+ All Categories
Home > Documents > UPDATE ON THE DEVELOPMENT, TESTING, AND … ON THE DEVELOPMENT, TESTING, AND MANUFACTURE OF HIGH...

UPDATE ON THE DEVELOPMENT, TESTING, AND … ON THE DEVELOPMENT, TESTING, AND MANUFACTURE OF HIGH...

Date post: 20-Apr-2018
Category:
Upload: vunhan
View: 217 times
Download: 3 times
Share this document with a friend
23
John Creasy Program Manager Nuclear Material Applications Y-12 National Security Complex November 6, 2012 UPDATE ON THE DEVELOPMENT, TESTING, AND MANUFACTURE OF HIGH DENSITY LEU-FOIL TARGETS FOR THE PRODUCTION OF MO-99
Transcript

John Creasy

Program Manager

Nuclear Material Applications

Y-12 National Security Complex

November 6, 2012

UPDATE ON THE DEVELOPMENT, TESTING,

AND MANUFACTURE OF HIGH DENSITY

LEU-FOIL TARGETS FOR THE PRODUCTION

OF MO-99

Overview

• Target comparison

• Target processing overview

• Project objectives

• Team participants and roles

• Test plan

• Foil fabrication

• Target analysis

• Target assembly/disassembly

• Discussion

. UAlx Dispersion vs. LEU-Foil Target

UAlx Dispersion Plate Targets

Manufactured to Materials & Test Reactor (MTR) fuel specifications and Quality Control Program requirements

Long history - more than 10,000 safely irradiated an processed

U-density of HEU targets currently in use is upwards to 1.6 gU/cc

U-density of LEU targets now used by CNEA, ANSTO, and NECSA is in the range of 2.5 – 3.0 gU/cc [ 8 - 9 gU/cc needed for HEU equivalency ]

Disassembly not utilized for process dissolution step

UAlx Dispersion vs. LEU-Foil Annular (cont)

LEU-Foil Annular Targets

Not currently manufactured to Quality Control

Program requirements (NQA-1 compliant quality

control requirements used on test targets)

Smaller history - <50 irradiated and processed to date

Not currently manufactured / “qualified” to an industry accepted standard. They are not a qualified reactor fuel type as are dispersion type targets

U-density of LEU-Foil targets is 19.0 gU/cc

Disassembly required to remove foil for process dissolution step (reduced waste stream)

LEU-Foil Target Manufacturing, Irradiation & Processing

Target Life Cycle Target Life Cycle

Component

Specifications

LEU-Foil

Incoming

Component

Inspections

Target Assembly

Irradiation Rig and

Reactor Loading

Coolant

Target Irradiation

150 – 200 h

Pool Decay

≤ 12 h

Target Transport

Target Disassembly

Target Life Cycle

LEU-Foil Target Development & Testing

Project Objectives:

Develop a target testing methodology that is bounding for all Mo-99 target irradiators

Develop target testing methodology by building upon the annular target design work and testing

previously performed by ANL and ANSTO/CERCA (circa 2004)

Expand upon ANSTO’s “safety case” document set of analyses

Establish max. target LEU-foil mass

Develop a LEU-foil target “safety case” document

Develop a bounding target failure analysis methodology (failure in reactor containment)

Optimize Safety vs. Economics

Goal is to manufacture a safe, but relatively inexpensive target to offset the inherent economic

disadvantage of using LEU in place of HEU

Develop target material specifications and manufacturing QC test criteria

LEU-Foil Target Development & Manufacturing

Y-12’s role:

Manufacturing, testing & quality control

Independent verification of analyses

Construction of flow circuit and test section Electron beam (EB) welding capability

Argonne’s role: Chemical processing of targets

Initial target design role MU/MURR role: Thermal hydraulic & structural analyses Evaluate target geometries Evaluate LEU-foil types (KAERI & Y-12)

MURR [LEU target irradiation/recoil barrier PIE]

ORNL [ foil/target irradiation / chem. processing ]

KAERI [ supply of roll cast U-foils ]

Cold Rolling Mill

Team Structure

NNSA HQ

Y-12 -Project Management

-Target Fabrication

MU -Target Analysis

-Equipment

MURR -LEU Target Irradiation

-PIE

ANL -Initial Design

-Chemistry

-Chemical Equipment

ORNL -Analysis

-Acid dissolution

- Foil irradiation

-Electro-chemical dissolution

High Level Test Plan

• Y-12, ORNL, MURR -Develop target quality control specifications to NQA-1 standards (January 2012)

• Y-12 -Manufacture targets for testing (March 2012)

