UPGRADE AND REPLACE BUILDING 123
STEAM LINE PIPING AND INSULATION Project No. 695-17-103
For the
Department of Veterans Affairs
Clement J. Zablocki Veterans Medical Center 5000 West National Avenue
Milwaukee, WI. 53295
PROJECT SPECIFICATIONS Bid Documents
February 15, 2017
GUIDON DESIGN, INC.
PROJECT CONTACTS:
OWNER: CLEMENT J. ZABLOCKI VA MEDICAL CENTER Attn: Kevin Matthews 5000 West National Avenue Attn: Facility Management Division Building 70, Room 250E Milwaukee, WI 53295 Phone: (414) 384-2000 x45723 email: [email protected]
CIVIL ENGINEER: GUIDON DESIGN, INC. Attn: Kyle Cyr 905 North Capitol Avenue Suite 100 Indianapolis, IN 46204 Phone: (317) 800-6388 x110 email: [email protected]
MECHANICAL ENGINEER: RING & DUCHATEAU, LLP Attn: Josh Nickols 17400 West Capitol Drive Brookfield, WI 53405 Phone: (414) 778-7421 email: [email protected]
Milwaukee VAMC February 15, 2017 Upgrade and Replace Building 123 Bid Set Submission Steam Line Piping and Insulation Project No. 695-17-103
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRSVHA MASTER SPECIFICATIONS
TABLE OF CONTENTS Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 15 List of Drawing Sheets 07-1500 31 00 Summary Report VA Hospital Utility Line Openings
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-1501 01 10 1HR 1 Hour Construction Smoke Barrier 03-1601 01 10 FSS Fire Safety and Control 11-1501 01 10 IC Infection Control 03-1601 01 10 SN Special Notes 07-1601 12 16 Work Schedule 11/1501 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 11/1501 33 23 Shop Drawings, Product Data, and Samples 07-1501 35 26 Safety Requirements 04-15
01 45 29 Testing Laboratory Services 06-1601 57 19 Temporary Environmental Controls 01-1101 74 19 Construction Waste Management 09-1301 74 19 A Construction Waste Management Appendix
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 02-1502 42 00 Cutting, Removal, Demolition, Restoration and Patching 11-15
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 12-15
DIVISION 05 – METALS
05 50 00 Metal Fabrications 07-14
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 13 52 Modified Bituminous Sheet Waterproofing 08-16
DIVISION 09 – FINISHES
09 06 00 Schedule for Finishes 04-15
Milwaukee VAMC February 15, 2017 Upgrade and Replace Building 123 Bid Set Submission Steam Line Piping and Insulation Project No. 695-17-103
00 01 10-2
09 91 00 Painting 01-16 DIVISION 26 – ELECTRICAL 26 05 11 Requirements for Electrical Installations 01-16 26 05 19 Low-Voltage Electrical Power Conductors and Cables 07-13 26 05 26 Grounding and Bonding for Electrical Systems 12-12 26 05 33 Raceway and Boxes for Electrical Systems 05-14 26 05 41 Underground Electrical Construction 12-12 26 27 26 Wiring Devices 01-16 26 29 21 Enclosed Switches and Circuit Breakers 12-12 26 56 00 Exterior Lighting 11-14 DIVISION 31 – EEARTHWORK 31 20 00 Earthwork 07-16 31 23 19 Dewatering 10-12 31 23 23.33 Flowable Fill 10-12 DIVISION 32 – EXTERIOR IMPROVEMENTS 32 05 23 Cement and Concrete for Exterior Improvements 08-16 32 12 16 Asphalt Paving 09-15 32 17 23 Pavement Markings 08-16 32 90 00 Planting 08-16 DIVISION 33 – UTILITIES 33 10 00 Water Utilities 01-14 33 63 00 Steam Energy Distribution 06-13
Milwaukee VAMC February 15, 2017
Upgrade and Replace Building 123 Bid Set Submission
Steam Line Piping and Insulation Project No. 695-17-103
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWINGS
The drawings listed below accompanying this specification form a part of the
contract.
Drawing No. Title
GI100 Cover Sheet
GI101 General Notes
GI102 Maintenance of Traffic
VF101 Topographic Survey
CS100 Demolition and Restoration Plan
CS500 Site Restoration Details
CU100 Overall Site Map
CU101 Plan and Profile Sta 0+00 to 2+00
CU102 Plan and Profile Sta 2+00 to 4+50
CU103 Plan and Profile Sta 4+50 to 7+90
CU250 Existing Steam Pit S6 Demolition Plan and
Sections
CU251 Existing Steam Pit S6 New Construction Plan and
Sections
CU252 New Steam Pit S7 New Construction Plan Sections
CU253 Building 123 Mechanical Room Demolition Plan and
Sections
CU254 Building 123 Mechanical Room New Construction Plan
and Sections
CU500 Steam Details
CU501 Steam Details
MU000 Overall Site Utility Plan
MU250 Existing Steam Pit S6 Demolition Plan and Sections
MU251 Existing Steam Pit S6 New Construction Plan and
Sections
MU252 New Steam Pit S7 New Construction Plan and Sections
MU253 Building 123 Mechanical Room Demolition Plan and
Sections
MU254 Building 123 Mechanical Room Demolition Plan and
Sections
Milwaukee VAMC February 15, 2017
Upgrade and Replace Building 123 Bid Set Submission
Steam Line Piping and Insulation Project No. 695-17-103
00 01 15 - 2
MU255 Building 123 Mechanical Room New Construction Plan
and Sections
MU500 Steam Details
EU001 Symbols, Abbreviations, Schedules, Details, and Sheet
Index
EU100 Overall Electrical Site Plan
EU250 Steam Pit – New/Existing/Demo Construction Plan –
Electrical
CJ101 Erosion & Sediment Control Plan
CJ501 Erosion & Sediment Control Details
- - - E N D - - -
© 2017 Microsoft Corporation
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
SECTION 01 00 00 GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS .............................. .............. 1
1.2 GENERAL INTENTION..................................................................................................................... 1
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR ......................................................... 2
1.4 CONSTRUCTION SECURITY REQUIREMENTS ............................................................................ 2
1.5 OPERATIONS AND STORAGE AREAS .......................................................................................... 4
1.6 ALTERATIONS ................................................................................................................................... 9
1.7 DISPOSAL AND RETENTION ..................................................................................................... 10
1.8 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUI PMENT,
UTILITIES, AND IMPROVEMENTS ......................................................................................... 10
1.9 RESTORATION ............................................................................................................................... 11
1.10 PROFESSIONAL SURVEYING SERVICES ............................................................................. 12
1.11 LAYOUT OF WORK ..................................................................................................................... 12
1.12 AS-BUILT DRAWINGS .............................................................................................................. 14
1.13 USE OF ROADWAYS ................................................................................................................... 14
1.14 TEMPORARY TOILETS ................................................................... ……………………………………………. 14
1.15 AVAILABILITY AND USE OF UTILITY SERVICES ........................................................ 14
1.16 TESTS ........................................................................................................................................... 16
1.17 INSTRUCTIONS .......................................................................................................................... 17
1.18 RELOCATED EQUIPMENT .......................................................................................................... 18
1.19 CONSTRUCTION SIGN .............................................................................................................. 19
1.20 SAFETY SIGN ............................................................................................................................ 19
1.21 TEMPORARY INTERIOR SIGNAGE ......................................................................................... 19
1.22 PHOTOGRAPHIC DOCUMENTATION ......................................................................................... 20
1.23 CONSTRUCTION COORDINATION DRAWINGS ...................................................................... 24
i
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
SECTION 01 00 00 GENERAL REQUIREMENTS
01 00 00 - 1
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection
control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations,
including demolition and removal of existing structures, and furnish
labor and materials and perform work for UPGRADE AND REPLACE BUILDING
123 STEAM LINE PIPING AND INSULATION as required by drawings and
specifications.
B. Visits to the site by Bidders may be made only as indicated in the
solicitation.
C. Routine Inspections and Maintenance During Construction:
a. Provide routine inspections and maintenance services as
prescribed in Operations & Maintenance manuals required under
this contract.
b. Provide services during construction and until items below are
complete:
i. VA Inspection complete.
ii. Successful commissioning
iii. Training of VA Maintenance staff
iv. Acceptance of VA of each system described in other
specifications related to this contract
01 00 00 - 2
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
v. O&M Manual submittals received, reviewed, and appro ved
by VA.
D. SUBMIT with O&M Manuals one spreadsheet based compr ehensive summary
schedule of routine inspection and maintenance for systems.
E. All employees of general contractor and subcontract ors shall comply
with VA security management program and obtain perm ission of the VA
police, be identified by project and employer, and restricted from
unauthorized access.
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
All drawings and specifications (contract documents ) may be obtained from
the FedBizOps website where the solicitation is pos ted and they will
also be posted on VAMC Milwaukee’s file sharing sit e “Buzzsaw” for
contractor use. Additional copies will be the respo nsibility and
expense of the contractor(s).
A. In the case of conflicts or discrepanciesw within o r among the Contract
Drawings, the better quality, more stringent requir ements or greater
quantity of work, as determined by the Government, shall be provided.
1.4 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and adminis trative security
procedures that will remain effective for the entir e duration of the
project.
2. The General Contractor is responsible for assuring that all sub-
contractors working on the project and their employ ees also comply
with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site
without appropriate badge. They may also be subject to inspection
of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall g ive one week’s
notice to the Contracting Officer so that security can be provided
01 00 00 - 3
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
for the employees. This notice is separate from any notices
required for utility shutdown described later in th is section.
3. No photography of VA premises is allowed without wr itten permission
of the Contracting Officer.
4. VA reserves the right to close down or shut down th e project site
and order General Contractor’s employees off the pr emises in the
event of a national emergency. The General Contract or may return to
the site only with the written approval of the Cont racting Officer.
C. Guards:
1. The General Contractor shall provide unarmed guards at the project
site after construction hours.
2. The Contractor shall provide the guards and VA poli ce with
communication devices as directed.
3. The general Contractor shall install equipment for recording guard
rounds to ensure systematic checking of the premise s.
D. Key Control:
1. The General Contractor shall provide duplicate keys and lock
combinations to the Contracting officers representa tive (COR)for the
purpose of security inspections of every area of pr oject including
tool boxes and parked machines and take any emergen cy action.
2. The General Contractor shall turn over all permanen t lock cylinders
to the VA locksmith for permanent installation. See Section 08 71
00, DOOR HARDWARE and coordinate.
E. Document Control:
1. The General Contractor is responsible for safekeepi ng of all
drawings, project manual and other project informat ion. This
information shall be shared only with those with a specific need to
accomplish the project.
2. All paper waste or electronic media such as CD’s an d diskettes shall
be shredded and destroyed in a manner acceptable to the VA.
01 00 00 - 4
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
3. All electronic information shall be stored in speci fied location
following VA standards and procedures using an Engi neering Document
Management Software (EDMS).
a. Security, access and maintenance of all project dra wings, both
scanned and electronic shall be performed and track ed through the
EDMS system.
F. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle
entering the site and such request shall be submitt ed 24 hours
before the date and time of access. Access shall be restricted to
picking up and dropping off materials and supplies.
2. A limited number of (2 to 5) permits shall be issue d for General
Contractor and its employees for parking in designa ted areas only.
1.5 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (includ ing storage of
materials) on Government premises to areas authoriz ed or approved by
the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harml ess from liability
of any nature occasioned by the Contractor's perfor mance.
B. Temporary buildings (e.g., storage sheds, shops, of fices) and utilities
may be erected by the Contractor only with the appr oval of the
Contracting Officer and shall be built with labor a nd materials
furnished by the Contractor without expense to the Government. The
temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor a t its expense upon
completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandon ed and need not be
removed.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temp orary roadways
constructed by the Contractor when and as authorize d by the Contracting
Officer. When materials are transported in prosecut ing the work,
vehicles shall not be loaded beyond the loading cap acity recommended by
the manufacturer of the vehicle or prescribed by an y Federal, State, or
01 00 00 - 5
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
local law or regulation. When it is necessary to cr oss curbs or
sidewalks, the Contractor shall protect them from d amage. The
Contractor shall repair or pay for the repair of an y damaged curbs,
sidewalks, or roads.
D. Working space and space available for storing mater ials shall be as
shown on the drawings.
E. Workmen are subject to rules of Medical Center appl icable to their
conduct.
F. Execute work so as to interfere as little as possib le with normal
functioning of Medical Center as a whole, including operations of
utility services, fire protection systems and any e xisting equipment,
and with work being done by others. Use of equipmen t and tools that
transmit vibrations and noises through the building structure, are not
permitted in buildings that are occupied, during co nstruction, jointly
by patients or medical personnel, and Contractor's personnel, except as
permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Where access by Medical Center personnel to vacated portions of
buildings is not required, storage of Contractor's materials and
equipment will be permitted subject to fire and saf ety requirements.
G. Utilities Services: Where necessary to cut existing pipes, electrical
wires, conduits, cables, etc., of utility services, or of fire
protection systems or communications systems (excep t telephone), they
shall be cut and capped at suitable places where sh own; or, in absence
of such indication, where directed by COR. All such actions shall be
coordinated with the COR or Utility Company involve d:
1. Whenever it is required that a connection fee be paid to a public
utility provider for new permanent service to the c onstruction
project, for such items as water, sewer, electricit y, gas or steam,
payment of such fee shall be the responsibility of the Government
and not the Contractor.
H. Phasing:
01 00 00 - 6
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
The Medical Center must maintain its operation 24 h ours a day 7 days a
week. Therefore, any interruption in service must b e scheduled and
coordinated with the COR to ensure that no lapses i n operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and
schedule detailing, at a minimum, the procedures to be employed, the
equipment and materials to be used, the interim lif e safety measure to
be used during the work, and a schedule defining th e duration of the
work with milestone subtasks. The work to be outlin ed shall include,
but not be limited to:
To insure such executions, Contractor shall furnish the COR with a
schedule of approximate phasing dates on which the Contractor intends
to accomplish work in each specific area of site, b uilding or portion
thereof. In addition, Contractor shall notify the C OR two weeks in
advance of the proposed date of starting work in ea ch specific area of
site, building or portion thereof. Arrange such pha sing dates to insure
accomplishment of this work in successive phases mu tually agreeable to
COR and Contractor.
I. Building No. 123 will be occupied during performanc e of work but
immediate areas of alterations will be vacated.
1. Contractor shall take all measures and provide all material
necessary for protecting existing equipment and pro perty in
affected areas of construction against dust and deb ris, so that
equipment and affected areas to be used in the Medi cal Centers
operations will not be hindered. Contractor shall p ermit access
to Department of Veterans Affairs personnel and pat ients through
other construction areas which serve as routes of a ccess to such
affected areas and equipment. These routes whether access or
egress shall be isolated from the construction area by temporary
partitions and have walking surfaces, lighting etc to facilitate
patient and staff access. Coordinate alteration wor k in areas
occupied by Department of Veterans Affairs so that Medical Center
operations will continue during the construction pe riod.
2. Immediate areas of alterations not mentioned in pre ceding
Subparagraph 1 will be temporarily vacated while al terations are
performed.
01 00 00 - 7
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
J. Construction Fence: Before construction operations begin, Contractor
shall provide a chain link construction fence, 2.1m (seven feet)
minimum height, around the construction area indica ted on the
drawings. Provide gates as required for access with necessary
hardware, including hasps and padlocks. Fasten fenc e fabric to
terminal posts with tension bands and to line posts and top and
bottom rails with tie wires spaced at maximum 375mm (15 inches).
Bottom of fences shall extend to 25mm (one inch) ab ove grade.
Remove the fence when directed by COR.
K. Utilities Services: Maintain existing utility servi ces for Medical
Center at all times. Provide temporary facilities, labor, materials,
equipment, connections, and utilities to assure uni nterrupted
services. Where necessary to cut existing water, st eam, gases, sewer
or air pipes, or conduits, wires, cables, etc. of u tility services
or of fire protection systems and communications sy stems (including
telephone), they shall be cut and capped at suitabl e places where
shown; or, in absence of such indication, where dir ected by COR.
1. No utility service such as water, gas, steam, sewer s or electricity,
or fire protection systems and communications syste ms may be
interrupted without prior approval of COR . Electri cal work shall
be accomplished with all affected circuits or equip ment de-
energized. When an electrical outage cannot be acco mplished, work
on any energized circuits or equipment shall not co mmence without
a detailed work plan, the Medical Center Director’s prior
knowledge and written approval. Refer to specificat ion Sections
26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS , 27 05 11
REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS and 28 05 00,
COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY for
additional requirements.
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 7 days in advance of proposed inte rruption.
Request shall state reason, date, exact time of, an d approximate
duration of such interruption.
01 00 00 - 8
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
3. Contractor will be advised (in writing) of approval of request, or
of which other date and/or time such interruption w ill cause
least inconvenience to operations of Medical Center . Interruption
time approved by Medical Center may occur at other than
Contractor's normal working hours.
4. Major interruptions of any system must be requested , in writing, at
least 15 calendar days prior to the desired time an d shall be
performed as directed by the COR.
5. In case of a contract construction emergency, servi ce will be
interrupted on approval of COR. Such approval will be confirmed
in writing as soon as practical.
6. Whenever it is required that a connection fee be pa id to a public
utility provider for new permanent service to the c onstruction
project, for such items as water, sewer, electricit y, gas or
steam, payment of such fee shall be the responsibil ity of the
Government and not the Contractor.
L. Abandoned Lines: All service lines such as wires, c ables,
conduits,ducts, pipes and the like, and their hange rs or supports,
which are to be abandoned but are not required to b e entirely
removed, shall be sealed, capped or plugged at the main, branch or
panel they originate from. The lines shall not be c apped in finished
areas, but shall be removed and sealed, capped or p lugged in
ceilings, within furred spaces, in unfinished areas , or within walls
or partitions; so that they are completely behind t he finished
surfaces.
M. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to park ing and to
occupied areas of buildings clear of construction m aterials,
debris and standing construction equipment and vehi cles. Wherever
excavation for new utility lines cross existing roa ds, at least
one lane must be open to traffic at all times with approval.
2. Method and scheduling of required cutting, altering and removal of
existing roads, walks and entrances must be approve d by the COR.
01 00 00 - 9
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
N. Coordinate the work for this contract with other co nstruction
operations as directed by COR. This includes the sc heduling of traffic
and the use of roadways, as specified in Article, U SE OF ROADWAYS.
1.6 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a
thorough survey with the COR and a representative o f VA Supply Service,
of areas of buildings in which alterations occur an d areas which are
anticipated routes of access, and furnish a report, signed by all
three, to the Contracting Officer. This report shal l list by rooms and
spaces:
1. Existing condition and types of resilient flooring, doors, windows,
walls and other surfaces not required to be altered throughout
affected areas of buildings.
2. Existence and conditions of items such as plumbing fixtures and
accessories, electrical fixtures, equipment, etc., required by
drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and e xisting
conditions at site.
4. Shall designate areas for working space, materials storage and
routes of access to areas within buildings where al terations occur
and which have been agreed upon by Contractor and C OR.
B. Any items required by drawings to be either reused or relocated or
both, found during this survey to be nonexistent, o r in opinion of
COR, to be in such condition that their use is impo ssible or
impractical, shall be furnished and/or replaced by Contractor with new
items in accordance with specifications which will be furnished by
Government. Provided the contract work is changed b y reason of this
subparagraph B, the contract will be modified accor dingly, under
provisions of clause entitled "DIFFERING SITE CONDI TIONS" (FAR 52.236-
2) and "CHANGES" (FAR 52.243-4 and VAAR 852.236-88) .
C. Re-Survey: Thirty days before expected partial or f inal inspection
date, the Contractor and COR together shall make a thorough re-survey
of the areas of buildings involved. They shall furn ish a report on
conditions then existing, of resilient flooring, wa lls and other
01 00 00 - 10
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
surfaces as compared with conditions of same as not ed in first
condition survey report:
1. Re-survey report shall also list any damage caus ed by Contractor to
such flooring and other surfaces, despite protectio n measures; and,
will form basis for determining extent of repair wo rk required of
Contractor to restore damage caused by Contractor's workmen in
executing work of this contract.
D. Protection: Provide the following protective measur es:
1. Temporary protection against damage for portions of existing
structures and grounds where work is to be done, ma terials handled
and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from
damage, dust and weather inclemency. Wherever work is performed,
floor surfaces that are to remain in place shall be adequately
protected prior to starting work, and this protecti on shall be
maintained intact until all work in the area is com pleted.
1.7 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition
of buildings or structures, or parts thereof, shall be disposed of as
follows:
1. Reserved items which are to remain property of the Government are
noted on drawings or in specifications as items to be stored. Items
that remain property of the Government shall be rem oved or dislodged
from present locations in such a manner as to preve nt damage which
would be detrimental to re-installation and reuse. Store such items
where directed by COR.
2. Items not reserved shall become property of the Con tractor and be
removed by Contractor from Medical Center Campus.
1.8 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUI PMENT, UTILITIES, AND IMPROVEMENTS
A. The Contractor shall preserve and protect all struc tures, equipment,
and vegetation (such as trees, shrubs, and grass) o n or adjacent to the
01 00 00 - 11
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
work site which are not to be removed and do not un reasonably interfere
with the work required under this contract. The Con tractor shall only
remove trees when specifically authorized to do so, and shall avoid
damaging vegetation that will remain in place. If a ny limbs or branches
of trees are broken during contract performance, or by the careless
operation of equipment, or by workmen, the Contract or shall trim those
limbs or branches with a clean cut and paint the cu t with a tree-
pruning compound as directed by the Contracting Off icer.
B. The Contractor shall protect from damage all existi ng improvements and
utilities at or near the work site and on adjacent property of a third
party, the locations of which are made known to or should be known by
the Contractor. The Contractor shall repair any dam age to those
facilities, including those that are the property o f a third party,
resulting from failure to comply with the requireme nts of this contract
or failure to exercise reasonable care in performin g the work. If the
Contractor fails or refuses to repair the damage pr omptly, the
Contracting Officer may have the necessary work per formed and charge
the cost to the Contractor.
(FAR 52.236-9)
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for
additional requirements on protecting vegetation, s oils and the
environment. Refer to Articles, "Alterations", "Res toration", and
"Operations and Storage Areas" for additional instr uctions concerning
repair of damage to structures and site improvement s.
1.9 RESTORATION
A. Remove, cut, alter, replace, patch and repair exist ing work as
necessary to install new work. Except as otherwise shown or specified,
do not cut, alter or remove any structural work, an d do not disturb any
ducts, plumbing, steam, gas, or electric work witho ut approval of the
COR. Existing work to be altered or extended and th at is found to be
defective in any way, shall be reported to the COR before it is
disturbed. Materials and workmanship used in restor ing work, shall
conform in type and quality to that of original exi sting construction,
except as otherwise shown or specified.
01 00 00 - 12
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and
electrical work, lawns, paving, roads, walks, etc.) disturbed or
removed as a result of performing required new work , shall be patched,
repaired, reinstalled, or replaced with new work, a nd refinished and
left in as good condition as existed before commenc ing work.
C. At Contractor's own expense, Contractor shall immed iately restore to
service and repair any damage caused by Contractor' s workmen to
existing piping and conduits, wires, cables, etc., of utility services
or of fire protection systems and communications sy stems (including
telephone) which are not scheduled for discontinuan ce or abandonment.
D. Expense of repairs to such utilities and systems no t shown on drawings
or locations of which are unknown will be covered b y adjustment to
contract time and price in accordance with clause e ntitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING S ITE CONDITIONS" (FAR
52.236-2).
1.10 PROFESSIONAL SURVEYING SERVICES
A registered professional land surveyor or register ed civil engineer
whose services are retained and paid for by the Con tractor shall
perform services specified herein and in other spec ification sections.
The Contractor shall certify that the land surveyor or civil engineer
is not one who is a regular employee of the Contrac tor, and that the
land surveyor or civil engineer has no financial in terest in this
contract.
1.11 LAYOUT OF WORK
A. The Contractor shall lay out the work from Governme nt established base
lines and bench marks, indicated on the drawings, a nd shall be
responsible for all measurements in connection with the layout. The
Contractor shall furnish, at Contractor's own expen se, all stakes,
templates, platforms, equipment, tools, materials, and labor required
to lay out any part of the work. The Contractor sha ll be responsible
for executing the work to the lines and grades that may be established
or indicated by the Contracting Officer. The Contra ctor shall also be
responsible for maintaining and preserving all stak es and other marks
established by the Contracting Officer until author ized to remove them.
01 00 00 - 13
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
If such marks are destroyed by the Contractor or th rough Contractor's
negligence before their removal is authorized, the Contracting Officer
may replace them and deduct the expense of the repl acement from any
amounts due or to become due to the Contractor.
(FAR 52.236-17)
C. Following completion of general mass excavation and before any other
permanent work is performed, establish and plainly mark (through use of
appropriate batter boards or other means) sufficien t additional survey
control points or system of points as may be necess ary to assure proper
alignment, orientation, and grade of all major feat ures of work. Survey
shall include, but not be limited to, location of l ines and grades of
footings, exterior walls, center lines of columns i n both directions,
major utilities and elevations of floor slabs:
1. Such additional survey control points or system of points thus
established shall be checked and certified by a reg istered land
surveyor or registered civil engineer. Furnish such certification to
the COR before any work (such as footings, floor sl abs, columns,
walls, utilities and other major controlling featur es) is placed.
2. Elevations of bottoms of footings and tops of slabs of each
structure.
3. Lines and elevations of sewers and of all outside d istribution
systems.
E. Whenever changes from contract drawings are made in line or grading
requiring certificates, record such changes on a re producible drawing
bearing the registered land surveyor or registered civil engineer seal,
and forward these drawings upon completion of work to COR.
F. Upon completion of the work, the Contractor shall f urnish the COR one
electronic copy and reproducible drawings at the sc ale of the contract
drawings, showing the finished grade on the grid de veloped for
constructing the work. These drawings shall bear th e seal of the
registered land surveyor or registered civil engine er. The Contractor
shall perform the surveying and layout work of this and other articles
and specifications in accordance with the provision s of Article
"Professional Surveying Services".
01 00 00 - 14
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
1.12 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings
which will be kept current during construction of t he project, to
include all contract changes, modifications and cla rifications.
B. All variations shall be shown in the same general d etail as used in the
contract drawings. To insure compliance, as-built d rawings shall be
made available for the COR review, as often as requ ested.
C. Contractor shall deliver two approved completed set s of as-built
drawings in the electronic version (scanned PDF) to the COR within 15
calendar days after each completed phase and after the acceptance of
the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop d rawings.
E. Contractors shall update (as work is completed) the VA electrical,
medical gas, domestic plumbing, and mechanical pipi ng master schematic
books. These books are located in the FM office.
1.13 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical
Center property and, when authorized by the COR, su ch temporary roads
which are necessary in the performance of contract work. Temporary
roads shall be constructed and restoration performe d by the Contractor
at Contractor's expense. When necessary to cross cu rbing, sidewalks, or
similar construction, they must be protected by wel l-constructed
bridges.
1.14 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required a mounts of utilities
available to the Contractor from existing outlets a nd supplies, as
specified in the contract. The amount to be paid by the Contractor for
chargeable electrical services shall be the prevail ing rates charged to
the Government. The Contractor shall carefully cons erve any utilities
furnished without charge.
B. The Contractor, at Contractor's expense and in a wo rkmanlike manner, in
compliance with code and as satisfactory to the Con tracting Officer,
shall install and maintain all necessary temporary connections and
distribution lines, and all meters required to meas ure the amount of
01 00 00 - 15
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
electricity used for the purpose of determining cha rges. Before final
acceptance of the work by the Government, the Contr actor shall remove
all the temporary connections, distribution lines, meters, and
associated paraphernalia and repair restore the inf rastructure as
required.
C. Contractor shall install meters at Contractor's exp ense and furnish the
Medical Centera monthly record of the Contractor's usage of electricity
as hereinafter specified.
D. Heat: Furnish temporary heat necessary to prevent i njury to work and
materials through dampness and cold. Use of open sa lamanders or any
temporary heating devices which may be fire hazards or may smoke and
damage finished work, will not be permitted. Mainta in minimum
temperatures as specified for various materials:
1. Obtain heat by connecting to Medical Center heat ing distribution
system.
E. Electricity (for Construction and Testing): Furnish all temporary
electric services.
1. Obtain electricity by connecting to the Medical Center electrical
distribution system. The Contractor shall meter and pay for
electricity required for electric cranes and hoisti ng devices,
electrical welding devices and any electrical heati ng devices
providing temporary heat. Electricity for all other uses is
available at no cost to the Contractor.
F. Water (for Construction and Testing): Furnish tempo rary water service.
1. Obtain water by connecting to the Medical Center wa ter distribution
system. Provide reduced pressure backflow preventer at each
connection as per code. Water is available at no co st to the
Contractor.
2. Maintain connections, pipe, fittings and fixtures a nd conserve
water-use so none is wasted. Failure to stop leakag e or other wastes
will be cause for revocation (at COR’s discretion) of use of water
from Medical Center's system.
01 00 00 - 16
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
G. Fuel: Natural and LP gas and burner fuel oil requir ed for boiler
cleaning, normal initial boiler-burner setup and ad justing, and for
performing the specified boiler tests will be furni shed by the
Government. Fuel required for prolonged boiler-burn er setup,
adjustments, or modifications due to improper desig n or operation of
boiler, burner, or control devices shall be furnish ed and paid by the
Contractor at Contractor's expense.
1.15 TESTS
A. As per specification section 23 05 93 the contracto r shall provide a
written testing and commissioning plan complete wit h component level,
equipment level, sub-system level and system level breakdowns. The
plan will provide a schedule and a written sequence of what will be
tested, how and what the expected outcome will be. This document will
be submitted for approval prior to commencing work. The contractor
shall document the results of the approved plan and submit for approval
with the as built documentation.
B. Pre-test mechanical and electrical equipment and sy stems and make
corrections required for proper operation of such s ystems before
requesting final tests. Final test will not be cond ucted unless
pre-tested.
C. Conduct final tests required in various sections of specifications in
presence of an authorized representative of the Con tracting Officer.
Contractor shall furnish all labor, materials, equi pment, instruments,
and forms, to conduct and record such tests.
D. Mechanical and electrical systems shall be balanced , controlled and
coordinated. A system is defined as the entire syst em which must be
coordinated to work together during normal operatio n to produce results
for which the system is designed. For example, air conditioning supply
air is only one part of entire system which provide s comfort conditions
for a building. Other related components are return air, exhaust air,
steam, chilled water, refrigerant, hot water, contr ols and electricity,
etc. Another example of a system which involves sev eral components of
different disciplines is a boiler installation. Eff icient and
acceptable boiler operation depends upon the coordi nation and proper
01 00 00 - 17
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
operation of fuel, combustion air, controls, steam, feedwater,
condensate and other related components.
E. All related components as defined above shall be fu nctioning when any
system component is tested. Tests shall be complete d within a
reasonably period of time during which operating an d environmental
conditions remain reasonably constant and are typic al of the design
conditions.
F. Individual test result of any component, where requ ired, will only be
accepted when submitted with the test results of re lated components and
of the entire system.
1.16 INSTRUCTIONS
A. Contractor shall furnish Maintenance and Operating manuals (hard copies
and electronic) and verbal instructions when requir ed by the various
sections of the specifications and as hereinafter s pecified.
B. Manuals: Maintenance and operating manuals and one compact disc (four
hard copies and one electronic copy each) for each separate piece of
equipment shall be delivered to the CORcoincidental with the delivery
of the equipment to the job site. Manuals shall be complete, detailed
guides for the maintenance and operation of equipme nt. They shall
include complete information necessary for starting , adjusting,
maintaining in continuous operation for long period s of time and
dismantling and reassembling of the complete units and sub-assembly
components. Manuals shall include an index covering all component parts
clearly cross-referenced to diagrams and illustrati ons. Illustrations
shall include "exploded" views showing and identify ing each separate
item. Emphasis shall be placed on the use of specia l tools and
instruments. The function of each piece of equipmen t, component,
accessory and control shall be clearly and thorough ly explained. All
necessary precautions for the operation of the equi pment and the reason
for each precaution shall be clearly set forth. Man uals must reference
the exact model, style and size of the piece of equ ipment and system
being furnished. Manuals referencing equipment simi lar to but of a
different model, style, and size than that furnishe d will not be
accepted.
01 00 00 - 18
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
C. Instructions: Contractor shall provide qualified, f actory-trained
manufacturers' representatives to give detailed tra ining to assigned
Department of Veterans Affairs personnel in the ope ration and complete
maintenance for each piece of equipment. All such t raining will be at
the job site. These requirements are more specifica lly detailed in the
various technical sections. Instructions for differ ent items of
equipment that are component parts of a complete sy stem, shall be given
in an integrated, progressive manner. All instructo rs for every piece
of component equipment in a system shall be availab le until
instructions for all items included in the system h ave been completed.
This is to assure proper instruction in the operati on of inter-related
systems. All instruction periods shall be at such t imes as scheduled by
the COR and shall be considered concluded only when the COR is
satisfied in regard to complete and thorough covera ge. The contractor
shall submit a course outline with associated mater ial to the COR for
review and approval prior to scheduling training to ensure the subject
matter covers the expectations of the VA and the co ntractual
requirements. The Department of Veterans Affairs re serves the right to
request the removal of, and substitution for, any i nstructor who, in
the opinion of the COR, does not demonstrate suffic ient qualifications
in accordance with requirements for instructors abo ve.
1.17 RELOCATED EQUIPMENT AND ITEMS
A. Contractor shall disconnect, dismantle as necessary , remove and
reinstall in new location, all existing equipment a nd items indicated
by symbol "R" or otherwise shown to be relocated by the Contractor.
B. Perform relocation of such equipment or items at su ch times and in such
a manner as directed by the COR.
C. Suitably cap existing service lines, such as steam, condensate return,
water, drain, gas, air, vacuum and/or electrical, a t the main whenever
such lines are disconnected from equipment to be re located. Remove
abandoned lines in finished areas and cap as specif ied herein before
under paragraph "Abandoned Lines".
D. Provide all mechanical and electrical service conne ctions, fittings,
fastenings and any other materials necessary for as sembly and
01 00 00 - 19
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
installation of relocated equipment; and leave such equipment in proper
operating condition.
E. Contractor shall employ services of an installation engineer, who is an
authorized representative of the manufacturer of th is equipment to
supervise assembly and installation of existing equ ipment, required to
be relocated.
F. All service lines such as noted above for relocated equipment shall be
in place at point of relocation ready for use befor e any existing
equipment is disconnected. Make relocated existing equipment ready for
operation or use immediately after reinstallation.
1.18 CONSTRUCTION SIGN
A. Provide a Construction Sign where directed by the C OR. All wood members
shall be of framing lumber. Cover sign frame with 0 .7 mm (24 gage)
galvanized sheet steel nailed securely around edges and on all
bearings. Provide three 100 by 100 mm (4 inch by 4 inch) posts (or
equivalent round posts) set 1200 mm (four feet) int o ground. Set bottom
of sign level at 900 mm (three feet) above ground a nd secure to posts
with through bolts. Make posts full height of sign. Brace posts with 50
x 100 mm (two by four inch) material as directed.
B. Paint all surfaces of sign and posts two coats of w hite gloss paint.
Border and letters shall be of black gloss paint, e xcept project title
which shall be blue gloss paint.
C. Maintain sign and remove it when directed by the CO R.
D. Detail Drawing of construction sign showing require d legend and other
characteristics of sign is shown on the drawings.
1.19 SAFETY SIGN
A. Provide a Safety Sign where directed by COR. Face o f sign shall be 19
mm (3/4 inch) thick exterior grade plywood. Provide two 100 mm by 100
mm (four by four inch) posts extending full height of sign and 900 mm
(three feet) into ground. Set bottom of sign level at 1200 mm (four
feet) above ground.
01 00 00 - 20
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
B. Paint all surfaces of Safety Sign and posts with on e prime coat and two
coats of white gloss paint. Letters and design shal l be painted with
gloss paint of colors noted.
C. Maintain sign and remove it when directed by COR.
D. Standard Detail Drawing Number SD10000-02(Found on VA TIL) of safety
sign showing required legend and other characterist ics of sign isshown
on the drawings.
E. Post the number of accident free days on a daily ba sis.
1.21 TEMPORARY INTERIOR SIGNAGE
A. When the contractor’s work blocks doors and/or exit s, changes paths,
etc., the General Contractor is to provide all temp orary signage to
reroute personnel and block the doors or exits. Loc ations to be
determined based on the ILSM.
1.21 PHOTOGRAPHIC DOCUMENTATION
A. During the construction period through completion, provide photographic
documentation of construction progress and at selec ted milestones
including electronic indexing, navigation, storage and remote access to
the documentation, as per these specifications.
B. Photographic documentation elements:
1. Each digital image shall be taken with a profession al grade camera
with minimum size of 6 megapixels (MP) capable of p roducing
200x250mm (8 x 10 inch) prints with a minimum of 22 72 x 1704 pixels
and 400x500mm (16 x 20 inch) prints with a minimum 2592 x 1944
pixels.
2. Indexing and navigation system shall utilize actual AUTOCAD
construction drawings, making such drawings interac tive on an on-
line interface. For all documentation referenced he rein, indexing
and navigation must be organized by both time (date -stamped) and
location throughout the project.
3. Documentation shall combine indexing and navigation system with
inspection-grade digital photography designed to ca pture actual
conditions throughout construction and at critical milestones.
01 00 00 - 21
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
Documentation shall be accessible on-line through u se of an internet
connection. Documentation shall allow for secure mu ltiple-user
access, simultaneously, on-line.
4. Before construction, the building pad, adjacent str eets, roadways,
parkways, driveways, curbs, sidewalks, landscaping, adjacent
utilities and adjacent structures surrounding the b uilding pad and
site shall be documented. Overlapping photographic techniques shall
be used to insure maximum coverage. Indexing and na vigation
accomplished through interactive architectural draw ings. If site
work or pad preparation is extensive, this document ation may be
required immediately before construction and at sev eral pre-
determined intervals before building work commences .
5. Construction progress for all trades shall be track ed at pre-
determined intervals, but not less than once every thirty (30)
calendar days (“Progressions”). Progression documen tation shall
track both the exterior and interior construction o f the building.
Exterior Progressions shall track 360 degrees aroun d the site and
each building. Interior Progressions shall track in terior
improvements beginning when stud work commences and continuing until
Project completion.
6. As-built condition of pre-foundation utilities and site utilities
shall be documented prior to pouring footers, placi ng concrete
and/or backfilling. This process shall include all underground and
in-slab utilities and utility runs in the immediate vicinity of
buildings envelope(s). Overlapping photographic tec hniques shall be
used to insure maximum coverage. Indexing and navig ation
accomplished through interactive site utility plans .
7. As-built conditions of mechanical, electrical, plum bing and all
other systems shall be documented post-inspection a nd pre-
insulation, sheet rock or dry wall installation. Th is process shall
include all finished systems located in the walls a nd ceilings of
all buildings at the Project. Overlapping photograp hic techniques
shall be used to insure maximum coverage. Indexing and navigation
accomplished through interactive architectural draw ings.
01 00 00 - 22
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
8. Miscellaneous events that occur during any Contract or site visit, or
events captured by the Department of Veterans Affai rs independently,
shall be dated, labeled and inserted into a Section in the
navigation structure entitled “Slideshows,” allowin g this
information to be stored in the same “place” as the formal scope.
9. Customizable project-specific digital photographic documentation of
other details or milestones.
10. Weekly (21 Max) Site Progressions - Photographic do cumentation
capturing the project at different stages of constr uction. These
progressions shall capture underground utilities, e xcavation,
grading, backfill, landscaping and road constructio n throughout the
duration of the project.
11. Detailed Exact-Built of all Slabs for all project s lab pours just
prior to placing concrete or as directed by the COR
12. In event a greater or lesser number of images than specified above
are required by the COR, adjustment in contract pri ce will be made
in accordance with clause entitled "CHANGES" (FAR 5 2.243-4 and VAAR
852.236-88).
C. Images shall show distinctly, at as large a scale a s possible, all
parts of work embraced in the picture.
D. Contractor shall provide all on-line domain/web hos ting, security
measures, and redundant server back-up of the docum entation.
E. Contractor shall provide technical support related to using the system
or service.
F. Upon completion of the project, final copies of the documentation (the
“Permanent Record”) with the indexing and navigatio n system embedded
(and active) shall be provided in an electronic med ia format, typically
a DVD or external hard-drive. On-line access termin ates upon delivery
of the Permanent Record.
1.22 CONSTRUCTION COORDINATION DRAWINGS
A. Prepare and provide coordination drawings showing t he location of
openings through slabs, the pipe sleeves and hanger inserts, as well as
the location and elevation of utility lines, includ ing, but not limited
01 00 00 - 23
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
to, conveyor systems, pneumatic tubes, ducts, all e xisting utilities,
and conduits and pipes 50 mm (2 inches) and larger in diameter.
Drawings required for all areas being remodeled or new and ancillary
areas required by such utility runs. Ancillary area drawings to include
equal space on each side of main runs from main sou rce to final
location.
B. These drawings, including plans, elevations, and se ctions as
appropriate shall clearly show the manner in which the utilities fit
into the available space and how they relate to eac h other and to
existing building elements and controls for mainten ance operations.
Drawings shall be of appropriate scale to satisfy t he previously stated
purposes, but not smaller than 9 mm (3/8 inch) scal e. Drawings must be
composite (with distinctive colors for the various trades) including
but not limited to HVAC equipment, HVAC ductwork, m echanical piping,
plumbing, fire protection, electrical, medical gas es,
telecommunications, etc..
C. The submitted drawings for a given area of the proj ect shall show the
work of all trades which will be involved in that p articular area. A
complete composite drawing set or complete sets of separate
reproducible drawings and AutoCAD files shall be re ceived by the
Government not less than 20 days prior to the sched uled start of the
work in the area illustrated by the drawings, for t he purpose of
showing the contractor's planned method of installa tion. The objectives
of such drawings are to promote carefully planned w ork sequence and
proper trade coordination, in order to assure the e xpeditious solutions
of problems and the installation of lines and equip ment as contemplated
by the contract documents while avoiding or minimiz ing additional costs
to the contractor and to the Government.
D. In the event the contractor, in coordinating the va rious installations
and in planning the method of installation, finds a conflict in
location or elevation of any of the utilities with themselves, with
structural items or with other construction items, the contractor shall
bring this conflict to the attention of the contrac ting officer
immediately. In doing so, the contractor shall expl ain the proposed
method of solving the problem or shall request inst ructions as to how
to proceed if adjustments beyond those of usual tra des coordination are
01 00 00 - 24
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
necessary. Contractor to include initial and two re visions as part of
original contract.
E. Utilities installation work will not proceed in any area prior to the
submission and completion of the Government review of the coordinated
drawings for that area, nor in any area in which co nflicts are
disclosed by the coordination drawings until the co nflicts have been
corrected to the satisfaction of the contracting of ficer.
F. It is the responsibility of the contractor to submi t the required
drawings in a timely manner consistent with the req uirements to
complete the work covered by this contract within t he prescribed
contract time.
- - - E N D - - -
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
00 01 10 (1HR)-1
SECTION 01 01 10 (1-HR)
1 HOUR CONSTRUCTION SMOKE BARRIER
03/2016
1. DESCRIPTION
A. This section specifies the control of the construction barrier surrounding the construction area that
the General Contractor must consider for construction & renovation projects in the medical facility
and surrounding buildings on the VAMC campus.
B. The construction barrier consists of both existing walls and new construction (typically the ante-
room) walls. The intent of the barrier is to provide a fire-rated and smoke tight 1-hour construction
partition around the construction area. Contractor must coordinate the erection of any new walls
for construction barriers with the Milwaukee Specification 01 01 10-IC and any additional infection
control requirements.
C. This Milwaukee specification includes the precautionary management of various types of
construction activities, including “Inspections and Non-Invasive”, “Small-Scale or Short-Duration”,
“Moderate” and “Major” demolition/construction activities as detailed in the below TABLE.
D. Type “A” and “B” activities are those in which the fire/smoke hazard risks are MINIMAL. Type “C”
and “D” activities are those in which the fire/smoke hazard risks are HIGH. The General Contractor
is obligated to consider the specified containment measures with the costs included within the
various contract items of work. A Construction Barrier and Fire Risk Assessment Matrix of
Precautions for construction and renovation for activities follows.
00 01 10 (1HR)-2
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
TYPE A
Minimal
Fire Risk
TYPE B
Limited
Fire Risk
TYPE C
Moderate
Fire Risk
TYPE D
Significant
Fire Risk
Inspection and Non-Invasive Activities.
Includes, but is not limited to:
� removal of ceiling tiles for visual inspection limited to 1 tile per 50 square feet
� painting (but not sanding)
� wall covering, electrical trim work, minor plumbing, and activities which do not
generate dust or require cutting of walls or access to ceilings other than for
visual inspection.
� Removal of floor tile less than 25 square feet, non-ACM and no grinding or dust
generating activities
Small scale, short duration activities that can be completed within 3 calendar days.
Work that requires a moderate level of demolition and does not pose a potential
fire hazard. Cutting/burning operations that require a burn permit are prohibited.
No electrical corded power tools permitted.
Includes, but is not limited to:
� installation of telephone and computer cabling
� access to chase spaces
� asbestos abatement of flooring tile/mastic removal, glove bag operations,
Transite panel removals
� duct work , electrical, plumbing, piping work above ceiling within a 50 square
foot area.
� cutting of walls or ceiling where fire hazard is minimal.
� sanding of walls for painting or wall covering
� removal of floor coverings, ceiling tiles and casework
Work that requires a moderate to high level of demolition, cutting/burning
operations or requires demolition or removal of any fixed building components or
assemblies. Power corded tools and work that provides a potential fire hazard.
Includes, but is not limited to:
� Removal of building components or elements requiring use of open flame or
power chisel
� new construction or renovations over 3 days duration
� major duct work, plumbing, piping, or electrical work
� soldering or brazing operations
� ANY activity that requires a burn permit
Major demolition and construction projects involving cutting/burning operations
or requires demolition or removal of any fixed building components or assemblies.
Power corded tools and work that provides a potential fire hazard.
Includes, but is not limited to:
� activities which require consecutive work shifts
� requires heavy demolition or removal of a complete building system
� new construction or renovations over 3 days duration
00 01 10 (1HR)-3
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
2. TEMPORARY CONSTRUCTION PARTITIONS (ANTE-ROOM CONSTRUCTION)
A. Type A: Provide authority to proceed with work in area, includes a ceiling permit as required,
when working above ceilings.
B. Type B:
i. Coordinate temporary construction partition installation with Section 01 01 10-IC.
ii. Provide plastic from floor to ceiling above and seal joints and penetrations. All plastic
will be labeled with the VA ILSM TEMPORARY BARRIER orange tag once installed
indicating the start of the three days. At openings, install z-wall overlapping plastic flap
barriers or equivalent.
ILSM TEMPORARY BARRIER TAG
PROJECT:
PRIME CONTRACTOR:
SUB CONTRACTOR:
EMERGENCY CONTACT NO.
BARRIER INSTALLATION DATE:
BARRIER EXPIRATION DATE:
(MAX 3 DAYS)
C. Type C:
i. Coordinate temporary construction partition installation with Section 01 01 10-IC.
ii. Ante-room construction (as part of 1-hour construction barrier):
a) Ante-room shall be a 1-hour fire-rated smoke-tight temporary construction partition
and shall be full height, extending through suspended ceilings to the floor slab or
roof deck above.
b) Ante-room shall be constructed from one-hour fire-rated 5/8-in type “X” gypsum
board both sides of metal stud wall, mudded and taped in accordance with ASTM
C840.
1. “Double” gypsum board installation on one side (exterior) of the ante-room
is authorized to achieve the 1-hour fire-rated smoke-tight temporary
construction partition requirement with prior COR approval.
c) In this case, the ante-room 1-hour fire-rated smoke-tight temporary construction
partition walls will also function as infection control barriers. Contractor shall add
00 01 10 (1HR)-4
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
appropriate infection control measures (e.g., plastic sheeting between metal studs
and gypsum board). Refer to 01 01 10-IC for more information.
d) Ante-room gypsum board walls shall be taped to the existing floors utilizing 2-in
wide glass foil tape: 7.3 mil aluminum foil laminated glass cloth silver tape with
silicone adhesive backing. Where the ante-room walls meet the existing deck or a 1-
hour rated existing wall, the seams shall be firecaulked.
e) The ante-room must also have a dedicated heat detector installed. See paragraph
(iv.) below for heat detector requirements.
f) Ante-room outer construction door opening requires a Class C, 45-minute fire rated
door with self-closing and self-latching devices.
g) Ante-room inner door must at least be plastic Z-Type door.
iii. Ante-room construction (for infection control purposes only):
a) Ante-room need not be a 1-hour fire-rated smoke-tight temporary construction
partition. Its walls do not need to go to the concrete deck above, nor is a hard
ceiling required. At a minimum, the contractor must tape the top of the ante-room
walls to the underside of the existing acoustical tile ceiling to achieve the smoke
tight and infection control requirements.
b) Ante-room shall be constructed from one-hour fire-rated 5/8-in type “X” gypsum
board one side of metal stud wall, mudded and taped in accordance with ASTM
C840.
c) Contractor shall add appropriate infection control measures (e.g., plastic sheeting
between metal studs and gypsum board). Refer to 01 01 10-IC for more
information.
d) Ante-room gypsum board walls shall be taped to the existing floors, walls or ceilings
utilizing 2-in wide glass foil tape: 7.3 mil aluminum foil laminated glass cloth silver
tape with silicone adhesive backing. Where the ante-room walls meet the existing
deck or a 1-hour rated existing wall, the seams shall be firecaulked.
e) The ante-room does not require a dedicated heat detector.
f) Ante-room outer construction door opening requires a Class C, 45-minute fire rated
door with self-closing and self-latching devices.
g) Ante-room inner construction door opening requires a Class C, 45-minute fire rated
door with self-closing and self-latching devices.
iv. Provide heat detectors and notification devices (i.e., audio-visual devices) tied into the
Building Siemens Pyrotronics System at the rate of one (1) detector per 1000 square foot of
clear construction area. Heat detectors to be FTP-11 Addressable, Tri-Color LED, 135°F,
Combination Fixed or Rate of Rise. The Contractor shall provide certification documentation
once the heat detectors and notification devices (i.e., audio-visual devices) are installed
and/or moved and tested prior to any construction work taking place in the space. Inside
the construction space, existing units can be used if they are moved to the floor deck above.
v. Other than ante-room, all other temporary construction partitions shall be full height,
extending through suspended ceilings to the floor slab or roof deck above and shall be
one-hour fire rated 5/8-in type “X” gypsum board both sides of metal stud wall, mudded
00 01 10 (1HR)-5
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
and taped in accordance with ASTM C840. If sprinklers are installed per a hydraulically
calculated stamped and certified system and sprinklers are operational on both sides of
the temporary partition and ceilings are fully intact and complete, then the partition
indicated above may be permitted to terminate at the ceiling in accordance with NFPA
241.
vi. Coordinate with Section 01 01 10-SN Section 1.10 for Card Reader and Physical Access
Control System (PACS) requirements at ante-room outer construction door.
D. Type D:
i. All requirements for Type C construction activities above are required for Type D
construction activities.
ii. When required by the project, install one-hour fire-rated temporary construction
partitions to maintain integrity of existing exit stair enclosures, exit passageways, fire-
rated enclosures of hazardous areas, horizontal exits, smoke barriers, vertical shafts and
openings and other enclosures as required by the current Life Safety Code NFPA 101.
This may include new horizontal egress tunnels, exit stairs, etc. Coordinate these
activities with the COR.
3. EXISTING WALLS TO BE USED FOR CONSTRUCTION PARTITIONS AND PHASING
A. The construction site must be completely surrounded by a 1-hour fire-rated gypsum board,
smoke-tight, and fire-stopped construction partitions. Infection control procedures (as
required) shall be initiated prior to any other construction activities.
B. All existing walls surrounding the construction area are to be inspected, repaired, patched, and
fire-stopped as required to bring them up to current smoke barrier construction requirements.
C. Construction cores made through the construction barriers or any other rated assembly need to
have an ILSM firestop (mineral wool filling) and an “ILSM FIRESTOP” orange tag label as
indicated below. All penetrations are to be made temporarily smoke resistant (mineral wool
filling) by the end of the construction day, and all penetrations are to be permanently fire
caulked/sealed within 30 days of being made.
00 01 10 (1HR)-6
M U
15, 2017 bmission 5-17-103
ilwaukee VAMC February pgrade and Replace Building 123 Bid Set Su team Line Piping and Insulation Project No. 69
01 01 10 (FSS)-1
Milwaukee VAMC February 15, 2017 Upgrade and Replace Building 123 Bid Set Submission Steam Line Piping and Insulation Project No. 695-17 -103
SECTION 01 01 10 (FSS)
FIRE SAFETY AND CONTROL
11/2015
PART 1 - GENERAL
1.1 DESCRIPTION: This section covers safety precautions required by all contractor personnel to
safeguard patients, visitors, and Department of Veterans Affairs employees.
1.2 RELATED SECTION
A. Section 01 00 00 - GENERAL REQUIREMENTS
1.3 APPLICABLE PUBLICATIONS
A. NFPA standard No. 241 - Safeguarding Construction, Alteration, and Demolition Operations.
B.NFPA Standard No. 51B - Fire Protection in use of cutting and welding Processes.
C.NFPA Standard No. 101 - Life Safety Code (Current Edition)
D. OSHA Regulations 29CFR1926 - Construction Industry Standards. 1.Sub-
part P- Fire Protection and Prevention
2.Sub-part J- welding and Cutting
PART 2 - PRODUCTS
2.1 PRODUCTS:
01 01 10 (FSS)-2
Milwaukee VAMC February 15, 2017 Upgrade and Replace Building 123 Bid Set Submission Steam Line Piping and Insulation Project No. 695-17 -103
A. Table F-1 indicates which fire extinguishers are required for various combustible materials.
Table F-1 FIRE EXTINGUISHERS DATA
TYPE OF AGENT
Each class of fire calls for the right
kind of extinguisher. Using the
wrong extinguisher is dangerous
and may do more harm than good.
For your own protection, you
should know the classes of fire,
the different types of
extinguishers, how to use them
and why.
Fires in ordinary combustible
materials - paper, wood, and many
plastics. Quenching by water or
insulating by Multi-Purpose
(ABC),dry chemical is effective.
Fires in flammable liquids such as
gasoline, oils, grease, tars, paints,
lacquers and flammable gases.
Multi-Purpose (ABC). Regular Dry
Chemical, Halon 1211, and Carbon
Dioxide agents smother these
fires.
Fires in electrical equipment..
Motors, generators, switches and
appliances.. where a non
conducting extinguishing agent
Multi-Purpose (ABC), Regular Dry
Chemical, Halon 1211 or Carbon
Dioxide is required.
RANGE --------------------
Discharge Time ----------
Multi-Purpose Dry
Chemical
Monoammonium
Phosphate
Yes-excellent Adheres to
burning materials amd
forms a coating which
will smother the fire and
minimize reflash.
Yes-excellent Dry
chemical agent smothers
fire. Screen of agent
shields user from heat.
Yes-excellent Dry
chemical agent is non-
conductive. Screen of
agent shields user from
heat.
5 to 20 feet
10 to 25 seconds
Regular
Dry Chemical Sodium
Phosphate
No
Yes-excellent Dry chemical
agent smothers fire. Screen
of agent shields user from
heat.
Yes-excellent Dry chemical
agent is non-conductive.
Screen of agent shields user
from heat.
5 to 20 feet
10 to 25 seconds
Halon 1211
Bromoclorodi-fluoromethane
Yes-excellent
Halon 1211 leaves no
residue. May not normally
affect equipment.
Yes-excellent
Halon 1211 leaves no
residue. May not normally
affect equipment.
Yes-excellent
Halon 1211 is a non-
conductor, leaves no residue,
may not normally affect or
damage electrical
equipment.
8 to 18 feet
8 to 18 seconds
Depending on size
Carbon Dioxide
(CO2)
No
Yes-excellent
Carbon Dioxide leaves no
residue, may not normally
affect or damage
equipment.
Yes-excellent
Carbon Dioxide is a non-
conductor, leaves no
residue, may not normally
affect or damage electrical
equipment.
3 to 8 feet
8 to 30 seconds
Water
Yes
Water saturates
materials and prevents
rekindling.
No
Water will spread
flammable liquids and
not put it out.
No
Wate, a conductor,
should never be used on
live electrical fires.
Up to 40 feet
Up to 60 seconds
B.C over Plates
1. Receptacles - Manufactured by H. B. Enterprises or equal. Catalog No. 007
2.Switches - Manufactured by N. 13. Enterprises. Catalog No. 003
01 01 10 (FSS)-3
Milwaukee VAMC February 15, 2017 Upgrade and Replace Building 123 Bid Set Submission Steam Line Piping and Insulation Project No. 695-17 -103
PART III - EXECUTION
3.1 Construction offices and trailers used as storage are required to a located minimum distance from
permanent structures. Veterans Administration approval of location does not relieve the contractor at this
ultimate responsibility of meeting OSHA and NFPA Regulation.
3.2 Contractor is required to obtain a permit from the office of the Chief Engineer prior to start of each
welding/cutting operation. The Chief Engineer reserves the right to delegate the Project Manager as
approving official. The following form is acceptable for obtaining approval and may be reproduced at
contractor's expense. Other form must be submitted for approval by the Project Engineer prior to use.
3.3 The following checklist is provided to the contractor as a quick reference only. NFPA 513 should be
consulted for official requirements for protection of the area.
01 01 10 (FSS)-4
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10 (FSS)-5
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10 IC-1
SECTION 01 01 10 - IC
INFECTION CONTROL
DESCRIPTION
A. This section specifies the control of environmental infection control and risk assessment that the Contractor
must consider for construction & renovation projects in the medical facility. It includes Precautionary
management of, Inspections and Non invasive activities, small scale, short duration activities, that create
minimal dust. Major demolition and construction projects that generate a moderate to high levels of dust.
Movement of materials and equipment, and resources that are encountered or generated by the Contractor. The
Contractor is obligated to consider the specified control measures with the costs included within the various
contract items of work. An Infection Control Risk Assessment Matrix of Precautions for construction and
renovation for activities follows.
Step 1. Identify Construction Activity – see specification section 01 01 10 1-HR
TYPE A Minimal Fire Risk
Consult IC if
construction activity
occurs in highest patient
risk group
Inspection and Non-Invasive Activities. Includes, but is not limited to:
� removal of ceiling tiles for visual inspection limited to 1 tile per 50 square feet
� painting (but not sanding)
� wall covering, electrical trim work, minor plumbing, and activities which do not
generate dust or require cutting of walls or access to ceilings other than for
visual inspection.
� removal of floor tile less than 25 square feet, non-ACM and no grinding or dust generating activities
TYPE B
Limited Fire Risk
Consult IC if
construction activity
occurs in highest patient
risk group
Small scale, short duration activities which create minimal dust. Includes, but is
not limited to:
� installation of telephone and computer cabling
� access to chase spaces
� Cutting of walls or ceiling where dust migration can be controlled.
TYPE C
Moderate Fire Risk
Consult IC if
construction activity
occurs in any and all
patient risk group
Work that generates a moderate to high level of dust or requires demolition or
removal of any fixed building components or assemblies. Includes, but is not limited to:
� sanding of walls for painting or wall covering
� removal of floor coverings, ceiling tiles and casework
� new construction or renovations over 3 days duration
� major duct work, cabling activity, plumbing, piping, or electrical work
� soldering or brazing operations
� ANY activity that requires a burn permit
� Any activity that cannot be completed within a single workshift
TYPE D Significant Fire Risk
Consult IC if
construction activity
occurs in any and all
patient risk group
Major demolition and construction projects. Includes, but is not limited to:
� activities which require consecutive work shifts
� requires heavy demolition or removal of a complete building/cabling system
� New construction or renovations over 3 days duration
APIC Infection Prevention Manual for Construction Renovation 2015
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10 IC-2
B. Infection Control Risk and damage is defined as the presence of chemical, physical, or biological elements
or agents which:
1. Adversely effect human health or welfare,
2. Unfavorably alter ecological balances of importance to human life.
Using the following table, identify the Patient Risk Groups that will be affected.
If more than one risk group will be affected, select the higher risk group:
Step 2. Identify Patient Risk Group
Low Risk Medium Risk High Risk Highest Risk
� Office areas
� Warehouse
� Cardiology
� Echocardiography
� Endoscopy
� Physical Therapy
� Respiratory Therapy
� Outpatient Mental
Health
� Outpatient Clinics
� Simulation Lab
� Comp and Pen
� Emergency Room
� Laboratories (specimen)
� Linen
� Kitchen & Canteen
� Radiology/MRI
� Nuclear medicine
� Physical Therapy Tank
Area
� Any area caring for
immunocompromised
patients
� Pharmacy
� Cardiac Cath Lab / EP Lab
� Logistics Supply
� Central Sterile Supply
� Intensive Care Units
� Medical / Mental Health
Unit
� Negative pressure isolation rooms
� Oncology / Radiation
Oncology
� Inpatient and outpatient
operating rooms
� Dialysis
� Surgical Units
� Post Anesthesia Care Unit
� APC Unit
� Sterile Processing Services
C. Match the Patient Risk Group with Construction Project Type on the following matrix to find the level of
infection control activities required.
Patient Risk Group (Low, Medium, High, Highest) with the planned …
Construction Project Type (A, B, C, D) on the following matrix, to find the …
Class of Precautions (I, II, III or IV) or level of infection control activities required.
1) Infection Control approval will be required when the Construction Activity and Risk Level
indicate that CCllaassss IIIIII or CCllaassss IIVV control procedures are necessary. Contact the VA Project
engineer and the infection control officer before proceeding.
01 01 10 IC-3
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
TTYYPPEE AA TTYYPPEE BB TTYYPPEE CC TTYYPPEE DD
LLOOWW Risk Group II IIII IIII IIIIII//IIVV
MMEEDDIIUUMM Risk Group II IIII IIIIII IIVV
HHIIGGHH Risk Group II IIII IIIIII//IIVV IIVV
HHIIGGHHEESSTT Risk Group IIII IIIIII//IIVV IIIIII//IIVV IIVV
Step 3. Identify Level of Infection Control Activities Required
IC Matrix - Class of Precautions: Construction Project by Patient Risk
Patient Risk Group
Construction Project Type
D. Description of Required Infection Control Precautions by Class
During Construction Project Upon Completion of Project
1. Execute work by methods to minimize raising
dust from construction operations.
2. Immediately replace a ceiling tile displaced for
visual inspection
1. Terminal cleaning upon project completion.
CL
AS
S I
1. Provide active means to prevent airborne dust
from dispersing into atmosphere.
2. Water mist work surfaces to control dust while cutting.
3. Seal unused doors with duct tape.
4. Block off and seal air vents.
5. Place dust mat at entrance and exit of work area
6. *Remove or isolate HVAC system in areas
where work is being performed.
1. Wipe work surfaces with disinfectant.
2. Contain construction waste before transport in
tightly covered containers.
3. Wet mop and/or vacuum with HEPA filtered
vacuum before leaving work area.
4. Remove isolation of HVAC system in areas
where work is being performed.
5. Terminal cleaning as needed and/or upon project
completion.
CL
AS
S I
I
CL
AS
S I
II
1. *Remove or Isolate HVAC system in area where
work is being done to prevent contamination of
duct system.
2. Complete all critical barriers i.e. sheetrock,
plywood, plastic, to seal area from non-work area
or implement control cube method (cart with
plastic covering and sealed connection to work
site with HEPA vacuum for vacuuming prior to
exit) before construction begins.
3. Maintain negative air pressure within work site
utilizing HEPA equipped air filtration units.
4. Contain construction waste before transport in
tightly covered containers.
5. Cover transport receptacles or carts. Tape
covering unless solid lid.
* Use window for negative HEPA air exhaust when
accessible. Obtain V.A, resident engineer approval
for exhausting in existing exhaust ductwork.
1. Do not remove barriers from work area until
completed project is inspected by the owner’s
Safety Department and/or Infection Control
Department and thoroughly cleaned by the
owner’s Environmental Services Department.
2. Remove barrier materials carefully to minimize
spreading of dirt and debris associated with
construction.
3. Vacuum work area with HEPA filtered vacuums.
4. Wet mop area with disinfectant.
5. Remove isolation of HVAC system in areas
where work is being performed.
6. Terminal cleaning as needed and/or upon project
completion.
01 01 10 IC-4
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
1. Isolate HVAC system in area where work is
being done to prevent contamination of duct
system.
2. Complete all critical barriers i.e. sheetrock,
plywood, plastic, to seal area from non-work
area or implement control cube method (cart
with plastic covering and sealed connection to
work site with HEPA vacuum for vacuuming
prior to exit) before construction begins.
3. Maintain negative air pressure within work site
utilizing HEPA equipped air filtration units.
4. Seal holes, pipes, conduits, and punctures
appropriately.
5. Construct anteroom and require all personnel to
pass through this room so they can be vacuumed
using a HEPA vacuum cleaner before leaving
work site or they can wear cloth or paper
coveralls that are removed each time they leave
the work site.
6. All personnel entering work site are required to
wear shoe covers. Shoe covers must be changed
each time the worker exits the work area.
7. Do not remove barriers from work area until
completed project is inspected by the owner’s
Safety Department and Infection Control
Department and thoroughly cleaned by the
owner’s Environmental Services Department.
1. Remove barrier material carefully to minimize
spreading of dirt and debris associated with
construction.
2. Contain construction waste before transport in
tightly covered containers.
3. Cover transport receptacles or carts. Tape
covering unless solid lid
4. Vacuum work area with HEPA filtered vacuums.
5. Wet mop area with disinfectant.
6. Remove isolation of HVAC system in areas
where work is being performed.
CL
AS
S I
V
Step 4. Identify the areas surrounding the project area, assessing potential impact
Unit Below Unit Above Lateral Lateral Behind Front
Risk Group Risk Group Risk Group Risk Group Risk Group Risk Group
Appendix: Identify and communicate the responsibility for project monitoring that includes infection control
concerns and risks. The ICRA may be modified throughout the project Revisions must be communicated to the
Project Manager.
(Note: Renovation/construction area shall be isolated from the occupied areas during construction and shall
be negative with respect to surrounding areas)
Step 5. Identify specific site of activity eg, patient rooms, medication room, etc.
Step 6. Identify issues related to: ventilation, plumbing, electrical in terms of the occurrence
of probable outages.
Step 7. Identify containment measures, using prior assessment. What types of barriers?
(Eg, solids wall barriers); Will HEPA filtration be required?
01 01 10 IC-5
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
Step 8. Consider potential risk of water damage. Is there a risk due to compromising
structural integrity? (eg, wall, ceiling, roof)
Step 9. Work hours: Can or will the work be done during non-patient care hours?
Step 10. Do plans allow for adequate number of isolation/negative airflow rooms?
Step 11. Do the plans allow for the required number & type of handwashing sinks?
Step 12. Does the infection control staff agree with the minimum number of sinks for this
project? (Verify against AIA Guidelines for types and area)
Step 13. Does the infection control staff agree with the plans relative to clean and soiled
utility rooms?
Step 14. Plan to discuss the following containment issues with the project team. Eg, traffic
flow, housekeeping, debris removal (how and when)
01 01 10 IC-6
Milwaukee VAMC Upgrade and Replace Building 123
February 15, 2017 Bid Set Submission
Steam Line Piping anIdnf
Iencstuiloanti
Coonntrol Construction Perm
Pirtoject No. 695-17-1
Permit No: Location of Construction: Project Start Date:
Project Coordinator: Estimated Duration:
Contractor Performing Work Permit Expiration Date:
Supervisor: Telphone:
YES NO CONSTRUCTION ACTIVITY YE NO INFECTION CONTROL, RISK GROUP
TYPE A: Inspection, non-invasive activity GROUP 1: Low Risk
TYPE B: Small scale, short duration,
moderate to high levels GROUP 2: Medium Risk
TYPE C: Activity generates moderate to high levels of
dust, re Lures eater 1 work shift for completion GROUP 3: Medium/high Risk
TYPE. D: Major duration arid construction activities
Requiring consecutive work shifts GROUP 4: Highest Risk
CLASS I 1. Execute work by methods to minimize raising dust from 3. Minor Demolition for Remodeling
construction operations.
2. Immediately replace any ceiling tile displaced for visual inspection.
CLASS 11 1, Provides active means to prevent air-bone dust from 6. Contain construction waste before transport in tightly
dispersing into atmosphere covered containers.
2. Water mist work surfaces to control dust while cutting. 7. Wet mop and/or vacuum with HEPA filtered vacuum 3. Seal unused doors with duct tape. before leaving work area. 4. Block off and seal air vents. S. Place dust mat at entrance and exit of work area. S. Wipe surfaces with disinfectant. 9. Remove or isolate HVAC system in areas where work
is being performed.
CLASS 111
Date
Initial
1. Obtain infection control permit before construction begins. 6. Vacuum work with HEPA filtered vacuums.
2. Isolate HVAC system in area where work is being done to 7. Wet mop with disinfectant
prevent contamination of the duct system. S. Remove barrier materials carefully to minimize 3. Complete all critical barriers or implement control cube spreading of dirt and debris associated with
method before construction begins. construction. 9. Contain construction waste before transport in
4. Maintain negative air pressure within work site utilizing tightly covered containers.
HEPA equipped air filtration units. 10. Cover transport receptacles or carts. Tape covering.
S. Do not remove barriers from work area until complete 11. Remove or isolate HVAC system in areas where work project is thoroughly cleaned by Env. Services Dept. is being performed/
Class IV
Date
Initial
l. Obtain infection control permit before construction begins. 7. All personnel entering work site are required to wear
2. Isolate HVAC= system in area where work is being done to shoe covers prevent contamination of duct system. S. Do not remove barriers from work area until completed
3. Complete all critical barriers or implement control cube project is thoroughly cleaned by the Environmental method before construction begins. Service Dept.
4. Maintain negative air pressure within work site utilizing 9. Vacuum work area with HEPA filtered vacuums.
HEPA equipped air filtration units. 10. Wet mop with disinfectant. 5. Seal holes, pipes, conduits, and punctures appropriately. 11. Remove barrier materials carefully to minimize
6. Construct anteroom and require all personnel to pass spreading of dirt and debris associated with
through this room so they can be vacuumed using a HEPA construction. vacuum cleaner before leaving work site or they can wear 12. Contain construction waste before transport in tightly cloth or paper coveralls that are removed each time they covered containers.
leave the work site. 13. Cover transport receptacles or carts. Tape covering. 14. Remove or isolate HVAC system in areas where is
being done.
Additional Requirements:
Exceptions/Additions to this permit Date
Date Initials Initials are noted b attached memoranda
Permit Request By: Permit Authorized By:
Date: Date:
03
01 01 10 IC-7
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
E. Apply Life Safety and standards (APIC) and the following criteria would need to be assured in order
to maintain the supply air side open during Class 4 construction activity:
• The air supply is 100% fresh air and the site and adjacent areas can be kept under negative pressure at
all times.
• There is no re circulated air in this section
• There is no duct work involved in this section of the demolition
• The site can never be positive to the adjacent areas (i.e. keep the negative air machines on at all times
or for 1-2 hours post site work until the negative action can be maintained.
• A log is maintained to document that the negative pressure is checked and has been maintained during
those hours when the negative air machines are turned off. (An alarmed device is recommended for
this purpose and should be maintained and monitored by the construction personnel).
PART 2 - PRODUCTS, MATERIALS AND EQUIPMENT
2.1 MATERIALS AND EQUIPMENT
GENERAL REQUIREMENTS
A. All materials shall be delivered in their original package, container or bundle bearing the name of the
manufacturer and the brand name (where applicable). When transporting new materials & equipment
though the hospital use 4 mil Poly sheeting encasing materials, tools and equipment or use a totally
enclosed cart.
B. Store all materials subject to damage off the ground, away from wet or damp surfaces and under cover
sufficient enough to prevent damage or contamination. Flammable materials cannot be stored inside
buildings. Replacement materials shall be stored outside of the regulated/work area until construction
is completed.
C. The Contractor shall not block or hinder use of buildings by patients, staff, and visitors to the VA in
partially occupied buildings by placing materials/equipment in any unauthorized place.
D. The Competent Person shall inspect for damaged, deteriorating or previously used materials. Such
materials shall not be used and shall be removed from the worksite and disposed of properly.
E. Demolition materials must be transported in totally enclosed containers.
1) Demolition on above ground floors may use a window debris chute to convey materials to an
enclosed dumpster that provides dust and noise control. The contractor is responsible to maintain
the original appearance of the building fascia.
2.1.2 NEGATIVE PRESSURE FILTRATION SYSTEM
A. The Contractor shall provide enough negative air machines to completely exchange the regulated area
air volume 4 actual times per hour. The Competent Person shall determine the number of units needed
for each regulated area by dividing the cubic feet in the regulated area by 15 and then dividing that
result by the actual cubic feet per minute (cfm) for each unit to determine the number of units needed
to effect 4 air changes per hour. Provide a standby unit in the event of machine failure and/or
emergency in an adjacent area.
2.1.3 DESIGN AND LAYOUT
A. Before start of work for each phase of the project, the contractor is to submit for approval, an
infection control plan which will include the design and layout of the regulated area to include the type
and location of infection control construction barriers to be used, access points, ante room location, etc.
The submittal shall indicate the number of, location of and size of negative air machines and exhaust
route & location of the windows to be used. The point(s) of exhaust, air flow within the regulated area,
anticipated negative pressure differential, and supporting calculations for sizing shall be provided. In
addition, submit the following:
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10 IC-8
B. Manufacturer's information on the negative air machine(s).
C. Method of supplying power to the units and designation/location of the panels.
D. Description of testing method(s) for correct air volume and pressure differential. Provide
manufacturer's product data on the pressure differential measuring device used.
E. If auxiliary power supply is to be provided for the negative air machines, provide a schematic diagram
of the power supply and manufacturer's data on the generator and switch.
F. Location of isolation negative air pressure monitor.
G. The following is a SAMPLE plan:
SAMPLE INFECTION CONTROL PLAN
2.1.4 NEGATIVE AIR MACHINES
A. Negative Air Machine Cabinet: The cabinet shall be constructed of steel or other durable material
capable of withstanding potential damage from rough handling and transportation. The width of the
cabinet shall be less than 30" in order to fit in standard doorways. The cabinet must be factory sealed
to prevent dust from being released during use, transport, or maintenance. Any access to and
replacement of filters shall be from the inlet end. The unit must be on casters or wheels.
B. Negative Air Machine Fan: The rating capacity of the fan must the air moving capacity under actual
operating conditions. Manufacturer's typically use "free-air" (no resistance) conditions when rating
fans. The fan must be a centrifugal type fan.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10 IC-9
C. Negative Air Machine Final Filter:
1) When exhausting directly to the outside from a window or penetration the filter shall be a
minimum MERV 8 pleated filter media completely sealed on all edges within a structurally rigid
frame.
2) When exhausting to a exhaust duct: the final filter shall be a HEPA filter. The filter media must be
completely sealed on all edges within a structurally rigid frame. The filter shall align with a
continuous flexible gasket material in the negative air machine housing to form an air tight seal.
Each HEPA filter shall be individually tested and certified by the manufacturer to have an
Testing shall have been done in accordance with Military Standard MIL- STD-282 and Army
Instruction Manual 136-300-175A. Each filter must bear a UL586 label to indicate ability to
perform under specified conditions. Each filter shall be marked with the name of the manufacturer,
serial number, air flow rating, efficiency and resistance, and the direction of test air flow.
D. Negative Air Machine Pre-filters: The pre-filters, which protect the final HEPA filter by removing
larger particles, are required to prolong the operating life of the HEPA filter. Two stages of pre-
filtration are required. A first stage pre-filter shall be a low efficien
larger. A second stage pre-
or larger. Pre-filters shall be installed either on or in the intake grid of the unit and held in place with a
special housing or clamps.
F. Negative Air Machine Safety and Warning Devices: An electrical/ mechanical lockout must be provide
to prevent the fan from being operated without a HEPA filter. Units must be equipped with an
automatic shutdown device to stop the fan in the event of a rupture in the HEPA filter or blockage in
the discharge of the fan. Warning lights are required to indicate normal operation; too high a pressure
drop across filters; or too low of a pressure drop across filters.
G. Negative Air Machine Electrical: All electrical components shall be approved by the National
Electrical Manufacturer's Association (NEMA) and Underwriter's Laboratories (UL). Each unit must
be provided with overload protection and the motor, fan, fan housing, and cabinet must be grounded.
2.1.5 PRESSURE DIFFERENTIAL
A. The fully operational negative air system within the regulated area shall continuously maintain a
pressure differential of -0.02" water column. Before any disturbance of any material or building
system, this shall be demonstrated to the VA by use of a pressure differential meter/manometer as
required by OSHA 29 CFR 1926.1101(e)(5)(i). The Competent Person shall be responsible for
providing and maintaining the negative pressure and air changes as required by OSHA and this
specification.
2.1.6 TESTING THE SYSTEM
A. The negative pressure system must be tested before any disturbedance. After the regulated area has
been completely prepared, the decontamination units set up, and the negative air machines installed,
start the units up one at a time. Demonstrate and document the operation and testing of the negative
pressure system to the VA using smoke tubes and a negative pressure gauge. Testing must also be done
at the start of each work shift.
2.1.7 DEMONSTRATION OF THE NEGATIVE AIR PRESSURE SYSTEM
A. The demonstration of the operation of the negative pressure system to the VA shall include, but not be
limited to, the following:
1) Contractor to install Triatek (Web site www.Ttk.com) negative air isolation monitoring stations
at the sites access doors or at opposite sides of the construction area check with COTR for number
of units and location.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10 IC-10
2) Curtains of the decontamination units move in toward regulated area.
3) Use smoke tubes to demonstrate air is moving air across all areas in which work is to be done.
4) Plastic barriers and sheeting move lightly in toward the regulated area.
2.1.8 USE OF SYSTEM DURING CONSTRUCTION OPERATIONS
A. Start units before beginning any disturbance occurs. After work begins, the units shall run
continuously, maintaining 4 actual air changes per hour at a negative pressure differential of 5.0 Pa (-
0.02") water column, for the duration of the work until a final visual clearance and final air clearance
has been completed.
B. The negative air machines shall not be shut down for the duration of the project unless authorized by
the VA, in writing.
C. Construction work shall begin at a location closest from the units and proceed away from them. If an
electric failure occurs, the Competent Person shall stop all work and not resume until power is restored
and all units necessary are operating properly again.
D. The negative air machines shall continue to run after all work is completed and until a final visual
clearance and a final air, clearance has been completed for that regulated area.
2.2 CONTAINMENT BARRIERS AND COVERINGS IN THE REGULATED AREA
2.2.1 GENERAL
A. Seal off the perimeter to the regulated area to completely isolate the regulated area from adjacent
spaces. All surfaces in the regulated area must be covered to prevent contamination and to facilitate
clean-up. Should adjacent areas become contaminated, immediately stop work and clean up the
contamination at no additional cost to the Government.
2.2.3 CONTROLLING ACCESS TO THE REGULATED AREA
A. Access to the regulated area is allowed only through the personnel decontamination facility (PDF). All
other means of access shall be eliminated and OSHA warning signs posted as required by OSHA. If
the regulated area is adjacent to or within view of an occupied area, provide a visual barrier of opaque
fire retardant poly sheeting at least 4 mils thick to prevent building occupant observation. If the
adjacent area is accessible to the public, the barrier must be solid and capable of withstanding the
negative pressure.
2.2.4 CRITICAL BARRIERS
A. Completely separate the regulated area from adjacent areas using fire retardant poly at least 6 mils
thick and duct tape. Individually seal with two layers of 6 mil poly and duct tape all HVAC openings,
cap off exhaust into the regulated area. Individually seal all lighting fixtures, clocks, doors, windows,
convectors, speakers, or any other objects in the regulated area. Use care with hot/warm surfaces see
fig 1.
2.2.5 PRIMARY BARRIERS
A. Temporary Construction Partitions:
1. Install and maintain temporary construction partitions to provide separations between construction
areas and adjoining areas. Construct partitions of gypsum board or treated plywood (flame spread
rating of 25 or less in accordance with ASTM E84) on one side of wood or metal steel studs. Seal
with one layers of 6 mil poly for a vapor barrier under gypsum or plywood. Extend the Poly
through suspended ceilings to floor slab or roof. Seal penetrations at door openings, install tight-
fitting yellow construction doors with self-closing devices see fig. 2 for barrier construction.
Contractor to provide the construction(s) door for the project.
2.2.6 CONTRACTOR SPILL RESPONSE KIT
A. The kit should include the following:
01 01 10 IC-11
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
1. Shop Vacuum.
2. Multi-Purpose Spill Control Sorbents to absorb nonaggesive liquids up to 30 gallons.
3. Sorbents pillows.
4. Pipe leak clamps for copper & steel pipe in sufficient size range and quantity base on project
piping scope.
5. Bucket & mop and water resistant duct tape.
Figure 1
01 01 10 IC-12
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
Figure 2
Figure 3
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–1 (SN)
SECTION 01 01 10 (SN)
SPECIAL NOTES
7/2016
PART 1: GENERAL
1.1 Not Used.
1.2 FIRE ALARM SYSTEM:
FIRE/SECURITY ALARM SYSTEMS: Contractor shall advise the Graphic Control Center and/or the Police Desk at
extension 41010/42222 respectively, prior to any work which might result in the Fire Alarm System or Security
System (this includes but is no limited to: Smoke Detectors, Water Flow Switches, Pull Stations, Sprinkler
Heads, Motion Detectors, Door Contacts, Security Door Controls, etc.) being activated, in addition to having an
approved outage form from the Facility Management Department. Notification to Graphics and/or the Police
Desk and having an outage form, does not absolve the contractor from following the proper procedures to
prevent the system from activating, i.e. covering the smoke heads with paper bags, closing valves, containing
dust, monitoring and controlling security devices, etc.). If any system activates due to the contractor's failure to
notify the Graphic Control Center, the Contractor’s failure to follow proper procedures, or the Contractor’s
failure to obtain an outage form, a Modification/Settlement by Determination deduction of $2,500.00 per
alarm/event or notice from the Police that a construction area was left unsecured will be issued to the
contractor.
1.3 SCHEDULING OF WORK:
A. Contractor shall verbally schedule work areas with COR not less than fifteen (15) calendar days in advance
of commencement of work. Verbal notification shall be backed up and verified in writing.
