+ All Categories
Home > Documents > UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

Date post: 04-Apr-2022
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
38
AFRICAN DEVELOPMENT FUND UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT FOR GOOD GOVERNANCE - PHASE THREE (ISPGG III) OSGE January 2016 Public Disclosure Authorized Public Disclosure Authorized
Transcript
Page 1: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

AFRICAN DEVELOPMENT FUND

UNITED REPUBLIC OF TANZANIA

INSTITUTIONAL SUPPORT PROJECT FOR GOOD GOVERNANCE -

PHASE THREE (ISPGG III)

OSGE

January 2016

Pu

bli

c D

iscl

osu

re A

uth

ori

zed

Pu

bli

c D

iscl

osu

re A

uth

ori

zed

Page 2: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

TABLE OF CONTENTS

Acronyms and Abbreviations

Currency Equivalents, Fiscal Year, Weights and Measures

Loan Information

Project Executive Summary

Results-based Logical Framework

Project Timeframe

I. PROJECT STRATEGIC THRUST AND RATIONALE

1.1 Project Linkages with Country Strategy and Objectives

1.2 Rationale for Bank’s Involvement

1.3 Development Partners Coordination

II – PROJECT DESCRIPTION

2.1 Project Components

2.2 Technical Solution retained and other alternatives explored

2.3 Project Type

2.4 Project Cost and Financing Arrangements

2.5 Project’s Target Area and Population: Beneficiaries

2.6 Participatory Process for Project Identification, Design and Implementation

2.7 Bank Group Experience and Lessons reflected in Project Design

2.8 Project’s Key Performance Indicators

III – PROJECT FEASIBILITY AND IMPACTS

3.1 Economic and Financial Performance

3.2 Environmental, Gender and Social Impacts

IV – IMPLEMENTATION

4.1 Implementation Arrangements

4.2 Financial Management, Disbursement and Audit

4.3 Procurement Arrangement

4.4 Monitoring and Evaluation

4.5 Governance

4.6 Sustainability

4.7 Risk Management

4.8 Knowledge-building

V – LEGAL INSTRUMENTS AND AUTHORITY

5.1 Legal Instruments

5.2. Conditions Associated with Bank’s Intervention

5.3 Compliance with Bank Policies

VI – RECOMMENDATION

i

ii

iii

iv

v

viii

1

1

2

4

5

5

8

9

9

11

11

12

13

13

13

13

14

14

15

16

17

17

18

18

19

19

19

19

20

20

Page 3: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

LIST OF TABLES

Table 2.1 : Project Components

Table 2.2 : Project alternatives considered and reasons for rejection

Table 2.3 : Project Cost Estimates by Component

Table 2.4 : Sources of Financing

Table 2.5 : Project Cost by Category of Expenditure

Table 2.6 : Expenditure Schedule by year

Table 2.7 : Lessons learned from Previous Operations and Other Analytical Reports

Table 4.1 : Project Implementation Schedule

Table 4.2 : Risks and Mitigation Measures

Appendices

Appendix I. Tanzania Selected Socio-Economic Indicators

Appendix II. Bank Group Portfolio in Tanzania

Appendix III. Donor Coordination Matrix for Tanzania

Appendix IV. Lessons Learned from ISPGG II and GECSP

Appendix V. Public Financial Management: 2013 PEFA Indicators

Appendix VI. ISPGG III Analytical Work Underpinnings

Appendix VII. Map of Tanzania

Page 4: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

i

Acronyms and Abbreviations

AfDB African Development Bank Group MEM Ministry of Energy and Minerals

ADF African Development Fund MoF Ministry of Finance and Planning

BRN Big Results Now MoU Memorandum of Understanding

CAG Controller & Auditor General MTFF Medium-term Fiscal Framework

CCM Chama Cha Mapidunzi MTR Mid-Term Review

CIDA Canadian International Development Agency NDP National Development Plan

CPI Corruption Perception Index NPS National Panel Survey

CPIA Country Policy and Institutional Assessment

CPPR Country Portfolio Performance Review PA&OB Public Authorities and Other Bodies

CSP Country Strategy Paper PAF Performance Assessment Framework

DfID Department for International Development

DPs Development Partners PBO Program Based Operation

EARC East Africa Regional Resource Centre PE Public enterprises

EIPC Energy Infrastructure Procurement Coordinator PCR Project Completion Report

EPP Emergency Power Plants PEFA Public Expenditure and Financial

Accountability

EU European Union PFM Public Financial Management

EWURA Energy and Water Utilities

Regulatory Authority

PFMRP Public Financial Management Reform

programme

FDI Foreign Direct Investment PPP Public private Partnerships

FM Financial Management PPRA Public Procurement Regulatory Authority

FYDP Five Year Development Plan PRSP Poverty Reduction Strategy Paper

GBS General Budget Support PSP Private Sector Participation

GCI Global Competitiveness Index REA Rural Energy Agency

GDP Gross Domestic Product RMC Regional Member Countries

GECSP Governance and Economic

Competitiveness Support Programme

SIDA Swedish International Development

Cooperation Agency

GOT Government of Tanzania SOE State-Owned Enterprises

IFMIS Integrated Public Financial Management

Information System

STAMICO State Mining Corporation

IPP Independent Power Producers TANESCO Tanzania National Electric supply Company

IPTL Independent Power Tanzania Limited TPDC Tanzania Petroleum Development

Corporation

IPSAS

ISPGG

International Public Sector Accounting Standards

Institutional Support Project for Good Governance

TYS Ten-Year Strategy (AfDB)

JAST Joint Assistance Strategy of Tanzania TZFO

TZS

Tanzania Field Office

Tanzania Shilling

JICA Japan International Cooperation Agency UA Units of Account

KPIs Key Performance Indicators USAID United States Agency for International

Development

LGA Local Government Authorities USD United States Dollars

MDA Ministries, Departments & Agencies VAT Value Added Tax

MDG Millennium Development Goals WB World Bank

Page 5: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

ii

Currency Equivalents

As of November 2015

1 UA = TZS 3,026.08

1 USD = TZS 2,166.33

1 UA = USD 1.40

Fiscal Year

1st July – 30th June

Weights and Measures

1 metric tonne = 2204 pounds (lbs)

1 kilogramme (kg) = 2.200 lbs

1 metre (m) = 3.28 feet (ft)

1 millimetre (mm) = 0.03937 inch (“)

1 kilometre (km) = 0.62 mile

1 hectare (ha) = 2.471 acres

Page 6: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

iii

Loan Information

Client’s information

RECIPIENT: United Republic of Tanzania

EXECUTING AGENCY: Ministry of Finance and Planning

Financing plan

Source Amount (UA) Instrument

ADF

12.00 million

Loan

GOT 1.33 million Counterpart Funds

TOTAL COST 13.33 million

Timeframe - Main Milestones (expected)

Concept Note approval

July 2015

Preparation

Appraisal

July, 2015

October, 2015

Project approval January, 2016

Effectiveness February, 2016

Mid-term Review June 2017

Completion December 2018

Last Disbursement June 2019

Page 7: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

iv

PROJECT EXECUTIVE SUMMARY Paragraph Topics covered

Project

Overview

Project name: Institutional Support Project for Good Governance-Phase Three (ISPGG III)

Geographic scope: Entire country

Implementation timeframe: 2016-2018

Project cost: UA 13.33 million

Expected Outcomes and Outputs: The expected outcomes are (i) Effectiveness in the management of public finances

improved; and (ii) Business enabling environment improved. This will be achieved through the following output level

results: (i) Procurement capacity strengthened; (ii) External audit capacity enhanced; (iii) Internal audit function

strengthened; (iv) Business registration and licensing regime modernised; (v) Anti-corruption measures and capacity

strengthened; (vi) Capacity to implement the PPP framework developed.

Project direct beneficiaries: The direct project beneficiaries are: the Ministry of Finance and Planning, the Public

Procurement Regulatory Authority (PPRA), Internal Auditor General’s Office (IAGO), the Controller and Auditor

General (CAG), the Prevention and Combatting of Corruption Bureau (PCCB) and the Ethics Secretariat in the Mainland.

For Zanzibar, the beneficiaries are the following institutions: MoF, Zanzibar Investment Promotion Agency (ZIFA),

Department of Stock and Verification, the Accountant General’s Office, the Zanzibar Office of the Controller and Auditor

General, the PPP Unit and the Ministry of Trade. The indirect beneficiaries are the general population of Tanzania, who

will benefit from improved value for money in public procurement, improved service delivery arising from transparency

and accountability and enhanced economic opportunities, including employment creation, arising from stimulation of

private sector investments as a result of improved business climate. Benefits will also accrue to women as a result of the

project’s support to gender-based audits, capacity building for women’s effective participation in public procurement

activities. The private sector will also benefit from improved PFM (a competitive and transparent procurement system)

and PPP opportunities.

Needs

Assessmen

In spite of achievements in macroeconomic performance, there are still weaknesses in the implementation of policy and

institutional reforms, particularly in PFM, business enabling environment and overall public sector governance. Apart

from the need to continue the fight against corruption, stakeholders have highlighted challenges arising from lack of

appropriate reforms sequencing, poor institutional arrangements and implementation capacity constraints. Thus, under

this project, the focus of Component 1 is informed by PFMRP IV which aims to address these challenges through five

key result areas: (i) performance, scope and coverage of IFMIS; (ii) cash management; (iii) flow of funds; (iv) quality of

financial reporting and auditing; and (v) domestic revenue mobilisation and budget management. Through PFMRP, GOT

has been reforming its PFM systems over the past decade, enacting new laws (on procurement, audit and PFM), reviewing

policies and procedures , designing new systems such as IFMIS and establishing new institutions like IAGO. The full

benefits of these reforms are yet to be realised in terms of fiscal discipline, enhanced domestic resource mobilisation,

strategic allocation of resources and effective service delivery. GOT therefore designed a medium-term PFMRP to

address the challenges. The proposed project will complement implementation of PFMRP IV. In the area of the business

environment, the 2016 Doing Business Report ranked Tanzania 139/189 countries, a one step improvement over the 2015

ranking of 140/189. The same report ranked Tanzania 122/189 on the starting business score, respresenting a slippage of

7 steps from the 2015 rank of 129th position. The Government recognizes the private sector as a key engine of economic

growth, with a strong potential to play a critical role in contributing towards achieving Vision 2025. However, based on

the Government’s own assessment, the business environment in Tanzania is characterized as being cumbersome, heavily

bureaucratic, and costly and this reality is reflected in Tanzania’s relatively low ranking in global performance indices.

The Global Competitive Index for example has identified corruption and inefficient government bureaucracy as key

weaknesses, among others. This necessitated the introduction of the the Business Environment Improvement (BE)

Priority Area under Big Results Now, following the Government’s recognition of the need to create an enabling

environment for the private sector to not only effectively do business, but also to thrive and contribute towards job creation

and economic growth. Two of the six National Key Results Areas (NKRAs) are (i) realigning regulations and institutions

and (ii) curbing corruption. Three main intervention areas under BRN are (i) streamlining legal and regulatory

frameworks; (ii) modernizing processes; and (iii) building institutional and individual capacity. The choice of focus areas

of Component II of ISPGG III was guided by these priorities.

