+ All Categories
Home > Documents > Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI...

Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI...

Date post: 14-Jul-2020
Category:
Upload: others
View: 3 times
Download: 0 times
Share this document with a friend
194
Page 1 Updated Resettlement Plan and Social Due- Diligence Report Document Stage: Updated Loan Number: 2778 (IND) September 2017 India: Gujarat Solar Power Transmission Project Prepared by Gujarat Energy Transmission Corporation Limited (GETCO) The Updated Resettlement Plan and Social Due Diligence Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area
Transcript
Page 1: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 1

Updated Resettlement Plan and Social Due- Diligence Report

Document Stage: Updated Loan Number: 2778 (IND) September 2017

India: Gujarat Solar Power Transmission Project Prepared by Gujarat Energy Transmission Corporation Limited (GETCO)

The Updated Resettlement Plan and Social Due Diligence Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area

Page 2: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 2

TABLE OF CONTENTS

Page

Abbreviations 5 Executive Summary 7 PART-A: UPDATED RESETTLEMENT PLAN 10

I INTRODUCTION AND PROJECT DESCRIPTION 11 A. Introduction

B. Background C. Change in Project Components D. Project Components

1. 400/220/66 kV substation at Charanka Solar Park 2. 220 kV Bays at Jangral Substation 3. 400/220/66 kV Substation Sankhari 4. Charanka to Jangral 220 kV Transmission Line 5.Charanka to Sankhari 400 kV Transmission Line 6. Supply of 66 kV underground cable (140 kms) for Charanka Substation 7. Transmission Lines Route and Towers Details

11 11 12 13

II SCOPE OF LAND ACQUISITION AND RESETTLEMENT A. General B. Land requirements for construction of Substations C. Impacts due to Construction of 220 k/V line D. Impacts due to Construction of 400 k/V line

20 20 21 21 22

III SOCIOECONOMIC INFORMATION AND PROFILE A. General B. Socio Economic Profile

1. Demography 2. Basic Infrastructure 3. Household Economy 4. Health

C. Impact on Gender D. Impact on Indigenous Peoples

23

IV INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION A. Consultation B. Disclosure

26 26 28

V GRIEVANCE REDRESS MECHANISMS 29 VI POLICY AND LEGAL FRAMEWORK

A. ADB’S Safeguard Policy Statement, 2009 (SPS) B. The Electricity Act, 2003 C. The Indian Telegraph Act, 1885 D. Core Involuntary Resettlement Principles E. Cut-off-Date

30

VII ENTITLEMENT, ASSISTANCE AND BENEFIT A. General B. Valuation of Losses 1. Crops 2. Trees

35

VIII RESETTLEMENT BUDGET AND FINANCIAL PLAN 37 IX INSTITUTIONAL ARRANGEMENTS

37

X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING

39

Page 3: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 3

Page PART-B: SOCIAL DUE DILIGENCE REPORT 40

I INTRODUCTION A. Need and Scope of Social Due Diligence Report B. Methodology

41

II FINDINGS OF DUE DILIGENCE STUDY A. Updating of RP and Progress of Implementation B. Payment of Compensation 1. Loss of Crops 2. Loss of Trees C. Compensation to Non-Titleholders and Informal Lease Holders 1. Non-Title Holders 2. Compensation to Informal Leaseholders, actual Users and disputed

ownership D. Assistance to Vulnerable APs E. Institutional Arrangements and Grievance Redress Mechanism F. Other Social Issues G. Perception of People and consultation Findings H. Compliance with Loan Covenants I. Compliance with Entitlement Matrix

42

III CORRECTIVE ACTION PLAN

51

LIST OF TABLES Table-1 Change in Project Components 13 Table-2 Transmission Lines Details 15 Table-3 Land Requirements for Sub Stations 21 Table-4 Impacts due to construction of 220 k/V Line 21 Table-5 Impacts due to construction of 400 k/V Line 22 Table-6 Summary Findings on Public Consultations 26 Table-7 Summary of GETCO Practice 30 Table-8 Entitlement Matrix 35 Table-9 Tentative Resettlement Cost 37

Table-10 Institutional Roles and Responsibilities for Resettlement activities 37 Table-11 Implementation Schedule 38 Table-12 Project Features and Progress of Implementation 42 Table-13 Summary Details on Payment of Compensation 43 Table-14 Compliance on Safeguards as per Loan Agreement 47 Table-15 Compliance with the Entitlement Matrix 50 Table-16 Corrective Action Plan 51

LIST OF FIGURES

Figure-1 Power Map of Gujarat 15 Figure-2 Satellite Map of the Solar Park 16 Figure-3 220 kV Charanka Jangral Transmission line (Part 1) 17 Figure-4 220 kV Charanka Jangral Transmission line (Part 2) 18 Figure-5 400 kV Charanka Sankhari Transmission Line 19 Figure-6 Grievance Redress Mechanism 29

Page 4: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 4

Page

LIST OF ANNEXURES

Annexure-1 Details on Towers For 220 kV Line 54 Annexure-2 Details on Towers For 400 kV Line 81 Annexure-3 Details on consultations 92 Annexure-4 Sample Monitoring Format 112 Annexure-5 Sample Compensation Form (C- Form) 116 Annexure-6 Details of Compensation Payment for 220kV Line 126 Annexure-7 Details of Compensation Payment for 400 kV Line 156 Annexure-8 Formation of GRC 173 Annexure-9 Photographs showing the HIV/AIDS Awareness Program 175 Annexure-10 Copy of CSR Activities for the Project 176 Annexure 11 Tree Cutting Compensation _220 KV Charanka Jangral TL (GETCO) 180 Annexure 12 Tree Cutting Compensation _400 KV Charanka Veloda TL (GETCO) 192

Page 5: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 5

ABBREVIATION

ADB – Asian Development Bank AH – Affected Household AP – Affected Person BPL – Below Poverty Line DC or D/C – Double Circuit DPR – Detailed Project Report EA – Executing Agency EHV – Extra High Voltage ESU – Environment and Social Unit FGD – Focus Group Discussion GETCO – Gujarat Energy Transmission Corporation GOG – Government of Gujarat GoI – Government of India GPCL – Gujarat Power Corporation Limited GRC – Grievance Redress Committee GRM – Grievance Redress Mechanism IA – Implementing Agency INR – Indian Rupee IP – Indigenous Peoples ha – Hectare HVDS – High-Voltage Distribution System LA – Land Acquisition PMU – Project Management Unit RFCLARRA – Right to Fair Compensation and Transparency in Land Acquisition

Rehabilitation and Resettlement Act, 2013 ROW – Right of Way RP – Resettlement Plan SPS – Safeguards Policy Statement, 2009 ST – Scheduled Tribe WHH – Women Headed Household

WEIGHTS AND MEASURES

ha (hectare) – Unit of area km (kilometer) – 1,000 meters kV – kilovolt (1,000 volts) kW – kilowatt (1,000 watts) kWh – kilowatt-hour MW – Mega Watt MU – Million Units

Page 6: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 6

NOTE TO FINAL REPORT The Final document submitted on June 2017 comprises of the following sections as attached: PART- A: UPDATED RESETTLEMENT PLAN prepared in April 2014 and revised as per comments from ADB on April 2015 and subsequently revised as per discussions & comments received from ADB on December, 2015, June 2016, December 2016 and further comments received on April, May & June 2017. Further the same is updated on September 2017. PART- B: SOCIAL DUE-DILIGENCE REPORT prepared in April 2014 and revised as per comments from ADB on April 2015 and subsequently revised as per discussions & comments received from ADB on December, 2015, June 2016, December 2016 and further comments received on April, May & June 2017. Further the same is updated on September 2017. PART- C: CORRECTIVE ACTION PLAN prepared in April 2014 and revised as per comments from ADB on April 2015 and subsequently revised as per discussions & comments received from ADB on December, 2015, June 2016, December 2016 and further comments received on April, May & June 2017. Further the same is updated on September 2017.

Page 7: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 7

EXECUTIVE SUMMARY

i. This is a combined Updated Resettlement Plan and Social Due Diligence Report which

is prepared for the Project, "Loan - 2778 (IND): Gujarat Solar Power Transmission Project". A draft Resettlement Plan (RP) was prepared in March, 2011 during the loan processing which was preliminary in nature. The design was changed post the loan processing and loan signing. Additionally, implementation was started without updating the draft RP which was supposed to be submitted to ADB for review and approval. As per, Asian Development Bank's (ADB) Safeguard Policy Statement, 2009 (SPS), the RP needs to be updated in case there is change in the design. The design change of the project's transmission lines, which deviate from the original alignment by about 80 percent, caused new and unanticipated social impacts in their new alignment. These were not covered in the safeguards documents applicable at the time of project processing and loan agreement in 2011. Therefore an updated resettlement plan (RP) is to be prepared by Gujarat Energy Transmission Corporation Limited (GETCO) which is reviewed and approved by ADB. It was noted that due to the design change in the transmission lines alignment, which now deviated from the original alignment by about 80 percent caused new and unanticipated social impacts in their new alignment. These were not covered in the safeguards documents (Resettlement Plan) applicable at the time of project processing and loan agreement in 2011. The GETCO funded portion of the 220 kV line (14.52 km) is also subject to the safeguards requirements of the ADB Safeguards Policy Statement 2009 (SPS), because it is part of the overall project, being a section which connects the Charanka grid substation with the remainder of the 220 kV line and the 220 kV Jangral substation expansion, all of which are ADB funded. Thus, an updated RP is required to be prepared by GETCO, and reviewed and approved by ADB in addition to the due diligence reports assessing the status of compliance with the applicable requirements of the RP and corrective actions, if required. The DDR also includes Corrective Action Plan (CAP) where gaps are identified and further corrective actions are suggested. Therefore, this combined report has three parts such as part-A comprises of updated resettlement plan, part-B comprises of social due diligence report and part-C comprises of corrective action plan.

ii. Transmission projects are different in nature compared to other liner projects. The exact route and tower locations are known during the detailed design and at the time of construction. At the outset, preliminary route survey is undertaken taking in to consideration three alternate routes and accordingly, the best alternative route is selected. Based on the agreed alignment, a walkover survey is conducted to prepare preliminary alignment with tentative angle points. Finally the detailed survey is done either by the executing agency or by the construction contractor where exact location of each tower is marked and the right of way is fixed. Based on the detailed survey, land ownership details are collected and notification is given to each affected land owner. Valuation of crop and trees are done based on the detailed survey and compensation for the loss of tree & crop is paid accordingly. Impacts are temporary in nature in terms of loss of crops and the impacts are related to construction activities such as foundation work, erection work and stringing work. Impacts occur in these three phases, therefore, assessment is done separately for these construction activities and cannot be assessed prior hand. Therefore, valuation and payment of compensation is done simultaneously with the construction activities. iii. Transmission projects apart from being a linear project are drawn substantially high above the ground avoiding possible encounter with sensitive areas as well as habitations. The distance of two towers (span) also plays an important role in minimizing impact on land. However, for tower foundation a very small area is excavated and which after construction is resurfaced properly resulting in temporary damages to the crop only and owner is allowed to

Page 8: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 8

continue cultivation after construction. As per the present provision in the Electricity Act, 2003 read with relevant provisions of Indian Telegraph Act, 1885, all the tree & crop damages (without acquisition of subject land) accrued to person while placing the tower and line are to be compensated. Typical construction components of a transmission projects are as follows and attempts are always made to minimize the impacts and for this reason, no household is expected to be significantly affected:

Towers foundations and footings: All towers foundations and towers footings are dug and laid, including transportation of material and land clearance, generally at the end of a crop season to avoid impacts on cultivations and need for compensation. After construction of transmission towers, farmers are allowed to continue agricultural activity below tower.

Towers erection: Because the concrete needs time to dry and settle, all towers are erected normally three weeks later, after the end of the following crop season and before the following one.

Stringing: Given the limited time needed for the stringing, the latter can be done right after the tower construction, before the following crop season.

iv. The project does not require acquisition of agricultural land. The substations (shankhari, Jangral1 and Charanka) are on government land and GETCO has purchased the land from the concerned government departments. The absence of land acquisition is owed to the application of the Indian Electricity Act and Indian Telegraph Act which provide for the right to use of agricultural land without acquisition and compensation of the standing tree & crop damage during execution. The total length of the transmission line from Charanka to Jangral 220 kV grid substation is 110.654 km in length out of which the ADB funded section is 96.134 km and the GETCO funded section is 14.52 km of length. The total length of the transmission line from Charanka to Sankhari (Valod Moti) 400 kV grid substation is 95.741 km in length. Construction of transmission lines will cause temporary loss of crops during foundation, erection and stringing activities. Loss of trees is also foreseen during the construction of transmission lines v. The work of 220kV line has been completed. The total numbers of towers are 359 of which 302 towers are ADB funded and 57 towers are GETCO funded. An assessment has been done (approximate 16 Mt. breath below the conductor is considered for entire length of 110.654 Km) to calculate the approximate area of land affected temporarily in terms of loss of crops due to the construction of line and towers. For the 220 kV line, approximate current affected area is 177.04 ha which is considrered for compensation of crop losses during foundation, erection and stringing (53.11 ha for each foundation, erection & stringing stages of work) including land temporarily affected and considered for crop compensation for other impacts such as damage near the tower area, preparing the access road, bringing the equipment etc. Total number of affected persons as per the current data is 768 in ADB funded portion and 95 in GETCO funded portion. vi. The work of 400kV line has been completed. The total numbers of towers are 266. An assessment has been done (approximate 16 Mt. breath below the conductor is considered for entire length of 95.741 Km) to calculate the approximate area of land affected temporarily in terms of loss of crops due to the construction of line and towers. For the 400 kV line, approximate current affected area is 153.18 ha which is considrered for compensation of crop

1 No additional land is required. This is extension of Bay within the existing premises.

Page 9: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 9

losses during foundation, erection and stringing (45.96 ha for each foundation, erection & stringing stages of work) including land temporarily affected and considered for crop compensation for other impacts such as damage near the tower area, preparing the access road, bringing the equipment etc. Total number of affected persons as per the current data is 619 (same person can be affected in all category of work). vii. Consultations were carried out with APs during preparation of draft RP and during updation of RP and during due diligence study. Project information will be disseminated by the project through the disclosure of updated resettlement plan. The draft RP was disclosed in March, 2011. A Resettlement information pamphlet prepared in Gujarati which will contain necessary details in summary forms such as entitlement matrix, grievance redress mechanism, consultation, implementation schedule, institutional arrangements etc was disclosed to the APs. The pamphlet will be kept in all relevant panchayats and GETCO's site offices. A Grievance Redress Mechanism (GRM) has been established and a Grievance Redress Committee (GRC) has been formed to ensure affected persons (APs) grievances are addressed to facilitate timely project implementation. However, no cases have been reported to the GRC as the APs prefer to approach to the court of law. ix. The project does not require agricultural land acquisition and therefore, there is no physical displacement. Impacts are limited to loss of crops and trees. The applicable national laws and policies are the Electricity Act 2003 and the Indian Telegraph Act of 1885. Under the Telegraph Act, land is not acquired; however losses such as crops and trees are compensated at market value as per the assessment of revenue authority. ADB's Safeguard Policy Statement, 2009 is applicable for compensation and assistance. Compensation will be paid to the APs for the loss of crops and trees as per replacement cost/ market rate. Vulnerable APs will be provided with additional allowances (3 months of minimum wage) which will be on and above the compensation.

x. The Energy and Petrochemical Department of the Government of Gujarat (GOG) will be the Executing Agency (EA) for the overall coordination. Gujarat Energy Transmission Corporation Limited (GETCO) will be the EA for the implementation of the project. GETCO will also act as the Implementing Agency (IA). GETCO has set up a Project Management Unit (PMU), and concerned staffs have been designated to deal with the implementation of social safeguards activities of the project. GETCO will be responsible for payment of compensation to the APs. GETCO has delegated the task to the contractors for carrying out detailed surveys, collection of land details, liaise with APs and other concerned departments for assessment of losses and valuation of compensation. However, GETCO is responsible for the compensation and closely monitors the implementation. xi. Payment of compensation and assistance to APs for loss of crops and trees will be completed in a phased manner before/ during start of construction work. The indicative budget is INR 372.32 million. RP implementation will be closely monitored by GETCO. Semiannual monitoring reports will be submitted by GETCO to ADB which will provide the progress of RP implementation and future plan of action. xii. The due diligence study reported some gaps and non-compliance during the implementation. The grievance redress mechanism needs to be strengthened and the GRC should be more functional. A Corrective Action Plan (CAP) is prepared during the due diligence study which highlights the gaps and provides corrective measures to be taken by GETCO.

Page 10: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 10

PART-A: UPDATED RESETTLEMENT PLAN

Page 11: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 11

I. INTRODUCTION AND PROJECT DESCRIPTION

A. Introduction 1. This section (Part-A) consists of Updated Resettlement Plan (RP). The design change of the project's transmission lines, which deviate from the original alignment by about 80 percent causes new and unanticipated social impacts in their new alignment. These are not covered in the safeguards documents applicable at the time of project processing and loan agreement in 2011. A draft RP was prepared in March, 2011 during the loan processing which was preliminary in nature due to lack of detailed and actual impact assessment. The alignment was not final because detailed surveys were not carried out. Location of tower and exact right of way (RoW) were also not known. The design was changed post the loan processing and loan signing. Additionally, implementation was started without updating the draft RP which was supposed to be submitted to ADB for review and approval. As per, Asian Development Bank's (ADB) Safeguard Policy Statement, 2009 (SPS), the RP needs to be updated in case there is change in the design. Therefore, this updated resettlement plan is prepared by Gujarat Energy Transmission Corporation Limited (GETCO) and is submitted to ADB for necessary review and approval. The category of the Project remains same for social safeguards. The project is categorized as “B” for Involuntary Resettlement (IR) and “C” for Indigenous Peoples as per the ADB’s SPS. The core principles are consistent with the standards of the original safeguards documents and loan covenants. However the updated RP covers the involuntary rsettlement impact caused by the change of the project alignment. B. Background 2. Government of Gujarat (GoG) and Gujarat Power Corporation Ltd (GPCL) are developing all necessary infrastructures for a 500 MW solar park at Charanka Village, Patan district, Gujarat, with the intention to encourage private developers to build solar generating capacity on a number of individual plots of land. The Gujarat Solar Power Transmission Project (hereafter referred to as the Project) funded by Asian Development Bank (ADB) covers the power evacuation from solar power generators associated with the solar park. 3. The Project’s outcome is the successful development and operation of a transmission link to evacuate power from the Solar Park at Charanka to the Gujarat transmission grid. The Project was envisaged in 2012 in consultation with GOI and other beneficiary constituents for the reliable evacuation of the 500 MW generated at the solar park from 400/220/66 kV substation at Charanka, via two dedicated 200 kV and 400 kV double ciruit lines to the existing 220 kV substation at Jangral and the proposed 400 kV Sankhari substation. The two transmission lines will be connected to different parts of the Grid in order to maintain adequate system reliability. 4. The Solar Park is a mix of Solar Photovoltaic (SPV) with a range of 5 MW to 25 MW, small wind power, and Concentrated Solar Power (CSP) with a range of 25 MW to 50 MW adding up-to approximate total capacity of 500 MW. The power generated from SPVs and CSPs will be evacuated at 66 kV level to the electrical pooling substation in the solar park through underground cables in order to avoid shadow of transmission towers and conductors on solar panels. In addition, as per Government of Gujarat Solar Power Policy dated 6 January 2009, transmission line from the switchyard of the solar substation to the pooling substation of GETCO shall be laid by GETCO. 5. The project is estimated to cost US$ 134 Million (without IDCs and contingencies) with the ADB share at $80 million. The erection/commissioning of all these facilities are being implemented by Gujarat Energy Transmission Corporation Limited (GETCO). GETCO, along

Page 12: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 12

with GoG, is the Executing Agency (EA) for the transmission and power evacuation component. GETCO is responsible for supervising project implementation and monitoring of project operational performance. GETCO has established a Project Management Unit (PMU) headed by a Project Director to be responsible for day-to-day implementation of the Project. A Steering Committee headed by GOG facilitates overall coordination between GETCO and GPCL, the Implementation Agency for the Charanka Solar Park, for smooth implementation of the project and review of progress and achievement of the Project. C. Change in Project Components 6. As per regulatory regime, projects commissioned beyond January 2012 would attract offtake of power at a rate lower than approved Power Purchase Agreements (PPA). This led the private developers of Charanka Solar Park to expedite their completion to avail offtake of power as per the original Power Purchase Agreements i.e. at a higher rate. This created an immediate urgency on GETCO to develop evacuation facility. As the implementation was time critical, GETCO considered it prudent to realign the transmission lines and link the solar park substation with the nearest feasible point of connection to the grid through a 14.52 km long 220 kV transmission line section constructed with its own funds. Therefore, construction of this minor part facilitated immediate evacuation of power from Charanka Solar project. Subsequently, GETCO submitted draft bidding documents for the balance/realigned 220 kV and 400 kV line to ADB with an explanation that the realigned route is shorter by 11.51 km for the 220 kV line and 9.92 km for the 400 kV lines therefore resulting significant cost savings and would lead to economic delivery of power at a cost lesser than anticipated, thereby benefitting the consumer.

7. Currently, GETCO has awarded the work for 400 kV line and the 220 kV line to EPC contractors (400 kV to M/s. Gammon India and 220 kV line to M/s L&T). The survey work for the 400 kV line is complete between AP-18 and AP-31 and the construction of foundations has been started; whereas for the 220 kV line, the tower construction is nearly complete and the stringing will start soon. The EPC contractors have been empowered by GETCO to initiate, negotiate and finalise the compensation payment for crops damaged during execution work. 8. A review mission was conducted by ADB from 10 November 2013 to 16 November 2013. The Mission reviewed the status of social safeguards implementation and monitoring and identified further actions to be taken in order to comply with ADB's requirements. It was noted by the Mission that civil works contracts were awarded and civil works were carried out at both, the GETCO funded and the ADB funded portions of the 220 kV transmission line and the 400kV transmission lines, without submission of updated RP to ADB and without the approval of ADB. It was noted that due to the design change in the transmission lines alignment, which now deviated from the original alignment by about 80 percent caused new and unanticipated social impacts in their new alignment. These were not covered in the safeguards documents (Resettlement Plan) applicable at the time of project processing and loan agreement in 2011. The GETCO funded portion of the 220 kV line (14.52 km) is also subject to the safeguards requirements of the ADB Safeguards Policy Statement 2009 (SPS), because it is part of the overall project, being a section which connects the Charanka grid substation with the remainder of the 220 kV line and the 220 kV Jangral substation expansion, all of which are ADB funded. Thus, an updated RP is required to be prepared by GETCO, and reviewed and approved by ADB in addition to the due diligence reports assessing the status of compliance with the applicable requirements of the RP and corrective actions, if required. The change in scope of Projects is described in Table-1.

Page 13: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 13

Table 1: Change in Project Components

SNo.

As per loan agreement and as per Old Scope (2011)

As per Aide Memoire dated 22 Nov 2013 and as per new

scope

As per the latest information received from GETCO (Nov

2014)

a. Creation of 109.48 km. of 400 kV double circuit transmission line to Sankhari, Patan District, Gujarat.

Realigned route of 400 kV double circuit Charanka-Sankhari Transmission line -99.62 km with OPGW and Earthwire cable

Realigned route of 400 kV double circuit Charanka-Sankhari Transmission line -95.741 km with OPGW and Earthwire cable

b.

Creation of 121.52 km of 220 kV double circuit transmission line to Jangral (ADB funded section is only 109 km of 220 kV double circuit transmission line from transmission tower numbered AP-16/0 (located around 12 km from the Solar Park) to Jangral, Patan District, Gujarat)

14.52 km long section with GETCO’s own funds from Charanka GSS to AP-13/0.

Realigned route of 220 kV double circuit transmission line - 95.48 km from AP 13/0 to Jangral gantry and OPGW.

14.52 km long section with GETCO’s own funds from Charanka GSS to AP-13/0.

Realigned route of 220 kV double circuit transmission line - 96.134 km from AP 13/0 to Jangral gantry and OPGW

c. 66kV underground cable grid of about 137 km within the Solar Park

Supply of 66 kV underground cable at Charanka Park

Supply of 66 kV underground cable at Charanka Park

d.

400/220/66 kV substation comprising of 2 nos. of 315 MVA transformers and one 125 MVAR bus reactor; 8 nos. of 100 MVA transformers at 220/66 kV voltage level; 2 nos. of feeder bays at substations at Sankhari and Jangral, Patan District, Gujarat

400/220/66 kV substations at Charanka, Sankhari, and Jangral

400/220/66 kV substations at Charanka, Sankhari, and Jangral

D. Project Components 9. The Project will consist of two transmission lines, three substations and supply of underground cabling within the solar park. Figure 1 provides the power transmission map of Gujarat and Figure 2 provides the satellite map of the Solar Park area. Figure 3, 4 and 5 provide the topographical maps (1:50,000 scale) which show the transmission line routes and the 400/220/66 kV Pooling substation at Charanka and 220 kV bay at existing 220/66 kV Jangral and 400/220/66 kV proposed Sankhari substation. 1. 400/220/66 kV substation at Charanka Solar Park

10. The electrical substation land is a government owned land and has been provided by GPCL. Therefore, acquistion of agricultural land is not required. The substation is located at

the right side adjoining to the Charanka Fangli Road about 3 km from Charanka village. The

total land area allotted for the new substation is 349,465.15 square meters (approximately 34.95 hectares), which is barren and has no vegetation. 2. 220 kV Bays at Jangral Substation

11. Bay extension will be done within the existing substation premise which does not require acquisition of land. The land for the substation bays is located within the premise of the GETCO 220 kV substation that houses a 220/66 kV receiving substation. The land area inside the substation is mainly plain and has no trees. The existing Vadavi-Kansari 220 kV transmission line also runs within the vicinity of the project site (close to the boundary of the

Page 14: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 14

proposed land). Thus, inter-connection to the proposed new 220 kV grid substation to the Vadavi-Kandari 220 kV transmission line is only a few metres and would not involve removal of green cover vegetation and avoid any adverse physical impacts to the adjoining properties. 3. 400/220/66 kV Substation Sankhari 12. The proposed land for the substation is located near Sankhari Village in Patan District about 2 km away from Valod Moti village accessible through the Valod Moti-Nayta Mota village road. Terrain of the proposed land is generally flat and barren with light shrubs and trees. The total land area is 242,632 square meters (approximately 24.26 hectares). This is a government owned land which is a waste land and has been purchased by GETCO.

4. Charanka to Jangral 220 kV Transmission Line

13. The 220 kV D/C Charanka-Jangaral line route passes through 4 different tehsils i.e Santalpur with 13 villages, Radhanpur with 27 villages, Harij with 47 villages and Patan with 6 villages. Double Circuit 220 kV Transmission line is being laid between Charanka and existing 220 kV GETCO sub-station at Jangral, with GETCO’s standard lattice type tower design. High Ampere capacity AL59 type (equal weight to ACSR Zebra type) conductor will be used for low transmission power loss and also high power transfer capability. The total length of the transmission line from Charanka to Jangral 220 kV grid substation is 110.654 km in length out of which the ADB funded section is 96.134 km and the GETCO funded section is 14.52 km of length. Total number of towers is 359 of which 302 towers are ADB funded and 57 towers are GETCO funded. The transmission line traverses through the undulating terrain and passes nearby to a number of villages in the Santalpur, Harij, Radhanpur, Sami and Patan Tehsils. The transmission line traveses through the barren land, cultivated and uncultivated lands. 5. Charanka to Sankhari 400 kV Transmission Line 14. The 400 kV double circuit (D/C) Charanka-Sankhari Line passes through 3 different tehsils viz. Santalpur with 13 villages, Radhanpur with 27 villages, Harij with 27 villages in district Patan. 400 kV double circuit transmission line will be laid between Charanka and 400 kV Sankhari sub-station, using GETCO’s standard lattice type tower design. Twin ACSR MOOSE conductors will be used for the transmission line. The total length of the transmission line from Charanka to Sankhari (Valod Moti) 400 kV grid substation is 95.741 km in length having 266 number of towers. The transmission line traveses through the barren land, cultivated and uncultivated lands.

6. Supply of 66 kV underground cable (140 kms) for Charanka Substation 15. Power generation from the Solar photovoltaic plants will be transferred to the Charanka electric pooling substation using single core 66 kV power cables. Total five routes are identified for PV power transfer. One circuit of 630 sq. mm. size cables is considered for maximum of 8 Solar Photovoltaic (SPV) plots based on power transfer capacity. Each circuit will contain 3 cables laid in Trefoil formation for 3 phases and 1 spare cable. Each Concentrated Solar Power (CSP) developer will be connected to pooling station with separate circuit and interconnection of two CSP will provide redundancy. Cable will be laid surrounded by sand and pre-cast reinforced cement concrete (RCC) slabs for protection. Pre-warning tape will be laid above buried power cable to avoid accidental contact.

Page 15: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 15

7. Transmission Lines Route and Towers Details 16. Overview of the transmission lines is provided in Table 2 below. The table also provides the status of construction of ADB funded portion.

Table 2: Transmission Lines Details SNo. Detail 220 kV Transmission Line 400 kV Transmission Line

1 Line Length 110.654 km (Total) -(ADB funded section 96.134 km, GETCO portion 14.52 km)

95.741 km

2 Total numbers of Towers Total= 359 ADB funded=302 GETCO funded= 57

266

3 Total numbers of villages line passing by

93 of Patan District 67 nos. of Patan District.

4 Start of Construction 28.03.2013 09.10.2013

5 Name of EPC Contractor L&T Limited, Chennai Gammon India Ltd., Nagpur

Figure 1: Power Map of Gujarat

Page 16: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 16

Figure2: Satellite Map of the Solar Park

Page 17: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 17

Figure 3: 220 kV Charanka Jangral Transmission line (Part 1)

Page 18: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 18

Figure 4: 220 kV Charanka Jangral Transmission line (Part 2)

Page 19: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 19

Figure 5: 400 kV Charanka Sankhari Transmission Line

Page 20: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 20

II. SCOPE OF LAND ACQUISITION AND RESETTLEMENT

A. General 17. The project does not require acquisition of land. Physical displacement will not occur. All the substations are on government land and the internal cabling is done within the solar park. Construction of transmission lines will cause temporary loss of crops during foundation, erection and stringing activities. Loss of trees is also foreseen during the construction of transmission lines. Details on each tower, type of land and ownership of land etc. for 220 kV and 400 kV lines are provided in Annexure -1 and Annexure-2 respectively. 18. Transmission projects are different in nature compared to other liner projects. The exact route and tower locations are known during the detailed design and during the time of construction. At the outset, preliminary route survey is undertaken taking in to consideration three alternate routes and accordingly, the best alternative is selected. Based on the agreed alignment, a walkover survey is conducted to prepare preliminary alignment with tentative angle points. Finally the detailed survey is done either by the executing agency or by the construction contractor where exact location of each tower is marked and the right of way is fixed. Based on the detailed survey, land ownership details are collected and notification is given to each affected land owner. Valuation of crop and trees are done based on the detailed survey and compensation is paid accordingly. Impacts are temporary in nature in terms of loss of crops and the impacts are related to construction activities such as foundation work, erection work and stringing work. Impacts occur in these three phases, therefore, assessment is done separately for these construction activities and cannot be assessed prior hand. Therefore, valuation and payment of compensation is done simultaneously with the construction activities. 19. Transmission projects apart from being a linear project are drawn substantially high above the ground avoiding possible encounter with sensitive areas as well as habitations. The distance of two towers (span) also plays an important role in minimizing impact on land. However, for tower foundation a very small area is excavated and which after construction is resurfaced properly resulting in temporary damages to the land only and owner is allowed to continue cultivation after construction. As per the present provision in the Electricity Act, 2003 read with relevant provisions of Indian Telegraph Act, 1885 all the damages (without acquisition of subject land) accrued to person while placing the tower and line are to be compensated. Typical construction components of a transmission projects are as follows and attempts are always made to minimize the impacts and for this reason, no household is expected to be significantly affected:

Towers foundations and footings: All towers foundations and towers footings are dug and laid, including transportation of material and land clearance, generally at the end of a crop season to avoid impacts on cultivations and need for compensation. After construction of transmission towers, farmers are allowed to continue agricultural activity below tower.

Towers erection: Because the concrete needs time to dry and settle, all towers are erected normally three weeks later, after the end of the following crop season and before the following one.

Stringing: Given the limited time needed for the stringing, the latter can be done right after the tower construction, before the following crop season.

Page 21: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 21

B. Land requirements for construction of Substations 20. As stated above, all the new substations are being constructed on government land. Total area of the charanka s/s is 34.95 hectares and the total area for Shankhari s/s is 24.26 hectares. Extension of bay at Jangral s/s does not require any additional land. Land details of each substation are given in Table 3.

Table 3: Land Requirements for Sub Stations

Sr. No

Name of the Sub Station

Area of the substation

(square meter (hectare)

Type of Government

Land

Cost of the Land/Amount

Paid (INR/Million INR)

Date of Allotments

1 Charanka Substation

349,465.15 (34.95 ha)

Allotted by GPCL 155,768,634.60 (155.77 million)

07-May-2011

2 Shankhari Substation

2,42,632 (24.26 ha)

Govt. Waste Land

85,557,227.00 (85.56 million)

04-Nov-2011

3 220 kV Bays at

Jangral Substation

Not Applicable (within existing

premise) Not Applicable Not Applicable Not Applicable

Source: GETCO, Nov-2014

C. Impacts due to Construction of 220 k/V line

Total length of the line under ADB funding is 96.134 kilometres. Final survey has been

completed. The GETCO funded transmission line have total of 57 Nos. of towers and ADB

funded transmission line have 302 Nos. of towers. Impacts, in terms of loss of crops, occur

during various phases of construction such as foundation, erection and stringing. Compensation

is paid for loss of crops during each phase of the construction. The estimated affected area

considered (Approximate 16 Mt breath below the conductor is considered for entire length of

110.654 Km) for loss of crop compensation during foundation, erection and stringing including

land temporarily affected & considered for crop compensation for other impacts such as

damage near the tower area, preparing the access road, bringing the equipment etc is 531,139

sqmt (53.11 ha) at each stage No such case of non title holders AP has been identified so far.

Vulnerable APs for the 220 KV line are compensated as per entitlement matrix. Details on

estimated impacts are given in Table 4.

Table 4: Impacts due to construction of 220 KV Line

Sr. No

Particulars Unit

Quantity (Actual

till March, 2017)

Pending Work (%)

Estimated Quantity for

Pending Work

Total Quantity

1 Length of the Line kms ADB = 96.134, GETCO=14.52, Total= 110.654

2 Total number of Towers Numbers ADB= 302, GETCO= 57 and Total= 359

3

Approximate land temporarily affected & considered for loss of crop and compensation for other impacts (access, bringing equipment, etc)

Square meter

(hectare)

1,770,464 sqmt. (177.04 ha) (Approximate 16 Mt breath below the conductor is considered for entire length of 110.654 Km.)

4

Temporary affected land considered for compensation for loss of crop (Foundation) (Considered approximate 30 %)

Square meter

(hectare)

531,139 sqmt.

(53.11 ha) Nil Nil

531,139 sqmt.

(53.11 ha)

5 Temporary affected land considered for compensation for loss of crop (Erection) (Considered approximate 30 %)

Square meter

(hectare)

531,139 sqmt.

(53.11 ha)) Nil Nil

531,139 sqmt.

(53.11 ha))

Page 22: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 22

6 Temporary affected land considered for compensation for loss of crop (Stringing) (Considered approximate 30 %)

Square meter

(hectare)

531,139 sqmt.

(53.11 ha) Nil Nil

531,139 sqmt.

(53.11 ha)

7

Land temporarily affected and considered for crop compensation for other impacts (access, bringing equipment, etc) (Considered approximate 10 %)

Square meter

(hectare)

177,046 sqmt

(17.70 ha) Nil Nil

177,046 sqmt

(17.70 ha)

8 Total Area temporarily affected for crop compensation (foundation + erection +

stringing + other impacts) ha 177.04 Nil Nil 177.04

9 Number of affected persons (ADB funded)

Numbers 768 Nil Nil 768

10 Number of affected persons (GETCO funded)

Numbers 95 Nil Nil 86

Source: GETCO, March-2017

D. Impacts due to Construction of 400 k/V line 21. Total length of the line under ADB funding is 95.741 kilometres. Final survey has been completed. ADB funded transmission line have 266 Nos. of towers. Impacts, in terms of loss of crops, occur during various phases of construction such as foundation, erection and stringing. Compensation is paid for loss of crops during each phase of the construction. The estimated affected area considered (Approximate 16 Mt breath below the conductor is considered for entire length of 95.741 Km) for loss of crop compensation during foundation, erection and stringing including land temporarily affected & considered for crop compensation for other impacts such as damage near the tower area, preparing the access road, bringing the equipment etc is 459,557 Sqmt (45.96 ha) at each stage. Details on the tress are not available at the moment. Number of trees will be counted prior to commissioning of the lines following which compensation will be paid. No such case of non title holders AP has been identified so far. Vulnerable APs for the 400 KV line are compensated as per entitlement matrix. Details on estimated impacts are given in Table 5.

Table 5: Impacts due to construction of 400 KV Line

Sr. No

Particulars Unit

Quantity (Actual

till March, 2017)

Pending Work (%)

Estimated Quantity for

Pending Work

Total Quantity

1 Length of the Line kms 95.741

2 Total number of Towers Numbers 266

3

Approximate land temporarily affected & considered for loss of crop and compensation for other impacts (access, bringing equipment, etc)

Square meter

(hectare)

1,531,856 sqmt. (153.18 ha) (Approximate 16 Mt breath below the conductor is considered for entire length of 95.741 Km.)

4

Temporary affected land considered for compensation for loss of crop (Foundation) (Considered approximate 30 %)

Square meter

(hectare)

459,557 sqmt.

(45.96 ha) Nil Nil

459,557 sqmt.

(45.96 ha)

5 Temporary affected land considered for compensation for loss of crop (Erection) (Considered approximate 30 %)

Square meter

(hectare)

459,557 sqmt.

(45.96 ha) Nil Nil

459,557 sqmt.

(45.96 ha)

6 Temporary affected land considered for compensation for loss of crop (Stringing) (Considered approximate 30 %)

Square meter

(hectare)

459,557 sqmt.

(45.96 ha) Nil Nil

459,557 sqmt.

(45.96 ha)

Page 23: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 23

7

Land temporarily affected and considered for crop compensation for other impacts (access, bringing equipment, etc) (Considered approximate 10 %)

Square meter

(hectare)

153,186 sqmt

(15.32 ha) Nil Nil

153,186 sqmt

(15.32 ha)

8 Total Area temporarily affected for crop compensation (foundation + erection +

stringing + other impacts) ha 153.18 Nil Nil 153.18

9 Number of affected persons (ADB funded)

Numbers 619 Nil Nil 619

Source: GETCO, March-2017

III. SOCIO-ECONOMIC INFORMATION AND PROFILE A. General 22. This chapter contains the same socio-economic profile as mentioned in the previous resettlement plan. This is a general socio-economic profile of the subproject areas. A sample socio-economic survey was carried out between December 2010 to January 2011 in 18 villages and 290 households in the project area. Villages covered under the survey were Abluva, Chunsara, Churanka, Dadar, Dai Gunda, Daudpur, Gochanad, Jangural, Mehamadpura, Mota Jorapura, Nani Pipli, Navagaon, Parsun, Rajusar, Sherpura, Udargada, Vaghpura and Vandhiya. Following section describes general socio-economic profile. B. Socio-Economic Profile

1. Demography 23. The total population of Patan district is 11,82,709. The overall sex ratio is 932 female for every 1000 males (rural 938 and urban 932). About 80 % of the population live in rural areas. The total literacy rate is 60.4 %, 73.6 % among males and 46.3 % among females. About 90 % of households are Hindu and 10 % are Muslim. The average family size of sampled households is 5.37. The sex ratio of households is 849 females for every 1000 males. The overall literacy rate of surveyed households is 71 %. Literacy among males is about 79 %, while for females it is 62%. Women traditionally have lower levels of secondary and higher education. Overall, only 2 % of households have members who are graduates.

2. Basic Infrastructure 24. Availability of water is a problem for households. Although 86 % have piped water supply, 95 % of households still depend on outside sources of water. On average, it takes peoples 26 minutes to get water from outside sources. In terms of sanitation facilities, more than one-third of households have no toilet facility in their homes. Similarly, about one third of households do not have a bathroom for females. About 94 % of households use wood as cooking fuel. Other fuels used include dung cakes and kerosene though 94 % of households report to have electricity in the home.

3. Household Economy

25. Occupationally, 45 % of peoples in the age group of 18 years and above work as agricultural labourers, farmers and/or cultivators. About 57 % of women report to be home makers. Jobs in the private sector are restricted to males with more than 5 % engaged in the sector. Skilled workers and entrepreneurship/self employment in the project area is limited. Most males work in agriculture as labourers on a seasonal basis. Nearly one fourth of

Page 24: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 24

households report having a single earning member. In one third of households, there are two earning members. In 53 % of households, no female members reported contributing to the household income. Though the study tried to explore types of skills training possessed by household members, it was noted that few inherited skills of tailoring or carpentry informally, therefore, it appears people receive very little skill based training from either the government or private institutions. This is apparent for both genders. 26. In surveyed households, a little more than one fifth (22 %) reported of possessing agricultural land. In the project area, wheat and bajra are the main crops followed by cotton and Jira (Cumin seeds). Among households, of those that have agricultural land, 65 % cultivate Bajra and 33 % cultivate wheat. Cotton and Jira are cultivated by 13 % of households and Jawar by 11 %. About two-thirds of households report having live stock at their respective homes. The most frequently owned durable goods are television sets, electric fans and telephones/mobiles (70 % or more households). Similar is the case for ownership of radio - 46 % of the total sampled household reported of having a radio. Luxury items like air conditioners are not owned by households covered under the study. Similarly, four wheelers like cars/jeeps, washing machines, refrigerators and sewing machines are owned by few households. In the surveyed project area it was found that the major earning was from labour (daily wages and seasonal) followed by agriculture as farmers. Only 8 % of the households reported earnings from job and services and dairy products each. 27. The total average annual income from all sources is Rupees 50,709/-. Income from daily wage labour contributes to the maximum earnings. However, the average income from agriculture is Rupees 56,696/- highest among all sources in the project area followed by income from other sectors. The average annual expenditure of households is slightly higher than their average annual income. This suggests that many households either take loans or have concealed the exact income. Among the households, nearly 39 % of expenditure is spent on food and 20 % on social functions like rituals, festivals and marriages. Expenditure on education is only 2 % as most households access government educational services. Findings suggest that the majority of households are from lower economic backgrounds and have limited access to skilled based jobs. The majority are employed as daily wage agricultural labourers which is generally seasonal.

4. Health 28. Medical coverage is equally divided between government and private sector services. The nearest health facility for two thirds of households is a primary health centre. However, 73 %, of households have a health facility available outside their respective villages. The average distance to a health centre is 11.3 kilometres. About 84 % of households travel a minimum of 8 kilometres to access health services. Most households reported having visited a health worker during the last six months preceding the survey. The majority, about 87 %, receive messages and services on polio immunization which is a universal health programme run by the state government and the United Nation's World Health Organization. Family planning services are also available though coverage is not widespread. Many households receive health information on malaria, dengue, maternity and child health and HIV/AIDS.

C. Impact on Gender

29. Though most women classified themselves as home workers, nearly half of all women surveyed work as agricultural labourers and 39 % are engaged in cultivation. About 14 % of women also work as daily wage labourers. In the project area, women’s participation in household decision making is high. More than 90 % of households report that women participate in decisions like finance, education and child health care, purchase of assets and

Page 25: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 25

day to day activities. The perception of women and children’s safety and mobility is positive in the project area. However the provision of adequate street lights is inadequate in the project area. About 95 % of households admitted that that the provision of street lighting will result in an increase of women’s mobility during the evening. 30. Women will not be affected negatively due to the project. Any negative impacts of a sub-project on female-headed families will be taken up on a case-to-case basis and assistance to these families will be treated on a priority basis. During disbursement of compensation and provision of assistance, priority will be given to female-headed families if found. Additionally, women headed families are considered as vulnerable and provision for additional assistance has been made in the entitlement of the RP as well as in the RF. Provision for equal wage and health safety facilities during the construction will be ensured by the EA. Therefore, the sub project activities will not have any negative impact on women.

D. Impact on Indigenous People 31. Indigenous peoples (IP) are defined as those having a distinct social, cultural, economic, and political traditions and institutions compared with the mainstream or dominant society. ADB defines IP who have peculiar characteristics which are: (i) descent from population groups present in a given area before territories were defined; (ii) maintenance of cultural and social identities separate from dominant societies and cultures; (iii) self identification and identification by others are being part of a distinct cultural group; (iv) linguistic identity different from that of dominant society; (v) social, cultural, economic and political traditions and institutions distinct from dominant culture; (vi) economic systems oriented more toward traditional production systems rather than mainstream; and (vii) unique ties and attachments to traditional habitats and ancestral territories. In India, some of the Scheduled Tribes (STs) are considered to be the IPs who have some similarities with the definition of ADB. The Indian Constitution (Article 342) defines STs with special characteristics such as (i) primitive traits, (ii) distinctive culture, (iii) shyness with the public at large, (iv) geographical isolation, (v) social and economic backwardness. However, Constitutional protection and programs for tribal development have brought significant changes since 1947 which played a major role to bring the STs in to mainstream society. 32. The number of STs in the project area is low. According to the census of India, 2011 Gujarat has 14.75 % population as scheduled tribe. However, the project district (Patan) has less than 1% of ST population (0.99%). These groups, generally, are known to interact closely with mainstream society and hence considered to be mainstreamed as far as their language, socio-economic status and cultural practices. The STs are not considered primitive or seen to have distinct characteristics different from other groups. There will be no land acquisition for the project hence STs will not suffer from any physical displacement. Potential impact on IPs was evaluated and was found that no such impacts are foreseen on Indigenous peoples. Temporary impacts are foreseen on a minimum extent on crop damage during the construction of towers and lines which will be compensated in through cheque during the time of implementation and prior/ during to start of the construction.

Page 26: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 26

IV. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION

A. Consultations 33. Public consultation and information disclosure is an integral part of safeguard planning and implementation. Public consultations were carried out by the social survey team during processing stage through focused group discussions (FGDs) in various villages along the project site. During the updating of resettlement plan, consultations were again conducted along the route alignment during January and February 2014. Public consultations were carried out by the survey team through focused group discussion along the project site. Consultations were carried out at various villages such as Abluva, Arjansar, Bhelot, Charanka, Dabi, Devpura, Dharusan, Ganeshpura, Jarusa, Jekada, Kalodhi, Kanoshan, Kasara, Melusan, Memdabad, Odha, Rangpura, Sariyad, Savpura, Sidhwara, Tantiyna, and Vadiya. Table 6 gives a summary of findings on public consultations. Annexure 3 indicates details of public consultations conducted during the field survey along with names of the participants.

Table 6: Summary Findings on Public Consultations Issues

Discussed People’s views and perceptions GETCO's response/assurance

General Perception about

Project

Majority of the communities were aware of the proposed transmission line passing through their areas. Some communities have heard it but not sure about the details of the project components. Almost all the people were positive and supportive towards the proposed project.

GETCO and its contractors are in continuous consultation with the APs and local people during the final surveys and construction activities.

Support of local people for

proposed project

Since the project has been perceived to be great potential for the people of the area, they expressed their full support during implementation of the project. They also hoped that the new projects will contribute to provide employment to local unemployed youth. At the other end, some communities were concerned about the loss of valuable lands as agriculture is found to be the main source of livelihood. Most of the communities expressed that there should be no adverse impact due to the project on their cultivations, and safety. At the same time they expressed the willingness to support the project provided the project adequately compensates any losses in cash.

GETCO assures that all the losses will be compensated as per the current market rate and as per the resettlement plan.

Critical issue and concern by the local people for

the project

For the majority of the community, there were no critical issues regarding the project. However, some of the communities raised issues/concerns that included (a) fear of losing or causing damages to their cultivations, and livelihoods; (b) fear of affecting the cotton harvesting due to project activities (c) fear of not receiving reasonable compensation for the affected assets like agricultural land (d) perception that they will lose portion of agricultural land as the land size is very small. Therefore, they expressed all these concerned should be taken in to consideration by the engineering team while finalizing the design.

GETCO assures that people are given adequate advance notice so that they can harvest their crops. Usually, most of the construction activities are planned in such a way that construction activities are done during off-season. As per, the existing laws and regulation, GETCO will not be able to compensate for the land for towers. However, crops and trees will be compensated appropriately as per the government norms.

Criteria liked to see during project design, operation

stage and construction

Most of the community opined that the projects should avoid/minimize harm to residences, plantations, cultivations, other forms of livelihoods, religious and other places of community importance such as schools play grounds, community gathering places etc. Some of them suggested that tower should be erect on the boundary of the land and not inside or centre of the land. Necessary precautions must be taken to ensure safety of people during project construction.

GETCO has assured that there will be no physical displacement. Line routes are planned in such a way that these will avoid residential, habitat areas and other religious and community places. As far as the safety issues are concerned, GETCO follows the safety standard such as maintaining adequate ground clearance and heights of the towers and conductors.

Page 27: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 27

Issues Discussed

People’s views and perceptions GETCO's response/assurance

Employment potential in the

project

Majority of the communities felt that the project will provide employment opportunities to local people. Some of them requested that they should be involved not only in unskilled labour job but also in the supervisory work. Some unemployed youth held that they should be provided training during the construction stage. They complained that the construction work is generally handed over to contractors who would bring their own labour force from outside. They hoped that instead of hiring people from outside the local people should be given employment.

Employment is temporary in nature. Though GETCO intends to encourage local employment, however, it seems difficult to commit as the construction activities are done by the contractors. Construction of transmission line work needs special skill and hard work which is often difficult to find suitable people for the same work. Thefore, providing employment to local people seems difficult and cannot be guaranteed. However, GETCO will encourage the employment of local people where feasible.

Socio economic standing: land use, cropping

pattern

The main source of livelihood for the communities was agriculture, dairy related business and wage labour in the agricultural field. Most of the communities practised two times cropping in a year. Some families with good irrigation facilities also resorted to three times cropping. The average land holding size was between 5 to 10 bigha.

Source of drinking water

Piped water/tap supply from Narmada was found to be the main source for majority communities. The Gram Panchayat played an active role in the piped water supply to the communities. The other important source of drinking water was bore well.

Shortage of water

Majority of the families experience shortage of water during the summer season for human consumption. Water quality was an issue also as the water remained salty during the summer.

Negative impact on food grain,

availability /land use

In general, people did not see any adverse impact on food/grain availability. However, they cautioned that if electricity polls/towers are installed in the paddy fields or other cultivable land, it would reduce the cultivable area of the farmers.

People will be allowed to cultivate the land below the tower post the construction and GETCO will not object. Therefore, these impacts are temporary in nature.

Will project cause widespread

imbalance by cutting fruit and

commercial trees in the locality

People were unable to give a precise answer to this question as they did not know the exact extent to which the trees would be cut-down. The majority did not foresee such an imbalance. However, they cautioned that if the project cuts down valuable commercial trees e.g. fruit trees, timber trees in significant numbers it would drastically affect the livelihoods and incomes of families who are dependent on those trees.

GETCO has the provision for compensating all the trees which will be cut. A detailed assessment will be done through appropriate tree counting to assess the quantity and type of trees. These activities will be done after the stringing work and prior to commissioning of the line.

Will project cause health and safety

issues

Very few communities expressed their fears of increasing risks to their lives from lightening when they have to live closer to electricity lines and towers. Some others believed that living closer to electricity lines can harm the health condition. But the majority did not foresee any health or safety issues. Installing towers in the middle of settlements would raise safety issues particularly for children and communities suggested that such towers should be fenced around.

GETCO will follow all the heath safety measures while constructing the lines.

Health status

In majority of the villages there is lack of public health facilities such as sub-centre and primary health centre. The Community Health Centres and district hospitals are not so much equipped for the treatment of chronic and more problematic diseases. However, private medical centres were available in some areas.

Page 28: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 28

Issues Discussed

People’s views and perceptions GETCO's response/assurance

Will project setting change migration pattern of animals

None of the communities were conscious of the presence of any migrant birds or animals in their localities and therefore did not foresee any impacts on such animals, birds or their habitats.

Migration pattern

Outward migration was reported in majority of the villages. Most of the young generation especially the boys have migrated to places such as Mehsana, Palanpur, Surat for Agriculture Labor; Kathiawad for construction work; and Patan, Surat, Ahmadabad for other work.

Type of compensation

expected

Adequate cash compensation was expected for any losses to their houses, properties, cultivations and livelihoods. Some communities asked for replacement of land and [if lands and houses were acquired] within the same geographical area in addition to cash compensation. When compensating for loss of cultivations and trees, they requested that prospective income losses from such cultivations and trees should be considered. Some families did not have any legitimate rights (legal entitlement certificate for land) for the land they lived and cultivated. But they should be compensated properly.

GETCO has assured that there will be no impact to houses and buildings. All the losses related to crops and trees will be compensated as the resettlement plan and its entitlement matrix.

Perceived benefits from

project

Most communities were of the view that the proposed projects would benefit the country as a whole but they would not accrue much direct benefits to their individual communities. They thought that projects would contribute to minimize the prevailing energy crisis, load shedding in the country; increase the rate of rural electrification and provide energy for the industrial sector. At micro level, they hoped that projects would provide electricity to non-electrified households in their communities and offer labour work during project construction.

Perceived loss It is temporary in nature due to loss of crops and trees and can be compensated by GETCO.

GETCO will ensure full compensation for each loss of crops and trees as per the provision.

34. Power transmission projects are linear project, every location is different from each other and posses different & unique challenges. In power transmission projects, consultation is required for each & every location, which GETCO has done before execution of work.

B. Disclosure

35. The draft Resettlement Plan was disclosed on ADB's website in March 2011. The same was also disclosed in GETCO's website. This report (updated resettlement plan and social due diligence report) will also be disclosed in the similar fashion. A Resettlement information pamphlet will be prepared in Gujarati which will contain necessary details in summary forms such as entitlement matrix, grievance redress mechanism, consultation, implementation schedule, institutional arrangements etc and will be disclosed to the APs. The pamphlet will be kept in all relevant panchayats and GETCO's site offices. The consultation process will be continued as necessary. The following public consultation measures are envisaged for the project:

GETCO will disclose the construction schedule before the commencement of construction works to ensure that local villages are notified and informed of said activities.

Page 29: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 29

GETCO will inform the communities about progress made in the implementation of social safeguards activities

GETCO will inform the APs on compensation and assistance to be paid for the temporary loss of crops and trees.

All monitoring reports will be disclosed. Attempts will be made to ensure that vulnerable groups understand the process and

that their specific needs are taken into account.

V. GRIEVANCE REDRESS MECHANISM 36. The Grievance Redress Committee (GRC) consisting of the head of Panchayat, project engineer (line in field), nominated district revenue officer as nodal officer and the designated official of GETCO dealing with safeguards has been established. The GRC will meet as and when grievances arise. The main responsibilities of the GRC are to: (i) provide support to APs on problems arising from land/property acquisition if any; (ii) record AP grievances and action them within 4 weeks. The procedure for grievance redress will be done through various steps such as (i) Minor grievances will be redressed at the site level through the concerned project engineer and contractor (15 working days), (ii) if this fails, the grievance will be referred to the GRC which will take all necessary actions within 30 working days. However, APs can submit their grievances and complaints to a court of law at any time and independently of the grievance redress mechanism. Records will be kept of all grievances received including: contact details of complainant, date the complaint was received, nature of grievance, agreed corrective actions and the date these were effected, and final outcome. The GRCs will continue to function during the life of the Project including the defects liability period. The flow chart showing Grievance Redress Mechanism is presented in Figure 6.

Figure 6: Grievance Redress Mechanism

37. GETCO has a standard practice to deal with grievances which is as follows. Summary details are described in Table 7.

1. Assurance to APs of GETCO’s practice for providing proper and adequate compensation to the affected person/community.

2. An established GETCO procedure for estimation - which involves assessment by Mamlatdar (a revenue official) of that area and Panchayat of that village.

3. GETCO shall make the payment of compensation as per the assessment of Government revenue authority and hence does not expect any complaint in this regard. However, in the event of any complain, the following procedure will be adopted: a. Minor Grievance, if arises, will be addressed by GETCO site engineer. b. In case of protest from local villagers for planting a tower in owner’s land – GETCO

Grievance Not Addressed (Major Grievances)

Aggrieved Party

(Affected Persons)

Grievance

Redressed

Grievance Redress Committee (GRC)

Grievance

Redressed

GETCO

(Filed Level Staff)

Within 15 working days

Within 30 working days

Page 30: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 30

shall take up the clearance of District Collector citing power vested with transmission licensee as per Electricity Act 2003.

c. In case of objection from the local villagers for crop and tree compensation, Grievance Redressal Committee consisting of following members shall resolve the dispute amicably:

Project Engineer (Line) in the field.

Panchayat Head.

Nominated District Revenue officer (Nodal officer for the company). 4. In case of any other complain other than above, shall also be addressed by the

Grievance Redressal Committee. Summary details are described in Table 7.

Table 7: Summary of GETCO Practice SNo. Grievance Issues Mitigation

1 Crop and tree compensation Paid as per assessment of Revenue Authority 2 Land Acquisition No land acquisition is required for transmission line. 3 Transmission line Proper compensation while construction of line. 4 Sub-station land Substation is located in the Govt. wasteland, where

there are no habitats. Consent from villagers is obtained by collector for wasteland.

VI. POLICY AND LEGAL FRAMEWORK

38. A different policy and regulatory framework applies to: a) the substation projects, than b) the transmission lines. In the case of substations, the project envisages permanent land acquisition which generates long term impacts on affected families. Applicable laws and policies for the land acquisition will be the national laws/Act, Right to Fair Compensation and Transparency in Land Acquisition Rehabilitation and Resettlement Act, 2013 (RFCTLARRA). However, this project does not require land acquisition. The RFCTLARRA, 2013 exempts cases under the Electricity and Telegraph Act. Impacts generated during the construction of the transmission lines are temporary in nature, thus the applicable laws or policies will ensure addressing the impacts accordingly. The applicable national laws and policies are the Electricity Act 2003 and the Indian Telegraph Act of 1885. Under the Telegraph Act, land is not acquired; however losses such as crops and trees are compensated at replacement cost. ADB's Safeguard Policy Statement, 2009 is applicable for compensation and assistance. Entitlements, compensation and assistance packages are designed in accordance with the national laws, in addition to ADB‘s SPS 2009.

A. ADB’S Safeguard Policy Statement, 2009 (SPS) 39. ADB has adopted Safeguard Policy Statement (SPS) in 2009 including safeguard requirements for environment, involuntary resettlement and indigenous people. The objectives of the Involuntary Resettlement Safeguard policy is to avoid involuntary resettlement wherever possible; to minimize involuntary resettlement by exploring project and design alternatives; to enhance, or at least restore, the livelihoods of all displaced persons in real terms relative to pre-project levels; and to improve the standards of living of the displaced poor and other vulnerable groups. 40. The involuntary resettlement safeguards covers physical displacement (relocation, loss of residential land, or loss of shelter) and economic displacement (loss of land, assets, access to assets, income sources, or means of livelihoods) as a result of (i) involuntary acquisition of land, or (ii) involuntary restrictions on land use or on access to legally designated parks and protected areas. It covers them whether such losses and involuntary restrictions are full or

Page 31: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 31

partial, permanent or temporary. The main policy principles of the Involuntary Resettlement Safeguard are:

(i) Screen the project early on to identify past, present, and future involuntary resettlement impacts and risks. Determine the scope of resettlement planning through a survey and/or census of displaced persons, including a gender analysis, specifically related to resettlement impacts and risks.

(ii) Carry out meaningful consultations with affected persons, host communities, and concerned non-government organizations. Inform all displaced persons of their entitlements and resettlement options. Ensure their participation in planning, implementation, and monitoring and evaluation of resettlement programs. Pay particular attention to the needs of vulnerable groups, especially those below the poverty line, the landless, the elderly, women and children, and Indigenous Peoples, and those without legal title to land, and ensure their participation in consultations. Establish a grievance redress mechanism to receive and facilitate resolution of the affected persons’ concerns. Support the social and cultural institutions of displaced persons and their host population. Where involuntary resettlement impacts and risks are highly complex and sensitive, compensation and resettlement decisions should be preceded by a social preparation phase.

(iii) Improve, or at least restore, the livelihoods of all displaced persons through (i) land-based resettlement strategies when affected livelihoods are land based where possible or cash compensation at replacement value for land when the loss of land does not undermine livelihoods, (ii) prompt replacement of assets with access to assets of equal or higher value, (iii) prompt compensation at full replacement cost for assets that cannot be restored, and (iv) additional revenues and services through benefit sharing schemes where possible.

(iv) Provide physically and economically displaced persons with needed assistance, including the following: (i) if there is relocation, secured tenure to relocation land, better housing at resettlement sites with comparable access to employment and production opportunities, integration of resettled persons economically and socially into their host communities, and extension of project benefits to host communities; (ii) transitional support and development assistance, such as land development, credit facilities, training, or employment opportunities; and (iii) civic infrastructure and community services, as required.

(v) Improve the standards of living of the displaced poor and other vulnerable groups, including women, to at least national minimum standards. In rural areas provide them with legal and affordable access to land and resources, and in urban areas provide them with appropriate income sources and legal and affordable access to adequate housing.

(vi) Develop procedures in a transparent, consistent, and equitable manner if land acquisition is through negotiated settlement to ensure that those people who enter into negotiated settlements will maintain the same or better income and livelihood status.

(vii) Ensure that displaced persons without titles to land or any recognizable legal rights to land are eligible for resettlement assistance and compensation for loss of non-land assets.

