University of Akron Addendum No. 1 For Project #: 150015 Lee Jackson Practice Field Turf Replacement University of Akron Capital Planning & Facilities Management Lincoln Building Akron, Ohio 44325-0405 v: 330.972.8316 f: 330.972.5838 Web site: www.uakron.edu
Transcript
Page 1: University of Akron Addendum No. 1installation, schedule and conduct a meeting at the project site to review existing conditions and other factors affecting turf installation work.

University of Akron Addendum No. 1 For Project #: 150015 Lee Jackson Practice Field Turf Replacement University of Akron Capital Planning & Facilities Management Lincoln Building Akron, Ohio 44325-0405 v: 330.972.8316 f: 330.972.5838 Web site: www.uakron.edu

Page 2: University of Akron Addendum No. 1installation, schedule and conduct a meeting at the project site to review existing conditions and other factors affecting turf installation work.

Office of the Vice President

Capital Planning and Facilities Management Akron, Ohio 44325-0405

(330) 972-8316 Office (330) 972-5838 Fax

Date: February 10, 2015 Project: The University of Akron Project #150015 Lee Jackson Practice Field Turf Replacement Akron, Ohio 44325 Addendum No. 1 This addendum varies the Bidding and Contract Documents dated 1/27/2015 and titled: Project #150015 Lee Jackson Practice Field Turf Replacement This Addendum shall form part of the Contract Documents and is to be read, interpreted and coordinated with all other parts. The cost of all work contained herein shall be included in the Contract sum. The following revisions supersede the information contained in the original specifications and drawings issued for the above-named project. Acknowledge receipt of this Addendum by inserting its number, date and pages in 00 41 16 – Bid Form Summary of Attachments:

1. Addendum No. 1; Summary and General Clarifications. Includes the following sections: a. General Clarfications b. Revised Specifications c. General Questions and Answers

2. Updated Specification Sections

Page 3: University of Akron Addendum No. 1installation, schedule and conduct a meeting at the project site to review existing conditions and other factors affecting turf installation work.

1

Office of the Vice President

Capital Planning and Facilities Management Akron, Ohio 44325-0405

(330) 972-8316 Office (330) 972-5838 Fax

Date: February 10, 2015 Project: The University of Akron Project #150015 Lee Jackson Practice Field Turf Replacement Akron, Ohio 44325 Addendum No. 1 Summary and General Clarifications 1.0 General Clarifications

1.1 The following substitutions have been approved:

1.1.1 Section 32 18 13 Synthetic Turf Base Bid 1A; 2.3B Pre-Approved Products and Manufacturers by owner are: 5. The Motz Group LLC – Sportgrass

2.0 Revised Specifications

2.1 DOCUMENT 32 18 13 SYNTHETIC TURF BASE BID 1A 2.1.1 2.2 Synthetic Turf Products: revised item 4. Tufted pile height to Min. 2.25”,

finished 2.1.2 INCLUDE in 2.3B Pre-Approved Products and Manufacturers by owner are: 5.

The Motz Group LLC – Sportgrass 2.2 DOCUMENT 32 18 13 SYNTHETIC TURF BASE BID 1B

2.2.1 2.2 Synthetic Turf Products: revised item 4. Tufted pile height to Min. 2.25”, finished

2.3 DOCUMENT 32 18 13 SYNTHETIC TURF BASE BID 1C 2.3.1 2.2 Synthetic Turf Products: revised item 4. Tufted pile height to Min. 2.25”,

finished 3.0 General Questions and Answers

3.1 Q: What is the thickness of the existing shock pad to be removed?

A: 6 mm 3.2 Q: The fiber height is listed as 2” minimum and the infill depth is 1.5”. The proper and

best performing fiber needs to be .75” above the infill which will make the fiber height 2.25”? A: See revised specifications above.

Page 4: University of Akron Addendum No. 1installation, schedule and conduct a meeting at the project site to review existing conditions and other factors affecting turf installation work.

2

3.3 Q: You have listed a minimum weight on the fiber why not the infill? A: Infill is to the manufacturer’s standard mixture of rubber granules and washed silica sand per the specifications.

3.4 Q: Our seaming (Not patented) is sewing to a selvedge edge that is built into each side of our 5-yard panels. This allows us to sew the seam and then is tucked under the field. The other method of sewing is butt sewn seams. This method can expose the stitching cord to the athletes and is nowhere near as durable as selvedge edge sewn seams. A: Seams will be installed per specific manufacturer’s recommendation.

3.5 Q: Our warranty is an 8-year pre-paid insured warranty through a third party A++ insurance company. There is no deductible and non-prorated. It’s worth an aggregate annual limit of $32 Million. A: See specification for warranty requirements.

Page 5: University of Akron Addendum No. 1installation, schedule and conduct a meeting at the project site to review existing conditions and other factors affecting turf installation work.

University of Akron Lee Jackson Practice Field Turf Replacement Issued for Bid Project No. 150015 January 2015 Revised: Addendum 1 February 10, 2015

SYNTHETIC TURF SYSTEM BID 1A 32 18 13 - 1

SECTION 32 18 13

SYNTHETIC TURF SYSTEM BASE BID 1A PART I - GENERAL 1.1 Related Documents A. Draws and general provisions of the Contract, including General and Supplementary Conditions

and other Division 01 Specification Sections, apply to this Section. 1.2 Summary A. The work to be performed under this section consists of furnishing all labor, materials, utilities,

and equipment necessary to supply, transport and install a complete synthetic turf system as indicated on the drawings and as specified herein.

