Preparation of detailed design, bidding documents and resettlement action plan for upgrading of Baku- Shamakhi Road Final Abbreviated Resettlement Action Plan, Section 1, km 44+600 – 67+500 October 2012 Prepared for Azerroadservice OJSC of the Ministry of Transport SFG1634 V1
Transcript
Page 1: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Preparation of detailed design, bidding documents and resettlement action plan for upgrading of Baku-Shamakhi RoadFinal Abbreviated Resettlement Action Plan, Section 1, km 44+600 – 67+500October 2012

Prepared for

Azerroadservice OJSC of the Ministry of Transport

SFG1634 V1

Page 2: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

URS Infrastructure & Environment UK LimitedScott House, Alençon Link, Basingstoke, RG21 7PP United Kingdom

Tel +44 (0) 1256 310200Fax +44 (0) 1256 310201

www.ursglobal.com

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

Revision Schedule

Final Abbreviated Resettlement Action PlanOctober 2012

Rev Date Details Prepared by Reviewed by Approved by

    11 April 2012 Draft Nilufar EgamberdiRAP Specialist

Ayse KudatRAP SpecialistTanya RomanenkoRAP Team Leader

Simon RobertsProject Manager

    31 May 2012 Final Tanya RomanenkoRAP Team Leader

          

          

    07 August 2012

Final rev 2 Tanya RomanenkoRAP Team Leader

Simon RobertsProject Manager

Martin EdgeProject Director

20 October 2012

Final rev 3 Tanya RomanenkoRAP Team Leader

Simon RobertsProject Manager

Martin EdgeProject Director

Page 3: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

Limitations

URS Infrastructure & Environment UK Limited (“URS”) has prepared this Report for the sole use of Azerroadservice OJSC of the Ministry of Transport (“Client”) in accordance with the Agreement under which our services were performed (Contract For Consultants’ Services; Azerbaijan Highway project II Additional Financing IBRD Loan No.7516AZ; Selection of widening alternatives, preparation of detailed design and bidding documents, resettlement action plan for upgrading of Baku-Shamakhy road, section of Baku-Shamakhy-Yevlakh; dated 03/12/2010). No other warranty, expressed or implied, is made as to the professional advice included in this Report or any other services provided by URS. This Report is confidential and may not be disclosed by the Client nor relied upon by any other party without the prior and express written agreement of URS.

The conclusions and recommendations contained in this Report are based upon information provided by others and upon the assumption that all relevant information has been provided by those parties from whom it has been requested and that such information is accurate. Information obtained by URS has not been independently verified by URS, unless otherwise stated in the Report.

The methodology adopted and the sources of information used by URS in providing its services are outlined in this Report. The work described in this Report was undertaken between November 2011 and April 2012 and is based on the conditions encountered and the information available during the said period of time. The scope of this Report and the services are accordingly factually limited by these circumstances.

Where assessments of works or costs identified in this Report are made, such assessments are based upon the information available at the time and where appropriate are subject to further investigations or information which may become available.

URS disclaim any undertaking or obligation to advise any person of any change in any matter affecting the Report, which may come or be brought to URS’ attention after the date of the Report.

Certain statements made in the Report that are not historical facts may constitute estimates, projections or other forward-looking statements and even though they are based on reasonable assumptions as of the date of the Report, such forward-looking statements by their nature involve risks and uncertainties that could cause actual results to differ materially from the results predicted. URS specifically does not guarantee or warrant any estimate or projections contained in this Report.

Where field investigations are carried out, these have been restricted to a level of detail required to meet the stated objectives of the services. The results of any measurements taken may vary spatially or with time and further confirmatory measurements should be made after any significant delay in issuing this Report.

Copyright

© This Report is the copyright of URS Infrastructure & Environment UK Limited. Any unauthorised reproduction or usage by any person other than the addressee is strictly prohibited.

Page 4: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

Table of Contents

1 Project Background..........................................82 RATIONALE FOR PREPARATION OF ABBREVIATED

RESETTLEMENT ACTION PLAN (ARAP)................93 OBJECTIVES AND METHODOLOGY OF THE

ABBREVIATED RESETTLEMENT ACTION PLAN (ARAP)...........................................................11

3.1 ARAP OBJECTIVES..........................................................................................113.2 ARAP METHODOLOGY....................................................................................11

4 CATEGORIES OF RESETTLEMENT AND LAND ACQUISITION IMPACTS...................................12

4.1 SUMMARY OF KEY IMPACTS.........................................................................124.2 UNAVOIDABLE IMPACTS................................................................................15

5 PROJECT AFFECTED AREA (PAA)......................166 PROJECT AFFECTED PEOPLE (PAPs).................177 LEGAL FRAMEWORK.......................................207.1 NATIONAL LEGAL FRAMEWORK...................................................................207.2 WORLD BANK OP 4.12....................................................................................217.3 GAP ANALYSIS BETWEEN AZERI LAWS AND REGULATIONS AND THE

WORLD BANK OP 4.12....................................................................................22

8 ELIGIBILITY CRITERIA AND COMPENSATION VALUATION....................................................24

8.1 IDENTIFICATION OF ELIGIBILITY...................................................................248.2 PRINCIPLES OF COMPENSATION.................................................................248.3 VALUATION AND COMPENSATION METHODOLOGY..................................258.3.1 COMPENSATION FOR LAND......................................................................................258.3.2 CROP COMPENSATION..............................................................................................258.3.3 FOR FRUIT TREES AND PERENNIAL CROPS...........................................................258.3.4 COMPENSATION FOR BUILDINGS AND STRUCTURES...........................................258.3.5 COMPENSATION FOR SACRED SITES......................................................................268.3.6 COMPENSATION FOR PHYSICAL RELOCATION......................................................268.3.7 COMPENSATION FOR SEVERE IMPACT...................................................................268.3.8 COMPENSATION FOR PEOPLE WITHOUT LEGAL LAND RIGHTS..........................268.3.9 COMPENSATION FOR LOST/ DISRUPTED INCOME................................................26

9 ENTITLEMENT MATRIX....................................28

Final ARAP km 44+600 to 67+500 October 2012

Page 5: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

10 IMPLEMENTATION PROCESS AND RESPONSIBILITIES..........................................29

10.1 PRINCIPLES OF LAND ACQUISITION AND RESETTLEMENT......................30

11 GRIEVANCE REDRESS MECHANISM..................3111.1 LINKING RESETTLEMENT IMPLEMENTATION TO CIVIL WORKS...............33

12 MONITORING & EVALUATION (M&E)................3412.1 INTERNAL PERFORMANCE MONITORING...................................................3412.2 EXTERNAL IMPACT MONITORING.................................................................34

13 PUBLIC CONSULTATION AND DISCLOSURE.......3614 ARAP IMPLEMENTATION ACTIVITIES TIMETABLE40Annex 1: Guiding Questions for Focus Group

Discussions....................................................41Annex 2: Questions for Semi-Structured Interviews. 43Annex 3 – Household Survey Questionnaire.............48Annex 4: Verification of the Centreline and ROW

against the Cadastral Mapping.......................56Annex 5: The Survey of this Potentially Affected Household57

Final ARAP km 44+600 to 67+500 October 2012

Page 6: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

EXECUTIVE SUMMARY

The Government of Azerbaijan (GoA) is implementing the Highway III Project (“the Project”) with financial support of the World Bank that will improve several segments of a highway to the west and south of city of Baku, the country’s capital. In particular, the Project will include improvement and rehabilitation of the existing Baku-Shamakhi road, which will be mostly limited to widening of the existing two lane road to a four lane road between Baku and Shamakhi over a distance of 71,4 km. The road is classified as Category II road with a right-of-way (ROW) of 60 meters, i.e. 30m either side of the centre-line.

It was decided that three section-specific Resettlement Action Plans (RAPs) – Section 1, 2 and 3 will assess section differentiated resettlement and land acquisition impacts and will be prepared prior to the commencement of civil works, thus providing compensation and rehabilitation measures for all Project-Affected Persons (PAPs), as defined by the World Bank OP 4.12, the guiding safeguard policy for this Project. Acquisition of land and other assets will take place only after all compensation and rehabilitation measures are defined in the relevant section specific RAPs.

This ARAP has been based on: (a) Resettlement Policy Framework (RPF) prepared by Scott Wilson in 2009; (b) household survey of affected households in 2 settlements adjacent to the ROW – Dzhangi and Dzheirankechmaz carried out in December 2011; (c) community consultations carried out Dzhangi and Dzheirankechmaz in December 2011; (d) cadastral mapping and inventory of affected assets undertaken in March 2012. In addition, data on unit prices of the land and other assets within the Project affected area was obtained from the Report on “The Survey on Market Price of Land along Baku-Shamakhi Highway” prepared by the World Bank team in February 2010.

All land along Section 1 is state owned, and the land requirements for the road widening and, therefore, the resettlement impacts are insignificant. Given that there is a requirement for a land take of state forest fund lands there will be losses of trees that have been estimated. The measures in relation to tree losses and cost estimates for implementation of these measures should be defined by the Environmental Management Plan.

The following structures fall within the new RoW, and mitigation measures of compensatory nature are considered by this ARAP, if appropriate:

km 46+510: there is a disused bakery workshop at 26.7 meter distance from the new centre-line that is not expected to be demolished, but access may need to be altered.

km 47+040: there is a residential house at 18 m distance from the new centre-line that potentially may need to be demolished, or access may need to be altered. The former, involving relocation, would seem to be a preferred option given safety considerations, and disturbance to the household during the construction and operation of the highway. As the land belongs to the state, the home owners would be asked to relocate themselves with compensation at full replacement cost1. Thus, upon received the compensation considered for constructions and trees by the affected household, they have requested to locate themselves in the public land based on the same conditions by the land status lost in the area of same household. These requests has been reviewed by the regional executive power which in turn stated possibility to comply with the request within the current conditions.

km 47+076: there is a stone wall fence at 20 m distance from the new centre-line. The fence belongs to the State Forest Authority and will need to be moved, and compensated at full replacement cost2.

1 Cost of construction materials and labour at market rates plus any transaction/registration costs.2 Cost of construction materials and labour at market rates..

Final ARAP km 44+600 to 67+500 October 2012

6

Page 7: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

km 48+040: there is a cafe at 29.46 m distance from the new centre-line. The café is not expected to be demolished, but access may need to be altered.

The key impacts including temporary impacts are

Temporary loss of access to the road and hence limited adverse impact on incomes derived from roadside petty trade;

Temporary loss of access to pastures without significant adverse income impacts; Temporary and minor disruption of social and community life resulted from temporary loss of

access to the road; Limited health and safety concerns.

The implementation of the ARAP will be led by the Land Acquisition Department (LAD) of the Azerroadservice OJSC (ARS) of the Ministry of Transport of Azerbaijan.

Final ARAP km 44+600 to 67+500 October 2012

7

Page 8: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

1 Project BackgroundThe Government of Azerbaijan (GoA) is implementing the Highway III Project (“the Project”) with financial support of the World Bank that will improve several segments of a highway to the west and south of Baku, the country’s capital. The Project will include improvement and rehabilitation of the existing Baku-Shamakhi road, and therefore will be mostly limited to widening of the existing two lane road to a four lane road between Baku and Shamakhi over a distance of 71,4 km. The road is classified as Category II road with a right-of-way (ROW) of 60 meters, i.e. 30 meters either side of the centre-line.

