribute to off-site

erosion or instability have been designated for intensive monitoring and erosion control measures.

Special consideration has been given to the sensitivity of soils and geologic features to disturbance in

the post-fire environment, and appropriate design features, mitigations and monitoring have been

incorporated in the project to reduce any project effects to the minimum possible. Consequently, there

should be no significant effects, and no extraordinary circumstances, as a consequence of the proposed

project, specific to geologic resources and slope instability. Unavoidable post-fire effects may occur

within and outside of the project area related to the condition of the burned landscape, but not as a

consequence of project activities.

Project Design Features – Soils and Geology

The following project-specific design features, as described in the DM, will help assure that there will be

little or no project-related erosion, slope failure, and/or sediment delivery as a consequence of project

activities (see DM for a complete list of project design features and BMPs):

Ground Based Equipment and Landings

All landings required for operations are located outside of Riparian Reserves.

Where feasible use existing skid trails, except where existing skid trails from prior entry are or

will cause detrimental soil and hydrologic conditions that could be avoided. If new skids trails

are warranted; limit cumulative soil disturbance to 15 percent or less of the harvest unit area.

The timber sale contract will require erosion control treatments such as water barring on skid

trails and yarding corridors, particularly on moderate to steep slopes with erosive soils, prior to

extended wet weather operational shut down and immediately prior to acceptance per contract

provisions by subdivision (identified on sale area map).

Ground-based equipment will operate on relatively dry soils of high soil strength or bearing

capacity. For the majority of soil types affected in the project area, this is when soil is dry to the

Page 9: Trinity County Collaborative Group - From Fire Kill to ...a123.g.akamai.net/.../11558/www/nepa/103383_FSPLT3_3083713.pdf · Geology Summary - prepared by: Fred S. Levitan, Six Rivers

9

upper 4 inches depth of mineral soil. This may be waived upon site inspection and

determination by a Forest Service earth scientist.

If present, maintain a well-distributed soil cover of 50 percent on moderate slopes of less than

25 percent, and 60 to 70 percent cover on steeper slopes. Priority for placement of cover is

primary skid trails and winching locations, and shall be completed following each operating

season. Soil cover consists of unburned duff and needle cast, basal live plant cover, fine woody

debris, downed logs and rock.

All landings, skid trails and yarding (end-lining or winching logs) will be assessed in the field in

coordination with the sale administrator, prior to being accepted in compliance with contractual

provision to ensure soil mitigations measures achieve SRNF LRMP standards.

o If during skidding and yarding operations, gouges or gullies are inadvertently created,

acting to channel storm water run-off and delivery off-site to unstable or potentially-

unstable areas, the timber sale contract provisions will require the operator to construct

water-bars, and may be required to place slash material to remedy resource impacts if

necessary. If the Forest Service earth scientist indicates these provisions are insufficient,

slopes may be re-contoured to their pre-operation conditions. Additional manual

placement of fine slash (duff and needle cast), realignment of downed trees (log

contouring), and back-blading debris where soils are barren may be required. These

activities will implemented and funded either by agency personnel, via an agreement or

an independent service contract.

o Prior to contract acceptance, landings should be out-sloped to avoid puddling and drain

storm water run-off. Slash in excess of other resource needs will be scattered. If

feasible, desired soil cover is 50 percent or more on moderate slopes of less than 25

percent, and 60 to 70 percent cover or more on steeper slopes. Material may consist of

either: slash, wood chips, or any combination.

o Skid trails, landings and landing access spurs that are located adjacent to Forest roads

will be blocked with available material (large wood or boulders) and may be mulched in

order to discourage unauthorized motorized vehicles access.

Roads (System and Temporary) including Landing Access Spurs

Existing temporary roads used for operations located within or adjacent to harvest units will be

closed post-operations, prior to winter wet weather shut-down. If a second entry is anticipated

2017-2018, all temporary roads and landing access spurs will be winterized with erosion control

measures installed at the end of the operating season.

