+ All Categories
Home > Documents > TULIP GROVE ELEMENTARY SCHOOL · 2016-09-15 · TULIP GROVE ELEMENTARY SCHOOL Good afternoon...

TULIP GROVE ELEMENTARY SCHOOL · 2016-09-15 · TULIP GROVE ELEMENTARY SCHOOL Good afternoon...

Date post: 18-Jun-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
6
TULIP GROVE ELEMENTARY SCHOOL Good afternoon Community of Tulip Grove, Welcome back to a new school year and hope you had a great summer! The purpose of this newsletter is to provide an update to the Tulip Grove Community regarding the status of the Major Renovation & Addition project. Phases 1 and 2 have been completed and communicated in previously issued newsletters. This update will focus on the 3 rd phase leading up to Construction. During this phase, our project goals were to receive State approval for the project to proceed into procurement, procurement and successful award of the construction team, PGCPS Board approval for contract award, State approval for contract award, DPIE issuance of permit approval for construction, and the commencement of construction. Although there have been some successfully completed critical activities, we have incurred a couple challenges through-out this phase that will have an impact on the project schedule and delayed the commencement of construction. STATE CD DESIGN APPROVAL As a requirement by the state, all construction projects over $350,000 are required to submit numerous design submissions for review and approval prior to proceeding to procurement and finalizing contract award. The State’s design review process is typically 6 weeks per submission. After nearly 7 months of review, the project received approval from the state to proceed to procurement in April. The state’s approval was contingent upon the design team incorporating the state’s comments within an updated bid set package prior to issuance to bid. The design team work feverishly to provide this updated bid set to PGCPS Department of Capital Programs for review, acceptance, and issuance to procurement in May. Procurement After receiving approval from the state, the project was finally able to proceed into procurement. The project was submitted to PGCPS Department of Purchasing and Supply Services to procure the services of a contractor to construct the TGES Major Renovation and Addition project. The solicitation was issued to bid on June 7th, with the bid opening scheduled for July 11 th . Due to the amount of bid clarifications and addenda issued, the decision was made to extend the bid opening date to July 20 th . The extension was provided to allow sufficient time for the contractors to review the clarifications and make adjustments to their proposals, but meant the project couldn’t be submitted to the Board for contract award approval during the scheduled July 19 th Board meeting. On July 20 th , the bid opened resulting in two responsive bids, Tuckman-Barbee Construction Company, Inc. and Keller Brothers, Inc. After review, PGCPS Department of Capital Programs identified Tuckman-Barbee Construction Company as the Lowest Responsive Bidder and submitted our recommendation for contract award to the Board for final approval during the scheduled August 25 th Board meeting. A few days after the contract award submission to the Board, PGCPS Department of Purchasing and Supply received a “Request to Withdraw Bid” letter from Tuckman-Barbee, the successful lowest responsive bidder. Upon meeting with the contractor, it was determined their original bid was substantially low due to a bid calculation error. As a result of this error, both contractors were given the opportunity to submit their “Best and Final Offer” for final review and acceptance on August 15, 2016, resulting in Tuckman-Barbee being the lowest responsive bidder. After Tuckman-Barbee’s BAFO was received and again determined to be the lowest responsive bid, the contract award submission to the Board was amended to include the revised pricing and was scheduled to be approved during the August 25 th Board meeting. The morning of August 25 th , PGCPS Department of Purchasing and Supply Services received a letter from Keller Brothers, Inc. protesting the contract award of TGES Major Renovation and Addition project to Tuckman-Barbee Construction Company, Inc. Immediately, PGCPS Capital Programs department was informed and forced to withdraw the contract award from the Board’s agenda scheduled to be approved later that night. The result of past bid protests of other projects resulted in contract awards being placed on hold for weeks, with the final outcome requiring the solicitation to be re-advertised. Based on past history, our department has decided to cancel the contract award and proceed with reissuing the solicitation for bid. While not an easy decision, we feel it is in the best interest of the project, TGES community, and PGCPS. By re-advertising the solicitation, we anticipate generating additional contractor’s interest to competitively bid this great project. Major Renovation Quarterly Update | 9/12/2016 3 RD PHASE PROJECT SUMMARY
Transcript
Page 1: TULIP GROVE ELEMENTARY SCHOOL · 2016-09-15 · TULIP GROVE ELEMENTARY SCHOOL Good afternoon Community of Tulip Grove, Welcome back to a new school year and hope you had a great summer!

TULIP GROVE ELEMENTARY SCHOOL

Good afternoon Community of Tulip Grove,

Welcome back to a new school year and hope you had a great summer! The purpose of this newsletter is to provide an update to the Tulip Grove Community regarding the status of the Major Renovation & Addition project. Phases 1 and 2 have been completed and communicated in previously issued newsletters. This update will focus on the 3rd phase leading up to Construction.

During this phase, our project goals were to receive State approval for the project to proceed into procurement, procurement and successful award of the construction team, PGCPS Board approval for contract award, State approval for contract award, DPIE issuance of permit approval for construction, and the commencement of construction. Although there have been some successfully completed critical activities, we have incurred a couple challenges through-out this phase that will have an impact on the project schedule and delayed the commencement of construction.

STATE CD DESIGN APPROVAL

As a requirement by the state, all construction projects over $350,000 are required to submit numerous design submissions for review and approval prior to proceeding to procurement and finalizing contract award. The State’s design review process is typically 6 weeks per submission. After nearly 7 months of review, the project received approval from the state to proceed to procurement in April. The state’s approval was contingent upon the design team incorporating the state’s comments within an updated bid set package prior to issuance to bid. The design team work feverishly to provide this updated bid set to PGCPS Department of Capital Programs for review, acceptance, and issuance to procurement in May.