It was decided that three section-specific Resettlement Action Plans (RAPs) – Section 1, 2 and 3 will assess section-differentiated resettlement and land acquisition impacts and will be prepared prior to the commencement of civil works, thus providing compensation and rehabilitation measures for all Project-Affected Persons (PAPs), as defined by the World Bank OP 4.12, the guiding safeguard policy applied for this Project. Acquisition of land and other assets will take place only after all compensation and rehabilitation measures defined in the relevant section specific RAPs have been implemented.

Based on the OP 4.12, with regard to Section 1 that covers 44.6 km to 67.5 km of the Project, it was recommended that the Project resettlement land acquisition impacts will be guided by an Abbreviated Resettlement Action Plan (ARAP) as those impacts have been categorized as insignificant as the number of people to be displaced with a loss of assets or restriction of access to assets is less than 200 persons.

The ARAP has been designed to provide guidance and procedures to the Project to ensure its full compliance with the relevant laws and regulations of the Republic of Azerbaijan, and safeguard policies of the World Bank Group. The implementation of the ARAP will be led by the Land Acquisition Department (LAD) of the Azerroadservice OJSC (ARS) of the Ministry of Transport of Azerbaijan.

Final ARAP km 44+600 to 67+500 October 2012

8

Page 9: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

2 RATIONALE FOR PREPARATION OF ABBREVIATED RESETTLEMENT ACTION PLAN (ARAP)The Word Bank’s safeguard policy on Involuntary Resettlement (OP 4.12) applies whenever land or other property must be acquired for a Project, or its use is modified, and that acquisition or modification results in the loss of income, residence or access to resources, either permanent or temporary and whether the occupation is legal or illegal. OP 4.12 allows that “for projects in which the number of people to be displaced with a loss of assets or restriction of access to assets is small (less than 200 persons will experience resettlement effects), an abbreviated resettlement plan (ARAP) shall be prepared”.

Resettlement and land acquisition impacts of the Section 1 of Baku-Shamakhi Project (km 44.6 km to 67.5) meet these conditions. There are only two communities located along the Section 1 of the road – Dzhangi and Dzheirankechmez -where a total of 76 households or 456 persons live. No acquisition of private land is expected as the land to be taken is in public ownership, including State Forest Fund. Some of the households reside within 100 meters from the ROW. These will be affected indirectly by the Section 1.

At km 47+040 there is a residential house at 18 m distance from the new centre-line that will need to be demolished, and this would involve relocation. Thus, upon received the compensation considered for constructions and trees by the affected household, they have requested to locate themselves in the public land based on the same conditions by the land status lost in the area of same household. These requests has been reviewed by the regional executive power which in turn stated possibility to comply with the request within the current conditions.

As a result, this abbreviated resettlement action plan (ARAP) has been prepared in accordance with laws, regulations and guidelines for land acquisition and resettlement set by the Government of Azerbaijan and the World Bank’s Operational Policy O.P4.12. Where there is a gap between Azerbaijan legislation law and the World Bank policy, the World Bank policy shall apply in this ARAP.

OP 4.12 requires that a project formulates an ARAP that must cover the following minimum elements:

a. a census survey of displaced persons and valuation of assets;b. description of compensation and other resettlement assistance to be provided to all

project affected people (PAP);c. consultations with displaced people about acceptable alternatives;d. institutional responsibility for implementation and procedures for grievance redress;e. arrangements for monitoring and implementation; andf. a timetable and budget.

For this purpose, this ARAP covers the following issues:

Categories of PAPs and the identified potential Project resettlement and land acquisition impacts;

Eligibility criteria for defining various categories of the PAPs; Review of the pertinent Azerbaijan legal and regulatory framework and the World Bank

OP 4.12 requirements and measures to bridge any gaps between them; Assets valuation methodology; Organizational procedures for delivery of entitlements; Implementation mechanism; Grievance and Redress mechanisms;

Final ARAP km 44+600 to 67+500 October 2012

9

Page 10: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

Public Consultation and Disclosure Plan; Monitoring and Evaluation (M&E); and Entitlement Matrix.

Final ARAP km 44+600 to 67+500 October 2012

10

Page 11: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

3 OBJECTIVES AND METHODOLOGY OF THE ABBREVIATED RESETTLEMENT ACTION PLAN (ARAP)

3.1 ARAP OBJECTIVES

The key objective of this ARAP is to minimize land acquisition and resettlement impacts that will occur as a result of Section 1 road widening; and propose mitigation measures that address the specific needs of the affected population. The ARAP applies to all persons affected by Project (PAPs), namely Section 1 regardless of the severity of impact and whether or not they have legal title to land or any other productive assets. Particular consideration has been given to the needs of vulnerable groups within the project area, especially the poor, the landless, , women and children, unemployed youth.

The ARAP will ensure that the livelihoods of all PAPs are maintained or are restored at least to the pre-Project level via compensation and rehabilitation measures that will be developed according to the severity of impact. The compensation and entitlement package will be based on the requirements of the Government of Azerbaijan (GoA) and the World Bank for land acquisition and resettlement.

The objectives of the ARAP also include:

Raising awareness of the Project and its consequences among local communities and other stakeholders (local authorities, NGOs);

Estimating of the costs necessary for land acquisition and relocation; Prepare an implementation plan that sets out schedules and responsibilities set to

mitigate adverse effects of the Project related to resettlement and land acquisition; Defining of principles of a public consultations and disclosure plan; Provide a clear M&E framework to supervise the progress of the ARAP

implementation.

3.2 ARAP METHODOLOGY

Methodology used for this ARAP included collection, review and analysis of land acquisition and resettlement impacts via

a. review of legal framework applicable for Section 1;b. socio-economic household survey of affected households in 2 settlements adjacent to

the right of way (ROW) – Dzhangi and Dzheirankechmaz – carried out in December 2011;

c. community consultations carried out in Dzhangi and Dzheirankechmaz with key stakeholders in December 2011;

d. verification of the centreline and ROW prepared by the Detailed Design Consultant’s engineering team against the cadastral mapping;

e. a summary inventory of affected assets undertaken in March 2012.

In addition, data on unit prices of the land and other assets within the Project affected area was obtained from the Report on “The Survey on Market Price of Land along Baku-Shamakhi Highway” prepared by the World Bank team in February 2010. The ARAP is also largely based on a Resettlement Policy Framework (RPF) prepared by Scott Wilson in 2009.

Final ARAP km 44+600 to 67+500 October 2012

11

Page 12: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

4 CATEGORIES OF RESETTLEMENT AND LAND ACQUISITION IMPACTSIn order to achieve the underlying objectives of Section 1 of the Project such that PAPs derive maximum benefit, assessment of categories of land acquisition and resettlement impacts relied on:

(a) Stakeholder Consultation – via Community Meetings, Focus Group Discussion and Interviews with all stakeholder groups and affected communities;

(b) Evaluation of Project Impacts – via Survey of Affected Households, Cadastral Mapping and Inventory of Affected Assets.

This section provides a summary of categories of potential impacts which are based on these activities.

4.1 SUMMARY OF KEY IMPACTS

All of the land in Section 1 – km 44.6 km to 67.5 - is state-owned. Verification of the centreline and ROW against the cadastral mapping is provided in Appendix 4.

One residential house is located within a proposed RoW at km 47+040 as follows

The survey of this potentially affected household is provided in Appendix 5. As stated Paragraph 2 upon received the compensation considered for constructions and trees by the affected household, they relocation into the public land based on the same conditions by the land status lost in the area of same household will be orginized.

As the land that the house is located on belongs to the state, the home owners will be asked to relocate themselves with compensation at full replacement cost.

Two small scale private businesses (a non-functional bakery at km 46+510 and a café at km 48+060) are also located within proposed ROW as follows

Final ARAP km 44+600 to 67+500 October 2012

12

Construction matreial Size NOTEstone, bricks 9.80 x 4.90 x 2.70 1 - floor

brick 7.30 x 4.30 x 1.60wood 2 x 2

stone-brick length25.70 x height-1.90 height-1.10-stone-0.8-brick

TYPE QUANTITY NOTEGrape 7Fig 10Quince 25Apple 11Pomegranate 4Cherry 3Pear 2Apricot 5Mulberry 17Almond 2Pine 13Plane 1total: 100

Bath

TREES

Stone fence

STRUCTURE USER - MURSAL?YEV N?ZAM? ASADADASHStructures

House - flat roofStable - flat roof

Page 13: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

Construction Material Size NOTEStone length.12.70 x width8.45

height-3.0m

OWNER - FIRST -AQROKOM -LLCStructure

BAKERY PLANT

The bakery workshop at 26.7 meter distance from the new centre-line and is not expected to be demolished, but access may need to be altered. As the Project will provide the alternative access, no compensation would be necessary.

OWNER: Eyyubov Salim AhmadagaSTRUCTURE Construction Material Size

Café stone, brick length.13.60 x width.12.93height.4 1- floor

The cafe at 29.46 m distance from the new centre-line is not expected to be demolished, but access may need to be altered.

It has been confirmed by the cadastral mapping verification that all land along Section 1 is state owned, and the land requirement for the road widening is as follows:

Additional land area in construction site

STATE FUND LANDS - ha

STATE FOREST FUND - ha

TOTAL AREA - ha

14.92 8.98 23.90

The land is used informally by the local communities of Dzhangi and Dzheirankechmaz for pastures and also small scale gathering of some steppe herbs to sell to road users.

Given that there is a requirement for a land take of state forest fund lands there will be losses of state forest fund trees that have been estimated. The measures in relation to tree losses and cost estimates for implementation of these measures should be defined by the Environmental Management Plan.

The territory of the office facilities of Dzhangi Forestry Department is fenced off, and the fence falls in the proposed RoW as well as some smaller auxiliary structures and will need to be moved and the material and works compensated.

Details of the structure are as follows: DZHANGI FORESTRY DEPARTMENT

STRUCTURE Construction material SizeStone brick fence Stone brick length.50 m x height.2.60

Steel door steel width - 5 x height - 2.5 mToilet stone 1.5 x 1.5 x 2m

The key impacts from land acquisition include temporary and permanent impacts:

Temporary loss of access to the road and hence with limited impact on incomes derived from roadside petty trade;

Temporary and negligible loss of access to pastures; Loss of building structures; Temporary disruption of social and community life resulted from temporary loss of

access to the road; and Limited health and safety concerns

In addition, a number of potential positive impacts of the Project are also anticipated, including:

Lower transport costs;

Final ARAP km 44+600 to 67+500 October 2012

13

Page 14: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

Shortened travel time; Reduced deterioration of vehicles and maintenance costs (i.e. reduced VOCs); Enhanced rural connectivity; Facilitation of better, safer access to social services, located in and outside the area; Increased local and international travel; Promotion of services targeting road users; Creation of short and mid-term income-generating opportunities for the PAPs, the

poor, women and youth along the roadside businesses; Creation of business opportunities for local enterprises producing building/construction

materials; Creation of work opportunities for vendors in the communities where the entry to the

highway is allowed; Increased marketing opportunities for agriculture and horticulture produce and thus

increased incomes; Increased availability of agricultural inputs and lower their costs; Increased non-agricultural incomes; and Strengthened social interactions, both in Project area and outside the Project area.