Tree felling operations and yarding of logs over unstable cut- or fillslopes, will be avoided to the

extent possible. If damage does result from project activities, and material deposited within the

road prism, it would be removed and placed in a stable location.

Erosion control measures such as waterbarring, recontouring or slash material placement will be

performed to mitigate these impacts. An earth scientist would oversee repairs as needed.

Page 10: Trinity County Collaborative Group - From Fire Kill to ...a123.g.akamai.net/.../11558/www/nepa/103383_FSPLT3_3083713.pdf · Geology Summary - prepared by: Fred S. Levitan, Six Rivers

10

Riparian Reserves

No project activities shall occur within designated Riparian Reserves. These include tree felling,

tree removal, landings and heavy equipment. Exceptions include log haul on system roads, and

trees determined to be a safety hazard to operations.

Limit heavy equipment disturbance within 20 feet on either side of swales (defined as a sloping

concave feature with no existing channel scour present) by avoiding equipment use upslope of

their axes, and minimizing equipment crossings except where approved by the Forest Service.

Best Management Practices

Implement Water Quality BMPs and include monitoring as described below.

Apply appropriate BMPs, either National or Regional, associated with all project activities, including

timber harvest and road activities and development.

The following BMPs from the Region 5 Regional Water Quality Management Handbook and/or the USDA

Forest Service National Core BMPs will apply to soil and water-quality protections and protection of

unstable or potentially unstable areas within or adjacent to harvest units. The practices that provide the

greatest water quality and soil productivity protections will be selected from one or the other BMP

guidance document.

These BMPs will be identified on the ground and recorded on a by-unit, site-specific basis. Best

Management Practice sites will be subject to 100 percent implementation monitoring post-harvest, by

means of a checklist and harvest maps and cards (standard waiver provision), and to 100 percent

effectiveness monitoring following one or more post-harvest winters (special provision for this project).

Effectiveness monitoring results, and any follow-up corrective measures taken, will be reported to the

Water Board by July 15th in the year following harvest. If areas are entered in a subsequent year to

harvest later dying trees, these same provisions and timetable will apply, based on the year of entry.

Effectiveness monitoring results will be scored and reported using the Regional BMPEP methodology.

Applicable Regional BMPs for soils/geology/slope stability:

1.1 Timber Sale Planning Process

1.2 Timber Harvest Unit Design

1.3 Determining Surface Erosion Hazard for Timber Harvest Unit Design

1.6 Protecting Unstable Lands

1.9 Determining Tractor-loggable Ground

1.10 Tractor Skidding Design

1.12 Log Landing Location

1.13 Erosion Prevention and Control Measures During Timber Sale Operations

1.14 Special Erosion-prevention Measures on Disturbed Land

Page 11: Trinity County Collaborative Group - From Fire Kill to ...a123.g.akamai.net/.../11558/www/nepa/103383_FSPLT3_3083713.pdf · Geology Summary - prepared by: Fred S. Levitan, Six Rivers

11

1.16 Log Landing Erosion Control

1.17 Erosion Control on Skid Trails

1.20 Erosion-control Structure Maintenance

1.21 Acceptance of Timber Sale Erosion-control Measures Before Sale Closure

2.30 Timing of Construction Activities

2.11 Control of Sidecast

2.22 Maintenance of Roads

Applicable National Core BMPs:

Veg-1 Vegetation Management Planning

Veg-2 Erosion Prevention and Control

Veg-3 Aquatic Management Zones

Veg-4 Ground-Based Skidding and Yarding Operations

Veg-6 Landings

Veg-8 Mechanical Site Treatment

Road-3 Road Construction and Reconstruction

Road-4 Road Operations and Maintenance

Road-5 Temporary Roads

Road-6 Road Storage and Decommissioning

Road-7 Stream Crossings

Road-9 Parking and Staging Areas

Road-10 Equipment Refueling and Servicing

Monitoring

The following monitoring guidelines will be followed, and accompanied by a detailed, site-specific

monitoring plan to ensure water quality waiver compliance and minimization of erosion, sediment

delivery and slope failure:

Soil Monitoring

Daily monitoring of haul routes, landings, and skid trails consisting of BMP forms or daily diaries will

document implementation and effectiveness of BMPs. Project activities will be curtailed and corrective

action taken when any of the following are encountered or expected:

Page 12: Trinity County Collaborative Group - From Fire Kill to ...a123.g.akamai.net/.../11558/www/nepa/103383_FSPLT3_3083713.pdf · Geology Summary - prepared by: Fred S. Levitan, Six Rivers

12

Erosion of Road Material

o Scour or sediment deposition evident and extending more than 20 feet below outlet

of cross drain.

o Scour or sediment movement into riparian reserve or drainage way from road

surface, cut slope, or fill slope.

Ruts/Rill

o More than 10% of road segment length has rills more than 2 inches deep and 20

feet in length that continue off road.

o Ruts formed that can channel water past erosion control structures.

o Numerous rills present at stream crossing (>1 rill per lineal 5 feet), apparently active

or enlarging, evidence of some sediment delivery to stream.

Culverts

o Sediments or debris is blocking 30% of inlet or outlet.

o More than 10% of the flow to pass beneath or around culvert, or noticeable piping

evident.

Skid Trails/ Harvest Areas

o More than 20% of skid trail or log skid path lengths have rills present that are over 2

inches deep and more than 10 feet in length. Log skid paths are channeling water

and/or sediment offsite or to sensitive or unstable areas.

o More than 10% of skid trail surface length has ruts greater than 2 inches deep.

o Rills or sediment deposition extends more than 20 feet below waterbar outlet.

o More than 10% of waterbars fail to divert flow off skid trails or cableways

o Sediment movement into a riparian reserve.

o Presence of gullies (erosional features greater than 4” deep and 6”wide).

Landings

o Rills (greater than ½” deep and 10’ in length) or sediment deposition has extended

more than 20 feet off of landing.

o More than 1 cubic yard of material (from erosion or slope failure) has moved into

riparian reserve.

BMP Implementation and Effectiveness Monitoring, Water Quality Monitoring

Follow an enhanced BMPEP monitoring plan. Track implementation of all BMPs through the timber sale

administration program, via sale administrator’s daily diaries (SF-181s) and the standardized BMP

Page 13: Trinity County Collaborative Group - From Fire Kill to ...a123.g.akamai.net/.../11558/www/nepa/103383_FSPLT3_3083713.pdf · Geology Summary - prepared by: Fred S. Levitan, Six Rivers

13

implementation checklists. Document BMP monitoring locations on project maps and/or harvest cards.

Post-harvest, according to the monitoring schedule described below, monitor all potential project-

related sediment sources in the project area identified during BMP implementation monitoring (100%

BMPEP effectiveness monitoring). Intensively monitor site-specific areas where erosional problems

occur or BMP violations are observed, until the sites are in compliance with BMPs and are stabilized.

Prepare and submit a monitoring plan to the NCRWQCB for the project area. The plan will be developed

in cooperation with NCRWQCB representatives, and will fulfill the intent of preserving water quality in

the downstream watersheds, and correcting any potential sediment discharges or other threats to water

quality associated with the proposed action. The plan will include an Erosion Control Plan (ECP) for the

project area that identifies all Controllable Sediment Discharge Sources (CSDS) within the project area.

CSDS are defined as any sediment sources that 1) are anthropogenic in nature; 2) are actively

discharging or are capable of discharging to a watercourse; 3) can reasonably and feasibly be repaired.