B. This section provides for a FIFA Recommended Proprietary Monofilament Synthetic Turf

System, including but not limited to:

1. Aggregate base 2. Synthetic turf carpeting and accessories 3. Synthetic turf anchoring system 4. Turf infill materials 5. Striping and numbering (inlaid) 6. Special project warranty

1.3 Reference Standards A. General: Section 01 42 00 – References.

B. American Society for Testing and Materials (ASTM)

1. ASTM D789 Standard Test Methods for Determination of Relative Viscosity and Moisture Content of Polyamide (PA)

2. ASTM D1335 Standard Test Method for Tuft Bind of Pile Floor Coverings 3. ASTM D1577 Standard Test Methods for Linear Density of Textile Fibers 4. ASTM D2256 Standard Test Method for Tensile Properties of Yarns by the Single-

Strand Method 5. ASTM D2859 Standard Test Method for Ignition Characteristics of Finished Textile

Floor Covering Materials 6. ASTM D4158 Standard Guide for Abrasive Resistance of Textile Fabrics (Uniform

Abrasion) 7. ASTM D4632 Standard Test Method for Grab Breaking Load and Elongation of

Geotextiles 8. ASTM F355 Standard Test Method for Shock-Absorbing Properties of Playing

Surface Systems and Materials 9. ASTM F1015 Standard Test Method for Relative Abrasiveness of Synthetic Turf

Playing Surfaces 10. ASTM F1551 Standard Test Methods for Comprehensive Characterization of Synthetic

Turf Playing Surfaces and Materials

Page 6: University of Akron Addendum No. 1installation, schedule and conduct a meeting at the project site to review existing conditions and other factors affecting turf installation work.

University of Akron Lee Jackson Practice Field Turf Replacement Issued for Bid Project No. 150015 January 2015 Revised: Addendum 1 February 10, 2015

SYNTHETIC TURF SYSTEM BID 1A 32 18 13 - 2

C. National Collegiate Athletic Association (NCAA)

1. NCAA Soccer and Football Rules and Interpretations, latest edition

D. Ohio Department of Transportation (ODOT)

1. Section 204, Subgrade Compaction and Proof Rolling, Construction and Material Specifications, latest edition

E. Federation Internationale de Football Associaton (FIFA)

1. FIFA Quality Concept for Football Turf Recommended 1.4 System Description B. System performance requirements:

1. Abrasion Resistance: ASTM D4158 2. Relative Abrasion Index: less than 25 when tested in accordance with ASTM F1015 3. System Gmax Values when tested in accordance with ASTM F355: a. Value at contract completion shall not be greater than 130 b. Value at conclusion of eight year warranty period shall not exceed 170 4. Ball Rebound: ASTM F1551 5. Surface Burning Characteristics:

a. Yarn Melting Point: not less than 250 degrees when tested in accordance with ASTM D789

b. Critical Radiant Flux: 24 BTUs/hour/square foot when testing in accordance with ASTM D648

c. Pill Burn Test Results (when tested with infill): passes per ASTM D2859 6. Synthetic Turf Permeability: System shall have the capacity to transfer surface water

through turf carpeting and free draining aggregate base for a minimum rainfall of ten inches per hour in accordance with ASTM F-1551.

1.5 Submittals A. General: Section 01 33 00 – Submittals

B. Manufacturer’s product data for specified components:

1. Synthetic turf system components 2. Turf grooming tractor attachment

C. Qualification Data:

1. Manufacturer’s qualification statement 2. Manufacturer’s certification of system installer

D. Shop Drawings: Sections, details, and plans for turf installation, including interfaces with

surround fence/mowing table and line marking plan.

E. Product Samples:

Page 7: University of Akron Addendum No. 1installation, schedule and conduct a meeting at the project site to review existing conditions and other factors affecting turf installation work.

University of Akron Lee Jackson Practice Field Turf Replacement Issued for Bid Project No. 150015 January 2015 Revised: Addendum 1 February 10, 2015

SYNTHETIC TURF SYSTEM BID 1A 32 18 13 - 3

1. 12” x 12” synthetic turf carpeting and sample

F. Material Certificates:

1. Synthetic turf materials

G. Manufacturer’s installation instructions

H. Laboratory test reports by a certified independent testing agency that the following products comply with specified performance requirements:

1. Synthetic turf carpeting 2. Specified Gmax values of system

I. Qualification data for firms and individuals identified in Quality Assurance article below. 1.6 Quality Assurance A. General: Section 01 40 00 – Quality Requirements B. Manufacturer’s Qualifications: Manufacturer shall be a consistent producer of synthetic turf

systems equivalent to the type and extent required for this project for a period of not less than ten years. Document at least seven projects of the type and extent required for this project completed within the previous three years.

C. Installer’s Qualifications: Engage an installing firm that has a minimum of 5 years of experience

installing synthetic turf systems of the type and extent required for the project. Document at least four projects of the type and extent required for this project completed within the previous three years. Synthetic turf system work shall be performed only by experienced workmen familiar with synthetic turf installation work under the supervision of a qualified experienced supervisor.

