Upcoming Cold Projects. Sabine Pass LNG. Distrigaz LNG Terminal in Boston, MA. Cheniere Energy Trial. Insulation Incorporated: contractor Install on 36” line 80mm Cryogel system vs 9.5” (2 layer FOAMGLAS system) Results For large bore pipe and fittings: 80% faster install rate for Cryogel - PowerPoint PPT Presentation
30
Confidential & Propriet -1- Upcoming Cold Projects Distrigaz LNG Terminal in Boston, MA Sabine Pass LNG
Transcript
Page 1: Upcoming Cold Projects

Confidential & Proprietary

-1-

Upcoming Cold Projects

Distrigaz LNG Terminalin Boston, MA

Sabine Pass LNG

Page 2: Upcoming Cold Projects

Confidential & Proprietary

-2-

Cheniere Energy Trial

• Insulation Incorporated: contractor

• Install on 36” line– 80mm Cryogel system vs 9.5” (2 layer FOAMGLAS system)

• Results– For large bore pipe and fittings: 80% faster install rate for Cryogel

– For small bore pipe and fittings: 10-20% faster install for Cryogel(note small bore applies when half sections are applied)

Page 3: Upcoming Cold Projects

Confidential & Proprietary

Cryogel Installation Demo at theDistrigas LNG Terminal

Everett, MA

October, 2007

Page 4: Upcoming Cold Projects

Confidential & Proprietary

-4-

Background Info On 1st Cryogel Installation by Suez LNG NA

• Between Friday, October 12 and Tuesday, October 16, crews from Zampell Insulation installed foil-faced Cryogel on a section of piping at the Distrigas LNG terminal in Everett, MA

Moored position of boat

Install location

LNG storage tanks

Liquid and vapor lines

Scope of work included two 26 ft pipe sections abutting sliding shoes:• 24” liquid transfer line

• 12” vapor return line12” line

24” line

Page 5: Upcoming Cold Projects

Confidential & Proprietary

Installation

Page 6: Upcoming Cold Projects

Confidential & Proprietary

-6-

Brush Pipe and Existing Vapor Stop with 90-66 Prior to 1st Piece

Photo courtesy Zampell Insulation

Page 7: Upcoming Cold Projects

Confidential & Proprietary

-7-

Liquid Transfer Line Used 7 Layers (70 mm) Applied In 4 Pieces

Photo courtesy Zampell Insulation

Page 8: Upcoming Cold Projects

Confidential & Proprietary

-8-

Every Vertical and Horizontal Seam Butyl Taped

Photo courtesy Zampell Insulation

Page 9: Upcoming Cold Projects

Confidential & Proprietary

-9-

90-66 Application On Liquid Line Prior to 3rd Piece

Photo courtesy Zampell Insulation

Page 10: Upcoming Cold Projects

Confidential & Proprietary

-10-

Installing 3rd Piece (Layers 5 and 6) On the Liquid Line

Photo courtesy Zampell Insulation

Page 11: Upcoming Cold Projects

Confidential & Proprietary

-11-

Build Cryogel Up to Existing Vapor Stop Diameter At Each End

Cryogel diameter

Shoe diameter

10 inch Cryogel transition piece

Photo courtesy Zampell Insulation

Page 12: Upcoming Cold Projects

Confidential & Proprietary

-12-

Vapor Stop From Existing Cellular Glass to Cryogel

Photo courtesy Zampell Insulation

Page 13: Upcoming Cold Projects

Confidential & Proprietary

-13-

Finishing Up Liquid Line with Alumaguard

Photo courtesy Zampell Insulation

Page 14: Upcoming Cold Projects

Confidential & Proprietary

-14-

Finished Aerogel Product On LNG and Vapor Lines

Photo courtesy Zampell Insulation

Page 15: Upcoming Cold Projects

Confidential & Proprietary

IR Survey

Page 16: Upcoming Cold Projects

Confidential & Proprietary

-16-

Predictions Match Observed Behavior for All Four Systems*

* Note that the IR camera used for this study (an Infracam SD from FLIR) does not compensate well for low-emissivity surfaces like Alumaguard. Therefore, although the relative temperature differences between observed surfaces are correct (particularly for surfaces imaged in the same frame), the absolute value of the temperature readings may not be accurate.

Freezingobserved Condensation

observed

Page 17: Upcoming Cold Projects

Confidential & Proprietary

-17-

The Cryogel-Insulated Piping Performed As Designed

24” LNGline

HDfoamglas

shoes

12” vaporline

Concretepad

Shows extent of Cryogel insulated sections

Bare pipe

Page 18: Upcoming Cold Projects

Confidential & Proprietary

-18-

70 mm Cryogel Matches Performance of 150 mm Cellular Glass

150 mm (6”) cellular glass70 mm (2.75”) Cryogel

Page 19: Upcoming Cold Projects

Confidential & Proprietary

-19-

Foam Glass Expansion / Contraction Joints Are Cold Spots

Page 20: Upcoming Cold Projects

Confidential & Proprietary

-20-

Other Trouble Spots Relate to Old (Original?) PUF

Page 21: Upcoming Cold Projects

Confidential & Proprietary

-21-

Summary and Conclusions

• Despite some early delays re: the vapor stop specification and the most efficient cutting tools, the Cryogel system clearly offers productivity advantages

– Faster installation

– Ease-of-use in awkward or confined areas

– Elimination of expansion / contraction joints

• All the insulation systems near the dock behaved as expected, and showed no defects in either material or workmanship. These included:

– 3” HD foamglas on the pipe shoes

– 4” and 6” standard foamglas

– 2.8” (7 layers of 10 mm) Cryogel 10201-Z

• Note that the sections using 3” and 4” foamglas are clearly underinsulated

Page 22: Upcoming Cold Projects

Confidential & Proprietary

Saudi Aramco Gas Project

Page 23: Upcoming Cold Projects

Confidential & Proprietary

-23-

Uthmaniyah Gas Plant Saudi Arabia

Size: 8”

Fluid: NGL (C2+)

Temperature: -90 oF

Existing FOAMGLASS thickness: 150 mm.( Two layers of 75 mm, prefabricated pipe cover).

Cryogel Thickness: 60 mm

Cryogel install time: 15 minutes

Cryogel Advantages:

Reduction in the outside diameter of the insulated pipe thus less cladding material is used.

No fabrication required and less install time required.

Less accessories.

Page 24: Upcoming Cold Projects

Confidential & Proprietary

-24-

Saudi Aramco Trial

Page 25: Upcoming Cold Projects

Confidential & Proprietary

-25-

Saudi Aramco Trial

Page 26: Upcoming Cold Projects

Confidential & Proprietary

-26-

Saudi Aramco Trial

Page 27: Upcoming Cold Projects

Confidential & Proprietary

-27-

Saudi Aramco Trial

Page 28: Upcoming Cold Projects

Confidential & Proprietary

-28-

Here you can see the spacesaving with used ofCryogel. 2x10mm.

Here its used normalInsulation.

Foamglass 50mm.

Ormen Lange Norway Trial

Page 29: Upcoming Cold Projects

Confidential & Proprietary

-29-

Technip cryogenic PIP

• System qualified Bureau Veritas

Page 30: Upcoming Cold Projects

Thank You