B. Contractor shall verbally schedule outages or service interruptions with COR not less than fifteen (15)
calendar days in advance of intended commencement of work. Notification does not guarantee the date
of scheduled outage or service interruption however COR will schedule such dates and inform the
contractor. Date will be scheduled with medical center personnel when service interruption will minimize
affect to hospital patients and operations. Contractor to submit VA System Outage Request form to COR
not less than fifteen (15) calendar days in advance of intended commencement of outage work.
Contractor to attend (2) weekly pre-outage meetings with Engineering and staff to coordinate actual date
of outage, duration, time of outage, phasing, and affected services. In addition, contractor to attend the
pre-outage meeting one hour prior to outage to coordinate communications, readiness, pre-outage
checklist, document requirements, temporary measures, lock out tag out and other outage requirements
and procedures.
C. Contractor to attend weekly construction meetings.
1.4 PROTECTION OF WORK AREAS:
Contractor to provide drop cloths when working in occupied areas to avoid staining or damaging existing
carpets or vinyl tile floors.
1.5 HOURS OF WORK:
A. The hours of contract work shall be from 7:00 a.m. until 4:30 p.m. the normal work shift for hospital
employees, the contractor shall verify shift or shifts required for construction areas. Other than normal,
after (off) hours, including federal holidays shall be scheduled two days prior to starting with the Project
Manager. These off hours will be required to complete the project in the time allotted for the contract at no
additional cost to the Department of Veterans Affairs. Upon approval of the Department of Veterans
Affairs, the contractor will propose the scope or extent of off hour work due to individual contractor
resources available to accomplish this project in the time allotted. In addition, these off hours will be
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–2 (SN)
required for utility/service interruptions, and any/other work that may interrupt the operation of the
occupied space, i.e., some road construction, demolition, work in occupied areas, work affecting occupied
areas, etc. Some noise producing demolition operations will be required to be scheduled for off work hours
as directed by COR and described on drawings.
B. Certain work items, which require off-hour work, have been identified. These items are indicated on the
drawings. Refer, in particular, to Phasing Notes on Drawings. All drawings shall be reviewed for off-hour
work requirements and items creating disturbance to the hospital staff or patient care must be performed
during off-hour working periods as established and approved by the VA Engineer.
C. Building will be occupied during performance of work, but areas of alterations will be vacated. Contractor
shall take all measures and provide all material necessary for protecting existing equipment and property
in affected areas of construction against dust and debris, so that equipment and affected areas to be used
in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of
Veterans Affairs personnel and patients through other construction areas, which serve as routes of access
to such affected areas and equipment. Coordinate alteration work in areas occupied by the VA so that
Medical Center operations will continue during the construction period. Contractor to construct 7 feet tall
by 5 feet wide metal stud and drywall tunnels through occupied space as deemed necessary by the VA for
access by Medical Center personnel and maintaining construction operations.
1.6 SUBMITTALS:
A. Start of Construction: The contractor submittals must be forwarded in sufficient time to permit proper
consideration and approval by the government and be timed to permit adequate lead time for procurement of
contract required items. Delivery of submittals to the COR or verbal acknowledgement of receipt by the Project
Manager does not constitute approval.
B. Sole Source Items: There will be no substitutions for the products and services listed below. Sole source
items to be in accordance with VAAR 852.236-90 Restriction on submission and use of equal products.
This clause applies to the following items:
System / Equipment Manufacturer and Model In Contract
(Yes or No)
Fire Alarm System
Siemens Cerberus Pyrotronics System
No
Security System & Code Blue
Johnson Controls Pegasys/P2000 System
No
Pneumatic Tube System
Swiss Translogic
No
Medical Gas Alarms
Puritan Bennett Medical Gas alarms
No
Nurse Call
Jeron Health Care Call System Provider 790 Nurse
Call System
No
Isolation Room Controls
Employ Critical Room Control
No
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–3 (SN)
Doors, Hardware, Locks and Keying
Employ Best Patented cylindrical and mortise sets
with Medeco 7-pin interchangeable cylindrical cores,
LCN Closers (Mechanical, Electronic Hold-Open,
Electromagnetic),Von Duprin Exit Devices, Hager
Hinges
--
Automatic Door Operator
Tormax 1301 Super HD Automatic Door Operator
(Low Energy)
No
Building Automation and HVAC
Controls
Johnson Controls Metasys control system
No
Refrigerator Temperature Controls
Cooper Atkins Temp Trak Refrigeration Temperature
Control System
No
Wander Guard
Accutech ES2200 Patient Wandering Prevention
System
No
Modular Furniture
Herman Miller Products
No
Patient Ceiling Lifts
Guldmann GH3+ Ceiling
No
Modular Brick
Belden Brick (County Materials) Seal Brown Velour A,
Modular Brick
No
Automatic Transfer Switches
Eaton Magnum Transfer Switches
No
Electrical Metering
Eaton/Cutler Hammer PowerXpert system
No
Interiors
Reference Interior Schedule
No
Tile Grout Sealant
Microguard Inorganic Protective Barrier
No
Firestop Systems
HILTI Firestop Systems
No
Prefabricated Modular
Wall/Partition Systems and
DIRTT Environmental Solutions
No
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–4 (SN)
Enclosures
Stone Flex Aggregate Panels
CEP Panels, Inc., Bermuda White SN 100, Fine Grade
Aggregate Finish
No
Curtain Track Rail Support System
(CTRSS)
Barrier Free Lift RX-6001/Architex Speed Fabric
No
Interior Signage
2/90 Sign Systems
No
1.7 EMERGENCY SERVICE:
All offerors, if successful, must be able to respond to all contract and contractor created emergency services
resulting from contractor actions and installations, as determined by the Department of Veterans Affairs COR,
with qualified staff personnel within one (1) hour of verbal notification during construction stages and warranty
period. Bidders must be prepared to show proof, in writing, that they can satisfy this requirement prior to
award.
1.8 KEYS:
Keys for access to construction/work areas may be issued to the contractor at the discretion of the Project
Manager. Up to three sets of keys will be provided at no cost. All keys will be assigned through the SAMS box
and the contractor will be given access based on their VA ID Card. Upon completion of the work, failure to
return all issued keys to the Project Manager will result in the issuance of a Settlement by Determination in the
amount of $100.00 for each outstanding key. In addition, a $50.00 fee will be paid to VA for each outstanding
key. Keys will be provided through the FM SAM Box. Keys are to be picked up and returned daily. If keys are
not returned by the end of the day, a modification of $50.00/key per day will be assessed against the
contractor.
1.9 SAFETY ITEMS:
A. Training:
• All employees of contractor and subcontractor shall be aware of the egress routes from the
construction areas. It is the contractor's responsibility to ensure all employees are aware of the
fire alarm codes for the building they are working in and participate in fire alarm drills and actual
fire alarms.
• Project Site Superintendent shall have the 30-hour OSHA certified Construction Safety course.
• All employees of general contractor or subcontractors shall have the 10-hour OSHA certified
Construction Safety course.
• Submit training records of all such employees for approval before the start of any work onsite.
B. Barricades: The contractor is responsible to erect barricades, construction and safety signs, and new
egress routes. The barricades will be erected to restrict areas where hazardous operations are
performed. The construction and safety signs shall consist of caution signs as determined and approved
by VA; egress signs, where egress has been altered for construction; and any applicable hazardous
warning signs. If the egress is changed due to construction, the contractor shall provide temporary
directional signs for changes as determined by VA and for construction of any walkways, steps, or
overhead protection scaffolding or the like as required providing a new means of egress. Emergency
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–5 (SN)
egress plan shall be developed by the contractor and submitted for approval by the designated VA
safety manager before egress routes are altered.
C Fire Extinguisher: The contractor and subcontractors shall provide fully charged and fully operational fire
extinguishers as required and in accordance with section FSS on the job site(s) at all times. Reference
section 01 01 10 FSS. NFPA 10 requires the bottom of the extinguisher to be at least 4-inches above
finished floor and the top of the extinguisher shall be no higher than 60-inches above finished floor.
D. Debris: Combustible storage and debris shall be kept to the lowest level necessary for required daily
operations. The construction area shall be kept clean as indicated in general requirements and conditions
E. Gasoline Powered Equipment: Gasoline powered equipment shall not be used within the confines of any
building on the Medical Center without specific written permission from the Chief, Engineering Service.
F. Fire/Smoke Doors: Fire and/or smoke doors shall not be propped open or prevented from closing and
latching. This includes mechanical equipment rooms and utility closet doors.
G. Construction Site Phone: Contractor to run wiring from telephone closet to the construction space for the
installation of a VA phone in the constitution space. Installation of the phone is required prior to
construction can begin. The VA will provide the phone.
H. Construction Hard Hats: General Contractor to provide (4) sets of hard hats and safety glasses for each
worksite for VA staff use.
I. Exit Signs:
a. Inside Construction Space: Contractor to provide luminescent Exit Signs throughout the
construction space such that while standing in any place within the construction space, an Exit
sign is visible and the path of egress can be followed.
b. Outside Construction Space: Contractor will cover, relocate, etc. Exit signs impacted due to their
construction operations as directed by the ILSM and the VA Safety Officer.
1.10 SECURITY OF CONSTRUCTION SITES – Contractor Regulations
A. All construction sites must be secured to prevent inappropriate access by patients, visitors, and employees.
While such security fences, doors, and barricades are temporary, they must be substantially installed to
control access to the site. The existing security (Pegasys by Johnson Controls and Ingersoll Rand) system
must be extended to each construction access door. Each construction door must be provided with an
Ingersoll Rand Integrated Reader Lock programmed to the existing VA security system. Construction sites
and all security measures must be monitored daily to ensure that security is maintained. Local VA Police
must be alerted about the construction project. At the close of activity daily, before securing the site or
portions of the site, the contractor must ensure that there are no patients, visitors, or staff in the area. If
construction site problems arise, the Contracting Officer and COR will take appropriate action to correct
any and all safety and security conditions.
B. VA engineering, safety/fire department, and police staff must have the right to access the construction site
as needed to perform their assigned responsibilities.
C. Lock up the worksite at all times to prevent patients and other unauthorized people from entering the site.
D. The need for job site security is much greater when work is being conducted in psychiatric areas to protect
the safety of the patients. All job boxes, tools, etc., must be locked up even when workers are on site
unless there’s enough activity to assure that patients cannot access tools or site. Verify that no one is in the
construction area upon locking up the site for the evening.
E. Two evacuation routes from the worksite must be maintained at all times.
F. Contractors may lock up their tools etc., with personal locks.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–6 (SN)
1.11 PENETRATIONS:
A. WALL:
a. All wall and/or floor penetrations created by work on this contract, whether by demolition or new
construction, shall be patched by the general contractor or as assigned by the general contractor. All
patching materials shall be of like kind or a suitable substitute approved by NFPA or UL.
b. If the permit is for other than inspection, a Follow-Up Inspection page will need to be filled out by the
person performing the installation/removal work, which then needs to be signed and returned to
whoever originally issued the permit. The permit initiator is then responsible for checking the areas
listed on the permit to ensure firestopping was completed according to Facility standards and
penetrations sealed with an approved fire/smoke sealant compound so as to maintain fire and smoke
separation integrity. Documentation of the sealant or system used in the penetration must be made
available at the affected penetration by the permit requestor at the time of permit completion
inspection. The program or person completing the follow up inspection must validate that the sealant
compound or system is properly rated and installed for maintaining the rating of the affected smoke or
firewall. Photo-documentation in lieu of interim inspections can be performed to validate work.
c. ONLY (1) one type of fire sealant is permissible per hole.
d. The permit will be in this person’s possession while all inspections and/or work are being performed.
B. CEILINGS:
a. To ensure that proper ceiling penetrations are sealed, all internal departments and contractors doing
any cabling, wiring, plumbing, etc., must obtain a ceiling access permit from Facilities Services prior to
installation.
b. All wall penetrations must be located, marked, and sealed by contractor responsible for penetration.
As penetrations are sealed, Facilities Service must be contacted to inspect penetrations for proper
sealing.
c. If the permit is for other than inspection, a Follow-Up Inspection page will need to be filled out by the
person performing the installation/removal work, which then needs to be signed and returned to
whoever originally issued the permit. The permit initiator is then responsible for checking the areas
listed on the permit to ensure firestopping was completed according to Facility standards and
penetrations sealed with an approved fire/smoke sealant compound so as to maintain fire and smoke
separation integrity. Documentation of the sealant or system used in the penetration must be made
available at the affected penetration by the permit requestor at the time of permit completion
inspection. The program or person completing the follow up inspection must validate that the sealant
compound or system is properly rated and installed for maintaining the rating of the affected smoke or
firewall. Photo-documentation in lieu of interim inspections can be performed to validate work.
d. The permit will be in this person’s possession while all inspections and/or work are being performed.
e. At the end of each work day and prior to leaving work site, the contractor shall replace all ceiling tiles
temporarily removed to do work above finished ceilings in corridors.
f. If it is not practical to replace all ceiling tiles on a daily basis the contractor is to construct 7 feet tall by 5
feet wide metal stud and drywall tunnels through occupied spaces as deemed necessary by the VA for
access by Medical Center personnel and maintaining construction operations. Upon the first incident of
the contractor not replacing the ceiling tiles, this tunnel construction will have to commence
immediately prior to any further construction on the project.
C. Reference section 01 01 10 – 1HR for additional information.
1.12 PHASING AND UNUSUALLY SEVERE WEATHER CONDITIONS:
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–7 (SN)
Phasing on this contract is critical as portions of the area to be remodeled shall remain occupied throughout the
construction work. Contractor will be working in an operational hospital and not be provided designated
elevators or entrances. The contractor will share the corridors, the B-Bank elevators, loading dock, etc. with
staff, patients and other contractors. Each phase shall be as described on the drawings and/or specifications
shall be completed in the sequence described. Also refer to Section 01 00 00, Article 1.6.G. Phasing.
Unusually Severe Weather Conditions: The contractor is expected to understand the seasonal conditions
affecting the work and to take into account normal weather variations at the site location during the planned
period of performance. Before a determination that the contractor is entitled to additional time extension
(excused delay) for unusually severe weather, the contractor must demonstrate (1) that the weather was
unforeseeable and unusually severe and (2) that critical path work was actually delayed by the weather. Risk
allocation for unusually severe weather conditions is the responsibility of the contractor and is not
compensable.
1.13 PROTECTION OF PROPERTY
The contractor is required to preserve and protect all structures, equipment, and vegetation on or adjacent to the
work site, which are not to be removed and which do not unreasonably interfere with the work required under the
contract. The contractor will be required to repair any damage to facilities resulting from failure to exercise
reasonable care in performing the work.
1.14 SCAFFOLDING:
All scaffolds and other work platforms construction activities shall comply with 29 CFR 1926. Contractor is to
provide copies of daily scaffolding inspections with daily logs.
1.15 ENERGY EFFICIENCY REQUIREMENTS:
A. Federal Executive Order #13423/#13514 requires all energy efficiency materials, equipment, and systems to
be evaluated and if feasible incorporated into VA Projects. The A/E, prime contractor, and all subcontractors
shall cooperate with the Federal Government in specifying, evaluating, documenting, purchasing, and
installing energy efficient equipment that meet basic energy efficiency criteria established by the VA.
B. All design and installation will be in accordance with current VAMC, HVAC design guides, NEC, NFPA,
ASHRAE 90.1, state, local and all VA and federal codes.
C. The VA intends to provide energy savings equipment and design modifications for current energy usage to
the most efficient and economical level possible.
1.16 INSPECTIONS:
All mechanical and electrical work shall be inspected by Engineering Service (Shop & COR) personnel prior to
being put into operation or closing up if work will be hidden by walls, ceilings, drop ceilings, cover plates, access
panels, etc. Contractor shall notify the VA RE a minimum of two days prior to the inspection date, times and
dates shall be scheduled and agreed upon by VA. Installations will be inspected by these VA personnel for work
in compliance with State, Federal, Local, Dept. of Veterans Affairs Codes, regulations and contract
specifications. If corrections, alterations, adjustments, new construction etc. is required, the VA will be notified
within 48 hours of completion of such items. These inspections and corrections, alterations, etc. will be made
at no additional time or cost to VA.
1.17 CONTRACTOR’S AGREEMENT - RULES AND REGULATIONS FOR ALL CONTRACTORS
The following is the contractor’s agreement required to be signed at the pre-construction meeting and updated
monthly when new subcontractors start working on the job site. The agreement is the general contractor’s
responsibility to ensure all subcontractor personnel are trained and acknowledge (sign) the agreement.
A. STANDARD POLICY:
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–8 (SN)
All outside General contractors and Sub-contractors will coordinate all work within the hospital with
Facilities Management before beginning work.
B. PURPOSE:
General Contractor will ensure that each individual General Contractor and Sub-Contractor employee is
responsible for complying with established hospital standards, applicable OSHA Safety Requirements,
federal, state and local environmental regulations, wearing prescribed safety equipment, and preventing
avoidable accidents.
C. PROCEDURE
The contractor will ensure that each individual contractor and sub-contractor employee review,
understand and acknowledge (sign) the following information prior to the commencement of work
scheduled at this facility. General Contractor will forward copies of signed acknowledgements to
Project Engineer of all new employees on a monthly basis.
The following building rules and regulations affect all contractor personnel, suppliers, and vendors:
D. Access to Construction Areas
• Access is limited to areas such as critical care and surgical units, as well as mechanical/electrical
rooms, etc. Access can be obtained through Facilities Service.
• Access to any floors of the facility after normally scheduled work hours (Monday-Friday, 7:00 a.m.-
5:00 p.m.) must be scheduled in advance with the Project section of Facilities Service. Police and
Security reserves the right to refuse access to anyone without prior authorization and identification.
• Ready access for the Engineering, Safety, Police and (the Fire Department) shall be maintained to all
areas under construction at all times.
• Areas under construction shall be locked during off-hours. Keys and cylinders for this purpose are
obtained through Facilities Service. Contractors will not put their locks on any doors without VA
approval.
E. Accidents and Injuries
• First Aid/Medical Aid/Emergency Treatment for workers: The contractor must post emergency phone
numbers and treatment facilities if any contractor employees are injured on the job, or need medical
treatment
• Work site injuries must be reported to the VA. The VA has an accident reporting form (form number
2162). The COTS/ Safety/ or Security and Police Service will initiate the 2162. Once the VA has
completed the supervisor’s portion the injured individual will be required to complete the narrative
portion of the report. The service chief responsible for the contract is also required to sign the report
and forward the original report to the Safety Section.
F. Asbestos
• There are both friable and non-friable asbestos-containing materials located within the hospital
complex. Inspection reports are located in the Facilities Service Department. Contractors are required
to be aware of the asbestos materials located in the vicinity of their work. Further, all contractors are
expressly forbidden to disturb any asbestos-containing materials unless specifically authorized in
writing by VA. Under no circumstances are any materials supplied or installed by the contractor to
contain asbestos in any form or quantity.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–9 (SN)
• Asbestos removal contractors will be trained and licensed, and will follow all OSHA rules, VA
specifications, state and local regulations from notification to disposal.
• A VA representative will verify the adequacy of the barriers and ventilation before any asbestos
removal work is conducted.
• The contractor is responsible for monitoring his own employees’ exposure to asbestos.
• Additional specific asbestos removal specifications will apply.
• Contractor to provide a Fiscal Year breakdown of Asbestos Costs on the project.
G. ACM TRACE WORK OPERATIONS:
• ACM TRACE RESULTS - Should renovation activities deem the material friable due to cutting, grinding
or other mechanical means of removal, an employer is bound by OSHA 29 CFR regulations 1926.1200
(d) (5) (iv) to protect their employees. This may determine that removal of the materials be
performed by asbestos abatement workers trained in 29 CFR 1926.1101.
*OSHA regulation 1910.1200 HAZARDOUS COMMUNICATION Section (d)(5) Hazard determination
“…employer shall determine the hazards of mixture of chemicals as follows: (iv) “If the…employer has
evidence to indicate that a component present in the mixture in concentrations of less than one
percent…could be released in concentrations which would exceed an established OSHA permissible
exposure limit…or could present a health risk to employees in those concentrations, the mixture shall
be assumed to present the same hazard.”
• General Summary:
1. Employees, contractors, etc. must be warned about the presence of asbestos.
2. The contractor must have a competent person on site during work. (At a minimum, it should be
a trained, certified asbestos supervisor).
3. Personal exposure assessments (negative exposure assessment) are required (PCM analysis) and
workers should begin work with PPE.
4. Wet methods and daily clean up and sealing waste in leak tight containers are required. The
following is a list of references from OSHA guides. Note: The reference to the word “sheet rock”
is based on trace (<1%) of asbestos being present in the “sheet rock.”
• The contractor will be responsible for proper work practices and prohibitions for all construction
activities involving material that contains any amount of asbestos regardless of the exposure levels.
And the standard has exposure-based requirements, consisting of a 0.1 fiber/cc 8-hour TWA PEL and
a 1 fiber/cc 30-minute excursion limit, and other requirements that apply whenever worker
exposures exceed either or both of the limits, regardless of the amount of asbestos contained in the
materials involved.
• If some of the items associated with the installed sheetrock contain some asbestos but none of them
contain >1% asbestos, then removal of the sheetrock is considered unclassified asbestos work. This
means that only certain ones of the standard's work practice and engineering control obligations, and
prohibitions pertain. Some of the general ones do not pertain because they apply to installed
building materials containing >1% asbestos (ACM). How many of the eligible general work practice
and engineering control obligations, and prohibitions are applicable depends on whether the
employee levels of exposure to airborne asbestos exceed either of the asbestos PELs. In further
explanation: These OSHA references are specific to this issue.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–10 (SN)
• If the employees' asbestos exposures exceed neither asbestos PEL, then only two of standard's
general work practice control procedures and three of the standard's general prohibitions pertain to
the sheetrock removal operation; none of the standard's engineering control methods pertain to the
sheetrock removal operation. Those general work practice procedures and general prohibitions the
employer must observe under such a condition are those presented at:
• 29 CFR 1926.1101(g)(1)(ii), which requires: wet methods, or wetting agents, to control employee
exposures during asbestos handling, ... removal, cutting, ... and cleanup, except where employers
demonstrate that the use of wet methods is infeasible due to for example, the creation of electrical
hazards ... [and] equipment malfunction...; 29 CFR 1926.1101(g)(1)(iii), which requires: prompt
clean-up and disposal of wastes and debris contaminated with asbestos in leak-tight containers...;
29 CFR 1926.1101(g)(3)(i), which prohibits: high-speed abrasive disc saws that are not equipped
with point of cut ventilator or enclosures with HEPA filtered exhaust air; 29 CFR 1926.1101(g)(3)(ii),
which prohibits: compressed air used to remove asbestos, or materials containing asbestos, unless
the compressed air is used in conjunction with an enclosed ventilation system designed to capture
the dust cloud created by the compressed air; and 29 CFR 1926.1101(g)(3)(iv), which prohibits:
employee rotation as a means of reducing employee exposure to asbestos.
H. Clean-Up
• All work activity within occupied portions of the facility shall be immediately cleaned and restored to
its original finished condition upon completion of the activity. If the activity continues into the next
workday, the area shall be left safe, clean, and presentable.
• Public restrooms are not to be used for the cleaning of tools or equipment, i.e., paintbrushes, rollers,
finishing tools, etc. Janitor’s slop sinks are available for this purpose. If janitor’s closets are used, they
must be cleaned.
• Trash, combustible waste, and excess construction materials must be removed daily to prevent
accumulation. Contractors must arrange for the removal of their debris and waste.
• All work for an area must be confined within that space. Public corridors, stairwells, equipment
rooms, and vacant floors are not to be used for the storage of materials or as a workshop. Tracking of
construction dirt into the public corridors or stairwells must be prevented. The contractor will provide
dampened walk-off mats at all entrances and exits from the construction area.
• If smoke detectors are covered during dust-producing activities, they must be uncovered daily.
I. Compressed Gas Cylinders:
• Compressed gas cylinders are very dangerous if not treated properly.
• Employees who work with compressed gas cylinders must have specific training.
• Make sure that they are secured properly when in use or in storage.
• Always keep the caps on the cylinders when they are not in use.
• See also Hot Work section.
J. Confined Space:
• Confined Space Entries. All Confined Spaces are clearly marked on campus. NO ENTRY is allowed in
the areas without prior approval by the Project Engineer. NO ONE will be allowed to enter these
areas without the proper qualifications, equipment and training as required by the OSHA Standards
(29 CFR 1910.147)
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–11 (SN)
• Identify storm sewers, underground electrical vaults, and all other areas that require confined space
permits. (e.g., a map showing the locations of all the confined spaces located in the Facilities Service
Department).
• All hospital personnel that would require entry into these spaces must abide by the Confined Space
Program Procedure.
• It is the sole responsibility of any outside contractor doing work on a VA Medical Center campus to
coordinate entry into any of these spaces or any other marked permit required confined spaces with
the medical center.
• Anyone entering a permit-required confined space must follow Occupational Safety and Health
Administration (OSHA) Regulations, 29 CFR 1910.120.
• Contractor to submit as a formal submittal the Confined Space Entry program (and CSE Permit if
needed).
K. Contractor Room/Space Guidelines:
• Materials will be kept on the job site, in the contractor’s room or in storage space provided by the
Contractor via trailer located in the VA corporation yard on the North East section of the VA grounds.
• Any shared space within storage room(s) must be accessible to Facilities Service. Do not block access
to electric panels or fire protection equipment.
• Hallways are not to be used for storage.
• Contractors will manage the area and assure the site is kept clean and safe. (OSHA standards apply.)
• Any disputes or concerns will be directed to the Facilities Service Manager.
L. Damage by Contractors:
• Any damage caused by the contractor’s employees is to be reported to the COR or Facilities Service
Project Section immediately.
M. Deliveries:
• All material deliveries at the loading dock must be coordinated with the Receiving Department in
advance.
N. Dress Code:
• All personnel must be appropriately dressed for their work. T-shirts or garments with obscene or
suggestive messages are not permitted. Personnel found improperly dressed will be asked to leave
the facility. No construction staff is allowed to remove shirts or other clothing. No articles may
include offensive statements/graphics.
O. Dust Barriers and Ventilation Requirements:
• Reference section 01 01 10 IC.
• Dust barriers are needed to protect occupied areas on any portion of the job that has potential to
create dust.
P. Elevator Usage:
• Contractors shall not hold or block from use any public elevators in any building unless authorized by
the COR.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–12 (SN)
• Contractors shall use “B“ bank freight elevators only for the delivery and transportation of materials
and demolition materials. Contractors shall not hold or block public elevators from use in any
building. .
Q. Emergencies:
Fire Plan - There is no difference between a fire drill and an actual fire.
General Contractor will ensure that each employee on the worksite knows where the pull stations are
in the areas you are working.
If you are in the area of the fire:
R Rescue anyone from the area if necessary
A Pull the nearest Pull Station
C. Contain the fire by closing all doors in the area
E Extinguish if possible or Evacuate the area immediately
If you are NOT in the area of the fire:
Construction Workers are to cease activities, stay in place, and wait for further instructions or
cancellation of the fire drill.
DO NOT move through the hospital. DO NOT use the elevators or stairwells.
• Medical Emergencies - Any contractor who witnesses a medical emergency is to pick up a nearest
phone and dial “911” or the operator and describe the condition of the emergency.
• Accidents/Injuries - The contractor must post emergency phone numbers and treatment facilities for
any injured employee.
• Worksite injuries must be reported to the VA immediately using the VA accident reporting form
(Number 2162). The COR/Safety/or Security and Police Service will initiate the 2162.
• Patients and visitors may be anxious or irritated because of their situation. If you are faced with any
patient or visitor that gets aggressive with you, simply call Ext. 42222 and say “Code Green” and
describe the situation. Security will respond immediately.
R. Equipment Safety:
• Ladders are not to be left unattended in public areas during breaks and lunch hours. Ladders shall be
laid down and placed out of traffic areas during these periods.
• No tools, carts, ladders or other equipment are to be left unattended outside a secure area.
• Yellow safety barricades must be used when working in public areas.
• Use of hospital equipment is permitted only if the contractor receives permission from Facilities
Service and is properly trained on the USC of the equipment.
S. Equipment and Supplies:
• Caution must be used with all flammable materials, i.e., adhesives, thinners, varnishes, etc.
• All paints shall be low odor latex paint. The contractor will use odor reducing agents in all paints and
solvents. Ventilation will be required if toxic or foul-smelling materials have to be applied.
• Only a one-day supply of paints, oils, and gas cylinders is permitted within the facility, unless it’s
properly stored in a flammable liquid storage cabinet.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–13 (SN)
T. Fire Alarm System:
• Care must be exercised to prevent the accidental tripping of smoke detectors or fire alarms.
• Notify Facilities Service of your activities and location.
• Cover and protect the smoke alarms with paper bags when raising dust or creating smoke in short
duration(less than 3 days) ancillary work areas. All other construction areas to follow section 01 01
10 – 1HR. (You must inform Facilities Service Fire Department when bagging smoke alarms.)
• Remove the paper bag upon completion of your work and at the end of each workday.
• If you accidentally trip an alarm, notify Facilities Service (Fire Department) immediately.
U. Hazardous Materials and Waste:
• A listing of all hazardous materials that will be used on the job and their material safety data sheets
(MSDS) will be provided to the VA before the chemicals are used.
• Any excess or used chemicals will be removed from the hospital promptly and properly disposed of
by the contractor in accordance with federal, state and local regulations.
• Any hazardous waste generated at the facility must be properly contained and labeled and stored in
accordance with local, state, federal and hospital regulations.
• Do not store flammable materials in the facility unless stored in an approved non-combustible
storage cabinet or prior approval by the Project Engineer and Safety Office.
V. Heavy Lifting:
• Hoisting heavy materials/items require prior review by the Project Engineer.
W. Housekeeping:
• Housekeeping in public areas of the hospital will be maintained at the highest level, even while work
is on going.
• In secured areas, housekeeping will be performed as needed, but at a minimum at the end of each
job task, and at the end of the workday.
• Debris and waste will not be allowed to accumulate on the work site and disposal must be arranged
to keep the amounts low.
X. Hot Work Permits:
• Hot work permits are required before cutting, soldering, welding operations begin. Before any
cutting, soldering or welding is conducted, the contractor or sub-contractor shall obtain permission
through a hot work permit. The contractor shall be responsible for obtaining the hot work permits
from the Project Engineer.
• Gas and oxygen canisters shall be properly chained and protected and two 10-pound fire
extinguishers shall be present.
• A fire watch shall be maintained on the worksite during the hot work operations, and for 30 minutes
after the hot work is completed.
• All burn permits will be completed, signed and scanned within 48 hrs and posted to Buzzsaw.
Y. Identification Badges:
• ID Badges are required for all contractor employees working at the V.A.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–14 (SN)
• Before beginning work on any project, all outside contractors shall obtain a VA contractor badge from
the Police / Security Desk and obtain a contractor’s I.D. badge. The Contractor will complete the
badge application and email it to the COR, who will forward to the Police. The contractor will stop at
the Police Desk 1-2 days later to complete the badge process. The outside contractor will supply the
following information: location of work site, authorization, duration, and any pertinent information
that is required.
• All contractors working at the Milwaukee VA will be finger printed and the finger prints processed
prior to obtaining a VA badge. There is an approximate 5 day wait once finger prints are given to
when processed and the contractor can return to obtain the photo ID badge. Badges will be active
for only 90 days at a time.
• General Contractor will be required to request, thru the COR, for reactivation/continued activation of
all contractor badges every 90 days.
Z. Infection Control:
• Reference section 01 01 10 IC.
• Sensitive/High Risk areas of the hospital require extra precautions to assure patient safety. These
areas include but are not limited to the operating rooms, intensive care units, chemotherapy and
transplant units. Contact infection control for other areas that may require special precautions.
• When working in patient care areas, please be sure to read and follow the directions listed on any
Infection Control Precaution sheets posted outside of a patient’s room. Generally this means
permission must be obtained from Nursing staff before entry.
• Temporary walls or dust barriers are required to enclose areas under construction.
• Under some circumstances it may be necessary to block return and supply ducts, and install special
HEPA exhaust ventilation from the worksite. There should be no re-circulation of air from
construction area to rest of hospital.
• Dampened walk-off mats must be located outside of construction area.
• Dust mops/wet mops must be available to remove any dust tracked outside barriers.
• Standard Precautions assumes that any person may carry a contagious disease. In order to protect
you from these diseases always assume blood, non-intact skin, mucous membranes and all other
body fluids and excretions are infectious. Do not touch any such materials but contact a VA employee
immediately. Needle container boxes are provided for the disposal of syringes and other sharps used
in the medical center. These must be properly disposed of and should be moved only by VA
personnel. The VA Medical Center provides written guidelines, education, and personal protective
equipment (PPE) for anyone working at VA Medical Center campus to prevent their exposure to
bloodborne pathogens.
AA. Interim Life Safety:
• The hospital will document whether and to what extent Interim Life Safety Measures will be
implemented for each project.
• VA Safety will ensure what interim life safety measures (ILSM) are required by the General Contractor
to temporarily compensate for the hazards posted by existing Life Safety Code (LSC) deficiencies or
construction activities in areas of the Medical Center.
• Implementation of ILSM will be required in or adjacent to all construction areas and throughout
buildings with existing LSC deficiencies, ILSM applies to both construction workers and affected
hospital employees, and will be implemented upon construction development and continuously
enforced through construction completion.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–15 (SN)
• Almost always, Interim Life Safety Measures will require walkthrough inspections by the job foreman,
the project manager, and safety staff at varying intervals.
• Training of workers and any affected staff will always be a significant part of the
• Interim Life Safety Measures procedures.
BB. Life Safety:
• Any life safety code violations incurred during construction or renovation must be resolved and will
result in close coordination with Project Engineer and Safety Section to implement the hospital’s
Interim Life Safety Measures. These measures are required by JCAHO and NFPA.
CC. Lock Out/Tag Out:
• Lock Out/Tag Out - No contract worker is allowed to change the status/position of ANY switch, valve
or any other energy source without prior approval from the Project Engineer. All Lock out/Tag Out
activities need approval prior to being implemented. Any activity requiring a Lockout/Tagout process
must comply with the hospital policy.
• Per OSHA Regulation 29 CFR 1910.147, all contractors must comply with OSHA’s Safety
Lockout/Tagout procedures.
• Coordinate all shut downs with Hospital Personnel.
• Only VA staff is authorized to shut down utilities unless permission is specifically granted.
• Contractor to submit as a formal submittal the Lock Out / Tag Out Program policies and
procedures.
DD. Safety Data Sheets (SDS):
• Formerly called Material Safety Data Sheets (MSDS)
• SDS must be provided for any hazardous materials that you will be shipping or delivering to the VA
Medical Center.
• SDS are available for all materials used in the medical center. Contact the COR if you need an SDS for
a VA owned material.
• See also Hazardous Materials and Wastes.
EE. Noise:
• All core drilling, chipping, and hole drilling shall be done at a time and day determined by occupants
on that floor and the floors above and below. The COR shall coordinate and approve it.
• The patients, visitors, and staff deserve consideration and the quiet enjoyment of their premises.
Anyone found being loud, rude, or otherwise annoying to the patients, their guests, or staff will be
asked to leave the facility. Use of vulgar language will not be tolerated.
• All work activity within occupied portions of the facility shall be accomplished with minimal
disruption to the patients, physicians, visitors, and staff.
• The playing of radios, tapes, and CD players is not permitted in any occupied area. “Walk-man”
radios/tapes/CD players are not permitted anywhere.
• The playing of radios, tapes, and CD players is permitted in vacant areas but shall not be heard
outside the vacant area.
• In inpatient areas, coordinate construction activities and debris removal with the Nurse Manager or
Charge Nurse to minimize disruption.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–16 (SN)
FF. OSHA Compliance:
• All contractors are subject to Occupational Safety and Health Administration (OSHA) regulations,
these standards and are expected to enforce these standards in the performance of their work, OSHA
regulations can be found in chapter 29 of the Code of Federal Regulations (CFR). Failure on the part of
any contractor employee to comply with these standards and/or conduct their work in a safe fashion
will result in an interruption in the work schedule for which the contractor will be solely responsible,
Any contractor found deviating from regulatory standards and/or policy and SOPS will immediately
be issued a stop work order and will be responsible for contractual conflicts related to the work
stoppage.
GG. Parking:
• Facilities Service Project Section will designate parking. Contractors my not block fire lanes or other
roadways. Violators will be ticketed. During large construction projects, a staging site may be
available for parking to contractors.
• All Contractors who need parking must contact Facilities Service for a parking permit.
• If special parking is required, permission shall be granted and coordinated through Facilities
Management. Contractors should park in the designated Visitor parking areas. Limited loading and
unloading will be permitted at the loading dock area, afterwards contractor employees will be
required to park in designated areas.
II. Patient/Visitor Privacy:
• Patient/Visitor Privacy. No construction staff is allowed to review, acknowledge or move any patient
information or records.
• No construction staff may acknowledge any patient or visitor unless spoken to - even if the individual
is known on a personal basis.
• Radios are NOT allowed on campus.
• Cell phones are to be used only in designated areas.
JJ. Personal Protective Equipment:
• There are many situations that require specific personal protective equipment for worker safety
according to OSHA. It is the responsibility of the individual contractor to know when it is to be used
and is responsible to wear them.
KK. Restroom Usage:
• Contractors are to use public restroom unless otherwise instructed to specific restrooms or portable
facilities.
LL. Requests for Information:
• All contractor requests for assistance and information shall be addressed to the Facilities Service
Project Section or Facilities Service Department.
MM. Safety Regulations:
• Contractors are expected to comply with all Occupational Safety and Health Administration (OSHA)
regulations, 29 CFR 1926 and 19 10.
• Work that is performed within a corridor or occupied space must be confined by dust barriers or non-
combustible partitions.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–17 (SN)
• Appropriate job signs and barricades are to be placed in the area of construction to prevent
occupants from straying into the job site.
• Stairwell doors shall not be propped open or blocked at any time. Equipment cannot be stored in the
stairwells.
• All contractors are encouraged to frequently review these guidelines with their employees and/or
subcontractors on site (e.g., during weekly Tool Box Safety Meetings).
• All contractors and their subcontractors are responsible for complying with these guidelines and all
other conditions, OSHA requirements, and safety regulations.
NN. Scaffolding:
• All scaffolds and other work platforms construction activities shall comply with 29 CFR 1926.
Contractor is to provide copies of daily scaffolding inspections with daily logs.
OO. Smoking:
• The Smoking policy of the hospital is no smoking in any building nor within 50 feet of any the building
entrance and only in areas designated for smoking. All construction employees must comply with
this policy. A copy of the hospital smoking policy will be supplied at the pre-construction conference.
• Violation of the smoking policy will result in the worker being removed from the worksite for the
duration of the project.
• The designated smoking areas are: Smoking Shelter located outside the East entrance
• Job site supervisors will enforce this smoking policy.
PP. Stop Work:
• The hospital safety officer and COR have the Director’s permission and authority to stop work
whenever conditions pose an imminent threat to life and health or threaten damage to equipment or
buildings.
QQ. Subcontractors:
• The general contractor has the responsibility to assure that all the subcontractors and their workers
are properly trained and follow these safety guidelines. Assistance from VA staff will be providing on
a case by case basis on technical issues.
• The VA reserves the right to approve of any subcontractor being used to complete a project.
• A worker on-site must be designated “in charge” at all times during the project.
RR. Traffic Control:
• Contractors shall provide trained personnel and/or equipment, signage, barricades etc., to regulate
traffic whenever construction operations affect traffic patterns.
SS. Trenching:
• OSHA regulations must be followed during trenching operations.
TT. Waste Management:
• Reference section 01 74 19.
• Trash, combustible waste, and excess construction materials must be removed daily to prevent
accumulation. Contractors must arrange for the removal of their debris and waste. The building’s
dumpster shall not be used unless appropriate arrangements are made with Facilities Service.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–18 (SN)
• The contractor is encouraged to contact utilize our recycling program for the disposal of recyclables.
• The contractor is expected to comply with all environmental regulations.
• Contractor to provide a Fiscal Year breakdown of Waste Management/Recycling Costs on the project.
UU. Work Site Requirements:
• Contractor to provide a list of emergency contacts at the entrance to construction site.
• All contractors are to maintain their work area as clean as possible while working and cleanup
thoroughly every day.
• Prior to any utilities or critical systems being interrupted, a two weeks written notification to Facilities
Management Project Engineer is mandatory. Only Facilities Management personnel will shut off a
utility.
• All contractors are expected to use courtesy. Loud, vulgar, abusive language, sexual harassment and
aggressive behavior will not be tolerated.
• All contractors working above the ceiling are required to replace all disturbed ceiling tile by the end of
each day.
• Prior to making any penetrations in walls, floors or ceilings, it is the contractor’s responsibility to
identify rated systems and be verified through review of as builts, line diagrams, etc.
• All repaired penetrations on rated systems must be completed using a fire rated material matching
the rating of the system and must inspected by the Project Engineer before ceiling tiles are replaced
or area is concealed.
• Temporary construction partitions of non-combustible materials shall be installed as required to
provide a smoke tight separation between the areas undergoing renovation and/or construction and
adjoining areas that are occupied by the facility.
• Exits for occupied areas of the building including rooms, suites, corridors and floors shall not be
blocked by the construction or by construction materials. Exit may be blocked temporarily if it is
unavoidable and adequate alternative measures are provided, such as signage, instructions to
occupants and approved in advance by the Project Engineer.
• Existing fire protection systems including fire alarm systems, smoke detection systems, and sprinkler
systems shall not be altered except as required for the alteration and/or renovation project. Any
alteration to the system shall be coordinated with Project Engineer. When sprinkler or fire and smoke
detector systems are out of service for more than eight hours general contractor shall be responsible
to institute a Fire Watch till systems are operational.
• At the end of each workday, combustible packaging and crating materials for building products and
equipment to be installed shall be removed from the occupied building.
• It is the responsibility of each contractor to know exactly where the fire extinguishers and pull
stations are in the areas they are working.
• Fire hazard inspections shall be conducted daily by the contractor once construction starts and until
the work is turned back over to the facility.
• All temporary electrical wiring and equipment used for construction shall be installed and used in
accordance with pertinent provisions of NFPA 70 and National Electrical Code.
• Contractor shall maintain construction site to permit access by the fire department as necessary.
Clear building construction areas of obstructions so that all portions are accessible for fire
department apparatus and permit emergency egress of patients and other personnel.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–19 (SN)
• All necessary precautions shall be taken by the contractor to prevent accidental operation of any
existing smoke detectors by minimizing the amount of dust generated in the vicinity of any smoke
detectors. Any activity that may generate dust or smoke shall be reviewed with the Project Engineer
and the infectious control nurse.
X. Apprentices Working on Project:
Apprentices are authorized to work on all projects disciplines providing the following requirements are
met:
• Completion of OHSA-10 training and certification turned in as required for all other workers
• Apprenticeship documentation turned in to contracting and continued direct supervision by a
journeyman.
• Apprentices are not allowed to work at the Clement J Zablocki VA Medical Center on their own
nor without continuous direct supervision.
1.18. IDENTIFICATION AND LABELING
A. Identify devices located above ceiling.
a. Provide markers on all removable ceiling and ceiling access panels to indicate locations of valves,
dampers, smoke detectors, etc and other mechanical items that may need servicing or
adjustment.
b. Use access panel markers (metal tack style) for acoustical tile ceilings, or engraved plastic style,
3/4in square, for mounting on panel door or equipment nameplates.
c. Color code and annotate markers as follows:
Color Notation
Red D – Fire Damper
V – Valve (sprinkler shutoff)
S – Smoke Detector
H- Heat Detector
Yellow V- Valve (steam, radiation,
reheat and chilled water)
Gold V- Valve (HVAC)
D- Damper (HVAC)
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–20 (SN)
Blue (valves only) O- Oxygen
V- Vacumn
A - Medical Air
N – Nitrogen
NO – Nitrous Oxide
EV – Anesthesia Evacuation
T – Temperature control air
d. Where fire protection devices are located inside ductwork, provide an additional tag on the duct
access door identifying device inside with letter size equal to or greater than 1-1/2 inches high.
1.19. STANDARD REQUIRED FORMS
A. The following forms are required as noted below:
a. Con tra cto r’ s Ch eckl ist – Completed and signed by General Contractor prior to start of construction.
b. Con tra cto r’ s I mp act St at e men t – Completed and signed by every contractor / subcontractor
working on the project prior to start of construction.
c. Daily Log of Construction – Completed daily by General Contractor and scanned in and posted to Buzzsaw
weekly by Wednesday of the following week.
d. Daily Intermediate Life Safety Measures (ILSM) Inspection Form – Completed daily by General Contractor
and scanned in and posted to Buzzsaw weekly by Wednesday of the following week.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–21 (SN)
CONTRACTOR CHECKLIST
This agreement is between and
Project Name (ref. #)
Project Start Date
Ending Date
Work Allowed Between Hours AM/PM and AM/PM
Before performing any work on facility premises, outside contractors must read this checklist and comply with all local,
state, federal and facility safety policies.
1.1 Life Safety Will the contractor compromise any part during the Life Safety System of this facility (ceiling tiles,
penetrations in smoke or fire walls, blocking exits, shutting down fire/smoke detection or fire suppression, etc.) Y N
Describe.
1.2 Is Interim Life Safe necessary? Y N, if yes, attach and follow interim plan.
2.1 Services Will there be any compromises to patient services during the work performed? Y N
2.2 What adjustments need to be implemented to minimize impact to residents, visitors and staff? Y N
3.1 Chemical Will hazardous chemicals (liquids or gases) be used on-site? Y N
If yes, what risks do they create for facility staff? Is there any chance of exposure?
3.2 Are there any facility chemicals being used, stored or handled where the contractor will be working? Y N
If yes, has the contractor been informed by issuing MSDS’s? Y N
4.1 “ Ho t Wor k”: Will the contractor use equipment which will generate open flames, sparks or other ignition sources Y N
4.2 Will flammable chemicals be in the area? Y N
4.3 Will a Fire Watch be necessary to be posted during all Hot Work activities? Y N
5.0 Confined Spaces: Does the work involve entry into a confined space? Y N
If yes, retain a copy of contractor’s Confined Space Entry program (and CSE Permit if needed).
6.1 Lockout/Tagout : Does the work involve maintenance on energized equipment or systems? Y N (If yes, retain a copy of
the contractor’s LOCKOUT/TAGOUT program)
6.2 Is there any impact to residents, visitors, or staff during this procedure? Y N
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–22 (SN)
If so, describe the impact, ways to minimize the impact and who has been notified.
7.0 Unsafe Conditions/ Impact to Residents, Visitors and Staff Are there any unusual or unsafe conditions which need to
be addressed and/or communicated to facility staff, visitors or residents? ? Y N
Describe.
8.1 Description of Work Area The departments/areas you will be working are
List:
8.2 The potential hazards to you/your workers in the areas you are working in
List
8.3 The specific problems that can be caused by the wrong actions in the areas you are working
List
9.0 C o n tr ac to r ’s Em p lo ye e s
Safety Officer Contact
Facility Project Manager
First Aid Plan
Fire Plan
Disaster Plan
Restricted Areas
10.0 Restricted Areas
The following are the areas of the hospital where construction workers are allowed to go in the hospital.
List
(Contractor Representative) (Facility Project Manager)
Date: Date:
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–23 (SN)
Contractor’s Impact
System Possible Interruption Possible Effect to Patients
Electrical - Changing position of switches and
breakers
- Cutting or splicing into wires
- Disconnecting wires or terminals
- Disturbing Junction Boxes/Electrical
Panels
- Core Drilling
- Demolition of walls
- Excavation
Electrical Systems provides LIFE
SUPPORT (Directly and Indirectly)
- Can cause DEATH to critical patients
Water Lines - Turning valves
- Cutting into lines
- Demolition & Excavation
Dialysis, OR, HVAC, ICU, X Ray, etc
Can cause DEATH to critical patients
Infection Control issues
Major Cleanup issues
Medical Gases:
Oxygen
Air
Vacuum
Nitrous Oxide
Nitrogen
- Cutting or disturbing into lines (labeled,
unlabeled)
- Changing valve positions
- Deactivating alarms
- Demolition & Excavation
Oxygen, vacuum, air, etc.
ICU, OR, Med/Surg.
Can cause DEATH to critical patients
HVAC - Shutting down
- Modifying
- Changing controls
- Cutting into the roof
- Producing foul odors near intakes
- Cutting into chilled water lines
- Obstruct fresh air intake
Temperature is critical in OR, ICU, etc.
Infection Control issues
Major Air Quality Issues
Fire Alarm and
Sprinklers
- ANY modifications
- covering or removing smoke heads
- Demolition & Excavation utilities
- Damage or set off sprinkler heads
- Duct work modifications
- Compromising Fire Safety
- False Alarms
- Floods
- Major disruptions and distractions
ALL THE ABOVE CAN RESULT IN DEATH
Code Alarms
Nurse Call
Wander Guards
- Demolition & Excavation
- Unplugging
- Changing position of switches/breakers
Lack of communicating system can
result in patient death or injury
IF THERE IS ANY QUESTION REGARDING ANY OF THE INFORMATION ON THIS DOCUMENT, IMMEDIATELY
CONTACT FACILITY MANAGEMENT OR SAFETY OFFICE TO RESOLVE ISSUES PRIOR TO WORK COMMENCEMENT.
Contract Company:
Receipt
Acknowledged:
Signature:
Date:
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–24 (SN)
DAILY LOG OF CONSTRUCTION M T W Th F Pkg. No.
PROJECT:
BUILDING CONTRACT NO.
V69DC-
DATE
CONTRACTOR CONTRACTOR REPRESENTATIVE ON JOB
WEATHER (Rain, Snow, Cloudy, Windy, etc., OR NA if all indoors) TEMP. SITE CONDITIONS (CLEAN, DEBRIS, DUST, ETC.)
High Low
NO. CONTRACTOR'S MEN BY JOB CATEGORIES NO. SUBCONTRACTOR’S MEN BY JOB CATEGORIES
EQUIPMENT ON JOB
Brief description of size
No.
Units
Working
Yes No
MATERIALS DELIVERED
OFFICIAL VISITORS TO JOB SITE
ITEM
NO.
STATUS OF WORK
Brief description of work in progress, questionable performance, unforeseen developments on job etc. Include tests made and samples taken.
STATUS OF INFECTIOUS CONTROL MEASURES (NEGATIVE AIR FLOW, CLEAN WALK OFF MAT, ANTE-ROOM SECURE,…)
NEGATIVE AIR FLOW PRESSURE READING:
SAFETY COMMENTS
DIFFICULTIES WITH CONTRACTOR OR REPRESENTATIVE
UNFORESEEN DEVELOPMENTS ON JOB CONTINUED (Describe conditions, action taken; person contacted, recommended actions)
SIGNATURE TITLE
PROJECT SUPERINTENDENT
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–25 (SN)
Daily Intermediate Life Safety Measures (ILSM) Inspection Form
FORM QCA-01A
INSTRUCTIONS: This form is to be utilized when significant hazards posed by existing NFPA 101 deficiencies or
construction activities are in progress. ILSM must be implemented upon project start and continuously enforced
through project completion to provide a level of life safety comparable to that described in Chapter 1-7, 31 and
applicable occupancy chapters of the Life Safety Code. WHERE APPLICABLE NOTE EXCEPTIONS ONLY OF AREA
IDENTIFIED AS BEING DEFICIENT DURING INSPECTION AND EXPLAIN IN SUFFICIENT DETAIL IN THE COMMENTS
SECTION OF THIS FORM. TURN COMPLETED FORMS INTO THE LHS SAFETY OFFICER.
PROJECT: DATE MON TUE WED THR FRI SAT SUN
1. Are exits readily accessible and provide unobstructed
egress?
2. If required, due to inaccessibility of existing, have
alternate exits been established?
3. If alternate exists have been established, are
personnel in the area informed and aware of their
relocation and existence?
4. Are the existing and relocation exits clearly identified
and able to be seen in the event of an emergency or
fire?
5. Are fire evacuation routes posted and do they reflect
up-to-date changes and alternate escape routes due
to construction deficiencies?
6. Are written procedures and guidelines posted in the
immediate and adjacent areas for what to do and who
to call in the event of fire or emergency?
7. Are personnel in the immediate and adjacent areas
aware and informed as to the procedures and
guidelines to follow in the event of fire or emergency?
8. Do fire alarms, detection, and suppression equipment
and systems appear to be operational?
9. If the fire alarm or suppression systems are impaired
or temporarily made nonfunctional has a fire watch, as
required or necessary, of the area been established?
10. If the existing fire alarm or suppression
systems/equipment are impaired, have measures
been taken to provide equivalent equipment/systems
for adequate protection? Note date of installation for
equivalent measures to the right.
11. If the fire alarm or suppression systems are impaired,
are the temporary equipment/systems being
inspected and tested at least monthly?
12. If temporary fire alarm or suppression systems are
installed, are personnel in the area aware and
informed on how to operate or utilize in the event of
fire or emergency?
13. Has the LHS “No Smoking” policy been posted,
implemented and enforced in the construction area?
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–26 (SN)
14. Are construction/remodel area storage, waste and
debris being maintained to minimize potential for fire
or safety hazards during daily operations?
Daily Intermediate Life Safety Measures (ILSM) Inspection Form (Continued)
PROJECT: DATE MON TUE WED THR FRI SAT SUN
15. Are temporary partitions built to be smoke tight and
of noncombustible/fire retardant materials to
minimize spread of smoke or fire within the building?
16 Do electrical panels, temporary wiring, extension
cords, tools and equipment appear to be installed,
utilized, and functioning in a safe manner?
17. In general, are the exterior construction site, buildings,
and ground free of hazard and potential safety
violations?
18. If there is any gas/arc welding or cutting being
performed within the building or on site, have
additional fire safety precautions been taken and the
necessary equipment provided and utilized?
19. If there is any gas/arc welding or cutting being
performed within the building or on site, has the Plant
Operations department been notified?
20. If there are hand and safety rails required, are they in
place and maintained in good condition?
21. Are extension cords that are being used a 3 wire
grounded type?
22. If there are temporary electrical outlets provided, do
they have ground fault protection at the receptacle or
at the panel?
23. I f hazardous chemicals are present and/or being used,
are they being limited to the amount needed and used
daily?
24. Are MSDS sheets readily available for any hazardous
chemicals that are present or being used?
25. Do ladders and scaffolds appear to be in satisfactory
condition and being utilized in a safe manner?
26. Is personnel protective equipment, such as safety
glasses, hard hats and etc. needed or required and
being used?
27. If infection control is required, are the appropriate
policies and procedures known and being followed?
28. If electrical equipment needs to be de-energized, are
applicable “Lockout/Tagout” procedures being
followed?
PLACE INITIALS OF PERSON PERFORMING DAILY INSPECTION
TO THE RIGHT.
INSPECTION COMMENTS/FINDINGS:
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 01 10–27 (SN)
DATE PROJECT STARTED DATE PROJECT COMPLETED_
PROJECT CE #: GENERAL CONTRACTOR
AREAS(S) OF PROJECT/JOB INSPECTED
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 12 16-1
PART 1 - GENERAL
1.1 DESCRIPTION:
SECTION 01 12 16 WORK SCHEDULE
Work Sequence requirements for 695-15-122L 111 TJC and Safety Corrections FY2015 .
1.2 GENERAL REQUIREMENTS
A. Contractor is responsible to prepare and maintain a construction schedule describing the sequencing, means-and-metho ds of construction, installation and removal of temporary facilities an d protections and their impact and coordination with the Owner’s cont inued occupation and operations.
1. Master Production Schedule shall be in the form of a bar graph (Gantt chart) using Critical Path Method (CPM), see Section 01 32 16.15 Project Schedules .
2. Schedule shall be submitted to the Resident Enginee r / COR for review not later than 10 days after issuance of NTP.
3. For each Construction Progress Meeting, submit a 3- Week Short- Interval Production Schedule (SIPS) or Construction Activity Plan (CAP) to show current work in process. Schedule is to reflect trades on sight, days for each trade on site during the pe riod, and list any and all issues/concerns/delays. Milestone dates sha ll be in agreement with the Master Production Schedule.
B. Sequencing, means-and-methods of construction, safe ty, and all temporary items remain the responsibility of the Contractor.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
- - - END - - -
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 32 16.15 - 1
SECTION 01 32 16.15 PROJECT SCHEDULES
(SMALL PROJECTS – DESIGN/BID/BUILD)
PART 1- GENERAL
1.1 DESCRIPTION:
A. The Contractor shall develop a Critical Path Method (CPM) plan and schedule demonstrating fulfillment of the contract requirements (Project Schedule), and shall keep the Project Sche dule up-to-date in accordance with the requirements of this section an d shall utilize the plan for scheduling, coordinating and monitoring wo rk under this contract (including all activities of subcontractor s, equipment vendors and suppliers). Conventional Critical Path Method ( CPM) technique shall be utilized to satisfy both time and cost applicati ons. The contractor’s CPM shall be submitted within 30 days of the Notice to Proceed. The Contractor’s representative shall enga ge the services of an outside consultant to complete the CPM.
1.2 CONTRACTOR'S REPRESENTATIVE:
A. The Contractor shall designate an authorized repres entative responsible for the Project Schedule including preparation, rev iew and progress reporting with and to the Contracting Officer's Rep resentative (COR).
B. The Contractor's representative shall have direct p roject control and complete authority to act on behalf of the Contract or in fulfilling the requirements of this specification section.
C. The Contractor’s representative shall have the opti on of developing the project schedule within their organization or to en gage the services of an outside consultant. If an outside scheduling con sultant is utilized, Section 1.3 of this specification will ap ply.
1.3 CONTRACTOR'S CONSULTANT:
A. The Contractor shall submit a qualification proposa l to the COR, within 10 days of bid acceptance. The qualification propos al shall include:
1. The name and address of the proposed consultant.
2. Information to show that the proposed consultant ha s the qualifications to meet the requirements specified i n the preceding paragraph.
3. A representative sample of prior construction proje cts, which the proposed consultant has performed complete project scheduling services. These representative samples shall be of similar size and scope.
B. The Contracting Officer has the right to approve or disapprove the proposed consultant, and will notify the Contractor of the VA decision
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 32 16.15 - 2
within seven calendar days from receipt of the qual ification proposal. In case of disapproval, the Contractor shall resubm it another consultant within 10 calendar days for renewed cons ideration. The Contractor shall have their scheduling consultant a pproved prior to submitting any schedule for approval.
1.4 COMPUTER PRODUCED SCHEDULES
A. The contractor shall provide monthly, to the Depart ment of Veterans Affairs (VA), all computer-produced time/cost sched ules and reports generated from monthly project updates. This monthl y computer service will include: three copies of up to five different reports (inclusive of all pages) available within the user defined rep orts of the scheduling software approved by the Contracting Off icer; a hard copy listing of all project schedule changes, and associ ated data, made at the update and an electronic file of this data; and the resulting monthly updated schedule in PDM format. These must be submitted with and substantively support the contractor’s monthly payment request and the signed look ahead report. The COR shall identif y the five different report formats that the contractor shall provide.
B. The contractor shall be responsible for the correct ness and timeliness of the computer-produced reports. The Contractor sh all also responsible for the accurate and timely submittal of the update d project schedule and all CPM data necessary to produce the computer reports and payment request that is specified.
C. The VA will report errors in computer-produced repo rts to the Contractor’s representative within ten calendar day s from receipt of reports. The Contractor shall reprocess the compute r-produced reports and associated diskette(s), when requested by the C ontracting Officer’s representative, to correct errors which affect the payment and schedule for the project.
1.5 THE COMPLETE PROJECT SCHEDULE SUBMITTAL
A. Within 45 calendar days after receipt of Notice to Proceed, the Contractor shall submit for the Contracting Officer 's review; digital PDF file, three blue line copies of the interim sch edule on sheets of paper 765 x 1070 mm (30 x 42 inches) and an electro nic file in the previously approved CPM schedule program. The submi ttal shall also include three copies of a computer-produced activit y/event ID schedule showing project duration; phase completion dates; a nd other data, including event cost. Each activity/event on the co mputer-produced schedule shall contain as a minimum, but not limite d to, activity/event ID, activity/event description, duration, budget am ount, early start date, early finish date, late start date, late fini sh date and total float. Work activity/event relationships shall be r estricted to finish- to-start or start-to-start without lead or lag cons traints. Activity/event date constraints, not required by th e contract, will not be accepted unless submitted to and approved by the Contracting Officer. The contractor shall make a separate writt en detailed request
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 32 16.15 - 3
to the Contracting Officer identifying these date c onstraints and secure the Contracting Officer’s written approval b efore incorporating them into the network diagram. The Contracting Offi cer’s separate approval of the Project Schedule shall not excuse t he contractor of this requirement. Logic events (non-work) will be p ermitted where necessary to reflect proper logic among work events , but must have zero duration. The complete working schedule shall refle ct the Contractor's approach to scheduling the complete project. The final Project Schedule in its original form shall contain no contract chan ges or delays which may have been incurred during the final network dia gram development period and shall reflect the entire contract durati on as defined in the bid documents. These changes/delays shall be entered at the first
update after the final Project Schedule has been ap proved. The Contractor should provide their requests for time a nd supporting time extension analysis for contract time as a result of contract changes/delays, after this update, and in accordanc e with Article, ADJUSTMENT OF CONTRACT COMPLETION.
D. Within 30 calendar days after receipt of the comple te project interim Project Schedule and the complete final Project Sch edule, the Contracting Officer or his representative, will do one or both of the following:
1. Notify the Contractor concerning his actions, opini ons, and objections.
2. A meeting with the Contractor at or near the job si te for joint review, correction or adjustment of the proposed pl an will be scheduled if required. Within 14 calendar days afte r the joint review, the Contractor shall revise and shall submi t three blue line copies of the revised Project Schedule, three copie s of the revised computer-produced activity/event ID schedule and a revised electronic file as specified by the Contracting Off icer. The revised submission will be reviewed by the Contracting Offi cer and, if found to be as previously agreed upon, will be approved.
E. The approved baseline schedule and the computer-pro duced schedule(s) generated there from shall constitute the approved baseline schedule until subsequently revised in accordance with the r equirements of this section.
1.6 WORK ACTIVITY/EVENT COST DATA
A. The Contractor shall cost load all work activities/ events except procurement activities. The cumulative amount of al l cost loaded work activities/events (including alternates) shall equa l the total contract price. Prorate overhead, profit and general conditi ons on all work activities/events for the entire project length. Th e contractor shall generate from this information cash flow curves ind icating graphically the total percentage of work activity/event dollar value scheduled to be in place on early finish, late finish. These cas h flow curves will be used by the Contracting Officer to assist him in determining
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 32 16.15 - 4
approval or disapproval of the cost loading. Negative work activity/event cost data will not be acceptable, except on VA issued contract changes.
B. The Contractor shall cost load work activities/events for guarantee period services, test, balance and adjust various systems in accordance with the provisions in Article, FAR 52.232 – 5 (PAYMENT UNDER FIXED-PRICE CONSTRUCTION CONTRACTS) and VAAR 852.236 – 83 (PAYMENT UNDER FIXED-PRICE CONSTRUCTION CONTRACTS).
C. (BLANK)
D. The Contractor shall cost load work activities/events for all BID ITEMS including ASBESTOS ABATEMENT. The sum of each BID ITEM work shall equal the value of the bid item in the Contractors' bid.
1.7 PROJECT SCHEDULE REQUIREMENTS
A. Show on the project schedule the sequence of work activities/events required for complete performance of all items of work. The Contractor Shall:
1. Show activities/events as:
a. Contractor's time required for submittal of shop drawings,templates, fabrication, delivery and similar pre-constructionwork.
b. Contracting Officer's and Architect-Engineer's review andapproval of shop drawings, equipment schedules, samples,template, or similar items.
c. Interruption of VA Facilities utilities, delivery of Governmentfurnished equipment, and rough-in drawings, project phasing andany other specification requirements.
d. Test, balance and adjust various systems and pieces of equipment,maintenance and operation manuals, instructions and preventivemaintenance tasks.
e. VA inspection and acceptance activity/event with a minimumduration of five work days at the end of each phase andimmediately preceding any VA move activity/event required by thecontract phasing for that phase.
2. Show not only the activities/events for actual construction work foreach trade category of the project, but also trade relationships toindicate the movement of trades from one area, floor, or building,to another area, floor, or building, for at least five trades whoare performing major work under this contract.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 32 16.15 - 5
3. Break up the work into activities/events of a durat ion no longer than 20 work days each or one reporting period, exc ept as to non-construction activities/events (i.e., procureme nt of materials, delivery of equipment, concrete and asphalt curing) and any other activities/events for which the COR may approve the showing of a longer duration. The duration for VA approval of an y required submittal, shop drawing, or other submittals will n ot be less than 20 work days.
4. Describe work activities/events clearly, so the wor k is readily identifiable for assessment of completion. Activiti es/events labeled "start," "continue," or "completion," are not speci fic and will not be allowed. Lead and lag time activities will not b e acceptable.
5. The schedule shall be generally numbered in such a way to reflect either discipline, phase or location of the work.
B. The Contractor shall submit the following supportin g data in addition to the project schedule:
1. The appropriate project calendar including working days and holidays.
2. The planned number of shifts per day.
3. The number of hours per shift.
Failure of the Contractor to include this data shal l delay the review of the submittal until the Contracting Officer is i n receipt of the missing data.
C. To the extent that the Project Schedule or any revi sed Project Schedule shows anything not jointly agreed upon, it shall no t be deemed to have been approved by the COR. Failure to include any el ement of work required for the performance of this contract shall not excuse the Contractor from completing all work required within any applicable completion date of each phase regardless of the COR ’s approval of the Project Schedule.
D. Compact Disk Requirements and CPM Activity/Event Re cord Specifications: Submit to the VA an electronic file(s) containing o ne file of the data required to produce a schedule, reflecting all the activities/events of the complete project schedule being submitted.
E. Required Inspections: The follow are a list of required inspections to
be included in the project schedule. These inspecti ons are to be included if the relevant trades are present in the project scope. See attached schedule at end of section.
# Inspections
1 Pre-site inspection of existing conditions
2 ACM containment
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 32 16.15 - 6
3 Demo completion
4 After ACM clearance (prior to tear down)
5 Chalk line
7 MEP outlet box 8 MEP & Backing in-trench 9 MEP insulation
16 Hardware 18 Commissioning/Equipment Testing 19 Pre-Final Inspection (Punchlist) 20 Final Inspection (Punchlist
Verification)
1.8 PAYMENT TO THE CONTRACTOR:
A. Monthly, the contractor shall submit the application and certificate for payment documents reflecting updated schedule activities and cost data in accordance with the provisions of the following Article, PAYMENT AND PROGRESS REPORTING, as the basis upon which progress payments will be made pursuant to Article, FAR 52.232 – 5 (PAYMENT UNDER FIXED PRICE CONSTRUCTION CONTRACTS). The Contractor shall be entitled to a monthly progress payment upon approval of estimates as determined from the currently approved updated project schedule. Monthly payment requests shall include: a listing of all agreed upon project schedule changes and associated data; and an electronic file (s) of the resulting monthly updated schedule.
B. Approval of the Contractor’s monthly Application for Payment shall be contingent, among other factors, on the submittal of a satisfactory monthly update of the project schedule.
1.9 PAYMENT AND PROGRESS REPORTING
A. Monthly schedule update meetings will be held on dates mutually agreed to by the COR and the Contractor. Contractor and their CPM consultant (if applicable) shall attend all monthly schedule update meetings. The Contractor shall accurately update the Project Schedule and all other data required and provide this information to the COR three work days in advance of the schedule update meeting. Job progress will be reviewed to verify:
1. Actual start and/or finish dates for updated/completedactivities/events.
2. Remaining duration for each activity/event started, or scheduled tostart, but not completed.
3. Logic, time and cost data for change orders, and supplementalagreements that are to be incorporated into the Project Schedule.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 32 16.15 - 7
4. Changes in activity/event sequence and/or duration which have been made, pursuant to the provisions of following Artic le, ADJUSTMENT OF CONTRACT COMPLETION.
5. Completion percentage for all completed and partial ly completed activities/events.
6. Logic and duration revisions required by this secti on of the specifications.
7. Activity/event duration and percent complete shall be updated independently.
B. After completion of the joint review, the contracto r shall generate an updated computer-produced calendar-dated schedule a nd supply the Contracting Officer’s representative with reports i n accordance with the Article, COMPUTER PRODUCED SCHEDULES, specified .
C. After completing the monthly schedule update, the c ontractor’s representative or scheduling consultant shall rerun all current period contract change(s) against the prior approved month ly project schedule. The analysis shall only include original workday du rations and schedule logic agreed upon by the contractor and Contracting Officer’s Representative for the contract change(s). When the re is a disagreement on logic and/or durations, the Contractor shall use the schedule logic and/or durations provided and approved by the Contr acting Officer’s Representative. After each rerun update, the result ing electronic project schedule data file shall be appropriately i dentified and submitted to the VA in accordance to the requiremen ts listed in articles 1.4 and 1.7. This electronic submission is separate from the regular monthly project schedule update requirement s and shall be submitted to the Contracting Officer’s Representati ve within fourteen
(14) calendar days of completing the regular schedu le update. Before inserting the contract changes durations, care must be taken to ensure that only the original durations will be used for t he analysis, not the reported durations after progress. In addition, onc e the final network diagram is approved, the contractor must recreate a ll manual progress payment updates on this approved network diagram an d associated reruns for contract changes in each of these update period s as outlined above for regular update periods. This will require detai led record keeping for each of the manual progress payment updates.
D. Following approval of the CPM schedule, the VA, the General Contractor, its approved CPM Consultant, RE office representati ves, and all subcontractors needed, as determined by the SRE, sh all meet to discuss the monthly updated schedule. The main emphasis sha ll be to address work activities to avoid slippage of project schedu le and to identify any necessary actions required to maintain project schedule during the reporting period. The Government representatives an d the Contractor should conclude the meeting with a clear understand ing of those work and administrative actions necessary to maintain pr oject schedule status during the reporting period. This schedule c oordination meeting
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 32 16.15 - 8
will occur after each monthly project schedule upda te meeting utilizing the resulting schedule reports from that schedule u pdate. If the project is behind schedule, discussions should incl ude ways to prevent further slippage as well as ways to improve the pro ject schedule status, when appropriate.
1.10 RESPONSIBILITY FOR COMPLETION
A. If it becomes apparent from the current revised mon thly progress schedule that phasing or contract completion dates will not be met, the Contractor shall execute some or all of the followi ng remedial actions:
1. Increase construction manpower in such quantities a nd crafts as necessary to eliminate the backlog of work.
2. Increase the number of working hours per shift, shi fts per working day, working days per week, the amount of construct ion equipment, or any combination of the foregoing to eliminate the b acklog of work.
3. Reschedule the work in conformance with the specifi cation requirements.
B. Prior to proceeding with any of the above actions, the Contractor shall notify and obtain approval from the COR for the pro posed schedule changes. If such actions are approved, the represen tative schedule revisions shall be incorporated by the Contractor i nto the Project Schedule before the next update, at no additional c ost to the Government.
1.11 CHANGES TO THE SCHEDULE
A. Within 30 calendar days after VA acceptance and app roval of any updated project schedule, the Contractor shall submit a rev ised electronic file (s) and a list of any activity/event changes includ ing predecessors and successors for any of the following reasons:
1. Delay in completion of any activity/event or group of activities/events, which may be involved with contr act changes, strikes, unusual weather, and other delays will not relieve the Contractor from the requirements specified unless t he conditions are shown on the CPM as the direct cause for delaying t he project beyond the acceptable limits.
2. Delays in submittals, or deliveries, or work stoppa ge are encountered which make rescheduling of the work nec essary.
3. The schedule does not represent the actual prosecut ion and progress of the project.
4. When there is, or has been, a substantial revision to the activity/event costs regardless of the cause for th ese revisions.
B. CPM revisions made under this paragraph which affec t the previously approved computer-produced schedules for Government furnished equipment, vacating of areas by the VA Facility, co ntract phase(s) and sub phase(s), utilities furnished by the Government to the Contractor,
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 32 16.15 - 9
or any other previously contracted item, shall be f urnished in writing to the Contracting Officer for approval.
C. Contracting Officer's approval for the revised proj ect schedule and all relevant data is contingent upon compliance with al l other paragraphs of this section and any other previous agreements b y the Contracting Officer or the VA representative.
D. The cost of revisions to the project schedule resul ting from contract changes will be included in the proposal for change s in work as specified in FAR 52.243 – 4 (Changes) and VAAR 852. 236 – 88 (Changes – Supplemental), and will be based on the complexity of the revision or contract change, man hours expended in analyzing th e change, and the total cost of the change.
E. The cost of revisions to the Project Schedule not r esulting from contract changes is the responsibility of the Contr actor.
1.12 ADJUSTMENT OF CONTRACT COMPLETION
A. The contract completion time will be adjusted only for causes specified in this contract. Request for an extension of the c ontract completion date by the Contractor shall be supported with a ju stification, CPM data and supporting evidence as the COR may deem ne cessary for determination as to whether or not the Contractor i s entitled to an extension of time under the provisions of the contr act. Submission of proof based on revised activity/event logic, durati ons (in work days) and costs is obligatory to any approvals. The sched ule must clearly display that the Contractor has used, in full, all the float time available for the work involved in this request. Th e Contracting Officer's determination as to the total number of d ays of contract extension will be based upon the current computer-p roduced
calendar-dated schedule for the time period in ques tion and all other relevant information.
B. Actual delays in activities/events which, according to the computer- produced calendar-dated schedule, do not affect the extended and predicted contract completion dates shown by th e critical path in the network, will not be the basis for a change to the contract completion date. The Contracting Officer will withi n a reasonable time after receipt of such justification and supporting evidence, review the facts and advise the Contractor in writing of the C ontracting Officer's decision.
C. The Contractor shall submit each request for a chan ge in the contract completion date to the Contracting Officer in accor dance with the provisions specified under FAR 52.243 – 4 (Changes) and VAAR 852.236 – 88 (Changes – Supplemental). The Contractor shall i nclude, as a part of each change order proposal, a sketch showing all CP M logic revisions, duration (in work days) changes, and cost changes, for work in question and its relationship to other activities on the app roved network diagram.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 32 16.15 - 10
D. All delays due to non-work activities/events such a s RFI’s, WEATHER, STRIKES, and similar non-work activities/events sha ll be analyzed on a month by month basis.
- - - E N D - - -
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 33 23 - 1
SECTION 01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
1-1. Refer to Articles titled SPECIFICATIONS AND DR AWINGS FOR
CONSTRUCTION (FAR 52.236-21) and, SPECIAL NOTES (VA AR 852.236-
91), in GENERAL CONDITIONS.
1-2. For the purposes of this contract, samples, te st reports,
certificates, and manufacturers' literature and dat a shall also
be subject to the previously referenced requirement s. The
following text refers to all items collectively as SUBMITTALS.
1-3. Submit for approval one electronic Submittal R egister, in
Microsoft Excel format. VA can furnish Excel file e xample to
successful bidder. Submit an RFI to request file.
1-4. Submit for approval, all of the items specific ally mentioned
under the separate sections of the specification, w ith
information sufficient to evidence full compliance with contract
requirements. Materials, fabricated articles and th e like to be
installed in permanent work shall equal those of ap proved
submittals. After an item has been approved, no cha nge in brand
or make will be permitted unless:
A. Satisfactory written evidence is presented to, and approved by
Contracting Officer, that manufacturer cannot make scheduled
delivery of approved item or;
B. Item delivered has been rejected and substitution o f a suitable
item is an urgent necessity or;
C. Other conditions become apparent which indicates ap proval of such
substitute item to be in best interest of the Gover nment.
1-5. Forward submittals in sufficient time to permi t proper
consideration and approval action by Government. Ti me submission
to assure adequate lead time for procurement of
contract - required items. Delays attributable to u ntimely and
rejected will not serve as a basis for extending co ntract time
for completion.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 33 23 - 2
1-6. Submittals will be reviewed for compliance wit h contract
requirements by Architect-Engineer, and action ther eon will be
taken by Contracting Officer’s Representative (COR) on behalf of
the Contracting Officer.
1-7. Upon receipt of submittals, Architect-Engineer will assign a file
number thereto. Contractor, in any subsequent corre spondence,
shall refer to this file and identification number to expedite
replies relative to previously approved or disappro ved
submittals.
1-8. The Government reserves the right to require a dditional
submittals, whether or not particularly mentioned i n this
contract. If additional submittals beyond those req uired by the
contract are furnished pursuant to request therefor by
Contracting Officer, adjustment in contract price a nd time will
be made in accordance with Articles titled CHANGES (FAR 52.243-4)
and CHANGES - SUPPLEMENT (VAAR 852.236-88) of the G ENERAL
CONDITIONS.
1-9. Schedules called for in specifications and sho wn on shop drawings
shall be submitted for use and information of Depar tment of
Veterans Affairs and Architect-Engineer. However, t he Contractor
shall assume responsibility for coordinating and ve rifying
schedules. The Contracting Officer, COR, and Archit ect- Engineer
assumes no responsibility for checking schedules or layout
drawings for exact sizes, exact numbers and detaile d positioning
of items.
1-10. Submittals must be submitted by Contractor on ly and shipped
prepaid. Contracting Officer assumes no responsibil ity for
checking quantities or exact numbers included in su ch submittals.
A. Submittals will receive consideration only when cov ered by a
transmittal letter signed by Contractor. Letter sha ll be sent via
first class mail and shall contain the list of item s, name of
Medical Center, name of Contractor, contract number , applicable
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 33 23 - 3
specification paragraph numbers, applicable drawing numbers (and
other information required for exact identification of location
for each item), manufacturer and brand, ASTM or Fed eral
Specification Number (if any) and such additional i nformation as
may be required by specifications for particular it em being
furnished. In addition, catalogs shall be marked to indicate
specific items submitted for approval.
1. A copy of letter must be enclosed with items, and a ny items
received without identification letter will be cons idered
"unclaimed goods" and held for a limited time only.
2. Each certificate, manufacturers' literature, and da ta shall be
labeled to indicate the name and location of the Me dical
Center , name of Contractor, manufacturer, brand, c ontract
number and ASTM or Federal Specification Number as applicable
and location(s) on project.
3. Required certificates shall be signed by an authori zed
representative of manufacturer or supplier of mater ial, and by
Contractor.
D. If submittal samples have been disapproved, resubmi t new
samples as soon as possible after notification of d isapproval.
Such new samples shall be marked "Resubmitted Sampl e" in
addition to containing other previously specified i nformation
required on label and in transmittal letter.
E. Approved samples will be kept on file by the Reside nt Engineer at
the site until completion of contract, at which tim e such samples
will be delivered to Contractor as Contractor's pro perty. Where
noted in technical sections of specifications, appr oved samples
in good condition may be used in their proper locat ions in
contract work. At completion of contract, samples t hat are not
approved will be returned to Contractor only upon r equest and at
Contractor's expense. Such request should be made p rior to
completion of the contract. Disapproved samples tha t are not
requested for return by Contractor will be discarde d after
completion of contract.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 33 23 - 4
F. Submittal drawings (shop, erection or setting drawi ngs) and
schedules, required for work of various trades, sha ll be checked
before submission by technically qualified employee s of
Contractor for accuracy, completeness and complianc e with
contract requirements. These drawings and schedules shall be
stamped and signed by Contractor certifying to such check.
1. For each drawing required, submit one legible photo graphic
paper or vellum reproducible.
2. Reproducible shall be full size.
3. Each drawing shall have marked thereon, proper desc riptive
title, including Medical Center location, project n umber,
manufacturer's number, reference to contract drawin g number,
detail Section Number, and Specification Section Nu mber.
4. A space 120 mm by 125 mm (4-3/4 by 5 inches) shall be reserved
on each drawing to accommodate approval or disappro val stamp.
5. Submit drawings, ROLLED WITHIN A MAILING TUBE, full y protected
for shipment.
6. One reproducible print of approved or disapproved s hop
drawings will be forwarded to Contractor.
7. When work is directly related and involves more tha n one
trade, shop drawings shall be submitted to Architec t-Engineer
under one cover.
1-11. Samples, shop drawings, test reports, certifi cates and
manufacturers' literature and data, shall be submit ted for
approval to:
Guidon Design, Inc.
905 N. Capitol Ave. Suite 100
Indianapolis, IN 46204
1-12. At the time of transmittal to the Architect-E ngineer, the
Contractor shall also send a copy of the complete s ubmittal
directly to the COR.
- - - E N D - - -
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 35 26-1
SECTION 01 35 26 Safety REQUIREMENTS
TABLE OF CONTENTS
1.1 APPLICABLE PUBLICATIONS ........................... .................... 2
1.2 DEFINITIONS ....................................... .................... 3
1.3 REGULATORY REQUIREMENTS ........................... .................... 3
1.4 ACCIDENT PREVENTION PLAN (APP) .................... .................... 4
1.5 ACTIVITY HAZARD ANALYSES (AHAs) ................... .................... 7
1.6 PRECONSTRUCTION CONFERENCE ........................ .................... 8
1.7 “SITE SAFETY AND HEALTH OFFICER” (SSHO) and “COMPET ENT PERSON” (CP) .... 9
1.8 TRAINING .......................................... .................... 9
1.9 INSPECTIONS .................................................. ....... 10
1.10 ACCIDENTS, OSHA 300 LOGS, AND MAN-HOURS ........................... 10
1.11 PERSONAL PROTECTIVE EQUIPMENT (PPE) ................................ 11
1.12 INFECTION CONTROL ................................................. 11
1.13 TUBERCULOSIS SCREENING ................... Error! Bookmark not defined.
1.14 FIRE SAFETY .................................................. ..... 12
1.15 ELECTRICAL .................................................. ...... 13
1.16 FALL PROTECTION .................................................. . 14
1.17 SCAFFOLDS AND OTHER WORK PLATFORMS ................................ 15
1.18 EXCAVATION AND TRENCHES ........................................... 15
1.19 CRANES .................................................. .......... 16
1.20 CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAGOUT) ....................... 16
1.21 CONFINED SPACE ENTRY .............................................. 17
1.22 WELDING AND CUTTING ............................................... 17
1.23 LADDERS .................................................. ......... 17
1.24 FLOOR & WALL OPENINGS ............................................. 17
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 35 26-2
SECTION 01 35 26 SAFETY REQUIREMENTS
4/2015
1.1 APPLICABLE PUBLICATIONS:
A. Latest publications listed below form part of this Article to extent referenced. Publications are referenced in text by basic designations only.