Bank’s

Added Value

The project builds upon Bank-supported capacity building and PFM reforms in Tanzania, and complements DPs’

interventions. Experience from ISPGG I and ISPGG II, and budget support operations, generated lessons which informed

the design of the project. TZFO facilitated understanding of the political context and technical issues, and this enriched

project design. In addition, the Bank is seen by GOT as a reliable and trusted partner. The strong basis for policy dialogue

built over the years makes it easy to engage with the government on critical and sensitive issues such the the fight against

corruption. The Bank’s vast experience in implementing similar projects across the continent is also a source of value

addition.

Knowledge

Management

The Project will contribute to knowledge building through skills transfers, from consultants and training providers, to

staff of beneficiary institutions. Knowledge will also accrue from appropriate study visits to sensitise public officials on

best practices in institutions in other countries. In addition, the support under PPPs will generate knowledge on best

practices in this important area, in terms of PPPs design and assessment, value for money analysis and measurement of

the risks and necessary mitigation actions. The Bank will disseminate knowledge through sharing findings of supervision

missions, progress reports, and the Project Completion Report. Lessons learned will inform future operations.

Page 8: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

v

RESULTS-BASED LOGICAL FRAMEWORK

Country and project name: Tanzania: Institutional Support Project for Good Governance III

Purpose of the project: Promote inclusive growth and macroeconomic stability by enhancing economic and financial governance

through more effective public financial management and improved business environment..

RESULTS CHAIN PERFORMANCE INDICATORS

MEANS OF

VERIFICATION

RISKS/MITIGA

TION

MEASURES Indicator

(including CSI) Baseline

Target

IMP

AC

T

Improved economic

performance

Real GDP Growth 2013/14

7.3% 2018/19

7.8%

IMF report Risk 1:

Implementation

capacity constraints.

Weak implementation capacity within

Government.

Mitigation: Continue supporting targeted

TA interventions.

Existing PIU also to

be used to manage and

coordinate project

implementation. TZFO will also

provide

implementation support, in addition to

supervision missions

Risk 2: Fiduciary risk.

Although Tanzania has

made good progress in strengthening

institutions and

addressing corruption, weaknesses still

remain, and these will

continue to pose a risk

Mitigation: Project

support will improve

fiduciary environment.

Compliance with the

Bank’s procurement of

goods and services, annual audit reports

and training.

iii. The new

Government’s

commitment to

reforms:

It is not clear if the

newly elected Government’s reform

priorities will be the

same as those of the previous Government.

Mitigation: Persistent dialogue with the new

Government and the

key sector stakeholders.

Private Investment as share of GDP 23.9% 26% IMF report

OU

TC

OM

E

Effectiveness in the

management of public

finances improved

Accountability, control and scrutiny

of public finances (as measured by

PEFA)

% of unqualified audit opinions

2013

PI-21: D+

PI-26: C+

90%

2018

PI-21: B

PI-26: B+

95% (2018)

PEFA

CAG Annual

Report

Public Procurement compliance rate 65% (2014)

75% (2018)

PPRA annual

report

Business enabling

environment improved

Starting a business score (WB Doing

Business)

78.63 (2015) 83 (2018)

WB Doing

Business

Corruption Perception Index score 31 (2014) 34 (2018) Transparency

International CPI

Number of public procurement bids

awarded to women entrepreneurs

N/A (2014) 100 bids (2018) Progress reports

Supervision

reports

OU

TP

UT

S

Component 1: Enhancing the effectiveness of public financial management

1.1 Procurement capacity

strengthened

E-procurement infrastructure

installed

No e-

procurement infrastructure installed

(2015)

E-procurement

infrastructure

installed (2018)

Progress reports

and Supervision

reports

Number of procuring entities

strengthened through roll out of e-

procurement applications

0 (2015) 200 (2018)

Progress reports

Supervision

reports

Guidelines for monitoring and

auditing PPP projects developed and

disseminated

No

guidelines

(2014)

Guidelines

developed and

disseminated

(2016)

Progress reports

Supervision

reports

Procurement operational manual

updated

Old

Procurement

manual

(2014)

Procurement

manual

updated (2016)

Progress reports

Supervision

reports

Study on cost overruns/variations

during contract execution conducted

No study

conducted

(2014)

Study report

prepared

(2016)

Progress reports

Supervision

reports

Page 9: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

vi

Training (including for women

entrepreneurs) (number of

beneficiaries, with at least 30%

women)

Gender policy for TANESCO

0 (2014)

No Gender

Policy in

place

(2014)

250 (2017)

Gender

Policy

prepared

(2016)

Progress reports

Supervision

reports

1.2. External audit capacity

enhanced

Audit offices equipped with hardware

and software: new offices in Dodoma

No new

installations

(2014)

Office

hardware and

software

installed

Progress reports

Supervision

reports

Audit guidelines on emerging themes

such as oil & gas, PPP

Number of

audit

manuals/gui

delines

developed

0 (2014) 4 (2016)

Training and study tours for CAG,

ZAO, including those targeting CSOs

and Parliamentarians conducted

(number of beneficiaries (with at

least 30% women)

0 (2014) 150 (20157) Progress reports

Supervision

reports

1.3: Internal audit function

strengthened

Study on the effectiveness of

governance arrangements in selected

key processes in PSOs conducted

No study

conducted

(2014)

Study report

prepared (2016)

Progress reports

Supervision

reports

Internal audit of government budget

process and payroll conducted

No audit of

conducted

Audit

conducted

Progress reports

Supervision

reports

Training for IAG staff, audit

committee members and

management teams in MDAs/LGAs

conducted (number of beneficiaries

(with at least 30% women)

0 (2014) 100 (2017)

Progress reports

Supervision

reports

IAG capacity strengthened through

enhanced connectivity

No new

LAN/WAN

installations

(2014)

LAN/WAN

installed

(2017)

Progress reports

Supervision

reports

Component 2: Creating an enabling environment for private investments

2.1. Business registration and

licensing regime modernised

Relevant business laws and

regulations on procedures to start a

business amended

Old laws in

place

Rel Relevant business

laws amended

Progress reports

Supervision

reports

Legislation to enable online license

processing developed

No enabling

law in place

Enabling law

developed

Progress reports

Supervision

reports

Online portal for licenses and

procedures established

No online

portal in

place

Online portal

developed

Progress reports

Supervision

reports

2.2 Anti-corruption measures

and capacity strengthened

Number of PCCB staff trained on

forensics, investigation techniques,

asset tracing and money laundering

(at least 30% women)

0 (2014) 300 (2017) Progress reports

Supervision

reports

PCCB district offices capacitated

through installation of Local Area

Network for district offices

No LAN for

district

offices

Integrated LAN

installed

Progress reports

Supervision

reports

Page 10: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

vii

Develop National Anti-corruption

Policy

No anti-

corruption

policy (2014)

Anti-corruption

policy

developed

(2016)

Progress reports

Supervision

reports

Reinforce the Ethics Secretariat’s

capacity to conduct asset

verification.

No asset

verification

framework in

place 92014)

Asset

verification

framework

developed

(2017)

Progress reports

Supervision

reports

2.3 Capacity to implement the

PPP framework developed

Draft PPP Manual reviewed to

synchronise with new PPP Law

Draft PPP

Manual in

place (2014)

PPP Manual

finalised an

approved

(2016)

Progress reports

Supervision

reports

PPP feasibility studies conducted

No PPP

feasibility

studies

(2014)

2 PPP

feasibility

studies

conducted

Progress reports

Supervision

reports

PPP training (including on gender

responsive aspects) conducted

(number of beneficiaries, with at

least 30% women).

0 75 Progress reports

Supervision

reports

KE

Y

AC

TIV

ITI

ES

COMPONENTS INPUTS

Component 1: Enhancing the effectiveness of public financial management

Component 2 : Creating an enabling environment for private investments

Inputs : - Funding in million UA

ADF : UA 12 million

GoT: UA 1.33 million

Total project cost: UA 13.33 million

Page 11: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

viii

Table 1: Project Implementation Schedule

Tanzania: Institutional Support Project for Good Governance III

Years Action By

Quarter Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2

Activities

Project life cycle

Loan approval AfDB

Fulfilment of conditions for disbursement GoT

Start of the project and launch AfDB & GoT

Supervision and Monitoring AfDB

Mid-term review AfDB/ GoT

Disbursement of Funds AfDB

Aubmission of annual audit reports GoT

Government completion report GoT

AfDB Project Completion Report AfDB

All Components

General Procurement Notice published GoT

Recruitment of contractors GoT

Contract local partner training institute GoT

Procurement of IT equipment and software GoT

Submission of progress reports from contractors GoT

Training and workshops GoT

2016 2017 2018 2019

Page 12: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

1

REPORT AND RECOMMENDATION OF MANAGEMENT TO THE BOARD OF

DIRECTORS ON A PROPOSED LOAN TO THE UNITED REPUBLIC OF

TANZANIA TO FINANCE THE INSTITUTIONAL SUPPORT PROJECT FOR GOOD

GOVERNANCE PHASE THREE (ISPGG III)

Management submits the following Report and Recommendation on a proposed ADF Loan of

UA 12 million to the United Republic of Tanzania to finance the ISPGG III.

I. STRATEGIC THRUST AND RATIONALE

1.1 Project Linkages with Country and Bank Strategies and Objectives

1.1.1 The proposed operation is strongly anchored on the Tanzania National Strategy

for Growth and Reduction of Poverty II (NSGRP II ). The overarching objective of the

Strategy is to (i) promote growth and reduction of income poverty; (ii) improve the quality of

life and social well-being of the Tanzanian people; and (iii) enhance good governance and

national unity. For the Mainland NSGRP II focuses on three broad clusters: (i) growth and

reduction of income poverty; (ii) improvement of quality of life and social well-being; and (iii)

governance and accountability. For Zanzibar, the Zanzibar Strategy for Growth and Reduction

of Poverty (ZSGRP II) focuses on (i) growth and reduction of income poverty; (ii)

improvement of social services and well-being; and (iii) good governance and national unity.

In 2012, GOT unveiled the Long Term Perspective Plan (LTPP) operationalized through a

series of Five-Year Development Plans (FYDPs) to steer implementation of Vision 2025. GOT

has also launched the Big Results Now (BRN) initiative, to improve efficiency in the

implementation of policies and strategies. To fast track implementation of FYDP, projects

identified under BRN have been prioritized into seven National Key Results Areas: energy,

water, agriculture, transport, education, business

environment and resource mobilization. A Presidential

Delivery Bureau has been established to assess

implementation progress against performance indicators.

The proposed operation, ISPGG III, is designed

specifically to continue to contribute to, and consolidate,

the gains that have been registered in Tanzania in the

Bank’s support of capacity building in the public sector.

These gains, clearly evident in the on-going turn-around

of key oversight institutions, should be consolidated as

they are critical for successful implementation of the

country’s medium term development strategy..

1.1.2 The proposed operation is complementary to

the Government’s multi-donor supported Public

Finance Management Reform Programme (PFMRP

IV) launched in 2012 to support efforts to realise the

national policy objectives of Vision 2025, FYDP and

MKUKUTA//MKUZA II (the National Strategy for

Growth and Reduction of Poverty II). As is the case with the proposed operation, the PFMRP

IV is designed to, among other objectives, improve planning and budgeting, and promote

transparency, accountability and efficiency in the use of public resources. Thus the Bank

Group’s proposed project complements and reinforces the capacity-building support of other

development partners (DPs).

