+ All Categories
Home > Documents > UPCOMING AIM INFRASTRUCTURE PROJECTS · UPCOMING AIM INFRASTRUCTURE PROJECTS ... TWY P & P7...

UPCOMING AIM INFRASTRUCTURE PROJECTS · UPCOMING AIM INFRASTRUCTURE PROJECTS ... TWY P & P7...

Date post: 29-Aug-2018
Category:
Upload: nguyenkhue
View: 214 times
Download: 0 times
Share this document with a friend
51
1 UPCOMING AIM INFRASTRUCTURE PROJECTS Somer Shindler, Senior Director Airport Infrastructure Management October 22, 2014
Transcript

1

UPCOMING AIM INFRASTRUCTURE PROJECTS

Somer Shindler, Senior DirectorAirport Infrastructure ManagementOctober 22, 2014

Welcome and Agenda

– Airside Projects

– Landside Projects

– Concourse B Pavement

– Survey Requirements

– BIM Requirements

– Additional Requirements

2

3

UPCOMING AIRSIDE PROJECTS

GLENN M. FRIELER P.E.DIRECTOR OF INFRASTRUCTURE AND QAOctober 22, 2014

Organizational Chart

4

Airside Engineering

Landside Engineering

Survey Unit

Quality Assurance

2015 DIA Projects (That did not make the cut)

9

DIA Main Terminal

2015 DIA Projects (That did not make the cut)

10

Pena Boulevard Expansion

2015 DIA Projects (That did not make the cut)

11

2015 DIA Projects (That did not make the cut)

12

DIA Space Port

2015 DIA Projects (That did not make the cut)

13

DIA Barr Lake Concourse

14

UPCOMING AIRSIDE PROJECTS

Keith Johnson & Brent NicholsAirside Engineering Project ManagersOctober 22, 2014

Runway 17L/35R Pavement Rehabilitation                    June – September , 2015

15

Description:Remove and replace deteriorated concrete slabs in Runway 17L/35R Complex, as well as the northern east‐west portion of TWY ED, parallel TWY P and connectors TWY P1 through TWY P9.  Project will include grading and erosion control on the slope northeast of Runway 35 Glideslope.  Replace airfield lighting components as required by the replacement of concrete panels.ROM Construction: $35MDBE Goal: 22%

Pavement Rehabilitation

Glycol Facility Drainage Improvements

Description:

The project consist of repairing the TWY F slope above the Glycol Recycling Facility and storm drainage improvements to prevent erosion of the slope and flooding of the Glycol Recycling Facility.  The project includes new storm water system of concrete swales, inlets and pipes, repairing damaged slope from erosion and restoring the secondary containment around storage tanks.ROM Construction: $2MDBE Goal: 4%(both subject to change)

16

Erosion

Mud in facilityMud in Containment area

Mud entering pond Broken pipes

Airfield Drainage Improvements‐On going

Description:This is an on‐going project.  For the year 2015, work will be performed on TWY P and TWY P7, shown on the next slide.  Some drainage structures have deteriorated or are inadequate.  Drainage channels have eroded allowing standing water.  Rehabilitate or replace deteriorated structures and construct new drainage improvements along the channels in airfield areas.  Repair erosion in existing drainage channels to eliminate standing water.   The scope of work for each year will be determined from field evaluation and the Drainage Master Plan.    

17

TWY P & P7 Drainage ImprovementsMarch – June, 2015

Description: Work for the On‐going Airfield Drainage Improvements for 2015 will include TWY P and TWY P7.  Construct a concrete trickle channel in the existing drainage swale in order to improve the flow and minimize standing water in a portion of the drainage system on RW 17L‐35R complex.  A new 2 inch water quality line and outfall will be installed for an existing dead end water line near ARFF Station 3. ROM Construction: $923,000DBE Goal: 17%(both subject to change)

18

2015 Annual Airfield Pavement & Joint Rehabilitation May ‐ October  2015

Description: The Pavement Rehabilitation and the Joint rehabilitation are combined into one project.   The Portland Cement Concrete Panels on Concourses A, B and C aprons and associated taxiways are exhibiting  distresses.  Panels will be removed and replaced.  The joints associated with these panels, will be rehabilitated by removing  and replacing the joint seal material and repairing spalls, as well as crack sealing.  The above mentioned  work will be performed during day and night time operations.ROM Construction: $5,925,000DBE Goal: 15%

2015 Airfield Pavement Evaluation

20

Description:This project would provideProfessional engineering services to evaluate existing airfield pavement conditions and update the existing Pavement Management Program.  The FAA requires an airfield pavement evaluation every 3‐5 years.  Evaluationshould occur in the spring of 2015 followed by the updating of the pavement management system.ROM: $500,000M/WBE Goal: 5%

