UNIVERSITI PUTRA MALAYSIA
COST CONTROL STRATEGIES FOR IBS CONTRACTORS IN MALAYSIA
LEW YOKE LIAN
FK 2002 43
COST CONTROL STRATEGIES FOR IBS CONTRACTORS IN MALAYSIA
By
LEW YOKE LIAN
Thesis Submitted to the School of Graduate Studies, Universiti Putra Malaysia, in Fulfilment of the Requirement for the Degree of Master of Science
August 2002
Abstract of thesis presented to the Senate of Universiti Putra Malaysia in fulfilment of the requirement for the degree of Master of Science
COST CONTROL STRATEGIES FOR IDS CONTRACTORS IN MALAYSIA
Dy
LEW YOKE LIAN
August 2002
Chairman: Salihudin Hassim, Jr.
Faculty: Faculty of Engineering
Industrialised Building System (IBS) is a system widely used in construction industry
in Malaysia. This study is a survey to identify the factors contributing to cost control
problems faced by local contractors in IBS projects and to identify the strategies used
to reduce the cost variation in IBS projects. From the finding of the survey, a
computer-based cost control model was developed to improve the effectiveness of
cost control on IBS.
The survey shows that management team capability & performance, buildability of
design, and timely decision making were the top-ranked factors contributing to cost
control problems in IBS construction in Malaysia. Strategies like increase the
working hours, increase manpower and/or equipment, provide close supervision to
subordinates for minimising abortive work, and coordinate closely with
subcontractors were identified as the most popular method used to reduce cost
variation of IBS projects.
In hypotheses testing of this study, it was found that there is significant association
between type of IBS used and the perceived contributor to cost control problems.
1\
Results of Logistic Regression Analysis shows that allowance of partially handover,
delay of payment from client to the contractor, deposit needed for IBS before delivery
of the precast components, and application of tracking curve for cost control are likely
to influence the cost variance of IBS construction projects.
The developed computer-based cost control model could assist constructor of IBS
(with prefabricated elements) to plan their expenses and progress of work.
Additionally, monitoring during the construction is made available through a series of
user-friendly electronic forms. With identification of potential problem contributors,
strategies to overcome cost variation, and application of the cost control model, cost
control of IBS projects in Malaysia would be unproblematic to any new or existing
IBS practitioners.
III
Abstrak tesis yang dikemukakan kepada Senate Universiti Putra Malaysia sebagai memenuhi kepeduan untuk ijazah Mastaer Sains
STRA TEGI KA W ALAN KOS UNTUK KONTRAKTOR IBS DI MALAYSIA
Oleh
LEW YOKE LIAN
Ogos 2002
Pengerusi: Salihudin Hassim, Ir.
Faculti: Faculty of Engineering
Industrialised Building System (IBS) merupakan satu sistem yang digunakan secara
meluas di industri pembinaan di Malayisa. Projek ini adalah satu kajian untuk
mengenalpasti faktor-faktor yang menyebabkan masalah kawalan kos semasa
pembinaan dan juga strategi yang digunakan untuk mengatasi variasi kos yang teIjadi.
Daripada hasil kajian yang didapati, satu sistem kawalan kos berdasarkan komputer
telahpun dihasilkan.
Daripada kajian yang dijalankan, keupayaan dan kecekapan kumpulan pengurusan,
kebolehbinaan sesuatu rekabentuk dan kepantasan keputusan dibuat merupakan faktor
utama yang menyebabkan masalah kawalan kos dalam pembinaan IBS di Malaysia.
Peningkatan masa keIja, peningkatan tenaga buruh dan/atau peralatan, pengawalan
yang lebih ketat kepada pekeIja serta sub-kontraktor merupakan strategi yang paling
kerap digunakan untuk mengurangkan variasi kos dalam projek pembinaan IBS.
Dalam pengujian hipotesis dalam kajian ini, jenis IBS yang digunakan didapati
mempunyai perhubungan dengan faktor penyebab masalah kawalan koso Keputusan
iv
Regrasi Logistic pula menunjukkan kebenaran penyerahan mengikut bahagian,
kelambatan pembayaran daripada pelanggan, keperluan pembayaran wang
pendahuluan oleh pembekal IBS dan penggunaan tracking curve akan mempengaruhi
variasi kos projek pembinaan IBS .