Box I: PFMRP IV Objectives

The objective of PFMRP IV, 2012/13 –

2016/17 is stated as strengthening and

improving PFM systems in a more

coordinated manner, to meet fiscal

policy challenges. It is desgned to

support MKUKUTA/MKUZA II and

Vision 2025, with 3 key elements to

achieve: (i) fiscal sustainability and

balance in the public sector; (ii)

restructuring and reallocations for

growth and poverty reduction; and (iii)

improved public sector efficiency and

effectiveness in administration for

improved service delivery and

development results for Tanzanians.

Page 13: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

2

1.1.3 The project will complement the on-going Bank-supported PFM reforms under the

Power Sector Reform and Governance Support Programme (PSRGSP) approved in May,

2015. It will contribute to further strengthening key oversight institutions that played a critical,

and commendable role in dealing with the recent IPTL alleged corruption Case in the energy

sector. In the process, the project will focus on further strengthening compliance with financial

regulations governing use of public resources, in line with International Public Sector

Accounting Standards (IPSAS); enhance transparency, competition and professional standards

in public procurement; strengthen GOT’s capacity to oversee IFMIS transactions; and improve

fiscal control and reporting at the local level through upgrading IFMIS. Under ISPGG III,

improved oversight, compliance and controls will contribute to improved PFM environment

which, in turn, will generate increased mobilisation and effective use of domestic resources.

The proposed operation will be well co-ordinated with PFMRP IV, to avoid duplication of

effort and ensure a comprehensive framework for development partners’ dialogue with GOT,

with a view to ensuring that DP interventions are aligned with national priorities .

1.1.4 The proposed project is aligned with the Bank’s Tanzania Country Strategy Paper

(CSP 2011-2015) aimed at supporting the country achieve greater competitiveness and

more inclusive growth through two pillars: (i) Infrastructure Development and (ii)

Building an enabling institutional and business environment. It is consistent with the CSP’s

emphasis on supporting reforms and capacity development in PFM to improve the

macroeconomic and business environment, including promoting transparency in public

procurement. Through further improvements to procurement systems, corruption will be

reduced and competition enhanced, with positive impact on the business environment. By

focusing on capacity enhancement for PFM reform and business climate improvements, the

proposed project is aligned to the Bank’s Ten Year Strategy 2013-2022 (good governance and

private sector development). It is reinforced by two of the new Bank Group High-5 institutional

priorities, namely (i) Industrialize Africa (through the business enabling environment

supporting business registration and licensing, anti corruption and Public-Private-

Partnerships); and (ii) Improve the quality of life of the people of Africa (through the PFM

interventions which will help improve effectiveness in the management of public finances,

enhance economic performance and hence, the quality of life of Tanzanians). The proposed

project is also consistent with all three pillars (Public Sector and Economic Management,

Sector Governance, and Investment and Business Climate) of the Governance Strategic

Framework and Action Plan (GAP II, 2014-2018): GAP II seeks to build effective and capable

institutions, promote transparency and accountability, and improve the business climate,

thereby enhancing the quality of growth. The project is also aligned with the Private Sector

Development Strategy. In addition, by ensuring that women are deliberately given the

opportunity to benefit significantly from the capacity building activities under the project, and

by developing a gender policy and supporting gender-based auditing, the operation is

consistent with the Bank Group’s Strategy on Gender.

1.2 Rationale for Bank’s Involvement

1.2.1 The socio-economic challenges facing Tanzania require continued pursuit of

institutional capacity building in order to fight corruption, improve efficiency and

transparency in the management and utilisation of public resources, and improve the business

enabling environment. Fully achieving the GOT objectives in these critically important areas

of governance will take time, is still a works-in-progress, and requires continued Bank support.

1.2.2 Through earlier capacity building projects (ISPGG I-II), the Bank provided

support to the strengthening of public procurement, external audit and anti-corruption

functions, which contributed to improving transparency and accountability in PFM to

Page 14: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

3

enhance quality of the budget processes. Positive results were registered in strengthening

CAG and PCCB, improving value for money audit and public procurement; and improving

procurement compliance rates. For example, PEFA (PI-26) on scope, nature and follow up on

external scrutiny of audit improved from C in 2008 to C+ 2013; CAG improved from

AFROSAI –E rating Level 1 in 2008 to level 3 in 2013; and the compliance rate of procuring

entities improved from 50% in 2008/09 to 64% in 2012/13. While these achievements are

commendable, more needs to be done. Further capacity building is required to address existing

weaknesses as well as deal with new and

emerging challenges such as the audit of oil and

gas

activities and PPP projects. The weak internal

audit function also remains a challenge, hence

the addition of the Internal Auditor General to

the list of beneficiaries under ISPGG III.

1.2.3 The proposed intervention will,

therefore, further build capacity of the

selected institutions to enable the effective

implementation of reforms in PFM, in

particular strengthening financial controls

and compliance with existing PFM systems

in accounting, IFMIS and procurement.

GOT is continuing to pursue policy and

institutional reforms to improve PFM. These

reforms need continued support. The PFM

outstanding reform agenda calls for sustained

human and institutional capacity development,

as well as plugging loopholes that cause

revenue losses. It is in this context that GOT has recognized the need to strengthen financial

controls and compliance, in order to mobilise required resources to support poverty reduction

and inclusive growth efforts.

1.2.4 The proposed operation will contribute to addressing weaknesses in PFM and the

business environment, and intensifying and sustaining capacity building efforts in

Tanzania. While improvements have been recorded in areas such as the legal environment and

budget procedures, the full benefits of the reforms are yet to be realised for optimal controls,

accountability, fiscal discipline and improved service delivery. With PFMRP IV currently

under implementation, the proposed project has identified areas for complementary support to

enhance capacity development. Recent PFM assessments, PEFA reports and other analytical

works have identified a number of weaknesses in Tanzania’s PFM systems, which have been

taken into account in the design of this project. The key challenges are summarized in Box 3.

Weaknesses also persist in the area of the business environment. The business environment in

Tanzania has long been characterized as cumbersome, heavily bureaucratic, and costly. This reality

is reflected in Tanzania’s relatively low ranking in global performance indices. Amongst the most

critical factors that negatively affect the business environment is corruption, which increases

the cost of doing business, thereby rendering Tanzanian businesses less competitive. The

project complements efforts of other DPs who are focussing on various related aspects of

governance, such as local government reform, PFM, macroeconomic management, public

sector reform and anti-corruption.(see Appendix III).

Box 2: Achievements of ISPGG I and II ISPGG I and II contributed to improving transparency and

accountability in PFM to enhance quality of the budget

processes, and support efforts to reduce fiscal deficits and

stimulate economic growth. They have helped in

strengthening oversight institutionsISPGG I contributed to

(i) improving compliance of procurement entities with the

Procurement Act 2004 from 39% in 2005 to 50% in 2008/09;

(ii) formulating anti-corruption strategy in procurement; (iii)

establishing procurement cadre in the public service; (iv)

reducing time to dispose of court cases by 400% in Zanzibar;

and (v) issuance of the audited accounts of Zanzibar on time

as from FY 2007/08. These achievements were consolidated

under ISPGG II, which represented an appropriate use of

resources for Tanzania, when the country was experiencing

worsening fiscal deficits and needed to strengthen PFM.

The operation deepened PFM reforms and mainstreamed

anti-corruption initiatives. Achievements included (i)

improved value for money audit; (ii) improved value for

money in public procurement; and (iii) improved

procurement compliance rates. In addition, GOT made

good progress in increasing implementation of CAG’s

audit recommendations.

Page 15: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

4

1.2.5 An added value of this operation lies in the fact that the Bank is seen by GOT as a reliable

and trusted partner. Hence, the strong basis for policy dialogue built over the years makes it

easy to engage with the government on critical and sensitive issues such as the fight against

corruption. The Bank’s vast experience in implementing similar projects, both in Tanzania and

across the continent, is also a source of value addition.

1.2.6 Analytical Works Underpinning: The design of this project is guided by various

analytical and diagnostic reports as well as broad consultations during the preparation

and appraisal missions. The main analytical underpinning is provided by the PFMRP IV Mid-

Term Review Draft Final Report (July, 2015); PPRA Annual Reports; the Reforming Tanzania

Public Sector Report: An Assessment and Future Direction (November, 2013); the BRN

Strategic documents; the Public Expenditure and Financial Accountability (PEFA)

assessments; Corruption Perception Index; the World Bank June 2015 Development Policy

Operation (DPO) for Tanzania; the 2014 General Budget Support Annual Review, Final Report

(September, 2015); World Bank Doing Business Report 2015 and 2016; and World Economic

Forum Global Competitiveness Report 2014 and 2015. Discussions with other DPs on PFM,

PPP and overall capacity building have also provided a basis for the project design and

identification of complementary areas of focus. In addition, lessons have been drawn from

previous operations of both the Bank and other development partners. The lessons include the

need to: (a) further strengthen implementation capacity in PFM institutions; (b) limit the

number of activities envisaged, and conditions set, in project design, in order to avoid putting

excessive burden on GOT implementation capacity: this will assist avoid the risk of slippages

in project execution; (c) strengthen Information Management and filing systems; (d) achieve

stronger Tanzania performance in domestic resource mobilisation to finance its development

programme; and (e) implement projects and programmes within the existing GOT/DPs

coordination structures: this will enhance complementarity and avoid duplication of effort.

Box 3:.Key Challenges in Tanzania’s PFM Systems and the Business Environment

A. The updated Country Fiduciary Risk Assessment concurs with the PEFA 2013 analysis which stated that

major PFM challenges include managing the non-salary internal controls. GOT is committed to PFM reforms

through its PFM strategy and other initiatives. The required safeguards to mitigate the key risks/weaknesses,

such as non-salary internal controls, are being addressed in the PFMRP IV and are discussed annually through

a dialogue of DPs and GOT with key issues put in the Performance Assessment Framework (PAF) and the

PFMRP IV supervised annually with the Bank’s participation. The Bank has also been supporting the PFM

strategy through the ISPGG I and II operations.

B. Corruption negatively affects the business environment in Tanzania by increasing the cost of doing

business, which renders Tanzanian businesses less competitive. Government bureaucracy is also a major avenue

for bribery and corruption and could be minimized through enhancing the capacity of anti-corruption bodies

such as PCCB, and use of automation to reduce the time to process applications for business registration and

licenses. Despite the putting in place of a PPP framework, Tanzania has not succeeded in attracting significant

investment flows through PPPs. Building capacity to help operationalize the PPP framework is therefore critical.

1.3 Development Partners’ Coordination

1.3.1 Development partners’ support to Tanzania is coordinated by the Ministry of

Finance and Planning, responsible for aid mobilisation, coordination and reporting.

Development partners’ collaboration is generally good, but there is room for improvement of

the aid coordination mechanism particularly in budget support. There are mechanisms for DP

coordination, particularly through the Sector Working Groups, although these SWGs need to

be strengthened. PFM reform dialogue is conducted through the PFMRP IV framework, in

Page 16: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

5

which the Bank participates through the Field Office, TZFO, which has been active in

institutional capacity and PFM dialogue between GOT and development partners.