The most direct economic benefit of the Project is associated with civil works created during the construction and operation of the highway. The jobs potentially created by the Project will have at least three types of impact: (a) direct, (b) indirect, and (c) multiplier. Direct impacts include the jobs available for highway’s construction and operation through the civil works and the local road maintenance. Indirect jobs will include those created by suppliers of goods and services during construction and operation. The multiplier effect will include opportunities created by the increased economic activity triggered by the direct and indirect benefits.

It is expected that some of the highway construction will require highly skilled and moderately skilled workers with highway construction experience. In addition to the direct unskilled construction jobs, a substantial number of unskilled jobs will be created by the industries that will supply the building materials for the Project.

The Project will potentially bring increased employment opportunities during the construction phase for local communities, especially to the unemployed youth and women. Provision of food and other necessities to the work crews is another potential job-creating benefit to the local areas. Construction benefits include both incomes during construction and assets that remain after the construction work is completed. In the proximity of work camps, restaurants and other retail facilities are likely to be built to accommodate contractor staff. Many of the jobs created are likely to be targeted for women (e.g. provision-of-food and other necessity services).

When the Project is operational, improved mobility and access to markets would also positively contribute towards the economy of the communities, the region and Azerbaijan at large. However, the majority of the PAPs are not envisaged to significantly increase use of their personal vehicles as the car ownership is considerably low while cost of maintenance, as well petrol prices are high.

As the main agricultural markets for the communities along Section 1 are located in Baku and Shamakhi, the Project communities depend economically on Baku and Shamakhi for the selling of their produce. It is anticipated that an upgraded widened road could provide improved and safer access to this market, as well as other parts of the country, as needed.

Although large-scale transport and highway projects contribute to an increase in the spread of various communicable diseases, including sexually transmitted infections (STI) and HIV, it is unlikely that Section 1 will have a significant HIV impact on the Project communities in spite of some of the risk factors that exist (poverty, unemployment and presence of young population).

Final ARAP km 44+600 to 67+500 October 2012

14

Page 15: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

Culturally conservative environment in the Project areas that is noted by distinct segregation between male and female populations, including limited access of women and girls to the public domain combined with strict norms and values placed on social interaction between the genders is likely to play a preventive role with regard to the spread of communicable and sexually transmitted diseases, including HIV. Overall, as the HIV epidemic is concentrated among high risk populations such as injecting drug users (IDUs), sex workers and prisoners, the Project-induced STI and HIV risks are improbable, especially in Section 1.

4.2 UNAVOIDABLE IMPACTSThe two lane Baku – Shamakhi Road is classified as Category II road with a right-of-way (ROW) of 60 meters; i.e., 30m on each side from the existing road centreline. Since the land acquisition policy of Azerroadservice will require acquisition of land based on a RoW of 30m derived from the new centreline, the expansion of the existing carriageway within the existing ROW is not feasible. Therefore, land acquisition is unavoidable. It is also envisioned that part of the grazing land – public land used for pastures informally by the residents of the two communities (Dzhangi and Dzheirankechmaz) along Section 1 – will be acquired by the Project, thus leading to the potential loss of income to households that rely on livestock as their main source of income.It is also anticipated that loss of income derived from roadside petty trade will be unavoidable during and after construction. However, the land used for pastures and gathering include vast areas, which will allow the population to use available alternative land for grazing and gathering.

Table 1 provides the categories of PAPs likely to be affected by the Project.

Table 1: Categories of Impact – Section 1Type of PAPs Type of ImpactInformal Users of Land Private users with and without verbal agreement with local municipalities on use of

communal land for grazing pastures in alternative areas.Roadside Private Businesses

Private Business Owners – cafe, small convenient stores – potential temporary inconveniences to operations due to accesses.Employees of Private Businesses - cafes, restaurants, small convenient stores – potential employment instability given potential temporary inconveniences to operations.

Roadside vendors Children and adolescentsWomen

Owners of Assets without Land Ownership Rights

Owners of assets, including a residential house, auxiliary structures, and fruit trees without land ownership rights

No sites of any significance in terms of cultural property, such as graveyards and cultural monuments will be affected by Section 1. Table 2 provides categories of impacts and specific losses associated with these impacts.

Table 2: Impacts and Losses

Category of Impact Specific Losses

Business premises Possible need for alteration of access to the premises.Loss of assets and relocation Need to relocate for a private house located on public land.Loss of assets or loss of land Temporary and insignificant loss of access agricultural and/or grazing land Access to land No adverse impacts on access to grazing land as other pastures could be easily

made availableLoss of income/source of livelihood

Most PAPs rely on animal husbandry. However, the impact on loss of use of grazing land will not lead to significant loss of animal husbandry-related income.

Final ARAP km 44+600 to 67+500 October 2012

15

Page 16: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

5 PROJECT AFFECTED AREA (PAA)The Project will widen the existing road along Section 1. The exact scale of land to be acquired has been established through cadastral mapping as follows

Additional land area in construction site

STATE FUND LANDS - ha

STATE FOREST FUND - ha

TOTAL AREA - ha

14.92 8.98 23.90

All land of the Section 1 Project road belongs to the State, including State Land Fund and State Forest Fund. The actual use of land is limited to informal use of state land for grazing livestock by residents for Dzhangi and to a lesser degree Dzheirankechmaz. Tables 3 and 4 provide the details of land ownership along Section 1 of the Project.

Table 3: Land Ownership Section 1

No. Chainage (from) Chainage (to) Confirmed upgrade option Ownership status1 44+600 53+729.86 Widening, LHS State2 53+729.86 54+963.27 Transition State3 54+963.27 54+993.63 Widening, RHS State4 54+993.63 55+836.86 New Alignment State5 55+836.86 56+482.19 Widening, RHS State6 56+489.19 56+860.06 New Alignment State7 56+860.06 59.840.86 Widening, RHS State8 59+840.86 60+908.00 New Alignment State9 60+908.00 62+638.94 Widening, RHS State

10 62+638.94 62+851.87 Transition State11 62+851.87 62+923.35 Widening, LHS State12 62+923.35 63+368.55 New Alignment, R State13 63+368.55 64+996.46 Widening, LHS State14 64+996.46 68+506.63 New Alignment State15 68+506.63 68+697.38 Widening, LHS State

Social infrastructure services in the Project communities are extremely poor, as there is only one school operating in Dzhangi. There are no health facilities in either of Dzhangi or Dzeirankechmaz making it very difficult for the residents of both communities to access health and educational providers, with the closest located in Shamakhi region.

Final ARAP km 44+600 to 67+500 October 2012

16

Page 17: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

6 PROJECT AFFECTED PEOPLE (PAPs)The Section 1 of the Project road runs through land that is sparsely inhabited. Although the road does not cut through settlements, two small communities are located in relatively close proximity to it, i.e. 100 meters away from the ROW. These communities include two small settlements of Gobustan region of Azerbaijan, namely:

Dzhangi Dzheirankechmaz

According to the national statistical data, there are 18 households or 109 persons registered in Dzhangi and 6 households or 23 persons in Dzheirankechmaz. However, the household survey conducted for the purposes of this ARAP in December 2011 indicated that there are 70 households in Dzhangi and 6 households in Dzheirankechmaz.

The survey sample included total of 105 persons represented by 16 selected households in both communities, as presented in Table 4.

Table 4: Section 1 Survey Sample in Project Affected Area

Gobustan district Number of households

Number of persons

Dzhangi 10 64Dzheirankechmaz 6 41Total 16 105

With Dzhangi located on the right side of the road and Dzheirankechmaz on both sides of the road (Table 5), the level of impact of the Project on these communities is mainly associated with access to the road and loss of grazing land as the residents heavily rely on the road for their transport needs and to access the grazing land on both sides of the road. This is most apparent for residents of Dzhangi.

Table 5: Proximity of Project Affected Households to the ROW

Dzhangi Dzheirankechmaz Total

Distance from main road (km) 0.100 0.108 0.103

Distance from district centre (km) 30.0 12.0 23.3

Distance to nearest bus station (km) 0.10 0.11 0.10

Although most of the residents of both Dzhangi and Dzheirankechmaz live in nuclear families with up to six people per household (Table 6), extended family members typically reside close by, such as parents and at least one of the grandparents. Women and children take significant part in domestic labour, as well as caring for the livestock, and gardening. They also make a large number of those engaged in seasonal and occasional low-paid manual labour inside and outside their communities. There is a residential home within a proposed right of way (ROW) that will be directly affected by the Project.

Final ARAP km 44+600 to 67+500 October 2012

17

Page 18: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

Table 6: Average Household Size of PAPs

Dzhangi Dzheirankechmaz Total

Number of children under 6 year 2.8 2.3 2.6Number of children under 16 year 2.6 2.5 2.6Total number of household members, including:

6.5 6.8 6.6

men 3.1 3.5 3.3 women 3.4 3.3 3.4

Although the residents of Dzhangi and Dzheirankechmaz do not have official titles to land plots, they are de-facto utilizing the land adjacent to their settlement, including household plots used for subsistence gardening and horticulture. The household survey indicated that almost all grow vegetables (tomatoes, cucumber, green pepper, eggplant and potato), and to a lesser degree beans and greens. Due to the lack of water especially for irrigation, there are only a few fruit trees in the Project communities.

As most people migrated to the Project area in the mid-1970s from other settlements of Gobustan region, i.e. Arabshalbash, Dzhangi residents have their officially registered plots located in the place of their origin. For most of the Dzhangi inhabitants, who have relied on livestock production for generations, the houses they have built in Dzhangi are considered to be their winter homes; most people stay in Arabshalbash during the summer.

Survey data show that average land plot in Dzhangi is about 0.5 ha or arable land in addition to 1.6 ha of non-arable land. Dzheirankechmaz residents do not have arable land; however they have up to 1.8 ha of non-arable land.

The main source of employment for the surveyed households is livestock production (Table 7), as this population represents livestock producing families that were historically residents of other districts of Gobustan region with predominant reliance on animal husbandry.

Table 7: Reliance of PAPs on Livestock and Poultry (average figures)

  Dzhangi Dzheirankechmaz Total

Cows 2,7 11,3 7,0Ox . 2,0 2,0Young cattle . 6,0 6,0Sheep 1,0 51,7 39,0Goat . 11,0 11,0Poultry 10,5 33,3 20,3Turkey 10,0 10,0 10,0

In addition, dependence on subsistence agriculture, horticulture, and roadside businesses is apparent in the surveyed communities. The types of businesses along the existing road (NB outside the RoW) include small shops, cafes and restaurants, butcher shops and car service workshops. Households also heavily rely on cash incomes such as wages, salaries, and pensions making no more than 180 AZN per monthly on average while women receive 111 AZN per month. Income-generating opportunities are not widely available in the communities as well as the region. Local processing enterprises have been closed down, productive land is scarce, and water is in short supply, while basic infrastructure (transportation, communication) and social services have not been developed significantly.

