+ All Categories
Home > Documents > UltraTech Cement Limited Hotgi Cement Works€¦ · Hanumanthappa - Manager 3. Mr. Viwek Zode...

UltraTech Cement Limited Hotgi Cement Works€¦ · Hanumanthappa - Manager 3. Mr. Viwek Zode...

Date post: 20-Oct-2020
Category:
Upload: others
View: 9 times
Download: 0 times
Share this document with a friend
28
UltraTech Cement Limited Hotgi Cement Works Team Members 1. Mr. Kasi Viswanadham – Deputy General Manager 2. Mr. Hanumanthappa - Manager 3. Mr. Viwek Zode – Asst. Manager August 2020
Transcript
  • UltraTech Cement LimitedHotgi Cement Works

    Team Members

    1. Mr. Kasi Viswanadham – Deputy General Manager

    2. Mr. Hanumanthappa - Manager

    3. Mr. Viwek Zode – Asst. Manager

    August 2020

  • 1.a. Unit Introduction – Plant Details

    ULTRATECH CEMENT LIMITED, HOTGI CEMENT WORKS

    Land Acquisition – 265 Acres 1994

    Line-1 commissioned – Capacity 1.2 MTPA Products – OPC 43, OPC 53, PPC & PPCS

    23 July 1995

    Introduction of PPC at Line 1 - Capacity enhanced by 0.8 MTPA Total Capacity 2 MTPA

    2008

    Line-2 commissioned with Capacity – 2.0 MTPA Products – OPC 43, OPC 53 & PPC

    20th March 2013

    Total Plant Capacity is 4.0 MTPA

    Located at South Solapur, Maharashtra on Mumbai – Hyderabad broad gauge line Caters market of entire South-West Maharashtra.

  • 1.b. Unit Introduction – Process Overview

    Clinker from RCW

    BCCW Rake

  • 2. Energy Consumption Overview

    Overall Energy consumption data

    YearElectrical Energy

    (kwh)Thermal Energy

    (Kcal)Total Energy

    (TOE)

    2017-18 70619000 0 6072.14

    2018-19 61646000 0 5300.60

    2019-20 68315000 0 5874.03

    100

    0

    Total Energy (%) Consumed 2019-20

    Electrical Energy (kwh)

    Thermal Energy (kcal)

    100% Electrical Energy consumption

  • 3.a. Sp. Energy Consumption – Product Specific(FY 2017-20)

    26.28

    26.0726.03

    25.9

    25.95

    26

    26.05

    26.1

    26.15

    26.2

    26.25

    26.3

    2017-18 2018-19 2019-20

    OPC Grade Sp. Power kwh/MT

    2017-18 2018-19 2019-20

    25.4525.31

    24.58

    24

    24.2

    24.4

    24.6

    24.8

    25

    25.2

    25.4

    25.6

    2017-18 2018-19 2019-20

    PPC Grade Sp. Power kwh/MT

    2017-18 2018-19 2019-20

    Grade Improvement %

    OPC 0.95

    PPC 3.42

    Reasons for improvement

    Installation of Thin classifying Liners

    C-194 Seperator fan impeller replaced.

    Installation of Expert Optimizer

    Grinding Media Regradation

  • 3.b. Sp. Energy Consumption – Section Wise(FY 2017-20)

    25.95

    0.7522.81

    25.74

    0.7542.88

    25.55

    0.6652.57

    0

    5

    10

    15

    20

    25

    30

    Total Grinding Power Packing Power Misc. Power

    Sp. Power – Section Wise

    2017-18 2018-19 2019-20

    Section Improvement % Reason for variationGrinding Power 1.54 Thin classifying liners, Expert Optimizer, C-194 Impeller

    replacement, Grinding Media Regradation, VFD operated bag filters, Roller profiling in every six months etc.

    Packing Power 11.57 Wagon loading bay extension, VFD operated bag filters, Increase in Packer speed, Increase in BCCW dispatches, installation powerless bag diverters etc.

    Misc. Power 8.54 VSD compressors in place of IR, AC energy savers, reduction of idle running of equipment's, Installation of LED lights utilization of only one cooling tower in monsoon etc.