Sistem kawalan kos yang dihasilkan akan dapat membantu pembina IBS (yang
menggunakan elemen pasang-siap) untuk merancang perbelanjaan dan kemajuan
kerja. Tambahan pula, pengawalan semasa pembinaan boleh dilakukan melalui
borang kawalan dalam komputer. Dengan pengenalpastian penyebab masalah, stategi
untuk mengatasi variasi kos dan penggunaan sistem kawalan kos, kawalan kos projek
IBS di Malaysia akan menjadi lebih mudah.
v
ACKNOWLEDGEMENT
I would like to express my deepest and sincere appreciation to my supervisor, Ir.
Salihudin Hassim for his invaluable advise, guidance, suggestions and unfailing help
throughout the project. My sincere thanks are also extended to the chairman of the
VIVA examination, Prof. D. N. Trikha; my examiners, Prof. Madya Ir. Dr. Mohd.
Razali Abdul Kadir and Mr. Law Teik Hwa for their comments and suggestions in
this project.
Besides, I would like to thanks to all practitioners of IBS that have shared their
invaluable experience and knowledge. Last but not least, I would like to express my
gratitude to the senior students and friends who have helped me during this project.
vi
I certify that an Examination Committee met on 12th August 2002 to conduct the final examination of Lew Yoke Lian on her Master of Science thesis entitled "Cost Control Strategies for IBS Contractors in Malaysia" in accordance with Universiti Pertanian Malaysia (Higher Degree) Act 1980 and Universiti Pertanian Malaysia (Higher Degree) Regulations 1981. The Committee recommends that tha candidate be awarded the relevant degree. Members of the Examination Committee are as follows:
D.N. TRIKHA, Ph.D. Professor Faculty of Engineering Universiti Putra Malaysia (Chairman)
SALIHUDIN BIN HASSIM, Ir. Faculty of Engineering Universiti Putra Malaysia (Member)
MOHD. RAZALI BIN ABDUL KADIR, Ph.D., Ir. Assoc. ProfessorlDeputy Dean (Development) Faculty of Engineering Universiti Putra Malaysia (Member)
LAW TEIK HUA Faculty of Engineering Universiti Putra Malaysia (Member)
�
"
SHAMSHER MOHAMAD RAMADILI, Ph.D. Professor/ Deputy Dean School of Graduate Studies Universiti Putra Malaysia
Date: i 3 NOV 2002
VII
This thesis submitted to the Senate of Universiti Putra Malaysia has been accepted as fulfilment of the requirement for the degree of Master Science. The members of the Supervisory Committee are as follows:
SALIHUDIN BIN HASSIM, Ir. Faculty of Engineering Universiti Putra Malaysia (Chairman)
MOHD. RAZALI BIN ABDUL KADIR, Ph.D., Ir. Assoc. ProfessorlDeputy Dean (Development) Faculty of Engineering Universiti Putra Malaysia (Member)
LAW TEIK HUA Faculty of Engineering Universiti Putra Malaysia (Member)
AINI IDERIS, Ph.D. ProfessorlDean School of Graduate Studies Universiti Putra Malaysia
Date: 9 JA�' ,;r-'')
viii
DECLARATION
I hereby declare that the thesis is based on my original work except for quotations and citations which have been duly acknowledged. I also declare that it has not been previously or concurrently submitted for any other degree at UPM or other
institutions.