D. Pre-Installation Conference: Within seven days of the proposed start of the synthetic turf

installation, schedule and conduct a meeting at the project site to review existing conditions and other factors affecting turf installation work. Attendees shall include installer, system manufacturer, construction manager, associate engineer and landscape architect, and trade contractors whose work will be affected by turf system installation. Record and distribute meeting proceedings to all attendees. Do not proceed with installation until all issues related to turf installation are satisfactorily resolved.

1.7 Delivery, Storage And Handling A. General: Comply with general provisions for delivery, storage, and handling in Section 01600 –

General Product Requirements. B. Deliver and store synthetic turf products in a manner that will permit inventory and inspection of

their condition until installation. C. Provide protective measures to prevent theft, contamination, or deterioration of synthetic turf

products

1.8 Warranty A. General: Refer to applicable portions of the Conditions of the Contract and Division 1 for general

provisions regarding warranties and guarantees.

Page 8: University of Akron Addendum No. 1installation, schedule and conduct a meeting at the project site to review existing conditions and other factors affecting turf installation work.

University of Akron Lee Jackson Practice Field Turf Replacement Issued for Bid Project No. 150015 January 2015 Revised: Addendum 1 February 10, 2015

SYNTHETIC TURF SYSTEM BID 1A 32 18 13 - 4

B. Special Project Warranty: System manufacturer shall furnish a warranty for the installed system,

supported by a bond executed by a corporate surety licensed to conduct business in the State of Ohio and with at least a B rating in the current Best’s Key Rating Guide. The Owner shall be named as the bond obligee. The warranty shall provide for repair or replacement of defective synthetic turf system components, including excessive deterioration or failure of system components when the system is subjected to normal use. Normal use shall include the occasional transit of maintenance vehicles across the synthetic turf system for, but not limited to, normal field maintenance and the changing of lamps associated with the overhead sports lighting system by means of a “cherry picker.” Repair or replacement shall include all costs associated with verifying failures, removal of deteriorated or defective products, replacement, testing, transportation, travel, and other expenses related to corrective measures. The warranty period shall be eight (8) years from the date of Substantial Completion of the project.

1.9 Maintenance

A. Maintenance Materials: provide the following:

1. Four (4) sealed 55-gallon drums filled with specified rubber granules for Owner’s maintenance purposes. Deliver to a location approved by the Owner and obtain a signed receipt. Submit receipt at project closeout.

2. Turf grooming tractor attachment with hitch for connecting to Owner’s maintenance equipment.

PART 2 – PRODUCTS

2.1 Base Materials

A. Base Materials: Provide free draining open graded aggregate as approved by the manufacturer.

Additional base material must be compatible with existing aggregate.

2.2 Synthetic Turf Products

A. Synthetic Turf Carpet: Slip-resistant polyethylene fiber tufted into a permeable double-layered polypropylene primary backing with heat-fused urethane secondary backing, with the following physical characteristics: 1. Pile weight: 40 ounces per square yard 2. Primary backing weight: 8 ounces per square yard 3. Secondary backing weight: 20 ounces per square yard 4. Tufted pile height: Min 2.25 inches, finished 5. Stitch gauge: ¾-inch on center 6. Yarn breaking strength: (Monofilament) 20 pounds when tested in accordance with ASTM D2256 7. Yarn maximum elongation: (Monofilament) 50 percent when testing in accordance with ASTM D2256 8. Yarn density: Min. 8,800 Denier when tested in accordance with ASTM D1577 9. Tuft bind without infill: 7.75 pounds when tested in accordance with ASTM D1335 10. Grab tear strength: 170 pounds when tested in accordance with ASTM D4632

Page 9: University of Akron Addendum No. 1installation, schedule and conduct a meeting at the project site to review existing conditions and other factors affecting turf installation work.

University of Akron Lee Jackson Practice Field Turf Replacement Issued for Bid Project No. 150015 January 2015 Revised: Addendum 1 February 10, 2015

SYNTHETIC TURF SYSTEM BID 1A 32 18 13 - 5

B. Infill Material: Manufacturer’s standard mixture, applied to an average depth of 1½ inches of the

following:

1. Rubber granules containing no steel particles 2. Washed silica sand (use varies with manufacturer)

C. Accessories: Provide all necessary accessories recommended by the manufacturer to complete

the installation in accordance with the Contract Documents, including terminations, edges, splicing materials, fasteners, and other necessary appurtenances.

2.3 Manufacturers And Products

A. Base Bid FIFA Recommended Proprietary Monofilament Synthetic Turf System: B. Pre-Approved Products and Manufacturers by owner are: 1. Pro Grass LLC - Xtreme Turf DX 60 2. Shaw Sports Turf - Powerblade Bolt 3. Field Turf - Field Turf Revolution 4. Astro Turf - Astro Play GT 5. The Motz Group, LLC - Sportgrass 2.4 Synthetic Turf Anchoring System

A. The synthetic turf system must be installed in a manner compatible with the existing anchoring

system.

PART 3 – EXECUTION 3.1 Execution, General A. Refer to Section 01700 – Execution Requirements 3.2 Base Installation

A. Install free draining aggregate base as required by the manufacturer.

3.3 Synthetic Turf System Installation

A. Lay out synthetic turf carpet with seams perpendicular to the direction of play. Orient inlaid

(tufted) lines according to approved shop drawings.

B. Sew all seams in accordance with manufacturer’s approved methods.

C. Place infill material in accordance with manufacturer’s instructions, using skilled applicators.

1. Brooms shall have only nylon bristles. No metal tools shall be used to place and distribute infill.

Page 10: University of Akron Addendum No. 1installation, schedule and conduct a meeting at the project site to review existing conditions and other factors affecting turf installation work.