  • 4.a. Benchmarking(RP +Ball Mill Circuit)

    Internal Benchmarking

    Line Present Sp. Power Kwh/MT

    External Benchmark kwh/MT

    CM 1 25.09 24.37

    CM 2 26.49 25.90

    Grade Present Sp. Power Kwh/MT

    Internal Benchmarkkwh/MT

    OPC 25.30(Lowest across UTCL)

    25.30

    PPC 26.27(3rd lowest across UTCL)

    25.68

    ** Normalized SPC (kWh/MT) of PPC in RP+ Ball Mill Circuit at 380 m2/kg cement Blaine, 30 % fly ash & 300 m2/kg fly ash Blaine

    Benchmarking Source: UltraTech Technology & Performance Monitoring Cell Benchmarking report

    External Benchmarking

    Benchmarking Source: In reference to CII Energy benchmarking report for Indian Cement Industry (May 2019, V-4).

    Short term & Long Term Target

    Line Present Sp. Power Kwh/MT

    Short Term Target (Mar’21)kwh/MT

    Long Term Target (Mar’22)kwh/MT

    CM 1 25.09 24.71 24.37

    CM 2 26.49 26.20 25.90

  • 4.b. Encon initiatives planned in 2020-21

    S.No Encon projects planned in 2020-21Approx. SavingsLac units/annum

    1 Installation of separate Kaiser compressor for Line-2 bulk Loading operation. 1.08

    2 Direct coupling of bag filter fans (4 Nos) at line 1 0.69

    3 Direct coupling of bag filter fans (4 Nos) at Packing plant 0.43

    4Installation of Powerless diverters in place of motorized diverters (3 no's) in Packing plant

    0.18

    5Replacement of 70 watts conventional lights with 18 watts LED lights in phase manner (60 no's)

    0.13

    6Replacement of 400 watts conventional lights with 200 watts LED lights in phase manner. (24 Nos)

    0.19

    7Modification of K22 BC7 discharge so that direct feeding of limestone is done to its hopper at Line 2

    0.11

    8Reduction in Separator Power consumption by installing Vortex plate in SKS Separator.

    0.32

    9Installation of Proxy sensor device on the belt to identify the bags on the belt and accordingly should trip for delay in no bags on belt.

    0.08

    10Optimization of Bag filter fan speed by modifying cleaning cycle with reference to differential pressure of bag filter in Packing Plant

    0.14

    Total energy Savings expected (Lac Units/annum) 3.35

  • 5. Energy Saving projects implemented (FY 2017 -20)

    613 11

    166.60

    60.71

    138.86

    160.71

    51.41

    121.1

    0

    20

    40

    60

    80

    100

    120

    140

    160

    180

    2017-18 2018-19 2019-20

    Summary

    Proposals (Nos) Investment (Rs in Lacs) Savings (Rs in Lacs)

  • 5. Energy Saving projects implemented (FY 2017 -20)

    Sl. No Project DetailsInvestments(Rs in Lacs)

    Savings per annum(Rs in Lacs)

    Payback(Years)

    1Installation of Thin Classifying Liners at line 1 (2019-20)

    105 74.24 1.41

    2Installation of Expert Optimizer at Line 1 & 2(2019-20)

    52.00 30.00 1.73

    3Installation of energy efficient impeller for C-194 Seperator fan. (2019-20)

    21.34 15.59 1.37

    4Installation of Airtron energy conservation units for AC's (2019-20)

    9.43 5.86 1.61

    5Direct Coupling of C142 & C318 Bag Filter Fans (2019-20)

    0.35 1.85 0.19

    6 Installation of VFD for P&V system (2019-20) 1.10 1.77 0.62

    7Installation of air control valves for segregating compressed air lines of PP from CM at line 1 & 2 (2019-20)

    2.20 1.71 1.29

    8Temperature interlocking of VFD Panels with their inverter cooling fans - 8 Nos (2019-20)

    0.05 1.59 0.03

    9Silo top BE3 discharge chute modification thereby eliminated the usage of 2.2 KW blower (2019-20)

    0.20 0.78 0.26

  • 5. Energy Saving projects implemented (FY 2017 -20)

    Sl. No Project DetailsInvestments(Rs in Lacs)

    Savings per annum(Rs in Lacs)

    Payback(Years)

    10Replacement of Water Cooled fixed speed Compressor with VSD air cooled compressor. (2018-19)

