Urbanisation in Kenyan Counties This map shows the level of urbanisation and absolute urban population in every county. It gives a general picture of the distribution and sizes of urban centres per county and nationally. KEY BELOW 10% 10-20% 20-30% 30-40% 40-50% 50-60% Above 60% CITIES MAJOR TOWNS OTHER TOWNS SMALLER TOWNS Isiolo Samburu Laikipia Meru Garissa Wajir Marsabit Turkana Baringo West Pokot Nyeri Embu Tharaka Nithi Kirinyaga Machakos Makueni Kitui Tana river Kwale Lamu Kajiado Taita Taveta Kilifi Mombasa Mandera Narok 58,500 7% URBAN POPULATION Bomet Nyamira Kericho Vihiga Nandi Uasin Gishu Kisumu Siaya Busia Kakamega Kisii Migori Homa bay Elgeyo- Marakwet Trans nzoia Bungoma 167,400 20% 298,700 22% 252,600 15% 91,000 11% 174,100 31% 507,700 52% 228,300 38% 132,300 15% 271,700 22% 311,500 34% 138,000 14% 102,300 14% 345,600 39% 53,200 14% 122,100 16% Nakuru 735,000 46% Nyandarua 110,500 16% 169,600 25% 82,900 16% 8,500 7% 190,000 12% 146,700 24% 99,100 25% 61,500 11% 284,900 41% 104,200 12% 571,400 52% 139,900 14% 36,100 15% 20,200 20% 285,500 26% 64,300 15% 66,300 23% 68,300 14% 285,500 100% 38,700 17% 62,300 44% 64,000 22% 121,700 14% 42,700 8% 96,900 15% 185,600 18% 83,400 16% Kiambu Murang’a Nairobi 145,000 16% 1,017,500 61% 3,138,400 100% This series of urban maps and info-graphics was produced by SymbioCity Kenya in 2015. Their purpose is to start a dialogue on urbanisation in Kenya. The maps are produced with financial assistance from the Swedish International Development Agency (Sida). They are put together from available information from secondary sources and are not to be interpreted as a flawless description of the actual situation. Any mistakes or oversights are unintentional and the responsibility of SymbioCity Kenya. You are welcome to copy, distribute and present the maps, provided that you attribute the content to SymbioCity Kenya.
Transcript
Page 1: Urbanisation in Kenyan Counties urbanisation and absolute ...symbiocitykenya.org/wp-content/uploads/2019/04/Urban-Maps-2015... · Urbanisation in Kenyan Counties This map shows the

Urbanisation in Kenyan Counties This map shows the level of urbanisation and absolute urban population in every county. It gives a general picture of the distribution and sizes of urban centres per county and nationally.KEY

BELOW 10%

10-20%

20-30%

30-40%

40-50%

50-60%

Above 60%

CITIES

MAJOR TOWNS

OTHER TOWNS

SMALLER TOWNS

Isiolo

Samburu

Laikipia Meru

Garissa

Wajir

Marsabit

Turkana

Baringo

West Pokot

Nyeri

Embu

Tharaka Nithi

Kirinyaga

Machakos

Makueni

KituiTana river

Kwale

Lamu

Kajiado

Taita Taveta

Kilifi

Mombasa

Mandera

Narok

58,5007%

URBAN POPULATION

BometNyamira

Kericho

Vihiga

Nandi

Uasin Gishu

Kisumu

Siaya

Busia Kakamega

Kisii

Migori

Homa bay

Elgeyo-MarakwetTrans nzoia

Bungoma

167,40020%

298,70022%

252,60015%

91,00011% 174,100

31%

507,70052%

228,30038%

132,30015%

271,70022%

311,50034%

138,00014%

102,30014%

345,60039%

53,20014%

122,10016%

Nakuru

735,00046%

Nyandarua

110,50016%

169,60025%

82,90016%

8,5007%

190,00012%

146,70024%

99,10025%

61,50011%

284,90041%

104,20012%

571,40052%

139,90014% 36,100

15%

20,20020%

285,50026%

64,30015%

66,30023%

68,30014%

285,500100%

38,70017% 62,300

44%

64,00022%

121,70014%

42,7008%

96,90015%

185,60018%

83,40016%

Kiambu

Murang’a

Nairobi

145,00016%

1,017,50061%

3,138,400100%

This series of urban maps and info-graphics was produced by SymbioCity Kenya in 2015. Their purpose is to start a dialogue on urbanisation in Kenya. The maps are produced with financial assistance from the Swedish International Development Agency (Sida). They are put together from available information from secondary sources and are not to be interpreted as a flawless description of the actual situation. Any mistakes or oversights are unintentional and the responsibility of SymbioCity Kenya. You are welcome to copy, distribute and present the maps, provided that you attribute the content to SymbioCity Kenya.