1.3.2 The Ministry of Finance and Planning requested development partners to align

and coordinate their assistance for institutional support and overall capacity building in

the public sector. With technical assistance from development partners, the Ministry

developed PFMRP IV, which provides a framework for coordinated DP support. The DPs in

the Multi-Donor Trust Fund (MDTF) around PFMRP IV include DFID (UK), Canada,

Germany, Denmark, Ireland and Finland; a potential new member in the near future could be

Norway. The proposed project will strongly complement the MDTF PFMRP IV, through

targeted focus on accounting and audit, procurement and financial control, anti-corruption, and

overall support for measures and actions enhancing transparency and accountability in the

public sector. The contribution of the various DPs to capacity building in Tanzania is presented

in Appendix III.

II. PROJECT DESCRIPTION

2.1 Project Components

2.1.1 Project Objectives: The proposed project’s broad development objective is to support

GOT in promoting inclusive growth and macroeconomic stability by enhancing economic and

financial governance through more effective public financial management and improved

business environment. It will support efforts geared towards enhancing capacity, accountability

and integrity in the management of public resources by key oversight and economic/finance

institutions. It will also help the fight againts corruption; the streamlining of business

registration and licensing processes and operationalising the PPP framework.

2.1.2 Project Components: The project has two components: (i) Enhancing the

Effectiveness of Public Financial Management and (ii) Creating an Enabling Environment for

Private Investments.

Component 1: Enhancing the Effectiveness of Public Financial Management

The objective of this Component is to strengthen the procurement function through

capacity building of PPRA, particularly in new and emerging areas such as PPP and the

oil and gas sector. The training will also target women entrepreneurs to facilitate their access

to public procurement opportunities. The Component will address specific procurement issues,

conduct studies and prepare Manuals and Guidelines for effective operationalisation of the

public procurement framework, in line with the Public Procurement Act and related

regulations. It will support interventions geared towards the development of e-procurement in

Tanzania. This includes both the installation of the e-procurement infrastructure and the roll-

out of the system to procuring entities. Capacity building support will also be provided to the

Public Procurememt Regulatory Authority (PPRA) to develop appropriate tools and guidelines

that will enable the Authority to effectively perform its monitoring role, particularly in the

emerging oil and gas sectors of the economy. The review and implementation of the system for

checking and monitoring compliance will hence be boosted. In addition, this Component will

also strengthen the internal and external audit funtions, to ensure that strong control systems

are in place within the Government’s PFM system and that there is adequate accountability in

the use of public resources. Support to this function will be delivered through capacity building

and the use of ICT (both hardware and software) for more effective and efficient delivery of

the internal and external audit mandate. The training will also target gender, through capacity

building for gender-based auditing and the development of a gender policy for TANESCO,

Page 17: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

6

which is one of the commitments under the on-going Bank-financed PSRGSP, covering policy

dialogue in public procurement, among other intiatives.

Component 2: Creating an Enabling Environment for Private Investments

The objective of this Component is to support GOT’s ongoing efforts to increase private

investments in Tanzania by creaing a more conducive environment for business activity.

This support will be channelled through three interventions. First, modernise the business

registration and licensing regime to improve the current lengthy and costly procedures to

register a business in Tanzania (particularly Zanzibar). According to the 2015 World Bank

Doing Business Report, starting a business in Tanzania requires 9 procedures and takes 26

days, placing the country at a ranking of 129th out of 189 economies on ease of starting a

business, representing a slippage of 7 steps from the 2015 ranking of 122. Secondly, address

the problem of corruption, which is not only an issue for the public sector, but for the private

sector as well, given its impact on the cost of doing business and, hence, on the competitiveness

of Tanzania as an investment destination. According to Transparency International’s 2014

Corruption Perception Index, Tanzania ranked 119 out of 175 countries, compared to 111 out

of 177 countries in 2013, a slippage of 8 steps. The recent alleged corruption scandal involving

withdrawal of funds from Tegeta Escrow account, and related controversial transfer of

ownership of Independent Power Tanzania Limited (IPTL), brought the issue of corruption to

the fore in Tanzania. Hence, this intervention will build on the achievements of support to

PCCB through earlier Bank interventions (ISPGG I and II). It will also support the Ethics

Secretariat by helping to reinforce its capacity to conduct asset verifications, among other

activities. Thirdly, the Component will support GOT efforts to operationalise the PPP

framework. The recently amended PPP Law has helped to streamline the hitherto confusing

roles of numerous entities (Prime Minister’s Office, Ministry of Finance and Planning,

Tanzania Investment Centre) involved in the PPP process. Despite the existence of a PPP

framework, capacity for PPP implementation within government remains weak and so far

Tanzania has not succeeded in attracting significant amounts of private capital through PPP

arrangements.The project will support capacity building in PPPs, particularly by focusing on

project identification, appraisal and due diligence to help ensure value for money in PPP

transactions. It will also support review and finalisation of the PPP Manual/Guidelines, and

feasibility studies on three pilot PPP projects. These three sub-components of the Business

Environment Component of the proposed project are mutually reinforcing. By helping to

modernise the business registration and licensing regime, processes will be faster and this will

minimise the need to offer bribes for speedier processing of applications. This will in turn

contribute to a reduction in the cost of doing business, hence making Tanzania more

competitive. Theincreased competitiveness will in turn attract more private investments,

including through PPPs.

Table 2.1 presents a summary of major activities under the two project Components, and

Technical Annex B.2 presents a detailed budget for both the Mainland and Zanzibar over the

3-year peiod 2016-2018.

Table 2.1: Project Components and Estimated Cost

Components Component description Estimated

Cost

(UA’000)

Component 1: ENHANCING THE EFFECTIVENESS OF PUBLIC FINANCIAL MANAGEMENT

Page 18: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

7

Components Component description Estimated

Cost

(UA’000)

Sub-component 1.1:

Strengthening the

public procurement

function

This component will help to strengthen capacity in the areas of public

procurement, internal and external audit. The focus of the capacity building will

be on training, automation of systems and processes, development of manuals and

guidelines to help with process standardization. These interventions will

eventually help to enhance accountability, control and scrutiny of public finances,

enhance capacity to prepare and audit government accounts and improve public

procurement compliance rates.

The sub-component will undertake the following activities:-

Installation of infrastructure and roll out of e-procurement applications to

procuring entities

Guidelines for monitoring and auditing PPP projects developed and

disseminated

Procurement operating manual developed

Study on cost overruns/variations during contract execution conducted

Training and study tours

Workshops/seminars for women entrepreneurs for enhanced participation in

public procurement

2,873

Sub-component 1.2:

Enhancing the external

audit function

Through the sub-component, the project will support implementation of the

following activities:

Equipment and IT infrastructure installed for the Comptroller and Auditor

General’s Office

Training for CAG and ZAG staff

Capacity building of non-state actors (citizen engagement in the audit process)

2,005

Enhancing the internal

audit function

Through the sub-component, the project will support implementation of the

following activities:

Study on the effectiveness of governance arrangements in selected key

processes in PSOs conducted

Interna audit of the government budet process and payroll conducted

Training for IAG staff and audit committee members and management teams

in MDAs/LGAs conducted

1,792

Component 1 Sub-total 6,670

Component 2: CREATING AN ENABLING ENVIRONMENT FOR PRIVATE INVESTMENTS

Sub-component

2.1: Modernising the

busness registration and

licensing regime

This component will help to modernise the business registration and licensing

regime through automation and hence reduce the bureaucracy associated with such

processes. It will also strengthen capacity to fight corruption as well as build

capacity to operationbalise the PPP framework. These interventions will help

improve Tanzani’a overall business environment and hence attract private

investments.

Under this sub-component, the Project will support:

Amendments to relevant business laws and regulations on procedures to start a

busness

Development of legislation to enable online license processing developed

Development of a system for online business registration

1,499

Sub-component 2.2:

Capacity strengthening

for anti-corruption

Under this subcomponent, the Project will support:

Installation of Local Area Network for PCCB district offices

Development of National Anti-corruption Policy

Training and research for PCCB and Ethics Secretariat staff

Development of asset verification framework and related capacity building for

the Ethics Secretariat

2,597

Sub-component 2.3:

Operationalising the PPP

framework

Under this subcomponent, the Project will support:

Review and finalisation of the draft PPP Manual/Guidelines

PPP feasibility studies for pilot projects

Training ad technical assistance

1,347

Page 19: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

8

Components Component description Estimated

Cost

(UA’000)

Component 2 Sub-total 5,443

Component III: Project Management

The PIU team will be handling and coordinating all activities for the beneficiaries

both in Mainland and Zanzibar. Under this component, the project will support:

Project operating costs

Project audits costs

Training activities for the PIU teams

586

Phisical contingency (2%)

& Price contingency (3%)

634

TOTAL 13,133

2.2 Technical Solution Retained and Other Alternatives Explored

2.2.1 During project preparation and appraisal, the following technical issues were

explored regarding: areas of intervention; the number of institutions to support; the scale

of investments in each area; and the modality of delivering the capacity building support.

Based on these considerations, the recommendations from analytical works, as well as lessons

from the Bank’s and other DPs’ capacity-building operations, it was agreed with GOT to

continue to utilise the tried, tested and successful arrangements under ISPGG II to consolidate

the gains that have been achieved. As highlighted in the July 2015 Project Completion Report

(PCR) for ISPGG II, the technical arrangements used under ISPGG II have delivered the

expected results. these arrangements will thus be retained for ISPGG III. They involve

continuing with provision of training and technical assistance, supply of equipment, ICT

software and hardware, and other capacity building activities, through 2 PIUs, one for Zanzibar

beneficiaries and the other for the Mainland beneficiaries. The areas of focus of ISPGG III

were carefully selected to build on the achievements of ISPGG I and II, while also providing

for support to new pertinent emerging areas such as Public-Private-Partnerships. The use of

two PIUs, one for the Mainland and one for Zanzibar, has ensured that delays in one part of the

country do not affect the other part, while at the same time provding opportunities for

experience-sharing between the two PIUs. This arrangement has proven to be successful and

will hence continue under ISPGG III.

2.2.2 In terms of the funding modality, the appraisal mission engaged in discussions

with development partners, particularly the PFMRP IV team and the World Bank, as

well as the Ministry of Finance and Planning, on synergy and complementarity issues in

order to ensure DPs’ coordination, avoid duplication and reduce transaction costs. In this

connection, consideration was given to disbursing the funds of the proposed project through

the PFMRP IV multi-donor trust fund. In the end, given the positive results obtained from the

alternative modalities utilised for ISPGG II, the appraisal team and GOT agreed to continue

with past modalities, while reinforcing the complementarities and co-ordination with the on-

going PFMRP IV.

Page 20: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

9

Table 2.2: Project Alternatives Considered and Reasons for Rejection

Alternative Brief Description Reasons for Rejection

Basket

Funding The Government and some DPs have established a

Multi-Donor Trust Fund arrangement to pool

resources directed to support the PFMRP. The

MDTF arrangement was intended to provide the

government with flexibility in the implementation of

PFMRP. The appraisal team discussed the MDTF

modality with government and DPs, to assess the

utility and efficiency of this mode of financing. The

appraisal team concluded that it was better to retain

direct project funding.

The reasons for not using the MDTF modality

are as follows: (i) The Bank’s past approach of

direct project funding was effective and

delivered results. It was well co-ordinated with

the multi-donor PFMPR IV and hence the risk

of duplication was minimised. Hence, the team

found no reason to change the delivery

modality.