(viii) Prepare a resettlement plan elaborating on displaced persons’ entitlements, the income and livelihood restoration strategy, institutional arrangements, monitoring and reporting framework, budget, and time-bound implementation schedule.

(ix) Disclose a draft resettlement plan, including documentation of the consultation process in a timely manner, before project appraisal, in an accessible place and a form and language(s) understandable to affected persons and other

Page 32: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 32

stakeholders. Disclose the final resettlement plan and its updates to affected persons and other stakeholders.

(x) Conceive and execute involuntary resettlement as part of a development project or program. Include the full costs of resettlement in the presentation of project’s costs and benefits. For a project with significant involuntary resettlement impacts, consider implementing the involuntary resettlement component of the project as a stand-alone operation.

(xi) Pay compensation and provide other resettlement entitlements before physical or economic displacement. Implement the resettlement plan under close supervision throughout project implementation.

(xii) Monitor and assess resettlement outcomes, their impacts on the standards of living of displaced persons, and whether the objectives of the resettlement plan have been achieved by taking into account the baseline conditions and the results of resettlement monitoring. Disclose monitoring reports.

B. The Electricity Act, 2003 41. The Electricity Act (2003) and as amended in 2007 has also been taken into consideration. Section 67 and 68 of Part-VIII and Section 164 of part-XVII are relevant. The Electricity Act makes provision for payment of compensation for damage of standing tree & crop and refers that land will be acquired as per LAA, 1984. The Electricity Act has the provision for issuing notification to all the concerned villages and people prior to any construction activities. The Electricity Act does refer to the need of payment of compensation for acquiring the land and the land will be acquired as LAA, 1984. In section 40, sub-section (1) of clause (b) and section 41, subsection (5) of the Land Acquisition Act, 1984, the term "work" shall be deemed to include electricity supplied or to be supplied by means of the work to be constructed. The Appropriate Government may, on recommendation of the Appropriate Commission in this behalf, if it thinks fit, on the application of any person, not being a company desirous of obtaining any land for its purposes, direct that he may acquire such land under the provisions of the Land Acquisition Act, 1894 in the same manner and on the same conditions as it might be acquired if the person were a company 42. The Appropriate Government may, by order in writing, for the placing of electric lines or electrical plant for the transmission of electricity or for the purpose of telephonic or telegraphic communications necessary for the proper co-ordination of works, confer upon any public officer, licensee or any other person engaged in the business of supplying electricity under this Act, subject to such conditions and restrictions, if any, as the Appropriate Government may think fit to impose and to the provisions of the Indian Telegraph Act, 1885, any of the powers which the telegraph authority possesses under that Act with respect to the placing of telegraph authority possesses under that Act with respect to the placing of telegraph lines and posts for the purposes of a telegraph established or maintained, by the Government or to be so established or maintained. C. The Indian Telegraph Act, 1885

43. Indian Telegraph Act (1885) has also been taken in to consideration for its relevant applicability. Part-III especially section 10, 11 and 18 of the Act7 is applicable for transmission

and distribution projects. The Indian Telegraph Act does not have any provision for permanent land acquisition except for payment of compensation for construction of lines and towers as

7 Power to place Telegraph Lines and Posts

Page 33: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 33

temporary impacts. The Indian Telegraph Act, 1885 is usually followed, which does not have any provision of land acquisition for construction of transmission pillars and lines. The act exercises the power to remove any trees interrupting the transmission lines, however, subsection of section 18 of the Act provides the opportunity for compensation for cutting the trees if the tree is in existence before the telegraph line was placed. The telegraph authority may, from time to time, place and maintain a telegraphic line under, over, along or across, and post in or upon, any immovable property provided that the telegraph authority shall not exercise the powers conferred by this section except for the purpose of a telegraph established or maintained by the Central Government, or to be so established or maintained. The Central Government shall not acquire any right other than that of user only in the property under, over, along, across, in or upon which the telegraph authority places any telegraph line or posts. The telegraph authority shall not exercise those powers in respect of any property vested in or under the control or management of any local authority, without the permission of that authority. The telegraph authority shall do as little damage as possible, and, when it has exercised those powers in respect of any property other than that referred to, shall pay full compensation to all persons interested for any damage sustained by them by reason of the exercise of those powers. In case of property and dispute other than that of a local authority where the power is to be exercised, the District Magistrate may, in his discretion, order that the telegraph authority shall be permitted to exercise them. 44. If any tree standing or lying near a telegraph line interrupts, or is likely to interrupt, telegraphic communication, a Magistrate of the first or second class may, on the application of the telegraph authority, cause the tree to be removed or dealt with in such other way as he deems fit. When disposing of an application under sub-section (1), the Magistrate shall, in the case of any tree in existence before the telegraph line was placed, award to the persons interested in the tree such compensation as he thinks reasonable, and the shall be final. D. Core Involuntary Resettlement Principles

45. The core involuntary resettlement principles for the Project to be followed are: (i) land acquisition, and other involuntary resettlement impacts will be avoided in the future for substations; (ii) resettlement plans (RPs) will be finalized and updated (iii) consultation with APs on compensation, disclosure of resettlement information to APs, and participation of APs in implementing sub-projects will be ensured; (iv) vulnerable groups will be provided special assistance8

; (v) payment of compensation to APs at current market value (as per assessment of revenue authority) including non-titled persons (e.g., informal dwellers/squatters) at replacement rates for temporary impacts such as tower footings and right of way ; (vi) payment of compensation and resettlement assistance prior to commencement of any construction activities in specific section of the lines; and (viii) establishment of appropriate grievance redress mechanisms and its due redress. 46. Additionally, the issues related to the Right of Way (RoW) for the transmission lines will be dealt with proper care especially for the temporary loss. For the loss of crops and trees due to construction of overhead lines, compensation payable by cheque will be provided before/ during commencement of construction works. Although, the Right of Way is reserved for future activities, i.e., repair etc by the EA, but in practice, people will be allowed to use the land only for cultivation below the lines after the construction and will not be allowed to grow bigger trees or construct any houses. The EA will provide compensation to the APs for the temporary loss of crop and loss of trees if occurred, during the time of maintenance and repair.

8 Vulnerable groups include poor household, women headed household, household headed by

physically handicapped and scheduled tribes households.

Page 34: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 34

D. Cut-off-Date

47. The cut-off-date will be declared during the final survey by the contractor for finalization of route alignment, right of way and location of tower footings. GETCO through the help of the contractor will prioritize each section of alignment for civil construction works and accordingly an advance notice will be served to affected persons. Section wise approach will be followed for declaring the cut-off-date which means cut-off-date will be declared in that section of the alignment which is ready for construction. Once the alignment is final in a particular section, GETCO through its contractor initiates the collection of land details and owners' details. GETCO through its contractor provides an advance notice (one to two weeks) to the APs regarding the nature of impact and losses. Therefore, the date of issuing notice to individual APs in the particular section will be considered as cut-off-date.

Page 35: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 35

VII. ENTITLEMENTS, COMPENSATION AND ALLOWANCES/ASSITANCES

A. General

48. The APs entitled for compensation and allowances/assistance provisions for the Project include (i) All APs losing crops and trees either covered by legal title/traditional land rights, or without legal status; (ii) Registered and un registered tenants and sharecroppers; and (iii) Owners of crops, plants, or other objects attached to the land; .Compensation eligibility is limited by a cut-off date. APs who settle in the affected areas after the cut-off date will not be eligible for compensation. The Project does not require acquisition of land and there is no physical displacement. Impacts are limited to temporary in nature which is loss of crops during the construction of transmission lines which include towers and right of way (RoW) for which adequate compensation will be provided as per the entitlement matrix. The entitlement matrix is described in Table 8.

Table 8: Entitlement Matrix

S N Type of Loss Application Definition of Entitled

Person Entitlement Details

1

Loss of Government

land

Vacant plot, Agricultural

land and homestead

land

Appropriate government departments

Payment of land value to concerned government department and departmental land transfer

Transfer of land through inter government department

Payment of land value by GETCO to the concerned government and departmental transfer of ownership.

2 Loss of trees

and crops

Standing trees and

crops

Farming households/Legal

titleholder/ tenant/leaseholder/sha

recropper/non-titled AP

Compensation at market value as per assessment of revenue authority

Notice to APs about the execution of work and to harvest standing crops

Notice to APs about execution of work

Notice to harvest standing seasonal crops

Compensation for standing crop (or share of crop for sharecroppers) at market value

Compensation for trees based on timber value at market price, and compensation for perennial crops and fruit trees at annual net product market value multiplied by remaining productive years; to be determined in consultation with the Forest Department for timber trees and the Horticulture Department for other trees/crops.

3 Impact on Vulnerable

Groups

Land temporarily required for sub-project construction

and temporary impact on

crops/trees

Affected households or individuals

irrespective of their legal status

(poor household, women headed

household, household headed by physically

handicapped and scheduled tribes

households)

Additional Assistance in addition to the compensation

Vulnerable households will be provided an additional allowance ( 3 months of minimum wage).

4 Any other loss not identified

- - Unanticipated involuntary impacts will be

documented and mitigated based on the principles of the Resettlement Plan.

5

Loss due to delay in

payment for compensation

- Affected Households

or Individuals Additional

assistance

Additional assistance at per the bank interest on the entire compensation amount for the delayed period will be paid

Page 36: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 36

S N Type of Loss Application Definition of Entitled

Person Entitlement Details

or disbursement of

compensation after the

scheduled commissioning

period

by the project authority within 30 – 45 days after completion of construction works in the affected area subject to submission of complete documentary proof by the APs.

B. Valuation of Losses 1. Crops 49. Location of each tower is finalized based on the final survey. Once the location of each tower is final, GETCO through its contractors, collect the revenue paper (7/12 form). The '7/12 form' is a revenue paper which shows the ownership. Assessment of crop loss is done with the help of contractor, GETCO, farmer, local revenue person (Talati/Patwari) in a specific form which is called 'C' form which is certified by revenue official (Mamletdar/Tehasildar) prior to payment of compensation. Assessment of compensation for loss of crop is based on the following parameters:

Area of the land considered for loss of crop

Type of crops which are existing during the construction (i.e., wheat/cotton, ground nut etc)

Yielding or productivity of the specific crops. This data is collected from the local Tehasil office where the list (quantity) of yielding of various crops is available for each area

The unit rate of the affected crop is collected from daily news paper which is the latest

market rate available. The market price index (mandi rate) in the news paper is the latest market which is updated on a regular basis.

Once the unit rate is collected, the actual amount of compensation for loss of crop is calculated by multiplying affected area, yielding and unit rate. (Affected area in sqmt. X yielding per sqmt.X unit rate per sqmt.)

50. All the above details are mentioned in the 'C' form. This assessment paper is signed by the GETCO official, sarpanch (local elected representative), local revenue official (Patwari) and the affected person (owner of the land). Following the approval, cheque is made in favour of the owner and the payment is usually released within 15 to 20 days. 2. Trees 51. Valuation of compensation for loss of trees is done by the horticulture department. Compensation for non-fruit trees will be based on timber value at market price. Compensation for perennial crops and fruit trees will be based on annual net product market value multiplied by remaining productive years. Enumeration of loss of trees has not yet started. This is usually done during after the stringing work and prior to the commissioning. Trees are marked for cutting during the stringing. Following stringing, trees are compensated prior to commissioning of the line. A detailed assessment on loss of trees and the valuation will be done at the later stage and the same will be incorporated during the further update of this RP.

Page 37: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 37

VIII. RESETTLEMENT BUDGET AND FINANCING PLAN

52. The resettlement budget in this report is indicative. The budget includes various items such as cost for purchase of government land, compensation for loss of crops and trees, support cost for implementaion of resettlement plan, cost for monitoring. This also includes an additional 10% as contingency. GETCO will ensue that the budget should be made avialable in advance for the timely payment of compensation. GETCO has already loaded these costs to the contractors' cost as part of their bid. The indicative budget is INR 372.32 million. This needs further update and the actual cost will be reflected durinng the final assessment. Details are given in Table 9.

Table 9: Tentative Resettlement Cost

S No Item Unit Rates (INR) Quantity Amount (INR)

A Cost for purchasing government land for substations Actual

241,325,862

B Compensation for loss of trees and standing crop (Per km) including other assistance as per entitlement matrix.

500,000 192 96,000,000

C Resettlement Support Cost Lump sum

150,000

D Cost for Monitoring Lump sum

1,000,000

Total (A+B+C+D) 338,475,862

Contingency (10% of the Compensation) 33,847,586

Grand Total (INR) 372,323,448

Grand Total (Million INR) 372.32

IX. INSTITUTIONAL ARRANGEMENTS

53. The Energy and Petrochemical Department under the Government of Gujarat (GOG) will be the Executing Agency (EA) for the overall coordination. GETCO will be the EA and the Implementing Agency (IA) for the implementation of the project. GETCO has set up a Project Management Unit (PMU), under which staff have been designated to deal with social safeguard issues at a corporate and at site level. The designated social staff along with the contractors will be responsible for the overall implementation of the RP. GETCO has delegated the duties related to final surveys and assessment of compensation to the contractors. The contractors work in close consultation and representation of GETCO's concerned officials. Details on agencies responsible for updating and implementation of RP are provided in Table 10 below.

Table 10: Institutional Roles and Responsibilities for Resettlement activities Activity Responsible Agency

Sub-project Initiation Stage

Setting up of PMU/ ADB Cell/ESD and staff GETCO/GOG

Finalization of sites for sub-projects GETCO

RP Updating Stage

Collection of land detaails and AP details GETCO/PMU//Contractor

Conducting FGDs/meetings/ GETCO/PMU/

Updating of RP GETCO/PMU//Contractor

Approval of updated RP ADB

Disclosure of updated RP GETCO/ADB

RP Implementation Stage

Fixing the compensation value GETCO/PMU through Appropriate Government Line Departments/Contractor

Payment of compensation and Assistance GETCO/Contractor

Taking possession of land GETCO/GOG

Grievance redressal GETCO/PMU//GRC/Contractor

Monitoring GETCO/PMU

Implementation of Corrective Action Plan GETCO/PMU

ADB=Asian Development Bank, AP=Affected Person, FGD=focus group discussion, GETCO= Gujarat Energy Transmission Corporation Limited GRC=Grievance Redress Committee, PMU= Project Management Unit, and RP=Resettlement Plan

Page 38: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 38

X. IMPLEMENTATION SCHEDULE

54. All land purchase (government land in this case) for sub station is done prior to the construction of substation. Payment of compensation (temporary impacts on crops) will be will be made in parallal with the civil works. All land required will be provided free of encumbrances to the contractor prior to handing over of project sites and the start of civil works. However, public consultation and monitoring will be continued in an intermittent basis as needed during the entire duration of the project. Construction of transmission lines, being liner project, often faces challenges to complete the payment of compensation for entire lines. Therefore, phase wise approach will be adopted to deal with payment of compensation to APs. GETCO through its contractors will prioritize each section of line ready for construction based on the final surveys and accordingly assessment on loss of crops and tress are done. Once, the assessment is done, GETCO through its contractors initiates the payment of compensation to APs in that particular section and the compenation is paid simultaneously along with the construction of lines. A tentative implementation schedule is given in Table 11.

Table 11: Implementation Schedule

Subproject R&R Component/Activities Month

1 2 3 4 5 6 7 8 9 10 11 12

Final Identification and surveys of towers and alignment

Community Consultation

Collection of Land Owners and social details

Preparation of updated RP

Submission of updated RP for ADB Approval

Disclosure of RP

Compensation of APs

Payment of all eligible assistance

Monitoring

Grievance Redress

Start of Civil Work

Implementaion of Corrective Action Plan

Page 39: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 39

XI. MONITORING AND REPORTING

55. Monitoring is the responsibility of GETCO through its PMU. The implementation of RP will be closely monitored. Regular monitoring activities will be carried out internally by GETCO through its PMU.GETCO is required to implement safeguard measures and relevant safeguard plans, as provided in the legal agreements, and to submit semi-annual monitoring reports on their implementation performance. GETCO will (i) monitor the progress of implementation of RP which includes the payment of compensation, assistance, number of APs, number of consultations, number of grievance etc., (ii) document and disclose monitoring results and identify necessary corrective and preventive actions in the periodic monitoring reports, (iii) follow up on these actions to ensure progress toward the desired outcomes, and (iv) submit semi-annual monitoring reports on safeguard measures as agreed with ADB.

56. GETCO monitoring will include daily planning, implementation, feedback and trouble shooting, consultations, the resolution of grievances and complaints, and the completion and submission of progress reports. GETCO will be responsible for managing and maintaining a database of project affected persons (those directly affected by the project per the entitlement matrix). Monitoring reports documenting progress on resettlement implementation will be submitted by GETCO, through its PMU to ADB, on a semi-annual basis. Additionally, ADB will monitor projects on an ongoing basis until a project completion report is issued. A sample monitoring format is given in Annexure 4.

Page 40: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 40

PART-B: SOCIAL DUE DILIGENCE REPORT

Page 41: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 41

I. INTRODUCTION A. Need and Scope of Social Due- Diligence Report 57. This section of the report deals with social due diligence. The objective of conducting due diligence was to assess the adequacy and compliance of applicable laws and procedure during the payment of compensation. The design of the transmission lines changed and the alignments were changed substantially after the loan processing. Change in design resulted in change in the impacts. Additionally, a procedural non-compliance occurred when civil works contracts were awarded and civil works were carried out at both, the GETCO funded and the ADB funded portions of the 220 kV transmission line, without preparation of the necessary safeguards documents and their approval by ADB. Thus, in addition to the updated RP, social due diligence report (DDR) assessing the status of compliance with the applicable requirements of the RP and corrective actionsis prepared by GETCO which will be reviewed and approved by ADB. 58. GETCO has awarded the work for 400 kV line and the 220 kV line to EPC contractors (400 kV to M/s. Gammon India and 220 kV line to M/s L&T). The survey work for 220 kV line is complete and the construction of foundation, erection and stringing is ongoing. Similarly, survey work for the 400 kV line is near to completion and the construction of foundations and erection has been started. The EPC contractors have been empowered by GETCO to carry out impact assesment and initiate, payment of compensation with due representation from GETCO for the loss of tress and crops. 59. As per ADB's safeguard requirement, a due diligence report is required where constructions have already been started or completed to assess whether appropriate social safeguards measures have been taken and whether compensation and assistance was paid as per the RP and ADB's Safeguard Policy Statement, 2009 (SPS-2209). Therefore, preparation of a due diligence report is required fully accounting for the implementation of all compensation measures due under the updated resettlement plan at locations where civil works were already carried out before submission of an updated RP to ADB. The DDR also includes the 14.52 km section of the 220 KV transmission line established under GETCO financing. A corrective action plan will is also prepared as part of the DDR which needs to be implemented by GETCO. The DDR covers various findings related to status of survey work, construction, payment of compensation, valuation methods, consultations, grievance redress etc. This will also assess whether the implementation carried out so far is in compliance with the basic principle of RP and SPS, 2009 as outlined in the loan covenants and entitlement matrix. The DDR covers a Corrective Action Plan (CAP) which provides corrective actions to be taken by GETCO to adress the gaps recorded during the implementation. B. Methodology

60. The DDR is based on review of available information received from the GETCO and contractor. The review of documents included detailed project report, contractors' reports and other reports prepared during loan processing. Field visits were made at various project sites by the consultant team along with GETCO's and contractors's concerned officials at sites. Consultations were also carried out with the GETCO official and contractors to collect the data on the entire process of compensation for tower and lines. Consultations with local people were also carried out to know about people’s view on the new project and compensation rate etc paid by GETCO and contractor. Following are the key methods used for preparation of the DDR:

Assessment was based on reviewing status of all tower locations under construction by GETCO’s EPC contractors.

Page 42: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 42

Interviewing representatives of the contractors engaged on the line erection and survey work, and GETCO officials.

Reviewing the process followed by GETCO and contractor regarding information sharing and dissemination;

Reviewing the process of grievance

Informal consultation with affected persons (APs) Comparing the basic entitlement matrix and conditions as set in loan covenants with the applied work practices and the policy framework of the project.

II. FINDINGS OF DUE DILIGENCE STUDY

A. Updating of RP and Progress of Implementaion

61. The RP prepared in March 2011 during the loan processing was not updated even though the scope of project has changed. Construction was started prior to submission and approval of updated RP. As a procedural requirement, any change in the design should trigger for new assessment and updating the existing document with new impacts. This was missing as observed during the due diligence work. GETCO has already awarded the contracts (i- L & T Limited, Chennai for 220 kV Lines and ii- Gammon India Ltd., Nagpur for the 400 kV line). Final surveys and the construction activities are ongoing by the contractors. GETCO through its contractors have been collecting the land details for assessment of loss of crops where final surveys are completed. However, these details are not incorporated to update the draft resettlement plan. Therefore, an updated resettlement plan is also being submitted. A brief summary about the progress of various activities is given in Table 12.

Table 12: Project Features and Progress of Implementation

Sr. No

Particulars

220 kV Lines (ADB Funded) 220 kV Lines (GETCO Funded) 400kV Lines

Actual Status

(March,14)

Status of progress

(%)

Pending Status

(%)

Actual Status

(March,14)

Status of progress

(%)

Pending Status

(%)

Actual Status

(March,14)

Status of

progress (%)

Pending Status

(%)

1 Total Length (Kilometers)

96.134

14.52

95.741

2 Total Number of Towers 302

57

266

3 Total Length for which final survey has been completed (Kilometers)

96.134 100 % 0% 14.52 100% 0% 95.741 100% 0%

4 Number of Towers for which foundation has been completed

302 100 % 0% 57 100% 0% 266 100% 0%

5 Number of Towers for which erection has been completed

302 100 % 0% 57 100% 0% 266 100% 0%

6

Length of transmission line for which stringing has been completed (kilometers)

96.134 100 % 0% 57 100% 0% 95.741 100% 0%

Source: GETCO, March, 2017

Page 43: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 43

B. Payment of Compensation

1. Loss of Crops

62. During the due diligence exercise, it was noted that compensation was paid to the APs who are being affected by of loss of crops during the construction. All the losses were assessed and compensated. GETCO has adopted an acceptable approach to determine the prices at current market value. Assessment was done at three phases of line construction such as during foundation, erection and stringing. It was also observed that losses caused by other construction activities such as carrying equipments, using the machine and tractor etc. have also been considered for compensation. The method of valuation of compensation for trees and crops is as follows: Based on the final surveys, each tower location is identified along with the right of way. Area being affected for the loss of crop is measured and ownership details are collected. The type of standing crop on the affected land is identified. Details on the yielding of various crops are listed in the Tehasil office for each area. The unit rate of the crops is based on the daily market index which is collceted from the daily news paper. The highest value is considered for the compansation. All these activities are done in close consultaion with APs, GETCO, contractor and local revenue official following which the form is signed by all concerned parties. Upon the approval of the form by the Tehasildar, the cheque is issued in the name of the owner and the disbursement of compensation is done within 2 weeks of time from the approval of compensation amount. A sample copy of the form (original and the summary translation in English) containing the procedures and compensation method is provided in Annexure- 5. 63. As the work is completed, updated total no. of affected people who have been compensated are provided in Table 13: Summary Details on Payment of Compensation. Detailed list of affected persons, compensation amount for each tower and other losses for 220 kV and 400kV lines are provided in Annexure-6 and Annexure-7 respectively.

Table 13: Summary Details on Payment of Compensation

S N Compensation for Loss of

Crops

Total Paid Remaining

Number Number % Number %

A 220 kV Line (ADB Funded)

A-1 Compensation to APs for Foundation, Erection And Stringing

768 768 100 % 0 0%

B 220 kV Line (GETCO Funded)

B-1 Compensation to APs for Foundation, Erection And Stringing

95 95 100% 0 0%

C 400 kV Line

C-1 Compensation to APs for Foundation, Erection And Stringing

822 822 100 % 0 0%

Note: 1. The figures are based on available information with GETCO upto September, 2017.

Page 44: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 44

64. Under the Electricity Act of 2003 and the Indian Telegraph Act of 1885, compensation is paid only for the loss of crops and trees in the transmission projects while land is not acquired. As per ADB's policy, all the compensation is paid at replacement cost. The impacts are considered to be temporary in nature as per Indian Laws related to transmission line, therefore compensation is paid only for loss of crops and trees whenever occur during various phases of construction. GETCO provides the compensation for loss of crops as per the latest market rate as per the assessment of revenue authority. 65. It is noted during the due diligence study that GETCO has delegated the task of assessment of losses and payment of compensation to the contractors. However, GETCO closely monitors the entire process of assessment of losses and payment of compensation through its designated official and concerned line departments to ensure that APs receive actual compensation as per their entitlements. GETCO ensured transparency in the entire process and it is found that APs receive the actual compensation as per their entitlements. 2. Loss of Trees 66. It is found that assessment on loss of trees is not done until the stringing work is completed and prior to the commissioning of line. Therefore, assessment of loss of trees and its compensation for 400 KV Line has not yet been done. Assessment of loss of trees has been done by GETCO for 220 KV Line and APs are compensated accordingly. The detail of loss of trees and compensation paid for 220 KV Line is annexed as Annexure 11. C. Compensation to Non-Titled APs and Informal Lease Holders

1. Non-tited APs 67. The due diligence study reported that GETCO has considered the title holder APs for payment of compensation. As far as the compensation to the non title holders AP with no legal ownership is concerned, such case has not been identified so far and if such case identified in future, GETCO will provide compensation as per the provision of Electricity Act 2003 and loan & project agreement. 2. Compensation to Informal Leaseholders, actual Users and disputed ownership 68. The due diligence study reported various other cases such as informal lease holders/sharecroppers, absentee owners, problem in ownership transfer in case of recent buying and selling. Approximately 15 cases have been reported where the land is being used on an informal share cropping or informal lease holding basis. There is no written evidence made or found between the owner and the user. As mentioned, the impacts are temporary in nature in terms of loss of crops. Therefore, the present user (farmer) shall also be eligible for receiving compensation. Since the real owner is different from cultivator, there are certain concern for eligibility for receiving the compensation. However, GETCO through its contractors and with the help of local representative initiated certain positive steps in this regard to make these farmers eligible for receiving the compensation. These are internal and informal arrangements. A no objection letter is made through the help of local revenue official and sarpanch where they certify the real user of the land during the assessment. In this case, the owner gives the consent that the real user shall be eligible for compensation. The cheque is made in favour of the real owner; however, the owner transfers the compensation to the real user/farmer as per their informal sharing methods. 69. There are cases reported during due diligence that land ownership is not transferred in case of the recent buying and selling of the land. The land has been sold recently; however, the ownership is not transferred in the legal revenue document. In this case, the current owner shows the documentary proof (sale/deed) and gets the endorsement from the revenue official

Page 45: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 45

and sarpanch regarding the current ownership and become eligible for receiving the compensation. D. Assitance to Vulnerable APs 70. As per the entitlement matrix, as agreed during the loan processing, vulnerable APs are entitled to receive additional assistance equivalent to 3 months of minimum wage. Vulnerable APs are female-headed households, scheduled tribe households, poor households (Below Poverty Line), and households headed by physically handicapped or disabled persons). GETCO have identified total Vulnerable APs in 220 KV D/C Charanka- Jangral Line and 400 KV D/C Charanka- Sankhari Line and accordingly compensated as per the entitlement matrix of Resettlement Plan. Data on number of vulnerable APs for the 220 KV line and 400 KV line are submitted below. Total Nos. of Vulnerable Affected People in 220 KV D/C Charanka- Jangral Line and 400 KV D/C Charanka- Sankhari Line

Sr. No.

Particulars 220 KV D/C Charanka-

Jangral Line 400 KV D/C Charanka-

Sankhari Line

Nos. of APs Nos. of APs

1 Household headed by Physically Handicapped 6 9

2 Poor Household (Under BPL Category) 68 88

3 Women headed household 19 36

4 Schedule Tribal 0 0

Total Nos. of Vulnerable Affected Persons 93 133

Socio-Economic Information and Profile of Vulnerable APs is as under:

71. Vulnerable APs are classified in 4 category i.e. Household headed by Physically Handicapped, Poor Household (Under BPL Category), Women headed household and Schedule Tribal. Vulnerable APs have provided the assistance as per entitlement matrix of this Resettlement plan. Vulnerable APs are mostly in Villages like Abluva, Aganwada, Allahabad, Anandpura, Arjansar, Bamroli, Deopura, Dhabhi, Dhanera, Jaroosha, Jekda, Karsanpura, Koida, Kolapur, Kolivada, Lodhi, Memadavad, Memnabad, Mota Jampur, Odha, Patanka, Porana, Prem Nagar, Rangpura, Sariyad, Savpura, Shergung, Sidhara, Tatiyana, Toravada, Totana, Vhilod, Vithlod, Zanzansa. Following section describes general socio-economic profile of Vulnerable APs.

72. Household Economy: Vulnerable APs are mostly farmers/ cultivators. Most Vulnerable APs work as agriculture farmer on a seasonal basis. In the project area, wheat and bajra are the main crops followed by cotton and Jira (Cumin seeds). Most of the vulnerable households, cultivate Bajra, wheat, etc. About two-thirds of vulnerable households report having live stock. Vulnerable Skilled workers are getting employment in near about town.

73. Education: Vulnerable APs are having primary & secondary education levels. Few vulnerable households have members who are graduates.

74. Basic Infrastructure: Availability of water is a problem for every household including Vulnerable APs in the project area. Although few have piped water supply, around 95 % of vulnerable households still depend on outside sources of water. Most of the vulnerable households use wood as cooking fuel. Other fuels used include dung cakes, coal, kerosene and LPG cylinder. Vulnerable households report to have electricity in the home.

75. Medical coverage is equally divided between government and private sector services. Basic medical facilities are provided through primary health centre, which are available for vulnerable households as it is for other households. In case of serious issue, nearest Government hospital or private clinics are available. Several health related Government schemes are also available to vulnerable households.

Page 46: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 46

E. Institutional Arrangements and Grievance Redress Mechanism 76. Project Management Unit (PMU) has been established to implement the Project. GETCO has designated its official to deal with safeguards implementation. GETCO has delegated the work to its contractors who are responsible for assessing the impacts and providing the compensation. GETCO closely monitors all the compensation activities along with the representation from local revenue officials and the local elected representative (Sarpanch) and the APs. 77. Grievance Redress Committee (GRC) consist of the Nominated District Revenue Officer as nodal officer, Panchayat Head, Project Engineer, GETCO (Line in Field), and the designated official in GETCO dealing with safeguards has been established. A copy of the original letter along with an English translated version containing the formation of GRC is attached in the Annexure-8. As per the official record, there is no complain/ case reported in the GRC as on date. It is observed that minor grievance is usually addressed on the spot with due consultation with the APs, GETCO and contractors which are usually not recorded. However, APs always prefer to go to court in case of major grievance and they do not approach GRC, therefore, no cases have been reported. The grievance redress mechanism needs to be more strengthened at the field level especially some pro active action from the contactor with due assistance from GETCO's field engineer. GETCO and contractor shall facilitate the APs to solve their grievance. Some measures to strengthen the GRM are proposed in the corrective action plan. As a matter of concern, most of the grievances are addressed verbally and through dialogue at ground level by the GETCO site official and contractor without keeping a record. In this context, it is required that all the grievance, may it be minor grievance, shall be noted and recorded so as to understand the nature of grievance, date of grievance, date of consultation related to grievance and the outcome of the grievance redress along with the date of settlement. Therefore, the grievance whether formal or informal shall be recorded and highlighted in the monitoring report.

F. Other Social Issues

78. The project was expected to generate employment opportunities for local communities during the construction and maintenance phase. During the due diligence, it is found that employment opportunities were generated, however, these are not necessarily meant for APs and local communities. Contractors chose to hire the labour force to be engaged. There are cases where local people have received some temporary employment, and also some of the labour force is from outside the project area. GETCO ensures that Contractor are following core labour standard. GETCO ensures that the contracts for civil works require contractors: (i) not to employ or use children for labor; (ii) to disseminate information at worksites on risks of sexually transmitted diseases and HIV/AIDS as part of health and safety measures for those employed during construction; and (iii) to follow and implement legally mandated provisions on labour (including equal pay for equal work), health, safety, sanitation, and working conditions. In this context, GETCO conducted awareness programs on HIV/AIDS for labour community in the month of July 2014. Photographs showing HIV/AIDS awareness program is provided in Annexure-9. Additionally GETCO has initiated the implementation of Gender Action Plan (GAP) through TA. GETCO has also initiated some infrastructure development under its corporate social responsibility (CSR) which includes water and sanitation work, educational facilities. In this regard, Primary school of Charanka village has been taken up for development/ renovation under GETCO's CSR Plan. A copy of GETCO's CSR activities for the Project is attached in Annexure-10.

Page 47: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 47

G. Perception of People and consultation Findings

79. Consultations were carried out at various locations (at 21 villages along the lines) during the updating of RP and during due diligence study in the month of January and February 2014 which includes APs also. Majority of the communities were aware of the proposed transmission line passing through their areas. Some communities have heard it but not sure about the details of the project components. Almost all the people were positive and supportive towards the proposed project. According to the people, there were no critical issues regarding the project. However, some of the communities raised issues/concerns that included (a) fear of losing or causing damages to their cultivations; (b) fear of affecting the cotton harvesting due to project activities (c) fear of not receiving reasonable compensation for the affected assets like agricultural land (d) perception that they will lose portion of agricultural land as the land size is very small. Therefore, they expressed all these concerned should be taken in to consideration by the engineering team while finalizing the design. These issues are being addressed suitably by GETCO and its contractors by assessing real losses and valuation of

each loss at market rate for payment of compensation and giving time in advance to harvest

any standing crops. Most of the community opined that the projects should avoid/minimize harm to residences, plantations, cultivations, other forms of livelihoods, religious and other places of community importance such as schools play grounds, community gathering places etc. Some of them suggested that tower should be erected on the boundary of the land and not inside or centre of the land. Necessary precautions must be taken to ensure safety of people during project construction. In general, people did not see any adverse impact on food/grain availability. However, they cautioned that if electricity polls/towers are installed in the paddy fields or other cultivable land, it would reduce the cultivable area of the farmers. Also, they feel that land being affected by the tower is a kind of permanent impact and GETCO should acquire them permanently instead of treating it as temporary impacts as it may restrict their usage. As a standard practice, the transmission lines are designed in such a manner that it avoids residential or commercial structures and other community or religious infrastructures. People will be allowed to cultivate the land under the tower post the construction. H. Compliance with Loan Covenants

80. Details on the compliance as per loan agreement on various parameters are given in Table 14.

Table 14: Compliance on Safeguards as per Loan Agreement Loan Agreement (Schedule 5) Status Remarks

1. Resettlement

The State and GETCO shall ensure that all land and all rights-of-way required for the Project are made available to the Works contractor in accordance with the schedule agreed under the related Works contract and all land acquisition and resettlement activities are implemented in compliance with: (a) all applicable laws and regulations of the Borrower relating to land acquisition and involuntary resettlement; (b) the Involuntary Resettlement Safeguards; and (c) all measures and requirements set forth in the RP, and any corrective or preventive actions set forth in the Safeguards Monitoring Report. Without limiting the application of the Involuntary Resettlement Safeguards or the RP, the State

Complied

GETCO has initiated the process of updating the information and accordingly, an updated RP is being prepared and being submitted to ADB for review. No land acquisition is required in this project. All the substations are being constructed on government land which is free from any use. Payments of compensation are going on simultaneously along with the construction work. Transmission lines, being a linier Project, needs phase wise approach and therefore, GETCO is making payments in phases following which construction starts in the same phase.

Page 48: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 48

Loan Agreement (Schedule 5) Status Remarks

shall ensure that no physical or economic displacement takes place in connection with the Project until: (a) compensation and other entitlements have been provided to affected people in accordance with the RP; and (b) a comprehensive income and livelihood restoration program has been established in accordance with the RP

2. Indigenous Peoples

The State and GETCO shall ensure that the Project does not impact indigenous peoples within the meaning of the Safeguard Policy Statement. If due to unforeseen circumstances, the Project impacts indigenous peoples, the State and GETCO shall take all steps necessary or desirable to ensure that the Project complies with all applicable laws and regulations of the Borrower and the State and with the Safeguard Policy Statement.

Complied No impacts on IPs are found in the Project

3. Safeguards Related Provisions in Bidding Documents and Works Contracts

GETCO shall ensure effective implementation of following activities, including as required, that all bidding documents and contracts for Works contain provisions that require contractors to:

(a) comply with the measures relevant to the contractor set forth in the RP, and any corrective or preventative actions set forth in a Safeguards Monitoring Report;

Complied Some activities part of contract award documents for EPC contractor to be satisfied besides compensation arrangement.

(b) make available a budget for all such social measures;

Complied Budget included in the contractor's scope of work

(c) provide GETCO with a written notice of any unanticipated social; environmental risks or impacts that arise during construction, implementation or operation of the Project that were not considered in the IEE, RP and the EMP

Not Complied

Procedural non-compliance occurred when civil works contracts were awarded and civil works were carried for lines while the scope of work had changed for both lines and where an updated RP was not prepared and submitted to ADB.

(d) reinstate pathways, other local infrastructure, and land to at least their pre-project condition upon the completion of construction.

Complied Part of contract award documents for EPC contractor

4. Safeguards Monitoring and Reporting

The State shall do or cause GETCO to do the following: (a) submit semi-annual Safeguards Monitoring Reports to ADB and disclose relevant information from such reports to affected persons promptly upon submission;

Complied GETCO have submited semi annual combined Environment and Social Monitoring Report (ESMR) to ADB As per revised format of this report.

5. Labour Standard

GETCO shall ensure that civil works contracts under the Project follow all applicable labor laws of the Borrower and the State and that these further include provisions to the effect that contractors: (a) carry out HIV/AIDS awareness programs for labor and disseminate information at worksites on risks of sexually transmitted diseases and HIV/AIDS as part of health and safety measures for those employed during construction; and (b) follow and implement all statutory provisions on labor (including not employing or

Complied

GETCO/Contractors conducted awareness programs on HIV/AIDS for labour community in the month of July 2014. In addition to this, GETCO has initiated the implementation of GAP through TA and its CSR activities.

Page 49: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 49

Loan Agreement (Schedule 5) Status Remarks

using children as labor, equal pay for equal work), health, safety, welfare, sanitation, and working conditions. Such contracts shall also include clauses for termination in case of any breach of the stated provisions by the contractors

6. Grievance Redress and Project Website

The State shall maintain a grievance redress committee or committees with representation from all stakeholders in the Project facilities for the purpose of addressing any grievances from affected peoples concerning resettlement, environment and any other social issues in a timely manner.

Complied

The GRC was officially formed. However, no cases have been reported. APs prefer to go to court. The GRM needs further action to make it more functional.

I. Compliance with Entitlement Matrix

81. Details on the compliance as per loan agreement on various parameters are given in Table 15.

Page 50: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 50

Table 15: Compliance with the Entitlement Matrix

Sl No

Type of Loss Application Definition of

Entitled Person Entitlement Details

Compliance/Non-

Compliance Remarks

1

Loss of Government

land

Vacant plot, Agricultural land and homestead

land

Appropriate government departments

Departmental land transfer

Transfer of land through inter government department

Payment of land value by GETCO to the concerned government and departmental transfer of ownership.

Complied

Government land for substations has adequately been allotted to GETCO after GETCO paid the amount for cost of land to concerned government departments.

2 Loss of trees

and crops Standing trees

and crops

Farming households/Legal

titleholder/ tenant/leaseholder/sharecropper/no

n-titled AP

Compensation at market value

Notice to harvest standing crops

Notice to harvest standing seasonal crops

If notice cannot be provided, compensation for standing crop (or share of crop for sharecroppers) at market value

Compensation for trees based on timber value at market price, and compensation for perennial crops and fruit trees at annual net product market value multiplied by remaining productive years; to be determined in consultation with the Forest Department for timber trees and the Horticulture Department for other trees/crops.

Complied

GETCO has considered the title holder APs for payment of compensation. As far as the compensation to the non title holders AP with no legal ownership is concerned, such case has not been identified so far and if such case identified in future GETCO will provide compensation as per the provision of Electricity Act 2003 and loan & project agreement. Also, the cutting of trees will take places before commissioning of line, hence compensation for loss of trees will be assesed and paid accordingly before commissioning of line.

3 Impact on Vulnerable

Groups

Land temporarily required for sub-

project construction and

temporary impact on

crops/trees

Affected households or

individuals irrespective of

their legal status

Additional Assistance in addition to the compensation

Vulnerable households will be provided an additional allowance (@ 3 months of minimum wage).

Complied GETCO have compensated vulnerable APs for the 220 KV line and 400 KV line as per the entitlement matrix.

4 Any other loss not identified

- - - Unanticipated involuntary impacts will be

documented and mitigated based on the principles of the Resettlement Plan.

Complied

5

Loss due to delay in

payment for compensation or disbursement of compensation

after the scheduled

commissioning period

- Affected

Households or Individuals

Additional assistance

Additional assistance at per the bank interest on the entire compensation amount for the delayed period will be paid by the project authority within 30 – 45 days after completion of construction works in the affected area subject to submission of complete documentary proof by the APs.

Complied

Payments have been made as per schedule based on the assessment and valuation done for each phase of construction activities.

Page 51: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 51

III. CORRECTIVE ACTION PLAN 82. The due diligence study reported some non compliances which needs to be addressed and corrected by GETCO through proper steps and additional actions. GETCO needs to review the DDR and shall take action to address the gaps in order to comply with ADB's requirements on social safeguards during updating and implementing the RP. A corrective action Plan has been prepared and described in Table 16. The CAP generally highlights major non compliance as observed during the due diligence study and suggests further action as corrective measures. Corrective Action Plan along with GETCO commitment is as under:

Table 16: Corrective Action Plan

No Issues/Non

Compliances Corrective Action

Responsible Agency

Time Line Commitment

1

Updation of Resettlement Plan Updating the Draft Resettlement Plan as per the latest scope of work and change in design. The draft RP was not updated prior to the start of the civil work.

The draft RP needs to be updated based on the available information collected so far as per final surveys for the 220 kV and 400kV lines.

GETCO

Immediately for the portion where construction has started and where survey has been completed.

Complied GETCO has submitted updated Resettlement Plan along with the DDR for approval of ADB.

2

Payment of Compensation for Loss of Trees

There is no data available on the number and type of trees to be affected

There is no data available on number of APs losing trees

There is no assessment done for valuation of trees and compensation is not yet paid for loss of trees

An assessment needs to be done to calculate numbers and type of trees to be affected

The concerned department (horticulture) needs to be involved in assessing the losses and the amount of compensation.

GETCO and Contractor

After completion of the stringing work and prior to commissioning.

Complied Cutting/ trimming of trees is done at the time of commissioning of line. For 220 KV line, loss of tree has been assessed and compensation has also been paid. (Annexure 11). For 400 KV line, loss of tree has been assessed and compensation has also been paid. (Annexure 12)..

3

Grievance Redress Mechanism

There is no grievance redress mechanism active in the field except the fact that GETCO has formed the GRC by issuing the letter to concerned official/departments.

No cases of grievance has been reported which seems to be unusual in such liner projects.

People do no approach the GRC rather they prefer to go the court.

GETCO through its contractors need to sensitize the APs regarding the role of the GRC

This needs further consultation with APs regarding the formation and exisnce of GRC.

GETCO shall disclose GRC related information to make the APs aware about the role of GRC in the field.

Records shall be kept in case of both formal and informal complaints.

GETCO and Contractor

Immediate

Complied GETCO has formed GRC as per the requirement of Resettlement Plan and informed APs regarding formation and role of GRC.

Page 52: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 52

No Issues/Non

Compliances Corrective Action

Responsible Agency

Time Line Commitment

4

Monitoring of Social Safeguards Issues

The current monitoring format containing the social information is not adequate.

A revised and sample monitoring format has been prepared and appended with the updated RP.

GETCO and Contractor

Immediate

Complied GETCO has submitted all the bi-annual Safeguard monitoring report as per the revised monitoring format of this report.

Page 53: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 53

ANNEXURES

Page 54: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 54

ANNEXURE 1: DETAILS ON TOWERS FOR 220 KV LINE

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

1 12/5 Sidhada Yes Govt.

2 13A/0 Sidhada Yes Agri. 1 Dharsibhai Rugnathbhai

Thakor 1800

3 13B/0 Sidhada Yes Agri. 1 Dharsibhai Rugnathbhai

Thakor 1597 2400

Yes 900

Dhrshibhai Rugnathbhai Thakor

4 13B/1

Yes Govt.

5 13B/2 Sidhada Yes Agri. 1 Babiben Karimkhan

Theba 1800 1800

6 13B/3

Yes Govt.

7 13B/4 Bamroli Yes Agri. 1 Rabari Jivanbhai

Bavabhai 1800 1800

8 13B/5 Bamroli Yes Agri. 1 Dhaniben Vaghjibhai

Malek 1575 1575

9 13B/6 Bamroli Yes Agri. 1 Thakor Masabhai

Surabhai 1800 1800

10 13B/7 Bamroli Yes Agri. 1 Ramsibhai Dharamsibhai

Thakor 1800 1800

11 13B/8 Daldi Yes Agri. 1 Lakhmanbhai Rajabhai

Rabari 1800 1800

12 13B/9 Daldi Yes Agri. 1 Jagshibhai Rajabhai

Thakor 1575 1575

13 13B/10 Dabhi Yes Agri. 1 Thakor Mevabhai

Malubhai 1800 1800 2800

14 13B/10

to 13B/11

Dabhi Yes Agri. 1

Yes 700 Thakor Rameshbhai

Mevabhai

15 13B/11 Dabhi Yes Agri. 1 Thakor Jevatbhai

Dharamsibhai 1575 1575 1800

16 13B/12 Dabhi Yes Agri. 1 Thaor Bajubhai

Lagdhirbhai 1575 1575 1800

17 13B/11

to Dabhi Yes Agri. 1

900

Thakor Kantebhai Khodabhai

Page 55: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 55

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

13B/12

18 13B/11

to 13B/12

Dabhi Yes Agri. 1

800 Thakor Khodabhai

Bavabhai

19 13B/11

to 13B/12

Dabhi Yes Agri. 1

800 Thakor Prabhu

Khodabhai

20 13B/13 Dabhi Yes Agri. 1 Momjibhai Dhulabhai

Takor 1575 1575

21 13B/13

to 13B/14

Dabhi Yes Agri. 1

400 Thakor Savdanbhai

Chothabhai

22 13B/13

to 13B/14

Dabhi Yes Agri. 1

700 Thakor Chandabhai

Rupabhai

23 13B/13

to 13B/14

Dabhi Yes Agri. 1

400 Thakor Govindbhai

Rupabhai

24 13B/14 Dabhi Yes Agri. 1 Thakor Vershibhai

Bhagvanbhai 1575 1575

25 13B/14

to 13B/15

Dabhi Yes Agri. 1

26 13B/14

to 13B/15

Dabhi Yes Govt.

Yes 400 Thakor Hanhjibhai

Valabhai

27 13B/14

to 13B/15

Dabhi Yes Agri. 1 Thakor Mansukhbhai

Laksmanbhai 1800 Yes 400

Raval Chhaganbhai Karsanbhai

28 13B/15 Dabhi Yes Govt.

29 13B/15

to 13B/16

Dabhi Yes Agri. 1

Yes 1500 Raval Sajuben

MavjiBhai

30 13B/16 Dabhi Yes Gov.

Page 56: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 56

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

31 13B/16

to 13B/17

Dabhi Yes Agri. 1

Yes 1500 Thakor Mansukhbhai

Laksmanbhai

32 13B/16

to 13B/17

Dabhi Yes Agri. 1

Yes 1500 Thakor Lavingbhai

Dajabhai

33 13B/16

to 13B/17

Dabhi Yes Agri. 1

Yes 400 Thakor Ranchhodbhai

Revabhai

34 13B/17 Dabhi Yes Agri. 1 Varjiben Amthubhai

Thakor 1575 1575 1800

35 13B/17

to 13B/18

Dabhi Yes Agri. 1

Yes 400 Jevatbhai Dharamsibhai

Thakor

36 13B/17

to 13B/18

Dabhi Yes Agri. 1

Yes 400 Rabari Valabhai

Sangrambhai

37 13B/18 Dabhi Yes Agri. 1 Jevatbhai Dharamsibhai

Thakor 1800 1800 1800

38 13B/18

to 13B/19

Dabhi Yes Agri. 1

620 Raval Bharubhai

Mavjibhai

39 13B/19 Dabhi Yes Govt.

40 13B/19 to 14/0

Dabhi Yes Agri. 1

Yes 2000 Thakor Mansukhbhai

Laksmanbhai

41 13B/19 to 14/0

Dabhi Yes Agri. 1

Yes 400 Thakor Babubhai

Rugnathbhai

42 13B/19 to 14/0

Dabhi Yes Agri. 1

Yes 400 Thakor Babubhai

Rugnathbhai

43 14/0 Dabhi Yes Agri. 1 Gadhavi hareshdan

Sagardan 1800 1800 742

44 14/0 to

14/1 Yes Govt.

Yes 450

Thakor Lavingbhai Talsibhai

45 14/1 Dabhi Yes Agri. 1 Harsanbhai Talsibhai

Thakor 1575 1575 1800

Page 57: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 57

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

46 14/1 to

14/2 Dabhi Yes Agri. 1

620

Thakor Laksmanbhai Rupabhai

47 14/1 to

14/2 Dabhi Yes Agri. 1

400

Thakor Vajibhai Talsibhai

48 14/2 Dabhi Yes Agri. 1 Maganbhai Prabhabhai

Thakor 2250 2250 1800

49 15/0

Yes Govt.

50 15/1 Korda Yes Agri. 1 HUSSAINBHAI K SIPAI 1800

51 15/2

Yes Govt.

52 15/3 Korda Yes Agri. 1 Amratbhai Ramsibhai

Thakor 1575 1575

53 15/4 Korda Yes Agri. 1 Jitabhai Pachabhai

Thakor 1575 1575

54 16/0 Jarusha Yes Agri. 1 Raval Nagjibhai

Jagshibhai 2400 2400 2800

55 16/1

Yes Govt.

56 16/2

Yes Govt.

57 16/3 Jarusha Yes Agri. 1 Prajapati Khemabhai

Mithabhai 1800 1800 1800

58 16/4 Jarusha Yes Agri. 1 Patel Devrajbhai

Dharamsibhai 1800

59 16/5 Jarusha Yes Agri. 1 Patel Virambhai Jivabhai 1800 1800

60 16/6 Jarusha Yes Agri. 2 (1)Panchanbhai Jivabhai

(2)Patel Virambhai Jivabhai

2400 1800

16/6 to

16/7 Jarusha Yes Agri. 1

Yes 400 Panchanbhai Jivabhai

38 16/7 Jarusha Yes Agri. 1 KARMABHAI K PATEL 1800

39 16/8 Jarusha Yes Agri. 1 Chaudhry Jemaben

Naranbhai 1800 1800 1800

40 16/9 Jarusha Yes Agri. 1 Sipai Sikandarbhai

Hamirbhai 1800 1800

Page 58: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 58

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

41 16/10 Jarusha Yes Agri. 1 Khokhar(Sipai)

Gajibhaibhai Ibrahimbhai 1800 1800

42 16/11 Jarusha Yes Agri. 1 Khokhar(Sipai)

Nurmahmad Husenbhai 1800 1800

43 16A/0 Jekda Yes Agri. 1 Prahladbhai M Sadhu 2400 2400

44 16A/1

Yes Govt.

45 16A/2

Yes Govt.

46 16A/3

Yes Govt.

47 16A/4

Yes Govt.

48 16A/5

Yes Govt.

49 16A/6

Yes Govt.

50 16A/7 Jekda Yes Agri. 1 Gafurbhai Mafabhai

Gamara 2400 2400

51 16A/8

Yes Govt.

52 17/0

Yes Govt.

53 17/1

Yes Govt.

54 17/2

Yes Govt.

55 17/3

Yes Govt.

56 17/4

Yes Govt.

57 17/5

Yes Govt.

58 17/6 Santhali Yes Agri. 1 Jethabhai S Patel 576 540

59 17/7 Santhali Yes Agri. 1 Haribhai L Patel 576 540

60 17/8

Yes Govt.

61 17/9 Rangpura Yes Agri. 1 BHAGWANBAHI K

RABARI 1644 1644

62 17/10 Rangpura Yes Agri. 1 NATHABHAI D THAKOR 1644 1644

Page 59: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 59

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

63 17/11 Rangpura Yes Agri. 1 VIRVANBHAI M

TAHKOR 2544 1575

64 17/12 Rangpura Yes Agri. 1 LAXMANBHAI L RABARI 1644 1644

65 17/13 Rangpura Yes Agri. 1 BHEMABHAI L RABARI 1644 1644

66 17A/0

Yes Govt.

67 17B/0

Yes Govt.

68 17B/1

Yes Govt.

69 17B/2

Yes Govt.

70 17B/3 Bhilot Yes Agri. 1 AMALBHAI R NADODA 2060 2060

71 18/0 Bhilot Yes Agri. 1 Jethiben V Rabari 1800

72 19/0 Bhilot Yes Agri. 1 Gaurishankar K Raval 2400 2400 3200

73 19/1 Bhilot Yes Agri. 1 Thakor Ramsang

Ramjibhai 1800 1800 906

74 19/2 Bhilot Yes Agri. 1 Vaghela Dilubha Bhaguji 1800

75 19/3 Bhilot Yes Agri. 1 Rupsinh H Waghela 1800 1800

76 19/4 Bhilot Yes Agri. 1 Raghubhai Ranchodbhai

Kumbhar 1800 1800

77 19/5 Bhilot Yes Agri. 1 Thakor Amthuji

Kunvarbhai 1800

78 19/6 Bhilot Yes Agri. 1 Shankarbhai

Ranchhodbhai Chaudhri 1800

79 20/0 Bhilot Yes Agri. 1 Rajabhai Dalabhai

Chaudhri 1597.4

5

20/0 to 20A/0

Bhilot Yes Agri. 1

Yes 903 Bhavanbhai R Patel

80 20A/0 Bhilot Yes Agri. 2 (1)Jethabhai Kalabhai

Chaudhri (2)Prahladbhai S Lavar

2400

555

81 20/1 Bhilot Yes Agri. 1 Raval Jivabhai Devjibhai 1800

332 Yes 1500 Raval Jivabhai

Devjibhai

Page 60: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 60

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

20/1 to

20/2 Bhilot Yes Agri. 1

Yes 280 Ranchhodbhai S Thakor

20/1 to

20/2 Bhilot Yes Agri. 1

Yes 280 Ranchhodbhai S Thakor

82 20/2 Bhilot Yes Agri. 1 Lataben Ramjibhai Joshi 1800 1800

20/2 to

20/3 Bhilot Yes Agri. 1

Yes 300 Bhavsangji K Vaghela

20/2 to

20/3 Bhilot Yes Agri. 1

Yes 4700 Vasudevbhai S Thakar

83 20/3 Bhilot Yes Agri. 1 Ramjibhai Panchabhai 1800 1800 3600

20/3 to

20/4 Bhilot Yes Agri. 1

Yes 336 Hatubhai K Waghela

20/3 to

20/4 Bhilot Yes Agri. 1

Yes 300 Bhurubha K Waghela

20/3 to

20/4 Bhilot Yes Agri. 1

Yes 720 Bhomaji L Waghela

20/3 to

20/4 Bhilot Yes Agri. 1

Yes 440 Govindbhai S Tkakor

84 20/4 Bhilot Yes Agri. 1

1800 1800 222 Yes 1500 Joshnaben Dineshbhai

Chaudhry

20/4 to

20/5 Bhilot Yes Agri. 1

Yes 2000 Kanjibhai G Patel

20/4 to

20/5 Bhilot Yes Agri. 1

Yes 900 Natubhai L Waghela

20/4 to

20/5 Bhilot Yes Agri. 1

Yes 344

Vankur Santhaben Gandabhai

85 20/5 Bhilot Yes Agri. 1 Kuberbhai Danabhai

Chaudhri 1800 1800 558

86 20/6 Memdavad Yes Agri. 1 Ganchi Daud Jamubhai 1800 1800

87 20/7 Memdavad Yes Agri. 1 Jethabhai Kholabhai 1800 1800 1650 Yes 1500 Jethabhai Kholabhai

20/7 to

20/8 Memdavad Yes Agri. 1 Parbatbhai r Chaudhry

240

20/7 to Memdavad Yes Agri. 1 Haribhai A Chaudhry

240

Page 61: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 61

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

20/8

88 20/8 Memdavad Yes Agri. 1 Kanbi Rragnathbhai

Nanjibhai 1800

89 20/9 Memdavad Yes Agri. 1 Thakkar Kanubhai

Vakuthram 1800 1800

90 20/10 Memdavad Yes Agri. 1 Ganchi Ibrahim Akkal 1800 1800 1800 Yes 600 Ganchi Ibrahim Akkal

91 20/11 Memdavad Yes Agri. 1 Harijan Okhabhai

Mohanbhai 1800 1800

92 20/12 Memdavad Yes Agri. 1 Danabhai Bhemabhai

Chaudhri 1800 1800 332

93 20/13 Memdavad Yes Agri. 1 Dungarbhai Valabhai

Chaudhri 1800 1800 558

94 20/14 Memdavad Yes Agri. 1 Bhikhabhai govindbhai

Panchal 1800 1800

95 21/0 Memdavad Yes Agri. 1 Dayabhai Govindbhai

Thakor 2400

96 22/0 Memdavad Yes Agri. 1 Shivabhai Samabhai

Rabari 1597.5

97 22/1

Yes Govt.

98 22/2 Memdavad Yes Agri. 1 Harijan Okhabhai

Mohanbhai 1800 1800

99 22/3

Yes Govt.

100 22/4

Yes Govt.

101 22/5 MEMDAVA

D Yes Agri. 1

OKHABHAI MOHANBHAI HARIJAN

1800 1800

102 22/6 Memdavad Yes Agri. 1 Patel Bhagvanbhai

Govindbhai 1800 1800

103 22/7 SERGANJ Yes Agri.

RAMABHAI MAGABHAI VANKAR ( HARIJAN)

1800 1800

104 22/8 SERGANJ Yes Agri.

GANDABHAI JASWANTBHAI KANBI

1800 1800

105 22/9 SERGANJ Yes Agri.

CHAUDHARI PRAGJIBHAI LALJIBHAI

1800 1800

Page 62: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 62

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

106 22/10

Yes Agri. 1

107 22/11 SERGANJ Yes Agri. 1 MASTANPIR DARGAH

TRUST 1800 1800

108 23/0

Govt.

23/0 to

24/0 SERGANJ Yes Agri. 1

Yes 110

Dhudabhai Amthabhai Patel

109 24/0 Sherganj Yes Agri. 1 Nai Shaileshbhai

Raghubhai 1800 1674

110 25/0 Sherganj Yes Agri. 1 Nai Jagdishbhai

Vaghabhai 1800 586.5

111 25/1 Kolhapur Yes Agri. 1 Sendha bhai

Karmshibhai Rabari 1190 1190

112 25/2 Kolhapur Yes Agri. 1 Varjangbhai Mavjibhai

Thakor 1190 1190

113 25/3 Kolhapur Yes Agri. 1 Satabhai Sangrambhai

Rabari 1190 1190

114 25/4 Kolhapur Yes Agri. 1 Kamuben Chhaganji

Thakor 1190 1190

115 25/5

Yes Govt.

116 25/6

Yes Govt.

117 25/7

Yes Govt.

118 25/8 Alahbad Yes Agri. 1 VERSIBHAI VIHABHAI

THAKOR 1800 1800

119 25/9 Alahbad Yes Agri. 1 RAMABHAI

KARSANBHAI BHARWAD

1190 1190

120 25/10 Alahbad Yes Agri. 1 Solanki Ajiben

Mohanbhai 1190 1050

121 25/11

Yes Govt.

122 25/12

Yes Govt.

123 25/13

Yes Govt.

Page 63: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 63

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

124 25/14

Yes Agri 1 BHAVABHAI A

CHUADARI 1597

125 25/15

Yes Govt.

126 25/16 Arajansar Yes Agri. 1 VALABHAI K CHAUDARI 1800

127 25/17 Arajansar Yes Agri.

JAGUBHAI LALUBHAI PRAJAPATI

1190

128 25/18 Arajansar Yes Agri. 1 Karsanbhai Mavabhai

Chaudhry 1190 1190

129 25/19 Arajansar Yes Agri. 1 Pababhai Velabhai Kanbi 1190 1190

130 25/20 Arajansar Yes Agri. 1 Vihabhai Jivabhai

Chaudhary 1190 1190

131 26/0

Yes Govt.

132 26/1 ARJANSA

R Yes Agri. 1

SEVADAS BAJRANGDAS SADHU

1800 1800

133 26/2 Arajansar Yes Agri. 1 Harkhabhai Panabhai

Patel 1190 1190

134 26/3 Arajansar Yes Agri. 1 MANAJI HEMRAJJI

THAKOR 1190 1190

135 26/4 Arajansar Yes Agri. 1 JEMABHAI VALABHAI KANDI (CHAUDHARY)

1190 1190

136 26/5 Arajansar Yes Agri. 1 Somabhai Virabhai

Thakor 1190 1190

137 26/6 Arajansar Yes Agri. 1 Revaben Ramsibhai

Chaudhary 1190 1190 490

138 26/7 ARJANSA

R Yes Agri. 1

NAGJI KALABHAI RABARI

1190 1190 906

139 26/8 ARJANSA

R Yes Agri. 1

BABABHAI MOTIBHAI HARIJAN

1190 1190 332

140 26/8 to

26/9 ARJANSA

R Yes Agri. 1

Yes 380 Viraben Kamabhai Patel

141 26/9 TATIYANA Yes Agri. 1 VASANTBHAI

AMRATBHAI THAKKAR 1190 1190

142 26/10 Tatiyana Yes Agri. 1 Bhavabhai Parmabhai 1190 1190 332

Page 64: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 64

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

Patel

143 26/10

to 26/11

Tatiyana Yes Agri. 1

Yes 224 Ramchandji Motiji

Gaynodha

144 26/11 Tatiyana Yes Agri. 1 MANAJI VIHAJI

THAKOR 1800 1190 332

145 26/12 Tatiyana Yes Agri. 1 Shankarji Mohanji Thakor 1050 1050 332 Yes 284 Shankarji Mohanji

Thakor

146 27/0

Tatiyana Yes Agri. 1 JSALIYA CHOTHABHAI

REVABHAI 1190 1800 332 Yes 700

JSALIYA CHOTHABHAI

REVABHAI

Tatiyana Yes Agri. 1 JIVANJI DHULAJI

THAKOR 1190 576 900 Yes 332

JIVANJI DHULAJI THAKOR

147 27/0 to

27/1 Tatiyana Yes Agri. 1

Yes 232.5

Ashvinkumar Kirtilal Shah

148 27/1 Tatiyana Yes Agri. 1 Okhabhai Rajabhai

Rabari 1050 1050 813

149 27/2 Tatiyana Yes Agri. 1 LEBABHAI MEVABHAI

RABARI 1190 1190 332

150 28/0 Tatiyana Yes Agri.