Page 2: Urbanisation in Kenyan Counties urbanisation and absolute ...symbiocitykenya.org/wp-content/uploads/2019/04/Urban-Maps-2015... · Urbanisation in Kenyan Counties This map shows the

Urban Infrastructure and Services Map

Muranga

This map shows general urban level connectivity by road. It also shows access to various services, namely: electricity, water and sanitation. KEY

BELOW 10%

10-20%

20-30%

30-40%

ABOVE 40%

ROAD

MAJOR TOWN

WATER SUPPLY

SEWERAGE AND SANITATION

CONNECTIVITY(ROAD)

SHARE OF URBAN POPULATION %

OTHER TOWN

ELECTRICITY%

Samburu

Marsabit

Turkana

Mandera

Isiolo

KajiadoLamu

2% 18% 74%

68% 27% 0.1%

N/A 76% 89%

Nakuru

Elgeyo marakwet

Kiambu

Nairobi

5% N/A 51% 16%

Trans nzoia

77% 90% 77%

West pokot

----- 35% 78%

85% 56% 0.1%

Garissa

0.1% 52% 76%Kirinyaga

1% 99% 57% 16%

3.1% 97% 66% 46%

Baringo

7% 57% 35%Laikipia

2.6% 89% 63%

Meru

2% 33% 37%

Embu

2% 98% 62% 16%

Machakos

1.8% 97% 58% Kitui

0.3% 69% 51%

Tana river

0.2% 23% 56%

Makueni

0.9% 98% 57% 12%

41%

52%

Kilifi

1.5% 66% 76%

Taita Taveta

1.5% 94% 70% 23% Kwale

N/A 47% 66% 18%

Nyandarua

0.8%100%68% 19%Nyeri

4% 100% 69%

Wajir

0.2% 13% 74%

Kisii

Nyamira

Siaya

BusiaKakamega

Nandi

Bungoma

Uasin Gishu

Homa bay

Vihiga

Bomet

KerichoKisumu

0.5% N/A 83% 16%

N/A 97% 89% 22%

0.7% N/A 47% 11%

1.2% 81% 44% 14%

2.9% 84% 56% 14%

1.5%98% 89% 39%

5% 92% 56%

0.3% 95% 41% 18%

28%

22%

4.5% N/A 69% 14%

N/A 99% 68%

14%N/A 61% 39%

60% 87% 60% 52%

Narok

0.2% 71% 34% 6%

14%

22%18%

8%

11%

2% 12%

14% 15%

44%

x%

24%

25% 98% 65%

Tharaka Nithi

7%40% 91% N/A

25% 100% 75% 100%

Mombasa

Migori

N/A 61% 47% 34%

7% 100% 78% 61%

44% 99% 83% 100%

20%

26%

0.5% 74% 72%

24%

Samburu

0.1% 27% 68% 17%

N/A 34% 52%

Elgeyo marakwet

Trans nzoia

77% 90% 77% 20%

*N/A’ refers to ‘Data not available’

6% N/A 76% 31%

N/A N/A 76% 15%

This series of urban maps and info-graphics was produced by SymbioCity Kenya in 2015. Their purpose is to start a dialogue on urbanisation in Kenya. The maps are produced with financial assistance from the Swedish International Development Agency (Sida). They are put together from available information from secondary sources and are not to be interpreted as a flawless description of the actual situation. Any mistakes or oversights are unintentional and the responsibility of SymbioCity Kenya. You are welcome to copy, distribute and present the maps, provided that you attribute the content to SymbioCity Kenya.

Page 3: Urbanisation in Kenyan Counties urbanisation and absolute ...symbiocitykenya.org/wp-content/uploads/2019/04/Urban-Maps-2015... · Urbanisation in Kenyan Counties This map shows the

Tharaka Nithi

Isiolo

Nakuru

Samburu

Laikipia

Meru

Garissa

Wajir

Marsabit

Turkana

West pokot

Baringo

NyandaruaNyeri

EmbuKirinyaga

Muranga

Kiambu

Machakos

Makueni

Kitui

Tana river

Kwale

LamuKajiado

Taita Taveta

Kilifi

Mombasa

Narok

Bomet

Nyamira

Kericho

Vihiga Nandi

Uasin Gishu

Bungoma

Trans nzoia

Kisumu

Siaya

BusiaKakamega

Kisii

Migori

Elgeyo Marakwet

Mandera

Nairobi

Urban Planning InitiativesThis map shows various planning initiatives going on in each county

Homa bay

Aimed at improving living conditions in informal settlements in selected towns in Kenya by strengthening institutions and programme management, enhancing ten-ure security, investing in infrastructure and service deliver and planning for urban growth

Kenya Informal Settlements Improvement Project (KISIP)

The Master Plan integrates all the existing Master Plans of various infrastructure within the city of Nairobi and its surrounding. Infrastructure includes urban transport, railway, airport, power and water supply, sewerage, telecommunication and solid waste management.

Nairobi Integrated Urban Development Master Plan (NIUPLAN)

To strengthen local governance and improve service delivery in selected municipalities

Kenya Municipal Programme (KMP)

Mombasa is preparing a master plan for the town to help undress climate change problems, urbanization problems and disaster relate issues.