University of Akron Lee Jackson Practice Field Turf Replacement Issued for Bid Project No. 150015 January 2015 Revised: Addendum 1 February 10, 2015

SYNTHETIC TURF SYSTEM BID 1A 32 18 13 - 6

D. Install edge-anchoring system in accordance with manufacturer’s instructions.

E. Install inlaid (tufted) field markings in accordance with manufacturers approved methods (cutting

and splicing turf with minimum 6” overlap which is secured with adhesive).

3.4 Striping and Marking (inlaid permanent colors)

A. Striping and markings shall comply with NCAA requirements, including but not limited to “Field Diagram” and “Field Diagram Details.”

3.5 Inspection

A. Arrange for manufacturer’s factory representative to review and inspect installation prior to acceptance to ensure conformance of installation with manufacturer’s standards.

3.6 Demonstration and Training

A. Provide turf maintenance training for Owner’s personnel. Identify appropriate tools and methods for proper turf maintenance in accordance with manufacturer’s recommendations and published maintenance instructions.

3.7 Clean-Up

A. Remove scraps and debris from work areas and legally dispose of off the project site.

B. Remove surplus infill and carpet materials from work areas and transport to a location designated by the Owner.

END OF SECTION 32 18 13

Page 11: University of Akron Addendum No. 1installation, schedule and conduct a meeting at the project site to review existing conditions and other factors affecting turf installation work.

University of Akron Lee Jackson Practice Field Turf Replacement Issued for Bid Project No. 150015 January 2015 Revised: Addendum 1 February 10,2015

SYNTHETIC TURF SYSTEM BID 1B 32 18 13 - 1

SECTION 321813

SYNTHETIC TURF SYSTEM BASE BID 1B PART I - GENERAL 1.1 Related Documents A. Draws and general provisions of the Contract, including General and Supplementary Conditions

and other Division 01 Specification Sections, apply to this Section. 1.2 Summary A. The work to be performed under this section consists of furnishing all labor, materials, utilities,

and equipment necessary to supply, transport and install a complete synthetic turf system as indicated on the drawings and as specified herein.

B. This section provides for a FIFA Recommended Proprietary Blended or Hybrid Synthetic Turf

System, including but not limited to:

1. Aggregate base 2. Synthetic turf carpeting and accessories 3. Synthetic turf anchoring system 4. Turf infill materials 5. Striping and numbering (inlaid) 6. Special project warranty

1.3 Reference Standards A. General: Section 01 42 00 – References.

B. American Society for Testing and Materials (ASTM)

1. ASTM D789 Standard Test Methods for Determination of Relative Viscosity and Moisture Content of Polyamide (PA)

2. ASTM D1335 Standard Test Method for Tuft Bind of Pile Floor Coverings 3. ASTM D1577 Standard Test Methods for Linear Density of Textile Fibers 4. ASTM D2256 Standard Test Method for Tensile Properties of Yarns by the Single-

Strand Method 5. ASTM D2859 Standard Test Method for Ignition Characteristics of Finished Textile

Floor Covering Materials 6. ASTM D4158 Standard Guide for Abrasive Resistance of Textile Fabrics (Uniform

Abrasion) 7. ASTM D4632 Standard Test Method for Grab Breaking Load and Elongation of

Geotextiles 8. ASTM F355 Standard Test Method for Shock-Absorbing Properties of Playing

Surface Systems and Materials 9. ASTM F1015 Standard Test Method for Relative Abrasiveness of Synthetic Turf

Playing Surfaces 10. ASTM F1551 Standard Test Methods for Comprehensive Characterization of Synthetic

Turf Playing Surfaces and Materials

Page 12: University of Akron Addendum No. 1installation, schedule and conduct a meeting at the project site to review existing conditions and other factors affecting turf installation work.

University of Akron Lee Jackson Practice Field Turf Replacement Issued for Bid Project No. 150015 January 2015 Revised: Addendum 1 February 10,2015

SYNTHETIC TURF SYSTEM BID 1B 32 18 13 - 2

C. National Collegiate Athletic Association (NCAA)

1. NCAA Soccer and Football Rules and Interpretations, latest edition

D. Ohio Department of Transportation (ODOT)

1. Section 204, Subgrade Compaction and Proof Rolling, Construction and Material Specifications, latest edition

E. Federation Internationale de Football Associaton (FIFA)

1. FIFA Quality Concept for Football Turf Recommended 1.4 System Description B. System performance requirements:

1. Abrasion Resistance: ASTM D4158 2. Relative Abrasion Index: less than 25 when tested in accordance with ASTM F1015 3. System Gmax Values when tested in accordance with ASTM F355: a. Value at contract completion shall not be greater than 130 b. Value at conclusion of eight year warranty period shall not exceed 170 4. Ball Rebound: ASTM F1551 5. Surface Burning Characteristics:

a. Yarn Melting Point: not less than 250 degrees when tested in accordance with ASTM D789

b. Critical Radiant Flux: 24 BTUs/hour/square foot when testing in accordance with ASTM D648

c. Pill Burn Test Results (when tested with infill): passes per ASTM D2859 6. Synthetic Turf Permeability: System shall have the capacity to transfer surface water

through turf carpeting and free draining aggregate base for a minimum rainfall of ten inches per hour in accordance with ASTM F-1551.