    16.32 20.27 0.81

    11Installation of 1 HT VFD & 5 LT VFD’s in CM 1 & Packing Plant (2018-19)

    45.61 22.09 2.06

    12BCN rake loading bay extension to reduce the loading hours (2018-19)

    4.80 3.91 1.23

    13Reduction in Solar Deemed Generation by connecting solar power to Line 2 Cement Mill (2018-19)

    1.15 5.28 0.22

    14Replaced Conventional lighting 70 Watt SV lamp into LED 18 Watt in Cement Mill 1 & 2 area.(450 Nos) (2018-19)

    1.43 5.20 0.28

    15Replaced fluorescent lights 72 watts with 18 watts LED tubes at offices & load center areas (250 Nos) (2018-19)

    1.00 3.00 0.33

    16Regradation & Optimization of Grinding Media.(Weight of Grinding Media Before - 235MT; After 220MT) (2017-18)

    18.00 86.94 0.21

    17Cement transfer from line-1 to line-2 by providing air slide. (2017-18)

    91.75 55.41 1.66

  • 1. Thin Classifying Liners:Line-1 Hotgi Cement Works was installed in 1995 is of Polysius make containing Polycom + Ball mill

    circuit. The Ball mill has bolted normal class shell liners, which were in use since inception except for

    minor replacement for normal wear and tear. Entire liners need to be replaced for smooth running of

    mill as life of existing is completed.

    Instead of going for bolted normal class shell liners again, we installed thin classifying liners of AIA

    make, which gave us additional benefit of reduction in specific power consumption by 1 kwh/MT.

    Installation Month & Year: Aug’2019.

    Investment Cost: Rs. 105 Lacs

    Savings expected per annum: Rs. 74.24 Lacs

    Replication potential: Yes, can be replicated in all ball mills.

    6. Innovative Projects implemented

  • 6. Innovative Projects implemented

    2. Installation of Expert Optimizer at both line 1 & 2: Expert Optimizer is a hybrid intelligent-system product developed by ABB for expert closed-loop process control and

    optimization of cement grinding processes. It possesses human-like knowledge within specific domain. It makes

    decisions and takes actions to improve plant performance & to reach profitability and sustainability goals.

    Main benefits of Expert Optimizer:

    Increase in output & Reduction in power consumption.

    * Estimated savings in 0.4 kwh/t

    Installation Month & Year: Feb’2019

    Investment Cost: Rs. 52 Lacs

    Expected Annual Savings: Rs. 30.00 Lacs

    Replication potential: Yes, can be replicated in all cement plants.

    3. Airtron Control Units for Packaged AC (AC Energy Savers): At Line 2, AC systems - 8 Nos (24 Nos AC compressors) at MCC/ substation are being continuously operated 24 hours a

    day for maintaining the healthy condition of Equipment's. Estimated Electrical Consumption per Day - 1030 kwh.

    Resulting in running expenses around Rs. 21.05 Lacs / annum.

    Installed Airtron Controller units (ON/OFF duty cycle ratio) with Frigitech Solution

    for AC systems to obtain 20 % savings in power consumption. Average electrical

    consumption per day after installation is 731 kwh (23.65%).

    Installation Month & Year: Dec’2019

    Investment Cost: Rs. 9.43 Lacs

    Expected Annual Savings: Rs. 6.16 Lacs

    Replication potential: Yes, can be replicated in all cement plants.

  • 6. Innovative Projects implemented

    4. Reduction in Solar Deemed Generation by connection Solar power to Line 2:

    Issue: Earlier solar power was connected to line-1 load, whenever line-1 was stopped, the generation was considered

    under deemed. Hence we were incurring loss by compensating non-utilised solar power.

    Work carried out: Spare HT capacitor feeder used as Solar incomer 2 for line 2 load and configured the reverse power protection with the help of M/s Siemens on 6.6 KV panel. Provided reverse power option for line-2 incomer. Provided castle interlocking keys for solar breaker 1&2 with new drive box arrangement thereby reduced the changeover time & increased the human safety.

    Benefits: Solar power can be utilized for both line 1 & 2 thereby reduced the solar deemed generation.