PACHABHAI KARSHANBHAI KHADLECHA

1190 1190 242

3 JSALIYA HARCHAND

DEVSIBHAI 1190 1190

148.8

LILABHAI RAJUBHAI

RABARI 1190 1190 600

151 28/0 to

28/1 Tatiyana Yes Agri. 1

Yes 280

Gandabhai Ramabhai Charkta

148 28/1 Tatiyana Yes Agri. 1 SHANKARBHAI K DESAI 720 720 1800 Yes 320 SHANKARBHAI K

DESAI

149 28/2 PADAR Yes Agri. 1 BALDEVBHAI

JESUNGBHAI RABARI 1190 1190

150 28/3 TATIYANA Yes Agri. 1 BHALABHAI RAJABHAI

RABARI 1800 1800

Page 65: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 65

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

151 28/4 UN Yes Agri. 1 RANIBEN VERSIJI

THAKOR 1190 1190 332

152 28/4 to

28/5 TATIYANA Yes Agri. 1

Yes 448 Jayntiji Hiraji Thakor

153 28/5 savpura Yes Agri. 1 BHIMABHAI

GANESHBHAI CHAUDHARI

1190 1190 332

154 28/5 to

28/6 TATIYANA Yes Agri. 1

Yes 336

Somaji Chotaji Kakrecha

155 28/6

Yes Govt

156 28/6 to

28/7 TATIYANA Yes Agri 1

Yes 298

Sukhdevbhai Panchaji Ranera

157 28/7 savpura Yes Agri. 1 KAILASHBEN

RAMNIKLAL SHAH 1190 1190

158 28/7 to

28/8 Savpura Yes Agri. 1

Yes 440

Shampuji Punaji Sabosana

159 28/7 to

28/8 Savpura Yes Agri. 1

Yes 320 Punaji Ravaji Thakor

160 28/7 to

28/8 Savpura Yes Agri. 1

Yes 320

Shantaji Sagramji Thakor

161 28/8 savpura Yes Agri. 1 THAKOR JOGAJI

RAVAJI 1190 1190 890

162 28/8 to

29/0 Savpura Yes Agri. 1

Yes 144 Madhiben B Sabosana

163 28/8 to

29/0 Savpura Yes Agri. 1

Yes 475 Rameshji A Sabosana

164 28/8 to

29/0 Savpura Yes Agri. 1

Yes 280 Rajuji Sangramji Thakor

165 29/0 savpura Yes Agri. 1 Thakor Savsiji Jethaji 2475 1190 900

166 29/1 to

29/0 Savpura Yes Agri. 1 Ishvarji Babuji Thakor

440

167 29/1 to

29/0 Savpura Yes Agri. 1 Vinaji Bajuji Thakor

368

168 29/1 savpura Yes Agri. 1 PANCHABHAI 1190 1190

Page 66: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 66

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

SURABHAI RAVAL

169 29/2 savpura Yes Agri. 1 SHANKARJI SAGRAMJI

THAKOR 1190 1190 332

170 29/3 savpura Yes Agri. 1 BHAGVANJI RAJUJI

THAKOR 1190 1190 900

171 29/4 savpura Yes Agri. 1 VINAJI HAJURJI

THAKOR 1190 1190 332

172 29/4 to

30/0 savpura Yes Agri. 1

Rajeshkumar Bhailalbhai Soni

316.4

173 29/4 to

30/0 savpura Yes Agri. 1

Rajeshkumar Bhailalbhai Soni

280

174 30/0 Bhalgam Yes

Agri. 1 Thakor Raghuji Hajurji 1190 1190

Agri. 1 BHARATSINH JIVUBHA

VAGHELA 1190 1190 1800

175 31/0 Karsanpura Yes Agri. 1 Chhatraji visaji Thakor 1800 1597.

5 3200

176 31/1 Karasanpur

a Yes Agri. 2

Fojalal Okhalal Babariya 1260 1225 900

Falguni Ankitkumar Shah 1260 1225 900

177 31/2 Karasanpur

a Yes Agri. 1 Kotak Varadlal Aatmaram 1800 1800 1800

178 31/3 ANANDPU

RA Yes Agri. 1

PACHABHAI SODABHAI RABARI

1190 1190 1800

179 31/4 KARSHAN

PURA Yes Agri. 1

SANUBHA PRABHATSINH

THAKOR 1190 1190 1800

180 32/0 Anandpura Yes Agri. 1

Bhatakiya Bababhai Khodabhai

1800 1800 1400

1 Shah Velchand Chhotalal 625 625 400

181 32/1 ANANDPU

RA Yes Agri. 1

JOYTAJI MAFAJI LOTIYA

1190 1190

182 32/2 ANANDPU

RA Yes Agri. 1

BECHARJI SANKARJI BHATKIYA

1190 1190

183 32/3 ANANDPU Yes Govt

Page 67: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 67

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

RA

184 32/4 ANANDPU

RA Yes Agri. 1

CHATURJI LAKHMAN BHATKIYA

1190 1190

185 32/5 ANANDPU

RA Yes Agri. 1

CHATURJI LAKHMAN BHATKIYA

1190 1190

186 33/0 Anandpura Yes Agri. 1 Preajapati Hirabhai

Ramjibhai 2475 1190

187 33/1 Odha Yes Govt

188 33/1 to

33/2 Odha Yes Agri. 1

Yes 800 Bhudarji C Somaniya

189 33/1 to

33/2 Odha Yes Agri. 1

Yes 870 Nemabhai K Tharecha

190 33/1 to

33/2 Odha Yes Agri. 1

Yes 822

RAMANBHAI B VAGHRI

191 33/2 Odha Yes Agri. 1 SAVSIJI KHETAJI

THAKOR 1800 1190

Yes 720

SAVSIJI KHETAJI THAKOR

192 33/3 Odha Yes Agri. 1

193 33/3-33/4

Odha Yes Agri. 1

Yes 720 SADIK BHAI M GHIA

194 33/3-33/4

Odha Yes Agri. 1

Yes 876 ASGHARBHAI N

GHIYA

195 33/4 Odha Yes Agri. 1 DHARSIJI NANAJI

THAKOR 1800 1190

196 33A/0 Odha Yes Agri.

Thakor Bhimaji Ramsiji 2500 2500 1800 Yes 800 Thakor Bhimaji Ramsiji

197 33A/0

to 33A/1

Odha Yes Agri. 1

Yes 1032 Arajanji H Kakrecha

198 33A/0

to 33A/1

Odha Yes Agri. 1

Yes 1032 BHEMABHAI R

SONETHA

199 33A/1 Odha Yes Govt 1

200 33A/1

to Odha Yes Agri. 1

Yes 1032 Dineshji H Kakrecha

Page 68: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 68

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

33A/2

201 33A/2 Odha Yes Govt

202 33A/2 to 34/0

Odha Yes Agri. 1

Yes 1032 Najamuddin A Ghiya

203 33A/2 to 34/0

Odha Yes Agri. 1

Yes 1500 Idrishbhai A Ghiya

204 33A/2 to 34/0

Odha Yes Agri. 1

Yes 1500 Chhaganbhai A

Dhandhoh

205 34/0 Odha Yes Agri. 1 Vora Abbasbhai

Hasanbhai 2500 2500

206 34/1 Totana Yes Agri. 1 MEMAN AJITBHAI

VLIBHAI 1800 1800 1092

207 35/0 Totana Yes Agri. 1 Patani Lakshmanbhai

Jagmalbhai 2500 1190 1026

208 35/0 to

35/1 Totana Yes Agri. 1

Yes 600 Hirabhai P Suthar

209 35/1 Totana Yes Agri. 1 VELJI PACHAJI

SUTHAR 1800 1190 1092

210 35/1 to

35/2 Totana Yes Agri. 1

Yes 978

Onecha Tarsangji Haribhai

211 35/1 to

35/2 Totana Yes Agri. 1

Yes 246

Onecha Mobatji Haribhai

212 35/1 to

35/2 Totana Yes Agri. 1

Yes 408

Onecha Dhasarathji Haribhai

213 35/1 to

35/2 Totana Yes Agri. 1

Yes 408

Onecha Pradhanji Babuji

214 35/2 Totana Yes Agri. 1 JORAJI HARIJI THAKOR 1800 1190

1584 JORAJI HARIJI

THAKOR

215 35/2 to

35/3 Totana Yes Agri. 1

Yes 876 Jamabhai B Bharvad

216 35/3 Totana Yes Agri. 1 HAIDARBHAI RASULJI

MODH 1800 1800

217 35/3 to

35/4 Totana Yes Agri. 1

Yes 330 Paragbhai v Suthar

Page 69: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 69

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

218 35/4 Totana Yes Agri. 1 SARDARJI HARIJI

THAKOR 1800 1800

1500

SARDARJI HARIJI THAKOR

219 35/4 to

35/5 Totana Yes Agri. 1

Yes 2016 Paragbhai v Suthar

220 35/5 Totana Yes Agri. 1 PRAGJIBHAI

VIRAMJIBHAI SUTHAR 1800 1190

221 35/5 - 35/6

Totana Yes Agri. 1 Manguda Malabhai

Raghabhai 966

222 35/5 to

35/6 Totana Yes Agri. 1 BABUBHAI R PARMAR

1230 Yes 768 Naranbhai r Bharvad

223 35/6 Totana Yes Agri. 1 MADHABHAI SAGTHABHAI

BHARWAD 1800 1190

224 35/6 to

36/0 Totana Yes Agri. 1 BABUBHAI R PARMAR

1877

225 36/0 Totana Yes Agri. 1 Bharvad Malabhai

Raghabhai 2500 1800 1000

226 36/0 - 36/1

Totana Yes Agri. 1 Thakkar Kuberdas

Dhanapatray 1092

227 36/1 Totana Yes Agri. 1 KUBERDAS

DALPATRAM THAKKAR 1800 1190 2475

228 36/1 to

36/2 Totana Yes Agri. 1 Paragji B Balodhana

1422 Yes 600 Paragji B Balodhana

229 36/2 Totana Yes Govt

230 36/2 to

36/3 Totana Yes Agri. 1 Janaji d Thakor

1308

231 36/2 to

36/3 Totana Yes Agri. 1 Janavanji Punaji Thakor

1308

232 36/3 Totana Yes Govt

233 36/3 to

36/4 Totana Yes Agri. 1 Navinbhai Fojalal Shah

1644

234 36/3 to

36/4 Totana Yes Agri. 1

Yes 440 Gangoh Namaji Lilaji

235 36/4 Totana Yes Govt

Page 70: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 70

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

236 37/0 Totana Yes Govt

237 38/0 Totana Yes Govt

238

38/0 - 38/1 & 38/1 - 38/2

Mota Jampur

Yes Agri. 1 Solanki Pratapji Takhaji

2475

239 38/1 Totana Yes Govt

240 38/2 Totana Yes Govt

241 38/3 KASARA Yes Agri. 1 JESABHAI MEVABHAI

RAVAL 1800 1190

242 38/4 KASARA Yes Agri. 1 MAVJIBHAI RAVABHAI

RAVAL 1800 1190

243 38/4 - 38/5

Kasara Yes Agri. 1 Patel Jayendra Amritlal

1308

244 38/5 Kasara Yes Agri. 1 JAYENDRAKUMAR AMRUTBHAI PATEL

1190 1190 1400

245 38/5 - 38/6

Kasara Yes Agri. 1 Patel Gangaben Amritlal

1308

246 38/6 Kasara Yes Agri. 1 GOVINDBHAI MOTIBHAI

JOSHI 1800 1190

247 38/7 Kasara Yes Agri. 1 DEVCHAND

GOVINDBHAI JOSHI 1800 1190

248 38/8 Kasara Yes Agri. 1 HUSAINKHAN

CHAKARKHAN BLOCH 1800 1190 1400

249 38/8 - 38A/0

Kasara Yes Agri. 1 Baloch Hussainkhan

Chakrkhan 1092

250 38A/0 Kasara Yes Agri. 1 Goswami Babupuri

Devpuri 2500 2500 1638

251 38A/1 Kasara Yes Agri. 1 Chaudhry Kuberbhai

Rambhai 1800 1190

252 38A/2 Kasara Yes Agri. 1 Goswami Virampuri

Devpuri 1800 1190 1638

253 38A/3 Kasara Yes Agri. 1

Page 71: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 71

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

254 38A/4 Kasara Yes Govt

255 38A/5 Kasara Yes Govt

256 39/0 Devpura Yes Agri. 1 Bijolbhai Arjanbhai

Rabari 1800 1800

257 39/1 Devpura Yes Govt.

258 39/2 Devpura Yes Govt

259 39/3 Devpura Yes Agri. 1 Desai Rupabhai

Arajanbhai 1800 1800 1650 Yes 1500

Desai Rupabhai Arajanbhai

260 39/4 Devpura Yes Agri. 2 Thakor Kursiji Bajiji 1800 1800 903.

6 Yes 720 Thakor Kursiji Bajiji

261 39/5 Devpura Yes Govt

262 40/0 Dhanera Yes Agri. 1 Rabari Lebabhai

Punjabhai 2500 2500

263 40/1 Dhanera Yes Agri. 1 Jadeja Kailashba Anduba 1800 1800 1650

264 40/1 to

40/2 Dhanera Yes Agri. 1

Desai Tejabhai Cheharabhai

1800

265 40/2 Sariyad Yes Agri. 1 Joshi Jivrambhai

Ujambhai 1800 1800 384

266 40/3 Sariyad Yes Agri. 1 Chaudhry Ramsibhai

Devsibhai 1800 1800

267 40/4 Sariyad Yes Agri. 1 Joshi Shrirambhai

Amrutbhai 1800 1800

268 40/4 - 40/5

Sariyad Yes Agri. 1 Joshi Hemmat kumar

Ganeshbhai 390

269 40/4 - 40/5

Sariyad Yes Agri. 1 Joshi Jeevrambhai Dalsa

bhai 546

270 40/4 - 40/5

Sariyad Yes Agri. 1

Yes 400 Shantibhai Jesangbhai

Joshi

271 40/5 Sariyad Yes Agri. 1 JOSHI HARDEV

BHIMJIBHAI 1800 1800

272 40/5 - 40/6

Sariyad Yes Agri. 1 Joshi Hardevbhai

Bhimajibhai 870

Page 72: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 72

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

273 40/6 Sariyad Yes Agri. 1 Joshi Prahaladbhai

Ramsankar 1800 1800 1740

274 40/6-40/7

Sariyad Yes Agri. 1 Joshi Prabhuram

Khodabhai 715

275 40/7 Sariyad Yes Agri. 1 Joshi Bharatbhai

Gopalbhai 1800 1800

276 40/7-40/8

Sariyad Yes Agri. 1 Joshi Manshiben

BaldevBhai 984

277 40/8 Sariyad Yes Agri. 1 Joshi Alkeshbhai

Baldevbhai 1800 1800

278 40/8 to

40/9 Sariyad Yes Agri. 1 Ambarambhai V Joshi

320

279 40/9 Sariyad Yes Agri. 1 Joshi Ambaram

Vaghabhai 1800 1800

280 40/10 Sariyad Yes Agri. 1 Chaudhry Ramsibhai

Devsibhai 1800 1800

281 40/11 Sariyad Yes Agri. 1 Panchal Lakhamanbhai

Dhudabhai 1800 1800 930

282 41/0 Sariyad Yes Agri. 1 Chaudhari Dungarbhai

Ramabhai 1800 1800 1380

283 41/1 Sariyad Yes Agri. 1 Joshi Bharatbhai

Gopalbhai 1800 1800

284 41/1 to

41/2 Sariyad Yes Agri. 1

Joshi Hardevbhai Bhimajibhai

522

285 41/2 Sariyad

Yes

Agri. 2

Joshi Prabhuram Jemabhai

1260 1225 630

Yes Joshi Vasudevbhai

Bhanjibhai 1260 1260

286 41/2 - 41A/0

Sariyad Yes Agri. 1 Joshi Baldevbhai

Bhanjibhai 582

287 41/2 - 41A/0

Sariyad Yes Agri. 1 Joshi Lakshmi ram

Shivaram 1092

288 41A/0 Sariyad Yes Agri. 1 Brahman Lakhiram

Shivram 2500 1800 1400

289 41A/0 - Sariyad Yes Agri. 1 Joshi Dayabhai

546

Page 73: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 73

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

41A/1 Devrambhai

290 41A/0 - 41A/1

Sariyad Yes Agri. 1 Desai Revabhai Vasibhai

600

291 41A/1 Sariyad Yes Agri. 1 Desai Revabhai Vasibhai 1800 1800

292 41A/1 - 41A/2

Sariyad Yes Agri. 1 Rameshbhai ramsi bhai

660

293 41A/2 Sariyad Yes Agri. 1 Chaudhari Dhaniben

Laxmanbhai 1800 1800 650

294 41A/3 Sariyad Yes Agri. 1 Chaudhari Parmabhai

Devabhai 1800 1800

295 42/0 Sariyad Yes Agri. 1 Chaudhari Ranchodbhai

Bhimabhai 2500 1800

296 42/1 Sariyad Yes Agri. 1 Makwana Manilal

Laljibhai 1800 1800

297 42/2 Sariyad Yes Agri. 1 Nai Punabhai Jemabhai 1800 1800

298 42/3 Sariyad Yes Agri. 1 Chaudhari Lakshmanbhai

Ganeshbhai 1800 1800 320

299 42/3 to

42/4 Sariyad Yes Agri. 1

Yes 450 Chaudhry Kanjibhai V

300 42/3 to

42/4 Sariyad Yes Agri. 1

Yes 480

Jitabhai Jagmalbhai Chaudhry

301 42/4 Lodhi Yes Agri. 1 Thakor Gandaji Madarji 1800 1800 2800

302 42/4 to

42/5 Lodhi Yes Agri. 1

Yes 2000 Somabhai J Desai

303 42/5 Lodhi Yes Agri. 1 Rabari Jorabhai

Vastabhai 1800 1800

304 43/0 Lodhi Yes Agri. 1 Rabari Versibhai

Kalyanbhai 1800 1800 2192 Yes 2400

Rabari Versibhai Kalyanbhai

305 43/0 to

43/1 Lodhi Yes Agri. 1

Rabari Meghrajbhai Vasibhai

572

306 43/0 to

43/1 Lodhi Yes Agri. 1

Rabari Ishvarbhai Khengarbhai

350

307 43/1 Lodhi Yes Agri. 1 Harijan Hirabhai 1800 1800 900

Page 74: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 74

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

Govabhai

308 43/1 to

43/2 Lodhi Yes Agri. 1

Yes 600 Hargovanbhai S Desai

309 43/2 Lodhi Yes Govt

310 43/3 Lodhi Yes Govt

311 43/3 to

43/4 Lodhi Yes Agri. 1 Thakor Rekhaji Jahuji

1356

312 43/3 to

43/4 Lodhi Yes Agri. 1

Rabari Amratbhai Jorabhai

624

313 43/4 Dhanasara Yes Agri. 1 Bhudarbhai Prabhuram

joshi 1800

314 43/5 Lodhi Yes Agri. 1 Rabari Nagji bhai

Vasrambhai 1800 1800 756

315 43/5 to

43/6 Lodhi Yes Agri. 1

Yes 700 Chhaganbhai M Desai

316 43/6 Vadiya Yes Agri. 1 Thakor Pradhanji

Ramchandraji 1800 1800 690

317 43/7 Vadiya Yes Govt

Dhirajlal Punamchand Shah

1800 1800

318 43/7 to

44/0 Lodhi Yes Agri. 1 Umidji Khumaji Thakor

965

319 43/7 to

44/0 Vadiya Yes Agri. 1

Yes 360 Rabari Karmsibhai K

320 43/7 to

44/0 Vadiya Yes Agri. 1

Yes 720

Rabari Revabhai Govabhai

321 44/0 Kalodhi Yes Govt

Shah Puskar Kumar Nathalal

1800 1800

322 44/0-44/1

LODHI Yes Agri. 1 THAKOR VADANJI

MAGANJI 1217

323 44/0-44/1

LODHI Yes Agri. 1 THAKOR SOBHAJI

MAVAJI 765

324 44/0-44/1

VADIYA Yes Agri. 1 THAKOR GAMBHIRJI

HAJURJI 935

Page 75: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 75

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

325 44/0-44/1

VADIYA Yes Agri. 1

Yes 332 Rupaben Chelabhai

Rabari

326 44/1 Vadiya Yes Agri. 1 Thakor Savsiji Ghemarji 1800 1800 1800

327 44/1-44/2

Vadiya Yes Agri. 1 SHAH PIYUSHKUMAR

NATHALAL 1375

328 44/2 Vadiya Yes Agri. 1 Thakor Chinaji Dajiji 1800 1800 905

329 44/2-44/3

Vadiya Yes Agri. 1 THAKOR KANTIJI

ABHAJI 450

330 44/2-44/3

Vadiya Yes Agri. 1

Yes 525 Thakor Madarji H

331 44/2-44/3

Vadiya Yes Agri. 1 THAKOR KESHAJI

ABHAJI 618

332 44/2-44/3

Vadiya Yes Agri. 1 THAKOR PAJIJI DAJUJI

550

333 44/3 Vadiya Yes Agri. 1 Thakor Manjaji Abhaji 1800 1800

334 44/3-44/4

Vadiya Yes Agri. 1 THAKOR GAMBHIRJI

MANSANGJI 450

335 44/3-44/4

Vadiya Yes Agri. 1

Yes 332 Sajaji Kaluji Thakor

336 44/4 Vadiya Yes Agri. 1 Thakor Okhaji Kaluji 1800 1800 870

337 44/5 Kalodhi Yes Govt.

338 45/0 Kalodhi Yes Agri. 1 Thakor Varsungji Rayji 1800 1800

339 45/1 Kalodhi Yes Agri. 1 Rupeshkumar Bhogilal

Bhatkiya 1800 1800

340 45/2 Kalodhi Yes Agri. 1 Thakor Kananji Mobatji 1800 1800

341 45/3 Sadasan Yes Agri. 1 Thakor Narsangji

Karsanji 1800 1800

342 45A/0 Kalodhi Yes Agri. 1 Thakor Babuji Dhulaji 1800 1800

343 45B/0 Melusan

Agri. 1

344 45B/1 Melusan Yes Agri. 1 Rabari Haribhai

Vasrambhai 1800 1225

Page 76: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 76

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

Melusan 1 Rabari Babubhai

Khengarbhai 1225

345 45B/2 Melusan Yes Agri. 1 Rabari Govabhai

Vasrambhai 1800 1800

346 45B/3

Melusan

Yes Agri.

1 Rabari Nagjibhai

Masarubhai 1260 1225

Melusan 1 Rabari Jethabhai

Ratanbhai 1260 1225

347 46/0

Melusan

Yes Agri.

1 Rabari Vershibhai

Vasrambhai 625 750

Melusan 1 Rabari Khengarbhai

Rambhai 625 750

Melusan 1 Rabari Haribhai

Vasrambhai 1260 1225

348 46/1 Melusan Yes Govt

349 46/2 Dhanasara Yes Agri. 1 Joshi Dhudabhai

Bhikhabhai 1800 1800

350 46/3 Dhanasara Yes Agri. 1 Joshi Bhagvanbhai

Sankarbhai 1800 1800

351 46/4 Dhanasara Yes Agri. 1 BHUDARBHAI

PARBHURAM JOSHI 1800

352 46/5 Dhanasara Yes Govt.

353 47/0

Dharusan

Yes Agri. 3

Joshi Bharatbhai Lakshmanbhai

625 750

Dharusan Joshi Hardevbhai

Lakhirambhai 1260 700

Dharusan Brahman Nagjibhai

Mayaram 625 750

354 47/0 to

47/1 Dharusan Yes Agri. 1

Joshi Naranbhai Devchand

4800

355 47/0 to

47/1 Dharusan Yes Agri. 1

Joshi Srirambhai Ramjibhai

2800

356 47/0 to

47/1 Dharusan Yes Agri. 1

Joshi Jyantibhai Trikambhai

3200

Page 77: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 77

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

357 47/0 to

47/1 Dharusan Yes Agri. 1

Joshi Jaganathbhai Trikambhai

2800

358 47/1

Dharusan

Yes Agri. 2

Joshi Jaynti Trikambhai 1260 1225

Dharusan Brahman Jayram

Mulajibhai 1260 750

359 47/1 to

47/2 Dharusan Yes Agri. 1

Joshi Hardevbhai Ramjibhai

4800

360 47/1 to

47/2 Dharusan Yes Agri. 1

Joshi Sahdevbhai Ramjibhai

4200

361 47/1 to

47/2 Dharusan Yes Agri. 1

Joshi Dayabhai Jesungbhai

3200

362 47/2 Dharusan Yes Agri. 1 Joshi Hardevbhai

Ramjibhai 1800 1800

363 47/3 Kanosan Yes Agri. 1 Thakor Ranchhodji

Virbhanji 1800 1800

364 47/3 to

47/4 Kanosan Yes Agri. 1

Thakor Sahdevji Pradhanji

600

365 47/3 to

47/4 Kanosan Yes Agri. 1 Thakor Ajamalji Dhiraji

600

366 47/3 to

47/4 Kanosan Yes Agri. 1 Thakor Joytaji Hansaji

600

367 47/3 to

47/4 Kanosan Yes Agri. 1 Thakor Devaji Modanji

1400

368 47/3 to

47/4 Kanosan Yes Agri. 1 Thakor Bhomaji Pratapji

1400

369 47/4 Kanosan Yes Agri. 1 Thakor Ashokji Jogaji 1800 1800 1800

370 48/0 Kanosan Yes Agri. 1 Thakor Madarji Gambhirji 1800 1800 1800

371 49/0 Kanosan Yes Agri. 1 Bhangi sankarbhai

Radhabhai 1800 1800

Yes 300

Bhangi sankarbhai Radhabhai

372 49/0 to

49/1 Kanosan Yes Agri. 1

Yes 405 Fulaji C Thakor

373 49/1 Kanosan Yes Agri. 1 Thakor Dalsangji Nagarji 1800 1800

Yes 378 Thakor Dalsangji

Nagarji

Page 78: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 78

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

374 49/1 to

49/2 Kanosan Yes Agri. 1

Yes 580 Dargaji H Thakarda

375 49/2 Kanosan Yes Agri. 1 PANCHAL RAMANLAL

CHUNILAL 1800 1800

Yes 273

PANCHAL RAMANLAL CHUNILAL

376 49/2 to

49/3 Kanosan Yes Agri. 1

Yes 900 Fulaji Gamaji Thakor

377 49/3 Ganeshpur

a Yes Agri. 1

Rabari Ishvarbhai Khodabhai

1800 1800

Yes 378 Rabari Ishvarbhai

Khodabhai

378 49/4 Ganeshpur

a Yes Agri. 1

Desai Babubhai Sartanbhai

1800

Yes 1476 Desai Babubhai

Sartanbhai

379 49/5 Ganeshpur

a Yes Agri. 1 Rajput Udesinh Dalaji 1800

Yes 774 Rajput Udesinh Dalaji

380 49/6 Ganeshpur

a Yes Agri. 2

(1)Rabari Tarjabhai Varavabhai

(2)Bharatbhai Sartanbhai Rabari

1800 1800

Yes 300 Bharatbhai Sartanbhai

Rabari

381 49/6 to

49/7 Ganeshpur

a Yes Agri. 1

Yes 390 Ramjibhai R raval

382 49/7 Ganeshpur

a Yes Agri. 1

Raval Ramchandrabhai Nanabhai

1800 1800

Yes

383 49/7 to

49/8 Ganeshpur

a Yes Agri. 1

Yes 546 Ramjibhai R raval

384 49/8 Ganeshpur

a Yes Agri. 1

Rabari Talajabhai Sartanbhai

1800 1800

Yes 600 Rabari Talajabhai

Sartanbhai

385 50/0 Ganeshpur

a Yes Agri. 1

SOMABHAI JORABHAI RABARI

1800 1800 651 Yes 558 SOMABHAI JORABHAI

RABARI

386 50/1 Ablauva Yes Agri. 1 KANJIBHAI NATHABHAI

RABARI 1800 1800

Yes 1260

KANJIBHAI NATHABHAI RABARI

387 50A/0 Ablauva Yes Agri. 1 Darji Nagjibhai

Maganbhai 1800 1800 1056

388 50A/1 Ablauva Yes Agri. 1 BALVANTJI

BHAICHANDJI THAKOR 1800 1800 648

389 50A/1

to 50A/2

Ablauva Yes Agri. 1

Yes 140 Savdanji V Thakor

Page 79: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 79

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

390 50A/1

to 50A/2

Ablauva Yes Agri. 1

Yes 100 Isvarji M thakor

391 50A/1

to 50A/2

Ablauva Yes Agri. 1

Yes 100 Chenjiji K Thakor

392 50A/1

to 50A/2

Ablauva Yes Agri. 1

Yes 224 Vanvirji R Thakor

393 50A/1

to 50A/2

Ablauva Yes Agri. 1

Yes 160 Babuji K Thakor

394 50A/2 Ablauva Yes Agri. 1 Chaturji Kaluji Thakor 1800 1800 336

395 50A/2 to 51/0

Ablauva Yes Agri. 1

Yes 300 Kanjibhai Nathabhai

Rabari

396 51/0 Ablauva Yes Agri. 1 Amrutbhai Chehrabhai

Rabari 1800 1800 1008

397 51/1 Ablauva Yes Agri. 1 Amrutbhai Nathabhai

Rabari 1800 1800 408

398 51/2 Ablauva Yes Agri. 1 Rabari Muliben Virabhai 1800 1800 560

399 51/3 Ablauva Yes Agri. 1 Thakor Vadnuji Chunaji 1800 1800 904

400 51/3 to

51/4 Ablauva Yes Agri. 1

Yes 676 Ramjiji B Thakor

401 51/4 Ablauva Yes Agri. 1 Amrutbhai Maganbhai

Rabari 1800 1800 504

402 51A/0

Ablauva

Yes Agri. 2

Rahimbhai Jamalbhai Muman

440 1225 280

Ablauva Habibbhai Dadubhai

Muman 440 1225 280

403 51A/0

to 51B/0

Ablauva Yes Agri. 1

Yes 2000 Vajisang Jivaji Thakor

404 51A/0

to Ablauva Yes Agri. 1

Yes 950 Vajisang Jivaji Thakor

Page 80: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 80

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

n

Nam

e o

f A

ffec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

e o

f A

ffec

ted

Pe

rso

n f

or

oth

er

Imp

ac

t

51B/0

405 51B/0 Ablauva Yes Agri. 1 Muman Ibrahim Alimad 1800 1800 560

406 51B/0

to 51B/1

Ablauva Yes Agri. 1

Yes 2000 Muman Hamidaben

Vallibhai

407 51B/0

to 51B/1

Ablauva Yes Agri. 1

Yes 1500 Dineshbhai Amthabhai

Rabari

408 51B/0

to 51B/1

Ablauva Yes Agri. 1

Yes 1500 Kanjibhai Amthabhai

Rabari

409 51B/1 Ablauva Yes Agri. 1 Panchal Ambalal

Hemchand 1800 1800

410 51B/2 Delvada Yes Agri. 1 BharatKumar Kantilal

Brahmbhatt 1800 1800

411 51B/3 Delvada Yes Agri. 1 RASHMIKANT NATWARLAL

BRAHMBHATT 1800 1800

412 52/0 Jangral Yes Agri. 2

RANJITBHAI RUGHNATHBHAI

BAROT 1800 1800 3200

BHARATBHAI RUGHNATHBHAI

BAROT 1800 1800 1800

413 53/0

Jangral

Yes Agri. 3

Barot Rajendrakumar Mafatlal

1800 1800

Jangral Brambhatt Lakshiben

Amrutlal 1800 1800 1400

Jangral Brambhatt Ghanshyam

Rugnathbhai 1800

414 56/0 Jangral Yes Agri. 2

Bharatkumar Jaydevlal Barot

1800 1800

JAYESHBHAI JIVANLAL BAROT

1575 1575

Page 81: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 81

ANNEXURE 2: DETAILS ON TOWERS FOR 400 KV LINE

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

ns

Nam

e o

f th

e

Aff

ec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

es

of

Aff

ec

ted

Pe

rso

n

1 17/1 - - GOV. LAND - - - - - - - -

2 17/2 - - - - - - - - - - -

3 17/3 - - - - - - - - - - -

4 17/4 Jarusha Yes Agriculture 1 Jagmalbhai Kalabhai 1371 1371 - - - -

5 17/5 Jarusha Yes Agriculture 1 Patel jagmal Haribhai 1370 - - - - -

6 17/6 Jarusha Yes Agriculture 1 Sipai Ganibhai

Husenbhai 1371 1371 - Yes 600 Sipai Ganibhai

Husenbhai

7 17/7 Jarusha Yes Agriculture 1 Rameshbhai P Patel 1371 1371 - - - -

8 17/8 Jarusha Yes Agriculture 1 Nai Naranbhai B 1370 1371 - - - -

9 17 /9 Jarusha Yes Agriculture 1 MANABEN

HEMRAJBHAI PATEL 1372 1371 - Yes 200

MANABEN HEMRAJBHAI

PATEL

10 17/10 Jekda Yes Agriculture 1 Govindbhai H Patel 1371 - - - - -

11 17/11 - Yes - - - - - - - - -

12 17/12 jekda Yes Agriculture 1 bhil gomtiben

gandabhai 1370 1370 - - - -

13 17/13 Jekda Yes Agriculture 1 Luhar Laxmanbhai B 1764 - - - - -

14 17/14 Jekda Yes - - - - - - - - -

15 17A/0 - Yes - - - - - - - - -

16 18/0 - Yes - - - - - - - - -

17 18/1 Jekda Yes Agriculture 1 Chaudhari Gajabhai K 2035 1371 - Yes 102 Chaudhari Gajabhai K

18 18/2 Jekda Yes GOV. LAND 1 Bharvad Varsangbhai R 1230 - - - - -

19 18/3 Jekda Yes Agriculture 1 Thakor Maghabhi

Devsibhai 1600 1371 - - - -

20 18/4 Jekda Yes Agriculture 1 Solanki Babubhai 1600 1371 - Yes 175 Solanki Babubhai

Page 82: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 82

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

ns

Nam

e o

f th

e

Aff

ec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

es

of

Aff

ec

ted

Pe

rso

n

Harkhabhai Harkhabhai

21 18/5 Jajansar Yes Agriculture 1 Ishvarbhai D Prajapati 1120 1371 - Yes 102 Ishvarbhai D

Prajapati

22 18/6 Jajansar Yes Agriculture 1 Virambhai V Thakor 1591 1371 - Yes 205 Virambhai V Thakor

23 18/7 Jajansar Yes Agriculture 1 Dharmaben G Thakor 1371 1371 - Yes 244 Dharmaben G Thakor

24 18/8 - Yes - - - - - - - - -

25 18/9 - Yes - - - - - - - - -

26 18/10 Jajansar Yes GOV. LAND 1 Gemarbhai R Thakor 2035 1371 - - - -

27 18/11 Rangpura Yes Agriculture 1 Bijalbhai L Thakor 1371 1371 - Yes 300 Bijalbhai L Thakor

28 18/12 Rangpura Yes Agriculture 1 KHETABHAI

SAVSIBHAI THAKOR 1600 1371 - Yes 550

KHETABHAI SAVSIBHAI THAKOR

29 18/13 - Yes - - - - - - - - -

30 18/14 Kolivada Yes Agriculture 1 Heeraben S Harijan 1377 1371 - - - -

31 18 /15 Kolivada Yes Agriculture 1 HABIBKHAN ALIKHAN

MALEK 1371 1371 - Yes 300

HABIBKHAN ALIKHAN MALEK

32 18 /16 Kolivada Yes - - - - - - - - -

33 18/17 Kolivada Yes Agriculture 1 Patel Mavji Bhai

Haribhai 1600 1371 - Yes 200 Patel Mavji Bhai

Haribhai

34 19/0 - Yes - - - - - - - - -

35 20/0 - Yes - - - - - - - - -

36 20/1 Bhilot Yes Agriculture 1

Vaghela Hanubha Kubersang

1270 1030 - - - -

Agriculture 1 Gagdasbhai R Chaudhri 271 343 - - - -

37 20/2 Bhilot Yes Agriculture 1 Vaghela Vajubhai

Dungarbhai 2035 1371 - Yes 505

Vaghela Vajubhai Dungarbhai

38 20/3 Bhilot Yes Agriculture 1 Raval Gaurisankar

Kevalram 1147 1147 - - - -

Page 83: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 83

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

ns

Nam

e o

f th

e

Aff

ec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

es

of

Aff

ec

ted

Pe

rso

n

Agriculture 1 Prahladram G. Joshi 600 600 - - - -

39 20/4 Bhilot Yes Agriculture 1 Joshi Prahladram

Ganpatram 1600 1371 - - - -

40 20/5 Bhilot Yes Agriculture 1 Vaghela Hanubha

Bhaguji 1371 1371 - - - -

41 20/6 Bhilot

Yes Agriculture 1 Nadoda Devabhai

Dhanabhai 1200 1030 - - - -

Yes Agriculture 1 Vaghela Sultansinh

Ratansinh 343 343 - Yes 68

Vaghela Sultansinh Ratansinh

42 21/0 - Yes - - - - - - - - -

43 21A/0 - Yes - - - - - - - - -

44 21B/0 Bhilot Yes Agriculture 1 DajaBhai S. Chaudhary 1764 1371 - Yes 550 DajaBhai S. Chaudhary

45 21B/1 - Yes - - - - - - - - -

46 21B/2 Bhilot Yes Agriculture 1 Chaudhry Joshnaben D 1371 1371 - Yes 887 Chaudhry Joshnaben D

47 21B/03 Bhilot

Yes Agriculture 1 Ramjibhai G Patel - - - Yes 120 Ramjibhai G

Patel

Yes Agriculture 1 Kuberbhai D Chudhry 1670 1371 - Yes 437 Kuberbhai D

Chudhry

48 21B/04 Bhilot Yes Agriculture 1 Rameshbhai Virambhai

Chaudhry 1260 1371 - Yes 380

Rameshbhai Virambhai Chaudhry

49 21B/05 - Yes - - - - - - - - -

50 21B/06 Memdavad Yes Agriculture 1 Amaratgar Swami 860 - - Yes 300 Amaratgar Swami

51 21B/07 Memdavad Yes Agriculture 1 HarunBhai B Ganchi 1225 - - Yes 450 HarunBhai B

Ganchi

52 21B/08 Memdavad Yes Agriculture 1 KhemaBhai Manjibhai

Harijan 1600 1371 - Yes 350 KhemaBhai

Manjibhai Harijan

53 21B/09 Memdavad Yes Agriculture 1 Devabhai K Patel 1650 1371 - - - -

54 21B/10 Memdavad Yes Agriculture 1 Kanjibhai. J. Chaudhry 1371 1147 - Yes 864 Kanjibhai. J.

Page 84: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 84

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

ns

Nam

e o

f th

e

Aff

ec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

es

of

Aff

ec

ted

Pe

rso

n

Chaudhry

21B/10 Memdavad Yes Agriculture 1 Valabhai B Patel 600 365 - Yes 600 Valabhai B Patel

55 21B/11 Memdavad Yes Agriculture 1 Patel Devabhai

Kalabhai 1568 1371 - - - -

56 22/0 - Yes - - - - - - - - -

57 23/0 - Yes - - - - - - - - -

58 23/1 Premnagar Yes Agriculture 1 Thakor Hemabhai

Khetabhai 1600 1371 - Yes 402 Thakor Hemabhai

Khetabhai

59 23/2 Mehmdavad Yes Agriculture 1 Thkor Chothiben Ranchhodbhai

1370 1371 - Yes 168 Thkor Chothiben Ranchhodbhai

60 23/3 Mehmdavad Yes Agriculture 1 Rabari Govindbhai

Vaghabhai 1317 1371 - Yes 380

Rabari Govindbhai Vaghabhai

61 23/4 Mehmdavad Yes gov. land 1 okhabhai mohanbhai

harijan 1317 - - - - -

62 23/5 - - - - - - - - - - -

63 23/6 Sherganj Yes Agriculture 1 Chaudhry Maghabhai

Manabhai 1371 1371 - Yes 171

Chaudhry Maghabhai Manabhai

64 23/7 Sherganj Yes Agriculture 1 Sadabhai D Thakor 1371 1371 - Yes 175 Sadabhai D Thakor

65 23/8 Sherganj Yes Agriculture 1 Goswami Karsanpuri

Manipuri 1371 1371 - Yes 200

Goswami Karsanpuri Manipuri

66 23/9 - Yes - - - - - - - - -

67 24/0 - Yes - - - - - - - - -

68 25/0 - Yes - - - - - - - - -

69 26/0 - Yes - - - - - - - - -

70 26/1 Sherganj Yes Agriculture 1 Bharvad Jijiben

Saktabhai 1598 1371 - Yes 200 Bharvad Jijiben

Saktabhai

71 26/2 Sherganj Yes Agriculture 1 Vankar Amthubhai

Khengarbhai 1596 1371 - Yes 399 Vankar Amthubhai

Khengarbhai

Page 85: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 85

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

ns

Nam

e o

f th

e

Aff

ec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

es

of

Aff

ec

ted

Pe

rso

n

72 26/3 Kolapur Yes Agriculture 1 Thakor Mafa Devsi 2075 1371 - Yes 300 Thakor Mafa

Devsi

73 26/4 Porana Yes Agriculture 1 Malabhai R. Chaudhary 1371 - - - - -

74 26/5 Kolapur Yes Agriculture 1 Rabari Bababhai

Govindbhai 1307 1371 - Yes 550 Rabari Bababhai

Govindbhai

75 26/6 Alahbad Yes Agriculture 1 Patel Naranbhai

Devjibhai 1370 1371 - Yes 403 Patel Naranbhai

Devjibhai

76 26/7 Porana Yes Agriculture 1 Panchal Ganeshbhai

Jayntibhai 1370 - - - - -

77 26/8 - Yes - - - - - - - - -

78 26/9 Alahbad Yes Agriculture 1 Thakor Devanbhai

Ajubhai 1369 - - - - -

79 26/10 Alahbad Yes Agriculture 1 Patel Arajanbhai

Valabhai 1371 1371 - - - -

80 26/11 - Yes - - - - - - - - -

81 26/12 - Yes - - - - - - - - -

82 26/13 - Yes - - - - - - - - -

83 26/14 - Yes - - - - - - - - -

84 26/15 - Yes - - - - - - - - -

85 26/16 Arajansar Yes Agriculture 1 Gogabhai M Rabari 1275 1371 - - - -

86 26/17 Arjansar Yes Agriculture 1 Nai Ramabhai

Maghabhai 1650 1371 - Yes 450

Nai Ramabhai Maghabhai

87 26/18 Arjansar Yes Agriculture 1 Patel Naranbhai

narsungbhai 1118 +

289 1371 - - - -

88 26/19 Arjansar Yes Agriculture 1 Prajapati Kantibhai

Bhavanbhai 1591 1371 - - - -

89 26/20 Arjansar Yes Agriculture 1 Patel Memabhai

Ganeshbhai 1370 1371 - Yes 463

Patel Memabhai Ganeshbhai

90 27/0 Arjansar Yes GOV. LAND 1 Thakor Dajabhai

Gagaram 1371 - - - - -

91 27/1 Arjansar Yes Agriculture 1 Patel Jivabhai

Paragbhai 1326 1371 - - - -

Page 86: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 86

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

ns

Nam

e o

f th

e

Aff

ec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

es

of

Aff

ec

ted

Pe

rso

n

92 27/2 Arjansar Yes Agriculture 1 Chaudhry Bhavanbhai

Balvantbhai 1598 1371 - Yes 156

Chaudhry Bhavanbhai Balvantbhai

93 27/3 Arjansar Yes Agriculture 1 Patel Bhemabhai

Valabhai 1319 1371 - - - -

94 27/4

Arjansar Yes Agriculture 1 Thakor Bhemaji

Chamanji - - - Yes 339

Thakor Bhemaji Chamanji

Arjansar Yes Agriculture 1 Thakor Ganeshji

Chamanji 1218+1087

1371 - Yes 250 Thakor Ganeshji

Chamanji

95 27/5 Arjansar Yes Agriculture 1 Choudhry Ramabhai

Ajamalbhai 1642+

344 1371 - - - -

96 27/6 - Yes - - - - - - - - -

97 27/7 - Yes - - - - - - - - -

98 27/8 Tatiyana Yes Agriculture 1 Patel bhavabhai

Parmabhai 3135 1370 - - - -

99 27/9 Tatiyana Yes Agriculture 1 Panchal Dayabhai

Ramabhai - - - Yes 260

Panchal Dayabhai Ramabhai

100 27/10 - Yes - - - - - - - - -

101 28/0 - Yes - - - - - - - - -

102 28/1 - Yes - - - - - - - - -

103 28/2 Tatiyana Yes Agriculture 1

Rabari Sendhabhai Ramabhai

- - - Yes 363 Rabari

Sendhabhai Ramabhai

Tatiyana Yes Agriculture 1 Hamirbhai Ramabhai 1370 1370 - - - -

104 28/3 Tatiyana Yes Agriculture 1 Rabari Karsanbhai

Khetabhai 1371 1370 - - - -

105 28/4 Tatiyana Yes Agriculture 1 Khambhala Sudabhai

Karsanbhai 1225 1371 - - - -

106 28/5 - Yes - - - - - - - - -

107 28/6 - Yes - - - - - - - - -

108 28/7 Savpura Yes Agriculture 1 Thakor Tejaji Ravaji 1370 1370 - - - -

Page 87: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 87

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

ns

Nam

e o

f th

e

Aff

ec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

es

of

Aff

ec

ted

Pe

rso

n

109 28/8 Savpura Yes Agriculture 1

Patel Shaileshkumar Baldevbhai

800 737 - Yes 250 Patel

Shaileshkumar Baldevbhai

Savpura Yes Agriculture 1 Thakor Jogaji Ravaji 685 680 - - - -

110 28/9 Savpura Yes Agriculture 1 Thakor Talaji Kamaji 1370 1370 - - - -

111 28/10

Savpura Yes Agriculture 1 Rabari Gokalbhai

Devabhai 1230 1371 - - - -

Savpura Yes Agriculture 1 Thakor Chamanji Sonaji - - - Yes 239 Thakor Chamanji

Sonaji

112 28/11 Savpura Yes Agriculture 1 Thkor Madhuji Sagramji 1363 1371 - Yes 200 Thkor Madhuji Sagramji

113 28/12 Savpura Yes Agriculture 1 Thakor Shankarji

Sangramji 2131 1760 - - - -

114 31/0 - No - - - - - - - - -

115 32/0 - No - - - - - - - - -

116 32/1 - No - - - - - - - - -

117 32/2 - No - - - - - - - - -

118 32/3 - No - - - - - - - - -

119 33/0 - No - - - - - - - - -

120 33/1 ANADPURA Yes Agriculture 1 VARSUNGJI MANAJI

THAKOR 1371 - - - - -

121 33/2 ANADPURA Yes Agriculture 1 Kalaniya Chehrabhai

Punjabhai 1371 - - Yes 250

Kalaniya Chehrabhai Punjabhai

122 33/3 - Yes - - - - - - - - -

123 34/0 - Yes - - - - - - - - -

124 34/1 odha

Yes Agriculture 1 maganji khetaji - - - Yes 380 maganji khetaji

- - - - - - - - -

125 34/2 Odha Yes Agriculture 1 Ghia Saifudeen

Husainbhai 1371 1371 - - - -

Page 88: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 88

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

ns

Nam

e o

f th

e

Aff

ec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

es

of

Aff

ec

ted

Pe

rso

n

126 34/3 Odha Yes Agriculture 1 Yusufali Ibrahim Ghiya 1030+

300 1370+

380 - - - -

127 34/4 Odha Yes Agriculture 1 Farudeen Husainbhai

Ghiya 1371 1370 - - - -

128 34/5 Odha Yes GOV. LAND - Ludharia Bhemabhai V 1370 - - - - -

129 34/6 - Yes - - - - - - - - -

130 34 /7 Totana Yes Agriculture 1 PATNI RAMABHAI

MOHANBHAI 1371 - - - - -

131 34/8 Totana Yes Agriculture 1 Thakor Babuji Lakhaji 1370 1370 - Yes 300 Thakor Babuji Lakhaji

132 34/9 Totana Yes Agriculture 1 Noruddin Rajbali vana 1371 1370 - - - -

133 34/10 Totana Yes Agriculture 1 Dodia Mohseenbhai I 1370 1370 - Yes 300 Dodia

Mohseenbhai I

134 34/11 Totana Yes Agriculture 1 Bhimat Sirajbhai

Hsenbhai 1371 1370 - - - -

134 34/12 Totana Yes Agriculture 1 THAKOR VERASIJI

MOHANJI 1371 - - - - -

135 34/13 Totana Yes Agriculture 1 TOTANIYA BAJUJI

RAMASIJI 1371 - - - - -

136 35/0 Totana Yes Agriculture 1 Govindbhai Madhabhai

Joshi 1370 - - - - -

137 35/1 Totana Yes Agriculture 1 Malubhai K Bharvad 1370 1370 - Yes 300 Malubhai K Bharvad

138 35/2 Totana Yes Agriculture 1 Suthar Bhanubhai V 1380 1370 - - - -

139 35/3 - Yes - - - - - - - - -

140 35/4 - Yes - - - - - - - - -

141 35/5 - Yes - - - - - - - - -

142 35/6 Totana Yes Agriculture 1 Bharvad Babubhai

Ganesh Bhai 1380 - - - - -

143 35/7 - Yes - - - - - - - - -

144 35/8 - Yes - - - - - - - - -

Page 89: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 89

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

ns

Nam

e o

f th

e

Aff

ec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

es

of

Aff

ec

ted

Pe

rso

n

145 35/9 - Yes - - - - - - - - -

146 35/10 - Yes - - - - - - - - -

147 35/11 - Yes - - - - - - - - -

148 36/0 - Yes - - - - - - - - -

149 37/0 - Yes - - - - - - - - -

150 37/1 - Yes - - - - - - - - -

151 37/2 Vithlod Yes GOV. LAND 1 Thakor Ramsanji Babaji 1370 - - - - -

152 37/3 Vithlod Yes GOV. LAND 1 Vershiji Kamaji Thakor 1370 - - - - -

153 37/4 Vithlod Yes GOV. LAND 1 Thakor Lembuji Devsiji 1370 - - - - -

154 37/5 Vithlod Yes Agriculture 1 Thakor Makanji

Sursangji 1370 - - - - -

155 37/6 Vithlod Yes Agriculture 1 Thakor Lilaji Devsiji 1370 - - - - -

156 37/7 devpura Yes Agriculture 1 sarupji rasunji thakor 1370 - - - - -

157 37/8 devpura Yes Agriculture 1 sarupji rasunji thakor 1370 - - - - -

158 38/0 devpura Yes Agriculture 1 Vaghri Samuben

Bharmalbhai 1625 - - - - -

159 38/1 - Yes - - - - - - - - -

160 39/0 - Yes - - - - - - - - -

161 39/1 devpura Yes Agriculture 1 thakor vershiji talaji 695 - - - - -

162 39/2 - Yes - - - - - - - - -

163 39/3 - Yes - - - - - - - - -

164 39/4 - Yes - - - - - - - - -

165 39/5 - Yes - - - - - - - - -

166 39/6 Vithlod Yes Agriculture 1 Cheharabhai J

Chaudhri 1371 - - - - -

167 39/7 - Yes - - - - - - - - -

Page 90: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 90

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

ns

Nam

e o

f th

e

Aff

ec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

es

of

Aff

ec

ted

Pe

rso

n

168 39/8 Sariyad Yes Agriculture 1 Thakor Chandanji

Rudaji 1471 - - - - -

169 40/0 Sariyad Yes Agriculture 1 Talaji Laxmanji Thakor 1370 - - Yes 400 Talaji Laxmanji Thakor

170 40/1 Sariyad Yes Agriculture 1 Lakhiram D Joshi 1400 - - - - -

171 40/2 Sariyad Yes Agriculture 1 Shamjibhai A Joshi 1380 - - Yes 300 Shamjibhai A Joshi

172 40/3 Sariyad Yes Agriculture 1 Joshi Baldevbhai

Tejabhai 1370 1370 - Yes 650

Joshi Baldevbhai Tejabhai

173 40/4 - Yes - - - - - - - - -

174 40/5 Sariyad Yes Agriculture 1 Prajapati Jashiben

Mafabhai 1370 - - Yes 300

Prajapati Jashiben Mafabhai

175 40/6 Sariyad Yes Agriculture 1 Pajapati Gandabhai

Haribhai 1370 - - Yes 300

Pajapati Gandabhai

Haribhai

176 40/7 Sariyad Yes Agriculture 1 Varshaben Hirabhai

Chaudhry 1370 - - - - -

177 40/8 Sariyad Yes Agriculture 1 Joshi Bavabhai Nathurambhai

1370 - - Yes 330 Joshi Bavabhai Nathurambhai

178 41/0 - Yes - - - - - - - - -

179 41/1

Sariyad Yes Agriculture 1 Chaudhry

Ranchhodbhai Vershibhai

- - - Yes 500 Chaudhry

Ranchhodbhai Vershibhai

Sariyad Yes Agriculture 1 Chaudhry Jesangbhai

Laxmanbhai 1370 - - Yes 350

Chaudhry Jesangbhai Laxmanbhai

180 41/2 Sariyad Yes Agriculture 1 Ranchhodbhai

Ramabhai Chaudhry

1380 - - Yes 400 Ranchhodbhai

Ramabhai Chaudhry

- - - Yes 300 Ranchhodbhai

Ramabhai Chaudhry

181 41/3 Sariyad Yes Agriculture 1 Chaudhry Devrajbhai

Hirabhai 1370 - - Yes 800 Chaudhry

Devrajbhai

Page 91: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 91

S.

No

.

To

we

r N

o.

Nam

e o

f th

e

Vil

lag

e

Co

mp

leti

on

of

fin

al

su

rve

ys a

nd

pe

gg

ing

of

tow

er

(Ye

s/

No

Ow

ne

rsh

ip

(Ag

ric

ult

ure

) o

r

Go

ve

rnm

en

t

Nu

mb

er

of

Aff

ec

ted

Pe

rso

ns

Nam

e o

f th

e

Aff

ec

ted

Pe

rso

n

Are

a a

ffe

cte

d

du

rin

g

fou

nd

ati

on

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

Du

rin

g E

rec

tio

n

(sq

ua

re m

ete

rs)

Are

a A

ffe

cte

d

du

rin

g s

trin

gin

g

(sq

ua

re m

ete

rs)

Oth

er

Imp

ac

ts

su

ch

as

ap

pro

ac

h r

oa

d,

ad

dit

ion

al

are

a

du

rin

g e

xe

cu

tio

n

of

wo

rk (

ye

s/N

o)

If Y

es

, a

rea

fo

r

cro

p d

am

ag

e

(sq

ua

re m

ete

r)

Nam

es

of

Aff

ec

ted

Pe

rso

n

Hirabhai

182 41/4 Sariyad Yes Agriculture 1 Chamar Isvarbhai

Chelabhai 1370 - - Yes 300

Chamar Isvarbhai Chelabhai

183 42/0

Sariyad

Yes Agriculture

1 Nai Narotambhai

Virambhai 1370 - - Yes 400 Nai Narotambhai

Virambhai

Sariyad 1 Velabhai Balvantbhai

Nai - - - Yes 300 Nai Velabhai

Balvantbhai

Sariyad 1 Mafabhai sanakarbhai

nai - - - Yes 150

Mafabhai sanakarbhai nai

184 42/1

Sariyad Yes Agriculture 1 Nai Velabhai Balvantbhai

- - - Yes 650 Nai Velabhai Balvantbhai

Sariyad Yes Agriculture 1 Valabhai sagrambhai

chudhari 1370 - - Yes 450

Valabhai sagrambhai

chudhari

185 42/2 - Yes - - - - - - - - -

186 42/3 Sariyad Yes Agriculture 1 nathekhan bhikhan

khan baloch 1370 - - Yes 750

nathekhan bhikhan khan

baloch

187 42/4 Sariyad Yes Agriculture 1 Lila bhai Karsanbhai

Rabari 1370 - - Yes 750

Lila bhai Karsanbhai Rabari

188 42/5 - Yes - - - - - - - - -

189 42/6 Lodhi Yes Agriculture 1 Revabhai Hamirbhai

Rabari 1370 - - - - -

190 43/0 - Yes - - - - - - - - -

191 43/1 Lodhi Yes Agriculture 1 Jorabhai Vastabhai

rabari 1371 - - - - -

192 43/2 - Yes - - - - - - - - -

193 43/3 - Yes - - - - - - - - -

194 43/4 - Yes - - - - - - - - -

195 44/0 - Yes - - - - - - - - -

Page 92: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 92

ANNEXURE 3: DETAILS ON CONSULTATIONS

Village Date Participants

Issues and Public Perceptions

Abluva 3-2-2014 10 Villagers are aware about project and project components. There is assurance from the villagers to support the project

People do not have any major concern about the project

The total population of village is about 7000. There are 20 shops and 5 Flour Mills.

There is no industrial set up around the village

Main economic activities in the village are agriculture and agriculture labour. Average land holding is 5 bigha to 10 bigha. The cropping pattern is 3 seasonal. Wheat, Arandi, Mustard, cotton are major crops. Average value of crops are Wheat -300/ 20Kg, Mustard- 600/ 20Kg, Cotton – 700/ 20Kg, Arandi- 700/ 20 Kg.

Nearly one-fourth of agricultural land is irrigated through Bore well, tube well. Majority depend on rain fed water.

Average rate for land is Rs 3 to 4 lakh per bigha for agricultural land.

Villagers are getting power supply from Government Grid, with no other alternative source of electricity. The average expenditure for electricity per household is around Rs 250 – 300 per month.

Sources of drinking water are Gram Panchayat Bore well, and piped water supply.

There is no loss of residential/commercial structures due to the project as well as no effect on community life like any market places or community activities

There is some shortage of water for human consumption, irrigation, and other downstream uses in village.

There will be no resettlement and land acquisition due to the project activities and no protected areas (national park, protected forest), religiously sensitive sites, historical or archaeological sites in village

There is no public health facility in village, and no chronic disease reported. People are not aware about HIV/AIDS.

There are 51 HHs in the village belong to BPL category. There is one primary school and one middle school. Most of the villagers are unemployed and some in lean season migrate to Patan and Surat for diamond work and other construction and factory work.

People expect cash compensation for the project activities.

There are no organizations of a social nature (NGOs/CBOs/Civil Society) are present in village. All decisions are taken by the Gram Panchayat, with Sarpanch as head.

People of the village feel the consultation was very useful and will help the project in all possible ways.

Arjansar

8-02-2014

5 Villagers are aware about project and project components. There is assurance from the villagers to support the project

People do not have any major concern about the project

There are 500 HHs and the total population of village is about 3000. There are 20 shops and four Flour mills.

There is no industrial set up around the village

Main economic activities in the village are related to agriculture, animal husbandry and agriculture labour.

Some of the agricultural land is irrigated through canal water, tube well. Majority depend on rain fed water.

Average rate for land is Rs 3.6 lakh per bigha for agricultural land.

Page 93: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 93

Village Date Participants

Issues and Public Perceptions

Source of drinking water is piped water supply from Narmada.

There is no loss of residential/commercial structures due to the project as well as no effect on community life like any market places or community activities

There is no shortage of water for human consumption, irrigation, and other downstream uses in village.

There will be no resettlement and land acquisition due to the project activities and no protected areas (national park, protected forest), religiously sensitive sites, historical or archaeological sites in village.

There is one private health clinic with a distance of 13 km from village, No chronic disease reported. People are not aware about HIV/AIDS.

There are 100 HHs in the village belong to BPL category. There is one primary school and one high school near to village. There is one Collage in Radhanpur, 13Km from the village. Some people migrate to Mehsana, Palanpur, and Surat.

People expect cash compensation for the project activities.

There are no social organizations (NGOs/CBOs/Civil Society) present in village. All decisions are taken by the Gram Panchayat, with Sarpanch as head.

People of the village feel the consultation was very useful and will help the project in all possible ways.

Bhelot 9-2-2014 7 Villagers are aware about project and project components. Villagers provided assurance to support the project.

People do not have any major concern about the project

There are 450 HHs and the total population of village is about 5000. There are 2 shops and 10 Flour mills.

There is no industrial set up around the village

Main economic activities in the village are Agriculture, Dairy. Other means of livelihood are agriculture labor and construction labor.

Most of the villagers fully depend on rain fed water as there is no source for irrigation.

Average rate for land is Rs 4.5 lakh per bigha for agricultural land.

Source of drinking water is piped water supply by Gram Panchayat from Narmada.

Villagers are getting power supply from Government Grid, with no other alternative source of electricity. The average expenditure for electricity per household is around Rs 400 – 500 per month.

