+ All Categories
Home > Documents > UL/NIST Studies Tactical Findings Implementation into Zone 1 Tactical Considerations and Best...

UL/NIST Studies Tactical Findings Implementation into Zone 1 Tactical Considerations and Best...

Date post: 17-Dec-2015
Category:
Upload: georgiana-melton
View: 217 times
Download: 2 times
Share this document with a friend
Popular Tags:
19
UL/NIST Studies Tactical Findings Implementation into Zone 1 Tactical Considerations and Best Practices
Transcript
Page 1: UL/NIST Studies Tactical Findings Implementation into Zone 1 Tactical Considerations and Best Practices.

UL/NIST StudiesTactical Findings

Implementation into Zone 1Tactical Considerations

and Best Practices

Page 2: UL/NIST Studies Tactical Findings Implementation into Zone 1 Tactical Considerations and Best Practices.

Four Key Concepts

• Initial Size up• Fire Attack Considerations• Controlling the Flow Path• Ventilation

Page 3: UL/NIST Studies Tactical Findings Implementation into Zone 1 Tactical Considerations and Best Practices.

Key Concepts

Initial Size Up of the Structure

Page 4: UL/NIST Studies Tactical Findings Implementation into Zone 1 Tactical Considerations and Best Practices.

Initial Size Up of the Structure

The first arriving unit must perform a size up that will address the following:• Determine the location of the fire– Conduct a 360– Identify basement, exterior fire– Stress the use of the TIC during size up.– Announce location of fire to in coming units.

Page 5: UL/NIST Studies Tactical Findings Implementation into Zone 1 Tactical Considerations and Best Practices.

Initial Size Up of the Structure

• Identify the flow pathVentilationLimited

Single OpeningBi-Directional

Page 6: UL/NIST Studies Tactical Findings Implementation into Zone 1 Tactical Considerations and Best Practices.

Initial Size Up of the Structure

• Rescue– Determination of immediate rescue.

– Fire extinguishment may be warranted before rescue is started.

Page 7: UL/NIST Studies Tactical Findings Implementation into Zone 1 Tactical Considerations and Best Practices.

Initial Size Up of the Structure

• Cooling the space/Extinguishment

From Best Practices:Water should be applied to the fire as soon as possible from the safest location to reduce the heat release rates from burning materials. Any limited-duration water stream applied from the exterior should be immediately followed by an aggressive interior attack of any remaining fire.

Page 8: UL/NIST Studies Tactical Findings Implementation into Zone 1 Tactical Considerations and Best Practices.

Key Concepts

Fire Attack Considerations

Page 9: UL/NIST Studies Tactical Findings Implementation into Zone 1 Tactical Considerations and Best Practices.

From Best Practices:While front door tactics provide quick access to most areas of the structure, water applied from the safest area – interior or exterior – will result in the fastest way to improve interior conditions for both occupants and fire control

• Front Door• Exterior/Front Door• Front Door/Exterior

Page 10: UL/NIST Studies Tactical Findings Implementation into Zone 1 Tactical Considerations and Best Practices.

Fire Attack Considerations

• Why hit it from outside?– Cool the space.– Reduces flashover.– Interior application delayed.– Solid or straight stream directed at the ceiling to

create large water droplets.

An exterior attack is Offensive Mode if you remain forward moving

Page 11: UL/NIST Studies Tactical Findings Implementation into Zone 1 Tactical Considerations and Best Practices.

Fire Attack Considerations

• Water application to cool hot smoke– Reduce flashover

Page 12: UL/NIST Studies Tactical Findings Implementation into Zone 1 Tactical Considerations and Best Practices.

LA County FD

http://www.youtube.com/watch?v=6lkM2AsZqlM

Page 13: UL/NIST Studies Tactical Findings Implementation into Zone 1 Tactical Considerations and Best Practices.

Key Concepts

Controlling the Flow Path

Page 14: UL/NIST Studies Tactical Findings Implementation into Zone 1 Tactical Considerations and Best Practices.

Controlling the Flow Path

• Opening doors and or windows is venting– Smoke and heat will travel to low pressure- an

opening to the outside– Ventilation to flashover timeline.

Page 15: UL/NIST Studies Tactical Findings Implementation into Zone 1 Tactical Considerations and Best Practices.

LA County FD Controlling the Flow Path

• Techniques for door controlhttp://www.youtube.com/watch?v=-Uans40KdVI

Page 16: UL/NIST Studies Tactical Findings Implementation into Zone 1 Tactical Considerations and Best Practices.

Key Concepts

Ventilation

Page 17: UL/NIST Studies Tactical Findings Implementation into Zone 1 Tactical Considerations and Best Practices.

Ventilation

• Coordination of fire attack and ventilation– Ventilation too early will promote rapid buildup of

fire• Venting is not cooling.• Ventilating and water application is cooling.• Requires Communication between fire attack

and ventilation crews

Page 18: UL/NIST Studies Tactical Findings Implementation into Zone 1 Tactical Considerations and Best Practices.

Implementation

1. Pre Assignment: Lesson from UL Learnshare- http://content.learnshare.com/courses/73/456883/story.html

2. PowerPoint and discussion/lecture by Operations Battalion Chiefs.

3. Tabletop Applications: Tactical Training Program.4. Hands on training: EMTG Live Fire Training November

and December 20145. Review the use of the concepts at each PIA.

Page 19: UL/NIST Studies Tactical Findings Implementation into Zone 1 Tactical Considerations and Best Practices.

Other On-Line Resources

• http://www.fireengineering.com/articles/2014/01/ventilation-limited-fire-keeping-it-rich-and-other-tactics-based-off-science.html

Good article about ventilation and tactics

• https://www.youtube.com/watch?v=82OJqcftNVgGreat three-part series on flow path, in 1-hour segments


Recommended