Mombasa Master Plan

Aimed at improving the livelihoods of people living and working in slums and informal settlement in the urban areas of Kenya through the provision of security of tenure and physical and social infrastructure as well as providing opportunities for housing improvement and income generation

Kenya Slum Upgrading Programme (KENSUP)

A department responsible for urban planning established within the 10 executive positions. Activities within the docket include rating and valuation, property management, forward planning, development control, urban design, land survey, enforcement of policies, rental housing development & management, low cost housing, slum upgrading, and urban environment control among others

County Executives in charge of Urban Planning

Aimed at creating awareness of collaboration benefits among stakeholders involved in the Global Programme for Public Space project and the Kenya Municipal Programme

Urban Collaboration and Planning Workshop for Stakeholders

The County Government’s Act, 2012 (CGA), 104 obligates a county to develop among other county plans, a County Integrated Development Plan (CIDP). This is a 5-year plan that shall inform the county’s annual budget. it shall reflect the strategic mid-term priorities of the county governments

County Integrated Development Plans (CIDPs)

Aimed at capacity building of the civil society and local authorities, public mobilization for participation; and effective non-sector actors participation in County planning

Establishing Effective, Participatory & Accountable Governance At County Level

A platform that brings together over 900 Civil Society Organiza-tions (CSOs), County Officials and Private sector actors to promote knowledge based dialogue on the evolving urban landscape in Kenya

Local Urban Forums (LUFs)

KEY

This series of urban maps and info-graphics was produced by SymbioCity Kenya in 2015. Their purpose is to start a dialogue on urbanisation in Kenya. The maps are produced with financial assistance from the Swedish International Development Agency (Sida). They are put together from available information from secondary sources and are not to be interpreted as a flawless description of the actual situation. Any mistakes or oversights are unintentional and the responsibility of SymbioCity Kenya. You are welcome to copy, distribute and present the maps, provided that you attribute the content to SymbioCity Kenya.

Page 4: Urbanisation in Kenyan Counties urbanisation and absolute ...symbiocitykenya.org/wp-content/uploads/2019/04/Urban-Maps-2015... · Urbanisation in Kenyan Counties This map shows the

ish

ga

Mom-basa

Laikipia

NyandaruaNyeri

Muranga

Baringo

Garissa

Isiolo

Mandera

Marsabit

Samburu

Kirinyaga

Kitui

Tana River

Machakos

Kiambu

Nakuru

Nairobi

Nairobi

Meru

Tharaka Nithi

Uasin Gishu

Turkana

Wajir

Bungoma

Trans Nzoia

West Pokot

Kakamega

Nandi

Kericho

SiayaVihiga

Homa Bay

Migori

Kisumu

Kisii

Bomet

Narok

Kajiado

Taita Taveta

Makueni

Kilifi

Lamu

Kwale

Embu

KEY

Evolving County Urban Legislation Map

A

A

A

A

A

A

A

A

A

A

A

AA

A

A

A

A

A

A

A

A

A

A

A

II

I

C

C

C

D

D

D

E

E

E

E

E

F

F

F

G

B

B

B

B

B

B

B

B

BB

B

B

B

B

B

B

B

B

B

B

E

I

I

I

I

I

I

J

J

K

HFormulates mechanism for parking and traffic issues in the towns and establishes legal mechanism to regulate motorists and related purposes

Designated Parking Places

L

M

M

M

M

M

M

M

N

N

Nyamira

O

O

OPQ

R

R

R

S

T

T

UU

V

W

X

Elgeyo Marakwet

YZ

Zi

Busia

Mombasa

A

Regulates the manufacturing, sale, advertisement and distribution of alcoholic drinks, within the counties and with collaboration with other counties and in line with the national policy.

Baringo, Bomet, Kakamega Elgeyo/ Marakwet, , Kitui, Machakos, Meru, Nairobi, UasinGishu, Mombasa, Nakuru, Vihiga, Busia, Kiambu, Taita Taveta, Marsabit, Nyamira, Makueni, Kajiado, Kericho, Samburu, West Pokot, Turkana, Murang’a

Alcoholic Drinks Control/Liquor licencing

OProvides for the establishment of a microfinance Corporation and for connected purposes

Bungoma, Meru, Uasin Gishu

Microfinance

VRegulates public entertainment and the use of public amenities and for connected purposes

Nakuru

Public Entertainment and Amenities

WProvides mechanism for the establishment of a Fire and Rescue Services Authority and its functions and powers, water supply for firefighting, training and pension schemes for the authority

Nakuru

Fire and Rescue Services

XRegulates and addresses matters related to wayleaves and related purposes.