There is no loss of residential/commercial structures due to the project as well as no effect on community life like any market places or community activities

In summer there is shortage of water for human consumption. Shortage is also reported for irrigation, and other downstream uses in village.

Previous the department acquired land for canal and paid compensation.

There is no health facility around the village, No chronic disease reported. People are not aware about HIV/AIDS.

Around 40% are employed. There is hardly any migration reported.

People expect cash compensation for the project activities as they perceived permanent lose of land..

There are no social organizations (NGOs/CBOs/Civil Society) present in village. All decisions are taken by the Gram Panchayat, with Sarpanch as head.

People of the village feel the consultation was very useful and will help the project in all possible ways.

Charanka

9-2-2014 10 Villagers are aware about project and project components. Villagers provided assurance to support the project.

Page 94: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 94

Village Date Participants

Issues and Public Perceptions

Despite 31 people trained by GPCL they are not engaged till date (solar related technician).

There are 400 HHs and the total population of village is about 2000. There are 8 shops and one Flour mills.

There is no industrial set up around the village

Main economic activities in the village are Agriculture. Other means of livelihood are agriculture labor and construction labor. The cropping pattern is 3 seasonal. Bajara, Jeera, and Jwar are major crops.

Most of the villagers fully depend on rain fed water as there is no source for irrigation.

Average rate for land is Rs. 4 lakh per bigha for agricultural land.

Source of drinking water is water supply by tanker.

Villagers are getting power supply from Government Grid, with no other alternative source of electricity. The average expenditure for electricity per household is around Rs 400 – 500 per month.

There is no loss of residential/commercial structures due to the project as well as no effect on community life like any market places or community activities

There is 4 to 5 RMPs in the village, No chronic disease reported. People are not

aware about HIV/AIDS.

Majority are employed with mainly in Animal Husbandry. There is migration to

GandhiDham & Mehshana.

People expect cash compensation for the project activities as they perceive lose of own land..

There are no social organizations (NGOs/CBOs/Civil Society) present in village. All decisions are taken by the Gram Panchayat, with Sarpanch as head.

People of the village feel the consultation was very useful and will help the project in all possible ways.

Dabi 12-2-2014

6 Villagers are not aware about project and project components. However they gave assurance to support the project.

People do not have any major concern about the project

The total population of village is about 3500. There are 4 shops and 2 Flour mills.

There is no industrial set up around the village

Main economic activities in the village are Agriculture and dairy. Other means of livelihood is agriculture labor.

The source of irrigation is through bore well. But most of the villagers fully depend on rain fed water.

Average rate for land is Rs. 3.5 lakh per bigha for agricultural land.

Source of drinking water is water supply from Narmada river.

Villagers are getting power supply from Government Grid. The average expenditure for electricity per household is around Rs 250 – 300 per month.

There is no loss of residential/commercial structures due to the project as well as no effect on community life like any market places or community activities

There are 2 RMPs in the village, No chronic disease reported. People are not

aware about HIV/AIDS.

There are 40 HHs in the village belong to BPL category. There is one middle

school in the village.

Majority are employed. There is migration to Kathiawad for construction work.

People expect cash compensation for the project activities.

There are no social organizations (NGOs/CBOs/Civil Society) present in village. All decisions are taken by the Gram Panchayat, with Sarpanch as head.

Page 95: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 95

Village Date Participants

Issues and Public Perceptions

People want the rate of the land should be higher.

People of the village feel the consultation was very useful and will help the project in all possible ways.

Devpura

6-2-2014 16 Villagers are not aware about project and project components. However they want to support the project.

People do not have any major concern about the project

There are 300 HHs and total population of village is about 1500. There are 4 shops and 1 Flour mill.

There is no industrial set up around the village

Main economic activities in the village are Agriculture and dairy. Other means of livelihood is agriculture labor. There is single cropping in the year and main crops are Arandi, Wheat, Cotton, Mustard

The source of irrigation is through bore well. Majority depend on rain fed water.

Average rate for land is Rs. 2.5 lakh per bigha for agricultural land.

Source of drinking water is bore well.

Villagers are getting power supply from Government Grid. The average expenditure for electricity per household is around Rs 200 – 300 per month.

There is no loss of residential/commercial structures due to the project as well as no effect on community life like any market places or community activities

There are few RMPs in the village, No chronic disease reported. People are not

aware about HIV/AIDS.

There are 100 HHs in the village belong to BPL category. There is one primary

school in the village.

Half of the workforces are employed. There is migration to Patan, Surat, and

Ahmadabad for work.

People expect cash compensation for the project activities.

There are no social organizations (NGOs/CBOs/Civil Society) present in village. All decisions are taken by the Gram Panchayat, with Sarpanch as head.

People want health facilities near to village.

People of the village feel the consultation was very useful and will help the project in all possible ways.

Dharusan

4-2-2014 10 Villagers are not aware about project and project components.

There are 600 HHs and total population of village is about 2500. There are 6 shops and 2 Flour mills.

There is one oil mill (Krishna oil mill) near the village.

Main economic activities in the village are Agriculture, business and dairy. Other means of livelihood is agriculture labor. Average landholding size is 3 to 4 bigha. Main crops are wheat, arandi, bajara, jawar.

The source of irrigation is through canal water.

Average rate for land is Rs. 5 lakh per bigha for agricultural land and 1 lakh per

bigha for govt. land.

Source of drinking water is bore well. Salty water is not fit for drinking water.

Villagers are getting power supply from Government Grid. The average expenditure for electricity per household is around Rs 200 – 250 per month.

There is no loss of residential/commercial structures due to the project as well as no effect on community life like any market places or community activities

There is a recently opened PHC near to village, No chronic disease reported.

Page 96: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 96

Village Date Participants

Issues and Public Perceptions

People are not aware about HIV/AIDS.

There are 150 HHs in the village belong to BPL category. There is one primary

and one middle school in the village.

Around 15% of the workforces are employed. There is migration to Patan, Surat,

Mumbai, Ahmdabad for work.

People expect cash compensation for the project activities.

There are no social organizations (NGOs/CBOs/Civil Society) present in village. All decisions are taken by the Gram Panchayat, with Sarpanch as head.

People of the village feel the consultation was very useful and will help the

coming project in all possible ways.

Ganeshpura

4-2-2014 12 Villagers are aware about project and project components. They want to support the project.

People do not have any major concern about the project

There are 800 HHs and total population of village is about 4000. There are 10 shops and 2 Flour mills.

There is no industrial set up around the village

Main economic activities in the village are Agriculture and dairy. Other means of livelihood is agriculture labor. The average land holding size- 20-25 Bigha. The main crops are Wheat, Cotton, Arandi, Mustard, Bajara, Jwar

The source of irrigation is through canal water and bore well.

Average rate for land is Rs. 3 to 4 lakh per bigha for agricultural land.

Source of drinking water is bore well.

Villagers are getting power supply from Government Grid. The average expenditure for electricity per household is around Rs. 300 – 500 per month.

There is no loss of residential/commercial structures due to the project as well as no effect on community life like any market places or community activities

No public health facility near the village. No chronic disease reported. People are

not aware about HIV/AIDS.

There are 60 HHs in the village belong to BPL category. There is one primary

school and one middle school in the village.

Half of the workforces are employed.

People expect cash compensation for the project activities.

There are no social organizations (NGOs/CBOs/Civil Society) present in village. All decisions are taken by the Gram Panchayat, with Sarpanch as head.

People of the village feel the consultation was very useful and will help the project in all possible ways.

Jarusa 12-2-2014 10 Villagers are not aware about project and project components. However, they want to support the project.

People want the project work to be done during off season

There are 900 HHs and total population of village is about 5000. There are 12 shops and 2 Flour mills.

There is no industrial set up around the village

Main economic activities in the village is Agriculture. Other means of livelihood is agriculture labor. Average land holding size is 5-10 Bigha, and there are 2 Crops per season. The main crops are Jeera, Arandi, Mustard, Jwar, Bajara, Cotton

Page 97: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 97

Village Date Participants

Issues and Public Perceptions

The source of irrigation is through bore well. One canal is under construction. Majority depend on rain fed water.

Average rate for land is Rs. 3 to 5 lakh per bigha for agricultural land.

Source of drinking water is water supply by gram panchayat from Narmada.

There is shortage of water for human consumption and also the drinking water quality is not good during summer.

Villagers are getting power supply from Government Grid. The average expenditure for electricity per household is around Rs. 250 – 350 per month.

There is no loss of residential/commercial structures due to the project as well as no effect on community life like any market places or community activities

For Canal construction the govt. Paid 3.5 Lakh Per Bigha

No public health facility near the village. No chronic disease reported. People are

not aware about HIV/AIDS.

There are half of the HHs (270 HHs) in the village belong to BPL category. There is one primary school in the village. People migrate to Gandhidham, Ahmadabad for construction work.

Half of the workforces are employed.

People expect cash compensation for the project.

There are no social organizations (NGOs/CBOs/Civil Society) present in village. All decisions are taken by the Gram Panchayat, with Sarpanch as head.

People of the village feel the consultation was very useful and will help the project in all possible ways.

Jekada 12-2-2014 8 Villagers are aware about project but not in detail. However, they want to support the project.

People have the concern that due to project work a lot of trees would be removed.

There are 450 HHs and total population of village is about 3000. There are 6 shops and 2 Flour mills.

There is no industrial set up around the village

Main economic activities in the village is Agriculture. Other means of livelihood is agriculture labor.

The source of irrigation is through bore well. One canal is under construction. Majority depend on rain.

Average rate for land is Rs. 3 to 5 lakh per bigha for agricultural land.

Source of drinking water is water supply by gram panchayat from Narmada.

There is shortage of water for human consumption and also the drinking water quality is not good during summer.

Villagers are getting power supply from Government Grid. The average expenditure for electricity per household is around Rs. 5000 – 700 per month.

There is no loss of residential/commercial structures due to the project as well as no effect on community life like any market places or community activities

For Canal construction the Gujarat govt. paid Rs 1000-24000 per Bigha.

No public health facility near the village. No chronic disease reported. People are

Page 98: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 98

Village Date Participants

Issues and Public Perceptions

not aware about HIV/AIDS.

There are one-third of the HHs (150 HHs) in the village belong to BPL category. There is one primary school in the village. People migrate to Gandhidham, and Ahmadabad for construction work.

Around 40% to 50% of the workforces are employed.

People expect cash compensation for the project.

There are no social organizations (NGOs/CBOs/Civil Society) present in village. All decisions are taken by the Gram Panchayat, with Sarpanch as head.

People of the village feel the consultation was very useful and will help the project in all possible ways.

Kalodhi 5-2-2014 7 Villagers are aware about project and project components. They assured full support to the project.

People do not have any major concern about the project

There are 200 HHs and total population of village is about 1000. There are 2 shops and 1 Flour mill.

There is no industrial set up around the village

Main economic activities in the village are Agriculture and dairy. Other means of livelihood is agriculture labor. Average land holding size is 5-10 Bigha.

The source of irrigation is only through canal. Some depend on rain fed water.

Average rate for land is Rs. 2 lakh per bigha for agricultural land.

Source of drinking water is piped water supply by gram panchayat from Narmada.

There is shortage of water for human consumption and also the drinking water quality is not good during summer.

Villagers are getting power supply from Government Grid. The average expenditure for electricity per household is around Rs. 250 – 300 per month.

There is no loss of residential/commercial structures due to the project as well as no effect on community life like any market places or community activities

For Canal construction the govt. Paid 3.5 Lakh Per Bigha

There is one Rogi Arogya Kendra near the village. No chronic disease reported.

People are not aware about HIV/AIDS.

There is one primary school in the village. People migrate to Patan, Melusan for agriculture labor and construction work.

Majority of the workforces are employed.

People expect cash compensation for the project.

There are no social organizations (NGOs/CBOs/Civil Society) present in village. All decisions are taken by the Gram Panchayat, with Sarpanch as head.

People of the village feel the consultation was very useful and will help the project in all possible ways.

Kanoshan

4-2-2014 12 Villagers are not aware about project and project components. However, they assured full support to the project.

People do not have any major concern about the project

There are 400 HHs and total population of village is about 2000. There are 10 shops and 3 Flour mill.

There is no industrial set up around the village

Main economic activities in the village are Agriculture and dairy. Other means of

Page 99: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 99

Village Date Participants

Issues and Public Perceptions

livelihood is agriculture labor. The main crops are Wheat, Arandi, Mustard, and Cotton.

The source of irrigation is only through canal and bore well. Some depend on rain fed water.

Average rate for land is Rs. 6 lakh per bigha for agricultural land and Rs. 3 lakh per bigha for govt. land.

Source of drinking water is bore well by gram panchayat.

There is shortage of water for human consumption and also the drinking water quality is not good during summer.

Villagers are getting power supply from Government Grid. The average expenditure for electricity per household is around Rs. 200 – 250 per month.

There is no loss of residential/commercial structures due to the project as well as no effect on community life like any market places or community activities

A case is filed in the Patan session court on compensation paid to farmers.

For Canal construction the govt. Paid 3.5 Lakh Per Bigha

There is one Rogi Arogya Kendra near the village. No chronic disease reported.

People are not aware about HIV/AIDS.

There are 65 BPL HHs in the village. There are one primary school and one high school in the village. People migrate to Surat for work.

Majority of the workforces are employed.

People expect cash compensation for the project as they perceived loss of land.

There are no social organizations (NGOs/CBOs/Civil Society) present in village. All decisions are taken by the Gram Panchayat, with Sarpanch as head.

People of the village feel the consultation was very useful.

Kasara 13-2-2014 5 Villagers are not aware about the project details. They assured full support to the project.

People do not have any major concern about the project

There are 400 HHs and total population of village is about 3000. There are 15 shops and 2 Flour mill.

There is no industrial set up around the village

Main economic activities in the village are Agriculture, small business and dairy. Other means of livelihood is agriculture labor. There are 2 crops in a year but farmers who have facilities of tube well able to harvest 3 crops. The main crops are Bajara, Jawar, Cotton, Arandi, Jeera, and Wheat.

The source of irrigation is only through bore well. Some depend on rain fed water.

Average rate for land is Rs. 2 to 4 lakh per bigha for agricultural land.

Source of drinking water is bore well by gram panchayat.

There is no shortage of water for human consumption and also for the drinking water purpose.

Villagers are getting power supply from Government Grid. The average expenditure for electricity per household is around Rs. 400 – 500 per month.

There is no loss of residential/commercial structures due to the project as well as no effect on community life like any market places or community activities

Page 100: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 100

Village Date Participants

Issues and Public Perceptions

There is no health facility near the village. No chronic disease reported. People

are not aware about HIV/AIDS.

There are around 50 BPL HHs. There is one primary school in the village. People migrate to Ghantiwada (Solar Plant work), and Ahmadabad for Iron work.

Majority of the workforces are employed.

People expect cash compensation for the project.

There are no social organizations (NGOs/CBOs/Civil Society) present in village. All decisions are taken by the Gram Panchayat, with Sarpanch as head.

People of the village feel the consultation was very useful and will help the project in all possible ways.

Melusan

13-2-2014 6 Villagers are aware about project and project components. They assured full support to the project.

The land for the tower has been taken but compensation provided is less as compared to market value.

There are 250 HHs and total population of village is about 1200. There are 20 shops and 3 Flour mills.

There is no industrial set up around the village

Main economic activities in the village are Agriculture and dairy. Other means of livelihood is agriculture labor. There are two cropping seasons in a year. Bajara, Jawar, Moong, Wheat, Mustard, Arandi.

The source of irrigation is only through canal water.

Average rate for land on road side is 15-20 Lakh per bigha and for farming Land it is 5 Lakh per Bigha.

Source of drinking water is bore well.

There is shortage of water for human consumption and also the drinking water quality is not good during summer.

Villagers are getting power supply from Government Grid. The average expenditure for electricity per household is around Rs. 400 – 500 per month.

There is no loss of residential/commercial structures due to the project as well as no effect on community life like any market places or community activities

There is one Rogi Arogya Kendra near the village. No chronic disease reported.

People are not aware about HIV/AIDS.

Around 60 BPL HHs in the village. There is one primary school in the village.

People migrate to Surat, and Ahmadabad for Diamond work

Majority of the workforces are employed.

People expect cash compensation for the project.

There are no social organizations (NGOs/CBOs/Civil Society) present in village. All decisions are taken by the Gram Panchayat, with Sarpanch as head.

People of the village feel the consultation was very useful.

Memdabad

9-2-2014 10 Villagers are not aware about project and project components. But they assured full support to the project.

Page 101: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 101

Village Date Participants

Issues and Public Perceptions

People have the concern that Agriculture land today is very costly and any compensation should be based on that.

There are 900 HHs and total population of village is about 5000. There are 12 shops and 4 Flour mills.

There is no industrial set up around the village.

Main economic activities in the village are Agriculture and dairy. Other means of livelihood is agriculture labor. There are two crops in a year. The main crops are Wheat, Jawar, Jeera, Bajara, Cotton, Arandi, and Mustard.

The source of irrigation is only through canal and bore well. Some depend on rain fed water.

Average rate for land is Rs. 2.5 lakh per bigha for agricultural land.

Source of drinking water is piped water supply by gram panchayat from Narmada.

There is shortage of water for human consumption during summer.

Villagers are getting power supply from Government Grid. The average expenditure for electricity per household is around Rs. 400 – 500 per month.

There is no loss of residential/commercial structures due to the project as well as no effect on community life like any market places or community activities

After court interference the government paid 3 Lakh Per Bigha for land acquisition for canal construction.

No chronic disease reported. People are not aware about HIV/AIDS.

Around half of the HHs in the village are BPL. There is one primary school in the

village. People migrate to Radhanpur for Construction work.

Around 40% of the workforces are employed.

People expect cash compensation for the project.

There are no social organizations (NGOs/CBOs/Civil Society) present in village. All decisions are taken by the Gram Panchayat, with Sarpanch as head.

People of the village feel the consultation was very useful and will help the project in all possible ways.

Odha 9-2-2014 8 Though villagers are not aware about project and project components they assured full support to the project.

People feel that during the cotton harvesting season there should be no project work.

There are 250 HHs and total population of village is about 1200. There are 10 shops and 2 Flour mill.

There is no industrial set up around the village

Main economic activities in the village is Agriculture. Other means of livelihood is agriculture labor.

The source of irrigation is only through canal and bore well. Some depend on rain fed water.

Source of drinking water is water supply by gram panchayat from Narmada.

There is no shortage of water for human consumption.

Villagers are getting power supply from Government Grid. The average expenditure for electricity per household is around Rs. 300 – 350 per month.

Page 102: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 102

Village Date Participants

Issues and Public Perceptions

There is no loss of residential/commercial structures due to the project as well as no effect on community life like any market places or community activities

There is no health facility in the village. No chronic disease reported. People are

not aware about HIV/AIDS.

There is one primary school in the village. People migrate to Patan, Surat for

work.

Around 50% of the workforces are employed.

People expect cash compensation for the project.

There are no social organizations (NGOs/CBOs/Civil Society) present in village. All decisions are taken by the Gram Panchayat, with Sarpanch as head.

People of the village feel the consultation was very useful and will help the project in all possible ways.

Rangpura

12-2-2014 10 Villagers are not aware about project and project components. But they assured full support to the project.

During the construction tower should be erected on the boundary of the land and not inside or center of the land

There are 250 HHs and total population of village is about 1200. There are 6 shops and 2 Flour mills.

There is no industrial set up around the village.

Main economic activities in the village is Agriculture. Other means of livelihood is agriculture labor. Average land holding size is 5 Bigha and main crops are Jawar, Cotton, Bajara, Wheat, Arandi, Jeera

The source of irrigation is only through bore well. Majority depend on rain fed water. One canal is under construction from last 2 years.

Average rate for land is Rs. 2.5 lakh per bigha for agricultural land.

Source of drinking water is bore well of gram panchayat.

There is shortage of water for human consumption during summer.

Villagers are getting power supply from Government Grid. The average expenditure for electricity per household is around Rs. 250 – 400 per month.

There is no loss of residential/commercial structures due to the project as well as no effect on community life like any market places or community activities

For canal Rs. 4 Lakh Per Bigha provided to all affected.

No chronic disease reported. People are not aware about HIV/AIDS.

Around 80 HHs in the village are BPL. There is one primary school in the village.

People migrate to Kathiawad, Ahmadabad for labor work. .

Around 60% of the workforces are employed.

People expect cash compensation for the project.

There are no social organizations (NGOs/CBOs/Civil Society) present in village. All decisions are taken by the Gram Panchayat, with Sarpanch as head.

People of the village feel the consultation was very useful and will help the project in all possible ways.

Sariyad 5-2-2014 5 Villagers are aware about project and project components and they assured full support to the project.

There is no critical concern regarding the project.

Page 103: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 103

Village Date Participants

Issues and Public Perceptions

There are 2000 HHs and total population of village is about 10000. There are 100 shops and 6 Flour mills.

There is no industrial set up around the village.

Main economic activities in the village are Agriculture and other small business. Other means of livelihood is agriculture labor. Average land holding size is 10 Bighas. There are 2-3 crops per year and main crops are Arandi, cotton, wheat, mustard, jeera.

The source of irrigation is only through bore well. Majority depend on rain fed water.

Average rate for land is 1.5 -5 Lakh per Bigha for agricultural land and the government rate is 1.85 Lakh Per Bigha.

Source of drinking water is bore well of gram panchayat.

There is shortage of water for human consumption during summer and the water remain salty.

Villagers are getting power supply from Government Grid. The average expenditure for electricity per household is around Rs. 500 – 600 per month.

There is no loss of residential/commercial structures due to the project as well as no effect on community life like any market places or community activities.

One government clinic is in the village. No chronic disease reported. People are

not aware about HIV/AIDS.

Around one-fourth HHs in the village are BPL. There is one primary school and

one secondary school in the village. People migrate to Patan, Gandhidham for

labor work. .

Around 40% of the workforces are employed.

People expect cash compensation for the project.

There are no social organizations (NGOs/CBOs/Civil Society) present in village. All decisions are taken by the Gram Panchayat, with Sarpanch as head.

People of the village feel the consultation was very useful and will help the project in all possible ways.

Savpura

7-2-2014 9 Villagers are not aware about project and project components. But they assured full support to the project.

There is no critical concern regarding the project.

There are 200 HHs and total population of village is about 1000. There are 2 shops and 1 Flour mill.

There is no industrial set up around the village.

Main economic activities in the village are Agriculture and Diary related activities. Other means of livelihood is agriculture labor.

The source of irrigation is only through bore well. Majority depend on rain fed water.

Source of drinking water is bore well of gram panchayat.

There is shortage of water for human consumption during summer.

Villagers are getting power supply from Government Grid. The average expenditure for electricity per household is around Rs. 250 – 300 per month.

Page 104: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 104

Village Date Participants

Issues and Public Perceptions

There is no loss of residential/commercial structures due to the project as well as no effect on community life like any market places or community activities

There is no public health facility. No chronic disease reported. People are not

aware about HIV/AIDS.

There is one primary school in the village. People migrate to Kathiyawad,

Ahmadabad, Surat for labor work. .

Around half of the workforces are employed.

People expect cash compensation for the project.

There are no social organizations (NGOs/CBOs/Civil Society) present in village. All decisions are taken by the Gram Panchayat, with Sarpanch as head.

People of the village feel the consultation was very useful and will help the project in all possible ways.

Sidhwara

11-2-2014 6 Villagers are aware about project and project components. They assured full support to the project.

There is no critical concern regarding the project.

There are 500 HHs and total population of village is about 2500. There are 20 shops and 3 Flour mills.

There is no industrial set up around the village.

Main economic activities in the village are Agriculture and Diary. Other means of livelihood is agriculture labor. Average land holding size is 10 to 15 Bigha and main crops are Jeera, Arandi, Jwar.

Most of the people depend on rain fed water.

Average rate for land is Rs. 2.5 lakh per bigha for agricultural land.

Source of drinking water is piped water supply from Narmada.

There is shortage of water for human consumption during summer.

Villagers are getting power supply from Government Grid. The average expenditure for electricity per household is around Rs. 250 – 300 per month.

There is no loss of residential/commercial structures due to the project as well as no effect on community life like any market places or community activities.

There are few RMPs in the village. No chronic disease reported. People are not

aware about HIV/AIDS.

Around half of the HHs in the village are BPL. There is one primary school in the

village. No migration reported..

Around one fourth of the workforces are employed.

People expect cash compensation for the project.

There are no social organizations (NGOs/CBOs/Civil Society) present in village. All decisions are taken by the Gram Panchayat, with Sarpanch as head.

People of the village feel the consultation was very useful and will help the project in all possible ways.

Tantiyna

7-02-2014 7 Villagers are well aware about project and project components. They assured full support to the project.

There is no critical concern regarding the project.

There are 600 HHs and total population of village is about 3500. There are 10 shops and 2 Flour mills.

There is no industrial set up around the village.

Main economic activities in the village is Agriculture. Other means of livelihood is agriculture labor. Average land holding size is 5-7 bighas and there are 2 crops in

Page 105: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 105

Village Date Participants

Issues and Public Perceptions

a year.

The source of irrigation is only through bore well and canal water.

Average rate for land is Rs. 5 lakh per bigha for agricultural land.

Source of drinking water is bore well of gram panchayat.

There is shortage of water for human consumption during summer.

Villagers are getting power supply from Government Grid.

There is no loss of residential/commercial structures due to the project as well as no effect on community life like any market places or community activities

Lack of health facility in the village. No chronic disease reported. People are not

aware about HIV/AIDS.

Around 50 HHs in the village are BPL. .

Majority of the workforces are employed.

People expect cash compensation for the project.

There are no social organizations (NGOs/CBOs/Civil Society) present in village. All decisions are taken by the Gram Panchayat, with Sarpanch as head.

People of the village feel the consultation was very useful and will help the project in all possible ways.

Vadiya 5-2-2014 17 Villagers are aware about project and project components. They assured full support to the project.

There is no critical concern regarding the project.

There are 100 HHs and total population of village is about 650. There are 2 shops and 1 Flour mills.

There is no industrial set up around the village.

Main economic activities in the village are Agriculture and diary. Other means of livelihood is agriculture labor.

The source of irrigation bore well and canal water. Majority depend on rain fed water.

Average rate for land is Rs. 2.5 to 5 lakh per bigha for agricultural land.

Source of drinking water are pipeline and bore well of gram panchayat.

There is shortage of water for human consumption during summer.

Villagers are getting power supply from Government Grid. The average expenditure for electricity per household is around Rs. 250 – 300 per month.

There is no loss of residential/commercial structures due to the project as well as no effect on community life like any market places or community activities

Gas line has passed through the village.

No chronic disease reported. People are not aware about HIV/AIDS.

Around 20 HHs in the village are BPL. There is one primary school in the village.

People migrate to Patan and Surat for work..

Majority of the workforces are employed.

People expect cash compensation for the project.

There are no social organizations (NGOs/CBOs/Civil Society) present in village. All decisions are taken by the Gram Panchayat, with Sarpanch as head.

People of the village feel the consultation was very useful.

Page 106: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 106

LIST OF PARTICIPANTS Date – 3-2-2014 Village – Abluva District – Patan

Sl. No Name of the Participant Occupation Signature of the (participants)

1 Sri Amrit Bhai Natha Bhai Agriculture

2 Sri Ramji Bhai Shop

3 Sri Lalu Thakur Service

4 Sri Narsukhji Dhiraji Thakur Agriculture

5 Sri Veeraji Mohanji Thakur Agriculture

6 Sri Amritji Hazoorji Thakur Agriculture

7 Sri Mahesh Bhai Thakur Agriculture

8 Sri Dala Bhai Thakur Agriculture

9 Sri Mafaji Harshaji Thakur Agriculture

10 Sri Bhavesh Bhai Agriculture

Date – 8-2-2014 Village – Arjansar District – Patan

Sl. No Name of the Participant Occupation Signature of the (participants)

1 Sri SevaDas Bajrang Das Service

2 Sri JeetaJi Gemal Ji Agriculture

3 Sri Kama Bhai Dungar Bhai Patel Agriculture

4 Sri Karsan Bhai Kheta Bhai Patel Agriculture

5 Jeeva Bhai Prag Bhai Patel Agriculture

Date – 9-2-2014 Village – Bhelot District – Patan

Sl. No Name of the Participant Occupation Signature of the (participants)

1 Sri Ramji Bhai Pacha Bhai Choudhary Agriculture

2 Sri Dana Bhai Hari Bhai Agriculture

3 Sri Ganesh Bhai Kheta Bhai Agriculture

4 Sri Tatana Bhai Sagata Bhai Agriculture

5 Sri Baja Bhai Sagtu Bhai Agriculture

6 Sri RamaBhai Agriculture

7 Sri Gova Bhai Heera Bhai Agriculture

Date – 9-2-2014 Village –Charanka District –Patan

Sl. No Name of the Participant Occupation Signature of the (participants)

1 Raju Bhai Jadeja Unemployed

2 Sehe Bhai Jadeja Agriculture

3 Parbat Bhai Agriculture Labor

4 Malu Bhai Rauma Agriculture Labor

5 Jeeva Bhai Rabari Animal Husbandry

6 Bela Bhai Koli Agriculture Labor

7 Khenga Bhai Ahir Agriculture Labor

8 Nagdan Gadhavi Agriculture

9 Narayan Jeeva Kali Agriculture Labor

10 Amargar Khingar ShopKeeper

Date – 12-2-2014 Village –Dabi District – Patan

Page 107: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 107

Sl. No Name of the Participant Occupation Signature of the (participants)

1 Sri Rataji Chhaganji Thakur Agriculture

2 Sri Kantilal Prabhi Lal Thakur Shop Owner

3 Sri Prabhu Bhai Khoda Bhai Agriculture

4 Sri Jevat Bhai Dharam Singh Bhai Agriculture

5 Sri Mevaji Mallu Ji Agriculture

6 Suman Khan Ayub Khan Mallik Agriculture

Date – 6-2-2014 Village – Devpura District – Banaskanta

Sl. No Name of the Participant Occupation Signature of the (participants)

1 Sri Sartariji Bhikaji Agriculture

2 Sri Parjapati D.M. Agriculture

3 Sri. I.M. Desai Agriculture

4 Sri Balaji Chaturaji Agriculture

5 Sri Abhaji Surobji Agriculture

6 Sri Parbatji Bhikaji Agriculture

7 Sri Mamji Keera Bhai Agriculture

8 Sri Mevaji Neeraji Agriculture

9 Sri Chamanji Partapji Agriculture

10 Sri Sarobji Rasukhji Agriculture

11 Sri Ashokji Jogaji Agriculture

12 Sri Balaji Mobataji Agriculture

13 Sri Bhavaji Bacchuji Agriculture

14 Sri UJaji Sarvanji Agriculture

15 Sri Yogaji Anarji Agriculture

16 Sri Katuji Chamaji Agriculture

Date – 4-2-2014 Village – Dharusan District – Patan

Sl. No Name of the Participant Occupation Signature of the (participants)

1 Sri Prahlad Daya Bhai Agriculture

2 Sri MoolChand Bhai Agriculture

3 Sri Sriram Bhai Agriculture

4 Sri DayaRam Bhai Agriculture

5 Sri Narsun Bhai Agriculture

6 Sri Gokul Bhai Agriculture

7 Sri Gulabji Agriculture

8 Sri Babu Bhai Agriculture

9 Sri Kanji Bhai Agriculture

10 Sri Mulji Devram Bhai Agriculture

Date – 4-2-2014 Village – Ganeshpura District –Patan

Sl. No Name of the Participant Occupation Signature of the (participants)

1 Sri Soma Bhai Jora Bhai Agriculture

2 Sri Kanji Bhai Sartan Bhai Agriculture

3 Sri Kanji Bhai Nogji Bhai Agriculture

4 Sri Babu Bhai Sartan Bhai Agriculture

5 Sri Vishnu Bhai Mafa Bhai Agriculture

Page 108: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 108

6 Sri Ankit Bhai Shibha Bhai Student

7 Sri Raja Bhai Jishan Bhai Agriculture

8 Sri Teja Bhai Veera Bhai Agriculture

9 Sri Narayan Bhai Moti Bhai Agriculture

10 Sri Moti Bhai Malji Bhai Agriculture

11 Sri Lakha Bhai Moti Bhai Agriculture

12 Sri Parbhat Bhai Agriculture

Date – 12-2-2014 Village – Jarusa District – Patan

Sl. No Name of the Participant Occupation Signature of the (participants)

1 Sri Patel Mahesh Bhai Karman Bhai Student

2 Sri Heera Bhai Khemji Bhai Prajapati Agriculture

3 Sri Dharam Singh Bhai Daya Bhai Agriculture

4 Sri Laxman Bhai Heera Bhai Tailor

5 Sri Natoo Bhai Laxman Bhai Thakur Agriculture

6 Sri Bharat Bhai Kanti Bhai Agriculture

7 Sri Sanjay Bhai Laxman Bhai Tailor

8 Smt. Ch. Kami Ben Parma Bhai Surpanch

9 Sri Parma Bhai Karman Bhai Agriculture

10 Sri Vashram Bhai Amrit Bhai Agriculture

Date – 12-2-2014 Village – Jekada District – Patan

Sl. No Name of the Participant Occupation Signature of the (participants)

1 Harka Bhai Vashram Bhai Prajapati Agriculture

2 Heera Bhai Karamsine Bhai Patel Agriculture

3 Govardhan Bhai Harji Bhai Patel Agriculture

4 Himmat Bhai Nanji Bhai Agriculture

5 Mahadev Bhai Shaker Bhai Agriculture

6 Khoda Bhai Jewat Bhai Agriculture

7 Hamir Bhai Karam Singh Bhai Agriculture

8 Nathu Bhai Hemraj Bhai Agriculture

Date – 5-2-2014 Village – Kalodhi District –Patan

Sl. No Name of the Participant Occupation Signature of the (participants)

1 Sri Batuji Mata Ji Agriculture Labor

2 Sri Cheharaji Ranchod ji Agriculture Labor

3 Smt. Sita Ben Barsingh ji Agriculture Labor

4 Smt. Sabi Ben Babuji Agriculture Labor

5 Sri Ahluji Bihaji Agriculture Labor

6 Sri Mangalji Bisaji Agriculture Labor

7 Smt. Pushpa Ben Aww

Date – 4-2-2014 Village – Kanoshan District –Patan

Sl. No Name of the Participant Occupation Signature of the (participants)

1 Sri Keshji Nirpan Ji Agriculture

2 Sri Kranji Sardar Ji Agriculture

Page 109: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 109

3 Sri Tulaji Gamaji Agriculture

4 Sri Chatar Ji Agriculture

5 Sri Barat Ji Vasta Ji Agriculture

6 Sri Jesarrji Tarsanji Agriculture

7 Sri Shantiji Vaktaji Agriculture

8 Sri Fulaji Chandan ji Agriculture

9 Sri Kiranji Ashok ji Agriculture

10 Sri Kamrajji Vastaji Agriculture

11 Sri Vakta Ji Chaturji Agriculture

12 Sri Pratap JI Agriculture

Date – 13-2-2014 Village –Kasara District – Banaskanta

Sl. No Name of the Participant Occupation Signature of the (participants)

1 Veeram puri Dev Puri Goswami Agriculture

2 Govind Puri Dev Puri Goswami Agriculture

3 Bharat puri Viceram Puri Goswami Agriculture

4 Suresh Bhai Meghraj Bhai Joshi Student

5 Prakash Puri Govind Puri Student

Date –13-2-2014 Village – Melusan District – Patan

Sl. No Name of the Participant Occupation Signature of the (participants)

1 Magan Bhai Goa Bhai Agriculture

2 Parma Bhai Vegansi Bhai Agriculture

3 Amrit Bhai Mala Bhai Agriculture

4 Talja Bhai Teja Bhai Agriculture

5 Abhay Bhai Mohan Bhai Agriculture

6 Mallu Bhai Bhagar Pujari

Date – 9-2-2014 Village – Memdabad District –Patan

Sl. No Name of the Participant Occupation Signature of the (participants)

1 Sri Dungar Bhai Vala Bhai Coudhary Agriculture

2 Sri Hemraj Bhai Hari Bhai Agriculture

3 Sri Dana Bhai Beshema Bhai Agriculture

4 Bhika Bhai Govind Bhai Panchal Agriculture

5 Thakur Kanu Bhai Baikunth Ram Agriculture

6 Okha Bhai Mohan Bhai Agriculture

7 Abraham Bhai Akal Bhai Agriculture

8 Shiva Bhai Shyams Bhai Rewari Agriculture

9 Govind Bhai Bheema Bhai Thakur Agriculture

10 Poonam Bhai Bavan Bhai Choudhary Agriculture

Date – Village – Odha District – Banaskanta

Sl. No Name of the Participant Occupation Signature of the (participants)

1 Bhimaji Ramsal Thakur Agriculture

2 Raman Bhai Baba Bhai Patani Agriculture

3 Fakara Bhai Agriculture

Page 110: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 110

4 Shankar ji Arjan Ji Agriculture

5 Lalaji Bhimaji Agriculture

6 Bachuji Bhimaji Agriculture

7 Leraji Ramaji Agriculture

8 Narkhan Ji Ramaji Agriculture

Date – 12-2-2014 Village – Rangpura District – Patan

Sl. No Name of the Participant Occupation Signature of the (participants)

1 Arjun Bhai Lemba Bhai Agriculture

2 Veerbhan Bhai Daya Bhai Agriculture

3 Pancha Bhai Laxman Bhai Agriculture

4 Resu Bhai Barsan Bhai Thakur Agriculture

5 Bheema Bhai Lala Bhai Agriculture

6 Amrit Bhai Bheema Bhai Agriculture

7 Manju Ben Kheta Bhai Agriculture

8 Kheta Bhai Sabsi bhai Agriculture

9 Agar bhai Moma Bhai Agriculture

10 Veerban Bhai Mohan Bhai Agriculture

Date – 5-2-2014 Village – Sariyad District – Patan

Sl. No Name of the Participant Occupation Signature of the (participants)

1 Sri Bharat Bhai Gopal Bhai Agriculture

2 Ch. Manchi Bhai Rama Bhai Agriculture

3 Sri Dungar Bhai Rama Bhai Agriculture

4 Sri Joshi Shyamji Bhai Agriculture

5 Sri Jeevan Bhai Ujjam Bhai Agriculture

Date – 7-2-2014 Village –Savpura District – Banaskanta

Sl. No Name of the Participant Occupation Signature of the (participants)

1 Vela ji Raichand ji Agriculture

2 Lalaji Raichand ji Agriculture

3 Kesha ji Raichand ji Agriculture

4 Pratap ji Raichand ji Agriculture

5 Narkhan ji Raichandji Agriculture

6 Bhupad ji Mana ji Agriculture

7 Baba ji Agriculture

8 Iswar ji Agriculture

9 Bhavesh ji Agriculture

Date –11-2-2014 Village – Sidhwara District –Patan

Sl. No Name of the Participant Occupation Signature of the (participants)

1 Dharshi Bhai Raghunath Bhai Agriculture

2 Mafa Bhai Dharshi Bhai Agriculture

3 Sata Bhai Meghraj Bhai Agriculture

4 Trikam Bhai Mavji Bhai Patel Agriculture

5 Mansingh Raba Bhai Agriculture

Page 111: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 111

6 Mujad Khan Panji Khan Agriculture

Date – 7-2-2014 Village – Tantiyna District – Banaskanta

Sl. No Name of the Participant Occupation Signature of the (participants)

1 Sri Viha Bhai Miba Bhai Agriculture

2 Sri Narsu Bhai Rama Bhai Agriculture

3 Sri Amir Bhai Rama Bhai Agriculture

4 Sri Lila Bhai Raja Bhai Agriculture

5 Sri Harsan Bhai Devsi Bhai Agriculture

6 Sri Pancha Bhai Kamchhi Bhai Agriculture

7 Sri Shobhanji Vana Ji Agriculture

Date – 5-2-2014 Village – Vadiya District – Patan

Sl. No Name of the Participant Occupation Signature of the (participants)

1 Sri Naveen Kumar Puranchand Agriculture

2 Sri Bhagwanji Sukha ji Agriculture

3 Sri Uday Singh Chander ji Agriculture

4 Sri Sabsiji Gemar ji Agriculture

5 Sri Balaji Amirji Agriculture

6 Sri Paraji Durgaji Agriculture

7 Sri Pochaji Anraji Agriculture

8 Sri Madanji Magan ji Agriculture

9 Sri Tarsakji Ravata ji Agriculture

10 Sri Kantiji Kapoorji Agriculture

11 Sri Dasaji Pratapji Agriculture

12 Sri Geetaji Meharuji Agriculture

13 Sri Bopaji Desrajji Agriculture

14 Sri Tarchandji Tarsumji Agriculture

15 Sri Anuji Dhuraji Agriculture

16 Sri Dhanaji Pradhanji Agriculture

17 Sri Hasmukh Bhai Agriculture

Page 112: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 112

ANNEXURE 4: SAMPLE SOCIAL SAFEGUARDS MONITORING FORMAT

A. PROJECT DETAILS

Name of Project

Project Component (Name of the Transmission Line)

Loan Number

Report No.

Report for the period

Date of reporting

B. MONITORING OF DISBURSEMENT OF COMPENSATION AND ALLOWANCES

Item

Target as per RP Actions during reporting period Total to date

Comments AP Unit

Unit rate (Rs.)

Total (Rs.)

AP Unit Unit rate (Rs.)

Total (Rs.)

AP Unit Unit rate (Rs.)

Total (Rs.)

% of target

1. Loss of Crops for Charanka to Jangral 220 kV Transmission Line

Foundation

Erection

Stringing

Other associated Impacts

2. Loss of Crops for Charanka to Sankhari 400 kV Transmission Line

Foundation

Erection

Stringing

Other associated Impacts

3. Loss of Trees for Charanka to Jangral 220 kV Transmission Line

Type of Trees

Page 113: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 113

Item

Target as per RP Actions during reporting period Total to date

Comments AP Unit

Unit rate (Rs.)

Total (Rs.)

AP Unit Unit rate (Rs.)

Total (Rs.)

AP Unit Unit rate (Rs.)

Total (Rs.)

% of target

4. Loss of Trees for Charanka to Sankhari 400 kV Transmission Line

Type of Trees

5. Compensation to Non-Title Holders for Charanka to Jangral 220 kV Transmission Line

Non-title holders

6. Compensation to Non-Title Holders for Charanka to Sankhari 400 kV Transmission Line

Non-title holders

7. Compensation to Non-Title Holders for Charanka to Sankhari 400 kV Transmission Line

Non-title holders

8. Allowances for Vulnerable APs for for Charanka to Jangral 220 kV Transmission Line

Allowances (vulnerable APs)

7. Allowances for Vulnerable APs for Charanka to Sankhari 400 kV Transmission Line

Allowances (vulnerable APs)

C. STATUS/PROGRESS OF WORK

CONTRACTOR'S RESPONSIBILITY

Name of Component

Target as per RP Actual Status during reporting period

Total Status to date Remaining/Pending Status

Remarks

a. Final Surveys

Line Length of Line (kms)

Number of Towers

Length of Line (kms)

Number of Towers

Length of Line (kms)

Number of Towers

Length of Line (kms)

Number of Towers

220 kV Line

400 kV Line

Page 114: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 114

b. Status on Completion of Foundation

220 kV Line

400 kV Line

c. Status on Completion of Erection

220 kV Line

400 kV Line

c. Status on Completion of Erection

220 kV Line

400 kV Line

D. RP PROCESS MONITORING

RP Activity

Task Completed

()

AP (No.) Comments

Completed to date

Total %

Preparation and disclosure of Draft RP

Designating concerned staff for Social Safeguards in PMU

Mobilization of Contractor

Consultation meeting

Establish and operate GRM

Finalize detailed technical design/Final Surveys

Carry out and updating Inventory of APs & Inventory of Lost Assets (Loss of Crops and trees etc)

Declare cut-off date and notify APs

Valuation of Loss of crops and trees

Updating the RP

Submission of updated RP to ADB

Disclosure of RP

Page 115: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 115

RP Activity

Task Completed

()

AP (No.) Comments

Completed to date

Total %

Allocation of fund by GETCO for crop compensation and RP implementation

Hold consultation meeting on disbursement and RP implementation schedule

Disbursement of compensation completed

Disbursement of Allowances completed

Civil works commenced (where RP provisions are implemented)

E. CONSULTATION MONITORING FORMAT Date Location Participants Issues / Decisions / Agreements Comments Charanka to Jangral 220 kV Transmission Line

Charanka to Sankhari 400 kV Transmission Line

F. GRIEVANCE REDRESS MECHANISM MONITORING FORMAT

Date Complainant Receiving Officer Complaint Resolution Comments Charanka to Jangral 220 kV Transmission Line

Charanka to Sankhari 400 kV Transmission Line

Page 116: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 116

ANNEXURE-5: SAMPLE COMPENSATION FORM (C-FORM) AND VALUATION

Page 117: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 117

Page 118: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 118

Page 119: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 119

Page 120: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 120

Page 121: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 121

Page 122: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 122

SUMMARY TRANSLATION IN ENGLISH OF THE C-FORM

GETCO NOTICE

DOR/CONST/Tech/Notice/1166

Construction Sub Division, Deodar

Date- 17.11.2013

To,

Shri Rabari Amrutbhai Nathabhai

Village Ablauva

Tal: Sarasvati (Patan)

Dist. Patan

This is to inform to the public that GETCO as per clause 39 of the Electricity Act 2003,

GETCO is doing transmission activity in the State of Gujarat as per Notification No. GHU-

2004-31-GEB-1104-2946-K dated 29.05.2004.

As per clause 164 of Electricity Act 2003, Govt of Gujarat has given power of telegraphic

authority to GETCO and its officials to erect transmission line and tower to provide electric

power supply vide Notification No. GU-2007-5-ELA-1106-4884-K dated 05.01.2007.

It is to inform to public through this public notice that GETCO has decided to erect

transmission line/ tower and it will pass through area of Village Ablauva for about ... Km for

construction of 220 KV D/C Charanka- Jangral Line. This is decided to provide consistent/

reliable power supply.

Above mentioned activities is being approved by competent authority under Act.

For above activities, Survey No. 342 of Village Ablauva, Tal: Sarasvati, which is under your

ownership and possession, tower and transmission line/ overhead will be erected in this land.

This is to inform you through this notice that GETCO is expecting your support and

cooperation during erection of transmission line.

Any damage to the tree & crop will be reasonably compensated by GETCO as per the Act.

Deputy Engineer (Const.)

Construction Sub Division,

GETCO (GEB)

Deodar

Copy F W R:

1. Mamlatdar, - for further necessary action.

2. Executive Engineer (Construction) GETCO Division Office, Deesa - for further

necessary action.

Page 123: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 123

FORM C

GETCO (Construction) Division, Deesa, Construction Sub- Division Deesa/ Palanpur/

Deodar/ Radhanpur

PANCHKYAS

We the undersigned (1) Rabari Mukeshbhai Amrut, (2) Rabari Amrut Chehara, (3) Rabari

Maheshbhai ishwar, Village Ablauva, Tal: Patan, Dist. Patan today dated 21.12.2013,

Satarday at 6:30 PM, willingly remain present on call of Deputy Engineer GETCO for

assessment of damage of crop/ tree/ house in farm of person from our village Shri Amrutbhai

Nathabhai Rabari, owner of survey No. 88/1, due to erection of tower/ stringing of GETCO’s

220 KV Charanka- Jangral Line, tower No. 51/1 to ....

Detail of tentative damage are as under:

A. Detail of damage of Crop: Castor

Sr.

No. Detail

Area of

Damage in

Sq Mt

Average

output as per

village

revenue

register

Total damage

of Crop

20 Kg (Mann)

Wholesale rate

20 Kg

Rs.

Total

estimated

damage

Rs.

Details = Crop damage during foundation work

45X40 = 1800

0.75 X 21 X 685 = 10788

12 X 58 = 696

0.29 X 21 X 685 = 4171

Total 10788+4171 = 14959

= 15000/

Rs. Fifteen Thousand Only.

Out of above, estimated damage after deducting fertiliser, labour cost & marginal income

from crop damage is Rs. 15,000/-

B. Detail of damage of house: Nil

C. Detail of damage of tree: Nil

Above detail is true to the best of our knowledge & belief.

CONSENT LETTER

Owner of Farm

Name & Sign

Revenue Authority

Village Ablauva,

Dist: Patan

Deputy Engineer

GETCO

Name & Sign

Member of Village

Committee

1.

2.

3.

Page 124: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 124

We the undersigned given in writing that the compensation toward damage of home/ crop/

tree, survey No. 88/1 to be paid to Amrutbhai Nathabhai Rabari.

We have no objection and we will not raise any objection in future for such compensation, if

given to Amrutbhai Nathabhai Rabari.

Name

Sign

ADVANCE RECEIPT I am hereby confirming that i have received DD No. 334 amounting Rs. 15,000 (Rs. Fifteen

Thousand Only) from Executive Engineer (Construction) GETCO Division Office, Deesa

toward damage of my tree/ crop/ house.

Sign

VILLAGE FORMAT NO. 8A (LAND PASSBOOK)

Page No. 2034047424

1 of 1

No. D404706

Village Ablauva, Tal: Patan,

A/c No. 596 Dist. Patan

Name of Owners:

Rabari Kanjibhai Nathabhai (2096)

Rabari Amrutbhai Nathabhai (2096)

Registration

No. of Form

6

Block

Survey No.

& part

Area

Ht/ RA/

Sq Mt

Shape

B. Khe. V

Local

Cess

Educational

Cess Other

2096 88/1 0-34-40 0.77 - - Agriculture

Land Total 88/1 0-34-40 0.77 - -

In person

Sarpanch/ Talati

Village Ablauva,

Dist: Patan

Page 125: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 125

7 and 12 FORM NO. H 2834961

Page No. 1032885008

1 of 1

Village Form No. 7 & 12

Block/ Survey No.- 88/1

Type- Old Condition

Farm Name- -

Land Area

Ht/ RA/ Sq mt

A/c No. 596

Area

Ht/ RA/ Sq mt

Registration No. and possession

in the name of

Total 0-34-40 0-34-40

Rabari Kanjibhai Nathabhai

Rabari Amrutbhai Nathabhai

Area 0-34-40 0-34-40

Shape 0.77 0.77

- - Register entry No.

11, 1144, 1999, 2096, 2827..

Other rights & liability- 1437, 1569, 463, 497, 722

Irrigation and non- irrigation recovery – Rs. 3984 pending (Register No. 3202)

Village Ablauva,

Tal: Patan

Dist: Patan

Page 126: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 126

ANNEXURE 6: DETAILS OF COMPENSATION PAYMENT FOR 220KV LINE (ADB FUNDED) DETAILS OF COMPENSATION PAID BY GETCO IN 220KV D/C CHARANKA-JANGRAL LINE

Loc. No Name of Farmer Village Survey No DD No. DD Date

Compensation paid for all Category including

vulnerability Assistance (If Applicable) Rs.