B. American Society of Safety Engineers (ASSE):
A10.1-2011...........Pre-Project & Pre-Task Safety and Health Planning
A10.34-2012..........Protection of the Public on or Adjacent to Construction Sites
A10.38-2013..........Basic Elements of an Employer’ s Program to Provide a Safe and Healthful Work Environment American National Standard Construction and Demolition Operations
C. American Society for Testing and Materials (ASTM):
E84-2013.............Surface Burning Characteristic s of Building Materials
D. The Facilities Guidelines Institute (FGI):
FGI Guidelines-2010Guidelines for Design and Constr uction of Healthcare Facilities
E. National Fire Protection Association (NFPA):
10-2013..............Standard for Portable Fire Ext inguishers
30-2012..............Flammable and Combustible Liqu ids Code
51B-2014.............Standard for Fire Prevention D uring Welding, Cutting and Other Hot Work 70-
2014..............National Electrical Code
70B-2013.............Recommended Practice for Elect rical Equipment Maintenance
70E-2012 ............Standard for Electrical Safety in the Workplace
99-2012..............Health Care Facilities Code
241-2013.............Standard for Safeguarding Cons truction, Alteration, and Demolition Operations
F. The Joint Commission (TJC)
TJC Manual ..........Comprehensive Accreditation an d Certification Manual
G. U.S. Nuclear Regulatory Commission
10 CFR 20 ...........Standards for Protection Again st Radiation
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 35 26-3
H. U.S. Occupational Safety and Health Administration (OSHA):
29 CFR 1904 .........Reporting and Recording Injuries & Illness es
29 CFR 1910 .........Safety and Health Regulations for General Industry
29 CFR 1926 .........Safety and Health Regulations for Construc tion Industry
CPL 2-0.124 ..........Multi-Employer Citation Policy
I. VHA Directive 2005-007
1.2 DEFINITIONS:
A. OSHA “Competent Person” (CP). One who is capable of identifying existing and predictable hazards in the surroundings and wor king conditions which are unsanitary, hazardous or dangerous to employees , and who has the authorization to take prompt corrective measures to eliminate them (see 29 CFR 1926.32(f) ).
B. "Qualified Person" means one who, by possession of a recognized degree, certificate, or professional standing, or who by ex tensive knowledge, training and experience, has successfully demonstra ted his ability to solve or resolve problems relating to the subject m atter, the work, or the project.
C. High Visibility Accident is any mishap which may ge nerate publicity or high visibility.
D. Medical Treatment. Treatment administered by a phys ician or by registered professional personnel under the standin g orders of a physician. Medical treatment does not include first aid treatment even through provided by a physician or registered perso nnel.
E. Recordable Injuries or Illnesses. Any work-related injury or illness that results in:
1. Death, regardless of the time between the injury an d death, or the length of the illness;
2. Days away from work (any time lost after day of inj ury/illness onset);
3. Restricted work;
4. Transfer to another job;
5. Medical treatment beyond first aid;
6. Loss of consciousness; or,
7. A significant injury or illness diagnosed by a phys ician or other licensed health care professional, even if it did n ot result in (1) through (6) above.
1.3 REGULATORY REQUIREMENTS:
A. In addition to the detailed requirements included i n the provisions of this contract, comply with 29 CFR 1926 , comply with 29 CFR 1910 as incorporated by reference within 29 CFR 1926 , comply with ASSE A10.34, and all applicable federal, state, and local laws, ordinances, criteria, rules and regulations . Submit matters of interpretation of standards for resolution before starting work. Wher e the requirements
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 35 26-4
of this specification, applicable laws, criteria, o rdinances, regulations, and referenced documents vary, the mos t stringent requirements govern except with specific approval a nd acceptance by the Contracting Officer Representative.
1.4 ACCIDENT PREVENTION PLAN (APP):
A. The APP (aka Construction Safety & Health Plan) sha ll interface with the Contractor's overall safety and health program. Include any portions of the Contractor's overall safety and hea lth program referenced in the APP in the applicable APP element and ensure it is site-specific. The Government considers the Prime C ontractor to be the "controlling authority" for all worksite safety and health of each subcontractor(s). Contractors are responsible for i nforming their subcontractors of the safety provisions under the t erms of the contract and the penalties for noncompliance, coordinating t he work to prevent one craft from interfering with or creating hazardo us working conditions for other crafts, and inspecting subcont ractor operations to ensure that accident prevention responsibilities ar e being carried out.
B. The APP shall be prepared as follows:
1. Written in English by a qualified person who is emp loyed by the Prime Contractor articulating the specific work and hazards pertaining to the contract (model language can be f ound in ASSE A10.33). Specifically articulating the safety requi rements found within these VA contract safety specifications.
2. Address both the Prime Contractors and the subcontr actors work operations.
3. State measures to be taken to control hazards assoc iated with materials, services, or equipment provided by suppl iers.
4. Address all the elements/sub-elements and in order as follows:
a. SIGNATURE SHEET. Title, signature, and phone number of the following:
(1) Plan preparer (Qualified Person such as corporate s afety staff person or contracted Certified Safety Professional with construction safety experience);
(2) Plan approver (company/corporate officers authorize d to obligate the company);
(3) Plan concurrence (e.g., Chief of Operations, Corpor ate Chief of Safety, Corporate Industrial Hygienist, project man ager or superintendent, project safety professional). Provi de concurrence of other applicable corporate and proje ct personnel (Contractor).
b. BACKGROUND INFORMATION. List the following:
(1) Contractor;
(2) Contract number;
(3) Project name;
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 35 26-5
(4) Brief project description, description of work to b e performed, and location; phases of work anticipated (these wil l require an AHA).
c. STATEMENT OF SAFETY AND HEALTH POLICY. Provide a copy of current corporate/company Safety and Health Policy Statemen t, detailing commitment to providing a safe and healthful workpl ace for all employees. The Contractor’s written safety program goals, objectives, and accident experience goals for this contract should be provided.
d. RESPONSIBILITIES AND LINES OF AUTHORITIES . Provide the following:
(1) A statement of the employer’s ultimate responsibili ty for the implementation of his SOH program;
(2) Identification and accountability of personnel resp onsible for safety at both corporate and project level. Contrac ts specifically requiring safety or industrial hygiene personnel shall include a copy of their resumes.
(3) The names of Competent and/or Qualified Person(s) a nd proof of competency/qualification to meet specific OSHA Competent/Qualified Person(s) requirements must be attached;
(4) Requirements that no work shall be performed unless a designated competent person is present on the job s ite;
(5) Requirements for pre-task Activity Hazard Analysis (AHAs);
(6) Lines of authority;
(7) Policies and procedures regarding noncompliance wit h safety requirements (to include disciplinary actions for v iolation of safety requirements) should be identified;
e. SUBCONTRACTORS AND SUPPLIERS. If applicable, provide procedures for coordinating SOH activities with other employer s on the job site:
(1) Identification of subcontractors and suppliers (if known);
(2) Safety responsibilities of subcontractors and suppl iers.
f. TRAINING.
(1) Site-specific SOH orientation training at the time of initial hire or assignment to the project for every employe e before working on the project site is required.
(2) Mandatory training and certifications that are appl icable to this project (e.g., explosive actuated tools, crane operator, rigger, crane signal person, fall protection, elect rical lockout/NFPA 70E, machine/equipment lockout, confin ed space, etc…) and any requirements for periodic retraining/recertification are required.
(3) Procedures for ongoing safety and health training f or supervisors and employees shall be established to a ddress changes in site hazards/conditions.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 35 26-6
(4) OSHA 10-hour training is required for all workers o n site and the OSHA 30-hour training is required for Competent Persons (CPs).
g. SAFETY AND HEALTH INSPECTIONS.
(1) Specific assignment of responsibilities for a minim um daily job site safety and health inspection during periods of work activity: Who will conduct (e.g., “Site Safety and Health CP”), proof of inspector’s training/qualifications, when inspections will be conducted, procedures for documentation, de ficiency tracking system, and follow-up procedures.
(2) Any external inspections/certifications that may be required (e.g., contracted CSP or CSHT)
h. ACCIDENT INVESTIGATION & REPORTING. The Contractor shall conduct mishap investigations of all OSHA Recordable Incide nts. The APP shall include accident/incident investigation proce dure & identify person(s) responsible to provide the follo wing to the Contracting Officer Representative :
(1) Exposure data (man-hours worked);
(2) Accident investigations, reports, and logs.
i. PLANS (PROGRAMS, PROCEDURES) REQUIRED. Based on a risk assessment of contracted activities and on mandator y OSHA compliance programs, the Contractor shall address a ll applicable occupational risks in site-specific compliance and accident prevention plans. These Plans shall include but are not be limited to procedures for addressing the risks asso ciates with the following:
(1) Emergency response ;
(2) Contingency for severe weather;
(3) Fire Prevention;
(4) Medical Support;
(5) Posting of emergency telephone numbers;
(6) Prevention of alcohol and drug abuse;
(7) Site sanitation (housekeeping, drinking water, toil ets);
(8) Night operations and lighting;
(9) Hazard communication program;
(10) Welding/Cutting “Hot” work;
(11) Electrical Safe Work Practices (Electrical LOTO/NFP A 70E);
(12) General Electrical Safety;
(13) Hazardous energy control (Machine LOTO);
(14) Site-Specific Fall Protection & Prevention;
(15) Excavation/trenching (AHA review & approval require d, see checklist in appendix)
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 35 26-7
(16) Asbestos abatement;
(17) Lead abatement;
(18) Crane Permits (see appendix);
(19) Respiratory protection;
(20) Health hazard control program;
(21) Radiation Safety Program;
(22) Abrasive blasting;
(23) Heat/Cold Stress Monitoring;
(24) Crystalline Silica Monitoring (Assessment);
(25) Demolition plan (to include engineering survey);
(26) Formwork and shoring erection and removal;
(27) PreCast Concrete.
C. Submit the APP to the Contracting Officer Represent ative for review for compliance with contract requirements in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES 15 calendar days prior to the date of the preconstruction conference for acce ptance. Work cannot proceed without an accepted APP.
D. Once accepted by the Contracting Officer Representa tive, the APP and attachments will be enforced as part of the contrac t. Disregarding the provisions of this contract or the accepted APP wil l be cause for stopping of work, at the discretion of the Contract ing Officer, until the matter has been rectified.
E. Once work begins, changes to the accepted APP shall be made with the knowledge and concurrence of the Contracting Office r Representative. Should any severe hazard exposure, i.e. imminent da nger, become evident, stop work in the area, secure the area, an d develop a plan to remove the exposure and control the hazard. Notify the Contracting Officer within 24 hours of discovery. Eliminate/rem ove the hazard. In the interim, take all necessary action to restore a nd maintain safe working conditions in order to safeguard onsite per sonnel, visitors, the public (as defined by ASSE/SAFE A10.34) and the environment.
1.5 ACTIVITY HAZARD ANALYSES (AHAS):
A. AHAs are also known as Job Hazard Analyses, Job Saf ety Analyses, and Activity Safety Analyses. Before beginning each wor k activity involving a type of work presenting hazards not exp erienced in previous project operations or where a new work crew or sub- contractor is to perform the work, the Contractor(s) performing that work activity shall prepare an AHA (Example electronic AHA forms can be found on the US Army Corps of Engineers web site).
B. AHAs shall define the activities being performed an d identify the work sequences, the specific anticipated hazards, site c onditions, equipment, materials, and the control measures to b e implemented to eliminate or reduce each hazard to an acceptable le vel of risk.
C. Work shall not begin until the AHA for the work act ivity has been accepted by the Contracting Officer Representative and discussed with
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 35 26-8
all engaged in the activity, including the Contract or, subcontractor(s), and Government on-site representa tives at preparatory and initial control phase meetings.
1. The names of the Competent/Qualified Person(s) shal l be identified and included in the AHA. Certification of their competency/qualification shall be submitted to the Government Designated Authority (GDA) for acceptance prior to the start of that work activity.
2. The AHA shall be reviewed and modified as necessary to address changing site conditions, operations, or change of competent/qualified person(s).
a. If more than one Competent/Qualified Person is used on the AHA activity, a list of names shall be submitted as an attachment to the AHA. Those listed must be Competent/Qualified f or the type of work involved in the AHA and familiar with current site safety issues.
b. If a new Competent/Qualified Person (not on the ori ginal list) is added, the list shall be updated (an administrative action not requiring an updated AHA). The new person shall ack nowledge in writing that he or she has reviewed the AHA and is familiar with current site safety issues.
3. Submit AHAs to the Contracting Officer Representati ve for review for compliance with contract requirements in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES for review at least 15 calendar days prior to the start of each phase. Subsequent AHAs as shall be formatted as amendments to the APP. The analysis should be used during daily inspections to ensure the impl ementation and effectiveness of the activity's safety and health c ontrols.
4. The AHA list will be reviewed periodically (at leas t monthly) at the Contractor supervisory safety meeting and updated a s necessary when procedures, scheduling, or hazards change.
5. Develop the activity hazard analyses using the proj ect schedule as the basis for the activities performed. All activit ies listed on the project schedule will require an AHA. The AHAs will be developed by the contractor, supplier, or subcontractor and prov ided to the prime contractor for review and approval and then submitt ed to the Contracting Officer Representative .
1.6 PRECONSTRUCTION CONFERENCE:
A. Contractor representatives who have a responsibilit y or significant role in implementation of the accident prevention p rogram, as required by 29 CFR 1926.20(b)(1) , on the project shall attend the preconstruction conference to gain a mutual underst anding of its implementation. This includes the project superinte ndent, subcontractor superintendents, and any other assigned safety and health professionals.
B. Discuss the details of the submitted APP to include incorporated plans, programs, procedures and a listing of anticipated A HAs that will be developed and implemented during the performance of the contract. This list of proposed AHAs will be reviewed at the confe rence and an agreement will be reached between the Contractor an d the Contracting
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 35 26-9
Officer's representative as to which phases will re quire an analysis. In addition, establish a schedule for the preparati on, submittal, review, and acceptance of AHAs to preclude project delays.
C. Deficiencies in the submitted APP will be brought t o the attention of the Contractor within 14 days of submittal, and the Contractor shall revise the plan to correct deficiencies and re-subm it it for acceptance. Do not begin work until there is an acc epted APP.
1.7 “SITE SAFETY AND HEALTH OFFICER” (SSHO) AND “COMPET ENT PERSON” (CP):
A. The Prime Contractor shall designate a minimum of o ne SSHO at each project site that will be identified as the SSHO to administer the Contractor's safety program and government-accepted Accident Prevention Plan. The Prime Contractor shall designate a minimu m of one CP in compliance with 29 CFR 1926.20 (b)(2 ) that will be identified as a CP to administer their safety program.
B. These Competent Persons can have collateral duties as the subcontractor’s superintendent and/or work crew lea d persons.
C. The SSHO or an equally-qualified Designated Represe ntative/alternate will maintain a presence on the site during constru ction operations in accordance with FAR Clause 52.236-6: Superintendence by the Contractor . CPs will maintain presence during their constructio n activities in accordance with above mentioned clause. A listing o f the designated SSHO and all the CPs shall be submitted prior to th e start of work as part of the APP with the training documentation and /or AHA as listed in Section 1.8 below.
D. The repeated presence of uncontrolled hazards durin g a contractor’s work operations will result in the designated CP as being deemed incompetent and result in the required removal of t he employee in accordance with FAR Clause 52.236-5: Material and W orkmanship, Paragraph (c).
1.8 TRAINING:
A. The designated Prime Contractor SSHO must meet the requirements of all applicable OSHA standards and be capable (through t raining, experience, and qualifications) of ensuring that the requiremen ts of 29 CFR 1926.16 and other appropriate Federal, State and local requ irements are met for the project. As a minimum the SSHO must have comple ted the OSHA 30-hour Construction Safety class and have five (5) years o f construction industry safety experience or three (3) years if he /she possesses a Certified Safety Professional (CSP) or certified Co nstruction Safety and Health Technician (CSHT) certification or have a safety and health degree from an accredited university or college.
B. All designated CPs shall have completed the OSHA 30 -hour Construction Safety course within the past 5 years.
C. All other construction workers shall have the OSHA 10-hour Construction Safety Outreach course and any necessary safety tra ining to be able to identify hazards within their work environment.
D. Submit training records associated with the above t raining requirements to the Contracting Officer Representative /for revi ew for compliance with contract requirements in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES 15 calendar days prior to the date of the preconstruction conference for acceptance.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 35 26-10
E. Prior to any worker for the contractor or subcontra ctors beginning work, they shall undergo a safety briefing provided by the SSHO or his/her designated representative. As a minimum, th is briefing shall include information on the site-specific hazards, c onstruction limits, VAMC safety guidelines, means of egress, break area s, work hours, locations of restrooms, use of VAMC equipment, emer gency procedures, accident reporting etc... Documentation shall be pr ovided to the Resident Engineer that individuals have undergone c ontractor’s safety briefing.
F. Ongoing safety training will be accomplished in the form of weekly documented safety meeting.
1.9 INSPECTIONS:
A. The SSHO shall conduct frequent and regular safety inspections (daily) of the site and each of the subcontractors CPs shal l conduct frequent and regular safety inspections (daily) of the their work operations as required by 29 CFR 1926.20(b)(2) . Each week, the SSHO shall conduct a formal documented inspection of the entire construc tion areas with the subcontractors’ present in their work areas. Coordi nate with, and report findings and corrective actions weekly to Co ntracting Officer Representative.
B. A Certified Safety Professional (CSP) with speciali zed knowledge in construction safety or a certified Construction Saf ety and Health Technician (CSHT) shall randomly conduct a monthly site safety inspection. The CSP or CSHT can be a corporate safe ty professional or independently contracted. The CSP or CSHT will prov ide their certificate number on the required report for verif ication as necessary.
1. Results of the inspection will be documented with t racking of the identified hazards to abatement.
2. The Contracting Officer Representative will be noti fied immediately prior to start of the inspection and invited to acc ompany the inspection.
3. Identified hazard and controls will be discussed to come to a mutual understanding to ensure abatement and prevent futur e reoccurrence.
4. A report of the inspection findings with status of abatement will be provided to the Contracting Officer Representative within one week of the onsite inspection.
1.10 ACCIDENTS, OSHA 300 LOGS, AND MAN-HOURS:
A. Notify the Contracting Officer Representative as so on as practical, but no more than four hours after any accident meeting the definition of OSHA Recordable Injuries or Illnesses or High Visib ility Accidents, property damage equal to or greater than $5,000, or any weight handling equipment accident. Within notification include con tractor name; contract title; type of contract; name of activity, installation or location where accident occurred; date and time of accident; names of personnel injured; extent of property damage, if an y; extent of injury, if known, and brief description of accident (to inc lude type of construction equipment used, PPE used, etc.). Prese rve the conditions and evidence on the accident site until the Contrac ting Officer
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 35 26-11
Representative determine whether a government inves tigation will be conducted.
B. Conduct an accident investigation for recordable in juries and illnesses, for Medical Treatment defined in paragra ph DEFINITIONS, and property damage accidents resulting in at least $20 ,000 in damages, to establish the root cause(s) of the accident. Comple te the VA Form 2162, and provide the report to the Contracting Officer R epresentative within 5 calendar days of the accident. The Contracting Of ficer Representative will provide copies of any required or special forms.
C. A summation of all man-hours worked by the contract or and associated sub-contractors for each month will be reported to the Contracting Officer Representative monthly.
D. A summation of all OSHA recordable accidents experi enced on site by the contractor and associated sub-contractors for each month will be provided to the Contracting Officer Representative monthly. The contractor and associated sub-contractors’ OSHA 300 logs will be made available to the Contracting Officer Representative as requested.
1.11 PERSONAL PROTECTIVE EQUIPMENT (PPE):
A. PPE is governed in all areas by the nature of the w ork the employee is performing. For example, specific PPE required for performing work on electrical equipment is identified in NFPA 70E, Sta ndard for Electrical Safety in the Workplace.
B. Mandatory PPE includes:
1. Hard Hats – unless written authorization is given b y the Contracting Officer Representative in circumstances of work ope rations that have limited potential for falling object hazards s uch as during finishing work or minor remodeling. With authorizat ion to relax the requirement of hard hats, if a worker becomes expos ed to an overhead falling object hazard, then hard hats would be requ ired in accordance with the OSHA regulations.
2. Safety glasses – unless written authorization is gi ven by the Contracting Officer Representative, appropriate saf ety glasses meeting the ANSI Z.87.1 standard must be worn by ea ch person on site.
3. Appropriate Safety Shoes – based on the hazards pre sent, safety shoes meeting the requirements of ASTM F2413-11 sha ll be worn by each person on site unless written authorization is given by the Contracting Officer Representative.
4. Hearing protection – Use personal hearing protectio n at all times in designated noise hazardous areas or when performing noise hazardous tasks.
1.12 INFECTION CONTROL
A. Infection Control is critical in all medical center facilities. Interior construction activities causing disturbanc e of existing dust, or creating new dust, must be conducted within vent ilation-controlled areas that minimize the flow of airborne particles into patient areas. Exterior construction activities causing disturbanc e of soil or creates dust in some other manner must be controlled. Refer to Specification
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 35 26-12
Section 01 01 10 IC for more detailed information r egarding Infection Control .
1.13 FIRE SAFETY
A. Fire Safety Plan: Establish and maintain a site-spe cific fire protection program in accordance with 29 CFR 1926 . Prior to start of work, prepare a plan detailing project-specific fir e safety measures, including periodic status reports, and submit to Co ntracting Officer Representative for review for compliance with contr act requirements in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES. This plan may be an element of the Accident Prevent ion Plan. Refer to Specification Section 01 01 10 FSS for mor e detailed information regarding Fire Safety .
B. Site and Building Access: Maintain free and unobstr ucted access to facility emergency services and for fire, police an d other emergency response forces in accordance with NFPA 241.
C. Separate temporary facilities, such as trailers, st orage sheds, and dumpsters, from existing buildings and new construc tion by distances in accordance with NFPA 241. For small facilities with less than 6 m (20 feet) exposing overall length, separate by 3m (10 f eet).
D. Temporary Construction Partitions:
1. Install and maintain temporary construction partiti ons to provide smoke-tight separations between construction areas, the areas that are described in phasing requirements, and adjoinin g areas. Construct partitions of gypsum board or treated ply wood (flame spread rating of 25 or less in accordance with ASTM E84) on both sides of fire retardant treated wood or metal steel studs. Extend the partitions through suspended ceilings to floor slab deck or roof. Seal joints and penetrations. At door opening s, install Class C, ¾ hour fire/smoke rated doors with self-closing devices.
2. Install one-hour, two-hour fire-rated temporary con struction partitions as shown on drawings to maintain integri ty of existing exit stair enclosures, exit passageways, fire-rated enclosures of hazardous areas, horizontal exits, smoke barriers, vertical shafts and openings enclosures.
3. Close openings in smoke barriers and fire-rated con struction to maintain fire ratings. Seal penetrations with liste d through- penetration firestop materials in accordance with Section 07 84 00, FIRESTOPPING.
E. Temporary Heating and Electrical: Install, use and maintain installations in accordance with 29 CFR 1926 , NFPA 241 and NFPA 70.
F. Means of Egress: Do not block exiting for occupied buildings, including paths from exits to roads. Minimize disru ptions and coordinate with Contracting Officer Representative.
G. Egress Routes for Construction Workers: Maintain fr ee and unobstructed egress. Inspect daily. Report findings and correcti ve actions weekly to Contracting Officer Representative.
H. Fire Extinguishers: Provide and maintain extinguish ers in construction areas and temporary storage areas in accordance wit h 29 CFR 1926 , NFPA 241 and NFPA 10.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 35 26-13
I. Flammable and Combustible Liquids: Store, dispense and use liquids in accordance with 29 CFR 1926 , NFPA 241 and NFPA 30.
J. Standpipes: Install and extend standpipes up with e ach floor in accordance with 29 CFR 1926 and NFPA 241. Do not charge wet standpipes subject to freezing until weather protected.
K. Sprinklers: Install, test and activate new automati c sprinklers prior to removing existing sprinklers.
L. Existing Fire Protection: Do not impair automatic s prinklers, smoke and heat detection, and fire alarm systems, except for portions immediately under construction, and temporarily for connections . Provide fire watch for impairments more than 4 hours in a 24-hour peri od. Request interruptions in accordance with Article, OPERATION S AND STORAGE AREAS, and coordinate with Contracting Officer Representat ive. All existing or temporary fire protection systems (fire alarms, spr inklers) located in construction areas shall be tested as coordinated w ith the medical center. Parameters for the testing and results of a ny tests performed shall be recorded by the medical center and copies provided to the Contracting Officer Representative.
M. Smoke Detectors: Prevent accidental operation. Remo ve temporary covers at end of work operations each day. Coordinate with Contracting Officer Representative.
N. Hot Work: Perform and safeguard hot work operations in accordance with NFPA 241 and NFPA 51B. Coordinate with Contracting Officer Representative at least 10 days in advance. Designa te contractor's responsible project-site fire prevention program ma nager to permit hot work.
O. Fire Hazard Prevention and Safety Inspections: Insp ect entire construction areas weekly. Coordinate with, and rep ort findings and corrective actions weekly to Contracting Officer Re presentative.
P. Smoking: Smoking is prohibited in and adjacent to c onstruction areas inside existing buildings and additions under const ruction. In separate and detached buildings under construction, smoking is prohibited except in designated smoking rest areas.
Q. Dispose of waste and debris in accordance with NFPA 241. Remove from buildings daily.
R. If required, submit documentation to the Contractin g Officer Representative that personnel have been trained in the fire safety aspects of working in areas with impaired structura l or compartmentalization features.
1.14 ELECTRICAL
A. All electrical work shall comply with NFPA 70 (NEC) , NFPA 70B, NFPA 70E, 29 CFR Part 1910 Subpart J – General Environmental Controls, 29 CFR Part 1910 Subpart S – Electrical, and 29 CFR 1926 Subpart K in addition to other references required by contract.
B. All qualified persons performing electrical work un der this contract shall be licensed journeyman or master electricians . All apprentice electricians performing under this contract shall b e deemed unqualified persons unless they are working under the immediate supervision of a licensed electrician or master electrician.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 35 26-14
C. All electrical work will be accomplished de-energiz ed and in the Electrically Safe Work Condition ( refer to NFPA 70 E for Work Involving Electrical Hazards, including Exemptions to Work Pe rmit). Any Contractor, subcontractor or temporary worker who f ails to fully comply with this requirement is subject to immediate termi nation in accordance with FAR clause 52.236-5(c). Only in rare circumsta nce where achieving an electrically safe work condition prior to beginn ing work would increase or cause additional hazards, or is infeasi ble due to equipment design or operational limitations is energized work permitted. The Contracting Officer Representative with approval of the Medical Center Director will make the determination if the circums tances would meet the exception outlined above. An AHA specific to en ergized work activities will be developed, reviewed, and accepte d prior to the start of that work.
1. Development of a Hazardous Electrical Energy Contro l Procedure is required prior to de-energizing. A single Simple Lo ckout/Tagout Procedure for multiple work operations can only be used for work involving qualified person(s) de-energizing one set of conductors or circuit part source. Task specific Complex Lockout/ Tagout Procedures are required at all other times.
2. Verification of the absence of voltage after de-ene rgizing and lockout/tagout is considered “energized electrical work” (live work) under NFPA 70E, and shall only be performed by qual ified persons wearing appropriate shock protective (voltage rated ) gloves and arc rate personal protective clothing and equipment, us ing Underwriters Laboratories (UL) tested and appropriately rated co ntact electrical testing instruments or equipment appropriate for th e environment in which they will be used.
3. Personal Protective Equipment (PPE) and electrical testing instruments will be readily available for inspectio n by the Contracting Officer Representative.
D. Before beginning any electrical work, an Activity H azard Analysis (AHA) will be conducted to include Shock Hazard and Arc F lash Hazard analyses (NFPA Tables can be used only as a last alterative and it is strongly suggested a full Arc Flash Hazard Analyses be condu cted). Work shall not begin until the AHA for the work activity has b een accepted by the Contracting Officer Representative and discussed wi th all engaged in the activity, including the Contractor, subcontract or(s), and Government on-site representatives at preparatory a nd initial control phase meetings.
E. Ground-fault circuit interrupters. All 120-volt, si ngle-phase 15- and 20-ampere receptacle outlets on construction sites shall have approved ground-fault circuit interrupters for personnel pro tection. “Assured Equipment Grounding Conductor Program” only is not allowed.
1.15 FALL PROTECTION
A. The fall protection (FP) threshold height requireme nt is 6 ft (1.8 m) for ALL WORK, unless specified differently or the O SHA 29 CFR 1926 requirements are more stringent, to include steel e rection activities, systems-engineered activities (prefabricated) metal buildings, residential (wood) construction and scaffolding wor k.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 35 26-15
1. The use of a Safety Monitoring System (SMS) as a fa ll protection method is prohibited.
2. The use of Controlled Access Zone (CAZ) as a fall p rotection method is prohibited.
3. A Warning Line System (WLS) may ONLY be used on flo ors or flat or low-sloped roofs (between 0 - 18.4 degrees or 4:12 slope) and shall be erected around all sides of the work area (See 2 9 CFR 1926.502(f) for construction of WLS requirements). Working with in the WLS does not require FP. No worker shall be allowed in the a rea between the roof or floor edge and the WLS without FP. FP is re quired when working outside the WLS.
4. Fall protection while using a ladder will be govern ed by the OSHA requirements.
1.16 SCAFFOLDS AND OTHER WORK PLATFORMS
A. All scaffolds and other work platforms construction activities shall comply with 29 CFR 1926 Subpart L .
B. The fall protection (FP) threshold height requireme nt is 6 ft (1.8 m) as stated in Section 1.16.
C. The following hierarchy and prohibitions shall be f ollowed in selecting appropriate work platforms.
1. Scaffolds, platforms, or temporary floors shall be provided for all work except that can be performed safely from the g round or similar footing.
2. Ladders less than 20 feet may be used as work platf orms only when use of small hand tools or handling of light materi al is involved.
3. Ladder jacks, lean-to, and prop-scaffolds are prohi bited.
4. Emergency descent devices shall not be used as work ing platforms.
D. Contractors shall use a scaffold tagging system in which all scaffolds are tagged by the Competent Person. Tags shall be c olor-coded: green indicates the scaffold has been inspected and is sa fe to use; red indicates the scaffold is unsafe to use. Tags shall be readily visible, made of materials that will withstand the environme nt in which they are used, be legible and shall include:
1. The Competent Person’s name and signature;
2. Dates of initial and last inspections.
E. Mast Climbing work platforms: When access ladders, including masts designed as ladders, exceed 20 ft (6 m) in height, positive fall protection shall be used.
1.17 EXCAVATION AND TRENCHES
A. All excavation and trenching work shall comply with 29 CFR 1926 Subpart P.
B. All excavations and trenches 5 feet in depth or gre ater shall require a written trenching and excavation permit (NOTE – som e States and other local jurisdictions require separate state/jurisdic tion-issued excavation permits). The permit shall be completed and provided to the Contracting Officer Representative prior to commenc ing work for the
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 35 26-16
day. At the end of the day, the permit shall be clo sed out and provided to the Contracting Officer Representative and/or other Government Designated Authority. The permit shall b e maintained onsite and include the following:
1. Determination of soil classification.
2. Indication that utilities have been located and ide ntified. If utilities could not be located after all reasonable attempt, then excavating operations will proceed cautiously.
3. Indication of selected excavation protective system .
4. Indication that the spoil pile will be stored at le ast 2 feet from the edge of the excavation and safe access provided within 25 feet of the workers.
5. Indication of assessment for a potential toxic, exp losive, or oxygen deficient atmosphere.
C. If not using an engineered protective system such a s a trench box, shielding, shoring, or other Professional Engineer designed system and using a sloping or benching system, soil classifica tion cannot be Solid Rock or Type A. All soil will be classified as Type B or Type C and sloped or benched in accordance with Appendix B of 29 CFR 1926 .
1.18 CRANES
A. All crane work shall comply with 29 CFR 1926 Subpart C .
B. Prior to operating a crane, the operator must be li censed, qualified or certified to operate the crane. Thus, all the provi sions contained with Subpart CC are effective and there is no “Phas e In” date of November 10, 2014.
C. A detailed lift permit shall be submitted 14 days p rior to the scheduled lift complete with route for truck carryi ng load, crane load analysis, siting of crane and path of swing. The li ft will not be allowed without approval of this document.
D. Crane operators shall not carry loads
1. Over the general public or VAMC personnel
2. Over any occupied building unless
a. The top two floors are vacated
b. Or overhead protection with a design live load of 3 00 psf is provided
1.19 CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAGOUT)
A. All installation, maintenance, and servicing of equ ipment or machinery shall comply with 29 CFR 1910.147 except for specifically referenced operations in 29 CFR 1926 such as concrete & masonry equipment 1926.702(j), heavy machinery & equipment 1926.600(a )(3)(i), and process safety management of highly hazardous chemicals (19 26.64). Control of hazardous electrical energy during the installation , maintenance, or servicing of electrical equipment shall comply with Section 1.15 to include NFPA 70E and other VA specific requirements discussed in the section.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 35 26-17
1.20 CONFINED SPACE ENTRY
A. All confined space entry shall comply with 29 CFR 1910.146 except for specifically referenced operations in 29 CFR 1926 such as excavations/trenches 1926.651(g).
B. A site-specific Confined Space Entry Plan (including permitting process) shall be developed and submitted to the Contracting Officer Representative.
1.21 WELDING AND CUTTING
As specified in section 1.14, Hot Work: Perform and safeguard hot work operations in accordance with NFPA 241 and NFPA 51B. Coordinate with Contracting Officer Representative. Obtain permits from Contracting Officer Representative at least _10_ days in advance .
1.22 LADDERS
A. All Ladder use shall comply with 29 CFR 1926 Subpart X .
B. All portable ladders shall be of sufficient length and shall be placed so that workers will not stretch or assume a hazardous position.
C. Manufacturer safety labels shall be in place on ladders.
D. Step Ladders shall not be used in the closed position.
E. Top steps or cap of step ladders shall not be used as a step.
F. Portable ladders, used as temporary access, shall extend at least 3 ft (0.9 m) above the upper landing surface.
1. When a 3 ft (0.9-m) extension is not possible, a grasping device(such as a grab rail) shall be provided to assist wo rkers inmounting and dismounting the ladder.
2. In no case shall the length of the ladder be such that ladderdeflection under a load would, by itself, cause the ladder to slipfrom its support.
G. Ladders shall be inspected for visible defects on a daily basis and after any occurrence that could affect their safe use. Broken or damaged ladders shall be immediately tagged "DO NOT USE," or with similar wording, and withdrawn from service until restored to a condition meeting their original design.
1.23 FLOOR & WALL OPENINGS
A. All floor and wall openings shall comply with 29 CFR 1926 Subpart M .
B. Floor and roof holes/openings are any that measure over 2 in (51 mm) in any direction of a walking/working surface which persons may trip or fall into or where objects may fall to the level below. See 21.F for covering and labeling requirements. Skylights located in floors or roofs are considered floor or roof hole/openings.
C. All floor, roof openings or hole into which a person can accidentally walk or fall through shall be guarded either by a railing system with toeboards along all exposed sides or a load-bearing cover. When the cover is not in place, the opening or hole shall be protected by a removable guardrail system or shall be attended when the guarding system has been removed or other fall protection system.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 35 26-18
1. Covers shall be capable of supporting, without failure, at leasttwice the weight of the worker, equipment and materi al combined.
2. Covers shall be secured when installed, clearly marked with the word“HOLE”, “COVER” or “Danger, Roof Opening-Do Not Remo ve” or color-coded or equivalent methods (e.g., red or orange “X” ). Workers mustbe made aware of the meaning for color coding and eq uivalentmethods.
3. Roofing material, such as roofing membrane, insulation or felts ,covering or partly covering openings or holes, shall be immediatelycut out. No hole or opening shall be left unattended unless covered.
4. Non-load-bearing skylights shall be guarded by a load-bearingskylight screen, cover, or railing system along all exposed sides.
5. Workers are prohibited from standing/walking on skylights.
- - - E N D - - -
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 35 26-19
AWE Focus Program Review 2016 Construction: Excavation Safety
DATE: NAME OF REVIEWER:
ME
T
NO
T M
ET
N/A
REQUIREMENT
16.6A. Are the estimated locations of utility installations, such as sewer, telephone, fuel, electric, water lines, or any other underground installations that reasonably may be expected to be encountered during excavation work determined prior to opening an excavation? [OSHA 29 CFR 1926.651(b)(1)]
16.6B. Are utility companies contacted within established or customary local response times, advised of the proposed work, and asked to establish the location of utility underground installations up to their own meters prior to the start of actual excavation? [OSHA 29 CFR 1926.651(b)(2)]
16.6C. On VHA property, is the proposed dig site being marked, “as built” drawings reviewed, and visual indicators (manholes, valves, meters, permanent markers, etc…) of the utilities being utilized to establish the location of utility underground installations by in-house VHA personnel or a contracted private locator service? [OSHA 29 CFR 1926.651(b)(2)]
16.6D. On VHA property, are locations of utility underground installations being marked and maintained by use of stakes, paint, flags, or other clearly identifiable materials to show the field location of underground facilities, in accordance with the current color code standard of the American Public Works Association.? [OSHA 29 CFR 1926.651(b)(2)]
16.6E. If utility companies or the VHA cannot locate underground utility installations or cannot establish the exact location of these installations, are excavation contractors proceeding with caution and using detection equipment or other acceptable means to locate utility installations (careful hand digging, pot-holing and vacuum excavation, hand tools that use air or water under pressure, exploratory bar, or other)? [OSHA 29 CFR 1926.651(b)(2)]
16.6F. When excavation operations approach the estimated location (within 2 feet) of underground installations, are the exact location of the installations determined by safe and acceptable means (careful hand digging, pot-holing and vacuum excavation, hand tools that use air or water under pressure , exploratory bar, or other)? [OSHA 29 CFR 1926.651(b)(3)]
16.6G. While the excavation is open, are underground installations protected, supported or removed (LockOut/Tagout, supports built, etc…) as necessary to safeguard employees? [OSHA 29 CFR 1926.651(b)(4)]
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 35 26-20
16.6H. Are Activity Hazard Analyses and excavation permits being completed prior to opening excavations? (FAR 52.236-13, Accident Prevention; VA Master Specs, Div. 01, Section 01 35 26 Safety Requirements, Subtopic 1.5 & 1.18)
16.6I. Where workers enter an excavation greater than 5 feet in depth, are soils being classified in accordance with OSHA classification system (Solid Rock, Type A, Type B, or Type C)? [OSHA Directive CPL 2- 0.124; VHA Directive 2011-036, Subpar. 4(l)(7)] Note: If using an excavation protective system of sloping or benching, then the soil classification cannot be Solid Rock or Type A. Thus, the angle of repose cannot be steeper than 1 to 1 (45 degrees) (OSHA 29 CFR 1926.652 & associated Appendix A; VA Master Specs, Div. 01, Section 01 35 26 Safety Requirements, Subtopic 1.18, Par. C)?
16.6J. Where workers enter an excavation greater than 5 feet in depth, are protective systems being designed in accordance with 29 CFR 1926, Subpart P, Appendices B to E or designed by Professional Engineer [OSHA 29 CFR 1926.652(a)] Note: excavations in excess of 20 feet in depth must be designed by PE and sloping or benching systems cannot have an angle of repose steeper than 1 to 1 (45 degrees) as provided above.
Reviewer Signature:
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 45 29 - 1
SECTION 01 45 29 TESTING LABORATORY SERVICES
PART 1 - GENERAL
1.1 DESCRIPTION:
This section specifies materials testing activities and inspection
services required during project construction to be provided by a
Testing Laboratory retained by the General.
1.2 APPLICABLE PUBLICATIONS:
A. The publications listed below form a part of this specification to the
extent referenced. The publications are referred to in the text by the
basic designation only.
B. American Association of State Highway and Transportation Officials
(AASHTO):
T27-11..................Standard Method of Test for Sieve Analysis of
Fine and Coarse Aggregates
T96-02 (R2006)..........Standard Method of Test for Resistance to
Degradation of Small-Size Coarse Aggregate by
Abrasion and Impact in the Los Angeles Machine
T99-10..................Standard Method of Test for Moisture-Density
Relations of Soils Using a 2.5 Kg (5.5 lb.)
Rammer and a 305 mm (12 in.) Drop
T104-99 (R2007).........Standard Method of Test for Soundness of
Aggregate by Use of Sodium Sulfate or Magnesium
Sulfate
T180-10.................Standard Method of Test for Moisture-Density
Relations of Soils using a 4.54 kg (10 lb.)
Rammer and a 457 mm (18 in.) Drop
T191-02(R2006)..........Standard Method of Test for Density of Soil In-
Place by the Sand-Cone Method
C. American Concrete Institute (ACI):
506.4R-94 (R2004).......Guide for the Evaluation of Shotcrete
D. American Society for Testing and Materials (ASTM):
A325-10.................Standard Specification for S tructural Bolts,
Steel, Heat Treated, 120/105 ksi Minimum
Tensile Strength
A370-12.................Standard Test Methods and Definitions for
Mechanical Testing of Steel Products
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 45 29 - 2
A490-12.................Standard Specification for Heat Treated Steel
Structural Bolts, 150 ksi Minimum Tensile
Strength
C31/C31M-10.............Standard Practice for Makin g and Curing
Concrete Test Specimens in the Field
C33/C33M-11a............Standard Specification for Concrete Aggregates
C39/C39M-12.............Standard Test Method for Co mpressive Strength
of Cylindrical Concrete Specimens
C109/C109M-11b..........Standard Test Method for Co mpressive Strength
of Hydraulic Cement Mortars
C136-06.................Standard Test Method for Si eve Analysis of Fine
and Coarse Aggregates
C138/C138M-10b..........Standard Test Method for De nsity (Unit Weight),
Yield, and Air Content (Gravimetric) of
Concrete
C143/C143M-10a..........Standard Test Method for Sl ump of Hydraulic
Cement Concrete
C172/C172M-10...........Standard Practice for Sampl ing Freshly Mixed
Concrete
C173/C173M-10b..........Standard Test Method for Ai r Content of freshly
Mixed Concrete by the Volumetric Method
C330/C330M-09...........Standard Specification for Lightweight
Aggregates for Structural Concrete
C1019-11................Standard Test Method for Sa mpling and Testing
Grout
C1064/C1064M-11.........Standard Test Method for Te mperature of Freshly
Mixed Portland Cement Concrete
C1077-11c...............Standard Practice for Agenc ies Testing Concrete
and Concrete Aggregates for Use in Construction
and Criteria for Testing Agency Evaluation
D422-63(2007)...........Standard Test Method for Pa rticle-Size Analysis
of Soils
D698-07e1...............Standard Test Methods for L aboratory Compaction
Characteristics of Soil Using Standard Effort
D1140-00(2006)..........Standard Test Methods for A mount of Material in
Soils Finer than No. 200 Sieve
01 45 29 - 3
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
D1188-07e1..............Standard Test Method for Bu lk Specific Gravity
and Density of Compacted Bituminous Mixtures
Using Coated Samples
D1556-07................Standard Test Method for De nsity and Unit
Weight of Soil in Place by the Sand-Cone Method
D1557-09................Standard Test Methods for L aboratory Compaction
Characteristics of Soil Using Modified Effort
(56,000ft lbf/ft3 (2,700 KNm/m3))
D2166-06................Standard Test Method for Un confined Compressive
Strength of Cohesive Soil
D2167-08)...............Standard Test Method for De nsity and Unit
Weight of Soil in Place by the Rubber Balloon
Method
D2216-10................Standard Test Methods for L aboratory
Determination of Water (Moisture) Content of
Soil and Rock by Mass
D2974-07a...............Standard Test Methods for M oisture, Ash, and
Organic Matter of Peat and Other Organic Soils
D3666-11................Standard Specification for Minimum Requirements
for Agencies Testing and Inspecting Road and
Paving Materials
D3740-11................Standard Practice for Minim um Requirements for
Agencies Engaged in Testing and/or Inspection
of Soil and Rock as used in Engineering Design
and Construction
D6938-10................Standard Test Method for In -Place Density and
Water Content of Soil and Soil-Aggregate by
Nuclear Methods (Shallow Depth)
E94-04(2010)............Standard Guide for Radiogra phic Examination
E164-08.................Standard Practice for Conta ct Ultrasonic
Testing of Weldments
E329-11c................Standard Specification for Agencies Engaged in
Construction Inspection, Testing, or Special
Inspection
E543-09.................Standard Specification for Agencies Performing
Non-Destructive Testing
01 45 29 - 4
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
E605-93(R2011)..........Standard Test Methods for T hickness and Density
of Sprayed Fire Resistive Material (SFRM)
Applied to Structural Members
E709-08.................Standard Guide for Magnetic Particle
Examination
E1155-96(R2008).........Determining FF Floor Flatne ss and FL Floor
Levelness Numbers
E. American Welding Society (AWS):
D1.D1.1M-10.............Structural Welding Code-Ste el
1.3 REQUIREMENTS:
A. Accreditation Requirements: Construction materials testing laboratories
must be accredited by a laboratory accreditation au thority and will be
required to submit a copy of the Certificate of Acc reditation and Scope
of Accreditation. The laboratory’s scope of accredi tation must include
the appropriate ASTM standards (i.e.; E329, C1077, D3666, D3740, A880,
E543) listed in the technical sections of the speci fications.
Laboratories engaged in Hazardous Materials Testing shall meet the
requirements of OSHA and EPA. The policy applies to the specific
laboratory performing the actual testing, not just the “Corporate
Office.”
B. Inspection and Testing: Testing laboratory shall in spect materials and
workmanship and perform tests described herein and additional tests
requested by COR. When it appears materials furnish ed, or work
performed by Contractor fail to meet construction c ontract
requirements, Testing Laboratory shall direct atten tion of COR to such
failure.
C. Written Reports: Testing laboratory shall submit te st reports to COR,
Contractor, unless other arrangements are agreed to in writing by the
COR. Submit reports of tests that fail to meet cons truction contract
requirements on colored paper.
D. Verbal Reports: Give verbal notification to COR imm ediately of any
irregularity.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.1 EARTHWORK:
A. General: The Testing Laboratory shall provide quali fied personnel,
materials, equipment, and transportation as require d to perform the
01 45 29 - 5
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
services identified/required herein, within the agr eed to schedule
and/or time frame. The work to be performed shall b e as identified
herein and shall include but not be limited to the following:
1. Observe fill and subgrades during proof-rolling to evaluate
suitability of surface material to receive fill or base course.
Provide recommendations to the COR regarding suitab ility or
unsuitability of areas where proof-rolling was obse rved. Where
unsuitable results are observed, witness excavation of unsuitable
material and recommend to COR extent of removal and replacement of
unsuitable materials and observe proof-rolling of r eplaced areas
until satisfactory results are obtained.
2. Provide full time observation of fill placement and compaction and
field density testing in vault areas and provide pa rt
timeobservation of fill placement and compaction an d field density
testing in pavement areas to verify that earthwork compaction
obtained is in accordance with contract documents.
3. Provide supervised geotechnical technician to inspe ct excavation,
subsurface preparation, and backfill for structural fill.
B. Testing Compaction:
1. Determine maximum density and optimum moisture cont ent for each type
of fill, backfill and subgrade material used, in co mpliance with
ASTM D698 , D1557, Method A ASTM D698, and/or ASTM D1557.
2. Make field density tests in accordance with the pri mary testing
method following ASTM D6938 wherever possible. Fiel d density tests
utilizing ASTM D1556 or ASTM D2167shall be utilized on a case by
case basis only if there are problems with the vali dity of the
results from the primary method due to specific sit e field
conditions. Should the testing laboratory propose t hese alternative
methods, they should provide satisfactory explanati on to the COR
before the tests are conducted.
a. Slab Subgrade: At least one test of subgrade. In ea ch compacted
fill layer, perform one test at minimum for overlay ing building
slab.
b. Foundation Wall Backfill: One test per 30 m (100 fe et) of each
layer of compacted fill but in no case fewer than t wo tests.
01 45 29 - 6
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
c. Pavement Subgrade: One test for each 335 m 2 (400 square yards),
but in no case fewer than two tests.
d. Curb, Gutter, and Sidewalk: One test for each 90 m (300 feet),
but in no case fewer than two tests.
e. Trenches: One test at maximum 30 m (100 foot) inter vals per 1200
mm (4 foot) of vertical lift and at changes in requ ired density,
but in no case fewer than two tests.
C. Fill and Backfill Material Gradation: One test per 10 cubicyards
stockpiled or in-place source material. Gradation o f fill and backfill
material shall be determined in accordance with AST M C136, ASTM D422,
and ASTM D1140.
D. Testing Materials: Test suitability of on-site and off-site borrow as
directed by COR.
3.2 LANDSCAPING:
A. Test topsoil for organic materials, pH, phosphate, potash content, and
gradation of particles.
1. Test for organic material by using ASTM D2974.
2. Determine percent of silt, sand, clay, and foreign materials such as
rock, roots, and vegetation.
B. Submit laboratory test report of topsoil to COR.
3.3 ASPHALT CONCRETE PAVING:
A. Aggregate Base Course:
1. Determine maximum density and optimum moisture cont ent for aggregate
base material in accordance with ASTM D1557, Method D.
2. Make a minimum of three field density tests on each day's final
compaction on each aggregate course in accordance w ith ASTM D1556.
3. Sample and test aggregate as necessary to insure co mpliance with
specification requirements for gradation, wear, and soundness as
specified in the applicable state highway standards and
specifications.
B. Asphalt Concrete:
1. Aggregate: Sample and test aggregates in stock pile and hot-bins as
necessary to insure compliance with specification r equirements for
gradation (AASHTO T27), wear (AASHTO T96), and soun dness (AASHTO
T104).
01 45 29 - 7
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
2. Temperature: Check temperature of each load of asph alt concrete at
mixing plant and at site of paving operation.
3. Density: Make a minimum of two field density tests in accordance
with ASTM D1188 of asphalt base and surface course for each day's
paving operation.
3.4 SITE WORK CONCRETE:
Test site work concrete including materials for con crete as required in
Article CONCRETE of this section.
3.5 CONCRETE:
A. Batch Plant Inspection and Materials Testing:
1. Perform continuous batch plant inspection until con crete quality is
established to satisfaction of COR with concurrence of Contracting
Officer and perform periodic inspections thereafter as determined by
COR.
2. Periodically inspect and test batch proportioning e quipment for
accuracy and report deficiencies to COR.
3. Sample and test mix ingredients as necessary to ins ure compliance
with specifications.
4. Sample and test aggregates daily and as necessary f or moisture
content. Test the dry rodded weight of the coarse a ggregate whenever
a sieve analysis is made, and when it appears there has been a
change in the aggregate.
5. Certify, in duplicate, ingredients and proportions and amounts of
ingredients in concrete conform to approved trial m ixes. When
concrete is batched or mixed off immediate building site, certify
(by signing, initialing or stamping thereon) on del ivery slips
(duplicate) that ingredients in truck-load mixes co nform to
proportions of aggregate weight, cement factor, and water-cement
ratio of approved trial mixes.
B. Field Inspection and Materials Testing:
1. Provide a technician at site of placement at all ti mes to perform
concrete sampling and testing.
2. Review the delivery tickets of the ready-mix concre te trucks
arriving on-site. Notify the Contractor if the conc rete cannot be
placed within the specified time limits or if the t ype of concrete
delivered is incorrect. Reject any loads that do no t comply with the
Specification requirements. Rejected loads are to b e removed from
01 45 29 - 8
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
the site at the Contractor’s expense. Any rejected concrete that is
placed will be subject to removal.
3. Take concrete samples at point of placement in acco rdance with ASTM
C172. Mold and cure compression test cylinders in a ccordance with
ASTM C31. Make at least three cylinders for each 40 m3 (50 cubic
yards) or less of each concrete type, and at least three cylinders
for any one day's pour for each concrete type. Labe l each cylinder
with an identification number. COR may require addi tional cylinders
to be molded and cured under job conditions.
4. Perform slump tests in accordance with ASTM C143. T est the first
truck each day, and every time test cylinders are m ade. Test pumped
concrete at the hopper and at the discharge end of the hose at the
beginning of each day’s pumping operations to deter mine change in
slump.
5. Determine the air content of concrete per ASTM C173 . For concrete
required to be air-entrained, test the first truck and every 20 m 3
(25 cubic yards) thereafter each day. For concrete not required to
be air-entrained, test every 80 m 3 (100 cubic yards) at random. For
pumped concrete, initially test concrete at both th e hopper and the
discharge end of the hose to determine change in ai r content.
6. If slump or air content fall outside specified limi ts, make another
test immediately from another portion of same batch .
7. Perform unit weight tests in compliance with ASTM C 138 for normal
weight concrete and ASTM C567 for lightweight concr ete. Test the
first truck and each time cylinders are made.
8. Notify laboratory technician at batch plant of mix irregularities
and request materials and proportioning check.
9. Verify that specified mixing has been accomplished.
10. Environmental Conditions: Determine the temperature per ASTM C1064
for each truckload of concrete during hot weather a nd cold weather
concreting operations:
a. When ambient air temperature falls below 4.4 degree s C (40
degrees F), record maximum and minimum air temperat ures in each
24 hour period; record air temperature inside prote ctive
enclosure; record minimum temperature of surface of hardened
concrete.
01 45 29 - 9
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
b. When ambient air temperature rises above 29.4 degre es C (85
degrees F), record maximum and minimum air temperat ure in each 24
hour period; record minimum relative humidity; reco rd maximum
wind velocity; record maximum temperature of surfac e of hardened
concrete.
11. Inspect the reinforcing steel placement, including bar size, bar
spacing, top and bottom concrete cover, proper tie into the chairs,
and grade of steel prior to concrete placement. Sub mit detailed
report of observations.
12. Observe conveying, placement, and consolidation of concrete for
conformance to specifications.
13. Observe condition of formed surfaces upon removal o f formwork prior
to repair of surface defects and observe repair of surface defects.
14. Observe curing procedures for conformance with spec ifications,
record dates of concrete placement, start of prelim inary curing,
start of final curing, end of curing period.
15. Observe preparations for placement of concrete:
a. Inspect handling, conveying, and placing equipment, inspect
vibrating and compaction equipment.
b. Inspect preparation of construction, expansion, and isolation
joints.
16. Observe preparations for protection from hot weathe r, cold weather,
sun, and rain, and preparations for curing.
17. Observe concrete mixing:
a. Monitor and record amount of water added at project site.
b. Observe minimum and maximum mixing times.
18. Measure concrete flatwork for levelness and flatnes s as follows:
a. Perform Floor Tolerance Measurements F F and F L in accordance with
ASTM E1155. Calculate the actual overall F- numbers using the
inferior/superior area method.
b. Perform all floor tolerance measurements within 48 hours after
slab installation and prior to removal of shoring a nd formwork.
c. Provide the Contractor and the COR with the results of all
profile tests, including a running tabulation of th e overall F F
and F L values for all slabs installed to date, within 72 h ours
after each slab installation.
01 45 29 - 10
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
C. Laboratory Tests of Field Samples:
1. Test compression test cylinders for strength in acc ordance with ASTM
C39. For each test series, test one cylinder at 7 d ays and one
cylinder at 28 days. Use remaining cylinder as a sp are tested as
directed by COR. Compile laboratory test reports as follows:
Compressive strength test shall be result of one cy linder, except
when one cylinder shows evidence of improper sampli ng, molding or
testing, in which case it shall be discarded and st rength of spare
cylinder shall be used.
2. Make weight tests of hardened lightweight structura l concrete in
accordance with ASTM C567.
3. Furnish certified compression test reports (duplica te) to COR. In
test report, indicate the following information:
a. Cylinder identification number and date cast.
b. Specific location at which test samples were taken.
c. Type of concrete, slump, and percent air.
d. Compressive strength of concrete in MPa (psi).
e. Weight of lightweight structural concrete in kg/m 3 (pounds per
cubic feet).
f. Weather conditions during placing.
g. Temperature of concrete in each test cylinder when test cylinder
was molded.
h. Maximum and minimum ambient temperature during plac ing.
i. Ambient temperature when concrete sample in test cy linder was
taken.
j. Date delivered to laboratory and date tested.
3.6 REINFORCEMENT:
A. Review mill test reports furnished by Contractor.
3.7 TYPE OF TEST:
Approximate Number of Tests Required
A. Earthwork:
Laboratory Compaction Test, Soils:
(ASTM D1557) (ASTM D698) 10
Field Density, Soils (AASHTO T191, T205, or T238) 5
Penetration Test, Soils 5
01 45 29 - 11
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
B. Landscaping:
Topsoil Test 2
C. Aggregate Base:
Laboratory Compaction, (ASTM D1557) 5
Field Density, (ASTM D1556) 2
Aggregate, Base Course Gradation (AASHTO T27) 1
Wear (AASHTO T96) 1
Soundness (AASHTO T104) 1
D. Asphalt Concrete:
Field Density, (AASHTO T230 5
Aggregate, Asphalt Concrete Gradation (AASHTO T27) 2
Wear (AASHTO T96) 1
Soundness (AASHTO T104) 1
E. Concrete:
Making and Curing Concrete Test Cylinders (ASTM C31 )
Compressive Strength, Test Cylinders (ASTM C39)
4
12
Concrete Slump Test (ASTM C143) 5
Concrete Air Content Test (ASTM C173) 5
Unit Weight, Lightweight Concrete (ASTM C567) 1
Aggregate, Normal Weight: Gradation (ASTM C33) 1
Deleterious Substances (ASTM C33) 1
Soundness (ASTM C33) 1
Abrasion (ASTM C33) 1
Aggregate, Lightweight Gradation (ASTM C330) 1
Deleterious Substances (ASTM C330) 1
Unit Weight (ASTM C330) 4
Flatness and Levelness Readings (ASTM E1155) (numbe r of days) 2
L. Inspection:
Technical Personnel (Man-days) 40
01 45 29 - 12
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
- - - E N D - - -
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 57 19- 1
SECTION 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies the control of environmental pollution and damage
that the Contractor must consider for air, water, a nd land resources. It
includes management of visual aesthetics, noise, so lid waste, radiant
energy, and radioactive materials, as well as other pollutants and
resources encountered or generated by the Contracto r. The Contractor is
obligated to consider specified control measures wi th the costs included
within the various contract items of work.
B. Environmental pollution and damage is defined as th e presence of
chemical, physical, or biological elements or agent s which:
1. Adversely effect human health or welfare,
2. Unfavorably alter ecological balances of importance to human life,
3. Effect other species of importance to humankind, or ;
4. Degrade the utility of the environment for aestheti c, cultural, and
historical purposes.
C. Definitions of Pollutants:
1. Chemical Waste: Petroleum products, bituminous mate rials, salts,
acids, alkalis, herbicides, pesticides, organic che micals, and
inorganic wastes.
2. Debris: Combustible and noncombustible wastes, such as leaves, tree
trimmings, ashes, and waste materials resulting fro m construction or
maintenance and repair work.
3. Sediment: Soil and other debris that has been erode d and transported
by runoff water.
4. Solid Waste: Rubbish, debris, garbage, and other di scarded solid
materials resulting from industrial, commercial, an d agricultural
operations and from community activities.
5. Surface Discharge: The term "Surface Discharge" imp lies that the
water is discharged with possible sheeting action a nd subsequent soil
erosion may occur. Waters that are surface discharg ed may terminate
in drainage ditches, storm sewers, creeks, and/or " water of the
United States" and would require a permit to discha rge water from the
governing agency.
6. Rubbish: Combustible and noncombustible wastes such as paper, boxes,
glass and crockery, metal and lumber scrap, tin can s, and bones.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 57 19- 2
7. Sanitary Wastes:
a. Sewage: Domestic sanitary sewage and human and anim al waste.
b. Garbage: Refuse and scraps resulting from preparati on, cooking,
dispensing, and consumption of food.
1.2 QUALITY CONTROL
A. Establish and maintain quality control for the envi ronmental protection
of all items set forth herein.
B. Record on daily reports any problems in complying w ith laws,
regulations, and ordinances. Note any corrective ac tion taken.
1.3 REFERENCES
A. The publications listed below form a part of this s pecification to the
extent referenced. The publications are referred to in the text by basic
designation only.
B. U.S. National Archives and Records Administration ( NARA):
33 CFR 328..............Definitions
1.4 SUBMITTALS
A. In accordance with Section, 01 33 23, SHOP DRAWINGS , PRODUCT DATA, AND
SAMPLES, furnish the following:
1. Environmental Protection Plan: After the contract i s awarded and
prior to the commencement of the work, the Contract or shall meet with
the COR to discuss the proposed Environmental Prote ction Plan and to
develop mutual understanding relative to details of environmental
protection. Not more than 20 days after the meeting , the Contractor
shall prepare and submit to the COR for approval, a written and/or
graphic Environmental Protection Plan including, bu t not limited to,
the following:
a. Name(s) of person(s) within the Contractor's organi zation who is
(are) responsible for ensuring adherence to the Env ironmental
Protection Plan.
b. Name(s) and qualifications of person(s) responsible for
manifesting hazardous waste to be removed from the site.
c. Name(s) and qualifications of person(s) responsible for training
the Contractor's environmental protection personnel .
d. Description of the Contractor's environmental prote ction personnel
training program.
e. A list of Federal, State, and local laws, regulatio ns, and permits
concerning environmental protection, pollution cont rol, noise
control and abatement that are applicable to the Co ntractor's
proposed operations and the requirements imposed by those laws,
regulations, and permits.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 57 19- 3
f. Methods for protection of features to be preserved within
authorized work areas including trees, shrubs, vine s, grasses,
ground cover, landscape features, air and water qua lity, fish and
wildlife, soil, historical, and archeological and c ultural
resources.
g. Procedures to provide the environmental protection that comply
with the applicable laws and regulations. Describe the procedures
to correct pollution of the environment due to acci dent, natural
causes, or failure to follow the procedures as desc ribed in the
Environmental Protection Plan.
h. Permits, licenses, and the location of the solid wa ste disposal
area.
i. Drawings showing locations of any proposed temporar y excavations
or embankments for haul roads, material storage are as, structures,
sanitary facilities, and stockpiles of excess or sp oil materials.
Include as part of an Erosion Control Plan approved by the
District Office of the U.S. Soil Conservation Servi ce and the
Department of Veterans Affairs.
j. Environmental Monitoring Plans for the job site inc luding land,
water, air, and noise.
k. Work Area Plan showing the proposed activity in eac h portion of
the area and identifying the areas of limited use o r nonuse. Plan
should include measures for marking the limits of u se areas. This
plan may be incorporated within the Erosion Control Plan.
B. Approval of the Contractor's Environmental Protecti on Plan will not
relieve the Contractor of responsibility for adequa te and continued
control of pollutants and other environmental prote ction measures.
1.5 PROTECTION OF ENVIRONMENTAL RESOURCES
A. Protect environmental resources within the project boundaries and those
affected outside the limits of permanent work durin g the entire period
of this contract. Confine activities to areas defin ed by the
specifications and drawings.
B. Protection of Land Resources: Prior to construction , identify all land
resources to be preserved within the work area. Do not remove, cut,
deface, injure, or destroy land resources including trees, shrubs,
vines, grasses, top soil, and land forms without pe rmission from the
COR. Do not fasten or attach ropes, cables, or guys to trees for
anchorage unless specifically authorized, or where special emergency use
is permitted.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 57 19- 4
1. Work Area Limits: Prior to any construction, mark t he areas that
require work to be performed under this contract. M ark or fence
isolated areas within the general work area that ar e to be saved and
protected. Protect monuments, works of art, and mar kers before
construction operations begin. Convey to all person nel the purpose of
marking and protecting all necessary objects.
2. Protection of Landscape: Protect trees, shrubs, vin es, grasses, land
forms, and other landscape features shown on the dr awings to be
preserved by marking, fencing, or using any other a pproved
techniques.
a. Box and protect from damage existing trees and shru bs to remain on
the construction site.
b. Immediately repair all damage to existing trees and shrubs by
trimming, cleaning, and painting with antiseptic tr ee paint.
c. Do not store building materials or perform construc tion activities
closer to existing trees or shrubs than the farthes t extension of
their limbs.
3. Reduction of Exposure of Unprotected Erodible Soils : Plan and conduct
earthwork to minimize the duration of exposure of u nprotected soils.
Clear areas in reasonably sized increments only as needed to use.
Form earthwork to final grade as shown. Immediately protect side
slopes and back slopes upon completion of rough gra ding.
4. Temporary Protection of Disturbed Areas: Construct diversion ditches,
benches, and berms to retard and divert runoff from the construction
site to protected drainage areas approved under par agraph 208 of the
Clean Water Act.
a. Reuse or conserve the collected topsoil sediment as directed by
the COR. Topsoil use and requirements are specified in Section 31
20 00, EARTH MOVING.
5. Erosion and Sedimentation Control Devices: The eros ion and sediment
controls selected and maintained by the Contractor shall be such that
water quality standards are not violated as a resul t of the
Contractor's activities. Construct or install all t emporary and
permanent erosion and sedimentation control feature s shown on the
Erosion Control Plan. Maintain temporary erosion an d sediment control
measures such as berms, dikes, drains, sedimentatio n basins,
grassing, and mulching, until permanent drainage an d erosion control
facilities are completed and operative.
6. Protect adjacent areas from despoilment by temporar y excavations and
embankments.
01 57 19- 5
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
7. Handle and dispose of solid wastes in such a manner that will prevent
contamination of the environment. Place solid waste s (excluding
clearing debris) in containers that are emptied on a regular
schedule. Transport all solid waste off Government property and
dispose of waste in compliance with Federal, State, and local
requirements.
8. Store chemical waste away from the work areas in co rrosion resistant
containers and dispose of waste in accordance with Federal, State,
and local regulations.
9. Handle discarded materials other than those include d in the solid
waste category as directed by the COR.
C. Protection of Water Resources: Keep construction ac tivities under
surveillance, management, and control to avoid poll ution of surface and
ground waters and sewer systems. Implement manageme nt techniques to
control water pollution by the listed construction activities that are
included in this contract.
1. Washing and Curing Water: Do not allow wastewater d irectly derived
from construction activities to enter water areas. Collect and place
wastewater in retention ponds allowing the suspende d material to
settle, the pollutants to separate, or the water to evaporate.
2. Control movement of materials and equipment at stre am crossings
during construction to prevent violation of water p ollution control
standards of the Federal, State, or local governmen t.
3. Monitor water areas affected by construction.
D. Protection of Fish and Wildlife Resources: Keep con struction activities
under surveillance, management, and control to mini mize interference
with, disturbance of, or damage to fish and wildlif e. Prior to beginning
construction operations, list species that require specific attention
along with measures for their protection.
E. Protection of Air Resources: Keep construction acti vities under
surveillance, management, and control to minimize p ollution of air
resources. Burning is not permitted on the job site . Keep activities,
equipment, processes, and work operated or performe d, in strict
accordance with the State of Wisconsin and Federal emission and
performance laws and standards. Maintain ambient ai r quality standards
set by the Environmental Protection Agency, for tho se construction
operations and activities specified.
1. Particulates: Control dust particles, aerosols, and gaseous by-
products from all construction activities, processi ng, and
preparation of materials (such as from asphaltic ba tch plants) at all
01 57 19- 6
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
EARTHMOVING MATERIALS HANDLING
FRONT LOADERS 75 CONCRETE MIXERS 75
BACKHOES 75 CONCRETE PUMPS 75
DOZERS 75 CRANES 75
TRACTORS 75 DERRICKS IMPACT 75
SCAPERS 80 PILE DRIVERS 95
times, including weekends, holidays, and hours when work is not in
progress.
2. Particulates Control: Maintain all excavations, sto ckpiles, haul
roads, permanent and temporary access roads, plant sites, spoil
areas, borrow areas, and all other work areas withi n or outside the
project boundaries free from particulates which wou ld cause a hazard
or a nuisance. Sprinklering, chemical treatment of an approved type,
light bituminous treatment, baghouse, scrubbers, el ectrostatic
precipitators, or other methods are permitted to co ntrol particulates
in the work area.
3. Hydrocarbons and Carbon Monoxide: Control monoxide emissions from
equipment to Federal and State allowable limits.
4. Odors: Control odors of construction activities and prevent obnoxious
odors from occurring.
F. Reduction of Noise: Minimize noise using every acti on possible. Perform
noise-producing work in less sensitive hours of the day or week as
directed by the COR. Maintain noise-produced work a t or below the
decibel levels and within the time periods specifie d.
1. Perform construction activities involving repetitiv e, high-level
impact noise only between 8:00 a.m. and 6:00p.m unl ess otherwise
permitted by local ordinance or the COR. Repetitive impact noise on
the property shall not exceed the following dB limi tations:
Time Duration of Impact Noise Sound Level in dB
More than 12 minutes in any hour 70
Less than 30 seconds of any hour 85
Less than three minutes of any hour 80
Less than 12 minutes of any hour 75
2. Provide sound-deadening devices on equipment and ta ke noise abatement
measures that are necessary to comply with the requ irements of this
contract, consisting of, but not limited to, the fo llowing:
a. Maintain maximum permissible construction equipment noise levels
at 15 m (50 feet) (dBA):
01 57 19- 7
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
GRADERS 75 JACK HAMMERS 75
TRUCKS 75 ROCK DRILLS 80
PAVERS, STATIONARY
80 PNEUMATIC TOOLS 80
PUMPS 75 BLASTING N/A
GENERATORS 75 SAWS 75
COMPRESSORS 75 VIBRATORS 75
b. Use shields or other physical barriers to restrict noise
transmission.
c. Provide soundproof housings or enclosures for noise -producing
machinery.
d. Use efficient silencers on equipment air intakes.
e. Use efficient intake and exhaust mufflers on intern al combustion
engines that are maintained so equipment performs b elow noise
levels specified.
f. Line hoppers and storage bins with sound deadening material.
g. Conduct truck loading, unloading, and hauling opera tions so that
noise is kept to a minimum.
3. Measure sound level for noise exposure due to the c onstruction at
least once every five successive working days while work is being
performed above 55 dB(A) noise level. Measure noise exposure at the
property line or 15 m (50 feet) from the noise sour ce, whichever is
greater. Measure the sound levels on the A weighing network of a
General Purpose sound level meter at slow response. To minimize the
effect of reflective sound waves at buildings, take measurements at
900 to 1800 mm (three to six feet) in front of any building face.
Submit the recorded information to the COR noting a ny problems and
the alternatives for mitigating actions.
G. Restoration of Damaged Property: If any direct or i ndirect damage is
done to public or private property resulting from a ny act, omission,
neglect, or misconduct, the Contractor shall restor e the damaged
property to a condition equal to that existing befo re the damage at no
additional cost to the Government. Repair, rebuild, or restore property
as directed or make good such damage in an acceptab le manner.
H. Final Clean-up: On completion of project and after removal of all
debris, rubbish, and temporary construction, Contra ctor shall leave the
construction area in a clean condition satisfactory to the COR. Cleaning
shall include off the station disposal of all items and materials not
01 57 19- 8
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
required to be salvaged, as well as all debris and rubbish resulting
from demolition and new work operations.
- - - E N D - - -
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 74 19 - 1
SECTION 01 74 19 CONSTRUCTION WASTE MANAGEMENT
PART 1 – GENERAL
1.1 DESCRIPTION
A. This section specifies the requirements for the man agement of non-
hazardous building construction and demolition wast e.
B. Waste disposal in landfills shall be minimized to t he greatest extent
possible. Of the inevitable waste that is generated , as much of the
waste material as economically feasible shall be sa lvaged, recycled or
reused.
C. Contractor shall use all reasonable means to divert construction and
demolition waste from landfills and incinerators, a nd facilitate their
salvage and recycle not limited to the following:
1. Waste Management Plan development and implementatio n.
2. Techniques to minimize waste generation.
3. Sorting and separating of waste materials.
4. Salvage of existing materials and items for reuse o r resale.
5. Recycling of materials that cannot be reused or sol d.
D. At a minimum the following waste categories shall b e diverted from
landfills:
1. Soil.
2. Inerts (eg, concrete, masonry and asphalt).
3. Clean dimensional wood and palette wood.
4. Green waste (biodegradable landscaping materials).
5. Engineered wood products (plywood, particle board a nd I-joists,
etc).
6. Metal products (eg, steel, wire, beverage container s, copper, etc).
7. Cardboard, paper and packaging.
9. Plastics (eg, ABS, PVC).
1.2 RELATED WORK
A. Section 02 41 00, DEMOLITION.
B. Section 01 00 00, GENERAL REQUIREMENTS.
C. Lead Paint: Section 02 83 33.13, LEAD BASED PAINT R EMOVAL AND DISPOSAL.
1.3 QUALITY ASSURANCE
A. Contractor shall practice efficient waste managemen t when sizing,
cutting and installing building products. Processes shall be employed
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 74 19 - 2
to ensure the generation of as little waste as poss ible. Construction
Demolition waste includes products of the following :
1. Excess or unusable construction materials.
2. Packaging used for construction products.
3. Poor planning and/or layout.
4. Construction error.
5. Over ordering.
6. Weather damage.
7. Contamination.
8. Mishandling.
9. Breakage.
B. Establish and maintain the management of non-hazard ous building
construction and demolition waste set forth herein. Conduct a site
assessment to estimate the types of materials that will be generated by
demolition and construction.
C. Contractor shall develop and implement procedures t o recycle
construction and demolition waste to a minimum of 5 0 percent.
D. Contractor shall be responsible for implementation of any special
programs involving rebates or similar incentives re lated to recycling.
Any revenues or savings obtained from salvage or re cycling shall accrue
to the contractor.
E. Contractor shall provide all demolition, removal an d legal disposal of
materials. Contractor shall ensure that facilities used for recycling,
reuse and disposal shall be permitted for the inten ded use to the
extent required by local, state, federal regulation s. The Whole
Building Design Guide website http://www.wbdg.org/t ools/cwm.php
provides a Construction Waste Management Database t hat contains
information on companies that haul, collect, and pr ocess recyclable
debris from construction projects.
F. Contractor shall assign a specific area to facilita te separation of
materials for reuse, salvage, recycling, and return . Such areas are to
be kept neat and clean and clearly marked in order to avoid
contamination or mixing of materials.
G. Contractor shall provide on-site instructions and s upervision of
separation, handling, salvaging, recycling, reuse a nd return methods to
be used by all parties during waste generating stag es.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 74 19 - 3
H. Record on daily reports any problems in complying w ith laws,
regulations and ordinances with corrective action t aken.
1.4 TERMINOLOGY
A. Class III Landfill: A landfill that accepts non-haz ardous resources
such as household, commercial and industrial waste resulting from
construction, remodeling, repair and demolition ope rations.
B. Clean: Untreated and unpainted; uncontaminated with adhesives, oils,
solvents, mastics and like products.
C. Construction and Demolition Waste: Includes all non -hazardous resources
resulting from construction, remodeling, alteration s, repair and
demolition operations.
D. Dismantle: The process of parting out a building in such a way as to
preserve the usefulness of its materials and compon ents.
E. Disposal: Acceptance of solid wastes at a legally o perating facility
for the purpose of land filling (includes Class III landfills and inert
fills).
F. Inert Backfill Site: A location, other than inert f ill or other
disposal facility, to which inert materials are tak en for the purpose
of filling an excavation, shoring or other soil eng ineering operation.
G. Inert Fill: A facility that can legally accept iner t waste, such as
asphalt and concrete exclusively for the purpose of disposal.
H. Inert Solids/Inert Waste: Non-liquid solid resource s including, but not
limited to, soil and concrete that does not contain hazardous waste or
soluble pollutants at concentrations in excess of w ater-quality
objectives established by a regional water board, a nd does not contain
significant quantities of decomposable solid resour ces.
I. Mixed Debris: Loads that include commingled recycla ble and non-
recyclable materials generated at the construction site.
J. Mixed Debris Recycling Facility: A solid resource p rocessing facility
that accepts loads of mixed construction and demoli tion debris for the
purpose of recovering re-usable and recyclable mate rials and disposing
non-recyclable materials.
K. Permitted Waste Hauler: A company that holds a vali d permit to collect
and transport solid wastes from individuals or busi nesses for the
purpose of recycling or disposal.
L. Recycling: The process of sorting, cleansing, treat ing, and
reconstituting materials for the purpose of using t he altered form in
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 74 19 - 4
the manufacture of a new product. Recycling does no t include burning,
incinerating or thermally destroying solid waste.
1. On-site Recycling – Materials that are sorted and p rocessed on site
for use in an altered state in the work, i.e. concr ete crushed for
use as a sub-base in paving.
2. Off-site Recycling – Materials hauled to a location and used in an
altered form in the manufacture of new products.
M. Recycling Facility: An operation that can legally a ccept materials for
the purpose of processing the materials into an alt ered form for the
manufacture of new products. Depending on the types of materials
accepted and operating procedures, a recycling faci lity may or may not
be required to have a solid waste facilities permit or be regulated by
the local enforcement agency.
N. Reuse: Materials that are recovered for use in the same form, on-site
or off-site.
O. Return: To give back reusable items or unused produ cts to vendors for
credit.
P. Salvage: To remove waste materials from the site fo r resale or re-use
by a third party.
Q. Source-Separated Materials: Materials that are sort ed by type at the
site for the purpose of reuse and recycling.
R. Solid Waste: Materials that have been designated as non-recyclable and
are discarded for the purposes of disposal.
S. Transfer Station: A facility that can legally accep t solid waste for
the purpose of temporarily storing the materials fo r re-loading onto
other trucks and transporting them to a landfill fo r disposal, or
recovering some materials for re-use or recycling.
1.5 SUBMITTALS
A. In accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, and
SAMPLES, furnish the following:
B. Prepare and submit to the Resident Engineer a writt en demolition debris
management plan. The plan shall include, but not be limited to, the
following information:
1. Procedures to be used for debris management.
2. Techniques to be used to minimize waste generation.
3. Analysis of the estimated job site waste to be gene rated:
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 74 19 - 5
a. List of each material and quantity to be salvaged, reused,
recycled.
b. List of each material and quantity proposed to be t aken to a
landfill.
4. Detailed description of the Means/Methods to be use d for material
handling.
a. On site: Material separation, storage, protection w here
applicable.
b. Off site: Transportation means and destination. Inc lude list of
materials.
1) Description of materials to be site-separated and s elf-hauled
to designated facilities.
2) Description of mixed materials to be collected by d esignated
waste haulers and removed from the site.
c. The names and locations of mixed debris reuse and r ecycling
facilities or sites.
d. The names and locations of trash disposal landfill facilities or
sites.
e. Documentation that the facilities or sites are appr oved to
receive the materials.
C. Designated Manager responsible for instructing pers onnel, supervising,
documenting and administer over meetings relevant t o the Waste
Management Plan.
D. Monthly summary of construction and demolition debr is diversion and
disposal, quantifying all materials generated at th e work site and
disposed of or diverted from disposal through recyc ling.
1.6 APPLICABLE PUBLICATIONS
A Publications listed below form a part of this spe cification to the
extent referenced. Publications are referenced by t he basic designation
only. In the event that criteria requirements confl ict, the most
stringent requirements shall be met.
B. U.S. Green Building Council (USGBC):
LEED Green Building Rating System for New Construct ion
1.7 RECORDS
Maintain records to document the quantity of waste generated; the
quantity of waste diverted through sale, reuse, or recycling; and the
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 74 19 - 6
quantity of waste disposed by landfill or incinerat ion. Records shall
be kept in accordance with the LEED Reference Guide and LEED Template.
PART 2 - PRODUCTS
2.1 MATERIALS
A. List of each material and quantity to be salvaged, recycled, reused.
B. List of each material and quantity proposed to be t aken to a landfill.
C. Material tracking data: Receiving parties, dates re moved,
transportation costs, weight tickets, tipping fees, manifests,
invoices, net total costs or savings.
PART 3 - EXECUTION
3.1 COLLECTION
A. Provide all necessary containers, bins and storage areas to facilitate
effective waste management. VA dumpsters may be use d if available and
if approved by COR. Contractor to reimburse VA for use of such
equipment if approved.
B. Clearly identify containers, bins and storage areas so that recyclable
materials are separated from trash and can be trans ported to respective
recycling facility for processing.Submit report fro m construction and
demolition “recycle” facility. One such facility th at can/has been used
is the Wast Management C&D Recycling facility. 1070 0 West Brown Deer
Road, Milwaukee, WI, 53224. Facility will give cont ractor estimated
weight of recycled materials and approximate amount of materials that
cannot be recycles. Other facilities offering simil ar reporting and
methods can be proposed by Contractor.
C. Hazardous wastes shall be separated, stored, dispos ed of according to
local, state, federal regulations.
3.2 DISPOSAL
A. Contractor shall be responsible for transporting an d disposing of
materials that cannot be delivered to a source-sepa rated or mixed
materials recycling facility to a transfer station or disposal facility
that can accept the materials in accordance with st ate and federal
regulations.
B. Construction or demolition materials with no practi cal reuse or that
cannot be salvaged or recycled shall be disposed of at a landfill or
incinerator.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
01 74 19 - 7
3.3 REPORT
A. With each application for progress payment, submit a summary of
construction and demolition debris diversion and di sposal including
beginning and ending dates of period covered.
B. Quantify all materials diverted from landfill dispo sal through salvage
or recycling during the period with the receiving p arties, dates
removed, transportation costs, weight tickets, mani fests, invoices.
Include the net total costs or savings for each sal vaged or recycled
material.
C. Quantify all materials disposed of during the perio d with the receiving
parties, dates removed, transportation costs, weigh t tickets, tipping
fees, manifests, invoices. Include the net total co sts for each
disposal.
- - - E N D - - -
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
Introduction.
This site based Construction Waste Management Plan has been developed to manage the non-hazardous building construction and demolition waste by diverting waste from the landfills through salvaging, recycling, or reusing building materials for the Department of Veterans Affairs during construction activities. The Construction Waste Management Plan has been designed to establish records to quantify construction and demolition debris diversion and disposal. Based on the work that is scheduled to be part of the contract and the engineering practices to be implemented in conjunction with the work, every effort is being made to protect the people, assets, and the environment of the Department of Veterans Affairs.
Contents.
ORGANIZATION AND RESPONSIBILITIES Job Site Superintendent General Contractor All Other On-site Personnel Construction/Renovation Area
SITE DESCRIPTION
PERSONNEL WASTE MANAGEMENT GOALS
PLAN IMPLEMENTATION, OVERSIGHT & ENFORCEMENT
MEETINGS & COMMUNICATION
SITE ASSESSMENT DISPOSAL AND HANDLING
WASTE AUDITING PROCEDURES
WASTE MANAGEMENT DOCUMENTATION
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
Personnel Organization and Responsibilities.