Uasin Gishu

Wayleaves YProvides for the establishment of County Corporations; for control and regulation of County Corporations; to give effect to the provisions of the Constitution on devolved government and for connected purposes

Uasin Gishu

Corporations ZGives effect to Article 176 (2) and 185 and Schedule IV of the Constitution and provides for the establishment of county project management and implementation units and for connected purposes

Uasin Gishu

Projects implementation and Management Zi

Provides for the regulation and administration of tax waivers to give further effect to Article 210 of the Constitution and connected purposes

Nairobi, Taita Taveta

Tax Waivers Administration

QRegulates the supply of electricity in the retail market; to set out the functions of persons engaged in the conveyance and supply of electricity and for connected purposes

Busia

Electricity Reticulation RProvides for matters relating to traffic, parking, county roads, street lighting, public roads transport and connected purposes

Kisii, Uasin Gishu, Narok

Transport

SEstablishes relevant authority and mechanism to promote urban agriculture and related purposes

Nairobi

Urban Agriculture

T Provides for the control and licensing of betting and gaming premises; for the imposition and recovery of a tax on betting and gaming; for the authorizing of public lotteries in the county; and for connected purposes

Nairobi, Nakuru

Betting, Lotteries and Gaming

UPrevents nuisance and related issues

Nakuru, Bomet

Nuisance

PProvides for the promotion of energy production through the use of renewable energy sources in accordance with climatic, environmental and macroeconomic considerations in order to reduce dependence on fossil fuels, ensure security of supply and reduce emissions of CO2 and other greenhouse gases and for connected purposes

Busia

Energy Development

IProvides for the imposition of rates on land and buildings in the Counties and for connected purposes

Baringo, Elgeyo/Marakwet, Kisumu, Laikipia, Machakos, Nakuru, Kiambu, Mombasa, Nyandarua

Valuation and Rating JProvides for land survey, mapping and for connected purposes

Laikipia, Kiambu

Survey And Mapping K

Provides mechanism on how to conserve and protect the environment and natural resources of the County from the use and disposal of plastic and polythene material.

Baringo

Polythene Materials Control and Management L

Provides for control on manufacturing, usage and disposal of plastic carry bags in the County in order to restore and protect the environment

Nairobi

Plastic Carry Bags Control M

Provides for the grant of trade licenses and for connected purposes

Baringo, Machakos, Bomet, Elgeyo/ Marakwet, Marsabit, Uasin Gishu, Nyandarua

Trade Licence NProvides for the regulation of permits, fees and fines for advertisements and for related purposes

Bungoma, Nakuru

Outdoor Advertising

B Provides mechanism for engaging the public in matters of decision making and governance process as required in Articles 1, 10, 174 and 232 of the Kenya Constitution and also Section 87 of the County Government Act

Baringo, Bomet, Bungoma, Busia, Elgeyo Marakwet, Laikipia, Nakuru, Kericho, Kiambu, Nandi, Nairobi, Nyandarua, Machakos, Meru, Siaya, Turkana, West Pokot, TharakaNithi, Kajiado, Kitui

Public Participation

C

Provides for the establishment for Solid Waste management funds, necessary institutions, and the mechanisms and regulations in connection to solid waste.

Nakuru, Marsabit, Bomet

Solid Waste management (draft stage)

E Provides for the preparation of county spatial plans and related physical development plans, and for connected purposes

Kiambu, Laikipia, Kericho, Nairobi, Marsabit, Nyamira

Spatial PlanningF

Provides for the establishment of institutional framework for coordination and promotion of county development and for connected purposes.

Laikipia, Kisumu, Nairobi

Investment and Development G

Regulates activities in market places and provides for governance of markets and towns and related purposes

Nyandarua

Trade and Markets

DProvides for the development, regulation and management of county public works related to water and sanitation services, storm water, management systems, water conservation and for connected purposes

Meru, Machakos, Nakuru

Water and Sanitation Services

Counties have developed and passed a number of legislation. Some of

these legislation are general, others deal directly or mainly with urban issues. The latter are the pieces of

legislation mapped here.

Disclaimer:This series of urban mapsand info-graphics was produced by SymbioCity Kenya in 2015. Their purpose is to start a dialogue on urbanisation in Kenya. The maps are

produced with financial assistance from the Swedish International Development Agency (Sida). They are put together from available information from secondary sources and are not to be interpreted as a flawless description of the actual situation. Any mistakes or oversights are unintentional and the responsibility of

SymbioCity Kenya.You are welcome to copy, distribute and present the maps, provided that you attribute the content to SymbioCity Kenya.

Page 5: Urbanisation in Kenyan Counties urbanisation and absolute ...symbiocitykenya.org/wp-content/uploads/2019/04/Urban-Maps-2015... · Urbanisation in Kenyan Counties This map shows the

County Revenue Sources and Expenditure Map

DISCLAIMER:This series of urban mapsand info-graphics was produced by SymbioCity Kenya in 2015. Their purpose is to start a dialogue on urbanisation in Kenya. The maps are produced with fi nancial assistance from the Swedish International Development Agency (Sida). They are put together from available information from secondary sources and are not to be interpreted as a fl awless description of the actual situation. Any mistakes or oversights are unintentional and the responsibility of SymbioCity Kenya.You are welcome to copy, distribute and present the maps, provided that you attribute the content to SymbioCity Kenya.