1.5 Submittals A. General: Section 01 33 00 – Submittals

B. Manufacturer’s product data for specified components:

1. Synthetic turf system components 2. Turf grooming tractor attachment

C. Qualification Data:

1. Manufacturer’s qualification statement 2. Manufacturer’s certification of system installer

D. Shop Drawings: Sections, details, and plans for turf installation, including interfaces with

surround fence/mowing table and line marking plan.

E. Product Samples:

Page 13: University of Akron Addendum No. 1installation, schedule and conduct a meeting at the project site to review existing conditions and other factors affecting turf installation work.

University of Akron Lee Jackson Practice Field Turf Replacement Issued for Bid Project No. 150015 January 2015 Revised: Addendum 1 February 10,2015

SYNTHETIC TURF SYSTEM BID 1B 32 18 13 - 3

1. 12” x 12” synthetic turf carpeting and sample

F. Material Certificates:

1. Synthetic turf materials

G. Manufacturer’s installation instructions

H. Laboratory test reports by a certified independent testing agency that the following products comply with specified performance requirements:

1. Synthetic turf carpeting 2. Specified Gmax values of system

I. Qualification data for firms and individuals identified in Quality Assurance article below. 1.6 Quality Assurance A. General: Section 01 40 00 – Quality Requirements B. Manufacturer’s Qualifications: Manufacturer shall be a consistent producer of synthetic turf

systems equivalent to the type and extent required for this project for a period of not less than ten years. Document at least seven projects of the type and extent required for this project completed within the previous three years.

C. Installer’s Qualifications: Engage an installing firm that has a minimum of 5 years of experience

installing synthetic turf systems of the type and extent required for the project. Document at least four projects of the type and extent required for this project completed within the previous three years. Synthetic turf system work shall be performed only by experienced workmen familiar with synthetic turf installation work under the supervision of a qualified experienced supervisor.

D. Pre-Installation Conference: Within seven days of the proposed start of the synthetic turf

installation, schedule and conduct a meeting at the project site to review existing conditions and other factors affecting turf installation work. Attendees shall include installer, system manufacturer, construction manager, associate engineer and landscape architect, and trade contractors whose work will be affected by turf system installation. Record and distribute meeting proceedings to all attendees. Do not proceed with installation until all issues related to turf installation are satisfactorily resolved.

1.7 Delivery, Storage And Handling A. General: Comply with general provisions for delivery, storage, and handling in Section 01600 –

General Product Requirements. B. Deliver and store synthetic turf products in a manner that will permit inventory and inspection of

their condition until installation. C. Provide protective measures to prevent theft, contamination, or deterioration of synthetic turf

products

1.8 Warranty A. General: Refer to applicable portions of the Conditions of the Contract and Division 1 for general

provisions regarding warranties and guarantees.

Page 14: University of Akron Addendum No. 1installation, schedule and conduct a meeting at the project site to review existing conditions and other factors affecting turf installation work.

University of Akron Lee Jackson Practice Field Turf Replacement Issued for Bid Project No. 150015 January 2015 Revised: Addendum 1 February 10,2015

SYNTHETIC TURF SYSTEM BID 1B 32 18 13 - 4

B. Special Project Warranty: System manufacturer shall furnish a warranty for the installed system,

supported by a bond executed by a corporate surety licensed to conduct business in the State of Ohio and with at least a B rating in the current Best’s Key Rating Guide. The Owner shall be named as the bond obligee. The warranty shall provide for repair or replacement of defective synthetic turf system components, including excessive deterioration or failure of system components when the system is subjected to normal use. Normal use shall include the occasional transit of maintenance vehicles across the synthetic turf system for, but not limited to, normal field maintenance and the changing of lamps associated with the overhead sports lighting system by means of a “cherry picker.” Repair or replacement shall include all costs associated with verifying failures, removal of deteriorated or defective products, replacement, testing, transportation, travel, and other expenses related to corrective measures. The warranty period shall be eight (8) years from the date of Substantial Completion of the project.

1.9 Maintenance

A. Maintenance Materials: provide the following:

1. Four (4) sealed 55-gallon drums filled with specified rubber granules for Owner’s maintenance purposes. Deliver to a location approved by the Owner and obtain a signed receipt. Submit receipt at project closeout.

2. Turf grooming tractor attachment with hitch for connecting to Owner’s maintenance equipment.

PART 2 – PRODUCTS

2.1 Base Materials

A. Base Materials: Provide free draining open graded aggregate as approved by the manufacturer.

Additional base material must be compatible with existing aggregate.

2.2 Synthetic Turf Products

A. Synthetic Turf Carpet: Slip-resistant polyethylene fiber tufted into a permeable double-layered polypropylene primary backing with heat-fused urethane secondary backing, with the following physical characteristics: 1. Pile weight: 40 ounces per square yard 2. Primary backing weight: 8 ounces per square yard 3. Secondary backing weight: 20 ounces per square yard 4. Tufted pile height: Min 2.25 inches, finished 5. Stitch gauge: ¾-inch on center 6. Yarn breaking strength: (Monofilament) 20 pounds when tested in accordance with ASTM D2256 (Slit Film) 8 pounds when tested in accordance with ASTM D2256 7. Yarn maximum elongation: (Monofilament) 50 percent when testing in accordance with ASTM D2256 (Slit Film) 25 percent when testing in accordance with ASTM D2256 8. Yarn density: Min. 8,800 Denier when tested in accordance with ASTM D1577

Page 15: University of Akron Addendum No. 1installation, schedule and conduct a meeting at the project site to review existing conditions and other factors affecting turf installation work.

