+ All Categories
Home > Documents > ts03F 01 lui ng kwong ppt 1286 - FIGPlacing of Surcharge and wait for Consolidation to complete 12...

ts03F 01 lui ng kwong ppt 1286 - FIGPlacing of Surcharge and wait for Consolidation to complete 12...

Date post: 25-Mar-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
6
Vincent LUI, Jacky NG (Leica Geosystems Ltd) Alan K.L. KWONG (Department of Civil Engineering, The University of Hong Kong) Reclamation Ground Settlement Monitoring by using GPS and other Technologies at Shenzhen Airport FIG Working Week 2007, Hong Kong 2 Background Current reclamation practices Dredging environmentally unfriendly Surcharging with Prefabricated Vertical Drains time consuming We need to strengthen soft marine clay in a friendly way, however Compaction, deep compaction, blasting environmentally unfriendly Deep cement and lime mixing, grouting and thermal modification costly Electro-osmosis ineffective 3 Background Objectives of this research To study technical feasibility of offshore vacuum preloading (under water for at least 2 3m), to see possibility of adopting existing approaches from onshore vacuum preloading (shallow water, usually 1m or less) to offshore vacuum preloading To study consolidation mechanism and representative stress path in vacuum preloaded clay Investigate new techniques for achieving the objectives above and using GPS & other technologies in monitoring ground settlement in this approach 4 Hong Kong has a Long History in Reclaiming Land 5 Example of a Reclamation Project in Hong Kong October 1995 December 1995 April 1996 October 1996 6 Major Factor to be Considered in Reclamation: Settlement of Soft Marine Mud (Clay)
Transcript
Page 1: ts03F 01 lui ng kwong ppt 1286 - FIGPlacing of Surcharge and wait for Consolidation to complete 12 Disadvantages of Pre-consolidation Process Cost of Wick Drains is high Construction

Vincent LUI, Jacky NG (Leica Geosystems Ltd)Alan K.L. KWONG (Department of Civil Engineering, The University of Hong Kong)

Reclamation Ground Settlement Monitoring by using GPS and other Technologies at Shenzhen AirportFIG Working Week 2007, Hong Kong

2

Background

Current reclamation practices

Dredging – environmentally unfriendly

Surcharging with Prefabricated Vertical Drains – time consumingWe need to strengthen soft marine clay in a friendly way,

howeverCompaction, deep compaction, blasting – environmentally

unfriendlyDeep cement and lime mixing, grouting and thermal

modification – costlyElectro-osmosis – ineffective

3

Background

Objectives of this research

To study technical feasibility of offshore vacuum preloading(under water for at least 2 – 3m), to see possibility of adopting existing approaches from onshore vacuum preloading (shallow water, usually 1m or less) to offshore vacuum preloading

To study consolidation mechanism and representative stress path in vacuum preloaded clay

Investigate new techniques for achieving the objectives above and using GPS & other technologies in monitoring ground settlement in this approach

4

Hong Kong has a Long History in Reclaiming Land

5

Example of a Reclamation Project in Hong Kong

October 1995 December 1995

April 1996 October 1996

6

Major Factor to be Considered in Reclamation:Settlement of Soft Marine Mud (Clay)

Page 2: ts03F 01 lui ng kwong ppt 1286 - FIGPlacing of Surcharge and wait for Consolidation to complete 12 Disadvantages of Pre-consolidation Process Cost of Wick Drains is high Construction

7

Two Conventional Methods in dealing with Settlement, by:

1. Removing the Soft Marine Mud (Clay) by Dredging and replacing it by Sand Fill

2. Expelling water in the Soft Marine Mud (Clay) by Installing Vertical Wick Drains and Pre-compressing it with heavy load (Pre-consolidation Process or Surcharging)

8

Disadvantages of Dredging

Adverse environmental impact to the marine ecology during the dredging process

Adverse environment impact to the nearby residents

Disposal of large volumes of marine mud (Diminishing of dumping ground)

Unnecessary large consume natural resources – The more is dredged, the more is the volume of sand required for filling. The more is the sand required for filling, the more dredging is required for sand borrowing.