Focus

areas of

the

operation

The Government submitted a long list of capacity

building needs, ranging from statistical capacity

building to oil and gas sector capacity building.

Following thorough assessment by the team, it was

decided to strictly aply the selectivity principle,

hence the few focus areas of the project. A separate

operation will de signed next year to support other

areas, particularly domestic resource mobilization

and oil and gas sector capacity building.

It would have been difficult to manage such a

huge operation with totally unrelated

components. The selectivity principle would

not have been adhered to.

2.3 Project Type

The proposed project is an institutional support for capacity building designed as

a follow up to ISPGG II, and complementing the multi-donor PFMRP IV. It aims at

contributing to consolidating institutional reforms through a public sector investment project.

2.4 Project Cost and Financing Arrangements

The estimated total cost of the project, net of taxes and duties, is UA 13.33 million

(including 10% GOT contribution). A price contingency of 5%, and a physical contingency

of 3%, have been factored in the project cost. Tables (2.3) and (2.4) present the estimated

project cost by component and sources of finance, whereas Tables (2.5) and (2.6) present the

estimated project costs by Category of Expenditure. Details of the project cost by component

and expenditure category are also presented in Technical Annex B2. The Bank will finance

UA 12 million while the GOT contribution is UA 1.33 million.

Page 21: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

10

Table 2.3: Project Cost Estimate by Component

Table 2.4: Sources of Financing

Table 2.5: Project Cost by Category of Expenditure

Table 2.6: Expenditure Schedule by year

%

Foreign Local Total Foreign

Component I : Enhancing transparency and

accountability in public financial management4,246.03 2,423.54 6,669.57 64%

Componant II: Creating an enabling environment

for business and private investments3,271.72 2,171.13 5,442.85 60%

Component III: Project Management 72.31 513.66 585.97 12%

TOTAL BASE COST 7,590.06 5,108.33 12,698.39 60%

Physical contingency 2% 151.80 102.17 253.97

Price contingency 3% 227.70 153.25 380.95

TOTAL PROJECT COST 7,969.56 5,363.74 13,333.30 60%

Total Cost '000 UA

Component

Foreign Local Total

ADF Loan 7,970 4,030 12,000 90.0%

GoT Counterpart funding 1,333 1,333 10.0%

TOTAL PROJECT COST 7,970 5,364 13,333 100%

% of total

amountSource of funding

Costs in Thousands UA

Expenditure Account Foreign Local Total %Foreign

Goods 2,454.83 - 2,454.83 100%

Services 5,135.23 1,914.38 7,049.61 73%

Operating Costs - 3,193.95 3,193.95 0%

TOTAL BASE COST 7,590.06 5,108.33 12,698.39 60%

Physical Contingency 2% 151.80 102.17 253.97

Price Contingency 3% 227.70 153.25 380.95

TOTAL PROJECT COST 7,969.56 5,363.74 13,333.30 60%

COMPONENT 2016 2017 2018 Total

Enhancing transparency and accountability in

public financial management3,613.52 1,851.05 1,538.48 7,003.05

Creating an enabling environment for business

and private investments2,483.25 2,040.84 1,190.90 5,714.99

Project Management 225.78 194.74 194.74 615.27

Total Project Cost (incl. contingency) 6,322.56 4,086.63 2,924.12 13,333.30

Page 22: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

11

2.5 Project’s Target Area and Population; Beneficiaries

The direct project beneficiaries are: for the Mainland, the Ministry of Finance and

Planning, PPP Unit, the Public Procurement Regulatory Authority (PPRA), Internal

Auditor General’s Office (IAGO), the Controller and Auditor General (CAG), the

Prevention and Combatting of Corruption Bureau (PCCB) and the Ethics Secretariat.For

Zanzibar, the beneficiaries are the following institutions: MoF, Zanzibar Investment Promotion

Agency (ZIFA), Department of Stock Verification, the Accountant General’s Office, the

Zanzibar Office of the Controller and Auditor General, the PPP Unit and the Ministry of Trade.

The indirect beneficiaries are the general population of Tanzania, who will benefit from

improved value for money in public procurement, improved service delivery arising from

transparency and accountability and enhanced economic opportunities, including employment

creation, arising from stimulation of private sector investments as a result of improved business

climate. Benefits will also accrue to women, as a result of the project’s contribution to

supporting incorporation of gender-based audits, as well as provision of training for women

(with at least 30% of all training under the project explicitly allocated for women). Women

entrepreneurs will also benefit from special workshops to be organised by PPRA aimed at

capacitating them to effectively participate in public procurement activities.The private sector,

businesses and contractors, will also benefit from improved PFM resulting in a more

competitive and transparent procurement system.

2.6 Participatory Process for Project Identification, Design and Implementation

Wide stakeholder consultation was carried out with Ministries, Departments &

Agencies (MDAs), development partners, the private sector, NGOs, women associations

and civil society during project preparation and appraisal. The private sector was

adequately consulted, mainly through umbrella bodies, and views expressed guided the

selection of focus areas under Component 2. The appraisal mission held discussions within the

PFMRP IV secretariat to maximise synergies with this multi-donor basket-funding operation,

and promote harmonisation. In addition, project design benefitted from the results of earlier

extensive consultations, in which TZFO participated, that were undertaken among DPs in

preparing the PFMRP IV. The regular DP meetings on PFM and capacity development also

provided useful information and perspectives for developing the project. Meetings were also

held with key development partners currently supporting interventions in the area of the

investment climate, such as the World Bank, to ensure harmonization on Component II. The

appraisal mission also met other key PFM and business environment stakeholders, to solicit

their views on the scope and priorities of the proposed operation, and ensure complementarity

with other interventions. The important observations highlighted during these consultations

include the need for: country ownership, gender mainstreaming, sustainability, alignment with

the country’s development priority and harmonization with other DP interventions. These

observations and suggestions informed the design of the proposed project.Thus, the Project is

prepared taking into account the various potential beneficiaries’ strategic/corporate plans, and

the Bank’s CSP which are products of consultative processes. During the implementation stage,

regular consultations will continue, particularly with private sector bodies and women’s groups

to ensure that their concerns are addressed. The half yearly supervision missions, and the mid-

term review of project implementation, will ensure continued engagement with all

stakeholders, including non-state actors.

Page 23: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

12

2.7 Bank Group Experience and Lessons Reflected in Project Design

2.7.1 In designing the proposed project, the experience and lessons from previous Bank

interventions in Tanzania were exploited. These sources of experience and lessons include

the Project Completion Reports (PCRs) for ISPGG I and II, and the budget support GECSP;

the implementation of the CSP 2011-2015; the findings of the CSP Mid-Term Review; and of

the Country Portfolio Performance Review Report. The PCRs, in particular, made a number of

recommendations, from lessons learned, which have influenced the design of this operation.

These recommendations and lessons are captured in Table 2.7.

2.7.2 As at November 2015, the Bank’s active portfolio in Tanzania amounted to UA

1,427.6 million, comprising 15 national operations of UA 1,104.5 million and 10

multinational operations of UA 225.3 million and 3 private sector operations of UA

97.8 million (see Appendix 2. for a comprehensive list of ongoing operations). The average

cumulative disbursement ratio for national operations was 30.14% at 30 November, 2015 and

the average age of the national portfolio stood at 3.82 years. The portfolio is rated as

satisfactory with a score of 2.4 (on a 0-3 scale) according to the 2015 CPPR. The portfolio has

no project at risk or commitments at risk. Key challenges facing the portfolio include the need

to improve performance in areas such as quality at entry, capacity constraints of implementing

agencies, contract management, monitoring and evaluation and fulfilment of first disbursement

conditions. These challenges are being addressed by GOT and the Bank through the

implementation of the Country Portfolio Improvement Plan.

Table 2.7: Lessons Learned from Bank Interventions in Tanzania

Lessons learned Actions taken to integrate lessons into the PAR

i. The need to strengthen implementation

capacity in PFM institutions. The lack of

capacity poses a threat to the successful

implementation of Government’s programmes

The project is focussed on capacity building and the development

of systems and processes to strengthen implementation capacity

in beneficiary institutions.

ii. Limiting the number of project

activities, to avoid putting heavy burden on

Government, which could undermine effective

project implementation

The project has been designed to focus on just a limited number

of components and activities to facilitate beneficiary institutions

focusing on specific, implementable activities within the project

timeframe. This has guided the team in the selection of focus

areas of the project

iii. The need to avoid duplication of effort Steps were taken to ensure co-ordination and alignment of the

project with the ongoing PFMRP IV as well as the World Bank’s

support in improving the business environment. Activities were

carefully selected to avoid duplication

iv. The need to support PBOs with

institutional support projects for more effective

programme implementation

Component 1 of the project supports the government efforts to

implement e-procurement. This is a trigger under the PSRGSP

which is currently under implementation.

2.7.3 Lessons learned, from other sources, which have influenced the design of the

project include (i) care should be taken in the choice of initiatives/beneficiaries to support, so

that the scope, complexity and ambition of the project or programme is managed to ensure

adequate attention to GOT priorities; (ii) in order to facilitate the measurement of the impact

of training programmes, benchmark measurements, where feasible, should be undertaken to

understand the level of staff competences prior to provision of training; These are among the

recommendations emerging from lessons learnt under the on-going PFMRP IV.

Page 24: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

13

2.8 Project Performance Indicators

The key performance indicators identified, and the expected outcomes on project

completion, are set out in the Logical Framework.. The expected outcome from the first

Component “Enhancing the Effectiveness of Public Financial Management” is: (i)

Effectiveness in the management of public finances improved. This is measured by key

indicators, such as PEFA scores, % of unqualified audit opinions and pubic procurement

compliance rate. The expected outcome under the second Component: “Creating an Enabling

Environment for Private Investments” is an improvement in the business enabling environment

to stimulate private sector development. This is measured by the following indicators: (i)

Starting a business score (WB Doing Business ranking); (ii) Corruption Perception Index; and

(iii) Number of public procurement contracts awarded to women.

3. PROJECT FEASIBILITY

3.1 Economic and Financial Performance

The economic and financial benefits from the project will be indirect, and will be

felt across the economy, in terms of efficiency gains, contribution to reduction of

corruption and stimulation of private sector activity and private investments. The benefits

are ultimately seen in improved capacity in public procurement and in the audit function, better

performance of the PFM institutions, and greater attractiveness of the country in terms of the

business environment and stimulation of private investments. The ultimate economic

justification of the proposed project is its contribution to a better functioning government

through improved capacity. The benefits will derive from (a) improved control and

accountability in the management of public finances; (b) enhanced competition, efficiency and

transparency in public procurement; (c) improved timeliness and regularity of financial

reporting; and (d) improved business environment. The project, by contributing to the

development of human resource capacity, will also ensure that the benefits will be sustained

over time. In economic and financial terms, the project has the potential to help increase private

investments from 23.9% of GDP in 2013/14 to 26% in 2018/19. Furthermore, it will contribute

to increasing GDP growth rate from 7.3% in 2013/14 to 7.8% in 2018/19.