LEW YOKE LIAN
ix
TABLE OF CONTENTS
Page
ABSTRACT II ABSTRAK IV ACKNOWLEDGEMENTS VI APPROVAL Vll
DECLARATION IX
LIST OF TABLES Xll LIST OF FIGURES xnll LIST OF ABBREVIATIONSINOTATIONS/GLOSSARY OF TERMS XVI
CHAPTER
INTRODUCTION Problem Statement S ignificant of Study Objectives Justification
4 5 6 9 10 11 12
S cope and Limitation Framework of Study Thesis Overview
2 LITERATURE REVIEW Introduction 15 Industrialised Building System 15
Industrialisation 16 Standardisation 17 Modular Co-ordination 18 Open and Closed System 19 Classification of IBS 20 Advantages of IBS 25 Cost Performance of IBS 26 Industrialised Building System in Malaysia 28
Cost Control 30 Items to be Controlled 33 Stages of Cost Control 42 Methods of Cost Control 44 Pertinent Studies on Cost Control in Construction 49 Cost Variance 54 Cost Modelling Methods 61 Factors Affecting Cost in Construction 65
3 METHODOLOGY Introduction Data Collection
Sampling Design Variables
Data Analysis
79 79 83 84 86
x
Chi-Square Homogeneity Test Logistic Regression
Development of Model
87 88 93
4 RESULTS & DISCUSSION Introduction 97 Background of Respondents 98 Factors Contributing to Problems of Cost Control 106
Client Characteristic 110 Consultant and Design Characteristic 110 Contractor Characteristic 110 Project Characteristic 111 Contract Procedure and Procurement Method 111 External Factors 112 10 Top-Ranked Factors 112
Strategies to Reduce Cost Variance 123 Hypotheses Testing 125
Hypothesis 1: Relationship between Types of IBS and Factors Contributing to Cost Control Problems 127 Hypotheses 2 - 18: Factors that are Likely to Influence
Cost Variance 13 1
5 COMPUTER-BASED COST CONTROL MODEL DEVELOPMENT Introduction Work Breakdown Structure Cost Control Model
Data Acquisition Cost Control Forms Data Storage Data Processing
6 SUMMARY & CONCLUSION Summary and Conclusion Recommendation
REFERENCE APPENDIX A APPENDIX B BIODAT A OF THE AUTHOR
141 141 144 144 148 151 153
155 158
159 167 174 181
Xl
LIST OF TABLES
Table Page
2.1 Direct and Indirect Cost Variances Summary 58
2.2 Summary of Factors Affecting Cost of Construction Projects 69
3.1 Example of Cross-Tabulation Table 90
3.2 Summary of Analysis Conducted 92
4.1 Characteristics of the projects investigated 98
4.2 Respondents Characteristic (1) 100
4.3 Respondents Characteristic (2) 101
4.4 Types of IBS Used 104
4.5 Factors Contributing to Cost Control Problems 108
4.6 10 Top-Ranked Factors Contributing to Cost Control Problems 113
4.7 Comparison of 10 Top-Ranked Factors Contributing to Cost
Control Problems with Other Studies 114
4.8 Summary of Research Works for Comparison of 10 Top-Ranked
Factors 115
4.9 Strategies to Reduce Cost Variance 123
4.10 Main Contributors to Cost Control Problems 128
4.11 Crosstabulation of Type of IBS Vs Category of Perceived Factors 130
4.12 Factors Contributing to Cost Variance 137
XII
LIST OF FIGURES
Figure Page
1.1 Thesis Layout 14
2.1 Badir-Razali Building System Classification 24
2.2 The Four Basic Elements of Cost Control 32
2.3 Diagrammatic Representation of a Unit Rate 34
2.4 Flow Chart of Material Cost Control 35
2.5 Stages of Cost Control 42
2.6 The Earned Value Model; Calculation of Cost Performance 45
2.7 Tracking Curve 46
2.8 Project-Control Checklist 47
2.9 Integrated Cost/Schedule Report 50
2.10 Integrated of Cost, Schedule, and Time Variances 51
2.11 Direct Cost Variances 55
2.12 Overhead Cost Variances 56
2.13 Cost Modelling 61
3.1 Flow Chart of Study 82
3.2 Relationship of 'Type of Client' and 'Cost Variance' 91
3.3 Flowchart of Cost Control Model 93
4.1 Types of Projects Investigated 99
4.2 Academic Qualification of Respondents 102
4.3 Academic Discipline of Respondents 102
4.4 Respondents' Nature of Business 103
4.5 Types of IBS Used 105
4.6 Relationship of 'Delay in payment' and ' Increased Cost Variance' 132
XIII
4.7 Relationship of ' Allowance of Partially Handover' and
' Increased Cost Variance' 132
4.8 Relationship of ' Requirement of Deposit by IBS Supplier'
and ' Increased Cost Variance' 133
4.9 Relationship of 'Application of Tracking Curve' and
' Increased Cost Variance' 133
4.10 Relationship of ' Academic Qualification' and
' Increased Cost Variance' 134
4.11 Relationship of 'Type of IBS ' and ' Increased Cost Variance' 134
4.12 Relationship of ' Construction Method' and ' Increased
Cost Variance' 135
4.13 Relationship of 'Time lag of Delivery' and ' Increased
Cost Variance' 135
4.14 Relationship of ' Application of CPM Method' and ' Increased
Cost Variance' 136
5.1 Cost Breakdown Structure (CBS) 143
5.2 Work Breakdown Structure (WBS) 143
5.3 Data Acquisition Form - General Information 146
5.4 Data Acquisition Form - Industrialized Building System 146
5.5 Data Acquisition Form - WBS 147
5.6 Links to Cost Control Forms 147
5.7 Cost Control Form - Overall Progress 148
5.8 Cost Control Form - Material 149
5.9 Cost Control Form - Manpower 149
5.10 Cost Control Form - Equipment 150
xiv
5.11 Report generated from Cost Control Model 154
B l General Information 174
B2 Information of Industrialized Building System 175
B3 Overall Progress for Wall Panel 176
B4 Data of Wall Panel 176
B5 Details of Manpower Required 177
B6 Details of Equipment Required 177
B7 Variance Report Generated 178
B8 Data Stored in Microsoft Excel Workbook 180
xv
NOTATIONS
IBS Industrialised Building System
WBS Work Breakdown Structure
CBS Cost Breakdown Structure
XVI
CHAPTER!
