Date post: | 05-Jan-2016 |
Category: |
Documents |
Upload: | barrie-booker |
View: | 217 times |
Download: | 3 times |
Upper Newsome Creek Habitat Improvement Pre-solicitation
Restoration of Upper Newsome Stream Reach 3 and
Haysfork Sediment Pond Restoration
Newsome Stream Reach 3
Newsome Stream Reach 3 – Stream Crossing (Bridge Provided)
Newsome Stream Reach 3 Restoration
• Construction Access Improvements (placement of 2 government furnished temporary timber bridges)
• Tailings pile removal to repository site
• Instream Habitat Structure Construction
• Repository reclamation (topsoil and brush scattered over site)
Haysfork Sediment Pond
• Removal of fence and existing pipe in sediment pond
• Plug existing drainage adits and construct new spillway
• Re-naturalize site
Sediment Pond
Hayfork Spillway Construction Plans (Sheet 1 of 3)
Hayfork Spillway Construction Plans (Sheet 2 of 3)
Hayfork Spillway Construction Plans (Sheet 3 of 3)
Timeline
• Looking to solicit contract late by February or March 2012
• Implementation window is June 1 – September 30th 2012. Instream work cannot begin until July 1 and must be done by September 30th.
• Snow, high water, and saturated ground conditions typically restrict access until early July.
Questions?
• Karen Ruklic, Forest Service Contracting Officer 983-5144