+ All Categories
Home > Documents > Unit_2 Pengurusan Projek

Unit_2 Pengurusan Projek

Date post: 04-Jun-2018
Category:
Upload: anonymous-59kjvq4olb
View: 252 times
Download: 5 times
Share this document with a friend

of 20

Transcript
  • 8/13/2019 Unit_2 Pengurusan Projek

    1/20

    UNIT 2: CHART AND PROJECT IMPLEMENTATION

    SHCEDULE

    INTRODUCTION

    This unit will be discuss about the application of Bar Chart, Critical Path Method and

    Microsoft Project Basic Operation in the project management.

    2.1 BAR CHART METHOD

    Schedule is a tool; it can be used to manage, coordinate, control and report.

    Depending on the sophistication of the user, the schedule can take different forms.

    There are a number of different forms of schedules that may be used, including written

    schedules, bar graph, network schedules, and others.

    Bar Chart also called a Gantt Chart is graphically the most simple of scheduling

    methods. Bar Chart is one of the oldest scheduling technique and wide acceptance

    because it is readily understood by almost every one. It is very easy to develop and

    used, useful technique for a small project, task schedule can be graphically presented

    on the time-scale but the main weakness is that Relationship that exists between the

    tasks cannot be shown (no defined relationship). Figure 2.1(a) below shows Bar

    Charts that graphically simple, easily to read and understood, and inexpensive to

    produce.

  • 8/13/2019 Unit_2 Pengurusan Projek

    2/20

    Example 2.1

    From the Figure 2.1(b) below shows a simple bar graph schedule for a construction

    project. Calculate scheduled and actual cumulative progress and plotted for the first

    three weeks for physical progress of the project.

    Notes:

    The column headed Hours indicates the estimated number of labour-hours required

    for each activity. The column Weight indicates the portion of the total project effort

    accounted for by each activity. Notice that two horizontal blocks are provided opposite

    each activity. The upper block (SCH) represents scheduled progress and the lower

    block (ACT) is used to record actual progress as work proceeds. For each block, a barextends from starting to ending times. The number above each bar indicate

    percentage of activity completion at each major time division.

    The Normal Progress Curve or S-Curve is shown in Figure 2.1(c). As the curve

    indicates, progress is slow at the beginning of a project as work is organized and

    workers become familiar with work assignments and procedures. Thus, only about 15%

    of the project is completed in the first 25% of the project time. After that, progress is

    made at a rather constant rate until 85% of the work is completed at the end of 75% of

    project time. Progress again slows as finishing work and project demobilization take

    place.

  • 8/13/2019 Unit_2 Pengurusan Projek

    3/20

    Figure 2.1(b)

    Figure 2.1(c)

  • 8/13/2019 Unit_2 Pengurusan Projek

    4/20

    Solution:

    Step 1 : Calculate Weighting Factors

    Example, Clearing and Stripping activity required 750 labour-hours of work, which

    represent 4.7% of the 15,900 labour-hours required for the entire project.

    (750 / 15900 ) x 100% = 4.7%

    Step 2 : Calculate Scheduled Cumulative Progress and plotted

    Cumu lat ive prog ress = Activ i ty Progress x Weight

    Example calculation for the scheduled cumulative progress for the first three weeks of

    the project as follow.

    End of First Week

    Progress Activity 1 = (0.20 x 4.7) = 0.9%

    End of Second Week

    Progress Activity 1 + Activity 2 + Activity 3

    = (0.70 x 4.7) + (0.60 x 0.9) + (0.15 x 26.4) = 7.8%

    End of Third Week

    Progress Activity 1 + Activity 2 + Activity 3

    = (1.00 x 4.7) + (1.00 x 0.9) +(0.40 x 26.4) = 16.2%

    Step 3 : Calculate Actual Cumulative Progress and plotted

    End of First Week

    Progress Activity 1 = (0.00 x 4.7) = 0.0%

    End of Second Week

    Progress Activity 1 + Activity 2 + Activity 3

    = (0.45 x 4.7) + (0.30 x 0.9) + (0.05 x 26.4) = 3.7%

  • 8/13/2019 Unit_2 Pengurusan Projek

    5/20

    End of Third Week

    Progress Activity 1 + Activity 2 + Activity 3

    = (1.00 x 4.7) + (1.00 x 0.9) + (1.00 x 26.4) = 16.2%

    Step 4 : Draw Progress Curve

    Frequently, cumulative progress curves for a project are superimposed on the project s

    bar graph schedule as illustrated in Figure 2.1 (d).

  • 8/13/2019 Unit_2 Pengurusan Projek

    6/20

    Exercise 2.1

    Q1. Discuss about the effective of planning in construction management.

