Tutorial
Copyright © 2000 - 2009 BRainTool Software GmbH
Start
2 of 99
1. What is A-Plan for Windows?
2. Range of applications3. Help4. How data is displayed5. Organizing your data6. Creating the project
structure7. Allocating resources /
Working times8. Scheduling tasks
0. Contents
9. Linking tasks10. Additional entry fields11. Printing12. Filters13. Options / Profiles14. Automated scheduling15. Others
3 of 99
1. What is A-Plan for Windows?
A-Plan for Windows is an easy-to-learn planning program which may be used for a variety of applications and tasks due to its high flexibility.
A-Plan for Windows is an inexpensive alternative to conventional project planning software which is far too complex for many applications and therefore hard to learn and handle.
A-Plan for Windows is suitable for project planning as well as for tasks such as:• Resource and capacity planning• Cost planning• Scheduling• Task management • Allocation of rooms and buildings• Holiday planning
A-Plan for Windows has been licensed for more than 90,000 users (as of Apr., 2009).
4 of 99
1. What is A-Plan for Windows?
2. Range of applications
3. Help4. How data is displayed5. Organizing your data6. Creating the project
structure7. Allocating resources /
Working times8. Scheduling tasks
0. Contents
9. Linking tasks10. Additional entry fields11. Printing12. Filters13. Options / Profiles14. Automated scheduling15. Others
5 of 99
Project planning
2. Range of applications
6 of 99
2. Range of applications
Project planning Resource and capacity planning
7 of 99
2. Range of applications
Project planning Resource and capacity planning Production planning
8 of 99
2. Range of applications
Project planning Resource and capacity planning Production planning Cost planning
9 of 99
2. Range of applications
Project planning Resource and capacity planning Production planning Cost planning Assignment of rooms and buildings
10 of 99
2. Range of applications
Project planning Resource and capacity planning Production planning Cost planning Assignment of rooms and buildings Absence of resources
11 of 99
1. What is A-Plan for Windows?
2. Range of applications3. Help4. How data is displayed5. Organizing your data6. Creating the project
structure7. Allocating resources /
Working times8. Scheduling tasks
0. Contents
9. Linking tasks10. Additional entry fields11. Printing12. Filters13. Options / Profiles14. Automated scheduling15. Others
12 of 99
3. Help- Tooltips
Short description of buttons („Tooltips“)
13 of 99
3. Help
– bottom line
Short description of the functions available at the current position of the mouse pointer
14 of 99
3. Help – direct help 1
Clicking on the button „Direct help“ ...
15 of 99
3. Help – direct help 2
... and clicking on any A-Plan element afterwards (the Gantt chart in this example) ...
16 of 99
3. Help – direct help 3
... will automatically display the respective chapter of the online help file.
17 of 99
1. What is A-Plan for Windows?
2. Range of applications3. Help4. How data is
displayed5. Organizing your data6. Creating the project
structure7. Allocating resources /
Working times8. Scheduling tasks
0. Contents
9. Linking tasks10. Additional entry fields11. Printing12. Filters13. Options / Profiles14. Automated scheduling15. Others
18 of 99
4. How data is displayed – levels
Break activities down to as many as 99 levels
Level 1 („Folder“)
Level 2 („Project“)
Level 3 („Task“)
Level 4 („Task“)
Level 5 („Task“)
19 of 99
4. How data is displayed – task table
Task table:- Have up to 65 different columns displayed or hidden as you like
- Set the sequence, width and title of columns to suit your needs
20 of 99
4. How data is displayed - select the columns displayed in the main table
Right-click on the headline ...
... to have the Options dialogue box displayed with all columns existing in A-Plan.
•Double-click on the designation to edit it
•Double-click on the designation to edit it
•Make column visible yes/no
•Make column visible yes/no
•Choose the number of fixed columns, i.e. which do not disappear when scrolling in the main table
•Choose the number of fixed columns, i.e. which do not disappear when scrolling in the main table
•Adjust the position of the selected column
•Adjust the position of the selected column
21 of 99
4. How data is displayed – expanded levels
Rows containing subtasks can be expanded ...
22 of 99
4. How data is displayed – collapsed levels
Expand allCollapse all
… or collapsed
23 of 99
4. How data is displayed – number of subtasks
Figures given in parentheses indicate the number of included subtasks
24 of 99
4. How data is displayed – Gantt chart
The Gantt chart (calendar in landscape view) shows the project schedule as a sequence of task bars.
