Date post: | 25-Jan-2019 |
Category: |
Documents |
Upload: | hoangtuong |
View: | 216 times |
Download: | 0 times |
RAMI methods for DEMO development
Euratom-Tekes 2013 Annual Seminar27-28 May 2013, M/S Silja Serenade
Risto Tuominen & Toni AhonenVTT Technical Research Centre of FinlandRisk and Reliability Management
230/05/2013
RAMI in EFDA/DEMO Work Programmes PPPT WP12-DTM-02: Reliability Growth and Risk Minimisation of In-vessel Components
PPPT WP13-DTM-02: Reliability, Availability, Maintainability & Inspectability (RAMI)
- 1 ppy (PS) + 0.5 ppy (BS)- CCFE (UK)- ENEA (Italy)- CIEMAT (Spain)- VTT/Tekes- LEI (Lithuenia)- IST (Portugal)
- 4/2012 →
- 2 ppy (PS) - CCFE (UK)- ENEA (Italy)- CIEMAT (Spain)- VTT/Tekes- LEI (Lithuenia)
- 4/2013 →
330/05/2013
Motives for the WP Task dedicated to RAMI
DEMO builds the bridge from experimental fusion facilities to first fusionpower plant (FPP)
DEMO is expected to show FPP being an commercially feasible & environmentally justifiable power source
Availability (A) is a primary measure of effectiveness for a FPP and directly affects the cost of generated electricity:
CAC, COM, CF, etc. are the annualized costs of plant acquisition, operation & maintenance, fuel, etc; PE is the net electrical power produced to the grid; A is the plant availability for production
430/05/2013
Motives for the WP Task dedicated to RAMI
(Operational) availability is intrinsically dependant on three qualities of the plant that are driven by design and technology choices: Reliability – impacts tUDT
Maintainability – impacts tSDT & tUDT
Inspectability – impacts tSDT & tUDT
Maintenance support performance – impacts tSDT & tUDT
These qualities can obviously be traded-off against each other, or against other measures of plant effectiveness, for example:
– Less reliability may be acceptable if maintainability is improved– Improved inspectability may allow less maintenance– Lower performance required may provide higher reliability,– etc.
530/05/2013
Motives for the WP Task dedicated to RAMI
Thus RAMI is very much a Systems Engineering issue that cannot be considered in isolation
formal RAMI program with associated processes, tools and methodsthat is strongly integrated in the DEMO development & design process from the start
building on the RAMI knowledge available from previous fusion programs (JET, Tore Supra, ITER, IFMIF, etc.), and the experience from other fields of technology
responding to the challenges that switching from experimental facilities to a power producing plant, technology scale up, and novelty / first-of-kind plant introduce
noticing the uncertainties arising from gaps in knowledge/experience and how they affect the confidence of RAMI predictions
focus on reactor systems and components
safety excluded from the scope (considered in own WP)
630/05/2013
RAMI Management Process for DEMO iterative process over DEMO life; progressing in parallel to development/design
activities
730/05/2013
RAMI requirements analysis & allocation
approach for allocation of initial availability targets to the systems of DEMO consistent with the overall plant operational availability target.
CCFE 2012
830/05/2013
Top-down availability apportionment methodologybased on expert judgment
CCFE 2012
930/05/2013
Tranferring the initial availability targets into R, M & I requirements
1030/05/2013
RAMI input data for assessments
many DEMO systems ”first-of-kind”, or represent large scaling in performance demands from existing equipment
need to collect and integrate reliability data from a diverse range of sources of varying quality and relevance to the analysis case
expert judment has also an important role as source of data confidence in expert judgment data requires the use of formal methods
and transparency of the EJ procedure
1130/05/2013
RAMI input data for assessments
WP13-T02-1 (VTT): Specification of structured expert judgment methods for producing RAMI input data for DEMO systems consolidate previous work & experience on EJ methods, relevant standards establish preferred methods and guidelines for expert data elicitation, aggregation
and evaluation
T02-2: Specification of agreed/standard approaches for integration of data from different sources evaluation of subjective and objective information fusion methods; special attention for Bayesian methods (with theoretical justifications of use in small
sample cases) in collaboration with ENEA and LEI
LEI 2013
1230/05/2013
Fusion Component Failure Rate Database (FCFRDB)
ENEA compiled and maintained database for F4E and ITER organizations
comprises more than 4000 records reporting failure rate (and MDTF) data for components in fusion systems no data records on RH systems are currently available
Available on-line http://fus-se.frascati.enea.it:8080/Enea access is restricted to users operating in fusion field, typically for ITER access requires a granted User account
Merges data from several: plants (Europe - JET, TLK, Tore Supra, Asdex-U; USA - INL, DIII-D,
TFTR&NSTX, TSTA; Japan - TPL) report sources ( ENEA, INEL, EIReDA, IAEA TECDOC, IFMIF Data, OREDA,
WASH1400, etc.)