9

Mud plumes from dredging

10

Pre-consolidation Process or Surcharging

Cross-section of reclamation

Wick drainMarine Mud

Desired Formation Level

11

Placing of Surcharge and wait for Consolidation to complete

12

Disadvantages of Pre-consolidation Process

Cost of Wick Drains is highConstruction and removal time of surcharge is more than 2 yearsLarge volume of sand is required to be moved on and off sitePossible failure if surcharge is constructed too fastQuality of wick drains is difficult to control

Page 3: ts03F 01 lui ng kwong ppt 1286 - FIGPlacing of Surcharge and wait for Consolidation to complete 12 Disadvantages of Pre-consolidation Process Cost of Wick Drains is high Construction

13

Set up a Project – and its principle objectives

To investigate a practical “offshore” vacuum suction techniquethat could replace conventional dredging such that environmental problems related to reclamation could be completely eliminated

To establish rational design and construction guidelines for improving the strength of soft marine clay in Hong Kong

To demonstrate the feasibility of the technique in Hong Kong waters by conducting and monitoring large-scale field tests

Introduce GPS in the monitoring task and compare the result against conventional manual leveling & geotechnical sensor measuring method.

14

Previous “Onshore” Vacuum Preloading Technique applied in Tianjin (�� ) and Qiandao (��) Harbor Area (shallow water)

Site visits with Tianjin University (����) and Ocean University of China (������) in August 2003

15

Test Site – an area close to Shenzhen Airport

16

Setup vacuum preloading

ClaySoftPermeableLow

Sand Cushion Geomembrane Vacuum PumpDrainpipe

Vertical Drains

17

Test Site – apply vacuum suction and installed instruments

18

Test Site – Apply vacuum suction over water

Page 4: ts03F 01 lui ng kwong ppt 1286 - FIGPlacing of Surcharge and wait for Consolidation to complete 12 Disadvantages of Pre-consolidation Process Cost of Wick Drains is high Construction

19

Installation of instruments: Monitoring Program

Settlement Plate

GPS Antenna

Inclinometer

ExtensometerPiezometerVacuum Sensor

LEGEND

23m 22m 2.5m

A A

Area Covered WithGeomembrane

20

Vertical section of instrumentation installation

0

1m

2m

3m

4m

5m

6m

7m

8m 8m

7m

6m

5m

4m

3m

2m

1m

0

Vacuum SensorPiezometerExtensometer

Inclinometer

GPS Antenna

Settlement Plate

Geomembrane

Firm Stratum

Sand Cushion

LEGEND

Water Surface

Water

A - A Section

LowPermeable

SoftClayLayer

21

Settlement monitoring by conventional manual leveling

Settlement Plate

gradienter(level instrument)

Sopwith StaffSopwith Staff

Steady Point(reference point)

22

Settlement Monitoring by GPS – WHY ?

Absolute 3D coordinates measurement including height

All weather operation

high measurement rate – up to 20Hz is possible

Real-time result presentation

synchronized measurement –provide timing for other sensors

Good for area that is difficult to access regularly

can measure over long baselines

low maintenance and a long service life

23

Advanced GPS Monitoring Principle Real-time / Post-processing is possible

Double check of the positioning results

ReferenceStation 1.

Reference station 2.

Monitoring point

Monitoring point

The baseline between the reference stations can also be monitored to check

their long term stability.

24

Selecting the ideal GPS monitoring receiver GMX901 vs GMX902 vs GRX1200 GG ProSelect the GMX901 when you need:

Lowest cost, single frequency12 channels L11Hz data ratePost processing, short baselines (<10km)

Select the GMX902 when you need:Low cost, dual frequency, PPS12 channels L1 + L2High speed (20Hz)Real time, long baselines

Select the GRX1200 GG Pro when you need:72 channels GPS + GLONASSHigh speed (20Hz)Onboard logging, web interface

Page 5: ts03F 01 lui ng kwong ppt 1286 - FIGPlacing of Surcharge and wait for Consolidation to complete 12 Disadvantages of Pre-consolidation Process Cost of Wick Drains is high Construction

25

GPS Monitoring SolutionsGPS Management and Processing Software

Leica GPS Spider v2.0 Positioning is the most flexible application software for managing GPS receivers and centrally processing all combination of baselines at high rates (up to 20Hz) with the highest accuracy in both real time and post-processing.