    Avoided stoppage of packing plant, cement transfer circuit from line-2 to line-1 during change over

    Installation Month & Year: Nov’2018

    Investment Cost: Rs. 1.15 Lacs

    Expected Annual Savings: Rs. 3.51 Lacs (0.63 lac units)

    Replication potential: Site Specific.

  • 6. Innovative Projects implemented

    5. Enhancement of Truck Loaders capacity (In house): Issue: Truck loading machines 2 and 3 of packer-1 has a limitation for loading up to 27 MT. More retention of 32MT

    trucks due to unavailability of infrastructure (32 MT trucks had to wait till the loading of other 32 MT trucks is finished

    on TLM 1 & 4).

    Work carried out: In house modification done by increasing the length of luffing by 750 MM & feed trolley by 1500 mm.

    Now all 4 Nos truck loaders of Packer 1 can be used for loading 32MT vehicles.

    Benefits:

    • Shift out put increased by 228MT by loading 32MT trucks continuously thereby eliminated 1.5 Hours of Packer 1 &

    its loading belts operation. Approximate savings of 0.86 Lac units/annum - Rs 4.78 Lacs

    • Purchase of new higher capacity machine is avoided thereby saved Rs 40.00 Lacs.

    • Meets the Logistic requirement. Gain from market by increase in shift output is Rs 16.40 Lacs per annum.

    • Avoided retention time (idle hours) of 32MT trucks.

    Month & Year: Jul’2017

    Investment Cost: Rs. 4.00 Lacs

    Expected Annual Savings: Rs. 21.18 Lacs

    Replication potential: Yes, can be replicated in all packing plants where truck loading capacity is 27 MT.

    Before After

  • 6. Cement transfer from Line 1 to Line 2 by air slide: At Hotgi Cement Works, average Sp.Power Consumption of line-2 is more than line-1. There was a huge

    difference of 3 Kwh/MT. Cement transport through belt conveyors was available from line-2 to line-1

    but there was no infrastructure to transfer cement from line-1 to line-2. Wagon bulk loading system is

    available at line 2 only.

    Provided an air slide duct between line-1 to line-2 along with bag filters to transfer cement from line-1

    to line-2 thereby reduced the Specific Power by 2.4 kwh/MT by increasing the utilization of line-1

    Month & Year: Aug’2017

    Investment Cost: Rs. 91.75 Lacs

    Expected Annual Savings: Rs. 55.41 Lacs

    Replication potential: Site Specific

    6. Innovative Projects implemented

  • 7. Utilisation of Renewable Energy sources

    YearInvestment(in million)

    Onsite/OffsiteGeneration

    Installed Capacity / Enhanced Capacity

    (MW)

    Power Generation (million kWh)

    % of overall electrical

    energy

    2018-19 52.96 Onsite 1.00 1.03 1.67

    2019-20 Nil Onsite - 1.34 1.96

    • Solar power generation was started from 20th June 2018 with installed capacity of 1 MW.

    • Achieved 2.81 MU against RPO target of 1.83 MU in 2 years.

    • RPO obligation – Yes (Solar obligation is fulfilled against wheeling power).

  • Environment Compliance status

    8. GHG Inventorisation

    HOCW

    PM Limit

    as per

    MoEF

    PM Cement mill

    NOXLimit as

    per MoEF

    NOX

    SOXLimit as

    per MoEF

    SOX

    UOM mg/Nm3 2017 2018 2019 µg/M3 2017 2018 2019 µg/M3 2017 2018 2019

    Line 1 Cement Mill ESP

    30 29.83 21.48 16.76 - NA NA NA - NA NA NA

    Line 2 Mill Vent Bag

    House30 24.01 22.47 16.11 - NA NA NA - NA NA NA

    Line 2 Seperator Vent

    30 27.05 23.34 16.21 - NA NA NA - NA NA NA

    AAQM - NA NA NA 80 12.87 9.96 8.61 80 27.61 28.10 25.11

  • Public disclosure

    8. GHG Inventorisation

    Environment display board displays

    daily monitoring results of Air

    Emissions & control, STP, Hazardous

    waste generation etc.

    Continuous monitoring & display of

    ambient Air quality from AAQMS &

    data transfer to MPCB & CPCB.