This map shows the proportion of: exchequer allocation to counties;

to counties own revenue; to conditional grants and loans. Comparatively, the map

shows which counties have high own revenue sources and conditional grants and loans. Counties can learn from one another in these two important areas

77

ga

Marsabit

99%

1%0%

Muranga

Kirinyaga

KEY

National Government percentage

Recurrent

Own sources percentage

Development

Conditional Grants percentage

Lands, housing and urban management

ish

Uasin Gishu

Bungoma

Trans Nzoia

Kericho

SiayaSiayaSiaya

Migori

KisumuKisumuKisumuKisumu

Bomet

Kakamega

Elgeyo MarakwetMarakwetMarakwetMarakwetMarakwetMarakwetMarakwetMarakwetMarakwetMarakwet

ish

84%

41%

5%59%

11%

Bomet

Garissa

91%

68%

32%3%

6%

27%

18%

55%46%

54%

KakamegaBusia

95%

5%0%

42%

58%

92%54%

46%2%4%

Homa Bay

Bungoma68%

32%0%

56%

42%

Kajiado87%

13%0%

74%

26%

Elgeyo Marakwet83%

57%

43%3%14%

Kericho92%

8%0%

61%

39%

Kiambu50%

50%

0%

57%

43%

Kilifi 72%

26%2%

65%

35%

Embu83%

14% 48%

52%

0%

80%

20%0%

53%

47%

Isiolo

Baringo

15%

72% 63%

13% 37%

Kisii

17% 15%

85%

2%

79%

Kisumu

56%

32%

13%

63%

13%24%

Kitui89%

8%11%

58%

42%

Kwale

85%

8%7%

74%

26%

Laikipia

67%

26%7%

46%

54%

Lamu

83%

17%0%

62%

38%

Machakos

69%

31%0%

47%

53%

Kirinyaga

70%

30%13%0%

62%

38%

Makueni

96%

4%0%

Mandera

93%

3%3%

47%

53%

51%

49%

Meru

75%13%

12% 37%

79%

Migori87%

0%

13%

66%

34%

Mombasa

40%

60%

0%

49%

51%

77%

Muranga

23%0%

33%

66%

Nairobi

37%

60%

3%

59%

30%

Nakuru81%

19%0%

58%

38%

Nandi

91%

9%0%

39%

61%

Narok46%

54%

0%

59%

41%

Nyamira98%

45%

55%2%0%

Nyandarua

96% 39%

61%4%0%

Nyeri

9%1%

89%

47%

53%

Samburu

87%

7%7%

52%

48%

Siaya96%

4%0%

48%

52%

Taita Taveta

91%

9%0%

58%

42%

Tana River97%

3%0%

63%

37%

Tharaka Nithi

97%

3%0%

45%

55%

Trans Nzoia89%

11%0%

65%

35%

Turkana

93%

4%3%

36%

64%

Uasin Gishu75%

25%0%

65%

35%

Vihiga

6%

94%

60%

40%0%

Wajir

98%

2%0%

40%

60%

West Pokot100%

0% 0%

32%

68%

1.89%

4.23%

3.76%

1.75%

0%

0%

0%

3.04%

6.72%

0%

0%

0.32%4%

0%

0%

0%

0.39%

27%

0%

0.5%

15.9%7.19%

0.44%

5.3%

0%

1.44%24%

0%

9.03%

1.63%

2.23%

0%

0%

8.67%

2.3%

8.4%

0.29%

39%

4.32%

5.47%

34.89%

6.74%

5.26%

2%

0%

4.23%

7%7%

Page 6: Urbanisation in Kenyan Counties urbanisation and absolute ...symbiocitykenya.org/wp-content/uploads/2019/04/Urban-Maps-2015... · Urbanisation in Kenyan Counties This map shows the
Page 7: Urbanisation in Kenyan Counties urbanisation and absolute ...symbiocitykenya.org/wp-content/uploads/2019/04/Urban-Maps-2015... · Urbanisation in Kenyan Counties This map shows the

Development Partners Urban Initiatives

ish

ga

Laikipia

Nyandarua

Nyeri

Muranga

Baringo

Garissa

Isiolo

Mandera

Marsabit

Samburu

Kirinyaga

Kitui

Tana River

Machakos

Kiambu

Nakuru

Nairobi

Nairobi

Meru

Tharaka Nithi

Elgeyo Marakwet

Uasin Gishu

Turkana

Wajir

Trans Nzoia

West Pokot

Kakamega

Nandi

Kericho

Busia

Siaya

Homa Bay

Migori

Kisumu

Kisii

Kisii

Nyamira

Bomet

Narok

Kajiado

Taita Taveta

Makueni

Kilifi

Lamu

Kwale

Embu

Mombasa

Disclaimer:This series of urban mapsand info-graphics was produced by SymbioCity Kenya in 2015. Their purpose is to start a dialogue on urbanisation in Kenya. The maps are produced with fi nancial assistance from the Swedish International Development Agency (Sida). They are put together from available information from secondary sources and are not to be interpreted as a fl awless description of the actual situation. Any mistakes or oversights are unintentional and the responsibility of SymbioCity Kenya.You are welcome to copy, distribute and present the maps, provided that you attribute the content to SymbioCity Kenya.