INTRODUCTION
Between years 1 995 to 2020, Malaysia will need a total of 8,850,554 houses,
including 4,964,560 units of new housing to cater for the increase in population
during this period. Unfortunately, only 1 ,382,9 1 7 units were constructed under the
6th ( 1 99 1 - 1 995) and ih ( 1 996-2000) Malaysia Plan. We have another 3 ,5 8 1 ,643
units to be built within the next twenty years. That is on average 1 ,790,820 units to
be built for every ten years. It is clear that unless a drastic change of policy
pertaining to population growth is adopted, or some new solutions for this increase in
housing demand is implemented, the housing problem is expected to continue for
years to come (Chen, 2000).
Industrialised Building System (IBS) has been proposed in many writings as
the solution for this increasing housing demands (Koo, 2000; Omar, 2000; Engletrik,
2000; Trikha, 1 999; Karim and Adeeb, 1 993 ; Din, 1 984). Chew ( 1 986) from
Ministry of Housing and Local Government, Malaysia mentioned that shorter
construction time, saving in labour cost/dependency, material saving, better quality
control, immunity to weather changes and the cost factor are among the advantages
of IBS . Shorter construction time offered by IBS seems to be the panacea for the
housing demand in Malaysia and it is proven successful in some of the countries,
namely Finland, England, and United States (CIDB, 1 998).
From the records in PAM's publications, different types of IBS have been
used in Malaysia since mid-50s and it is still expanding (Loo, 1986). Though some
of the IBS projects were successful in sustaining lower costs, others ended up with
higher costs in comparison to similar conventional housing proj ects. (Din, 1986)
Survey done by Malaysian Institute of Architects (PAM) on Industrialised
System for Housing in year 1986 (Loo, 1986) shows that in order to strengthen the
weaknesses for its improvements, it is essential to examine each activity from the
total delivery cycle of construction work in order to diagnose the real weaknesses.
In the background of early 80's the prefabrication method would cost more
due to their destitution of experience. However, the logic of the day was to set-off
the benefits of faster completion time against the higher unit cost in view of the
escalating prices due to the inflationary trend and that early delivery would save the
buyers interest charges and rentals. Cost overrun in the IBS projects are still
common in Malaysia until today and it is one of the reasons that limit the
development of IBS (Lew, 2000). In a research done in year 2000, 60% of the
projects studied experience delay of progress. The survey shows that more than half
of the projects studied have experienced cost overrun and material is the cost element
that contributes most of the variances (Lew et. aI. , 2000). Importance of cost
consciousness during construction is still not widespread in local construction
projects. Cost control for IBS is conducted as part of cost control of whole
construction project. In most of the cases, IBS works are awarded to suppliers or
subcontractors that specialized in IBS where monitoring of cost control over IBS
works has been overlooked (Lew et. aI., 2000).
2
According to Flanagan and Tate ( 1 997), the aim of cost control on
construction is to achieve faster construction to a higher quality at a lower cost. A
project may be regarded as ' successful ' if the building is completed on time, within
budget, without any accident, to the specified quality standards and overall clients'
satisfaction (Chan and Kumaraswamy, 2002). Kharbanda et. al. ( 1 987) mentioned
that the basic concepts of cost control are nothing new due to the size and complexity
of modern projects and the risks thereby involved, cost control today is more vital,
and more necessary than ever before. Therefore, cost control for local IBS projects
will be just applying the same old concepts of cost control with more emphasis given
on the differences between IBS and conventional construction methods, local site
conditions and availability of information or data needed in doing so.