25 of 99
4. How data is displayed – Gantt chart settings 1
The Gantt chart can be displayed in 16 resolutions ranging from one year ...
26 of 99
4. How data is displayed – Gantt chart settings 2
... down to 10 minutes per calendar interval
27 of 99
4. How data is displayed – Gantt chart settings 3
Setting the left margin of the Gantt chart to determine the starting date of the displayed calendar.
Show Current Day
28 of 99
4. How data is displayed – resources 1
Have your resources displayed in the lower half of the A-Plan window
29 of 99
4. How data is displayed – resources 2
Tasks allocated to resource Stevens
30 of 99
4. How data is displayed – resources 3
100% capacity usage
Capacity not yet allocated
Resource is absent with no capacity allocated
Although allocated, resource is absent
50% capacity usage
Resource is overallocated
Activate the option Show working times and capacities in task bars (see „Screen setup“ / „Task bars“) to have the time bars displayed.
Activate the option Show working times and capacities in task bars (see „Screen setup“ / „Task bars“) to have the time bars displayed.
31 of 99
1. What is A-Plan for Windows?
2. Range of applications3. Help4. How data is displayed5. Organizing your
data6. Creating the project
structure7. Allocating resources /
Working times8. Scheduling tasks
0. Contents
9. Linking tasks10. Additional entry fields11. Printing12. Filters13. Options / Profiles14. Automated scheduling15. Others
32 of 99
5. Organizing your data
– multiple project planning
Each folder of an A-Plan database is capable of holding up to 32,000 projects.
As a consequence, projects related to different topics may all be planned in one database and resources can be allocated to several projects of the database.
33 of 99
5. Organizing your data – filters / access permissions
A variety of filters and access permissions enable you to have the data of interest displayed only and to prevent unauthorized users from making changes.
A variety of filters and access permissions enable you to have the data of interest displayed only and to prevent unauthorized users from making changes.
34 of 99
5. Organizing your data
– archiving completed projects
A-Plan allows you to cut completed projects and paste them into another (= archive) database. This is done most easily by starting A-Plan a second time and opening the archive database.
Just select (1) and cut (2) the completed project from the current database. Then, select a folder in the archive database (3) and paste (4) the project you cut into the selected folder.
Any other database may be used as an archive. To create an archive database, just use „Save as...“ to have a copy of the current database saved under a new name.
(1)
(2)
(3)
(4)
35 of 99
5. Organizing your data
– master templates
(1)
(2)
(3)
(4)
Use a third database to create master project templates to avoid the need of starting new projects from scratch.
When starting a new project, just copy a template from the master into the current database. This will save you a lot of work.
To adjust the dates of an entire project, just select the row representing the highest project level and choose the command Postpone dates.
36 of 99
5. Organizing your data
- adjusting the time range when using templates
Adjusting the time range when starting a new project from an inserted template is quite easily - just select the top project row and choose the command Postpone Date... :
You may choose from the following options:• Either enter the requested amount of time or• Have the postponement calculated by A-Plan by
specifying, for example, the begin of the former project („Starting date“) and of the new project („Target date“).
You may choose from the following options:• Either enter the requested amount of time or• Have the postponement calculated by A-Plan by
specifying, for example, the begin of the former project („Starting date“) and of the new project („Target date“).
37 of 99
1. What is A-Plan for Windows?
2. Range of applications3. Help4. How data is displayed5. Organizing your data6. Creating the
project structure7. Allocating resources /
Working times8. Scheduling tasks
0. Contents
9. Linking tasks10. Additional entry fields11. Printing12. Filters13. Options / Profiles14. Automated scheduling15. Others
38 of 99
6. Creating the project structure
– create a database
...creates a new database.
Click on „No“.
39 of 99
6. Creating the project structure
– give the database a name
Choose „Save as...“ …
… and type the database name
40 of 99
6. Creating the project structure – insert a folder
Click on New Row on Level 1 (folder) (or use the keyboard shortcut Ctrl+F1)
41 of 99
6. Creating the project structure – enter a folder name
Type the folder name
42 of 99
6. Creating the project structure – insert a project
Click on New Row on Level 2 (project) (or use the keyboard shortcut Ctrl+F2)
43 of 99
6. Creating the project structure – enter a project name
Type the project name
All your entries are saved immediately (to ensure that all database users are always provided with the latest version of the data contained in the database).
For this reason, you do not need to save your data manually!