This map shows development partners working in urban areas and their location per county. It focuses only on o� cial bilateral

and multi-lateral partners

KEYAfrican Development Bank (AfDB)

Arab Bank for Economic Development in Africa (BADEA)

Danish International Development Agency (DANIDA)

European Development Fund (EDF)

European Investment Bank (EIB)

German Development Bank (KFW)

Government of Belgium

Government of Canada

Government of China

Government of Finland (FINLAND)

Government of France (AFD France)

Government of Germany (KFW GERMANY)

Government of Netherlands (NETHERLANDS)

Government of Italy

Government of Japan

Government of Spain

Icelandic International Development Agency (ICEIDA)Nordic Development Fund (NDF)

Organization for Petroleum Exporting Countries (OPEC)

State of Kuwait

United Kingdom

United Nations Development Programme (UNDP)

United Nations International Children Education Fund (UNICEF)

WORLD BANK

Government of Sweden

Bungoma

Vihiga

Page 8: Urbanisation in Kenyan Counties urbanisation and absolute ...symbiocitykenya.org/wp-content/uploads/2019/04/Urban-Maps-2015... · Urbanisation in Kenyan Counties This map shows the

Development Partners Urban InitiativesThis map shows development

partners working in urban areas and their location per county. It focuses only on o� cial bilateral

and multi-lateral partners

ga

Mom-basa

Laikipia

Nyandarua

Nyeri

Baringo

Garissa

Isiolo

Mandera

Marsabit

Samburu

Kirinyaga

Kitui

Tana River

Machakos

Nakuru

Meru

Tharaka Nithi

Turkana

WajirWest

Narok

Taita Taveta

Makueni

Kilifi

Lamu

Kwale

Embu

Uasin Gishu

Bungoma

Nandi

Migori

ish

Elgeyo Marakwet

Uasin Gishu

Bungoma

Trans Nzoia

Kakamega

Nandi

Kericho

Busia

Siaya

Vihiga

Homa Bay

Migori

Kisumu

Kisii

Nyamira

Bomet

Nairobi

MombasaMombasa

Nairobi

KEY

Government of Netherlands (NETHERLANDS)

African Development Bank (AfDB)

Arab Bank for Economic Development in Africa (BADEA)

Danish International Development Agency (DANIDA)

European Development Fund (EDF)

European Investment Bank (EIB)

German Development Bank (KFW)

Government of Belgium

Government of Canada

Government of China

Government of Finland (FINLAND)

Government of France (AFD France)

Government of Germany (KFW GERMANY)

Government of Italy

Government of Japan

Government of Spain

Icelandic International Development Agency (ICEIDA)Nordic Development Fund (NDF)

Organization for Petroleum Exporting Countries (OPEC)

State of Kuwait

United Kingdom

United Nations Development Programme (UNDP)

United Nations International Children Education Fund (UNICEF)

WORLD BANK

Kiambu

Muranga

Kajiado

Disclaimer:This series of urban mapsand info-graphics was produced by SymbioCity Kenya in 2015. Their purpose is to start a dialogue on urbanisation in Kenya. The maps are produced with fi nancial assistance from the Swedish International Development Agency (Sida). They are put together from available information from secondary sources and are not to be interpreted as a fl awless description of the actual situation. Any mistakes or oversights are unintentional and the responsibility of SymbioCity Kenya.You are welcome to copy, distribute and present the maps, provided that you attribute the content to SymbioCity Kenya.

Government of Sweden

Page 9: Urbanisation in Kenyan Counties urbanisation and absolute ...symbiocitykenya.org/wp-content/uploads/2019/04/Urban-Maps-2015... · Urbanisation in Kenyan Counties This map shows the
Page 10: Urbanisation in Kenyan Counties urbanisation and absolute ...symbiocitykenya.org/wp-content/uploads/2019/04/Urban-Maps-2015... · Urbanisation in Kenyan Counties This map shows the

Kisumu

Kwale

Kitui

Laikipia

Baringo

BusiaAfrican Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP)To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

European Development Fund (EDF)

Northern Corridor Rehabilitation Programme – Phase III (Eldoret-Webuye-Malaba)Rehabilitation of Eldoret-Webuye (59km) and Webuye-Malaba Road (61km) projects. Widening the shoulders from the current 1.5m to 2.0m. reconstruction of seriously deteriorated sections

Government of Sweden

Lake Victoria Environment Management Programme (LVEMP) Aimed at generating information to guide policy decisions on sustainable management of the Lake Victoria Basin (LVB). It’s an East African Community (EAC) project under implementation in the fi ve countries that share the Lake Victoria Basin: Burundi, Kenya, Rwanda, Tanzania and Uganda.