    Q2. From the Table 2.1(a) below shows that small project activities.i. Draw the bar chart using graph paper.

    ii. Try to track Schedule vs Actual for physical progress of the project

    No. List of activities SchedulePeriod (Week)

    Successor Actual Period (Week)

    1 Setting Out & Excavation 3 2 4

    2 Footing 2 3 2

    3 Ground Beam 2 4,5 2

    4 Slab 1 - 1

    5 Column 3 6 1

    6 Roof Beam 1 7,8 0

    7 Brick Wall 7 - 0

    8 M & E 7 9 0

    9 Building Envelope 2 10 0

    10 Ark. Finishing 3 - 0

    Table 2.1(a)

  • 8/13/2019 Unit_2 Pengurusan Projek

    7/20

    2.2 CRITICAL PATH METHOD (CPM)

    2.2.1 LOGICAL RELATIONSHIP OF PROJECT ACTIVITIES

    Understand the order of how the job to be accomplished in the field. The planner must

    understand how various activities of the project related to each other in term of their

    logical sequence. Example preparing formwork before reinforcement could be place &

    than pouring concrete.

    2.2.2 PREDECESSORS AND SUCCESSORS

    The project network indicates the order in which activities may be performed. From

    the Figure 2.2 (c), activity A is a Predecessor of activity B and activity B is a

    successors of activity A.

  • 8/13/2019 Unit_2 Pengurusan Projek

    8/20

    From the Figure 2.2 (d) :, Activity D has predecessors A, B & C. Only one activity is

    allowed between two verticles; dummy activities may be defined if necessary (with

    zero duration). Activities (3,5) and (4,5) are dummy activities with zero duration

    Figure 2.2(d) : Dummy activities

    In this module there are two type of network methods. There is Precedence Diagram

    Method (PDM) and Arrow Diagram Method (ADM) but only Arrow Diagram Method

    (ADM) will be discuss in detail for this unit.

  • 8/13/2019 Unit_2 Pengurusan Projek

    9/20

    2.2.3 PRECEDENCE DIAGRAM METHOD (PDM)

    Precedence Diagram Method (PDM) also known as Activity On Node (AON). PDM

    activity is place on the node. The arrow used to connect between project task to showtheir logical relationship. From the Figure 2.2 (e) shows that structure of PDM diagram

    for pad footing.

    Figure 2.2(e)

    See the example below, Table 2.2 (a) shows list of tasks, predecessor and duration ofproject. Figure 2.2 (f) is a network diagram using PDM. The diagram must draw from

    start until end of activity.

    Figure 2.2 (f)

    bzzz

  • 8/13/2019 Unit_2 Pengurusan Projek

    10/20

    Task Predecessor Duration

    A none 5

    B A 3

    C none 3

    D B 2

    E B,C 4

    F D 4

    G D 2

    H E 8

    I A 5

    J F,G,H 3

    Table 2.2 (a)

    2.2.4 ARROW DIAGRAM METHOD (ADM)

    Arrow Diagram Method (ADM) also known as Activity on Arrow (AOA. In arrow diagram

    project task or activities are represented by the arrow and connected by the node to

    express their logical relationship. Each activity as illustrated in Figure 2.2 (g) must start

    and terminate at an event (represent by a circle). Events are numbered for identification

    purposes and event numbers are also utilized to identify activities on the diagram.

    Thus activity 5-6 refers to the activity starting at event 5 and ending at event 6.

    Following are formula time, must to calculate from start activity until end. From the

    calculation, Latest Time of Finish Event (LF) for last activity is actually a total project

    period.

    i. ES is the Earliest Time of Start Event

    EF = ES + Duratio n

    ii. LS is the Latest Time of Start Event

    LS = LF Duration

  • 8/13/2019 Unit_2 Pengurusan Projek

    11/20

    iii. EF is the Earliest Time of Finish Event

    iv. LF is the Latest Time of Finish Event

    v. Activity duration (D) is the time to complete an activity

    Figure 2.2 (g): Arrow diagram notation

    Figure 2.2 (h) and Figure 2.2 (i) shows a simple network diagram for a constructionproject. As mentioned earlier, the diagram graphically indicates the relationships

    between activities. Activities progress in the direction shown by the arrows. Good

    diagramming practice requires that diagrams present a clear picture of the project logic

    and generally flow from left to right. Arrows should not point backward, although they

    may point straight up or down.

    Notice the dashed arrow in Figure 2.2 (h) and Figure 2.2 (i). This is called dummy

    activity or simply a dummy . Dummies are used to impose logic constraints and prevent

    duplication of activity numbers. They do not represent any work and, hence, always

    have a duration of zero.

  • 8/13/2019 Unit_2 Pengurusan Projek

    12/20

    Figure 2.2 (h): Arrow Diagram Method (ADM)

    Figure 2.2 (i) : Arrow Diagram Method (ADM)

  • 8/13/2019 Unit_2 Pengurusan Projek

    13/20

    Task Predecessor Duration

    A none 5

    B A 3

    C none 3

    D B 2

    E B,C 4

    F D 4

    G D 2

    H E 8

    I A 5

    J F,G,H 3

    Table 2.2 (b)

    Example 2.2

    From the Table 2.2 (c) and Figure 2.2 (j) below ;

    i. Calculate ES,EF,LS,LF from the project activities.ii. Determine critical line

    iii. Determine project period

    Bil List of activities completed period

    (Week)

    1 Site Clearing 4

    2 Setting Out 3

    3 Piling 2

    4 Pile Cap & stump 2

    5 Ground Beam 4

    6 Slab 2

    7 Column 3

    8 Roof Beam 4

    Table 2.2 (c)

  • 8/13/2019 Unit_2 Pengurusan Projek

    14/20

    Figure 2.2 (j) : Arrow Diagram Method (ADM)

    Solution:

    Step 1: Calculate ES,EF (forward pass)

    Forward Pass a process to find the earliest start time for all activities.