This will include any project-related sediment sources as well as any identified legacy sediment sources

within the project area. The Plan will include:

o An ID number for CSDS.

o A map showing each site with its ID number.

o What the problem is at the site.

o The volume of potential sediment delivery if the site were to fail or erode. (This would equal the

sediment delivery prevented with site repairs.)

o The proposed repairs and a schedule for the repairs. Details of repair construction and timing

will be included, as best known at the time the plan is drafted. Repair scheduling will be

prioritized based on the severity and immediacy of potential sediment delivery.

o Per discussions with NCRWQCB representatives, the ECP may be developed iteratively,

presenting known CSDS and augmenting that information during subsequent project planning,

implementation, and monitoring visits. Monitoring visits will be conducted according to the

following schedule:

1. Prior to and during project implementation to discover and document existing sediment sources and

any that are unavoidably created during project operations, as well as to assist the sale administrator in

minimizing any sedimentation issues;

2. If there no operations outside the NOS, as anticipated: by November 15 to assure project areas are

secure for the winter; if there are operations outside the NOS: Immediately following cessation of

winter period operations to assure areas with winter activities are secure for the winter;

3.Once following ten (10) inches of cumulative rainfall commencing on November 15 and prior to March

1, if worker safety and access allows, and;

4. After April 1 and before June 15, or as soon as ground conditions allow, to assess the effectiveness of

management measures (BMPs) designed to address CSDS and to determine if any new sources have

developed.

Page 14: Trinity County Collaborative Group - From Fire Kill to ...a123.g.akamai.net/.../11558/www/nepa/103383_FSPLT3_3083713.pdf · Geology Summary - prepared by: Fred S. Levitan, Six Rivers

14

The monitoring plan, including the ECP, will be developed and presented to the NCRWQCB following

signing of the Decision Memo and prior to project implementation.

The Six Rivers National Forest shall provide the North Coast Regional Water Quality Control Board

(NCRWQCB) with any monitoring results requested, and shall allow NCRWQCB representatives access to

the project area at any time prior, during or following project implementation for the purposes of

collecting information applicable to the conditions of the Categorical Waiver for Discharges Related to

Timber Harvest Activities on Federal Lands Managed by the United States Department of Agriculture,

Forest Service (Order No. R1-2015-0021).

References

Cannon, Susan H., Joseph E. Gartner, Michael G. Rupert, John A. Michael, Alan H. Rea and Charles. 2010.

Predicting the probability and volume of post-wildfire debris flows in the intermountain western United

States. Geological Society of America Bulletin (2010), 122(1-2):127

Dumitru, T. A., J. Wakabayashi, J. E. Wright, and J. L. Wooden, 2010. Early Cretaceous transition from

nonaccretionary behavior to strongly accretionary behavior within the Franciscan subduction complex.

Tectonics 29, TC5001.

Levitan, Fred S. 2014. Thoughts on high severity fire, deep-seated landslides, and fuels treatments in the

Sims Fire restoration area. Unpublished white paper, USDA Forest Service, Eureka, CA.

McLaughlin, R.J., Ellen, S.D., Blake, M.C., Jayko, A.S., Irwin, W.P., Aalto, K.R., Carver, G.A., Clarke, S.H.,

Barnes, J.B., Cecil, J.D., and Cyr, K.A. 2000. Geology of the Cape Mendocino, Eureka, Garberville, and

southwestern part of the Hayfork 30 X 60 minute quadrangles and adjacent offshore area, northern

California, with digital database. Miscellaneous Field Studies Map MF-2336, US Geological Survey, Menlo

Park, California.

Mikulovsky, R. P.; de la Fuente, J. A.; Bell, A.; Stevens, M.; Levitan, F. 2012. Activation of Deep-Seated

Landslides in Northwestern California After Wildfires in 2006 and 2008. American Geophysical Union,

Fall Meeting 2012, abstract and poster.

USDA Forest Service BAER Team 2015. Burned-Area Report (FS-2500-8), Mad River Complex Fires,

September 9, 2015, unpublished internal report, USDA Forest Service, Eureka, CA.


Recommended