Date post: | 04-Apr-2018 |
Category: |
Documents |
Upload: | bratishkaity |
View: | 219 times |
Download: | 0 times |
of 19
7/29/2019 Ultra power plant
1/19
Presentation
on UltraMega &
Super CriticalProjects
Organized ByFICCI & MOP
May 2006
7/29/2019 Ultra power plant
2/19
ay 006
Year
GROWTH OF INSTALLED GENERATING CAPACITY (MW)
Hydro
Nuclear
Thermal *
Hydro 508 940 1917 4124 6905 11384 14460 18308 20506 26910 29676 32326
Nuclear 0 0 0 0 640 640 1095 1565 1720 2720 2720 3360
Thermal * 854 1755 2736 4903 9059 16424 27030 43417 57244 78343 80860 88601
Dec-47 Dec-55 Mar-61 Mar-66 Mar-74 Mar-80 Mar-85 Mar-90 Mar-95 Mar-03 Sep-04 Mar-06
13622695 4653 9027
16604
28448
42585
63290
79470
124287
* - Includes Wind Capacity
107973113256
7/29/2019 Ultra power plant
3/19
Thermal
Hydro
Nuclear
Renewables
Installed Capacity
Thermal82410.54 MW (66%)
Hydro32325.77 MW (26%)
Nuclear3360 MW
Renewables6190 MW
(Coal 68518)
7/29/2019 Ultra power plant
4/19
64.5667.47
68.7469.97
72.34 72.9674.82
73.6
55
60
65
70
75
80
1998-
99
1999-
00
2000-
01
2001-
02
2002-
03
2003-
04
2004-
05
2005-
06
PLF%--->
Plant Load Factor Of Thermal Stations
7/29/2019 Ultra power plant
5/19
500 MW Group >84 %250 MW Group >90 %
Central Sector >82%
PLF - Some Highlights
7/29/2019 Ultra power plant
6/19
Growth In Unit Size/Parameters
Unit
Size
(MW)
Yr of
Introduction
MS Pr
kg/cm2MS /RH
Temp (o C)
< 30 1950 42 455
100 1970 90 535
2101977 & 1983 130 &150 535/535
500 1984 170 538/538
660 Under Const. 247 535/566
7/29/2019 Ultra power plant
7/19
Hydro Thermal Nuclear Total2007-12XI Plan
18781 40220 3160 68504
2012-17
XII Plan 20000 30000 10000 6000 66000
Figs in MW
COAL OTHERS
6343
Capacity Addition Targets
7/29/2019 Ultra power plant
8/19
Drivers For Ultra Mega
Power Projects LARGE CAPACITY ADDITION PLANNED OVER
NEXT DECADE IN 11TH PLAN BEYOND
PACE OF THERMAL CAPACITY ADDITION TO
INCREASE FROM ~ 5000 MW/Yr TO ~ 10,000 MW/Yr
ADVANCED PROVEN TECHNOLOGY WITH HIGHEFFICIENCY FOR
OPTIMAL USE OF RESOURCES HIGHER
EFFICIENCY
ECOFRIENDLY POWER GENERATIONECONOMY OF SCALE
OPERATIONAL FLEXIBILITY( Faster Start Up, Load
Cycling)
7/29/2019 Ultra power plant
9/19
Concept Of
Ultra Mega Power Project
A FEW PRE-IDENTIFIED PROJECTS EACH WITH ACAPACITY OF ABOUT 4000 MW ENVISAGED ABOUT 7NOS. AT PRESENT
SASAN, MP PIT HEAD
AKALTARA, CHATTISGARH
MUNDRA, GUJARAT GIRYE, MAHARASTHRA COASTAL
TADRI, KARNATAKA
ORISSAPITHEAD UNDER
ANDHRA PRADESH - COASTAL CONSIDERATION
USE OF LARGE UNIT SIZES OF 600 MW & ABOVESUPERCRITICAL TECHNOLOGY
FIRST FIVE TARGETTED FOR FINALISATION BY 31ST DEC.2006
PIT HEAD STATIONS WOULD HAVE COAL BLOCKSALLOCATED WITH CAPTIVE MINING
7/29/2019 Ultra power plant
10/19
Road Map For Implementation OfUltra Mega Power Projects
POTENTIAL SITES IDENTIFICATION ANDSELECTION BY CEA THROUGH SATELLITEIMAGING, VISITS AND INTEGRATION WITH
STATE AND LOCAL AGENCIES.
SEPARATE SPV FOR EACH PROJECT FORPROJECT DEVELOPMENT.
PFC IDENTIFIED AS NODAL AGENCY FORSETTING UP OF SHELL COMPANIES.
-------- CONTD.
7/29/2019 Ultra power plant
11/19
SHELL COMPANIES TO TAKE FOLLOWINGACTION
- PREPARATION OF PROJECT REPORT
- INITIAL LAND ACQUISITION- COAL LINKAGES/COAL BLOCKS ALLOCATIONS FOR
PIT HEAD PROJECTS
- ALLOCATION OF WATER
SHELL COMPANIES TO APPOINT
CONSULTANTS FOR ICB BID DOCUMENTPREPARATION & EVALUATION.
SELECTION OF DEVELOPER THROUGH TARIFFBASED ICB.
SHELL COMPANIES THEN TO BETRANSFERRED TO THE SUCCESSFUL BIDDERFOR PROJECT EXECUTION.