21

UPCOMING LANDSIDE PROJECTS

Michelle MartinLandside Engineering SupervisorOctober 22, 2014

Bridge Rehabilitation (Airport Blvd to First Creek – 10 Structures)

22

Description:Repair and overlay of 10 structures on Inbound  Pena Boulevard. The work includes: deck repair, polyester concrete overlay of decks, removal and replacement of curb, bridge rail and guardrail, and expansion devices. This project will be advertised in November 2014, with an anticipated NTP date in March 2015.Goals: 18%

Corroded and damaged bridge railingExpansion devices needing replacement

Reinforcing and anchor bolts not per plan

Bridge deck worn down and delaminated

Miscellaneous Roadway & Parking Lot Improvements On-Call

23

Description:Repair, maintenance, and improvements of Airport roadways and parking lots. Work may include, but is not limited to: concrete panel replacements, correction of erosion and drainage issues, landscape maintenance, new parking lot or roadway construction, and preventative maintenance. Work already scheduled for this Contract includes the construction of Fire Station 35 Access Road, and erosion maintenance at the West Garage exit. Tasks may require significant night work hours to accommodate DIA’s 24/7 operation.  There will be two (2) On‐Call Task Order contracts totaling $8M each; the RFP will be advertised in October 2014, with an NTP date in March 2015 for a 3‐year term. Goals: 20%

Erosion issues along Pena Boulevard

Damaged guardrail 

Concrete panel replacements

Asphalt patching

Wastewater System Rehabilitation

24

Description:Repair and rehabilitation of over 200 sanitary manholes, facility‐wide, including Landside and Airside. Construction is scheduled to be performed between 2015 and 2021, as approved by the State. The work may be apportioned and included in other scopes of work to minimize operational disruptions.

71st Avenue Water Quality Improvements

25

Description:Construction of a water quality facility, including an improved channel and an extended detention along 71st Avenue, west of Robertsdale Street. This project is anticipated to be advertised in November 2014, with a NTP date in April 2015. 

26

UPCOMING AIM INFRASTRUCTURE PROJECTS

GLENN M. FRIELER P.E.DIRECTOR OF INFRASTRUCTURE AND QAOctober 22, 2014

QUESTIONS?

27

CONCOURSE B PAVEMENT

Kara LentzAIM – Project ManagerOctober 22, 2014

Apron Pavement Rehabilitation - Scope

– Remove and replacing apron pavement around Concourses B and C

– Restore the pavement slope to enhance drainage

– Install additional drains– Relocate and rehabilitate designated

utilities– Provide passenger loading bridge

enhancements as required– Associated apron work in the

immediate vicinity

28

CONCOURSE B AND C OVERVIEW

29

2015

2016

2017

Apron Pavement Rehabilitation - Qualifications

– Experience – Company and Key Personnel

– Experience working around active gates

– Paving and utilities experience

– City and County of Denver permitting experience

– CM/GC experience

– Project Approach

– Project Controls Methods

– Subconsultant and M/WBE Teaming

– Fee Percentage

– ROM Construction: $42M M/WBE Goals: 19% 30

31

CONTRACTOR SURVEY REQUIREMENTS

Dennis Hamlin, PLSLand Surveyor Supervisor – AIM/ConstructionOctober 22, 2014

WORK NOTICE

– Must give 48 hours written advance notice to DIA Project

Manager and Survey Manager before beginning work

– Contact DIA Operations for work in movement and non-

movement areas

– Contractor responsible for employee security training and

proper badging, before start of work– DIA Operations may require escort for contractor employees

for work in specific areas

– Discuss with DIA Operations in specific meeting

32

STATEMENT OF WORK PLAN

– Summarize project objective and location

– List FAA advisory circulars used as guidance

– List if submitting imagery plan, survey quality control plan,

geodetic control plan

– List geodetic control information to be used

– List imagery (needs six month NGS approval time, through

AGIS before survey work begins)

– Note the validation of DIA Airport PACS and SACS Points

– Identify survey requirements used, and specifications 3

SURVEY QUALITY CONTROL PLAN

– Project Summary Information:

– List type of project

– Why needed

– Data to be collected

– Why you collect data

– Purpose of Survey work.

4

SURVEY QUALITY CONTROL PLAN

– Field Survey Information:

– List field data collection procedures

– Define method, tools and techniques used to determine

position of objects

– List Airport control points for use in control work and

construction staking

– Describe survey observation techniques to be used

– List survey instruments to be used in control and construction

surveys

4

SURVEY QUALITY CONTROL PLAN CONTINUED.