13A/0 DHARSIBHAI RAGUNATHBHAI THAKOR

SIDHADA 48P2

374091 28-Feb-14

67500 004846 27-Sep-14

004847 27-Sep-14

005202 26-Dec-14

13A/0 to 13B/0

SATABHAI M THAKOR SIDHADA 48P1 005200 26-Dec-14 9000

13B/0 DHARSIBHAI RAGUNATHBHAI THAKOR

SIDHADA 48

374600 24-Jul-14 20000

004845 27-Sep-14 15000

005203 26-Dec-14 20000

13B/0 to 13B/1

KALUBHAI U THEBA SIDHADA 23 005196 26-Dec-14 15000

SHAKINABEN M THEBA SIDHADA 47 005198 26-Dec-14 11000

13B/1

MIYABHAI SAHENKHAN GHORI SIDHADA 24

005131 19-Dec-14 60000

005132 19-Dec-14 40000

005168 26-Dec-14 20000

JUSABBHAI VAGHJIBHAI RAUMA

SIDHADA 044564 6-Jul-15

30000 038608 18-Apr-15

13B/1 to 13B/2

ALIMAMAD R THEBA SIDHADA 510P1 005199 26-Dec-14 15000

469P1 005206 26-Dec-14 17000

ABDULKHAN R THEBA SIDHADA 470P1 005204 26-Dec-14 11000

ZAHIRKHAN RASULKHAN THEBA

SIDHADA 485 038589 18-Apr-15 7500

13B/2 BABIBEN KARIM THEBA SIDHADA

510P2

004844 27-Sep-14 45000

005213 26-Dec-14

RAHIM K THEBA SIDHADA 005214 26-Dec-14 11000

13B/2 to 13B/3

ZAHIRKHAN R THEBA SIDHADA 483 004924 14-Nov-14 5000

RAMJANBHAI T THEBA SIDHADA 511 004927 14-Nov-14 5000

ALIMAMAD R THEBA SIDHADA 510P1 004925 14-Nov-14 5000

JUSHALBHAI VAGHAJI RAUMA SIDHADA 512 004928 14-Nov-14 5000

005209 26-Dec-14 15000

RAMJANKHAN T THEBA SIDHADA 511 005210 26-Dec-14 20000

13B/3 NAGORI JAMBAI PUNJABHAI SIDHADA 508P1

004994 17-Nov-14 55000

004995 17-Nov-14

JAVEDKHAN K THEBA SIDHADA 508P1 005427 10-Feb-15 20000

13B/3 to 13B/4

REMATKHAN M THEBA SIDHADA 16, 505 005197 26-Dec-14 16000

HABIBKHAN FATHEMAMAD THEBA

SIDHADA 506 005205 26-Dec-14 7000

HARUNKHAN KAREEMKHAN THEBA

SIDHADA 038606 18-Apr-15 12000

RASULKHAN M THEBA SIDHADA 506 005212 26-Dec-14 9500

13B/4 JIVABHAI BAVABHAI RABARI BAMROLI 101/1

374096 26-Feb-14

48000 374097 26-Feb-14

005190 26-Dec-14

13B/4 to 13B/5

RAHIMBHAI A THEBA BAMROLI 102/1, 102/2 005201 26-Dec-14 13500

SOHRABKHAN REMATKHAN THEBA

SIDHADA 038607 18-Apr-15 22000

13B/5

DHANIBEN VAGHAJIBHAI MALIK

KORDA 103/1

374098 26-Feb-14 15000

374099 26-Feb-14 15000

DANIBEN AYUBKHAN THEBA 005191 26-Dec-14 20000

15000

13B/5 to 13B/6

AYUBKHAN A PATHAN BAMROLI 111 005184 26-Dec-14 15000

13B/6 MASABHAI SURABHAI THAKOR

BAMROLI 61/2

374100 26-Feb-14

53000 374101 26-Feb-14

005193 26-Dec-14

13B/6 to 13B/7

NARSUNGBHAI R THAKOR BAMROLI 62 005188 26-Dec-14 10000

13B/7 RAMSIBHAI DHARAMSHIBHAI THAKOR

BAMROLI 62 374102 26-Feb-14

53000 374103 26-Feb-14

Page 127: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 127

005194 26-Dec-14

13B/7 to 13B/8

MANUBHA RASULLKHAN Malek

BAMROLI 58 005187 26-Dec-14 15000

13B/8 LAKHMANBHAI BABABHAI RABARI

BAMROLI 274

374104 26-Feb-14

56000 374105 26-Feb-14

005192 26-Dec-14

13B/8 to 13B/9

SAKTABHAI MOTIBHAI THAKOR

DALDI 278/2 005189 26-Dec-14 8000

13B/9 JAGSHIBHAI RAJABHAI THAKOR

DALDI 281, 282

374081 26-Feb-14

67000 374106 26-Feb-14

005195 26-Dec-14

13B/10 MEVABHAI MALUBHAI THAKOR

DABHI 80

374082 26-Feb-14

50000 374083 26-Feb-14

004725 12-Sep-14

13B/10 to 13B/11

RAMESHBHAI MEVABHAI THAKOR

DABHI 134 004726 12-Sep-14 5400

13B/11 JEVATBHAI DHARAMSHIBHAI THAKOR

DABHI

81 374084 26-Feb-14

49150 374085 26-Feb-14

170 004736 12-Sep-14

81 005281 21-Jan-15

13B/11 to 13B/12

KHODABHAI BHAVABHAI THAKOR

DABHI 82 004733 12-Sep-14 6500

KANTHIBHAI KHODABHAI THAKOR

DABHI 84 004729 12-Sep-14 7500

13B/12

BAJUBHAI LAGDHIRBHAI THAKOR

DABHI 94

374178 7-Mar-14 15000

374179 7-Mar-14 15000

BAJUBHAI L THAKOR 004743 12-Sep-14 15000

005284 21-Jan-15 4000

13B/12 to 13B/13

PRABHUBHAI KHODAHBHAI THAKOR

DABHI 93 004742 12-Sep-14 6500

GEMARBHAI K THAKOR DABHI 228 005282 21-Jan-15 4000

13B/13 MOMAJIBHAI DHULABHAI THAKOR

DABHI 92

374145 5-Mar-14

49000 374146 5-Mar-14

004741 12-Sep-14

005283 21-Jan-15

13B/13 to 13B/14

GOVINDBHAI RUPABHAI THAKOR

DABHI 98 004740 12-Sep-14 3000

`CHANDABHAI RUPABHAI THAKOR

DABHI 13 004739 12-Sep-14 5400

SAVDHANBHAI CHOTHABHAI THAKOR

DABHI 14 004737 12-Sep-14 3500

13B/14 VERSHI BHAGAVANBHAI THAKOR

DABHI 15

374147 5-Mar-14 15000

374148 5-Mar-14 15000

005277 21-Jan-15 15000

3000

13B/14 to 13B/15

CHHAGANBHAI KARSHANBHAI RAVAL

DABHI 10 004738 12-Sep-14 3500

HANJIBHAI VALABHAI THAKOR DABHI 11 004724 12-Sep-14 3500

13B/15 MANSUKHBHAI LAKHMANHBHAI THAKOR

DABHI 1P

0

0

004752 12-Sep-14 15000

005279 21-Jan-15 15000

13B/15 to 13B/16

SAJUBEN MAVAJIBHAI RAVAL DABHI 207 004734 12-Sep-14 10000

13B/16 MANSUKHBHAI LAKHMANHBHAI THAKOR

DABHI 1P

0

0

004753 12-Sep-14 14000

004754 12-Sep-14 15000

005280 21-Jan-15 15000

13B/16 to 13B/17

RANCHODBHAI REVABHAI THAKOR

DABHI 161 004732 12-Sep-14 3500

LAVINGBHAI DAJABHAI THAKOR

DABHI 160 004731 12-Sep-14 10000

13B/17 VARAJIBEN AMTHUBHAI THAKOR

DABHI 171

374180 7-Mar-14

49300 374181 7-Mar-14

004730 12-Sep-14

005285 21-Jan-15

Page 128: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 128

13B/17 to 13B/18

VALABHAI SAGRAMBHAI RABARI

DABHI 172 004755 12-Sep-14 3500

JEVATBHAI DHARAMSHIBHAI THAKOR

DABHI 169 004735 12-Sep-14 6700

13B/18 JEVATBHAI DHARAMSHIBHAI THAKOR

DABHI 81

374151 5-Mar-14 15000

374152 5-Mar-14 15000

004744 12-Sep-14 15000

13B/18 to 13B/19

BHARUBHAI MAVJIBHAI RAVAL

DABHI 209P 004756 12-Sep-14 5300

13B/19 MANSUKHBHAI LAKHMANHBHAI THAKOR

DABHI 208

0

0

005278 21-Jan-15 15000

13B/19 to 14/0

BABUBHAI RUGNATHBHAI THAKOR

DABHI 204P2 004751 12-Sep-14 3500

004750 12-Sep-14 3500

AP14/0 HARESHDAN SAGARDAN GADHVI

DABHI 204

374153 5-Mar-14 15000

374154 5-Mar-14 15000

004667 12-Sep-14 25000

004668 12-Sep-14 20000

004669 12-Sep-14 20000

14/0 to 14/1 LAVINGBHAI TALSHIBHAI THAKOR

DABHI 214 004749 12-Sep-14 4000

14/1

HARSANBHAI TARSHIBHAI THAKOR

DABHI 222

374155 5-Mar-14 15000

374156 5-Mar-14 15000

HARCHANDBHAI T THAKOR 004745 12-Sep-14 15000

005287 21-Jan-15 4300

14/1 to 14/2

VAJIBHAI TALSHIBHAI T HAKOR

DABHI 220 004747 12-Sep-14 3500

LAXMANBHAI RUPABHAI THAKOR

DABHI 46 004746 12-Sep-14 4800

14/2 MAGANBHAI PRABHAHAI THAKOR

DABHI 219

374157 5-Mar-14

49000 374158 5-Mar-14

004748 12-Sep-14

005286 21-Jan-15

AP15/0

0

0

0

0

15/1 HUSSENKHAN KARIMKHAN SIPAI

KORDA 837

374601 25-Jul-14 15000

005074 9-Dec-14 15000

20000

15/2

0

0

0

0

15/3 AMARATBHAI RAMSHIBHAI THAKOR

JEKDA 870

374159 5-Mar-14 15000

004919 14-Nov-14 30000

0

15/4 JITABHAI PACHABHAI THAKOR JEKDA 260P

374161 5-Mar-14

60000 374162 05-Mar-14

005211 26-Dec-14

15/4 to 16/0 SAHEBKHAN KARIMKHAN MALLIK

JHARUSA 172 005079 9-Dec-14 5000

AP16/0 NAGJIBHAI JAGSHIBHAI RAVAL

JHARUSA 174

374564 5-Jul-14

60000 004848 27-Sep-14

004849 27-Sep-14

16/0 to 16/1

RAMABHAI K PATEL JHARUSA 204 005056 9-Dec-14 7950

BHURIBEN BHONABHAI BHARWAD

JHARUSA 174 005068 9-Dec-14 3730

16/1 GANESHBHAI T PATEL JHARUSA 183 004901 17-Oct-14

60000

0

0

16/1 to 16/2

GANESHBHAI T PATEL JHARUSA 183 005055 9-Dec-14 6650

NATUBHAI L THAKOR JHARUSA 181 005054 9-Dec-14 12950

AMBABEN K PATEL JHARUSA 180 005057 9-Dec-14 7000

PARMABHAI TRIKAMBHAI PATEL

JHARUSA 112P1 005134 19-Dec-14 50000

JHARUSA 112P1 005576 26-Feb-15 50000

16/2 SIVABHAI K PATEL JHARUSA 180/1 004899 17-Oct-14

60000

0

0

Page 129: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 129

0

005058 9-Dec-14 8620

16/2 to 16/3 HASMUKHBHAI R RANA JHARUSA `192 005064 9-Dec-14 10600

16/3 KHEMABHAI MITHABHAI PRAJAPATHI

JHARUSA 202

374563 5-Jul-14 15000

4832 27-Sep-14 30000

0

16/3 to 16/4

CHHAGANBHAI D PRAJAPATHI JHARUSA 203/1 005061 9-Dec-14 14560

BAJANIYA DUDABHAI PABABHAI

JHARUSA 162 005062 9-Dec-14 14008

DUDABHAI K THAKOR JHARUSA 201 005063 9-Dec-14 6000

DINESHBHAI NARANBHAI CHAUDHARY

JHARUSA 223/2P 036478 25-Mar-15 7500

16/4

PATEL DEVRAJBHAI DHARAMSHIBHAI

JHARUSA 218P1 374562 5-Jul-14 15000

SHARADABEN P THAKOR JHARUSA 218P1 005081 9-Dec-14 15000

RAHIMBHAI H SIPAI JHARUSA 218P1 005076 9-Dec-14 20000

16/4 to 16/5 PACHANBHAI JIVABHAI PATEL JHARUSA 245/1 005060 9-Dec-14 5300

HARKHABHAI N PATEL JHARUSA 234/1P 005066 9-Dec-14 6000

16/5 VIRAMBHAI JIVABHAI PATEL JHARUSA 234P2

374561 5-Jul-14 15000

004839 27-Sep-14 15000

005084 9-Dec-14 25000

16/5 to 16/6 JAGMAL H PATEL JHARUSA `243 005067 9-Dec-14 2850

PACHANBHAI J PATEL JHARUSA 234/1P 005069 9-Dec-14 3645

16/6

VIRAMBHAI J PATEL JHARUSA

244 374559 5-Jul-14 10000

004840 27-Sep-14 7500

134/1 005050 9-Dec-14 30800

145/1 005051 9-Dec-14 8000

235 005052 9-Dec-14 5000

244 005088 9-Dec-14 12500

PACHANBHAI J PATEL JHARUSA

245 374560 5-Jul-14 10000

245/2 004841 27-Sep-14 7500

235 004842 27-Sep-14 3000

245/2 005087 9-Dec-14 12500

16/6 to 16/7 MEMABHAI JIVABHAI PATEL

JHARUSA 234/2 005053 9-Dec-14 5000

244 005059 9-Dec-14 21900

RAMJIBHAI K RAVAL JHARUSA 249 005071 9-Dec-14 10268

16/7 KARMANBHAI KHEMABHAI PATEL

JHARUSA 251

374613 24-Jul-14 15000

004997 17-Nov-14 15000

004996 17-Nov-14 15000

044553 6-Jul-15 9000

45616 17-Aug-15 9000

16/7 to 16/8

KANTHIBHAI P PRAJAPATHI JHARUSA 257/1 005065 9-Dec-14 11000

RAMESHBHAI DHARAMSHIBHAI KUMBHAR

JHARUSA 227 036479 25-Mar-15 7500

SHANKARBHAI DHUDABHAI THAKOR

JHARUSA 122 036480 25-Mar-15 7500

16/8 JEMABEN NARANBHAI CHAUDHARY

JHARUSA 261

374557 5-Jul-14

45000 004843 27-Sep-14

16/8 to 16/9

RAMJIBHAI KAMABHAI RAVAL JHARUSA 273 005070 9-Dec-14 11000

JEMABEN NARANBHAI CHAUDHARY

JHARUSA 261 005208 26-Dec-14 5000

RAMESHBHAI PACHANBHAI PATEL

JHARUSA 57/1P 036477 25-Mar-15 7500

16/9 SIKANDARBHAI HAMIRBHAI SIPAI

JHARUSA 271/2

374556 5-Jul-14 15000

004838 27-Sep-14 15000

005082 9-Dec-14 20000

16/9 to 16/10

KARSHANBHAI O BHARWAD JHARUSA 40 005072 9-Dec-14 6300

HAZRATALI U SIPAI JHARUSA 146/2/3 005073 9-Dec-14 5430

16/10 KHOKAR GAJIBHAI IBRAHIMABHAI

KORDA 146/2/2

374555 5-Jul-14

50000 004837 27-Sep-14

004938 14-Nov-14

16/10 to 16/11

MAVAJIBHAI KARAMANBHAI PATEL

JHARUSA 7 036481 25-Mar-15 10000

16/11 NURMAMAD HUSSENKHAN SIPAI

KORDA 146/1/2

374554 5-Jul-14

45000 004836 27-Sep-14

004937 14-Nov-14

16/11 to 16A/0

RAGABHAI S CHAUDHARY KORDA 145P1 004918 14-Nov-14 35000

RAYMALBHAI JEVATBHAI PATEL

JEKDA 77 038758 16-Apr-15 7500

Page 130: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 130

16A/0 PRAHLADBHAI M SADHU JEKDA 16, 407/2

004655 9-Sep-14

75000 004932 14-Nov-14

407/1 038759 16-Apr-15

16A/0 to 16A/1

PRABHATBA SHIVUBA VAGHELA

GADHA 52 038760 16-Apr-15 12000

16A/1

0

0

0

16A/1 to 16A/2

KARMANBHAI KHETABHAI PATEL

JEKDA 19 038761 16-Apr-15 15800

16A/2

ARAVINDSINH KANUSINHJI VAGHELA

GADHA 41/3

036396 25-Mar-15 15000

15000

038596 18-Apr-15 20000

038597 18-Apr-15 14000

036397 25-Mar-15 26710

NAVUBHA BHIKUBHA VAGHELA

GADHA 41/2 005559 26-Feb-15 23400

16A/2 to 16A/3

RAYABHAI DHARAMSHIBHAI SUTHAR

JEKDA 28 038762 16-Apr-15 8000

038763 16-Apr-15 6000

AMRATBHAI RAMSHIBHAI RAVAL

JEKDA 27/2 038764 16-Apr-15 2000

16A/3 RASIKBHAI NANAJIBHAI PRAJAPATHI

JEKDA 26P

005560 26-Feb-15 15000

15000

038766 16-Apr-15 15000

038765 16-Apr-15 34400

16A/3 to 16A/4

SUTHAR KAMABHAI SHANKARBHAI

JEKDA 30 038767 16-Apr-15 20000

16A/4

HIMAT NANJIBHAI PRAJAPATHI

JEKDA 31

005561 26-Feb-15

15000

15000

9600

038769 16-Apr-15 25000

038768 16-Apr-15 15000

KHODABHAI JEVATBHAI CHAUDHARY

JEKDA 32P2 005569 26-Feb-15 20000

16A/4 to 16A/5

KALABHAI MEHABHAI PATEL JEKDA 81 038770 16-Apr-15 16000

16A/5 BHIKHABHAI MEHABHAI CHAUDHARY

JEKDA

005574 26-Feb-15 15000

15000

038383 16-Apr-15 20000

038771 16-Apr-15 30000

16A/5 to 16A/6

RASUBEN VAJABHAI CHAUDHARI

JEKDA 111 038384 16-Apr-15 10000

16A/6 HARIBHAI PUNABHAI PATEL JEKDA 75

005562 26-Feb-15 15000

15000

038385 16-Apr-15 30000

038386 16-Apr-15 24500

16A/6 to 16A/7

BHARVAD BHIKHABHAI BHARVAD

JEKDA 114/2 038387 16-Apr-15 5000

16A/7 GAFURBHAI MAFABHAI THAKOR

JEKDA 211 4835 27-Sep-14 40000

0

16A/7 to 16A/8

MANUBHAI KHEGARBHAI BHIL JEKDA 472/1 038388 16-Apr-15 7500

TEJABHAI DEVABHAI PATEL JEKDA 215 038389 16-Apr-15 7500

MADHABHAI PARMABHAI PATEL

JEKDA 212 038390 16-Apr-15 5000

16A/8

0

0

0

16A/8 to 17/0

NANUBEN TEJABHAI PATEL JEKDA 121 038391 16-Apr-15 7500

LILABEN BHAGVAN PATEL JEKDA 222 038392 16-Apr-15 13950

17/0 HARIBHAI MANABHAI CHAUDHARY

JEKDA 259

005563 26-Feb-15

100000 038393 16-Apr-15

038394 16-Apr-15

17/0 to 17/1

NATHABHAI MAHDEVBHAI CHAUDHARI

JEKDA 255/1P 038395 16-Apr-15 11700

NANJIBHAI MOMJIBHAI CHAUDHARI

JEKDA 258 038396 16-Apr-15 11700

17/1 BHEMABHAI MAHADEVBHAI CHAUDHARY

JEKDA 255/1P 005564 26-Feb-15 15000

15000

Page 131: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 131

005565 26-Feb-15 5000

038397 16-Apr-15 30000

038398 16-Apr-15 35000

17/2 PURIBEN BHEMABHAI CHAUDHARY

JEKDA 250

005566 26-Feb-15 15000

15000

038399 16-Apr-15 30000

038400 16-Apr-15 40000

17/3 DEHALBHAI MEGHRAJ THAKOR

JEKDA 241

004920 14-Nov-14 40000

0

038401 16-Apr-15 20000

038402 16-Apr-15 8000

17/3 to 17/4 VERASIBHAI MALABHAI THAKOR

JARJANAR 148 038403 16-Apr-15 7500

17/4 THAKOR VALABHAI KHETABHAI

SANTHALI 58

038702 16-Apr-15 30000

038703 16-Apr-15 30000

038704 16-Apr-15 30000

0

17/4 to 17/5

SUNDABHAI MOHANBHAI THAKOR

SANTHALI 56/2 038706 16-Apr-15 11700

CHHATHABHAI MOHANBHAI THAKOR

SANTHALI 56/1P1 45608 17-08-2015 11625

17/5 MASABHAI R THAKOR SANTHALI 55, 57

004935 14-Nov-14 30000

0

45610 17-Aug-15 15000

10000

17/6 JETHABHAI SHANKARBHAI PATEL

SANTHALI 34, 34P1, 54, 54P1

004447 15-Jul-14 30000

0

038707 16-Apr-15 15000

038708 16-Apr-15 7500

17/6 to 17/7 MEGHABHAI PARBATBHAI PATEL

SANTHALI 48/1 038709 16-Apr-15 8900

17/7 HARIBHAI LAKHABHAI PATEL SANTHALI 47

4446 15-Jul-14 30000

0

036392 25-Mar-15 30000

036393 25-Mar-15 18160

17/7 TO 17/8

AMTHUBHAI MEGHABHAI PATEL

SANTHALI 38/3P 036394 25-Mar-15 4650

KHETABHAISAKTABHAI PATEL SANTHALI 46 036395 25-Mar-15 10800

17/8 DALABHAI MANSANGBHAI MALI

SANTHALI 84

004939 14-Nov-14

56900 036399 25-Mar-15

036400 25-Mar-15

17/8 to 17/9

VIRBHANBHAI LEBABHAI THAKOR

RANGPURA 86 036500 25-Mar-15 5400

VALABHAI TALASHIBHAI THAKOR

RANGPURA 65P1 036501 25-Mar-15 8400

BHAGVANBHAI MANJIBHAI MALI

RANGPURA 37 036390 25-Mar-15 6900

MAGHABHAI GANGARAMBHAI MALI

RANGPURA 4[1 036391 25-Mar-15 8900

17/9 BHAGVANBHAI KARSHANBHAI RABARI

RANGPURA

91, 92 4347 2-Jul-14 30000

0

93P2 036493 25-Mar-15 15000

036494 25-Mar-15 9600

17/9 to 17/10

RAMABHAI TALSIBHAI THAKOR

RANGPURA 90 036484 25-Mar-15 4800

VALABHAI TALASHIBHAI THAKOR

RANGPURA 85 036485 25-Mar-15 5700

17/10 NATHABHAI DHARAMSIBHAI THAKOR

RANGPURA 84

4348 2-Jul-14 30000

0

036488 25-Mar-15 15000

036489 25-Mar-15 5400

17/10 to 17/11

SUNDABHAI SAVSIBHAI THAKOR

RANGPURA 107 036486 25-Mar-15 15000

NAGJIBHAI SAVSIBHAI THAKOR

RANGPURA 107P1 036499 25-Mar-15 6000

17/11 VIRBHANBHAI MOHANBHAI THAKOR

RANGPURA 6, 50P1,

108

4346 2-Jul-14 30000

0

036492 25-Mar-15 15000

10000

Page 132: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 132

17/11 to 17/12

KALYANBHAI DHARSIHBHAI THAKOR

RANGPURA 102 036487 25-Mar-15 15000

TALSIBHAI MAVABHAI THAKOR

RANGPURA 114 036502 25-Mar-15 15000

110 036503 25-Mar-15 15000

17/12 LAXMANBHAI LALBHAI RABARI RANGPURA 111

4349 2-Jul-14 30000

0

036497 25-Mar-15 15000

036498 25-Mar-15 9000

17/12 to 17/13

GIRISH ARJANBHAI RABARI SANTHALI 136 036401 25-Mar-15 10000

VELABHAI LAKHABHAI RABARI RANGPURA 112 038710 16-Apr-15 4700

17/13 BEMABHAI LALABHAI RABARI RANGPURA 132

4350 2-Jul-14 30000

0

036495 25-Mar-15 15000

036496 25-Mar-15 9600

17/13 to 17A/0

RAMABHAI SAVSHIBHAI THAKOR

RANGPURA 133 036389 25-Mar-15 11160

THAKOR HAMIRBHAI GANDABHAI

RANGPURA 196 044541 6-Jul-15 12000

17A/0

UDESING K VAGHELA BHILOT 196 005295 21-Jan-15

70000

005296 21-Jan-15

DOLUBHA H VAGHELA BHILOT 198 005320 21-Jan-15 20000

20000

GANDABHAI M THAKOR BHILOT 137P1 005309 21-Jan-15 8000

17A/0 to 17B/0

HAMIRJI GANDABHAI THAKOR BHILOT 005321 21-Jan-15 8000

BALABHAI GANESHBHAI RABARI

BHILOT 274 036475 25-Mar-15 7500

17B/0 VIRBHANBHAI DAYABHAI THAKOR

RANGPURA 4P3

4352 2-Jul-14 30000

0

005330 21-Jan-15 30000

036490 25-Mar-15 20000

036491 25-Mar-15 20000

0

17B/0 to 17B/1

CHOTHIBEN ISHWARBHAI THAKOR

RANGPURA 4P1 036506 25-Mar-15 14000

036387 25-Mar-15 10460

17B/1

RUGHUNATHBHAI MOHANBHAI THAKOR

RANGPURA 6 4394 2-Jul-14 30000

0

VIRBHANBHAI M THAKOR RANGPURA 6

005332 21-Jan-15 30000

0

036482 25-Mar-15 15000

036483 25-Mar-15 12900

DHARSHIBHAI VISABHAI THAKOR

RANGPURA 10P1 4395 2-Jul-14 30000

17B/1 to 17B/2

DHARSHIBHAI VISABHAI THAKOR

RANGPURA 10P1 036505 25-Mar-15 12510

RUGHNATHBHAI MOHANBHAI THAKOR

RANGPURA 137P1 036388 25-Mar-15 5400

17B/2 PURIBA MANUBA JADEJA BHILOT 10P2 005297 21-Jan-15 60000

17B/2 to 17B/3

MAMUBHA JETHUJI VAGHELA BHILOT 414 005308 21-Jan-15 10000

GIRISH ARJANBHAI RABARI RANGPURA 12P 036504 25-Mar-15 10300

17B/3 AJMALBHAI RAMUBHAI NADODHA

BHILOT 178P1

004351 2-Jul-14 30000

0

036466 25-Mar-15 15000

036467 25-Mar-15 16500

17B/3 to 18/0

VASHRAMBHAI SHANKARBHAI PATEL

BHILOT 161/2 036468 25-Mar-15 15000

PRAVINKUMAR JAYSHANKAR JOSHI

BHILOT 130 036476 25-Mar-15 7500

18/0 HIRABHAI HARJIBHAI KANBI BHILOT 161/1P1, 687/2P2

617043 8-Oct-14 30000

617044 8-Oct-14 30000

611517 (Chq)

1-Aug-14 20000

036472 25-Mar-15 15000

036473 25-Mar-15 15000

036474 25-Mar-15 15000

18/0 to 19/0 JETHIBEN VIRAMBHAI RABARI BHILOT 149P2P2 004633 9-Sep-14 15000

JEEVABHAI D RAVAL BHILOT 456 005322 21-Jan-15 12000

Page 133: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 133

DEVJIBHAI B THAKOR BHILOT 449 004931 14-Nov-14 5000

VASHRAMBHAI S PATEL BHILOT 161/2 005323 21-Jan-15 6700

JETHABHAI R KANBI BHILOT 161/1P2 005301 21-Jan-15 17400

REVASHANKAR P RAVAL BHILOT 277 005303 21-Jan-15 5000

VAJABHAI HARJIBHAI KANBI BHILOT 48P1 036471 25-Mar-15 15000

19/0 GAURISHANKAR K RAVAL

BHILOT 165

004651 9-Sep-14 20000

004652 9-Sep-14 20000

004653 9-Sep-14 25000

036398 25-Mar-15 15000

GAGDAS R RABARI 146 004930 14-Nov-14 5000

19/0 to 19/1 SUNDABHAI RAMJIBHAI THAKOR

BHILOT 138 005305 21-Jan-15 14000

374553 07-May-14 15000

19/1 RAMSANGBHAI RAMJIBHAI THAKOR

BHILOT 138

004649 9-Sep-14 30000

0

005293 21-Jan-15 30000

0

005294 21-Jan-15 13200

19/1 to 19/2 HARIBHAI ROOGNATHLAL THAKOR

BHILOT 685 005306 21-Jan-15 9300

19/2 DILUBHA BHAGUJI VAGHELA BHILOT 121

374552 5-Jul-14 15000

45611 17-Aug-15

15000

15000

10000

19/2 to 19/3 KARSANJI HAMIRJI VAGHELA BHILOT 122 005311 21-Jan-15 15000

19/3 RUPSINHJI HAMIRJI VAGHELA BHILOT 122

005324 21-Jan-15

15000

15000

20000

10000

004654 9-Sep-14

30000

0

0

19/3 to 19/4

MAGANBHAI MEHABHAI THAKOR

BHILOT 149P3P1 005304 21-Jan-15 3000

LALJI PACHANJI VAGHELA BHILOT 117 005307 21-Jan-15 15000

GAJUBHA BHURUBHAU VAGHELA

BHILOT 115 005316 21-Jan-15 12800

BHURUBHA NARANJI VAGHELA

BHILOT 573 005319 21-Jan-15 12800

19/4 RAGHUBHAI R KUMBHAR BHILOT 240

4650 11-Feb-15 30000

0

005300 21-Jan-15 17300

005327 21-Jan-15 15000

005328 21-Jan-15 8600

19/4 to 19/5 005329 21-Jan-15 8600

19/4 to 19/5 ARJANBHAI V THAKOR BHILOT 590/2 005310 21-Jan-15 7500

19/5 AMATHABHAI KUVARABHAI THAKOR

BHILOT 242P2

374549 5-Jul-14

49000 005288 21-Jan-15

005289 21-Jan-15

19/5 to 19/6

VAGHABHAI MAFABHAI THAKOR

BHILOT 242P1 005299 21-Jan-15 5000

BALABHAI KUNVARABHAI THAKOR

BHILOT 242P1 005315 21-Jan-15 13800

19/6 SHANKARBHAI R CHAUDHARY

BHILOT 255

374405 25-Apr-14 15000

005290 21-Jan-15 15000

15000

RADHABEN S PATEL 255P1 005292 21-Jan-15 5000

19/6 to 20/0 RADHABEN S PATEL BHILOT 255P1 005291 21-Jan-15 10200

GANESHBHAI K PRAJAPATHI BHILOT 254 005326 21-Jan-15 3500

20/0 RAJABHAI DALABHAI CHAUDHARY

BHILOT 251

374403 25-Apr-14 20000

036464 25-Mar-15 20000

20000

036465 25-Mar-15 20000

20000

20/0 to 20A/0

VIBHABHAI R RABARI BHILOT 455 005302 21-Jan-15 10000

20A/0 JETHABHAI KALABHAI KANBI BHILOT 453

374404 25-Apr-14

80000 036469 25-Mar-15

036470 25-Mar-15

Page 134: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 134

20A/0 to 20/1

PRAHLADBHAI S LAVAR BHILOT 454 004643 9-Sep-14 15000

20/1 JIVABHAI D RAVAL BHILOT 456

374406 25-Apr-14 15000

004634 9-Sep-14 15000

004635 9-Sep-14 10000

20/1 to 20/2 RANCHHODBHAI S THAKOR MEMDABAD

295P3 004630 9-Sep-14 7500

257 004631 9-Sep-14 7500

BHAVANBHAI R PATEL BHILOT 490/1 004656 9-Sep-14 15000

20/2 LATHABEN RAMABHAI JOSHI BHILOT 467P1

374401 25-Apr-14 15000

004940 14-Nov-14 30000

0

20/2 to 20/3

VASUDEVBHAI S THAKOR BHILOT 467P2 004644 9-Sep-14 11000

HATUBHA K VAGHELA BHILOT 501 004645 9-Sep-14 5600

BHURUBHA K VAGHELA BHILOT 501 004646 9-Sep-14 5000

GANESHBHAI PARAGBHAI KANABI

BHILOT 497P1 45637 17-Aug-15 7000

BHOMAJI L VAGHELA BHILOT 502P2 004647 9-Sep-14 20000

BHAVSANGJI K VAGHELA BHILOT 501 004657 9-Sep-14 5000

20/3 RAMJIBHAI P PATEL BHILOT 498

374399 25-Apr-14

72000

374400 25-Apr-14

004636 9-Sep-14

004637 9-Sep-14

005313 21-Jan-15

20/3 to 20/4

GOVINDBHAI SAKLAJI THAKOR

MEMDABAD 261P 004629 9-Sep-14 7500

RAJENDUSINH P VAGHELA BHILOT 503 005312 21-Jan-15 15000

20/4 JOSHNABEN D CHAUDHARY BHILOT 514P3

374548 5-Jul-14 15000

004640 9-Sep-14 30000

0

004639 9-Sep-14 10000

20/4 to 20/5

VANKAR SANTABEN GANDABHAI

BHILOT 465/1/2 004709 12-Sep-14 5700

NATUBHAI L VAGHELA BHILOT 197 004648 9-Sep-14 7500

KANJIBHAI G PATEL BHILOT 514P2 004638 9-Sep-14 15000

20/5 KUBERBHAI DANABHAI CHAUDHARY

BHILOT 518

374397 25-Apr-14 15000

374398 25-Apr-14 15000

004641 9-Sep-14 15000

004642 9-Sep-14 15000

005314 21-Jan-15 5000

20/6 DAUDHBHAI JAMABHAI GACHI MEMDABAD 167P1

20703 24-Apr-14 15000

20704 24-Apr-14 15000

004934 14-Nov-14 15000

20/7 JETHABHAI KHODABHAI CHAUDHARY

MEMDABAD 161P2

20701 24-Apr-14 15000

20702 24-Apr-14 15000

004619 9-Sep-14 15000

004620 9-Sep-14 10000

20/7 to 20/8 PRABHATBHAI R CHAUDHARY MEMDABAD 166P1 004627 9-Sep-14 4000

HARIBHAI A CHAUDHARY MEMDABAD 166P2 004628 9-Sep-14 4000

20/8 RUGHNATHBHAI NANAJIBHAI CHAUDHARY

MEMDABAD 159

20470 24-Apr-14

45000 20471 4-Apr-14

005126 19-Dec-14

20/9 KANUBHAI VIKUTRAM THAKKAR

MEMDABAD 154

20468 4-Apr-14 15000

20469 4-Apr-14 15000

004933 14-Nov-14 15000

20/10 IBRAHIMBHAI A GACHI MEMDABAD 125

20466 4-Apr-14 15000

20467 4-Apr-14 15000

004618 9-Sep-14 15000

004617 9-Sep-14 10000

20/11 OKHABHAI MOHANBHAI HARIJAN

MEMDABAD 130

20464 4-Apr-14

45000 20465 4-Apr-14

036457 25-Mar-15

20/12 DANABHAI BHEMABHAI CHAUDHARY

MEMDABAD 50

20462 4-Apr-14 15000

20463 4-Apr-14 15000

004616 9-Sep-14 15000

20/13 DUNGARBHAI VALABHAI CHAUDHARY

MEMDABAD 58

20460 4-Apr-14 15000

20461 4-Apr-14 15000

004621 9-Sep-14 15000

20/14 BHIKHABHAI GOVINDBHAI 20458 4-Apr-14 45000

Page 135: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 135

PANCHAL 20459 4-Apr-14

45612 17-Aug-15

21/0 DAYABHAI GOVINDBHAI THAKOR

MEMDABAD 25

374396 25-Apr-14 20000

005577 26-Feb-15 60000

0

22/0 SHIVABHAI S RABARI MEMDABAD 783/3P1

374395 25-Apr-14 20000

005077 9-Dec-14 20000

036460 25-Mar-15 20000

036461 25-Mar-15 6000

22/1 LAXMAN HARDASBHAI RABARI MEMDABAD 783/4

038711 16-Apr-15

54000

45613 17-Aug-15

22/1 to 22/2

DUNGARBHAI AMBABHAI HARIJAN

RADHANPUR 783/5 036445 25-Mar-15 7320

KALABHAI MELABHAI THAKOR MEMDABAD 13 036447 25-Mar-15 4800

22/2 OKHABHAI MOHANBHAI HARIJAN

MEMDABAD 761

353 16-Dec-13

58020 374024 8-Feb-14

036455 25-Mar-15

036456 25-Mar-15

22/2 to 22/3

AJUBHAI PRAGBHAI CHAUDHARY

MEMDABAD 754P1 036449 25-Mar-15 8300

CHOTHIBEN RANCHHODBHAI THAKOR

MEMDABAD 782 036451 25-Mar-15 14880

22/3 NATUBHAI SHANKARBHAI PATEL

MEMDABAD 751

635136 (CHQ)