Procurement After receiving approval from the state, the project was finally able to proceed into procurement. The project was submitted to PGCPS Department of Purchasing and Supply Services to procure the services of a contractor to construct the TGES Major Renovation and Addition project. The solicitation was issued to bid on June 7th, with the bid opening scheduled for July 11th. Due to the amount of bid clarifications and addenda issued, the decision was made to extend the bid opening date to July 20th. The extension was provided to allow sufficient time for the contractors to review the clarifications and make adjustments to their proposals, but meant the project couldn’t be submitted to the Board for contract award approval during the scheduled July 19th Board meeting.

On July 20th, the bid opened resulting in two responsive bids, Tuckman-Barbee Construction Company, Inc. and Keller Brothers, Inc. After review, PGCPS Department of Capital Programs identified Tuckman-Barbee Construction Company as the Lowest Responsive Bidder and submitted our recommendation for contract award to the Board for final approval during the scheduled August 25th Board meeting.

A few days after the contract award submission to the Board, PGCPS Department of Purchasing and Supply received a “Request to Withdraw Bid” letter from Tuckman-Barbee, the successful lowest responsive bidder. Upon meeting with the contractor, it was determined their original bid was substantially low due to a bid calculation error. As a result of this error, both contractors were given the opportunity to submit their “Best and Final Offer” for final review and acceptance on August 15, 2016, resulting in Tuckman-Barbee being the lowest responsive bidder. After Tuckman-Barbee’s BAFO was received and again determined to be the lowest responsive bid, the contract award submission to the Board was amended to include the revised pricing and was scheduled to be approved during the August 25th Board meeting.

The morning of August 25th, PGCPS Department of Purchasing and Supply Services received a letter from Keller Brothers, Inc. protesting the contract award of TGES Major Renovation and Addition project to Tuckman-Barbee Construction Company, Inc. Immediately, PGCPS Capital Programs department was informed and forced to withdraw the contract award from the Board’s agenda scheduled to be approved later that night. The result of past bid protests of other projects resulted in contract awards being placed on hold for weeks, with the final outcome requiring the solicitation to be re-advertised. Based on past history, our department has decided to cancel the contract award and proceed with reissuing the solicitation for bid. While not an easy decision, we feel it is in the best interest of the project, TGES community, and PGCPS. By re-advertising the solicitation, we anticipate generating additional contractor’s interest to competitively bid this great project.

Major Renovation Quarterly Update | 9/12/2016

3RD PHASE PROJECT SUMMARY

Page 2: TULIP GROVE ELEMENTARY SCHOOL · 2016-09-15 · TULIP GROVE ELEMENTARY SCHOOL Good afternoon Community of Tulip Grove, Welcome back to a new school year and hope you had a great summer!

PGCPS Board Approval

As a result of the bid protest by Keller Brothers, Inc., PGCPS Department of Capital Programs was forced to remove and cancel the Construction Contract Award BAS scheduled for approval during the board meeting. After the project is advertised and a successfully awarded contractor is identified, the contract award will be re-submitted to the board for approval.

Permitting

Initially submitted in October, the project has received permit approval and is ready for issuance. Upon successful contract award for construction services, the permit will be issued to begin construction.

IAC Contract Award Approval

As a requirement by the state, all construction projects receiving state funding are required to receive contract award approval from the state, prior to finalizing contract award and proceeding into construction. After the project is advertised and a successfully awarded contractor is identified, the contract award will be submitted to the state for approval.

PROJECT UPDATE SUMMARY The project has incurred some critical delays in the 3rd phase as a result of the bid protest for contract award. Taking advantage of this opportunity, Capital Programs is working to modify and reissue the solicitation to help develop additional interest of qualified contractors to competitively bid on the project. The anticipated date for bid opening is scheduled for December with PGCPS Board and State approval expected by February 2017. While the start of construction is delayed, the project is on pace to be delivered for the start of the 2018 school year. Thank you in advance for your continued support of the Tulip Grove Major Renovation & Addition project. PROJECT FUN FACTS • The original school was built in 1964. • Total sq.ft. of Existing Building – 42,275 sq.ft. • Total sq.ft. to be Renovated – 28,588 sq.ft. • Total sq.ft. of New/Addition – 41,480 sq.ft. • Total sq.ft. to be Demolished – 12,976 sq.ft. • Project Budget has been $22,900,000 since approval in 2013.

UPCOMING 3RD PHASE MILESTONES

CRITICAL MILESTONES

IFB BID OPENING AWARD DEC 16

BOARD AWARD APPROVAL JAN 17

IAC CONTRACTOR AWARD FEB 17

CONSTRUCTION FEB 17

SCHOOL OPENING SEP 18

Prince George’s County Public Schools Department of Capital Programs Will Smith Project Management Supervisor

MAJOR RENOVATION UPDATE PAGE 2

Page 3: TULIP GROVE ELEMENTARY SCHOOL · 2016-09-15 · TULIP GROVE ELEMENTARY SCHOOL Good afternoon Community of Tulip Grove, Welcome back to a new school year and hope you had a great summer!
Page 4: TULIP GROVE ELEMENTARY SCHOOL · 2016-09-15 · TULIP GROVE ELEMENTARY SCHOOL Good afternoon Community of Tulip Grove, Welcome back to a new school year and hope you had a great summer!
Page 5: TULIP GROVE ELEMENTARY SCHOOL · 2016-09-15 · TULIP GROVE ELEMENTARY SCHOOL Good afternoon Community of Tulip Grove, Welcome back to a new school year and hope you had a great summer!
Page 6: TULIP GROVE ELEMENTARY SCHOOL · 2016-09-15 · TULIP GROVE ELEMENTARY SCHOOL Good afternoon Community of Tulip Grove, Welcome back to a new school year and hope you had a great summer!

Recommended