3.2 Environmental and Social Impact

3.2.1 Environment and Climate Change: The proposed project is classified as Category

3 in the Bank’s environmental categorization system. The project will not have a negative

impact on the environment, as its activities are limited to training, technical assistance, studies

and procurement of logistic resources, office automation and computer hardware. Project

activities that are focused on such human and institutional capacity building have no negative

impact on climate change. The project’s support to CAG has potential to contribute positively

to the environment because funds will be allocated to train its staff on undertaking

environmental audits.

3.2.2 Social Impact: The Project will contribute to strengthening governance

institutions and improving the business climate. This will eventually result in a more

effective public sector administration, reduction in corruption and an increase in private

investments. This will enhance competitiveness and further unlock the country’s economic

growth potential. The impact on poverty reduction will be indirect, but significant. The project

will promote women empowerment, through the various capacity building activities in which

at least 30% of the beneficiaries will be women, as well as the Gender Policy that will be

prepared by TANESCO. The project will create economic opportunities for women

entrepreneurs by capacitating them to take advantage of public procurement bidding

opportunities. The youth will also benefit indirectly through increased employment and

Page 25: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

14

entrepreneurial opportunities created by an improved business climate resulting in increased

investment flows.

3.2.3 The proposed project, by supporting capacity building of public financial

management institutions, has the potential to generate substantial social benefits over the

medium-term. The support in public procurement and financial accountability will reduce

inefficient and wasteful use of resources, and result in social benefits accruing from increased

availability of resources to support delivery of social services. The envisaged training in

performance and value for money audits will assist combat corruption in sectors such as roads,

water and sanitation; while provision of training in assets tracking and recovery will generate

resources that would be available for spending in health, education and other social services.

3.2.4 The project is expected to contribute to economic growth and poverty reduction

through improved PFM systems and a more conducive environment for business. It will

contribute to strengthening transparency, accountability and efficiency in the management of

public resources. Transparent and accountable management of resources will lead to increased

confidence in government on the part of stakeholders, including CSOs, particularly in the

aftermath of the IPTL Case. The computerization of transactions and processes would lead to

better and faster public services delivery. The project will encourage private investments by

contributing to improving the legal and regulatory environment and enhancing capacity in

identification of bankable transactions in the area of PPPs. The increased flow of investments

resulting from an improved business environment will also create economic opportunities,

create jobs and contribute to poverty alleviation. No negative social impacts are expected from

project implementation.

3.2.5 Gender Impact: The project is expected to benefit women involved in

procurement, audit and accountancy assignments. Thus female staff in PPRA, CAG,

Internal Auditor General’s Department, and PCCB in the Mainland, and ZIPA, Accountant

General’s Office and the Auditor General’s Office in Zanzibar, will benefit from the training

programmes. In order to ensure wide coverage of women, nominations for training must

include women candidates in all beneficiary institutions. The project will continue, as in the

previous operation, to provide training in gender-based auditing, to help create awareness and

enhance capacity for gender-based audits. The training programmes envisaged for the

Ministries of Finance of both the Mainland and Zanzibar will also benefit a significant number

of female staff. GOT is committed to promoting gender equality to ensure that all Tanzanians

are empowered to fully contribute to, and benefit from, the country’s development. Thus, the

project will contribute to achieving this objective. Special capacity building activities targeting

women will also help them actively participate in public procurement processes. Support will

be provided to TANESCO to prepare a gender policy, which is a critical measure under the

Bank PSRGSP, currently under implementation. In addition, under the project, dialogue will

be pursued with GOT so that the on-going gender mainstreaming initiatives in the public sector

cover the project beneficiary institutions. There are no negative impacts on gender expected

from implementing the project.

4. IMPLEMENTATION

4.1 Implementation Arrangements

4.1.1 Project Executing Agency: In line with the implementation arrangements that were used

under ISPGG II, the Public Procurement and Regulatory Authority, a robust and well-endowed

national institution, will continue to be the Executing Agency of the proposed project, which

will be implemented over a three-year period. PPRA will also continue to serve as the PIU for

Page 26: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

15

the Mainland and the activities earmarked for beneficiary institutions in Zanzibar will continue

to be managed by the PIU set up within the Ministry of Finance in Zanzibar.

4.1.2 Project Steering Committees

4.1.3 For the Tanzania Mainland Component, the overall implementation of the project

will be the responsibility of a Project Steering Committee (PSC) chaired by the Chief

Executive Officer (CEO) of PPRA. The members of the steering committee will include

representatives of each beneficiary agency, i.e. MoFEA, CAG, PCCB, IAGO, and the Ethics

Secretariat. The PSC will meet at least once every quarter to review overall progress in

implementation and take action when necessary to resolve emerging or outstanding issues. A

Project Coordination Unit (PIU) will be set up by the CEO from staff of PPRA. The PIU will

be headed by an experienced Procurement Specialist as Project Coordinator, assisted by a

Project Accountant, Administrative Assistant/Clerk and a Secretary. The PIU will coordinate

and manage the day-to-day project tasks for each beneficiary agency, particularly in respect

of matters relating to procurement, contract supervision, monitoring and reporting on project

implementation. The PCU will ensure that robust and comprehensive Procurement Plans are

prepared by each beneficiary institution, and forwarded to the Bank for discussion and approval

before Board presentation of this proposed project. Under the recently closed ISPGG II, these

arrangements were utilised and (from experience gained and lessons learnt) were found to be

fit for purpose in terms of effective project implementation. Hence, the same arrangements will

be used again for implementation of this proposed follow up project.

4.1.4 For the Zanzibar Component, a similar institutional arrangement will be deployed

for the implementation of the project. A Project Steering Committee, under the chairmanship

of the MoF Principal Secretary, will be established. Membership of the PSC will include

representatives of all the beneficiary agencies, i.e. Office of the Controller and Auditor General

(OCAG), MoF, ZIFA, the Department of Stock Verification, the Accountant General’s Office,

the PPP Unit and the Ministry of Trade. The PSC will meet at least once every quarter to review

overall progress in project implementation and take necessary action to resolve any emerging

or outstanding issues. A PIU will be set up by the Permanent Secretary MoF from staff of the

ministry. The PIU will be headed by an experienced Procurement Specialist as Project

Coordinator, assisted by a Project Accountant, an Administrative Assistant/Clerk and a

Secretary. The Project Coordinator will manage the day-to-day tasks for each beneficiary

agency, particularly in respect of procurement, contract supervision, monitoring and reporting

on project implementation. As in the case of the Mainland, the Zanzibar PIU will also ensure

that robust and comprehensive Procurement Plans are prepared by each beneficiary institution,

and forwarded to the Bank for discussion and approval before Board presentation of this

proposed project. In addition, for both the Mainland and Zanzibar, the CVs of proposed

candidates for the key positions of PIU Coordinators and Accountants, with details of their

professional qualifications and experiences, will be forwarded to the Bank for review and

approval prior to their appointment.

4.2 Financial Management, Disbursement and Audit Arrangements

4.2.1 The Financial management Specialist (FMS) has conducted an assessment of the

adequacy of the financial management system of the proposed ISPGG III covering

Tanzania Mainland and Zanzibar. The assessment based on the Bank’s FM Implementation

Guidelines-2014 concluded that the overall residual risk is “Moderate”. The proposed

mitigation measures, as per the risk table, Annex 1, when implemented will enhance the Project

ability to (i) use the funds for the intended purposes in an efficient and economical way; (ii)

Page 27: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

16

prepare accurate, reliable and timely periodic financial reports, and (iii) safeguard the entities’

assets.

4.2.2 In line with the Paris Declaration on Aid Effectiveness and Accra Agenda for

Action, the proposed project will substantially make use of the country’s financial

management systems. The day-to-day management of the project will be as per the rules and

procedures stipulated in the Mainland PPRA and the Zanzibar MoF financial policies and

procedures. The Director of Corporate Services (head of Accounting Functions) of PPRA and

the Accountant General for Zanzibar will be the Officers responsible for overall financial

management of the Project in their respective organization/ Ministry. The Internal Audit

Departments (PPRA and Zanzibar) will audit the project financial transactions regularly. The

internal audit reports will be shared with the Bank during supervision missions.

4.2.3 Disbursement Arrangements: Disbursement will be in accordance with the Bank

Group’s Rules of Procedure for Disbursement, as stipulated in the Disbursement

Handbook (2012 Version). The Executing Agencies will each open two special accounts (one

denominated in US Dollars and the other in Tanzanian Shillings) for the purpose of this project,

at a bank acceptable to ADF. The loan resources will be deposited in the special accounts and

will be operated as a revolving fund. The ADF will replenish the special accounts at the request

of the Executing Agencies, after justifications for the use of at least 50% of the most recent

deposits and 100% of all the other older advances have been provided. The four disbursement

methods will be available for use during project implementation. The Bank will issue a

disbursement letter, which will provide specific guidelines on key disbursement procedures

and practices.

4.2.4 Financial Reporting and Auditing: The Project Coordinators will keep accurate

accounts for their respective components of the project, in accordance with sound and

acceptable accounting practices. The accounts kept should allow identification of

expenditures by Component, Category and Source of Finance. The Project will follow the

Tanzania Mainland and Zanzibar financial year of 1st July to June 30th,. and an

independent external auditor acceptable to the Fund, precluding CAG Mainland and CAG

Zanzibar, who are both beneficiaries in the project, shall carry out the audit. The audits will

be conducted in accordance with the terms of reference for Bank-financed projects. Two

separate audit reports for PPRA and MoF- Zanzibar, complete with Management Letters, will

be submitted to the Bank within six months of the end of the financial year. PPRA and MoF

executed successfully ISPGG I & II without major financial management issues, and were up

to date in the submission of audit reports, with few delays that have been addressed in the

design of this follow up project. The PIUs will make available to the selected auditor a copy of

the Bank Group’s Guidelines for Auditing Projects.

4.3 Procurement Arrangements

Procurement of ICB contracts and Consulting services for the proposed project

would be carried out in accordance with the Bank’s Rules and Procedures: “Rules and

Procedures for Procurement of Goods and Works”, dated May 2008, revised July 2012 as

amended from time to time; and “Rules and Procedures for the Use of Consultants”, dated May

2008, revised July 2012 as amended from time to time using the relevant Bank Standard

Bidding Documents, and the provisions stipulated in the Financing Agreement. For Tanzania

Mainland, procurement of NCB contracts will be carried out in accordance with the public

procurement law, the Public Procurement Act, 2011 using the national Standard Bidding

Documents. For Zanzibar, the Bank’s Rules and Procedures and documents will be used. The

Page 28: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

17

overall project risk for procurement is moderate. The Procurement Plans, and related

procurement documents, were agreed and finalized before project Loan negotiations. Detailed

procurement arrangements are provided in Technical Annex B5.

4.4 Monitoring and Evaluation

4.4.1 The project is scheduled for implementation over a 36-month period, from

January 2016 to December 2018. This schedule is reasonable, given the scope of activities to

be implemented and project implementation capacity in Tanzania, particularly given that the

respective PIUs have had a good track record implementing ISPGG II (which had an

implementation slippage of only 4 months). The project task team on the Bank side and the 2

PIUs will be responsible for project monitoring and evaluation, using the Result Monitoring

Framework (Technical Annex B7) and the project log frame. The periodic performance

assessment and result reporting will be carried out by the task team in collaboration with the

project Coordinators and the beneficiary institutions. Quarterly and annual activity reports will

also be prepared and submitted to the Bank. The Bank will undertake monitoring of project

implementation, and the use of project resources, through regular contact with the PIUs,

frequent supervision missions and the mandatory mid-term review mission. The Bank will also

sustain regular consultations with DPs supporting GOT capacity-building under the ongoing

PFMRP IV. The Field Office, TZFO, being on the ground, will play an active role in the

coordination, country dialogue, and project supervision and monitoring. A Project Completion

Report will be prepared to evaluate progress against outputs and outcomes and draw lessons

for possible follow-up operations. Table 4.2 presents the Project Implementation and

Monitoring Schedule.