United Kingdom

East Africa Transit Improvement Programme (Eatip)/ East Africa Trade Facilitation ProgrammeInfrastructure development at the Taveta and Busia border posts

World Bank Western Kenya Community Driven Development and Flood Mitigation ProjectThe project comprises of community driven development. This will support community prioritized investment projects to improve livelihoods and build demand and capacity for local level development

World Bank Energy Sector Recovery Project (ESRP)Strengthening the energy sector regulator capacity to carry out an electricity tariff study and set power tariff s and prepare the secondary legislation

Elgeyo Marakwet

World Bank Water and Sanitation Services Improvement Project (WaSSIP)Description: Rehabilitating and extending existing water supply facilities in Lake Victoria North Water Service Board (LVNWSB) and new intake works

Embu African Development Bank (AfDB)

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the Tana Water Services Boards (TWSB)

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development

African Development Bank (AfDB)

Power Transmission System Improvement ProgrammeConstruction of 431km of 132kV lines, the extension of 6 sub-stations and the construction of 8 new sub-stations that will contribute to the capacity of Kenya to increase the number of new connections by 200,000 annually

Government of Italy

Installation of High Mast Flood lighting structures High Mast Floodlighting structures distributed in slums

World Bank Kenya Informal Settlements Improvement Project (KISIP)To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery ; and plan for urban growth

Government of Sweden

Kenya Municipal Programme (KMP) To support the Government of Kenya through strengthening local governance and improving urban service delivery

Government of Sweden

Kenya Informal Settlements Improvement Project (KISIP) To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery; and planfor urban growth

EmbuEmbuga

Garissa African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

African Development Bank (AfDB)

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the Northern Water Services Boards (NWSB)

Government of Canada

Improving Access to Quality EducationTo increase the number of school going children, especially girls, and provide them with a better education

Government of Sweden

Kenya Municipal Programme (KMP) To support the Government of Kenya through strengthening local governance and improving urban service delivery

Government of Sweden

Kenya Informal Settlements Improvement Project (KISIP) To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery; and planfor urban growth

Organization for Petroleum Exporting Countries (OPEC)

Garissa Sewerage Project Sewerage project to cover Garissa and its environs

United Nations Development Programme (UNDP)

Economic Empowerment ProgrammeTo enhance and mainstream inclusiveness of the poor and vulnerable in the institutional and policy framework and private sector participation in job-rich and pro-poor growth; and to empower the poor and vulnerable

World Bank Kenya Informal Settlements Improvement Project (KISIP)To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery ; and plan for urban growth

HomabayAfrican Development Bank (AFDB)

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the Lake Victoria South Water Services Boards (LVSWSB)

Government of Sweden

Lake Victoria Initiative (LVI)To contribute to poverty reduction in a sustainable development framework in the Lake Victoria Region. This is an East African Community (EAC) project under implementation in the fi ve countries that share the Lake Victoria Basin: Burundi, Kenya, Rwanda, Tanzania and Uganda.

Government of Sweden

Lake Victoria Environment Management Programme (LVEMP) Aimed at generating information to guide policy decisions on sustainable management of the Lake Victoria Basin (LVB). It’s an East African Community (EAC) project under implementation in the fi ve countries that share the Lake Victoria Basin: Burundi, Kenya, Rwanda, Tanzania and Uganda.

World Bank Water and Sanitation Services Improvement Project (WaSSIP)The project strives to (a) increase access to reliable, aff ordable and sustainable water supply and sanitation services; and (b) to improve the water and waste water services

HomabayAfrican Development Bank (AFDB)Government of Sweden

Kiambu

Kilifi

Kericho African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP)To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

African Development Bank (AfDB)

Power Transmission System Improvement ProgrammeConstruction of 431km of 132kV lines, the extension of 6 sub-stations and the construction of 8 new sub-stations that will contribute to the capacity of Kenya to increase the number of new connections by 200,000 annually

Government of Germany (KFW GERMANY)

Development of Water and Sanitation SectorTo supply water to Kericho and Kisii to meet the demand for clean and safe water

Government of Japan

Olkaria Lessos Kisumu Power Lines Construction Project Construction works for transmission lines, expansion of substations and consulting services

Government of Sweden

Kenya Municipal Programme (KMP) To support the Government of Kenya through strengthening local governance and improving urban service delivery

Government of Sweden

Kenya Informal Settlements Improvement Project (KISIP) To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery; and planfor urban growth

World Bank Kenya Informal Settlements Improvement Project (KISIP)To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery ; and plan for urban growth

World Bank Northern Corridor Transport Improvement Project (NCTIP)Rehabilitation of Northern corridor and emergency restoration of damaged public assets in order tuo enhance effi ciency and eff ectiveness of Kenya’s transport sector

African Development Bank (AfDB)

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the Athi Water Services Boards (AWSB)