All your entries are saved immediately (to ensure that all database users are always provided with the latest version of the data contained in the database).
For this reason, you do not need to save your data manually!
44 of 99
6. Creating the project structure – insert a task
Click on New Row on Level 3 (task) (or use the keyboard shortcut Ctrl+F3)
45 of 99
6. Creating the project structure – enter a task name
Type the task name
46 of 99
6. Creating the project structure – enter additional tasks
Enter additional tasks (on 3rd level). Using Ctrl+F3 is the fastest way of doing it.
47 of 99
6. Creating the project structure – enter a subtask on 4th level
... and click on New Row on Level 4 (task) or use the keyboard shortcut (Ctrl+F4)
Select the 3rd level task to which you want to add subtaks ...
48 of 99
6. Creating the project structure – edit a task name
Double-click on the task name to edit it
49 of 99
6. Creating the project structure – change the sequence 1
Holding down the left mouse button allows you to move a row to another position.
50 of 99
6. Creating the project structure – change the sequence 2
Moving an entire block (including all subtasks) to another position
51 of 99
6. Creating the project structure – submenus
Right-clicking on the designation of a row will bring up a context menu.
52 of 99
1. What is A-Plan for Windows?
2. Range of applications3. Help4. How data is displayed5. Organizing your data6. Creating the project
structure7. Allocating
resources / Working times
8. Scheduling tasks
0. Contents
9. Linking tasks10. Additional entry fields11. Printing12. Filters13. Options / Profiles14. Automated scheduling15. Others
53 of 99
7. Allocating resources – create a resource group
Click on the lower half of the A-Plan window and press Ctrl+F1 to enter a resource name
If you do not use resources in your planning, click on this button to close the resource view and to jump to Slide 61!
54 of 99
7. Allocating resources – create a resource
Just press Ctrl+F2 and type the name of the resource.
55 of 99
7. Allocating resources – allocate a resource to a task
Double-click on the resource columnand choose a resource from the list
56 of 99
7. Allocating resources – view calendars (= working hours)
Click here to view calendars (= working hours)
The default calendar (marked with*) is used if no resources are allocated to tasks or if resources work during standard hours only.
A calendar covering 7 days per week and 12 hours per day is used for machinery etc.
57 of 99
7. Allocating resources – create a new calendar
Create a new calendar by choosing „Insert“ / „New calendar“ or pressing Ctrl+F2
58 of 99
7. Allocating resources – set working hours
Insert a break by shortening the existing time bar and double-clicking to create a second time bar
59 of 99
7. Allocating resources – close the calendar view
Close the calendar view by clicking on the button again
60 of 99
7. Allocating resources – assign a calendar to a resource
Assigning a calendar to a resource
61 of 99
1. What is A-Plan for Windows?
2. Range of applications3. Help4. How data is displayed5. Organizing your data6. Creating the project
structure7. Allocating resources /
Working times8. Scheduling tasks
0. Contents
9. Linking tasks10. Additional entry fields11. Printing12. Filters13. Options / Profiles14. Automated scheduling15. Others
62 of 99
8. Scheduling tasks- set the landscape view calendar
Choose a higher resolution of the Gantt chart to facilitate the scheduling of tasks.
In the Options dialog box, click on the tabs Database settings / Time/Week numbers to set the Time increment to be used when entering data. For example, choosing 1 day has the effect that hours and minutes cannnot and need not be entered any longer. Important: This setting always applies to all data and all users of a database.
In the Options dialog box, click on the tabs Database settings / Time/Week numbers to set the Time increment to be used when entering data. For example, choosing 1 day has the effect that hours and minutes cannnot and need not be entered any longer. Important: This setting always applies to all data and all users of a database.
63 of 99
8. Scheduling tasks – enter task bars
Double-clicking at the requested position allows you to create up to 32,000 task bars per row.
Task bars in summary rows (= headlines) are created automatically. In such rows, you cannot enter task bars manually.
{
64 of 99
8. Scheduling tasks – use the mouse to set the begin and end
Hold down the left mouse button to set the begin and/or end of a task bar.
The begin, end, duration and resulting work (if applicable) are displayed synchronously.
65 of 99
8. Scheduling tasks– postpone dates
Shift a task bar by pointing to the center of the bar and holding down the left mouse button while moving the bar.
66 of 99
8. Scheduling tasks– enter the begin and end by typing the values
To change the begin or end of a task, you may double-click the current value and type a new value.
