UPDATES ON HLURB POLICIES
Before
• DAR conversion order - a mandatory documentary requirement before the issuance of a certificate of registration and license to sell.
Now
DAR conversion order – no longer a requirement in the issuance of certificate of
registration and license to sell if the property is already classified as residential,
commercial, industrial under the CLUP
Documentary requirements for the certificate of registration and license to sell relaxed
(Board Res. 748, 17 September 2003)
BeforeBuilding permit – a
mandatory requirement prior to the issuance of registration and license to sell for condominium
projects
Now
Building permit - only a post requirement to the registration and
licensing of condominium projects
(Board Res. 756, 17 December 2003)
Board Resolution no.756 series of 2003
• Issuance of temporary license to sell for condominium projects now allowed
Before• Signatories to site
development plan:– Architect who is an
environmental planner; or– Civil engineer who is an
environmental planner; or– Geodetic engineer who is an
environmental planner; or– An architect + EP– Civil engineer + EP– Geodetic engineer + EP
Now
Authorized signatory is not limited to environmental
plannersArchitect or civil engineer
or geodetic engineer or environmental planner
are now allowed signatories
(Res. 794, 11 September 2006)
Developers required to submit a copy of the special/temporary permit from the
PRC and of the separate permit from the DOLE for foreign architects hired to
prepare and sign plans
Board Resolution 839, 25 May 2009
(Resolution No. 812, S. of 2007)
Before
• Waiting period of 2 weeks after publication
• Total processing time was 33 days
Now
• Waiting period reduced to 5 days after publication
• One time computation of fees allowed
Processing time now 21 days
• Establishment of a pilot area in Luzon• Establishment of similar OSS in Visayas
and Mindanao Regions
One-Stop-Shop Processing CenterResolution no. 833, Series of 2009
Recommended to the DILG the adoption by the LGUs of standard requirements in the
issuance of development permits for subdivision project
Res. 834, 25 February 2009
Minimum lot frontage
Before• For rowhouse = 4m
Now
3.5m.
Rationale: Previous rules on minimum lot frontage is 3.5 m; while National Building Code permits 3.00 m. frontage for accessoria type of housing
Amendments to development standards for socialized housing projects
(resolution no. 824, series of 2008)
Minimum lot area (for socialized housing projects)
Before
• For row house= 32 sq.m.
Now
28 sq.m.
Rationale: Allowing 3.5 m. frontage and 8.0 meter lot depth, minimum lot is reduced to 28 sq.m.
BeforeFireblock
When 2 living units abut each other, fireblock of masonry construction required
FirewallFirewall required for duplex/single attached units and at every unit for rowhouses.
Now• Provision on fireblock under
deleted.Rationale: to resolve conflicting provisions on fireblock and firewall.
• Ceiling should be compartmentalized and not continuous from one living unit to another.
Rationale: for safety purposes
Fireblock and Firewall
BeforeFor multi-family dwellings, the parking required is in accordance with the provisions of the National Building Code and its IRR.(1 slot per dwelling unit)
Now
One parking slot per 8 dwelling units without size qualification
Rationale: Adopt the minimum requirement of the NBC without any qualification in terms of floor area. Target beneficiaries of BP 220 are not expected to have personal vehicles
The driveway may be used as parking area provided that the minimum right-of-way shall be maintained.
Parking Requirement
BeforeProvision of elevators is in accordance with the requirements of the National Building Code of the Philippines. (elevator required for 5 storey buildings and above)
NowOriginal provision of old NBC applied (elevator required for buildings of six storeys and above)
Rationale: 1.Cost of putting up elevator and its subsequent maintenance is staggering for low end beneficiaries2.NBC provides in its scope of application that buildings under BP 220 are not covered by NBC
Elevator
Participation in the following now allowed as compliance:• Resettlement
– Northrail and southrail linkage projects administered by NHA
(res. 805, 16 May 2007)• Joint venture project with housing agencies and LGUs
(Res. 811, 12 Nov. 2007)• Community Mortgage Projects (CMP)
– As developer or financier
Expanded Modes of compliance to section 18 of RA 7279
• Gawad Kalinga projects (Res. 819, 21 July 2008)
• Socialized condominium (Res. 777, 7 February 2005)
• Habitat for Humanity projects (Res. 831,30Jan. 2009)
• HGC and Pag-ibig Bonds• Advance credit – projects for 10 years old and
below(Res. 843, 31 July 2009)
Expanded modes of compliance continued
HLURBCLASSIFICATION
Classification per HUDC Res. 05, S. of 2007 & Res. 01,S. of 2008
Price ceiling Standards Applied
Socialized Low-cost level 1A 400,000 and below
BP 220 socialized
Economic Level 1BAbove 400,000 to 1,250,000
BP 220 economic
Level 2 BP 220 economicLevel 3 PD 957 medium
costMedium Cost Medium cost Above 3M-4M PD 957 medium
costOpen Market Open Market Above 4M PD 957 open
market
Clarification on applicable development standards to levels of housing classification by HUDCC
(Res. 835, 26 March 2009)
Before Now
Planting of trees in areas designated as planting strip not required
Planting of trees in areas designated as planting
strip required.
The concern and public clamor for greening residential subdivisions was addressed.
Policies to ensure completion of projectsBoard Res. 775, 06 December 2004
Requiring developers to submit an inventory of housing units
constructed for the period 2005-2007 and a quarterly
report on the number of housing units actually
constructed as a condition to the issuance of CR/LS
Board Res. 817, 16 April 2008
To monitor private sector contribution to one million homes program of the government.
Before
Minimum level of development required prior to issuance of license to sell
• For subdivision projects- land clearing, grubbing, road tracing, sub base and base preparation, and gate if advertised
. For condominium projects – civil and structural works of foundation to include excavation per approved plan, excavation permit, pile driving, concreting, steel reinforcement and formworks.
Now• For subdivision projects – land
clearing and grubbing, road tracing, sub-base and base preparation and gate if reflected in brochure, advertisement
• For condominium projects – civil and structural works of foundation to include excavation per approved plan/excavation permit, pile driving, concreting, steel reinforcement and formworks
Minimum level of development requirement for CR/LS of subdivision and condominium projects
Res. 830-A, 28 November 2008 (10Sept.2009)
Requiring minimum level of development for projects in compliance to Section 18 of RA 7279 by way of joint venture with local government units prior to the issuance of license to sell.
Resolution No. 836, series of 2009
Guidelines for the registration of northrail; southrail(emorandum Circular no. 25 & 29, S. of 2006)
Declaring off-site Gawad Kalinga projects as projects not covered by the license to sell of HLURB (Res. 820, 21 July 2008)
Declaring Habitat for Humanity Philippines projects as projects not covered by the License to Sell of HLURB (Res. 823, 17 October 2008)
Related issuances to Section 18