© City of Edmonton | Integrated Infrastructure Services | Utility Infrastructure Delivery | Tweddle Place Dry Pond Open House | 06.07.2017 Tweddle Place Dry Pond Expansion & 86 / 88 Street Cul-De-Sacs Sewer Upgrades Construction Open House 1
Transcript
Page 1: Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades ...€¦ · Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades - Open House Presentation - June 2017 Author: City of Edmonton

© City of Edmonton | Integrated Infrastructure Services | Utility Infrastructure Delivery | Tweddle Place Dry Pond Open House | 06.07.2017

Tweddle Place Dry Pond Expansion & 86 / 88 Street Cul-De-Sacs Sewer Upgrades

Construction Open House

1

Page 2: Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades ...€¦ · Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades - Open House Presentation - June 2017 Author: City of Edmonton

© City of Edmonton | Integrated Infrastructure Services | Utility Infrastructure Delivery | Tweddle Place Dry Pond Open House | 06.07.2017

Agenda

•Introduction of Project Team

•Project Description

•Construction Impacts

•Planned Detours

•Project Schedule

•Concurrent Construction Projects

•Property Damage Claim Process

2

Page 3: Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades ...€¦ · Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades - Open House Presentation - June 2017 Author: City of Edmonton

© City of Edmonton | Integrated Infrastructure Services | Utility Infrastructure Delivery | Tweddle Place Dry Pond Open House | 06.07.2017

Project Team

•Project Owner: City of Edmonton - Utilities Infrastructure

•Engineering Consultant: Stantec Consulting Ltd.

•General Contractor: Weinrich Contracting Ltd.

3

Page 4: Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades ...€¦ · Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades - Open House Presentation - June 2017 Author: City of Edmonton

© City of Edmonton | Integrated Infrastructure Services | Utility Infrastructure Delivery | Tweddle Place Dry Pond Open House | 06.07.2017

Project Locations

4

Tweddle Place Dry Pond

86 & 88 Street Cul-de-Sacs

Page 5: Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades ...€¦ · Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades - Open House Presentation - June 2017 Author: City of Edmonton

© City of Edmonton | Integrated Infrastructure Services | Utility Infrastructure Delivery | Tweddle Place Dry Pond Open House | 06.07.2017

Project Description

•Expand existing Tweddle Place Dry Pond

•Remove existing earth berm

•Install new sewers, inlets

•Create pathway detour during construction

•Restore pathway after construction along 91 Street, with new connections to neighbourhood pathways and sidewalks

•Install vegetated sound barrier along dry pond

•Install new sewers and restore surface in cul-de-sacs of 86 Street and 88 Street, north of 40 Avenue

5

Page 6: Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades ...€¦ · Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades - Open House Presentation - June 2017 Author: City of Edmonton

© City of Edmonton | Integrated Infrastructure Services | Utility Infrastructure Delivery | Tweddle Place Dry Pond Open House | 06.07.2017

Construction Impacts

6

•Construction noise - noise bylaw will be adhered to

•Sidewalk and one-lane road closures on 86 & 88 Street cul-de-sacs

•Temporary full road closure for connection on 40 Avenue (TBC)

•No street parking near construction sites

•Home access will be maintained

•Emergency access will be maintained

•Waste disposal services to be maintained

Page 7: Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades ...€¦ · Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades - Open House Presentation - June 2017 Author: City of Edmonton

© City of Edmonton | Integrated Infrastructure Services | Utility Infrastructure Delivery | Tweddle Place Dry Pond Open House | 06.07.2017

Detours

•Multi-use Trail to be closed and bike/pedestrian traffic to be re-routed

•Detour to begin Summer 2017 and last until late summer 2018

7

Page 8: Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades ...€¦ · Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades - Open House Presentation - June 2017 Author: City of Edmonton

© City of Edmonton | Integrated Infrastructure Services | Utility Infrastructure Delivery | Tweddle Place Dry Pond Open House | 06.07.2017

Project Schedule

Project Startup: July 2017

Dry Pond Construction•Initial Berm Excavation:•Underground Work in Pond:

July - September 2017 July – October 2017

•Remaining Pond Excavation: October 2017 - March 2018 •Sound Barrier Installation:•Pathway Restoration:

May - August 2018 June – August 2018

•Landscaping/Site Restoration: August – November 2018

86/88 Street Sewer Construction•Underground Construction: July - August 2017•Road Restoration: August – September 2017

8

Page 9: Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades ...€¦ · Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades - Open House Presentation - June 2017 Author: City of Edmonton

© City of Edmonton | Integrated Infrastructure Services | Utility Infrastructure Delivery | Tweddle Place Dry Pond Open House | 06.07.20179