    Site Clearing work

    Node 1 & 2

    Start ES at first node with 0, ES1=0

    Calculate EF use this formula, EF = ES + Duration

    EF2 = ES1+Duration EF2 = 0+4 = 4

    Setting Out work

    Node 2 & 3

    ES2 =4 (Start from Node 2,ES2=EF2)

    Calculate EF use this formula, EF = ES + Duration

    EF3 = ES2+Duration EF3 = 4+3 = 7

  • 8/13/2019 Unit_2 Pengurusan Projek

    15/20

    Piling work

    Node 2 & 4

    ES2 =4 (Start from Node 2,ES2=EF2)

    Calculate EF use this formula, EF = ES + Duration

    EF4 = ES2+Duration EF4 = 4+2 = 6

    Dummy

    Node 3 & 4

    ES3 =7 (Start from Node 3,ES3=EF3)

    Calculate EF use this formula, EF = ES + Duration

    EF4 = ES3+Duration EF4 = 7+0 = 7

    Now we have two arrow from node 2 and node 3 meet at node 4. From the Forward

    Pass Theory, we must take the largest time of EF4 before continuing define ES4 for

    Ground Beam work. Between 6 and 7, the largest must be 7, then fill 7 in the EF4 box.

    Figure 2.2 (k)

  • 8/13/2019 Unit_2 Pengurusan Projek

    16/20

    Continue calculate the ES and EF until finish (node 9) and fill in the table below.

    Activity Duration ES EF LS LFSite Clearing 4 0 4

    Setting Out 3 4 7

    Piling 2 4 7

    Pile Cap & Stump 2 4 11

    GB 4 7 11

    Slab 2 11 13

    Col 3 11 14RB 4 14 18

    Table 2.2 (c)

    Step 2 : Calculate LS,LF (backward)

    Backward a process to find latest finish time for all activities.

    Roof Beam work

    Node 9 & 8

    Start LF 9 at last node with same value of EF 9=18

    Calculate LS use this formula : LS = LF Duration

    LF8 = LF 9 - Duration

    EF 2 = 18-4 = 14

  • 8/13/2019 Unit_2 Pengurusan Projek

    17/20

    Figure 2.2(l)

    From the Backward Theory, if two arrow meet at one node, take the lowest time of LF

    between the two value. Continue calculate the LS and LF until finish (from node 9 until

    1) and fill in the table below.

    Activity Duration ES EF LS LF

    Site Clearing 4 0 4 0 4

    Setting Out 3 4 7 4 7

    Piling 2 4 7 4 7

    Pile Cap & Stump 2 4 11 4 12

    GB 4 7 11 7 11

    Slab 2 11 13 12 14

    Col 3 11 14 11 14

    RB 4 14 18 14 18

    Table 2.2 (d)

  • 8/13/2019 Unit_2 Pengurusan Projek

    18/20

    Figure 2.2 (m)

    Step 3: Determine critical line / critical path

    Critical line / critical path are the longest paths of the planning from start to finish.

    Usually the activity has same duration time start and finish. From the figure 2.2 (m), this

    project critical for activities of site clearing, setting out, ground beam, column and roof

    beam. The critical line is 1-2-3-4-5-8-9 with 18 week.

    Step 4 : Determine project period

    Total project period is 18 week

  • 8/13/2019 Unit_2 Pengurusan Projek

    19/20

    Exercise 2.2

    Q1. From the Table 2.2 (e) below shows list of project activity to construct the pad

    footing at Surau Sek Keb Sri Gading.

    i. Draw the logical network of the project

    ii. Calculate ES,EF,LS,LF from the project activities.

    iii. Determine critical line

    iv. Determine project period

    Nod List of activities Completed

    period (Week)

    1-2 Setting Out 2

    2-4 Excavation 4

    1-5 Order/prepare concrete material 1

    1-3 Order/prepare bar reinforcement 3

    3-4 Prepare Formwork 4

    4-6 install bar reinforcement & formwork 2

    5-6 Dummy -

    6-7 Concrete 2

    Table 2.2 (e)

  • 8/13/2019 Unit_2 Pengurusan Projek

    20/20

    Q2. From the Table 2.2 (f) below shows list of small project activities those undertaken by a

    contractor company.

    i. Draw the logical network of the project

    ii. Calculate ES,EF,LS,LF from the project activities.

    iii. Determine critical line & project period

    Bil List of activities Completed period

    (Week)

    1 1-2 4

    2 1-3 1

    3 1-6 12

    4 2-4 10

    5 3-5 8

    6 4-6 8

    7 5-6 8

    8 5-7 4

    9 6-8 8

    10 7-8 7

    Table 2.2 (f)


Recommended