Final ARAP km 44+600 to 67+500 October 2012

18

Page 19: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

Unemployment in both Dzhangi and Dzheirankechmaz is commonplace while most households are confronted with a need to save the money necessary for family needs such as weddings, house building or children’s education and health. There is a high incidence of de-facto female-headed and single-female or single-elderly-headed households disproportionately impacting women, elderly and children. Community consultations also pointed at discrepancies between male and female transport burdens being apparent in the Project communities particularly in the context of the increasing poverty leading to rural out-migration to Baku and outside the country. Labour migration is quite apparent among local men who remain main breadwinners while women who are responsible for major productive roles continue to constitute an economically disadvantaged group. Women in the Project communities are largely unemployed, with a few who are employed are typically entrenched in low paid or non-cash jobs (e.g. daily and/or odd jobs). In addition to unpaid domestic and reproductive labour (i.e. child-rearing), women also care for elderly and disabled.

There is a need for a special attention to be paid by the Project to the type of transport services available to rural communities and travel patterns that are gender segregated. Like elsewhere in the rural Azerbaijan, men and women in the Project communities share varying degrees of travel burden associated with (a) household travel including collection of water and household needs; (b) travel to and from work and source of economic activity (e.g. trips to agricultural fields, location of seasonal and casual labour market); (c) trips to markets for food and sales of household produce (e.g. agricultural and livestock produce); and (d) travel to basic social services (schools and health facilities), and to maintain social relations. By comparison women carry a much heavier load related to domestic travel that consumes a considerable amount time and energy.

The qualitative data also indicated that women travel outside of their communities significantly less than men due to the high cost of travel, especially long-distance travel. When household transport demands are disaggregated by gender and age with respect to overall household incomes and expenditures, the travel needs of women and the elderly (whether to access health, education or social services) remain mainly unsatisfied compared to those of men. On the other hand, women and children who walk long distances seeking labour along the main roads are exposed to health and life-threatening risks, i.e. road accidents much more than men.

Final ARAP km 44+600 to 67+500 October 2012

19

Page 20: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

7 LEGAL FRAMEWORK7.1 NATIONAL LEGAL FRAMEWORK

Until recently, no specific laws existed in Azerbaijan that provided regulatory and legal grounds to deal with issues related to resettlement and land acquisition, compensation for loss of assets, public consultation and disclosure, or grievance mechanisms. In April 2010, the first-ever expropriation law was endorsed, notably the law “On the Expropriation of Lands for State Needs, No.987 III-Q”, and later in 2011 the President decree on the Additional Activities related to application of the Low was enacted .

Law on Expropriation of Lands for State Needs, No 987 III-Q

The expropriation law sets forward a comprehensive regulatory framework on expropriation of land (publically, privately and municipally owned) and assets for state needs (public domain). The new law provides comprehensive grounds for compensation based on asset valuation in accordance with market value or replacement costs, and sets procedures for public disclosure and consultation. The law also takes into consideration compensation for the loss of income resulting from an expropriation of the land, asset or source of income (Article 7). One of the main achievements of the new law is an inclusive eligibility criteria set for those who fall into categories of persons eligible for compensation and basic resettlement assistance, including users and owners of property. Under Article 7, both owners and users of land and any other asset, where formally or informally registered, as well as absentee owners, are eligible for compensation.

The new law also governs activities related to collection and use of data on the type of affected assets, persons, including carrying out a census of all affected land and persons, cadastral mapping, as well as public meetings that announce officially the start-up of expropriation, and the type of compensation to be given to all affected people.

Constitution of Azerbaijan (November 12, 1995)

Article 29 of the Constitution of Azerbaijan establishes the right of citizens to possess property and the protection of their property rights. It also ensures that no one acquires land without appropriate legal recourse, and that alienation of property for state needs shall only be allowed upon fair reimbursement of the market value of the asset in question.

Other Relevant National Laws and Regulations

A number of other regulatory instruments provide additional a basis for regulating and managing the acquisition of and compensation for land, property and productive assets, namely:

Land Code (25 June 1999)

Civil Code (1 December 1998)

Cabinet of Ministers Resolution No.42 (15 March 2000)

Cabinet of Ministers Resolution No.110 (June 1999) on Approval of Regulations for an Inventory Cost Estimation of Buildings

Decree on Application of the Road Law (2000)

Decree on Additional Activities for Regulating the Use of Road Reserves (2004)

Final ARAP km 44+600 to 67+500 October 2012

20

Page 21: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

Decree of the President (December 26, 2007) on ensuring the execution of the law No 506-3 QD dated 7 December 2007 about “Amendments and Additions to the Civil Code of the Azerbaijan Republic”.

Among these, the Land Code 1999 is a critical law that regulates projects of national interest as it provides (a) compensation principles for loss of land and (b) the basis through court while the sides are dissatisfied with the decision on land acquisition and compensation that was estimated.

In addition to the Land Code, the Civil Code 1998

Civil Code provides that any rights on property will be state registration. Acqusition of land shall only be allowed upon fair reimbursement of the market value by the land owners for state needs.

Procedures for land acquisition are set by the Cabinet of Ministers Resolution No.42 (15 March 2000).

The Cabinet of Ministers Resolution No.110 (June 1999) on Approval of Regulations for an Inventory Cost Estimation of Buildings outlines procedures for acquisition and compensation valuation for affected buildings and immovable property based on standard rates of construction costs by region within Azerbaijan.

The Presidential Decree (2007) provides that 20% additional compensation will be added to the market price of affected assets in order to compensate for damages resulting from the purchase of property, as well as lost income and loss connected with the pre-termination of commitments against third parties.

Relevant Road Regulations

Other relevant regulation includes those related to the control and maintenance of roads such as:

Decree No 228, July 1976

Decree on the Application of the Road Law 2000

Decree No 18, February 2004

Decree of the President, July 8, 2008

Road related legislation regulates usage of the road reserves, maintenance, defines standards for noise and vibration, as well as construction, width requirements, as well as assigns rights for the road authorities to evict illegal occupants.

Collectively, as presented above, the Azeri regulations provide a comprehensive framework for adequate land acquisition and compensation for the Project.

7.2 WORLD BANK OP 4.12 The Word Bank’s safeguard policy on Involuntary Resettlement (OP 4.12) applies whenever land or other property must be acquired for Project, or its use is modified, and that acquisition or modification results in the loss of income, residence or access to resources, either permanent or temporary and whether the occupation is legal or illegal.

Final ARAP km 44+600 to 67+500 October 2012

21

Page 22: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

The OP 4.12 requires avoiding involuntary resettlement whenever possible. Where displacement is unavoidable, the following measures are necessary:

Compensation based on a replacement value of the lost asset Participation of PAPs in planning, implementation and monitoring of the resettlement

process Public consultation and disclosure Restoration of income and living standards to pre-resettlement levels Compensation provided prior to construction

7.3 GAP ANALYSIS BETWEEN AZERI LAWS AND REGULATIONS AND THE WORLD BANK OP 4.12 In general, and certainly in relation to the specific land acquisition impacts associated with Section 1 of the current project, it is considered that the World Bank’s OP 4.12 requirements are comprehensively incorporated in current Azerbaijan legislation, whereby the new expropriation law – Law on Expropriation of Lands for State Needs, No 987 III-Q – plays a critical role Critical areas in this respect include the following (amongst others):

Requirement for resettlement planning including with participation of affected and host communities in order to ensure negative impacts are minimised and needs are met, rather than simply focusing on payment of compensation (Law on Expropriation of Lands for State Needs 2010);

Requirement to meet the needs of vulnerable groups (Law on Expropriation of Lands for State Needs 2010);

Provide transitional, relocation and income restoration assistance as required ((Law on Expropriation of Lands for State Needs 2010));

Requirement to pay compensation in advance where land is compulsory acquired (Law on Expropriation of Lands for State Needs 2010);

Need for compensation to be paid based at full replacement cost (applying market rates), or through grant of another land plot or building of equal quality, size and characteristics;

Avoidance, wherever possible, of impact on agricultural land and forests (Cabinet of Ministers Decree No. 42);

Compensation for losses, whether temporary or permanent, in production or damage to productive assets and crops (Cabinet of Ministers Decree No. 42);

Provision for pre-judicial avenues for resolution of disputes and rights of appeal;

Procedures for public disclosure and consultation (Law on Expropriation of Lands for State Needs 2010);

Compensation for the loss of income resulting from an expropriation of the land, asset or source of income (Law on Expropriation of Lands for State Needs 2010);

Inclusive eligibility criteria and basic resettlement assistance, including users and owners of property, as well as absentee owners (Law on Expropriation of Lands for State Needs 2010).

Final ARAP km 44+600 to 67+500 October 2012

22

Page 23: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

Collection and use of data on the type of affected assets, persons, including carrying out a census of all affected land and persons, cadastral mapping (Law on Expropriation of Lands for State Needs 2010);

Public meetings that announce officially the cut-off and start up of the expropriation (Law on Expropriation of Lands for State Needs 2010);

Public consultation where required with host communities (Law on Expropriation of Lands for State Needs 2010);

Monitoring of resettlement implementation and impacts (Law on Expropriation of Lands for State Needs 2010).

Final ARAP km 44+600 to 67+500 October 2012

23

Page 24: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

8 ELIGIBILITY CRITERIA AND COMPENSATION VALUATION

8.1 IDENTIFICATION OF ELIGIBILITYA survey of PAPs carried out in December 2011 in two communities along Section 1 – Dzhangi and Dzheirankechmaz determined the type and severity of resettlement and land acquisition impacts and hence eligibility for compensation. Overall, the impacts can classified as insignificant for the following reasons:

1. No direct impact leading to acquisition of land is foreseen on any members of the Project communities.

2. No private land is being affected as all land falling under Section 1 is state-owned.

3. Only 1 house will be demolished.

4. Only one cafe will be impacted in terms of temporary loss of access.

5. An insignificant part of the land acquired for the Project that has been used for grazing by the communities will not be accessed by the communities; however, alternative access to other public land will be provided for communities to use as pastures.

8.2 PRINCIPLES OF COMPENSATIONFor the land acquisition process of Section 1, the Azerroadservice OJSC (ARS) will adopt a policy for entitlements that accords with the provisions laid out in this ARAP and the Entitlement Matrix (Table 8). Compensation for loss of/ damage to structures will be based on the replacement cost without depreciation. The compensation will follow the principles set forth in this ARAP, which in summary are as follows:

All PAPs, without regard to legal status of property ownership, will be compensated under the current Azerbaijan legislation, the Expropriation Law 2010, and the World Bank OP 4.12.

Loss of commercial structure due to relocation will be compensated for at replacement value without depreciation.

Loss of net income and wages will be compensated as defined in the Entitlement Matrix for different categories of PAP.

Loss of crops or fruits and vegetables will be avoided by adjusting the construction schedule so farmers are able to harvest annual crops, however, if unavoidable, it will be compensated for at replacement value. Valuation will be based on market prices.

Immovable assets which have been removed during construction works will be compensated for at replacement value without depreciation. Those assets that can be transferred, such as wire-fences, will be transferred to alternative suitable locations and restored as preferred by PAP at the cost of the project.

Those who do not legally occupy or use land will be compensated for the loss of non-land assets, excluding standing crops, buildings and trees.

Final ARAP km 44+600 to 67+500 October 2012

24

Page 25: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

8.3 VALUATION AND COMPENSATION METHODOLOGYThe OP 4.12 stipulates that compensation for lost properties would be calculated based on replacement cost without depreciation. The policy also provides that, if the impact is significant and compensation at replacement value is not sufficient to restore livelihood of the affected people, additional rehabilitation measures should be provided so the affected people would, on a net basis, be able to restore livelihood.