Rendering of Completed Dry Pond Expansion

Page 10: Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades ...€¦ · Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades - Open House Presentation - June 2017 Author: City of Edmonton

© City of Edmonton | Integrated Infrastructure Services | Utility Infrastructure Delivery | Tweddle Place Dry Pond Open House | 06.07.2017 10

Sample Dry Pond in South Campus

Page 11: Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades ...€¦ · Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades - Open House Presentation - June 2017 Author: City of Edmonton

© City of Edmonton | Integrated Infrastructure Services | Utility Infrastructure Delivery | Tweddle Place Dry Pond Open House | 06.07.2017

Current Millbourne Flood Mitigation Projects

11

Tweddle Place Storm & Sanitary Sewer Upgrades Project AreaConstruction:2015 - 2021

Malcolm Tweddle & Edith Rogers Dry Pond and Sewer Improvements Project AreaConstruction: 2017 - 2023

Page 12: Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades ...€¦ · Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades - Open House Presentation - June 2017 Author: City of Edmonton

© City of Edmonton | Integrated Infrastructure Services | Utility Infrastructure Delivery | Tweddle Place Dry Pond Open House | 06.07.2017

Malcolm Tweddle & Edith Rogers Dry Ponds and Sewer Improvements Project

12

Dry Ponds Construction: Oct 2017 - July 2018

Sewer Improvements Construction:2018 or 2019 - 2023

Page 13: Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades ...€¦ · Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades - Open House Presentation - June 2017 Author: City of Edmonton

© City of Edmonton | Integrated Infrastructure Services | Utility Infrastructure Delivery | Tweddle Place Dry Pond Open House | 06.07.2017

Concurrent Construction Projects

13

88 St. Cul-de-sac

Malcolm Tweddle & Edith Rogers Dry Pond:Oct 2017 - July 2018- Tree removals/relocations tentatively mid June to July- ATCO gas line relocation tentatively July or August- Public information session likely week of September 11

Page 14: Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades ...€¦ · Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades - Open House Presentation - June 2017 Author: City of Edmonton

© City of Edmonton | Integrated Infrastructure Services | Utility Infrastructure Delivery | Tweddle Place Dry Pond Open House | 06.07.2017

88 Street Cul-de-Sac

14

• New storm sewer and catch basins to collect flows from the cul-de-sac and alleyways.

• Includes restoration of landscaping, concrete and asphalt in the street and alleyways.

• Project underway, continuing into July.

Page 15: Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades ...€¦ · Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades - Open House Presentation - June 2017 Author: City of Edmonton

© City of Edmonton | Integrated Infrastructure Services | Utility Infrastructure Delivery | Tweddle Place Dry Pond Open House | 06.07.2017

Building Condition Assessment

• If you received a pre-construction assessment in 2015 or 2016, you will receive a post-construction assessment

• 2015 construction on 89 St & south of 42A Ave: Post-construction assessment reports will be delivered to homeowners by the end of June 2017.

• 2016 construction on 89 St & 44 Ave or 88 St south of 44 Ave: Post-construction assessments will be conducted in September 2017 after the construction is completed and will be provided.

• 2017 construction in the cul-de-sacs of 86 St & 88 St: Pre-construction assessments are ongoing, post-construction assessments will only be done if requested.

15

Page 16: Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades ...€¦ · Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades - Open House Presentation - June 2017 Author: City of Edmonton

© City of Edmonton | Integrated Infrastructure Services | Utility Infrastructure Delivery | Tweddle Place Dry Pond Open House | 06.07.2017

• Did damage occur?

• Identify the type of damagea. Damage to exterior property: Contact Project Managerb. Damage inside your home: Submit a claim

• Post-construction assessment A post-construction assessment will be done if requested.

• For more information visit: https://www.edmonton.ca/programs_services/damage-or-injury-claims.aspx

Property Damage Claims Process

16

Page 17: Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades ...€¦ · Tweddle Place Dry Pond Expansion & Cul-de-Sac Upgrades - Open House Presentation - June 2017 Author: City of Edmonton

© City of Edmonton | Integrated Infrastructure Services | Utility Infrastructure Delivery | Tweddle Place Dry Pond Open House | 06.07.2017

Thank You

Thank you for your attendance and we welcome any questions you have.

Tweddle Place Storm and Sanitary Sewer UpgradesGary Fei, P.Eng.Project Manager - Utility Infrastructure Delivery, City of [email protected]

Malcolm Tweddle & Edith Rogers Dry Pond & Sewer ImprovementsDarwin Smith, P.Eng.Project Manager - Utility Infrastructure Delivery, City of [email protected]