28-Jan-15

15000

15000

15000

036462 25-Mar-15 10000

036463 25-Mar-15 10000

22/3 to 22/4 RATANBHAI SHANKARBHAI PATEL

MEMDABAD 752/1 036450 25-Mar-15 14000

22/4 RAMANBHAI AAMADBHAI RAUMA

MEMDABAD 750

038712 16-Apr-15

85000 044563 6-Jul-15

45609 17-08-2015

22/4 to 22/5 LAXMANBHAI BHAGVANBHAI CHAUDHARY

MEMDABAD 57 036444 25-Mar-15 7800

22/5 DEVJIBHAI VASABHAI KANBI MEMDABAD 747

352 16-Dec-13 15000

374023 8-Feb-14 15000

036452 25-Mar-15 15000

3600

22/5 to 22/6

AMRATBHAI GANESHBHAI SUTHAR

MEMDABAD 743/2 036446 25-Mar-15 8700

ACHARATLAL MOHANLAL PATEL

MEMDABAD 742/P2 036448 25-Mar-15 8200

22/6 BHAGVANBHAI GOVINDBHAI PATEL

MEMDABAD 742/P1

351 16-Dec-13 15000

374022 8-Feb-14 15000

036453 25-Mar-15 15000

036454 25-Mar-15 8100

22/6 to 22/7

RATNABHAI DEVUBHAI THAKOR

SHERGANJ 194/2/1 036433 25-Mar-15 6800

POPATBHAI MAFABHAI THAKOR

SHERGANJ 194/2/1 036437 25-Mar-15 13500

SADABHAI DAYABHAI THAKOR SHERGANJ 193/2 036438 25-Mar-15 14400

22/7 RAMABHAI MAGANBHAI VANKAR

SHERGANJ 194/2P

350 16-Dec-13

55000 374007 1-Feb-14

45614 17-Aug-15

22/7 to 22/8 RAMABHAI MAVJIBHAI THAKOR

SHERGANJ 193/2 036439 25-Mar-15 10000

22/8 GANDABHAI JASWANTBHAI PATEL

SHERGANJ 194/1P2

349 16-Dec-13 15000

374005 16-Dec-13 15000

036441 25-Mar-15 15000

036442 25-Mar-15 6600

22/8 to 22/9 DILIPBHAI GANDABHAI CHAUDHARY

SHERGANJ 194/3 036431 25-Mar-15 14000

22/9 PRAGJIBHAI LALJIBHAI CHAUDHARY

SHERGANJ 43

348 16-Dec-13

54300 374005 1-Feb-14

036459 25-Mar-15

Page 136: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 136

036458 25-Mar-15

22/10 MAFABHAI S CHAUDHARY SHERGANJ 199/2

005177 26-Dec-14 30000

0

005637 26-Feb-15 30000

038745 16-Apr-15 25000

038744 16-Apr-15 15000

22/10 to 22/11

RANCHODBHAI DANABHAI PATEL

SHERGANJ 204/4P1 036432 25-Mar-15 9300

AJMALBHAI HARJIBHAI CHAUDHARY

SHERGANJ 204/4P3 036434 25-Mar-15 4200

22/11 NURMOHAMED GANIBHAI VHORA

SHERGANJ 207

347 16-Dec-13 15000

374004 1-Feb-14 15000

036436 25-Mar-15 15000

036435 25-Mar-15 12600

22/11 to 23/0

JESUNGHBHAI JEVATBHAI PATEL

SHERGANJ 206 036440 25-Mar-15 10400

23/0 JASAVANTHBHAI HARJIBHAI PATEL

SHERGANJ 22P1

005169 26-Dec-14 30000

005170 26-Dec-14 30000

044546 6-Jul-15 30000

30000

23/0 to 24/0

DHUDABHAI AMTHABHAI PATEL

SHERGANJ 208/2P 004713 12-Sep-14 5000

HITESH KANTILAL KORADIA SHERGANJ 208/3P1 038714 16-Apr-15 13000

24/0

SAILESHBHAI NAGABHAI NAYI SHERGANJ '15/1

374413 2-May-14

60000 004711 12-Sep-14

004712 12-Sep-14

SHAILESHBHAI RAGHUBHAI NAYI

SHERGANJ 42P1 036427 25-Mar-15

60000 036428 25-Mar-15

24/0 to 25/0

INDUBEN G NAYI SHERGANJ 16P1 004926 14-Nov-14 7500

BHAVABHAI REVABHAI NAYI SHERGANJ 42P1 036424 25-Mar-15 15000

036423 25-Mar-15 10000

DINESHBHAI VAGHABHAI NAYI SHERGANJ 16P2 036429 25-Mar-15 5000

25/0 JAGDISHBHAI VAGHABHAI NAYI

SHERGANJ 15/3

374411 2-May-14

97500

005085 9-Dec-14

036421 25-Mar-15

005086 9-Dec-14

036422 25-Mar-15

25/0 to 25/1

NARESHBHAI GANDABHAI NAYI

SHERGANJ 15/2 036425 25-Mar-15 8400

INDUBEN GANDABHAI NAYI SHERGANJ 15/2 036426 25-Mar-15 9800

BABUBHAI VAGHABHAI NAYI SHERGANJ 15/3 036430 25-Mar-15 8400

25/1 SENDHABHAI KARAMSHI RABARI

KOLAPUR 28P3

225 23-Oct-13 15000

226 23-Oct-13 15000

036403 25-Mar-15 30000

0

036404 25-Mar-15 15000

030405 25-Mar-15 15000

25/1 to 25/2

ADESINGJI VAGAJIBHAI GOHEL

KOLAPUR 29P2 005598 26-Feb-15 10000

29P1 036409 25-Mar-15 7500

MADARSING VAGHJIBHAI GOHIL

SHERGANJ 29P2 038713 16-Apr-15 7500

KAMABHAI KARSANBHAI CHAUDHARY

SHERGANJ 37 036443 25-Mar-15 10230

25/2 VARJANG MAVJIBHAI THAKOR KOLAPUR 32

223 23-Oct-13 15000

224 23-Oct-13 15000

005602 26-Feb-15 15000

005603 26-Feb-15 11000

25/3 SATABHAI SAGRAMBHAI RABARI

KOLAPUR 97P

242 28-Oct-13 15000

222 23-Oct-13 15000

036406 25-Mar-15 20000

20000

036407 25-Mar-15 15000

036408 25-Mar-15 10000

25/3 to 25/4

MERAMBHAI RANABHAI RABARI

SHERGANJ 39P2 005592 26-Feb-15 4950

005593 26-Feb-15 3000

PACHANBHAI VIRABHAI THAKOR

KOLAPUR 86 005601 26-Feb-15 8400

KAMUEN DAYABHAI THAKOR KOLAPUR 39P3 005606 26-Feb-15 7350

MANABHAI RAMSIBHAI THAKOR

KOLAPUR 86P 005607 26-Feb-15 6300

Page 137: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 137

25/4 KAMUBEN CHHAGANBHAI THAKOR

KOLAPUR 86P

221 23-Oct-13 15000

241 28-Oct-13 15000

005605 26-Feb-15 15000

6300

25/4 to 25/5

VASANTHBHAI RUGNATHBHAI THAKOR

PORANA 195 005620 26-Feb-15 5125

GALALBHAI SENDHABHAI THAKOR

KOLAPUR 27/4 005594 26-Feb-15 18300

MEVABHAI SAVSIBHAI THAKOR

KOLAPUR 86P 005595 26-Feb-15 8400

CHHOTABHAI VIRABHAI THAKOR

KOLAPUR 86P 005604 26-Feb-15 14400

25/5

MANABHAI DUDABHAI THAKOR

PORANA 194

005175 26-Dec-14 40000

0

005622 26-Feb-15 20000

4400

VASANTHKUMAR R THAKOR PORANA 194 005174 26-Dec-14 5000

25/6 SUNDAJI VIRAJI THAKOR PORANA 184

005083 9-Dec-14 20000

15000

005599 26-Feb-15 20000

005600 26-Feb-15 15000

25/6 to 25/7

NAGJIBHAI AMARATBHAI BHARVAD

PORANA 158 005609 26-Feb-15 5000

PETHABHAI HARJIBHAI PATEL PORANA 183/2 005618 26-Feb-15 6000

NANAJIBHAI BHAGVANBHAI KANABI

PORANA 73 005619 26-Feb-15 7320

HENGABHAI AMARABHAI BHARWAD

PORANA 145 005597 26-Feb-15 12080

SENDHABHAI AMARATBHAI BHARVAD

PORANA 151PA 005608 26-Feb-15 5000

25/7 MAVJIBHAI VIRABHAI CHAUDHARY

PORANA 187

005171 26-Dec-14 15000

15000

005173 26-Dec-14 20000

005172 26-Dec-14 30000

0

25/7 to 25/8 VIRABHAI BHAGVANBHAI PATEL

PORANA 127 036402 25-Mar-15 20000

25/8 VERSIBHAI VIHABHAI THAKOR ALAHABAD 156

271 18-Nov-13 15000

272 18-Nov-13 15000

005615 26-Feb-15 25000

0

005617 26-Feb-15 10000

25/8 to 25/9

VASHRAM BHEMBHAI THAKOR PORANA 155 005625 26-Feb-15 5500

BHAGABHAI BHIJALBHAI BHARVAD

PORANA 51/1B 005596 26-Feb-15 17425

25/9 RAMABHAI KARSHANBHAI BHARVAD

PORANA 152

269 18-Nov-13 15000

270 18-Nov-13 15000

005587 26-Feb-15 20000

005588 26-Feb-15 10000

25/9 to 25/10

SOMABHAI DHARAMSIBHAI SUTHAR

ALAHABAD 82P1 005623 26-Feb-15 4900

KANJIBHAI DHARAMSHIBHAI SUTHAR

ALAHABAD 82P2 005624 26-Feb-15 4500

MULABHAI BHIJALBHAI BHARWAD

ALAHABAD 83 005578 26-Feb-15 12810

25/10

AJIBEN MOHANBHAI SOLANKI ALAHABAD 81P3

268 18-Nov-13

60000 374182 7-Mar-14

'036411 25-Mar-15

RAMESHBHAI PETHABHAI CHAUDHARY

ALAHABAD 81P3 036412 25-Mar-15 25000

25/10 to 25/11

GANDABHAI NARASANGBHAI PATEL

ALAHABAD 78 005591 26-Feb-15 9900

PETHABHAI HARJIBHAI CHAUDHARY

ALAHABAD 68P1 036417 25-Mar-15 30000

25/11 REVABEN VIHABHAI CHAUDHARY

ALAHABAD 49

267 18-Nov-13

80000 005075 9-Dec-14

036415 25-Mar-15

036416 25-Mar-15

25/11 to 25/12

DHARAMSHIBHAI AMTHABHAI PRAJAPATHI

ALAHABAD 63P1 005611 26-Feb-15 10065

VALABHAI AMTHABHAI ALAHABAD 59 005614 26-Feb-15 11000

Page 138: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 138

PRAJAPATHI

25/12

PABABHAI KAMABHAI PATEL

ALAHABAD

62/1P

005178 26-Dec-14 30000

0

005179 26-Dec-14 30000

0

005613 26-Feb-15 4075

SHANKARBHAI VAJABHAI PRAJAPATHI

63P2 005183 26-Dec-14 5000

DHARAMSHIBHAI AMTHABHAI PRAJAPATHI

63P1 005185 26-Dec-14 5000

25/13 JIVANBHAI KAMABHAI PATEL ALAHABAD 62/2

005180 26-Dec-14 30000

0

005612 26-Feb-15 19500

005181 26-12-2014 30000

0

25/14 BHAVABHAI AMTHABHAI PATEL

ALAHABAD 18

374603 24-Jul-14 20000

004922 14-Nov-14 15000

036413 25-Mar-15 32200

0

036414 25-Mar-15 7000

25/14 to 25/15

SHANKARBHAI AMTHABHAI PATEL

ALAHABAD 18P 005610 26-Feb-15 17550

JITHABHAI MEMABHAI PATEL ALAHABAD 20P1 005621 26-Feb-15 15600

25/15 LAKSMANBHAI AJUBHAI CHAUDHARY

ALAHABAD 20P2

005182 26-Dec-14 15000

15000

005186 26-Dec-14 30000

0

005585 26-Feb-15 35000

005586 26-Feb-15 25000

25/15 to 25/16

NARMADABEN HARGOVANBHAI JOSHI

ALAHABAD 21 005584 26-Feb-15 19280

TEJABHAI HARJIBHAI CHAUDHARY

ALAHABAD 19-Jan 036410 25-Mar-15 3400

25/16

VALABHAI KARAMSHIBHAI CHAUDHARY

ALAHABAD 26

374602 24-Jul-14 15000

NATHABHAI VALABHAI PATEL

005080 9-Dec-14 15000

005582 26-Feb-15 25000

005583 26-Feb-15 17050

0

25/17 JAGUBHAI LALABHAI PRAJAPATHI

ARJANSAR 26/4

266 18-Nov-13

40000 004936 14-Nov-14

45615 17-Aug-15

25/17 to 25/18

RAMESHBHAI PARSHOTTAMBHAI PANCHAL

ARJANSAR 28 005635 26-Feb-15 8150

PABABHAI MAVABHAI PATEL ARJANSAR 31P1 036420 25-Mar-15 5700

25/18 KARSHANBHAI MAVABHAI PATEL

ARJANSAR 31P1

219 23-Oct-13 15000

220 23-Oct-13 15000

005432 10-Feb-15

60000

0

0

005433 10-Feb-15 20000

25/18 to 25/19

AJUBHAI MEMABHAI PATEL ARJANSAR 32/2 005626 26-Feb-15 10500

JAYANTIBHAI AJUBHAI CHADHARY

ARJANSAR 66 005628 26-Feb-15 5000

RAMJIBHAI VASHRAMBHAI PANCHAL

ARJANSAR 32/1 044550 6-Jul-15 10740

SOMABHAI DEVABHAI PATEL ARJANSAR 42 005580 26-Feb-15 8880

25/19

PABABHAI VELABHAI

ARJANSAR 43P

217 23-Oct-13 30000

218 23-Oct-13

BHAVABHAI AJUBHAI PATEL 005629 26-Feb-15 15000

005630 26-Feb-15 9000

25/19 to 25/20

GANESHBHAI CHELABHAI PATEL

ARJANSAR 47/2 005631 26-Feb-15 9600

REVABHAI CHELABHAI PATEL ARJANSAR 47/1 005632 26-Feb-15 14400

HIRABHAI LALJIBHAI PATEL ARJANSAR 49/1 005633 26-Feb-15 2400

25/20 VIHABHAI JIVABHAI PATEL ARJANSAR 62/2

215 23-Oct-13 15000

216 23-Oct-13 15000

005579 26-Feb-15 15000

8500

Page 139: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 139

25/20 to 26/0

NARANBHAI AJUBHAI CHAUDHARY

ARJANSAR 46/2 005636 26-Feb-15 7200

NARANBHAI VALABHAI CHAUDHARY

ARJANSAR 261/1P1 036418 25-Mar-15 17000

JASHIBEN MEMABHAI PATEL ARJANSAR 59 044551 6-Jul-15 9600

NARANBHAI VALABHAI CHAUDHARY

ARJANSAR 79/6 036419 25-Mar-15 17000

26/0 KAMABHAI DUNGARBHAI PATEL

ARJANSAR 60P2

4917 14-Nov-14

60000

0

0

004998 17-Nov-14 20000

005125 19-Dec-14 20000

0

26/0 to 26/1

NARANBHAI AJUBHAI CHAUDHARY

ARJANSAR 46/1 005115 19-Dec-14 6000

KARSHANDAS BHAJARANGDAS SADHU

ARJANSAR 57 45605 17-08-2015 6000

SHANTILAL PARMABHAI SOLANKI

ARJANSAR 58/1 005116 19-Dec-14

12000 005581 26-Feb-15

26/1 SEVADAS BHAJARANGDAS SADHU

ARJANSAR 57P1

233 23-Oct-13 15000

265 18-Nov-13 15000

005120 19-Dec-14 15000

26/1 to 26/2

NARSINH T THAKOR ARJANSAR 57P1 005108 19-Dec-14 10400

MAFAJI D THAKOR ARJANSAR 79/5/5P10 005129 19-Dec-14 5000

DEVSIBHAI G THAKOR ARJANSAR 79/5/5P10 005130 19-Dec-14 7000

26/2 HARKHABHAI P CHAUDHARY ARJANSAR 79/5/5P15

231 23-Oct-13 15000

232 23-Oct-13 15000

005634 26-Feb-15 15000

005122 19-Dec-14 15000

26/2 to 26/3 ARJANBHAI M RABARI ARJANSAR 165 005104 26-Dec-14 3000

26/2 to 26/3 KARSHANBHAI M PATEL ARJANSAR 79/5/5P14 005109 19-Dec-14 9700

RUPABHAI V RABARI ARJANSAR 152 005112 19-Dec-14 6000

26/3 MANAJI H THAKOR ARJANSAR 149

60 2-Aug-13

30000 346 16-Dec-13

005121 19-Dec-14

26/3 to 26/4 PRABHUBHAI D NAYI ARJANSAR 149 005111 19-Dec-14 11500

DAZABHAI O PATEL ARJANSAR 164/1P2 005117 19-Dec-14 7600

26/4 JEMABHAI V PATEL ARJANSAR 164/2

58 2-Aug-13 15000

264 18-Nov-13 15000

005119 19-Dec-14 15000

005118 19-Dec-14 14000

26/4 to 26/5

LEBUBHAI L THAKOR ARJANSAR 169/1 005102 26-Dec-14 8600

DALCHABHAI M NAYI ARJANSAR 166 005110 19-Dec-14 13500

JAGMALBHAI K KANABI ARJANSAR 171 005113 19-Dec-14 3000

DALACHHABHAUI MOHANBHAI NAI

ARJANSAR 166 044557 6-Jul-15 7500

SHAKUBEN K PATEL ARJANSAR 171 005114 19-Dec-14 3000

26/5 SOMABHAI V THAKOR ARJANSAR 173

59 2-Aug-13 15000

200 22-Oct-13 15000

005123 19-Dec-14 15000

005124 19-Dec-14 15000

005627 26-Feb-15 5000

26/6 REVABEN R CHAUDHARY ARJANSAR 224

57 2-Aug-13

56500

201 22-Oct-13

004710 12-Sep-14

005105 19-Dec-14

26/6 to 26/7 LILAJI K THAKOR ARJANSAR 227 005107 19-Dec-14 18500

26/7 NAGJIBHAI KALABHI RABARI ARJANSAR 229

61 2-Aug-13 15000

263 18-Nov-13 15000

004708 12-Sep-14 15000

45604 17-08-2015 10000

26/7 to 26/8 BALWANTHJI C THAKOR ARJANSAR 231 005106 19-Dec-14 8000

26/8 BABABHAI M SOLANKI ARJANSAR 232

62 2-Aug-13

60000 262 18-Nov-13

004707 12-Sep-14

005128 19-Dec-14

26/8 to 26/9 VIRANBEN K PATEL ARJANSAR 296P3 004706 12-Sep-14 10250

005103 26-Dec-14 10000

26/9 VASANTHBHAI AMARATBHAI TATIYANA 360P3 212 22-Oct-13 15000

Page 140: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 140

THAKKAR 261 18-Nov-13 15000

005127 19-Dec-14 15000

005575 26-Feb-15 15000

26/10 BHAVABHAI PARMABHAI PATEL

TATIYANA 354

65 3-Aug-13 15000

199 22-Oct-13 15000

004705 12-Sep-14 15000

26/10 to 26/11

BHUDARJI SHIVAJI DHANDHANIYA

TATIYANA 366P1, 65 005207 26-Dec-14 8600

26/11 MANAJI VIHAJI THAKOR TATIYANA 351

63 2-Aug-13

51000 64 3-Aug-13

004703 12-Sep-14

004704 12-Sep-14

26/12 SHANKARJI MOHANJI THAKOR TATIYANA 295P1

355 16-Dec-13

49700 374092 26-Feb-14

004701 12-Sep-14

004702 12-Sep-14

27/0

JASALIYA CHHOTABHAI REVABHAI

TATIYANA 227P2

234 23-Oct-13 7500

4465 15-Jul-14 16931

0

4466 15-Jul-14 5569

JIVANJI DHULAJI THAKOR TATIYANA 227P1

235 23-Oct-13 7500

0

004471 15-Jul-14 14512

27/0 to 27/1

JIVANJI DHULAJI THAKOR TATIYANA 227P1 4470 15-Jul-14 8000

ASWINKUMAR KIRTHILAL SHAH

TATIYANA 296 004700 12-Sep-14 5000

27/1 OKHABHAI RAJABHAI BHANGARA

TATIYANA 218

354 16-Dec-14

60000 374090 26-Feb-14

004698 12-Sep-14

004699 12-Sep-14

27/1 to 27/2

MEVABHAI RAMJIBHAI BHANGARA

TATIYANA 177/P2 044545 6-Jul-15 12080

ASHWINKUMAR KIRTILAL SHAH

TATIYANA 296 044547 6-Jul-15 6000

MAHADEVBHAI KARSHANBHAI RABARI

TATIYANA 205 044549 6-Jul-15 13020

27/2 LEBHABHAI MEVABHAI RABARI

TATIYANA 180P1

210 22-Oct-13

45000 211 22-Oct-13

004697 12-Sep-14

28/0

PANCHAJI KARAMSHIJI KHAKHALECHA

TATIYANA 173P1

208 22-Oct-13

7750 209 22-Oct-13

004670 12-Sep-14

HARCHANDJI DEVSIJI JASALIYA

TATIYANA 181P

206 22-Oct-13

7750 207 22-Oct-13

004695 12-Sep-14

LILABHAI RAJABHI RABARI TATIYANA 170

204 22-Oct-13

17500 205 22-Oct-13

004696 12-Sep-14

28/0 to 28/1

GANDABHAI RAMABHAI CHARKATA

TATIYANA 171P1 004679 12-Sep-14 7500

JAVANBEN KARSHANBHAI CHARAKTA

TATIYANA 1004/2 038598 18-Apr-15 25000

28/1

SHANKARBHAI KARSHANBHAI DESAI

TATIYANA 1004/2/3/4/5

0

0

MANABEN SHANKARBHAI CHARAKTA

038593 18-Apr-15 25000

SHANKARBHAI KARSHANBHAI DESAI

004472 15-Jul-14 66000

004473 15-Jul-14 8400

004474 15-Jul-14 45600

28/2 BALDEVBHAI JESUNBHAI RABARI

PADAR 1000

203 22-Oct-13 15000

260 18-Nov-13 15000

044540 6-Jul-15 15000

10000

28/3 BHALABHAI RAJABHAI RABARI TATIYANA 844P

56 2-Aug-13 15000

273 18-Nov-13 15000

044546 6-Jul-15 15000

10000

28/4 RANIBEN VERSHIJI THAKOR TATIYANA 849/2

119 25-Sep-13

38000 118 25-Sep-13

004694 12-Sep-14

Page 141: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 141

044555 6-Jul-15

28/4 to 28/5 JAYANTHIJI HIRAJI KHAKHLECHA

TATIYANA 190P1 004693 12-Sep-14 12000

28/5 BHIMABHAI GANESHBHAI CHAUDHARY

SAVPURA 41

52 2-Aug-13 15000

53 2-Aug-13 15000

004692 12-Sep-14 15000

044544 6-Jul-15 8000

28/5 to 28/6 SOMAJI K CHOTAJI TATIYANA 1005 004680 12-Sep-14 9000

28/6

0

0

0

28/6 to 28/7

SUKHDEVBHAI PANCHAJI RANERA

TATIYANA 25/2 004689 12-Sep-14 8000

VINAJI CHATURJI SABOSANA SAVPURA 37P1 038602 18-Apr-15 10000

28/7 KAILASHBEN RAMNIKLAL SHAH

SAVPURA 37P2

50 2-Aug-13 15000

51 2-Aug-13 15000

45617 17-Aug-15 15000

9000

28/7 to 28/8

SHAMPUJI PUNAJI SABOSANA SAVPURA 36P1 004688 12-Sep-14 12000

PUNAJI RAVAJI THAKOR SAVPURA 36P6 004690 12-Sep-14 8600

SANTHAJI SANGRAMJI THAKOR

SAVPURA 22P4 004691 12-Sep-14 8600

MANASUNGJI RAVAJI SABOSANA

SAVPURA 51P2 038590 18-Apr-15 8000

28/8 JOGAJI RAVAJI THAKOR SAVPURA 35P2P2

227 23-Oct-13 15000

228 23-Oct-13 15000

004687 12-Sep-14 15000

004686 12-Sep-14 25000

28/8 to 29/0

MADHIBEN B SOBASANA SAVPURA 33p7 004683 12-Sep-14 7750

RAMESHJI A SOBASANA SAVPURA 35P1 004685 12-Sep-14 10250

RAJUJI SAMGRAMJI THAKOR SAVPURA 34 004684 12-Sep-14 7500

29/0 SAVSIJI JETHAJI THAKOR SAVPURA 33P6

49 2-Aug-13

60000

198 22-Oct-13

038594 18-Apr-15

038595 18-Apr-15

004682 12-Sep-14

29/0 to 29/1 ISWARJI BAJUJI THAKOR SAVPURA 31P3 004678 12-Sep-14 12000

VINAJI BAJUJI THAKOR SAVPURA 32P3 004681 12-Sep-14 10000

29/1 PANCHABHAI SURABHAI RAVAL

SAVPURA 29P/4

48 2-Aug-13

38000 197 22-Oct-13

044554 6-Jul-15

29/1 to 29/2 NARKHANJI SARTANJI THAKOR

SAVPURA 33P5 038601 18-Apr-15 7500

29/2 SHANKARJI SAGRAMJI THAKOR

SAVPURA 26P1, 26P4

47 2-Aug-13 15000

196 22-Oct-13 15000

004677 12-Sep-14 15000

29/3 BHAGVANJI RAJUJI THAKOR SAVPURA 22P/2

45 2-Aug-13

30000 46 2-Aug-13

004676 12-Sep-14

29/4 VINAJI HAJURJI THAKOR SAVPURA 15P3/P1

44 2-Aug-13 15000

195 22-Oct-13 15000

004675 12-Sep-14 15000

29/4 to 30/0 RAJESHKUMAR BHAILALBHAI SONEE

SAVPURA 17 004673 12-Sep-14 8500

29/4 to 30/0 BHAILALBHAI SANTHIBHAI SONEE

SAVPURA 15P3P1 004674 12-Sep-14 7500

30/0

RAGHUJI HAJURJI TAKOR BHALGAM

46/2

43 2-Aug-13 3750

194 22-Oct-13 3750

KESHAJI RAYCHANDJI SABOSANA

BHALGAM 038599 18-Apr-15 10000

038600 18-Apr-15 5000

BHARATSINH JIVUBA VAGHELA

BHALGAM 49

42 2-Aug-13 11250

004671 12-Sep-14 15000

004672 41894 30000

0

038592 18-04-2015 15000

038591 18-04-2015 25000

31/0 CHHATRAJI VISAJI THAKOR KARSHANPUR

A 90

374344 5-Apr-14 20000

374345 5-Apr-14 20000

990871 5-Jul-14 25000

Page 142: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 142

31/1

FOJALAL OKHALAL BABARIYA KARSHANPUR

A 57

40 2-Aug-13 7500

374288 31-Mar-14 7500

374539 5-Jul-14 7500

FALGUNI ANKITKUMAR SHAH KARSHANPUR

A 59

20705 24-Apr-14 7500

20706 24-Apr-14 7500

374565 5-Jul-14 7500

31/2 VARADLAL AATMARAM KOTAK KARSHANPUR

A 47

39 2-Aug-13 15000

374289 31-Mar-14 15000

374540 5-Jul-14 15000

31/3 PACHABHAI SODABHAI RABARI

ANANDPURA 19P2

282 18-Nov-13 15000

283 18-Nov-13 15000

374541 5-Jul-14 15000

31/4 SANUBHA PRABHATSINH THAKOR

KARSHANPURA

18P1

37 1-Aug-13 15000

284 18-Nov-13 15000

374542 5-Jul-14 15000

32/0

SHAH VELCHAND CHHOTALAL ANANDPURA 121P1

35 1-Aug-13 3750

274 18-Nov-13 3750

374544 5-Jul-14 3750

BABABHAI KHODABHAI BHATAKIYA

ANANDPURA 122P1

36 1-Aug-13 11250

275 18-Nov-13 11250

374543 5-Jul-14 11250

32/0 to 32/1 BALVATJI TEJAJI THAKOR ANANDPURA 96P1 044558 6-Jul-15 15000

32/1 JOYTAJI MAFAJI LOTIYA ANANDPURA

89P1

34 1-Aug-13

61300

33 1-Aug-13

038732 16-Apr-15

114P1 038739 16-Apr-15

89P1 038733 16-Apr-15

32/2

BECHARJI SANKARJI BHATKIYA

ANANDPURA 100

229 1-Aug-13 30000

230 23-Oct-13

BECHARJI SANKARJI SOLANKI 038734 16-Apr-15 15000

038735 16-Apr-15 12600

32/3 ANANDPURA GRAMPANCHAYAT

ANANDPURA

0

0

0

32/4

CHATURJI LAKHMAN BHATKIYA

ANANDPURA 5/1

30 1-Aug-13 30000

29 1-Aug-13

SOLANKI CHANDUJI CHATURJI 038728 16-Apr-15 15000

038729 16-Apr-15 7700

32/4 to 32/5 DAYABHAI GEMARBHAI BHATKIYA

ANANDPURA 42P1 038737 16-Apr-15 9300

32/5 TEJAJI NANJI BHATKIYA ANANDPURA 41

27 1-Aug-13 15000

28 1-Aug-13 15000

038730 16-Apr-15 15000

038731 16-Apr-15 4700

32/5 to 33/0

GORADHANBHAI PUNABHAI PRAJAPATHI

ANANDPURA 36P3 038736 16-Apr-15 10200

DHARAMSIBHAI PUNABHAI MEHRIYA

ANANDPURA 36P2 038738 16-Apr-15 8500

33/0

HIRABHAI RAMJIBHAI PRAJAPATI

ANANDPURA 36P1

26 1-Aug-13 30000

192 22-Oct-13

HIRABHAI RAMJIBHAI MEHRIYA

038740 16-Apr-15 30000

038741 16-Apr-15 8500

33/1 SAGANJI MAVAJI THAKOR / GRAM Panchyat

ODHA

24 1-Aug-13 15000

0

0

33/1 to 33/2 BHUDARJI C SOMANIYA ODHA 16, 17 4367 2-Jul-14 6800

NEMABHAI K THARECHA ODHA 18, 19 4368 2-Jul-14 8000

33/2 SAVSIJI KHETAJI THAKOR ODHA 35P1

22 1-Aug-13 15000

23 1-Aug-13 15000

0

33/2 to 33/3 RAMANBHAI B VAGHRI ODHA 42 4370 2-Jul-14 7500

SAVSIJI K THARECHA ODHA 35P1 4371 2-Jul-14 6600

33/3 SAVABHAI KALABHAI BHANGI ODHA 41

20 1-Aug-13 15000

0

0

33/3 to 33/4

SADIKBHAI N GHIA ODHA 41 4369 2-Jul-14 6600

ASGHARBHAI N GHIA ODHA 40, 60, 38P1P1

4372 2-Jul-14 16000

33/4 DHARSIJI NANAJI THAKOR ODHA 70 18 1-Aug-13 50600

Page 143: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 143

19 1-Aug-13

044542 07-06-2015

33A/0 BHEMAJI R SONETHA ODHA 62

17 1-Aug-13

54998 191 1-Aug-13

4392 2-Jul-14

84 4393 2-Jul-14

33A/0 to 33A/1

ARJANBHAI H KANKRECHA ODHA 63P1 4391 2-Jul-14 12000

33A/1 SAGANJI AMTHAJI THAKOR / GRAM PANCHYAT

ODHA 88

3 23-Jul-13 15000

0

0

33A/1 to 33A/2

DINESHJI H KAKRECHA ODHA 99 4390 2-Jul-14 12000

33A/2 ODHA GRAMPANCHAYAT ODHA

0

0

0

33A/2 to 34/0

CHHAGANBHAI AMTHABHAI DHANDHOH

ODHA 87 4373 2-Jul-14 12500

NAJMUDIN A GHIYA ODHA 86 4374 2-Jul-14 10000

ODHA 86 45618 17-Aug-15 15000

CHHAGANJI A GHANGHOS ODHA 87 044565 6-Jul-15 12500

IDRISHBHAI ABBASHBHAI GHIYA

ODHA 86 4375 2-Jul-14 12000

34/0 ABBASBHAI HASANBHAI VORA ODHA 86

2 23-Jul-13 15000

190 22-Oct-13 15000

0

34/1 AJITBHAI VALIBHAI MALAKANI TOTANA 97P2

76 5-Aug-13 15000

189 22-Oct-13 15000

4386 2-Jul-14 15000

35/0 LAXMANBHAI J PATNI TOTANA 71P1

610800 23-Jul-13 15000

188 22-Oct-13 15000

4385 2-Jul-14 20000

044559 6-Jul-15 20000

35/0 to 35/1 HIRABHAI P SOOTHAR TOTANA 48P1 4384 2-Jul-14 13000

35/1 VELAJI PACHAJI THAKOR T OTANA 48P2

610799 23-Jul-13 15000

14 1-Aug-13 15000

4383 2-Jul-14 15000

35/1 to 35/2

MOBATJI H UNECHA TOTANA 43P1, P3 4380 2-Jul-14 1500

DHARASIJI HARIJI UNECHA TOTANA 43P1P1 4381 2-Jul-14 2500

PRADHANJI B UNECHA TOTANA 43P1 4382 2-Jul-14 2500

TARASANGJI HARIBHAI UNECHA

TOTANA 44 4387 2-Jul-14 7200

35/2 JORAJI HARIJI THAKOR TOTANA 43P1P2

610798 23-Jul-13

57500 610797 23-Jul-13

044560 6-Jul-15

4398 2-Jul-14

35/2 to 35/3 JAMABHAI B BARVAD TOTANA 42P3, 42P1 4379 2-Jul-14 16000

35/3 HAIDARBHAI RASULJI MODH TOTANA 6

15 1-Aug-13

55000 610796 23-Jul-13

45619 17-Aug-15

35/3 to 35/4 SARDARJI H MAKVANA TOTANA 12 4378 2-Jul-14 12500

PARAGBHAI V SUTHAR TOTANA 15 4399 2-Jul-14 3000

35/4 SARDARJI HARIJI THAKOR TOTANA 12

72 5-Aug-13 15000

73 5-Aug-13 15000

45620 17-Aug-15 15000

10000

35/4 to 35/5 PARAGBHAI V SUTHAR TOTANA 444 4396 2-Jul-14 14000

35/5 PRAGJIBHAI VIRAMJIBHAI SUTHAR

TOTANA 444

610793 23-Jul-13 15000

610792 23-Jul-13 15000

45621 17-Aug-15 15000

35/5 to 35/6 BABUBHAI K PARMAR TOTANA 417P1, 445 4377 2-Jul-14 9000

NARANBHAI R BHARVAD TOTANA 425 4397 2-Jul-14 7000

35/6 MADHABHAI SAGTHABHAI BHARWAD

TOTANA 427

74 5-Aug-13

55000 75 5-Aug-13

45622 17-Aug-15

35/6 to 36/0 BABUBHAI K PARMAR TOTANA 130 4376 2-Jul-14 17300

Page 144: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 144

36/0 MALABHAI R MAGUNDA TOTANA 419P1

610789 23-Jul-13 15000

374547 5-Jul-14 15000

4241 6-Jun-14 8300

36/1 KUBERDAS D THAKOR TOTANA 408P1

610787 23-Jul-13 15000

610788 23-Jul-13 15000

4242 6-Jun-14 10000

SAVEETHABEN K THAKKAR TOTANA 408P1 005331 21-Jan-15 15000

36/1 to 36/2 PARAGJI B BALODHANA TOTANA 87 4345 2-Jul-14 13000

36/2

0

0

0

36/2 to 36/3 JAVANJI PUNAJI THAKOR TOTANA 66 4341 2-Jul-14 12000

JANIJI P THAKOR TOTANA 110 4342 2-Jul-14 12000

36/3

0

0

0

36/3 to 36/4 NAVINBHAI F SHAH TOTANA 112 4339 2-Jul-14 15000

NAMAJI L GHANGHOH TOTANA 111 4340 2-Jul-14 4000

36/4

0

0

0

37/0

0

0

0

38/0

0

0

0

38/1

0

0

0

38/1 to 38/2 PRATAPJI TAKHAJI SOLANKI MOTA

JAMPUR 230 4243 6-Jun-14 15000

38/2

0

0

0

38/3 JESABHAI MEVABHAI RAVAL KASARA 188/A/1 P

6P1

610786 23-Jul-13

45000 67 3-Aug-13

45623 17-Aug-15

38/4 MAVJIBHAI RAVABHAI RAVAL KASARA 188/A/1 P 9

610785 23-Jul-13

45000 66 3-Aug-13

45624 17-Aug-15

38/5 JAYENDRA A PATEL KASARA 190P4

610784 23-Jul-13 15000

610783 23-Jul-13 15000

4239 6-Jun-14 12000

38/5 to 38/6 GANGABEN A PATEL KASARA 190P1 4240 6-Jun-14 12000

38/6 GOVINDBHAI MOTIBHAI JOSHI KASARA 163

610781 23-Jul-13 15000

610782 23-Jul-13 15000

45625 17-Aug-15 15000

38/7 DEVCHAND GOVINDBHAI JOSHI

KASARA 161/1 P 9

610779 23-Jul-13 15000

610780 23-Jul-13 15000

45626 17-Aug-15 15000

38/8 HUSAINKHAN C BLOCH KASARA 150P3

610772 22-Jul-13 15000

70 3-Aug-13 15000

45627 17-Aug-15 15000

150P2 4238 6-Jun-14 10000

38A/0 BABUPURI DEVPURI GAUSWAMI

KASARA 142P2

610771 22-Jul-13

65000 276 18-Nov-13

038751 16-Apr-15

038752 16-Apr-15

38A/0 to 38A/1

VIRAMPURI DEVPURI GAUSWAMI

KASARA 149P2 4343 2-Jul-14 15000

REVABEN VIRAMBHAI CHAUDHARI

KASARA 15P1 038753 16-Apr-15 18000

BAVA B GAUSWAMI KASARA 142P1 4344 2-Jul-14 15000

38A/1 CHAUDHARI KUBERBHAI RAMBHAI

KASARA 126/1

610770 22-Jul-13 15000

69 3-Aug-13 15000

038754 16-Apr-15 15000

038755 16-Apr-15 17250

0

Page 145: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 145

38A/1 to 38A/2

CHAUDHARI PARMABHAI RATNABHAI

KASARA 124P1 038746 16-Apr-15 13800

38A/2 VIRAMPURI DEVPURI GAUSWAMI

KASARA 120

610769 22-Jul-13 15000

68 3-Aug-13 15000

038749 16-Apr-15 15000

038748 16-Apr-15 10000

038750 16-Apr-15 9300

38A/2 to 38A/3

BHAGVANBHAI RATNABHAI CHAUDHARI

KASARA 105P2 038747 16-Apr-15 12000

38A/3 SUKHDEVSINH TAKATSINH SODA

KASARA 112/1P3

005567 26-Feb-15 30000

30000

038604 18-Apr-15 43000

0

005568 26-Feb-15 30000

38A/4 SUKHDEVSINH TAKATSINH SODA

KASARA 112/1P1

005570 26-Feb-15 30000

30000

038603 18-Apr-15 43000

0

005571 26-Feb-15 30000

38A/5 DHARMAVIRSINH SUKHDEVSINH SODA

KASARA 119P1

005572 26-Feb-15 30000

30000

038605 18-Apr-15 43000

0

005573 26-Feb-15 30000

39/0 BIJOLBHAI ARAJANBHAI RABARI

DEVPURA 120/2

374256 24-Mar-14 15000

374257 24-Mar-14 15000

038757 16-Apr-15 20000

15000

39/1

0

0

0

39/2

0

0

0

39/3 RUPABHAI ARJANBHAI DESAI DEVPURA 127P1

610768 22-Jul-13 15000

278 18-Nov-13 15000

004623 9-Sep-14 15000

004624 9-Sep-14 10000

39/4 KURSEEJI BAJOOJI THAKOR DEVPURA 126P2

610767 22-Jul-13 15000

374259 24-Apr-14 15000

004625 9-Sep-14 15000

004626 9-Sep-14 6000

39/4 to 39/5 BHIJOLBHAI ARJANBHAI RABARI

DEVPURA 120/2 '038756 16-Apr-15 10000

39/5

0

0

0

40/0 LEBABHAI PUJABHAI DESAI DHANERA 85

610766 22-Jul-13

53000 279 18-Nov-13

044543 6-Jul-15

40/1 KAILASHBA INDUBA JADEJHA DHANERA 68/1

000079 5-Aug-13 15000

277 18-Nov-13 15000

004622 9-Sep-14 15000

40/1 to 40/2 TEJABHAI CHEHRABHAI DESAI DHANERA 84/2 4140 24-Apr-14 16400

40/2 JIVRAMBHAI UJAMBHAI JOSHI

SARIYAD

610764 22-Jul-13 15000

374242 24-Mar-14 15000

038623 18-Apr-15 15000

PRAHLADBHAI J JOSHI 282 4232 6-Jun-14 3800

40/3 CHAUDHARI RAMSHIBHAI DEVSHIBHAI

SARIYAD 285P1

610763 22-Jul-13 15000

374260 24-Mar-14 15000

038579 18-Apr-15 15000

40/4 SHRIRAM AMRUTBHAI JOSHI SARIYAD 463/1P1

610762 22-Jul-13 15000

374241 24-Mar-14 15000

038578 18-Apr-15 15000

40/4 to 40/5

HEMANTHKUMAR G JOSHI SARIYAD 308/1AP3 4235 6-Jun-14 3000

JIVRAMBHAI D JOSHI SARIYAD 308/1AP4 4233 6-Jun-14 5000

SANTHIBHAI JESUNGBHAI JOSHI

SARIYAD 308P1B 4454 15-Jul-14 10750

Page 146: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 146

40/5 HARDEVBHAI BHIMJIBHAI JOSHI

SARIYAD 308/P1

610761 22-Jul-13 15000

374239 24-Mar-14 15000

038620 18-Apr-15 15000

40/5 to 40/6 HARIDEVBHAI B JOSHI SARIYAD 308/1K 4234 6-Jun-14 7500

40/6 JOSHI PRAHALAD RAMSHANKAR

SARIYAD 315

610760 22-Jul-13 15000

374240 24-Mar-14 15000

038626 18-Apr-15 10000

044542 6-Jul-15 5000

40/6 to 40/7 PRAHLADBHAI R JOSHI SARIYAD 315 4228 6-Jun-14 16000

PRABHURAM K JOSHI SARIYAD 323P1 4225 6-Jun-14 6500

40/7 BHARATBHAI GOPALBHAI JOSHI

SARIYAD 321P2

610759 22-Jul-13 15000

374238 24-Mar-14 15000

038621 18-Apr-15 15000

40/7 to 40/8 MANCHIBEN B JOSHI SARIYAD 343P1 4223 6-Jun-14 9000

40/8

JOSHI ALKESHBHAI BALDEVBHAI

SARIYAD 343P1

610758 22-Jul-13 15000

374237 24-Mar-14 15000

MANCHIBEN BALDEVBHAI JOSHI

038586 18-Apr-15 15000

40/9 AMBARAMBHAI V JOSHI SARIYAD 347

610757 22-Jul-13

48600 374236 24-Mar-14

038622 18-Apr-15

004632 9-Sep-14

40/10 CHAUDHARI RAMSHIBHAI DEVSHIBHAI

SARIYAD 396

610756 22-Jul-13 15000

374332 3-Apr-14 15000

038580 18-Apr-15 15000

40/11 LAKHAMAN DHUDABHAI PANCHAL

SARIYAD 398

610755 22-Jul-13 15000

374258 24-Mar-14 15000

038582 18-Apr-15 10000

40/11 to 41/0

LAXMANBHAI D PANCHAL SARIYAD 398 4230 6-Jun-14 8500

AP41/0 DUNGARBHAI RAMABHAI CHAUDHARY

SARIYAD 402

610778 22-Jul-13 15000

374255 24-Mar-14 15000

038625 18-Apr-15 10000

4467 15-Jul-14 16477

41/1 BHARATBHAI GOPALBHAI JOSHI

SARIYAD 465P1 P

610754 22-Jul-13 15000

374254 24-Mar-14 15000

038584 18-Apr-15 15000

4000

41/1 to 41/2 HARIDEVBHAI B JOSHI SARIYAD 464/2 4227 6-Jun-14 4000

41/2

VASUDEV BHANJIBHAI JOSHI SARIYAD 463P1

610751 22-Jul-13 7500

374252 24-Mar-14 7500

038619 18-Apr-15 7500

PARBHURAM JEMABHAI JOSHI SARIYAD 457

610752 22-Jul-13 7500

374253 24-Mar-14 7500

038628 18-Apr-15 7500

41/2 to 41A/0

PRABHURAM J JOSHI SARIYAD 463/2 4224 6-Jun-14 5300

BALDEVBHAI B JOSHI SARIYAD 481/3P1 4222 6-Jun-14 5000

41A/0 LAXMIRAM S JOSHI SARIYAD 485/2

610750 22-Jul-13 15000

374380 21-Apr-14 15000

038583 18-Apr-15 15000

4236 6-Jun-14 10000

41A/0 to 41A/1

DAYABHAI D JOSHI SARIYAD 485/3 4237 6-Jun-14 5000

REVABHAI V DESAI SARIYAD 506/2 4226 6-Jun-14 5500

41A/1 REVABHAI VASIBHAI DESAI SARIYAD 506P1

610749 22-Jul-13 15000

374250 24-Mar-14 15000

038627 18-Apr-15 15000

41A/1 to 41A/2

RAMESHBHAI RAMSIBHAI DEVSIBHAI

SARIYAD 505 4231 6-Jun-14 9000

DHANIBEN L CHAUDHARY SARIYAD 535 4229 6-Jun-14 6000

41A/2 DHANIBEN LAKSHMANBHAI CHAUDHARI

SARIYAD 379

610744 20-Jul-13

45000 374249 24-Mar-14

038581 18-Apr-15

41A/3 PARMABHAI DEVABHAI CHAUDHARI

SARIYAD 545

610743 20-Jul-13 15000

374248 24-Mar-14 15000

038624 18-Apr-15 15000

42/0 RANCHHODBHAI BHIMABHAI CHAUDHARI

SARIYAD 111

610742 20-Jul-13

45000 374247 24-Mar-14

038618 18-Apr-15

42/1 MANILAL LALJIBHAI MAKVANA SARIYAD 563 610741 20-Jul-13 15000

Page 147: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 147

374246 24-Mar-14 15000

45636 17-Aug-15 15000

42/2 PUNABHAI JEMABHAI NAI SARIYAD 598/2

610740 20-Jul-13

45000 374245 24-Mar-14

038585 18-Apr-15

42/3 LAXMANBHAI GANESHBHAI CHAUDHARY

SARIYAD 603P3

610739 20-Jul-13 15000

374244 24-Mar-14 15000

038629 18-Apr-15 8000

4463 15-Jul-14 17600

42/3 to 42/4

JITHABHAI JAGMALBHAI CHAUDHARY

SARIYAD 603P1 4462 15-Jul-14 5400

KANJIBHAI VIRABHAI CHAUDHARY

SARIYAD 603P2 4464 15-Jul-14 5063

42/4 GANDAJI MADARJI THAKOR LODHI 89/13

610738 20-Jul-13 15000

374290 12-Mar-14 15000

4469 15-Jul-14 22930

42/4 to 42/5 SOMABHAI J DESAI LODHI 89/22 4468 15-Jul-14 15935

42/5 JORABHAI VASTABHAI RABARI LODHI 89/23

610737 20-Jul-13 15000

374291 31-Mar-14 15000

038610 18-Apr-15 15000

43/0 VERASHIBHAI KALYANBHAI RABARI

LODHI 89/30

610736 20-Jul-13 15000

374392 31-Mar-14 15000

4143 24-Apr-14 20000

4453 15-Jul-14 20000

43/0 to 43/1

ISHWARBHAI KHENGARBHAI RABARI

LODHI 89/35/P2 4144 24-Apr-14 2700

MEGHRAJBHAI VASIBHAI RABARI

LODHI 127 4138 24-Apr-14 4300

43/1 PANIBEN HIRABHAI CHAMAR LODHI 89/36

120 25-Sep-13

52200 374293 31-Mar-14

038609 18-Apr-15

4455 15-Jul-14

43/1 to 43/2 HARGOVANBHAI SUNDABHAI DESAI

LODHI 43 4451 15-Jul-14 4725

43/2

0

0

0

43/3 SHIVAJI KACHRAJI THAKOR / NO Owner

LODHI

610734 20-Jul-13 15000

0

0

43/3 to 43/4 REKHAJI JAHUJI THAKOR LODHI GP 4142 24-Apr-14 15000

NAGJIBHAI VSRAMBHAI RABARI

LODHI 37/1P 4139 24-Apr-14 5700

43/4

0

0

0

43/5

NAGJIBHAI VASRAMBHAI RABARI

LODHI 33/2 P

610733 20-Jul-13 15000

374294 31-Mar-14 15000

AMRUTBHAI JORABHAI RABARI

4141 24-Apr-14 5700

43/5 to 43/6 CHHAGANBHAI MALABHAI DESAI

LODHI 30P 4452 15-Jul-14 5400

43/6 PRADHANJI RAMCHANDJI THAKOR

VADIYA 9P

610732 20-Jul-13 15000

374295 31-Mar-14 15000

004834 27-Sep-14 15000

43/6 to 43/7 PRADHANJI RAMCHANDJI THAKOR

VADIYA 9P 4137 24-Apr-14 7000

43/7

DHIRAJLAL PUNAMCHAND SHAH

VADIYA 7/2

374088 26-Feb-14 15000

374089 26-Feb-14 15000

45628 17-Aug-15 15000

UMIDJI KUMARJI THAKOR LODHI 72/2 4091 4-Apr-14 8400

43/7 to 44/0

KARAMSHIBHAI KHENGARBHAI RABARI

VADIYA 71P1 4459 15-Jul-14 4050

RAVABHAI G RABARI VADIYA 71 4460 15-Jul-14 6000

44/0

SHAH PIYUSHKUMAR NATHALAL

KALONDHI 71

374185 7-Mar-14 15000

374186 7-Mar-14 15000

45629 17-Aug-15 15000

RUPABEN C RABARI VADIYA 71P2 4456 15-Jul-14 4950

44/0 to 44/1 THAKOR GAMBHIRJI VADIYA 66P1 4093 4-Apr-14 7800

THAKOR SOBHAJI VADIYA 73/2P 4092 4-Apr-14 7000

Page 148: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 148

THAKOR VADHANJI VADIYA 73/2P 4090 4-Apr-14 9000

44/1 SAVSIJI GHEMARJI THAKOR VADIYA 66P3

78 5-Aug-13

50000 374296 31-Mar-14

4458 15-Jul-14

038612 18-Apr-15

44/1 to 44/2 SHAH PIYUSHKUMAR VADIYA 53 4094 4-Apr-14 11600

44/2 CHENAJI DAJUJI THAKOR VADIYA 51/4

610730 20-Jul-13 15000

374297 31-Mar-14 15000

004833 27-Sep-14 15000

44/2 to 44/3

THAKOR PARJIJI LODHI 51/4 4097 4-Apr-14 4200

THAKOR KESAJI LODHI 51/2 P 4096 4-Apr-14 4700

THAKOR KANTIJI LODHI 51/2 P 4095 4-Apr-14 4100

MADARJI AJUJI THAKOR LODHI 51P2 4449 15-Jul-14 4000

44/3 MANJAJI ABHA JI THAKOR VADIYA 51P1

610729 20-Jul-13 15000

374298 31-Mar-14 15000

4450 15-Jul-14 15000

038613 18-Apr-15 10000

44/3 to 44/4 THAKOR GAMBHIRJI VADIYA 48P 4098 4-Apr-14 4500

SOJAJI KALUJI THAKOR VADIYA 45 4457 15-Jul-14 3974

44/4 OKHAJI KALUJI THAKOR VADIYA 45

610728 20-Jul-13 15000

374299 31-Mar-14 15000

4461 15-Jul-14 15000

038611 18-Apr-15 8000

44/5

0

0

0

45/0 VARSUNGJI RAYAJI THAKOR KALONDHI 126P1

610727 20-Jul-13 15000

374300 31-Mar-14 15000

038719 16-Apr-15 15000

45/1 RUPESHKUMAR BHOGILAL BHATKIYA

KALONDHI 129/1P

374183 7-Apr-14 15000

374184 7-Mar-14 15000

45630 17-Aug-15 15000

45/2 KANANJI MOBATJI THAKOR KALONDHI 132/P3

610725 20-Jul-13 15000

374301 31-Mar-14 15000

45631 17-Aug-15 15000

45/3 NARSANGJI KARSANJI THAKOR

SADASAN 134P2

610724 20-Jul-13 15000

374306 31-Mar-14 15000

038718 16-Apr-15 15000

45A/0 THAKOR BABUJI DHULAJI KALONDHI 89

344 16-Dec-13 15000

374333 3-Apr-14 15000

45632 17-Aug-15 15000

45B/0 VAGHAJIBHAI M RABARI MELUSAN 24 005436 10-Feb-15

30000

0

0

45B/1

HARIBHAI VASRAMBHAI RABARI

MELUSAN 20/1P2

610723 20-Jul-13

40750 374302 31-Mar-14

005437 10-Feb-15

005438 10-Feb-15

BABUBHAI K RABARI MELUSAN 17P9

374308 31-Mar-14 7500

005439 10-Feb-15 3750

005440 10-Feb-15 3500

45B/1 to 45B/2

VELABHAI C RABARI MELUSAN 12/4 005441 10-Feb-15 5500

GOVABHAI V RABARI MELUSAN 20/1P1 005442 10-Feb-15 3500

MOHANBHAI M RABARI MELUSAN 18/1P2 005443 10-Feb-15 5500

BHIKHABHAI M RABARI MELUSAN 18/1P1 005444 10-Feb-15 7000

VERSHIBHAI V RABARI MELUSAN 20/1P3 005445 10-Feb-15 3500

45B/2 GOVABHAI V RABARI MELUSAN 12/4

610722 20-Jul-13

50500 374309 31-Mar-14

005469 10-Feb-15

005470 10-Feb-15

45B/2 to 45B/3

LILUBEN J RABARI MELUSAN 7P4 005454 10-Feb-15 3000

TALJABHAI R RABARI MELUSAN 7P2 005455 10-Feb-15 3000

RAJABHAI L RABARI MELUSAN 11/3 005456 10-Feb-15 4300

KAMSHIBHAI R RABARI MELUSAN 7P5 005467 10-Feb-15 5500

MENABEN I RABARI MELUSAN 11/2 005468 10-Feb-15 4000

45B/3

JETHABHAI RATNABHAI RABARI MELUSAN 11/4

610745 20-Jul-13

15000 374310 31-Mar-14

NAGJIBHAI M RABARI 610721 20-Jul-13 25500

Page 149: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 149

374311 31-Mar-14

005452 10-Feb-14

005453 10-Feb-14

JETHABHAI R RABARI MELUSAN 7P1 005465 10-Feb-14 7500

005466 10-Feb-14 3500

46/0

VERASHIBHAI V RABARI MELUSAN 6/1P2

610718 19-Jul-13 3750

374312 31-Mar-14 3750

005457 10-Feb-14 5000

005458 10-Feb-14 4500

HARIBHAI VASRAMBHAI RABARI

MELUSAN 6/2

610719 19-Jul-13 7500

374307 31-Mar-14 7500

0

KHENGARBHAI RAMBHAI RABARI

MELUSAN 5/3 P2

610720 19-Jul-13 3750

374303 31-Mar-14 3750

45635 17-Aug-15 3750

1500

HARIBHAI V RABARI MELUSAN 6/4 005459 10-Feb-14 10000

005460 10-Feb-14 4000

46/0 to 46/1

GOVABHAI V RABARI MELUSAN 6/4 005447 10-Feb-15 5000

BABUBHAI H RABARI MELUSAN 6/2 005448 10-Feb-15 12000

GOVABHAI V RABARI MELUSAN 6/1P1 005449 10-Feb-15 5000

BABUBHAI H RABARI MELUSAN 6/3P2 005450 10-Feb-15 4000

NAVDHANBHAI H RABARI MELUSAN

6/4 005461 10-Feb-15 9300

6/2

005462 10-Feb-15 3000

005463 10-Feb-15 4000

005464 10-Feb-15 9500

46/1 DANASARA GRAMPANCHAYAT DANASARA

610717 19-Jul-13 15000

0

0

46/1 to 46/2

MAGANBHAI TEJABHAI RABRI MELUSAN 69 005434 10-Feb-15 10000

MOHANBHAI TEJABHAI RABARI

MELUSAN 69 005435 10-Feb-15 5500

KAMSHIBHAI N RABARI MELUSAN 71/2P2 005446 10-Feb-15 7000

LILABHAI M RABARI MELUSAN 71/2P2 005451 10-Feb-15 3000

46/2 DHUDABHAI B JOSHI DHANASARA 45P1

610716 19-Jul-13 15000

374304 31-Mar-14 15000

005482 10-Feb-15 15000

005481 10-Feb-15 5500

46/2 to 46/3

JIVRAMBHAI R JOSHI DHANASARA 43P1 005477 10-Feb-15 11000

KASHIRAMBHAI P JOSHI DHANASARA 44 005478 10-Feb-15 7000

PACHANBHAI G BRAHMAN DHANASARA 40P3 005479 10-Feb-15 3500

JAYARAMBHAI P JOSHI DHANASARA 44 005480 10-Feb-15 7000

DALCHABHAI S JOSHI DHANASARA 3/26 005488 10-Feb-15 7000

RAMJIBHAI P JOSHI DHANASARA 44P 005490 10-Feb-15 7000

46/3 NARMADASHANKAR B JOSHI DHANASARA 43P2

610715 19-Jul-13 15000

374305 31-Mar-14 15000

005473 10-Feb-15 25000

005472 10-Feb-15 15000

46/3 to 46/4

NANJI BHAI JIVANBHAI JOSHI DHANASARA 30/3 005471 10-Feb-15 9500

DANSUNGBHAI K JOSHI DHANASARA 51P4 005484 10-Feb-15 3000

KASHIRAMBHAI M JOSHI DHANASARA 30/2P3 005474 10-Feb-15 4000

NATWARBHAI K JOSHI DHANASARA 51P5 005489 10-Feb-15 11000

NARANBHAI S JOSHI DHANASARA 33/4P3 005491 10-Feb-15 15000

46/4 JAYANTHIBHAI R JOSHI DHANASARA 31

610714 19-Jul-13 15000

005475 10-Feb-15 15000

15000

005476 10-Feb-15 7000

46/4 to 46/5

RAMESWARBHAI T JOSHI DHANASARA 24P4 005483 10-Feb-15 8000

DILIPKUMAR H JOSHI DHANASARA 23P2 005485 10-Feb-15 7000

KANAIYALAL H JOSHI DHANASARA 23P1 005486 10-Feb-15 7000

RAMJIBHAI K JOSHI DHANASARA 32P2 005487 10-Feb-15 7500

JESUNGHBHAI D JOSHI DHARUSAN 78 005505 10-Feb-15 7500

BHOLABHAI JASUNGBHAI BHRAHMAN

DHARUSAN 78 005506 10-Feb-15 5000

PARAGBHAI D BHRAHMAN DHARUSAN 78 005507 10-Feb-15 7500

46/5 MULJIBHAI D JOSHI DHARUSAN 78 005428 10-Feb-15

60000

0

0

005431 10-Feb-15 15000

Page 150: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 150

46/5 to 47/0

NARANBHAI D JOSHI DHARUSAN 71/5/P1 005425 10-Feb-15 30000

AMARATBHAI R JOSHI DHARUSAN 75P1P2 005492 10-Feb-15 11000

VISHNUBHAI R JOSHI DHARUSAN 74P1 005493 10-Feb-15 11000

BALDEVBHAI R BRAHMAN DHARUSAN 124 005499 10-Feb-15 10000

SRIRAMBHAI R JOSHI DHARUSAN 61/1P 005500 10-Feb-15 20000

SOMABHAI M BHRAHMAN DHARUSAN 76/1P1 005502 10-Feb-15 2000

BABUBHAI M BHRAHMAN DHARUSAN 75P2 005503 10-Feb-15 2000

SHRIRAMBHAI M BHRAHMAN DHARUSAN 76/1P1 005504 10-Feb-15 3000

47/0

BHARATBHAI L JOSHI DHARUSAN 75P2

610713 19-Jul-13 3750

374337 3-Apr-14 3750

005494 10-Feb-15 20000

76/1P2 005495 10-Feb-15 12000

MANSUKHBHAI L JOSHI DHARUSAN 74/6/P1 005496 10-Feb-15 15000

038587 18-Apr-15 10000

HARIDEVBHAI RAMJIBHAI JOSHI

DHARUSAN 74/6

610711 19-Jul-13

67500 005498 10-Feb-15

005497 10-Feb-15

038588 18-Apr-15

NAGJIBHAI M JOSHI DHARUSAN 74/4

610712 19-Jul-13 3750

374336 3-Apr-14 1875

005501 10-Feb-15 15000

47/0 to 47/1

DANSUNHBHAI V JOSHI DHARUSAN 49/2/2 004921 14-Nov-14 10000

NARANBHAI DEVCHANDBHAI JOSHI

DHARUSAN 71/5/1 004893 17-Oct-14 40000

44796 17-Aug-15 32159

SRIRAMBHAI RAMJIBHAI JOSHI

DHARUSAN 61/1 004895 17-Oct-14 24000

JAGANNATHBHAI TRIKAMBHAI JOSHI

DHARUSAN 61/2 004898 17-Oct-14 21000

47/1

JAYRAM MULJIBHAI DHARUSAN 62/1 P2

610709 19-Jul-13 7500

374338 3-Apr-14 7500

44795 17-Aug-15 7500

5000

JAYANTIBHAI TRIKAMBHAI JOSHI

DHARUSAN 61/2/1

610710 19-Jul-13

45000 374339 3-Apr-14

004897 17-Oct-14

DHARUSAN 61/2/P1 005426 10-Feb-15

47/1 to 47/2

HARDEVBHAI R BRAHMAN DHARUSAN 61/1 004892 17-Oct-14 40000

44797 17-Aug-15 30000

SAHDEVBHAI RAMJIBHAI JOSHI

DHARUSAN 51 004894 17-Oct-14 35000

DAYABHAI JESUNGBHAI JOSHI

DHARUSAN 49/3/1 004896 17-Oct-14 26000

47/2

HARDEVBHAI RAMJIBHAI BRAHMAN DHARUSAN 50/1

610708 19-Jul-13 15000

374318 3-Apr-14 15000

HARDEVBHAI R JOSHI 005424 10-Feb-15 30000

47/3 RANCHODBHAI VIRBHANBHAI THAKOR

KANOSAN 48P1

610707 19-Jul-13

50000 374319 3-Apr-14

004923 14-Nov-14

47/3 to 47/4

SAHDEVJI PRADHANJI THAKOR

KANOSAN 46P3 004723 12-Sep-14 5000

AJMALJI DHIRAJI THAKOR KANOSAN 48P2 004722 12-Sep-14 5000

JOITAJI HANSHAJI THAKOR KANOSAN 46P2 004721 12-Sep-14 5000

DEVAJI MODENJI THAKOR KANOSAN 46P3 004720 12-Sep-14 10000

BHOMAJI PRATAPJI THAKOR KANOSAN 46P1 004719 12-Sep-14 5000

004718 12-Sep-14 5000

47/4 ASHOKJI JOGAJI THAKOR KANOSAN 53P1

71 5-Aug-13

45000 374320 3-Apr-14

004717 12-Sep-14

47/4 to 48/0 DINAJI CHANDANJI THAKOR KANOSAN 85/2 004716 12-Sep-14 10000

BACHUBEN GAMAJI THAKOR KANOSAN 25P1 004715 12-Sep-14 10000

48/0 MADARJI G THAKOR KANOSAN 60P2

610705 19-Jul-13 15000

374321 3-Apr-14 15000

4389 2-Jul-14 20000

48/0 to 49/0 KEDARJI GAMBHIRJI THAKOR KANOSAN 60P2 004714 12-Sep-14 20000

49/0 SAKARBHAI RADHABHAI BHANGI

KANOSAN 80

610704 19-Jul-13

50000 374322 3-Apr-14

038716 16-Apr-15

KANOSAN 80 4353 2-Jul-14

49/0 to 49/1 FULAJI C THAKOR KANOSAN 36P3 4363 2-Jul-14 5000

Page 151: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 151

49/1 DALSANGJI NAGRAJI THAKOR KANOSAN 86

610703 19-Jul-13 15000

374323 3-Apr-14 15000

038717 16-Apr-15 15000

49/1 to 49/2 DALSANGBHAI N THAKOR KANOSAN 86 4354 2-Jul-14 2300

DARGAJI H THAKOR KANOSAN 162P3, 40 4355 2-Jul-14 5000

49/2 PANCHAL RAMANLAL CHUNILAL

KANOSAN 159

374378 21-Apr-14 15000

374377 21-Apr-14 15000

038715 16-Apr-15 15000

49/2 to 49/3

PANCHAL RAMANLAL CHUNILAL

KANOSAN 159 4356 2-Jul-14 2300

FULAJI GAMAJI THAKOR KANOSAN 25P1 4357 2-Jul-14 5000

49/3 ISHVARBHAI KHODABHAI RABARI

GANESHPURA 185

610701 19-Jul-13 15000

374326 3-Apr-14 15000

038726 16-Apr-15 15000

49/3 to 49/4 ISWARBHAI K RABARI GANESHPURA 185 4358 2-Jul-14 2000

49/4 BABUBHAI SARTANBHAI DESAI

GANESHPURA 198P

610700 19-Jul-13 15000

374545 5-Jul-14 15000

038725 16-Apr-15 15000

49/4 to 49/5 BABUBHAI S RABARI GANESHPURA 198 4365 2-Jul-14 8200

UDAJI D RAJPUT GANESHPURA 253 4366 2-Jul-14 7100

49/5 UDESINH DALAJI RAJPUT GANESHPURA 253P

610699 19-Jul-13 15000

374546 5-Jul-14 15000

038722 16-Apr-15 15000

49/5 to 49/6 BARATBHAI S RABARI GANESHPURA 155P1 4359 2-Jul-14 5000

49/6 BHARATBHAI SARTANBHAI RABARI

GANESHPURA 155P1

122 25-Sep-13

45000 374327 3-Apr-14

038724 16-Apr-15

49/6 to 49/7 RAMJIBHAI R RAVAL GANESHPURA 145 4360 2-Jul-14 3600

49/7

RAMCHANDBHAI NANABHAI RAVAL

GANESHPURA 142

610697 19-Jul-13 30000

374379 21-Apr-14

RAMJIBHAI RAMCHANDBHAI RAVAL

038723 16-Apr-15 15000

49/7 to 49/8 TALJABHAI S RABARI GANESHPURA 86 4361 2-Jul-14 5500

RAMJIBHAI R RAVAL GANESHPURA 142 4364 2-Jul-14 5000

49/8 TALJABHAI SARTANBHAI RABARI

GANESHPURA 86P

610748 22-Jul-13

45000 374329 3-Apr-14

038727 16-Apr-15

50/0 SOMABHAI J RABARI GANESHPURA 79P2

459 21-Jan-14 15000

460 21-Jan-14 15000

4388 2-Jul-14 20000

4362 2-Jul-14 5100

50/1 KANJIBHAI NATHABHAI RABARI

ABLUVA 266/1P2

461 21-Jan-14 15000

462 21-Jan-14 15000

038617 18-Apr-15 15000

4445 15-Jul-14 7000

50A/0 NAGJIBHAI MAGANBHAI DARJI ABLUVA 272

330 16-Dec-13 15000

374187 7-Mar-14 15000

4431 15-Jul-14 21087

50A/1 BALWANTHJI BHAICHANDJI THAKOR

ABLUVA 285P2

331 16-Dec-13

62415 394 26-Dec-13

45633 17-Aug-15

4432 15-Jul-14

50A/1 to 50A/2

VANVIRJI R THAKOR ABLUVA 281/1/4 4433 15-Jul-14 6020

BABUJI K THAKOR ABLUVA 281/1/2 4439 15-Jul-14 4300

CHENJIJI K THAKOR ABLUVA 280/3A 4440 15-Jul-14 2688

ISWARJI M THAKOR ABLUVA 280/2/3 4441 15-Jul-14 2688

SAVDHANJI V THAKOR ABLUVA 280/2/2 4442 15-Jul-14 3763

50A/2 CHATURJI KALUJI THAKOR

ABLUVA 280/2/1

332 16-Dec-13

45000 374188 7-Mar-14

038616 18-Apr-15

CHATURJI K THAKOR 4434 15-Jul-14 7020

50A/2 to 51/0

KANJIBAHI N RABARI ABLUVA 324 4400 2-Jul-14 2500

51/0 AMRATBHAI CHEHRABHI RABARI

ABLUVA 325

333 16-Dec-13 15000

374189 7-Mar-14 15000

4443 15-Jul-14 17370

44794 17-Aug-15 10500

51/1 AMRATBHAI NATHABHAI RABARI

ABLUVA 88P1 334 16-Dec-13 15000

374190 7-Mar-14 15000

Page 152: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 152

038614 18-Apr-15 15000

4435 15-Jul-14 10965

51/2 MULIBEN VIRABHAI RABARI ABLUVA 368/1

335 16-Dec-13

45000 374191 7-Mar-14

4448 15-Jul-14

51/3 VADANJI CHUNAJI THAKOR ABLUVA 364P5

336 16-Dec-13

49719 376 26-Dec-13

4436 15-Jul-14

51/3 to 51/4 RAMIJI B THAKOR ABLUVA 368/1 4437 15-Jul-14 18168

51/4 RABARI AMRUTBHAI MAGANBHAI

ABLOVA 387/1P2

337 16-Dec-13 15000

374192 7-Mar-14 15000

038615 18-Apr-15 15000

51/4 to 51A/0

AMRATBHAI MAGANBHAI RABAI

ABLUVA 387/1P2 4438 15-Jul-14 13545

51A/0

RAHIMBHAI JAMAIBHAI MUMAN

ABLUVA 372/1P2

338 16-Dec-13 7500

374331 3-Apr-14 7500

4401 2-Jul-14 7500

HABIB DADU MUMAN ABLUVA 372/3P1

339 16-Dec-13

22500 374330 3-Apr-14

4444 15-Jul-14

51A/0 to 51B/0

VAJISINH JVIHABHAI THAKOR ABLUVA 371/1P2 004727 12-Sep-14 16000

004728 12-Sep-14 8000

51B/0 IBRAHIMBHAI ALIMADBHAI MUMAN

ABLUVA

387/5

340 16-Dec-13

70000

374340 3-Apr-14

4402 2-Jul-14

390/2 45606 17-08-2015

45607 17-08-2015

51B/0 to 51B/1

MUMAD HAMIDABEN VALIBHAI ABLUVA 372/3P2 004659 12-Sep-14 15000

DINESHBHAI AMTHABHAI RABARI

ABLUVA 386/1P1 004665 12-Sep-14 10750

KANJIBHAI AMTHABHAI RABARI

ABLUVA 387/1P3 004666 12-Sep-14 10000

51B/1 PANCHAL AMBALAL HEMCHAND

ABLOVA 373/1

342 16-Dec-13 15000

374341 3-Apr-14 15000

45634 17-Aug-15 15000

51B/2 BHARATKUMAR KANTILAL BRAHMBHATT

DELVADA 149

343 16-Dec-13 15000

374342 3-Apr-14 15000

038721 16-Apr-15 15000

51B/3 RASHMIKANT NATWARLAL BRAHMBHATT

DELVADA 148/1

463 21-Jan-14 15000

464 21-Jan-14 15000

038720 16-Apr-15 15000

52/0

RANJITKUMAR RUGHNATHBHAI BAROT

JANGRAL 497

447 21-Jan-14 10000

448 21-Jan-14 10000

004661 12-Sep-14 10500

501P2 004663 12-Sep-14 15000

BHARATKUMART RAGHNATHBHAI BAROT

JANGRAL 502

449 21-Jan-14 10000

450 21-Jan-14 10000

004664 12-Sep-14 15000

53/0

LAXMIBEN AMRUTBHAI PATEL JANGRAL 500

455 21-Jan-14

32000 456 21-Jan-14

004660 12-Sep-14

RAJENRAKUMAR MAFATLAL BHAROT

JANGRAL

495/P1 457 21-Jan-14 10000

458 21-Jan-14 10000

GHANSYAM RUGHNATHBHAI BRAHMPATT

496/2 004662 12-Sep-14 15000

RAJENDRA CHANDULAL BAROT

476P 044561 6-Jul-15 30000

56/0

BHARATKUMAR JAIDEVLAL BHAROT

JANGRAL 475

374087 26-Feb-14 10000

0

0

451 21-Jan-14 15000

452 21-Jan-14 15000

374086 26-Feb-14 15000

JAYESHBHAI JIVANLAL BAROT JANGRAL 474 038742 16/04/15

60000

0

0

0

2,08,50,382

Page 153: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 153

DETAILS OF COMPENSATION PAYMENT FOR 220KV LINE (GETCO FUNDED)

Loc.no. Name of Owner Village Survey

No. Draft No.

Date

Total Compensation

paid for all Category

Gentry GETCO s/s Charanka Gov.Land 0

1/0. Nagdanbhai Devdanbhai Gov.Land 2396 11.02.2012 38000

2/0. Gelabhai Raimalbhai Aluvash 151/7 1724

20.09.2011 13000

2/1. Aluvash 159

3/0. Karnabhai Devadanbhai Aluvash 2398 11.02.2012 38000

3/1. Aluvash Gov.Land 0

4/0. Aluvash Gov.Land 0

4/1. Babubhai Devayatbhai Aluvash 49 1841 12.11.2011 12000

2399 11.02.2012 25000

4/2. Babubhai Devayatbhai Aluvash 49 1842 12.11.2011 12000

2400 11.02.2012 25000

4/3. Ramabhai Manabhai Aluvash 54 1843 12.11.2011 12000

11.02.2012

2401 11.02.2012 25000

5/0. Ramabhai Manabhai Aluvash 55 1844 12.11.2011 12000

6/0. Ayar Naranbhai Jivabhai Patanka 407

305 29.08.2011 12000

1829 11.11.2011 13000

2062 26.12.2011 13000

6/1. Thakor Dharshibhai Shivabhai Patanka 394

306 29.08.2011 12000

1830 11.11.2011 13000

2063 26.12.2011 13000

6/2. Koli Sendhabhai Balubhai Patanka 397

307 29.08.2011 12000

1706 16.06.2011 13000

2064 26.12.2011 13000

6/3.

Jivanbhai Khimabhai

Patanka 377/1 1707 16.09.2011 25000

2394 11.02.2012 13000

6/4. Patanka 333

6/5. Devshibhai Shivabhai Patanka 371

1708 16.09.2011 12000

1831 11.11..2011 13000

2065 26.12.2011 13000

6/6. Patanka 326

7/0. Jethabhai Dayabhai Patanka 277/2/1

1709 16.09.2011 12000

1832 11.11.2011 13000

2066 26.12.2011 13000

7/1. 261

7/2. 261

8/0. Ayar Devabhai Pachanbhai Patanka 268/3

308 29.08.2011 12000

1833 11.11.2011 13000

2067 26.12.2011 13000

8/1. Ayar Nagabhai Pachanbhai Patanka 268/2

309 29.08.2011 12000

1710 16.09.2011 13000

2068 26.12.2011 13000

8/2. Ajabhai Alabhai Patanka 271/1 1834 11.11.2011 25000

2069 26.12.2011 13000

8/3.

Ramdanbhai Pratapbhai

Patanka 273/1

1711 16.092011 12000

1835 11.11.2011 13000

2070 26.12.2011 13000

8/4.

Hajabhai Akhabhai

Patanka 243/1

1712 16.09.2011 12000

Rudabhai Hajabhai 1836 11.11.2011 13000

2071 26.12.2011 13000

8/5. Ambadan Narhardan

Patanka 244 1713 16.09.2011 12000

1837 11.11.2011 13000

Page 154: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 154

2072 26.12.2011 13000

8A/0

Haridan Samaratdan

Patanka 246/2

323 19.09.2011 12000

1839 12.11.2011 13000

2073 26.12.2011 13000

8A/1

Jitudan Ravatdan

Patanka 218

1724 20.09.2011 12000

1864 17.11.2011 13000

2074 26.12.2011 13000

8A/2

Lumbhabhai Balubhai

Patanka 221/2

322 19.09.2011 12000

1865 17.11.2011 25000

2075 26.12.2011 13000

8A/3

Bhalabhai Ukabhai

Patanka 197/2

321 19.09.2011 12000

1866 17.11.2011 13000

2076 26.12.2011 13000

8B/0

Bhalabhai Hardasbhai

Patanka 196/2

320 19.09.2011 12000

2077 26.12.2011 6500

8B/0

Pachanbhai Dayabhai

195/1 1867 17.11.2011 12500

2078 26.12.2011 6500

8B/1

Hirabhai Valabhai

194 1868 17.11.2011 25000

2079 26.12.2011 13000

9/0.

Ayar Aja Pacha

185 1869 17.11.2011 25000

2118 29.12.2011 13000

9/1. Forest 185 0

0

9/2. Forest 185 0

0

10/0.

Govt Land

Sindhada

362 0

Babubhai Isabkhanbhai 381

2120 29.12.2011 38000

10/1. Rauma Dauabhai Raydhanji 363 456 03.12.2011 25000

10/2. 363

10/3. 382 & 381

10/4. 379

11/0. 421

11/1. 420

11/2. 420

12/0. 420

12/1. 401

12/2. 406

12/3. 527

12/4. 526

12/5. 523

13/0. Dharsibhai Rugnathbhai 48/1 1840 12.11.2011 7500

13A/0 Alimamadbhai Kalujibhai

75

2119 29.12.2011 44950

LILo Point 73

Hetabkhan Bhanji 53 2121 29.12.2011 38000

8A/5 & 8A/6 Laxmanbhai Vaghabhai 190/2 450 03.12.2011 7000

11/0. Karmanbhai Haribhai 421 452 03.12.2011 5690

11/1. Trikambhai Khemabhai 420 453 03.12.2011 10500

12/1. Bibiben Karimkhan 20 454 03.12.2011 3750

12/1. Hussainaben Rasulkhan 401 455 03.12.2011 3896

Trikambhai Khemabhai 2122 29.12.2011 14850

Trikambhai Khemabhai 2123 29.12.2011 13850

Rajabhai Khodabhai 2124 29.12.2011 10465

Ajabhai Alabhai 2125 29.12.2011 10465

Umedkhan Alimamad 2126 29.12.2011 7872

Jitudanbhai Ravatdanbhai 2136 31.12.2011 4575

Lumbhabhai Bhalabhai 2137 31.12.2011 9025

Page 155: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 155

Nathabhai Ranabhai 2138 31.12.2011 17000

Ranabhai bhurabhai 2139 31.12.2011 2765

Ajabhai Pachanbhai 2140 31.12.2011 9775

Bahubhai Isbtkhan 2141 31.12.2011 15000

Sedhabhai Balubhai Koli 2142 31.12.2011 15000

Nagabhai Panchanbhai 2143 31.12.2011 7625

10/0 To 10/2 Sundabhai Bhikhabhai 2180 04.01 .2012 11000

10/0 To 10/2 Hamirbhai Okhabhai 2181 04.01 .2012 3000

10/3 To 10/4 Mimjibhai Mavjibhai 2182 04.01 .2012 7200

10/4 To 11/0 Aadam Babubhai 2183 04.01 .2012 4000

10/4 To 11/0 Sundabhai Revabhai 2184 04.01 .2012 7200

11/1 To 11/2 To 12/0

Trikambhai Khembhai 2185 04.01 .2012 12000

12/1 To 12/2 Aambabhai Kumbhabhai 2186 04.01 .2012 14000

12/1 To 12/2 Bibiben Karimkhan 2187 04.01 .2012 9000

12/1 To 12/2 Isabkhan Umarkhan 2188 04.01 .2012 8000

12/1 To 12/2 Jakirbhai Rasulbhai 2189 04.01 .2012 6000

12/2 To 12/3 Kasambhai Alikhan 2190 04.01 .2012 6000

12/2 To 12/3 Kasambhai Punjabhai 2191 04.01 .2012 10000

12/3 To 12/4 Nitu Punja 2192 04.01 .2012 10000

12/3 To 12/4 Babu Pragji 2193 04.01 .2012 16000

12/3 To 12/4 Kalu Mobatkhan 2194 04.01 .2012 6000

12/3 To 12/4 Rahim Mamod 2195 04.01 .2012 9000

12/5 To 13/0 Kalubhai Pragjibhai 2196 04.01 .2012 6000

12/5 To 13/0 Karim Hamirji 2197 04.01 .2012 10000

12/5 To 13/0 Mohad Saumbha 2198 05.01.2012 4000

13/0 To 13B/0

Kadarkhan Mobatkhan 2199 05.01.2012 5000

13/0 To 13B/0

Janmmoad Haji Sulemen 2200 05.01.2012 9000

13B/0 To 13A/0

Hebatkhan Bhanji 2201 05.01.2012 7200

13/0 To 13B/0

Shankarbhai Bhojabhai 2202 05.01.2012 4000

10/4 To 11/0 Satabhai Mavjibhai 2203 05.01.2012 7000

11/0 To 11/1 Karmanbhai Haribhai 2204 05.01.2012 3000

10/3 To 10/4 Babubhai Isabkhan 2205 05.01.2012 17000

10/3 To 10/4 Maksud Isabkhan 2206 05.01.2012 14000

Rasulkhan Ranaji 583 07.01.2012 38000

Bibiben Karimkhan 582 07.01.2012 38000

Satabhai Megarajbhai 581 07.01.2012 6500

Trikam Khema 580 07.01.2012 76000

Trikam Khema 579 07.01.2012 38000

Momji Mavji 578 07.01.2012 38000

Daudbhai Raidhanji 577 07.01.2012 9500

Muzabkhan Bhanji 576 07.01.2012 18000

Hanif Isabkhan 575 07.01.2012 16000

Fejmohmdabhai Kasambhai 2225 11.01.2012 38000

13B/0. Gafurbhai Alimohmad 2224 11.01.2012 11500

12/4. Babubhai Pragjibhai 2223 11.01.2012 38000

Karmanbhai Haribhai 2222 11.01.2012 38000

Raumabhai Daoudbhai 2221 11.01.2012 13000

Thejubhai Mohmadbhai 2220 11.01.2012 38000

Dharsibhai Rugnathbhai 2219 11.01.2012 38000

Kalubhai Pragjibhai 2218 11.01.2012 38000

8A/3 Bhalabhai Ukabhai 451 03.12.2011 12000

10/3. Kureshi Rahimbhai Mahammadbhai

1872 17.11.2011 5670

8A/0 Kishordan Shaktidan 1871 17.11.2011 7875

8A/0 kana Mahadev 1870 17.11.2011 5480

Page 156: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 156

ANNEXURE-7: DETAILS OF COMPENSATION PAYMENT FOR 400 KV LINE

Details of Compensataion_400 Kv Charanka - Veloda line

Sr.no Name of Farmer Village Survey

No. Loc. No

Compensation paid for all Category including

vulnerability Assistance (If Applicable) Rs.

