Various applications of international RCC dam construction
By: Ted Warren USA
Al Wehdah RCC dam Jordan/Syria
• Medium paste RCC 60C/60A
103 Al Wehdah RCC dam nearing completion of RCC
• 6th fastest RCC dam constructed worldwide when completed
Conveyor layout Al Wehdah RCC Dam Jordan/Syria
Al Wehdah under construction 2005-2006
• Simple installation process• Less capital costs = Alliance asset and can be sold for
various uses in the mining and quarrying industry
Conveyor Configuration
C5C4
C3
C2
C1
Conveyor sections removed as the dam rises
C1
C2 Swinger
RCC delivery system• 350 m overland conveyor with integrated stepped sectional conveyor tranfers with swinger discharge conveyor for loading haul trucks on the fill
• Simple system used worldwide successfully for RCC dam construction
• This system was used on 8 of the top 10 fasted constructed RCC dams in the world (MDA database) with placement rates ranging from 52,000 m3 per month to 125,000 m3 per month
• Al Wehdah Dam was the 6th fastest RCC Dam constructed with an average monthly rate of 75,000 m3/ month of the 360 RCC dams completed world wide. (MDA database)
• Access walkways for safety, continuous maintenance ,and inspection purposes without an interruption to the RCC operation while in production
• Simply mechanical system = Less down time
• Wider conveyor = less speed = less segregation and less maintenance
• Less up front Capital = better value for money
Al Wehdah complete
155 m tal Ralco RCC dam Chile
All conveyor RCC delivery system
155 m Ralco Dam Chile
RCC placement 24 hrs5 th fastest RCC dam constructed worldwide when completed
• I.6 million m3 RCC
• Main conveyor with transfer to feed link conveyor combined with a tripper conveyor and Crawler Placer system on the fill
• Trucks were loaded on the fill directly from main conveyor when the complex system used for placement on the dam was being installed and during down time.
• This system is very effective for large and extremely complicated RCC dams generally over 1 million m3.
•
Ralco nearing completion
GERCC application
Mc Alpine RCC/CVC Navigation lock USA
Yeywa Hydropower project Myanmar/Burma
• 134 m tall• 2.34 million m3 RCC• 790 MW hydropower scheme• Non Gated OGEE spillway• Converging spillway chute with “ski jump”
and plunge pool discharge
Yeywa RCC Dam Myanmar ?Burma
Yeywa dam nearing completion
• Powerhouse under construction• Headrace penstocks for powerhouse
intake
Dong Nai 4 Vietnam
• 130 m tall• Hydropower project• 1.3 million m3 RCC
Dong Nai 4 RCC startup
Don Nai 3 Vietnam
• 103 m tall• 1.01 million m3 RCC
Prepared by: Ted Warren RCC consultant USA partial listing of RCC projects