8.3.1 COMPENSATION FOR LANDThere will be no compensation for land as no private land will be acquired from private owners/users. All land under Section 1 is state-owned.

8.3.2 CROP COMPENSATIONThe Section 1 Project is not expected to result in loss of annual crops. If such an impact becomes potential and unavoidable, loss of annual crops will be compensated for at the market value of loss. Prevailing prices for crops will be verified with the assistance from the Valuation Committee based on the data of the State Department of Statistics. A market price survey conducted in 2010 will also be used to assess prevailing market prices for each crop type to adjust and fine-tune the results of valuation by the Valuation Committee. Each type of crop is to be compensated for using the same rate to ensure uniformity, consistency and transparency.

The following formula will be CrC =((RP xYd) –CC)xA xT

CrC = the compensation for loss of income from annual crops; RP = the retail price of the produce (AZN/100 kg);

Yd = the yield (100 kg/hectare);

CC = the growing costs including material inputs, agro-technical activities, transport, and taxes and duties (AZN/hectare);

A = the area cleared by the Project (hectares); and

T = the number of lost growing seasons

8.3.3 FOR FRUIT TREES AND PERENNIAL CROPSCompensation for loss of fruit trees and any perennial crops will be compensated in cash according to its market value and age, which will be equal to the gross market value of one year income times the number of years to grow a tree or crop to similar productivity (age), plus the purchase price of seedlings and starting materials.

8.3.4 COMPENSATION FOR BUILDINGS AND STRUCTURESLoss of or damage to building structures, fences, walls and other impacted structures will be compensated based on the replacement value. Cash compensation will be available as a preferred option for structures. The applicable replacement costs for construction materials, and associated labour costs needed to build replacement structures, will be used to calculate the values.

Final ARAP km 44+600 to 67+500 October 2012

25

Page 26: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

Replacement values will be based on:

Drawings of private building structures and support services;

Average replacement costs of different types of buildings and structures based on information on the quantity and type of materials used for construction (e.g. bricks, decorated aluminium roofs, doors);

Prices of these items collected in Gobustan district market;

Costs for the transportation and delivery of these items to be acquired or replacement land or building site; and

Estimates of construction cost of new buildings including the labour required.

8.3.5 COMPENSATION FOR SACRED SITES The use of sacred sites for any project activities is not permitted under this ARAP.

8.3.6 COMPENSATION FOR PHYSICAL RELOCATION One residential house is located within the proposed RoW. As stated above, upon received the compensation considered for constructions and trees by the affected households, they relocation into the public land based on the same conditions by the land status lost in the area of same household will be orginized.

8.3.7 COMPENSATION FOR SEVERE IMPACT Under Section 1, no severe impacts are foreseen.

The project RFP defines severe impact to be “more than 20% of land loss”. No land take of this extent is foreseen, and furthermore, all land under Section 1 is state-owned.

8.3.8 COMPENSATION FOR PEOPLE WITHOUT LEGAL LAND RIGHTS Those land users who have legally recognizable claims to land without complete registration will be compensated for the loss as per legal land owners. The Project will assist such land owners to complete the registration so that the ARS is able to legally purchase land from them. Those who use the land without any recognisable titles will be compensated only for the investments made by them, including structures built on the land, crops and other assets.

8.3.9 COMPENSATION FOR LOST/ DISRUPTED INCOME Socio-economic baseline data has been established during the survey of affected households, including 5,595 AZN annual income of a household in both communities. Sources of income include livestock production, subsistence agriculture, followed by pensions, state allowances and benefits; salaries and wages; and aid from relatives. The household survey identified livestock production as the highest source of primary income, bringing on average 1,225 AZN annually per household.

Final ARAP km 44+600 to 67+500 October 2012

26

Page 27: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

For disrupted income derived from temporary access inconveniences for commercial activities, such as the cafe that partly falls within the new right of way. To ensure that there will be as minimum as possible disruption to the business and no loss of income, operation in the structures will be allowed during the construction subject to health and safety considerations. Only then theold structures can be demolished

Where it is unavoidable to disrupt business, compensation will be calculated according to the loss of business income exposure over a period of impact plus the period of restoration. The period of restoration is the estimated number of months required to move and rebuild the business to a new permanent location and resume normal business operations.

Compensation will be paid into personal bank accounts of the PAP. If a PAP does not have a bank account, the Project will help them open one. Employees will be paid for wages over the period of business disruption based on the income statement of the business owners, or any other proof of wages provided to them.

The labour cost for preparing replacement land is based on costs for clearing the land, ploughing and planting seedlings and young trees. Labour costs will be paid in the relevant currency (AZN) per the prevailing labour law. The rate used for land compensation is to be updated to reflect values at the time compensation is paid.

Final ARAP km 44+600 to 67+500 October 2012

27

Page 28: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

9 ENTITLEMENT MATRIXTable 8 sets out the Entitlement Matrix applicable to Section 1 of the Project, which provides a summary of the package of entitlements for each category of PAP. The ARS will have the responsibility for ensuring that the actions defined in the ARAP are fully implemented.

Table 8: Entitlement Matrix

Relevance Affected People Compensation Entitlements Permanent Loss Residential/Commercial Land with title or registration pending

Likely not applicable to this segment3

Owner • Land for land compensation, plot comparable in value to lost plot, or • Cash compensation for affected land at full replacement cost free of taxes, registration and transfer costs

Squatter • Free or leased plot on State land

Permanent Loss of Access to Grazing land

minor Private Livestock farmersLivestock Farms Owners

• Acceptable alternative land for grazing

Buildings/Structures Structure on state land

Owner of permanent structures without regard to the legal status of ownership

• House for house swap; if replacement is lower value, cash compensation for the difference, or • Cash compensation at replacement rates for affected structure and other fixed assets

Owner of temporary, structures (kiosks, stalls) without regard to the legal status of ownership

• Approved site to re-locate. Moving costs will be provided.

Trees and any other perennial crops

Private trees on state land

All Affected persons, including squatters

- Cash compensation reflecting income replacement. Economic trees valued at gross market value of one year’s income times the number of years to grow a tree to similar productivity, plus purchase price of inputs.

Temporary LossLand used for construction

Not applicable to this segment

Owner (private or public)

• Contractor pays cash compensation at local commercial rental rates for duration of use • Land restored to original status at end of rental

Permanent Loss of Access to Grazing land

minor Private Livestock farmers/Owners

• Available alternative land for grazing

3 Cadastral plans and field verification at the time of the survey indicated that the land along Section 1 is state owned. However, some commercial structures owners could not be found or could not present a full set of ownerships documentation at the time of the survey. Therefore, it is recommended that the entitlement matrix contains reference to Residential/ Commercial Land Loss Entitlement in case of any future claims.

Final ARAP km 44+600 to 67+500 October 2012

28

Page 29: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

10 IMPLEMENTATION PROCESS AND RESPONSIBILITIESThe Azerroadservice OJSC (ARS) has the lead responsibility for the implementation of the Project including land acquisition and resettlement issues, and is specifically responsible for:

The execution of the compensation and valuation process; The implementation of the ARAP through its Land Acquisition Department (LAD); Public Consultations and Disclosure of ARAP; and Monitoring and evaluation (M&E) of the implementation of ARAP.

In accordance with the Law on Expropriation of Lands for State Needs, No 987 III-Q the ARS is expected to be a designated Expropriation Authority. The designation will be established by the Decree of the Cabinet of Ministers.

The Expropriation Authority will set up a Land Expropriation Group:

The group is set up to also include representatives of Ministry of Finance, State Committee on Property Issues and State Land and Cartography Committee.

Expropriation of the private, state and municipality lands.

If necessary carries out marking in the lands of the affected persons.

Receives and solves grievances given by affected persons during expropriation process in collaboration with the local Grievances Redress Commission.

Work together with Evaluation Commission.

Resettlement Commission

Expropriation authority coming to an agreement with the appropriate region (city) executive power sets up resettlement commission consisting of affected persons4. Its content shall not less than 3, more than 20 persons.

Functions are:

o to take part in the preparation and execution of resettlement plan or recommendations

In accordance with Clause 19 of the Law on Expropriation of Lands for State Needs, No 987 III-Q Valuation Commission is set up and this Commission together with the Expropriation Authority and land expropriation group executes the following:

Collection and analysis of data about the market value of expropriated land;

Collection and analysis of data in connection with replacement value of structures including land and movable property.

Independent evaluator is involved for the evaluation of expropriated land and other property.

After analysing the proposal of independent evaluator and the opinion of the control authority, resolution is made about the compensation rates.

4 The composition of resettlement commissions is subject to specific agreements between the expropriation authority and relevant executive powers.

Final ARAP km 44+600 to 67+500 October 2012

29

Page 30: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

Resolution is presented to the expropriation authority for implementation.

In accordance with the Law on Expropriation of Lands for State Needs, No 987 III-Q the Grievances Redress Commission (GRC) is set up. GRC is discussed in Section 11.

10.1 PRINCIPLES OF LAND ACQUISITION AND RESETTLEMENT

The following list of principles will govern the implementation of the Project:

Avoid residential areas wherever possible to minimize physical relocation of people, and select alignments that minimize acquisition of privately or publicly held productive land;

Adopt design standards that minimize the need to impose land use restrictions on adjoining areas;

Develop fair and transparent procedures to determine compensation for (i) temporary loss of land/ assets during construction; (ii) permanent acquisition of land and assets; and (iii) restrictions on use of land that may be applied to areas adjoining the corridor;

Put in place measures to minimize the potential risk of HIV transmission through adopting a policy of hiring local people for manual labour and requiring contractors to conduct HIV/AIDS awareness programmes for staff and contractors local people;

Acquire land (or right to use land) for state needs through negotiated agreement, with the use of the 2010 Expropriation Law only as a last resort;

Upon completion of construction, restore land as best as possible to its original condition to enable landowners/users/lessees to resume their pre-project activities;

Keep affected people and communities fully informed about the project, the process that will be followed to acquire and compensate for land, and their related rights and avenues for redress;

Develop a fair and accessible grievance redress mechanism;

PAPs will receive support of various kinds, as per the principles set out in the Entitlement Matrix, which enables them to restore the same level of livelihood as prior to the Project; and

PAPs will be notified of the project implementation schedule and consulted regarding the principles of land acquisition and loss of/ damage to assets.

Final ARAP km 44+600 to 67+500 October 2012

30

Page 31: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

11 GRIEVANCE REDRESS MECHANISMA grievance mechanism will be established in line with the provisions of the Law on Expropriation of Lands for State Needs, No 987 III-Q to allow all PAP’s to appeal any decision, practice or activity arising from land or other assets with which they disagree or have concern.

In accordance with the Expropriation Law the Grievances Redress Commission (GRC) is set up as follows:

İn the cases considered as necessary by the Cabinet of Ministries, an appropriate region (city) Executive Power sets up Grievances Redress Commission for administrative territorial division in which the land to be acquired consisting of appropriate persons.

It consists of at least 3, at most 5 persons

Grievances Redress Commission takes necessary measures about the grievances. If necessary, it can provide recommendations to expropriation authority.

If person is not satisfied with resolution of Grievances Redress Commission, then he can present the grievance to control authority.

If person is not satisfied with resolution of control authority as well, then he can apply to the court.