1 Nagdanbhai Devdanbhai Ayar Aluvas 151p1 1/0 14700

2 Lakhabhai lalabhai Ayar Aluvas 151P4 1/1 to 1/2 13535

3 jadeja javansinh ramsinh Aluvas 1 1/1 99000

4 Lakhabhai lalabhai Ayar Aluvas 151p4 1/2. 73535

5 Karnabhai devdanbhai Ayar Aluvas 40 1/3. 74390

6 Nagdanbhai Devdanbhai Ayar Aluvas 401P1 1/3 to 1/4 15165

7 Karshanbhai Devdanbhai PATANKA 40 1/3 to 1/4 14390

8 1/4 0

9 Vajabhai Devayatbhai Ayar Aluvas 49p 1A/0 14635

10 Babubhai Devayatbhai Ayar Aluvas 49 1A/1 100000

11 Babubhai Devayatbhai Ayar PATANKA 49P 1A/1 to 1A/2 17685

12 Babubhai Jagmalbhai PATANKA 60 1A/1 to 1A/2 14630

13 Alabhai Devayatbhai Ayar Aluvas 36 1A/1 to 1A/2 14890

14 BABUBHAI JAGMALBHAI AYAR

Aluvas 56 1A/2 60000

15 BABUBHAI JAGMALBHAI AYAR

Aluvas 60 1B/0 74900

16 Babubhai Jagmalbhai Aluvas 56 1B/0 14890

17 VIRAMBHAI B.THAKOR PATANKA 405 2/0. 67000

18 Rudabhai Nagibhai Rathod PATANKA 261 2/0 to 2/1 13000

19 DHARSHIBHAI S.THAKOR PATANKA 394 2/1. 63000

20 LAXMANJI BHURJI VAGHELA PATANKA 261 11200

21 BECHARBHAI S.THAKOR PATANKA 397 2/2. 64500

22 DEDAN NAGDAN AYAR PATANKA 377/2/1 2/2 TO 2/3 8000

23 Jivanbhai Khemabhai Ayar PATANKA 377/1. 2/3. 72392

24 Jadeja bhikubha tapubha PATANKA 261 2/4. 68960

25 Govindbhai Nagadanbhai Ayar PATANKA 261 2/5. 60000

26 LAXMANJI BHURJI VAGHELA PATANKA 261 2/5. 32950

27 Jadeja bhikubha tapubha PATANKA 261 2/5. 8000

28 Ayar Bharubhai kalabhi PATANKA 409 3/0. 4000

29 Madevbhai Vajabhai Ayar PATANKA 3/0 60000

30 Govindbhai Nagadanbhai Ayar PATANKA 4/0 60000

31 Arjanbhai Virambhai Ayar PATANKA 263 4/1. 84000

32 Bhjojbhai Khimabhai Ayar PATANKA 361 4/2 60000

33 Gadhvi Ramdan Pratapbhai PATANKA 258 4/3. 61550

34 Gadhvi Ramdan Pratapbhai PATANKA 258 4/3. 32450

35 Gadhvi Ramdan Pratapbhai PATANKA 258 4/4. 80210

36 Kishordn Shaktidan Gadhavi PATANKA 254 4/4. 14850

37 Gadhavi Ratandan Samarathdan

PATANKA 253 4/5. 62175

38 Gadhavi Ratandan Samarathdan

PATANKA 253 4/5. to 4/6 46375

39 Gadhavi Vishnudan Mobatdan PATANKA 244/1. 4/5. 6435

40 Gadhavi Khimdan Shivdan PATANKA 248/2. 4/6. 69000

41 Gadhavi Khimdan Shivdan PATANKA 248/2. 4/6. 26965

42 Gadhavi Khimdan Shivdan PATANKA 245 4/6. 2800

43 Ahir Savabhai Jivabhai PATANKA 243/2. 4/6. 3000

44 Maldan KANJI Gadhvi PATANKA 247 4/7. 104995

45 Gadhvi Hareshdan sagardan PATANKA 24/1. 4/7. 65005

46 Ayar Govindbhai Bhurabhai PATANKA 221 4/8. 69214

47 Nagdanbhai Kalabhai ayar PATANKA 197/1. 4/8. 16410

48 Ayar Bhachabhai Nanabhai PATANKA 200/2. 4/9. 64800

49 Thakor Talshibhai Rupshibhai PATANKA 200/2. 4/9. 6750

Page 157: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 157

50 Ayar Pachanbhai Dayabhai PATANKA 195/1. 4/10. 8000

51 Ayar Bhalabhai Hardasbhai PATANKA 98 4/10. 64500

52 Ayar Ranabhai Bhurabhai PATANKA 197p1p1 4/10. 4600

53 Thakor Nagabhai Bhagabhai PATANKA 140 4/11. 6750

54 Ayar Bhalabhai Dosabhai PATANKA 190/2. 4/11. 1550

55 Ayar Bhalabhai Dosabhai PATANKA 190/2. 4/11. 64000

56 Parbatsing Anadbha Jadeja PATANKA 29300

57 Kanjibhai Vaghabhai Thakor PATANKA 192/2p 5/0. 78430

58 Thakor Arjanbhai Vaghabhai PATANKA 226 5/0. 13785

59 Virjibhai Varsngbhai Thakor PATANKA 186 6/0. 67325

60 ishaben kanti Shidhada 361p1 8/0 12000

61 Thakor Sudabhai Bhikhbhai Shidhada 361p2 8/0. 95310

62 Kanjibhai Bhikhabhai thakor Sidhada 361p2 8/0 to 9/0 15715

63 Ramabhai Karshanbhai Thakor Sidhada 358 8/0 to 9/0 6730

64 Gadabhai Khetabhai Koli Shariyad 357 9/0. 91126

65 Hirabhai Hamirbhai Choudhariy Shidhada 384 9/1. 68000

66 Rafikbhai Anvarbhai Theba Shidhada 387 9/1 to 10/0 9250

67 Ramatkhan Modaji Theba Shidhada 16 9/1 to 10/0 10000

68 Hirabhai Hamirbhai Sidhada 384 9/1 to 10/0 8765

69 Vajiben chaturbhai koli Shidhada 387 10/0. 80000

70 Gandabhai Laxmanbhai Thakor

Shidhada 399 10/0 to 11/0 4000

71 Rafikbhai Anvarbhai Theba 20000

72 Dharshibhai Karshanbhai Koli Shidhada 396 11/0. to 11/0 9000

73 Vajiben chaturbhai koli Shidhada 387 11/0 115000

74 Chaudhary Saktabhai Ganeshbhai

Shidhada 399 11/0 to 11/1 14680

75 Jayantibhai Chaturbhai Thakor Shidhada 397 11/0 to 11/1 7000

76 Anvarkhan Gulmamad Theba Shidhada 397 11/0 to 11/1 10000

77 Bhuriben Chaturbhai Shidhada 397 11/0 to 11/1 8650

78 Thakor Dharshi Nabhabhai Shidhada 331 11/1. 71000

79 Patel Muljibhai Shidhada 11/1-11/2 7680

80 Balvantbhai Rameshbahi Chaudhary

Shidhada 330 11/1-11/2 8264

81 Ramshibhaai Gokalbhai Chaoudhary

Shidhada 330 11/2. 83000

82 Babiben Karimkhan Theba Shidhada 7215

83 Sarbhai Sermamad Theba Shidhada 529 11/2-11/3 6395

84 Mamad Subha theba Shidhada 529 11/3. 83512

85 Hasanbhai Raidhanji Theba Shidhada 6 11/3. 3500

86 Sabirhasan Gumamad Theba Shidhada 8 11/3-11/4 14650

87 Ramjanbhai Togaji Theba Shidhada 7 11/3-11/4 13000

88 Gulmahmad Dalumiya theba Shidhada 8 11/4. 104000

89 Ramzanbhai Togabhai Ayar Sidhada 11/4 to 11/5 6800

90 Dariyakhan Baubha Theba Sidhada 13p1 11/4 to 11/5 9350

91 Theba Mebub Karimkhan Sidhada 13p2 11/4 to 11/5 16076

92 Allararakhabhai Togaji Theba Sidhada 17 11/4 to 11/5 13889

93 Theba Dariyakhan nubha Shidhada 13p2 11/5. 3500

94 Hussenbhai Hamirbhai Theba-2 leg

Shidhada 19 11/5 54975

95 Kadarkhan Mehbub khan theba Shidhada 49 11/5-12/0 14350

96 Janmahmad Hajisuleman theba

Shidhada 49/p1 12/0. 70000

97 Janmahmad Hajisuleman theba

Shidhada 49/p1 12/0. 48500

98 Janmahmad Hajisuleman theba

Shidhada 49/p1 12/0. 32325

99 Kadrakhan Mohabatkhan Theba

Shidhada 49 12A/0 19675

Page 158: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 158

100 Dharshibhai Rugdanbhai Thakor

Shidhada 48/2. 12/0. 8500

101 Satabhai Meghrajbhai Thakor Shidhada 48/1. 12/0.-12a/0 7400

102 Janmahmad Hajisuleman theba

Shidhada 49/p1 12/0. 20000

103 Shkinaben Medaji Rauma Shidhada 47 12/0. 13635

104 Kadarkhan Mehbub khan theba Sidhada 49 12A/0 19675

105 Alimamad Kaluji Sidhada 46 12A/0 122000

106 Rabiyaben Bhihubhai THEPA Shidhada 45 12a/0-12a/1 4500

107 Alibhai Rehmatkhan Theba Shidhada 511 12a/0-12a/1 13275

108 Malujikhan Saheb khan theba Sidhada 44 12A/1 77000

109 Malujikhan Saheb khan theba Sidhada 44

12A/1 to 12A/2

13000

110 Maksudbhai isubkhan Theba Sidhada 25 12A/2 65000

111 Maksudbhai isubkhan Theba Sidhada 25 12A/2 55000

112 Mayuddin Noormamad Theba Sidhada 26 12A/2 16300

113 Theba abdulbhai jusabhai Shidhada 188 13/0. 9776

114 Notukhari Punjmiya Nagori Shidhada 27 13/0 110300

115 Radhabhai Bavabhai Rabari Shidhada 101p2 13/0 6400

116 Rematkhan sahebkhan malek Bamroli 103/2p 13/1 108330

117 Mansangbhai Bhikhabhai Thakor

Bamroli 110/1/1. 13/1 7500

118 Thakor Devanbhai Amthubhai Bamroli 55 13/2 30000

119 Thakor Devshibhai Amthubhai Bamroli 110/2. 13/2 73493

120 Thakor Mansangbhai Bhikhabhai

Bamroli 110/1/1. 13/2 2100

121 Manubhai Raaulkhan Malek Bamroli 58 13/2 to 13/3 6735

122 Malek Rehmadkhan Sahebkhan

Bamroli 55 13/3 40000

123 Barvad Ramji Khetabhai Bamroli 59 13/3 35000

124 Thakor Laghdhirbhai Nanji Bamroli 56 13/4 90385

125 Radhaben Danabhai Rabari Bamroli 48 14/0 70000

126 Vajabhai Ramjibhai Thakor Dabhi 79 14/1 75000

127 Mevabhai Malubhai Thakor Dabhi 77 14/2 74000

128 Rabari Sundabhai Sagrambhai Dabhi 85 14/3 74000

129 Thakor Savdanbhai Chothabhai

Dabhi 14 14/4 76000

130 Bhemabhai Ravatbhai Thakor Dabhi 17 14/5 80000

131 Dabhi Gram Panchayat

14/6 0

132 Thakor Bhagvanji Suraji Dabhi 163 14/7 80000

133 Thakor Jevatbhai Dharamshibhai

Dabhi 169 14/8 74000

134 Dayabhai MavjibhaiRaval Dabhi 209P 14/8 to 15/0 24285

135 Nemabhai Rupabhai Thakor Dabhi 167 14/8 to 15/0 2000

136 Swami Ratubharthi Vasubharthi

Dabhi 210 15/0 78000

137 Mukesh Arjanbhai Thakor Dabhi 219 15/0 to 15/1 10300

138 Somabhai Dayabhai Thakor Dabhi 78 15/0 to 15/1 3000

139 Thakor Harchandbhai Kanjibhai

Dabhi 223 15/1 98000

140 Virajibhai Chhathabhai thakor Dabhi 224p1 15/1 to 15/2 10650

141 Rathod Jamabhai Nagjibhai Korda 870 15/1. 14880

142 Rughnathbhai Lagdhirbhai Thakor

Dabhi 224P2 15/1 to 156/2 8000

143 Narshangbhai Mevabhai Thakor

Dabhi 227 15/2 105000

144 Panchabhai Lebabhai Rabari Dabhi 225P 15/2 to 16/0 5000

145 Rameshbhai Mevabhai Thakor Dabhi 134 15/2 to 16/0 4825

146 Mansangji Bhuraji Thakor Dabhi 16/0 60000

147 Husenbhai Karimbhai Sipai Korda 837 16/1 66500

Page 159: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 159

148 Jamabhai Nagjibhai Rajput Korda 870 16/1 to 16/2 14880

149 Sendabhai Thakor Korda 652 16/2 35500

150 Ajmalbhai Ramjibhai patel Korda 836 16/2 34850

151 Vrajlal Nagjibhai Suthar Jarusha 225 17/0 87000

152 Raval Nagjibhai Jakshbhai Jarusha 182 17/0 to 17/1 18000

153 Manjulaben Khemjibhai Brahman

Jarusha 7800

154 Hamirbhai Lakshmanbhai Jarusha 189 17/1 125000

155 sivabhai karmanbhai patel jarusha 193 17/1 to 17/2 31000

156 Natubhai Lakhmanbhai Thakor jarusha 190 17/1 to 17/2 9580

157 Patel Shivabhai Karmanbhai Jarusha 193 17/2 131000

158 Patel Ramabhai Karmanbhai Jarusha 198 17/2 to 17/3 35000

159 Ambaben Karmanbhai Patel Jarusha 192 17/2 to 17/3 15000

160 Memabhai Jivabhai Patel Jarusa 205 17/3 12500

161 Prajapati Chaganbhai D. Jarusa 203/1 17/3 12000

162 Chaganbhai Danabhai Prajapati-2 leg

Jarusha 203/1 17/3 49000

163 Memabhai Jivabhai Patel-2 leg Jarusha 205/200 17/3 41500

164 Jagmalbhai Kalabhai Jarusha 218 17/4 82000

165 prabhubhai jagmalbhai bhil jarusha 219 17/4 8345

166 virambhai jeevabhai jarusha 230 17/4 to 17/5 40000

167 Patel jagmal H Jarusha 243 17/5 44000

168 memabhai Jivabhai Patel jarusha 251 17/5 40000

169 viranbhai jeevabhai jarusha 250 17/5 to 17/6 20000

170 Sipai Ganibhai Husenbhai Jarusha 253/'262 17/6 82000

171 Sipai Ganibhai Husenbhai Jarusha 253 17/6 6000

172 Kantibhai Punabhai Prajapati Jarusha 271 14000

173 santokben ramjibhai patel jarusha 205 17/6 to 17/7 16000

174 rukhiben chamanbhai suthar jarusha 263 17/6 to 17/7 18000

175 Rameshbhai P Patel Jarusha 277 17/7 80000

176 rameshbahi pachabhai patel jarusha 296 17/7 to 17/7 30000

177 Baluben Haribhai Bhagi Jarusha 275 17/7-17/8 19570

178 Jagmalbhai Ganeshbhai Patel Jarusha 295 17/7-17/8 5375

179 Nai Naranbhai B Jarusha 279 17/8 100000

180 Laljibhai Hemabhai Chaudhary Jarusha 308 17/8 to 17/9 9235

181 Gajibhai Ambarambhai Sipai Jarusha 290 290 6775

182 MANABEN HEMRAJBHAI PATEL

Jarusha 288 17 /9 102215

183 Fakir Husensha Ramjansha Korda 150 17/9 to 17/10 4175

184 Nurmahmad Abrhamsha Jadeja

Korda 147p 17/9 to 17/10 4425

185 Fakir Jamsha Abhrahmsha Korda 147p 17/9 to 17/10 4215

186 Mahebusha Abhrahmsha Jadeja

Korda 147p 17/9 to 17/10 4345

187 Govindbhai Haribhai Patel Jekda 620 17/10. 87394

188 Bhikhabhai Mehabhai Chaudhary

Jekda 143 17/10 to 17/11 7500

189 Chaudhari Vajabhai Mahadevbhai

Jekda 13 17/11 92821

190 Rupabhai Vasabhai Chaudhary Jekda 365 17/11 to 17/12 18816

191 Rasuben Vajabhai Chaudhary Jekda 381 17/11 to 17/12 7345

192 Vajabhai Khaegarbhai Bhil Jekda 370 17/11 to 17/12 4215

193 bhil gomtiben gandabhai jekda 10 paiki 2 17/12 72355

194 Chaudhary Parmabhai Mahadevbhai

jekda 385 17/12 to 17/13 5500

Page 160: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 160

195 Patel Megrajbhai Gandabhai jekda 27 17/12 to 17/13 4500

196 Chaudhary Tejabhai Devabhai jekda 308 17/12 to 17/13 12000

197 Luhar Laxmanbhai B Jekda 23 17/13 66000

198 Shankar Bhai Vrsang Bhai Bharwad

Jekda 23 17/13 38000

199 Sankarbhai Nagjibhai Baravad Jekda 87 17/13 to 17/14 13475

200 Swami Chamanpuri Devpuri Jekda 86 17/14 76995

201 Devrambhai Bhemabhai Prajapati

Jekda 394 17/13 to 17/14 18000

202 Okhabhai Varjangbhai Suthar Jekda

17A/0 to 17/14

7214

203 Chaoudhari Mahadevbhai Harkhabhai

jekda 107p3 17A/0 3000

204 Bharwad Narshngbhai Nagjibhai

jekda 110/1. 17A/0 109845

205 Chaudhary Madevbhai Harkhabhai

jekda 792 17A/0 to 18/0 7860

206 Khemabhai Harkhabhai Patel jekda 791 17A/0 to 18/0 7652

207 Hamirbhai Sankar bhai patel jekda 471 18/0. 100000

208 Thakkar Amrutlal Dalpatram jekda 670 18/0 to 18/1 13130

209 Raghabhai Devrajbhai Chaudhry

jekda 672 18/0 to 18/1 7715

210 Chaudhari Gajabhai K Jekda 281 18/1 75329

211 Vajabhai Jamalbhai Thakor Jekda 708 18/1 to 18/2 5476

212 Rajabhai Jahabhai Patel Jekda 710 18/1 to 18/2 5570

213 Bhamabhai Sankarbhai Suthar Jekda 705 18/1 to 18/2 5714

214 Bharvad Varsangbhai R Jekda 289 18/2 64500

215 Amratbhai Bhanabhai Prajapati Jekda 732 18/2 to 18/3 4975

216 Revaben Karmshibhai Chaudhary

Jekda 703 18/2 to 18/3 7376

217 Thakor Maghabhi Devsibhai Jekda 299 18/3 67685

218 Tejabhai Devsibhai Thakor Jekda 736 18/3 to 18/4 3795

219 Hamirbhai Haribhai Thakor Jekda 730 18/3 to 18/4 5010

220 Solanki Babubhai Harkhabhai Jekda 303 18/4 77150

221 Parbatbhai Bhemabhai Thakor Jekda 740 18/4 to 18/5 8516

222 Ishvarbhai D Prajapati Jajansar 144 18/5 76250

223 Haribhai Manjibhai Chauthary Jekda 691 18/4 to 18/5 12285

224 Virambhai V Thakor Jajansar 159 18/6 57255

225 Virambhai V Thakor Jajansar 159 18/6 26000

226 Amthubhai Ravatbhai Thakor Jajansar 225 18/6 to 18/7 10270

227 Bhagwanbhai Hirabhai Thakor Jajansar 158 18/6 to 18/7 5975

228 Varsanbhai Bavabhai Thakor Jajansar 157 18/6 to 18/7 5147

229 Dharmaben G Thakor Jajansar 12 18/7 40000

230 Thakor Rameshbhai Gandabhai

Jajansar 12 18/7 37457

231 Dharmaben G Thakor Jajansar 12 18/7 to 18/8 6000

232 Hamirbhai Naranbhai Solanki 18/8 14950

233 Raymalbhai Harchandbhai Thakor

Jajansar 39 18/8 to 18/9 7350

234 Gemarbhai Jodhabhai Thakor Jajansar 42p1 18/8 to 18/9 5275

235 Vejiben Bharmalbhai Thakor Jajansar 42 18/8 to 18/9 5370

236 Thakor RoopsingbhaiSurabhai Jajansar gov. land 18/9 72010

237 kantibhai rupshibhai thakor Jajansar 40 18/9 4000

238 trikambhai kunvarbhai thakor Jajansar 18/9 9000

239 trikambhai versibhai parmar Jajansar 40 18/9 to 18/10 14710

240 kanti bhai rupshibhai thakor Jajansar 40 18/9 to 18/10 10180

241 Gemarbhai R Thakor Jajansar

38/1/1 GOV. LAND

18/10 65000

Page 161: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 161

242 amrutbhai dharasibhai thakor Rangpura 95 18/10 to 18/11 7410

243 nathanhai dharmashibhai thakor

rangpura 39 18/10 to 18/11 6315

244 Bijalbhai L Thakor Rangpura 10P1 18/11 65000

245 Bijalbhai L Thakor Rangpura 10P1 18/11 2500

246 ramabhai savshibhai thakor Rangpura 121p2 18/11 to 18/12 13171

247 shivabhai ramjibhai rabari koilvada 105 18/11 to 18/12 13285

248 talsibhai sivabhai harijan Kolivada 101p3 18/11 to 18/12 10000

249 KHETABHAI SAVSIBHAI THAKOR

Rangpura 121/1 18/12 75560

250 ganeshbhai mevabhai rabari Kolivada 123p2 18/12 to 18/13 13656

251 gugabhai mevabhai rabari Kolivada 122p 18/12 to 18/13 16500

252 Kababhai Mevabhai Rabari Kolivada 123p1p1 18/13 65000

253 somabhai ganeshbhai thakor kolivada 136 18/13 to 18/14 8000

254 Heeraben S Harijan Kolivada 91 18/14 67615

255 HABIBKHAN ALIKHAN MALEK

Kolivada 99 18 /15 92375

256 Naranbhai Dosabhai Chaudhary

Kolivada 121p1 18/15 to 18/16 11312

257 Rahimkhan Alikhan Malek Kolivada 184 18/15 to 18/16 15000

258 Virambhai Danabhai Chaoudhary

Kolivada 122 18/16 105312

259 virambhai haribhai chaudhary kolivada 196 18/16 to 18/17 7857

260 dineshbhai khemabhai parmar kolivada 193 18/16 to 18/17 3571

261 kanjibhai haribhai patel kolivada 194 18/16 to 18/17 6715

262 gemarbhai dhanabhai parmar Kolivada 193 18/16 to 18/17 3571

263 somabhai vasharabhai prajapati

Kolivada 219 18/16 to 18/17 6000

264 Patel Mavji Bhai Haribhai Kolivada 125\1-195 18/17 70857

265 ganeshbhai jethabhai prajapati Kolivada 511 18/7 to 19/0 17857

266 diviben chhaganbhai harijan kolivada 294 19/0 7438

267 Joshi Pravinkumar Jayshankar Bhai

Bhilot 55 19/0 87500

268 mahmadkhan Alikhan Malek Bhilot 295 19/0 10000

269 Suthar Jayrambhai Keshavlal Bhilot 49 20/0 91000

270 Bhogilal Revashankar Joshi Bhilot 49 20/0 43000

271 mahesh bhudarlal joshi bhilot 58 20/0 to 20/1 6800

272 chaudhari gadasbhai ranchhaodbhai

bhilot 48p2 20/0 to 20/1 15000

273 Vaghela Hanubha Kubersang Bhilot 61 20/1 54000

274 Gagdasbhai R Chaudhri Bhilot 48 /2 20/1 10000

275 nainaben diveshkumar Bhilot 71 20/1 to 20/2 6000

276 jethuji ajalji vaghela Bhilot 292 20/1 to 20/2 8375

277 gelubha Mobatsang Vagela bhilot 64 20/1 to 20/2 20000

278 Vaghela Vajubhai Dungarbhai Bhilot 70 20/2 40000

279 vaghela sardarsang Bhilot 41 20/2 to 20/3 25000

280 Vaghela Vajubhai Dungarbhai Bhilot 70 20/2 35000

281 khetuba sultansingh vaghela bhilot 249p1 20/2 20000

282 Raval Gaurisankar Kevalram Bhilot 77 20/3 30000

283 Prahladram G. Joshi Bhilot 76 20/3 34000

284 Prahladram G. Joshi Bhilot 81 20/3 to 20/4 25000

285 Amaratbhai Nagjibhai Rabari Bhilot 80 20/3 to 20/4 15000

286 Jagdishkumar Jayshankar Bhilot 127/1 20/3 to 20/4 8000

Page 162: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 162

Joshi

287 Jamnashankar Jayshankar Joshi

Bhilot 79 20/3 to 20/4 10000

288 Joshi Prahladram Ganpatram Bhilot 82+81 20/4 70000

289 Gelubha Mobatsang Vagela Bhilot 82 20/4 3000

290 ratubha bhaguji vaghela Bhilot 299 20/4 to 20/5 16500

291 Vaghela Hatubha Bhaguji Bhilot 100+366 20/5 125000

292 Rameshbahi Parsotambhai Thakar

Bhilot 232 20/5 to 20/6 7250

293 Prahladbhai Mohanbhai Thakar Bhilot 99 20/5 to 20/6 7000

294 Nadoda Devabhai Dhanabhai Bhilot 247 20/6 55000

295 Vaghela Sultansinh Ratansinh Bhilot 286 20/6 10000

296 Vaghela Sultansinh Ratansinh Bhilot 286 20/6 1000

297 khetuba sultansingh vaghela Bhilot 68p2 20/6 20000

298 Bhemabhai Haribhai Thakor Bhilot 250/1 p 2 20/6 to 21/0 6000

299 Vajubhai D Vaghela Bhilot 249 p 2 20/6 to 21/0 25000

300 Merambhai Talsibhai Thakor Bhilot 250/1/1 21/0 84000

301 Shivabhai Lalabhai Patel Bhilot 459 21/0 to 21A/0 34000

302 Govabhai Hirabhai Nadoda Bhilot 458P1 21A/0. 64000

303 Chaoudhari Ramabhai Devabhai

Bhilot 462 21A/0. 66000

304 Virchandbhai Bhagvanbhai Thakor

Bhilot 457 21A/0 to

21B/0 15000

305 DajaBhai S. Chaudhary Bhilot 75 21B/0 81000

306 Jivabhai Devabhai Raval Bhilot 468

21B/0 to 21B/1

5000

307 Vasudevbhai Somnath Thakar Bhilot 467P2

21B/0 to 21B/1

22050

308 Hanubhai Kuberji Vaghela Bhilot 1371

21B/0 to 21B/1

7620

309 Bhupatsang Lakhaji Vaghela Bhilot 502P1

21B/0 to 21B/1

15000

310 Dayabhai Jethabhai Thakkar Bhilot 467P1

21B/0 to 21B/1

26100

311 Pratapsing Naranji Vaghela Bhilot 503 21B/1 100000

312 Jairambhai Keshabhai Bhilot 512

21B/1 to 21B/2

25000

313 Pushpaben Chhotubhai Thakkar

Bhilot 354 21B/1 to

21B/2 5320

314 Prahladbhai Ganeshbhai Parmar

Bhilot 504 21B/1 to

21B/2 31250

315 Chaudhry Joshnaben D Bhilot 514\3 21B/2 86000

316 Ratnabhai Saktabhai Patel Bhilot 516

21B/2 to 21B/3

5260

317 Kanjibhai Govindbhai Kanabi Bhilot 514P2

21B/2 to 21B/3

37000

318 Ramjibhai G Patel Bhilot 520&514p1 21B/03 19000

319 Rafikbhai Daudbhai Ghanchi Bhilot 167P1P

21B/3 to 21B/4

10530

320 Kuberbhai D Chudhry Bhilot 518 21B/03 64900

321 Kuberbhai D Chudhry Bhilot 518 21B/03 24000

322 Ramjibhai Panchabhai Chaudhary

Bhilot 519 21B/03 16000

323 Rameshbhai Virambhai Chaudhry

Bhilot 528 21B/04 83000

324 Prem Devi Bhilot 527

21B/4 to 21B/5

12000

325 Haribhai Andabhai Chaudhary Memdavad 166p2

21B/4 to 21B/5

17000

326 Patel Jethabhai Khodabhai Memdavad 161P2

21B/4 to 21B/5

10000

327 Parbatbhai Ramjibhai Chaudhary

Memdavad 166p1 21B/4 to

21B/5 5150

Page 163: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 163

328 Bavabhai Khodabhai Patel Memdavad 161P1

21B/4 to 21B/5

25000

329 Swami Manger p Memdavad 11 21B/5 80000

330 Prahaladgiri M Goswami Memdavad 160 21B/5 50000

331 Chaudhary Rugnathbhai Nanajibhai

Memdavad 159P 21B/5 to

21B/6 30000

332 virambhai haribhai chaudhary Memdavad 159P

21B/5 to 21B/6

30000

333 Amaratgar Swami Memdavad 156 21B/06 62000

334 Thakor Jyantibhai Mevabhai Memdavad 157P3 21B/06 35000

335 Bababhai Virabhai Koli Memdavad 157P1

21B/6 to 21B/7

30000

336 Kanubhai V Thakkar Memdavad 154

21B/6 to 21B/7

35000

337 HarunBhai B Ganchi Memdavad 123P2 21B/07 93000

338 Bhagvanbhai Kanjibhai Chaudhary

Memdavad 124P2 21B/7 to

21B/8 30000

339 hasinaben ibrahimbhai ghachi memdavad 125

21B/7 to 21B/8

26000

340 KhemaBhai Manjibhai Harijan Memdavad 706 21B/08 42000

341 Ramabhai Mohanbhai Memdavad 127 21B/08 to 9 12500

342 Devabhai K Patel Memdavad 51 21B/09 76000

343 virambhai chelabhai patel Memdavad 56 21B/09 to 10 23000

344 Danabhai bhemabhai chaudhaari

Memdavad 50 21B/09 to 10 9750

345 Meghabhai Ramsibhai patel Memdavad 28 21B/09 to 10 20000

346 Kanjibhai. J. Chaudhry Memdavad 395 21B/10 73820

347 dungarbhai balabhai Memdavad 58p

21B/10 to 21B/11

30000

348 Valabhai B Patel Memdavad 57

21B/10 to 21B/11

26500

349 Patel Devabhai Kalabhai Memdavad 39 21B/11 90200

350 dayabhai govindbhai thakor Memdavad 30

21B/11 to 22/0

20000

351 shankarbhai mohanbha thakor Memdavad 31p2 21B11 to 22/0 19700

352 ramji amba chaudhary Memdavad 29 21B11 to 22/0 20250

353 Thakor Raychandbhai Govindbhai

Memdavad 784/1. 22/0 to 23/0 39254

354 Amthubhai Govandbhai Thakor Memdavad 30 22/0 to 23/0 30610

355 Daaniben Gandabhai Harijan Memdavad 783/14 22/0 65500

356 Veerabhai Khetabhai Koli Memdavad 783/12 P 1 22/0 to 23/0 16700

357 Raychandji Dayaji Thakor Memdavad 783/1 23/0 71260

358 Veerabhai Khetabhai Koli Memdavad 783/12 P 1 23/0 to 23/1 26450

359 Thakor Hemabhai Khetabhai Premnagar 783\12P2 23/1 80500

360 Thakor Sankarbhai Mohanbhai Memdavad 783/6p1 23/1 to 23/2 4500

361 Thkor Chothiben Ranchhodbhai

Mehmdavad 182 23/2 77465

362 Bhagvanbhai Sagrambhai Thakor

Mehmdavad 782 23/2 to 23/3 13300

363 Rabari Govindbhai Vaghabhai Mehmdavad 768 23/3 91120

364 okhabhai mohanbhai harijan Mehmdavad gov. land 23/4 72775

365 Valabhai Bhagwanbhai Patel Mehmdavad 749p 23/4 to 23/5 20000

366 Surjghar Shambhughar Swami Mehmdavad 748 23/5 120000

367 Ramchandbhai SedhabhaiThakor

Premnagar 765 23/5 to 23/6 7650

368 Chaudhry Maghabhai Manabhai

Sherganj 194P/2/2 23/6 73950

369 Chaudhary Bhemabhai Manabhai

Sherganj 193/1/1 p 23/6 to 23/7 9980

370 Raghubhai Dhayabhai Thakor Sherganj 193/2 23/6 to 23/7 7270

371 Sadabhai D Thakor Sherganj 193\2 23/7 67000

Page 164: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 164

372 Sankarbhai Jasvantbhai Chaudhary

Sherganj 194/1p1 23/7 to 27/8 14750

373 Ravabha Mavjibhai Thakor Sherganj 193/2 23/7 to 27/8 4500

374 Thakor Sadabhai Dayabhai Sherganj 193/2 23/7 to 27/8 17000

375 Goswami Karsanpuri Manipuri Sherganj 201\2P3 23/8 42000

376 Shradhdaben Natwarpuri Sherganj 201\2P3 23/8 49000

377 Shankarbhai Manabhai Patel Sherganj 202/1 23/8 to 23/9 30000

378 Vasharambhai Rajabhai Chaudhary

Sherganj 201/2/2 23/8 to 23/9 8000

379 Nathabhai mehabhai patel Sherganj 202p2 23/8 to 23/9 10760

380 Lalabhai Jivatbhai Kanbi Sherganj 203/1 23/8 to 23/9 10000

381 Babubhai Devabhai Chaudhary Sherganj 203 23/9 245000

382 Jagdishbhai Kamabhai Chaudhry

Sherganj 5 24/0 159600

383 Kamabhai Laxmanbhai Patel Sherganj 71 24/0 to 25/0 8000

384 Jesangbhai Valabhai Dave Sherganj 6p 24/0 to 25/0 30000

385 Dhudhabhai Amthabhai patel Sherganj 9p2 25/0 117000

386 Ganeshbhai Dhanabhai Sherganj 25/0 4850

387 Jaisungbhai Jevatbhai Chaudhary

Sherganj 206 25/0-26/0 16000

388 abhaysing gohil Sherganj 10 25/0-26/0 7500

389 Valabhai Harisankarbhai Dave Sherganj 14/2 25/0 to 26/0 6000

390 Pethabhai Jevatbhai Chaudhy Sherganj 12 26/0 90000

391 Ganeshbhai Rajabhai Patel Sherganj 13 26/0 4700

392 Narshangbhai Memabhai Chaoudhary

Sherganj 9p1 26/0 9456

393 chaudhary prakashbhai lalabhai

Sherganj 32 26/0 2000

394 vasarabhai vajabhai patel Sherganj 14 26/0-26/1 7221

395 kailashbha chandanbha gohil Sherganj 5 26/0-26/1 8672

396 ganeshbhai rajabhai patrel Sherganj 145 26/0-26/1 7445

397 babubhai rajabhai patel Sherganj 13 26/0-26/1 6365

398 Bharvad Jijiben Saktabhai Sherganj 30 26/1 76275

399 govabhai dhudabhai bhangi Sherganj 19 26/1- 26/2 8820

400 Vankar Amthubhai Khengarbhai

Sherganj 19\2\4P1 26/2 74235

401 THAKOR KARSAN BHAI JAGMAL BHAI

kolapr 36 26/2 TO 26/3 8465

402 Thakor Mafa Devsi Kolapur 68 26/3 66896

403 Rabari Malabhai Ramjibhai Porana 198 26/3 to 26/4 16562

404 Dayaji Rudaji Thakor Kolhapur 47p1 26/3 to 26/4 4515

405 Manjibhai Ranchod panchal Navapurana 196 26/4 1500

406 Malabhai R. Rabari Porana 198 26/4 60000

407 Haribhai Ranchhodbhai Rabari Porana 196 26/4 to 26/5 11570

408 Rabari Bababhai Govindbhai Kolapur 193\1 26/5 75495

409 Sitaram Manordas Sadhu Porana 193/2 26/5-26/6 5125

410 Kababhai Nagjibhai Rabari Porana 192 26/5-26/6 7316

411 Patel Naranbhai Devjibhai Alahbad 190\2 26/6 59081

412 Patel Naranbhai Devjibhai Alahbad 190\2 26/6 20000

413 chaudhary jagmalbhai ratna bhai

Porana 189 26/6-26/7 6025

414 patel khetabhai chelahbai Porana 188/2/1 26/6-26/7 4620

415 tejabhai ratnabhai chaudhary Porana 189 26/6-26/7 7320

416 chaudhary mahadevbhai ratnabhai

Porana 179/1/3 26/6-26/7 6785

417 Narkhanbhai Bajubhai Thakor Porana 179/1/p2 26/6-26/7 12000

418 Panchal Ganeshbhai Jayntibhai

Porana 165 26/7 75340

419 nagjibhai amrabhai bharvad Porana 159 26/7-26/8 7142

420 bharwad hengabhai amrabhai Porana 157 26/7-26/8 5125

Page 165: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 165

421 Bharvad Lakhmanbhai Karshanbhai

Alahbad 151/5 26/8 85000

422 Arjan bharwad Alahbad 26/8 to 26/9 5125

423 Thakor Devanbhai Ajubhai Alahbad 182 26/9 81625

424 Daniben Ratnabhai Solanki Alahbad 26/9 to 26/10 8750

425 pethabhai devabhai thakor Alahbad 26/9 to 26/10 5600

426 Prakashbhai Jagamalbhai Patel

Alahbad 132 26/9 to 26/10 20000

427 Patel Arajanbhai Valabhai Alahbad 88 26/10 98500

428 lagdhirbhai bhagabhai patel Alahbad 26/10 to 26/11 7500

429 Vejaben Kamabhai Patel Alahbad 67/3 26/11 78250

430 Karshanbhai Lalabhai Patel Alahbad 370 26/11 to 26/12 10373

431 Jivabhai Hamirbhai Chaudhary Alahbad 178 26/11 to 26/12 12455

432 0

433 Patel Laghjirbhai Bhagabhai Alahbad 67/2 26/11 8000

434 Prajapati khetabhai Okhabhai Alahbad 26 26/12. 91000

435 Chaudhary Jitabhai Harjibhai Alhabad 28 26/13 82000

436 Prakashbhai Jagmalbhai Patel Alhabad 29 26/13 to 26/14 20713

437 Jagshibhai Nathubhai Bharvad Alhabad - 26/13 to 26/14 5326

438 Bijalbhai Dosabhai Patel Alhabad 137 26/14 92000

439 gandabhai narsangbhai patel Alhabad 26/14 to 26/15 10000

440 ratnabhai jevatbhai patel Alhabad 26/14 to 26/16 9650

441 Chadhary Ramabhai Jagmalbhai

Alhabad 122p1 26/15 138500

442 hemabhai laxmanbhai chaudhary

Alhabad 333 26/15 to 26/16 21765

443 0

444 Gogabhai M Rabari Arajansar 24 26/16 40000

445 Prabhaubhai Amthabhai Kumbhar

Arajansar 24 26/16 29635

446 Sharma Ramabhai Maghabhai Arjansar 18P 26/17 83314

447 jagabhai kesarbhai patel Arjansar 26/17 to 26/18 7650

448 Patel Naranbhai narsungbhai Arjansar 9\2 26/18 76519

449 Prajapati Kantibhai Bhavanbhai

Arjansar 51 26/19 75039

450 khodabhai ajjubhai chaudhary Arjansar 26/19 to 26/20 14850

451 Goswami Padampuri Valpuri Arjansar 52 26/19 to 26/20 10110

452 Patel Memabhai Ganeshbhai Arjansar 53P3 26/20 107990

453 Patel Memabhai Ganeshbhai Arjansar 53P3 26/20 22000

454 shivabhai bhemabhai thakor Arjansar 26/20 to 27/0 12345

455 Chaudhary Bhagvanbhai Govabhai

Arjansar 56p1 26/0 to 27/0 18000

456 Sankarbhai Valabhai Chaudhary

Arjansar 56p1 26/0 to 27/0 17000

457 Thakor Dajabhai Gagaram Arjansar

79 /5 GOV. LAND

27/0 74252

458 Karashanbhai Khetabhai Patel Arjansar 27/0 to 27/1 6000

459 Ajubhai Bhemabhai Chaudhari Arjansar 27/0 to 27/1 6000

460 Rupabhai Virabhai Rabari Arjansar 152 27/0 to 27/1 8975

461 Patel Bhemabhai Paragbhai Arjansar 153p2 27/0 to 27/1 7389

462 Patel Jivabhai Paragbhai Arjansar 153 27/1 76575

463 Kuvarben Dhanjibhai Patel Arjansar 161 27/1 to 27/2 18000

464 Jemabhai Valabhai Chaudhary Arjansar 82 27/1 to 27/2 8650

Page 166: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 166

465 Chaudhry Bhavanbhai Balvantbhai

Arjansar 161/1P 27/2 78580

466 Suthar Lavji Jagshi Arjansar 160p2 27/2 to 27/3 7380

467 Kanbi Madev Balvantbhai Arjansar 79/5/5/p3 27/2 to 27/3 17850

468 Patel Dajabhai Okhabhai Arjansar 164/1p2 27/2 to 27/3 17000

469 Patel Bhemabhai Valabhai Arjansar 240\2 27/3 75934

470 Patel Shankarbhai Valabhai Arjansar 172 27/2 to 27/3 6000

471 Thakor Bhemaji Chamanji Arjansar 234P 27/3 to 27/4 11995

472 Chaudhary Chothiben Ramjibhai

Arjansar 239 27/3 to 27/4 14850

473 Thakor Ganeshji Chamanji Arjansar 236 27/4 77204

474 Tejabhai Vaghabhai Patel Arjansar 235p3 27/4 to 27/5 10000

475 Kuvarshibhai Karshanbhai Thakor

Arjansar 236p1 27/4 to 27/5 10630

476 Choudhry Ramabhai Ajamalbhai

Arjansar 234P 1 27/5 77000

477 Valaji Dhamaji Tatiyana 376 27/5 to 27/6 15749

478 Bhemabhai Mashabhai Thakor Arjansar 27/5 to 27/6 16380

479 Maganbhai Karshanbhai Solanki

Arjansar 233p1 27/5 to 27/6 8380

480 Thakkar Rasmeshbhai A Tatiyana 361 27/6 125000

481 Majibhai Ramsibhai Patel Tatiyana 372/2p1 27/7 98000

482 Amra Mavabhai Rabari Arjansar 9 27/7 to 27/8 8380

483 Patel bhavabhai Parmabhai Tatiyana 283 27/8 75980

484 Jalaji Mehaji Vanodara Tatiyana 206 27/9 33900

485 Chothaji Kuberji Ranavadiya Tatiyana 285 27/9 41000

486 Panchal Dayabhai Ramabhai Tatiyana 284 27/8 to 27/9 3800

487 Dayabhai Ramabhai Panchal Tatiyana 284 27/8 to 27/9 6870

488 Prakashbhai Jagamalbhai patel Tatiyana 132 27/8 to 27/9 18000

489 Amrutbhai Ramabhai Panchal Tatiyana 279p2 27/9 to 27/10 10320

490 Dharshibhai Vihaji Thakor Tatiyana 131 27/9 to 27/10 7678

491 Dharshibhai Vihaji Thakor Tatiyana 231 27/9 to 27/10 7678

492 Harchandbhai Devsiji Jasalia Tatiyana 239 27/10 53650

493 Thakor Khetaji Ramsiji Thakor Tatiyana 159 27/10 49000

494 Thakor Sataji Vihaji Tatiyana 240p1 27/10 to 28/0 6350

495 Thakor Vahaji Vihaji Tatiyana 290p2 27/10 to 28/0 5375

496 Shivaji Revaji Thakor Tatiyana 210p1 27/10 to 28/0 7318

497 Mahadevbhai Karshanbhai Rabari

Tatiyana 205 28/0 125000

498 Panchabhai Ramjibhai Rabari Tatiyana 209 28/0 to 28/1 8576

499 Khumabhai Karsanbhai Desai Tatiyana 474 28/0 to 28/1 7380

500 Rabari Mevabhai Ramjibhai Tatiyana 179p2 27/10 to 28/0 6000

501 Mevabhai Ramjibhai Bhangra Tatiyana 179/p2 28/0 to 28/1 21762

502 Mevabhai Ramjibhai Bhangra Tatiyana 189/1/1 28/0 to 28/1 20000

503 Jyantiji Hiraji Thakor Tatiyana 411 28/1 125000

504 Lagdhirji Jemaji Thakor Tatiyana 387p1 28/1 to 28/2 9836

505 Shankarji Rugnathbhai Thakor Tatiyana 184 28/1 to 28/2 7670

506 Rabari Sendhabhai Ramabhai Tatiyana 171P1 28/2 3000

507 Hamirbhai Ramabhai Rabari Tatiyana 223P2 28/2 75705

508 Okhabhai Rajabhai Luni Tatiyana 1002 28/2 to 28/3 6250

509 Nathubhai Rajabhai Rabari unn 822p2 28/2 to 28/3 7125

510 Senadhabhai Ramabhai Rabari Tatiyana 171p1 28/2 to 28/3 7685

511 Ramabhai Rajabhai Desai Luni Tatiyana 1409 28/2 to 28/3 4218

512 Rabari Karsanbhai Khetabhai Tatiyana 837P1 28/3 55150

513 Karshanbhai Khetabhai Rabari Tatiyana 463 28/3 20000

514 Bhagwanbhai Ramsungbhai Joshi

Tebi 843p1 28/3 to 28/4 19380

515 Ujambhai Kanjibhai Joshi Tebi 423 28/3 to 28/4 35000

516 Khambhala Sudabhai Karsanbhai

Tatiyana 844P3 28/4 79995

Page 167: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 167

517 Sidhrajsingh Prithvirajsingh Vaghela

Savpura 853 28/5 125000

518 Patel Rameshbhai Shivabhai Savpura 28/6 47000

519 irchandji Bavaji Vadhela Savpura 644 28/6 50000

520 Thakor Tejaji Ravaji Savpura 39 28/7 149985

521 Radhuji Sagramji Thakor Savpura 137+36 28/7 to 28/8 23000

522 Hathiji Chaturji Thakor Savpura 34 28/7 to 28/8 10000

523 Punaji Ravaji Thakor Savpura 33 28/7 to 28/8 9200

524 Shampuji Punaji Sabosana Savpura 32 28/7 to 28/8 12300

525 Patel Shaileshkumar Baldevbhai

Savpura 36P4 28/8 120000

526 Thakor Jogaji Ravaji Savpura 35P2P2 28/8 to 28/9 63450

527 Rameshji Ajmalji Sabosana Savpura 35P1 28/8 to 28/9 7000

528 Ishwarbhai Raghubhai Raval Savpura 29p1 28/8 to 28/9 8000

529 Mansungji Ravaji Sabosana Savpura 51p2 28/8 to 28/9 7000

530 Rajuju Sagramji Thakor Savpura 34 28/8 to 28/9 9000

531 Thakor Talaji Kamaji Savpura 33P8 28/9 84980

532 Vasarambhai Vershibhai Raval Savpura 29p6&4 28/9 to 28/10 20000

533 Ishvarji Bajuji Thakor Savpura 12 28/9 to 28/10 9320

534 Panchaji Bajuji Thakor Savpura 13 28/9 to 28/10 8600

535 Rabari Gokalbhai Devabhai Savpura 30 28/10 85000

536 Thakor Chamanji Sonaji Savpura 27P1 28/10 to 28/11 2500

537 Rameshji Babaji Sabosana Savpura 153 28/10 to 28/11 13000

538 Madhuji Sangramji Thakor Savpura 26P5 28/10 to 28/11 18000

539 Thakor Amratji Sonaji Savpura 153 28/10 to 28/11 13000

540 Thkor Madhuji Sagramji Savpura 26\5 28/11 62000

541 Raduji Sagramji Thakor Savpura 26p2 28/11 to 28/12 7000

542 Shantaji Sagramji Thakor Savpura 127 28/11 to 28/12 8900

543 Thakor Shankarji Sangramji Savpura 22 P 1 28/12 77990

544 Raduji Sagramji Thakor Savpura 137+36 28/12 to 31/0 20500

545 Bhupatji Manaji Sabosana Savpura 123 28/12 to 31/0 10000

546 Amthuben Bhupatji Sabosana Savpura 19/3/1 31/0 11795

547 Madhuji Chaturji Sabosana Savpura 94/2p1 31/0 to 32/0 9730

548 Narkhanji Raychandji Thakor Savpura 19p1 31/0 to 32/0 5000

549 Velaji Rayachandji Sabosana Savpura 19p1 31/0 to 32/0 36275

550 Keshaji Raychandji Sabosana Savpura 19p1 31/0 to 32/0 9700

551 Thakor Chatraji Vihaji Karshnpura 90 32/0. 82000

552 Sabosana Ravaji Vihaji Karshnpura 53 32/0 to 32/1 8281

553 Dhiraji Mevaji Thakor Karshnpura 56 32/1 70000

554 Bharatshi Jagat bhai Vaghela Karshnpura 27 31/1,32/2,32/3 13375

555 VRAJLAL Atmaram Thakker Karshnpura 27 32/2 82152

556 Rameshji Varsangji Adhgama ANADPURA 23p1 32/3. 70029

557 Panchabhai Sudabhai Desai ANADPURA 19/1 32/0,33/0 9384

558 Chhanubha Prabhatsinh Vaghela

Karshnpura 23p2 33/0. 83676

559 Sidhrajsingh Devisingh Vaghela

Karshnpura 121 33/0. 16651

560 Hamirbhai Harchandbhai Lotiya

Karshnpura 90P1 33/0. 4362

561 Dharshiji Nanaji Thakor ANADPURA 118 33/0 to33/1 18557

562 VARSUNGJI MANAJI THAKOR

ANADPURA 94 33/1 62000

563

Kalaniya Chehrabhai Punjabhai

ANADPURA 66 33/2 75155

564 Virchandji Kalanji Thakor Anandpura 61/1 33/2 to 33/3 2500

Page 168: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 168

565 Govindbhai Devshibhai Prajapati

Anandpura 64 33/2 to 33/3 3210

566 Prajapati Karshanbhai Laljibhai Anandpura 118p2p1 33/2 to 33/3 3000

567 Babuji Chaturji Solanki Anandpura 65p1 33/2 to 33/3 3750

568 Dharshiji Kalyanji Thakor ANADPURA 61/1. 33/3 53000

569 Solanki Amichandji Nemaji ANADPURA 63 33/3 18500

570 Solanki Joraji Solank Anandpura 42p5 33/3 to 33/4 4465

571 Dasharathji Joraji Anandpura 49p5 33/3 to 33/4 4500

572 Samji Gemarji Thakor Anandpura 44p4 33/3 to 33/4 3875

573 Joraji Gemarji Batakiya Anandpura 44p5 33/3 to 33/4 6344

574 Hirabhai Ramjibhai Mehriya Anandpura 56p1 33/3 to 33/4 3000

575 Bhatakiya Tejaji Nanjiji ANADPURA 40 33/4 86000

576 Joraji Gemarbhai ANADPURA 44p5 33/4. 3477

577 Bababhai Sankarbhai Sapariya odha 14 33/4. 2360

578 Bababhai Sankarbhai Odha 14 33/4 to 34/0 3626

579 Tejaji Nanjiji Bhatkiya Odha 40 33/4 to 34/0 11000

580 Sonetha Maganbhai Amathbhai

odha 64 34/0 82134

581 Sonetha Maganbhai Amathbhai

odha 64 34/0 5335

582 Mashurbhai Nurbhai Bhemat Totana 182 34/0 4083

583 Mashurbhai Nurbhai Bhemat Totana 182 34/0 5000

584 sagtabhai ravabhai kakrecha Odha 5/3 34/0 to 34/1 9275

585 Maganjee Kheta Odha 18 34/0 to 34/1 3400

586 Samjibhai Jajibhai Tharecha Odha 46 34/0 to 34/1 4637

587 maganji khetaji odha 35 34/1 4000

588 Rajabhai Mafabhai Bhangee odha 45 34/1 66956

589 Ghia Saifudeen Husainbhai Odha 37P1 34/2 88695

590 Kiran Ramesh Bhai Barot Odha 38/1/2 34/2 to 34/3 3500

591 jeetbhai Popatbhia Odha 54/1/2 34/2 to 34/3 6956

592 arjanbhai shankarjibhai kahrecha Odha 93/1

34/2 to 34/3 10144

593 kanboya devubhai nathaji Odha 93/3 34/2 to 34/3 10144

594 Yusufali Ibrahim Ghiya Odha 92 34/3 57956

595 Shankuben Raymalbhai Patani odha 56 34/3 28048

596 Ghia Fakruddeen Husenbhai odha 89/1 34/4 40000

597 Abdul Rasul F Ghiya odha 34/4 42607

598 Lakhman Radhabhai Totana 296p3p2 35/3 35/4. 6208

599 Kirankumar Mohanlal Parmar Anandpura 14 35/3 35/4. 2500

600 Ludharia Bhemabhai V Odha 75 34/5 78550

601 kurshiji bhemaji thakor Odha 74 34/5 to 34/6 18550

602 dalubhai shankarbhai changecha Odha 96/3

34/5 to 34/6 21739

603 bhemabhai valmaji ludariya Odha 82/1/1 34/6 to 34/7 9000

604 thakor raghuji kanji Shiya 70 34/6 to 34/7 2600

605 thakor dayaji kanji Shiya 70 34/6 to 34/7 2916

606 GRAMPANCHAYAT 34/6 0

607 PATNI RAMABHAI MOHANBHAI

Totana 134 34 /7 80750

608 Vaghari Naranbhai Mohanbhai Totana 134 34 /7 21150

609 Thakor Babuji Lakhaji Totana 123 34/8 43000

610 Babuji Lakhaji Thakor Totana 123 34/8 20000

611 Babuji Lakhaji Thakor Totana 123 34/8 1449

612 Balaji Jamaji Kudecha Totana 131/1/2 34/8 16875

613 Babuji Lakhaji Thakor Totana 123 34/8 2318

614 Patani Ragjibhai Kasubhai Totana 127p2 34/8 34/9 16231

615 Vaghari Dhanjibhai Kasubhai Totana 127p3 34/8 34/9 1050

616 Vaghari Shankarbhai Kashubhai Totana 127/1

34/8 34/9 2478

617 Vaghari Amthabhai Kanjibhai Totana 139/1 34/8 34/9 1750

618 Noruddin Rajbali vana Totana 141 34/9 40000

Page 169: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 169

619 Vana nuruden rajabali Totana 144 34/9 20000

620 Vana nuruden rajabali Totana 144 34/9 5869

621 Shirinbai kadarali Totana 145 34/9 ,10 1968

622 Shirinbai kadarali Totana 145 34/9 ,10 5217

623 Dodia Mohseenbhai I Totana 153P1P1 34/10 43000

624 Dodia Moshenbhai Ismalji Totana 153/1p1 34/10 20000

625 Dodia Moshenbhai Ismalji Totana 153/1p1 34/10 6086

626 Dodia Moshenbhai Ismalji Totana 153/1p1 34/10 4695

627 Dodia Moshenbhai Ismalji Totana 153/1p1 34/10 3478

628 Dodia Moshenbhai Ismalji Totana 153/1p1 34/10 6086

629 Bhimat Sirajbhai Hsenbhai Totana 115 34/11 60000

630 THAKOR VERASIJI MOHANJI Totana 207 34/12 48000

631 Thakor Vershiji Mohanji Totana 200/2 207 34/12,34/13 20000

632 Thakor Vershiji Mohanji Totana 200/2 207 34/12,34/13 24086

633 Babubhai Karsandas Totana 262 34/13 3000

634 TOTANIYA BAJUJI RAMASIJI Totana 202 34/13 60000

635 Govindbhai Maghabhai Joshi Totana 263 paiki 1 35/0 60000

636 Govindbhai Magabhai Joshi Totana 263p3 35/0 40000

637 Malubhai K Bharvad Totana 305P1 35/1 60000

638 Malubhai K Bharvad Totana 305P1 35/1 18501

639 Bharwad Malubha Karamshibhai Totana 305p-1p1

35/1 625

640 Bharwad Malubha Karamshibhai Totana 305p-1p1

35/1 1538

641 Bharwad Malubha Karamshibhai Totana 305p-1p1

35/1 1739

642 Raymalji Ajmalji Thakor Totana 350 35/1 35/2 5892

643 Suthar Bhanubhai V Totana 352/1/2 35/2 40000

644 Bhanubhai V Suthar Totana 352/1/2 35/2 20000

645 Bhanubhai V Suthar Totana 352/1/2 35/2 3260

646 Karashanji Rupshiji Santhaliya Totana 348 35/2 35/3 9500

647 Hajabhai Dayabhai Bharwad Totana 35/3 60000

648 Gandabhai Kasabhai Bharavad Totana 296/3/3 35/4 40000

649 Gandabhai Kasabhai Bharwad Totana 296p3 35/4 20000

650 Gandabhai Kasabhai Bharwad Totana 296p3 35/4 3347

651 Hirabhai Ragabhai Bharvad Totana 296p3p2 35/4 35/5 900

652 Bodhabhai Radhabhai Bharvad Totana 296/3/2 35/4 35/5 4005

653 Babu Naran Bharavad Totana 296/3/2 35/4 35/5 3378

654 Bharavad Khetabhai Radhabhai Totana 296/3/2

35/4 35/5 2475

655 Jamabhai Bhurabhai Bharvad Totana 296/3/2 35/5 63473

656 Bharvad Babubhai Ganesh Bhai

Totana 296\4 35/6 83977

657 Gafoorbhai KarsanBhai Bharvad

Totana 296/3/2 35/5 35/6 1575

658 Bhemabhai Rupabhai Bharvad Totana 296/3/2 35/5 35/6 1575

659 Jamabhai Bhurabhai Bharvad Totana 296/3/2 35/5 35/6 4500

660 Thakor Chelaji Wadhaji Totana 433/b/1 35/7 78926

661 Thakor Chelaji Wadhaji Totana 294 35/8. 60000

662 Charanbha Kanubha Vaghela Mota Jampur 433/1 35/9 60000

663 Charanbha Kanubha Vaghela Mota Jampur 433/1 35/10 63526

664 Pratapjee Thakhaji Solanki Mota Jampur 433/1 35/11 60000

665 Madhaji Ladhaji Thakor Mota Jampur 433 36/0 44000

666 Madhaji Ladhaji Thakor jampur 433 36/0 20000

667 Madhaji Ladhaji Thakor jampur 433 36/0 6144

668 Madhaji Ladhaji Thakor jampur 433 36/0 11159

669 Madhaji Ladhaji Thakor jampur 433 36/0 11594

670 Vaghela Jambha Champuji Mota Jampur 433/2 37/0 60000

671 Vaghela Sagubha Ramuji mota jampur 433p1 37/0 rod 15434

672 Pratapjee Thakhaji Solanki Mota Jampur 433/b/1 37/1 60000

673 Thakor Ramsanji Babaji Vithlod 8 37/2 62625

Page 170: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 170

674 Vershiji Kamaji Thakor Vithlod

7 GOV. LAND

37/3 70796

675 Thakor Lembuji Devsiji Vithlod

6 GOV. LAND

37/4 60000

676 Thakor Lembuji Devsiji Vithlod

6 GOV. LAND

37/4 6000

677 Thakor Makanji Sursangji Vithlod 4P1 37/5 45000

678 Thakor Makanji Surshangji Vithlod 4p1 37/5 20000

679 Thakor Makanji Surshangji Vithlod 4p1 37/5 1650

680 Thakor Makanji Surshangji Vithlod 4p1 37/5 5314

681 Thakor Makanji Surshangji Vithlod 4p1 37/5 4204

682 Thakor Lilaji Devsiji Vithlod 43P2 37/6 65314

683 Paragji Lilaji thakor Vithlod 31p1p3 37/6..37/5 3985

684 Sravanji pratapji thakor Vithlod 41p2 37/7..37/6 6575

685 Thakor gopalji pratapji Vithlod 41p2 37/7..37/6 11056

686 sarupji rasunji thakor devpura 89 37/7 44600

687 sarupji rasunji thakor devpura 89 37/7 20000

688 sarupji rasunji thakor devpura 75 37/8 66700

689 SAMUBEN B.VAGHARI DEVPURA 72/2 P1 38/0. 40000

690 SAMUBEN B.VAGHARI DEVPURA 72/2 P1 38/0. 11000

691 Vaghari Samuben Bharmalbhai Devpura 72/2p1 38/0 20000

692 Vaghari Samuben Bharmalbhai Devpura 72/2p1 38/0 8278

693 Hemaji Punjaji Thakor Devpura 63p4 38/0 38/1 4285

694 Devanji Sonaji Thakor Devpura 63p1 38/0 38/1 8570

695 Sartanji Bhikaji Thakor Devpura 74P1 38/0 37/0 11757

696 Samuben Bharmalbhai Vaghari devpura 45 38/0 51000

697 Liluben Jorabhai Desai devpura 64 38/1 75840

698 Thakor Bhupatsinh Bajuju devpura 25/1 38/1 5000

699 Thakor Sarupji Rasugji devpura 89 38/1 9284

700 Thakor Chandanji Bajuji devpura 25/1. 38/1 16607

701 Thakor Rameshji Punaji devpura 44p1 38/1 39/0 10500

702 Thakor Bhupatshi Bajuji devpura 67p2 39/0 6000

703 Mavajibhai Hirabhai Raval devpura 18/2/1 39/0 72000

704 Mavajibhai Hirabhai Raval devpura 18/2/1 39/0 6750

705 Babuji Kaliji Thakor devpura 14 39/0 to 39/1 8512

706 Galaji Chatraji Thakor devpura 15 39/0 to 39/1 7613

707 Thakor Bhupatshin Bajuji devpura 126p2 39/0 to 39/1 18675

708 thakor vershiji talaji devpura 193 39/1 40265

709 Lilaji Motiji Thakor devpura 192 39/1 39215

710 Umedji Mevaji Thakor devpura 155 39/1 to 39/2 7373

711 Prahladji Mevaji Thakor devpura 155 39/1 to 39/2 7475

712 Raychandbhai Amthabhai Vaghar

devpura 95 39/2 65000

713 Amratbhai Ramshanbhai Vaghri

devpura 92 39/2 to 39/3 3400

714 Chaudhary Shankarbhai Mavjibhai

devpura 49p1 39/2 to 39/3 17741

715 Chuadhary Askokbhai Laxmanbha

devpura 49p3/p1 39/2 to 39/3 7858

716 Kantibhai Valabhai Vaghri devpura 48 39/2 to 39/3 7513

717 Chaudhary Virambhai Velabhai Dhanera 47 39/3 120000

718 Bhsgvanbhai Govabhai Chaudhari

Dhanera 56/1 39/3 10000

719 Shankarbhai Devanbhai Chaudhary

Dhanera 46p1 39/3-39/4 19157

720 Nanjibhai Jevatbhai Chaudhary Dhanera 46p2 39/3-39/4 5212

721 Raychandbhai Khodabhai Chauhan

Dhanera 29p1 39/3-39/4 4565

722 Muljibhai Devanbhai Patel Dhanera 48p2 39/3-39/4 7380

Page 171: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 171

723 Chahan Rajubhai Kalabhai Dhanera 45 39/3-39/4 6300

724 Mohansing Jalamsing Jadeja Dhanera 30p1 39/3-39/4 9685

725 Shambhubhai B. Patani Dhanera 222/2/2 39/4 90475

726 Bahgwabhai Ramabhai Chaudhry

Dhanera 13p2 39/4 to 39/5 7645

727 Devjibhai Tejabhai Patel Dhanera 26 39/4 to 39/5 4515

728 Devusing Udaysing Jadeja Dhanera 25 39/5 150000

729 Lilaji devshiji Thakor Vithlod 43P2 39/5 to 39/6 20000

730 Lilaji devshiji Thakor Vithlod 43P2 39/5 to 39/6 1314

731 Devjibhai Kamabhai Chaudhary Dhanera 19

39/5 to 39/6 8405

732 Devrajbhai Paragbhai Patel Dhanera 44p3 39/5 to 39/6 5323

733 Motibhai Rashibhai Desai Dhanera 17/p2 39/5 to 39/6 5265

734 Devjibhai Tejabhai Patel Dhanera 27 39/5 to 39/6 19107

735 Gandabhai Bhavabhai Rabari Dhanera 17p1 39/5 to 39/6 9135

736 Cheharabhai J Chaudhri Vithlod 98\1 39/6 68625

737 Paragbhai Ranchhodbhai Chaudhari

Vithlod 98\2 39/6 5000

738 Bababhai Lebabhai Desai Dhanera 96/p1 39/6 to 39/7 6575

739 Mohanbhai Jemabhai Chaudhary

Dhanera 209p1 39/6 to 39/7 4975

740 Cheharbhai Jemabhai Chaudhry

Dhanera 98p1 39/6 to 39/7 4625

741 Desai Jabarben Hemabhai Dhanera 91p1 39/6 to 39/7 9375

742 Rajabhai Varshibhai Desai Dhanera 96/2 39/7 75690

743 Rajabhai Chehrabhai Deasai Sariyad 268 39/7 to 39/8 7215

744 Thakor Chandanji Rudaji Sariyad 273P1 39/8 74892

745 Shah Devendrabhai Somabhai Sariyad 274 39/8 to 40/0 12345

746 Amratbhai Ishvarbhai Brahman Sariyad 21 39/8 to 40/0 12370

747 Badsangji Rudaji Thakor Sariyad 276p1p 11214

748 0

749 Vadnji Chandanji Thakor Sariyad 276p1p 37050

750 Badsangji Rudaji Thakor Sariyad 4000

751 Talaji Laxmanji Thakor Sariyad 253 40/0 79575

752 Lakhiram D Joshi Sariyad 246\1 40/1 65000

753 0

754 Shamjibhai A Joshi Sariyad 241 40/2 64000

755 Shamjibhai A Joshi Sariyad 241 40/2 7000

756 Joshi Baldevbhai Tejabhai Sariyad 206 40/3 63000

757 Joshi Baldevbhai Tejabhai Sariyad 206 40/3 6500

758 Sevantilal Bhagwandas Patel Sariyad 122/1p2/p1 40/4. 10000

759 Sevantilal Bhagwandas Patel Sariyad 122/1p2/p1 40/4. 65000

760 Prajapati Jashiben Mafabhai Sariyad 188\1 40/5 72250

761 Pajapati Gandabhai Haribhai Sariyad 185\1 40/6 72000

762 somabhai bhabhai joshi Sariyad 187 40/6 to 40/7 17000

763 Varshaben Hirabhai Chaudhry Sariyad 158-397 40/7 67000

764 Joshi Bavabhai Nathurambhai Sariyad 426\2 40/8 76730

765 Naranbhai Jivrajbhai Joshi Sariyad 452/2 40/8 to 41/0 6320

766 PRATAPJI R.THAKOR SARIYAD 430p4 41/0 78941

767 Taljabhai Daljibhai Rabari Sariyad 451 41/0 37000

768 Mohanbhai Chelabhai Rabari Sariyad 443 41/0 to 41/1 8980

769 Revabhai Dhanabhai Rabari Sariyad 215 41/0 to 41/1 12000

770 Chaudhry Ranchhodbhai Vershibhai

Sariyad 441 41/1 8000

771 Chaudhry Jesangbhai Laxmanbhai

Sariyad 444 41/1 89680

772 Ranchhodhbai devshibhai chaudhary

Sariyad 445 41/1 to 41/2 15000

773 Ashaben Valabhai Chaudhary Sariyad 513p2 41/1 to 41/2 4310

774 Ranchhodbhai Ramabhai Chaudhry

Sariyad 512 41/2 87390

Page 172: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 172

775 Savjibhai Rupabhai Sariyad 512 41/2 to 41/3 14890

776 Jesangbhai Bhemabhai Chaudhary

Sariyad 266 41/2 to 41/3 6980

777 Prakashbhai Ramshibhai Chudhuri

Sariyad 531 41/2 to 41/3 9600

778 Ramshibhai Devshibhai Chaudhary

Sariyad 532/3 41/2 to 41/3 10380

779 Ranchhodbhai Ramabhai Chaudhry

Sariyad 512 41/2 3000

780 Ranchhodbhai Ramabhai Chaudhry

Sariyad 531 41/2 to 41/3 8000

781 Chaudhry Devrajbhai Hirabhai Sariyad 530\1 41/3 130000

782 Manshibhai Damarbhai Chaudhary

Sariyad 542/'1 41/3 to 41/4 5830

783 Meghabhai Velabhai Chaudhary

Sariyad 530p2 41/3 to 41/4 6380

784 Kankuben Bhavabhai Chaudhary

Sariyad 541p 41/3 to 41/4 6330

785 Chamar Laljibhai Bhikhabhai Sariyad 543p1 41/3 to 41/4 7935

786 ISHWERBHAI C.CHAMAR PATANKA 41/4 63000

787 Chamar Isvarbhai Chelabhai Sariyad 543P2 41/4 23000

788 Velabhai Balvantbhai Nai Sariyad 581 41/4 to 42/0 6380

789 Mafabhai sanakarbhai nai Sariyad 582 paiki 2 41/4 to 42/0 5000

790 danabhai kalabhai rabari Sariyad 568 41/4 to 42/0 3187

791 Narotambhai Virambhai Nayee Sariyad 581 42/0 74000

792 Narotambhai Virambhai Nayee Sariyad 581 42/0 to 42/1 11000

793 Mafabhai sanakarbhai nai Sariyad 582 paiki 2 42/0 8000

794 Pravinbhai Balwantbhai nai Sariyad 609/1/2 42/1 4500

795 Pravinbhai Balwantbhai nai Sariyad 582/2 42/1 6820

796 Nai Velabhai Balvantbhai Sariyad 587 42/1 8000

797 Valabhai sagrambhai chudhari Sariyad 581 42/1 70000

798 Ramabhai Khimabhai Parmar Shariyad 612 42/2. 75000

799 nathekhan bhikhan khan baloch

Sariyad 629 42/3 78500

800 Lila bhai Karsanbhai Rabari Sariyad 732 42/4 73000

801 Cheharabhai Sagthabhai desai Lodhi 2 42/4 5000

802 Nagjibhai Vashrambhai Rabari Lodhi 89/41 42/5 71000

803 Revabhai Hamirbhai Rabari Lodhi 89/43 42/6 65500

804 Rabari Sankabhai Lilabhai Lodhi 89/49 43/0 47000

805 Rabari Sankabhai Lilabhai Mota Veluda 89/49 43/0 20000

806 Rabari Sankabhai Lilabhai Mota Veluda 89/49 43/0 3000

807 Jorabhai Vastabhai Rabari Lodhi 89/50/1 43/1 43000

808 Jorabhai Vastabhai Rabari Lodhi 89/50p1 43/1 20000

809 Jorabhai Vastabhai Rabari Lodhi 89/50p1 43/1 5000

810 Bhikhabhai Danabhai Rabari 43/2 43000

811 Bhakhabhai Danabhai Rabari mota Veluda 56 43/2 20000

812 Bhakhabhai Danabhai Rabari mota Veluda 56 43/2 2500

813 Rabari Jamabhai Rama Bhai Veloda 58/5 43/3 55900

814 Jamabhai Naranbhai Rabari Veloda 62 43/4 40000

815 Dalabhai Danabhai Rabari Veloda 62 43/4 4000

816 Jamabhai Naranbhai Rabari Mota Veluda 62p 43/4 20000

817 Rabari Jamabhai Ramabhai mota Veluda 58/5 43/3 20000

818 Rabari Jamabhai Ramabhai mota Veluda 58/5 43/3 5000

819 Deewan Nurmamad Modisha Shidhada 46 43/4 30000

820 VAJABHAI M.CHAOUDHARI JEKADA 13 167/11 25000

821 Karamashibhai Nagjibhai Rabari Mota Veluda 81

44/0 40000

822 Panchab Bhai khengarbhai Rajput Mota Veluda 393

44/0 30000

Total 26573317

Page 173: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 173

ANNEXURE-8: COPY OF FORMATION OF GRIEVANCE REDRESS COMMITTEE

Page 174: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 174

ENGLISH TRANSLATION OF COPY OF FORMATION OF GRIEVANCE

REDRESS COMMITTEE

No. PRCH--/7027/13

Collector office, Patan

Date: 11.12.2013

To,

Executive Engineer (Construction)

GETCO Division Office,

Deesa.

Sub: Formation of Grievance Redress Committee (GRC) for Gujarat Solar Transmission SS &

Line under funding of Asian Development Bank (ADB).

Ref: 1. GETCO Head Office Letter No. GETCO/Solar Transmission/ GRC/ 3858 dated

23.07.2013.

2. GETCO Deesa office letter No. CDD/ Tech/13/file-79/GRC/3367 dated 10.08.2013.

Sir,

With reference to above subject and as desired by you, this is to inform you that approval is

hereby accorded for formation of Grievance Redress Committee (GRC) for Gujarat Solar

Transmission SS & Line under funding of Asian Development Bank (ADB).

Following will be the members by designation:

1. Prant Office Radhanpur- Nodal Officer,

2. Surpunch- respective village,

3. Deputy Engineer (Construction)- GETCO Sub Division Office, Deodar,

4. Executive Engineer (Construction)- GETCO Division Office, Deesa – Officer responsible

on behalf of GETCO to keep the work safe and out of danger by use of safety equipment

and consensus for activity related to above referred Solar Park.

For further needful action.

Collector

Patan

Copy To.

1. Prant Office Radhanpur,

2. Chief Engineer, GETCO Corporate Office, Vadodara,

3. Superintending Engineer, Transmission Circle Office, Palanpur.

Page 175: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 175

ANNEXURE-9: HIV AIDS AWARENESS PROGRAM

Page 176: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 176

ANNEXURE 10: COPY OF CSR ACTIVITIES FOR THE PROJECT

Project Brief Need Assessment Project Scope Beneficiaries Target Work Done Issues &

Challenges Achievement

Development &

renovation of

Charanka

Primary

School in

Charanka

Village, District

Patan under

GETCO CSR

Plan.

GETCO had taken

assistance of Pandit

Deendayal

Petroleum University

(PDPU) for scoping

and need analysis

study for

commencing

community

development

initiative.

Development &

renovation of

Charanka primary

school project was

selected based on

the need

assessment study.

Education Facility:

o Construction & of

building having two

classrooms.

Water & Sanitation

Infrastructure:

o Toilet block, soak pit,

septic tank,

o Water supply pipeline

with overhead tank,

Other infrastructure &

supporting facility.

o Prayer cum lunch shed.

o Supply of sports kit,

computers, musical

instruments, audio

system,

o Supply of vessels for

cooking,

o Supply of equipments

for children playground,

o Supply of steel

cupboards, etc.

Primary

beneficiaries:

Children of

Charanka school

having age

between 5 to 18

years _246

children (146

boys & 100 girls)

(Figs are form FY

2011-12, it may

change in present

time considering

dropout and new

admissions).

Secondary

beneficiaries:

Children of

surrounding

villages having

age between 5 to

18 years.

Activity taken

up in FY

2011-12

Target for

completion-

end of FY

2013-14.

Scoping and need

analysis study

completed.

Construction &

renovation of

building having two

classrooms, Toilet

block, soak pit,

septic tank, water

supply pipeline

with overhead

tank, prayer cum

lunch shed

completed.