The results are streamed out through serial ports, TCP-IP ports, files or to an SQL database in various formats like the well known NMEA format for interfacing with analysis software.

RINEX files can be generated from the real time data stream or by periodical downloading for post processing, archive or in-depth studies of multi-path effects and other investigations.

26

GPS Monitoring Result Analysis

High Speed AnalysisData input from NMEA GGA , GGQ and LLQ data stream, files and Spider Post Processing database

High speed (20Hz) data and graphing of data from serial and TCP/IP

Limit Checks and MessagingThree levels of absolute limit checks for each of longitudinal, transverse, height, 2D and 3D displacement

Messaging (email, SMS, external applications)

Site AssessmentQuality check of raw GPS observations

Multipath and SNR analysis

The Plot View tab showing a real time graph of height displacement for three NMEA data streams output by

Leica GPS Spider Positioning Products

27

Advanced GPS Processing with GPS Spider

Direct power supply (220v)

Reference Station(s)

GPS Spider

LANNMEAX,Y,Z

Monitoring Point Monitoring Point

Power Supply / Solar panel

Radio Modem, GSMWireless LAN

Cable (RS232, RS485)

Real time, permanent connection

orPeriodic downloading for

post processing (using GRX receiver)

GMX901 or GMX902 or GRX1200 receiver

GMX901/GMX902 GMX901/GMX902

-Profiling

-Limit checks

-Messaging

-Analysis

-GPS computation

-Raw data archiving

-Sensor configuration

GNSS QC

Other Sensors

GeoMoS

Power Supply / Solar panel

28

GPS receivers operation – overcame problem of manual leveling in inaccessible areas

29

Data Collection and Remote Data TransferSolar Panel

Battery

Datalogger

Modem

Antenna

Sensor Cables

Equipment Shed

Wireless

Modem link

30

Results: vacuum pumps

Vacuum Pump

- 100

- 80

- 60

- 40

- 20

0

20

40

10- 26- 06 11- 10- 06 11- 25- 06 12- 10- 06 12- 25- 06 1- 9- 07 1- 24- 07

Dat e

Vacu

um P

ress

ure(

kPa)

57372

57373

57374

Page 6: ts03F 01 lui ng kwong ppt 1286 - FIGPlacing of Surcharge and wait for Consolidation to complete 12 Disadvantages of Pre-consolidation Process Cost of Wick Drains is high Construction

31

Results: Surface Settlement

WaterSand CushionGeomembrane

0

100

200

300

400

500

600

700

800

-30 -20 -10 0 10 20 30

Set

telm

ent(m

m)

2006-11-22006-11-172006-12-22006-12-172007-1-22007-1-19

Distance(m)

CenterLift Right

32

Results: Leveling vs GPS measurement

-1.18

-1.15

-1.12

-1.09

-1.06

-1.03

-11-16-07 1-21-07 1-26-07 1-31-07 2-5-07

Date

Hei

ght(m

)

-1.1

-1-0.9

-0.8

-0.7-0.6

-0.510-30-06 11-22-06 12-15-06 1-7-07 1-30-07

Date

Hei

ght(m

)

GPS

Settlement Plateat center

0

150

300

450

600

750

10-10-06 11-9-06 12-9-06 1-8-07 2-7-07

Date

Sette

lmen

t(mm

)

100 mm

100 mm

Manual Leveling

GPS Leveling

33

Summary

Full-scale fully instrumented field test has shown that offshore vacuum preloading is feasible.

GPS monitoring result agreed very well with the conventional leveling measurement.

GPS proves to be operating in all weather condition and suitable in operating in difficult access location.

Remote wireless instrumentation and GPS provided movement measurements in inaccessible areas.

Many Thanks for Your Attention.


Recommended