The Expropriation Authority will be responsible for addressing the grievances of the PAP and in case of necessity forwarding them to the appropriate agency/office (according to the specific nature of each grievance respectively) for action.

Excluding the recommendations on compensation costs, the Expropriation Authority accepts the recommendations of GRC and takes appropriate measures or forwards them to the Control Authority.

Due to slight impact of this project, there is no need to set up the above mentioned commission. The possible grievances can be sent to PIU and LAG and responded by them. If necessary, PAP should address their grievances to the Control Authority.

Final ARAP km 44+600 to 67+500 October 2012

31

Page 32: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

Procedure for recording and processing grievances.

GMC will be responsible for ensuring that all grievances expressed either verbally or in writing are recorded using the form below.

Grievance Complaint Reference No:Date grievance received:Date grievance logged:Full Name:_______________________________________________________Contact InformationAddress:_____________________________________________________________________________________

Please mark how you wish to be contacted - (mail, telephone, e-mail)Telephone:___________________________________Email : ______________________________________Date of Incident/ Grievance

What is the nature of your complaint? (continue overleaf if necessary)

How has the grievance/incident affected you?

What would you like see happen to solve the problem?

Signature:Date:Please return this form to:

Final ARAP km 44+600 to 67+500 October 2012

32

Page 33: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

Affected persons will be exempt from all administrative and legal fees incurred pursuant to the grievance redress procedures. All complaints received in writing (or written up when received verbally) will be documented by PIU.

An external monitoring consultant shall be responsible for monitoring the progress of resettlement issues in relation to grievance redress.

In the instance that the Contractor’s staff and / or Supervising Engineer become aware of any grievances relating to resettlement or land acquisition matters these shall be reported to PIU Director and the external monitoring consultant.

At all monthly progress meetings with the Contractor, the supervising Engineer will record any new matters arising relating to resettlement and land acquisition and progress made regarding existing issues. A copy of the minutes will be provided by the supervising Engineer to LAD, PIU and external monitoring consultant.

A summary of grievances will be forwarded to the World Bank as part of routine reporting.

Throughout the preparation and implementation of this ARAP, the PAP will be fully informed by group meetings of their rights and the procedures for addressing complaints. In order to avoid going through a lengthy and formal procedure of logging-in of complaints and waiting for the redress, care will be applied to prevent grievances from occurring by fully disclosing and consulting all provisions in the ARAP to the PAP. The PAP will be informed of key principles of resettlement laid out in this ARAP and the nature of the Project and sub-projects.

11.1 LINKING RESETTLEMENT IMPLEMENTATION TO CIVIL WORKSThe PAP will be compensated in accordance with ARAP Compensation Methodology before the Project civil works can begin for the relevant road section. The land and assets may be taken away only after compensation has been paid and resettlement sites and relocation assistance have been provided to the PAP. Those project activities requiring relocation or resulting in loss of shelter will require that measures to assist the PAP have been implemented in accordance with the ARAP site-specific RAPs before displacement occurs.

Final ARAP km 44+600 to 67+500 October 2012

33

Page 34: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

12 MONITORING & EVALUATION (M&E)In order to comply with the World Bank OP 4.12 requirements, a comprehensive monitoring and evaluation (M&E) procedure will be set up for the implementation of the ARAP, including:

Internal performance monitoring Impact monitoring used to assess the effectiveness of the ARAP to its key objectives

M&E will help strengthen consistency and follow-up process of the ARAP implementation as well as the Project at large. One of the key elements of a successful M&E will include systematic and participatory public consultations and disclosure with all PAPs and other key stakeholders in order to ensure timely and effective identification of outstanding issues that may occur during ARAP implementation. M&E will help monitor the ARAP budget allocations, i.e. actual reimbursement of entitlements and compensation, as well as establish timely delivery of the compensation. It will also help evaluate the content of grievances, efficiency of procedures and accountability of handling the grievances. Finally, M&E will also help address the needs and interests of vulnerable PAP – the poor, women, children and elderly – to see whether compensation and other measures to restore the living standards of all PAPs have been properly designed and carried out.

The format for reporting will include (a) monthly, (b) quarterly and (c) annual progress reports.

M&E will also include monitoring by an external independent 3rd third party.

12.1 INTERNAL PERFORMANCE MONITORING

Internal Perforance Monitoring is a management tool intended to ensure that the ARAP is being implemented according to plan and the provisions of OP 4.12. Internal monitoring will be carried by the land acquisition department (LAD) and the PIU. Areas of reviewrfor the internal monitoring of the ARAP will include the following:

Budget and Timeframe – to track the budgets allocated on time and per each activity;

Delivery of ARAP – to monitor the progress on compensation and rehabilitation measures being allocated to the PAPs and whether the Project benefits are provided to the PAPs;

Institutional and management issues – the effectiveness of institutions and procedures associated with ARAP implementation;

Consultation, Grievance and Specific Issues – to monitor the delivery of the consultations held with the PAPs as scheduled, disclosure of ARAP, reporting and screening of the grievance.

12.2 EXTERNAL IMPACT MONITORING

The external impact monitoring will be used to verify internal performance monitoring (including for key third-party stakeholders, including Central Government and the World Bank) but with a greater emphasis on assessing the effectiveness of the ARAP and its implementation in meeting the needs of the PAPs. Reporting will be conducted on an annual basis following the first year of implementation and over a period of at least three years.

Final ARAP km 44+600 to 67+500 October 2012

34

Page 35: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

The methodology for annual impact monitoring undertaken by independent auditors should involve:

Field visits;

Interviews with a random sample of PAP from different sites comprising the Project in order to assess their knowledge and concerns regarding the resettlement process, their entitlements and rehabilitation;

Feedback from public consultations and disclosure with the PAP; Checking the type of grievance issues and the effective functioning of the grievance

redress mechanisms by interviewing aggrieved PAP and reviewing grievance and appeals processing;

Surveying the standard of living of the PAP after the implementation of the resettlement to assess whether the standards of living of the PAP have improved or been maintained, using baseline information for comparison;

Advise project management of changes necessary to improve implementation of the ARAP

An independent consultant will be engaged by the PIU to undertake external impact monitoring.

Final ARAP km 44+600 to 67+500 October 2012

35

Page 36: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

13 PUBLIC CONSULTATION AND DISCLOSUREThe World Bank Group’s policies on resettlement, land acquisition and compensation provide a framework for a public consultation and participation process, as well as establish measures to redress the grievances of affected people.

Public consultation and disclosure is a key element of the ARAP, since it formally provides an opportunity for a wide range of stakeholders to participate in activities associated with the design, implementation and monitoring of the Project, including providing feedback to the RAP. The establishment of a process to redress grievances allows the Project to deal with issues proactively in the interest of solving any such grievances before having to resort to use of the formal legal system.

OP 4.12 and the IFC manual ‘Doing Better Business through Effective Public Consultation and Disclosure: A Good Practice Manual’ provide action-oriented guidelines aimed at ensuring that consultation with the all key stakeholders – the affected population national, local governments, civil society and community-based and traditional organisations -– is both effective and meaningful. These guidelines emphasise the need for the Project to ensure that the process of public consultation is accessible to all potentially affected parties. Emphasis is placed on the engagement of the people (households, communities, families/clans or institutional owners) who will lose their land and other immovable assets to the project in the identification, valuation, expropriation and/or dispute resolution aspects of the land acquisition process.

Accordingly, the Project has to ensure that:

All stakeholders have access to Project information;

The information provided can be understood;

The locations for consultation are accessible to all who want to attend;

Affected households and other entities have a meaningful say in the design and implementation of the ARAP; and

Measures are put in place, which ensure that vulnerable or minority groups are consulted.

Public Consultation and Disclosure of ARAP, including (a) Phase 1 – consultation during ARAP preparation such as dissemination of key Project background and objectives, description of final alignment and potential impacts; (b) Phase 2 -community consultations on potential impact and proposed mitigations, as well as consultations with other key stakeholders (local government, NGOs), (c) Phase 3 – consultations upon the approval of the ARAP with the affected individuals and communities at large

Public Consultation and Disclosure describes the public consultation and disclosure processes the Project has to undertake in support of the ARAP. This includes measures taken by the Project to engage in consultation with key stakeholders and PAPs during the design of this ARAP. This also covers the commitment to consultations during Project implementation and M&E.

The OP 4.12 stipulates a process of public consultation and disclosure that includes:

Final ARAP km 44+600 to 67+500 October 2012

36

Page 37: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

o Identifying stakeholders (owners and users of affected immovable assets) and ensures that there are adequate mechanisms for stakeholder feedback and information sharing;

o Informing representatives of affected people – local government, village leaders and independent estate surveyors that the people have recruited.

o Ensuring, directly or through people’s representatives, that all directly affected populations (or claimants who include landowners and tenants) are informed of the project, of the need for land acquisition, and type of proposed compensation measures as well as duration of alternative land use arrangements, where applicable;

o Briefing all Project line managers and staff who will interact with affected people on the anticipated effects of the Project and measures to mitigate its land acquisition and resettlement impacts;

o Arranging for the responsible government agency to issue formal notice (after completion of a census and dissemination of a public notice on the eligibility for compensation, coving issues pertaining to asset valuation methods);

o Declaring a clear cut-off date to ensure that no new construction of buildings or capital improvements is made on the directly affected lands;

o Project should be prepared to compensate affected stakeholders for all immovable assets, including improvements made on the land during the period that lapsed after the preparation of the asset inventory;

o Project should also be prepared to update the asset inventory and the valuations to constitute the basis of negotiations should there be a delay in the final investment decision and thus in land acquisition;

o Preparing an illustrated information booklet with details on eligibility, rates of compensation and other entitlements, a timetable for implementation, and applicable grievance procedures as part of the disclosure process;

o Establishing a system for gathering feedback on RAP implementation from all affected groups and communities;

o Launching participatory monitoring and evaluation processes; and

o Preparing and issuing regular RAP information updates.

Public Consultation and Disclosure Activities for ARAP

Preparation of this ARAP involved a consultation process that included several rounds of discussions with the relevant government representatives, including the representatives of the ARS LAD, the officials from the affected Rayons, and the representatives of the affected communities that took place during the preparation of (a) the RPF in 2010 and (b) in December 2011 for the purposes of the ARAP.

Up-to-date, the Public Disclosure and Consultations activities conducted for Section 1 of the Project included four (4) focus group discussions, ten semi-structured interviews, and one

Final ARAP km 44+600 to 67+500 October 2012

37

Page 38: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

community meeting in Dzhangi and Dzheirakechmaz in December 2011 that covered approximately 100 persons. These activities were also complimented partially by the Household Survey (HHS) that followed the focus group discussions (FGDs), semi-structured interviews (SSIs) and the community meeting (CM).

Representatives of the community were selected for consultation during RAP preparation from the following groups:

unemployed young population families of more then 3 children housewives of different age people, taking up seasonal work people, who have income from cattle people, living on benefits.

Key issues discussed during these consultations are presented in Table 11, with the findings summarized below.