Table 4.1: Project Implementation Schedule

Task Responsible Party Start Date

Loan Approval ADF Janvier 2016

Loan Effectiveness ADF/GOT February 2016

Project Launching ADF/GOT February 2016

Procurement of goods and services GOT April 2016

Technical assistance and training program GOT June 2016

Annual Audit Report GOT March 2017

Supervision Mission ADFGOT July 2016

Mid-term Review ADF/GOT June, 2017

Project Completion Report ADF/GOT December, 2018

4.5 Governance

Financial management of the proposed project will be carried out by the PIU

under the supervision of the Chief Executive Officer PPRA for the Mainland Component. For the Zanzibar Component, this task will be carried out by the PIU under the supervision of

the MoF Principal Secretary. A Steering Committee for the Mainland Component will be

established under CEO of the PPRA, comprising representatives of the beneficiaries. A similar

Steering Committee will be established for Zanzibar under the Principal Secretary, Ministry of

Finance The 2 PCUs will prepare their respective manuals of administrative, financial and

accounting procedures. Accounting records will be kept, presenting project expenditure by

component, category and source of finance. The project accounts will be audited annually by

an external accountant acceptable to the Fund. On account of sound governance considerations,

and issues of conflict of interest, CAG is excluded from qualifying to audit the project since it

is itself a beneficiary in the project.

Page 29: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

18

4.6 Sustainability

4.6.1 The sustainability of the proposed project will, first and foremost, be anchored on

GOT’s strong commitment to implementing policy and institutional reforms in PFM and

enabling business environment, including PPP promotion. Embedded in the design of the

proposed project is a strong capacity building and knowledge transfer dimension. This will

help ensure that adequate capacity is built across Government during the project’s

implementation phase. In addition, the proposed project will finance certain activities, such as

the development of reference Manuals, which will guide and inform the day-to-day work of

public officials. Several manuals will be developed, including on the prevention and

investigation of procurement corruption allegations,; on PPP, and on monitoring and

evaluating the PFM program. These manuals will guide and inform the work of public officials

in these areas in the short to medium term. In addition, sustainability is also addressed through

the training of trainers in the envisaged activities of some of the beneficiaries, as well as the

use of local and regional training instituions, wherever feasible.

4.6.2 In terms of cost sustainability, the project is consistent with the principles of the Paris

Declaration on Aid Effectiveness, as its implementation does not involve the creation of new

institutions or hiring of additional staff, which will add to the already heavy GOT fiscal

burden.

4.7 Risk Management

4.7.1 The potential risks and mitigation measures for the project is summarized Table 4.2.

Table 4.2 : Risks and Mitigation Measures

Risks Probability

/ Impact

Mitigation Measures

Government’s commitment to

reforms:

It is not clear if the newly elected

Government’s reform priorities will

be the same as those of the previous

Government

Probability

Low and

impact

Medium

The previous Government’s commitment to, and ownership of,

reforms is high. Recent pronouncements indicate that the new

Government is strongly committed to to undertake ambitious

governance reform including anti-corruption and effective

economic and public financial management.. Through dialogue

with the new Government the project will continue to be

implemented, together with the multi-donor PFMRP IV.

Macroeconomic risk: The GOT

macroeconomic management,

which has led to considerable

stability, may falter and

compromise the reform efforts

Probability

medium and

impact

Medium

Continued implementation of fiscal and monetary policy,

supported by an IMF program. Continued implementation of

budget support operations, as well as policy dialogue with

partners including the Bank, will help to monitor and mitigate

the macro-economic risks.

Implementation capacity

constraints: Weak institutional and

human resources capacity could

cause delays or hamper

implementation of reform.

Probability

medium and

impact

Medium

The on-going multi-donor supported PFM reform program, and

the proposed ISPGG III project, would strengthen capacity of

public officials involved in reform coordination and

implementation monitoring. The project is providing additional

project management capacity including training.

Fiduciary risks: While Government

has made notable progress in

improving PFM, there are still

weaknesses in the fiduciary control

environment as revealed by IPTL.

Medium

probability/

High Impact

Annual Audit of the project. The project requires submission

of quarterly financial reports and audited financial statements

on an annual basis. The Bank’s regular supervision missions

will also help to mitigate the risk.

Page 30: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

19

4.8 Knowledge Management

4.8.1 The proposed project will build knowledge, and develop skills, in accounting and

cash management, various forms of audit, public procurement, PPP issues and in

investigations techniques and transparency and accountability practices in the fight

against corruption. The implementation of the project will strengthen PFM by (i) training

staff in IPSAS and IFMIS; (ii) enhancing staff skills in financial control and reporting; and

(iii) developing various important Manuals to guide and inform the work of public officials.

Knowledge will also be acquired through skill transfer by external experts, and study tours to

appropriate institutions in other countries. In addition, sensitisation and public awareness

workshops will be undertaken on issues relating to Ethics, Corruption and the role of

Parliament in accountability in the public sector. This is aimed at improving integrity,

transparency and accountability in the management of public resources. In the Component

dealing with PPPs, project support will generate knowledge on best practices in this important

area, in terms of PPPs design and assessment, value for money analysis and measurement of

the attendant risks and necessary mitigation actions. The Bank’s regular project supervisions,

the performance review at mid-term and the project completion report will also contribute to

knowledge-building and generate lessons to inform future interventions.

V – LEGAL INSTRUMENTS AND AUTHORITY

5.1 Legal Instrument

An ADF Loan will be used to finance this proposed project, governed by a Loan Agreement

between the United Republic of Tanzania and the African Development Fund.

.

5.2 A. Conditions Associated with Bank’s Intervention

5.2.1 Conditions Precedent to Entry into Force: The entry into force of the Loan

Agreement shall be subject to the fulfilment by the Borrower of the applicable provisions of

section 12.01 of the General Conditions Applicable to Loan Agreements and Guarantee

Agreements of the African Development Fund. The Loan Agreement shall enter into force on

the date of its signature by the United Republic of Tanzania and the African Development

Fund.

5.2.2 B. Conditions Precedent to First Disbursement: The first disbursement under the

loan shall be conditional upon the entry into force of the Loan Agreement, and the Recipient

providing evidence of the fulfilment of the following conditions, in form and substance

satisfactory to the Fund:

(a) Designation of two Project Coordination Units, one for Tanzania Mainland and the other

forZanzibar (evidenced by separate letters sent to the Bank by the Mainland (PPRA) and

Zanzibar (MoF)

(b) Opening of two Special Accounts (one denominated in US Dollars and the other in

Tanzania Shillings) by each Executing Agency in a Bank acceptable by the ADF

(evidenced by two letters, one from the Mainland (PPRA) and the other from Zanzibar

(MoF) indicating that the said accounts have been opened, with the account numbers

provided)

Page 31: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

20

5.3 Compliance with Bank Policies

This project complies with all applicable Bank policies.

VI. RECOMMENDATION

Management recommends that the Board of Directors approve an ADF Loan not

exceeding UA 12 million to the United Republic of Tanzania for the purposes of, and subject

to, the conditions stipulated in this report.

Page 32: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

- 1 -

APPENDIX 1: TANZANIA: SELECTED MACROECONOMIC INDICATORS

Page 33: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

- 2 -

APPENDIX 2: BANK GROUP CURRENT PORTFOLIO IN TANZANIA

SOURCE OF

FINANCE

APPROVAL

DATE

CLOSING DATE APPROVED

AMOUNT (UA mn)

DISB

RATE

Marketing Infrastructure, Value Addition and Rural Finance ADF Loan 29-Jun-2011 31-Dec-2016 40.00 42.03

SUB-TOTAL 40.00 42.03

Tanzania Road Sector Support Project I ADF Loan 2-Dec-2009 15-Dec-2017 152.00 68.30

Tanzania Road Sector Support Project II ADF Loan 5-Apr-2012 30-Sep-2017 140.00 29.95

ADB Loan 30-Sep-2015 31-Dec-2020 69.74 0.00

AGTF Loan 30-Sep-2015 31-Dec-2020 31.70 0.00

ADB Loan 26-Nov-2015 31-Oct-2021 192.50 0.00

ADF Loan 26-Nov-2015 31-Oct-2021 54.00 0.00

SUB-TOTAL 639.94 22.78

ADF Loan 15-Sep-2010 31-Dec-2015 59.00 100.00

RWSSF Grant 15-Sep-2010 31-Dec-2015 5.80 100.00

Zanzibar Urban Water & Sanitation Project ADF Loan 19-Dec-2012 31-Dec-2017 14.00 4.86

ADB Loan 16-Sep-2015 31-Dec-2020 102.84 0.00

ADF Loan 16-Sep-2015 31-Dec-2020 18.00 0.00

AGTF Loan 16-Sep-2015 31-Dec-2020 30.00 0.00

SUB-TOTAL 229.64 28.51

ADF Loan 14 Dec. 2007 31-Dec-2015 28.68 65.48

ADF Grant 14 Dec. 2007 31-Dec-2015 1.32 98.48

Iringa-Shinyanga Transmission Line ADF Loan 26-Oct-2010 31-Oct-2016 45.36 29.37

Scaling-Up Renewable Energy Program SCF Grant 20-Dec-2013 30-Sep-2016 0.50 0.00

SUB-TOTAL 75.86 44.03

Small Enterpreneurs Loan Facility (SELF) II ADF Loan 10-May-2010 31-Dec-2015 20.00 93.77

Alternative Learning and Skills Development (ALSD) II ADF Loan 29-Jun-2011 31-Dec-2016 15.00 12.60

Support to Technical Vocational Education and Training & Teacher ADF Loan 2-Apr-2014 31-Dec-2019 34.00 2.03

SUB-TOTAL 69.00 30.92

Power Sector Reform and Governance Support Program ADF Loan 20-May-2015 30-Nov-2015 50.00 100.00

SUB- TOTAL 50.00 100.00

NATIONAL PUBLIC SECTOR 1104.44 30.13

CRDB SME Partial Credit Guarantee Facility ADB Loan 22-Jul-2008 1-Apr-2016 1.39 98.60

ADB Loan 23-Apr-2014 32.35 0.00

ADB Loan 23-Apr-2014 32.35 0.00

EFC Tanzanie- Fund for Africa Private Sector Assistance (FAPA FAPA Grant 5-Jun-2012 31-Mar-2016 0.67 68.66

TZS Line of Credit to First National Bank Subsidiary in Tanzania ADB Loan 12-Dec-2012 30-Apr-2017 31.05 0.00

SUB-TOTAL 97.80 1.87

TOTAL NATIONAL (Public + Private sectors) 1202.24 27.83

Dsm-Isaka-Kigali/Keza-Musongati Railway Phase2 ADF Loan 17-Nov-2009 31-Dec-2015 1.66 75.90