University of Akron Lee Jackson Practice Field Turf Replacement Issued for Bid Project No. 150015 January 2015 Revised: Addendum 1 February 10,2015

SYNTHETIC TURF SYSTEM BID 1B 32 18 13 - 5

9. Tuft bind without infill: 7.75 pounds when tested in accordance with ASTM D1335 10. Grab tear strength: 170 pounds when tested in accordance with ASTM D4632

B. Infill Material: Manufacturer’s standard mixture, applied to an average depth of 1½ inches of the

following:

1. Rubber granules containing no steel particles 2. Washed silica sand (use varies with manufacturer)

C. Accessories: Provide all necessary accessories recommended by the manufacturer to complete

the installation in accordance with the Contract Documents, including terminations, edges, splicing materials, fasteners, and other necessary appurtenances.

2.3 Manufacturers And Products

A. Base Bid FIFA Recommended Proprietary Blended or Hybrid Synthetic Turf System: B. Pre-Approved Products and Manufacturers by owner are: 1. Pro Grass LLC - Primetime Turf BX 60 2. Shaw Sports Turf - Legion 3. Field Turf - Field Turf Vertex 2.4 Synthetic Turf Anchoring System

A. The synthetic turf system must be installed in a manner compatible with the existing anchoring

system.

PART 3 – EXECUTION 3.1 Execution, General A. Refer to Section 01700 – Execution Requirements 3.2 Base Installation

A. Install free draining aggregate base as required by the manufacturer.

3.3 Synthetic Turf System Installation

A. Lay out synthetic turf carpet with seams perpendicular to the direction of play. Orient inlaid

(tufted) lines according to approved shop drawings.

B. Sew all seams in accordance with manufacturer’s approved methods.

C. Place infill material in accordance with manufacturer’s instructions, using skilled applicators.

1. Brooms shall have only nylon bristles. No metal tools shall be used to place and distribute infill.

D. Install edge-anchoring system in accordance with manufacturer’s instructions.

Page 16: University of Akron Addendum No. 1installation, schedule and conduct a meeting at the project site to review existing conditions and other factors affecting turf installation work.

University of Akron Lee Jackson Practice Field Turf Replacement Issued for Bid Project No. 150015 January 2015 Revised: Addendum 1 February 10,2015

SYNTHETIC TURF SYSTEM BID 1B 32 18 13 - 6

E. Install inlaid (tufted) field markings in accordance with manufacturers approved methods (cutting

and splicing turf with minimum 6” overlap which is secured with adhesive).

3.4 Striping and Marking (inlaid permanent colors)

A. Striping and markings shall comply with NCAA requirements, including but not limited to “Field

Diagram” and “Field Diagram Details.”

3.5 Inspection

A. Arrange for manufacturer’s factory representative to review and inspect installation prior to acceptance to ensure conformance of installation with manufacturer’s standards.

3.6 Demonstration and Training

A. Provide turf maintenance training for Owner’s personnel. Identify appropriate tools and methods for proper turf maintenance in accordance with manufacturer’s recommendations and published maintenance instructions.

3.7 Clean-Up

A. Remove scraps and debris from work areas and legally dispose of off the project site.

B. Remove surplus infill and carpet materials from work areas and transport to a location designated by the Owner.

END OF SECTION 32 18 13

Page 17: University of Akron Addendum No. 1installation, schedule and conduct a meeting at the project site to review existing conditions and other factors affecting turf installation work.

University of Akron Lee Jackson Practice Field Turf Replacement Issued for Bid Project No. 150015 January 2015 Revised: Addendum 1 February 10,2015

SYNTHETIC TURF SYSTEM BID 1C 32 18 13 - 1

SECTION 321813

SYNTHETIC TURF SYSTEM BASE BID 1C PART I - GENERAL 1.1 Related Documents A. Draws and general provisions of the Contract, including General and Supplementary Conditions

and other Division 01 Specification Sections, apply to this Section. 1.2 Summary A. The work to be performed under this section consists of furnishing all labor, materials, utilities,

and equipment necessary to supply, transport and install a complete synthetic turf system as indicated on the drawings and as specified herein.

B. This section provides for a FIFA Recommended Proprietary Monofilament Synthetic Turf

System with “Rootzone” or “Thatch”, including but not limited to:

1. Aggregate base 2. Synthetic turf carpeting and accessories 3. Synthetic turf anchoring system 4. Turf infill materials 5. Striping and numbering (inlaid) 6. Special project warranty

1.3 Reference Standards A. General: Section 01 42 00 – References.

B. American Society for Testing and Materials (ASTM)

1. ASTM D789 Standard Test Methods for Determination of Relative Viscosity and Moisture Content of Polyamide (PA)

2. ASTM D1335 Standard Test Method for Tuft Bind of Pile Floor Coverings 3. ASTM D1577 Standard Test Methods for Linear Density of Textile Fibers 4. ASTM D2256 Standard Test Method for Tensile Properties of Yarns by the Single-

Strand Method 5. ASTM D2859 Standard Test Method for Ignition Characteristics of Finished Textile

Floor Covering Materials 6. ASTM D4158 Standard Guide for Abrasive Resistance of Textile Fabrics (Uniform

Abrasion) 7. ASTM D4632 Standard Test Method for Grab Breaking Load and Elongation of

Geotextiles 8. ASTM F355 Standard Test Method for Shock-Absorbing Properties of Playing

Surface Systems and Materials 9. ASTM F1015 Standard Test Method for Relative Abrasiveness of Synthetic Turf

Playing Surfaces 10. ASTM F1551 Standard Test Methods for Comprehensive Characterization of Synthetic

Turf Playing Surfaces and Materials

Page 18: University of Akron Addendum No. 1installation, schedule and conduct a meeting at the project site to review existing conditions and other factors affecting turf installation work.