67 of 99
8. Scheduling tasks – use dialog boxes
Click on this button to use a dialog box for setting the begin and/or end of a selected task bar.
Click here if you prefer to use a dialog box for setting the duration and/or the work of a selected task bar.
Click to switch from begin to end and vice versa
68 of 99
8. Scheduling tasks - have the designations and starting/ending time of task bars
displayed
Activate the check box to have the designations of task bars displayed
Shows the date and time of begin and end
Double-click on the designation to edit it.
69 of 99
8. Scheduling tasks - have working times in task bars displayed
With this option activated, non-working time periods such as weekends and nightime are displayed without colour. If a task bar is not charged to full capacity, it is coloured to a lower height only.
70 of 99
1. What is A-Plan for Windows?
2. Range of applications3. Help4. How data is displayed5. Organizing your data6. Creating the project
structure7. Allocating resources /
Working times8. Scheduling tasks
0. Contents
9. Linking tasks10. Additional entry fields11. Printing12. Filters13. Options / Profiles14. Automated scheduling15. Others
71 of 99
9. Linking tasks – postpone dates 1
Postponing the predecessor‘s linking point will have the effect that ...
72 of 99
9. Linking tasks – postpone dates 2
... all successors are postponed as well.
Time periods spent on a task as well as distances remain contant with non-working times being considered.
73 of 99
9. Linking tasks- link several tasks simultaneously
To link tasks, just select the headline or several rows and choose the type of link you want to establish.
To find out how the project end is calculated automatically, see slide 94
To find out how the project end is calculated automatically, see slide 94
74 of 99
9. Linking tasks - Distance = „0“ / Reverse linking
Reverse linking should be used to find out the starting date if a task has a fixed end (see also slide 95).
Pressing the SHIFT key when linking tasks will automatically set the distance between tasks to „0“. This is done in consideration of non-working times such as weekends or night hours.
75 of 99
9. Linking tasks – linking with the mouse: successors
To link tasks, please click on the successor first ...
76 of 99
9. Linking tasks – linking with the mouse: predecessors
... and on the predecessor (to the right from the center) afterwards while holding down the Alt key.
77 of 99
9. Linking tasks – disconnect tasks
To remove an existing link, just click on it and press the DEL key.
78 of 99
9. Linking tasks – dialog boxes
You may also use a dalog box for linking tasks:
Distance between tasks
79 of 99
1. What is A-Plan for Windows?
2. Range of applications3. Help4. How data is displayed5. Organizing your data6. Creating the project
structure7. Allocating resources /
Working times8. Scheduling tasks
0. Contents
9. Linking tasks10. Additional entry fields11. Printing12. Filters13. Options / Profiles14. Automated scheduling15. Others
80 of 99
10. Additional Entry Fields- notes
The words of the note will be displayed as long as the mouse pointer hovers over the note symbol (in printing, notes are printed as footnotes).
The words of the note will be displayed as long as the mouse pointer hovers over the note symbol (in printing, notes are printed as footnotes).
Double-click on a cell of the column entitled Nt. (= Note) to enter a note text of any length in a separate window.
81 of 99
10. Additional Entry Fields - create a link to other files (objects)
Double-click on a cell in the Object column to create a link to another file. Double-clicking on the file name of the linked file will start the assigned application and will open the file.
82 of 99
10. Additional Entry Fields – submenus 1
To make further settings (regarding memos, patterns and/or colours, alarm, recurring dates) just right-click the task bar concerned.
83 of 99
1. What is A-Plan for Windows?
2. Range of applications3. Help4. How data is displayed5. Organizing your data6. Creating the project
structure7. Allocating resources /
Working times8. Scheduling tasks
0. Contents
9. Linking tasks10. Additional entry fields11. Printing12. Filters13. Options / Profiles14. Automated scheduling15. Others
84 of 99
11. Printing- print preview
Takes you to the Printing Options
Allows you to specify the colums to be printed (irrespective of the columns displayed on your screen)
Copies the preview to the Windows Clipboard (at no loss of quality)
Choose File / Print Preview to check what the printout will look like
Choose File / Print Preview to check what the printout will look like
85 of 99
11. Printing* - print to several pages in horizontal direction
Number of overlapping pages in horizontal direction (up to 9 pages)
Set the begin and end or the time range covered by the Gantt chart
86 of 99
1. What is A-Plan for Windows?
2. Range of applications3. Help4. How data is displayed5. Organizing your data6. Creating the project
structure7. Allocating resources /
Working times8. Scheduling tasks
0. Contents
9. Linking tasks10. Additional entry fields11. Printing12. Filters13. Options / Profiles14. Automated scheduling15. Others
87 of 99
12. Filters- completed tasks
Use this button to either show or hide completed tasks.