East Africa Transport and Trade Facilitation (EAC) ADF Grant 29 Nov. 2006 31-Dec-2015 6.20 54.52

Transit Transport Facilitation Agency (TTFA) NEPAD IPPF 22-Dec-2010 31-Dec-2015 0.32 81.25

Arusha-Holili/Taveta-Voi Road Project ADF Loan 16-Apr-2013 31-Dec-2018 79.90 10.63

Lake Victoria Water Supply & Sanitation Programme Phase II ADF Grant 17-Dec-2010 30-Dec-2016 17.48 44.68

The EAC Payments & Settlement Systems Integration Project ADF Grant 5-Dec-2012 30-Jan-2017 15.00 17.53

Regional Rusumo Hydropower ADF Loan 27-Nov-2013 31-Aug-2019 22.41 0.09

EAC Railway Sector Enhancement Project NEPAD IPPF 29-Jun-2012 20-Dec-2016 0.82 39.24

EAC Centres of Excellence for Skills and Tertiary Education ADF Loan 3-Oct-2014 31-Dec-2019 6.25 0.48

Kenya -Tanzania Interconnection ADF Loan 18-Feb-2015 31-Dec-2019 75.29 0.00

SUB TOTAL 225.32 10.74

GRAND TOTAL (NATIONAL+ MULTINATIONAL) 1427.57 25.13

C. MULTINATIONAL OPERATIONS:

ENERGY

Electricity V Project

SOCIAL

MULTI-SECTOR

B. PRIVATE SECTOR

Bagamoyo Sugar Project

AGRICULTURE

A. NATIONAL OPERATIONS:

TANZANIA: ONGOING PORTFOLIO, 30 NOVEMBER 2015

Arusha Sustainable Urban Water Supply and SanitationDelivery

Porject

TRANSPORT

WATER SUPPLY/SANITATION

Rural Water Supply and Sanitation Programme II

Dar es Salaam Rapid Bus Transit Project

Transport Sector Support Program

Page 34: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

- 3 -

APPENDIX 3: DONOR COORDINATION MATRIX FOR TANZANIA

Sectors/Thematic Areas AfD

B

Wo

rld

Ba

nk

IM

F

DF

ID

EU

IL

O

IO

M

WF

P

Belg

ium

Ca

na

da

Den

ma

rk

Fin

lan

d

Fra

nce

Germ

an

y

Irela

nd

Ja

pa

n

Ko

rea

Neth

erla

nd

s

No

rw

ay

Sp

ain

Sw

ed

en

Sw

itzerla

nd

UK

/Oth

er

US

/MC

C

US

AID

UN

AID

S

UN

CD

F

UN

DP

UN

EP

UN

ES

CO

UN

-F

AO

UN

FP

A

UN

HC

R

UN

IC

EF

UN

-IF

AD

UN

ID

O

UN

-W

HO

UN

WO

ME

N

Agriculture 3 3 3 3 3 3 1 3 3 2 3

Industry and Trade (includes PSD) 3 3 1 3 3 3 3 3 3 3 3 3 3 2

Energy and Minerals 2 1 3 3 3 3 3 3 3 3 3 3

Natural Resources, Environment, and Tourism 3 3 3 3 3 3 3 1 3 3 3

Infrastructure (includes Transport) 2 3 3 3 3 3 3 1 3 3

Education 3 3 3 3 3 3 3 2 3 3

Water 3 1 3 3 3 2 3 3 3 3 3

Health 3 3 3 3 3 3 3 3 3 3 3 3 1 2 3

Public Financial Management 3 3 3 2 3 3 3 1 3 3 3 3 3 3 3

Macroeconomic Management 1 3 3 3 3 3 3 3 3 3

General Budget Support 3 3 3 2 3 3 3 3 3 3 3 3 1 3

Poverty Monitoring Group 1 2 3 3 3 3 3 3 3 3 3 3 3 3 3

Governance 3 3 3 3 1 3 2 3 3 3 3 3 3

Public Sector Reform 3 1 3 3

Local Government Reform 3 3 1 3 3 2 3 3 3 3 3 3 3

Gender 3 3 3 3 1 3 3 3 3 3 3 3 3 2

Social Protection 2 3 3 3 3 3 3 1 3

Anti-Corruption 3 3 2 3 3 3 3 1

Innovation and Technology 3 ∆ 3 1

HIV/AIDS 3 3 1 3 3 3 3 3 3 2 3 3 3 3 3

Humanitarian Assistance 3 3 2 3 3 3 3 3 3 1 3

Culture 1 3 3 3 3 3 3 3 3 2

Source: Compiled from information provided by the DPG Secretariat and staff consultations.

Note: 1 Lead or elected chair in donor group.

2 Deputy lead or elected co-chair in donor group.

3 Active development partner (provides financial/technical support and/or frequently joins meetings).

Page 35: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

- 4 -

APPENDIX 4: LESSONS LEARNED FROM ISPGG II AND GECSP

ISPGG II

Key issues (max 5, add

rows as needed) Key lessons learned

1. Strong Government

ownership of capacity-

building and

institutional

strengthening reforms

1. Ownership, leadership, and commitment of the government in the design and implementation

of the project were the most important success factors for the Institutional Support. For example,

the commitment to improve IT systems (e.g EPICOR) and procurement processes (involving

preparation of Manuals), and training manuals was important for sustainabilty. The Bank

merely played a complementary role and provided the resources for implementation of the

components.

2.Bank Group

comparative advantage

2. It is important, for project success, to focus the project on areas where the Bank has

developed a niche, such as the area of public procurement. Thus, over 50% of the project

resources were directed to strengthening public procurement processes, an area where the Bank

has a track record.

3. A simplified

approach to project

implementation

3. Project implementation success can be significantly ensured by adopting, during project

design, a simplified approach that avoids unnecessary conditions/conditionalities that could

jeopardize/delay project implementation. Under this simplified approach, supervision missions,

and mid-term review assessments, were evenly, regularly scheduled during implementation to

ensure early resolution of outstanding problems and smooth progress in implementation.

4.Strong coordination

amongst DPs avoids

duplication of efforts

4 There has been a positive impact from the Bank staff regular consultations with GOT and

DPs on progress in the implementation of the broader multi-donor basket funded PFMRP. This

regular consultation assisted minimize duplication of effort in the provision of capacity-bilding

support to Tanzania. Close coordination was an effective way to ensure efficiency in the use of

DP resources for capacity building.

GECSP

Key issues (max 5, add

rows as needed) Key lessons learned

1. Strong Government

ownership of reforms

1. Ownership, leadership, and commitment of the authorities, at the highest level, in the design

and implementation of the policy reform measures were the most important success factors for

the operation. For example, the commitment to improve and sustain macroeconomic growth

and stability was important. DPs merely played an advisory role and provided resources for

implementation of the reforms.

2.Vulnerability to

shocks and

sustainability of

reforms

2. Higher fuel prices, resulting in strong pickup of imports, was a major vulnerability (external

shock) for Tanzania, and it threatened GOT’s continued capacity to implement the reforms.

Timely provision of resources (such as the GECSP resources) is critical for enabling the

government to persevere with implementation of timely reforms needed at a time when the

country was facing a critical energy crisis, which was operating against public services delivery,

notably in the infrastructure sector.

3.Timeliness,

responsiveness and

relevance of funding

instruments

3. The GECSP resources met needs at a time the country had to boost its capacity/reserves for

importing critical inputs for the energy and social sectors as well as raw materials for the

productive sector. GECSP resources addressed effectively the needs of the country by providing

timely response based on clearly established prior actions.

4.Predictability of

Disbursements timing

4. The predictability of disbursement from year to year is highly dependent on government

performance in meeting conditions/prior actions, and meeting IMF benchmarks. Therefore, care

should be taken in discussing and agreeing conditions with government. It should be based on

sound policy dialogue, resulting in realistic conditions to underpin disbursement. This is an

important element in programme design that has important implications for the government

budget planning.

5. Strong coordination

amongst DPs avoids

duplication of efforts

and strengthens

monitoring of results

5. There has been a positive impact from the coordinated and harmonized policy dialogue

among DPs providing budget support. Government’s leadership role in coordinating

development assistance has been instrumental. The ability of the Bank to work in close

collaboration with GOT other Development Partners resulted in common results and policy

dialogue frameworks. Close coordination was an effective way to support budget planning and

execution.

Page 36: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

- 5 -

APPENDIX 5: PUBLIC FINANCIAL MANAGEMENT: 2013 PEFA INDICATORS

2010 PEFA 2013 PEFA Internal Controls

PI-18/ M1 Effectiveness of

payroll controls

C+/D+(i) A

(ii) C/D

(revised from NR)

(iii) C

(iv) C

B▲ (i) B▲

(ii) B ▲

(iii) B

(iv) B▲

PI-19/ M2 Competition, value

for money and

controls in

procurement

NR

NR This indicator was not rated. It was

revised in 2011 and is not

comparable with previous

framework.

PI-20/ M1 Effectiveness of

internal controls

for non-salary

expenditures

C+ (i) B

(ii) C

(iii) C

D+ (i) D

(ii) B

(iii) D

PI-21/ M1 Effectiveness of

internal audit C (i) C

(ii) C

(iii) C

D+ (i) C

(ii) B

(iii) D

External Scrutiny and Audit

PI-26/ M1 Scope, nature and

follow-up of

external audit

B (i) B

(ii) B

(iii) B

C+ (i) B

(ii) B

(iii) C

PI-27/ M1 Legislative

scrutiny of the

annual budget law

C+ (i) C

(ii) B

(iii) B

(iv) B

B+ (i) B

(ii) B

(iii) A

(iv) B

PI-28/ M1 Legislative

scrutiny of

external audit

reports

D+ (i) D

(ii) B

(iii) C

D+ (i) D

(ii) B

(iii) C

Page 37: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

- 6 -

APPENDIX 6: ISPGG III ANALYTICAL WORK UNDERPINNINGS

Component/Reform

Areas

Analytical Work Institution

Overall Strategic Context Tanzania Development Vision 2025;

and National and Zanzibar strategies for

growth and poverty reduction; and BRN

Strategic Documents

MoF

Tanzania Country Strategy Paper (2011-

2015)

AfDB and GoT

Public Service

Management

The Reforming Tanzania Public Sector

Report: An Assessment of Future

Direction (November, 2013)

GOT

Governance Governance and Corruption Survey

(2014)

GOT

Private Sector

Development

WB Doing Buisness Report 2015 and

2016; Global Competitiveness Report

2014 and 2015; President’s Delivery

Bureau: Big Results Now Background

Paper.

Public Finance

Management

PFMRP IV and Action Plan (2011) MoF

PFMRP IV Mid-Term Draft Final

Report, July, 2015

GOT and PFMRP

Secretariat

AfDB

2014 General Budget Support Annual

Review: Final Report, September, 2015

GOT

PEFA Assessments , 2010 and 2013 MoF

OPEV Joint PFM Evaluation Public

Finance Management Reform??? (2011)

AfDB

Development Policy Operation for

Tanzania

World Bank

Page 38: UNITED REPUBLIC OF TANZANIA INSTITUTIONAL SUPPORT PROJECT ...

- 7 -

APPENDIX 7: MAP OF TANZANIA


Recommended