Table 11: Key Issues Discussed during Public Disclosure and Consultations – Section 1, December 2011

Issues Composition of Participants Activity Project Basic Information: Objectives,

BackgroundVarious categories5 of women, men,

elderlyFGD, SSI, CM, HHS

Project Potential Adverse Impacts of Resettlement and Land Acquisition

Various categories of women, men, elderly

FGD, SSI, CM, HHS

Project Potential Benefits Various categories of women, men, elderly

FGD, SSI, CM, HHS

Recommendations/Suggestions for the Project on How to Mitigate Adverse Impacts and How to Ensure Project

Benefits

Various categories of women, men, elderly

FGD, SSI, CM, HHS

As various categories of the PAPs and community leadership were consulted, principal conclusions included the following:

Overall consent in their communities with the need for the Project to be commenced as a part of the national development agenda.

Understanding of potential Project benefits including access to safer and faster transport, greater income-generating opportunities, markets, and social development gains such as better access to health and educational facilities, as well as social networks between communities

Need for safer, reliable, and affordable transport services to become available for the PAP and especially to women, children and elderly

Need for income-generating opportunities directly available to the local communities, especially working-age men, youth and women during and after construction for skilled and non-skilled jobs due to high unemployment among PAPs

Fair compensation for all PAPs, regardless of their status (formal or informal users of land, house, building structure), permanent or temporary staff of livestock farms and small-scale businesses

5 Categories were determined taking account of age, marital status, education, employment anddisability

Final ARAP km 44+600 to 67+500 October 2012

38

Page 39: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

Protection of health and safety of PAPs, especially children and women who are engaged in small roadside trade

Need for meaningful participation of the PAPs in the Project implementation, and M&E of its progress via inclusion of community representatives in the ARAP implementation committees

Final ARAP km 44+600 to 67+500 October 2012

39

Page 40: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

14 ARAP IMPLEMENTATION ACTIVITIES TIMETABLE The schedule of the ARAP implementation specified by activities is proposed as shown in Table 12 below.

Table 12: Section 1 ARAP Implementation Schedule as per the 2010 Law on Acquisition of Land

Activities Months after ARAP Approval

0 1 2 3 4 5 6 7 8 9

ARAP approval

ARAP implementation plan finalised

Letter to the Cabin of Ministers informing about road widening land requirements issued by the ARS

The Cabinet of Ministers’ Instruction to determine the land requirements, and the appointment of a land buyer (ARS) issued

Verified cadastral mapping and list of Project Affected People finalised and issued to the Cabinet of Ministers by ARS

The Cabinet of Ministers’ Approval given and a valuation Committee is set-up

Entitlements Finalised by the Valuation Committee

Negotiations Finish and Compensation Starts

Internal M&E contracted

Civil Work Start

The schedule of activities for the implementation of the ARAP refers to time that is required for negotiations and reaching agreement between the Project and the affected communities and individuals.

Final ARAP km 44+600 to 67+500 October 2012

40

Page 41: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

Annex 1: Guiding Questions for Focus Group Discussions

FOCUS GROUP DISCUSSION: GUIDING QUESTIONS Village Rayon Location to the Road How many people in FGD?

Part 1: Socio-economic and Demographic Profile1. Can you please tell us about yourselves?

1a. Marital Status: __________ 1bAge ____ years 1c Ethic Group ________ 1d Gender: _______ 1e Highest Education Obtained_______________

2. How long have you lived in this village? If you have migrated from another location, please specify when and why?

3. What is your main occupation and since when? What about the rest of your community?

4. How do you consider the socio-economic status of your community?

5. What is the primary source of income of your households? What about the rest of your community?

6. How do your families in your community care for the land and who participates in this work? Please elaborate

7. How do your families in your community care for the livestock and who participates in this work? Please elaborate

PART 2: Access to Road and Transport Services

8. How often do members of your community use the road and for what purpose? Please specify by type of transport, age, gender, occupation

9. How much does one spends on transportation per trip? Please specify per type of transport, location and frequency

10. How far are the school, health facilities, community market and other places (e.g. cemetery) that your community members visit and how do you get there? How often do you visit them? Please specify per type

11. Is it safe to drive or walk to those facilities for you, adults, children, and elderly? Please specify

PART 3: Knowledge about the Project

12. Have you heard of the project? If so, please specify when and from where?

13. Do you want to know more about the Project? If so, what exactly would like to know? Please specify

14. What, in your opinions, are the potential benefits of the Project for you and your community? Please specify

15. What, in your opinions, are the potential negative impacts of the Project for you and your community? Please specify

Final ARAP km 44+600 to 67+500 October 2012

41

Page 42: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

16. How does your community resolve problems (disputes) that may arise in your community? Who do you and people like you approach if you seek resolution of a dispute?

17. What, in your opinion, the Project has to take into consideration in order to protect the needs of the affected communities? Please specify

Final ARAP km 44+600 to 67+500 October 2012

42

Page 43: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

Annex 2: Questions for Semi-Structured Interviews

PART 1: STRUCTURED QUESTIONS

1. What is your position to the Head of the Household? Specify_______ 2. Marital Status: __________ 3. Age ____ years 4. Nationality ________ 5. Gender:_______6. Education of Adult Members of Household:

1. Primary (1-4 grades) ________ persons2. Incomplete (5-9 grades) ________ persons3. Complete High School (10-11 grades) ________ persons4. Vocational training (technical) ________ persons5. Incomplete High School ________ persons6. Secondary ________ persons

7. How long have you lived in this village? ____________ years 7a. If you have migrated from another location, please specify when and why?8. What is your main occupation and since when?9. How many people reside in your households and what do they do? _______ Total (persons)

10. How does your family cultivate your land plot and who participate in this work (specify all family members who participate)? Please elaborate11. How does your family care for your cattle and who participate in this work (specify all family members who participate)? Please elaborate12. How do you consider your family in economic terms?

13. What are you main sources of income?

Please indicate main sources of income earned by all household members (specifty – in the last month, last season and last year), by gender and age:

Income from Land Plot (specify the year):

Income from cattle (specify year):

14. What type of expenses does your household have?

Type of Expenses MNT

Food

Clothes

Buying a house/apartment (specify)

Buying a tractor

Buying livestock

Buying poultry

Buying land

Final ARAP km 44+600 to 67+500 October 2012

43

Page 44: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

Productive costs (specify)

Utilities (specify)

Medical expenses (medicine, medical treatment – specify)

Education (specify)

Ceremonies (wedding, burial, etc, specify)

House/Building maintenance (construction materials)

Other (specify)

PART 2: OPEN-ENDED QUESTIONS

1. How often do you and your household’s members use the road and for what purpose? Please specify by type of transport and household member(s)

2. How much do you spend on transportation per trip? Please specify per type of transport, location and frequency

3. How far are the school, health facilities, community market and other places (e.g. cemetery) that you and your household members visit and how do you get there? How often do you visit them? Please specify per type

4. Is it safe to drive or walk to those facilities for you, adults, children, and elderly? Please specify

5. Have you heard of the project? If so, please specify when and from where?

6. Do you want to know more about the Project? If so, what exactly would like to know? Please specify

7. What, in your opinion, are the potential benefits of the Project for you and your community? Please specify

8. What, in your opinion, are the potential negative impacts of the Project for you and your community? Please specify

9. How does your community resolve problems (disputes) that may arise in your community? Who do you and people like you approach if you seek resolution of a dispute?

10. What, in your opinion, the Project has to take into consideration in order to protect the needs of the affected households? Please specify

11. Do you have the title and other documents required regarding the ownership of your land plot? How many people are the owners of the land plot and who (specify)?

Final ARAP km 44+600 to 67+500 October 2012

44

Page 45: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

12. Do you have the title and other documents required regarding the ownership of your house? How many people are the owners of the house and who (specify)

Annex 3: Community Information Sheet

Time of Survey: Day____ Month____, 2011. __________ Rayon (city) __________ Township (town) __________ Village ___________Village Group Name of Village Head: __________ Interviewed: __yes __no Code of the Village: __________ on the Road (Directly Affected?): Yes__ No__Names and positions of others interviewed _________________________________Distance from local rural road (km) _____ Distance from town (km) ___ Distance from Rayon center (km)___ Distance to nearest bus stop (km)____

Total number of households of the village:

Total population of the village (persons):

Total income of the village____

Number of males (persons):_____

Number of females (persons):_____

Number of people by nationality (persons): ______ ______

Number of adult workers:_______

Number of male adult workers:

Number of female adult workers:

Number of households in poverty:_____

Number of people living in poverty:______

Would you consider this village as predominately poor?___ Yes ___No

Total amount of cultivated land of the village (Ha):_____ Paddy field (Ha): Water irrigated

land (Ha): Dry land (Ha):

Orchard (Ha): Woodland (Ha): Vegetable garden (Ha):

Fish pond (Ha): Wasteland (Ha):

Other (Ha):

Net per capita income of households by different levels: (number of households)___ 1-400 AZM ___ 400-700 AZM ___ 700-1300 AZM ___ 1300-2000 AZM ___ 2000-3000 AZM ___ >3000AZM

Main crop production:Tons produced ____Percent consumed____Percent sold____Average free market price per ton____

Other main crops and agricultural products: Specify________________________________________________________________

Tons or Units

Produced:

________________________________________

Percent PercentConsumed Sold________ _____________ _____________ _____________ _____

Free Market Price per ton or per unit:________________________________________________

Final ARAP km 44+600 to 67+500 October 2012

45

Page 46: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

Migration in 2010 - 2011:Males out___ Females out___ where____(countries)Males in____ Females in____From (countries)_______

Number of people who graduated from middleschool: ___male ___female

Number of people who graduated from highschool: ___male ___female

Annual fees for school students _______

How would you rate the overall quality of education:

__excellent __very good __good __fair __poor

How many students from the village are now attending university? __male __female

Does village pay part of salaries for teachers? __yes __no

Percent of cultivated land that is:Private_____Communal_____Municipal______Reserve Fund_____Other(specify)________

Number of workers who work in: In Local area: Outside (far away):State enterprises: ___male ___female ___male ___femaleRural enterprises: ___male ___female ___male ___femaleGovernment: ___male ___female ___male ___femalePrivate hire: ___male ___female ___male ___female

Births in 2011: male____ female____

How would you rate the overall quality of health services:__excellent __very good __good __fair __poorDoes village pay part of salaries for medical staff? __yes __no

Are all houses connected to electricity network? __yes __no If no, what percentage are connected? ____Are all houses connected to gas network? __yes __no If no, what percentage are connected? ____ Are all houses connected to water network? __yes __no If no, what percentage are connected? ____Is water safe to drink without boiling? __yes __no Water source: wells___ springs___ surface water___ piped____What non-agricultural products are produced in the village for sale elsewhere?_______________ Where are they sold?________What is the total market price of annual production_______________ How are they transported to market or buyers_______________

What is the economic level of your village compared with other villages:

___ low ___ lower middle ___ middle ___ upper middle ___high

What is the economic level of your town compared with other townships:

___ low ___ lower middle ___ middle ___ upper middle ___high

What do you believe will be largest benefit that will be brought about by the Project?