1330/05/2013
Using FCFRDB to estimate component FR
ENEA 2013
1430/05/2013
Using FCFRDB for estimating component FR
1530/05/2013
Reliability and availability growth
Reliability/availability of developmental systems is typically not constant but follows a reliability (maturity) growth curve with initial reliability/availability, some characteristic reliability/availability growth rate, and mature reliability/availability (i.e. the ultimate operating reliability/availability)
For a novel system: What is a realistic initial availability that can be expected? What is a realistic mature availability that can/could be achieved? What is a realistic growth rate?
1630/05/2013
Reliability and availability growth
initial reliability is highly dependent on novelty in the design and the associated potential for unexpected failure modes (i.e. “knowledge-based failures”) the growth rate depends on novelty of the system (i.e. initial number and
types of defects) and the nature of tests and operations to reveal the defects and get them successfully resolved. mature reliability is highly dependent on complexity of the design –
simple designs have less opportunity for “process-based failures”
in a mature system the “knowledge-based failures” are practically eliminated and outweighed by “process-based failures”, that is, by random failures due to variations inherent to manufacturing, assembling, maintenance, and operating processes and environment.
1730/05/2013
Reliability and availability growth most early fission power plants began their operational lives with low availability values in
the 30% range the yearly on-line time then gradually improved into the 70% range modern fission plants now have availability averages in the 80 – 90% range
Fragola & Morse, 2012JET Neutral Beam Injectors (NBI)(Pinna et al. 2007)
Design defects &random failures Merely random failures
1830/05/2013
Defect model for reliability growth
The total uncertainty regarding the system reliability estimate regarding LOM events (at operation cycle N) is a combination of the uncertainty on the initial number of defects and the uncertainty associated with the growth model parameters λ and τ, υ, φ, γ, the latter depending on the specifics of the risk mitigation /management program implemented in the development process.
(Fragola & Morse, 2012)
1930/05/2013
Reports and papers:
Tuominen R., Ahonen T.; WP12-DTM02-REL-D04: RAMI assessmentmethodology for DEMO. IDM reference: EFDA_D_2GDFNJ. 64 p.
Ahonen T., Tuominen R.; WP12-DTM02-REL-D05: Evaluation of RAMI tools for DEMO. IDM reference: EFDA_D_2HCYBN. 23 p.
T. Pinna (ENEA), R. Tuominen, M. Siuko; WP11-DAS-RH-08-ENEA/TEKES: Outlines for the definition of RAMI guidelines for DEMO systems. IDM reference: EFDA_D_2KVG3G. 36 p.
Pinna, T. (ENEA), Tuominen, R. (VTT); Outlines of RAMI Guidelinesfor DEMO Systems. Paper presented in PSAM 11 & ESREL 2012 Conference, Helsinki, Finland, 25 - 29 June 2012. 10p.
2030/05/2013
VTT creates business from technology
2130/05/2013
Reliability/Availability assessment methodology
2230/05/2013
Motives for the WP Task dedicated to RAMI
(Operational) availability refers to the “fraction of total time that an item is able to operate as intended”, and can be calculated as:
top is the plant online time (i.e. mean up-time), tsdt is the scheduled down time and tudt is the unscheduled down time
IST 2012
2330/05/2013
Motives for the WP Task dedicated to RAMI
DEMO to build the bridge from experimental fusion facilities to first fusionpower plant (FPP)
DEMO is expected to show FPP being an commercially feasible & environmentally justifiable power source
FPP will have to be competitive with other available energy technologies on cost of generating electricity – currently ~2 to 7¢/kWh
socio-economic situationin 2030 ?
Harman, 2012
2430/05/2013
2530/05/2013
In operations and support: i d l f i d f ili i f RAMI bili
During realization and installation: control quality in manufacturing and installation so that the inherent RAMI qualities of
the design are not degraded
During plant development/engineering design phase: optimise RAMI qualities of sub-system designs (trade-off studies) verify design compliance with corresponding RAMI requirements & higher level targets
During pre-conceptual and conceptual design phases: understand the rationale of plant, operation & functions, and RAMI targets deduce initial RAMI requirements and constraints for the different systems/sub-systems identify key areas for R&D, to control progress & status
RAMI Management Process for DEMO
2630/05/2013
Reliability and availability growth
initial reliability is highly dependent on novelty in the design and the associated potential for unexpected failure modes (i.e. “knowledge-based failures”) reliability can be improved when the initial deficiencies in the design, the
manufacturing processes and the interactions with the operating environment get revealed by anomalies and failures in testing and/or operation, and are resolved. the growth rate depends on novelty of the system (i.e. initial number and
type of defects) and the nature of tests and operations. in a mature system the “knowledge-based failures” are practically
eliminated and outweighed by “process-based failures”, that is, by random failures due to variations inherent to manufacturing, assembling, maintenance, and operating processes and environment. mature reliability is highly dependent on complexity of the design -
simple designs have less opportunity for “process-based failures”