This construction project has been authorized by and is under the supervision of the Department of Veterans Affairs, Milwaukee, WI. Job Site Superintendent: [Superintendent Name] will be the on-site employee responsible for the implementation and enforcement of the Construction Waste Management Plan and is so delegated by [Prime Contractor Name]. Prime Contractor: [Prime Contractor Name] will oversee the work of all construction staff and subcontractors. The Contractor will be responsible for instituting the measures as outlined in this Construction Waste Management Plan and ensuring their effectiveness. All Other On-site Personnel: All other on-site construction personnel, including all subcontractors, will be responsible for adhering to the Construction Waste Management Plan as established by [Prime Contractor Name] as well as any additional practices, laws, and regulations for ensuring a safe work environment. Construction/Renovation Area: The work will take place at the Department of Veterans Affairs Medical Center, Milwaukee Wisconsin. The main construction area is contained at the [Contract Location] as shown on the drawings.
Site Description. The worksite is an enclosed steel, concrete and masonry building structure.
Personnel. As required in Specification Section 01 74 19 Construction Waste Management: All construction workers will be aware of the Construction Waste Management Plan through the project’s Pre- Construction Meeting as well as the Project Kick-Off Meeting conducted by [Prime Contractor Name]. The meetings will consist of the information contained in this Construction Waste Management Plan, including, but not limited to; the construction limits, waste management goals, plan implementation, oversight and enforcement, meetings and communication, documentation, site assessment-expected wastes, disposal and handling, trade contractor waste management plan, waste management progress report, and work area limits, as well as the safety guidelines of the VA. Upon completing this briefing [Superintendent Name] will enforce the Construction Waste Management Plan throughout the life of the project. Weekly contractor meetings will include the Construction Waste Management Plan as well as the Environmental Protection Plan in section 01 57 19 to ensure new and all workers onsite are aware of the requirements and procedures.
Waste Management Goals.
This Construction Waste Management Plan is the responsibility of the Prime Contractor and to be enforced for all subcontractors by the Prime Contractor. By effectively managing this Construction Waste Management Plan, [Prime Contractor Name] will recycle or salvage (for reuse) all feasible materials to a minimum of 50 percent by weight.
The Waste Management Plan outlines the expected wastes to be confronted on site, means of disposal and handling methods, and required documentation. The [Prime Contractor Name]
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
will provide non hazardous waste manifest identifying weight of all waste generated per delivery (dumpster)
This Construction Waste Management Plan is in conjunction with specification section 01 74 19 Construction Waste Management.
[Prime Contractor Name] will monitor, implement, and document this plan throughout the construction of this project. Monitoring of on-site compliance with this plan will be performed by the [Prime Contractor Name] Superintendents on a daily basis. During demolition, the demolition contractor will provide one metal scrap dumpster and one mixed waste dumpster that will be used for all materials. The metal dumpster will be taken by [Demolition Subcontractor Name, Address] for recycling. The mixed waste dumpster will be taken to [Company 1 Name, address], where it will be sorted and separated for recycling. Any non-recyclable material will be sent to landfill. Recyclable material will be weighed and recorded by [Company 1 Name, address]. During reconstruction there will be one dumpster provided for mixed waste. The mixed waste dumpster will be taken to [Company 2 Name], where it will be sorted and separated for recycling. Records will be provided in accordance with LEED Reference Guide and LEED Template. The reports will be submitted monthly.
Meetings and Communication.
Each and every trade contractor and subcontractor will be required to attend a Pre-Construction Meeting and Project Kick-Off Meeting. New construction personnel that are unable to attend are required to attend a brief safety meeting that will include a construction waste training session before being allowed to work on the site. Further, the Demolition Debris Management Plan will be on the agenda at regular construction meetings to update the project team on the status of [Prime Contractor Name] goals for diverted waste and what measures may need to be implemented if these goals are not being met.
SITE ASSESSMENT- DISPOSAL & HANDLING
Contractor to provide dumpsters for processing recyclables and waste; Examples are: 1) Concrete materials; 2) Metal; 3) mixed waste All of these to be sorted at landfill site or recycling facility.
Upon approval, [Prime Contractor Name] will use the VA-provided cardboard dumpster for all cardboard materials.
The following table lists expected wastes on this project, their disposal method, and handling procedures:
Hauler: [Company Name, Contact, Address]
Recycling:
[Company Name, Contact, Address]
Item Disposal method Handling Procedure Destination/Recipient
Masonry Recycle Place in concrete
dumpster
ACME WASTE, INC.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
Concrete Recycle Place in concrete
dumpster
ACME WASTE, INC.
Scrap Metals Recycle Place in Metal
dumpster
ACME WASTE, INC.
Cardboard Recycle or reuse Minimal packaging
where possible, or place
in cardboard dumpster
VA-provided cardboard
dumpster (permission
required)
Drywall Recycle Place in mixed
dumpster
ACME WASTE, INC.
Wood (clean) Recycle Place in mixed
dumpster
ACME WASTE, INC.
Plumbing Fixtures Recycle Place in mixed
dumpster
ACME WASTE, INC.
Glass Recycle Place in mixed
dumpster
ACME WASTE, INC.
Plastics
(noncontaminated)
Recycle Place in mixed
dumpster
ACME WASTE, INC.
Plastics (contaminated) Landfill Place in mixed
dumpster
ACME WASTE, INC.
Ceiling Tile Recycle Place in mixed
dumpster
ACME WASTE, INC.
Wiring Recycle/Salvage Electrician will reuse or
recycle
[Trade Subcontractor
Name]
Light Fixtures Recycle/Salvage Electrician will reuse,
salvage, or recycle
[Trade Subcontractor
Name]
Lamps (Universal
Waste)
Recycle/Salvage Electrician will reuse,
salvage, or recycle
[Trade Subcontractor
Name]
Ballasts Recycle/Salvage Electrician will reuse,
salvage, or recycle
[Trade Subcontractor
Name]
Carpet Recycle Carpet Subcontractor
place in mixed
dumpster or recycle
[Company Name]
Inerts Recycle Place in Concrete
Dumpster
[Company Name]
Soil Reuse Reuse throughout
project
[Contractor Name]
All Other Wastes Landfill Reduce waste where
possible, research
recycling or reuse
opportunities
[Company Name]
Waste Auditing. All subcontractors are responsible for daily site cleanup and ensuring that all recycling containers are kept free of contamination. [Prime Contractor Name] representatives shall be responsible for daily checks of trash and recycling containers to check for and ensure the
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
removal of contamination. Violators will be required to re-sort any misplaced waste and, if the problem continues, pay the cost of [Prime Contractor Name] time to sort recyclables from the trash. [Prime Contractor Name] representatives shall be responsible for contacting haulers for collection service.
Documentation. Documentation of the waste management plan will consist of the following:
1. Records will be provided in accordance with LEED Reference Guide and LEED Template. 2. Records will include the amount of material salvaged, recycled and re-used. 3. Records will include a list of materials taken to the landfill. 4. Material tracking data shall be provided indicating receiving parties, dates, weight tickets, tipping fees, manifests and the total resulting cost or savings.
The quantities in the report will be updated by [Prime Contractor Name] based on information provided by each Trade Contractor and the independent hauler under contract to provide the metal dumpsters. Each Trade Contractor shall be responsible for providing the following documentation for any waste generated on site that is not deposited in the dumpsters provided by [Prime Contractor Name].
1. A record of the type and quantity (by weight) of each material salvaged, reused, recycled, or disposed in a manner other than that provided by [Prime Contractor Name] through their independent hauler. 2. Disposal receipts: Provide copies of all receipts issued by a disposal facility for CDL waste that is disposed in a landfill. 3. Recycling Receipts: Provide copies of all receipts issued by an approved recycling facility. 4. Salvaged materials document: types and quantities (by weight) for materials salvaged for reuse on site, sold, or donated to a third party.
This documentation will then be compiled by [Prime Contractor Name] in monthly waste tracking reports.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
02 41 00 - 1
SECTION 02 41 00 DEMOLITION
PART 1 - GENERAL
1.1 DESCRIPTION:
This section specifies demolition and removal of bu ildings, portions of
buildings, utilities, other structures and debris f rom trash dumps
shown.
1.2 RELATED WORK:
A. Demolition and removal of roads, walks, curbs, and on-grade slabs
outside buildings to be demolished: Section 31 20 0 0, EARTHWORK Section
31 20 11.
B. Safety Requirements: Section 01 35 26 Safety Requir ements Article,
ACCIDENT PREVENTION PLAN (APP).
C. Disconnecting utility services prior to demolition: Section 01 00 00,
GENERAL REQUIREMENTS.
D. Reserved items that are to remain the property of t he Government:
Section 01 00 00, GENERAL REQUIREMENTS.
G. Environmental Protection: Section 01 57 19, TEMPORA RY ENVIRONMENTAL
CONTROLS.
H. Construction Waste Management: Section 017419 CONST RUCTION WASTE
MANAGEMENT.
I. Infectious Control: Section 01 00 00, GENERAL REQUI REMENTS, Article
1.7, INFECTION PREVENTION MEASURES.
1.3 PROTECTION:
A. Perform demolition in such manner as to eliminate h azards to persons
and property; to minimize interference with use of adjacent areas,
utilities and structures or interruption of use of such utilities; and
to provide free passage to and from such adjacent a reas of structures.
Comply with requirements of GENERAL CONDITIONS Arti cle, ACCIDENT
PREVENTION.
B. Provide safeguards, including warning signs, barric ades, temporary
fences, warning lights, and other similar items tha t are required for
protection of all personnel during demolition and r emoval operations.
Comply with requirements of Section 01 00 00, GENER AL REQUIREMENTS,
Article PROTECTION OF EXISTING VEGETATION, STRUCTUR ES, EQUIPMENT,
UTILITIES AND IMPROVEMENTS.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
02 41 00 - 2
C. Maintain fences, barricades, lights, and other simi lar items around
exposed excavations until such excavations have bee n completely filled.
D. Provide enclosed dust chutes with control gates fro m each floor to
carry debris to truck beds and govern flow of mater ial into truck.
Provide overhead bridges of tight board or prefabri cated metal
construction at dust chutes to protect persons and property from
falling debris.
E. Prevent spread of flying particles and dust. Sprink le rubbish and
debris with water to keep dust to a minimum. Do not use water if it
results in hazardous or objectionable condition suc h as, but not
limited to; ice, flooding, or pollution. Vacuum and dust the work area
daily.
F. In addition to previously listed fire and safety ru les to be observed
in performance of work, include following:
1. No wall or part of wall shall be permitted to fall outwardly from
structures.
2. Maintain at least one stairway in each structure in usable condition
to highest remaining floor. Keep stairway free of o bstructions and
debris until that level of structure has been remov ed.
3. Wherever a cutting torch or other equipment that mi ght cause a fire
is used, provide and maintain fire extinguishers ne arby ready for
immediate use. Instruct all possible users in use o f fire
extinguishers.
4. Keep hydrants clear and accessible at all times. Pr ohibit debris
from accumulating within a radius of 4500 mm (15 fe et) of fire
hydrants.
G. Before beginning any demolition work, the Contracto r shall survey the
site and examine the drawings and specifications to determine the
extent of the work. The contractor shall take neces sary precautions to
avoid damages to existing items to remain in place, to be reused, or to
remain the property of the Medical Center; any dama ged items shall be
repaired or replaced as approved by the COR. The Co ntractor shall
coordinate the work of this section with all other work and shall
construct and maintain shoring, bracing, and suppor ts as required. The
Contractor shall ensure that structural elements ar e not overloaded and
shall be responsible for increasing structural supp orts or adding new
supports as may be required as a result of any cutt ing, removal, or
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
02 41 00 - 3
demolition work performed under this contract. Do n ot overload
structural elements. Provide new supports and reinf orcement for
existing construction weakened by demolition or rem oval works. Repairs,
reinforcement, or structural replacement must have COR’s approval.
H. The work shall comply with the requirements of Sect ion 01 57 19,
TEMPORARY ENVIRONMENTAL CONTROLS.
I. The work shall comply with the requirements of Sect ion 01 00 00,
GENERAL REQUIREMENTS, Article 1.7 INFECTION PREVENT ION MEASURES.
1.4 UTILITY SERVICES:
A. Demolish and remove outside utility service lines s hown to be removed.
B. Remove abandoned outside utility lines that would i nterfere with
installation of new utility lines and new construct ion.
PART 2 - PRODUCTS (NOT USED)
PART 3 – EXECUTION
3.1 DEMOLITION:
A. Completely demolish and remove buildings and struct ures, including all
appurtenances related or connected thereto, as note d below:
1. As required for installation of new utility service lines.
2. To full depth within an area defined by hypothetica l lines located
1500 mm (5 feet) outside building lines of new stru ctures.
B. Debris, including brick, concrete, stone, metals an d similar materials
shall become property of Contractor and shall be di sposed of by him
daily, off the Medical Center to avoid accumulation at the demolition
site. Materials that cannot be removed daily shall be stored in areas
specified by the COR. Break up concrete slabs below grade that do not
require removal from present location into pieces n ot exceeding 600 mm
(24 inches) square to permit drainage. Contractor s hall dispose debris
in compliance with applicable federal, state or loc al permits, rules
and/or regulations.
C. In removing buildings and structures of more than t wo stories, demolish
work story by story starting at highest level and p rogressing down to
third floor level. Demolition of first and second s tories may proceed
simultaneously.
D. Remove and legally dispose of all materials, other than earth to remain
as part of project work, from any trash dumps shown . Materials removed
shall become property of contractor and shall be di sposed of in
compliance with applicable federal, state or local permits, rules
02 41 00 - 4
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
and/or regulations. All materials in the indicated trash dump areas,
including above surrounding grade and extending to a depth of 1500mm
(5feet) below surrounding grade, shall be included as part of the lump
sum compensation for the work of this section. Mate rials that are
located beneath the surface of the surrounding grou nd more than 1500 mm
(5 feet), or materials that are discovered to be ha zardous, shall be
handled as unforeseen. The removal of hazardous mat erial shall be
referred to Hazardous Materials specifications.
E. Remove existing utilities as indicated or uncovered by work and
terminate in a manner conforming to the nationally recognized code
covering the specific utility and approved by the C OR. When Utility
lines are encountered that are not indicated on the drawings, the COR
shall be notified prior to further work in that are a.
3.2 CLEAN-UP:
On completion of work of this section and after rem oval of all debris,
leave site in clean condition satisfactory to COR. Clean-up shall
include off the Medical Center disposal of all item s and materials not
required to remain property of the Government as we ll as all debris and
rubbish resulting from demolition operations.
- - - E N D - - -
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
02 42 00-1
SECTION 02 42 00
CUTTING, REMOVAL, DEMOLITION, RESTORATION AND PATCHING
PART 1 GENERAL
1.1 SCOPE:
A. Refer to SECTION 01 00 00 for special requirements, protection,
constraints, timing of work, scheduling of work, en closures and
similar requirements relating to this section.
B. This section covers cutting, demolition, removal wo rk, patching,
leveling and restoration work as necessary to accom plish and
complete all work under this contract, including an y relocation
or reuse of existing materials, equipment, systems, or other
work, as well as the disposition of salvaged materi als or debris.
This Section applies to all work under this contrac t, including
general construction, mechanical and electrical wor k.
C. Contractor and his subcontractors shall examine the spaces/work
site themselves to determine the actual conditions and
requirements. All removals, demolition, cutting, re storation,
new installations and other work shall be accomplis hed to
transform the existing spaces and conditions to the new
conditions required under the Contract, as well as to accomplish
all tie-in work of new to existing.
D. It is the intent that, unless specifically shown on the
schedules, or is inherent in the work to be accompl ished under
the general construction work of the area, that eac h contractor
shall perform the demolition, cutting, removals, re locations,
patching and leveling, and restoration as will be r equired to
accomplish the work under their contracts. All work indicated on
the schedules shall be accomplished by the General Contractor.
E. Except for general demolition of entire areas, it i s the intent
that at each area or space the contractor and each subcontractor
shall make removals, perform cutting or demolition and accomplish
relocations of work normal to his trade (i.e., Mech anical
Contractor removes or relocates piping, ductwork an d similar. At
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
02 42 00-2
areas of general demolition of entire area spaces, the Mechanical
Contractor shall make removals normal to their trad e or may be
called for, for reuse or relocation, make any reloc ations and
cutoffs, terminate, or otherwise discontinue servic es that will
be abandoned, shall be removed to the nearest activ e main. The
general contractor shall then demolish or remove al l unwanted
electrical or mechanical materials, items or elemen ts in the
area.
F. Contractor is required to restore all finishes, sur faces, items,
& materials as required to accommodate new finishes . For
example, if wall paper, vinyl wall covering, cerami c wall tile,
etc. is existing on wall, and new wall finish calls for wall to
be painted, contractor is required to remove existi ng wall paper,
vinyl wall covering, ceramic wall tile, etc. to acc ommodate new
painted finish. These surfaces are required to be v erified prior
to bid, as no change to contract will be provided a fter award if
existing finishes are clearly present.
PART 2: MATERIALS
2.1 SALVAGEABLE MATERIALS TO BE STORED BY OWNER (VA):
A. The owner shall mark or tag existing materials, equ ipment or
other items that are to be retained during a pre-de molition walk
through. Salvageable materials and items designated or marked to
remain the property of the government shall be care fully removed
by applicable trades, protected from damage and sto red adjacent
to the removal area as directed.
B. Consult the Project Manager concerning any possible salvageable
items prior to demolition thereof. Carefully remove and salvage
any materials designated to be retained.
C. Any materials not wanted by the government shall be removed from
the site by the contractor, without additional cost to the
government.
D. Removal from the area and the site to the governmen t’s storage
area shall be by the contractor.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
02 42 00-3
PART 3 EXECUTION: 3.1 TEMPORARY PROTECTION:
A. Provide temporary bracing, shoring, needling and su pport during
demolition, cutting, remodeling and related new con struction
necessary for the execution of the work and the pro tection of
persons and property. Perform all work with appropr iate
supports, protection and methods to prevent collaps e, settling or
damage to property or persons. Provide adequate sup ports for the
loads to be carried, with loads properly distribute d, and
including to lower levels and sound bearing, if nec essary.
B Provide protective covering and enclosures necess ary to prevent
damage to existing spaces and materials to remain.
C. Provide dust proof temporary enclosures (includi ng above
ceilings) separating areas under demolition and rem odeling from
the remainder of the buildings as well as temporary filters at
ductwork. If work produces fumes or odors that impa ct patient
care or staff operations, granulated active carbon filters shall
be provided for all HVAC intake units where operati ons provide
these odors or fumes. Provide temporary hinged door s in
temporary enclosures where necessary.Temporary and permanent
doors shall be completely sealed with tape or other suitable
material during demolition work and shall remain se aled until
dust has settled.
3.2 MECHANICAL AND ELECTRICAL WORK EXPOSED
A. Where unknown mechanical piping, ductwork or electr ical conduit
is exposed during removal of partitions, walls, flo ors and
ceilings, the removal or re-routing shall be by the Mechanical or
Electrical Contractor as applicable. The contractor is to
provide at minimum labor and materials required for one
journeyman electrician or plumber 40-manhours to re locate these
utilities. Re-routed piping shall be located where directed and
shall be re-connected to maintain all functions in proper
operation. Abandoned piping may be left in place wh ere it is
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
02 42 00-4
disconnected from its source and capped or as direc ted by Project
Manager. There shall be no"dead end" water, sewer, medical gas,
or vent piping existing in the completed work.
B. Removals, capping or otherwise terminating services which are
abandoned or need to be abandoned, shall be accompl ished without
additional cost to the government, whether shown or noted on
drawings or otherwise encountered.
C. Contractor is to remove all old abandoned oval pneu matic tube
lines, transfer boxes, and related equipment and co mponents
exposed within the construction area. The contracto r is to
provide at minimum labor and materials required for one
electrician or laborer 40-manhours for removal.
3.3 WORK OF EACH CONTRACT
A. The contractor and each subcontractor shall careful ly review the
contract documents, including those primarily for o ther trades,
with respect to the coordination of demolition, rem oval and
remodeling work and perform such removals normal to their
respective trade as may be shown, noted, or otherwi se required.
Cutting and patching incidental to demolition, remo val and/or
remodeling of general construction work shall be co nstrued as the
work of the general contractor when shown or indica ted on the
general construction drawings or schedules or speci fically noted
or called for on documents primarily for other trad es as being
accomplished by the general contractor. Other contr actors shall
perform such other cutting, demolition, patching, r eplacement and
restoration as may be required to accomplish their part of the
work.
3.4 PAINTING
A. Any painting to match adjacent or surrounding areas . 3.5 LEVELING OF FLOORS
A. Contractor shall submit for approval - brand of lat ex, floor
leveler to be used. Leveler shall include additive for
02 42 00-5
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
waterproofing. 3.6 PATCHING
A. Contractor shall be responsible for all patching re quired as a
result of installation of new work.
B. Contractor shall furnish all related components, tr ims, etc.
required to complete the work.
- - - END- - -
Milwaukee VAMC Upgrade and Replace Building 123
February 15, 2017 Bid Set Submission
03 30 00 - 1
Steam Line Piping and Insulation Project No. 695-17 -103
SECTION 03 30 00 CAST-IN-PLACE CONCRETE
PART 1 - GENERAL
1.1 DESCRIPTION:
This section specifies cast-in-place structural con crete and materials
and mixes for other concrete.
1.2 RELATED WORK:
A. Materials testing and inspection during constructio n: Section 01 45 29,
TESTING LABORATORY SERVICES.
B. Concrete roads, walks, and similar exterior site wo rk: Section 32 05
23, CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS.
1.3 TESTING AGENCY FOR CONCRETE MIX DESIGN:
A. Testing agency for the trial concrete mix design re tained and
reimbursed by the Contractor and approved by Contra cting Officer’s
Representative (COR). For all other testing, refer to Section 01 45 29
Testing Laboratory Services.
B. Testing agency maintaining active participation in Program of Cement
and Concrete Reference Laboratory (CCRL) of Nationa l Institute of
Standards and Technology.
C. Testing agency shall furnish equipment and qualifie d technicians to
establish proportions of ingredients for concrete m ixes.
1.4 TOLERANCES:
A. Formwork: ACI 117, except the elevation tolerance o f formed surfaces
before removal of shores is +0 mm (+0 inch) and -20 mm (-3/4 inch).
B. Reinforcement Fabricating and Placing: ACI 117, exc ept that fabrication
tolerance for bar sizes Nos. 10, 13, and 16 (Nos. 3 , 4, and 5)
(Tolerance Symbol 1 in Fig. 2.1(a), ACI, 117) used as column ties or
stirrups is +0 mm (+0 inch) and -13 mm (-1/2 inch) where gross bar
length is less than 3600 mm (12 feet), or +0 mm (+0 inch) and -20 mm (-
3/4 inch) where gross bar length is 3600 mm (12 fee t) or more.
C. Cross-Sectional Dimension: ACI 117, except toleranc e for thickness of
slabs 12 inches or less is +20 mm (+3/4 inch) and - 6 mm (-1/4 inch).
Tolerance of thickness of beams more than 300 mm (1 2 inch) but less
than 900 mm (3 feet) is +20 mm (+3/4 inch) and -10 mm (-3/8 inch).
D. Slab Finishes: ACI 117, Section 4.5.6, F-number met hod in accordance
with ASTM E1155, except as follows:
03 30 00 - 2
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
1. Test entire slab surface, including those areas wit hin 600 mm (2
feet) of construction joints and vertical elements that project
through slab surface.
2. Maximum elevation change which may occur within 600 mm (2 feet) of
any column or wall element is 6 mm (0.25 inches).
3. Allow sample measurement lines that are perpendicul ar to
construction joints to extend past joint into previ ous placement no
further than 1500 mm (5 feet).
1.5 REGULATORY REQUIREMENTS:
A. ACI SP-66 – ACI Detailing Manual.
B. ACI 318 - Building Code Requirements for Reinforced Concrete.
C. ACI 301 – Standard Specifications for Structural Co ncrete.
1.6 SUBMITTALS:
A. Submit in accordance with Section 01 33 23, SHOP DR AWINGS, PRODUCT
DATA, and SAMPLES.
B. Shop Drawings: Reinforcing steel: Complete shop dra wings that detail
fabrication, bending, and placement. Include bar si zes, lengths,
material, grade, bar schedules, stirrup spacing, be nt bar diagrams, bar
arrangements, tie spacing, hoop spacing, and suppor ts.
C. Mill Test Reports:
1. Reinforcing Steel.
2. Cement.
D. Manufacturer's Certificates:
1. Abrasive aggregate.
2. Lightweight aggregate for structural concrete.
3. Air-entraining admixture.
4. Chemical admixtures, including chloride ion content .
5. Waterproof paper for curing concrete.
6. Liquid membrane-forming compounds for curing concre te.
7. Non-shrinking grout.
8. Liquid hardener.
9. Waterstops.
10. Expansion joint filler.
11. Adhesive binder.
E. Testing Agency for Concrete Mix Design: Approval re quest including
qualifications of principals and technicians and ev idence of active
03 30 00 - 3
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
participation in program of Cement and Concrete Ref erence Laboratory
(CCRL) of National Institute of Standards and Techn ology.
F. Test Report for Concrete Mix Designs: Trial mixes i ncluding
water-cement fly ash ratio curves, concrete mix ing redients, and
admixtures.
G. Shoring and Reshoring Sequence: Submit for approval a shoring and
reshoring sequence for flat slab/flat plate portion s, prepared by a
registered Professional Engineer. As a minimum, inc lude timing of form
stripping, reshoring, number of floors to be re-sho red and timing of
re-shore removal to serve as an initial outline of procedures subject
to modification as construction progresses. Submit revisions to
sequence, whether initiated by COR (see FORMWORK) o r Contractor.
H. Test reports on splitting tensile strength (Fct) of lightweight
concrete.
1.7 DELIVERY, STORAGE, AND HANDLING:
A. Conform to ACI 304. Store aggregate separately for each kind or grade,
to prevent segregation of sizes and avoid inclusion of dirt and other
materials.
B. Deliver cement in original sealed containers bearin g name of brand and
manufacturer, and marked with net weight of content s. Store in suitable
watertight building in which floor is raised at lea st 300 mm (1 foot)
above ground. Store bulk cement and fly ash in sepa rate suitable bins.
C. Deliver other packaged materials for use in concret e in original sealed
containers, plainly marked with manufacturer's name and brand, and
protect from damage until used.
1.8 PRE-CONCRETE CONFERENCE:
A. General: At least 15 days prior to submittal of des ign mixes, conduct a
meeting to review proposed methods of concrete cons truction to achieve
the required results.
B. Agenda: Includes but is not limited to:
1. Submittals.
2. Coordination of work.
3. Availability of material.
4. Concrete mix design including admixtures.
5. Methods of placing, finishing, and curing.
6. Finish criteria required to obtain required flatnes s and levelness.
03 30 00 - 4
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
7. Timing of floor finish measurements.
8. Material inspection and testing.
C. Attendees: Include but not limited to representativ es of Contractor;
subcontractors involved in supplying, conveying, pl acing, finishing,
and curing concrete; lightweight aggregate manufact urer; admixture
manufacturers; COR; Consulting Engineer; Department of Veterans Affairs
retained testing laboratories for concrete testing and finish (F-
number) verification.
D. Minutes of the meeting: Contractor shall take minut es and type and
distribute the minutes to attendees within five day s of the meeting.
1.9 APPLICABLE PUBLICATIONS:
A. Publications listed below form a part of this speci fication to extent
referenced. Publications are referenced in text by basic designation
only.
B. American Concrete Institute (ACI):
117-10..................Specifications for Toleranc es for Concrete
Construction and Materials and Commentary
211.1-91(R2009).........Standard Practice for Selec ting Proportions for
Normal, Heavyweight, and Mass Concrete
211.2-98(R2004).........Standard Practice for Selec ting Proportions for
Structural Lightweight Concrete
214R-11.................Guide to Evaluation of Stre ngth Test Results of
Concrete
301-10..................Standard Practice for Struc tural Concrete
304R-00(R2009)..........Guide for Measuring, Mixing , Transporting, and
Placing Concrete
305.1-06................Specification for Hot Weath er Concreting 306.1-
90(R2002).........Standard Specification for Cold W eather
Concreting
308.1-11................Specification for Curing Co ncrete
309R-05.................Guide for Consolidation of Concrete
318-11..................Building Code Requirements for Structural
Concrete and Commentary
347-04..................Guide to Formwork for Concr ete
SP-66-04................ACI Detailing Manual
03 30 00 - 5
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
C. American National Standards Institute and American Hardboard
Association (ANSI/AHA):
A135.4-2004.............Basic Hardboard
D. American Society for Testing and Materials (ASTM):
A82/A82M-07.............Standard Specification for Steel Wire, Plain,
for Concrete Reinforcement
A185/185M-07............Standard Specification for Steel Welded Wire
Reinforcement, Plain, for Concrete
A615/A615M-09...........Standard Specification for Deformed and Plain
Carbon Steel Bars for Concrete Reinforcement
A653/A653M-11...........Standard Specification for Steel Sheet, Zinc
Coated (Galvanized) or Zinc Iron Alloy Coated
(Galvannealed) by the Hot Dip Process
A706/A706M-09...........Standard Specification for Low Alloy Steel
Deformed and Plain Bars for Concrete
Reinforcement
A767/A767M-09...........Standard Specification for Zinc Coated
(Galvanized) Steel Bars for Concrete
Reinforcement
A775/A775M-07...........Standard Specification for Epoxy Coated
Reinforcing Steel Bars
A820-11.................Standard Specification for Steel Fibers for
Fiber Reinforced Concrete
A996/A996M-09...........Standard Specification for Rail Steel and Axle
Steel Deformed Bars for Concrete Reinforcement
C31/C31M-10.............Standard Practice for Makin g and Curing
Concrete Test Specimens in the field
C33/C33M-11A............Standard Specification for Concrete Aggregates
C39/C39M-12.............Standard Test Method for Co mpressive Strength
of Cylindrical Concrete Specimens
C94/C94M-12.............Standard Specification for Ready Mixed Concrete
C143/C143M-10...........Standard Test Method for Sl ump of Hydraulic
Cement Concrete
C150-11.................Standard Specification for Portland Cement C171-
07.................Standard Specification for Sheet Materials for
Curing Concrete
03 30 00 - 6
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
C172-10.................Standard Practice for Sampl ing Freshly Mixed
Concrete
C173-10.................Standard Test Method for Ai r Content of Freshly
Mixed Concrete by the Volumetric Method
C192/C192M-07...........Standard Practice for Makin g and Curing
Concrete Test Specimens in the Laboratory
C231-10.................Standard Test Method for Ai r Content of Freshly
Mixed Concrete by the Pressure Method C260-
10.................Standard Specification for Air E ntraining
Admixtures for Concrete
C309-11.................Standard Specification for Liquid Membrane
Forming Compounds for Curing Concrete
C330-09.................Standard Specification for Lightweight
Aggregates for Structural Concrete
C494/C494M-11...........Standard Specification for Chemical Admixtures
for Concrete
C618-12.................Standard Specification for Coal Fly Ash and Raw
or Calcined Natural Pozzolan for Use in
Concrete
C666/C666M-03(R2008)....Standard Test Method for Re sistance of Concrete
to Rapid Freezing and Thawing
C881/C881M-10...........Standard Specification for Epoxy Resin Base
Bonding Systems for Concrete
C1107/1107M-11..........Standard Specification for Packaged Dry,
Hydraulic-Cement Grout (Non-shrink)
C1315-11................Standard Specification for Liquid Membrane
Forming Compounds Having Special Properties for
Curing and Sealing Concrete
D6-95(R2011)............Standard Test Method for Lo ss on Heating of Oil
and Asphaltic Compounds
D297-93(R2006)..........Standard Methods for Rubber Products Chemical
Analysis
D412—06AE2..............Standard Test Methods for V ulcanized Rubber and
Thermoplastic Elastomers - Tension
D1751-04(R2008).........Standard Specification for Preformed Expansion
Joint Filler for Concrete Paving and Structural
03 30 00 - 7
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
Construction (Non-extruding and Resilient
Bituminous Types)
D4263-83(2012)..........Standard Test Method for In dicating Moisture in
Concrete by the Plastic Sheet Method.
D4397-10................Standard Specification for Polyethylene
Sheeting for Construction, Industrial and
Agricultural Applications
E1155-96(R2008).........Standard Test Method for De termining F F Floor
Flatness and F L Floor Levelness Numbers F1869-
11................Standard Test Method for Measurin g Moisture
Vapor Emission Rate of Concrete Subfloor Using
Anhydrous Calcium Chloride.
E. American Welding Society (AWS):
D1.4/D1.4M-11...........Structural Welding Code - R einforcing Steel
F. Concrete Reinforcing Steel Institute (CRSI):
Handbook 2008
H. U. S. Department of Commerce Product Standard (PS):
PS 1....................Construction and Industrial Plywood
PS 20...................American Softwood Lumber
I. U. S. Army Corps of Engineers Handbook for Concrete and Cement:
CRD C513................Rubber Waterstops
CRD C572................Polyvinyl Chloride Watersto ps
PART 2 – PRODUCTS:
2.1 FORMS:
A. Wood: PS 20 free from loose knots and suitable to f acilitate finishing
concrete surface specified; tongue and grooved.
B. Plywood: PS-1 Exterior Grade B-B (concrete-form) 16 mm (5/8 inch), or
20 mm (3/4 inch) thick for unlined contact form. B- B High Density
Concrete Form Overlay optional.
C. Corrugated Fiberboard Void Boxes: Double faced, com pletely impregnated
with paraffin and laminated with moisture resistant adhesive, size as
shown. Design forms to support not less than 48 KPa (1000 psf) and not
lose more than 15 percent of their original strengt h after being
completely submerged in water for 24 hours and then air dried.
D. Form Lining:
1. Hardboard: ANSI/AHA A135.4, Class 2 with one (S1S) smooth side)
03 30 00 - 8
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
2. Plywood: Grade B-B Exterior (concrete-form) not les s than 6 mm (1/4
inch) thick.
3. Plastic, fiberglass, or elastomeric capable of repr oducing the
desired pattern or texture.
E. Concrete products shall comply with following stand ards for biobased
materials:
Material Type Percent by Weight
Concrete Penetrating Liquid 79 percent biobased mat erial
Concrete form Release Agent 87 percent biobased mat erial
Concrete Sealer 11 percent biobased material
The minimum-content standards are based on the weig ht (not the volume)
of the material.
F. Form Ties: Develop a minimum working strength of 13 .35 kN (3000 pounds)
when fully assembled. Ties shall be adjustable in l ength to permit
tightening of forms and not have any lugs, cones, w ashers to act as
spreader within form, nor leave a hole larger than 20 mm (3/4 inch)
diameter, or a depression in exposed concrete surfa ce, or leave metal
closer than 40 mm (1 1/2 inches) to concrete surfac e. Wire ties not
permitted. Cutting ties back from concrete face not permitted.
G. Chamfer strips: Wood, metal, PVC, or rubber strips, ¾ by ¾ inch,
minimum.
2.2 MATERIALS:
A. Portland Cement: ASTM C150 Type I or II.
B. Fly Ash: ASTM C618, Class C or F including suppleme ntary optional
requirements relating to reactive aggregates and al kalies, and loss on
ignition (LOI) not to exceed 5 percent.
C. Coarse Aggregate: ASTM C33.
1. Size 67 or Size 467 may be used for footings and wa lls over 300 mm
(12 inches) thick.
3. Maximum size of coarse aggregates not more than one-fifth of
narrowest dimension between sides of forms, one-thi rd of depth of
slabs,three-fourth of minimum clear spacing between reinforcing
bars, nor 0.75 inches.
D. Lightweight Aggregates for Structural Concrete: AST M C330, Table 1.
Maximum size of aggregate not larger than one-fifth of narrowest
03 30 00 - 9
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
dimension between forms, nor three-fourth of minimu m clear distance
between reinforcing bars. Contractor to furnish cer tified report to
verify that aggregate is sound and durable, and has a durability factor
of not less than 80 based on 300 cycles of freezing and thawing when
tested in accordance with ASTM C666.
E. Fine Aggregate: ASTM C33. Fine aggregate for applie d concrete floor
topping shall pass a 4.75 mm (No. 4) sieve, 10 perc ent maximum shall
pass a 150 µm (No. 100) sieve.
F. Mixing Water: Fresh, clean, and potable.
G. Admixtures:
1. Water Reducing Admixture: ASTM C494, Type A and not contain more
chloride ions than are present in municipal drinkin g water.
2. Water Reducing, Retarding Admixture: ASTM C494, Typ e D and not
contain more chloride ions than are present in muni cipal drinking
water.
3. High-Range Water-Reducing Admixture (Superplasticiz er): ASTM C494,
Type F or G, and not contain more chloride ions tha n are present in
municipal drinking water.
4. Non-Corrosive, Non-Chloride Accelerator: ASTM C494, Type C or E, and
not contain more chloride ions than are present in municipal
drinking water. Admixture manufacturer must have lo ng-term non-
corrosive test data from an independent testing lab oratory of at
least one year duration using an acceptable acceler ated corrosion
test method such as that using electrical potential measures.
5. Air Entraining Admixture: ASTM C260.
6. Microsilica: Use only with prior review and accepta nce of the COR.
Use only in conjunction with high range water reduc er.
7. Calcium Nitrite corrosion inhibitor: ASTM C494 Type C.
8. Cementitious Crystalline Concrete Waterproofing Adm ixture: Xypex C-
1000/C-100 NF or approved equal.
9. Prohibited Admixtures: Calcium chloride, thiocyanat e or admixtures
containing more than 0.05 percent chloride ions are not permitted.
10. Certification: Written conformance to the requireme nts above and
the chloride ion content of the admixture prior to mix design
review.
H. Vapor Barrier: ASTM D4397, 0.25 mm (10 mil) or 0.38 mm (15 mil).
03 30 00 - 10
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
I. Reinforcing Steel: ASTM A615, or ASTM A996, deforme d, grade 60. All
reinforcing to be epoxy coated per note M in this s ection.
J. Welded Wire Fabric: ASTM A185. All reinforcing to b e epoxy coated per
note M in this section.
K. Reinforcing Bars to be Welded: ASTM A706.
L. Galvanized Reinforcing Bars: ASTM A767.
M. Epoxy Coated Reinforcing Bars: ASTM A775, with less than 2 percent
damaged coating in each 12-inch bar length.
N. Cold Drawn Steel Wire: ASTM A82.
O. Supports, Spacers, and Chairs: Types which will hol d reinforcement in
position shown in accordance with requirements of A CI 318 except as
specified.
P. Expansion Joint Filler: ASTM D1751.
Q. Sheet Materials for Curing Concrete: ASTM C171.
R. Liquid Membrane-forming Compounds for Curing Concre te: ASTM C309, Type
I, with fugitive dye, and shall meet the requiremen ts of ASTM
C1315.Compound shall be compatible with scheduled s urface treatment,
such as paint and resilient tile, and shall not dis color concrete
surface.
S. Abrasive Aggregate: Aluminum oxide grains or emery grits.
T. Non-Shrink Grout:
1. ASTM C1107, pre-mixed, produce a compressive streng th of at least 18
MPa at three days and 35 MPa (5000 psi) at 28 days. Furnish test
data from an independent laboratory indicating that the grout when
placed at a fluid consistency shall achieve 95 perc ent bearing under
a 1200 mm x 1200 mm (4 foot by 4 foot) base plate.
2. Where high fluidity or increased placing time is re quired, furnish
test data from an independent laboratory indicating that the grout
when placed at a fluid consistency shall achieve 95 percent under an
450 mm x 900 mm (18 inch by 36 inch) base plate.
U. Adhesive Binder: ASTM C881.
V. Waterstops:
1. Self-Expanding Butyl Strip Waterstops: Manufactured rectangular or
trapezoidal strip, butyl rubber with sodium bentoni te or other
03 30 00 - 11
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
hydrophilic polymers, for adhesive bonding to concr ete, 3/8 by 3/4
inch.
2. Self-Expanding Rubber Strip Waterstops: Manufacture d rectangular or
trapezoidal strip, bentonite-free hydrophilic polym er-modified
chloroprene rubber, for adhesive bonding to concret e, 3/8 by 3/4
inch.
3. Install Self-Expanding Strip Waterstops in construc tion joints and
at other locations indicated according to manufactu rer’s written
instructions, adhesive bonding, mechanically fasten ing, and firmly
pressing into place. Install in longest lengths pra cticable.
W. Porous Backfill: Crushed stone or gravel graded fro m 25 mm to 20 mm (1
inch to 3/4 inch).
X. Fibers:
1. Synthetic Fibers: Monofilament or fibrillated polyp ropylene fibers
for secondary reinforcing of concrete members. Use appropriate
length and 0.9 kg/m 3 (1.5 lb. per cubic yard). Product shall have a
UL rating.
Y. Epoxy Joint Filler: Two component, 100 percent soli ds compound, with a
minimum shore D hardness of 50.
Z. Bonding Admixture: Non-rewettable, polymer modified , bonding compound.
2.3 CONCRETE MIXES:
A. Mix Designs: Proportioned in accordance with Sectio n 5.3,
"Proportioning on the Basis of Field Experience and /or Trial Mixtures"
of ACI 318.
1. If trial mixes are used, make a set of at least 6 c ylinders in
accordance with ASTM C192 for test purposes from ea ch trial mix;
test three for compressive strength at 7 days and t hree at 28 days.
2. Submit a report of results of each test series, inc lude a detailed
listing of the proportions of trial mix or mixes, i ncluding cement,
fly ash, admixtures, weight of fine and coarse aggr egate per m 3
(cubic yard) measured dry rodded and damp loose, sp ecific gravity,
fineness modulus, percentage of moisture, air conte nt,
water-cement -fly ash ratio, and consistency of eac h cylinder in
terms of slump. Include dry unit weight of lightwei ght structural
concrete.
03 30 00 - 12
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
3. Prepare a curve showing relationship between water- cement -fly ash
ratio at 7-day and 28-day compressive strengths. Pl ot each curve
using at least three specimens.
4. If the field experience method is used, submit comp lete standard
deviation analysis.
B. Fly Ash Testing: Submit certificate verifying confo rmance with ASTM 618
initially with mix design and for each truck load o f fly ash delivered
from source. Submit test results performed within 6 months of submittal
date. Notify COR immediately when change in source is anticipated.
1. Testing Laboratory used for fly ash certification/t esting shall
participate in the Cement and Concrete Reference La boratory (CCRL)
program. Submit most recent CCRL inspection report.
C. After approval of mixes no substitution in material or change in
proportions of approval mixes may be made without a dditional tests and
approval of COR or as specified. Making and testing of preliminary test
cylinders may be carried on pending approval of cem ent and fly ash,
providing Contractor and manufacturer certify that ingredients used in
making test cylinders are the same. COR may allow C ontractor to proceed
with depositing concrete for certain portions of wo rk, pending final
approval of cement and fly ash and approval of desi gn mix.
D. Cement Factor: Maintain minimum cement factors in T able I regardless of
compressive strength developed above minimums. Use Fly Ash as an
admixture with 20% replacement by weight in all str uctural work.
Increase this replacement to 40% for mass concrete, and reduce it to
10% for drilled piers and caissons.
03 30 00 - 13
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
TABLE I - CEMENT AND WATER FACTORS FOR CONCRETE
Concrete Strength Non-Air- Entrained
Air-Entrained
Min. 28 Day Comp. Str.
MPa (psi)
Min. Cement kg/m 3 (lbs/c.
yd)
Max. Water Cement Ratio
Min. Cement
kg/m 3
(lbs/c. yd)
Max. Water Cement Ratio
35 (5000) 1,3 375 (630) 0.45 385 (650) 0.40
30 (4000) 1,3 325 (550) 0.55 340 (570) 0.50
25 (3000) 1,3 280 (470) 0.65 290 (490) 0.55
25 (3000) 1,2 300 (500)
* 310 (520)
*
1. If trial mixes are used, the proposed mix design sh all achieve a
compressive strength 8.3 MPa (1200 psi) in excess o f f'c. For
concrete strengths above 35 Mpa (5000 psi), the pro posed mix design
shall achieve a compressive strength 9.7 MPa (1400 psi) in excess of
f’c.
2. Lightweight Structural Concrete. Pump mixes may req uire higher
cement values.
3. For concrete exposed to high sulfate content soils maximum water
cement ratio is 0.44.
4. Determined by Laboratory in accordance with ACI 211 .1 for normal
concrete or ACI 211.2 for lightweight structural co ncrete.
E. Maximum Slump: Maximum slump, as determined by ASTM C143 with
tolerances as established by ASTM C94, for concrete to be vibrated
shall be as shown in Table II.
TABLE II - MAXIMUM SLUMP, MM (INCHES)*
Type of Construction Normal Weight Concrete
Lightweight Structural Concrete
Reinforced Footings and Substructure Walls
75mm (3 inches) 75 mm (3 inches)
Slabs, Beams, Reinforced Walls, and Building Columns
100 mm (4 inches)
100 mm (4 inches)
F. Slump may be increased by the use of the approved h igh-range water-
reducing admixture (superplasticizer). Tolerances a s established by
ASTM C94. Concrete containing the high-range-water- reducing admixture
03 30 00 - 14
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
may have a maximum slump of 225 mm (9 inches). The concrete shall
arrive at the job site at a slump of 50 mm to 75 mm (2 inches to 3
inches), and 75 mm to 100 mm (3 inches to 4 inches) for lightweight
concrete. This should be verified, and then the hig h-range-water-
reducing admixture added to increase the slump to t he approved level.
G. Air-Entrainment: Air-entrainment of normal weight c oncrete shall
conform with Table III. Air-entrainment of lightwei ght structural
concrete shall conform with Table IV. Determine air content by either
ASTM C173 or ASTM C231.
TABLE III - TOTAL AIR CONTENT FOR VARIOUS SIZES OF COARSE AGGREGATES (NORMAL CONCRETE)
Nominal Maximum Size of Total Air Content
Coarse Aggregate, mm (Inches) Percentage by Volume
10 mm (3/8 in).6 to 10 13 mm (1/2 in).5 to 9
20 mm (3/4 in).4 to 8 25 mm (1 in).3-1/2 to 6-1/2
40 mm (1 1/2 in).3 to 6
TABLE IV
AIR CONTENT OF LIGHTWEIGHT STRUCTURAL CONCRETE
Nominal Maximum size of Total Air Content
Coarse Aggregate, mm’s (Inches) Percentage by Volume
Greater than 10 mm (3/8 in) 4 to 8
10 mm (3/8 in) or less 5 to 9
H. High early strength concrete, made with Type III ce ment or Type I
cement plus non-corrosive accelerator, shall have a 7-day compressive
strength equal to specified minimum 28-day compress ive strength for
concrete type specified made with standard Portland cement.
I. Lightweight structural concrete shall not weigh mor e than air-dry unit
weight shown. Air-dry unit weight determined on 150 mm by 300 mm (6
inch by 12 inch) test cylinders after seven days st andard moist curing
followed by 21 days drying at 23 degrees C ± 1.7 degrees C (73.4 ± 3
degrees Fahrenheit), and 50 (plus or minus 7) perce nt relative
humidity. Use wet unit weight of fresh concrete as basis of control in
field.
J. Concrete slabs placed at air temperatures below 10 degrees C (50 degrees
Fahrenheit) use non-corrosive, non-chloride acceler ator. Concrete
03 30 00 - 15
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
required to be air entrained use approved air entra ining admixture.
Pumped concrete, synthetic fiber concrete, architec tural concrete,
concrete required to be watertight, and concrete wi th a water/cement
ratio below 0.50 use high-range water-reducing admi xture
(superplasticizer).
K. Durability: Use air entrainment for exterior expose d concrete subjected
to freezing and thawing and other concrete shown or specified. For air
content requirements see Table III or Table IV.
L. Enforcing Strength Requirements: Test as specified in Section 01 45 29,
TESTING LABORATORY SERVICES, during the progress of the work. Seven-day
tests may be used as indicators of 28-day strength. Average of any
three 28-day consecutive strength tests of laborato ry-cured specimens
representing each type of concrete shall be equal t o or greater than
specified strength. No single test shall be more th an 3.5 MPa (500 psi)
below specified strength. Interpret field test resu lts in accordance
with ACI 214. Should strengths shown by test specim ens fall below
required values, COR may require any one or any com bination of the
following corrective actions, at no additional cost to the Government:
1. Require changes in mix proportions by selecting one of the other
appropriate trial mixes or changing proportions, in cluding cement
content, of approved trial mix.
2. Require additional curing and protection.
3. If five consecutive tests fall below 95 percent of minimum values
given in Table I or if test results are so low as t o raise a
question as to the safety of the structure, COR may direct
Contractor to take cores from portions of the struc ture. Use
results from cores tested by the Contractor retaine d testing agency
to analyze structure.
4. If strength of core drilled specimens falls below 8 5 percent of
minimum value given in Table I, COR may order load tests, made by
Contractor retained testing agency, on portions of building so
affected. Load tests in accordance with ACI 318 and criteria of
acceptability of concrete under test as given there in.
5. Concrete work, judged inadequate by structural anal ysis, by results
of load test, or for any reason, shall be reinforce d with additional
construction or replaced, if directed by the COR.
03 30 00 - 16
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
2.4 BATCHING AND MIXING:
A. General: Concrete shall be "Ready-Mixed" and comply with ACI 318 and
ASTM C94, except as specified. Batch mixing at the site is permitted.
Mixing process and equipment must be approved by CO R. With each batch
of concrete, furnish certified delivery tickets lis ting information in
Paragraph 16.1 and 16.2 of ASTM C94. Maximum delive ry temperature of
concrete is 38 0C (100 degrees Fahrenheit). Minimum delivery temper ature
as follows:
Atmospheric Temperature Minimum Concrete Temperatur e
-1. degrees to 4.4 degrees C
(30 degrees to 40 degrees F)
15.6 degrees C (60 degrees F.)
-17 degrees C to -1.1 degrees C (0 degrees to 30 degrees F.)
21 degrees C (70 degrees F.)
1. Services of aggregate manufacturer's representative shall be
furnished during the design of trial mixes and as r equested by the
COR for consultation during batching, mixing, and p lacing operations
of lightweight structural concrete. Services will b e required until
field controls indicate that concrete of required q uality is being
furnished. Representative shall be thoroughly famil iar with the
structural lightweight aggregate, adjustment and co ntrol of mixes to
produce concrete of required quality. Representativ e shall assist
and advise COR.
PART 3 – EXECUTION
3.1 FORMWORK:
A. General: Design in accordance with ACI 347 is the r esponsibility of the
Contractor. The Contractor shall retain a registere d Professional
Engineer to design the formwork, shores, and reshor es.
1. Form boards and plywood forms may be reused for con tact surfaces of
exposed concrete only if thoroughly cleaned, patche d, and repaired
and COR approves their reuse.
2. Provide forms for concrete footings unless COR dete rmines forms are
not necessary.
3. Corrugated fiberboard forms: Place forms on a smoot h firm bed, set
tight, with no buckled cartons to prevent horizonta l displacement,
and in a dry condition when concrete is placed.
03 30 00 - 17
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
B. Treating and Wetting: Treat or wet contact forms as follows:
1. Coat plywood and board forms with non-staining form sealer. In hot
weather, cool forms by wetting with cool water just before concrete
is placed.
2. Clean and coat removable metal forms with light for m oil before
reinforcement is placed. In hot weather, cool metal forms by
thoroughly wetting with water just before placing c oncrete.
3. Use sealer on reused plywood forms as specified for new material.
C. Size and Spacing of Studs: Size and space studs, wa les and other
framing members for wall forms so as not to exceed safe working stress
of kind of lumber used nor to develop deflection gr eater than 1/270 of
free span of member.
D. Unlined Forms: Use plywood forms to obtain a smooth finish for concrete
surfaces. Tightly butt edges of sheets to prevent l eakage. Back up all
vertical joints solidly and nail edges of adjacent sheets to same stud
with 6d box nails spaced not over 150 mm (6 inches) apart.
E. Lined Forms: May be used in lieu of unlined plywood forms. Back up form
lining solidly with square edge board lumber secure ly nailed to studs
with all edges in close contact to prevent bulging of lining. No joints
in lining and backing may coincide. Nail abutted ed ges of sheets to
same backing board. Nail lining at not over 200 mm (8 inches) on center
along edges and with at least one nail to each squa re foot of surface
area; nails to be 3d blued shingle or similar nails with thin
flatheads.
G. Wall Form Ties: Locate wall form ties in symmetrica lly level horizontal
rows at each line of wales and in plumb vertical ti ers. Space ties to
maintain true, plumb surfaces. Provide one row of t ies within 150 mm (6
inches) above each construction joint. Space throug h-ties adjacent to
horizontal and vertical construction joints not ove r 450 mm (18 inches)
on center.
1. Tighten row of ties at bottom of form just before p lacing concrete
and, if necessary, during placing of concrete to pr event seepage of
concrete and to obtain a clean line. Ties to be ent irely removed
shall be loosened 24 hours after concrete is placed and shall be
pulled from least important face when removed.
2. Coat surfaces of all metal that is to be removed wi th paraffin, cup
grease or a suitable compound to facilitate removal .
03 30 00 - 18
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
H. Inserts, Sleeves, and Similar Items: Flashing regle ts, steel strips,
masonry ties, anchors, wood blocks, nailing strips, grounds, inserts,
wire hangers, sleeves, drains, guard angles, forms for floor hinge
boxes, inserts or bond blocks for elevator guide ra ils and supports,
and other items specified as furnished under this a nd other sections of
specifications and required to be in their final po sition at time
concrete is placed shall be properly located, accur ately positioned,
and built into construction, and maintained securel y in place.
1. Locate inserts or hanger wires for furred and suspe nded ceilings
only in bottom of concrete joists, or similar concr ete member of
overhead concrete joist construction.
2. Install sleeves, inserts and similar items for mech anical services
in accordance with drawings prepared specially for mechanical
services. Contractor is responsible for accuracy an d completeness
of drawings and shall coordinate requirements for m echanical
services and equipment.
3. Do not install sleeves in beams, joists or columns except where
shown or permitted by COR. Install sleeves in beams , joists, or
columns that are not shown, but are permitted by th e COR, and
require no structural changes, at no additional cos t to the
Government.
4. Minimum clear distance of embedded items such as co nduit and pipe is
at least three times diameter of conduit or pipe, e xcept at stub-ups
and other similar locations.
5. Provide recesses and blockouts in floor slabs for d oor closers and
other hardware as necessary in accordance with manu facturer's
instructions.
I. Construction Tolerances:
1. Set and maintain concrete formwork to assure erecti on of completed
work within tolerances specified and to accommodate installation of
other rough and finish materials. Accomplish remedi al work necessary
for correcting excessive tolerances. Erected work t hat exceeds
specified tolerance limits shall be remedied or rem oved and
replaced, at no additional cost to the Government.
2. Permissible surface irregularities for various clas ses of materials
are defined as "finishes" in specification sections covering
individual materials. They are to be distinguished from tolerances
03 30 00 - 19
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
specified which are applicable to surface irregular ities of
structural elements.
3.2 PLACING REINFORCEMENT:
A. General: Details of concrete reinforcement in accor dance with ACI 318
unless otherwise shown. Use epoxy-coated bars confo rming to ASTM A775
for all applications.
B. Placing: Place reinforcement conforming to CRSI DA4 , unless otherwise
shown.
1. Place reinforcing bars accurately and tie securely at intersections
and splices with 1.6 mm (16 gauge) black annealed w ire. Use epoxy-
coated tie wire with epoxy-coated reinforcing. Secu re reinforcing
bars against displacement during the placing of con crete by spacers,
chairs, or other similar supports. Portions of supp orts, spacers,
and chairs in contact with formwork shall be made o f plastic in
areas that will be exposed when building is occupie d. Type, number,
and spacing of supports conform to ACI 318. Where c oncrete slabs are
placed on ground, use concrete blocks or other non- corrodible
material of proper height, for support of reinforce ment. Use of
brick or stone supports will not be permitted.
2. Lap welded wire fabric at least 1 1/2 mesh panels p lus end extension
of wires not less than 300 mm (12 inches) in struct ural slabs. Lap
welded wire fabric at least 1/2 mesh panels plus en d extension of
wires not less than 150 mm (6 inches) in slabs on g rade.
3. Splice column steel at no points other than at foot ings and floor
levels unless otherwise shown.
C. Spacing: Minimum clear distances between parallel b ars, except in
columns and multiple layers of bars in beams shall be equal to nominal
diameter of bars. Minimum clear spacing is 25 mm (1 inch) or 1-1/3
times maximum size of coarse aggregate.
D. Splicing: Splices of reinforcement made only as req uired or shown or
specified. Accomplish splicing as follows:
1. Lap splices: Do not use lap splices for bars larger than Number 36
(Number 11). Minimum lengths of lap as shown.
2. Welded splices: Splicing by butt-welding of reinfor cement permitted
providing the weld develops in tension at least 125 percent of the
yield strength (fy) for the bars. Welding conform t o the
03 30 00 - 20
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
requirements of AWS D1.4. Welded reinforcing steel conform to the
chemical analysis requirements of AWS D1.4.
a. Submit test reports indicating the chemical analysi s to establish
weldability of reinforcing steel.
b. Submit a field quality control procedure to insure proper
inspection, materials and welding procedure for wel ded splices.
c. Department of Veterans Affairs retained testing age ncy shall test
a minimum of three splices, for compliance, locatio ns selected by
COR.
3. Mechanical Splices: Develop in tension and compress ion at least 125
percent of the yield strength (fy) of the bars. Str esses of
transition splices between two reinforcing bar size s based on area
of smaller bar. Provide mechanical splices at locat ions indicated.
Use approved exothermic, tapered threaded coupling, or swaged and
threaded sleeve. Exposed threads and swaging in the field not
permitted.
a. Initial qualification: In the presence of COR, make three test
mechanical splices of each bar size proposed to be spliced.
Department of Veterans Affairs retained testing lab oratory will
perform load test.
b. During installation: Furnish, at no additional cost to the
Government, one companion (sister) splice for every 50 splices
for load testing. Department of Veterans Affairs re tained testing
laboratory will perform the load test.
E. Bending: Bend bars cold, unless otherwise approved. Do not field bend
bars partially embedded in concrete, except when ap proved by COR.
F. Cleaning: Metal reinforcement, at time concrete is placed, shall be
free from loose flaky rust, mud, oil, or similar co atings that will
reduce bond. Repair cut and damaged epoxy coatings with epoxy repair
coating according to ASTM D3963/D 3963 M.
G. Future Bonding: Protect exposed reinforcement bars intended for bonding
with future work by wrapping with felt and coating felt with a
bituminous compound unless otherwise shown.
3.3 VAPOR BARRIER:
A. Except where membrane waterproofing is required, in terior concrete slab
on grade shall be placed on a continuous vapor barr ier.
03 30 00 - 21
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
1. Place 100 mm (4 inches) of fine granular fill over the vapor barrier
to act as a blotter for concrete slab.
2. Vapor barrier joints lapped 150 mm (6 inches) and s ealed with
compatible waterproof pressure-sensitive tape.
3. Patch punctures and tears.
3.4 SLABS RECEIVING RESILIENT COVERING
A. Slab shall be allowed to cure for 6 weeks minimum p rior to placing
resilient covering. After curing, slab shall be tes ted by the
Contractor for moisture in accordance with ASTM D42 63 or ASTM F1869.
Moisture content shall be less than 3 pounds per 10 00 sf prior to
placing covering.
B. In lieu of curing for 6 weeks, Contractor has the o ption, at his own
cost, to utilize the Moisture Vapor Emissions & Alk alinity Control
Sealer as follows:
1. Sealer is applied on the day of the concrete pour o r as soon as
harsh weather permits, prior to any other chemical treatments for
concrete slabs either on grade, below grade or abov e grade receiving
resilient flooring, such as, sheet vinyl, vinyl com position tile,
rubber, wood flooring, epoxy coatings and overlays.
2. Manufacturer’s representative will be on the site t he day of
concrete pour to install or train its application a nd document. He
shall return on every application thereafter to ver ify that proper
procedures are followed.
a. Apply Sealer to concrete slabs as soon as final fin ishing
operations are complete and the concrete has harden ed
sufficiently to sustain floor traffic without damag e.
b. Spray apply Sealer at the rate of 20 m 2 (200 square feet) per
gallon. Lightly broom product evenly over the subst rate and
product has completely penetrated the surface.
c. If within two (2) hours after initial application a reas are
subjected to heavy rainfall and puddling occurs, re apply Sealer
product to these areas as soon as weather condition permits.
3.5 CONSTRUCTION JOINTS:
A. Unless otherwise shown, location of construction jo ints to limit
individual placement shall not exceed 24,000 mm (80 feet) in any
horizontal direction, except slabs on grade which s hall have
03 30 00 - 22
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
construction joints shown. Allow 48 hours to elapse between pouring
adjacent sections unless this requirement is waived by COR.
E. Install polyvinyl chloride or rubber water seals , as shown in
accordance with manufacturer's instructions, to for m continuous
watertight seal.
3.6 EXPANSION JOINTS AND CONTRACTION JOINTS:
A. Clean expansion joint surfaces before installing pr emolded filler and
placing adjacent concrete.
B. Install polyvinyl chloride or rubber water seals, a s shown in
accordance with manufacturer's instructions, to for m continuous
watertight seal.
C. Provide contraction (control) joints in floor slabs as indicated on the
contract drawings. Joints shall be either formed or saw cut, to the
indicated depth after the surface has been finished . Complete saw
joints within 4 to 12 hours after concrete placemen t. Protect joints
from intrusion of foreign matter.
3.7 PLACING CONCRETE:
A. Preparation:
1. Remove hardened concrete, wood chips, shavings and other debris from
forms.
2. Remove hardened concrete and foreign materials from interior
surfaces of mixing and conveying equipment.
3. Have forms and reinforcement inspected and approved by COR before
depositing concrete.
4. Provide runways for wheeling equipment to convey co ncrete to point
of deposit. Keep equipment on runways which are not supported by or
bear on reinforcement. Provide similar runways for protection of
vapor barrier on coarse fill.
B. Bonding: Before depositing new concrete on or again st concrete which
has been set, thoroughly roughen and clean existing surfaces of
laitance, foreign matter, and loose particles.
1. Preparing surface for applied topping:
a. Remove laitance, mortar, oil, grease, paint, or oth er foreign
material by sand blasting. Clean with vacuum type e quipment to
remove sand and other loose material.
b. Broom clean and keep base slab wet for at least fou r hours before
topping is applied.
03 30 00 - 23
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
c. Use a thin coat of one part Portland cement, 1.5 pa rts fine sand,
bonding admixture; and water at a 50: 50 ratio and mix to achieve
the consistency of thick paint. Apply to a damp bas e slab by
scrubbing with a stiff fiber brush. New concrete sh all be placed
while the bonding grout is still tacky.
C. Conveying Concrete: Convey concrete from mixer to f inal place of
deposit by a method which will prevent segregation. Method of conveying
concrete is subject to approval of COR.
D. Placing: For special requirements see Paragraphs, H OT WEATHER and COLD
WEATHER.
1. Do not place concrete when weather conditions preve nt proper
placement and consolidation, or when concrete has a ttained its
initial set, or has contained its water or cement c ontent more than
1 1/2 hours.
2. Deposit concrete in forms as near as practicable in its final
position. Prevent splashing of forms or reinforceme nt with concrete
in advance of placing concrete.
3. Do not drop concrete freely more than 3000 mm (10 f eet) for concrete
containing the high-range water-reducing admixture
(superplasticizer) or 1500 mm (5 feet) for conventi onal concrete.
Where greater drops are required, use a tremie or f lexible spout
(canvas elephant trunk), attached to a suitable hop per.
4. Discharge contents of tremies or flexible spouts in horizontal
layers not exceeding 500 mm (20 inches) in thicknes s, and space
tremies such as to provide a minimum of lateral mov ement of
concrete.
5. Continuously place concrete until an entire unit be tween
construction joints is placed. Rate and method of p lacing concrete
shall be such that no concrete between construction joints will be
deposited upon or against partly set concrete, afte r its initial set
has taken place, or after 45 minutes of elapsed tim e during concrete
placement.
6. On bottom of members with severe congestion of rein forcement,
deposit 25 mm (1 inch) layer of flowing concrete co ntaining the
specified high-range water-reducing admixture (supe rplasticizer).
Successive concrete lifts may be a continuation of this concrete or
concrete with a conventional slump.
03 30 00 - 24
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
E. Consolidation: Conform to ACI 309. Immediately afte r depositing, spade
concrete next to forms, work around reinforcement a nd into angles of
forms, tamp lightly by hand, and compact with mecha nical vibrator
applied directly into concrete at approximately 450 mm (18 inch)
intervals. Mechanical vibrator shall be power drive n, hand operated
type with minimum frequency of 5000 cycles per minu te having an
intensity sufficient to cause flow or settlement of concrete into
place. Vibrate concrete to produce thorough compact ion, complete
embedment of reinforcement and concrete of uniform and maximum density
without segregation of mix. Do not transport concre te in forms by
vibration.
1. Use of form vibration shall be approved only when c oncrete sections
are too thin or too inaccessible for use of interna l vibration.
2. Carry on vibration continuously with placing of con crete. Do not
insert vibrator into concrete that has begun to set .
3.8 HOT WEATHER:
Follow the recommendations of ACI 305 or as specifi ed to prevent
problems in the manufacturing, placing, and curing of concrete that can
adversely affect the properties and serviceability of the hardened
concrete. Methods proposed for cooling materials an d arrangements for
protecting concrete shall be made in advance of con crete placement and
approved by COR.
3.9 COLD WEATHER:
Follow the recommendations of ACI 306 or as specifi ed to prevent
freezing of concrete and to permit concrete to gain strength properly.
Use only the specified non-corrosive, non-chloride accelerator. Do not
use frozen materials or materials containing ice or snow. Do not use
calcium chloride, thiocyantes or admixtures contain ing more than 0.05
percent chloride ions. Methods proposed for heating materials and
arrangements for protecting concrete shall be made in advance of
concrete placement and approved by COR.
3.10 PROTECTION AND CURING:
A. Conform to ACI 308: Initial curing shall immediatel y follow the
finishing operation. Protect exposed surfaces of co ncrete from
premature drying, wash by rain and running water, w ind, mechanical
injury, and excessively hot or cold temperatures. K eep concrete not
covered with membrane or other curing material cont inuously wet for at
03 30 00 - 25
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
least 7 days after placing, except wet curing perio d for high-early-
strength concrete shall be not less than 3 days. Ke ep wood forms
continuously wet to prevent moisture loss until for ms are removed. Cure
exposed concrete surfaces as described below. Other curing methods may
be used if approved by COR.
1. Liquid curing and sealing compounds: Apply by power -driven spray or
roller in accordance with the manufacturer’s instru ctions. Apply
immediately after finishing. Maximum coverage 10m 2/L (400 square feet
per gallon) on steel troweled surfaces and 7.5m 2/L (300 square feet
per gallon) on floated or broomed surfaces for the curing/sealing
compound.
2. Plastic sheets: Apply as soon as concrete has harde ned sufficiently
to prevent surface damage. Utilize widest practical width sheet and
overlap adjacent sheets 50 mm (2 inches). Tightly s eal joints with
tape.
3. Paper: Utilize widest practical width paper and ove rlap adjacent
sheets 50 mm (2 inches). Tightly seal joints with s and, wood planks,
pressure-sensitive tape, mastic or glue.
3.11 REMOVAL OF FORMS:
A. Remove in a manner to assure complete safety of str ucture after the
following conditions have been met.
1. Where structure as a whole is supported on shores, forms for beams
and girder sides, columns, and similar vertical str uctural members
may be removed after 24 hours, provided concrete ha s hardened
sufficiently to prevent surface damage and curing i s continued
without any lapse in time as specified for exposed surfaces.
2. Take particular care in removing forms of architect ural exposed
concrete to insure surfaces are not marred or gouge d, and that
corners and arises are true, sharp and unbroken.
B. Control Test: Use to determine if the concrete has attained sufficient
strength and curing to permit removal of supporting forms. Cylinders
required for control tests taken in accordance with ASTM C172, molded
in accordance with ASTM C31, and tested in accordan ce with ASTM C39.
Control cylinders cured and protected in the same m anner as the
structure they represent. Supporting forms or shori ng not removed until
strength of control test cylinders have attained at least 70 percent of
minimum 28-day compressive strength specified.Exerc ise care to assure
03 30 00 - 26
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
that newly unsupported portions of structure are no t subjected to heavy
construction or material loading.
C. Reshoring: Reshoring is required if superimposed lo ad plus dead load of
the floor exceeds the capacity of the floor at the time of loading.
Reshoring accomplished in accordance with ACI 347 a t no additional cost
to the Government.
3.12 CONCRETE SURFACE PREPARATION:
A. Metal Removal: Unnecessary metal items cut back flu sh with face of
concrete members.
B. Patching: Maintain curing and start patching as soo n as forms are
removed. Do not apply curing compounds to concrete surfaces requiring
patching until patching is completed. Use cement mo rtar for patching of
same composition as that used in concrete. Use whit e or gray Portland
cement as necessary to obtain finish color matching surrounding
concrete. Thoroughly clean areas to be patched. Cut out honeycombed or
otherwise defective areas to solid concrete to a de pth of not less than
25 mm (1 inch). Cut edge perpendicular to surface o f concrete. Saturate
with water area to be patched, and at least 150 mm (6 inches)
surrounding before placing patching mortar. Give ar ea to be patched a
brush coat of cement grout followed immediately by patching mortar.
Cement grout composed of one part Portland cement, 1.5 parts fine sand,
bonding admixture, and water at a 50:50 ratio, mix to achieve
consistency of thick paint. Mix patching mortar app roximately 1 hour
before placing and remix occasionally during this p eriod without
addition of water. Compact mortar into place and sc reed slightly higher
than surrounding surface. After initial shrinkage h as occurred, finish
to match color and texture of adjoining surfaces. C ure patches as
specified for other concrete. Fill form tie holes w hich extend entirely
through walls from unexposed face by means of a pre ssure gun or other
suitable device to force mortar through wall. Wipe excess mortar off
exposed face with a cloth.
C. Upon removal of forms, clean vertical concrete surf ace that is to
receive bonded applied cementitious application wit h wire brushes or by
sand blasting to remove unset material, laitance, a nd loose particles
to expose aggregates to provide a clean, firm, gran ular surface for
bond of applied finish.
03 30 00 - 27
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
3.13 CONCRETE FINISHES:
A. Vertical and Overhead Surface Finishes:
1. Unfinished areas: Vertical and overhead concrete su rfaces exposed in
pipe basements, elevator and dumbwaiter shafts, pip e spaces, pipe
trenches, above suspended ceilings, manholes, and o ther unfinished
areas will not require additional finishing.
3. Interior and exterior exposed areas finished: Give a grout finish of
uniform color and smooth finish treated as follows:
a. After concrete has hardened and laitance, fins and burrs removed,
scrub concrete with wire brushes. Clean stained con crete surfaces
by use of a hone stone.
b. Apply grout composed of one part of Portland cement , one part
fine sand, smaller than a 600 µm (No. 30) sieve. Wo rk grout into
surface of concrete with cork floats or fiber brush es until all
pits, and honeycombs are filled.
c. After grout has hardened slightly, but while still plastic,
scrape grout off with a sponge rubber float and, ab out 1 hour
later, rub concrete vigorously with burlap to remov e any excess
grout remaining on surfaces.
d. In hot, dry weather use a fog spray to keep grout w et during
setting period. Complete finish of area in same day . Make limits
of finished areas at natural breaks in wall surface . Leave no
grout on concrete surface overnight.
4. Textured: Finish as specified. Maximum quantity of patched area 0.2
m2 (2 square feet) in each 93 m 2 (1000 square feet) of textured
surface.
B. Slab Finishes:
1. Monitoring and Adjustment: Provide continuous cycle of placement,
measurement, evaluation and adjustment of procedure s to produce
slabs within specified tolerances. Monitor elevatio ns of structural
steel in key locations before and after concrete pl acement to
establish typical deflection patterns for the struc tural steel.
Determine elevations of cast-in-place slab soffits prior to removal
of shores. Provide information to COR and floor con sultant for
evaluation and recommendations for subsequent place ments.
03 30 00 - 28
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
2. Set perimeter forms to serve as screed using either optical or laser
instruments. For slabs on grade, wet screeds may be used to
establish initial grade during strike-off, unless C OR determines
that the method is proving insufficient to meet req uired finish
tolerances and directs use of rigid screed guides. Where wet screeds
are allowed, they shall be placed using grade stake s set by optical
or laser instruments. Use rigid screed guides, as o pposed to wet
screeds, to control strike-off elevation for all ty pes of elevated
(non slab-on-grade) slabs. Divide bays into halves or thirds by hard
screeds. Adjust as necessary where monitoring of pr evious placements
indicates unshored structural steel deflections to other than a
level profile.
3. Place slabs monolithically. Once slab placement com mences, complete
finishing operations within same day. Slope finishe d slab to floor
drains where they occur, whether shown or not.
4. Use straightedges specifically made for screeding, such as hollow
magnesium straightedges or power strike-offs. Do no t use pieces of
dimensioned lumber. Strike off and screed slab to a true surface at
required elevations. Use optical or laser instrumen ts to check
concrete finished surface grade after strike-off. R epeat strike-off
as necessary. Complete screeding before any excess moisture or
bleeding water is present on surface. Do not sprink le dry cement on
the surface.
5. Immediately following screeding, and before any ble ed water appears,
use a 3000 mm (10 foot) wide highway straightedge i n a cutting and
filling operation to achieve surface flatness. Do n ot use bull
floats or darbys, except that darbying may be allow ed for narrow
slabs and restricted spaces.
6. Wait until water sheen disappears and surface stiff ens before
proceeding further. Do not perform subsequent opera tions until
concrete will sustain foot pressure with maximum of 6 mm (1/4 inch)
indentation.
7. Scratch Finish: Finish base slab to receive a bonde d applied
cementitious application as indicated above, except that bull floats
and darbys may be used. Thoroughly coarse wire broo m within two
hours after placing to roughen slab surface to insu re a permanent
bond between base slab and applied materials.
03 30 00 - 29
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
8. Float Finish: Slabs to receive unbonded toppings, s teel trowel
finish, fill, mortar setting beds, or a built-up ro of, and ramps,
stair treads, platforms (interior and exterior), an d equipment pads
shall be floated to a smooth, dense uniform, sandy textured finish.
During floating, while surface is still soft, check surface for
flatness using a 3000 mm (10 foot) highway straight edge. Correct
high spots by cutting down and correct low spots by filling in with
material of same composition as floor finish. Remov e any surface
projections and re-float to a uniform texture.
9. Steel Trowel Finish: Concrete surfaces to receive r esilient floor
covering or carpet, monolithic floor slabs to be ex posed to view in
finished work, future floor roof slabs, applied top pings, and other
interior surfaces for which no other finish is indi cated. Steel
trowel immediately following floating. During final troweling, tilt
steel trowel at a slight angle and exert heavy pres sure to compact
cement paste and form a dense, smooth surface. Fini shed surface
shall be smooth, free of trowel marks, and uniform in texture and
appearance.
10. Broom Finish: Finish exterior slabs, ramps, and sta ir treads with a
bristle brush moistened with clear water after surf aces have been
floated. Brush in a direction transverse to main tr affic. Match
texture approved by COR from sample panel.
11. Finished slab flatness (FF) and levelness (FL) valu es comply with
the following minimum requirements:
b. Areas that will be exposed:
1) Slab on grade:
a) Specified overall value FF 36/FL 20
b) Minimum local value FF 24/FL 15
2) Level suspended slabs (shored until after testing) and topping
slabs
a) Specified overall value FF 30/FL 20
b) Minimum local value FF 24/FL 15
3) Unshored suspended slabs:
a) Specified overall value FF 30
b) Minimum local value FF 24
03 30 00 - 30
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
4) Level tolerance such that 80 percent of all points fall within
a 20 mm (3/4 inch) envelope +10 mm, -10 mm (+3/8 in ch, -3/8
inch) from the design elevation.
c. "Specified overall value" is based on the composite of all
measured values in a placement derived in accordanc e with ASTM
E1155.
d. "Minimum local value" (MLV) describes the flatness or levelness
below which repair or replacement is required. MLV is based on
the results of an individual placement and applies to a minimum
local area. Minimum local area boundaries may not c ross a
construction joint or expansion joint. A minimum lo cal area will
be bounded by construction and/or control joints, o r by column
lines and/or half-column lines, whichever is smalle r.
12. Measurements
a. Contractor retained testing laboratory will take me asurements as
directed by COR, to verify compliance with FF, FL, and other
finish requirements. Measurements will occur within 72 hours
after completion of concrete placement (weekends an d holidays
excluded). Make measurements before shores or forms are removed
to insure the "as-built" levelness is accurately as sessed.
Profile data for above characteristics may be colle cted using a
laser level or any Type II apparatus (ASTM E1155, " profileograph"
or "dipstick"). Contractor's surveyor shall establi sh reference
elevations to be used by Department of Veterans Aff airs retained
testing laboratory.
b. Contractor not experienced in using FF and FL crite ria is
encouraged to retain the services of a floor consul tant to assist
with recommendations concerning adjustments to slab thicknesses,
finishing techniques, and procedures on measurement s of the
finish as it progresses in order to achieve the spe cific flatness
and levelness numbers.
13. Acceptance/ Rejection:
a. If individual slab section measures less than eithe r of specified
minimum local F F/F L numbers, that section shall be rejected and
remedial measures shall be required. Sectional boun daries may be
set at construction and contraction (control) joint s, and not
smaller than one-half bay.
03 30 00 - 31
Milwaukee VAMC Upgrade and Replace Building 123 Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
b. If composite value of entire slab installation, com bination of
all local results, measures less than either of spe cified overall
FF/F L numbers, then whole slab shall be rejected and reme dial
measures shall be required.
14. Remedial Measures for Rejected Slabs: Correct rejec ted slab areas by
grinding, planing, surface repair with underlayment compound or
repair topping, retopping, or removal and replaceme nt of entire
rejected slab areas, as directed by COR, until a sl ab finish
constructed within specified tolerances is accepted .
- - - E N D - - -
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
05 50 00- 1
SECTION 05 50 00 METAL FABRICATIONS
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies items and assemblies fabrica ted from structural
steel shapes and other materials as shown and speci fied.
B. Items specified.
1. Support for Wall and Ceiling Mounted Items: (SD0550 00-01,
SD055000-02, SD102113-01, SD102600-01, SD123100-01 &
SD123100-02)
2. Frames
4. Covers and Frames for Pits and Trenches.
5. Gratings
11. Ladders
12. Railings
1.2 RELATED WORK
A. Prime and finish painting: Section 09 91 00, PAINTI NG.
1.3 SUBMITTALS
A. Submit in accordance with Section 01 33 23, SHOP DR AWINGS, PRODUCT
DATA, AND SAMPLES.
B. Manufacturer's Literature and Data:
Grating, each type Floor plate
Trap door Wheel guards
Ceiling hatch Sidewalk Access door
Manhole Covers Safety nosing
C. Shop Drawings:
1. Each item specified, showing complete detail, locat ion in the
project, material and size of components, method of joining various
components and assemblies, finish, and location, si ze and type of
anchors.
2. Mark items requiring field assembly for erection id entification and
furnish erection drawings and instructions.
3. Provide templates and rough-in measurements as requ ired.
D. Manufacturer's Certificates:
1. Anodized finish as specified.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
05 50 00- 2
2. Live load designs as specified.
E. Design Calculations for specified live loads includ ing dead loads.
F. Furnish setting drawings and instructions for insta llation of anchors
to be preset into concrete and masonry work, and fo r the positioning of
items having anchors to be built into concrete or m asonry construction.
1.4 QUALITY ASSURANCE
A. Each manufactured product shall meet, as a minimum, the requirements
specified, and shall be a standard commercial produ ct of a manufacturer
regularly presently manufacturing items of type spe cified.
B. Each product type shall be the same and be made by the same
manufacturer.
C. Assembled product to the greatest extent possible b efore delivery to
the site.
D. Include additional features, which are not specific ally prohibited by
this specification, but which are a part of the man ufacturer's standard
commercial product.
1.5 APPLICABLE PUBLICATIONS
A. The publications listed below form a part of this s pecification to the
extent referenced. The publications are referenced in the text by the
basic designation only.
B. American Society of Mechanical Engineers (ASME):
B18.6.1-97..............Wood Screws
B18.2.2-87(R2005).......Square and Hex Nuts
C. American Society for Testing and Materials (ASTM):
A36/A36M-12.............Structural Steel
A47-99(R2009)...........Malleable Iron Castings
A48-03(R2012)...........Gray Iron Castings
A53-12..................Pipe, Steel, Black and Hot- Dipped, Zinc-Coated
Welded and Seamless
A123-12.................Zinc (Hot-Dip Galvanized) C oatings on Iron and
Steel Products
A240/A240M-14...........Standard Specification for Chromium and
Chromium-Nickel Stainless Steel Plate, Sheet
and Strip for Pressure Vessels and for General
Applications.
A269-10.................Seamless and Welded Austeni tic Stainless Steel
Tubing for General Service
05 50 00- 3
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
A307-12.................Carbon Steel Bolts and Stud s, 60,000 PSI
Tensile Strength
A391/A391M-07(R2012)....Grade 80 Alloy Steel Chain A786/A786M-
09...........Rolled Steel Floor Plate
B221-13.................Aluminum and Aluminum-Alloy Extruded Bars,
Rods, Wire, Shapes, and Tubes
B456-11.................Electrodeposited Coatings o f Copper Plus Nickel
Plus Chromium and Nickel Plus Chromium B632-
08.................Aluminum-Alloy Rolled Tread Plat e
C1107-13................Packaged Dry, Hydraulic-Cem ent Grout
(Nonshrink)
D3656-13................Insect Screening and Louver Cloth Woven from
Vinyl-Coated Glass Yarns F436-
11.................Hardened Steel Washers
F468-06(R2012)..........Nonferrous Bolts, Hex Cap S crews, Socket Head
Cap Screws and Studs for General Use
F593-13.................Stainless Steel Bolts, Hex Cap Screws, and
Studs
F1667-11................Driven Fasteners: Nails, Sp ikes and Staples
D. American Welding Society (AWS):
D1.1-10.................Structural Welding Code Ste el
D1.2-08.................Structural Welding Code Alu minum
D1.3-08.................Structural Welding Code She et Steel
E. National Association of Architectural Metal Manufac turers (NAAMM)
AMP 521-01..............Pipe Railing Manual
AMP 500-06..............Metal Finishes Manual
MBG 531-09..............Metal Bar Grating Manual
MBG 532-09..............Heavy Duty Metal Bar Gratin g Manual
F. Structural Steel Painting Council (SSPC)/Society of Protective
Coatings:
SP 1-04.................No. 1, Solvent Cleaning
SP 2-04.................No. 2, Hand Tool Cleaning
SP 3-04.................No. 3, Power Tool Cleaning
G. Federal Specifications (Fed. Spec):
RR-T-650E...............Treads, Metallic and Nonmet allic, Nonskid
05 50 00- 4
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
PART 2 - PRODUCTS
2.1 DESIGN CRITERIA
A. In addition to the dead loads, design fabrications to support the
following live loads unless otherwise specified.