• ANL -Manufacture chemical dissolution equipment (March 2012)

• MURR, Y-12 -Manufacture assembly and disassembly equipment (February 2012)

• ORNL -Install chemical dissolution equipment (April 2012)

• ORNL, MURR -Install disassembly equipment (March 2012)

• ORNL, MURR -Irradiate targets (Summer 2012)

• ORNL, MURR -Perform chemical processing and PIE of targets (Summer/Fall 2012)

• Issue target testing report document

Test Plan Key Evaluations

• Demonstrate viability of various U foil production techniques (Rolling methods, heat treatments, spin casting (KAERI)

• Demonstrate fission recoil barrier viability

• Demonstrate repeatable and high quality target fabrication techniques

• Demonstrate target disassembly device in hot cell

• Measure fission gas release from targets during disassembly

• Perform acidic dissolution process on irradiated foils

• Perform electrochemical dissolution process on irradiated foils

• Test targets to or beyond production level equivalent burnups

Test Locations

REDC at ORNL

MU Research Reactor

HFIR Test Locations

Rolling Target Foils and Grain Refinement

• Target foil thickness is not trivial to manufacture.

– < 150 m

• Sophisticated rolling schedule and heat treatment schedule necessary for large scale foil production

• 100 m foils are now possible.

• Drop quench furnace to be used for beta quench grain refinement of elongated as-rolled uranium grains.

112 µm thick foil

Electroplating

• Nickel foil is the current fission barrier for the target

• PDRD in FY’ 11 optimized the electroplating bath for coating uranium

• 15 m Ni applied

Target Structural Analyses Numeric Simulations

Analysis of annular target’s

structural integrity

Analysis to be validated by

testing in flow loop:

Model for conditions

experienced during irradiation:

thermal, fission gas pressure,

and macroscopic U-swelling

Colors represent the Von Mises stress in the target from interfacial heating.

Plate target modeled with an

interfacial heat source in between the

plates.

The edges in this model are not

constrained.

The areas with highest Von Mises

Stress occur around the edges of the

plate.

LEU-Foil Target Development & Testing

Laser Displacement

Measurement Test

Section

Electroplating of Ni Fission

Recoil Barrier to U-foil

≈ 9 μm of Ni on Stainless Steel, 1000x

Thermocouple Wires

Heater Power ≈ 5 kW (max. attainable)

Ni-Cr Heater Element

Actual Target

Power > 25 kW

During Irradiation

Validation of Numeric Simulations

Laser Displacement Measurement

Laser Head

Heated

Target

University of

Missouri

SEM images of center cut of surrogate target

SEM Imagining of Annular Target Surrogate

University of

Missouri

Annular Surrogate Target Design

Annular surrogate target with three

thermocouples placed radially on external (A)

and internal (B) cladding surfaces.

ANNULAR SURROGATE TARGET IN TEST

SECTION WITH HEATER FOR EXTERNAL

HEATING CONDITION TESTING.

Annular Target Disassembly Device - Prototype

Next generation prototype will be automated for remote operation

16.25 inch

Remotely Operated Disassembly Device

MU Design Phase I

Automated Disassembly Device

MU Design Phase II

Disassembly Process Design for Hot Cell Operations

Analytical Input Data Required

In order to develop a conservatively bounding “Safety Case” document, stakeholders would need to provide reactor specific irradiation data

For example:

max. thermal neutron flux ( ≤ 3.0E14 n/cm2 -s )

max. irradiation time ( ≤ 200 h )

% 235U burn-up ( ≤ 12% )

target heat flux limit ( W/cm2 )

Containment “free” volume ( m3 )

Depth (from pool surface ) at which targets are irradiated ( ≥ 7 m, 23 ft )

Target cooling period ( ≤ 12 h )

Current transport cask shielding design: total fission product activity at time of target transport

grams (or mols) of noble gases ( Kr & Xe ) generated during target irradiation

Ideal target dimensions (i.e., size) and LEU-foil mass

Ideal LEU-foil thickness (125 m [5 mils] – 180 m [7 mils] ); specific target power ( W/gU ) increases with decreasing foil thickness ( ≈ 5% per 25 m ∆ )

Target Development and Qualification Philosophy

• LEU-Foil target is a Mo-99 production “consumable” with a limited

life cycle

• Target must maintain its structural integrity during reactor irradiation and post-irradiation pool cooling - - - Reactor safety is of first priority

• However, does a Mo-99 production target need to be designed and qualified to the same extent as reactor fuel elements considering its inherently different role?


Recommended