  • 8. GHG Inventorisation

    S.No InitiativesAmount Invested

    Rs. In Lacs

    1. Installation of Ambient Air Quality Monitoring System (3 Nos)Stack

    Monitoring124.82

    2. Construction of Rain Water Harvesting Pits – 2 NosWater

    conservation1.48

    3 290 trees were planted under tree plantation scheme. Green Belt

    development0.32

    4 Water tanker used for suppression of dust emission Dust control

    initiative0.36

    5Cement Mill outlet, Seperator Bag house, other bag filters inspection & bags replacement at CM, WT, PP & RMH areas

    Dust control initiative

    6.34

    6Spiral chute installation, Vent line modifications, discharge chute modifications, skirt board modifications at CM, WT, PP & RMH areas.

    Dust controlinitiative

    5.97

    7Stopped usage of plastic bottles, plastic covers inside the plant.

    Environment 0.18

    Total (Rs in Lacs) 139.50

    Safeguarding Environment

  • 8. GHG Inventorisation

    Green Belt Development

    265

    87.45124.55

    0

    50

    100

    150

    200

    250

    300

    Total Area (Acres) Area to be developed (Acres) Green Belt area till date

    Green Belt

    Total Area (Acres) Area to be developed (Acres) Green Belt area till date

    Green belt should cover 33.0% of entire area

    47%

  • Environmental thinking in Supply Chain Management:

    • Clinker is sourced from Rajashree Cement Works, where AFR used as partial fuel in clinkerisation process thereby conserving fossil fuel reserves and reduce greenhouse gas emissions. Rajashree Cement Works is ISO 14001 & ISO 50001 certified plant.

    • Dry Ash which is waste product of power plant is used in making blended Cement. 35% dry ash is used in PPC whenever there is availability of dry ash from nearby NTPC which is a ISO 14001 certified plant.

    • Dry Ash is also obtained in jumbo bags through rake from distant sources in large quantities (bulk transport) & increased the PPC production to meet the market requirements. Road transportation is eliminated thus reducing GHG emissions.

    • Pond Ash which is also a waste product of power plant is used while making blended Cement. Increased the Pond Ash utilisation from 5% to 15% to cater the market requirement.

    • Chemical Gypsum which is a waste product of chemical industry is used at 50% for production of all grades of cement.

    • Replaced CFC truck with Diesel tanker (2500 L capacity) for procuring the diesel for plant operations.The result is that quantity of Diesel required in a month for plant operations is obtained in 6 trips through diesel tanker compared to 12 trips of CFC truck thereby reducing GHG emissions.

    9. Green Supply Chain Management

  • Monitoring system of Energy Consumption: 1) Daily Performance Review meeting chaired by Unit Head

    2) Monthly Performance Review meeting chaired by Cluster Head

    Sections covered during daily & monthly review meetings related to energy:

    a) Specific Power consumption of all grades. b) Packing Plant Power Consumption.c) Miscellaneous Power Consumption (Lighting, Material handling, utilities, Wagon Tippler).d) Power Wheeling – Wheeling lossese) Solar Power (renewable energy) generation – Deemed Generationf) Initiatives to be taken/action plan for reduction in power consumption.g) Comparison of specific power & flyash consumption with other grinding units in UltraTech.

    • Brainstorming sessions are conducted every quarter involving all the employees to generate ideas/suggestions for reducing the power consumption. Cross functional Task force teams are formed to implement the identified power saving initiatives.

    Budget for Energy Conservation: System in UltraTech Cement business:

    • All the energy conservation proposals from integrated plants, grinding units & bulk terminals will be sent to TPMC (Technology & Performance Monitoring Cell – includes SME’s) & Projects department at Head Office under Capex for review & finalisation. Proposals get sanctioned/approved based on the savings, investment, pay back, availability of cash flow etc.

    • TPMC will also have separate budget for implementing the new energy conservation initiatives across UltraTech (POC will be done at single/multiple units) & approved initiative will be implemented/ recommended to applicable units in UltraTech.

    10. Teamwork, Employee Involvement & Monitoring

  • Projects implemented from suggestions given by workers and supervisor - Kaizens

    • Bucket Elevator 3 discharge chute modified thereby eliminated the usage of 2.2 KW blower for transferring of

    material into silo. Estimated Annual Savings: 0.78 Lac units

    • Local start stop push button provided for all flyash compressors at flyash

    unloading area. Operator can stop compressor immediately after

    completion of unloading. Idle run hours are minimized.