B. Ladders and Rungs: 120 kg (250 pounds) at any point .
C. Railings and Handrails: 900 N (200 pounds) in any d irection at any
point.
D. Gratings: 500 kg/m 2 (100 pounds per square foot).
2.2 MATERIALS
A. Structural Steel: ASTM A36.
B. Stainless Steel: ASTM A240, Type 302 or 304.
C. Aluminum, Extruded: ASTM B221, Alloy 6063-T5 unless otherwise
specified. For structural shapes use alloy 6061-T6 and alloy 6061-
T4511.
E. Steel Pipe: ASTM A53.
1. Galvanized for exterior locations.
2. Type S, Grade A unless specified otherwise.
3. NPS (inside diameter) as shown.
F. Primer Paint: As specified in Section 09 91 00, PAI NTING.
G. Stainless Steel Tubing: ASTM A269, type 302 or 304.
H. Modular Channel Units:
1. Factory fabricated, channel shaped, cold formed she et steel shapes,
complete with fittings bolts and nuts required for assembly.
2. Form channel within turned pyramid shaped clamping ridges on each
side.
3. Provide case hardened steel nuts with serrated groo ves in the top
edges designed to be inserted in the channel at any point and be
given a quarter turn so as to engage the channel cl amping ridges.
Provide each nut with a spring designed to hold the nut in place.
4. Factory finish channels and parts with oven baked p rimer when
exposed to view. Channels fabricated of ASTM A525, G90 galvanized
steel may have primer omitted in concealed location s. Finish screws
and nuts with zinc coating.
5. Fabricate snap-in closure plates to fit and close e xposed channel
openings of not more than 0.3 mm (0.0125 inch) thic k stainless
steel.
I. Grout: ASTM C1107, pourable type.
05 50 00- 5
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
J. Insect Screening: ASTM D3656.
2.3 HARDWARE
A. Rough Hardware:
1. Furnish rough hardware with a standard plating, app lied after
punching, forming and assembly of parts; galvanized , cadmium plated,
or zinc-coated by electro-galvanizing process. Galv anized G-90 where
specified.
2. Use G90 galvanized coating on ferrous metal for ext erior work unless
non-ferrous metal or stainless is used.
B. Fasteners:
1. Bolts with Nuts:
a. ASME B18.2.2.
b. ASTM A307 for 415 MPa (60,000 psi) tensile strength bolts.
c. ASTM F468 for nonferrous bolts.
d. ASTM F593 for stainless steel.
2. Screws: ASME B18.6.1.
3. Washers: ASTM F436, type to suit material and ancho rage.
4. Nails: ASTM F1667, Type I, style 6 or 14 for finish work.
2.4 FABRICATION GENERAL
A. Material
1. Use material as specified. Use material of commerci al quality and
suitable for intended purpose for material that is not named or its
standard of quality not specified.
2. Use material free of defects which could affect the appearance or
service ability of the finished product.
B. Size:
1. Size and thickness of members as shown.
2. When size and thickness is not specified or shown f or an individual
part, use size and thickness not less than that use d for the same
component on similar standard commercial items or i n accordance with
established shop methods.
C. Connections
1. Except as otherwise specified, connections may be m ade by welding,
riveting or bolting.
2. Field riveting will not be approved.
3. Design size, number and placement of fasteners, to develop a joint
strength of not less than the design value.
05 50 00- 6
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
4. Holes, for rivets and bolts: Accurately punched or drilled and burrs
removed.
5. Size and shape welds to develop the full design str ength of the
parts connected by welds and to transmit imposed st resses without
permanent deformation or failure when subject to se rvice loadings.
6. Use Rivets and bolts of material selected to preven t corrosion
(electrolysis) at bimetallic contacts. Plated or co ated material
will not be approved.
7. Use stainless steel connectors for removable member s machine screws
or bolts.
D. Fasteners and Anchors
1. Use methods for fastening or anchoring metal fabric ations to
building construction as shown or specified.
2. Where fasteners and anchors are not shown, design t he type, size,
location and spacing to resist the loads imposed wi thout deformation
of the members or causing failure of the anchor or fastener, and
suit the sequence of installation.
3. Use material and finish of the fasteners compatible with the kinds
of materials which are fastened together and their location in the
finished work.
4. Fasteners for securing metal fabrications to new co nstruction only,
may be by use of threaded or wedge type inserts or by anchors for
welding to the metal fabrication for installation b efore the
concrete is placed or as masonry is laid.
5. Fasteners for securing metal fabrication to existin g construction or
new construction may be expansion bolts, toggle bol ts, power
actuated drive pins, welding, self drilling and tap ping screws or
bolts.
E. Workmanship
1. General:
a. Fabricate items to design shown.
b. Furnish members in longest lengths commercially ava ilable within
the limits shown and specified.
c. Fabricate straight, true, free from warp and twist, and where
applicable square and in same plane.
d. Provide holes, sinkages and reinforcement shown and required for
fasteners and anchorage items.
05 50 00- 7
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
e. Provide openings, cut-outs, and tapped holes for at tachment and
clearances required for work of other trades.
f. Prepare members for the installation and fitting of hardware.
g. Cut openings in gratings and floor plates for the p assage of
ducts, sumps, pipes, conduits and similar items. Pr ovide
reinforcement to support cut edges.
h. Fabricate surfaces and edges free from sharp edges, burrs and
projections which may cause injury.
2. Welding:
a. Weld in accordance with AWS.
b. Welds shall show good fusion, be free from cracks a nd porosity
and accomplish secure and rigid joints in proper al ignment.
c. Where exposed in the finished work, continuous weld for the full
length of the members joined and have depressed are as filled and
protruding welds finished smooth and flush with adj acent
surfaces.
d. Finish welded joints to match finish of adjacent su rface.
3. Joining:
a. Miter or butt members at corners.
b. Where frames members are butted at corners, cut leg of frame
member perpendicular to surface, as required for cl earance.
4. Anchors:
a. Where metal fabrications are shown to be preset in concrete, weld
32 x 3 mm (1-1/4 by 1/8 inch) steel strap anchors, 150 mm (6
inches) long with 25 mm (one inch) hooked end, to b ack of member
at 600 mm (2 feet) on center, unless otherwise show n.
b. Where metal fabrications are shown to be built into masonry use
32 x 3 mm (1-1/4 by 1/8 inch) steel strap anchors, 250 mm (10
inches) long with 50 mm (2 inch) hooked end, welded to back of
member at 600 mm (2 feet) on center, unless otherwi se shown.
5. Cutting and Fitting:
a. Accurately cut, machine and fit joints, corners, co pes, and
miters.
b. Fit removable members to be easily removed.
c. Design and construct field connections in the most practical
place for appearance and ease of installation.
d. Fit pieces together as required.
05 50 00- 8
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
e. Fabricate connections for ease of assembly and disa ssembly
without use of special tools.
f. Joints firm when assembled.
g. Conceal joining, fitting and welding on exposed wor k as far as
practical.
h. Do not show rivets and screws prominently on the ex posed face.
i. The fit of components and the alignment of holes sh all eliminate
the need to modify component or to use exceptional force in the
assembly of item and eliminate the need to use othe r than common
tools.
F. Finish:
1. Finish exposed surfaces in accordance with NAAMM AM P 500 Metal
Finishes Manual.
3. Steel and Iron: NAAMM AMP 504.
a. Zinc coated (Galvanized): ASTM A123, G90 unless not ed otherwise.
b. Surfaces exposed in the finished work:
1) Finish smooth rough surfaces and remove projections .
2) Fill holes, dents and similar voids and depressions with epoxy
type patching compound.
c. Shop Prime Painting:
1) Surfaces of Ferrous metal:
a) Items not specified to have other coatings.
b) Galvanized surfaces specified to have prime paint.
c) Remove all loose mill scale, rust, and paint, by ha nd or
power tool cleaning as defined in SSPC-SP2 and SP3.
d) Clean of oil, grease, soil and other detrimental ma tter by
use of solvents or cleaning compounds as defined in SSPC-
SP1.
e) After cleaning and finishing apply one coat of prim er as
specified in Section 09 91 00, PAINTING.
2) Non ferrous metals: Comply with MAAMM-500 series.
4. Stainless Steel: NAAMM AMP-504 Finish No. 4.
G. Protection:
1. Insulate aluminum surfaces that will come in contac t with concrete,
masonry, plaster, or metals other than stainless st eel, zinc or
white bronze by giving a coat of heavy-bodied alkal i resisting
bituminous paint or other approved paint in shop.
05 50 00- 9
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
2. Spot prime all abraded and damaged areas of zinc co ating which
expose the bare metal, using zinc rich paint on hot -dip zinc coat
items and zinc dust primer on all other zinc coated items.
2.5 SUPPORTS
A. General:
1. Fabricate ASTM A36 structural steel shapes as shown .
2. Use clip angles or make provisions for welding hang ers and braces to
overhead construction.
3. Field connections may be welded or bolted.
C. For Wall Mounted Items:
1. For items supported by metal stud partitions.
2. Steel strip or hat channel minimum of 1.5 mm (0.059 8 inch) thick.
3. Steel strip minimum of 150 mm (6 inches) wide, leng th extending one
stud space beyond end of item supported.
4. Steel hat channels where shown. Flange cut and flat ted for anchorage
to stud.
5. Structural steel tube or channel for grab bar at wa ter closets floor
to structure above with clip angles or end plates f ormed for
anchors.
6. Use steel angles for thru wall counters. Drill angl e for fasteners
2.6 COVERS AND FRAMES FOR PITS AND TRENCHES
A. Furnish steam pit entrance cover and frame as shown . Frame shall be
installed as shown on drawings.
B. Cover: 1/4“ thick aluminum diamond plate, 300 psf l ive load rating,
mill finish, lifting mechanism with reinforced comp osite tubes and
electro coated compression springs, automatic hold open arm, forged
aluminum hinges with stainless steel pins, neoprene gasketed standard
slam lock with keyed cylinder lock and underside re lease knob.
C. Frame: 1/4” thick extruded aluminum channel with co ntinuous concrete
anchor, with continuous EPDM debris gasket and 1-1/ 2” aluminum coupling
for drain.
D. Warranty: 10-year material.
2.7 GRATINGS
A. Fabricate gratings to support live loads specified and a concentrated
load as specified.
B. Provide clearance at all sides to permit easy remov al of grating.
05 50 00- 10
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
C. Make cutouts in gratings with 6 mm (1/4 inch) minim um to 25 mm (one
inch) maximum clearance for penetrations or passage of pipes and ducts.
Edge band cutouts.
D. Fabricate in sections not to exceed 2.3 m 2 (25 square feet) in area and
90 kg (200 pounds) in weight.
E. Fabricate sections of grating with end-banding bars .
F. Fabricate angle frames and supports, including anch orage as shown.
1. Fabricate intermediate supporting members from "T's " or angles.
2. Locate intermediate supports to support grating sec tion edges.
3. Fabricate frame to finish flush with top of grating .
4. Locate anchors at ends and not over 600 mm (24 inch es) o.c.
5. Butt or miter, and weld angle frame at corners.
G. Steel Bar Gratings:
1. Fabricate grating using steel bars, frames, support s and other
members shown in accordance with Metal Bar Grating Manual.
2. Galvanize steel members after fabrication in accord ance with ASTM
A123, G-90 for exterior gratings, gratings in concr ete floors, and
interior grating where specified.
2.8 LADDERS
A. Steel Ladders:
1. Fixed-rail type with steel rungs shouldered and hea ded into and
welded to rails.
2. Fabricate angle brackets of 50 mm (2 inch) wide by 13 mm (1/2 inch)
thick steel; brackets spaced maximum of 1200 mm (4 feet) apart and
of length to hold ladder 175 mm (7 inches) from wal l to center of
rungs. Provide turned ends or clips for anchoring.
3. Provide holes for anchoring with expansion bolts th rough turned ends
and brackets.
4. Where shown, fabricate side rails curved, twisted a nd formed into a
gooseneck.
5. Galvanize exterior ladders after fabrication, ASTM A123, G-90.
C. Ladder Rungs:
1. Fabricate from 25 mm (one inch) diameter steel bars .
2. Fabricate so that rungs will extend at least 100 mm (4 inches) into
wall with ends turned 50 mm (2 inches), project out from wall 175 mm
(7 inches), be 400 mm (16 inches) wide and be desig ned so that foot
cannot slide off end.
05 50 00- 11
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
3. Galvanized after fabrication, ASTM A123, G-90 rungs for exterior use
and for access to pits.
D. Safety Post
1. Provide galvanized assembly with release rod and pu ll up loop.
2. Post shall be fabricated of steel.
3. Post shall not have twist type locking mechanism.
2.9 RAILINGS
A. In addition to the dead load design railing assembl y to support live
load specified.
B. Fabrication General:
1. Provide continuous welded joints, dressed smooth an d flush.
2. Standard flush fittings, designed to be welded, may be used.
3. Exposed threads will not be approved.
4. Form handrail brackets to size and design shown.
5. Exterior Post Anchors.
a. Fabricate tube or pipe sleeves with closed ends or plates as
shown.
b. Where inserts interfere with reinforcing bars, prov ide flanged
fittings welded or threaded to posts for securing t o concrete
with expansion bolts.
c. Provide heavy pattern sliding flange base plate wit h set screws
at base of pipe or tube posts.
6. Interior Post Anchors:
a. Provide flanged fittings for securing fixed posts t o floor with
expansion bolts, unless shown otherwise.
b. Weld or thread flanged fitting to posts at base.
d. Provide sliding flange base plate on posts secur ed with set
screws.
D. Steel Pipe Railings:
1. Fabricate of steel pipe with welded joints.
2. Number and space of rails as shown.
3. Space posts for railings not over 1800 mm (6 feet) on centers
between end posts.
4. Form handrail brackets from malleable iron.
5. Fabricate removable sections with posts at end of s ection.
7. Opening Guard Rails:
05 50 00- 12
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
a. Fabricate rails with flanged fitting at each end to fit between
wall opening jambs.
b. Design flange fittings for fastening with machine s crews to steel
plate anchored to jambs.
c. Fabricate rails for floor openings for anchorage in sleeves.
9. Chains:
a. Chains: ASTM A391, Grade 63, straight link style, n ormal size
chain bar 8 mm (5/16 inch) diameter, eight links pe r 25 mm (foot)
and with boat type snap hook on one end, and throug h type eye
bolt on other end.
b. Fabricate eye bolt for attaching chain to pipe post s, size not
less than 9 mm (3/8 inch) diameter.
c. Fabricate anchor at walls, for engagement of snap h ook of either
a 9 mm (3/8 inch) diameter eye bolt or punched angl e.
d. Galvanize chain and bolts after fabrication.
PART 3 - EXECUTION
3.1 INSTALLATION, GENERAL
A. Set work accurately, in alignment and where shown, plumb, level, free
of rack and twist, and set parallel or perpendicula r as required to
line and plane of surface.
B. Items set into concrete or masonry.
1. Provide temporary bracing for such items until conc rete or masonry
is set.
2. Place in accordance with setting drawings and instr uctions.
3. Build strap anchors, into masonry as work progresse s.
C. Set frames of gratings, covers, corner guards, trap doors and similar
items flush with finish floor or wall surface and, where applicable,
flush with side of opening.
D. Field weld in accordance with AWS.
1. Design and finish as specified for shop welding.
2. Use continuous weld unless specified otherwise.
E. Install anchoring devices and fasteners as shown an d as necessary for
securing metal fabrications to building constructio n as specified.
Power actuated drive pins may be used except for re movable items and
where members would be deformed or substrate damage d by their use.
05 50 00- 13
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
F. Spot prime all abraded and damaged areas of zinc co ating as specified
and all abraded and damaged areas of shop prime coa t with same kind of
paint used for shop priming.
G. Isolate aluminum from dissimilar metals and from co ntact with concrete
and masonry materials as required to prevent electr olysis and
corrosion.
H. Secure escutcheon plate with set screw.
3.2 INSTALLATION OF SUPPORTS
A. Anchorage to structure.
1. Secure angles or channels and clips to overhead str uctural steel by
continuous welding unless bolting is shown.
2. Secure supports to concrete inserts by bolting or c ontinuous welding
as shown.
3. Secure supports to mid height of concrete beams whe n inserts do not
exist with expansion bolts and to slabs, with expan sion bolts.
unless shown otherwise.
4. Secure steel plate or hat channels to studs as deta iled.
C. Supports for Wall Mounted items:
1. Locate center of support at anchorage point of supp orted item.
2. Locate support at top and bottom of wall hung cabin ets.
3. Locate support at top of floor cabinets and shelvin g installed
against walls.
4. Locate supports where required for items shown.
H. Supports for Trapeze Bars:
1. Secure plates to overhead construction with fastene rs as shown.
2. Secure angle brace assembly to overhead constructio n with fasteners
as shown and bolt plate to braces.
3. Fit modular channel unit flush with finish ceiling, and secure to
plate with modular channel unit manufacturer's stan dard fittings
through steel shims or spreaders as shown.
a. Install closure plates in channel between eye bolts .
b. Install eyebolts in channel.
3.3 COVERS AND FRAMES FOR PITS AND TRENCHES
A. Set frame and cover flush with finish floor.
B. Secure plates to frame with flat head countersunk s crews.
C. Set gratings loose in drainage trenches or over pit s unless shown
anchored.
05 50 00- 14
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
D. Coating of aluminum steam pit frames: Coat aluminum frames that come
into contact with concrete with bitumastic or epoxy ocating. Where
frame coating has been damaged or is missing recoat before pouring
concrete.
3.4 GRATINGS
A. Set grating flush with finish floor; top of curb, o r areaway wall. Set
frame so that horizontal leg of angle frame is flus h with face of wall
except when frame is installed on face of wall.
B. Set frame in formwork before concrete is placed.
3.5 LADDERS
A. Anchor ladders to walls and floors with expansion b olts through turned
lugs or angle clips or brackets.
C. Ladder Rungs:
1. Set ladder rungs into formwork before concrete is p laced.
2. Set step portion of rung 150 mm (6 inches) from wal l.
3. Space rungs approximately 300 mm (12 inches) on cen ters.
4. Where only one rung is required, locate it 400 mm ( 16 inches) above
the floor.
3.6 RAILINGS
A. Steel Posts:
1. Secure fixed posts to concrete with expansion bolts through flanged
fittings except where sleeves are shown with pourab le grout.
2. Install sleeves in concrete formwork.
3. Set post in sleeve and pour grout to surface. Apply beveled bead of
urethane sealant at perimeter of post or under flan ge fitting as
specified in Section 07 92 00, JOINT SEALANTS on ex terior posts.
4. Secure removable posts to concrete with either mach ine screws
through flanged fittings which are secured to inver ted flanges
embedded in and set flush with finished floor, or s et posts in close
fitting pipe sleeves without grout.
5. Secure sliding flanged fittings to posts at base wi th set screws.
6. Secure fixed flanged fittings to concrete with expa nsion bolts. 7. Secure posts to steel with welds.
C. Anchor to Walls:
1. Anchor rails to concrete or solid masonry with mach ine screws
through flanged fitting to steel plate.
a. Anchor steel plate to concrete or solid masonry wit h expansion
bolts.
05 50 00- 15
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
b. Anchor steel plate to hollow masonry with toggle bo lts.
2. Anchor flanged fitting with toggle bolt to steel su pport in frame
walls.
F. Chains:
1. Eye bolt chains to pipe posts.
3.7 CLEAN AND ADJUSTING
A. Adjust movable parts including hardware to operate as designed without
binding or deformation of the members centered in t he opening or frame
and, where applicable, contact surfaces fit tight a nd even without
forcing or warping the components.
B. Clean after installation exposed prefinished and pl ated items and items
fabricated from stainless steel, aluminum and coppe r alloys, as
recommended by the metal manufacture and protected from damage until
completion of the project.
- - - E N D - - -
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
07 13 52 - 1
SECTION 07 13 52 MODIFIED BITUMINOUS SHEET WATERPROOFING
PART 1 - GENERAL 1.1 SUMMARY
A. Section Includes:
1. Modified bituminous sheet material used for exterio r below grade
waterproofing and split slab waterproofing.
1.2 APPLICABLE PUBLICATIONS
A. Comply with references to extent specified in this section.
B. Federal Specifications (Fed. Spec.):
1. UU-B-790A Notice 2- Building Paper, Vegetable Fiber : (Kraft,
Waterproofed, Water Repellent, and Fire Resistant).
C. ASTM International (ASTM):
1. D41/D41M-11 - Asphalt Primer Used in Roofing, Dampp roofing and
Waterproofing.
D. American Hardboard Association (AHA):
1. A135.4-2012 - Basic Hardboard. 1.3 PREINSTALLATION MEETINGS
A. Conduct preinstallation meeting at project site min imum 30 days before
beginning Work of this section.
1. Required Participants:
a. Contracting Officer's Representative.
b. Architect/Engineer.
c. Contractor.
d. Installer.
e. Other installers responsible for adjacent and inter secting work,
including substrate and flashing installers.
2. Meeting Agenda: Distribute agenda to participants m inimum 3 days
before meeting.
a. Installation schedule.
b. Installation sequence.
c. Preparatory work.
d. Protection before, during, and after installation.
e. Installation.
f. Terminations.
g. Transitions and connections to other work.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
07 13 52 - 2
h. Inspecting and testing.
i. Other items affecting successful completion.
3. Document and distribute meeting minutes to particip ants to record
decisions affecting installation.
1.4 SUBMITTALS
A. Submittal Procedures: Section 01 33 23, SHOP DRAWIN GS, PRODUCT DATA,
AND SAMPLES.
B. Submittal Drawings:
1. Show size, configuration, and installation details.
C. Manufacturer's Literature and Data:
1. Description of each product.
2. Installation instructions.
3. Warranty.
D. Samples:
1. Waterproofing and Flashing Sheet: 200 mm (8 inch) s quare, each type
and color.
2. Insulation: 200 mm (8 inch) square.
E. Test reports: Certify products comply with specific ations.
F. Certificates: Certify products comply with specific ations.
G. Qualifications: Substantiate qualifications comply with specifications.
1. Installer with project experience list. 1.5 QUALITY ASSURANCE
A. Installer Qualifications:
1. Regularly installs specified products.
2. Installed specified products with satisfactory serv ice on five
similar installations for minimum five years.
a. Project Experience List: Provide contact names and addresses for
completed projects. 1.6 DELIVERY
A. Deliver products in manufacturer's original sealed packaging.
B. Mark packaging, legibly. Indicate manufacturer's na me or brand, type,
color, production run number, and manufacture date.
C. Before installation, return or dispose of products within distorted,
damaged, or opened packaging.
1.7 STORAGE AND HANDLING
A. Store products indoors in dry, weathertight conditi oned facility.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
07 13 52 - 3
B. Protect products from damage during handling and co nstruction
operations.
1.8 FIELD CONDITIONS
A. Environment:
1. Product Temperature: Minimum 4 degrees C (40 degree s F) for minimum
48 hours before installation.
2. Weather Limitations: Install waterproofing only dur ing dry current
and forecasted weather conditions.
1.9 WARRANTY
A. Construction Warranty: FAR clause 52.246-21, "Warra nty of
Construction."
B. Manufacturer's Warranty: Warrant waterproofing syst em against material
and manufacturing defects and agree to repair any l eak caused by a
defect in the waterproofing system materials or wor kmanship of the
installer.
1. Warranty Period: 10 years.
PART 2 - PRODUCTS
2.1 SYSTEM DESCRIPTION
A. Waterproofing System: Modified bituminous sheet mat erial for exterior
below grade and split slab waterproofing.
2.2 PRODUCTS - GENERAL
A. Provide each product from one manufacturer. 2.3 BITUMINOUS SHEET (WALLS and ROOF)
A. Cold applied waterproofing membrane composed primar ily of modified
bituminous material prefabricated in sheet form des igned for below
grade exterior and split slab waterproofing. Sheet reinforced with
fibers at manufacturer's option.
B. Thickness: 1.5 mm (60 mils), plus or minus 0.13 mm (5 mils), and bonded
to 0.1 mm (4 mil) thick plastic sheet, with joints lapped minimum 6”.
C. Provide release sheet to prevent bonding of bitumin ous sheet to itself.
D. Tensile strength (ASTM D412): 250 psi min.
E. Ultimate elongation (ASTM D412): 300% min.
F. Brittleness Temperature (ASTM D746): 25 deg. F. (32 deg. C.).
G. Hydrostatic Head Resistance: 150 feet min.
07 13 52 - 4
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
H. Water Absorption (ASTM D570): Not more than 0.5% we ight gain for 48
hours of immersion at 70 deg. F.
2.4 BLINDSIDE MEMBRANE (UNDERSLAB)
A. Material: Composite sheet, HDPE film, adhesive and water resistant protective coating.
B. Elongation: 300%, ASTM D 412
C. Peel Adhesion to Concrete:5 lb./in. ASTM D903
D. Tensile Strength: 1200 lbs./in. ASTM D412
E. Hydrostatic Head Resistance: 230 feet min.
F. Accessories: Primer, mastic, joint sealers, Joint S eam Tape, cant straps and protection boards as recommended by manu facturers.
2.5 PROTECTION MATERIAL
A. Drain board: 0.4” High impact polystyrene, non-wove n geotextile fabric, 12 GPM flow rate. Apply service tap at joints 6 mm (1/4 inch) thick.
2.6 ACCESSORIES A. Patching Compound: Factory-prepared, non-shrinking, fast-setting,
cementitious adhesive compound containing no ferrou s metal or oxide.
B. Primer: ASTM D41/D41M.
1. Rubber based solvent (Oil Based). Suitable for appl ications to green
concrete. Roll or brush, and other accessories as r ecommended by
product manufacturer.
C. Joint sealers.
1. Liquid elastomeric, cold applied, towel applied.
2. Trowel, paddle mixer and other accessories as recom mend by product
manufacturer.
D. Cant strips.
PART 3 - EXECUTION
3.1 PREPARATION
A. Examine and verify substrate suitability for produc t installation.
1. Concrete surfaces cured minimum time recommended by waterproofing
manufacturer.
2. Substrate to be dry as recommended by waterproofing manufacturer.
B. Protect existing construction and completed work fr om damage.
C. Correct substrate deficiencies.
1. Fill voids, joints, and cracks with patching compou nd.
07 13 52 - 5
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
D. Clean substrates. Remove contaminants capable of pr eventing full
adhesion.
E. Priming:
1. Prime concrete and masonry surfaces.
2. Application method, amount of primer and condition or primer before
installation of bituminous sheet as recommended by primer
manufacturer.
3. Reprime when required according to manufacturer's i nstructions. 3.2 INSTALLATION - GENERAL
A. Install products according to manufacturer's instru ctions and approved
submittal drawings.
1. When manufacturer's instructions deviate from speci fications, submit
proposed resolution for Contracting Officer's Repre sentative
consideration.
3.3 WATERPROOFING INSTALLATION
A. Bituminous Sheet Installation:
1. Remove release sheet before application.
2. Lay bituminous sheet from low point to high point s o laps shed
water.
3. Treat expansion, construction and control joints an d evident working
cracks as expansion joints. Apply bituminous sheet in double
thickness over joint by first applying a strip of b ituminous sheet
minimum 200 mm (8 inches) wide, centered over joint .
4. Lap seams minimum 50 mm (2 inches).
5. Lay succeeding sheet with laps, and roll or press i nto place.
6. Repair misaligned or inadequately lapped seams acco rding to
manufacturer’s instructions.
7. Seal seams and terminations according to sheet manu facturer’s
instructions.
8. Install on exterior concrete surface (including flo ors) of new steam
pits, existing building structures and where detail ed.
B. Blindside Membrane (Underslab):
1. Roll membrane out over flat surface cleared of all sharp or
puncturing material. ALL seams shall be lap seems. Butt joint seam
are not allowed. Install adhesive side up. Lap seem s not less than
6 inch.
07 13 52 - 6
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
2. Roll excess membrane outside footprint of base slab to lap vertical
at least 6 inch on base slab.
3. Protect waterproofing during construction in accord ance with
manufacturer recommendation.
4. Installed over pit or tunnel floor bedding stone pr ior to
installation of rebar and concrete and where detail ed.
5. Extend minimum 18” onto existing construction or as shown on
drawings.
C. Corner Treatment:
1. At inside and outside corners, apply double cover u sing an initial
strip minimum 280 mm (11 inches) wide, centered alo ng axis of
corner.
2. Cover each strip completely by the regular applicat ion of bituminous
sheet.
3. Provide a fillet or cant on inside corners.
4. Form cants using patching compound.
5. Do not use wood, fiber, and insulating materials fo r cants.
D. Projection Treatment:
1. Apply a double layer of bituminous sheet around pip es and similar
projections at least 150 mm (6 inches) wide.
E. Patching:
1. Repair tears, punctures, air blisters, and inadequa tely lapped
seams, according to manufacturer’s instructions bef ore protection
course is applied.
F. Permanent Protection:
1. Drain Board:
a. Apply protection board in strict accordance with ma nufacturer's
directions to steam pit and box conduits as a prote ction board
for waterproofing. Use adhesive to secure protectio n board to
wall. Adhesive shall be compatible with waterproofi ng. Tape
all joints as work proceeds to prevent stones from migrating
between protection board and waterproofing.
b. Protection board should be laid with closed joints and staggered
end joints.
c. After membrane waterproofing barrier has been insta lled, allow a
24 hour waiting period before installation of board and
backfilling.
07 13 52 - 7
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
d. Backfill within two (2) days (or time as recommende d by the
manufacturer) to prevent shrinkage of the membrane and cracking.
e. Install over all waterproofed membrane surfaces of steam pits,
existing building structurers and where detailed.
G. Temporary Protection:
1. When waterproofing materials are subjected to damag e by sunlight and
cannot be immediately protected as specified, prote ct waterproofing
materials by waterproof building paper or suitable coating approved
by manufacturer of waterproofing system used.
3.4 FIELD QUALITY CONTROL
A. Inspection:
1. Do not cover waterproofed surfaces by other materia ls or backfill
until work is approved by Contracting Officer's Rep resentative.
3.5 CLEANING
A. Remove excess adhesive before adhesive sets.
B. Clean exposed waterproofing surfaces. Remove contam inants and stains. 3.6 PROTECTION
A. Protect waterproofing from construction operations.
B. Remove protective materials immediately before acce ptance.
C. Repair damage.
- - - E N D - - -
Milwaukee VAMC Upgrade and Replace Building 123
Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
09 06 00 - 1
SECTION 09 06 00 SCHEDULE FOR FINISHES
PART I – GENERAL
1.1 DESCRIPTION
This section contains a coordinated system in which requirements for materials specified in other
sections shown are identified by abbreviated materi al names and finish codes in the room finish
schedule or shown for other locations.
1.2 MANUFACTURERS
Manufacturer’s trade names and numbers used herein are only to identify colors, finishes, textures
and patterns. Products of other manufacturer’s equi valent to colors, finishes, textures and patterns
of manufacturers listed that meet requirements of t echnical specifications will be acceptable upon
approval in writing by contracting officer for fini sh requirements.
1.3 SUBMITALS
Submit in accordance with SECTION 01 33 23, SHOP DR AWINGS, PRODUCT DATA, AND SAMPLES provide
quadruplicate samples for color approval of materia ls and finishes specified in this section.
1.4 APPLICABLE PUBLICATIONS
A. Publications listed below form a part of this speci fication to the extent referenced. Publications
are referenced in text by basic designation only.
B. MASTER PAINTING INSTITUTE: (MPI)
2001....................Architectural Painting Spec ification Manual
Milwaukee VAMC Upgrade and Replace Building 123
Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
09 06 00 - 2
PART 2- PRODUCTS
2.1 DIVISION 31 - EARTHWORK
A. SECTION 32 17 23, PAVEMENT MARKINGS.
Color Manufacturer MFG. Color Name/No.
Yellow
White
2.2 DIVISION 05 – METALS
A. SECTION 05 50 00, METAL FABRICATION
Item Finish
Steel Grating and Frames
Steel Pipe Railings and Gates (not on Steel Stairs)
B. SECTION 09 91 00, PAINT AND COATINGS
1. MPI Gloss and Sheen Standards
Gloss @60 Sheen @85
Gloss Level 1 a traditional matte finish-flat max 5 units, and max 10 units
2. Paint code Gloss Manufacturer Mfg. Color Name/No .
P
P
P
P
Milwaukee VAMC Upgrade and Replace Building 123
Steam Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
09 06 00 - 3
Term Abbreviation Paint P
PART III EXECUTION
3.1 FINISH SCHEDULES & MISCELLANEOUS ABBREVIATIONS FINISH SCHEDULE & MISCELLANEOUS ABBREVIATIONS
--- E N D---
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
09 91 00 - 1
SECTION 09 91 00 PAINTING
PART 1 - GENERAL
1.1 DESCRIPTION:
A. Work of this Section includes all labor, materials, equipment, and
services necessary to complete the painting and fin ishing as shown on the
construction documents and/or specified herein, inc luding, but not limited
to, the following:
1. Prime coats which may be applied in shop under othe r sections.
2. Prime painting unprimed surfaces to be painted unde r this Section.
3. Painting items furnished with a prime coat of paint , including touching
up of or repairing of abraded, damaged or rusted pr ime coats applied by
others.
4. Painting ferrous metal (except stainless steel) exp osed to view.
5. Painting galvanized ferrous metals exposed to view.
6. Painting pipes, pipe coverings, conduit, ducts, ins ulation, hangers,
supports and other mechanical and electrical items and equipment
exposed to view.
7. Painting includes shellacs, stains, varnishes, coat ings specified, and
striping or markers and identity markings.
8. Incidental painting and touching up as required to produce proper
finish for painted surfaces, including touching up of factory finished
items.
9. Painting of any surface not specifically mentioned to be painted herein
or on construction documents, but for which paintin g is obviously
necessary to complete the job, or work which comes within the intent of
these specifications, is to be included as though s pecified.
1.2 RELATED WORK:
A. Activity Hazard Analysis: Section 01 35 26, SAFETY REQUIREMENTS.
B. Shop prime painting of steel and ferrous metals: Di vision 05 - METALS,
C. Type of Finish, Color, and Gloss Level of Finish Co at: Section 09 06 00,
SCHEDULE FOR FINISHES.
D. Asphalt and concrete pavement marking: Section 32 1 7 23, PAVEMENT
MARKINGS.
1.3 SUBMITTALS:
A. Submit in accordance with Section 01 33 23, SHOP DR AWINGS, PRODUCT DATA,
AND SAMPLES.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
09 91 00 - 2
B. Sustainable Design Submittals as described below:
1. Volatile organic compounds per volume as specified in
PART 2 - PRODUCTS.
C. Painter qualifications.
D. Manufacturer's Literature and Data:
1. Before work is started, or sample panels are prepar ed, submit
manufacturer's literature and technical data, the c urrent Master
Painters Institute (MPI) "Approved Product List" in dicating brand
label, product name and product code as of the date of contract award,
will be used to determine compliance with the submi ttal requirements of
this specification. The Contractor may choose to us e subsequent MPI
"Approved Product List", however, only one (1) list may be used for the
entire contract and each coating system is to be fr om a single
manufacturer. All coats on a particular substrate m ust be from a single
manufacturer. No variation from the MPI "Approved P roduct List" where
applicable is acceptable.
1.4 DELIVERY AND STORAGE:
A. Deliver materials to site in manufacturer's sealed container marked to
show following:
1. Name of manufacturer.
2. Product type.
3. Batch number.
4. Instructions for use.
5. Safety precautions.
B. In addition to manufacturer's label, provide a labe l legibly printed as
following:
1. Federal Specification Number, where applicable, and name of material.
2. Surface upon which material is to be applied.
3. Specify Coat Types: Prime; body; finish; etc.
C. Maintain space for storage, and handling of paintin g materials and
equipment in a ventilated, neat and orderly conditi on to prevent
spontaneous combustion from occurring or igniting a djacent items.
D. Store materials at site at least 24 hours before us ing, at a temperature
between 7 and 30 degrees C (45 and 85 degrees F).
1.5 QUALITY ASSURANCE:
A. Qualification of Painters: Use only qualified journ eyman painters for the
mixing and application of paint on exposed surfaces . Submit evidence that
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
09 91 00 - 3
key personnel have successfully performed surface p reparation and
application of coating on a minimum of three (3) si milar projects within
the past three (3) years.
B. Paint Coordination: Provide finish coats which are compatible with the
prime paints used. Review other Sections of these s pecifications in which
prime paints are to be provided to ensure compatibi lity of the total
coatings system for the various substrates. Upon re quest from other
subcontractors, furnish information on the characte ristics of the finish
materials proposed to be used, to ensure that compa tible prime coats are
used. Provide barrier coats over incompatible prime rs or remove and re-
prime as required. Notify the Contracting Officer R epresentative (COR) in
writing of any anticipated problems using the coati ng systems as specified
with substrates primed by others.
1.6 REGULATORY REQUIREMENTS:
A. Paint materials are to conform to the restrictions of the local
Environmental and Toxic Control jurisdiction.
1. Volatile Organic Compounds (VOC) Emissions Requirem ents: Field-applied
paints and coatings that are inside the waterproofi ng system to not
exceed limits of authorities having jurisdiction.
4. Chromate, Cadmium, Mercury, and Silica: Provide mat erials that do not
contain zinc-chromate, strontium-chromate, Cadmium, mercury or mercury
compounds or free crystalline silica.
5. Human Carcinogens: Provide materials that do not co ntain any of the
ACGIH-BKLT and ACGHI-DOC confirmed or suspected hum an carcinogens.
6. Use high performance acrylic paints in place of alk yd paints.
1.7 SAFETY AND HEALTH
A. Apply paint materials using safety methods and equi pment in accordance
with the following:
1. Comply with applicable Federal, State, and local la ws and regulations,
and with the ACCIDENT PREVENTION PLAN, including th e Activity Hazard
Analysis (AHA) as specified in Section 01 35 26, SA FETY REQUIREMENTS.
The AHA is to include analyses of the potential imp act of painting
operations on painting personnel and on others invo lved in and adjacent
to the work zone.
B. Safety Methods Used During Paint Application: Compl y with the requirements
of SSPC PA Guide 10.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
09 91 00 - 4
C. Toxic Materials: To protect personnel from overexpo sure to toxic
materials, conform to the most stringent guidance o f:
1. The applicable manufacturer’s Material Safety Data Sheets (MSDS) or
local regulation.
2. 29 CFR 1910.1000.
3. ACHIH-BKLT and ACGHI-DOC, threshold limit values .
1.8 APPLICABLE PUBLICATIONS:
A. Publications listed below form a part of this speci fication to the extent
referenced. Publications are referenced in the text by basic designation
only.
B. American Conference of Governmental Industrial Hygi enists (ACGIH):
ACGIH TLV-BKLT-2012.....Threshold Limit Values (TLV ) for Chemical
Substances and Physical Agents and Biological
Exposure Indices (BEIs)
ACGIH TLV-DOC-2012......Documentation of Threshold Limit Values and
Biological Exposure Indices, (Seventh Edition)
C. ASME International (ASME):
A13.1-07(R2013).........Scheme for the Identificati on of Piping Systems
D. Code of Federal Regulation (CFR):
40 CFR 59...............Determination of Volatile M atter Content, Water
Content, Density Volume Solids, and Weight Solids
of Surface Coating
E. Commercial Item Description (CID):
A-A-1272A...............Plaster Gypsum (Spackling C ompound)
F. Federal Specifications (Fed Spec):
TT-P-1411A..............Paint, Copolymer-Resin, Cem entitious (For
Waterproofing Concrete and Masonry Walls) (CEP)
G. Master Painters Institute (MPI):
8.......................Exterior Alkyd, Flat MPI Gl oss Level 1
9.......................Exterior Alkyd Enamel MPI G loss Level 6
10......................Exterior Latex, Flat
11......................Exterior Latex, Semi-Gloss
18......................Organic Zinc Rich Primer
22......................Aluminum Paint, High Heat ( up to 590% - 1100F)
27......................Exterior / Interior Alkyd F loor Enamel, Gloss
31......................Polyurethane, Moisture Cure d, Clear Gloss
36......................Knot Sealer
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
09 91 00 - 5
43......................Interior Satin Latex, MPI G loss Level 4
44......................Interior Low Sheen Latex, M PI Gloss Level 2
45......................Interior Primer Sealer
46......................Interior Enamel Undercoat
47......................Interior Alkyd, Semi-Gloss, MPI Gloss Level 5
48......................Interior Alkyd, Gloss, MPI Gloss Level 6
50......................Interior Latex Primer Seale r
51......................Interior Alkyd, Eggshell, M PI Gloss Level 3
52......................Interior Latex, MPI Gloss L evel 3
53......................Interior Latex, Flat, MPI G loss Level 1
54......................Interior Latex, Semi-Gloss, MPI Gloss Level 5
59......................Interior/Exterior Alkyd Por ch & Floor Enamel, Low
Gloss
60......................Interior/Exterior Latex Por ch & Floor Paint, Low
Gloss
66......................Interior Alkyd Fire Retarda nt, Clear Top-Coat (ULC
Approved)
67......................Interior Latex Fire Retarda nt, Top-Coat (ULC
Approved)
68......................Interior/ Exterior Latex Po rch & Floor Paint,
Gloss
71......................Polyurethane, Moisture Cure d, Clear, Flat
77......................Epoxy Cold Cured, Gloss
79......................Marine Alkyd Metal Primer
90......................Interior Wood Stain, Semi-T ransparent
91......................Wood Filler Paste
94......................Exterior Alkyd, Semi-Gloss
95......................Fast Drying Metal Primer
98......................High Build Epoxy Coating
101.....................Epoxy Anti-Corrosive Metal Primer
108.....................High Build Epoxy Coating, L ow Gloss
114.....................Interior Latex, Gloss
119.....................Exterior Latex, High Gloss (acrylic)
134.....................Galvanized Water Based Prim er
135.....................Non-Cementitious Galvanized Primer
138.....................Interior High Performance L atex, MPI Gloss Level 2
139.....................Interior High Performance L atex, MPI Gloss Level 3
09 91 00 - 6
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
140.....................Interior High Performance L atex, MPI Gloss Level 4
141.....................Interior High Performance L atex (SG) MPI Gloss
Level 5
163.....................Exterior Water Based Semi-G loss Light Industrial
Coating, MPI Gloss Level 5
G. Society for Protective Coatings (SSPC):
SSPC SP 1-82(R2004).....Solvent Cleaning
SSPC SP 2-82(R2004).....Hand Tool Cleaning
SSPC SP 3-28(R2004).....Power Tool Cleaning
SSPC SP 10/NACE No.2....Near-White Blast Cleaning
SSPC PA Guide 10........Guide to Safety and Health Requirements
H. Maple Flooring Manufacturer’s Association (MFMA):
I. U.S. National Archives and Records Administration ( NARA):
29 CFR 1910.1000........Air Contaminants
J. Underwriter’s Laboratory (UL)
PART 2 - PRODUCTS
2.1 MATERIALS:
A. Conform to the coating specifications and standards referenced in PART 3.
Submit manufacturer’s technical data sheets for spe cified coatings and
solvents.
2.2 PAINT PROPERTIES:
A. Use ready-mixed (including colors), except two comp onent epoxies,
polyurethanes, polyesters, paints having metallic p owders packaged
separately and paints requiring specified additives .
B. Where no requirements are given in the referenced s pecifications for
primers, use primers with pigment and vehicle, comp atible with substrate
and finish coats specified.
C. Provide undercoat paint produced by the same manufa cturer as the finish
coats. Use only thinners approved by the paint manu facturer, and use only
to recommended limits.
D. VOC Content: For field applications that are inside the weatherproofing
system, paints and coating to comply with VOC conte nt limits of
authorities having jurisdiction and the following V OC content limits:
1. Flat Paints and Coatings: 50 g/L.
2. Non-flat Paints and Coatings: 150 g/L.
3. Dry-Fog Coatings: 400 g/L.
4. Primers, Sealers, and Undercoaters: 200 g/L.
09 91 00 - 7
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
5. Anticorrosive and Antirust Paints applied to Ferrou s Metals: 250 g/L.
6. Zinc-Rich Industrial Maintenance Primers: 340 g/L.
7. Pretreatment Wash Primers: 420 g/L.
8. Shellacs, Clear: 730 g/L.
9. Shellacs, Pigmented: 550 g/L.
E. VOC test method for paints and coatings is to be in accordance with
40 CFR 59 (EPA Method 24). Part 60, Appendix A with the exempt compounds’
content determined by Method 303 (Determination of Exempt Compounds) in
the South Coast Air Quality Management District’s ( SCAQMD) “Laboratory
Methods of Analysis for Enforcement Samples” manual .
2.3 PLASTIC TAPE:
A. Pigmented vinyl plastic film in colors as specified in Section 09 06 00,
SCHEDULE FOR FINISHES or specified.
B. Pressure sensitive adhesive back.
C. Snap on coil plastic markers.
D. Widths as shown on construction documents.
PART 3 - EXECUTION
3.1 JOB CONDITIONS:
A. Safety: Observe required safety regulations and man ufacturer's warning and
instructions for storage, handling and application of painting materials.
1. Take necessary precautions to protect personnel and property from
hazards due to falls, injuries, toxic fumes, fire, explosion, or other
harm.
2. Deposit soiled cleaning rags and waste materials in metal containers
approved for that purpose. Dispose of such items of f the site at end of
each day’s work.
B. Atmospheric and Surface Conditions:
1. Do not apply coating when air or substrate conditio ns are:
a. Less than 3 degrees C (5 degrees F) above dew point .
b. Below 10 degrees C (50 degrees F) or over 35 degree s C
(95 degrees F), unless specifically pre-approved by the COR and the
product manufacturer. Under no circumstances are ap plication
conditions to exceed manufacturer recommendations.
c. When the relative humidity exceeds 85 percent; or t o damp or wet
surfaces; unless otherwise permitted by the paint m anufacturer’s
printed instructions.
09 91 00 - 8
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
2. Maintain interior temperatures until paint dries ha rd.
3. Do no exterior painting when it is windy and dusty.
4. Do not paint in direct sunlight or on surfaces that the sun will warm.
5. Apply only on clean, dry and frost free surfaces ex cept as follows:
a. Apply water thinned acrylic and cementitious paints to damp (not
wet) surfaces only when allowed by manufacturer's p rinted
instructions.
6. Varnishing:
a. Apply in clean areas and in still air.
b. Before varnishing vacuum and dust area.
c. Immediately before varnishing wipe down surfaces wi th a tack rag.
3.2 INSPECTION:
A. Examine the areas and conditions where painting and finishing are to be
applied and correct any conditions detrimental to t he proper and timely
completion of the work. Do not proceed with the wor k until unsatisfactory
conditions are corrected to permit proper installat ion of the work.
3.3 GENERAL WORKMANSHIP REQUIREMENTS:
A. Application may be by brush or roller. Spray applic ation only upon
acceptance from the COR in writing.
B. Furnish to the COR a painting schedule indicating w hen the respective
coats of paint for the various areas and surfaces w ill be completed. This
schedule is to be kept current as the job progresse s.
C. Protect work at all times. Protect all adjacent wor k and materials by
suitable covering or other method during progress o f work. Upon completion
of the work, remove all paint and varnish spots fro m floors, glass and
other surfaces. Remove from the premises all rubbis h and accumulated
materials of whatever nature not caused by others a nd leave work in a
clean condition.
D. Remove and protect hardware, accessories, device pl ates, lighting
fixtures, and factory finished work, and similar it ems, or provide in
place protection. Upon completion of each space, ca refully replace all
removed items by workmen skilled in the trades invo lved.
E. When indicated to be painted, remove electrical pan el box covers and doors
before painting walls. Paint separately and re-inst all after all paint is
dry.
09 91 00 - 9
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
F. Materials are to be applied under adequate illumina tion, evenly spread and
flowed on smoothly to avoid runs, sags, holidays, b rush marks, air bubbles
and excessive roller stipple.
G. Apply materials with a coverage to hide substrate c ompletely. When color,
stain, dirt or undercoats show through final coat o f paint, the surface is
to be covered by additional coats until the paint f ilm is of uniform
finish, color, appearance and coverage, at no addit ional cost to the
Government.
H. All coats are to be dry to manufacturer’s recommend ations before applying
succeeding coats.
I. All suction spots or “hot spots” in plaster after t he application of the
first coat are to be touched up before applying the second coat.
J. Do not apply paint behind frameless mirrors that us e mastic for adhering
to wall surface.
3.4 SURFACE PREPARATION:
A. General:
1. The Contractor shall be held wholly responsible for the finished
appearance and satisfactory completion of painting work. Properly
prepare all surfaces to receive paint, which includ es cleaning,
sanding, and touching-up of all prime coats applied under other
Sections of the work. Broom clean all spaces before painting is
started. All surfaces to be painted or finished are to be completely
dry, clean and smooth.
2. See other sections of specifications for specified surface conditions
and prime coat.
3. Perform preparation and cleaning procedures in stri ct accordance with
the paint manufacturer’s instructions and as herein specified, for each
particular substrate condition.
4. Clean surfaces before applying paint or surface tre atments with
materials and methods compatible with substrate and specified finish.
Remove any residue remaining from cleaning agents u sed. Do not use
solvents, acid, or steam on concrete and masonry. S chedule the cleaning
and painting so that dust and other contaminants fr om the cleaning
process will not fall in wet, newly painted surface s.
B. Ferrous Metals:
09 91 00 - 10
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
1. Remove oil, grease, soil, drawing and cutting compo unds, flux and other
detrimental foreign matter in accordance with SSPC- SP 1 (Solvent
Cleaning).
2. Remove loose mill scale, rust, and paint, by hand o r power tool
cleaning, as defined in SSPC-SP 2 (Hand Tool Cleani ng) and SSPC-SP 3
(Power Tool Cleaning).
3. Fill dents, holes and similar voids and depressions in flat exposed
surfaces of hollow steel doors and frames, access p anels, roll-up steel
doors and similar items specified to have semi-glos s or gloss finish
with TT-F-322D (Filler, Two-Component Type, For Den ts, Small Holes and
Blow-Holes). Finish flush with adjacent surfaces.
a. Fill flat head countersunk screws used for permanen t anchors.
b. Do not fill screws of item intended for removal suc h as glazing
beads.
4. Spot prime abraded and damaged areas in shop prime coat which expose
bare metal with same type of paint used for prime c oat. Feather edge of
spot prime to produce smooth finish coat.
5. Spot prime abraded and damaged areas which expose b are metal of factory
finished items with paint as recommended by manufac turer of item.
3.5 PAINT PREPARATION:
A. Thoroughly mix painting materials to ensure uniform ity of color, complete
dispersion of pigment and uniform composition.
B. Do not thin unless necessary for application and wh en finish paint is used
for body and prime coats. Use materials and quantit ies for thinning as
specified in manufacturer's printed instructions.
C. Remove paint skins, then strain paint through comme rcial paint strainer to
remove lumps and other particles.
D. Mix two (2) component and two (2) part paint and th ose requiring additives
in such a manner as to uniformly blend as specified in manufacturer's
printed instructions unless specified otherwise.
E. For tinting required to produce exact shades specif ied, use color pigment
recommended by the paint manufacturer.
3.6 APPLICATION:
A. Start of surface preparation or painting will be co nstrued as acceptance
of the surface as satisfactory for the application of materials.
09 91 00 - 11
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
B. Unless otherwise specified, apply paint in three (3 ) coats; prime, body,
and finish. When two (2) coats applied to prime coa t are the same, first
coat applied over primer is body coat and second co at is finish coat.
C. Apply each coat evenly and cover substrate complete ly.
D. Allow not less than 48 hours between application of succeeding coats,
except as allowed by manufacturer's printed instruc tions, and approved by
COR.
E. Apply by brush or roller. Spray application for new or existing occupied
spaces only upon approval by acceptance from COR in writing.
1. Apply painting materials specifically required by m anufacturer to be
applied by spraying.
2. In new construction and in existing occupied spaces , where paint is
applied by spray, mask or enclose with polyethylene , or similar air
tight material with edges and seams continuously se aled including items
specified in “Building and Structural Work Field Pa inting”; “Work not
Painted”; motors, controls, telephone, and electric al equipment, fronts
of sterilizes and other recessed equipment and simi lar prefinished
items.
F. Do not paint in closed position operable items such as access doors and
panels, window sashes, overhead doors, and similar items except overhead
roll-up doors and shutters.
3.7 PRIME PAINTING:
A. After surface preparation, prime surfaces before ap plication of body and
finish coats, except as otherwise specified.
B. Spot prime and apply body coat to damaged and abrad ed painted surfaces
before applying succeeding coats.
C. Additional field applied prime coats over shop or f actory applied prime
coats are not required except for exterior exposed steel apply an
additional prime coat.
D. Prime rabbets for stop and face glazing of wood, an d for face glazing of
steel.
E. Metals except boilers, incinerator stacks, and engi ne exhaust pipes:
1. Steel and iron: MPI 79 (Marine Alkyd Metal Primer). Use MPI 101 (Cold
Curing Epoxy Primer) where MPI 108 (High Build Epox y Marine Coating
finish is specified.
09 91 00 - 12
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
3.8 PAINT COLOR:
A. Color and gloss of finish coats is specified in Sec tion 09 06 00, SCHEDULE
FOR FINISHES.
B. For additional requirements regarding color see Art icles, “REFINISHING
EXISTING PAINTED SURFACE” and “MECHANICAL AND ELECT RICAL FIELD PAINTING
SCHEDULE”.
C. Coat Colors:
1. Color of priming coat: Lighter than body coat.
2. Color of body coat: Lighter than finish coat.
3. Color prime and body coats to not show through the finish coat and to
mask surface imperfections or contrasts.
D. Painting, Caulking, Closures, and Fillers Adjacent to Casework:
1. Paint to match color of casework where casework has a paint finish.
2. Paint to match color of wall where casework is stai nless steel, plastic
laminate, or varnished wood.
3.9 MECHANICAL AND ELECTRICAL WORK FIELD PAINTING SCHEDULE:
A. Field painting of mechanical and electrical consist s of cleaning,
touching-up abraded shop prime coats, and applying prime, body and finish
coats to materials and equipment if not factory fin ished in space
scheduled to be finished.
B. In spaces not scheduled to be finish painted in Sec tion 09 06 00, SCHEDULE
FOR FINISHES paint as specified below.
C. Paint various systems specified in Division 02 – EX ISTING CONDITIONS,
Division 23 – HEATING, VENTILATION AND AIR-CONDITIO NING, Division 26 –
ELECTRICAL.
D. Paint after tests have been completed.
E. Omit prime coat from factory prime-coated items.
F. Finish painting of mechanical and electrical equipm ent is not required
when located in interstitial spaces, above suspende d ceilings, in
concealed areas such as pipe and electric closets, pipe basements, pipe
tunnels, trenches, attics, roof spaces, shafts and furred spaces except on
electrical conduit containing feeders 600 volts or more.
G. Omit field painting of items specified in “BUILDING AND STRUCTURAL WORK
FIELD PAINTING”; “Building and Structural Work not Painted”.
H. Color:
1. Paint items having no color specified in Section 09 06 00, SCHEDULE FOR
FINISHES to match surrounding surfaces.
09 91 00 - 13
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
2. Paint colors as specified in Section 09 06 00, SCHE DULE FOR FINISHES
except for following:
a. Gray: Heating, ventilating, air conditioning and re frigeration
equipment (except as required to match surrounding surfaces), and
water and sewage treatment equipment and sewage eje ction equipment.
I. Apply paint systems on properly prepared and primed surface as follows:
1. Exterior Locations:
a. Apply two (2) coats of MPI 10 (Exterior Latex, Flat ) to galvanized
and zinc-copper alloy metal.
2. Interior Locations:
a. Apply two (2) coats of MPI 47 (Interior Alkyd, Semi -Gloss) to
following items:
1) Metal under 94 degrees C (201 degrees F) of items s uch as bare
piping, fittings, hangers and supports.
2) Equipment and systems such as hinged covers and fra mes for
control cabinets and boxes, cast-iron radiators, el ectric
conduits and panel boards.
3) Heating, ventilating, air conditioning, plumbing eq uipment, and
machinery having shop prime coat and not factory fi nished.
d. Apply two (2) coats of MPI 22 (High Heat Resista nt Coating) to
ferrous metal surface over 94 degrees K (290 degree s F) of following
items:
4) Steam line flanges, bare pipe, fittings, valves, ha ngers and
supports over 94 degrees K (290 degrees F).
3. Other exposed locations:
b. Cloth jackets of insulation of ducts and pipes i n connection with
plumbing, air conditioning, ventilating refrigerati on and heating
systems: One (1) coat of MPI 50 (Interior Latex Pri mer Sealer) and
one (1) coat of MPI 10 (Exterior Latex, Flat).
3.10 BUILDING AND STRUCTURAL WORK FIELD PAINTING:
A. Painting and finishing of interior and exterior wor k except as specified
here-in-after.
1. Painting and finishing of new and existing work inc luding colors and
gloss of finish selected is specified in Finish Sch edule, Section 09 06
00, SCHEDULE FOR FINISHES.
09 91 00 - 14
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
2. Painting of disturbed, damaged and repaired or patc hed surfaces when
entire space is not scheduled for complete repainti ng or refinishing.
3. Painting of ferrous metal and galvanized metal.
4. Painting of wood with fire retardant paint exposed in attics, when used
as mechanical equipment space (except shingles).
5. Identity painting and safety painting.
B. Building and Structural Work not Painted:
1. Prefinished items:
a. Casework, doors, elevator entrances and cabs, metal panels, wall
covering, and similar items specified factory finis hed under other
sections.
b. Factory finished equipment and pre-engineered metal building
components such as metal roof and wall panels.
2. Finished surfaces:
a. Hardware except ferrous metal.
b. Anodized aluminum, stainless steel, chromium platin g, copper, and
brass, except as otherwise specified.
c. Signs, fixtures, and other similar items integrally finished.
5. Labels:
a. Code required label, such as Underwriters Laborator ies Inc.,
Intertek Testing Service or Factory Mutual Research Corporation.
b. Identification plates, instruction plates, performa nce rating, and
nomenclature.
3.11 IDENTITY PAINTING SCHEDULE:
A. Identify designated service in new buildings or pro jects with extensive
remodeling in accordance with ASME A13.1, unless sp ecified otherwise, on
exposed piping, piping above removable ceilings, pi ping in accessible pipe
spaces, interstitial spaces, and piping behind acce ss panels. For existing
spaces where work is minor match existing.
1. Legend may be identified using snap-on coil plastic markers or by paint
stencil applications.
2. Apply legends adjacent to changes in direction, on branches, where
pipes pass through walls or floors, adjacent to ope rating accessories
such as valves, regulators, strainers and cleanouts a minimum of 12.2 M
(40 feet) apart on straight runs of piping. Identif ication next to
plumbing fixtures is not required.
3. Locate Legends clearly visible from operating posit ion.
09 91 00 - 15
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
4. Use arrow to indicate direction of flow using black stencil paint.
5. Identify pipe contents with sufficient additional d etails such as
temperature, pressure, and contents to identify pos sible hazard. Insert
working pressure shown on construction documents wh ere asterisk appears
for High, Medium, and Low Pressure designations as follows:
a. High Pressure - 414 kPa (60 psig) and above.
6. Legend name in full or in abbreviated form as follo ws:
COLOR OF COLOR OF COLOR OF LEGEND
PIPING EXPOSED PIPING BACKGROUND LETTERS ABBREVIATIONS
High Pressure Steam Green White H.P. *
High Pressure Condensate
Return Green White H.P. Ret *
Green White L.P. Ret *
Pumped Condensate Green White Pump Cond
3.12 PROTECTION CLEAN UP, AND TOUCH-UP:
A. Protect work from paint droppings and spattering by use of masking, drop
cloths, removal of items or by other approved metho ds.
B. Upon completion, clean paint from hardware, glass a nd other surfaces and
items not required to be painted of paint drops or smears.
C. Before final inspection, touch-up or refinished in a manner to produce
solid even color and finish texture, free from defe cts in work which was
damaged or discolored.
- - - E N D - - -
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 11 - 1
SECTION 26 05 11 REQUIREMENTS FOR ELECTRICAL INSTALLATIONS
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section applies to all sections of Division 26 .
B. Furnish and install electrical systems, materials, equipment, and
accessories in accordance with the specifications a nd drawings.
Capacities and ratings of motors, conductors and ca ble, , and other
items and arrangements for the specified items are shown on the
drawings.
C. D. Conductor ampacities specified or shown on the d rawings are based
on copper conductors, with the conduit and raceways sized per NEC.
Aluminum conductors are prohibited.
1.2 MINIMUM REQUIREMENTS
A. The latest International Building Code (IBC), Under writers
Laboratories, Inc. (UL), Institute of Electrical an d Electronics
Engineers (IEEE), and National Fire Protection Asso ciation (NFPA) codes
and standards are the minimum requirements for mate rials and
installation.
B. The drawings and specifications shall govern in tho se instances where
requirements are greater than those stated in the a bove codes and
standards.
1.3 TEST STANDARDS
A. All materials and equipment shall be listed, labele d, or certified by a
Nationally Recognized Testing Laboratory (NRTL) to meet Underwriters
Laboratories, Inc. (UL), standards where test stand ards have been
established. Materials and equipment which are not covered by UL
standards will be accepted, providing that material s and equipment are
listed, labeled, certified or otherwise determined to meet the safety
requirements of a NRTL. Materials and equipment whi ch no NRTL accepts,
certifies, lists, labels, or determines to be safe, will be considered
if inspected or tested in accordance with national industrial
standards, such as ANSI, NEMA, and NETA. Evidence o f compliance shall
include certified test reports and definitive shop drawings.
B. Definitions:
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 11 - 2
1. Listed: Materials and equipment included in a list published by an
organization that is acceptable to the Authority Ha ving Jurisdiction
and concerned with evaluation of products or servic es, that
maintains periodic inspection of production or list ed materials and
equipment or periodic evaluation of services, and w hose listing
states that the materials and equipment either meet s appropriate
designated standards or has been tested and found s uitable for a
specified purpose.
2. Labeled: Materials and equipment to which has been attached a label,
symbol, or other identifying mark of an organizatio n that is
acceptable to the Authority Having Jurisdiction and concerned with
product evaluation, that maintains periodic inspect ion of production
of labeled materials and equipment, and by whose la beling the
manufacturer indicates compliance with appropriate standards or
performance in a specified manner.
3. Certified: Materials and equipment which:
a. Have been tested and found by a NRTL to meet nation ally
recognized standards or to be safe for use in a spe cified manner.
b. Are periodically inspected by a NRTL.
c. Bear a label, tag, or other record of certification .
4. Nationally Recognized Testing Laboratory: Testing l aboratory which
is recognized and approved by the Secretary of Labo r in accordance
with OSHA regulations.
1.4 QUALIFICATIONS (PRODUCTS AND SERVICES)
A. Manufacturer’s Qualifications: The manufacturer sha ll regularly and
currently produce, as one of the manufacturer's pri ncipal products, the
materials and equipment specified for this project, and shall have
manufactured the materials and equipment for at lea st three years.
B. Product Qualification:
1. Manufacturer's materials and equipment shall have b een in
satisfactory operation, on three installations of s imilar size and
type as this project, for at least three years.
2. The Government reserves the right to require the Co ntractor to
submit a list of installations where the materials and equipment
have been in operation before approval.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 11 - 3
1.5 APPLICABLE PUBLICATIONS
A. Applicable publications listed in all Sections of D ivision 26 shall be
the latest issue, unless otherwise noted.
B. Products specified in all sections of Division 26 s hall comply with the
applicable publications listed in each section.
1.6 MANUFACTURED PRODUCTS
A. Materials and equipment furnished shall be of curre nt production by
manufacturers regularly engaged in the manufacture of such items, and
for which replacement parts shall be available. Mat erials and
equipment furnished shall be new, and shall have su perior quality and
freshness.
B. When more than one unit of the same class or type o f materials and
equipment is required, such units shall be the prod uct of a single
manufacturer.
C. Equipment Assemblies and Components:
1. Components of an assembled unit need not be product s of the same
manufacturer.
2. Manufacturers of equipment assemblies, which includ e components made
by others, shall assume complete responsibility for the final
assembled unit.
3. Components shall be compatible with each other and with the total
assembly for the intended service.
4. Constituent parts which are similar shall be the pr oduct of a single
manufacturer.
D. Factory wiring and terminals shall be identified on the equipment being
furnished and on all wiring diagrams.
1.7 VARIATIONS FROM CONTRACT REQUIREMENTS
A. Where the Government or the Contractor requests var iations from the
contract requirements, the connecting work and rela ted components shall
include, but not be limited to additions or changes to branch circuits,
circuit protective devices, conduits, wire, feeders , controls, panels
and installation methods.
1.8 MATERIALS AND EQUIPMENT PROTECTION
A. Materials and equipment shall be protected during s hipment and storage
against physical damage, vermin, dirt, corrosive su bstances, fumes,
moisture, cold and rain.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 11 - 4
1. Store materials and equipment indoors in clean dry space with
uniform temperature to prevent condensation.
2. During installation, equipment shall be protected a gainst entry of
foreign matter, and be vacuum-cleaned both inside a nd outside before
testing and operating. Compressed air shall not be used to clean
equipment. Remove loose packing and flammable mater ials from inside
equipment.
3. Damaged equipment shall be repaired or replaced, as determined by
the COR.
4. Painted surfaces shall be protected with factory in stalled removable
heavy kraft paper, sheet vinyl or equal.
5. Damaged paint on equipment shall be refinished with the same quality
of paint and workmanship as used by the manufacture r so repaired
areas are not obvious.
1.9 WORK PERFORMANCE
A. All electrical work shall comply with requirements of the latest NFPA
70 (NEC), NFPA 70B, NFPA 70E, NFPA 99, NFPA 110, OS HA Part 1910 subpart
J – General Environmental Controls, OSHA Part 1910 subpart K – Medical
and First Aid, and OSHA Part 1910 subpart S – Elect rical, in addition
to other references required by contract.
B. Job site safety and worker safety is the responsibi lity of the
Contractor.
C. Electrical work shall be accomplished with all affe cted circuits or
equipment de-energized. However, energized electric al work may be
performed only for the non-destructive and non-inva sive diagnostic
testing(s), or when scheduled outage poses an immin ent hazard to
patient care, safety, or physical security. In such case, all aspects
of energized electrical work, such as the availabil ity of
appropriate/correct personal protective equipment ( PPE) and the use of
PPE, shall comply with the latest NFPA 70E, as well as the following
requirements:
1. Only Qualified Person(s) shall perform energized el ectrical work.
Supervisor of Qualified Person(s) shall witness the work of its
entirety to ensure compliance with safety requireme nts and approved
work plan.
2. At least two weeks before initiating any energized electrical work,
the Contractor and the Qualified Person(s) who is d esignated to
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 11 - 5
perform the work shall visually inspect, verify and confirm that the
work area and electrical equipment can safely accom modate the work
involved.
3. At least two weeks before initiating any energized electrical work,
the Contractor shall develop and submit a job speci fic work plan,
and energized electrical work request to the COR, a nd Medical
Center’s Chief Engineer or his/her designee. At the minimum, the
work plan must include relevant information such as proposed work
schedule, area of work, description of work, name(s ) of Supervisor
and Qualified Person(s) performing the work, equipm ent to be used,
procedures to be used on and near the live electric al equipment,
barriers to be installed, safety equipment to be us ed, and exit
pathways.
4. Energized electrical work shall begin only after th e Contractor has
obtained written approval of the work plan, and the energized
electrical work request from the COR, and Medical C enter’s Chief
Engineer or his/her designee. The Contractor shall make these
approved documents present and available at the tim e and place of
energized electrical work.
5.
D. For work that affects existing electrical systems, arrange, phase and
perform work to assure minimal interference with no rmal functioning of
the facility. Refer to Article OPERATIONS AND STORA GE AREAS under
Section 01 00 00, GENERAL REQUIREMENTS.
E. New work shall be installed and connected to existi ng work neatly,
safely and professionally. Disturbed or damaged wor k shall be replaced
or repaired to its prior conditions, as required by Section 01 00 00,
GENERAL REQUIREMENTS.
F. Coordinate location of equipment and conduit with o ther trades to
minimize interference.
1.10 EQUIPMENT INSTALLATION AND REQUIREMENTS
A. Equipment location shall be as close as practical t o locations shown on
the drawings.
B. Working clearances shall not be less than specified in the NEC.
C. Inaccessible Equipment:
1. Where the Government determines that the Contractor has installed
equipment not readily accessible for operation and maintenance, the
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 11 - 6
equipment shall be removed and reinstalled as direc ted at no
additional cost to the Government.
2. "Readily accessible” is defined as being capable of being reached
quickly for operation, maintenance, or inspections without the use
of ladders, or without climbing or crawling under o r over obstacles
such as, but not limited to, motors, pumps, belt gu ards,
transformers, piping, ductwork, conduit and raceway s.
D. Electrical service entrance equipment and arrangeme nts for temporary
and permanent connections to the electric utility c ompany’s system
shall conform to the electric utility company's req uirements.
Coordinate fuses, circuit breakers and relays with the electric utility
company’s system, and obtain electric utility compa ny approval for
sizes and settings of these devices.
1.11 EQUIPMENT IDENTIFICATION
A. In addition to the requirements of the NEC, install an identification
sign which clearly indicates information required f or use and
maintenance of items such as switchboards and switc hgear, panelboards,
cabinets, motor controllers, fused and non-fused sa fety switches,
generators, automatic transfer switches, separately enclosed circuit
breakers, individual breakers and controllers in sw itchboards,
switchgear and motor control assemblies, control de vices and other
significant equipment.
B. Identification signs for Normal Power System equipm ent shall be
laminated black phenolic resin with a white core wi th engraved
lettering. Identification signs for Essential Elect rical System (EES)
equipment, as defined in the NEC, shall be laminate d red phenolic resin
with a white core with engraved lettering. Letterin g shall be a minimum
of 12 mm (1/2 inch) high. Identification signs shal l indicate equipment
designation, rated bus amperage, voltage, number of phases, number of
wires, and type of EES power branch as applicable. Secure nameplates
with screws.
C. Install adhesive arc flash warning labels on all eq uipment as required
by the latest NFPA 70E. Label shall show specific a nd correct
information for specific equipment based on its arc flash calculations.
Label shall show the followings:
1. Nominal system voltage.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 11 - 7
2. Equipment/bus name, date prepared, and manufacturer name and
address.
3. Arc flash boundary.
4. Available arc flash incident energy and the corresp onding working
distance.
5. Minimum arc rating of clothing.
6. Site-specific level of PPE.
1.12 SUBMITTALS
A. Submit to the COR in accordance with Section 01 33 23, SHOP DRAWINGS,
PRODUCT DATA, AND SAMPLES.
B. Maintenance and Operation Manuals:
1. Submit as required for systems and equipment specif ied in the
technical sections. Furnish in hardcover binders or an approved
equivalent.
2. Inscribe the following identification on the cover: the words
"MAINTENANCE AND OPERATION MANUAL," the name and lo cation of the
system, material, equipment, building, name of Cont ractor, and
contract name and number. Include in the manual the names,
addresses, and telephone numbers of each subcontrac tor installing
the system or equipment and the local representativ es for the
material or equipment.
3. Provide a table of contents and assemble the manual to conform to
the table of contents, with tab sheets placed befor e instructions
covering the subject. The instructions shall be leg ible and easily
read, with large sheets of drawings folded in.
4. The manuals shall include:
a. Internal and interconnecting wiring and control dia grams with
data to explain detailed operation and control of t he equipment.
b. A control sequence describing start-up, operation, and shutdown.
c. Description of the function of each principal item of equipment.
d. Installation instructions.
e. Safety precautions for operation and maintenance.
f. Diagrams and illustrations.
g. Periodic maintenance and testing procedures and fre quencies,
including replacement parts numbers.
h. Performance data.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 11 - 8
i. Pictorial "exploded" parts list with part numbers. Emphasis shall
be placed on the use of special tools and instrumen ts. The list
shall indicate sources of supply, recommended spare and
replacement parts, and name of servicing organizati on.
j. List of factory approved or qualified permanent ser vicing
organizations for equipment repair and periodic tes ting and
maintenance, including addresses and factory certif ication
qualifications.
C. Approvals will be based on complete submission of s hop drawings,
manuals, test reports, certifications, and samples as applicable.
D. After approval and prior to installation, furnish t he COR with one
sample of each of the following:
1. A minimum 300 mm (12 inches) length of each type an d size of wire
and cable along with the tag from the coils or reel s from which the
sample was taken. The length of the sample shall be sufficient to
show all markings provided by the manufacturer.
2. Each type of conduit coupling, bushing, and termina tion fitting.
3. Conduit hangers, clamps, and supports.
4. Duct sealing compound.
5. Each type of receptacle, toggle switch, lighting co ntrol sensor,
outlet box, manual motor starter, device wall plate , engraved
nameplate, wire and cable splicing and terminating material, and
branch circuit single pole molded case circuit brea ker.
I. Training, manuals, schematics, maintenance sched ules are required on
all new equipment installed. Each new equipment ite m to be labeled
as to equipment identification number, installation date, area
serving, feeder services, voltage, amperage, main b reaker rating,
etc.
1.13 SINGULAR NUMBER
A. Where any device or part of equipment is referred t o in these
specifications in the singular number (e.g., "the s witch"), this
reference shall be deemed to apply to as many such devices as are
required to complete the installation as shown on t he drawings.
1.14 ACCEPTANCE CHECKS AND TESTS
A. The Contractor shall furnish the instruments, mater ials, and labor for
tests.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 11 - 9
B. Where systems are comprised of components specified in more than one
section of Division 26, the Contractor shall coordi nate the
installation, testing, and adjustment of all compon ents between various
manufacturer’s representatives and technicians so t hat a complete,
functional, and operational system is delivered to the Government.
C. When test results indicate any defects, the Contrac tor shall repair or
replace the defective materials or equipment, and r epeat the tests for
the equipment. Repair, replacement, and re-testing shall be
accomplished at no additional cost to the Governmen t.
1.15 WARRANTY
A. All work performed and all equipment and material f urnished under this
Division shall be free from defects and shall remai n so for a period of
one year from the date of acceptance of the entire installation by the
Contracting Officer for the Government.
1.16 INSTRUCTION
A. Instruction to designated Government personnel shal l be provided for
the particular equipment or system as required in e ach associated
technical specification section.
B. Furnish the services of competent and factory-train ed instructors to
give full instruction in the adjustment, operation, and maintenance of
the specified equipment and system, including perti nent safety
requirements. Instructors shall be thoroughly famil iar with all
aspects of the installation, and shall be factory-t rained in operating
theory as well as practical operation and maintenan ce procedures.
C. A training schedule shall be developed and submitte d by the Contractor
and approved by the COR at least 30 days prior to t he planned training.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
---END---
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 19 - 1
SECTION 26 05 19 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies the furnishing, installation , connection, and
testing of the electrical conductors and cables for use in electrical
systems rated 600 V and below, indicated as cable(s ), conductor(s),
wire, or wiring in this section.
1.2 RELATED WORK
A. Section 26 05 11, REQUIREwMENTS FOR ELECTRICAL INST ALLATIONS:
Requirements that apply to all sections of Division 26.
B. Section 26 05 26, GROUNDING AND BONDING FOR ELECTRI CAL SYSTEMS:
Requirements for personnel safety and to provide a low impedance path
for possible ground fault currents.
C. Section 26 05 33, RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS: Conduits
for conductors and cables.
D. Section 26 05 41, UNDERGROUND ELECTRICAL CONSTRUCTI ON: Installation of
conductors and cables in manholes and ducts.
1.3 QUALITY ASSURANCE
A. Quality Assurance shall be in accordance with Parag raph, QUALIFICATIONS
(PRODUCTS AND SERVICES) in Section 26 05 11, REQUIR EMENTS FOR
ELECTRICAL INSTALLATIONS.
1.4 SUBMITTALS
A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11,
REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following
requirements:
1. Shop Drawings:
a. Submit sufficient information to demonstrate compli ance with
drawings and specifications.
b. Submit the following data for approval:
1) Electrical ratings and insulation type for each con ductor and
cable.
2) Splicing materials and pulling lubricant.
2. Certifications: Two weeks prior to final inspection , submit the
following.
a. Certification by the manufacturer that the conducto rs and cables
conform to the requirements of the drawings and spe cifications.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 19 - 2
b. Certification by the Contractor that the conductors and cables
have been properly installed, adjusted, and tested.
1.5 APPLICABLE PUBLICATIONS
A. Publications listed below (including amendments, ad denda, revisions,
supplements and errata) form a part of this specifi cation to the extent
referenced. Publications are reference in the text by designation only.
B. American Society of Testing Material (ASTM):
D2301-10................Standard Specification for Vinyl Chloride
Plastic Pressure-Sensitive Electrical
Insulating Tape
D2304-10................Test Method for Thermal End urance of Rigid
Electrical Insulating Materials
D3005-10................Low-Temperature Resistant V inyl Chloride
Plastic Pressure-Sensitive Electrical
Insulating Tape
C. National Electrical Manufacturers Association (NEMA ):
WC 70-09................Power Cables Rated 2000 Vol ts or Less for the
Distribution of Electrical Energy
D. National Fire Protection Association (NFPA):
70-17...................National Electrical Code (N EC)
E. Underwriters Laboratories, Inc. (UL):
44-14...................Thermoset-Insulated Wires a nd Cables
83-14...................Thermoplastic-Insulated Wir es and Cables
467-13..................Grounding and Bonding Equip ment
486A-486B-13............Wire Connectors
486C-13.................Splicing Wire Connectors
486D-15.................Sealed Wire Connector Syste ms
486E-15.................Equipment Wiring Terminals for Use with
Aluminum and/or Copper Conductors
493-07..................Thermoplastic-Insulated Und erground Feeder and
Branch Circuit Cables
514B-12.................Conduit, Tubing, and Cable Fittings
PART 2 - PRODUCTS
2.1 CONDUCTORS AND CABLES
A. Conductors and cables shall be in accordance with A STM, NEMA, NFPA, UL,
as specified herein, and as shown on the drawings.
B. All conductors shall be copper.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 19 - 3
C. Single Conductor and Cable:
1. No. 12 AWG: Minimum size, except where smaller size s are specified
herein or shown on the drawings.
2. No. 12 AWG and larger: Stranded.
3. No. 14 AWG and smaller: Solid; except shall be stra nded for final
connection to motors, transformers, and vibrating e quipment.
4. Insulation: XHHW-2.
E. Color Code:
1. No. 10 AWG and smaller: Solid color insulation or s olid color
coating.
2. No. 8 AWG and larger: Color-coded using one of the following
methods:
a. Solid color insulation or solid color coating.
b. Stripes, bands, or hash marks of color specified.
c. Color using 19 mm (0.75 inches) wide tape.
4. For modifications and additions to existing wiring systems, color
coding shall conform to the existing wiring system.
5. Conductors shall be color-coded as follows:
208/120 V Phase 480/277 V
Black A Brown
Red B Yellow
Blue C Orange
White Neutral Gray *
* or white with colored (other than green) tracer.
6. Lighting circuit “switch legs”, and 3-way and 4-way switch
“traveling wires,” shall have color coding that is unique and
distinct (e.g., pink and purple) from the color cod ing indicated
above. The unique color codes shall be solid and in accordance with
the NEC. Coordinate color coding in the field with the COR.
7. Color code for isolated power system wiring shall b e in accordance
with the NEC.
2.2 SPLICES
A. Splices shall be in accordance with NEC and UL.
B. Above Ground Splices for No. 10 AWG and Smaller:
1. Solderless, screw-on, reusable pressure cable type, with integral
insulation, approved for copper and aluminum conduc tors.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 19 - 4
2. The integral insulator shall have a skirt to comple tely cover the
stripped conductors.
3. The number, size, and combination of conductors use d with the
connector, as listed on the manufacturer's packagin g, shall be
strictly followed.
C. Above Ground Splices for No. 8 AWG to No. 4/0 AWG:
1. Compression, hex screw, or bolt clamp-type of high conductivity and
corrosion-resistant material, listed for use with c opper and
aluminum conductors.
2. Insulate with materials approved for the particular use, location,
voltage, and temperature. Insulation level shall be not less than
the insulation level of the conductors being joined .
3. Splice and insulation shall be product of the same manufacturer.
4. All bolts, nuts, and washers used with splices shal l be cadmium-
plated steel.
D.
G. Plastic electrical insulating tape: Per ASTM D23 04, flame-retardant,
cold and weather resistant.
2.3 CONNECTORS AND TERMINATIONS
A. Mechanical type of high conductivity and corrosion- resistant material,
listed for use with copper and aluminum conductors.
B. Long barrel compression type of high conductivity a nd
corrosion-resistant material, with minimum of two c ompression indents
per wire, listed for use with copper and aluminum c onductors.
C. All bolts, nuts, and washers used to connect connec tions and
terminations to bus bars or other termination point s shall be cadmium-
plated steel.
2.4 CONTROL WIRING
A. Unless otherwise specified elsewhere in these speci fications, control
wiring shall be as specified herein, except that th e minimum size shall
be not less than No. 14 AWG.
B. Control wiring shall be sized such that the voltage drop under in-rush
conditions does not adversely affect operation of t he controls.
2.5 WIRE LUBRICATING COMPOUND
A. Lubricating compound shall be suitable for the wire insulation and
conduit, and shall not harden or become adhesive.
B. Shall not be used on conductors for isolated power systems.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 19 - 5
PART 3 - EXECUTION
3.1 GENERAL
A. Neutral Conductor Installation
1. The use of single-phase, multi-wire branch circuits with a
common neutral is not permitted. All branch circuit s shall be
furnished and installed with an individual accompan ying
neutral, sized the same as the phase conductors.
A. Installation shall be in accordance with the NEC, a s shown on the
drawings, and manufacturer’s instructions.
B. Install all conductors in raceway systems.
C. Splice conductors only in outlet boxes, junction bo xes, pullboxes,
manholes, or handholes.
D. Conductors of different systems (e.g., 120 V and 27 7 V) shall not be
installed in the same raceway.