___ convenience of travel ___ convenient transport of goods ___ creation of job opportunities ___ more exchange of information that will be useful for business ___ development of township enterprise and increase of family income ___others (explain it here)

Final ARAP km 44+600 to 67+500 October 2012

46

Page 47: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

What do you believe will be the largest disadvantage that will be brought about by the Project?___ pollution ___ lack of safety ___ adverse impact to income ___ house relocation ___ adverse impact to living conditions ___destruction of water conservancy facilities ___ others (explain it here)Could you please rank in order of priority the four most important needs of the village? (enter 1 for highest priority, 2 for second, etc.)__ school ___ clinic ___ road ___ drinking water ___ electricity ___ water conservancy facilities ___ township enterprise ___ more loans for production___ others (explain)

Final ARAP km 44+600 to 67+500 October 2012

47

Page 48: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

Annex 3 – Household Survey Questionnaire A1. Code of questionnaire __________ A2. Name and code of interviewer _________________

A3. Date of survey: Day____ Month _____________2011

A4. ____________ District A5 _______________ city / town

A6. ____________ Village A7 _______________ name of community

A8. Distance from main road (km) _____

A9. Distance from district center (km) ___

A10. Distance from village / community road (km) _____

A11. Distance to nearest bus station (km) ____

A12. Type of village ________ mountain village ________ flat level village _______ near forest

village

A13. Name and surname of household head ___________________________

A14. Gender of household head men _____ women ____

A15. Household type: nuclear family __________ extended family ______

A16. Number of children under 6 year ____ A17. Number of children under 16 year ___

A18. Total number of dependant older _____ A19. men ____ women ____

A20. Total number of household members ______ A21. men _____ women ____

A22. Have this household financial difficult: Yes___ No __

B. Social demographic information of household members B1 B2 B3 B4 B5 B6

# Relation to household head

GenderMen -1

Women - 2Age Ethnicity Present

educational level Employment

1. Head2.3.4.5.6.7.8.9.

10.11.

For question 1. 01 - husband/wife02 - son / daughter03 - mother/father04 - mother / father in law 05 - brother / sister06 - brother / sister in law 07 - daughter / son in law08 - grandfather/mother of

For question 5. 1- Master’s degree 2- Bachelors 3- College, technicum

(vocational school)4- technical School

5- Secondary 6- Basic

For question 6. 1 - hired worker in state sector2 - hired worker in private sector (firm, company etc.)3 - hired worker in agriculture (farm, agricultural enterprise)4 - income from commercial activity, craftsman/ artisan5 - work in household production (agricultural) 6 - free professional activity (tutoring, repair, transport, services etc.)

Final ARAP km 44+600 to 67+500 October 2012

48

Page 49: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

head09 - other relatives

7- Primary8- No education

7- pension8 - other

B7. Number of household member who absent in survey date ______ of which:

# Absent person men women totalB7.1 Labour migrantB7.2 StudyingB7.3 Service in armyB7.4 Other (specify)

_________________

C. Economic conditions of household

Type of land sizeC1. Cultivated total area (100 m2): C2. Non-cultivated total area (100 m2): C3. Irrigated area (100 m2):C4. Non-irrigated area (100 m2):C5. Dry-farming land (100 m2):C6. Orchard (100 m2):C7. Forest (100 m2):C8. Vegetable crops (m2):C9. Hayfield (100 m2):

You is:C11. Owner of land? - yes - 1; no - 2C12. Leasing? - yes - 1; no - 2C13. Owner or lease of additional land? - yes - 1; no - 2C14. If you leasing of land, how much for 100 m2 per month paying? _________ manat

How you using your land? If don’t use go to question 20.

C15. We using ourselfC16. Giving to lease and for 100 m2 receiving? _________ manatC17. First part we using, second part giving to lease

C18. Cultivated crops: C 19. Type of trees:

C18 Crops:(specify by type)

Specify by type

How much money received

in last year: manat

C18.1 TomatoC18.2 CucumberC18.3 PepperC18.4 Egg-plantC18.5 PotatoC18.6 OnionC18.7 BeanC18.8 Fasol

Final ARAP km 44+600 to 67+500 October 2012

49

Page 50: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

C18.9 PeaC18.10 CabbageC18.11 Water-melonC18.12 MelonC18.13 GreeneryC18.14 Others________

C20. Main economic activity your household (specify) ____________________________________

C21. In economic activity your household involved how much family members:

C21.1. Men_____ C21.2. Women ____

C22. In economic activity your household involved how much workers from outside:C22.1. Men _____ C22.2. Women ____C22.3. ____ how much paying per working day (AZN) (specify)_________ C23. About livestock and poultry in your household:

C24. Animals using for transportation: of which:

C24.1 Horse _____ C24.2 Donkey _____ (specify number)

C25. Type of vehicles in the household

type number year:

1 - less than 5 year 2 - 5-10 year3 - more than 10 year

Approximately cost in AZN

condition: 1 - new 2 - good3 - old

123

Final ARAP km 44+600 to 67+500 October 2012

50

Number of livestock: NumberC23.1. CowsC23.2. BuffaloC23.3. OxC23.4. Young cattleC23.5. SheepC23.6. GoatC23.7. HorseC23.8. DonkeyC23.9. PoultryC23.10. TurkeyC23.11. Gas-duckC23.12. Beehives

Page 51: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

C26. Annual income of household

C26.1 – annual incomeC26.2 – forthcoming annual income for next year 1 - high :____(%), 2 – same, 3 - low____(%)

________AZN

C27. Structure of annual income of household # Incomes – (AZN)

С27.1 Income from crop production sales С27.2 Income from livestock sales С27.3 Income from forestry production salesС27.4 Income from fisheriesС27.5 Other business incomes of households, specify

_______

C28. Salary income, pension and benefits# Incomes – (AZN)

men member women memberС28.1 Wages С28.2 Pension

of which specify type:С28.2.1С28.2.2С28.2.3С28.2.4

C29. Money received from family members from abroad (AZN):C29.1. Specify whom ______________ C29.2. where _________________

C29.3. from men member C29.4. from women member:

C30. Household average monthly consumption expenses

№ Monthly AnnualC30.1 Total consumption expensesC30.2 Food and drinksC30.3 Clothing and FootwearC30.4 Housing, household utensils and

operationsC30.5 Medical care C30.6 EducationC30.7 Wedding and funeral repastC30.8C30.9

Communication: mobile phone normal phone

C30.10 Others (specify) _________________________

D. Household dwelling:D1. Total size of your overall area m2 ___________

Final ARAP km 44+600 to 67+500 October 2012

51

Page 52: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

D1.1. number of floor: _____ D1.2. number of rooms: _____

D2. Primary construction material of house D2.1. brick D2.2. baked brick D2.3. soldier D2.4. stone D2.5. mixed

D3. Construction time house D3.1. less than 5 year D3.2. 5-10 year D3.3. more than 10 year

D4. How many square meters is the plot of land on which your house is built with the plot of land (100 2 ): _______

D5. Type of house: D5.1. separate house D5.2. part of separate house D5.3. apartment D5.4. Others (specify)

D6. Dwelling condition:

№ inside outsideD6.1 WC 1 2D6.2 Bath and shower 1 2D6.3 Pipe water 1 2D6.4 Satellite dish (yes-1, no-2) 1 2

D7. If you would like build a house just like yours how much would it cost you ?

D7.1 ……………….............(manat) D7.2 999 - I do not know

D8. Do you have any other properties like house, shop and summerhouse other than this house?

D8.1. 1- Yes __________________ specify type D8.2. 2 - No

D9. If someone would like to buy it how much money would you ask for? (If more than one write

the total)

Property owned

Totally how much would it cost?

How much money would you ask in total?

D9.1. HouseD9.2. Flat  

D9.3. Shop  

D9.4. Other-Specify- …………..  

D10. Source of heating: D10.1 Electricity D10.2 Central heating D10.3 Generator D10.4 Gas D10.5 Oil stove D10.6 Firewood stoveD10.7 of dry dung stove D10.8. Other (specify)_______________

Final ARAP km 44+600 to 67+500 October 2012

52

Page 53: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

D11. Using equipment

# numberD.11.1 truckD.11.2 tractorD.11.3 other agriculture equipment and engineering

D12. Durable goods

number

D12.1. Black and white TV setD12.2. Colored TV setD12.3. Satellite dishD12.4. PC D12.5. Mobile phoneD12.6. Music CenterD12.7. Tape recorderD12.8. Video tape recorder D12.9. Video cameraD12.10. Air conditioner D12.11. RefrigeratorD12.12. Washing machineD12.13. Sewing or knitting machineD12.14. MotorcycleD12.15. Bicycle for adults

E. Access to transport services and expenses E1. Use of transport services

to work to school to market other

E1.1. Transport using by family members (1- bus, 2- car, 3- taxi)

E1.2. Time for transportation (hour, minute) E1.3. Total monthly transportation

expenditures of household (AZN)

E2. Improvement of transport:

Yes No Other (specify)E2.1. Your household member satisfied used transportation

services in generally? E2.2. How you think need to improve roads?

E3. Economic situation:

low low mean mean good high

E3.1. Economic condition of your village (city/town) in comparison with neighbouring

E3.2. Economic condition of your household (city/town) in comparison with neighbouring

Final ARAP km 44+600 to 67+500 October 2012

53

Page 54: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

G1. Do you expect any significant positive effects on your livelihood or lifestyle as a result of the project?

Yes No

G1.1. roadsG1.2. transportG1.3. unemploymentG1.4. good info for business G1.5. local entrepreneurshipG1.6. increase family incomeG1.7. schoolG1.8. access to health servicesG1.9. access to market

G1.10. access to relativesG1.11. other (specify) ____________________________________

G2. Given the impacts we have just measured, do you expect any significant negative effect to your livelihood or lifestyle as a result of the project?

G2.1. abuse of environment G2.2. low security G2.3. negative effect to incomes G2.4. remove housing G2.5. negative effect to living conditions G2.6. violation waterproof equipment G2.7. migration G2.8. health risks G2.9. other (specify) ______________________________________________________

G3. Project will improve, please circle by level of importance

G4. Are you aware of the proposed Project?

G4.1. 1( ) No, I didn’t knowG4.2. 2( ) Yes, I knew - How did you hear about the Project?

G4.2.01( ) Teams that visited before G4.2.02( ) Land teams identifying the corridor and the affected

parcelsG4.2.03( ) Social meetings held in and around the community by

people G4.2.04 ( ) Public meetings organised by the ProjectG4.2.05 ( ) Meetings organised by local officialsG4.2.06 ( ) RadioG4.2.07 ( ) NewspaperG4.2.08 ( ) TelevisionG4.2.09 ( ) HearsayG4.2.Other – Specify- ..................................................

Final ARAP km 44+600 to 67+500 October 2012

54

G3.1. school 1 2 3 4G3.2. hospital 1 2 3 4G3.3. market 1 2 3 4G3.4. dinking water 1 2 3 4G3.5. electricity 1 2 3 4G3.6. waterproof equipment 1 2 3 4G3.7. local entrepreneurship 1 2 3 4G3.8. other (specify) 1 2 3 4

Page 55: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

I would like to express my gratitude to you for your cooperation and assistance.

Final ARAP km 44+600 to 67+500 October 2012

55

Page 56: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

Annex 4: Verification of the Centreline and ROW against the Cadastral MappingPDF files

Final ARAP km 44+600 to 67+500 October 2012

56

Page 57: Upgrading of Baku Shamakhi Road - World Bankdocuments.worldbank.org/curated/en/343071468005060135/SF…  · Web view05/01/2016  · 10 implementation process and responsibilities

Azerroadservice OJSC of the Ministry of TransportUpgrading of Baku-Shamakhi Road

Annex 5: The Survey of this Potentially Affected Household