    Estimated Annual Savings: 0.57 Lac units

    • Temperature interlocking of VFD Panels with their inverter cooling fans.

    Provided temperature interlock with converter and inverter cooling fan,

    whenever VFD panel become idle after stopping the motor, cooling fans

    will stop after attaining desired temperature.

    Estimated Annual Savings: 0.22 Lac units

    • Installed 11 no's body cleaning blowers covering all the locations in plant thereby eliminated usage of compressed

    air for body cleaning & reduced the load on compressors.

    • Operation of bore wells through mobile starter thereby eliminated idle running hours, saved water & time.

    • Provision of hooter at wagon loading machines for diversion of bags towards desired wagon loading machine

    without stopping the belt & bag diverting operating panel is also placed near the loaders

    10. Teamwork, Employee Involvement & Monitoring

  • 11. Other Innovative technologies implemented

    ONLINE ROLLER PRESS GEAR BOX MONITORING SYSTEM: Objective: To avoid unplanned stoppages by detecting Gear and bearing failures of Gearbox in earlier stage.

    Technology Adoption: Installed the Dalog system for continuous online monitoring of critical Gearbox internal parameters and to carry out offline root cause analysis. Alarms will be triggered & email will be sent to responsible persons if there is any abnormality observed.

    Benefits: 1.Optimize Production Process. 2. Stable Mill Operation. 3. Detect Wear in Early Stage. 4. Avoid Subsequent Damage

    Installation Month & Year: Sep’2018

    Investment Cost: Rs. 79.64 Lacs

    Replication potential: Yes, can be replicated in all cement plants.

    SERVER ANTENNA WITH TORQUE SENSOR FIXED ROLLER

    SPEED SENSOR

    TORQUE SENSOR

  • Long Term Target of Energy Efficiency

    12. Long Term Vision on EE

    Line Present Sp. Power Kwh/MT

    Long Term Target (Mar’22)kwh/MT

    CM 1 25.09 24.37

    CM 2 26.49 25.90

    S.No Initiatives to be taken Support required Remarks

    1To increase the PPC production by using more dry flyash (up to 35%) thereby reducing the Sp. Power & clinker factor.

    Supplier engagement

    Availability of fly ash from nearby source (NTPC) gotreduced.

    2Upgradation of Packers at line 1 to increase productivity & decrease power consumption. (12 spouts to 16 spouts)

    FinancialCapex sanctioned in FY21 for Rs 110 Lacs. Planned to complete in FY22.

    3Replacement of conventional rollers with stud rollers in Polycom / Roller Press at line 1 & 2.

    Technical & Financial

    Technical & cost benefit discussions are in progress.

    4Replacement of Pneumatic slide gate with Hydraulic at Line 2 Roller Press

    FinancialReplacement planned in next year.

    5Installation of Low Pressure compressors in place of IR compressor at Line 2 for fly ash unloading.

    FinancialCapex Proposed – Rs 14 Lacs (ROI is > 2.5 Years)

    6Replacement of Overloaded, under loaded & inefficient motors with IE3/IE4 motors.

    FinancialCapex Proposed – Rs 26 Lacs (ROI is > 4 Years)

  • Accomplishments

    • Hotgi Cement Works Bagged a “Certificate of Merit” from NSCI Maharashtra Chapter for achieving “ZERO” Accident frequency rate for the year 2018.

    • In 2019-20, Hotgi Cement Works is the unit with least grinding specific power in OPC grade (RP + Ball Mill Circuit) across the UltraTech which includes integrated & grinding units. (Source – UTCL TPMC Benchmarking report)

    • Hotgi Cement Works is the highest pond ash consuming grinding unit (RP + Ball Mill Circuit) across the UltraTech. We have Increased the Pond Ash usage from 5% to 15% and increase the PPC Production thereby reducing the clinker factor.

    • UltraTech has received Green Pro certification from Confederation of Indian Industry’s (CII) Indian Green Building Council for its Portland Pozzolana Cement and Composite Cement products.

    Any other relevant information

  • Thank You

    [email protected]+91 7744051100

    mailto:[email protected]

Recommended