+ All Categories
Home > Documents > Updated 1/28/2011. Technical Requirements & Regulatory Issues In Interconnection Agreements March 9,...

Updated 1/28/2011. Technical Requirements & Regulatory Issues In Interconnection Agreements March 9,...

Date post: 14-Dec-2015
Category:
Upload: martha-laurie
View: 215 times
Download: 0 times
Share this document with a friend
Popular Tags:
13
Updated 1/28/2011
Transcript

Updated 1/28/2011

Technical Requirements & Regulatory Issues In Interconnection AgreementsMarch 9, 2011Jay [email protected] · 501.614.3220

3

SPP Wind

0

10000

20000

30000

40000

50000

60000

Q12007

Q22007

Q32007

Q42007

Q12008

Q22008

Q32008

Q42008

Q12009

Q22009

Q32009

Q42009

Q12010

Q22010

Q32010

MW

WIND UNDERSTUDYWIND UNDER GIA

Wind In The SPP Generation Queue

4

Annual Average Wind Speed - 80 meters

4

5

Wind In Service

6

Generation Interconnection Requests

7

• Cluster Studies – Intended to study multiple requests

simultaneously and allocate costs of network upgrades that are beneficial to the group.

– All interconnection requests in each queue that are received in a 180 day open season period are studied together.

– Allows for all interconnection requests in the queue to commence study process within six months and greatly lessens the queue backlog burden

Interconnection Study Measures

8

Interconnection Study Measures

• Cluster Studies (continued)– A set of upgrades that is necessary for the

interconnection of the entire cluster of interconnection requests is determined.

– The upgrade set’s costs are shared by the entire cluster of interconnection request based on a MW usage basis of each interconnection request.

– Upgrades that are required for the interconnection of the cluster (i.e. shared upgrades) cannot be suspended.

9

Low Voltage Ride Through (LVRT)

• Governed by FERC Order #661 and #661A• Comparable requirements for wind generation

and thermal based generation.• All wind generators are required to be able stay

on line and in service for a 3 phase fault at the Point of Interconnection of normal duration and normal clearing time of the fault.

• Wind generators must be able to comply either through enhanced ride through capabilities from the equipment manufacturers; or must install a dynamic reactive compensation device to help keep the wind farm on line and in service

10

Reactive Power Requirements• Governed by FERC Order #661 and #661A• If demonstrated in the interconnection study,

wind generation plants shall be capable of providing 95% lagging (providing vars) and 95% leading (absorbing vars) power factor at the point of interconnection.

• Requires wind generation plant to account for any losses in their distribution collector system, substation transformers, and any transmission line they operate.

• The requirement applies to wind generation plant at 100% nameplate generation. Does not apply to lower values of generation.

11

SCADA Requirements

• Governed by FERC Order #661 and #661A• Wind generation plants required to have

SCADA systems• Order #661A allows for mutual agreement

between the Transmission Owner/Operator and Generation Owner/Operator to decide the requirements

12

Interconnection Study Measures

• Wind generator developers provide collector system for wind turbines

• Wind generator developers provide transformer and transmission information

• Wind generator developers provide a PSS/E dynamic model for the wind generator turbines they are proposing to install.

• Dynamic Stability Analysis performed using these models

• LVRT analysis also performed using these models.

Concluding Remarks

• Renewables are generally not dispatchable, but can be and may need to be managed. Regardless, accurate models and forecasts are critical to optimize integration and deliveries– Significant efforts underway to create and

validate appropriate models without sharing proprietary and commercially sensitive details

– FERC is proposing that renewable developers need to share real time data to improve forecasting and better manage reliability margins

13


Recommended