University of Akron Lee Jackson Practice Field Turf Replacement Issued for Bid Project No. 150015 January 2015 Revised: Addendum 1 February 10,2015

SYNTHETIC TURF SYSTEM BID 1C 32 18 13 - 2

C. National Collegiate Athletic Association (NCAA)

1. NCAA Soccer and Football Rules and Interpretations, latest edition

D. Ohio Department of Transportation (ODOT)

1. Section 204, Subgrade Compaction and Proof Rolling, Construction and Material Specifications, latest edition

E. Federation Internationale de Football Associaton (FIFA)

1. FIFA Quality Concept for Football Turf Recommended 1.4 System Description B. System performance requirements:

1. Abrasion Resistance: ASTM D4158 2. Relative Abrasion Index: less than 25 when tested in accordance with ASTM F1015 3. System Gmax Values when tested in accordance with ASTM F355: a. Value at contract completion shall not be greater than 130 b. Value at conclusion of eight year warranty period shall not exceed 170 4. Ball Rebound: ASTM F1551 5. Surface Burning Characteristics:

a. Yarn Melting Point: not less than 250 degrees when tested in accordance with ASTM D789

b. Critical Radiant Flux: 24 BTUs/hour/square foot when testing in accordance with ASTM D648

c. Pill Burn Test Results (when tested with infill): passes per ASTM D2859 6. Synthetic Turf Permeability: System shall have the capacity to transfer surface water

through turf carpeting and free draining aggregate base for a minimum rainfall of ten inches per hour in accordance with ASTM F-1551.

1.5 Submittals A. General: Section 01 33 00 – Submittals

B. Manufacturer’s product data for specified components:

1. Synthetic turf system components 2. Turf grooming tractor attachment

C. Qualification Data:

1. Manufacturer’s qualification statement 2. Manufacturer’s certification of system installer

D. Shop Drawings: Sections, details, and plans for turf installation, including interfaces with

surround fence/mowing table and line marking plan.

E. Product Samples:

Page 19: University of Akron Addendum No. 1installation, schedule and conduct a meeting at the project site to review existing conditions and other factors affecting turf installation work.

University of Akron Lee Jackson Practice Field Turf Replacement Issued for Bid Project No. 150015 January 2015 Revised: Addendum 1 February 10,2015

SYNTHETIC TURF SYSTEM BID 1C 32 18 13 - 3

1. 12” x 12” synthetic turf carpeting and sample

F. Material Certificates:

1. Synthetic turf materials

G. Manufacturer’s installation instructions

H. Laboratory test reports by a certified independent testing agency that the following products comply with specified performance requirements:

1. Synthetic turf carpeting 2. Specified Gmax values of system

I. Qualification data for firms and individuals identified in Quality Assurance article below. 1.6 Quality Assurance A. General: Section 01 40 00 – Quality Requirements B. Manufacturer’s Qualifications: Manufacturer shall be a consistent producer of synthetic turf

systems equivalent to the type and extent required for this project for a period of not less than ten years. Document at least seven projects of the type and extent required for this project completed within the previous three years.

C. Installer’s Qualifications: Engage an installing firm that has a minimum of 5 years of experience

installing synthetic turf systems of the type and extent required for the project. Document at least four projects of the type and extent required for this project completed within the previous three years. Synthetic turf system work shall be performed only by experienced workmen familiar with synthetic turf installation work under the supervision of a qualified experienced supervisor.

D. Pre-Installation Conference: Within seven days of the proposed start of the synthetic turf

installation, schedule and conduct a meeting at the project site to review existing conditions and other factors affecting turf installation work. Attendees shall include installer, system manufacturer, construction manager, associate engineer and landscape architect, and trade contractors whose work will be affected by turf system installation. Record and distribute meeting proceedings to all attendees. Do not proceed with installation until all issues related to turf installation are satisfactorily resolved.

1.7 Delivery, Storage And Handling A. General: Comply with general provisions for delivery, storage, and handling in Section 01600 –

General Product Requirements. B. Deliver and store synthetic turf products in a manner that will permit inventory and inspection of

their condition until installation. C. Provide protective measures to prevent theft, contamination, or deterioration of synthetic turf

products

1.8 Warranty A. General: Refer to applicable portions of the Conditions of the Contract and Division 1 for general

provisions regarding warranties and guarantees.

Page 20: University of Akron Addendum No. 1installation, schedule and conduct a meeting at the project site to review existing conditions and other factors affecting turf installation work.