– Geodetic Control Information

– Describe method to be used to tie temporary construction

control points to Airport Control Points

– Describe type of temporary control points for construction

control (Note: Control Points must be a rebar or hub with tack)

– Describe plan to set temporary control points along

construction project

5

SURVEY QUALITY CONTROL PLAN CONTINUED.

– Imagery Information

– Only required if you plan to collect imagery for project

– If imagery to be collected, describe how the project will be

completed and how data will be collected and used

5

SURVEY QUALITY CONTROL PLAN CONTINUED.

– Existing Data Information

– Describe use of collected data, to meet requirements of project

– Provide information regarding the source, traceability and quality of

gathered data

– Data Processing

– Describe use of tools, techniques and processes to post process,

reduce, and collect the data to produce the final deliverable required

– Equipment Listing

– Provide complete listing of equipment to be used in the survey

– Include model and serial numbers, calibration and equipment

maintenance reports 6

SURVEY QUALITY CONTROL PLAN CONTINUED.

– Quality Assurance Information

– Describe quality control measures to ensure data collected is checked

for errors

– Describe how accuracy requirements will be met using accuracy

requirements listed in project documents

– Describe data backup and archive procedures and methods to ensure

original data collected is not modified

– Describe software to be used to develop data set, and how data

features and feature attribution will be compiled

– Describe tools, techniques and processes survey field team will use to

ensure quality data collection7

SUMMARY OF CONTRACTOR SURVEYING REQUIREMENTS

– Meeting with DIA Project Manager and Surveyor, to get control information.

– Submittal of Statement of Work Plan (SOW) and Survey and Quality

Control Plan (SQCP) to DIA Project Manager and Surveyor for approval.

– Get submitted SQCP and SOW plans, reviewed and approved by DIA

Project Manager and Surveyor, before beginning survey control work.

– Start survey construction control work on project, and submit control work

survey data to DIA Survey Section in electronic format for approval.

– Start survey work on construction project, after submitted survey control

work is approved by DIA Survey Section.

– Submit completed as built work to DIA Project Manager, in LDP

Coordinates.

Contact Information

– Dennis Hamlin – Survey Manager

[email protected]

– 303-342-4428

– Tom Breitnauer – Sr. Surveyor

[email protected]

– 303-342-4485

42

BIM REQUIREMENTS

Brendan DillonAIM – Asset ManagementOctober 22, 2014

BIM Overview

– BIM is all about the flow of

information for a project:

– Existing Conditions

– Design

– Construction / Construction

Admin

– Cx / Closeout

– FM / O & M

Existing BIM / Assets

Construction Model

Design Model

ProjectStart

DataHarvest

Cx / CxDMA

Accurate Living

Building Model

Design Standards Manual 12

44

– Design Standards Manual 12

– Chapter 2: CADD Procedures

Manual

– BIM Project Execution Plan (BPXP)

– Executed in Autodesk Civil 3D

BIM Levels

3DModelingRenderingAnimation

Existing ConditionsConstruction 

Documentation

AutodeskRevit

(Arch, MEP, Struct)Civil 3D

BIM SOFTWARE USED AT DENVER INTERNATIONAL AIRPORT

4DScheduling

Just In Time deliveryPlanning and Logistics

Autodesk NavisworksPrimavera P6

Synchro

5DQuantity Take OffBudget analysis

Cost related to time for Earned Value 

Analysis

Autodesk NavisworksPrimavera P6

Synchro

6DReconciled BIM ModelAccurate Facilities Management and Asset Management 

models

MaximoESRI ArcGISDIA MapsPropworks

The BIM Process in Design

– Design

– Existing Conditions Modeling

– Design Authoring

– Spatial Coordination

– Design Review

– Construction Administration

– Change Management

– Record Model Reconciliation

Airfield – Asset Models

47

− Construction

as-built

capture

− Object based

− Populated

feature Data

Tables

Integration with Maximo

48

− Jet-Bridge Conditions Assessment

Integration into GIS

− FAA Mandated

− Data exported from

Revit /Civil 3D into

ESRI ArcGIS

− Maintain Feature

data tables

− Allow for dynamic

Analytics

49

Questions?

– Reference DSM 12 for Design and Construction Req.

– Chapter 2 CADD Procedures Manual for Civil/Infrastructure

– http://business.flydenver.com/bizops/documents/bim-

dsm12.pdf

– Contact

– Brendan Dillon – BIM Manager

[email protected]

303.342.2676

50

51

UPCOMING AIM INFRASTRUCTURE PROJECTS

Somer Shindler, Senior DirectorAirport Infrastructure ManagementOctober 22, 2014


Recommended