E. Install cable supports for all vertical feeders in accordance with the
NEC. Provide split wedge type which firmly clamps e ach individual cable
and tightens due to cable weight.
F. In panelboards, cabinets, wireways, switches, enclo sures, and equipment
assemblies, neatly form, train, and tie the conduct ors with non-
metallic ties.
G. For connections to motors, transformers, and vibrat ing equipment,
stranded conductors shall be used only from the las t fixed point of
connection to the motors, transformers, or vibratin g equipment.
H. Use expanding foam or non-hardening duct-seal to se al conduits entering
a building, after installation of conductors.
I. Conductor and Cable Pulling:
1. Provide installation equipment that will prevent th e cutting or
abrasion of insulation during pulling. Use lubrican ts approved for
the cable.
2. Use nonmetallic pull ropes.
3. Attach pull ropes by means of either woven basket g rips or pulling
eyes attached directly to the conductors.
4. All conductors in a single conduit shall be pulled simultaneously.
5. Do not exceed manufacturer’s recommended maximum pu lling tensions
and sidewall pressure values.
J. No more than three branch circuits shall be install ed in any one
conduit.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 19 - 6
K. When stripping stranded conductors, use a tool that does not damage the
conductor or remove conductor strands.
3.2 SPLICE AND TERMINATION INSTALLATION
A. Splices and terminations shall be mechanically and electrically secure,
and tightened to manufacturer’s published torque va lues using a torque
screwdriver or wrench.
B. Where the Government determines that unsatisfactory splices or
terminations have been installed, replace the splic es or terminations
at no additional cost to the Government.
3.3 CONDUCTOR IDENTIFICATION
A. When using colored tape to identify phase, neutral, and ground
conductors larger than No. 8 AWG, apply tape in hal f-overlapping turns
for a minimum of 75 mm (3 inches) from terminal poi nts, and in junction
boxes, pullboxes, and manholes. Apply the last two laps of tape with no
tension to prevent possible unwinding. Where cable markings are covered
by tape, apply tags to cable, stating size and insu lation type.
3.4 EXISTING CONDUCTORS
A. Unless specifically indicated on the plans, existin g conductors shall
not be reused.
3.5 ACCEPTANCE CHECKS AND TESTS
A. Perform in accordance with the manufacturer's recom mendations. In
addition, include the following:
1. Visual Inspection and Tests: Inspect physical condi tion.
2. Electrical tests:
a. After installation but before connection to utiliza tion devices,
such as fixtures, motors, or appliances, test condu ctors phase-
to-phase and phase-to-ground resistance with an ins ulation
resistance tester. Existing conductors to be reused shall also
be tested.
b. Applied voltage shall be 500 V DC for 300 V rated c able, and 1000
V DC for 600 V rated cable. Apply test for one minu te or until
reading is constant for 15 seconds, whichever is lo nger. Minimum
insulation resistance values shall not be less than 25 megohms
for 300 V rated cable and 100 megohms for 600 V rat ed cable.
c. Perform phase rotation test on all three-phase circ uits.
- - - END - - -
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 26 - 1
SECTION 26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies the furnishing, installation , connection, and
testing of grounding and bonding equipment, indicat ed as grounding
equipment in this section.
B. C. The terms “connect” and “bond” are used intercha ngeably in this
section and have the same meaning.
1.2 RELATED WORK
A. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTA LLATIONS:
Requirements that apply to all sections of Division 26.
B. Section 26 05 19, LOW-VOLTAGE ELECTRICAL POWER COND UCTORS AND CABLES:
Low-voltage conductors.
C. Section 26 05 33, RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS: Conduit and
boxes.
1.3 QUALITY ASSURANCE
A. Quality Assurance shall be in accordance with Parag raph, QUALIFICATIONS
(PRODUCTS AND SERVICES) in Section 26 05 11, REQUIR EMENTS FOR
ELECTRICAL INSTALLATIONS.
1.4 APPLICABLE PUBLICATIONS
A. Publications listed below (including amendments, ad denda, revisions,
supplements, and errata) form a part of this specif ication to the
extent referenced. Publications are referenced in t he text by
designation only.
B. American Society for Testing and Materials (ASTM):
B1-13...................Standard Specification for Hard-Drawn Copper
Wire
B3-13...................Standard Specification for Soft or Annealed
Copper Wire
B8-11...................Standard Specification for Concentric-Lay-
Stranded Copper Conductors, Hard, Medium-Hard,
or Soft
D. National Fire Protection Association (NFPA):
70-17...................National Electrical Code (N EC)
70E-15..................National Electrical Safety Code
99-15...................Health Care Facilities
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 26 - 2
E. Underwriters Laboratories, Inc. (UL):
44-14 ..................Thermoset-Insulated Wires a nd Cables
83-14 ..................Thermoplastic-Insulated Wir es and Cables
467-13 .................Grounding and Bonding Equip ment
PART 2 - PRODUCTS
2.1 GROUNDING AND BONDING CONDUCTORS
A. Equipment grounding conductors shall be insulated s tranded copper,
except that sizes No. 10 AWG and smaller shall be s olid copper.
Insulation color shall be continuous green for all equipment grounding
conductors, except that wire sizes No. 4 AWG and la rger shall be
identified per NEC.
B. Bonding conductors shall be bare stranded copper, e xcept that sizes No.
10 AWG and smaller shall be bare solid copper. Bond ing conductors
shall be stranded for final connection to motors, t ransformers, and
vibrating equipment.
C. Conductor sizes shall not be less than shown on the drawings, or not
less than required by the NEC, whichever is greater .
D. Insulation: THWN-2.
PART 3 - EXECUTION
3.1 GENERAL
A. Installation shall be in accordance with the NEC, a s shown on the
drawings, and manufacturer’s instructions.
3.2 RACEWAY
A. Conduit Systems:
1. Ground all metallic conduit systems. All metallic c onduit systems
shall contain an equipment grounding conductor.
2. Non-metallic conduit systems, except non-metallic f eeder conduits
that carry a grounded conductor from exterior trans formers to
interior or building-mounted service entrance equip ment, shall
contain an equipment grounding conductor.
3. Metallic conduit that only contains a grounding con ductor, and is
provided for its mechanical protection, shall be bo nded to that
conductor at the entrance and exit from the conduit .
4. Metallic conduits which terminate without mechanica l connection to
an electrical equipment housing by means of locknut and bushings or
adapters, shall be provided with grounding bushings . Connect
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 26 - 3
bushings with a equipment grounding conductor to th e equipment
ground bus.
B. Feeders and Branch Circuits: Install equipment grou nding conductors
with all feeders, and power and lighting branch cir cuits.
C. Boxes, Cabinets, Enclosures, and Panelboards:
1. Bond the equipment grounding conductor to each pull box, junction
box, outlet box, device box, cabinets, and other en closures through
which the conductor passes (except for special grou nding systems for
intensive care units and other critical units shown ).
2. Provide lugs in each box and enclosure for equipmen t grounding
conductor termination.
E. Receptacles shall not be grounded through their mou nting screws. Ground
receptacles with a jumper from the receptacle green ground terminal to
the device box ground screw and a jumper to the bra nch circuit
equipment grounding conductor.
F. Ground lighting fixtures to the equipment grounding conductor of the
wiring system. Fixtures connected with flexible con duit shall have a
green ground wire included with the power wires fro m the fixture
through the flexible conduit to the first outlet bo x.
G. Fixed electrical appliances and equipment shall be provided with a
ground lug for termination of the equipment groundi ng conductor.
H.
3.3 CORROSION INHIBITORS
A. When making grounding and bonding connections, appl y a corrosion
inhibitor to all contact surfaces. Use corrosion in hibitor appropriate
for protecting a connection between the metals used .
---END---
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 33 - 1
SECTION 26 05 33 RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies the furnishing, installation , and connection of
conduit, fittings, and boxes, to form complete, coo rdinated, grounded
raceway systems. Raceways are required for all wiri ng unless shown or
specified otherwise.
B. Definitions: The term conduit, as used in this spec ification, shall
mean any or all of the raceway types specified.
1.2 RELATED WORK
A. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTA LLATIONS: General
electrical requirements and items that are common t o more than one
section of Division 26.
B. Section 26 05 26, GROUNDING AND BONDING FOR ELECTRI CAL SYSTEMS:
Requirements for personnel safety and to provide a low impedance path
for possible ground fault currents.
C. Section 26 05 41, UNDERGROUND ELECTRICAL CONSTRUCTI ON: Underground
conduits.
1.3 QUALITY ASSURANCE
Refer to Paragraph, QUALIFICATIONS, in Section 26 0 5 11, REQUIREMENTS
FOR ELECTRICAL INSTALLATIONS.
1.4 SUBMITTALS
A. Submit six copies of the following in accordance wi th Section 26 05 11,
REQUIREMENTS FOR ELECTRICAL INSTALLATIONS.
1. Shop Drawings:
b. Size and location of panels and pull-boxes.
c. Layout of required conduit penetrations through str uctural
elements.
d. Submit the following data for approval:
1) Raceway types and sizes.
2) Conduit bodies, connectors and fittings.
3) Junction and pull boxes, types and sizes.
2. Certifications: Two weeks prior to final inspection , submit the
following:
a. Certification by the manufacturer that raceways, co nduits,
conduit bodies, connectors, fittings, junction and pull boxes,
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 33 - 2
and all related equipment conform to the requiremen ts of the
drawings and specifications.
b. Certification by the Contractor that raceways, cond uits, conduit
bodies, connectors, fittings, junction and pull box es, and all
related equipment have been properly installed.
1.5 APPLICABLE PUBLICATIONS
A. Publications listed below (including amendments, ad denda, revisions,
supplements, and errata) form a part of this specif ication to the
extent referenced. Publications are referenced in t he text by
designation only.
B. American National Standards Institute (ANSI):
C80.1-05................Electrical Rigid Steel Cond uit
C. National Fire Protection Association (NFPA):
70-11...................National Electrical Code (N EC)
D. Underwriters Laboratories, Inc. (UL):
6-07....................Electrical Rigid Metal Cond uit - Steel
50-95...................Enclosures for Electrical E quipment
467-13..................Grounding and Bonding Equip ment
514A-13.................Metallic Outlet Boxes
514B-12.................Conduit, Tubing, and Cable Fittings
514C-07.................Nonmetallic Outlet Boxes, F lush-Device Boxes
and Covers
651-11..................Schedule 40 and 80 Rigid PV C Conduit and
Fittings
651A-11.................Type EB and A Rigid PVC Con duit
E. National Electrical Manufacturers Association (NEMA ):
TC-2-13.................Electrical Polyvinyl Chlori de (PVC) Tubing and
Conduit
TC-3-13.................PVC Fittings for Use with R igid PVC Conduit and
Tubing
FB1-12..................Fittings, Cast Metal Boxes and Conduit Bodies
for Conduit, Electrical Metallic Tubing and
Cable
FB2.10-13...............Selection and Installation Guidelines for
Fittings for use with Non-Flexible Conduit or
Tubing (Rigid Metal Conduit, Intermediate
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 33 - 3
Metallic Conduit, and Electrical Metallic
Tubing)
FB2.20-12...............Selection and Installation Guidelines for
Fittings for use with Flexible Electrical
Conduit and Cable
F. American Iron and Steel Institute (AISI):
S100-2007...............North American Specificatio n for the Design of
Cold-Formed Steel Structural Members
PART 2 - PRODUCTS
2.1 MATERIAL
A. Conduit Requirements General
1. Conduit within 5’ of the Steam Pit and within the S team Pit shall be
PVC Coated Rigid Metallic Steel Conduit (RMC). Appl y Copper Shield
anti-corrosion compound to all exposed pipe threads or exposed metal.
2. Conduit direct buried farther than 5’ from the Stea m Pit shall be
Schedule 80 PVC.
3. Conduit within 5’ of the Power Panel shall be PVC C oated Rigid
Metallic Steel Conduit (RMC).
4. All supports, connectors, and hardware shall be sta inless steel.
B. Conduit:
1. Size: In accordance with the NEC, but not less than 13 mm (0.75-
inch).
2. Rigid Steel Metallic Conduit (RMC): Shall conform t o UL 6 and ANSI
C80.1.
8. Direct Burial Plastic Conduit: Shall conform to UL 651 and UL 651A,
heavy wall PVC or high density polyethylene (PE).
C. Conduit Fittings:
1. Rigid Steel Metallic Conduit Fittings:
a. Fittings shall meet the requirements of UL 514B and NEMA FB1.
b. Standard threaded couplings, locknuts, bushings, co nduit bodies,
and elbows: Only steel or malleable iron materials are
acceptable. Integral retractable type IMC couplings are also
acceptable.
c. Locknuts: Bonding type with sharp edges for digging into the
metal wall of an enclosure.
d. Bushings: Metallic insulating type, consisting of a n insulating
insert, molded or locked into the metallic body of the fitting.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 33 - 4
Bushings made entirely of metal or nonmetallic mate rial are not
permitted.
e. Erickson (Union-Type) and Set Screw Type Couplings: Approved for
use in concrete are permitted for use to complete a conduit run
where conduit is installed in concrete. Use set scr ews of case-
hardened steel with hex head and cup point to firml y seat in
conduit wall for positive ground. Tightening of set screws with
pliers is prohibited.
f. Sealing Fittings: Threaded cast iron type. Use cont inuous
drain-type sealing fittings to prevent passage of w ater vapor.
In concealed work, install fittings in flush steel boxes with
blank cover plates having the same finishes as that of other
electrical plates in the room.
6. Direct Burial Plastic Conduit Fittings: Fittings shall meet the
requirements of UL 514C and NEMA TC3.
D. Conduit Supports:
1. Parts and Hardware: Stainless Steel.
2. Individual Conduit Hangers: Designed for the purpos e, having a
pre-assembled closure bolt and nut, and provisions for receiving a
hanger rod.
3. 4. Solid Masonry and Concrete Anchors: Self-drillin g expansion
shields, or machine bolt expansion.
E. Outlet, Junction, and Pull Boxes:
1. UL-50 and UL-514A.
2. Within the Steam Pit boxes shall be cast aluminum o r fiberglass.
3. Sheet Metal Boxes adjacent to the power panel shall be stainless
steel.
PART 3 - EXECUTION
3.1 PENETRATIONS
A. Cutting or Holes:
2. Cut holes through concrete and masonry in new an d existing
structures with a diamond core drill or concrete sa w. Pneumatic
hammers, impact electric, hand, or manual hammer-ty pe drills are not
allowed, except when permitted by the /COR where wo rking space is
limited.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 33 - 5
C. Waterproofing: At floor, exterior wall, and roof conduit penetrations,
completely seal the gap around conduit to render it watertight, as
specified in Section 07 92 00, JOINT SEALANTS.
3.2 INSTALLATION, GENERAL
A. In accordance with UL, NEC, NEMA, as shown on drawi ngs, and as
specified herein.
B. Raceway systems used for Essential Electrical Syste ms (EES) shall be
entirely independent of other raceway systems.
C. Install conduit as follows:
1. In complete mechanically and electrically continuou s runs before
pulling in cables or wires.
2. Unless otherwise indicated on the drawings or speci fied herein,
installation of all conduits shall be concealed wit hin finished
walls, floors, and ceilings.
3. Flattened, dented, or deformed conduit is not permi tted. Remove and
replace the damaged conduits with new conduits.
4. Assure conduit installation does not encroach into the ceiling
height head room, walkways, or doorways.
5. Cut conduits square, ream, remove burrs, and draw u p tight.
6. Independently support conduit at 2.4 M (8 feet) on centers with
specified materials and as shown on drawings.
7. Do not use suspended ceilings, suspended ceiling su pporting members,
lighting fixtures, other conduits, cable tray, boxe s, piping, or
ducts to support conduits and conduit runs.
8. Support within 300 mm (12 inches) of changes of dir ection, and
within 300 mm (12 inches) of each enclosure to whic h connected.
9. Close ends of empty conduits with plugs or caps at the rough-in
stage until wires are pulled in, to prevent entry o f debris.
11. Secure conduits to cabinets, junction boxes, pull-b oxes, and outlet
boxes with bonding type locknuts. For rigid steel a nd IMC conduit
installations, provide a locknut on the inside of t he enclosure,
made up wrench tight. Do not make conduit connectio ns to junction
box covers.
12. Flashing of penetrations of the roof membrane is sp ecified in
Section 07 60 00, FLASHING AND SHEET METAL.
13. Conduit bodies shall only be used for changes in di rection, and
shall not contain splices.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 33 - 6
14. Do not use aluminum conduits in wet locations.
D. Conduit Bends:
1. Make bends with standard conduit bending machines.
2. Conduit hickey may be used for slight offsets and f or straightening
stubbed out conduits.
3. Bending of conduits with a pipe tee or vise is proh ibited.
E. Layout and Homeruns:
1. Install conduit with wiring, including homeruns, as shown on
drawings.
2. Deviations: Make only where necessary to avoid inte rferences and
only after drawings showing the proposed deviations have been
submitted and approved by the COR.
3.3 CONCEALED WORK INSTALLATION
A. In Concrete:
1. Conduit: PVC Coated Rigid Metallic Steel. 2. Align and run
conduit in direct lines.
2. Conduit shall not be installed within concrete exce pt where passing
horizontally through a vertical steam pit vault.
3. Installation of conduit in concrete slabs is prohib ited.
4. Make couplings and connections watertight. Use thre ad compounds
that are UL approved conductive type to ensure low resistance ground
continuity through the conduits. Tightening setscre ws with pliers
is prohibited.
3.4 EXPOSED WORK INSTALLATION
A. Unless otherwise indicated on drawings, exposed con duit is only
permitted in steam pits and electrical rooms.
B. C. Conduit for Conductors 600 V and Below: PVC Coat ed Rigid
Metallic Steel Conduit.. Mixing different types of conduits in the
system is prohibited.
D. Align and run conduit parallel or perpendicular to the building lines.
E. Install horizontal runs close to the ceiling or bea ms and secure with
conduit straps.
F. Support horizontal or vertical runs at not over 2.4 M (8 feet)
intervals.
3.5 DIRECT BURIAL INSTALLATION
Refer to Section 26 05 41, UNDERGROUND ELECTRICAL C ONSTRUCTION.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 33 - 7
3.6 WET OR DAMP LOCATIONS
A. Use PVC Coated Rigid Steel Metallic Conduits unless as shown on
drawings.
B. Provide sealing fittings to prevent passage of wate r vapor where
conduits pass from warm to cold locations, i.e., re frigerated spaces,
constant-temperature rooms, air-conditioned spaces, building exterior
walls, roofs, or similar spaces.
C. Use PVC Coated Rigid Metallic Steel or IMC conduit within 1.5 M (5
feet) of the exterior and below concrete building s labs in contact with
soil, gravel, or vapor barriers, unless as shown on drawings. Conduit
shall be half-lapped with 10 mil PVC tape before in stallation. After
installation, completely recoat or retape any damag ed areas of coating.
D. Conduits run on roof shall be supported with integr al galvanized lipped
steel channel, attached to UV-inhibited polycarbona te or polypropylene
blocks every 2.4 M (8 feet) with 9 mm (3/8-inch) ga lvanized threaded
rods, square washer and locknut. Conduits shall be attached to steel
channel with conduit clamps.
3.7 CONDUIT SUPPORTS
A. Safe working load shall not exceed one-quarter of p roof test load of
fastening devices.
B. Use pipe straps or individual conduit hangers for s upporting individual
conduits.
C. Support multiple conduit runs with trapeze hangers. Use trapeze
hangers that are designed to support a load equal t o or greater than
the sum of the weights of the conduits, wires, hang er itself, and an
additional 90 kg (200 lbs). Attach each conduit wit h U-bolts or other
approved fasteners.
D. Support conduit independently of junction boxes, pu ll-boxes, fixtures,
suspended ceiling T-bars, angle supports, and simil ar items.
E. Fasteners and Supports in Solid Masonry and Concret e:
1. New Construction: Use steel or malleable iron concr ete inserts set
in place prior to placing the concrete.
2. Existing Construction:
a. Steel expansion anchors not less than 6 mm (0.25-in ch) bolt size
and not less than 28 mm (1.125 inch) in embedment.
b. Power set fasteners not less than 6 mm (0.25-inch) diameter with
depth of penetration not less than 75 mm (3 inch).
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 33 - 8
c. Use vibration and shock-resistant anchors and faste ners for
attaching to concrete ceilings.
F. Hollow Masonry: Toggle bolts.
G. Bolts supported only by plaster or gypsum wallboard are not acceptable.
H. Metal Structures: Use machine screw fasteners or ot her devices
specifically designed and approved for the applicat ion.
I. Attachment by wood plugs, rawl plug, plastic, lead or soft metal
anchors, or wood blocking and bolts supported only by plaster is
prohibited.
J. Chain, wire, or perforated strap shall not be used to support or fasten
conduit.
K. Spring steel type supports or fasteners are prohibi ted for all uses
except horizontal and vertical supports/fasteners w ithin walls.
L. Vertical Supports: Vertical conduit runs shall have riser clamps and
supports in accordance with the NEC and as shown. P rovide supports for
cable and wire with fittings that include internal wedges and retaining
collars.
3.8 BOX INSTALLATION
A. Boxes for Concealed Conduits:
1. Flush-mounted.
2. Provide raised covers for boxes to suit the wall or ceiling,
construction, and finish.
B. In addition to boxes shown, install additional boxe s where needed to
prevent damage to cables and wires during pulling-i n operations or
where more than the equivalent of 4-90 degree bends are necessary.
C. Locate pullboxes so that covers are accessible and easily removed.
Coordinate locations with piping and ductwork where installed above
ceilings.
D. Remove only knockouts as required. Plug unused open ings. Use threaded
plugs for cast metal boxes and snap-in metal covers for sheet metal
boxes.
E. Outlet boxes mounted back-to-back in the same wall are prohibited. A
minimum 600 mm (24 inch) center-to-center lateral s pacing shall be
maintained between boxes.
F. Flush-mounted wall or ceiling boxes shall be instal led with raised
covers so that the front face of raised cover is fl ush with the wall.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 33 - 9
Surface-mounted wall or ceiling boxes shall be inst alled with surface-
style flat or raised covers.
G. Minimum size of outlet boxes for ground fault circu it interrupter
(GFCI) receptacles is 100 mm (4 inches) square x 55 mm (2.125 inches)
deep, with device covers for the wall material and thickness involved.
H. Stencil or install phenolic nameplates on covers of all branch circuit
junction box covers.
I. Junction boxes to be labeled for voltage, service b reaker & panel, or
fire alarm system designation of equipment.
- - - E N D - - -
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 41 - 1
SECTION 26 05 41 UNDERGROUND ELECTRICAL CONSTRUCTION
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies the furnishing, installation , and connection of
underground ducts and raceways, and precast manhole s and pullboxes to
form a complete underground electrical raceway syst em.
B. The terms “duct” and “conduit” are used interchange ably in this
section.
1.2 RELATED WORK
A. Section 07 92 00, JOINT SEALANTS: Sealing of condui t penetrations.
B. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTA LLATIONS:
Requirements that apply to all sections of Division 26.
C. Section 26 05 26, GROUNDING AND BONDING FOR ELECTRI CAL SYSTEMS:
Requirements for personnel safety and to provide a low impedance path
for possible ground fault currents.
D. Section 31 20 00, EARTH MOVING: Trenching, backfill , and compaction.
1.3 QUALITY ASSURANCE
A. Quality Assurance shall be in accordance with Parag raph, QUALIFICATIONS
(PRODUCTS AND SERVICES) in Section 26 05 11, REQUIR EMENTS FOR
ELECTRICAL INSTALLATIONS.
B. Coordinate layout and installation of ducts, manhol es, and pullboxes
with final arrangement of other utilities, site gra ding, and surface
features.
1.4 SUBMITTALS
A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11,
REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following
requirements:
1. Shop Drawings:
a. Submit sufficient information to demonstrate compli ance with
drawings and specifications.
b. Submit information on ducts, and. c. Proposed devia tions
from the drawings shall be clearly marked on the su bmittals. If
it is necessary to locate manholes, pullboxes, or d uct banks at
locations other than shown on the drawings, show th e proposed
locations accurately on scaled site drawings, and s ubmit to the
COR for approval prior to construction.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 05 41 - 2
2. Certifications: Two weeks prior to the final inspec tion, submit the
following.
a. Certification by the manufacturer that the material s conform to
the requirements of the drawings and specifications .
b. Certification by the Contractor that the materials have been
properly installed, connected, and tested.
1.5 APPLICABLE PUBLICATIONS
A. Publications listed below (including amendments, ad denda, revisions,
supplements, and errata) form a part of this specif ication to the
extent referenced. Publications are referenced in t he text by
designation only.
B. American Concrete Institute (ACI):
Building Code Requirements for Structural Concrete
318-14/318M-14..........Building Code Requirements for Structural
Concrete & Commentary SP-66-
04................ACI Detailing Manual
C. American National Standards Institute (ANSI):
77-14...................Underground Enclosure Integ rity
D. American Society for Testing and Materials (ASTM):
C478 REV A-15...........Standard Specification for Precast Reinforced
Concrete Manhole Sections
C858-10.................Underground Precast Concret e Utility Structures
C990-09.................Joints for Concrete Pipe, M anholes and Precast
Box Sections Using Preformed Flexible Joint
Sealants.
E. National Electrical Manufacturers Association (NEMA ):
TC 2-13.................Electrical Polyvinyl Chlori de (PVC) Conduit
TC 3-15.................Polyvinyl Chloride (PVC) Fi ttings for Use With
Rigid PVC Conduit And Tubing
TC 6 & 8-13.............Polyvinyl Chloride (PVC) Pl astic Utilities Duct
For Underground Installations
TC 9-04.................Fittings For Polyvinyl Chlo ride (PVC) Plastic
Utilities Duct For Underground Installation
F. National Fire Protection Association (NFPA):
70-17...................National Electrical Code (N EC)
70E-15..................National Electrical Safety Code
G. Underwriters Laboratories, Inc. (UL):
26 05 41 - 3
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
6-07....................Electrical Rigid Metal Cond uit-Steel
467-13..................Grounding and Bonding Equip ment
651-11..................Schedule 40, 80, Type EB an d A Rigid PVC
Conduit and Fittings
651A-11.................Schedule 40 and 80 High Den sity Polyethylene
(HDPE) Conduit
PART 2 - PRODUCTS
2.1 DUCTS
A. Number and sizes shall be as shown on the drawings.
B.
B. Ducts (direct-burial):
1. Plastic duct:
a. Schedule 80 PVC or HDPE conduit.
b. Duct shall be suitable for use with 90˚ C (167˚ F) rated
conductors.
2. Rigid metal conduit: UL 6 and NEMA RN1 galvanized r igid metal, half-
lap wrapped with 10 mil PVC tape.
2.2 WARNING TAPE
A. 4-mil polyethylene 75 mm (3 inches) wide detectable tape, red with
black letters, imprinted with “CAUTION - BURIED ELE CTRIC CABLE BELOW”
or similar.
PART 3 - EXECUTION
3.1 MANHOLE AND PULLBOX INSTALLATION
A. Assembly and installation shall be per the requirem ents of the
manufacturer.
1. Install manholes and pullboxes level and plumb.
2. Units shall be installed on a 300 mm (12 inches) th ick level bed of
90% compacted granular fill, well-graded from the 2 5 mm (1 inch)
sieve to the No. 4 sieve. Granular fill shall be co mpacted with a
minimum of four passes with a plate compactor.
B. Access: Ensure the top of frames and covers are flu sh with finished
grade.
C. Grounding in Manholes:
1. Ground Rods in Manholes: Drive a ground rod into th e earth, through
the floor sleeve, after the manhole is set in place . Fill the sleeve
26 05 41 - 4
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
with sealant to make a watertight seal. Rods shall protrude
approximately 100 mm (4 inches) above the manhole f loor.
2. Install a No. 3/0 AWG bare copper ring grounding co nductor around
the inside perimeter of the manhole and anchor to t he walls with
metallic cable clips.
3. Connect the ring grounding conductor to the ground rod by an
exothermic welding process.
4. Bond the ring grounding conductor to the duct bank equipment
grounding conductors, the exposed non-current carry ing metal parts
of racks, sump covers, and like items in the manhol es with a minimum
No. 6 AWG bare copper jumper using an exothermic we lding process.
D. Steam Pit Lighting: Provide NEMA 3R lighting switch mounted no more
than 600 mm (2 feet) from top of ladder.
3.2 TRENCHING
A. Refer to Section 31 20 00, EARTH MOVING for trenchi ng, backfilling, and
compaction.
B. Before performing trenching work at existing facili ties, a Ground
Penetrating Radar Survey shall be carefully perform ed by a certified
technician to reveal all existing underground ducts , conduits, cables,
and other utility systems.
C. Work with extreme care near existing ducts, conduit s, and other
utilities to avoid damaging them.
D. Cut the trenches neatly and uniformly.
E. For Concrete-Encased Ducts:
1. After excavation of the trench, stakes shall be dri ven in the bottom
of the trench at 1.2 M (4 feet) intervals to establ ish the grade and
route of the duct bank.
2. Pitch the trenches uniformly toward manholes or bot h ways from high
points between manholes for the required duct line drainage. Avoid
pitching the ducts toward buildings wherever possib le.
3. The walls of the trench may be used to form the sid e walls of the
duct bank, provided that the soil is self-supportin g and that the
concrete envelope can be poured without soil inclus ions. Forms are
required where the soil is not self-supporting.
4. After the concrete-encased duct has sufficiently cu red, the trench
shall be backfilled to grade with earth, and approp riate warning
tape installed.
26 05 41 - 5
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
F. Individual conduits to be installed under existing paved areas and
roads that cannot be disturbed shall be jacked into place using rigid
metal conduit, or bored using plastic utilities duc t or PVC conduit, as
approved by the COR.
3.3 DUCT INSTALLATION
A. General Requirements:
1. Ducts shall be in accordance with the NEC, as shown on the drawings,
and as specified.
2. Join and terminate ducts with fittings recommended by the
manufacturer.
3. Slope ducts to drain towards manholes and pullboxes , and away from
building and equipment entrances. Pitch not less th an 100 mm (4
inches) in 30 M (100 feet).
4. Underground conduit stub-ups and sweeps to equipmen t inside of
buildings shall be galvanized rigid metal conduit h alf-lap wrapped
with PVC tape, and shall extend a minimum of 1.5 M (5 feet) outside
the building foundation. Tops of conduits below bui lding slab shall
be minimum 610 mm (24 inches) below bottom of slab.
5. Stub-ups and sweeps to equipment mounted on outdoor concrete slabs
shall be galvanized rigid metal conduit half-lap wr apped with PVC
tape, and shall extend a minimum of 1.5 M (5 feet) away from the
edge of slab.
6. Install insulated grounding bushings on the conduit terminations.
7. Radius for sweeps shall be sufficient to accomplish pulls without
damage. Minimum radius shall be six times conduit d iameter.
8. All multiple conduit runs shall have conduit spacer s. Spacers shall
securely support and maintain uniform spacing of th e duct assembly a
minimum of 75 mm (3 inches) above the bottom of the trench during
the concrete pour. Spacer spacing shall not exceed 1.5 M (5 feet).
Secure spacers to ducts and earth to prevent floati ng during
concrete pour. Provide nonferrous tie wires to prev ent displacement
of the ducts during concrete pour. Tie wires shall not act as
substitute for spacers.
9. Duct lines shall be installed no less than 300 mm ( 12 inches) from
other utility systems, such as water, sewer, chille d water.
10. Clearances between individual ducts:
a. For similar services, not less than 75 mm (3 inches ).
26 05 41 - 6
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
b. For power and signal services, not less than 150 mm (6 inches).
11. Duct lines shall terminate at window openings in ma nhole walls as
shown on the drawings. All ducts shall be fitted wi th end bells.
12. Couple the ducts with proper couplings. Stagger cou plings in rows
and layers to ensure maximum strength and rigidity of the duct bank.
13. Keep ducts clean of earth, sand, or gravel, and sea l with tapered
plugs upon completion of each portion of the work.
14. Spare Ducts: Where spare ducts are shown, they shal l have a nylon
pull rope installed. They shall be capped at each e nd and labeled as
to location of the other end.
15. Duct Identification: Place continuous strip of warn ing tape
approximately 300 mm (12 inches) above ducts before backfilling
trenches. Warning tape shall be preprinted with pro per
identification.
16. Duct Sealing: Seal ducts, including spare ducts, at building
entrances and at outdoor terminations for equipment , with a suitable
non-hardening compound to prevent the entrance of f oreign objects
and material, moisture, and gases.
17. Use plastic ties to secure cables to insulators on cable arms. Use
minimum two ties per cable per insulator.
B. Concrete-Encased Ducts:
1. Install concrete-encased ducts for medium-voltage s ystems, low-
voltage systems, and signal systems, unless otherwi se shown on the
drawings.
2. Duct banks shall be single or multiple duct assembl ies encased in
concrete. Ducts shall be uniform in size and materi al throughout the
installation.
3. Tops of concrete-encased ducts shall be:
a. Not less than 600 mm (24 inches) and not less than shown on the
drawings, below finished grade.
b. Not less than 750 mm (30 inches) and not less than shown on the
drawings, below roads and other paved surfaces.
c. Additional burial depth shall be required in order to accomplish
NEC-required minimum bend radius of ducts.
d. Conduits crossing under grade slab construction joi nts shall be
installed a minimum of 1.2 M (4 feet) below slab.
26 05 41 - 7
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
4. Extend the concrete envelope encasing the ducts not less than 75 mm
(3 inches) beyond the outside walls of the outer du cts.
5. Within 3 M (10 feet} of building and manhole wall p enetrations,
install reinforcing steel bars at the top and botto m of each
concrete envelope to provide protection against ver tical shearing.
6. Install reinforcing steel bars at the top and botto m of each
concrete envelope of all ducts underneath roadways and parking
areas.
7. Where new ducts and concrete envelopes are to be jo ined to existing
manholes, pullboxes, ducts, and concrete envelopes, make the joints
with the proper fittings and fabricate the concrete envelopes to
ensure smooth durable transitions.
8. Duct joints in concrete may be placed side by side horizontally, but
shall be staggered at least 150 mm (6 inches) verti cally.
9. Pour each run of concrete envelope between manholes or other
terminations in one continuous pour. If more than o ne pour is
necessary, terminate each pour in a vertical plane and install 19 mm
(0.75 inch) reinforcing rod dowels extending 450 mm (18 inches) into
concrete on both sides of joint near corners of env elope.
10. Pour concrete so that open spaces are uniformly fil led. Do not
agitate with power equipment unless approved by COR .
C. Direct-Burial Ducts:
1. Install direct-burial ducts only where shown on the drawings.
Provide direct-burial ducts only for low-voltage po wer and lighting
branch circuits.
2. Tops of ducts shall be:
a. Not less than 920 mm (36 inches) and not less than shown on the
drawings, below finished grade.
c. Additional burial depth shall be required in ord er to accomplish
NEC-required minimum bend radius of ducts.
3. Do not kink the ducts. Compaction shall not deform the ducts.
D. Connections to Manholes: Ducts connecting to manhol es shall be flared
to have an enlarged cross-section to provide additi onal shear strength.
Dimensions of the flared cross-section shall be lar ger than the
corresponding manhole opening dimensions by no less than 300 mm (12
inches) in each direction. Perimeter of the duct ba nk opening in the
manhole shall be flared toward the inside or keyed to provide a
26 05 41 - 8
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
positive interlock between the duct and the wall of the manhole. Use
vibrators when this portion of the encasement is po ured to ensure a
seal between the envelope and the wall of the struc ture.
E. Connections to Existing Manholes: For duct connecti ons to existing
manholes, break the structure wall out to the dimen sions required and
preserve the steel in the structure wall. Cut steel and extend into the
duct bank envelope. Chip the perimeter surface of t he duct bank opening
to form a key or flared surface, providing a positi ve connection with
the duct bank envelope.
F. Connections to Existing Ducts: Where connections to existing ducts are
indicated, excavate around the ducts as necessary. Cut off the ducts
and remove loose concrete from inside before instal ling new ducts.
Provide a reinforced-concrete collar, poured monoli thically with the
new ducts, to take the shear at the joint of the du ct banks.
G. Partially-Completed Ducts: During construction, whe rever a construction
joint is necessary in a duct bank, prevent debris s uch as mud and dirt
from entering ducts by providing suitable plugs. Fi t concrete envelope
of a partially completed ducts with reinforcing ste el extending a
minimum of 600 mm (2 feet) back into the envelope a nd a minimum of 600
mm (2 feet) beyond the end of the envelope. Provide one No. 4 bar in
each corner, 75 mm (3 inches) from the edge of the envelope. Secure
corner bars with two No. 3 ties, spaced approximate ly 300 mm (12
inches) apart. Restrain reinforcing assembly from m oving during pouring
of concrete.
3.4 ACCEPTANCE CHECKS AND TESTS
A. Duct Testing and Cleaning:
1. Upon completion of the duct installation, a standar d flexible
mandrel shall be pulled through each duct to loosen particles of
earth, sand, or foreign material left in the duct, and to test for
out-of-round conditions.
2. The mandrel shall be not less than 300 mm (12 inche s) long, and
shall have a diameter not less than 13 mm (0.5 inch ) less than the
inside diameter of the duct. A brush with stiff bri stles shall then
be pulled through each duct to remove the loosened particles. The
diameter of the brush shall be the same as, or slig htly larger than,
the diameter of the duct.
26 05 41 - 9
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
3. If testing reveals obstructions or out-of-round con ditions, the
Contractor shall replace affected section(s) of duc t and retest to
the satisfaction of the COR.
---END---
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 27 26 - 1
SECTION 26 27 26 WIRING DEVICES
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies the furnishing, installation , connection, and
testing of wiring devices.
1.2 RELATED WORK
A. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTA LLATIONS: General
electrical requirements that are common to more tha n one section of
Division 26.
B. Section 26 05 19, LOW-VOLTAGE ELECTRICAL POWER COND UCTORS AND CABLES:
Cables and wiring.
C. Section 26 05 26, GROUNDING AND BONDING FOR ELECTRI CAL SYSTEMS:
Requirements for personnel safety and to provide a low impedance path
to ground for possible ground fault currents.
D. Section 26 05 33, RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS: Conduit and
boxes.
1.3 QUALITY ASSURANCE
A. Refer to Paragraph, QUALIFICATIONS (PRODUCTS AND SE RVICES), in Section
26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS .
1.4 SUBMITTALS
A. Submit six copies of the following in accordance wi th Section 26 05 11,
REQUIREMENTS FOR ELECTRICAL INSTALLATIONS.
1. Shop Drawings:
a. Submit sufficient information to demonstrate compli ance with
drawings and specifications.
b. Include electrical ratings, dimensions, mounting de tails,
construction materials, grade, and termination info rmation.
2. Manuals:
a. Submit, simultaneously with the shop drawings, comp anion copies
of complete maintenance and operating manuals, incl uding
technical data sheets and information for ordering replacement
parts.
b. If changes have been made to the maintenance and op erating
manuals originally submitted, submit updated mainte nance and
operating manuals two weeks prior to the final insp ection.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 27 26 - 2
3. Certifications: Two weeks prior to final inspection , submit the
following.
a. Certification by the manufacturer that the wiring d evices conform
to the requirements of the drawings and specificati ons.
b. Certification by the Contractor that the wiring dev ices have been
properly installed and adjusted.
1.5 APPLICABLE PUBLICATIONS
A. Publications listed below (including amendments, ad denda, revisions,
supplements and errata) form a part of this specifi cation to the extent
referenced. Publications are referenced in the text by basic
designation only.
B. National Fire Protection Association (NFPA):
70-14...................National Electrical Code (N EC)
99-15...................Health Care Facilities
C. National Electrical Manufacturers Association (NEMA ):
WD 1-10.................General Color Requirements for Wiring Devices
WD 6-12 ................Wiring Devices – Dimensiona l Specifications
D. Underwriter’s Laboratories, Inc. (UL):
5-11....................Surface Metal Raceways and Fittings
20-10...................General-Use Snap Switches
231-08..................Power Outlets
467-13..................Grounding and Bonding Equip ment
498-12..................Attachment Plugs and Recept acles
943-15..................Ground-Fault Circuit-Interr upters
PART 2 - PRODUCTS
2.1 RECEPTACLES
A. General: All receptacles shall comply with NEMA, NF PA, UL, and as shown
on the drawings.
1. Mounting straps shall be nickel plated brass, brass , with break-off
plaster ears, and shall include self-grounding feat ure. Terminal
screws shall be brass, brass plated or copper alloy metal.
2. Receptacles shall have provisions for back wiring w ith separate
metal clamp type terminals (four minimum) and side wiring from four
captively held binding screws.
B.
1. Ground Fault Current Interrupter (GFCI) Duplex Rece ptacles: Shall be
an integral unit, 20Amp hospital-grade, suitable fo r mounting in a
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 27 26 - 3
standard outlet box, with end-of-life indication an d provisions to
isolate the face due to improper wiring. GFCI recep tacles shall be
self-test receptacles in accordance with UL 943.
a. Ground fault interrupter shall consist of a differe ntial current
transformer, self-test, solid state sensing circuit ry and a
circuit interrupter switch. Device shall have nomin al sensitivity
to ground leakage current of 4-6 milliamperes and s hall function
to interrupt the current supply for any value of gr ound leakage
current above five milliamperes (+ or – 1 milliampe re) on the
load side of the device. Device shall have a minimu m nominal
tripping time of 0.025 second.
b. Self-test function shall be automatically initiated within 5
seconds after power is activated to the receptacles . Self-test
function shall be periodically and automatically pe rformed every
3 hours or less.
c. End-of-life indicator light shall be a persistent f lashing or
blinking light to indicate that the GFCI receptacle is no longer
in service.
C. Receptacles - 20, 30, and 50 ampere, 250 Volts: Sha ll be complete with
appropriate cord grip plug.
D. Weatherproof Receptacles: Shall consist of a duplex receptacle, mounted
in a cast aluminum box with a gasketed, weatherproo f, cast aluminum
metal cover plate and cap over each receptacle open ing. The cap shall
be permanently attached to the cover plate by a spr ing-hinged flap. The
weatherproof integrity shall not be affected when h eavy duty
specification or hospital grade attachment plug cap s are inserted.
Cover plates on outlet boxes mounted flush in the w all shall be
gasketed to the wall in a watertight manner.
E. Weatherproof Switches shall consist of a single tog gle switch mounted
in cast aluminum box with a gasketed, weatherproof cast aluminum cover
plate and cap over each device opening. The cap sha ll be permanently
attached to the cover plate by a spring-hinged flap .
2.2 TOGGLE SWITCHES
A. Toggle switches shall be totally enclosed tumbler t ype with nylon
bodies. Handles shall be ivory in color unless othe rwise specified or
shown on the drawings.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 27 26 - 4
1. Switches installed in hazardous areas shall be expl osion-proof type
in accordance with the NEC and as shown on the draw ings.
2. Shall be single unit toggle, butt contact, quiet AC type, heavy-duty
general-purpose use with an integral self grounding mounting strap
with break-off plasters ears and provisions for bac k wiring with
separate metal wiring clamps and side wiring with c aptively held
binding screws.
3. Switches shall be rated 20 amperes at 120-277 Volts AC.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Installation shall be in accordance with the NEC an d as shown as on the
drawings.
B. Install wiring devices after wall construction and painting is
complete.
C. The ground terminal of each wiring device shall be bonded to the outlet
box with an approved green bonding jumper, and also connected to the
branch circuit equipment grounding conductor.
D. Outlet boxes for toggle switches shall be mounted a djacent to the entry
ladder.
E.
F. Coordinate the electrical work with the work of oth er trades to ensure
that wiring device flush outlets are positioned wit h box openings aligned
with the face of the surrounding finish material. P ay special attention
to installations in cabinet work, and in connection with laboratory
equipment.
G. Exact field locations of floors, walls, partitions, doors, windows, and
equipment may vary from locations shown on the draw ings. Prior to
locating sleeves, boxes and chases for roughing-in of conduit and
equipment, the Contractor shall coordinate exact fi eld location of the
above items with other trades.
H. Install wall switches 1.2 M (48 inches) above floor , with the toggle OFF
position down.
I.
J. Install receptacles 450 mm (48 inches) above floor, and 152 mm (6 inches)
above counter backsplash or workbenches. Install sp ecific-use
receptacles at heights shown on the drawings.
K. Install horizontally mounted receptacles with the g round pin to the
26 27 26 - 5
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
right.
L. When required or recommended by the manufacturer, u se a torque
screwdriver. Tighten unused terminal screws.
M. Label device plates with a permanent adhesive label listing panel and
circuit feeding the wiring device.
3.2 ACCEPTANCE CHECKS AND TESTS
A. Perform manufacturer’s required field checks in acc ordance with the
manufacturer's recommendations, and the latest NFPA 99. In addition,
include the following:
1. Visual Inspection and Tests:
a. Inspect physical and electrical conditions.
b. Vacuum-clean surface metal raceway interior. Clean metal raceway
exterior.
c. Test wiring devices for damaged conductors, high ci rcuit
resistance, poor connections, inadequate fault curr ent path,
defective devices, or similar problems using a port able
receptacle tester. Correct circuit conditions, remo ve
malfunctioning units and replace with new, and rete st as
specified above.
d. Test GFCI receptacles.
---END---
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 29 21 - 1
SECTION 26 29 21 ENCLOSED SWITCHES AND CIRCUIT BREAKERS
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies the furnishing, installation , and connection of
fused and unfused disconnect switches (indicated as switches in this
section), and separately-enclosed circuit breakers for use in
electrical systems rated 600 V and below.
1.2 RELATED WORK
A. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTA LLATIONS:
Requirements that apply to all sections of Division 26.
B. Section 26 05 19, LOW-VOLTAGE ELECTRICAL POWER COND UCTORS AND CABLES:
Low-voltage conductors.
C. Section 26 05 26, GROUNDING AND BONDING FOR ELECTRI CAL SYSTEMS:
Requirements for personnel safety and to provide a low impedance path
for possible ground faults.
D. Section 26 05 33, RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS: Conduits.
1.3 QUALITY ASSURANCE
A. Quality Assurance shall be in accordance with Parag raph, QUALIFICATIONS
(PRODUCTS AND SERVICES) in Section 26 05 11, REQUIR EMENTS FOR
ELECTRICAL INSTALLATIONS.
1.4 SUBMITTALS
A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11,
REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following
requirements:
1. Shop Drawings:
a. Submit sufficient information to demonstrate compli ance with
drawings and specifications.
b. Submit the following data for approval:
1) Electrical ratings, dimensions, mounting details, m aterials,
required clearances, terminations, weight, fuses, c ircuit
breakers, wiring and connection diagrams, accessori es, and
device nameplate data.
2. Manuals:
a. Submit complete maintenance and operating manuals i ncluding
technical data sheets, wiring diagrams, and informa tion for
ordering fuses, circuit breakers, and replacement p arts.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 29 21 - 2
1) Include schematic diagrams, with all terminals iden tified,
matching terminal identification in the enclosed sw itches and
circuit breakers.
2) Include information for testing, repair, troublesho oting,
assembly, and disassembly.
b. If changes have been made to the maintenance and op erating
manuals originally submitted, submit updated mainte nance and
operating manuals two weeks prior to the final insp ection.
3. Certifications: Two weeks prior to final inspection , submit the
following.
a. Certification by the manufacturer that the enclosed switches and
circuit breakers conform to the requirements of the drawings and
specifications.
b. Certification by the Contractor that the enclosed s witches and
circuit breakers have been properly installed, adju sted, and
tested.
1.5 APPLICABLE PUBLICATIONS
A. Publications listed below (including amendments, ad denda, revisions,
supplements, and errata) form a part of this specif ication to the
extent referenced. Publications are referenced in t he text by
designation only.
B. International Code Council (ICC):
IBC-15..................International Building Code
C. National Electrical Manufacturers Association (NEMA ):
FU l-12.................Low Voltage Cartridge Fuses
KS l-13.................Heavy Duty Enclosed and Dea d-Front Switches
(600 Volts Maximum)
D. National Fire Protection Association (NFPA):
70-17...................National Electrical Code (N EC)
E. Underwriters Laboratories, Inc. (UL):
98-16...................Enclosed and Dead-Front Swi tches
248 1-11................Low Voltage Fuses
489-13..................Molded Case Circuit Breaker s and Circuit
Breaker Enclosures
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 29 21 - 3
PART 2 - PRODUCTS
2.1 FUSED SWITCHES RATED 600 AMPERES AND LESS
A. Switches shall be in accordance with NEMA, NEC, UL, as specified, and
as shown on the drawings.
B. Shall be NEMA classified 4X Stainless Steel, Alumin um, or Fiberglass as
noted on plans.
C. Shall be horsepower (HP) rated.
D. Shall have the following features:
1. Switch mechanism shall be the quick-make, quick-bre ak type.
2. Copper blades, visible in the open position.
3. An arc chute for each pole.
4. External operating handle shall indicate open and c losed positions,
and have lock-open padlocking provisions.
5. Mechanical interlock shall permit opening of the do or only when the
switch is in the open position, defeatable to permi t inspection.
6. Fuse holders for the sizes and types of fuses speci fied.
7. Solid neutral for each switch being installed in a circuit which
includes a neutral conductor.
8. Ground lugs for each ground conductor.
9. Enclosures:
a. Shall be the NEMA types shown on the drawings.
b. Where the types of switch enclosures are not shown, they shall be
the NEMA types most suitable for the ambient enviro nmental
conditions.
c. Shall be finished with manufacturer’s standard gray baked enamel
paint over pretreated steel.
d. Safety Switches to be labeled as to voltage, fuse s ize, amperage,
equipment or service feeding and where it fed from (provide
similar data, i.e., V, A, Ckt #, Pnl #, etc.)
2.2 UNFUSED SWITCHES RATED 600 AMPERES AND LESS
A. Shall be the same as fused switches, but without pr ovisions for fuses.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Installation shall be in accordance with the NEC, a s shown on the
drawings, and manufacturer’s instructions.
26 29 21 - 4
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
3.2 ACCEPTANCE CHECKS AND TESTS
A. Perform in accordance with the manufacturer's recom mendations. In
addition, include the following:
1. Visual Inspection and Tests:
a. Compare equipment nameplate data with specification s and approved
shop drawings.
b. Inspect physical, electrical, and mechanical condit ion.
c. Verify tightness of accessible bolted electrical co nnections by
calibrated torque-wrench method.
d. Vacuum-clean enclosure interior. Clean enclosure ex terior.
---END---
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 56 00 - 1
RSECTION 26 56 00 EXTERIOR LIGHTING
PART 1 - GENERAL
1.1 DESCRIPTION
This section specifies the furnishing, installation , and connection of
exterior fixtures, poles, and supports. The terms “ lighting fixtures”,
“fixture” and “luminaire” are used interchangeably.
1.2 RELATED WORK
A. Section 03 30 00, CAST-IN-PLACE CONCRETE.
B. Section 09 06 00, SCHEDULE FOR FINISHES: Finishes f or exterior light
poles and luminaires.
C. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTA LLATIONS: General
electrical requirements and items that are common t o more than one
section of Division 26.
D. Section 26 05 19, LOW-VOLTAGE ELECTRICAL POWER COND UCTORS AND CABLES
(600 VOLTS AND BELOW): Low voltage power and lighti ng wiring.
E. Section 26 05 26, GROUNDING AND BONDING FOR ELECTRI CAL SYSTEMS:
Requirements for personnel safety and to provide a low impedance path
for possible ground fault currents.
F. Section 26 05 33, RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS: Conduits,
fittings, and boxes for raceway systems.
G. Section 26 05 41, UNDERGROUND ELECTRICAL CONSTRUCTI ON: Underground
handholes and conduits.
1.3 QUALITY ASSURANCE
A. Refer to Paragraph, QUALIFICATIONS (PRODUCTS AND SE RVICES), in Section
26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS .
1.4 SUBMITTALS
A. Submit six copies of the following in accordance wi th Section 26 05 11,
REQUIREMENTS FOR ELECTRICAL INSTALLATIONS.
1. Shop Drawings:
a. Submit the following information for each type of l ighting
fixture designated on the LIGHTING FIXTURE SCHEDULE , arranged in
order of lighting fixture designation.
b. Material and construction details, include informat ion on housing
and optics system.
c. Physical dimensions and description.
d. Wiring schematic and connection diagram.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 56 00 - 2
e. Installation details.
f. Energy efficiency data.
g. Photometric data based on laboratory tests complyin g with IES
Lighting Measurements testing and calculation guide s.
h. Lamp data including lumen output (initial and mean) , color
rendition index (CRI), rated life (hours), and colo r temperature
(degrees Kelvin).
i. Ballast data including ballast type, starting metho d, ambient
temperature, ballast factor, sound rating, system w atts, and
total harmonic distortion (THD).
j. For LED lighting fixtures, submit US DOE LED Lighti ng Facts
label, and IES L70 rated life.
k. Submit site plan showing all exterior lighting fixt ures with
fixture tags consistent with Lighting Fixture Sched ule as shown
on drawings. Site plan shall show computer generate d point–by-
point illumination calculations. Include lamp lumen and light
loss factors used in calculations.
2. Manuals:
a. Submit, simultaneously with the shop drawings, comp lete
maintenance and operating manuals, including techni cal data
sheets, wiring diagrams, and information for orderi ng replacement
parts.
b. If changes have been made to the maintenance and op erating
manuals originally submitted, submit updated mainte nance and
operating manuals two weeks prior to the final insp ection.
3. Certifications: Two weeks prior to final inspection , submit the
following.
a. Certification by the Contractor that the exterior l ighting
systems have been properly installed and tested.
1.5 APPLICABLE PUBLICATIONS
A. Publications listed below (including amendments, ad denda, revisions,
supplements, and errata) form a part of this specif ication to the
extent referenced. Publications are referenced in t he text by
designation only.
B. Aluminum Association Inc. (AA):
AAH35.1-06..............Alloy and Temper Designatio n Systems for
Aluminum
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
26 56 00 - 3
C. American National Standards Institute (ANSI):
C81.61-09 ..............Electrical Lamp Bases – Spe cifications for
Bases (Caps) for Electric Lamps
D. American Society for Testing and Materials (ASTM):
A123/A123M-12 ..........Zinc (Hot-Dip Galvanized) C oatings on Iron and
Steel Products
A153/A153M-09...........Zinc Coating (Hot-Dip) on I ron and Steel
Hardware
B108-03a-08 ............Aluminum-Alloy Permanent Mo ld Castings C1089-
13 ...............Spun Cast Prestressed Concrete Po les
E. Illuminating Engineering Society of North America ( IESNA):
HB-9-00.................Lighting Handbook
LM-72-10................Directional Positioning of Photometric Data LM-
79-08................Approved Method for the Electr ical and
Photometric Measurements of Solid-Sate Lighting
Products
LM-80-08................Approved Method for Measuri ng Lumen Maintenance
of LED Light Sources
F. National Electrical Manufacturers Association (NEMA ):
ICS 2-00 (R2005) .......Controllers, Contactors and Overload Relays
Rated 600 Volts
ICS 6-93 (R2006) .......Enclosures
G. National Fire Protection Association (NFPA):
70-11 ..................National Electrical Code (N EC)
H. Underwriters Laboratories, Inc. (UL):
496-08 .................Lampholders
1598-08 ................Luminaires
PART 2 - PRODUCTS
2.1 GENERAL REQUIREMENTS
Luminaires, materials and equipment shall be in acc ordance with NEC,
UL, ANSI, and as shown on the drawings and specifie d.
2.2 LUMINAIRES
A. Luminaires shall be weatherproof, heavy duty, outdo or types designed
for efficient light utilization, adequate dissipati on of lamp and
ballast heat, and safe cleaning and relamping.
26 56 00 - 4
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
B. Illumination distribution patterns, BUG ratings and cutoff types as
defined by the IESNA shall be as shown on the drawi ngs.
C. Incorporate ballasts in the luminaire housing, exce pt where otherwise
shown on the drawings.
D. Lenses shall be frame-mounted, heat-resistant, boro silicate glass, with
prismatic refractors, unless otherwise shown on the drawings. Attach
the frame to the luminaire housing by hinges or cha in. Use heat and
aging-resistant, resilient gaskets to seal and cush ion lenses and
refractors in luminaire doors.
E. F. Pre-wire internal components to terminal strips at the factory.
G. Bracket-mounted luminaires shall have leveling prov isions and clamp-
type adjustable slip-fitters with locking screws.
H. Materials shall be rustproof. Latches and fittings shall be non-
ferrous metal.
I. Provide manufacturer's standard finish, as schedule d on the drawings.
Where indicated on drawings, match finish process a nd color of pole or
support materials.
J. Luminaires shall carry factory labels, showing comp lete, specific lamp
and ballast information.
2.3 LAMPS
A. LED sources shall meet the following requirements:
1. Operating temperature rating shall be between -40 d egrees C (-40
degrees F) and 50 degrees C (120 degrees F).
2. Correlated Color Temperature (CCT): 5000K.
3. Color Rendering Index (CRI): ≥ 85.
4. The manufacturer shall have performed reliability t ests on the LEDs
luminaires complying with Illuminating Engineering Society (IES)
LM79 for photometric performance and LM80 for lumen maintenance and
L70 life.
F. Mercury vapor lamps shall not be used.
2.4 LED DRIVERS
A. LED drivers shall meet the following requirements:
1. Drivers shall have a minimum efficiency of 85%.
2. Starting Temperature: -40 degrees C (-40 degrees F) .
3. Input Voltage: 120 to 480 (±10%) volt.
4. Power Supplies: Class I or II output.
26 56 00 - 5
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
5. Surge Protection: The system must survive 250 repet itive strikes of
“C Low” (C Low: 6kV/1.2 x 50 µs, 10kA/8 x 20 µs) waveforms at 1-
minute intervals with less than 10% degradation in clamping voltage.
“C Low” waveforms are as defined in IEEE/ASNI C62.4 1.2-2002,
Scenario 1 Location Category C.
6. Power Factor (PF): ≥ 0.90.
7. Total Harmonic Distortion (THD): ≤ 20%.
8. Comply with FCC Title 47 CFR Part 18 Non-consumer R FI/EMI Standards.
9. Drivers shall be reduction of hazardous substances (ROHS)-compliant.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Install lighting in accordance with the NEC, as sho wn on the drawings,
and in accordance with manufacturer’s recommendatio ns.
3.3 ACCEPTANCE CHECKS AND TESTS
Verify operation after installing luminaires and en ergizing circuits.
- - - E N D - - -
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
SECTION 31 20 00 EARTHWORK
PART 1 - GENERAL
1.1 DESCRIPTION OF WORK:
A. This section specifies the requirements for furnish ing all equipment,
materials, labor, tools, and techniques for earthwo rk including, but
not limited to, the following:
1. Site preparation.
2. Excavation.
3. Underpinning.
4. Filling and backfilling.
5. Grading.
6. Soil Disposal.
7. Clean Up.
1.2 DEFINITIONS:
A. Unsuitable Materials:
1. Fills: Topsoil; frozen materials; construction mate rials and
materials subject to decomposition; clods of clay a nd stones larger
than 75 mm (3 inches); organic material, including silts, which are
unstable; and inorganic materials, including silts, too wet to be
stable and any material with a liquid limit and pla sticity index
exceeding 40 and 15 respectively. Unsatisfactory so ils also include
satisfactory soils not maintained within 2 percent of optimum
moisture content at time of compaction, as defined by ASTM D698.
2. Existing Subgrade (Except Footing Subgrade): Same m aterials as
1.2.A.1, that are not capable of direct support of slabs, pavement,
and similar items with possible exception of improv ement by
compaction, proofrolling, or similar methods.
3. Existing Subgrade (Footings Only): Same as paragrap h 1, but no fill
or backfill. If materials differ from design requir ements, excavate
to acceptable strata subject to COR's approval.
B. Building Earthwork: Earthwork operations required i n area enclosed by a
line located 1500 mm (5 feet) outside of principal building perimeter.
It also includes earthwork required for auxiliary s tructures and
buildings.
C. Trench Earthwork: Trenchwork required for utility l ines.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
31 20 00 - 2
D. Site Earthwork: Earthwork operations required in ar ea outside of a line
located 1500 mm (5 feet) outside of principal build ing perimeter and
within new construction area with exceptions noted above.
E. Degree of compaction: Degree of compaction is expre ssed as a percentage
of maximum density obtained by laboratory test proc edure. This
percentage of maximum density is obtained through u se of data provided
from results of field test procedures presented in ASTM D1556, ASTM
D2167, and ASTM D6938.
F. Fill: Satisfactory soil materials used to raise exi sting grades. In the
Construction Documents, the term “fill” means fill or backfill as
appropriate.
G. Backfill: Soil materials or controlled low strength material used to
fill an excavation.
H. Unauthorized excavation: Removal of materials beyon d indicated sub-
grade elevations or indicated lines and dimensions without written
authorization by the COR. No payment will be made f or unauthorized
excavation or remedial work required to correct una uthorized
excavation.
I. Authorized additional excavation: Removal of additi onal material
authorized by the COR based on the determination by the Government’s
soils testing agency that unsuitable bearing materi als are encountered
at required sub-grade elevations. Removal of unsuit able material and
its replacement as directed will be paid on basis o f Conditions of the
Contract relative to changes in work.
J. Subgrade: The undisturbed earth or the compacted so il layer immediately
below granular sub-base, drainage fill, or topsoil materials.
K. Structure: Buildings, foundations, slabs, tanks, cu rbs, mechanical and
electrical appurtenances, or other man-made station ary features
constructed above or below the ground surface.
L. Borrow: Satisfactory soil imported from off-site fo r use as fill or
backfill.
M. Drainage course: Layer supporting slab-on-grade use d to minimize
capillary flow of pore water.
N. Bedding course: Layer placed over the excavated sub -grade in a trench
before laying pipe. Bedding course shall extend up to the springline
of the pipe.
31 20 00 - 3
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
O. Sub-base Course: Layer placed between the sub-grade and base course for
asphalt paving or layer placed between the sub-grad e and a concrete
pavement or walk.
P. Utilities include on-site underground pipes, condui ts, ducts, and
cables as well as underground services within build ings.
Q. Debris: Debris includes all materials located withi n the designated
work area not covered in the other definitions and shall include but
not be limited to items like vehicles, equipment, a ppliances, building
materials or remains thereof, tires, any solid or l iquid chemicals or
products stored or found in containers or spilled o n the ground.
R. Contaminated soils: Soil that contains contaminates as defined and
determined by the COR or the Government’s testing a gency.
1.3 RELATED WORK:
A. Materials testing and inspection during constructio n: Section 01 45 29,
TESTING LABORATORY SERVICES.
B. Safety requirements, protection of existing utiliti es, fire protection
services, existing equipment, roads, and pavements: Section 01 00 00,
GENERAL REQUIREMENTS.
C. Subsurface Investigation: Section 01 00 00, GENERAL REQUIREMENTS,
Article, PHYSICAL DATA.
D. Erosion Control: Section 01 57 19, TEMPORARY ENVIRO NMENTAL CONTROLS,
and Section 32 90 00, PLANTING.
E. Site preparation: Section 31 23 19, DEWATERING, Sec tion 02 41 00,
DEMOLITION, and Section 02 42 00 CUTTING, REMOVAL, DEMOLITION,
RESTORATION, AND PATCHING.
F. Paving sub-grade requirements: Section 32 12 16, AS PHALT PAVING.
1.4 CLASSIFICATION OF EXCAVATION:
A. Unclassified Excavation: Removal and disposal of pa vements and other
man-made obstructions visible on surface; utilities , and other items
including underground structures indicated to be de molished and
removed; together with any type of materials regard less of character of
material and obstructions encountered.
1.5 SUBMITTALS:
A. Submit in accordance with Section 01 33 23, SHOP DR AWINGS, PRODUCT
DATA, AND SAMPLES.
31 20 00 - 4
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
B. Furnish to COR:
1. Contactor shall furnish resumes with all personnel involved in the
project including Project Manager, Superintendent, and on-site
Engineer. Project Manager and Superintendent should have at least 3
years of experience on projects of similar size.
2. Soil samples.
a. Classification in accordance with ASTM D2487 for ea ch on-site or
borrow soil material proposed for fill, backfill, e ngineered
fill, or structural fill.
b. Laboratory compaction curve in accordance with ASTM D698 for each
on site or borrow soil material proposed for fill, backfill,
engineered fill, or structural fill.
c. Test reports for compliance with ASTM D2940 require ments for
subbase material.
d. Pre-excavation photographs and videotape in the vic inity of the
existing structures to document existing site featu res, including
surfaces finishes, cracks, or other structural blem ishes that
might be misconstrued as damage caused by earthwork operations.
3. Contractor shall submit procedure and location for disposal of
unused satisfactory material. Proposed source of bo rrow material.
Notification of encountering rock in the project. A dvance notice on
the opening of excavation or borrow areas. Advance notice on
shoulder construction for rigid pavements.
1.6 APPLICABLE PUBLICATIONS:
A. Publications listed below form a part of this speci fication to extent
referenced. Publications are referenced in text by basic designation
only.
B. American Association of State Highway and Transport ation Officials
(AASHTO):
T99-10..................Standard Method of Test for Moisture-Density
Relations of Soils Using a 2.5 kg (5.5 lb)
Rammer and a 305 mm (12 inch) Drop
T180-10.................Standard Method of Test for Moisture-Density
Relations of Soils using a 4.54 kg (10 lb)
Rammer and a 457 mm (18 inch) Drop
C. American Society for Testing and Materials (ASTM):
C33-03..................Concrete Aggregate
31 20 00 - 5
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
D448-08.................Standard Classification for Sizes of Aggregate
for Road and Bridge Construction
D698-07e1...............Standard Test Method for La boratory Compaction
Characteristics of Soil Using Standard Effort
(12,400 ft. lbf/ft 3 (600 kN m/m 3))
D1140-00................Amount of Material in Soils Finer than the No.
200 (75-micrometer) Sieve
D1556-07................Standard Test Method for De nsity and Unit
Weight of Soil in Place by the Sand Cone Method
D1557-09................Standard Test Methods for L aboratory Compaction
Characteristics of Soil Using Modified Effort
(56,000 ft-lbf/ft 3 (2700 kN m/m 3))
D2167-08................Standard Test Method for De nsity and Unit
Weight of Soil in Place by the Rubber Balloon
Method
D2487-11................Standard Classification of Soils for
Engineering Purposes (Unified Soil
Classification System)
D2940-09................Standard Specifications for Graded Aggregate
Material for Bases or Subbases for Highways or
Airports
D6938-10................Standard Test Method for In -Place Density and
Water Content of Soil and Soil-Aggregate by
Nuclear Methods (Shallow Depth
D. Society of Automotive Engineers (SAE):
J732-07.................Specification Definitions - Loaders
J1179-08................Hydraulic Excavator and Bac khoe Digging Forces
PART 2 - PRODUCTS
2.1 MATERIALS:
A. General: Provide borrow soil material when sufficie nt satisfactory
soil materials are not available from excavations.
B. Fills: Material in compliance with ASTM D2487 Soil Classification
Groups GW, GP, GM, SW, SP, SM, SC, and ML, or any c ombination of these
groups; free of rock or gravel larger than 75 mm (3 inches) in any
dimension, debris, waste, frozen materials, vegetat ion, and other
deleterious matter. Material approved from on site or off site sources
31 20 00 - 6
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
having a minimum dry density of 1760 kg/m3 (110 pcf ), a maximum
Plasticity Index of 15, and a maximum Liquid Limit of 40.
C. Engineered Fill: Naturally or artificially graded m ixture of compliance
with ASTM D2487 Soil Classification Groups GW, GP, GM, SW, SP, SM, SC,
and ML, or any combination of these groups, or as a pproved by the
Engineer or material with at least 90 percent passi ng a 37.5-mm (1 1/2-
inch) sieve and not more than 12 percent passing a 75-µm (No. 200)
sieve, per ASTM D2940;.
D. Bedding: Naturally or artificially graded mixture o f natural or crushed
gravel, crushed stone, and natural or crushed sand; ASTM D2940; except
with 100 percent passing a 25 mm (1 inch) sieve and not more than 8
percent passing a 75- µm (No. 200) sieve.
E. Drainage Fill: Washed, narrowly graded mixture of c rushed stone, or
crushed or uncrushed gravel; ASTM D448; coarse-aggr egate grading Size
57; with 100 percent passing a 37.5 mm (1 1/2-inch) sieve and 0 to 5
percent passing a 2.36 mm (No. 8) sieve.
F. Granular Fill:
2. Bedding for sanitary and storm sewer pipe, crush ed stone or gravel
graded from 13 mm (1/2 inch) to 4.75 mm (No 4), per ASTM D2940.
G. Requirements for Offsite Soils: Offsite soils broug ht in for use as
backfill shall be tested for TPH, BTEX and full TCL P including
ignitability, corrosivity and reactivity. Backfill shall contain less
than 100 parts per million (ppm) of total hydrocarb ons (TPH) and less
than 10 ppm of the sum of Benzene, Toleune, Ethyl B enzene, and Xylene
(BTEX) and shall not fail the TCLP test. TPH concen trations shall be
determined by using EPA 600/4-79/020 Method 418.1. BTEX concentrations
shall be determined by using EPA SW-846.3-3a Method 5030/8020. TCLP
shall be performed in accordance with EPA SW-846.3- 3a Method 1311.
Provide Borrow Site Testing for TPH, BTEX and TCLP from a composite
sample of material from the borrow site, with at le ast one test from
each borrow site.
H. Buried Warning and Identification Tape: Polyethylen e plastic and
metallic core or metallic-faced, acid- and alkali-r esistant
polyethylene plastic warning tape manufactured spec ifically for warning
and identification of buried utility lines. Provide tape on rolls, 3
inch minimum width, color coded as specific below f or the intended
utility with warning and identification imprinted i n bold black letters
31 20 00 - 7
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
continuously over the entire tape length. Warning a nd identification
to read, “CAUTION, BURIED (intended service) LINE B ELOW” or similar
wording. Color and printing shall be permanent, Una ffected by moisture
or soil. Warning tape color codes:
Red: Electric
Blue: Water Systems
Green: Sewer Systems
White: Steam Systems
I. Warning Tape for Metallic Piping: Acid and alkali-r esistant
polyethylene plastic tape conforming to the width, color, and printing
requirements specified above. Minimum thickness of tape shall be 0.076
mm (0.003 inch). Tape shall have a minimum strength of 10.3 MPa (1500
psi) lengthwise, and 8.6 MPa (1250 psi) crosswise, with a maximum 350
percent elongation.
J. Detectable Warning Tape for Non-Metallic Piping: Po lyethylene plastic
tape conforming to the width, color, and printing r equirements
specified above. Minimum thickness of the tape shal l be 0.102 mm
(0.004 inch). Tape shall have a minimum strength of 10.3 MPa (1500 psi)
lengthwise and 8.6 MPa (1250 psi) crosswise. Tape s hall be
manufactured with integral wires, foil backing, or other means of
enabling detection by a metal detector when tape is buried up to 0.9 m
(3 feet) deep. Encase metallic element of the tape in a protective
jacket or provide with other means of corrosion pro tection.
K. Detection Wire For Non-Metallic Piping: Detection w ire shall be
Insulated single strand, solid copper with a minimu m of 12 AWG.
PART 3 - EXECUTION
3.1 SITE PREPARATION:
A. Clearing: Clear within limits of earthwork operatio ns as shown. Work
includes removal of trees, shrubs, fences, foundati ons, incidental
structures, paving, debris, trash, and other obstru ctions. Remove
materials from Medical Center Property.
B. Grubbing: Remove stumps and roots 75 mm (3 inch) an d larger diameter.
Undisturbed sound stumps, roots up to 75 mm (3 inch ) diameter, and
nonperishable solid objects a minimum of 900 mm (3 feet) below subgrade
or finished embankment may be left.
31 20 00 - 8
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
C. Trees and Shrubs: Trees and shrubs, not shown for r emoval, may be
removed from areas within 4500 mm (15 feet) of new construction and
2250 mm (7.5 feet) of utility lines when removal is approved in advance
by COR. Remove materials from Medical Center Proper ty. Box, and
otherwise protect from damage, existing trees and s hrubs which are not
shown to be removed in construction area. Immediate ly repair damage to
existing trees and shrubs by trimming, cleaning and painting damaged
areas, including roots, in accordance with standard industry
horticultural practice for the geographic area and plant species. Do
not store building materials closer to trees and sh rubs, that are to
remain, than farthest extension of their limbs.
D. Stripping Topsoil: Strip topsoil from within limits of earthwork
operations as specified. Topsoil shall be a fertile , friable, natural
topsoil of loamy character and characteristic of lo cality. Topsoil
shall be capable of growing healthy horticultural c rops of grasses.
Stockpile topsoil and protect as directed by COR. E liminate foreign
materials, such as weeds, roots, stones, subsoil, f rozen clods, and
similar foreign materials larger than 0.014 m3 (1/2 cubic foot) in
volume, from soil as it is stockpiled. Retain topso il on station.
Remove foreign materials larger than 50 mm (2 inche s) in any dimension
from topsoil used in final grading. Topsoil work, s uch as stripping,
stockpiling, and similar topsoil work shall not, un der any
circumstances, be carried out when soil is wet so t hat the composition
of the soil will be destroyed.
E. Concrete Slabs and Paving: Score deeply or saw cut to insure a neat,
straight cut, sections of existing concrete slabs a nd paving to be
removed where excavation or trenching occurs. Exten d pavement section
to be removed a minimum of 300 mm (12 inches) on ea ch side of widest
part of trench excavation and insure final score li nes are
approximately parallel unless otherwise indicated. Remove material from
Medical Center Property.
F. Lines and Grades: Registered Professional Land Surv eyor or Registered
Civil Engineer, specified in Section 01 00 00, GENE RAL REQUIREMENTS,
shall establish lines and grades.
1. Grades shall conform to elevations indicated on pla ns within the
tolerances herein specified. Generally grades shall be established
to provide a smooth surface, free from irregular su rface changes.
31 20 00 - 9
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
Grading shall comply with compaction requirements a nd grade cross
sections, lines, and elevations indicated. Where sp ot grades are
indicated the grade shall be established based on i nterpolation of
the elevations between the spot grades while mainta ining appropriate
transition at structures and paving and uninterrupt ed drainage flow
into inlets.
2. Locations of existing elevations indicated on plans are from a
site survey that measured spot elevations and subse quently generated
existing contours and spot elevations. Proposed spo t elevations
shall match existing elevations for restoration wor k. Contractor is
responsible to notify COR of any differences betwee n existing
elevations shown on plans and those encountered on site by
Surveyor/Engineer described above. Notify COR of an y differences
between existing or constructed grades, as compared to those shown
on the plans.
3. Subsequent to establishment of lines and grades, Co ntractor will be
responsible for any additional cut and/or fill requ ired to ensure
that site is graded to conform to elevations indica ted on plans.
4. Finish grading is specified in Section 32 90 00, PL ANTING.
G. Disposal: All materials removed from the property s hall be disposed of
at a legally approved site, for the specific materi als, and all
removals shall be in accordance with all applicable Federal, State and
local regulations. No burning of materials is permi tted onsite.
3.2 EXCAVATION:
A. Shoring, Sheeting and Bracing: Shore, brace, or slo pe, its angle of
repose or to an angle considered acceptable by the COR, banks of
excavations to protect workmen, banks, adjacent pav ing, structures, and
utilities.
1. Design of the temporary support of excavation syste m is the
responsibility of the Contractor. The Contractor sh all submit a
Shoring and Sheeting plan for approval 15 days prio r to starting
work. Submit drawings and calculations, certified b y a registered
professional engineer, describing the methods for s horing and
sheeting of excavations. Shoring, including sheet p iling, shall be
furnished and installed as necessary to protect wor kmen, banks,
adjacent paving, structures, and utilities. Shoring , bracing, and
31 20 00 - 10
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
sheeting shall be removed as excavations are backfi lled, in a manner
to prevent caving.
2. Construction of the support of excavation system sh all not interfere
with the permanent structure and may begin only aft er a review by
the COR.
3. Extend shoring and bracing to a minimum of 1500 mm (5 feet) below
the bottom of excavation. Shore excavations that ar e carried below
elevations of adjacent existing foundations.
4. If bearing material of any foundation is disturbed by excavating,
improper shoring or removal of existing or temporar y shoring,
placing of backfill, and similar operations, the Co ntractor shall
provide a concrete fill support in compliance with specifications
Section 31 23 23.33, FLOWABLE FILL, under disturbed foundations, as
directed by COR, at no additional cost to the Gover nment. Do not
remove shoring until permanent work in excavation h as been inspected
and approved by COR.
5. The Contractor is required to hire a Professional G eotechnical
Engineer to provide inspection of excavations and s oil/groundwater
conditions throughout construction. The Geotechnica l Engineer shall
be responsible for performing pre-construction and periodic site
visits throughout construction to assess site condi tions. The
Geotechnical Engineer shall update the excavation, sheeting and
dewatering plans as construction progresses to refl ect changing
conditions and shall submit an updated plan if nece ssary. A written
report shall be submitted, at least monthly, inform ing the
Contractor and COR of the status of the plan and an accounting of
the Contractor's adherence to the plan addressing a ny present or
potential problems. The Geotechnical Engineer shall be available to
meet with the COR at any time throughout the contra ct duration.
B. Subgrade Protection: Protect subgrades from softeni ng, undermining,
washout, or damage by rain or water accumulation. R eroute surface
water runoff from excavated areas and not allow wat er to accumulate in
excavations. Do not use excavated trenches as tempo rary drainage
ditches. When subgrade for foundations has been dis turbed by water,
remove disturbed material to firm undisturbed mater ial after water is
brought under control. Replace disturbed subgrade i n trenches with
concrete or material approved by the COR.
31 20 00 - 11
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
C. Trench Earthwork:
1. Utility trenches (except sanitary and storm sewer):
a. Excavate to a width as necessary for sheeting and b racing and
proper performance of the work.
b. Grade bottom of trenches with bell holes scooped ou t to provide a
uniform bearing.
c. Support piping on suitable undisturbed earth unless a mechanical
support is shown. Unstable material removed from th e bottom of
the trench or excavation shall be replaced with sel ect granular
material placed in layers not exceeding 150 mm (6 i nches) loose
thickness.
d. Length of open trench in advance of piping laying s hall not be
greater than is authorized by COR.
e. Provide buried utility lines with utility identific ation tape.
Bury tape 300 mm (12 inches) below finished grade; under
pavements and slabs, bury tape 150 mm (6 inches) be low top of
subgrade
f. Bury detection wire directly above non-metallic pip ing at a
distance not to exceed 300 mm (12 inches) above the top of pipe.
The wire shall extend continuously and unbroken, fr om manhole to
manhole. The ends of the wire shall terminate insid e the
manholes at each end of the pipe, with a minimum of 0.9 m (3
feet) of wire, coiled, remaining accessible in each manhole. The
wire shall remain insulated over its entire length. The wire
shall enter manholes between the top of the corbel and the frame,
and extend up through the chimney seal between the frame and the
chimney seal. For force mains, the wire shall termi nate in the
valve pit at the pump station end of the pipe.
g. Initial backfill material shall be placed and compa cted with
approved tampers to a height of at least one foot a bove the
utility pipe or conduit. The backfill shall be brou ght up evenly
on both sides of the pipe for the full length of th e pipe. Care
shall be taken to ensure thorough compaction of the fill under
the haunches of the pipe. Except as specified other wise in the
individual piping section, provide bedding for buri ed piping in
accordance with AWWA C600, Type 4, except as specif ied herein.
Backfill to top of pipe shall be compacted to 95 pe rcent of ASTM
31 20 00 - 12
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
D 698 maximum density. Plastic piping shall have b edding to
spring line of pipe. Provide materials as follows:
1) Class II: Coarse sands and gravels with maximum particle size
of 40 mm (1.5 inches), including various graded san ds and
gravels containing small percentages of fines, gene rally
granular and noncohesive, either wet or dry. Soil T ypes GW,
GP, SW, and SP are included in this class as specif ied in ASTM
D2487.
2. Storm sewer trenches:
a. Trench width below a point 150 mm (6 inches) above top of pipe
shall be 600 mm (24 inches) maximum for pipe up to and including
300 mm (12 inches) diameter, and four-thirds diamet er of pipe
plus 200 mm (8 inches) for pipe larger than 300 mm (12 inches).
Width of trench above that level shall be as necess ary for
sheeting and bracing and proper performance of the work.
1) Bed bottom quadrant of pipe on suitable undisturbed soil or
granular fill. Unstable material removed from the b ottom of
the trench or excavation shall be replaced with sel ect
granular material placed in layers not exceeding 15 0 mm (6
inches) loose thickness.1) Undisturbed: Bell holes shall be no
larger than necessary for jointing. Backfill up to a point 300
mm (12 inches) above top of pipe shall be clean ear th placed
and tamped by hand.
2) Granular Fill: Depth of fill shall be a minimum of 75 mm (3
inches) plus one sixth of pipe diameter below pipe to 300 mm
(12 inches) above top of pipe. Place and tamp fill material by
hand.
b. Place and compact as specified remainder of backfil l using
acceptable excavated materials. Do not use unsuitab le materials.
c. Use granular fill for bedding where rock or rocky m aterials are
excavated.
d. Provide buried utility lines with utility identific ation tape.
Bury tape 300 mm (12 inches) below finished grade; under
pavements and slabs, bury tape 150 mm (6 inches) be low top of
subgrade
e. Bury detection wire directly above non-metallic pip ing at a
distance not to exceed 300 mm (12 inches) above the top of pipe.
31 20 00 - 13
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
The wire shall extend continuously and unbroken, fr om manhole to
manhole. The ends of the wire shall terminate insid e the
manholes at each end of the pipe, with a minimum of 0.9 m (3
feet) of wire, coiled, remaining accessible in each manhole. The
wire shall remain insulated over it's entire length . The wire
shall enter manholes between the top of the corbel and the frame,
and extend up through the chimney seal between the frame and the
chimney seal. For force mains, the wire shall termi nate in the
valve pit at the pump station end of the pipe.
f. Initial backfill material shall be placed and compa cted with
approved tampers to a height of at least one foot a bove the
utility pipe or conduit. The backfill shall be brou ght up evenly
on both sides of the pipe for the full length of th e pipe. Care
shall be taken to ensure thorough compaction of the fill under
the haunches of the pipe. Except as specified other wise in the
individual piping section, provide bedding for buri ed piping in
accordance with AWWA C600, Type 4, except as specif ied herein.
