Technical Requirements & Regulatory Issues In Interconnection AgreementsMarch 9, 2011Jay [email protected] · 501.614.3220
3
SPP Wind
0
10000
20000
30000
40000
50000
60000
Q12007
Q22007
Q32007
Q42007
Q12008
Q22008
Q32008
Q42008
Q12009
Q22009
Q32009
Q42009
Q12010
Q22010
Q32010
MW
WIND UNDERSTUDYWIND UNDER GIA
Wind In The SPP Generation Queue
7
• Cluster Studies – Intended to study multiple requests
simultaneously and allocate costs of network upgrades that are beneficial to the group.
– All interconnection requests in each queue that are received in a 180 day open season period are studied together.
– Allows for all interconnection requests in the queue to commence study process within six months and greatly lessens the queue backlog burden
Interconnection Study Measures
8
Interconnection Study Measures
• Cluster Studies (continued)– A set of upgrades that is necessary for the
interconnection of the entire cluster of interconnection requests is determined.
– The upgrade set’s costs are shared by the entire cluster of interconnection request based on a MW usage basis of each interconnection request.
– Upgrades that are required for the interconnection of the cluster (i.e. shared upgrades) cannot be suspended.
9
Low Voltage Ride Through (LVRT)
• Governed by FERC Order #661 and #661A• Comparable requirements for wind generation
and thermal based generation.• All wind generators are required to be able stay
on line and in service for a 3 phase fault at the Point of Interconnection of normal duration and normal clearing time of the fault.
• Wind generators must be able to comply either through enhanced ride through capabilities from the equipment manufacturers; or must install a dynamic reactive compensation device to help keep the wind farm on line and in service
10
Reactive Power Requirements• Governed by FERC Order #661 and #661A• If demonstrated in the interconnection study,
wind generation plants shall be capable of providing 95% lagging (providing vars) and 95% leading (absorbing vars) power factor at the point of interconnection.
• Requires wind generation plant to account for any losses in their distribution collector system, substation transformers, and any transmission line they operate.
• The requirement applies to wind generation plant at 100% nameplate generation. Does not apply to lower values of generation.
11
SCADA Requirements
• Governed by FERC Order #661 and #661A• Wind generation plants required to have
SCADA systems• Order #661A allows for mutual agreement
between the Transmission Owner/Operator and Generation Owner/Operator to decide the requirements
12
Interconnection Study Measures
• Wind generator developers provide collector system for wind turbines
• Wind generator developers provide transformer and transmission information
• Wind generator developers provide a PSS/E dynamic model for the wind generator turbines they are proposing to install.
• Dynamic Stability Analysis performed using these models
• LVRT analysis also performed using these models.
Concluding Remarks
• Renewables are generally not dispatchable, but can be and may need to be managed. Regardless, accurate models and forecasts are critical to optimize integration and deliveries– Significant efforts underway to create and
validate appropriate models without sharing proprietary and commercially sensitive details
– FERC is proposing that renewable developers need to share real time data to improve forecasting and better manage reliability margins