3
Problem Statement
There are at least fourteen IBS being introduced in Malaysia (Thanoon et al. ,
1 996) for years, each of them have their own characteristics which are different from
conventional construction method. Therefore, management of IBS projects could not
be exactly the same as what we implement for conventional construction method.
Even though a number of cost control systems have been introduced for
construction projects, there is neither one which is specifically developed for the
construction projects using industrialised building system in Malaysia. According to
Dawood ( 1 994), most of the researches in the precast industry are concentrated on
the application of mathematical models to scheduling and long-range planning. Even
though there are models developed to calculate cost variance, it is not meant for IBS
industry and it is certainly not for Malaysia' s working environment. Many potential
users of IBS in Malaysia currently have no formal cost control system to monitor
their construction costs. We do have the traditional methods or systems of cost
control from centuries of trials, yet, we are still seeking for practicable cost control
system for IBS .
Generally, IBS are used in large projects with repetitive units and these
projects are extremely likely to have major overruns on both time and budget
(Hardie, 200 1 ) . Therefore, identification of potential problems and development of a
cost control model would absolutely assist in prevention and minimization of
negative cost variance occurrence.
4
Significant of Study
Due to the current economIC downturn, construction project cost control
become a great subject to all the practitioners in construction industry. Effective
construction systems that can maximize the profit determine the success of
construction companies. In conjunction with this, new systems have been introduced
to reduce the cost and improve the quality of work.
Industrialised Building System is one of the new methods introduced for
these purposes. These new building systems introduced are new methods of
construction that use new or modified materials and new technology. They are said
to be more effective in reducing manpower demand, duration of construction and
cost needed. Nevertheless, the degree of these systems' effectiveness are being
queried, can these systems really helps in reducing projects' cost by achieving the
advantages afore-mentioned? Or it is just a new idea of businessmen trying to
increase their profit? How do the project and other related characteristics that affect
the cost variance of these systems' construction affect their efficiency?
By identifying obstacles afore-mentioned, a cost control model will be
proposed based on the local working environments. This is extremely important
towards better cost control of IBS projects especially for contractors with limited
works in hand, higher competition and small margin on the profit from each project
during this recession time.
5
Objectives
This study is carried out to examine the factors contributing to problems
faced by local contractors that are related to the cost management of IBS projects in
Malaysia. The dominant objectives of this study are as follow:
1 . To identify the factors contributing to problems faced by local contractors
to control cost of IBS projects during construction.
2. To identify the strategies used by local contractors to reduce the cost
variation in IBS projects.
3. To propose a tentative cost control model for IBS projects.
The hypotheses that need to be tested in this study,
1. There is no relationship in problems faced by the local contractors during
construction of different building systems.
For first obj ective, the following hypotheses need to be tested:
2. Academic qualification of respondent IS likely to influence the cost
variance of IBS projects.
3. Respondent' s experience in IBS is likely to influence the cost variance of
IBS projects.
6
4. Project' s nature of work is likely to influence the cost variance of IBS
projects.
5. Type of client is likely to influence the cost variance of IBS projects.
6. Location of project is likely to influence the cost variance of IBS projects.
7. Type of contract is likely to influence the cost variance of IBS projects.
8. Allowance of partially handover is likely to influence the cost variance of
IBS projects.
9. Delayed payment from client is likely to influence the cost variance of
IBS projects.
1 0 . Frequency of meeting with client is likely to influence the cost variance
of IBS projects.
11 . Type of IBS is likely to influence the cost variance of IBS projects.
12. Construction method 1S likely to influence the cost vanance of IBS
projects.
1 3 . Frequency of meeting with supplier/subcontractor is likely to influence
the cost variance of IBS projects.
7
14 . Time lag of IBS elements' delivery is likely to influence the cost variance
of IBS projects.
1 5 . On site prefabrication IS likely to influence the cost vanance of IBS
projects.
1 6 . Requirement of deposit by the supplier before the first delivery is likely to
influence the cost variance of IBS projects.
1 7. Number of variation order is likely to influence the cost variance of IBS
projects.
1 8 . Application of cost control method is likely to influence the cost variance
of IBS projects.
8