User Manual Plant Maintenance Preventive Maintenance – Strategy Plan (Multi cycle) 1
Transcript
Page 1: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

Preventive Maintenance – Strategy Plan (Multi cycle)

1

Page 2: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

Abbreviations

R Required entry field (used in the end-user procedures)

O Optional entry field(used in the end-user procedures)

C Conditional field(used in the end-user procedures)

2

Page 3: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

Contents

Preventive Maintenance........................................................................................4

Purpose..............................................................................................................4

Creation of equipment task list..............................................................................5

Creating Of maintenance Packages ..................................................................5

Assign Maintenance Strategy To Task List..........................................................7

Creating Maintenance Plan ...............................................................................9

Scheduling Maintenance Plan..........................................................................10

Order Processing..............................................................................................11

Displaying Planned/Actual Costs..........................................................................

Closing the Internal Repair Order - Technically....................................................

Settling the Internal Repair Order.....................................................................12

Closing the Internal Repair Order – Business View..............................................

3

Page 4: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

Preventive Maintenance

Purpose

Ensuring a high availability of objects in the long term is an important part of Plant maintenance. Planned maintenance is used to avoid system breakdowns or the breakdown of other objects, which - in addition to the repair costs - often result in much higher costs subsequently owing to production breakdown.

Process Flow

In this business process you can use maintenance planning to describe the dates and scope of plan for maintenance and inspection activities at technical objects. You can ensure that your technical objects are maintained on time and thereby function optimally. The system generates maintenance call objects during the scheduling process. You begin to process by creating an order in the system.

After the preventive maintenance is carried out, the costs and materials are confirmed to the maintenance order. The costs are settled to the cost center.

Organizational and Master Data

The following data is used within the scenario:

Value Description

Company code Specify Specify

Plant: Specify Specify

Vendor Specify specify

Purchase organization Specify Purchasing Org.

Person Specify Specify

4

Page 5: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

Transactions for Service Processing

Creating a Technical Object of Type “Machines”

Use

The purpose of this activity is to create the piece of equipment in the system.

Procedure

1. Access the transaction using one of the following navigation options:

SAP menu Logistics Plant Maintenance Management of Technical Objects Equipment Create (General)

Transaction code IE01

2. On the Create Equipment: Initial screen, make the following entries:

Field Name Description User Action and Values

Comment

Valid On Enter today’s date

Equipment category

M

3. Confirm your entries with Enter.

4. On the Create Equipment: General data screen, make the following entries:

Field Name Description User Action and Values

Comment

Description Enter text of your choice that describes the equipment to be created

For example:

IR Dryer

5. Confirm your entries with Enter.

6. On Location tab page, make the following entries:

Field Name Description User Action and Values

Comment

MaintPlant specify 1000

5

Page 6: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

7. Confirm your entries with Enter.

8. On Organization tab page, make the following entries:

Field Name Description User Action and Values

Comment

Cost Center Specify 1702

Main Work Ctr specify MAINT-WC

9. Confirm your entries with Enter.

Creating a Task list for equipment

Use

You can use maintenance task lists for both recurring and planned maintenance. This includes inspections, preventive maintenance and planned repairs. This results in improved resources planning, production planning and machine availability.

1. Access the transaction using one of the following navigation options:

SAP menu Logistics Plant Maintenance Preventive Maintenance Work scheduling Task ListFor EquipmentCreate

Transaction code IA01

2. On the Create Equipment Task List: Initial screen, make the following entries:

Field Name Description User Action and Values

Comment

Key Date Enter today’s date

Equipment Number

M

6

Page 7: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

3. Confirm your entries with Enter.

4. Make the following entries in the Task list general header view for the equipment

Field Name Description User Action and Values

Comment

Group counter Specify 1

Description Specify

Usage Specify 4

Main Work Ctr specify MAINT-WC

Status Specify 4

Maintenance Specify

7

Page 8: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

Strategy

System condition

Specify

5. Select the operations key present at the top of the screen and enter the following,

Field Name Description User Action and Values

Comment

Operation Description

Specify

work Specify Eg: 15 Min

Units Specify Min/hr

Main Work Ctr specify Maint-wc

8

Page 9: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

Number Specify 1

6. Select the operation and maintenance package button at the bottom of the screen and check in the box for the execution of the operation depending on the strategy