Backfill to top of pipe shall be compacted to 95 pe rcent of ASTM
D698 maximum density. Plastic piping shall have be dding to
spring line of pipe. Provide materials as follows:
1) Class I: Angular, 6 to 40 mm (0.25 to 1.5 inches), graded
stone, including a number of fill materials that ha ve regional
significance such as coral, slag, cinders, crushed stone, and
crushed shells.
D. Site Earthwork: Earth excavation includes excavatin g pavements and
obstructions visible on surface; underground struct ures, utilities, and
other items indicated to be removed; together with soil, boulders, and
other materials not classified as rock or unauthori zed excavation.
Excavation shall be accomplished as required by dra wings and
specifications. Excavate to indicated elevations an d dimensions within
a tolerance of plus or minus 25 mm (1 inch). Extend excavations a
sufficient distance from structures for placing and removing concrete
formwork, for installing services and other constru ction, complying
with OSHA requirements, and for inspections. Remove subgrade materials
that are determined by COR as unsuitable, and repla ce with acceptable
material. If there is a question as to whether mate rial is unsuitable
or not, the contractor shall obtain samples of the material, under the
31 20 00 - 14
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
direction of the COR, and the materials shall be ex amined by an
independent testing laboratory for soil classificat ion to determine
whether it is unsuitable or not. When unsuitable ma terial is
encountered and removed, contract price and time wi ll be adjusted in
accordance with Articles, DIFFERING SITE CONDITIONS , CHANGES and
CHANGES-SUPPLEMENT of the GENERAL CONDITIONS as app licable. Adjustments
to be based on volume in cut section only.
1. Site Grading:
a. Provide a smooth transition between adjacent existi ng grades and
new grades.
b. Cut out soft spots, fill low spots, and trim high s pots to comply
with required surface tolerances.
c. Slope grades to direct water away from buildings an d to prevent
ponds from forming where not designed. Finish subgr ades to
required elevations within the following tolerances :
1) Lawn or Unpaved Areas: Plus or minus 25 mm (1 inch) .
2) Walks: Plus or minus 6 mm (1/4 inch).
3) Pavements: Plus or minus 6 mm (1/4 inch).
3.3 UNDERPINNING:
A. Design of the underpinning system is the responsibi lity of the
Contractor and should be designed by a registered p rofessional engineer
and is subject to review and approval by the COR. U nderpinning of
existing building foundations, as indicated on stru ctural drawings, or
where excavation undermines existing foundations, s hall be accomplished
in the following manner:
1. Make general excavation for new construction, where new foundations
are to be below existing foundations, to elevation of new
foundations (or sized stone subbase), maintaining a 45 degree sloped
berm.
2. For underpinning pits, underpin existing wall found ations by
excavating 1200 mm (4 feet) wide pits to depth show n on drawings
skipping 3 sections at any one time so as to mainta in support for
wall at all times.
3. Underpin intervening sections one at a time; no adj acent sections
shall be underpinned until concrete in adjacent sec tions shall have
reached 20 MPa (2500 psi) strength and have been dr y packed with
non-shrink grout to obtain positive bearing. Sheet and brace
31 20 00 - 15
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
underpinning pits if soil will not stand on a verti cal cut during
this operation, or as required for safety of workme n. Repack any
voids behind sheeting to prevent sloughing which co uld cause
settlement of existing foundations. Contractor perf orming this
portion of work shall have been prequalified by COR as having
previously performed successfully this type of work or will
demonstrate his capability for successfully perform ing this work. It
shall be sole responsibility of the Contractor to g uard against
objectionable movement or settlement and to preserv e integrity of
existing structures.
4. The tip elevation of the underpinning pits shall be a minimum of 900
mm (3 feet) below the adjacent excavation elevation .
5. Subgrades at the tip of the underpinning pit shall be clean, dry,
and free of debris and shall be observed by the COR prior to
concrete placement.
6. Concrete shall not be free fall greater than 3000 m m (10 feet) into
the pit.
3.4 FILLING AND BACKFILLING:
A. General: Do not fill or backfill until all debris, water,
unsatisfactory soil materials, obstructions, and de leterious materials
have been removed from excavation. For fill and bac kfill, use excavated
materials and borrow meeting the criteria specified herein, as
applicable. Borrow will be supplied at no additiona l cost to the
Government. Do not use unsuitable excavated materia ls. Do not backfill
until foundation walls have been completed above gr ade and adequately
braced, waterproofing or dampproofing applied, foun dation drainage, and
pipes coming in contact with backfill have been ins talled and work
inspected and approved by COR.
B. Placing: Place materials in horizontal layers not e xceeding 200 mm (8
inches) in loose depth for material compacted by he avy compaction
equipment, and not more than 100 mm (4 inches) in l oose depth for
material compacted by hand-operated tampers and the n compacted. Place
backfill and fill materials evenly on all sides of structures to
required elevations, and uniformly along the full l ength of each
structure. Place no material on surfaces that are m uddy, frozen, or
contain frost.
31 20 00 - 16
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
C. Compaction: Compact with approved tamping rollers, sheepsfoot rollers,
pneumatic tired rollers, steel wheeled rollers, vib rator compactors, or
other approved equipment (hand or mechanized) well suited to soil being
compacted. Do not operate mechanized vibratory comp action equipment
within 3000 mm (10 feet) of new or existing buildin g walls without
prior approval of COR. Moisten or aerate material a s necessary to
provide moisture content that will readily facilita te obtaining
specified compaction with equipment used. Backfill adjacent to any and
all types of structures shall be placed and compact ed to at least 90
percent laboratory maximum density for cohesive mat erials or 95 percent
laboratory maximum density for cohesionless materia ls to prevent
wedging action or eccentric loading upon or against the structure.
Compact soil to not less than the following percent ages of maximum dry
density, according to ASTM D698 or ASTM D1557 as sp ecified below:
1. Fills, Embankments, and Backfill
a. Under proposed structures, building slabs, steps, a nd paved
areas, scarify and recompact top 300 mm (12 inches) of existing
subgrade and each layer of backfill or fill materia l in
accordance with ASTM D698 95 percent.
b. Curbs, curbs and gutters, ASTM D698 95 percent.
c. Under Sidewalks, scarify and recompact top 150 mm ( 6 inches)
below subgrade and compact each layer of backfill o r fill
material in accordance with ASTM D698 95 percent.
d. Landscaped areas, top 400 mm (16 inches), ASTM D698 85 percent.
e. Landscaped areas, below 400 mm (16 inches) of finis hed grade,
ASTM D698 90 percent.
D. Borrow Material: Borrow material shall be selected to meet the
requirements and conditions of the particular fill or embankment for
which it is to be used. Borrow material shall be ob tained from the
borrow areas from approved private sources. Unless otherwise provided
in the contract, the Contractor shall obtain from t he owners the right
to procure material, pay royalties and other charge s involved, and bear
the expense of developing the sources, including ri ghts-of-way for
hauling. Borrow material from approved sources on G overnment-
controlled land may be obtained without payment of royalties. Unless
specifically provided, no borrow shall be obtained within the limits of
the project site without prior written approval. Ne cessary clearing,
31 20 00 - 17
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
grubbing, and satisfactory drainage of borrow pits and the disposal of
debris thereon shall be considered related operatio ns to the borrow
excavation.
E. Opening and Drainage of Excavation and Borrow Pits: The Contractor
shall notify the COR sufficiently in advance of the opening of any
excavation or borrow pit to permit elevations and m easurements of the
undisturbed ground surface to be taken. Except as o therwise permitted,
borrow pits and other excavation areas shall be exc avated providing
adequate drainage. Overburden and other spoil mater ial shall be
transported to designated spoil areas or otherwise disposed of as
directed. Borrow pits shall be neatly trimmed and d rained after the
excavation is completed. The Contractor shall ensur e that excavation
of any area, operation of borrow pits, or dumping o f spoil material
results in minimum detrimental effects on natural e nvironmental
conditions.
3.5 GRADING:
A. General: Uniformly grade the areas within the limit s of this section,
including adjacent transition areas. Smooth the fin ished surface within
specified tolerance. Provide uniform levels or slop es between points
where elevations are indicated, or between such poi nts and existing
finished grades. Provide a smooth transition betwee n abrupt changes in
slope.
B. Cut rough or sloping rock to level beds for foundat ions. In pipe spaces
or other unfinished areas, fill low spots and level off with coarse
sand or fine gravel.
C. Slope backfill outside building away from building walls for a minimum
distance of 1800 mm (6 feet).
D. Finish grade earth floors in pipe basements as show n to a level,
uniform slope and leave clean.
E. Finished grade shall be at least 150 mm (6 inches) below bottom line of
window or other building wall openings unless great er depth is shown.
F. Place crushed stone or gravel fill under concrete s labs on grade,
tamped, and leveled. Thickness of fill shall be 150 mm (6 inches)
unless otherwise shown.
G. Finish subgrade in a condition acceptable to COR at least one day in
advance of paving operations. Maintain finished sub grade in a smooth
and compacted condition until succeeding operation has been
31 20 00 - 18
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
accomplished. Scarify, compact, and grade subgrade prior to further
construction when approved compacted subgrade is di sturbed by
Contractor's subsequent operations or adverse weath er.
H. Grading for Paved Areas: Provide final grades for b oth subgrade and
base course to +/- 6 mm (0.25 inches) of indicated grades.
3.6 DISPOSAL OF UNSUITABLE AND EXCESS EXCAVATED MATERIAL:
A. Disposal: Remove surplus satisfactory soil and wast e material,
including unsatisfactory soil, trash, and debris, a nd legally dispose
of it off Medical Center property.
B. Place excess excavated materials suitable for fill and/or backfill on
site where directed.
C. Remove from site and dispose of any excess excavate d materials after
all fill and backfill operations have been complete d.
D. Segregate all excavated contaminated soil designate d by the COR from
all other excavated soils, and stockpile on site on two 0.15 mm (6 mil)
polyethylene sheets with a polyethylene cover. A de signated area shall
be selected for this purpose. Dispose of excavated contaminated
material in accordance with State and Local require ments.
3.7 CLEAN UP:
Upon completion of earthwork operations, clean area s within contract
limits, remove tools, and equipment. Provide site c lear, clean, free of
debris, and suitable for subsequent construction op erations. Remove all
debris, rubbish, and excess material from Medical C enter Property.
----- E N D -----
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
SECTION 31 23 19 DEWATERING
PART 1 - GENERAL
1.1 DESCRIPTION:
This section specifies performance of dewatering re quired to lower and
control ground water table levels and hydrostatic p ressures to permit
excavation, backfill, and construction to be perfor med in the dry.
Control of surface water shall be considered as par t of the work under
this specification.
1.2 SUMMARY:
A. The work to be completed by the Contractor includes , but is not
necessarily limited to the following:
1. Implementation of the Erosion and Sedimentation Con trol Plan.
2. Dewater excavations, including seepage and precipit ation.
B. The Contractor shall be responsible for providing a ll materials,
equipment, labor, and services necessary for care o f water and erosion
control. Excavation work shall not begin before the Erosion and
Sedimentation Control Plan is in place.
1.3 REQUIREMENT:
A. Dewatering system shall be of sufficient size and c apacity necessary to
lower and maintain ground water table to an elevati on at least 300 mm (1
foot) below lowest foundation subgrade or bottom of pipe trench and to
allow material to be excavated, piles to be driven, and concrete placed,
in a reasonably dry condition. Materials to be remo ved shall be
sufficiently dry to permit excavation to grades sho wn and to stabilize
excavation slopes where sheeting is not required. O perate dewatering
system continuously until backfill work has been co mpleted.
B. Reduce hydrostatic head below any excavation to the extent that water
level in the construction area is a minimum of 300 mm (1 foot) below
prevailing excavation surface.
C. Prevent loss of fines, seepage, boils, quick condit ions or softening of
foundation strata.
D. Maintain stability of sides and bottom of excavatio n.
E. Construction operations are performed in the dry.
F. Control of surface and subsurface water is part of dewatering
requirements. Maintain adequate control so that:
1. The stability of excavated and constructed slopes a re not adversely
affected by saturated soil, including water enterin g prepared subbase
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
31 23 19 - 2
and subgrades where underlying materials are not fr ee draining or are
subject to swelling or freeze-thaw action.
2. Erosion is controlled.
3. Flooding of excavations or damage to structures doe s not occur.
4. Surface water drains away from excavations.
5. Excavations are protected from becoming wet from su rface water, or
insure excavations are dry before additional work i s undertaken.
G. Permitting Requirements: The contractor shall compl y with and obtain the
required State and County permits where the work is performed.
1.4 RELATED WORK:
A. Materials testing and inspection during constructio n: Section 01 45 29,
TESTING LABORATORY SERVICES.
B. Safety Requirements: Section 00 72 00, GENERAL COND ITIONS, Article,
ACCIDENT PREVENTION.
C. Submittal requirements as specified in Section 01 3 3 23 SHOP DRAWINGS,
PRODUCT DATA, AND SAMPLES.
D. Protection of existing utilities, fire protection s ervices, existing
equipment, roads, and pavements: Section 01 00 00, GENERAL REQUIREMENTS.
E. Subsurface Investigation: Section 01 00 00, GENERAL REQUIREMENTS,
Article 1.11, PHYSICAL DATA.
F. Excavation, backfilling, site grade and utilities: Section 31 20 00,
EARTH MOVING.
1.5 SUBMITTALS:
A. Submit in accordance with Section 01 33 23, SHOP DR AWINGS, PRODUCT DATA,
AND SAMPLES.
B. Drawings and Design Data:
1. Submit drawings and data showing the method to be e mployed in
dewatering excavated areas 30 days before commencem ent of excavation.
2. Material shall include: location, depth and size of wellpoints,
headers, sumps, ditches, size and location of disch arge lines,
capacities of pumps and standby units, and detailed description of
dewatering methods to be employed to convey the wat er from site to
adequate disposal.
3. Include a written report outlining control procedur es to be adopted
if dewatering problem arises.
4. Capacities of pumps, prime movers, and standby equi pment.
5. Design calculations proving adequacy of system and selected
equipment. The dewatering system shall be designed using accepted and
professional methods of design and engineering cons istent with the
best modern practice. The dewatering system shall i nclude the deep
31 23 19 - 3
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
wells, wellpoints, and other equipment, appurtenanc es, and related
earthwork necessary to perform the function.
6. Detailed description of dewatering procedure and ma intenance method.
7. Materials submitted shall be in a format acceptable for inclusion in
required permit applications to any and all regulat ory agencies for
which permits for discharge water from the dewateri ng system are
required due to the discharge reaching regulated bo dies of water.
C. Inspection Reports.
D. All required permits.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.1 INSTALLATION:
A. Install a dewatering system to lower and control gr ound surface water in
order to permit excavation, construction of structu re, and placement of
backfill materials to be performed under dry condit ions. Make the
dewatering system adequate to pre-drain the water-b earing strata above
and below the bottom of structure foundations, util ities and other
excavations.
B. In addition, reduce hydrostatic pressure head in wa ter-bearing strata
below structure foundations, utility lines, and oth er excavations, to
extent that water levels in construction area are a minimum of 300 mm (1
foot) below prevailing excavation surface at all ti mes.
3.2 OPERATION:
A. Prior to any excavation below the ground water tabl e, place system into
operation to lower water table as required and oper ate it continuously
24 hours a day, 7 days a week until utilities and s tructures have been
satisfactorily constructed, which includes the plac ement of backfill
materials and dewatering is no longer required.
B. Place an adequate weight of backfill material to pr event buoyancy prior
to discontinuing operation of the system.
3.3 WATER DISPOSAL:
A. Dispose of water removed from the excavations in su ch a manner as:
1. Will not endanger portions of work under constructi on or completed.
2. Will cause no inconvenience to Government or to oth ers working near
site.
3. Will comply with the stipulations of required permi ts for disposal of
water.
4. Will Control Runoff: The Contractor shall be respon sible for control
of runoff in all work areas including but not limit ed to:
excavations, access roads, parking areas, laydown, and staging areas.
31 23 19 - 4
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
The Contractor shall provide, operate, and maintain all ditches,
basins, sumps, culverts, site grading, and pumping facilities to
divert, collect, and remove all water from the work areas. All water
shall be removed from the immediate work areas and shall be disposed
of in accordance with applicable permits.
B. Excavation Dewatering:
1. The Contractor shall be responsible for providing a ll facilities
required to divert, collect, control, and remove wa ter from all
construction work areas and excavations.
2. Drainage features shall have sufficient capacity to avoid flooding of
work areas.
3. Drainage features shall be so arranged and altered as required to
avoid degradation of the final excavated surface(s) .
4. The Contractor shall utilize all necessary erosion and sediment
control measures as described herein to avoid const ruction related
degradation of the natural water quality.
C. Dewatering equipment shall be provided to remove an d dispose of all
surface and ground water entering excavations, tren ches, or other parts
of the work during construction. Each excavation sh all be kept dry
during subgrade preparation and continually thereaf ter until the
structure to be built, or the pipe to be installed therein, is completed
to the extent that no damage from hydrostatic press ure, flotation, or
other cause will result.
3.4 STANDBY EQUIPMENT:
Provide complete standby equipment, installed and a vailable for
immediate operation, as may be required to adequate ly maintain de-
watering on a continuous basis and in the event tha t all or any part of
the system may become inadequate or fail.
3.5 CORRECTIVE ACTION:
If dewatering requirements are not satisfied due to inadequacy or
failure of the dewatering system (loosening of the foundation strata, or
instability of slopes, or damage to foundations or structures), perform
work necessary for reinstatement of foundation soil and damaged
structure or damages to work in place resulting fro m such inadequacy or
failure by Contractor, at no additional cost to Gov ernment.
3.6 DAMAGES:
Immediately repair damages to adjacent facilities c aused by dewatering
operations.
31 23 19 - 5
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
3.7 REMOVAL:
Insure compliance with all conditions of regulating permits and provide
such information to the Resident Engineer. Obtain w ritten approval from
Resident Engineer before discontinuing operation of dewatering system.
----- E N D -----
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
SECTION 31 23 23.33 FLOWABLE FILL
PART 1 - GENERAL
1.1 INTRODUCTION:
A. Flowable fill refers to a cementitious slurry consi sting of a mixture of
fine aggregate or filler, water, and cementitious m aterial(s), which is
used as a fill or backfill in lieu of compacted ear th. This mixture is
capable of filling all voids in irregular excavatio ns and hard to reach
places (such as under undercuts of existing slabs), is self-leveling,
and hardens in a matter of a few hours without the need for compaction
in layers. Flowable fill is sometimes referred to a s controlled density
fill (CDF), controlled low strength material (CLSM) , lean concrete
slurry, and unshrinkable fill.
B. Flowable fill materials will be used as only as a s tructural fill
replacement on VA projects. The materials and mix d esign for the
flowable fill should be designed to produce a compa rable compressive
strength to the surrounding soil after hardening, m aking excavation at a
later time possible /to produce the compressive str ength indicated for
the placed location, as determined by the COR.
1.2 DESCRIPTION:
Furnish and place flowable fill in a fluid conditio n, that sets within
the required time and, after curing, obtains the de sired strength
properties as evidenced by the laboratory testing o f the specific mix
design, at locations shown on the plans or as direc ted by the COR,
verbally and as shown in plan.
1.3 RELATED WORK:
A. Materials testing and inspection during constructio n: Section 01 45 29,
TESTING LABORATORY SERVICES.
B. Earthwork, excavation and backfill and compaction r equirements: Section
31 20 00, EARTH MOVING.
1.4 DEFINITIONS:
A. Flowable fill - Ready-mix Controlled Low Strength M aterial used as an
alternative to compacted soil, and is also known as controlled density
fill, and several other names, some of which are tr ademark names of
material suppliers. Flowable fill (Controlled Low S trength Material)
differs from portland cement concrete as it contain s a low cementitious
content to reduce strength development for possible future removal.
Unless specifically approved otherwise, by the COR, flowable fill shall
be designed as a permanent material, not designed f or future removal.
Design strength for this permanent type flowable fi ll shall be a
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
31 23 23.33 - 2
compressive strength of 2.1 MPa (300 psi) minimum a t 28 days. Chemical
admixtures may also be used in flowable fill to mod ify performance
properties of strength, flow, set and permeability.
B. Excavatable Flowable fill – flowable fill designed with a compressive
strength that will allow excavation as either machi ne tool excavatable
at compressive strength of 1.5 MPa (200 psi) maximu m at 1 year, or hand
tool excavatable at compressive strength of 0.7 MPa (100 psi) maximum at
1 year.
1.5 SUBMITTALS:
A. Submit in accordance with Section 01 33 23, SHOP DR AWINGS, PRODUCT DATA,
AND SAMPLES.
B. Flowable fill Mix Design: Provide flowable fill mix design containing
cement and water. At the contractor’s option, it ma y also contain fly
ash, aggregate, or chemical admixtures in any propo rtions such that the
final product meets the strength and flow consisten cy, and shrinkage
requirements included in this specifications. The m ix design should
state the sources and proportions of each of the fl owable fill
constituents. The coefficient of permeability of fl owable fill shall be
that of uniform fine sand, 4.0 X 10-1 cm/sec (0.16 in/sec) or as
indicated to provide a backfill material with perme ability equal to or
greater than that of the surrounding soil.
1. Test and Performance - Submit the following data:
a. Flowable fill shall have a minimum strength of 2.1 MPa (300 psi)
according to ASTM C 39 at 28 days after placement.
b. Flowable fill shall have minimal subsidence and ble ed water
shrinkage. Evaporation of bleed water shall not res ult in
shrinkage of more than 10.4 mm per m (1/8 inch per ft.) of
flowable fill depth (for mixes containing high fly ash content).
Measurement of a Final Bleeding shall be as measure d in Section 10
of ASTM C 940 “Standard Test Method for Expansion a nd Bleeding of
Freshly Mixed Grouts for Preplaced-Aggregate Concre te in the
Laboratory.
c. Flowable fill shall have a unit weight of 1500 - 19 00 kg/m3 (90 -
115 lbs/feet 3) measured at the point of placement after a 60
minute ready-mix truck ride.
C. Provide documentation that the admixture supplier h as experience of at
least one year, with the products being provided an d any equipment
required to obtain desired performance of the produ ct.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
31 23 23.33 - 3
D. Manufacturer's Certificates: Provide COR with docum entation issued by
the State Agency responsible for approving material s for burial,
indicating conformance with applicable rules and re gulations.
1.6 APPLICABLE PUBLICATIONS:
A. Publications listed below form a part of this speci fication to extent
referenced. Publications are referenced in text by basic designation
only.
B. American Society for Testing and Materials (ASTM):
D4832-10................Standard Test Method for Pr eparation and Testing
of Controlled Low Strength Material (CLSM) Test
Cylinders.
C618-12.................Standard Specifications for Coal Fly Ash and Raw
or Calcined Natural Pozzolan for use in
Concrete. (Use Fly Ash conforming to the
chemical and physical requirements for mineral
admixture, Class F listed, including Table 2
(except for Footnote A). Waive the loss on
ignition requirement.)
C403/C403M-08...........Standard Test Method for Ti me of Setting of
Concrete Mixtures by Penetration Resistance.
C150/C150M-11...........Standard Specification for Portland Cement
C33/C33M-11a............Standard Specification for Concrete Aggregates
C94/C94M-12.............Standard Specification for Ready-Mixed Concrete
C494/C494M-11...........Standard Specification for Chemical Admixtures
for Concrete
C685/C685M-11...........Standard Specification for Concrete Made by
Volumetric Batching and Continuous Mixing
C940-10a................Standard Specification for Expansion and
Bleeding of Freshly Mixed Grouts for Preplaced –
Aggregate Concrete in the Laboratory
D5971...................Sampling Freshly Mixed Cont rolled Low Strength
Material
D6103...................Flow Consistency of Control led Low Strength
Material
D6023...................Unit Weight, Yield, Cement Content and Air
Content (Gravimetric) of Controlled Low Strength
Material
C. American Concrete Institute (ACI):
SP-150-94...............Controlled Low-Strength Mat erials
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
31 23 23.33 - 4
1.7 QUALITY ASSURANCE:
A. Manufacturer: Flowable fill shall be manufactured b y a ready-mix
concrete producer with a minimum of 1 year experien ce in the production
of similar products.
B. Materials: For each type of material required for t he work of this
Section, provide primary materials that are the pro ducts of one
manufacturer. If not otherwise specified here, mate rials shall comply
with recommendations of ACI 229, “Controlled Low St rength Materials.”
C. Pre-Approval Procedures: The use of flowable fill d uring any part of the
project shall be restricted to those incidences whe re, due to field
conditions, the Contractor has made the COR aware o f the conditions for
which he recommends the use of the flowable, and th e COR has confirmed
those conditions and approved the use of the flowab le fill, in advance.
During the submittal process, the contractor shall prepare and submit
various flowable fill mix designs corresponding to required conditions
or if the contractor desires to use flowable fill d ue to economics.
Approval for the strength of the flowable fill shal l be obtained from
the COR when the contractor desires, or is required , to use flowable
fill at specific location(s) within the project. Pr ior to commencement
of field operations the contractor shall establish procedures to
maintain optimum working conditions and to coordina te this work with
related and adjacent work.
D. Sampling and Acceptance: Flowable fill shall be sam ples and testing in
the field in conformance with either ASTM C 94 or C 685. Samples for
tests shall be taken for every 115 cubic meters (15 0 cubic yards) of
material, or fraction thereof, for each day’s place ment. Tests shall
include temperature reading and four compressive st rength cylinders.
Compressive strength sampling and testing shall con form to ASTM D 4832
with one specimen tested at 7 days, two at 28 days, and one held for
each batch of four specimens. Sampling and testing shall be performed
by a qualified, independent commercial testing labo ratory. Test results
should be submitted within 48 hours of completion o f testing.
1.8 DELIVERY, STORAGE, AND HANDLING:
Deliver and handle all products and equipment requi red, in strict
compliance with manufacturer’s recommendations. Pro tect from damage due
to weather, excessive temperatures, and constructio n operations.
1.9 PROJECT CONDITIONS:
Perform installation of flowable fill only when app roved by the COR, and
when existing and forecasted weather conditions are within the limits
established by the manufacturer of the materials an d products used.
31 23 23.33 - 5
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
PART 2 - PRODUCTS
2.1 MATERIALS:
A. Provide flowable fill containing, at a minimum, cem entitious materials
and water. Cementitious materials shall be portland cement, pozzolanic
materials, or other self-cementing materials, or co mbinations thereof,
at the contractor’s option, and following approval by the COR. The
flowable fill mix design may also contain, fine agg regate or filler,
and/or chemical admixtures in any proportions such that the final
product meets the strength, flow consistency and sh rinkage requirements
included in this specification, as approved by the COR.
B. Portland Cement: ASTM C150, Type 1 or Type 2. Meeti ng Wisconsin State
DOT standards.
C. Mixing Water: Meeting Wisconsin State DOT standards for use as mix-water
for cast-in-place concrete.
D. Air-Entraining Admixture: ASTM C260.
E. Chemical Admixtures: ASTM C494.
F. Aggregate: ASTM C33.
2.2 FLOWABLE FILL MIXTURE:
A. Mix design shall produce a consistency that will re sult in a flowable
product at the time of placement which does not req uire manual means to
move it into place.
B. Flowable fill shall have a minimum strength of 2.1 MPa (300 psi)
according to ASTM C39 at 28 days after placement.
C. Flowable fill shall have minimal subsidence and ble ed water shrinkage.
Evaporation of bleed water shall not result in shri nkage of more than
10.4 mm per m (1/8 inch per foot) of flowable fill depth (for mixes
containing high fly ash content). Measurement of a Final Bleeding shall
be as measured in Section 10 of ASTM C 940 “Standar d Test Method for
Expansion and Bleeding of Freshly Mixed Grouts for Preplaced-Aggregate
Concrete in the Laboratory.
D. Flowable fill shall have a unit weight of 1500 - 19 00 kg/m3 (90 - 115
lbs/feet3) measured at the point of placement after a 60 minute ready-
mix truck ride. In the absence of strength data the cementitious content
shall be a maximum of 90 kg/m3 (150 lbs/cy).
E. Flowable fill shall have an in-place yield of at le ast 98% of design
yield for permanent type a maximum of 110% of desig n yield for removable
types at 1 year.
F. Provide equipment as recommended by the Manufacture r and comply with
manufacturer’s recommendations for the addition of additives, whether at
the production plant or prior to placement at the s ite.
31 23 23.33 - 6
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
PART 3 - EXECUTION
3.1 EXAMINATION:
Examine conditions of substrates and other conditio ns under which work
is to be performed and notify COR, in writing, of c ircumstances
detrimental to the proper completion of the work. D o not proceed until
unsatisfactory conditions are corrected.
3.2 APPLICATION OF FLOWABLE FILL:
Secure tanks, pipes and other members to be encased in flowable fill.
Insure that there are no exposed metallic pipes, co nduits, or other
items that will be in contact with the flowable fil l after placement. If
so, replace with non-metallic materials or apply ma nufacturers
recommended coating to protect metallic objects bef ore placing the
flowable fill. Replacement or protection of metalli c objects is subject
to the approval of the COR.
3.3 PROTECTION AND CURING:
Protect exposed surfaces of flowable fill from prem ature drying, wash by
rain or running water, wind, mechanical injury, and excessively hot or
cold temperature. Curing method shall be subject to approval by COR.
- - - E N D - - -
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
32 05 23 - 1
SECTION 32 05 23 CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS
PART 1 - GENERAL 1.1 SUMMARY
A. Section Includes:
1. Subbase for concrete pavements.
2. Curbs, gutters, and combination curbs and gutters.
3. Pedestrian Pavement: Walks. 1.2 RELATED REQUIREMENTS
A. Field Testing: Section 01 45 29, TESTING LABORATORY SERVICES.
B. Step Nosings and Railings: Section 05 50 00, METAL FABRICATIONS.
C. Subgrade Preparation and Subbase Compaction: Sectio n 31 20 00,
EARTHWORK.
1.3 APPLICABLE PUBLICATIONS
A. Comply with references to extent specified in this section.
B. American Association of State Highway and Transport ation Officials
(AASHTO):
1. M147-65-UL-04 - Materials for Aggregate and Soil-Ag gregate Subbase,
Base and Surface Courses.
2. M233-86 - Boiled Linseed Oil Mixture for Treatment of Portland
Cement Concrete.
C. American Concrete Institute (ACI):
1. 305R-10 - Guide to Hot Weather Concreting.
2. 306R-10 - Guide to Cold Weather Concreting.
D. American National Standards Institute (ANSI):
1. B101.3 - Wet DOCF of Common Hard Surface Floor Mate rials (Including
Action and Limit Thresholds for the Suitable Assess ment of the
Measured Values).
E. ASTM International (ASTM):
1. A615/A615M-16 - Deformed and Plain Carbon Steel Bar s for Concrete
Reinforcement.
2. A996/A996M-15 - Rail-Steel and Axle-Steel Deformed Bars for Concrete
Reinforcement.
3. A1064/A1064M-16 - Carbon-Steel Wire and Welded Wire Reinforcement,
Plain and Deformed, for Concrete.
4. C33/C33M-16 - Concrete Aggregates.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
32 05 23 - 2
5. C94/C94M-16 - Ready Mixed Concrete.
6. C143/C143M-15a - Slump of Hydraulic Cement Concrete .
7. C150/C150M-16 - Portland Cement.
8. C171-16 - Sheet Materials for Curing Concrete.
9. C260/C260M-10a - Air Entraining Admixtures for Conc rete.
10. C309-11 - Liquid Membrane Forming Compounds for Cur ing Concrete.
11. C494/C494M-15a - Chemical Admixtures for Concrete.
12. C618-15 - Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use
in Concrete.
13. C979/C979M-16 - Pigments for Integrally Colored Con crete.
14. C989/C989M-14 - Slag Cement for Use in Concrete and Mortars.
15. C1240-15 - Silica Fume Used in Cementitious Mixture s.
16. D1751-04(2013)e1 - Preformed Expansion Joint Filler for Concrete
Paving and Structural Construction (Nonextruding an d Resilient
Bituminous Types).
17. D5893/D5893M-10 - Cold Applied, Single Component, C hemically Curing
Silicone Joint Sealant for Portland Cement Concrete Pavements.
18. D6690-15 - Joint and Crack Sealants, Hot Applied, f or Concrete and
Asphalt Pavements.
1.4 PREINSTALLATION MEETINGS
A. Conduct preinstallation meeting at project site min imum 30 days before
beginning Work of this section.
1. Required Participants:
a. Contracting Officer's Representative.
b. Contractor.
c. Installer.
2. Meeting Agenda: Distribute agenda to participants m inimum 3 days
before meeting.
a. Installation schedule.
b. Installation sequence.
c. Preparatory work.
d. Protection before, during, and after installation.
e. Installation.
f. Terminations.
g. Transitions and connections to other work.
h. Inspecting and testing.
i. Other items affecting successful completion.
32 05 23 - 3
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
3. Document and distribute meeting minutes to particip ants to record
decisions affecting installation.
1.5 SUBMITTALS
A. Submittal Procedures: Section 01 33 23, SHOP DRAWIN GS, PRODUCT DATA,
AND SAMPLES.
B. Submittal Drawings:
1. Show size, configuration, and fabrication and insta llation details.
2. Show reinforcing.
3. Include jointing plan for concrete pavements, curbs and gutters.
C. Manufacturer's Literature and Data:
1. Description of each product.
2. Installation instructions.
D. Test reports: Certify products comply with specific ations.
1. Concrete materials.
2. Field test reports.
E. Certificates: Certify products comply with specific ations.
1. Expansion joint filler.
2. Reinforcement.
3. Curing materials.
4. Concrete protective coating.
F. Qualifications: Substantiate qualifications comply with specifications.
1. Installer with project experience list.
G. Concrete mix design.
H. Proposed hot and cold weather concreting methods. 1.6 QUALITY ASSURANCE
A. Installer Qualifications:
1. Regularly installs specified products.
2. Installed specified products with satisfactory serv ice on five
similar installations.
a. Project Experience List: Provide contact names and addresses for
completed projects.
3. Concrete mix design. 1.7 DELIVERY
A. Deliver steel reinforcement to prevent damage.
B. Before installation, return or dispose of distorted or damaged steel
reinforcement.
32 05 23 - 4
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
C. Bulk Products: Deliver bulk products away from buil dings, utilities,
pavement, and existing turf and planted areas. Main tain dry bulk
product storage away from contaminants.
1.8 STORAGE AND HANDLING
A. Store products indoors in dry, weathertight facilit y.
B. Protect products from damage during handling and co nstruction
operations.
1.9 FIELD CONDITIONS
A. Hot Weather Concreting Procedures: ACI 305R.
B. Cold Weather Concreting Procedures: ACI 306R.
1. Use non-corrosive, non-chloride accelerator admixtu re.
2. Do not use calcium chloride, thiocyanates or admixt ures containing
more than 0.05 percent chloride ions.
1.10 WARRANTY
A. Construction Warranty: FAR clause 52.246-21, "Wa rranty of
Construction."
PART 2 - PRODUCTS
2.1 CONCRETE MATERIALS
A. See section 03 30 00
B. Expansion Joint Filler: ASTM D1751.
C.
2.2 FORMS
A. Forms: Wood, plywood, metal, or other materials, ap proved by
Contracting Officer's Representative, of grade or t ype suitable to
obtain type of finish specified.
1. Plywood: Exterior grade, free of defects and patche s on contact
surface.
2. Lumber: Sound, grade-marked, S4S stress graded soft wood, minimum
50 mm (2 inches) thick, free from warp, twist, loos e knots, splits,
or other defects.
3. Form Coating: As recommended by Architect/Engineer.
B. Provide forms suitable in cross-section, depth, and strength to resist
springing during depositing and consolidating concr ete.
1. Do not use forms varying from straight line more th an 3 mm in
3000 mm (1/8 inch in 10 feet), horizontally and ver tically.
32 05 23 - 5
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
C. Provide flexible or curved forms for forming radii. 2.3 CONCRETE CURING MATERIALS
A. Concrete curing materials, conform to one of the fo llowing:
1. Burlap: Minimum 233 g/sq. m (7 ounces/sq. yd.) dry.
2. Sheet Materials for Curing Concrete: ASTM C171.
3. Curing Compound: ASTM C309, Type 1 clear liquid mem brane forming
type, without paraffin or petroleum.
32 05 23 - 6
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
2.4 CONCRETE MIXES
A. Design concrete mixes according to ASTM C94/C94M, O ption C.
B. Concrete Type: Air-entrained. See Table I.
TABLE I - CONCRETE TYPES
Concrete
Type
Minimum 28 Day
Compressive
Strength f'c
MPa (psi)
Non-Air-Entrained Air-Entrained
Min. Cement
kg/cu. m
(lbs./cu. yd.)
Max.
Water
Cement
Ratio
Min. Cement
kg/cu. m
(lbs./cu. yd.)
Max.
Water
Cement
Ratio
A 35 (5000)1,3 375 (630) 0.45 385 (650) 0.40
B 30 (4000)1,3 325 (550) 0.55 340 (570) 0.50
C 25 (3000)1,3 280 (470) 0.65 290 (490) 0.55
D 25 (3000)1,2 300 (500) * 310 (520) *
Footnotes:
1. If trial mixes are used, achieve compressive streng th 8.3 MPa (1,200 psi)
in excess of f'c. For concrete strengths greater th an 35 MPa (5,000 psi),
achieve compressive strength 9.7 MPa (1,400 psi) in excess of f’c.
2. For Concrete Exposed to High Sulfate Content Soils: Maximum water cement
ratio is 0.44.
3. Laboratory Determined according to ACI 211.1 for no rmal weight concrete.
C. Maximum Slump: ASTM C143/C143M. See Table II.
TABLE II - MAXIMUM SLUMP
APPLICATION MAXIMUM SLUMP
Curb & Gutter 75 mm (3 inches)
Pedestrian Pavement 75 mm (3 inches)
Vehicular Pavement 50 mm (2 inches) Machine Finishe d
100 mm (4 inches) Hand Finished
Equipment Pad 75 to 100 mm (3 to 4 inches)
D. Provide fibers, per 03 03 00, Article 2.2 (CC)
32 05 23 - 7
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
2.5 ACCESSORIES
A. Equipment and Tools: Obtain Contracting Officer's R epresentative's,
approval of equipment and tools needed for handling materials and
performing work before work begins.
B. Maintain equipment and tools in satisfactory workin g condition.
C. Sealants:
1. Concrete Paving Expansion Joints: ASTM D5893/D5893M , Type SL, single
component, self-leveling, silicone joint sealant.
2. Concrete Paving Joints: ASTM D6690, Type IV, hot-ap plied, single
component joint sealant.
D. Concrete Protective Coating: AASHTO M233 linseed oi l mixture.
PART 3 - EXECUTION
3.1 PREPARATION
A. Examine and verify substrate suitability for produc t installation.
B. Protect existing construction and completed work fr om damage.
C. Prepare, construct, and finish subgrade. See Sectio n 31 20 00,
EARTHWORK.
D. Maintain subgrade in smooth, compacted condition, i n conformance with
the required section and established grade until th e succeeding
operation has been accomplished.
3.2 SETTING FORMS
A. Form Substrate:
1. Compact form substrate to uniformly support forms a long entire
length.
2. Correct substrate imperfections and variations by c utting, filling,
and compacting.
B. Form Setting:
1. Set forms to indicated line and grade with tight jo ints. Rigidly
brace forms preventing movement.
2. Remove forms when removal will not damage concrete and when required
for finishing.
3. Clean and oil forms before each use.
4. Correct forms, when required, immediately before pl acing concrete.
C. Form Tolerances:
1. Variation from Indicated Line: Maximum 6 mm (1/4 in ch).
32 05 23 - 8
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
2. Variation from Indicated Grade: Maximum 3 mm in 300 0 mm (1/8 inch in
10 feet). 3.3 JOINTS - GENERAL
A. Place joints, where shown on approved submittal Dra wings.
1. Conform to details shown.
2. Install joints perpendicular to finished concrete s urface.
B. Make joints straight and continuous from edge to ed ge of pavement. 3.4 CONTRACTION JOINTS
A. Tool or cut joints to width, depth, and radius edge shown on drawings
using grooving tool, jointer, or saw.
B. Construct joints in curbs and gutters by inserting 3 mm (1/8 inch)
steel plates conforming to curb and gutter cross se ctions.
1. Keep plates in place until concrete can hold its sh ape.
C. Finish joint edges with edging tool.
D. Score pedestrian pavement with grooving tool or joi nter. 3.5 EXPANSION JOINTS
A. Form expansion joints with expansion joint filler o f thickness shown on
drawings.
1. Locate joints around perimeter of structures and fe atures abutting
site work concrete.
2. Create complete, uniform separation between structu re and site work
concrete.
B. Extend expansion joint material full depth of concr ete with top edge of
joint filler below finished concrete surface where sealant is indicated
on Drawings.
C. Cut and shape material matching cross section.
D. Anchor with approved devices to prevent displacing during placing and
finishing operations.
E. Round joint edges with edging tool. 3.6 PLACING CONCRETE - GENERAL
A. Preparation before Placing Concrete:
1. Obtain Contracting Officer's Representative approva l.
2. Remove debris and other foreign material.
3. Uniformly moisten substrate, without standing water .
B. Convey concrete from mixer to final location withou t segregation or
loss of ingredients. Deposit concrete to minimize h andling.
32 05 23 - 9
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
C. During placement, consolidate concrete by spading o r vibrating to
minimize voids, honeycomb, and rock pockets.
1. Vibrate concrete against forms and along joints.
2. Avoid excess vibration and handling causing segrega tion.
D. Place concrete continuously between joints without bulkheads.
E. Install construction joint in concrete placement su spended for more
than 30 minutes.
F. Replace concrete with cracks, chips, bird baths, an d other defects to
nearest joints, approved by Contracting Officer's R epresentative.
3.7 PLACING CONCRETE FOR CURB AND GUTTER AND PEDESTRIAN PAVEMENT
A. Place concrete in one layer conforming to cross sec tion shown on
Drawings after consolidating and finishing.
B. Deposit concrete near joints without disturbing joi nts. Do not place
concrete directly onto joint assemblies.
C. Strike concrete surface to proper section ready for consolidation.
D. Consolidate concrete by tamping and spading or with approved mechanical
finishing equipment.
E. Finish concrete surface with wood or metal float.
F. Construct concrete pads and pavements with sufficie nt slope to drain,
preventing standing water.
3.8 FORM REMOVAL
A. Keep forms in place minimum 12 hours after concrete placement. Remove
forms without damaging concrete.
B. Do not use bars or heavy tools against concrete to remove forms. Repair
damage concrete found after form removal. 3.9 CONCRETE FINISHING - GENERAL
A. Follow operation sequence below, unless otherwise i ndicated on
Drawings:
1. Consolidating, floating, striking, troweling, textu ring, and joint
edging.
B. Use edging tool with 6 mm (1/4 inch) radius.
C. Keep finishing equipment and tools clean and suitab le for use. 3.10 CONCRETE FINISHING - PEDESTRIAN PAVEMENT
A. Walks:
1. Finish concrete surfaces with metal float, troweled smooth, and
finished with a broom moistened with clear water.
32 05 23 - 10
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
2. Finish slab edges and formed transverse joints with edger.
3. Broom surfaces transverse to traffic direction.
a. Use brooming to eliminate flat surface produced by edger.
b. Produce uniform corrugations, maximum 1.5 mm (1/16 inch) deep
profile.
4. Provide surface uniform in color and free of surfac e blemishes, form
marks, and tool marks.
5. Paving Tolerances:
a. Variation from Indicated Plane: Maximum 5 mm in 300 0 mm (3/16
inch in 10 feet).
b. Variation from Indicated Thickness: Maximum 6 mm (1 /4 inch).
6. Replace paving within joint boundary when paving ex ceeds specified
tolerances.
3.11 CONCRETE FINISHING - CURBS AND GUTTERS
A. Round edges of gutter and top of curb with edging t ool.
B. Gutter and Curb Top:
1. Float surfaces and finish with smooth wood or metal float until true
to grade and section and uniform color.
2. Finish surfaces, while still plastic, longitudinall y with bristle
brush.
C. Curb Face:
1. Remove curb form and immediately rub curb face with wood or concrete
rubbing block removing blemishes, form marks, and t ool marks and
providing uniform color.
2. Brush curb face, while still plastic, matching gutt er and curb top.
D. Curb and Gutter Tolerances:
1. Variation from Indicated Plane and Grade:
a. Gutter: Maximum 3 mm in 3000 mm (1/8 inch in 10 fee t).
b. Curb Top and Face: Maximum 6 mm in 3000 mm (1/4 inc h in
10 feet).
E. Replace curbs and gutters within joint boundary whe n curbs and gutters
exceed specified tolerances.
F. Correct depressions causing standing water. 3.12 CONCRETE CURING
A. Concrete Protection:
1. Protect unhardened concrete from rain and flowing w ater.
32 05 23 - 11
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
2. Provide sufficient curing and protection materials available and
ready for use before concrete placement begins.
3. Protect concrete to prevent pavement cracking from ambient
temperature changes during curing period.
a. Replace pavement damaged by curing method allowing concrete
cracking.
b. Employ another curing method as directed by Contrac ting
Officer's Representative.
B. Cure concrete for minimum 7 days by one of the foll owing methods
appropriate to weather conditions preventing moistu re loss and rapid
temperature change:
1. Burlap Mat: Provide minimum two layers kept saturat ed with water
during curing period. Overlap Mats at least 150 mm (6 inches).
2. Sheet Materials:
a. Wet exposed concrete surface with fine water spray and cover
with sheet materials.
b. Overlap sheets minimum 300 mm (12 inches).
c. Securely anchor sheet materials preventing displace ment.
3. Curing Compound:
a. Protect joints indicated to receive sealants preven ting
contamination from curing compound.
b. Insert moistened paper or fiber rope into joint or cover joint
with waterproof paper.
c. Apply curing compound before concrete dries.
d. Apply curing compound in two coats at right angles to each
other.
e. Application Rate: Maximum 5 sq. m/L (200 sq. ft./ga llon), both
coats.
f. Immediately reapply curing compound to surfaces dam aged during
curing period.
3.13 CONCRETE PROTECTIVE COATING
A. Apply protective coating of linseed oil mixture to exposed-to-view
concrete surfaces, drainage structures, and feature s that project
through, into, or against concrete exterior improve ments to protect the
concrete against deicing materials.
B. Complete backfilling and curing operation before ap plying protective
coating.
32 05 23 - 12
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
C. Dry and thoroughly clean concrete before each appli cation.
D. Apply two coats, with maximum coverage of 11 sq. m/ L (50 sq.
yds./gal.); first coat, and maximum 16 sq. m/L (70 sq. yds./gal.);
second coat, except apply commercially prepared mix ture according to
manufacturer's instructions.
E. Protect coated surfaces from vehicular and pedestri an traffic until
dry.
F. Do not heat protective coating, and do not expose p rotective coating to
open flame, sparks, or fire adjacent to open contai ners or applicators.
Do not apply material at temperatures lower than 10 degrees C
(50 degrees F).
3.14 FIELD QUALITY CONTROL
A. Field Tests: Performed by testing laboratory spe cified in Section
01 45 29, TESTING LABORATORY SERVICES.
1. Compaction.
a. Pavement subgrade.
b. Curb, gutter, and sidewalk.
2. Concrete:
a. Delivery samples.
b. Field samples.
3. Slip Resistance: Steps and pedestrian paving. 3.15 CLEANING
A. After completing curing:
1. Remove burlap and sheet curing materials.
2. Sweep concrete clean, removing foreign matter from the joints.
3. Seal joints as specified. 3.16 PROTECTION
A. Protect exterior improvements from traffic and cons truction operations.
1. Prohibit traffic on paving for minimum seven days a fter placement,
or longer as directed by Contracting Officer's Repr esentative.
B. Remove protective materials immediately before acce ptance.
C. Repair damage.
1. Replace concrete containing excessive cracking, fra ctures, spalling,
and other defects within joint boundary, when direc ted by
Contracting Officer's Representative, and at no add itional cost to
the Government.
32 05 23 - 13
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
- - - E N D - - -
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
32 12 16 - 1
SECTION 32 12 16 ASPHALT PAVING
PART 1 - GENERAL
1.1 DESCRIPTION
This work shall cover the composition, mixing, cons truction upon the
prepared subgrade, and the protection of hot asphal t concrete pavement.
The hot asphalt concrete pavement shall consist of an aggregate or
asphalt base course and asphalt surface course cons tructed in
conformity with the lines, grades, thickness, and c ross sections as
shown. Each course shall be constructed to the dept h, section, or
elevation required by the drawings and shall be rol led, finished, and
approved before the placement of the next course.
1.2 RELATED WORK
A. Laboratory and field testing requirements: Section 01 45 29, TESTING
LABORATORY SERVICES.
B. Subgrade Preparation: Paragraph 3.3 and Section 31 20 00, EARTH MOVING.
C. Pavement Markings: Section 32 17 23, PAVEMENT MARKI NGS.
1.3 INSPECTION OF PLANT AND EQUIPMENT
The COR shall have access at all times to all parts of the material
producing plants for checking the mixing operations and materials and
the adequacy of the equipment in use.
1.4 ALIGNMENT AND GRADE CONTROL
The Contractor’s Registered Professional Land Surve yor shall establish
and control the pavement (aggregate or asphalt base course and asphalt
surface course) alignments, grades, elevations, and cross sections as
shown on the Drawings.
1.5 SUBMITTALS
A. In accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND
SAMPLES, furnish the following:
B. Data and Test Reports:
1. Aggregate Base Course: Sources, gradation, liquid l imit, plasticity
index, percentage of wear, and other tests required by State Highway
Department.
2. Asphalt Base/Surface Course: Aggregate source, grad ation, soundness
loss, percentage of wear, and other tests required by State Highway
Department.
3. Job-mix formula.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
32 12 16 - 2
C. Certifications:
1. Asphalt prime and tack coat material certificate of conformance to
State Highway Department requirements.
2. Asphalt cement certificate of conformance to State Highway
Department requirements.
3. Job-mix certification - Submit plant mix certificat ion that mix
equals or exceeds the State Highway Specification.
D. Provide MSDS (Material Safety Data Sheets) for all chemicals used on
ground.
PART 2 - PRODUCTS
2.1 GENERAL
A. Aggregate base and asphalt concrete materials shall conform to the
requirements of the following and other appropriate sections of the
latest version of the State Highway Material Specif ications, including
amendments, addenda and errata. Where the term "Eng ineer" or
"Commission" is referenced in the State Highway Spe cifications, it
shall mean the VA COR or VA Contracting Officer.
2.2 AGGREGATES
A. Provide aggregates consisting of crushed stone, gra vel, sand, or other
sound, durable mineral materials processed and blen ded, and naturally
combined.
B. Subbase aggregate (where required) maximum size: 38 mm(1-1/2").
C. Base aggregate maximum size:
1. Base course over 152mm(6") thick: 38mm(1-1/2");
2. Other base courses: 19mm(3/4").
D. Asphaltic base course:
1. Maximum particle size not to exceed 25.4mm(1”).
2. Where conflicts arise between this specification an d the
requirements in the latest version of the State Hig hway
Specifications, the State Specifications shall cont rol.
E. Aggregates for asphaltic concrete paving: Provide a mixture of sand,
mineral aggregate, and liquid asphalt mixed in such proportions that
the percentage by weight will be within comply with Wisconsin DOT
specifications.
2.3 ASPHALTS
A. Comply with provisions of Asphalt Institute Specifi cation SS2:
1. Asphalt cement: Penetration grade 50/60
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
32 12 16 - 3
2. Prime coat: Cut-back type, grade MC-250
3. Tack coat: Uniformly emulsified, grade SS-1H
2.4 SEALER
A. Provide a sealer consisting of suitable fibrated ch emical type asphalt
base binders and fillers having a container consist ency suitable for
troweling after thorough stirring, and containing n o clay or other
deleterious substance.
B. Where conflicts arise between this specification an d the requirements
in the latest version of the State Highway Specific ations, the State
Specifications shall control.
PART 3 - EXECUTION
3.1 GENERAL
The Asphalt Concrete Paving equipment, weather limi tations, job-mix
formula, mixing, construction methods, compaction, finishing,
tolerance, and protection shall conform to the requ irements of the
appropriate sections of the State Highway Specifica tions for the type
of material specified.
3.2 MIXING ASPHALTIC CONCRETE MATERIALS
A. Provide hot plant-mixed asphaltic concrete paving m aterials.
1. Temperature leaving the plant: 143 degrees C (290 d egrees F)
minimum, 160 degrees C (320 degrees F) maximum.
2. Temperature at time of placing: 138 degrees C (280 degrees F)
minimum.
3.3 SUBGRADE
A. Shape to line and grade and compact with self-prope lled rollers.
B. All depressions that develop under rolling shall be filled with
acceptable material and the area re-rolled.
C. Soft areas shall be removed and filled with accepta ble materials and
the area re-rolled.
D. Should the subgrade become rutted or displaced prio r to the placing of
the subbase, it shall be reworked to bring to line and grade.
E. Proof-roll the subgrade with maximum 45 tonne (50 t on) gross weight
dump truck as directed by VA COR or VA Contracting Officer. If
pumping, pushing, or other movement is observed, re work the area to
provide a stable and compacted subgrade.
3.4 BASE COURSES
A. Subbase (when required)
32 12 16 - 4
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
1. Spread and compact to the thickness shown on the dr awings.
2. Rolling shall begin at the sides and continue towar d the center and
shall continue until there is no movement ahead of the roller.
3. After completion of the subbase rolling there shall be no hauling
over the subbase other than the delivery of materia l for the top
course.
B. Base
1. Spread and compact to the thickness shown on the dr awings.
2. Rolling shall begin at the sides and continue towar d the center and
shall continue until there is no movement ahead of the roller.
3. After completion of the base rolling there shall be no hauling over
the base other than the delivery of material for th e top course.
C. Thickness tolerance: Provide the compacted thicknes ses shown on the
Drawings within a tolerance of minus 0.0mm (0.0") t o plus 12.7mm
(0.5").
D. Smoothness tolerance: Provide the lines and grades shown on the
Drawings within a tolerance of 5mm in 3m (3/16 inch in ten feet).
E. Moisture content: Use only the amount of moisture n eeded to achieve the
specified compaction.
3.5 PLACEMENT OF ASPHALTIC CONCRETE PAVING
A. Remove all loose materials from the compacted base.
B. Apply the specified prime coat, and tack coat where required, and allow
to dry in accordance with the manufacturer’s recomm endations as
approved by the Architect or Engineer.
C. Receipt of asphaltic concrete materials:
1. Do not accept material unless it is covered with a tarpaulin until
unloaded, and unless the material has a temperature of not less than
130 degrees C(280 degrees F).
2. Do not commence placement of asphaltic concrete mat erials when the
atmospheric temperature is below 10 degrees C (50 d egrees F), not
during fog, rain, or other unsuitable conditions.
D. Spreading:
1. Spread material in a manner that requires the least handling.
2. Where thickness of finished paving will be 76mm (3" ) or less, spread
in one layer.
E. Rolling:
32 12 16 - 5
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
1. After the material has been spread to the proper de pth, roll until
the surface is hard, smooth, unyielding, and true t o the thickness
and elevations shown own the drawings.
2. Roll in at least two directions until no roller mar ks are visible.
3. Finished paving smoothness tolerance:
a. No depressions which will retain standing water.
b. No deviation greater than 3mm in 1.8m (1/8" in six feet).
3.6 APPLICATION OF SEAL COAT
A. Prepare the surfaces, mix the seal coat material, a nd apply in
accordance with the manufacturer’s recommendations as approved by the
Architect or Engineer.
B. Achieve a finished surface seal which, when dry and thoroughly set, is
smooth, tough, resilient, of uniform black color, a nd free from coarse
textured areas, lap marks, ridges, and other surfac e irregularities.
C. When sealing new asphalt paving wait an entire year to allow for the
expansion and contraction of a year’s cycle of both warm and cool
temperatures. This allows for the asphalt’s oils to properly cure and
begin oxidation before applying a seal coat.
D. When seal coating in less than a year apply two coa ts, spray applied.
This application method is preferred for less than a year application
when there is still plenty of asphalt cement presen t for the seal coat
to bond to.
E. When seal coating existing paving that has new asph alt patches, apply
two coats sprayed to the existing asphalt and a sin gle lighter coat on
new patch work, just enough to make the color of th e new patches match
the rest of the reseal coated paving.
F. When resealing existing paving 5, 10, 15 years and older, that is
oxidized and is very light in color, squeegee apply the first coat of
seal coat and spray on a second coat. Two coats are preferred in older
paving when the asphalt cement has oxidized leaving the seal coat with
nothing to bond to other than the aggregate that in many cases has
polished over time leaving less than a desirable su rface to bond to.
3.7 PROTECTION
Protect the asphaltic concrete paved areas from tra ffic until the
sealer is set and cured and does not pick up under foot or wheeled
traffic.
32 12 16 - 6
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
3.8 FINAL CLEAN-UP
Remove all debris, rubbish, and excess material fro m the work area.
- - - E N D - - -
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
32 17 23 - 1
SECTION 32 17 23 PAVEMENT MARKINGS
PART 1 - GENERAL 1.1 SUMMARY
A. Section Includes:
1. Paint on pavement surfaces, in form of traffic lane s, parking bays,
areas restricted to handicapped persons, crosswalks , and other
detail pavement markings.
1.2 APPLICABLE PUBLICATIONS
A. Comply with references to extent specified in this section.
B. Federal Specifications (Fed. Spec.):
1. TT-B-1325D - Beads (Glass Spheres) Retro-Reflective .
2. TT-P-1952F - Paint, Traffic and Airfield Marking, W aterborne.
C. Master Painters Institute (MPI):
1. No. 97 - Traffic Marking Paint, Latex. 1.3 SUBMITTALS
A. Submittal Procedures: Section 01 33 23, SHOP DRAWIN GS, PRODUCT DATA,
AND SAMPLES.
B. Submittal Drawings:
1. Show pavement marking configuration and dimensions.
2. Show international symbol of accessibility at desig nated parking
spaces.
C. Manufacturer's Literature and Data:
1. Description of each product.
2. Application instructions.
D. Samples:
1. Paint: 200 mm (8 inches) square, each type and colo r.
E. Certificates: Certify products comply with specific ations.
F. Qualifications: Substantiate qualifications comply with specifications.
1. Installer with project experience list. 1.4 QUALITY ASSURANCE
A. Installer Qualifications:
1. Regularly installs specified products.
2. Installed specified products with satisfactory serv ice on five
similar installations for minimum five years.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
32 17 23 - 2
a. Project Experience List: Provide contact names and addresses for
completed projects.
1.5 DELIVERY
A. Deliver products in manufacturer's original sealed packaging.
B. Mark packaging, legibly. Indicate manufacturer's na me or brand, type,
color, production run number, and manufacture date.
C. Before installation, return or dispose of products within distorted,
damaged, or opened packaging. 1.6 STORAGE AND HANDLING
A. Store products indoors in dry, weathertight conditi oned facility.
B. Protect products from damage during handling and co nstruction
operations.
1.7 FIELD CONDITIONS
A. Environment:
1. Product Temperature: Minimum 13 degrees C (55 degre es F) for minimum
48 hours before installation.
a. Surface to be painted and ambient temperature: M inimum
10 degrees C (50 degrees F) and maximum 35 degrees C
(95 degrees F).
B. Field Measurements: Verify field conditions affecti ng traffic marking
installation. Show field measurements on Submittal Drawings.
1.8 WARRANTY
A. Construction Warranty: FAR clause 52.246-21, "Warra nty of
Construction."
PART 2 - PRODUCTS
2.1 SYSTEM PERFORMANCE
A. Design paint complying with specified performance:
1. Application: Fed. Spec. TT-P-1952. 2.2 PRODUCTS - GENERAL
A. Basis of Design: Section 09 06 00, SCHEDULE FOR FIN ISHES.
B. Provide each product from one manufacturer and from one production run. 2.3 SANDBLASTING EQUIPMENT
A. Air compressor, hoses, and nozzles of proper size a nd capacity as
required for cleaning painted surfaces. Compressor to provide minimum
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
32 17 23 - 3
0.08 cu. m/s (150 cfm) of air at pressure of minimu m 625 kPa (90 psi)
at each nozzle used.
2.4 PAINT APPLICATOR
A. Apply marking paint with approved mechanical equipm ent. Provide
equipment with constant agitation of paint and trav el at controlled
speeds. Synchronize one or more paint "guns" to aut omatically begin and
cut off paint flow in case of skip lines. Equipment to have manual
control to apply continuous lines of varying length and marking widths
as indicated on Drawings. Provide pneumatic spray g uns for hand
application of paint in areas where mobile paint ap plicator cannot be
used.
2.5 PAINT
A. Paint: MPI No. 97. For obliterating existing markin gs comply with
Fed. Spec. TT-P-1952. Provide minimum 18 L (5 gallo ns) containers.
2.6 REFLECTIVE GLASS BEADS
A. Beads: Comply with Fed. Spec. TT-B-1325, Type I, Gr adation A. In
regions of high humidity, coat beads with silicone or other suitable
waterproofing material to ensure free flow. Provide glass beads in
containers suitable for handling and strong enough to prevent loss
during shipment.
PART 3 - EXECUTION
3.1 PREPARATION
A. Examine and verify substrate suitability for produc t installation.
1. Allow new pavement surfaces to cure for period of m inimum 14 days
before application of marking materials.
B. Protect existing construction and completed work fr om damage.
C. Clean substrates. Remove contaminants capable of af fecting subsequently
installed product's performance.
1. Remove dust, dirt, and other granular surface depos its by sweeping,
blowing with compressed air, rinsing with water, or combination of
these methods.
2. Completely remove rubber deposits, existing paint m arkings, and
other coatings adhering to pavement with scrapers, wire brushings,
sandblasting, mechanical abrasion, or approved chem icals as directed
by Contracting Officer's Representative.
32 17 23 - 4
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
3. As an option, comply with Fed. Spec. TT-P-1952 for removal of
existing paint markings on asphalt pavement. Apply black paint in as
many coats as necessary to completely obliterate ex isting markings.
4. Scrub affected areas with several applications of t risodium
phosphate solution or other approved detergent or d egreaser, and
rinse thoroughly after each application, Where oil or grease are
present on old pavements to be marked.
a. After cleaning, seal oil-soaked areas with cut shel lac to
prevent bleeding through new paint.
5. Clean and dry surface before pavement marking. Do n ot begin any
marking until Contracting Officer's Representative inspected surface
and gives permission to proceed.
3.2 TEMPORARY PAVEMENT MARKING
A. Apply Temporary Pavement Markings of colors, widths and lengths shown
on drawings or directed by Contracting Officer's Re presentative. After
temporary marking has served its purpose and when s o ordered by
Contracting Officer's Representative, remove tempor ary marking by
carefully controlled sandblasting, approved grindin g equipment, or
other approved method to prevent damage on applied surface.
B. As an option, provide approved preformed pressure s ensitive, adhesive
tape type of temporary pavement marking of required colors, widths and
lengths in lieu of temporary painted marking. Conti nuous durability and
effectiveness of such marking is required during pe riod for which its
use is required. Remove any unsatisfactory tape typ e marking and
replace with painted markings.
3.3 INSTALLATION - GENERAL
A. Install products according to manufacturer's instru ctions and approved
submittal drawings.
1. When manufacturer's instructions deviate from speci fications, submit
proposed resolution for Contracting Officer's Repre sentative
consideration.
3.4 PAINT APPLICATION
A. Apply uniformly painted and reflective pavement mar king of required
colors, length, and width with true, sharp edges an d ends on properly
cured, prepared, and dried surfaces.
32 17 23 - 5
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
B. Comply with details as indicated on drawings and es tablished control
points.
C. Apply paint at wet film thickness of 0.4 mm (0.015 inch). Disperse
reflective glass beads evenly on wet paint at rate of 720 g/L (6 pounds
per gal.) of paint. Apply paint in one coat. When d irected by
Contracting Officer's Representative, apply additio nal coats at
markings showing light spots. Comply with paint man ufacturer's maximum
drying time requirements to prevent undue softening of asphalt, and
pick-up, displacement, or discoloration by tires of traffic.
D. When deficiency in marking drying occurs, discontin ue paint operations
until cause of slow drying is determined and correc ted.
E. Remove and replace marking applied less than minimu m material rates,
deviates from true alignment, exceeds stipulated le ngth and width
tolerances, or shows light spots, faulty distributi on of beads, smears,
or other deficiencies or irregularities.
F. Remove marking by carefully controlled sandblasting , approved grinding
equipment, or other approve method to prevent damag e on applied
surface.
3.5 DETAIL PAVEMENT MARKING APPLICATION
A. Apply Detail Pavement Markings, exclusive of actual traffic lane
marking as follows:
1. At exit and entrance islands and turnouts.
2. On curbs.
3. At crosswalks.
4. At parking bays.
5. Other locations as indicated on drawings.
B. Apply International Handicapped Symbol at indicated parking spaces.
Color as shown on drawings. Apply paint for symbol using suitable
template that will provide pavement marking with tr ue, sharp edges and
ends.
C. Install detail pavement markings of colors, widths and lengths, and
design pattern at locations indicated on drawings.
3.6 TOLERANCES
A. Length and Width of Lines: Plus or minus 75 mm (3 i nches) and plus or
minus 3 mm (1/8 inch), respectively, in case of ski p markings.
B. Length of intervals exceeding line length tolerance are not acceptable.
32 17 23 - 6
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
3.7 CLEANING
A. Remove excess paint before paint sets. 3.8 PROTECTION
A. Protect pavement markings from traffic and construc tion operations.
1. Protect newly painted markings from vehicular traff ic until paint is
dry and track free.
2. Place warning signs at beginning of wet line, and a t points well in
advance of marking equipment for alerting approachi ng traffic from
both directions.
3. Place small flags or other similarly effective smal l objects near
freshly applied markings at frequent intervals to r educe crossing by
traffic.
B. Repair damage.
- - - E N D - - -
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
32 90 00 - 1
SECTION 32 90 00 PLANTING
PART 1 - GENERAL 1.1 SUMMARY
A. Section Includes:
1. Sod. 1.2 RELATED REQUIREMENTS
1.3 DEFINITIONS
A. Pesticide: Any substance or mixture of substances, including biological
control agents, that may prevent, destroy, repel, o r mitigate pests and
is specifically labeled for use by U.S. Environment al Protection Agency
(EPA). Also, any substance used as plant regulator, defoliant,
disinfectant, or biocide.
B. Stand of Turf: 80 percent of established species. 1.4 APPLICABLE PUBLICATIONS
A. Comply with references to extent specified in this section.
B. American National Standards Institute (ANSI):
1. Z60.1-2014 - Nursery Stock.
C. American Society for Testing And Materials (ASTM):
1. B221-14 - Aluminum and Aluminum-Alloy Extruded Bars , Rods, Wire,
Profiles, and Tubes.
2. B221M-13 - Aluminum and Aluminum-Alloy Extruded Bar s, Rods, Wire,
Profiles, and Tubes.
3. C33/C33M-16-Concrete Aggregates.
4. C136/C136M-14 - Sieve Analysis of Fine and Coarse A ggregates.
5. C602-13a - Agricultural Liming Materials.
6. D977-13e1 - Emulsified Asphalt.
7. D5268-13 - Topsoil Used for Landscaping Purposes.
D. Hortus Third: Concise Dictionary of Plants Cultivat ed in United States
and Canada.
E. Tree Care Industry Association (TCIA):
1. A300P1-2008 - Tree Care Operations - Trees, Shrubs and Other Woody
Plant Maintenance Standard Practices (Pruning).
2. Z133.1-2012 - Arboricultural Operations - Safety Re quirements.
F. Turfgrass Producers International (TPI):
1. 2006 Guideline Specifications to Turfgrass Sodding.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
32 90 00 - 2
G. United States Department of Agriculture (USDA):
1. DOA SSIR 42-2014 - Soil Survey Laboratory Methods M anual.
2. Handbook No. 60 - Diagnosis and Improvement of Sali ne and Alkali
Soils.
1.5 PREINSTALLATION MEETINGS
A. Conduct preinstallation meeting at project site min imum 30 days before
beginning Work of this section.
1. Required Participants:
a. Contracting Officer's Representative.
b. Contractor.
c. Installer.
2. Meeting Agenda: Distribute agenda to participants m inimum 3 days
before meeting.
a. Inspection of planting materials.
b. Installation schedule.
c. Installation sequence.
d. Preparatory work.
e. Protection before, during, and after installation.
f. Installation.
g. Inspecting.
h. Environmental procedures.
3. Document and distribute meeting minutes to particip ants to record
decisions affecting installation.
1.6 SUBMITTALS
A. Submittal Procedures: Section 01 33 23, SHOP DRAWIN GS, PRODUCT DATA,
AND SAMPLES.
B. Manufacturer's Literature and Data:
1. Description of each product.
2. Photographs: Color photographs of each plant specie s showing actual
size and condition of plants to be provided with me asuring device
included for scale. Where more than 20 plants are r equired of any
species, submit minimum three photographs of averag e, best, and
worst quality plant to be provided. Include on each photograph,
plant full scientific name, size, and source nurser y.
3. Installation instructions.
4. Warranty.
a. Show type and quantity for each product.
32 90 00 - 3
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
C. Test reports: Certify products comply with specific ations.
D. Certificates: Certify products comply with specific ations.
1. Plant Materials: Department of Agriculture certific ation by State
Nursery Inspector declaring material to be free fro m insects and
disease.
2. Seed and Turf Materials: Notarized certificate of p roduct analysis.
E. Qualifications: Substantiate qualifications comply with specifications.
1. Installer, including supervisor with project experi ence list.
F. Operation and Maintenance Data:
1. Care instructions for each plant material. 1.7 QUALITY ASSURANCE
A. Installer Qualifications:
1. Regularly installs specified products.
2. Installed specified products with satisfactory serv ice on five
similar installations for minimum five years.
a. Project Experience List: Provide contact names and addresses for
completed projects.
3. Member in good standing of either Professional Land care Network or
American Nursery and Landscape Association.
4. Personnel assigned to Work certified in following c ategories from
Professional Landcare Network and submit one copy o f certificate to
Contracting Officer’s Representative:
a. Certified Landscape Technician (CLT) - Exterior, wi th
installation specialty areas, designated CLT-Exteri or.
B. Contracting Officer’s Representative may review pla nt materials either
at place of growth or project site before planting for compliance with
requirements. Contracting Officer’s Representative retains right to
inspect trees and shrubs to determine if any unacce ptable conditions
exist and to reject any trees or shrubs at any time during Project. All
rejected trees and shrubs must be immediately remov ed from Project
site.
1. Submit plant material source information to Contrac ting Officer’s
Representative seven days in advance of delivery to Project site. 1.8 DELIVERY
A. Deliver packaged products in manufacturer's origina l sealed packaging.
B. Bulk Products:
32 90 00 - 4
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
1. Deliver bulk products away from buildings, utilitie s, pavement, and
existing turf and planted areas. Maintain dry bulk product storage
away from contaminants.
2. Install erosion control materials to prevent erosio n or displacement
of bulk products. 1.9 STORAGE AND HANDLING
A. Plant Storage and Protection: Store and protect pla nts not planted on
day of arrival at Project site as follows:
1. Shade and protect plants in outdoor storage areas f rom wind and
direct sunlight until planted.
2. Heel-in bare root plants.
3. Protect balled and burlapped plants from freezing o r drying out by
covering balls or roots with moist burlap, sawdust, wood chips,
shredded bark, peat moss, or other approved materia l. Provide
covering that allows air circulation.
4. Keep plants in moist condition until planted by wat ering with fine
mist spray.
5. Do not store plant materials directly on concrete o r bituminous
surfaces.
B. Topsoil: Before stockpiling topsoil, eradicate on s ite undesirable
growing vegetation. Clear and grub existing vegetat ion three to four
weeks before stockpiling existing topsoil.
C. Root Control Barrier and Weed Control Fabric: Store materials in site
in enclosures or under protective covering in dry l ocation out of
direct sunlight. Do not store materials directly on ground.
D. Handling: Do not drop or dump plants from vehicles. Avoid damaging
plants being moved from nursery or storage area to planting site.
Remove damaged plants from Project site.
1.10 FIELD CONDITIONS
A. Environment:
1. Coordinate installation of planting materials durin g optimal
planting seasons for each type of plant material re quired.
2. Restrictions: Do not plant when ground is frozen, s now
covered, muddy, or when air temperature exceed 32 d egrees C
(90 degrees F).
B. Weather Limitations: Install plantings only during current and
forecasted weather conditions that are comply with plant requirements.
32 90 00 - 5
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
Apply associated products in compliance with manufa cturers'
instructions.
1.11 WARRANTY
A. Construction Warranty: FAR clause 52.246-21, "Warra nty of
Construction."
B. Manufacturer's Warranty: Warrant plantings and agai nst material
defects.
1. Warranty Period: Two years.
2. Plant and Turf Warranty Periods will begin from dat e of Government
acceptance of project or phase for beneficial use a nd occupancy.
3. Contracting Officer's Representative will reinspect plants and turf
at end of Warranty Period. Replace any dead, missin g, or defective
plant material and turf immediately. Warranty Perio d will end on
date of this inspection provided Contractor has com plied with
warranty work required by this specification. Compl y with following
requirements:
a. Replace any plants more than 25 percent dead, missi ng or
defective plant material before final inspection.
b. Only one replacement of each plant will be required except when
losses or replacements are due to failure to comply with these
requirements.
c. Complete remedial measures directed by Contracting Officer’s
Representative to ensure plant and turf survival.
d. Repair damage caused while making plant or turf rep lacements.
PART 2 - PRODUCTS
2.1 PRODUCTS - GENERAL
A. Provide each product from one source or manufacture r. 2.2 SOD
A. Sod: Nursery grown, certified and classified in TPI 's "Guideline
Specifications to Turfgrass Sodding" as GSS. Machin e cut sod at uniform
thickness of 19 mm (3/4 inch) within tolerance of 6 mm (1/4 inch),
excluding top growth and thatch. Each individual so d piece to be strong
enough to support its own weight when lifted by end s. Broken pads,
irregularly shaped pieces, and torn or uneven ends will not be
permitted.
B. Sod Species: Genetically pure, free of weeds, pests , and disease.
32 90 00 - 6
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
2.3 PLANTING SOILS
A. Planting Soil: Evaluate soil for use as topsoil acc ording to
ASTM D5268. From 5 to 10 percent organic matter as determined by
topsoil composition tests of Organic Carbon, 6A, Ch emical Analysis
Method described in USDA DOA SSIR 42. Maximum parti cle size, 19 mm
(3/4 inch), with maximum 3 percent retained on 6 mm (1/4 inch) screen.
Mix topsoil with following soil amendments as recom mended by soils
analysis.
B. Existing Planting Soil: Existing, native surface to psoil formed under
natural conditions retained during excavation proce ss and stockpiled
on-site. Verify suitability of native surface topso il to produce viable
planting soil. Clean soil of roots, plants, sod, st ones, clay lumps,
and other extraneous materials harmful to plant gro wth.
1. Supplement with planting soil when quantities are i nsufficient.
2. Mix existing, native surface topsoil with soil amen dments as
recommended by soils analysis.
C. Imported Planting Soil: Imported topsoil or manufac tured topsoil from
off-site sources are acceptable if sufficient topso il is not available
on site to meet specified depth. At least 10 days b efore topsoil
delivery, notify Contracting Officer’s Representati ve of topsoil
sources. Obtain imported topsoil displaced from nat urally well-drained
construction or mining sites where topsoil is at le ast 100 mm
(4 inches) deep. Topsoil from agricultural land, bo gs, or marshes will
be rejected.
2.4 INORGANIC SOIL AMENDMENTS
A. Lime: Commercial grade hydrated limestone containin g calcium carbonate
equivalent (CCE) specified in ASTM C602 of minimum 80 percent.
B. Sulfur: 100 percent elemental.
C. Iron Sulfate: 100 percent elemental.
D. Aluminum Sulfate: Commercial grade.
E. Perlite: Horticultural grade.
F. Agricultural Gypsum: Coarsely ground from recycled scrap gypsum board
comprised of calcium sulfate dehydrate 91 percent, calcium 22 percent,
sulfur 17 percent, minimum 96 percent passing throu gh 850 micrometers
20 mesh screen, 100 percent passing through 970 mic rometers 16 mesh
screen.
32 90 00 - 7
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
G. Coarse Sand: ASTM C33/C33M, clean and free of mater ials harmful to
plants.
H. Vermiculite: Horticultural grade for planters.
I. Diatomaceous Earth: Calcined, 90 percent silica, wi th approximately 140
percent water absorption capacity by weight.
J. Zeolites: Mineral clinoptilolite with at least 60 p ercent water
absorption by weight.
2.5 ORGANIC SOIL AMENDMENTS
A. Organic Matter: Commercially prepared compost. Free of substances toxic
to plantings and as follows:
1. Organic Matter Content: shredded hardwood, pine str aw mulch from
project site when available. Biobased content 100 p ercent. Wood
cellulose fiber processed to contain no growth or
germination-inhibiting factors, dyed with non-toxic , biodegradable
dye to appropriate color to facilitate visual meter ing of materials
application.
2. Feedstock: Agricultural, food, or industrial residu als; biosolids;
yard trimmings; or source-separated or compostable mixed solid
waste.
B. Peat: Natural product of peat moss derived from fre sh-water site,
conforming to ASTM D4427 and containing no invasive species, including
seeds. Shred and granulate peat to pass 12.5 mm (1/ 2 inch) mesh screen
and condition in storage pile for minimum 6 months after excavation.
Biobased content minimum 100 percent.
C. Composted Derivatives: Ground bark, nitolized sawdu st, humus, or other
green wood waste material free of stones, sticks, i nvasive species,
including seeds, and soil stabilized with nitrogen and having following
properties:
1. Particle Size: Minimum percent by weight passing:
a. 4.75 mm (No. 4) mesh screen: 95.
b. 2.36 mm (No. 8) mesh screen: 80.
2. Nitrogen Content: Minimum percent based on dry weig ht:
a. Fir sawdust: 0.7.
b. Fir or pine bark: 1.0.
3. Biobased Content: 100 percent.
32 90 00 - 8
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
D. Manure: Well-rotted, horse or cattle manure contain ing maximum 25
percent by volume of straw, sawdust, or other beddi ng materials; free
of seeds, stones, sticks, soil, and other invasive species.
2.6 WEED CONTROL FABRIC
A. Roll Type Polypropylene or Polyester Mats: Woven, n eedle punched, or
non-woven fabric treated for protection against det erioration due to
ultraviolet radiation. Minimum 99 percent opaque to prevent
photosynthesis and seed germination, fabric allows air, water, and
nutrients to pass through to plant roots.
1. Minimum weight: 0.11 kg per square meter (5 ounces per square yard).
2. Minimum thickness: 0.50 mm (20 mils). 2.7 WATER
A. Water: Source approved by Contracting Officer's Rep resentative and
suitable quality for irrigation, containing no elem ents toxic to plant
life, including acids, alkalis, salts, chemical pol lutants, and organic
matter. Use collected storm water or graywater when available.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine areas to receive plants for compliance with requirements and
conditions affecting installation and performance.
1. Verify that no materials that would inhibit plant g rowth are present
in planting area. If such materials are present, re move soil and
contaminants ad directed by Contracting Officer's R epresentative and
provide new planting soil.
2. Do not mix or place soils and soil amendments in fr ozen, wet, or
muddy conditions.
3. Suspend soil spreading, grading, and tilling operat ions if soil
moisture becomes excessive. Resume soil preparation s when moisture
content returns to acceptable level.
4. If soil is excessively dry, not workable, and too d usty, moisten
uniformly.
5. Special conditions may exist that warrant variance in specified
planting dates or conditions. Submit written reques t to Contracting
Officer’s Representative stating special conditions and proposed
variance.
32 90 00 - 9
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
B. Proceed with planting operations only after unsatis factory conditions
have been corrected.
3.2 PREPARATION
A. Protect existing and proposed landscape features, e lements, and site
construction and completed work from damage. Protec t trees, vegetation,
and other designated features by erecting high-visi bility, reusable
construction fencing. Locate fence no closer to tre es than drip line.
Plan equipment and vehicle access to minimize and c onfine soil
disturbance and compaction to areas indicated on dr awings.
B. Install erosion control materials at all areas insi de or outside limits
of construction that are disturbed by planting oper ations. Provide
erosion control and seeding with native plant speci es to protect
slopes.
3.3 PLANT BED PREPARATION
A. Verify location of underground utilities before exc avation. Protect
existing adjacent turf before excavations are made. Do not disturb
topsoil and vegetation in areas outside those indic ated on Drawings.
Where planting beds occur in existing turf areas, r emove turf to depth
that will ensure removal of entire roof system. Mea sure depth of plant
pits from finished grade. Provide depth of plant pi t excavation and
relation of top of root ball and finish grade as in dicated on drawings.
Install plant materials as specified in Article 3.8 . Do not plant trees
within 3 m (10 feet) of any utility lines or buildi ng walls.
B. For newly graded subgrades, loosen subgrade to mini mum 100 mm
(4 inches) deep. Remove stones larger than 25 mm (1 inch) in any
dimension and sticks, roots, rubbish, and other ext raneous matter and
legally dispose of them off Government's property.
1. Apply soil amendments directly to subgrade before l oosening, at
rates recommended by soils analysis.
2. Spread topsoil, apply soil amendments and fertilize r on surface, and
thoroughly blend planting soil.
3. Spread planting soil 100 mm (4 inches) deep but min imum required to
meet finish grades after light rolling and natural settlement. Do
not spread if planting soil or subgrade is frozen, muddy, or
excessively wet.
32 90 00 - 10
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
a. Spread approximately 1/2 thickness of planting soil over
loosened subgrade. Mix thoroughly into top 50 mm (2 inches) of
subgrade. Spread remainder of planting soil.
b. Reduce elevation of planting soil to allow for soil thickness of
sod.
C. Finish grade planting areas to smooth, uniform surf ace plane with
loose, uniformly fine texture. Grade to within plus or minus 13 mm
(1/2 inch) of finish elevation. Roll and rake, remo ve ridges, and fill
depressions to meet finish grades. Limit finish gra ding to areas that
can be planted in immediate future.
3.4 SODDING
A. Place sod maximum 36 hours after initial harvesting according to
TPI GSS, except as modified herein.
B. For slopes 2 to 1 and greater, lay sod with long ed ge perpendicular to
contour. For V-ditches and flat bottomed ditches, l ay sod with long
edge perpendicular to water flow. On sloped areas, start sodding at
bottom of slope.
C. Finishing: After sodding, blend edges of sodded are a smoothly into
surrounding area. Eliminate air pockets and provide true and even
surface. Trim frayed areas and patch holes and miss ing areas with sod.