To mark a task as completed, just right-click it and activate the command Completed from the menu (the task bar will then turn grey).
88 of 99
12. Filters - Set filters
Opens the dialog box for setting filters
As a result of this filter, only those tasks are displayed to which „Stevens“ has been allocated as a resource.
89 of 99
12. Filters - Reshow date
Activating this button will reshow all those tasks which have reached or passed the Reshow date (supposed that the 2 buttons next to it are deactivated).
Use Shift+Double-click to set a Reshow date for a task (and right-click the row to delete it).
Current day (light red)
Current day (light red)
Reshow dateReshow date
90 of 99
1. What is A-Plan for Windows?
2. Range of applications3. Help4. How data is displayed5. Organizing your data6. Creating the project
structure7. Allocating resources /
Working times8. Scheduling tasks
0. Contents
9. Linking tasks10. Additional entry fields11. Printing12. Filters13. Options / Profiles14. Automated scheduling15. Others
91 of 99
13. Others – options
Click here to view options
... and the printout are made independently of each other.
Settings regarding the screen display...
92 of 99
13. Others – profiles
Up to 99 profiles allow you to save all current settings (including print settings).
Create a new profile by overwriting the name of the current profile. To delete profiles, choose „Tools“ / „Delete Current Profile“ from the menu.
93 of 99
1. What is A-Plan for Windows?
2. Range of applications3. Help4. How data is displayed5. Organizing your data6. Creating the project
structure7. Allocating resources /
Working times8. Scheduling tasks
0. Contents
9. Linking tasks10. Additional entry fields11. Printing12. Filters13. Options / Profiles14. Automated scheduling15. Others
94 of 99
14. Automated scheduling- automated calculation of the end of the project (fixed begin)
With (estimated) required work entered in this column …
… the overall duration and the End of the selected project will be calculated.
Linked task bars (see slide 73) of different durations
Linked task bars (see slide 73) of different durations
The total duration of all tasks is calculated from allocated resources in consideration of their capacity usage and their working hours.
The total duration of all tasks is calculated from allocated resources in consideration of their capacity usage and their working hours.
95 of 99
14. Automated scheduling - automated calculation of the begin of the project (fixed end)
… the overall duration and the Begin of the selected project will be calculated.
Reverse linked task bars (see slide 74) of different durations
Reverse linked task bars (see slide 74) of different durations
The total duration of all tasks is calculated from allocated resources in consideration of their capacity usage and their working hours.
The total duration of all tasks is calculated from allocated resources in consideration of their capacity usage and their working hours.
With (estimated) required work entered in this column …
96 of 99
14. Automated scheduling- even distribution of work
… the capacity usage of all resources allocated to the selected project will be calculated.
Task bars of fixed duration.Task bars of fixed duration.
The capacity usage of all resources is calculated from required work in consideration of the duration of tasks and working hours of resources.
The capacity usage of all resources is calculated from required work in consideration of the duration of tasks and working hours of resources.
With (estimated) required work entered in this column …
97 of 99
14. Automated scheduling- time periods spent on a task are independent of the task duration
Create a separate row for each resource allocated to the task by clicking on the „+“ in the red square.
Use the „resource rows“ to assign to each resource the time period(s) during which the resource is to work on the task.
Total of the times spent on the task(at full height, all allocated resources work on the task)
Total of the times spent on the task(at full height, all allocated resources work on the task)
98 of 99
1. What is A-Plan for Windows?
2. Range of applications3. Help4. How data is displayed5. Organizing your data6. Creating the project
structure7. Allocating resources /
Working times8. Scheduling tasks
0. Contents
9. Linking tasks10. Additional entry fields11. Printing12. Filters13. Options / Profiles14. Automated scheduling15. Others
99 of 99
15. Others – where to find more detailed help?
More detailed information on using A-Plan is provided in the Online help of A-Plan and in the User manual which can be downloaded in pdf format from http://www.braintool.com/downloads.0.html?&L=2.
Both documents also provide information on subjects not covered here such as• Cost planning
• Comparison of actual vs. target values
• Using A-Plan in a networked environment
• Export/Import
• Synchronization with other A-Plan databases and with MS-
Outlook
• Time tracking