7/29/2019 Ultra power plant
12/19
Formation Of Shell Companies
FIVE SPV (SHELL COMPANIES) FORMED ARE :1. SASAN POWER LIMITED (M.P.)
2. COASTAL GUJARAT POWER LIMITED (MUNDRA PORT)
3. COASTAL MAHARASHTRA MEGA POWER LIMITED.
4. COASTAL KARNATAKA POWER LIMITED.
5. AKALTARA POWER LIMITED (CHATTISGARH)
STATE GOVTS. HAVE BEEN REQUESTED BY MOP TOPROVIDE NECESSARY SUPPORT.
MINISTRY OF COAL HAS AGREED IN-PRINCIPLE TOALLOCATE COAL BLOCKS, FOR PITHEAD STATIONS.
ADDITIONAL PIT HEAD SITE IN ORISSA AND COASTAL INANDHRA PRADESH BEING EXPLORED.
7/29/2019 Ultra power plant
13/19
Current Status Of Ultra Mega
Projects. FIVE SHELL COMPANIES FORMED.
EOI ISSUED FOR SADAV, MUNDRA, GIRYE& TADRI.
TECHNICAL CONSULTANTS APPOINTEDBY SHELL COS. FOR PREPARATION OFPROJECT REPORTS.
CONSULTANT APPOINTED FOR BID
DOCUMENTS AND BIDDING PROCESS. POWER ALLOCATION/POWER PURCHASE
AGREEMENTS ARE BEING FINALISED.
7/29/2019 Ultra power plant
14/19
Use Of
Super Critical Technology Supercritical Technology is widely established and
accepted with more than 500 units in operation.
Widely prevalent cycle parameters:
Pressure: 246 -250 kg/cm2
Temperature: 538/538 deg C 538/566 deg C (Sipat & Barh TPS)
566/593 deg C (Mainly in Japan &Germany)
593/593 or 600/600 deg C
Preferred steam parameters include higher steamtemp. of 566 to 593 deg C depending upon site specifictechno-economics. BHEL collaboration includes theseparameters.
Contd.
7/29/2019 Ultra power plant
15/19
1. Lara TPS,NTPC 3x800 MW Chattisgarh
2. Ib ValleyDaripalli,
NTPC
2x800 MW Orissa
3. Barh TPS, NTPC 2x800 MW Bihar4. Krishnapattanam 2x800 MW AP
5. More Future projects
Besides Ultra Mega Power Projects Supercritical
Units envisaged for following projects:-
7/29/2019 Ultra power plant
16/19
Expected Efficiency RangeParameters Parameters
247/535/566@ 247/566/592Tur.
HR
Blr
Eff
Gross
HR
Gross
Eff
Tur.
HR
Blr
Eff
Gross
HR
Gross
Eff
Case-I Turbine
Heat Rate =1904
as Quoted for 660MW & parameters
at @
1904
88% 2164 39.75
%
1879
88% 2135 40.28
%
86% 2214 38.84
%
86% 2180 39.45
%
Case-II Turbine
Heat Rate =1880
as per BHEL for660 MW &
parameters at @
1880
88% 2147 40.06
%
1855
88% 2108 40.79
%
86% 2197 39.15
%
86% 2157 39.87
%
Efficiency figures are on HHV basis and 100% load conditions86% boiler efficiency is assumed for Indian coal and 88% for
Imported coal
7/29/2019 Ultra power plant
17/19
List Of Foreign Suppliers ForSupercritical Units
BOILER STEAM TURBINE
1.Alstom, France.
2.MHI, Japan.
3.IHI, Japan.
4.Hitachi-Babcock, Japan.
5.Ansaldo, Italy.
6.TKZ, Russia.
7.Doosan, S. Korea.
8.Foster Wheeler, US.
9.Babcock & Wilcox, US.
10.Chinese (SEC, Dengfong,
Harbin).
1.Alstom, France.
2.MHI, Japan.
3.Siemens, Germany.
4.Ansaldo, Italy.
5.Hitachi, Japan.
6.Toshiba, Japan.
7.GE, USA.
8.Doosan, S. Korea.
9.Chinese (SEC, Dengfong,
Harbin).
10.Russian (Power Machines)
7/29/2019 Ultra power plant
18/19
Option of using Washed Coal
Indigenous coal generally have high ash content, widevariation in calorific value, presence of extranousmatter and is unsized.
Considering large unit size, it is desirable to have goodand consistent coal quality, free of extraneous matterwith a view to
Narrow down coal design range
Less wear and tear of coal handling and coalpulverizers
Reduced teething problems in initial stage oftechnology introduction
Comfort in plant operation
7/29/2019 Ultra power plant
19/19
CONCLUSION
A MAJOR SHARE OF CAPACITY ADDITION EXPECTEDTHROUGH LARGE SUPERCRITICAL UNITS IN ULTRAMEGA PROJECTS AND OTHER 800 MW SIZE UNITS BYNTPC, APGENCO & OTHER UTILITIES.
HIGHER STEAM PARAMETERS IN SUPERCRITICAL UNITSPREFERRED FOR BETTER EFFICIENCY.
FOR OVERALL ECONOMICS, PITHEAD STATIONS CAN BEINTEGRATED WITH COAL WASHING AND CFBC UNIT TOUSE WASHERY REJECTS.
DESIRABLE TO HAVE TECHNOLOGY TRANSFER WITHINDIGENOUS MANUFACTURING CAPACITY BUILDING TOMEET THE PROJECTED CAPACITY ADDITION TARGETSWITH ADEQUATE COMPETITION.