9

Page 10: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

7. Save the entries.

8. Equipment Task list is created.

Creating Maintenance plan

Use

You can create maintenance plans for the technical objects in your company, thereby ensuring that your technical objects function optimally. The maintenance plan contains scheduling information from the following sources: For strategy plans from the maintenance strategy assigned to the maintenance plan

10

Page 11: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

1. Access the transaction using one of the following navigation options:

SAP menu Logistics Plant Maintenance Preventive Maintenance Maintenance Planning Maintenance Plans Create Strategy Plan

Transaction code IP42

2. On the Create Maintenance plan: Initial screen, make the following entries:

Field Name Description User Action and Values

Comment

Maintenance plan category

Specify Maintenance Order

strategy Specify P.MAIN

11

Page 12: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

3. Confirm your entries with Enter.

4. Make the following entries in the Create Maintenance plan: Strategy Plan.

Field Name Description User Action and Values

Comment

Description Plan description

Specify

Equipment Specify Search for the equipment using the input help (F4) (Equipment by equipment list tab page)

12

Page 13: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

Order Type PM01 – Internal Repair Order

Priority Specify

5. Confirm your entries with Enter.

6. Enter the task list for the equipment.

Field Name Description User Action and Values

Comment

Task list type Specify

Group Specify

Group counter Specify

13

Page 14: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

7. Select the maintenance plan scheduling parameters tab, and make the following entries

Field Name Description User Action and Values

Comment

Scheduling period

Specify

Start of the cycle

Specify

8. Save the maintenance plan, and system issues message maintenance plan XXX created.

14

Page 15: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

Scheduling Of Maintenance Plan

Use

You schedule a maintenance plan with which the system generates maintenance call objects (for example, maintenance orders or service orders) for the defined cycles.

1. Access the transaction using one of the following navigation options:

SAP menu Logistics Plant Maintenance Preventive Maintenance Scheduling For Maintenance Plans Schedule

Transaction code IP10

2. Enter the maintenance plan number

15

Page 16: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

3. Confirm the entries with enter.

4. Enter start of the cycle and press enter

16

Page 17: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

5. Save the schedule and the system issues the message as maintenance plan is scheduled.6. Select the schedule maintenance plan,

17

Page 18: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

7. Select the call object and press display call object button at the bottom.

Procedure

1. Access the transaction using one of the following navigation options:

SAP menu Logistics Plant Maintenance Maintenance Processing Order Change

Transaction code IW32

2. Select the correct item and choose Enter.

3. On the Change Maintenance Order: central header, select Header Data or choose Enter.

18

Page 19: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

4. On the Change Maintenance Order: Central Header screen, enter a description .

5. On the Internal Maintenance Order: Components Tab screen make the following entries:

Field Name Description User Action and Values

Comment

Component Specify

Description spare part required

Specify

Reqmtn Qty quantity required 1

UM Unit of measure Specify

19

Page 20: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

6. Confirm your entries with Enter.

7. On the Components tab, select item 0010 and choose Purchasing.

Goods Movements For Components

Use

In This Activity , Components are Reserved & Goods Issue is done for the Maintenance Order.

Procedure

1. Access the transaction using one of the following navigation options:

SAP menu Logistics Plant Maintenance Maintenance Processing Order Change

Transaction code IW32

20

Page 21: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

2. Go to Components Tab , Select the Component item & choose General data. Note the

Reservation number.

3. Go to Goods Movement Screen (T.code – MIGO), Enter the Reservation Number & click ENTER. Save the Screen.

4. Document posted number is generated on the screen.

21

Page 22: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

Time Confirmation of Maintenance Order

Use

The Purpose of this activity is to Enter the time taken for executing a Particular Job.