University of Akron Lee Jackson Practice Field Turf Replacement Issued for Bid Project No. 150015 January 2015 Revised: Addendum 1 February 10,2015

SYNTHETIC TURF SYSTEM BID 1C 32 18 13 - 4

B. Special Project Warranty: System manufacturer shall furnish a warranty for the installed system,

supported by a bond executed by a corporate surety licensed to conduct business in the State of Ohio and with at least a B rating in the current Best’s Key Rating Guide. The Owner shall be named as the bond obligee. The warranty shall provide for repair or replacement of defective synthetic turf system components, including excessive deterioration or failure of system components when the system is subjected to normal use. Normal use shall include the occasional transit of maintenance vehicles across the synthetic turf system for, but not limited to, normal field maintenance and the changing of lamps associated with the overhead sports lighting system by means of a “cherry picker.” Repair or replacement shall include all costs associated with verifying failures, removal of deteriorated or defective products, replacement, testing, transportation, travel, and other expenses related to corrective measures. The warranty period shall be eight (8) years from the date of Substantial Completion of the project.

1.9 Maintenance

A. Maintenance Materials: provide the following:

1. Four (4) sealed 55-gallon drums filled with specified rubber granules for Owner’s maintenance purposes. Deliver to a location approved by the Owner and obtain a signed receipt. Submit receipt at project closeout.

2. Turf grooming tractor attachment with hitch for connecting to Owner’s maintenance equipment.

PART 2 – PRODUCTS

2.1 Base Materials

A. Base Materials: Provide free draining open graded aggregate as approved by the manufacturer.

Additional base material must be compatible with existing aggregate.

2.2 Synthetic Turf Products

A. Synthetic Turf Carpet: Slip-resistant polyethylene fiber tufted into a permeable double-layered polypropylene primary backing with heat-fused urethane secondary backing, with the following physical characteristics: 1. Pile weight: 40 ounces per square yard 2. Primary backing weight: 8 ounces per square yard 3. Secondary backing weight: 20 ounces per square yard 4. Tufted pile height: Min 2.25 inches, finished 5. Stitch gauge: ¾-inch on center 6. Yarn breaking strength: (Monofilament) 20 pounds when tested in accordance with ASTM D2256 7. Yarn maximum elongation: (Monofilament) 50 percent when testing in accordance with ASTM D2256 8. Yarn density: Min. 8,800 Denier when tested in accordance with ASTM D1577 9. Tuft bind without infill: 7.75 pounds when tested in accordance with ASTM D1335 10. Grab tear strength: 170 pounds when tested in accordance with ASTM D4632

Page 21: University of Akron Addendum No. 1installation, schedule and conduct a meeting at the project site to review existing conditions and other factors affecting turf installation work.

University of Akron Lee Jackson Practice Field Turf Replacement Issued for Bid Project No. 150015 January 2015 Revised: Addendum 1 February 10,2015

SYNTHETIC TURF SYSTEM BID 1C 32 18 13 - 5

B. Infill Material: Manufacturer’s standard mixture, applied to an average depth of 1½ inches of the

following:

1. Rubber granules containing no steel particles 2. Washed silica sand (use varies with manufacturer)

C. Accessories: Provide all necessary accessories recommended by the manufacturer to complete

the installation in accordance with the Contract Documents, including terminations, edges, splicing materials, fasteners, and other necessary appurtenances.

2.3 Manufacturers And Products

A. Base Bid FIFA Recommended Proprietary Monofilament Synthetic Turf System with

“Rootzone” or “Thatch”: B. Pre-Approved Products and Manufacturers by owner are: 1. Shaw Sports Turf - Powerblade SZ 2. Astro Turf - Gameday Grass 3D 2.4 Synthetic Turf Anchoring System

A. The synthetic turf system must be installed in a manner compatible with the existing anchoring

system.

PART 3 – EXECUTION 3.1 Execution, General A. Refer to Section 01700 – Execution Requirements 3.2 Base Installation

A. Install free draining aggregate base as required by the manufacturer.

3.3 Synthetic Turf System Installation

A. Lay out synthetic turf carpet with seams perpendicular to the direction of play. Orient inlaid

(tufted) lines according to approved shop drawings.

B. Sew all seams in accordance with manufacturer’s approved methods.

C. Place infill material in accordance with manufacturer’s instructions, using skilled applicators.

1. Brooms shall have only nylon bristles. No metal tools shall be used to place and distribute infill.

D. Install edge-anchoring system in accordance with manufacturer’s instructions.

Page 22: University of Akron Addendum No. 1installation, schedule and conduct a meeting at the project site to review existing conditions and other factors affecting turf installation work.

University of Akron Lee Jackson Practice Field Turf Replacement Issued for Bid Project No. 150015 January 2015 Revised: Addendum 1 February 10,2015

SYNTHETIC TURF SYSTEM BID 1C 32 18 13 - 6

E. Install inlaid (tufted) field markings in accordance with manufacturers approved methods (cutting

and splicing turf with minimum 6” overlap which is secured with adhesive).

3.4 Striping and Marking (inlaid permanent colors)

A. Striping and markings shall comply with NCAA requirements, including but not limited to “Field

Diagram” and “Field Diagram Details.”

3.5 Inspection

A. Arrange for manufacturer’s factory representative to review and inspect installation prior to acceptance to ensure conformance of installation with manufacturer’s standards.

3.6 Demonstration and Training

A. Provide turf maintenance training for Owner’s personnel. Identify appropriate tools and methods for proper turf maintenance in accordance with manufacturer’s recommendations and published maintenance instructions.

3.7 Clean-Up

A. Remove scraps and debris from work areas and legally dispose of off the project site.

B. Remove surplus infill and carpet materials from work areas and transport to a location designated by the Owner.

END OF SECTION 32 18 13