D. Rolling: Immediately after sodding, firm entire are a, except slopes in
excess of 3: 1, with roller maximum 134 kg (90 lbs. ) for each foot of
roller width.
E. Watering: Start watering sodded areas as required b y daily temperature
and wind conditions. Water at rate sufficient to en sure thorough
wetting of soil to minimum 150 mm (6 inches) deep. Prevent run-off,
puddling, and wilting. Do not drive watering trucks over turf areas,
unless otherwise directed. Prevent watering of othe r adjacent areas or
plant materials.
3.5 CLEANING
A. Remove and legally dispose of all excess soil and p lanting debris. 3.6 PROTECTION
A. Protect plants from traffic and construction operat ions.
B. Provide temporary fences or enclosures and signage, at planted areas.
Maintain fences and enclosures during maintenance p eriod.
C. Remove protective materials immediately before acce ptance.
32 90 00 - 11
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
D. Repair damage.
- - - E N D - - -
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
33 10 11-1
SECTION 33 10 00
WATER UTILITIES
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies materials and procedures for construction of
underground water distribution for domestic and/or fire supply systems
outside the building that are complete and ready fo r operation. This
includes piping, structures, appurtenances and all other incidentals.
1.2 RELATED WORK
A. Excavation, Trench Widths, Pipe Bedding, Backfill, Shoring, Sheeting,
Bracing: Section 31 20 00, EARTH MOVING.
B. Concrete: Section 03 30 00, CAST IN-PLACE CONCRETE.
C. Submittals: Section 01 33 23, SHOP DRAWINGS, PRODUC T DATA AND SAMPLES.
D. Erosion and Sediment Control: Section 01 57 19, TEM PORARY ENVIRONMENTAL
CONTROLS.
1.3 DEFINITIONS
A. Water distribution system: Pipelines and appurtenan ces which are part of
the distribution system outside the building for po table water and fire
supply.
B. Water service line: Pipeline from main line to 5 fe et outside of
building.
1.4 ABBREVIATIONS
A. PVC: Polyvinyl chloride plastic.
B. DI: Ductile iron pipe.
C. WOG: Water, Oil and Gas.
1.5 DELIVERY, STORAGE AND HANDLING
A. Deliver piping with factory-applied end caps. Maint ain end caps through
shipping, storage, and handling to prevent pipe-end damage and to
prevent entrance of dirt, debris, and moisture.
B. Protect stored piping from moisture and dirt by ele vating above grade.
Protect flanges, fittings, and specialties from moi sture and dirt.
C. Store plastic piping protected from direct sunlight and support to
prevent sagging and bending.
D. Cleanliness of Piping and Equipment Systems:
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
33 10 11-2
1. Care shall be exercised in the storage and handling of equipment and
piping material to be incorporated in the work. Deb ris arising from
cutting, threading and welding of piping shall be r emoved.
2. Piping systems shall be flushed, blown or pigged as necessary to
deliver clean systems.
1.6 COORDINATION
A. Coordinate connection to water main with COR 2 week s in advance.
1.7 QUALITY ASSURANCE:
A. Products Criteria:
1. When two or more units of the same type or class of materials or
equipment are required, these units shall be produc ts of one
manufacturer.
2. A nameplate bearing manufacturer's name or trademar k, including model
number, shall be securely affixed in a conspicuous place on
equipment. In addition, the model number shall be e ither cast
integrally with equipment, stamped, or otherwise pe rmanently marked
on each item of equipment.
B. Materials and equipment shall be the standard produ cts of a manufacturer
regularly engaged in the manufacture of the product s for at least three
years. Digital electronic devices, software and sys tems such as
controls, instruments or computer work stations sha ll be the current
generation of technology and basic design that has a proven satisfactory
service record of at least three years.
C. Regulatory requirements:
1. Comply with the rules and regulations of the public utility company
having jurisdiction over the connection to public w ater lines and the
extension and/or modifications to public utility sy stems.
2. Comply with the rules and regulations of the Federa l, State, and/or
Local Health Departments having jurisdiction for po table water-
service.
D. Provide certification of factory hydrostatic testin g of not less than
500 psi (3.5 MPa) in accordance with AWWA C151. Pip ing materials shall
bear the label, stamp or other markings of the spec ified testing agency.
E. Before any welding is performed, contractor shall s ubmit a certificate
certifying that welders comply with the following r equirements:
33 10 11-3
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
1. Qualify welding processes and operators for piping according to ASME
"Boiler and Pressure Vessel Code", Section IX, "Wel ding and Brazing
Qualifications".
2. Comply with provisions of ASME B31 series "Code for Pressure Piping".
3. Certify that each welder has passed American Weldin g Society (AWS)
qualification tests for the welding processes invol ved, and that
certification is current.
4. All welds shall be stamped according to the provisi ons of the
American Welding Society.
F. Where installation procedures or any part thereof a re required to be in
accordance with the recommendations of the manufact urer of the material
being installed, printed copies of these recommenda tions shall be
furnished to the Resident Engineer prior to install ation.
G. Applicable codes:
1. Plumbing Systems: IPC, International Plumbing Code.
2. Electrical components, devices and accessories shal l be listed and
labeled as defined in NFPA 70, Article 100, by a te sting agency
acceptable to authorities having jurisdiction and m arked for intended
use.
3. Fire-service main products shall be listed in the F M Global “Approval
Guide” or Underwriters Laboratories (UL) “Fire Prot ection Equipment
Directory”.
1.8 APPLICABLE PUBLICATIONS
A. The publications listed below form a part of this s pecification to the
extent referenced. The publications are referenced in the text by the
basic designation only.
B. American National Standards Institute (ANSI):
MSS SP-123-1998(R2006)..Non-Ferrous Threaded and So lder-Joint Unions
for Use With Copper Water Tube
C. American Society of Mechanical Engineers (ASME):
B31.....................Code for Pressure Piping St andards
D. American Society for Testing and Materials (ASTM):
A36/A36M-08.............Carbon Structural Steel
A536-84(2009)...........Ductile Iron Castings
33 10 11-4
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
A674-10.................Polyethylene Encasement for Ductile Iron Pipe
for Water or Other Liquids
B62-09..................Composition Bronze or Ounce Metal Castings
C651-05.................Disinfecting Water Mains
C858-10e1...............Underground Precast Utility Structures D1785-
06................Poly (Vinyl Chloride) (PVC) Plast ic Pipe,
Schedules 40, 80, and 120
D2239-03................Polyethylene (PE) Plastic P ipe (SIDR-PR) Based
on Controlled Inside Diameter
D2464-06................Threaded Poly (Vinyl Chlori de) PVC Pipe
Fittings, Schedule 80
D2466-06................Poly (Vinyl Chloride) (PVC) Pipe Fittings,
Schedule 40
D2467-06................Poly (Vinyl Chloride) (PVC) Plastic Pipe
Fittings, Schedule 80
D2609-02(2008)..........Plastic Insert Fittings for Polyethylene (PE)
Plastic Pipe
D3350-10a...............Polyethylene Plastics Pipe and Fittings
Materials
F714-10.................Polyethylene (PE) Plastic P ipe (SDR-PR) Based
on Outside Diameter F1267-
07................Metal, Expanded, Steel
E. American Water Works Association (AWWA):
B300-10.................Hypochlorites
B301-10.................Liquid Chlorine
C104-08.................Cement–Mortar Lining for Du ctile Iron Pipe and
Fittings
C105/A21.5-10...........Polyethylene Encasement for Ductile Iron Pipe
Systems
C110-08.................Ductile Iron and Gray-Iron Fittings
33 10 11-5
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
C111/A21.11-07..........Rubber-Gasket Joints for Du ctile Iron Pressure
Pipe and Fittings
C115/A21.11-11..........Flanged Ductile Iron Pipe w ith Ductile Iron or
Gray-Iron Threaded Flanges
C151/A21.51-09..........Ductile Iron Pipe, Centrifu gally Cast
C153/A21.53-11..........Ductile Iron Compact Fittin gs for Water Service
C510-07.................Double Check Valve Backflow Prevention Assembly
C512-07.................Air Release, Air/Vacuum and Combination Air
Valves
C550-05.................Protective Interior Coating s for Valves and
Hydrants
C600-10.................Installation of Ductile Iro n Mains and Their
Appurtenances
C605-11.................Underground Installation of Polyvinyl Chloride
(PVC) Pressure Pipe and Fittings for Water
C606-11.................Grooved and Shouldered Join ts
C651-05.................Disinfecting Water Mains
C700-09.................Cold-Water Meters, “Displac ement Type,” Bronze
Main Case
C800-05.................Underground Service Line Va lves and Fittings
C900-09.................Polyvinyl Chloride (PVC) Pr essure Pipe and
Fabricated Fittings, 4 In. Through 12 In. (100
mm Through 300 mm), for Water Transmission and
Distribution
C906-07.................Polyethylene (PE) Pressure Pipe and Fittings, 4
In. (100 mm) Through 64 In. (1,600 mm), for
Water Distribution and Transmission
C907-04.................Injection-Molded PVC Pressu re Fittings, 4 Inch
through 12 Inch (100 mm through 300 mm), for
Water Distribution
M23-2nd Ed..............PVC Pipe, Design and Instal lation
33 10 11-6
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
M44-2nd Ed..............Distribution Valves: Select ion, Installation,
Field Testing and Maintenance
F. National Fire Protection Association (NFPA):
NFPA 24-2010 Ed.........Installation of Private Fir e Service Mains and
Their Appurtenances
NFPA 1963-2009 Ed.......Fire Hose Connections
G. NSF International (NSF):
NSF/ANSI 14 (2013)......Plastics Piping System Comp onents and Related
Materials
NSF/ANSI 61-2012........Drinking Water System Compo nents - Health
Effects
NSF/ANSI 372-2011.......Drinking Water System Compo nents – Lead Content
H. American Welding Society (AWS):
A5.8/A5.8M-2004 ........Filler Metals for Brazing a nd Braze Welding
I. Underwriters' Laboratories (UL):
246.....................Hydrants for Fire-Protectio n Service
262.....................Gate Valves for Fire-Protec tion Service
312.....................Check Valves for Fire-Prote ction Service
405.....................Fire Department Connection Devices
753.....................Alarm Accessories for Autom atic Water-Supply
Control Valves for Fire Protection Service
789.....................Indicator Posts for Fire-Pr otection Service
1091....................Butterfly Valves for Fire-P rotection Service
1285....................Pipe and Couplings, Polyvin yl Chloride (PVC),
and Oriented Polyvinyl Chloride (PVCO) for
Underground Fire Service
1.9 WARRANTY
A. The Contractor shall remedy any defect due to fault y material or
workmanship and pay for any damage to other work re sulting therefrom
within a period of one year from final acceptance. Further, the
Contractor will furnish all manufacturers’ and supp lier's written
33 10 11-7
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
guarantees and warranties covering materials and eq uipment furnished
under this Contract.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Material or equipment containing a weighted average of greater than
0.25 percent lead shall not be used in any potable water system intended
for human consumption, and shall be certified in ac cordance with
NSF/ANSI 61 or NSF 372.
B. Plastic pipe, fittings, and solvent cement shall me et NSF/ANSI 14 and
shall be NSF listed for the service intended.
2.2 FACTORY-ASSEMBLED PRODUCTS
A. Standardization of components shall be maximized to reduce spare part
requirements. The contractor shall guarantee perfor mance of assemblies
of components, and shall repair or replace elements of the assemblies as
required to deliver specified performance of the co mplete assembly.
2.3 SAFETY GUARDS
A. All equipment shall have moving parts protected to prevent personal
injury. Pump shafts and couplings shall be fully gu arded by a sheet
steel guard, covering coupling and shaft but not be arings. Material
shall be minimum 16-gauge sheet steel; ends shall b e braked and drilled
and attached to pump base with minimum of four 1/4 inch (6 mm) bolts.
Reinforce guard as necessary to prevent side play f orcing guard onto
couplings.
2.4 LIFTING ATTACHMENTS
A. Equipment shall be provided with suitable lifting a ttachments to enable
equipment to be lifted in its normal position. Lift ing attachments shall
withstand any handling conditions that might be enc ountered, without
bending or distortion of shape, such as rapid lower ing and braking of
load.
2.5 DUCTILE IRON PIPE AND FITTINGS
A. Mechanical-Joint, Ductile-Iron Pipe: AWWA C151, wit h mechanical-joint
bell and plain spigot end unless grooved or flanged ends are indicated,
350 psi (2400 kPa).
1. Mechanical-Joint, Ductile-Iron Fittings: AWWA C110, ductile- or gray-
iron standard pattern or AWWA C153, ductile-iron co mpact pattern.
33 10 11-8
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
2. Glands, Gaskets, and Bolts: AWWA C111, ductile- or gray-iron glands,
rubber gaskets, and steel bolts.
B. Cement Mortar Internal Lining: Cement mortar lining and bituminous seal
coat as per AWWA C104.
C. Exterior Pipe Coating: The exterior of pipe shall h ave the standard
asphaltic coating.
2.6 POLYVINYL CHLORIDE PIPE AND FITTINGS
A. PVC, AWWA Pipe: AWWA C900, Class 200, with bell end with gasket, and
with spigot end.
1. Comply with UL 1285 for fire-service mains if indic ated.
2. PVC Fabricated Fittings: AWWA C900, Class 200, with bell-and-spigot
or double-bell ends. Include elastomeric gasket in each bell.
3. PVC Molded Fittings: AWWA C907, Class 150, with bel l-and-spigot or
double-bell ends. Include elastomeric gasket in eac h bell.
4. Mechanical-Joint, Ductile-Iron Fittings: AWWA C110, ductile- or gray-
iron standard pattern or AWWA C153, ductile-iron co mpact pattern.
a. Glands, Gaskets, and Bolts: AWWA C111, ductile- or gray-iron
glands, rubber gaskets, and steel bolts.
2.7 PE PIPE AND FITTINGS
A. PE, ASTM Pipe: ASTM D2239, SIDR No. 5.3, 7, or 9; w ith PE compound
number required to give pressure rating not less th an 200 psi (1380
kPa).
1. Insert Fittings for PE Pipe: ASTM D2609, made of PA , PP, or PVC with
serrated male insert ends matching inside of pipe. Include bands or
crimp rings.
2. Molded PE Fittings: ASTM D3350, PE resin, socket- o r butt-fusion
type, made to match PE pipe dimensions and class.
B. PE, AWWA Pipe: AWWA C906, DR No. 7.3, 9, or 9.3; wi th PE compound number
required to give pressure rating not less than 200 psi (1380 kPa).
2.8 PE, AWWA FITTINGS: AWWA C906, SOCKET- OR BUTT-FUSIO N TYPE, WITH DR NUMBER
MATCHING PIPE AND PE COMPOUND NUMBER REQUIRED TO GIVE PRESSURE RATING
NOT LESS THAN 200 PSI (1380 KPA).VALVES
A. Gate Valves: AWWA C509, Non-rising Stem, Resilient Seat, 200 psi (1380
kPa).
1. Valves 3 inches (75 mm) and larger: Resilient seat valve with gray-
or ductile iron body and bonnet; cast iron or bronz e double-disc
gate; bronze gate rings; non-rising bronze stem and stem nut.
33 10 11-9
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
2. Interior and exterior coating: AWWA C550, thermo-se tting or fusion
epoxy.
3. Underground valve nut: Furnish valves with 2 inch ( 50 mm) nut for
socket wrench operation.
4. Aboveground and pit operation: Furnish valves with hand wheels.
5. End connections shall be mechanical.
B. Gate Valve Accessories and Specialties
1. Tapping-Sleeve Assembly: ANSI MSS SP-60; sleeve and valve to be
compatible with the drilling matching.
a. Tapping Sleeve: Cast or Ductile Iron, two-piece bol ted sleeve.
Sleeve to match the size and type of pipe material being tapped.
b. Valve shall include one raised face flange mating t apping-sleeve
flange.
2. Valve Boxes: AWWA M44 with top section, adjustable extension of
length required for depth of burial of valve, plug with lettering
"WATER," and bottom section with base that fits ove r valve and with a
barrel.
3. Operating Wrenches: Steel, tee-handle with one poin ted end, stem of
length to operate deepest buried valve, and socket matching valve
operating nut. (Provide two wrenches for Project.)
4. Indicator Posts: UL 789, FMG approved, vertical-typ e, cast iron body
with operating wrench, extension rod, and adjustabl e cast iron barrel
of length required for depth of burial of valve.
2.9 DISINFECTION CHLORINE
A. Liquid chlorine: AWWA B301.
B. Sodium Hypochlorite: AWWA B300 with 5 percent to 15 percent available
chlorine.
C. Calcium hypochlorite: AWWA B300 supplied in granula r form of 5 g.
tablets, and shall contain 65 percent chlorine by w eight.
2.10 WARNING TAPE
A. Warning tape shall be standard, 4 mil. Polyethylene , 3 inch (76 mm) wide
tape, detectable type, blue with black letters and imprinted with
“CAUTION BURIED WATER LINE BELOW”.
33 10 11-10
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
PART 3 - EXECUTION
3.1 PIPING APPLICATIONS
A. Use pipe, fittings, and joining methods for piping systems according to
the following applications.
1. Transition couplings and special fittings with pres sure ratings at
least equal to piping pressure rating may be used, unless otherwise
indicated.
2. Do not use flanges or unions for underground piping .
3. Flanges, unions, grooved-end-pipe couplings, and sp ecial fittings may
be used, instead of joints indicated, on abovegroun d piping and
piping in vaults.
B. Underground water-service piping NPS 4 to NPS 16 (D N 100 to DN 400)
shall be any of the following:
1. Ductile iron, mechanical-joint pipe; ductile iron, mechanical-joint
fittings; and mechanical joints.
2. PE, AWWA pipe; PE, AWWA fittings; and heat-fusion j oints.
3. PVC, AWWA Class 200 pipe: PVC, AWWA Class 200 fabri cated mechanical-
joint, ductile iron fittings; and gasketed joints.
3.2 DUCTILE IRON PIPE
A. Install Ductile Iron, water-service piping accordin g to AWWA C600 and
AWWA M41-3rd Edition.
1. Install PE corrosion-protection encasement accordin g to ASTM A674 or
AWWA C105/A21.5.
B. Pipe shall be sound and clean before laying. When l aying is not in
progress, the open ends of the pipe shall be closed by watertight plug
or other approved means.
C. When cutting pipe is required, the cutting shall be done by machine,
leaving a smooth cut at right angles to the axis of the pipe. Bevel cut
ends of pipe to be used with push-on bell to confor m to the manufactured
spigot end. Cement lining shall be undamaged.
D. Push on joints shall be made in strict accordance w ith the
manufacturer’s instruction. Pipe shall be laid with bell ends looking
ahead.
3.3 PVC PIPE
A. PVC piping shall be installed in strict accordance with the
manufacturer’s instructions and AWWA C605. Place se lected material and
thoroughly compacted to one foot above the top of t he pipe.
33 10 11-11
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
B. Install Copper Tracer Wire, No. 14 AWG solid, singl e conductor,
insulated. Install in the trench with piping to all ow location of the
pipe with electronic detectors. The wire shall not be spiraled around
the pipe nor taped to the pipe. Wire connections ar e to be made by
stripping the insulation from the wire and solderin g with rosin core
solder per ASTM 828. Solder joints shall be wrapped with rubber tape and
electrical tape. At least every 1000 feet (300 m) p rovide a 5 pound (2.3
kg) magnesium anode attached to the main tracer wir e by solder. The
solder joint shall be wrapped with rubber tape and with electrical tape.
An anode shall also be attached at the end of each line.
3.4 ANCHORAGE INSTALLATION
A. Install water-distribution piping with restrained j oints. Anchorages and
restrained-joint types that may be used include: co ncrete thrust blocks.
B. Install anchorages for tees, plugs and caps, bends, crosses, valves, and
hydrant branches. Include anchorages for the follow ing piping systems:
1. Gasketed-Joint, Ductile Iron, Water-Service Piping: According to AWWA
C600.
2. Gasketed-Joint, PVC Water-Service Piping: According to AWWA M23.
3. Fire-Service-Main Piping: According to NFPA 24.
3.5 APPLY FULL COAT OF ASPHALT OR OTHER ACCEPTABLE CORROSION-RESISTANT
MATERIAL TO SURFACES OF INSTALLED FERROUS ANCHORAGE DEVICES.VALVE
INSTALLATION
A. AWWA Valves: Install each underground valve with st em pointing up and
with valve box.
B. Raise or lower existing valve and curb stop boxes a nd fire hydrants to
finish grade in areas being graded.
C.
3.6 CONNECTIONS
A. Drawings indicate general arrangement of piping, fi ttings, and
specialties. Install water service lines to a point of connection within
approximately 5 feet (1500 mm) outside of building( s) to which service
is to be connected and make connections thereto. If building services
have not been installed provide temporary caps and mark for future
connection.
33 10 11-12
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
3.7 FIELD QUALITY CONTROL
A. Conduct piping tests before joints are covered and after concrete thrust
blocks have hardened sufficiently. Fill pipeline 24 hours before testing
and apply test pressure to stabilize system. Use on ly potable water.
B. Prior to final acceptance, provide a video record o f all piping from the
building to the municipal connection to show the li nes are free from
obstructions, properly sloped and joined.
C. Perform hydrostatic tests at not less than one-and- one-half times
working pressure for two hours.
1. Increase pressure in 50-psi (350-kPa) increments an d inspect each
joint between increments. Hold at test pressure for 1 hour; decrease
to 0 psi (0 kPa). Slowly increase again to test pre ssure and hold for
1 more hour. Maximum allowable leakage is 2 quarts (1.89 L) per hour
per 100 joints. Remake leaking joints with new mate rials and repeat
test until leakage is within allowed limits.
D. Prepare reports of testing activities.
3.8 IDENTIFICATION
A. Install continuous underground warning tape 12 inch es (300 mm) directly
over piping.
3.9 CLEANING
A. Purge new water-distribution piping systems and par ts of existing
systems that have been altered, extended, or repair ed before use.
B. Use purging and disinfecting procedure prescribed b y local utility
provider or other authorities having jurisdiction o r, if method is not
prescribed by authorities having jurisdiction, use procedure described
in AWWA C651 or do as follows:
1. Fill the water system with a water/chlorine solutio n containing at
least 50 ppm of chlorine; isolate and allow to stan d for 24 hours.
2. Drain the system of the previous solution and refil l with
water/chlorine solution containing at least 200 ppm of chlorine;
isolate and allow system to stand for 3 hours.
3. After standing time, flush system with clean, potab le water until no
chlorine remains in water coming from system.
4. Submit water samples in sterile bottles to authorit ies having
jurisdiction. Repeat procedure if biological examin ation shows
evidence of contamination.
C. Prepare reports of purging and disinfecting activit ies.
33 10 11-13
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
--- E N D ---
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
33 63 00-1
SECTION 33 63 00
STEAM ENERGY DISTRIBUTION
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies materials and procedures for construction of
underground steam distribution and condensate retur n piping system,
including manholes, outside the buildings. System s hall be: pre-
engineered direct-buried drainable-dryable-testable (DDT).
1.2 RELATED WORK
A. Excavation, Trench Widths, Pipe Bedding, Backfill, Shoring, Sheeting,
Bracing: Section 31 20 00, EARTH MOVING.
B. Concrete Work, Reinforcing, Placement and Finishing : Section 03 30 00,
CAST-IN-PLACE CONCRETE.
C. General plumbing, protection of Materials and Equip ment, and quality
assurance: Section 22 05 11, COMMON WORK RESULTS FO R PLUMBING.
D. Painting exposed steel and other surfaces: Section 09 91 00, PAINTING.
E. Steel for trench and tunnel pipe supports: Section 05 50 00, METAL
FABRICATIONS.
F. Cathodic Protection of DDT Pre-Engineered Direct-Bu ried Systems: Section
26 42 00, CATHODIC PROTECTION.
G. Submittals: Section 01 33 23, SHOP DRAWINGS, PRODUC T DATA AND SAMPLES.
H. Metering: SECTION 25 10 10, ADVANCED UTILITY METERI NG SYSTEM.
I. Erosion and Sediment Controls: Section 01 57 19, TE MPORARY ENVIRONMENTAL
CONTROLS.
1.3 DEFINITIONS
A. System: The complete underground steam and condensa te distribution
system including all components such as carrier pip ing, pipe supports,
insulation, protective enclosures, anchors, corrosi on protection and
accessories.
B. Pre-Engineered Direct-Buried System: The factory-fa bricated system.
C. Drainable-Dryable-Testable (DDT) Pre-Engineered Dir ect-Buried System: A
factory-fabricated system.
D. Carrier Pipe: Pipe carrying the steam or condensate .
E. Encasement Pipe: Outer protective pipe on any main line pipe. Carrier
pipe and insulation are within the casing.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
33 63 00-2
F. HP Systems: High-pressure piping operating at more than 15 psi (104 kPa)
as required by ASME B31.1.
1.4 ABBREVIATIONS
A. HDPE: high-density polyethylene
B. RTRP: reinforced thermosetting resin plastic
C. RTRF: reinforced thermosetting resin fittings
D. WOG: water, oil and gas
1.5 DELIVERY, STORAGE AND HANDLING
A. The Contractor is solely responsible for the protec tion of equipment and
material against damage. Protect piping systems aga inst the entry of
water, mud or other foreign substances by installin g watertight covers
on open ends at all times. Protect direct-buried sy stem coatings from
ultraviolet light (sunlight). Existing equipment wo rked on by the
Contractor or in the Contractor's working area shal l be considered to be
in the custody and responsibility of the Contractor .
B. All insulated piping systems exposed to water must be replaced prior to
installation.
1.6 COORDINATION
A. Coordinate exterior steam lines and connections to building services up
to the actual extent of building wall.
1.7 QUALITY ASSURANCE:
A. Products Criteria:
1. When two or more units of the same type or class of materials or
equipment are required, these units shall be produc ts of one
manufacturer.
2. A nameplate bearing manufacturer's name or trademar k, including model
number, shall be securely affixed in a conspicuous place on
equipment. In addition, the model number shall be c ast integrally
with equipment, stamped, or otherwise permanently m arked on each item
of equipment.
B. Contractor shall restore damaged items to as-new op erating condition or
replace damaged items as directed by the Contractin g Officer’s
Representative, at no additional cost to the Govern ment.
C. Welding Qualifications: Qualify procedures and pers onnel according to
ASME Boiler and Pressure Vessel Code: Section IX.
1. Comply with provisions in ASME B31.9, Building Serv ices Piping and
ASME B31.1, Power Piping.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
33 63 00-3
2. Certify that each welder has passed AWS qualificati on tests for
welding processes involved and that certification i s current.
D. ASME Compliance: Comply with ASME B31.9, Building S ervices Piping, ASME
B31.1, Power Piping, for materials, products, and i nstallation.
E. ASME Compliance: Safety valves and pressure vessels shall bear
appropriate ASME labels.
1.8 SUBMITTALS
A. Manufacturers’ Literature and Data shall be submitt ed, as one package,
for pipes, fittings and appurtenances, including jo inting materials,
insulation, hangars and other miscellaneous items.
1.9 APPLICABLE PUBLICATIONS
A. The publications listed below form a part of this s pecification to the
extent referenced. The publications are referred in the text by basic
designation only.
B. Federal Specifications (Fed. Spec.):
A-A-60005 NOT 1.........Frames, Covers, Grating, St eps, Sump and Catch
Basin, Manhole
L-S-125.................Screening, Insect, Nonmetal lic
C. Military Specifications (Mil. Spec.):
MIL-S-901...............Shock Tests H.I. (High Impa ct) Shipboard
Machinery, Equipment and Systems
D. American Society for Testing and Materials (ASTM):
A36/A36M-08.............Carbon Structural Steel
A47/A47M-99(2009).......Ferritic Malleable Iron Cas tings
A53/A53M-10.............Pipe, Steel, Black and Hot- Dipped, Zinc-Coated,
Welded and Seamless
A105/A105M-10a..........Carbon Steel Forgings for P iping Applications
A106/A106M-10...........Seamless Carbon Steel Pipe for High-Temperature
Service
A126-04(2009)...........Gray Iron Castings for Valv es, Flanges, and
Pipe Fittings
A139/A139M-04(2010).....Electric-Fusion (Arc)-Welde d Steel Pipe (NPS 4
and Over)
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
33 63 00-4
A167-99(2009)...........Stainless and Heat-Resistin g Chromium-Nickel
Steel Plate, Sheet, and Strip
A193/A193M-10a..........Alloy-Steel and Stainless S teel Bolting for
High Temperature or High Pressure Service and
Other Special Purpose Applications
A194/A194M-10a..........Carbon and Alloy Steel Nuts for Bolts for High
Pressure or High Temperature Service, or Both
A197/A197M-00(2006) ....Cupola Malleable Iron
A234/A234M-10b..........Piping Fittings of Wrought Carbon Steel and
Alloy Steel for Moderate and High Temperature
Service
A240/A240M-10b..........Chromium and Chromium-Nicke l Stainless Steel
Plate, Sheet, and Strip for Pressure Vessels
and for General Applications
A307-10.................Carbon Steel Bolts and Stud s, 60 000 PSI
Tensile Strength
A666-10.................Annealed or Cold-Worked Aus tenitic Stainless
Steel Sheet, Strip, Plate, and Flat Bar
A733-03(2009)...........Welded and Seamless Carbon Steel and Austenitic
Stainless Steel Pipe Nipples B61-
08..................Steam or Valve Bronze Castings
C177-10.................Steady-State Heat Flux Meas urements and Thermal
Transmission Properties by Means of the
Guarded-Hot-Plate Apparatus
C411-05.................Hot-Surface Performance of High-Temperature
Thermal Insulation
C449-07.................Mineral Fiber Hydraulic-Set ting Thermal
Insulating and Finishing Cement
C450-08.................Fabrication of Thermal Insu lating Fitting
Covers for NPS Piping, and Vessel Lagging
C533-09.................Calcium Silicate Block and Pipe Thermal
Insulation
33 63 00-5
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
C547-07.................Mineral Fiber Pipe Insulati on
C552-07.................Cellular Glass Thermal Insu lation
C585-10.................Inner and Outer Diameters o f Thermal Insulation
for Nominal Sizes of Pipe and Tubing
C591-09.................Unfaced Preformed Rigid Cel lular
Polyisocyanurate Thermal Insulation
C655-09.................Reinforced Concrete D-Load Culvert, Storm
Drain, and Sewer Pipe
C920-10.................Elastomeric Joint Sealants
C1126-10a...............Faced or Unfaced Rigid Cell ular Phenolic
Thermal Insulation
C1136-10................Flexible, Low Permeance Vap or Retarders for
Thermal Insulation
D2996-01(2007)..........Filament-Wound Fiberglass ( Glass-Fiber-
Reinforced Thermosetting-Resin) Pipe
D4024-05................Machine Made Fiberglass (Gl ass-Fiber-Reinforced
Thermosetting Resin) Flanges
E84-10b.................Surface Burning Characteris tics of Building
Materials
E. American Society of Mechanical Engineers (ASME):
B1.20.1-2006............Pipe Threads, General Purpo se (Inch)
B16.3-2006..............Malleable Iron Threaded Fit tings: Classes 150
and 300
B16.4-2006..............Gray Iron Threaded Fittings : (Classes 125 and
250)
B16-5-2009..............Pipe Flanges and Flanged Fi ttings: NPS 1/2
through NPS 24 Metric/Inch Standard
B16.9-2007..............Factory-Made Wrought Buttwe lding Fittings
B16.11-2009.............Forged Fittings, Socket-Wel ding and Threaded
B16.21-2005.............Nonmetallic Flat Gaskets fo r Pipe Flanges
33 63 00-6
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
B18.2.1-2010............Square, Hex, Heavy Hex, and Askew Head Bolts
and Hex, Heavy Hex, Hex Flange, Lobed Head, and
Lag Screws (Inch Series)
B31.1-2010..............Power Piping
B31.9-2008..............Building Services Piping
B40.1000-2009...........Pressure Gauges and Gauge A ttachments
F. American Welding Society (AWS):
B2.1-B2.1M-BMG-2009.....Base Metal Grouping for Wel ding Procedures and
Performance Qualification
D10.12/D10.12M-2000.....Guide for welding Mild Stee l Pipe
G. American Association of State Highway and Transport ation Officials
(AASHTO):
M300-03.................Inorganic Zinc-Rich Primer
H. Manufacturer’s Standardization Society (MSS):
MSS SP 58...............Pipe Hangers and Supports-M aterials, Design,
Manufacture, Selection, Application and
Installation
I. NACE International (NACE):
SP0169-2007.............Control of External Corrosi on on Underground or
Submerged Metallic Piping Systems
J. National Fire Protection Agency (NFPA):
255-2006 Ed.............Test Burning Characteristic s of Building
Materials 1.10 WARRANTY
A. The Contractor shall remedy any defect due to fault y material or
workmanship and pay for any damage to other work re sulting there from
within a period of one year from final acceptance. Further, the
Contractor will provide all manufacturers and suppl ier's written
guarantees and warranties covering materials and eq uipment furnished
under this Contract.
33 63 00-7
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
PART 2 - PRODUCTS
2.1 STEEL PIPES AND FITTINGS
A. Steel Pipe: ASTM A53, Type E, Grade A, wall thickne ss as indicated in
"Piping Application" Article; black with plain ends for high pressure
steam pipe, except pumped condensate return and hig h pressure condensate
piping shall be schedule 80.
1. Pipe shall be butt welded for sizes 2.5 inches and larger and socket
welded for 2 inches and below. Where possible, stra ight sections
shall be supplied in 40 foot random lengths with 6 inches of piping
exposed at each end for field joint fabrication.
B. Steel Welding Fittings: ASME B16.9 and ASTM A234, s eamless or welded.
1. Welding Filler Metals shall comply with AWS D10.12 for welding
materials appropriate for wall thickness and chemic al analysis of
steel pipe being welded.
C. Nipples: ASTM A733, Standard Weight, seamless, carb on-steel pipe.
D. Pipe-Flange Gasket Materials: ASME B16.21, suitable for chemical and
thermal conditions of piping system contents, nonme tallic, flat,
asbestos free, 1/8 inch (3.2 mm) maximum thickness unless thickness or
specific material is indicated.
1. For flat-face, Class 125, cast-iron and cast-bronze flanges.
2. For raised-face, Class 250, cast-iron and steel fla nges.
E. Flange Bolts and Nuts: ASME B18.2.1, carbon steel, unless otherwise
indicated.
2.2 PRE-ENGINEERED, FACTORY-FABRICATED, DIRECT-BURIED, DRAINABLE-DRYABLE-
TESTABLE (DDT) SYSTEMS
A. Complete steam and condensate piping system with ca rrier pipes, carrier
pipe insulation with jackets and banding (Pre-Insul ated), air space,
0.25 inch (6.35 mm) thick steel casing, fusion-bond ed epoxy casing
coatings, insulation, HDPE jacket, and accessories. Do not locate
condensate pipes in casings (conduits) that contain steam pipes.
B. All components of system shall be suitable for carr ier pipe pressures
and temperatures as follows:
1. Steam System: 150 psi (1000 kPa); 366 deg F (185 de g C).
2. Condensate System: 50 psi (345 kPa); 310 deg F (154 deg C).
C. Steam Carrier Pipes and Condensate Carrier Pipes:
1. No piping joints are allowed in factory-fabricated straight sections
of pre-engineered direct-buried systems.
33 63 00-8
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
2. Factory-fabricated direct-buried piping sections th at are a portion
of an expansion loop or bend shall have all welded joints 100%
radiograph inspected.
3. Internal high pressure steam piping shall be standa rd weight carbon
steel, except pumped condensate return and condensa te piping which
shall be schedule 80. Pipe shall be butt welded for sizes 2.5 inches
and larger and socket weld for 2 inches and below. Where possible,
straight sections shall be supplied in 40 foot rand om lengths with 6
inches of piping exposed at each end for field join t fabrication.
Pipe shall be ASTM A53 Grade B Type S Seamless or T ype E ERW.
D. Carrier Pipe Insulation shall:
1. Conform to minimum thickness and type of insulation listed in Tables
1 and 2 below as required for service temperature i n carrier pipe as
listed below.
2. Section A: Steam temperature is 366 deg F (185 deg C), steam pressure
is 150 psi (kPa). Pumped condensate temperature is 300 deg F (93 deg
C). Drip return temperature is 212 deg F (100 deg C ).
3. Provide Class “A” insulation shall be mineral wool.
4. Allowable Carrier Pipe Insulation Type and Minimum Insulation
Thickness:
TABLE 1
Minimum Pipe Insulation Thickness mm (inches) For Steam 16 to 408 psi (110 to 2800 kPa) gage
Nominal Pipe Diameter Inches
(mm)
Mineral Wool
4 (100) 1- 1/2
Notes: Insulation listed has passed the 96-hour boi ling water test.
Pipes smaller than 1 inch (25 mm) shall have same i nsulation thickness
as 1 inch (25 mm) pipe.
TABLE 2
Minimum Pipe Insulation Thickness inches (mm) For Steam Less than 16 psi (110) gage, Condensate Return
Nominal Pipe Diameter inches
(mm)
Mineral Wool
2 (50) 1- 1/2 (40)
33 63 00-9
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
Notes: Insulation listed has passed the 96-hour boi ling water test
which indicates that satisfactory performance in un derground service
can be expected. Pipes smaller than 1 inch (25 mm) shall have the same
insulation thickness as required for 1 inch (25 mm) pipe.
E. Insulation Banding and Jacket: ASTM A167, stainless steel bands and
clips, at least 0.5 inches (13 mm) wide, (304 stain less steel), maximum
spacing 18 inches (460 mm). A minimum of two bands is required for each
4 foot (1300 mm) section of insulation.
F. Vinyl-coated fiberglass scrim jacket: Fed. Spec. L- S-125, Type II, Class
2, with 18 x 16 mesh (number of filaments per inch) and made of 0.013
inches (0.335 mm) diameter vinyl-coated fibrous gla ss yarn. Install
bands over the jacket to secure the insulation to t he carrier pipe.
G. Casing: ASTM A139, smooth-wall steel, electric resi stance welded.
Plastic casings are not permitted. Use eccentric co nnectors as necessary
between casing sections to provide continuous gravi ty drainage in bottom
of casing between manholes and between manholes and buildings.
Casing Diameter in. (mm) Minimum Thickness in. (mm) 6 – 46 (150 - 1170) 0.250 (6.35)
H. Casing End Seal Plates with Vents and Drains: ASTM A36, steel, minimum
thickness 0.375 inches (9.5 mm) for casings up thru 12 inches (300 mm)
diameter and 0.5 inches (13 mm) for casings over 12 inches (300 mm)
diameter. Provide 1 inch (25 mm) drain at the botto m and vent at the
top. Construct with threaded steel half couplings. Install threaded
brass plugs in drains.
I. Vent Riser Pipes: ASTM A53, Schedule 40, galvanized , extending through
top of manhole and terminate 12 inches (300 mm) abo ve grade with 180-
degree bend.
J. Gland Seals are not permitted because of the possib ility of water
entering the system thru the gland seal from a floo ded manhole.
K. Provide continuous 1 inch (25 mm) minimum air space between carrier pipe
insulation and casing.
L. Casing coating shall be dual layers of fusion-bonde d epoxy, inner green-
colored layer minimum thickness 0.020 inches (0.5 m m), outer black-
colored layer minimum thickness 0.010 inches (0.25 mm). Rated by coating
manufacturer for continuous service for at least 25 years at minimum
temperature of 230 deg F (110 deg C) and having a c oefficient of
33 63 00-10
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
expansion similar to that of steel. Coating shall b e applied in
accordance to recommendations of coating manufactur er including surface
preparation. Factory-inspect for holidays and make repairs as necessary.
M. Outer Conduit Insulation and Jacket
1. Conduit insulation shall be spray applied polyureth ane foam having a
minimum density of 2 lbs/cu.ft for the straight len gths and fittings.
2. Insulation thickness shall be 1 inch maximum.
3. Polyurethane foam shall have a minimum initial K va lve of 0.18,
maximum density of 2 lbs/cu.ft and a minimum closed cell content of
90%.
4. Outer jacket shall be 125 mils thick extruded seaml ess HDPE.
N. Coating of end plates and casing (conduit) sections extending in
manholes shall be zinc-rich coating that conforms t o AASHTO M300, Type
IA except that volatile organic compounds shall not exceed 2.8 pounds
per gallon (0.34 kg per liter). The zinc rich coati ng shall be applied
in accordance with the recommendations of the coati ng manufacturer
including surface preparation. No additional top co at shall be applied.
O. Primer and Paint Outer Conduit
1. Primer: Ethyl Silicate inorganic zinc-rich. Primer shall be suitable
for temperatures to at least 750 deg. F.
2. Finish Coat: Additional coat as Ethyl Silicate inor ganic zinc-rich.
P. Carrier pipe guides and supports shall be maximum s pacing 10 feet (3000
mm) on centers, no more than 5 feet (1500 mm) from pipe ends, minimum of
three guides per elbow section. Designed to permit thermal expansion
without damage, provide proper pipe guiding and sup port, and to allow
horizontal movement in two directions as necessary at expansion loops
and bends. Design of guides and supports must permi t continuous drainage
of water in bottom of casing. Pipe insulation shall extend thru the pipe
guides and supports and be protected by steel sleev es. Design of guides
and supports shall be such that no metal-to-metal c ontact exists between
the casing and the carrier pipe. Insulation or non- metallic material
used to ensure no metal to metal contact shall be d esigned to not be
compressed by the weight of the carrier pipe when f ull of water.
Q. Expansion Loops or Z-Bends
1. Installed in conduit sized to handle indicated pipe movement.
Conduit fittings and straight sections to be large enough to allow
33 63 00-11
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
expansion and contraction of the system without hav ing the insulation
touch the outer conduit
a. Carrier pipe alignment guides shall be factory-inst alled to direct
movement from expansion within conduit to aforement ioned expansion
loops or z-bends.
R. Anchor plates (provided by manufacturer) shall be A STM A36 steel, welded
to carrier pipe and casing, 0.5 inches (13 mm) mini mum thickness,
passages for air flow and water drainage thru the a nnular air space in
the system. Coated with same coating material as th e casing. Locate 3 to
5 feet (900 to 1500 mm) from piping entrance to manho le or building
wall. Walls of manholes and buildings cannot be uti lized as anchor
points.
S. Field connection of casing sections shall be steel section conforming to
casing specification, welded to casing sections, co ated on all surfaces
with system manufacturer’s coating field repair com pound, and covered
with a 0.05 inch (1.3 mm) minimum thickness polyeth ylene shrink sleeve
designed for a service temperature exceeding 176 de g F (80 deg C).
T. Manhole (steam pit) and building wall penetrations shall provide steel
leak plates welded to wall sleeves or to casings. W here a wall sleeve is
utilized, allow sufficient annular space between th e sleeve and the
casing and install a watertight seal, rated for 250 deg F (121 deg C)
minimum. Manhole and building walls cannot be used as anchor points.
1. Link Seal
a. Provide link seal within building wall or pit wall penetration to
act as a moisture barrier. Pipe system manufacturer shall provide
additional outer jacket stiffing in the wall penetr ation ends of
the pipe to allow for link type seals to be effecti ve in sealing.
This stiffening shall be the same gage as the outer conduit and
extend a minimum of 4 feet from the end of the wall penetration
pipe.
U. Provide sacrificial anode type cathodic protection system with
dielectric isolation devices and test stations for all systems. Design
system for 25 years service, assume two percent bar e metal. System shall
comply with NACE SP0169.
V. Provide embossed brass or stainless steel tag hung by a brass or
stainless steel chain at each end of each conduit o r insulated piping in
the manholes and buildings. The tag shall identify system manufacturer’s
33 63 00-12
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
name, date of installation, government contract, an d manufacturer’s
project number.
W. All branch piping connections must be located in ma nholes.
X. Accessories for Manholes:
1. See specification section 05 50 00 Metal Fabricatio ns.
a. Steam pit entrance hatch.
b. Steam pit ladder.
c. Steam pit sump basin grating.
Y. Drainage as shown on drawings. Provide a 24 inch (6 10 mm) square by 24
inch (610 mm) deep sump pit in each manhole where i ndicated on drawings.
2.3 STEAM CARRIER PIPING
A. Pipe: ASTM A53, steel, seamless, Grade B or ASTM A1 06, Grade B, electric
resistance welded or ASTM A53, Grade B, Schedule 40 . Standard weight
permitted for pipe sizes 12 inches (300 mm) and abo ve. Grade F, furnace
butt-welded pipe, is not permitted.
B. Joints:
1. In trenches and direct-buried systems: Butt-weld; s ocket weld for
pipe sizes 2 inches (DN 50) and below. Manufacturer ’s standard
sliding gasketed joints are permitted between secti ons of WSL pre-
engineered direct-buried systems. No joints are all owed in factory-
fabricated straight sections of pre-engineered dire ct-buried systems.
Factory-fabricated direct-buried piping sections th at are a portion
of an expansion loop or bend shall have all welded joints 100%
radiograph inspected. All radiographs shall be revi ewed and
interpreted by a American Society for Non-Destructi ve Testing (ASNT)
Certified Level III radiographer, employed by the t esting firm, who
shall sign the reading report.
2. In tunnels, manholes, steam pits and open areas: Bu tt weld pipe sizes
2-1/2 inches (65 mm) and above; thread or socket we ld pipe sized 2
inches (50 mm) and below.
C. Fittings:
1. Butt welded joints: ASTM A234 or ASME B16.9, steel, Grade B, same
schedule as adjoining pipe. All elbows shall be lon g radius unless
otherwise indicated. Tees shall be full size or red ucing as required,
having interior surfaces smoothly contoured.
33 63 00-13
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
2. Threaded joints: ASTM A47 or ASTM A197 or ASME B16. 3, malleable iron,
300 pound (2050 kPa) class.
3. Socket welded joints: ASME B16.11, forged steel, 20 00 psi (13,800
kPa) class.
D. Flanges and bolts: ASME B16.5, weld neck, forged st eel or ASTM A105,
pressure class 150 psi (1025 kPa). Bolts shall be h igh strength ASTM
A193, Class 2, Grade B8. Nuts shall be ASTM A194.
E. Unions: Pipe 2 inches (50 mm) and smaller shall be threaded, malleable
iron or steel, 300 psi (2050 kPa) class.
2.4 STEAM CONDENSATE CARRIER PIPING
A. Pipe: ASTM A53, seamless, Grade B or ASTM A53 elect ric resistance
welded, Grade B; Schedule 80. Grade F, furnace butt -welded, pipe is not
permitted.
B. Joints:
1. In Trenches and direct-buried systems: Butt weld jo ints. Socket weld
is required for pipe sizes 2 inches (50 mm) and bel ow. Manufacturer’s
standard sliding, gasketed joints are permitted bet ween factory-
fabricated sections of direct buried WSL system. No joints are
allowed in factory-fabricated straight sections of pre-engineered
direct-buried systems. Factory-fabricated direct-bu ried piping
systems that are a portion of expansion loops or be nds shall have all
welded joints 100% radiograph inspected. All radiog raphs shall be
reviewed and interpreted by an ASNT Certified Level III radiographer,
employed by the testing firm, who shall sign the re ading report.
2. In tunnels, manholes, steam pits and open areas: Bu tt weld pipe sizes
2-1/2 inches (65 mm) and above; thread or socket we ld pipe sizes 2
inches (50 mm) and below.
C. Fittings:
1. Welded joints: ASTM A234, steel, Grade B, or ASME B 16.9, same
schedule as adjoining pipe.
2. Threaded joints: ASTM A47 or A197, malleable iron, or ASME B16.3, 300
psi (2050 kPa) class.
3. Socket welded joints: ASME B16.11, forged steel, 20 00 psi (13,800
kPa) class.
D. Unions (Except in Trenches) are allowed on piping 2 inches (50 mm) and
under, 300 psi (2050 kPa) malleable iron or steel.
33 63 00-14
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
E. Flanges: Weld neck ASME B16.5 or ASTM A105, forged steel, 150 psi (1025
kPa).
2.5 EXPANSION LOOPS AND BENDS
A. Stresses: Less than the maximum allowable stress in the Power Piping
Code (ASME B31.1). Submit shop drawings and stress and anchor force
calculations for all loops and bends. Show location s of all anchors,
guides and supports. Base calculations on 150 psi ( 1000 kPa) and 366 deg
F (185 deg C) for steam line loops and bends and 50 psi (345 kPa) and
310 deg F (154 deg C) for condensate return line lo ops and bends. Base
calculations on actual pressures and temperatures i f they are higher
than those listed above.
2.6 VALVES
A. Gate Valves (ASTM A126):
1. Type 106 shall have:
a. Forged steel body, rated for 300 psi (2050 kPa) at 420 deg F (216
deg C) minimum Class 600 psi (4130 kPa) or Class 80 0 psi (5500
kPa), hardened stainless steel or satellite wedge a nd seats,
threaded ends, OS&Y, rising stem, bolted bonnet.
B. Globe Valves (ASTM A126):
1. Type 204:
a. ASTM B61, bronze body, rated for 200 psi (1375 kPa) saturated
steam, 400 psi (2750 kPa) WOG, hardened stainless s teel disc and
seat, threaded ends, rising stem, union bonnet, ren ewable seat
rings.
C. Check valves (ASTM A126):
1. Type 404 shall have:
a. Bronze body, swing-type, rated for 200 psi (1375 kP a) saturated
steam, 400 psi (2750 kPa) WOG, bronze disc, threade d ends,
regrinding disc.
D. Butterfly valves (ASTM A126):
1. Type 601 shall have:
a. Ductile iron body, wafer style, rated for 125 psi ( 850 kPa), 212
deg F (100 deg C), bronze disc, stainless steel ste m, EPDM liner,
EPDM stem seal and body seal, neck extending beyond pipe
insulation, geared handwheel operator for valves 4 inch (100 mm)
33 63 00-15
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
pipe size and larger, ratchet handle operator for s maller pipe
sizes.
2. Type 602:
a. Triple-offset, lug or flanged type, carbon steel bo dy, steam
service, rated for 150 psi (1025 kPa) at 500 deg F (260 deg C),
stainless steel nitrided disc, stellite seat, stain less steel
shaft, stainless steel/graphite-laminated seal ring , neck
extending beyond pipe insulation, geared handwheel operator for
valves 4 inch (100 mm) pipe size and larger, ratche t handle
operator for smaller pipe size valves.
E. Valve Applications (Steam Lines):
1. Gate valves, 2 inches (50 mm) and under: Type 106.
2. Globe valves, 2 inches (50 mm) and under: Type 204.
3. Butterfly valves, 2-1/2” and larger: Type 602.
F. Valve Applications (Condensate Lines):
1. Gate valves, 2 inches (50 mm) and under: Type 106.
2. Check valves, 2 inches (50 mm) and under: Type 404.
3. Butterfly valves, all sizes: Type 601.
2.7 STEAM TRAPS
A. Apply at steam line drip points.
B. Construct inverted bucket type with thermostatic ve nt in bucket. Each
type furnished by a single manufacturer. Select the traps for pressures
and capacities as shown or required. Fixed orifice or venturi type traps
are not permitted.
C. Traps: stainless steel bodies. Construction shall p ermit ease of removal
and servicing working parts without disturbing conn ecting piping.
Include stainless steel floats, hardened chrome ste el valves, stainless
steel mechanisms and bi-metallic air vent on invert ed bucket traps.
D. All traps shall include ports for future installati on of monitoring
devices. To facilitate future removal of plugs, rem ove plugs, install
Teflon tape on the threads, and reinstall the plugs .
E. Label each trap at the factory with an identificati on number keyed to
the contract drawings. Label shall be a metal tag p ermanently attached
to the trap.
33 63 00-16
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
2.8 STRAINERS, Y TYPE
A. Provide as shown on steam and condensate piping sys tems.
B. Include open end removable cylindrical screen and t hreaded blow off
connection.
C. For steam service up to 150 psi (1025 kPa) and at d rip traps, strainer
shall be rated for minimum 150 psi (1025 kPa) satur ated steam; rated for
150 psi (1025 kPa), flanged ends, cast steel, for p ipe sizes above 2
inches (50 mm). Use cast iron or bronze, rated for 250 psi (1725 kPa)
saturated steam, threaded ends, for pipe sizes 2 in ches (50 mm) and
under.
D. For condensate service, strainer shall be rated for 125 psi (850 kPa)
saturated steam, 175 psi (1200 kPa) WOG. Provide 12 5 psi (850 kPa),
flanged ends, cast iron, for pipe sizes above 2 inc hes (50 mm). Provide
cast iron or bronze, threaded ends, for pipe sizes 2 inches (50 mm) and
under.
E. Strainer screen shall be stainless steel, with a fr ee area not less than
2 1/2 times flow area of pipe. Diameter of openings shall be 0.05 inch
(1.3 mm) or less on steam service and 0.06 inch (1. 5 mm) or less on
water service.
F. Include gate type valve and quick couple hose conne ction on all blowoff
connections.
2.9 PIPE HANGERS AND SUPPORTS
A. Requirements: MSS SP 58 and ASME B31.1.
B. Applies to all piping not in factory-fabricated dir ect-buried system.
All systems shall be completely supported. Arrange supports so that all
loads due to weight, thermal expansion, seismic sho ck (if applicable),
and pressure are transferred from the support syste m to the structure.
The design and location of supports shall at all ti mes prevent excessive
forces, moments, and stresses from being imposed on the equipment,
structure, supported system, and supports. Heated s ystems generally
require resilient or roller/slide supports.
C. Manufacturer Certification: Factory built products of a manufacturer
whose principle business is pipe supports for 20 ye ars. All components
must have published load ratings. For concrete trenches, non-factory
built products that comply with details may be utilized.
33 63 00-17
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
D. Drawings:
1. Types, sizes, locations, and spacing of all hangers and supports.
2. Roller or slider supports for all horizontal steam and condensate
piping.
3. Special supports including anchors, guides and brac es.
4. If equipment and piping arrangement differs from th at shown on the
drawings, support locations and types shall be revi sed at no cost to
the government.
5. Supports to permit removal of valves and strainers from pipelines
without disturbing supports.
6. Roller hangers and sliding supports on all systems subject to
horizontal movement.
7. If vertical angle of hanger rod exceeds four degree s, rollers or
sliders are required.
8. Loads for all supports. On systems utilizing variab le spring
supports; show the loads at each support by calcula ting the forces
and moments throughout the system.
9. Individual drawing for each hanger assembly showing all components,
sizes, calculated loadings. Provide identification tags, on each
hanger part, keyed to the layout drawings.
E. Components:
1. Roller supports: MSS SP 58, Type 41, 43 and 46. Pro vide vertical
adjustment for Type 41 with threaded studs and nuts adjacent to the
roller.
F. Clevis supports: MSS SP 58, Type 1.
G. Wall brackets: MSS SP 58, Type 33.
H. Pipe stands: MSS SP 58, Type 38.
I. Trapeze supports: MSS SP 58, may be used where pipe s are close together
and parallel, structural steel channels or angles. Bolt roller supports
to steel to support piping subject to horizontal th ermal expansion.
Attach other piping with “U” bolts.
J. Pipe covering protection saddles: MSS SP 58, Type 3 9. Provide at all
support points on insulated pipe except where Type 3 pipe clamp is
provided.
K. Sliding supports: MSS SP 58, Type 35. Welded steel attachments to pipe
and structure with Teflon or graphite sliding surfa ces bonded to the
33 63 00-18
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
attachments. Provide steel guides, except at expans ion bends, to prevent
lateral movement of the pipe.
L. Pipe racks and miscellaneous supports: ASTM A36, st ructural steel
shapes. Manufactured strut systems are acceptable i f they have the
required load carrying ability.
M. Supports, including all structural steel, in trench es and manholes: Hot-
dip galvanized.
N. Fiberglass Insulation:
1. Preformed piping insulation: ASTM C547, 450 deg F ( 230 deg C).
2. Fitting insulation: ASTM C547, 450 deg F (230 deg C ), with polyvinyl
chloride, Type II Grade GU, and Type III, premolded fitted covering
0.020 inches (0.5 mm) thick.
O. Insulating and finishing cements: ASTM C449, as rec ommended by the
manufacturer for the type of insulation system and service conditions.
P. Insulation bands: ASTM A167, minimum of 1/2 inch (1 2 mm) wide by 0.015
inch (0.4 mm) thick stainless steel.
Q. Aluminum jackets: Minimum of 0.016 inch (0.4 mm) th ick aluminum, 3003
alloy, H-14 temper, with locking longitudinal joint s. Jackets for
elbows, tees and other fittings shall be factory fa bricated to match
material and construction of the straight run jacke ts. Factory
fabricated stainless steel bands shall be furnished and installed on all
circumferential joints. Bands shall be 0.75 inch (2 0 mm) wide on 18 inch
(450 mm) centers. Bands shall be applied with manuf acturers recommended
sealant. Entire system shall be watertight.
R. Service jackets: ASTM C1136, white kraft bonded to 0.001 inch (0.025 mm)
thick aluminum foil, fiberglass reinforced, pressur e sensitive adhesive
closure, beach puncture tested to 50 units, suitabl e for painting
without sizing. Jackets shall have a minimum 1-1/2 inch (40 mm) lap on
longitudinal joints and not less than 4 inch (100 m m) butt strips on end
joints. Butt strip material shall be same as the ja cket. Lap and butt
strips may be self-sealing type with factory-applie d pressure sensitive
adhesive.
S. Pipe covering protection saddles: MSS SP 58, Type 3 9 at all hanger
points except where Type 3 pipe clamps are provided .
33 63 00-19
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
2.10 BURIED UTILITY WARNING TAPE
A. Tape: 0.004 inch (0.1 mm) thick, 6 inches (150 mm) wide, yellow
polyethylene with a ferrous metallic core, acid and alkali-resistant and
shall have a minimum strength of 1750 psi (12,000 k Pa) lengthwise and
1500 psi (10,300 kPa) crosswise with an elongation factor of 350
percent. Provide bold black letters on the tape ide ntifying the type of
system. Tape color and lettering shall be unaffecte d by moisture and
other substances contained in the backfill material .
PART 3 - EXECUTION
3.1 GENERAL
A. If the carrier pipe insulation has failed (disinteg rated) in an existing
buried piping system, but the system is otherwise s ound, there is an
alternative to total replacement of injecting foam insulation into the
existing system from above grade.
B. Connect new work to existing work in a neat and wor kmanlike manner.
Where an existing structure must be cut or existing utilities interfere,
such obstruction shall be bypassed, removed, replac ed or relocated,
patched and repaired. Piping connections shall be m ade only in manholes,
tunnels or buildings.
C. Coordinate the location of all items of equipment a nd work of all
trades. Maintain operability and maintainability of the equipment and
systems. The contractor at his cost shall perform a ny relocation of
equipment or systems to comply with the requirement of operability and
maintainability.
D. Unless otherwise shown on drawings, steam lines sha ll be graded downward
not less than 2 inches in 40 feet (50 mm in 12 mete rs) in direction of
the flow. Provide eccentric reducing fittings on st eam mains and
branches, (except on vertical piping). Install said fittings to maintain
continuity of grade in bottom of pipeline. Provide risers with drip
pockets and steam traps on steam lines where space restrictions prevent
continuous grading. All steam traps must be located in manholes or
tunnels.
3.2 DEMOLITION
A. Perform work in accordance with requirements for ph asing and the
Drawings.
33 63 00-20
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
B. Completely remove all pipe, valves, fittings, insul ation, and all
hangers including the connection to the structure a nd any fastenings.
C. Seal all openings in manhole or building walls afte r removal of piping.
D. All material and equipment removed shall become the property of the
Contractor and shall be removed from Government pro perty and shall not
be stored in operating areas.
E. All flame cutting shall be performed with adequate fire protection
facilities available as required by safety codes an d Contracting
Officer’s Representative.
3.3 PIPING APPLICATION
A. HP Steam Piping:
1. NPS 2 (DN 50) and Smaller: Schedule 40, Type S, Gra de B, steel pipe;
Class 125 cast-iron fittings; and threaded joints.
2. NPS 2-1/2 through NPS 12 (DN 65 through DN 300): Sc hedule 40, Type
E, Grade B, steel pipe; Class 150 wrought-steel fit tings, flanges,
and flange fittings; and welded and flanged joints.
B. Condensate Piping:
1. NPS 2 (DN 50) and smaller shall be the following:
a. Schedule 80, Type S, Grade B, steel pipe; Class 125 cast-iron
fittings; and threaded joints.
b. RTRP and RTRF with adhesive or flanged joints.
2. NPS 2-1/2 (DN 65) and larger shall be the following :
a. Schedule 80, Type E, Grade B, steel pipe; Class 150 wrought-steel
fittings, flanges, and flange fittings; and welded and flanged
joints.
b. RTRP and RTRF with adhesive or flanged joints.
3.4 PIPING INSTALLATION
A. Drawings indicate general location and arrangement of piping systems.
Install piping insulation as indicated.
B. Standing water in the bottom of trench: Remove all water.
C. Pipe Bedding: Minimum 6 inch (150 mm) layer of sand .
D. Clearance: Minimum 6 inch (150 mm) clearance betwee n the pipes.
E. Testing: Do not insulate piping or backfill piping trench until field
quality-control testing has been completed and resu lts approved.
F. Grade:
33 63 00-21
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
1. Install condensate piping at uniform grade of 0.4 p ercent downward in
direction of flow.
2. Install piping at uniform grade of 0.2 percent down ward in direction
of flow or as indicated on the Drawings.
G. Drain Valves and Air Vents: In conduits, install at low points and air
vents at high points.
H. Install components with pressure rating equal to or greater than system
operating pressure.
I. Install piping free of sags and bends.
J. Install fittings for changes in direction and branc h connections.
K. Secure anchors with concrete thrust blocks.
L. Connect to steam and condensate piping where it pas ses through the
building wall.
3.5 DRAIN VALVES AND VENT VALVES
A. Provide 1-1/2 inch (40 mm) minimum pipe size drain valves on condensate
return carrier pipes at all low points in manholes. Provide 1 inch (25
mm) minimum air vent valves in manholes at all high points in condensate
return carrier piping.
3.6 PIPE SUPPORT INSTALLATION (IN TRENCHES, TUNNELS, MA NHOLES)
A. Coordinate support locations prior to erection of p iping. Layout
drawings must be available at the site during const ruction.
B. Upper Attachments to Structure:
1. New reinforced concrete construction shall have con crete inserts.
2. For existing reinforced concrete construction, uppe r attachment shall
be welded or clamped to steel clip angles (or other construction
shown on the drawings) that are expansion bolted to the concrete.
Expansion bolting shall be located so that loads pl ace bolts in
shear.
3. For steel deck and structural framing, upper attach ments shall be
welded or clamped to structural steel members.
C. In existing concrete construction, expansion fasten ers may be used for
hanger loads up to one third the manufacturer's rat ed strength of the
expansion fastener. Power set fasteners may be used for loads up to one
fourth of rated load. When greater hanger loads are encountered,
33 63 00-22
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
additional fasteners may be used and interconnected with steel members
combining to support the hanger.
D. Special Supports:
1. Secure horizontal pipes where necessary to prevent vibration or
excess sway.
2. Where hangers cannot be adequately secured as speci fied, make special
provisions for hanging and supporting pipe as appro ved by the
Contracting Officer’s Representative.
3. Do not attach pipe supports, hangers, clamps or anc hors to equipment
unless specified for that equipment or unless the C ontracting
Officer’s Representative gives written permission.
E. Locate spring hangar units within 1 foot (300 mm) o f the pipe
attachment, except in locations where spring assemb lies interfere with
pipe insulation.
G. Minimum Clearances in Tunnels and Trenches:
1. Floor to bottom of pipe support beam: 2 inches (50 mm)
2. Floor to bottom of pipe insulation jacket: 6 inches (150 mm)
3. Wall to side of pipe insulation jacket: 3 inches (7 5 mm)
4. Ceiling to top of pipe insulation jacket: 1 inch (2 5 mm)
3.7 PAINTING EXPOSED STEEL SURFACES IN MANHOLES, TUNNELS AND CONCRETE SHALLOW
TRENCHES
A. For manholes and walk-through tunnels, provide surf ace cleaning and
preparation and apply prime coat of rust resistant metal primer.
B. For concrete shallow trenches, provide surface clea ning and preparation,
apply primer and finish coat of zinc-rich paint.
3.8 DIRECT-BURIED SYSTEM INSTALLATION
A. The Contractor shall oversee the deliver, store, in stall and test the
system as per manufacturer’s recommendations. All w ork shall be in
strict accordance with the requirements specified b y the manufacturer.
Printed instructions must be available on site prio r to delivery of
system components. Any changes required to the desi gn and layout of the
system due to site conditions must be approved in w riting by the
Contracting Officer’s Representative. All branch pi ping connections,
valves and drip traps must be located within manhol es.
33 63 00-23
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
B. Excavation, Trenching, and Backfilling: Perform all excavation,
trenching, and backfilling as required by the syste m manufacturer’s
design. Beach sand or any sand with large amounts o f chlorides is not
permitted. Place system on a 6 inch (150 mm) thick sand bed and backfill
on all sides with 6 inch (150 mm) thick sand as mea sured from outside
the carrier pipe/insulation. Foundation for system must be firm and
stable. Foundation and backfill must be free from r ocks. Concrete anchor
blocks must be installed in undisturbed earth. Back filling must not
commence until elevations have been surveyed and ac cepted and system has
been satisfactorily pressure tested including testi ng of carrier pipes
welds and air testing of casings.
C. Maintain constant slope of carrier pipes as shown o r specified. Prior to
backfilling over the top of the casing, but after r emoval of temporary
supports, Contractor shall measure and record eleva tions of top of
casing in the trench. Elevations shall be taken at every field joint,
1/3 points along each pipe section, and at tops of elbows. These
measurements shall be checked against contract draw ings and shall
confirm that the conduit system has been installed to the elevations
shown on the contract drawings unless approved by t he Contracting
Officer’s Representative. Slope shall be uniform wi thin 0.1 percent.
Measurements shall be recorded by the Contractor, i ncluded in the direct
buried system manufacturer representative’s daily r eport, and given to
the Contracting Officer’s Representative prior to c overing the top of
the casing with backfill.
D. Provide cathodic protection for all steel casing sy stems and all buried
exposed metal. Provide dielectric pipe flanges and unions and isolation
devices at all points necessary. Provide test stati ons at grade on each
section of the piping system. Isolation flanges and unions shall be
rated for the carrier pipe service temperature and pressure.
E. Remove all dirt, scale, and other foreign matter fr om inside the piping
by use of a pipe swab or pipe “pig” before connecti ng pipe sections,
valves, or fittings.
F. Sections of system that have been fully or partiall y submerged in water
must be replaced. Moisture content of insulation du ring installation
shall not exceed five percent by weight.
G. At each casing termination (end plate) in buildings and manholes, plug
the casing drain openings with brass plugs and exte nd 1 inch pipe size
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
33 63 00-24
galvanized vent pipes (ASTM A53) from the casing ve nts through the tops
of the manholes or 1 foot (300 mm) above the condui t in buildings.
Terminate the outside vents in 180-degree bends.
H. Provide reports to the Contracting Officer’s Repres entative that
include:
1. Daily written report: Prepared daily and signed by the Contractor.
Submit the original report to the Contracting Offic er’s
Representative on the same day it is prepared. Prov ide one set of
field pictures of work daily.
2. Report Contents: State whether or not the condition and quality of
the materials used and the delivery, storage, insta llation and
testing of the system are in accordance with the ma nufacturer’s
recommendations, changes to drawings and specificat ions, any
corrective action that was taken of the system, ide ntify any
conditions that could result in an unsatisfactory i nstallation.
3. Report Certification: Daily reports are to be revie wed, signed and
sealed by the Professional Engineer responsible for the system
installation.
4. Report Submittals and Stop Order: Daily reports sha ll be submitted
with the payment requests. All work must stop if da ily reports are
not furnished and requests for payments shall be de nied if the daily
reports are not furnished.
5. Certification of Compliance: Upon completion of the work and 30 days
prior to final acceptance, deliver to Contracting O fficer’s
Representative a notarized Certificate of Complianc e signed by
principal officers of Contractor, stating that the installation is
satisfactory and in accordance with plans, specific ations, and
manufacturer’s instructions.
6. The Contractor shall retain copies of all the daily reports and the
Certificate of Compliance for 5 years after final a cceptance of the
system by the Government.
I. Sections of system that have been fully or partiall y submerged in water
must be replaced. Moisture content of insulation du ring installation
shall not exceed five percent by weight.
J. At each casing termination (end plate) in buildings and manholes, plug
the casing drain openings with brass plugs and exte nd 1 inch pipe size
ASTM A53 galvanized vent pipes from the casing vent s through the tops of
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
33 63 00-25
the manholes or 1 foot (300 mm) above the conduit i n buildings.
Terminate the outside vents in 180-degree bends.
3.9 JOINT CONSTRUCTION
A. Ream ends of pipes and tubes and remove burrs. Beve l plain ends of steel
pipe.
B. Remove scale, slag, dirt, and debris from inside an d outside of pipe and
fittings before assembly.
C. Threaded joints: ASME B1.20.1, tapered pipe threads . Cut threads full
and clean using sharp dies. Ream threaded pipe ends to remove burrs and
restore full ID. Join pipe fittings and valves as f ollows:
1. Apply appropriate tape or thread compound to extern al pipe threads
unless dry seal threading is specified. Joints made with oil and
graphite pipe joint compound shall have compound ap plied to male
threads only.
2. Do not use pipe or pipe fittings with threads that are corroded or
damaged. Do not use pipe sections that have cracked or open welds.
3. Pipe threads shall be cut to give proper engagement in threaded
fittings. Clean pipe and fittings before installati on and ream pipe
after cutting threads. Threaded pipe shall have cle an-cut threads;
dull or damaged pipe dies shall not be used.
D. Construct welded joints: AWS D10.12, using qualifie d processes and
welding operators according to "Quality Assurance" Article. Branch
connections shall be made with either welding tees or welding outlet
fittings. Welding outlet fittings shall be forged, integrally reinforced
to provide 100 percent pipe strength, beveled for f ull penetration
welding and funneled at inlet for full fluid flow.
E. Flanged joints: Select gasket material, size, type, and thickness for
service application. Install gasket concentrically positioned. Use
suitable lubricants on bolt threads. Gaskets and bo lting shall be
applied in accordance with the recommendations of t he gasket
manufacturer and bolting standards of ASME B31.1. S trains shall be
evenly applied without overstress of bolts. Gaskets shall cover entire
area of mating faces of flanges.
F. Conduit piping joints shall be assembled in section s and finished with
pourable or split insulation, exterior jacket sleev e, and apply shrink-
wrap seals.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
33 63 00-26
G. All pipe intersections and changes in direction sha ll be made with
factory-built-reinforced fittings. Field-fabricated fittings and miters
are not permitted.
3.10 INSTALLATION – VALVES
A. Do not locate valve stems below the horizontal cent erline of the pipe.
B. Locate valves to permit access for operation, maint enance, and
replacement.
C. Provide 3/4 inch (19 mm) globe-valved warm-up bypas ses at all steam gate
and butterfly valves 3 inch (80 mm) pipe size and l arger.
D. Provide 3/4 inch (19 mm) gate drains at each side o f steam gate and
butterfly valves where condensate could collect, du e to the slope of the
pipeline, when the main valve is shut.
3.11 THERMAL INSULATION
A. Steam, condensate and drip return piping, other tha n in pre-engineered
direct buried systems, shall be insulated as follow s:
1. Piping in concrete trenches and manholes: Insulated with fiberglass
and aluminum jacket.
2. Exposed piping in walk through tunnels: Insulated w ith calcium
silicate, fiberglass, or cellular glass pipe insula tion, all service
jacket. Condensate return piping may be insulated w ith rigid cellular
phenolic, all service jacket.
3. Piping in manholes: Insulated with calcium silicate or cellular glass
pipe insulation, glass cloth or aluminum jacket.
4. Minimum Insulation Thickness: Insulation thicknesse s given in Table 5
and 6 are minimum nominal thickness.
TABLE 5 Minimum Pipe Insulation Thickness inches (mm)
For Steam 16 to 250 psi (110 to 1724 kPa) gage Nominal Pipe
Diameter inches (mm)
MPT-PC MPT- PF
Delta Thermo-12 Super Caltemp
Foamglas
1 (25) 2 (50) 2- 1/2 (63) 4 (100) 4- 1/2 (110) 1- 1/2 (40) 2 (50) 2- 1/2 (63) 4 (100) 4- 1/2 (110)
2 (50) 2- 1/2 (63) 3- 1/2 (85) 4- 1/2 (110) 5 (125) 2- 1/2 (65) 2- 1/2 (63) 3- 1/2 (85) 4- 1/2 (110) 5 (125)
3 (80) 3 (75) 4 (100) 5 (125) 6 (150) 4 (100) 3 (75) 4 (100) 5 (125) 6 (150)
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
33 63 00-27
TABLE 6
Minimum Pipe Insulation Thickness inches (mm) For Steam less than 16 psi (110 kPa) gage, Condensate Return
Nominal Pipe Diameter
inch es (mm)
MPT-PC MPT- PF
Delta Foamglas Thermo-12
Super Caltemp
Insul-phen
1 (25) and under
1-1/2 (35) 2 (50) 3 (75) 1 (25)
1- 1/2 (40) 1- 1/2 (35) 2 (50) 3 (75) 1 (25) 2 (50) 1- 1/2 (35) 2 (50) 3 (75) 1 (25)
Parts not to be insulated are:
a. Threaded valves
b. Steam traps
c. Check valves
d. Unions
e. Threaded strainers
f. Strainer basket removal cover and bolting
g. Dielectric flanges and unions
h. Expansion joints
i. Flexible connectors
j. Ball joints except piping between joints
5. Installation of insulation:
a. Pressure Tests: Complete all pressure tests before installing.
b. Insulation material: New, clean, dry and stored in a clean dry
environment; jacketing materials to be clean and un marred; store
adhesives in original containers. Materials shall n ot have
exceeded the predicted shelf life as set by manufac turer.
c. Identify all materials incorporated in the job on m anufacturer’s
container by name, type and description.
d. Apply materials on clean, dry surfaces from which a ll dirt, loose
scale, construction debris has been removed by wire brushing.
e. The installation shall be neat, thermally and struc turally tight
without sag, neatly finished at all hanger or other penetrations
and shall provide a smooth finished surface primed as required to
receive specified painting.
f. Do not use scrap insulation. Repair any work damage d by welding,
burning, compressing due to concentrated constructi on loads.
g. Apply pipe covering protection saddles, MSS SP 58, Type 39, at all
hanger points. Fill space between saddle and piping with high
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
33 63 00-28
density insulation, thoroughly packed. Terminate ja cket clear of
saddle bearing area.
h. Insulation and jacket shall terminate hard and tigh t at all anchor
points.
i. Insulation termination at piping facilities not to be insulated
shall stop short, and be finished with 45 degree ch amfered section
of insulating and finishing cement, and covered wit h jacket.
j. Flanged fittings and valves shall be insulated with sections of
pipe insulation cut, fitted and arranged neatly, an d firmly wired
in place. Insulating cement shall fill all cracks, voids and outer
surface for covering with glass cloth. Insulation o f valve bonnet
shall terminate on valve side of bonnet flange to p ermit valve
repair.
k. Fiberglass insulated piping systems fittings over 2 inches (50 mm)
shall be insulated with specified molded pipe fitti ng insulation
or compressed blanket, finished with specified insu lating and
finishing cements and covered with specified PVC fi tting jacket.
On sizes 2 inches (50 mm) and under apply insulatin g and finishing
cements and cover with PVC fitting jacket.
3.12 WELDING (ASME B31.1 AND AWA B2.1-B)
A. The Contractor is entirely responsible for the qual ity of the welding
and shall:
1. Conduct tests of the welding procedures used on the project, verify
the suitability of the procedures used, verify that the welds made
will meet the required tests, and also verify that the welding
operators have the ability to make sound welds unde r standard
conditions.
2. Perform all welding operations required for constru ction and
installation of the distribution system.
B. Welder Qualifications: All welders shall be qualifi ed as per ASME B31.1
and AWS B2.1-B2.1M-BMG.
C. Field bevels and shop bevels: Done by mechanical me ans or by flame
cutting. Where beveling is done by flame cutting, s urfaces shall be
thoroughly cleaned of scale and oxidation just prio r to welding. Conform
to specified standards.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
33 63 00-29
D. Utilize split welding rings or approved alternate m ethod for field
joints on all carrier pipes above 2 inches (50 mm) to assure proper
alignment, complete weld penetration, and preventio n of weld spatter
reaching the interior of the pipe. Make field joint s 2 inches (50 mm)
and smaller with welding sockets.
E. Piping shall not be split, bent, flattened, or othe rwise damaged either
before, during, or after installation. Where the pi pe temperature falls
to 32 deg F (0 deg C) or lower, the pipe shall be h eated to
approximately 100 deg F (38 deg C) for a distance o f 1 foot (300 mm) on
each side of the weld before welding, and the weld shall be finished
before the pipe cools to 32 deg F (0 deg C).
F. Replace and reinspect defective welds. Repairing de fective welds by
adding weld material over the defect or by peening will not be
permitted. Welders responsible for defective welds must be requalified.
G. Electrodes shall be stored in a dry heated area, an d be kept free of
moisture and dampness during fabrication operations . Discard electrodes
that have lost part of their coating.
H. An approved independent testing firm regularly enga ged in radiographic
testing shall perform radiographic examination of a ll field welds in
steam pits, buildings and in walk-through tunnels, in accordance with
ASME B31.1. Furnish a set of films or pictures show ing each weld
inspected, a report evaluating the quality of each weld, and a location
plan showing the physical location where each weld is to be found in the
completed project, prior to installing conduit fiel d joints, trench
covers, backfilling and testing. All radiographs sh all be reviewed and
interpreted by an ASNT Certified Level III radiogra pher, employed by the
testing firm, who shall sign the reading report. Th e Contracting
Officer’s Representative reserves the right to revi ew all inspection
records, and if any welds inspected are found unacc eptable they shall be
removed, re-weld, and radiographically reexamined a t no cost to the
Government.
I. Retain a certified manufacturer field technician to observe and
supervise all field joints, conduit joints and pipe welded within direct
buried piping system. Submit manufacturer’s field t echnician
qualification to Owner for approval prior to test j oint work.
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
33 63 00-30
3.13 CLEANING OF PIPING:
A. Clean pipe and fittings inside and outside before a nd after assembly.
Remove all dirt, scale, and other foreign matter fr om inside the piping
by use of a pipe swab or pipe “pig” before connecti ng pipe sections,
valves, equipment or fittings.
3.14 IDENTIFICATION
A. Install continuous plastic underground warning tape s during back filling
of trenches for underground steam and condensate di stribution piping.
Locate tapes 12 inches (300 mm) below finished grad e, directly over
piping.
3.15 IDENTIFICATION SIGNS
A. Valves: Provide laminated plastic signs, with engra ved lettering not
less than 3/16 inch (5 mm) high, on all isolating v alves on steam and
condensate return system, identifying building or a rea served. Attach to
the valves with corrosion-resistant chains.
B. Pipes: Label service of all pipes in manholes and w alk-thru tunnels.
3.16 FIELD QUALITY CONTROL
A. Demonstrate leak-tightness of all piping systems by performing
operational tests. All labor, material and test ins truments must be
furnished by the Contractor. All instruments must b e approved by the
Contracting Officer’s Representative.
B. Provide a test field joint section. Field joint is intended to be a
learning joint. Joint shall be joined, completely t ested and jacketed
in the field with a certified manufacturer’s field technician observing
and instructing the process. Permanent field joints shall not be
attempted until the manufacturer’s technician appro ves the test joint.
C. Retain a certified manufacturer field technician to observe and
supervise all field joints. Submit manufacturer’s f ield technician
qualification to Owner for approval prior to test j oint work.
D. No field joint shall be made without the factory te chnician present.
Field joints that do not meet the manufacturer’s te chnician’s approval
shall be remade until they are satisfactory. Additi onal labor,
materials and manufacturer’s technician time requir ed for additional
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
33 63 00-31
attempts to make a satisfactory joint shall be prov ided with no
additional cost to Owner.
E. Pressure test direct-buried systems (outer conduit sleeve and inner
sleeve field joint) in conformance with requirement s stated in this
specification and in printed instructions for the s ystem supplied by the
manufacturer.
F. Holiday testing of direct-buried system steel casin gs: Test entire
surface of casings for faults in coating after inst allation in trench
prior to backfilling. Use test method and voltage r ecommended by coating
manufacturer. Repair any holidays found and retest. System shall not be
backfilled until all holidays are eliminated.
G. Before conducting steam system operating test, remo ve steam trap
elements or use bypass connections around traps; th en flush lines with
high pressure water until discharge shows no foreig n matter to the
satisfaction of Contracting Officer’s Representativ e.
H. Steam and condensate carrier piping shall be tested as follows:
1. Use Phased Array Ultrasonic (UT) test to each carri er (service) pipe
weld proceeding with direct-buried insulation and j acketing joint
closure work once test has been approved.
2. Weld test criteria shall be in accordance to ASME B 31.1 current
version.
3. 100% test of all welded joints shall be non-destruc tive tested.
4. Failed welds shall be ground out, re-welded and tes ted welds are
expected. The repair and re-testing shall have no a dditional cost to
the project.
5. After completion of satisfactory test, replace all elements that have
been removed prior to testing.
I. NACE-accredited corrosion specialist shall test cat hodic protection
systems and demonstrate proper operation and protec tion in accordance
with the recommendations and criteria in NACE SP016 9.
J. Steam and condensate conduit shall be tested as fol lows:
1. Following insulation install of carrier pipe, insta ll outer conduit
sleeve. This sleeve shall be welded in place and pr essure tested
with 15 lb compressed air and soap solution bubble check for leaks.
2. Once sleeve is tested and passed the sleeve and wel d shall be cleaned
and painted with two coats of high zinc content pai nt.
K. Field joint shall be tested as follows:
33 63 00-32
Milwaukee VAMC Upgrade and Replace Building 123 Steam Line Piping and Insulation
February 15, 2017 Bid Set Submission
Project No. 695-17-103
1. No test required.
L. Deficiencies discovered shall be corrected at the C ontractor's expense,
to satisfaction of Contracting Officer’s Representa tive. Major
deficiencies or failure to correct deficiencies, to the satisfaction of
the Contracting Officer’s Representative, may be co nsidered cause for
rejecting the entire installation.
M. Contractor will engage a qualified testing agency t o perform tests and
inspections of all pipe welds within steam pit and buildings.
N. Prepare test and inspection reports.
---- E N D ---