Supply of sports

kit, computers,

musical

instruments, audio

system, vessels for

cooking,

equipments for

children

playground, steel

cupboards, etc.

completed.

Non availability of

eligible contractors

due to remote

location of site.

Non availability of

basic facilities for

construction like

water etc.

Due to remote

location, skilled

labour & material

is costly.

Weather condition

is extremely hot in

summer and heavy

rains in rainy

season which

reduce the rate of

work.

Education level of

school is

increased.

Students &

teacher staffs,

particularly

females are

satisfied with

facilities

provided.

Spread positive

impact of project

in Charanka

Village &

surrounding

areas.

Page 177: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 177

Photographic presentation of current status of work

Page 178: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 178

Page 179: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 179

Page 180: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 180

Annexure 11: Tree Cutting Compensation _220 KV Charanka Jangral TL (GETCO)

Sl

No.

Location

No

Village

Name Plot No

Khata

No PS Dist Name of the Land Owner Address

Tree Cutting

Compensation

1 13B/5-

13B/6 Bamroli 111 457 Varahi Patan Ayubkhan Aehmadkhan Pathan Bamroli, Patan 9,261

2 13B/8-

13B/7 Bamroli 274 295 Varahi Patan

Lakhamanbhai Rabhabhai

Rabari Bamroli, Patan 10,522

3 16/1 Jarusha 183 28 Sathalpur Patan Ganeshbhai Trikambhai Patel Jarusha, Patan 5,497

4 16/10 Jarusha 146/2/2 331 Sathalpur Patan Gajibhai Abhrambhai Sipai Jarusha, Patan 5,316

5 16/11 Jarusha 146/1/2 209 Sathalpur Patan Nuramahamand H Sipai Jarusha, Patan 5,316

6 16/2 Jarusha 180/P1 58 Sathalpur Patan Sivabhai Karmanbhai Patel Jarusha, Patan 5,826

7 16/3 Jarusha 202 326 Sathalpur Patan Khimjibhai M. Prajapati Jarusha, Patan 6,100

8 16/3-16/4 Jarusha 201 105 Sathalpur Patan Dhudabhai K Thakor Jarusha, Patan 3,918

9 16/3-16/4 Jarusha 203/1 163 Sathalpur Patan Chaganbhai D Prajapati Jarusha, Patan 4,518

10 16/4-16/5 Jarusha 234/1P 155 Sathalpur Patan Harkhabhai N. Patel Jarusha, Patan 8,435

11 16/4-16/5 Jarusha 234P2 199 Sathalpur Patan Virambhai J. Patel Jarusha, Patan 4,775

12 16/5-16/6 Jarusha 234/2 199 Sathalpur Patan Memabhai J. Patel Jarusha, Patan 10,604

13 16/7-16/6 Jarusha 244 216 Sathalpur Patan Virambhai J. Patel Jarusha, Patan 4,775

14 16/9-16/10 Jarusha 146/2/3 332 Sathalpur Patan Hazratali U. Sipai Jarusha, Patan 5,316

15 17/10-

17/11 Rangpura 107 93 Radhanpur Patan Sundabhai Savsibhai Thakor Radhanpur, Patan 13,771

16 17/10-

17/11 Rangpura 107P1 94 Radhanpur Patan Nagjibhai Savsibhai Thakor Radhanpur, Patan 3,162

17 17/3-17/4 Zazansar 148 33 Radhanpur Patan Verasibhai Malabhai Thakor Zazansar, Patan 9,107

18 17/4-17/5 Sathali 56/1P1 37 Radhanpur Patan Chhathabhai Mohanbhai Thakor Radhanpur, Patan 5,724

19 17/7-17/8 Sathali 46(38/4) 49 Radhanpur Patan Khetabhai Saktabhai Patel Santhali , Patan 9,724

20 17/8 Sathali 84 224 Radhanpur Patan Mali Dalabhai Mansangbhai Santhali , Patan 16,829

21 17/8-17/9 Sathali 36/2 107 Radhannpur Patan Maghabhai Gangarambhai Mali Rangpura,Patan 19,454

22 17/9 Rangpura 91,92 12 Radhannpur Patan Bhagvanbhai Karsanbhai Rabari Rangpura,Patan 14,971

23 17B/2-

17B/2 Rangpura 10P1 60 Radhanpur Patan Dharshibhai Vishabhai Thakor Rangapura,Radhanpur 6,335

24 19/0-19/1 Bhilot 108 281 Bhilot Patan Bhurubha Naranji Vaghela Bhilot,Patan 6,836

Page 181: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 181

Sl

No.

Location

No

Village

Name Plot No

Khata

No PS Dist Name of the Land Owner Address

Tree Cutting

Compensation

25 19/1-19/0 Bhilot 138 190 Bhilot Patan Sundabhai Ramjibhai Thakor Bhilot,Patan 17,938

26 19/1-19/0 Bhilot 138 290 Bhilot Patan Ramsangbhai Ramjibhai Thakor Bhilot,Patan 9,503

27 19/1-19/2 Bhilot 449 232 Bhilot Patan Devjibhai Balvatbhai Thakor Bhilot,Patan 19,495

28 19/2-19/3 Bhilot 698 119 Bhilot Patan Manabhai Haribhai Thakor Bhilot,Patan 15,655

29 19/3-19/4 Bhilot 117 252 Bhilot Patan Lalaji Pachanji Vaghela Bhilot,Patan 5,890

30 19/3-19/4 Bhilot 115 417 Bhilot Patan Gajubha Bhurubha Vaghela Bhilot,Patan 5,995

31 19/5-19/4 Bhilot 240 41 Bhilot Patan Raghubhai Ranchhodbhai

Kumbhar Bhilot,Patan 20,115

32 20/12 Memdabad 50 531 Radhanpur Patan Danabhai Bhemabhai

Chaudhary Memdavad , Patan 6,446

33 20/13 Memdabad 58 392 Radhanpur Patan Dungarbhai Valabhai Chaudhari Memdabad,

Radhanpur 8,024

34 20/9 Memdavad 154 495 Radhanpur Patan Kanubhai Vikutram Thakkar Memdavad , Patan 12,557

35 21/0 Memdavad 25 53 Radhanpur Patan Dayabhai Govindbhai Thakor Radhanpur, Patan 7,322

36 21/0-20/14 Memdavad 25 53 Radhanpur Patan Raychandbhai Govindbhai

Thakor Memdavad , Patan 10,333

37 22/0 Memdabad 783/3P1 624 Radhanpur Patan Shivabhai S Rabari Memdabad , Patan 12,668

38 22/10 Sherganj 199/2 138 Radhanpur Patan Mafabhai Shankarbhai

Chaudhari Sherganj, Patan 22,805

39 22/10-

22/11 Sherganj 207 89 Radhanpur Patan Nurmohamed Ganibhai Vhora Sherganj, Patan 9,379

40 22/10-

22/11 Sherganj 204/4P1 168 Radhanpur Patan Ransodbhai Danabhai Patel Sherganj, Patan 15,140

41 22/11-23/0 Sherganj 22P1 165 Radhanpur Patan Jasavantbhai Harjibhai Patel Sherganj, Patan 16,746

42 22/2 Memdavad 761 194 Radhanpur Patan Okhabhai Mohanbhai Harijan Memdavd, Patan 19,159

43 22/4-22/5 Memdavad 57 205 Radhanpur Patan Laxmanbhai Bhagvanbhai

Chaudhary Memdavd, Patan 12,170

44 22/5-22/6 Memdavad 742/P2 1014 Radhanpur Patan Acharatlal Mohanlal Patel Memdavd, Patan 4,277

45 22/5-22/6 Memdavad 743/2 844 Radhanpur Patan Amratbhai Ganeshbhai Suthar Memdavd, Patan 4,277

46 22/6-22/7 Sherganj 194/2/2P 78 Patan Patan Shankarbhai Manabhai Patel Sherganj, Patan 13,888

47 22/6-22/7 Sherganj 194/2/1 46 Radhanpur Patan Kesabhai D. Thakor Sherganj, Patan 13827

48 22/8-22/9 Sherganj 194/3 42 Radhanpur Patan Dilipbhai Gandabhai Chaudhari Sherganj, Patan 2,335

Page 182: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 182

Sl

No.

Location

No

Village

Name Plot No

Khata

No PS Dist Name of the Land Owner Address

Tree Cutting

Compensation

49 22/9-22/10 Sherganj 43 114 Radhanpur Patan Pragjibhai Laljibhai Chaudhari Sherganj, Patan 33,357

50 23/0-22/11 Sherganj 206 179 Radhanpur Patan Jesingbhai Jevatbhai Patel Sherganj, Patan 10,164

51 23/0-24/0 Sherganj 208/3P1 304 Radhanpur Patan Hitesh Kantilal Koradia Sherganj, Patan 4,730

52 23/0-24/0 Sherganj 9P2 198 Radhanpur Patan Dhudabhai Amthabhai Patel Sherganj, Patan 1,039

53 23/0-24/0 Sherganj 208/2P 297 Radhanpur Patan Hardasbhai Amathabhai Ayar Sherganj, Patan 6,370

54 24/0 Sherganj 15/1 111 Radhanpur Patan Shaileshbhai Raghubhai Nayi Sherganj, Patan 5,950

55 25/0-25/1 Sherganj 15/2 54 Radhanpur Patan Nareshbhai Gandabhai Nayi Sherganj, Patan 7,494

56 25/11,25/12 Alhabad 63P1 188 Radhanpur Patan Dharamshibhai Amthabhai

Prjapati Radhanpur, Patan 13,928

57 25/12 Alhabad 63p2 124 Radhanpur Patan Shankuben V. Prajapati Alhabad, Patan 13,928

58 25/12 Alhabad 62/1P 21 Radhanpur Patan Pababhai Kamabhai Patel Alhabad, Patan 16,712

59 25/1-25/2 Sherganj 29P1 124 Radhanpur Patan Abhesing Pratapsing Gohil Sherganj, Patan 10,091

60 25/1-25/2 Sherganj 29P2 123 Radhanpur Patan Madarsih Vagjibhai Gohil Sherganj, Patan 18,263

61 25/13 Alhabad 62/2 93 Radhanpur Patan Jivanbhai Kamabhai Patel Alhabad, Patan 17,117

62 25/14,25/15 Alhabad 20P1 96 Radhanpur Patan Jitabhai Memabhai Patel Radhanpur, Patan 4,609

63 25/15-

25/16 Alhabad 20P2 138 Radhanpur Patan

Lakhmanbhai Ajubhai

Chaudhari Alhabad, Patan 4,912

64 25/17-

25/18 Arjansar 31P1 49 Radhanpur Patan Pababhai Mavabhai Patel Arjansar,Patan 2,440

65 25/18-

25/19 Arjansar 66 194 Radhanpur Patan Jayantibhai Ajubhai Chaudhary Arjansar,Patan 4,999

66 25/18-

25/19 Arjansar 43 338 Radhanpur Patan Patel Bhavabhai Ajubhai Arjansar,Patan 12,831

67 25/19-

25/20 Arjansar 49/1 293 Radhanpur Patan Revabhai Chelabhai Patel Arjansar,Patan 4,999

68 25/19-

25/20 Arjansar 45 492 Radhanpur Patan Arjan Dharamsinh Patel Arjansar,Patan 6,111

69 25/20-26/0 Arjansar 41 358 Radhanpur Patan Somabhai Devabhai Patel Arjansar,Patan 8,498

70 25/20-26/0 Arjansar 46/1 180 Radhanpur Patan Chaudhari Naranbhai Ajubhai Arjansar,Patan 3,884

71 25/20-26/0 Arjansar 49 490 Radhanpur Patan Rakeshbhai Memebhai

Chaudhari Arjansar,Patan 12,182

72 25/2-25/3 Kolapur 32 33 Radhanpur Patan Varjang Mavjibhai Thakor Kolapur, Patan 17,725

Page 183: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 183

Sl

No.

Location

No

Village

Name Plot No

Khata

No PS Dist Name of the Land Owner Address

Tree Cutting

Compensation

73 25/3-25/4 Kolapur 39P3 135 Radhanpur Patan Kamuben Dayabhai Thakor Kolapur, Patan 8,225

74 25/3-25/4 Kolapur 86 36 Radhanpur Patan Panchanbhai Virabhai Thakor Kolapur, Patan 6,964

75 25/3-25/4 Kolapur 86P 36 Radhanpur Patan Kamuben Chhaganbhai Thakor Kolapur, Patan 10,219

76 25/3-25/4 Kolapur 39P1 133 Kolapur Patan Merambhai Ranabhai Rabari Kolapur, Patan 9,002

77 25/4-25/5 Kolapur 86P 36 Radhanpur Patan Mevabhai Savshibhai Thakor Kolapur, Patan 8,161

78 25/4-25/5 Kolapur 86P 36 Radhanpur Patan Chothabhai Virabhai Thakor Kolapur, Patan 4,830

79 25/4-25/5 Kolapur 27/4 25 Radhanpur Patan Galalbhai Sendhabhai Thakor Kolapur, Patan 3,660

80 25/5 Porana 195 125 Radhanpur Patan Manabhai Dudabhai Thakor Porana, Patan 10,499

81 25/5-25/4 Porana 195 125 Radhanpur Patan Vasantbhai Rugnathabhai

Thakor Porana, Patan 11,990

82 25/6-25/7 Porana 183/2 115 Radhanpur Patan Pethabhai Haribhai Patel Porana, Patan 11,448

83 25/6-25/7 Porana 183/2 115 Radhanpur Patan Pethabhai Haribhai Patel Porana, Patan 22,043

84 25/7 Porana 187 101 Radhanpur Patan Mavjibhai Virabhai Chaudhary Porana, Patan 8,435

85 25/7-25/8 Porana 186 127 Radhanpur Patan Kantilal Manilal Lawar Porana, Patan 8,554

86 25/8 Allhabad 156 98 Radhanpur Patan Versibhai Vihabhai Thakor Allhabad, Patan 18,674

87 25/8,25/9 Allhabad 151/1B 146 Radhanpur Patan Bhagabhai Bijalbhai Bharvad Allhabad, Patan 6,111

88 25/8-25/9 Allhabad 155 105 Radhanpur Patan Vashram Bhembhai Thakor Allhabad, Patan 9,782

89 25/9,25/10 Allhabad 83 78 Radhanpur Patan Mulabhai Bijalbhai Bharavad Allhabad, Patan 15,323

90 25/9,25/10 Allhabad 82P2 22 Radhanpur Patan Kanjibhai Dharamshibhai Suthar Allhabad, Patan 3,884

91 25/9-25/10 Allhabad 84 34 Radhanpur Patan Sankarbhai Ratnabhai Solanki Allhabad, Patan 7,110

92 26/0-25/20 Arjansar 60P2 222 Radhanpur Patan Patel Kamabhai Dungar Arjansar,Patan 4,108

93 26/0-26/1 Arjansar 58/1 6 Radhanpur Patan Shantilal Parmabhai Solanki Arjansar,Patan 16,718

94 26/1 Arjansar 57P1 652 Radhanpur Patan Sevadas B. Sadhu Arjansar,Patan 7,558

95 26/10-26/9 Tatiyana 354 136 Thara Banasakantha Bhavbhai Parambhai Patel Tatiyana ,

Banasakantha 3,555

96 26/11-

26/12 Tatiyana 294P3 35 Kankrej Patan Govaji Ravaji Kamaliya Tatiyana, Patan 13,358

97 26/11-

26/12 Tatiyana 297P1P4 438 Kankrej Patan Kamaliya Babuji Dhanaji Tatiyana, Patan 10,624

98 26/11-

26/12 Tatiyana 294P2P1 69 Kankrej Patan Chatoorji Kanaji Kamaliya Tatiyana, Patan 7,729

Page 184: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 184

Sl

No.

Location

No

Village

Name Plot No

Khata

No PS Dist Name of the Land Owner Address

Tree Cutting

Compensation

99 26/11-

26/12 Tatiyana 353 125 Kankrej Patan Raychandji Motiji Thakor Tatiyana, Patan 6,111

100 26/11-

26/12 Tatiyana 351 348 Kankrej Patan Manaji Vihaji Ranavadiya Tatiyana, Patan 4,923

101 26/12 Tatiyana 295P1 127 Thara Banasakantha Shankarji Mohanji Thakor Tatiyana ,

Banasakantha 15,361

102 26/12-27/0 Tatiyana 226P2 243 Kankrej Patan Mevaji Kuberji Ranavadiya Tatiyana, Patan 15,279

103 26/1-26/2 Arjansar 79/5/5P10 436 Patan Patan Mafaji Devnji Thakor Arjansar,Patan 21,056

104 26/2-26/3 Arjansar 165 389 Radhanpur Patan Arajanbhai Mevabhai Rabari Arjansar,Patan 8,388

105 26/2-26/3 Arjansar 152 329 Radhanpur Patan Rupabhai Virabhai Rabari Arjansar,Patan 26,191

106 26/2-26/3 Arjansar 79/5/5P/4 55 Radhanpur Patan Karshanbhai Bhemabhai Patel Arjansar,Patan 8,280

107 26/3-26/4 Arjansar 164/1P1 154 Radhanpur Patan Dazabhai Okhabhai Patel Arjansar,Patan 16,345

108 26/4 Arjansar 26/4 93 Radhanpur Patan Jagubhai Lalbhai Prajapati Arjansar,Patan 2,440

109 26/4-26/5 Arjansar 116 156 Radhanpur Patan Dalachhabhai Mohanbhai Nayi Arjansar,Patan 9,548

110 26/4-26/5 Arjansar 169/1 190 Radhanpur Patan Lebubhai Lavajibhai Thakor Arjansar,Patan 2,664

111 26/4-26/5 Arjansar 122 524 Radhanpur Patan Thakor Somabhai Virabhai Arjansar,Patan 7,439

112 26/5-26/6 Arjansar 224P 134 Radhanpur Patan Revaben Ramshibhai Chaudhari Arjansar,Patan 2,888

113 26/7-26/8 Arjansar 231 471 Radhanpur Patan Balwantji Chamanji Thakor Arjansar,Patan 4,487

114 26/8 Arjansar 232 75 Radhanpur Patan Bababhai Motibhai Harijan Arjansar,Patan 7,733

115 26/8-26/9 Arjansar 216P3 228 Radhanpur Patan Patel Viranben Kamabhai Arjansar,Patan 25,051

116 27/0-27/1 Tatiyana 30/1 376 Kankrej Patan Vahajibhai Hemabhai Parmar Tatiyana, Patan 16,330

117 27/0-27/1 Tatiyana 227P1 261 Thara Banashkantha Jivanji Dhudaji Thakor Tatiyana,

Banashkantha 5,721

118 27/1-27/0 Tatiyana 218 63 Kankrej Patan Lilabhai Okhabhai Bhangara Tatiyana, Patan 8,638

119 27/1-27/0 Tatiyana 177/P2 512 Kankrej Patan Mevabhai Ramjibhai Bhangara Tatiyana, Patan 7,528

120 27/1-27/2 Tatiyana 296 457 Thara Banasakantha Ashwinkumar Kirtilal Shah Tatiyana ,

Banasakantha 18,904

121 27/1-27/2 Tatiyana 205 203 Kankrej Patan Mahadevbhai Karshanbhai

Rabari Tatiyana, Patan 15,224

122 27/2-27/1 Tatiyana 180P1 390 Thara Banasakantha Lebabhai Mevabhai Rabari

Tatiyana ,

Banasakantha

4,987

Page 185: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 185

Sl

No.

Location

No

Village

Name Plot No

Khata

No PS Dist Name of the Land Owner Address

Tree Cutting

Compensation

123 28/0-27/2 Tatiyana 181P 274 Thara Banasakantha Jasaliya Harchandji Devshiji Tatiyana ,

Banasakantha 7,005

124 28/0-28/1 Tatiyana 170 97 Thara Banasakantha Lilabhai R Rabari Tatiyana ,

Banasakantha 5,724

125 28/0-28/1 Tatiyana 171P1 105 Kankrej Patan Rabari Shedhabhai Ramabhai Tatiyana, Patan 9,608

126 28/1 Unn 1004/2 598 Kankrej Patan Javanben Karshanbhai

Charakata Unn, Patan 5,814

127 28/1-28/2 Unn 957/2P2 10 Kankrej Patan Vardhibhai Mehabhai Thakor Unn, Patan 11,372

128 28/1-28/2 Unn 1003/1/3 522 Kankrej Patan Changecha Ravaji Mohanji Unn, Patan 10,615

129 28/4-28/5 Unn 849P2 453 Kankrej Patan Raniben Vershiji Thakor Unn, Patan 6,219

130 28/5 Tatiyana 1005 489 Thara Banasakantha Somaji Chothaji Khakhlecha Tatiyana ,

Banasakantha 2,440

131 28/5-28/4 Savpura 41 54 Kankrej Patan Bhimabhai Ganeshbhai

Chaudhari Savpura, Patan 8,330

132 28/6-28/7 Savpura 37P1 45 Kankrej Patan Vinaji Chaturji Sabosana Savpura, Patan 11,296

133 28/7-28/8 Savpura 36P1 113 Kankrej Patan Shampuji Punaji Sabosana Savpura, Patan 2,712

134 28/7-28/8 Savpura 36P6 82 Kankrej Patan Punaji Ravaji Thakor Savpura, Patan 4,966

135 28/8-29/0 Savpura 35P1 106 Kankrej Patan Rameshji Ajmalji Sabosana Savpura, Patan 7,215

136 28/8-29/0 Savpura 33P5 67 Kankrej Patan Nataji Sataji Thakor Savpura, Patan 4,775

137 28/8-29/0 Savpura 33P5 67 Kankrej Patan Narkhanji Sartanji Thakor Savpura, Patan 6,219

138 28/8-29/1 Savpura 34 43 Kankrej Patan Rajuju Sagramji Thakor Savpura, Patan 20,599

139 29/0-29/1 Savpura 33P6 6 Kankrej Patan Savsiji Jethaji Thakor Savpura, Patan 16,714

140 29/0-29/1 Savpura 32P3 91 Kankrej Patan Vinaji Bajuji Thakor Savpura, Patan 6,772

141 29/0-29/1 Savpura 29P4 58 Kankrej Patan Panchabhai Surabhai Raval Savpura, Patan 5,328

142 29/1-29/2 Savpura 25/2-26/3 62 Kankrej Patan Shantaji Sangramji Thakor Savpura, Patan 8,490

143 29/2-29/3 Savpura 22P2 107 Kankrej Patan Bhagvanji Rajuji Thakor Savpura, Patan 6,100

144 30/0 Bhalgam 49 38 Kankrej Patan Bharatsih Jivubha Vaghela Anandpura, Patan 11,943

145 31/4-32/0 Anandpura - - Kankrej Patan Babubhai Jagamalbhai Mehariya Anandpura, Patan 11,634

146 32/0-32/1 Anandpura 114P1 85 Kankrej Patan Joytaji Mafaji Lotiya Anandpura, Patan 9,270

147 32/4-32/5 Anandpura 42p1 117 Kankrej Patan Dayabhai Gemarbhai Bhatkiya Anandpura, Patan 8,540

148 32/5-32/4 Anandpura 41 54 Kankrej Patan Tejaji Nanjiji Bhatkiya Anandpura, Patan 3,555

Page 186: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 186

Sl

No.

Location

No

Village

Name Plot No

Khata

No PS Dist Name of the Land Owner Address

Tree Cutting

Compensation

149 32/5-33/0 Anandpura 36P3 62 Kankrej Patan Goradhanbhai P Parjapat Anandpura, Patan 7,110

150 32/5-33/8 Anandpura 36/P1 50 Kankrej Patan Hirabhai Ramjibhai Mehriya Anandpura, Patan 8,164

151 33/3 to

33/2 Odha 42 23 Kankarej Patan Ramanbhai Bababhai Vaghri Odha,Patan 5,555

152 33/4 Odha 36P1 9 Kankrej Patan Dharasiji Nanaji Thakor Odha,Patan 4,871

153 33/4 to

33/3 Odha 40 4 Kankarej Patan Asagarbhai Nanabhai Ghiya Odha,Patan 15,611

154 33/4 to

33/3 Odha 38,P1 P1 4 Kankarej Patan Asagarbhai Nanabhai Ghiya Odha,Patan 8,380

155 33/4 to

33/3 Odha 99 18 Kankarej Patan Arjanji Hankarji Kakrecha Odha,Patan 7,110

156 34/0-33A/2 Odha 84 14 Odha Patan Bhimaji Ramshiji Thakor Odha,Patan 4,775

157 34/1-35/0 Totana 71P2 355 Kankarej Patan Laxmanbhai Jagmalbhai Patni Totana, Patan 4,161

158 34/1-35/0 Totana 97P2 253 Kankarej Patan Ajitbhai Valibhai Malakani Totana, Patan 27,835

159 35/0-35/1 Totana 48P1 236 Kankarej Patan Hiraji Panchaji Suthar Totana, Patan 11,226

160 35/1-35/2 Totana 43P1P3 377 Kankarej Patan Mobataji Hariji Unecha Totana, Patan 2,888

161 35/1-35/2 Totana 48/2 235 Kankarej Patan Velaji Pachaji Suthar Totana, Patan 4,891

162 35/1-35/2 Totana 44 90 Totana Patan Tarsangji Hariji Unecha Totana, Patan 4,891

163 35/3-35/4 Totana 28/1 46 Kankarej Patan Sonaben Bhurabhai Bharvad Totana, Patan 17,393

164 36/1-36/2 Totana 356/2 101 Patan Patan Totaniya Rayamachandji Motiji Totana, Patan 7110

165 38A/0 Kasara 120 268 Saraswati Patan Virmpuri Devpuri Goswami Kasara, Patan 10,720

166 38A/2-

38A/3 Kasara 105P2 182 Patan Patan

Bhagwanbhai Ratnabhai

Chaudhary Kasara, Patan 8,164

167 38A/3 Kasara 112/1P1 163 Patan Patan Sukhdevsinh Takhatsinh Sodha Kasara, Patan 5,890

168 39/3 Devpura 127P1 53 Patan Patan Rupabhai Arjanbhai Desai Devpura 10,167

169 39/3 Devpura 127P1 53 Patan Patan Panchabhai Arjanbhai Desai Devpura 10,167

170 40/10-

40/11 Sariyad 394 256 Saraswati Patan Nathabhai Vasharambhai Joshi Sariyad, Patan 5,995

171 40/10-

40/11 Sariyad 393/2/P1 1224 Sariyad Patan Bhemabhai Virambhai Joshi Sariyad, Patan 6,446

172 40/11 to

41/0 Sariyad 398 805 Sariyad Patan Laxmanbhai Dhulabhai Panchal Sariyad, Patan 3,977

Page 187: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 187

Sl

No.

Location

No

Village

Name Plot No

Khata

No PS Dist Name of the Land Owner Address

Tree Cutting

Compensation

173 40/11-41/0 Sariyad 40/P3 1152 Sariyad Patan Shantibhai Haribhai Joshi Sariyad, Patan 6,778

174 40/2-40/3 Sariyad 282 799 Saraswati Patan Jivanbhai Ujambhai Joshi Sariyad, Patan 9,445

175 40/4-40/5 Sariyad 151P2 64 Saraswati Patan Joshi Babubhai Jesangbhai Sariyad, Patan 15,329

176 40/4-40/5 Sariyad 308P1B 64 Sariyad Patan Santhibhai Jesungbhai Joshi Sariyad, Patan 16,223

177 40/5-40/6 Sariyad 308/1K 826 Saraswati Patan Joshi Hardevbhai Bhemjibhai Sariyad, Patan 20,667

178 40/6 to

40/7 Sariyad 315 1210 Sariyad Patan Prahlad Ramshankar Joshi Sariyad, Patan 20,205

179 40/8 Sariyad 347 822 Sariyad Patan Ambarambhai Vaghabhai Joshi Sariyad,Patan 8,991

180 40/8-40/9 Sariyad 344P1 259 Saraswati Patan Dasrathbhai Umedbhai

Chaudhari Sariyad, Patan 5,724

181 40/9-40/10 Sariyad 351 963 Saraswati Patan Brahman Ramjibhai Vaghabhai Sariyad, Patan 9,548

182 40/9-40/8 Sariyad 345 865 Saraswati Patan Devabhai Nathabhai Joshi Sariyad, Patan 9,591

183 41/0-41/1 Sariyad 403 91 Saraswati Patan Devchand Dayaram Joshi Sariyad, Patan 6,656

184 41/1-41/2 Sariyad 463/1P1P 1115 Saraswati Patan Vasudevbhai Bhanajibhai Joshi Sariyad, Patan 8,330

185 41/1-41/2 Sariyad 464/1B/P1 792 Saraswati Patan Abheram Ramshankar Joshi Sariyad, Patan 7,331

186 41/1-41/2 Sariyad 464/2 826 Saraswati Patan Joshi Hardevbhai Bhemjibhai Sariyad, Patan 11,553

187 41/2-41A/0 Sariyad 457 787 Saraswati Patan Prabhuram Jemabhai Joshi Sariyad, Patan 5,890

188 41A/0-41/2 Sariyad 479/6 591 Saraswati Patan Hirabhai Laxmanbhai Joshi Sariyad, Patan 9,212

189 41A/0-

41A/1 Sariyad 506/2 584 Saraswati Patan Desai Revabhai Vasibhai Sariyad, Patan 5,995

190 41A/1-

41A/2 Sariyad 538/P2 111 Saraswati Patan

Ranchhodbhai Bhemabhai

Chaudhary Sariyad, Patan 8,059

191 41A/1-

41A/2 Sariyad 446P 221 Saraswati Patan

Rameshbhai Ramsibhai

Chaudhari Sariyad, Patan 7,213

192 41A/2-

41A/3 Sariyad 537P1 674 Saraswati Patan

Ramilal Ben Shankar Lal

Chudhri Sariyad, Patan 4,775

193 41A/2-

41A/3 Sariyad 546/3/P1/P1 1216 Saraswati Patan Valabhai Sagrambhai Chaudhri Sariyad, Patan 5,995

194 41A/3-42/0 Sariyad 545 673 Saraswati Patan Parmabhai Devanbhai

Chaudhari Sariyad, Patan 4,775

195 41A/3-42/0 Sariyad 548 99 Saraswati Patan Valabhai Devanbhai Chaudhary Sariyad, Patan 9,548

196 42/0-42/1 Sariyad 546/2 111 Saraswati Patan Ranchhodbhai Bhemabhai

Chaudhary Sariyad, Patan 8,330

Page 188: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 188

Sl

No.

Location

No

Village

Name Plot No

Khata

No PS Dist Name of the Land Owner Address

Tree Cutting

Compensation

197 42/0-42/1 Sariyad 547/2 285 Saraswati Patan Kuriben Umedbhai Chaudhari Sariyad, Patan 7,110

198 42/0-42/1 Sariyad 530P/P 1110 Saraswati Patan Jivrajbhai Hirabhai Chaudhari Sariyad, Patan 9,445

199 42/1-42/2 Sariyad 586 1230 Saraswati Patan Visabhai Chehrabhai Rabari Sariyad, Patan 14,452

200 42/1-42/2 Sariyad 596 1229 Saraswati Patan Rabari Laxmanbhai Chehrabhai Sariyad, Patan 7,110

201 42/2-42/3 Sariyad 602/3 569 Saraswati Patan Ramjibhai Khodabhai

Chaudhari Sariyad, Patan 7,110

202 42/4-42/5 Sariyad 518 1002 Saraswati Patan Mansingbhai Demarbhai

Aanjana Sariyad, Patan 16,522

203 43/0 Lodhi 89/30 65 Patan Patan Vershibhai Kalyanbhai Rabari Lodhi,Patan 9,284

204 43/1-43/2 Lodhi 89/36/P5 198 Patan Patan Maheshbhai Heerabhai Chamar Lodhi,Patan 6,098

205 43/3 to

43/4 Lodhi 37/1 140 Patan Patan Amrutbhai Jorabhai Rabari Lodhi,Patan 12,878

206 43/3 to

43/4 Lodhi 37/3 140 Patan Patan Amrutbhai Jorabhai Rabari Lodhi,Patan 10,103

207 43/3-43/4 Lodhi 46P3 NA Lodhi Patan Thakor Rekhaji Jahuji Lodhi,Patan 19,111

208 44/0 TO

44/1 Vadiya 73/2 P 107 Patan Patan Thakor Shobhaji Vadiya,Patan 11,382

209 44/2 Vadiya 51/4 24 Patan Patan Chenjiji Dazuji Thakor Vadiya , Patan 14,179

210 44/2-44/3 Vadiya 51/2 98 Patan Patan Lalji Deshlaji Thakor Vadiya,Patan 10,283

211 44/4-44/5 Vadiya 45 19 Patan Patan Okhaji Kaluji Thakor Vadiya, Patan 13,886

212 44/5-45/0 Kalodhi 1P2 40 Patan Patan Jivanji Mulaji Thakor Kalodhi,Patan 6,219

213 45B/0-

45B/1 Malusan na na Malusan Patan Ranabhai Madhabhai Rabari Malusan, Patan 4,948

214 45B/1 Melusan 17P7 11 Patan Patan Babubhai Khengarbhai Rabari Melusan , Patan 11,553

215 45B/1 ,

45B/2 Melusan 115 294 Patan Patan Mohanbhai Malabhai Rabari Melusan , Patan 7,578

216 45B/1 ,

45B/2 Melusan 293 533 Patan Patan Bhikhabhai Malabhai Rabari Melusan , Patan 7,578

217 45B/1 ,

45B/2 Melusan 110 305 Vagdod Patan Govabhai Vasharambhai Rabari Melusan , Patan 3,392

218 45B/1-

45B/2 Melusan 6 140 Patan Patan Velabhai Cheharabhai Rabari Melusan , Patan 7,264

219 45B/2 ,

45B/3 Melusan 329 270 Patan Patan Kamshibhai Ratnabhai Rabari Melusan , Patan 10,557

Page 189: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 189

Sl

No.

Location

No

Village

Name Plot No

Khata

No PS Dist Name of the Land Owner Address

Tree Cutting

Compensation

220 45B/2 ,

45B/3 Melusan 331 132 Patan Patan Rajabhai Lebabhai Rabari Melusan , Patan 1,986

221 45B/2 ,

45B/3 Melusan 41 270 Patan Patan Kamshibhai Ratnabhai Rabari Melusan , Patan 9,113

222 45B/2 ,

45B/3 Melusan 332 115 Patan Patan Menaben Ishwarbhai Rabari Melusan , Patan 9,732

223 45B/2 ,

45B/3 Melusan 327 272 Patan Patan Talajabhai Ratnabhai Rabari Melusan , Patan 10,723

224 45B/2-

45B/3 Melusan 317 142 Patan Patan Dasharathbhai Jorabhai Rabari Melusan , Patan 11,055

225 45B/2-

45B/3 Malusan 141 983 Malusan Patan Liluben Jivabhai Rabari Malusan, Patan 9,276

226 45B/3 Malusan 1114 167 Malusan Patan Nagajibhai Mashrubhai Rabari Malusan, Patan 7,005

227 45B/3 Melusan 40 271 Patan Patan Jethabhai Ratnabhai Rabari Melusan , Patan 9,098

228 45B/3 ,

46/0 Melusan 319 292 Patan Patan Verashibhai Vasrambhai Rabari Melusan , Patan 12,873

229 46/0 Melusan 309 280 Patan Patan Taljabhai Khengarbhai Rabari Melusan , Patan 14,170

230 46/0 , 46/1 Melusan 6/2 191 Patan Patan Navdhanbhai Haribhai Rabari Melusan , Patan 7,918

231 46/0 , 46/1 Melusan 318 152 Patan Patan Govabhai Vasharambhai Rabari Melusan , Patan 6,020

232 46/0 , 46/1 Melusan 6/2 191 Patan Patan Babubhai Haribhai Rabari Melusan , Patan 8,376

233 46/1 , 46/2 Melusan 297 120 Patan Patan Maganbhai Tejabhai Rabari Melusan , Patan 8,388

234 46/1-46/2 Melusan 298 326 Patan Patan Mohanbhai Tejabhai Rabari Melusan , Patan 8,123

235 46/2 , 46/3 Dhanasara 44 153 Vagdod Patan Kashirambhai Pachanbhai Joshi Dhanasara , Patan 7,558

236 46/4 Dhanasara 31 56 Dhanasara Patan Jayantibhai R. Joshi Dhanasara , Patan 8,763

237 46/4 , 46/5 Dhanasara 23P1 87 Vagdod Patan Kanaiyalal Hargovanbhai Joshi Dhanasara , Patan 5,996

238 46/4 , 46/5 Dhanasara 24P4 18 Vagdod Patan Ramehwarbhai Trikambhai

Joshi Dhanasara , Patan 11,658

239 46/4 , 46/5 Dhanasara 32P2 75 Vagdod Patan Ramjibhai Karshanbhai Joshi Dhanasara , Patan 6,446

240 46/5-47/0 Dharusan 75P2P2 317 Saraswati Patan Babubhi Mahadevbhai Brahman Dharusan, Patan 13,337

241 47/0 Dharusan 74/6 210 Saraswati Patan Hardevbhai Lakhirambhai Joshi Dharusan, Patan 11,372

242 47/0-47/1 Dharusan 76/6/P1 41 Dharusan Patan Mansukhbhai Laxmiram Joshi Dharusan, Patan 6,944

243 47/0-47/1 Dharusan 74/5 186 Dharusan Patan Sahdevbhai Ramjibhai Joshi Dharusan, Patan 14,039

Page 190: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 190

Sl

No.

Location

No

Village

Name Plot No

Khata

No PS Dist Name of the Land Owner Address

Tree Cutting

Compensation

244 47/0-47/1 Dharusan 716P2 241 Patan Patan Joshi Amratbhai Vajrambhai Dharusan, Patan 15043

245 47/1 Dharusan 61/2/P1 255 Patan Patan Jayantibhai Trikambhai Joshi Dharusan, Patan 19035

246 47/1 Dharusan 62/1P2 287 Patan Patan Jayram Muljibhai Dharusan, Patan 10353

247 47/1-47/2 Dharusan 49/3P1 260 Saraswati Patan Dayabhai Jesungbhai Joshi Dharusan, Patan 3,479

248 47/1-47/2 Dharusan 61/2 257 Patan Patan Jagannathbhai Tikambhai Joshi Dharusan, Patan 19035

249 47/3-47/4 Kanosan 46P1 95 Saraswati Patan Ladjiji Pratapji Thakor Kanosan,Patan 20,176

250 47/3-47/4 Kanosan 47P1 98 Saraswati Patan Abheseeng Swarupji Thakore Kanosan,Patan 13,495

251 47/3-47/4 Kanosan 48P4 69 Saraswati Patan Veejayseeng Badsangji Thakore Kanosan,Patan 8,222

252 47/3-47/4 Kanosan 48P2 103 Saraswati Patan Ajmalji Dhiraji Thakore Kanosan,Patan 5,995

253 47/3-47/4 Kanosan 46P3 97 Patan Patan Sahdevji P. Thakor Kanosan, Patan 2607

254 47/4-48/0 Kanosan 53P1 111 Saraswati Patan Ashokji Jogaji Thakor Kanosan,Patan 31,728

255 47/4-48/0 Kanosan 54/1P1 61 Saraswati Patan Dalsangji Khumaji Thakore Kanosan,Patan 5,995

256 48/0 Kanosan 60 P2 116 Sharashwati Patan Madarji G Thakore Kanosan,Patan 12,878

257 49/0-49/1 Kanosan 85/1 84 Saraswati Patan Dargaji Hadaji Thakore Kanosan,Patan 5,993

258 49/0-49/1 Kanosan 85/3P2 129 Saraswati Patan Karshanji Thakhtji Thakor Kanosan,Patan 6,938

259 49/0-49/1 Kanosan 55P3 113 Saraswati Patan Genaji V Thakor Kanosan,Patan 8,991

260 49/0-49/1 Kanosan 85/3P1 128 Saraswati Patan Gamaji Kadvaji Thakore Kanosan,Patan 12,767

261 49/1 to

49/0 36 P 3 85/2 127 Saraswati Patan Fulaji Chandanji Thakor Kanosan,Patan 16,549

262 49/1-49/2 Kanosan 161P1 130 Saraswati Patan Dargaji Hadaji Thakore Kanosan,Patan 8,549

263 49/1-49/2 Kanosan 161P2 131 Saraswati Patan Agraji Vanvirji Thakore Kanosan,Patan 10,438

264 49/2-49/3 Kanosan 159 128 Saraswati Patan Ramanlal Chunilal Panchal Kanosan,Patan 12,939

265 49/2-49/3 Kanosan 123 147 Saraswati Patan Shivjiji Nathaji Thakor Kanosan,Patan 5,995

266 49/2-49/3 Ganeshpura 184/2 201 Kankrej Patan Gemarbhai Bababhai Rabari Ganeshpura, Patan 7,461

267 49/3 to49/4 Ganeshpura 240 21 Sarashwati Patan Ishwarbhai Khodabhai Rabari Ganeshpura,Patan 17,304

268 49/34

to49/5 Ganeshpura 201 21 Sarashwati Patan Ishwarbhai Khodabhai Rabari Ganeshpura,Patan 7,925

269 49/3-49/4 Ganeshpura 199 319 Kankrej Patan Samuben Maganbhai Rabari Ganeshpura, Patan 10,052

270 49/4 to

49/5 Ganeshpura 198 250 Sarashwati Patan Babubhai Sartanbhai Rabari Ganeshpura,Patan 9,291

Page 191: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 191

Sl

No.

Location

No

Village

Name Plot No

Khata

No PS Dist Name of the Land Owner Address

Tree Cutting

Compensation

271 49/4-49/5 Ganeshpura 269P 75 Kankrej Patan Ramsangji Hariji Rajput Ganeshpura, Patan 9,116

272 49/5-49/6 Ganeshpura 155P2 199 Saraswati Patan Gobarbhai Haribhai Rabari Ganeshpura, Patan 6,995

273 49/5-49/6 Ganeshpura 154/2 294 Kankrej Patan Kamsibhai Sartanbhai Rabari Ganeshpura, Patan 9,279

274 49/5-49/6 Ganeshpura 255P2 15 Kankrej Patan Somabhai Odharbhai Rabari Ganeshpura, Patan 8,825

275 49/6 to 49/7 Ganeshpura 142 226 Sarashwati Patan Ramjibhai Ramchandbhai Raval Ganeshpura,Patan 6,956

276 49/6 to 49/7 Ganeshpura 145 335 Sarashwati Patan Ramjibhai Ramchandbhai Raval Ganeshpura,Patan 6,390

277 49/6-49/7 Ganeshpura 156 33 Kankrej Patan Kanjibhai Sartanbhai Rabari Ganeshpura, Patan 8,276

278 49/6-49/7 Ganeshpura 128 23 Kankrej Patan Pratapji Galabji Rajput Ganeshpura, Patan 9,343

279 49/6-49/7 Ganeshpura 155P1 167 Kankrej Patan Ishaben Talajabhai Rabari Ganeshpura, Patan 9,838

280 49/8-50/0 Ganeshpura 125P1 167 Kankrej Patan Vaghjibhai Varvabhai Rabari Ganeshpura, Patan 6,474

281 49/8-50/0 Ganeshpura 82 3 Kankrej Patan Amthabhai Ramabhai Rabari Ganeshpura, Patan 4,417

282 50/0 Ganeshpura 79 P 2 175 Sarashwati Patan Somabhai Jorabhai Rabari Ganeshpura,Patan 16,411

283 50/0-50/1 Abluva 265/1 78 Patan Patan Varsangji Mohanji Thakore Abluva, Patan 8,330

284 50A/0 Abluva 272 257 Patan Patan Nagajibhai Maganbhai Darji Abluva, Patan 7,903

285 50A/1 Abluva 285P2 226 Patan Patan Balvantji B. Thakor Abluva, Patan 5108

286 50A/2-51/0 Abluva 329 514 Patan Patan Isvarbhai Cheharbhai Rabari Abluva, Patan 8,330

287 50A/2-51/0 Abluva 325 515 Patan Patan Amratbhai Chehrabhai Rabari Abluva, Patan 8,330

288 51/1-51/2 Abluva 342 698 Patan Patan Thakor Bhalaji Versiji Abluva, Patan 16,096

289 51/1-51/2 Abluva 88P1 596 Patan Patan Amratbhai Nathabhai Rabari Abluva, Patan 7,832

290 51/2-51/3 Abluva 366/P3 85 Patan Patan Amratbhai Jivvabhai Rabari Abluva, Patan 7,110

291 51/4-51A/0 Abluva 387/1P2 196 Patan Patan Amratbhai Maganbhai Rabari Abluva, Patan 8,330

292 51B/0-51B/1 Abluva 386/1P1 620 Patan Patan Dineshbhai Amthabhai Rabari Abluva, Patan 8,825

293 51B/0-51B/1 Abluva 387/1P3 325 Patan Patan Kanjibhai Amathabhai Rabari Abluva, Patan 8,330

294 51B/0-51B/1 Abluva 387/5 129 Patan Patan Ibrahimbhai Alimadbhai

Muman Abluva, Patan 2335

295 51B/1-51B/2 Abluva 373/1P 526 Patan Patan Ambalal Hemchand Panchal Abluva, Patan 5,995

296 51B/2-51B/3 Delvada 149P 13 Saraswati Patan Bharatkumar Kantilal Barot Jarusha, Patan 5,945

297 53/0-56/0 Jangral 464/2P 497 Jangral Patan Thakorlal Jagnnathbhai Barot Jangral, Patan 6,474

298 56/0 Jangral 474 109 Patan Patan Jayeshbhai J. Barot Jangral, Patan 10,789

TOTAL 28,92,990

Page 192: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 192

Annexure 12: Tree Cutting Compensation_400 KV Charanka Veloda Transmission Line

Sr. No. Name Location No Tree Cutting

Compensation DD No DD Date

1 Narkhanbhai Bajubhai Thakor 26/6 TO 26/7 7,188.00 007780 28.06.17

2 Chaudhari Khetabhai Chelabhai 26/6 TO 26/7 2,440.00 007781 28.06.17

3 Melaji Dhamaji Ranavadiya 27/5 TO 27/6 1,220.00 007782 28.06.17

4 Valaji Dhamaji Thakor 27/5 TO 27/6 10,651.00 007783 28.06.17

5 Shivaji Motiji Khakhlecha 28/0 TO 28/1 1,130.00 007784 28.06.17

6 Hamirbhai Ramabhai Rabari 28/1 TO 28/2 3,060.00 007785 28.06.17

7 Lilabhai Rajabhai Desai 28/1 TO 28/2 722.00 007786 28.06.17

8 Lagdhirji Jemaji Thakor 28/1 TO 28/2 1,444.00 007787 28.06.17

9 Shankarji Rugnathbhai Thakor 28/1 TO 28/2 4,060.00 007788 28.06.17

10 Ramabhai Rajabhai Desai Luni 28/2 TO 28/3 1,508.00 007789 28.06.17

11 Hirabhai Rajabhai Luni 28/2 TO 28/3 1,005.00 007790 28.06.17

12 Punaji Ravaji Thakor 28/7 TO 28/8 2,082.00 007564 21.06.17

13 Shampuji Punaji Sabosana 28/7 TO 28/8 2,486.00 007565 21.06.17

14 Rameshji Babaji Sabosana 28/10 TO 28/11 2,952.00 007566 21.06.17

15 Chmanji Sonaji Thakor 28/10 TO 28/11 8,500.00 007567 21.06.17

16 Thakor Shankarji Sagramji 28/11 TO 28/12 765.00 007568 21.06.17

17 Raduji Sagramji Thakor 28/11 TO 28/12 5,965.00 007569 21.06.17

18 Shantaji Sagramji Thakor 28/11 TO 28/12 4,930.00 007570 21.06.17

19 Talaji Chaturji Thakor 31/0 TO 32/0 7,830.00 007571 21.06.17

20 Madhji Chaturji Thakor 31/0 TO 32/0 2,270.00 007572 21.06.17

21 Keshaji Raychandji Sabosana 31/0 TO 32/0 8,015.00 007573 21.06.17

22 Kirankumar Mohanlal Parmal 33/4 TO 34/0 11,807.00 007574 21.06.17

23 Bababhai Shankarbhai Sapriya 33/4 TO 34/0 2,960.00 007575 21.06.17

24 Maganji Kheta 34/0 1,730.00 007576 21.06.17

25 Sagtajee Ravajee Kakrecha 34/0 TO 34/1 4,603.00 007577 21.06.17

26 Samjibhai Nanjibhai Tharecha 34/0 TO 34/1 7,935.00 007578 21.06.17

27 Maganji Kheta 34/0 TO 34/1 9,009.00 007582 22.06.17

28 Safudi Husainbhai Ghiya 34/1 TO 34/2 11,505.00 007583 22.06.17

29 Barot Kiranbhai Rameshbhai 34/2 TO 34/3 5,008.00 007584 22.06.17

30 Arjanbhai Shankarji Kahrecha 34/3 TO 34/4 8,060.00 007585 22.06.17

31 Fakruddin Yusuf Ali Giya 34/4 TO 34/5 3,980.00 007586 22.06.17

32 Abdulhusen Fakaruddeen Ghia 34/4 TO 34/5 6,822.00 007587 22.06.17

33 Joraji Nagjiji Ludariya 34/4 TO 34/5 4,880.00 007588 22.06.17

34 Bhemabhai Valmaji Ludariya 34/5 TO 34/6 3,050.00 007589 22.06.17

35 Raghuji Kanaji Thakor 34/6 TO 34/7 3,531.00 007590 22.06.17

36 Ramabhai Mohanbhai Patni 34/7 1,406.00 007591 22.06.17

37 Dhanjibhai Kasubhai Vaghari 34/8 TO 34/9 4,060.00 007592 22.06.17

38 Dodia Mohaseenbhai Ismailji 34/10 12,571.00 007593 22.06.17

39 Saratanji Ravaji Thakor 37/6 TO 37/7 3,444.00 007594 22.06.17

40 Hemaji Punjaji Thakor 38/0 TO 38/1 1,864.00 007595 22.06.17

41 Sarupji Rashungji Thakor 38/1 TO 39/0 4,580.00 007596 22.06.17

42 Chenaji Punaji Thakor 38/1 TO 39/0 2,211.00 007597 22.06.17

43 Rameshji Punaji Thakor 38/1 TO 39/0 8,830.00 007598 22.06.17

44 Chandanji Bajuji Thakor 38/1 TO 39/0 10,300.00 007599 22.06.17

45 Balaji Mobtaji Thakor 38/1 TO 39/0 3,083.00 007740 23.06.17

46 Galabji Chatraji Thakor 39/0 TO 39/1 3,522.00 007741 23.06.17

47 Balawatji Ravaji Thakor 39/0 TO 39/1 1,220.00 007742 23.06.17

48 Vershiji Talaji Thakor 39/0 TO 39/1 11,105.00 007743 23.06.17

49 Kantibhai Valabhai Vaghri 39/1 TO 39/2 5,252.00 007744 23.06.17

50 Kantibhai Valabhai Vaghri 39/2 TO 39/3 2,157.00 007745 23.06.17

51 Shankarbhai Mavjibhai Chaudhari 39/2 TO 39/3 3,291.00 007746 23.06.17

52 Shankarbhai Mavjibhai Chaudhari 39/2 TO 39/3 1,722.00 007747 23.06.17

53 Chaudhari Virambhai Velabhai 39/2 TO 39/3 5,856.00 007748 23.06.17

54 Mohansing Jalamsing Jadeja 39/3 TO 39/4 9,141.00 007749 23.06.17

55 Nanajibhai Jevatbhai Chaudhari 39/3 TO 39/4 8,626.00 007750 23.06.17

56 Devjibhai Tejabhai Chaudhary 39/3 TO 39/4 4,020.00 007751 23.06.17

Page 193: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 193

57 Devjibhai Tejabhai Chaudhary 39/4 TO 39/5 8,752.00 007752 23.06.17

58 Bhagabhai Ramabhai Chaudhari 39/4 TO 39/5 8,835.00 007753 23.06.17

59 Rayachandbhai Khodabhai Chauhan 39/4 TO 39/5 7,220.00 007754 23.06.17

60 Gandabhai Bhavabhai Rabari 39/5 TO 39/6 2,302.00 007755 23.06.17

61 Cheharabhai Jemabhai Patel 39/5 TO 39/6 1,500.00 007756 23.06.17

62 Mohanbhai Jemabhai Chaudhri 39/6 TO 39/7 10,787.00 007757 23.06.17

63 Mohanbhai Jemabhai Chaudhri 39/6 TO 39/7 1,417.00 007758 23.06.17

64 Bababhai Lebabhai Desai 39/6 TO 39/7 3,720.00 007759 27.06.17

65 Devrajbhai Paragbhai Patel 39/6 TO 39/7 7,642.00 007760 27.06.17

66 Bhanajibhai Damrbhai Jishi 39/7 TO 39/8 1,469.00 007761 27.06.17

67 Lakhiram Damarbhai Joshi 40/1 TO 40/2 6,944.00 007762 27.06.17

68 Jivrambhai Iswar Bhai Joshi 40/1 TO 40/2 3,933.00 007763 27.06.17

69 Bhanjibhai Damarbhai Joshi 40/1 TO 40/2 10,980.00 007764 27.06.17

70 Shamjibhai Ambaram Bhai Joshi 40/2 TO 40/3 3,172.00 007765 27.06.17

71 Jesungbhai Laxmanbhai Chaudhary 41/1 2,250.00 007766 27.06.17

72 Ranchodbhai Ramabhai Chudhri 41/1 TO 41/2 2,557.50 007767 27.06.17

73 Jesangbhai Bhemabhai Chaudhary 41/2 TO 41/3 1,001.00 007768 27.06.17

74 Kankuben Bhavabhai Chaudhri 41/3 TO 41/4 2,746.00 007769 27.06.17

75 Kankuben Bhavabhai Chaudhri 41/3 TO 41/4 8,610.00 007770 27.06.17

76 Govindbhai Ganeshbhai Chaudhri 41/3 TO 41/4 2,913.00 007771 27.06.17

77 Umedbhai Virabhai Chaudhary 42/1 TO 42/2 4,845.00 007772 27.06.17

78 Sendhabhai Khemabhai Chamar 42/1 TO 42/2 2,695.00 007773 27.06.17

79 Manshibhai Damarbhai Chudhri 42/2 TO 42/3 1,830.00 007774 27.06.17

80 Chandkhan Alikhan Baloch 42/2 TO 42/3 7,235.00 007775 27.06.17

81 Nathekhan Bhikhankhan Baloch 42/2 TO 42/3 9,722.00 007776 27.06.17

82 Sanjaybhai Punabhai Chamar 42/2 TO 42/3 9,495.00 007777 27.06.17

83 Rabari Jamabhai Rama Bhai 43/3 10,900.00 007791 28.06.17

84 Manshibhai Damarbhai Chudhri 42/3 TO 42/4 1,220.00 007796 28.06.17

85 Naranbhai Karsanbhai Rabari 42/3 TO 42/4 8,397.00 007792 28.06.17

86 Rabari Nagajibhai Vashrambhai 42/4 TO 42/5 4,305.00 007793 28.06.17

87 Mohanbhai Bijolbhai Rabari 42/5 TO 42/6 4,041.00 007794 28.06.17

88 Laxmanbhai Haribhai Rabari 42/6 TO 43/0 2,255.00 007795 28.06.17

89 Ramjibhai Panchbhai Chaudhari 21B/3 TO 21B/4 16,000.00 007817 11.07.17

90 Dadamben Valabhai Thakor 15/0 TO 15/1 2,995.00 007818 11.07.17

91 Thakor Mukeshbhai Arajanbhai 15/0 TO 15/1 1,550.00 007819 11.07.17

92 Rugnathbhai Lagdhirbhai Thakor 15/1 TO 15/2 4,885.00 007820 11.07.17

93 Virambhai Jivabhai 17/5 TO 17/6 8,141.00 007821 11.07.17

94 Baluben Haribhai 17/6 TO 17/7 3,050.00 007822 11.07.17

95 Rukhiben Chamanbhai Suthar 17/6 TO 17/7 5,730.00 007823 11.07.17

96 Ganibhai Husenbhai Sipai 17/6 TO 17/7 5,105.00 007824 11.07.17

97 Rameshbhai Pachanbhai Patel 17/6 TO 17/7 2,835.00 007825 11.07.17

98 Manaben Hemrajbhai Patel 17/8 TO 17/9 5,505.00 007826 11.07.17

99 Babubhai Harkhabhai Soalanki 18/4 TO 18/5 3,767.00 007827 11.07.17

100 Ishwarbhai Dannabhai Prajapati 18/4 TO 18/5 2,888.00 007828 11.07.17

101 Virajibhai Bhemabhai Thakor 18/4 TO 18/5 9,152.00 007829 11.07.17

102 Virambhai Vershibhai Tahkor 18/5 TO 18/6 3,729.00 007830 11.07.17

103 Amthubhai Ravatbhai Thakor 18/5 TO 18/6 4,405.00 007831 11.07.17

104 Kanubhai Bharmal Thakor 18/5 TO 18/6 8,670.00 007832 11.07.17

105 Lataben Ramabhai Joshi 21B/0 3,570.00 007833 11.07.17

106 Vasudevbhai Somnath Thakar 21B/0 TO 21B/1 6,340.00 007834 11.07.17

107 Jethabhai Khodabhai Chaudhari 21B/4 TO 21B/5 920.00 007835 11.07.17

108 Meghabhai Ramsibhai Patel 21B/9 TO 21B/10 2,755.00 007836 11.07.17

109 Veerabhai Chelabhai 21B/9 TO 21B/10 3,398.00 007798 11.07.17

110 Thakor Shankar Bhai Mohanbhai 21B/11 TO 22/0 7,430.00 007799 11.07.17

111 Dayabhai Govindbhai Thakor 21B/11 TO 22/0 5,505.00 007800 11.07.17

112 Balvantbhai Manabhai Chaudhary 21B/11 865.00 007801 11.07.17

113 Harijan Daniben Gandabhai 22/0 2,820.00 007802 11.07.17

114 Hemaji Khetaji Thakor 23/1 TO 23/2 14,751.00 007803 11.07.17

115 Chothiben Ranchhodbhai Thakor 23/1 TO 23/2 4,997.00 007804 11.07.17

Page 194: Updated Resettlement Plan and Social Due- Diligence Report · X IMPLEMENTATION SCHEDULE 38 XI MONITORING AND REPORTING 39 . Page 3 Page ... "Loan - 2778 (IND): Gujarat Solar Power

Page 194

116 Ajmalbhai Dharmshibhai Thakor 23/5 TO 23/6 1,837.00 007805 11.07.17

117 Hemabhai Lakhamanbhai Choudhari 23/5 TO 23/6 10,358.00 007806 11.07.17

118 Bhemabhai Manabhai Chaudhary 23/5 TO 23/6 5,410.00 007807 11.07.17

119 Ishvarbhai Harchand Bhai Thakor 23/5 TO 23/6 1,020.00 007808 11.07.17

120 Savshibhai Ramabhai Thakor 23/6 TO 23/7 4,880.00 007809 11.07.17

121 Hemabhai Lakhamanbhai Choudhari 23/6 TO 23/7 2,440.00 007810 11.07.17

122 Popatbhai Ramabhai Thakor 23/7 TO 23/8 6,010.00 007811 11.07.17

123 Shankarbhai Jasvantbhai Chaudhary 23/7 TO 23/8 6,535.00 007812 11.07.17

124 Vasharambhai Rajabhai Chaudhary 23/8 TO 23/9 5,290.00 007813 11.07.17

125 Shradhdaben Natwarpuri Gouswami 23/8 TO 23/9 11,730.00 007814 11.07.17

126 Jesangbhai Valabhai Dave 24/0 TO 25/0 935.00 007815 11.07.17

127 Kamabhai Laxmanbhai Patel 24/0 TO 25/0 1,566.00 007816 11.07.17

128 Jijiben Saktabhai Bharvad 26/0 TO 26/1 12,032.00 007838 12.07.17

129 Vashrambhai Vajabhai Patel 26/0 TO 26/1 11,724.00 007839 12.07.17

130 Chaudhari Bharatbhai Parbatbhai 26/3 TO 26/4 14,517.00 007840 12.07.17

131 Manjibhai Ranchod Panchal 26/3 TO 26/4 8,355.00 007841 12.07.17

132 Manabhai Jagmalbhai Thakor 26/3 TO 26/4 7,350.00 007842 12.07.17

133 Haribhai Ranchhodbhai Panchal 26/4 TO 26/5 3,207.00 007843 12.07.17

134 Rabari Malabhai Ramjibhai 26/4 TO 26/5 16,009.00 007844 12.07.17

135 Sitaram Manordas Sadhu 26/5 TO 26/6 3,164.00 007845 12.07.17

136 Melubhai Arjanbhai Thakor 26/5 TO 26/6 6,525.00 007846 12.07.17

137 Sadho Raghurambhai Manordas 26/5 TO 26/6 4,915.00 007847 12.07.17

138 Tejabhai Ratnabhai Chaudhari 26/6 TO 26/7 6,460.00 007855 12.07.17

139 Naranbhai D Patel 26/6 TO 26/7 11,310.00 007848 12.07.17

140 Ganeshbhai Jayntibhai Panchal 26/6 TO 26/7 5,000.00 007849 12.07.17

141 Madevbhai Ratnabhai Choudhari 26/6 TO 26/7 12,880.00 007850 12.07.17

142 Solanki Daniben Ratnabhai 26/9 TO 26/10 3,050.00 007856 12.07.17

143 Naranbhai Narsungabhai Patel 26/17 TO 26/18 3,110.00 007851 12.07.17

144 Goswami Padampuri Valpuri 26/19 TO 26/20 7,280.00 007852 12.07.17

145 Chaudhary Sodabhai Ajubhai 26/19 TO 26/20 3,720.00 007853 12.07.17

146 Patel Jagmalbhai Memabhai 26/20 TO 27/0 7,280.00 007854 12.07.17

TOTAL 7,86,712


Recommended