Procedure 1. Access the transaction choosing one of the following navigation options:

SAP menu Logistics -> Plant Maintenance -> Maintenance Processing -> Completion Confirmation -> Entry -> Individual Time Confirmation

Transaction Code IW42

1. Enter the Time taken to Execute the job.

2. Repeat the same process for other Operations.

3. For the Last Operation Enable Final Confirmation Indicator & No Remaining Work Indicator.

22

Page 23: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

Technical Confirmation Of Maintenance Order

Use

The purpose of this activity is to Record the Task & Activities done for executing a job.

23

Page 24: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

Procedure

1. Access the transaction choosing one of the following navigation options:

SAP menu Logistics -> Plant Maintenance -> Maintenance Processing -> Notification -> Change

Transaction code IW22

2. Task & Activities are entered using the Catalog Profile Copied from the Master Record.

3. After Entering Task & Activities , Click .

4. The Notification Status Changes to ATCO Which Means that All Tasks are Completed.

5. Once Again click Present on the Notification Header Screen Such that the Status Changes to NOCO Which means Notification is Closed.

24

Page 25: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

Displaying Planned/Actual Costs

Use

In this activity you check the planned/actual costs – specified for value categories.

Procedure

1. Access the transaction using one of the following navigation options:

SAP menu Logistics Plant Maintenance Maintenance Processing Order Display

Transaction code IW33

2. On the Change Order: Initial Screen, enter your order number created earlier and confirm your entry with Enter.

25

Page 26: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

3. Choose the Costs tab page to display the planned/actual costs.

Note the third-party material costs. Costs for specific value documents are displayed.

4. Choose the Report planned/actual icon.

Note the costs for the specific cost elements being displayed.

5. Check the data displayed and choose Back three times to return the SAP Easy Access menu.

26

Page 27: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

Closing the Internal Repair Order - Technically

Use

Once all the activities are complete and the completion confirmations are posted, you can set the status of the service order to technically complete.

Procedure

1. Access the transaction using one of the following navigation options:

Menu Logistics Customer Service Service Processing Order Service Order Change

Transaction code IW32

2. Enter your order number and confirm with Enter.

3. Check again that all expenses for the repairs have been entered on the Costs

tab page. You can also choose Document flow to display the assigned confirmation (double-click confirmation item) and choose Back.

4. Choose Complete (technically) to complete the service order technically.

5. Check the data in the complete message and confirm with Continue.

6. Confirm the Complete dialog box with Enter. The system issues a corresponding success message with the number of your document at the bottom of the screen.

7. To return to the SAP Easy Access menu, choose Back.

27

Page 28: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

Result

This completes the repairs technically and the device can be delivered to the customer.

Settling the Internal Repair Order

Use

The actual costs of the internal repair order are settled to the cost center.

Procedure

1. Access the transaction using one of the following navigation options:

Menu Logistics Customer Service Service Processing Completion Order Settlement Settle Individually

Transaction code KO88

28

Page 29: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

In the Set Controlling Area dialog box, enter 1000

2. On the Actual Settlement: Order screen, make the following entries:

Field Name Description User Action and Values Comment

Order Enter the service order number

Parameters

Settlement period

Current period

Fiscal year Current year

Processing options

Test run Deselect indicator

Check trans. data

Deselect indicator

3. Choose Execute.

4. To return to the SAP Easy Access menu, choose Back.

29

Page 30: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

Closing the Internal Repair Order – Business View

Use

In this activity, you complete the internal repair order.

30

Page 31: UM_STRATEGY_PLAN.doc

User Manual

Plant Maintenance

Procedure

1. Access the transaction using one of the following navigation options:

Menu Logistics Customer Service Service Processing Order Service Order Change

Transaction code IW32

2. Enter the service order number and press enter.

3. Choose Order Functions Complete Complete Business.

Result

The order attains the system status CLSD (closed) and can no longer be charged with costs.

31