Government of Belgium

Thika-Gatundu West Power line Reconstruction ProjectReconstruction of the Thika-Gatundu West 132Kv electrifi cation line

Government of China

Nairobi-Thika Highway Improvement Project, & Nbsp; Lot 3: Kenyatta University - ThikaImprovement of Thika Road to a four lane carriageway to decongest Thika Road

Government of China

Kenyatta University Teaching and Referral Hospital ProjectConstruction and equipment of teaching and referral hospital at Kenyatta University

Government of Sweden

Kenya Municipal Programme (KMP) To support the Government of Kenya through strengthening local governance and improving urban service delivery

Government of Sweden

Kenya Informal Settlements Improvement Project (KISIP) To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery; and planfor urban growth

World Bank Kenya Informal Settlements Improvement Project (KISIP)To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery ; and plan for urban growth

World Bank Water and Sanitation Services Improvement Project (WaSSIP)The project strives to (a) increase access to reliable, aff ordable and sustainable water supply and sanitation services; and (b) to improve the water and waste water services

World Bank Water and Sanitation Services Improvement Project (WaSSIP)Rehabilitating and extending existing water supply facilities in Athi Water Service Board and new intake works

World Bank Kenya Urban Water and Sanitation OBA Fund for Low Income AreasProject aims to increase the number of people in low income areas with access to improved water supply and sanitation services. In Ruiru and Juja areas water network extensions, non-revenue water reduction and household connections are being undertaken

World Bank Northern Corridor Transport Improvement Project (NCTIP)Rehabilitation of Northern corridor and emergency restoration of damaged public assets in order to enhance effi ciency and eff ectiveness of Kenya’s transport sector

World Bank National Urban Transport Improvement Project (NUTRIP)N/A

Government of Canada

Creating Safer SchoolsTo improve the safety and quality of school and community environments for 120,000 vulnerable boys and girls

Government of China

Rabai-Malindi-Garsen-Lamu Transmission Line320km 220Kv, 132/33Kv No23 MVA substations at Malindi, Garsen and Lamu to connect Lamu Port to the National grid and strengthen supply to the North Coast

Government of Italy

KKB Settlement Infrastructure Improvement Programme To improve infrastructure in the slum areas of Kilifi

Government of Italy

Installation of High Mast Flood lighting structures High Mast Floodlighting structures distributed in slums

Government of Italy

Slum Upgrading in Kilifi To upgrade the infrastructure of slums in Kilifi

Government of France

Coast Water and Sanitation Programme The project is meant to supply safe and clean water to the City of Mombasa and its environs through expansion and rehabilitation of water supply and sewerage systems

Government of Sweden

Kenya Municipal Programme (KMP) To support the Government of Kenya through strengthening local governance and improving urban service delivery

Government of Sweden

Kenya Informal Settlements Improvement Project (KISIP) To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery; and planfor urban growth

World Bank Kenya Informal Settlements Improvement Project (KISIP)To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery ; and plan for urban growth

World Bank Water and Sanitation Services Improvement Project (WaSSIP)The project strives to (a) increase access to reliable, aff ordable and sustainable water supply and sanitation services; and (b) to improve the water and waste water services

World Bank Water and Sanitation Services Improvement Project (WaSSIP)Rehabilitating and extending existing water supply facilities in Coast Water Service Board and new intake works

World Bank Kenya Urban Water and Sanitation OBA Fund for Low Income AreasProject aims to increase the number of people in low income areas with access to improved water supply and sanitation services.

World Bank East Africa Public Health Laboratory Network Project (EAPLHP)Rehabilitation, expansion and construction of 5 satellite laboratories to expand diagnostic services and develop capacity of laboratory personel carrying out operational research and facilitate knowledge sharing

World Bank Energy Sector Recovery Project (ESRP)Strengthening the energy sector regulator capacity to carry out an electricity tariff study and set power tariff s and prepare the secondary legislation

African Development Bank (AfDB)

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the Lake Victoria South Water Services Boards (LVSWSB)

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

European Development Fund

Maternal and child healthMaternal and child health, family planning and nutrition

Government of France

Kisumu Urban Project (KUP)A pilot project considered to be innovative both for Kenya and AfD . Its overall objective is to enhance the living conditions of Kisumu’s population by introducing a comprehensive urban programme. The project will fi nance needed public infrastructure and facilities, slum upgrading and local capacity

Government of France

Water and SanitationFinances the upgrading and extension of drinking water supply and sanitation facilities by building the management and planning capacities of regional water agencies and local public water companies.

Government of Japan

Olkaria Lessos Kisumu Power Lines Construction Project Construction works for transmission lines, expansion of substations and consulting services

Government of Sweden

Kenya Municipal Programme (KMP) To support the Government of Kenya through strengthening local governance and improving urban service delivery

Government of Sweden

Kenya Informal Settlements Improvement Project (KISIP) To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery; and planfor urban growth

Government of Sweden

Lake Victoria Initiative (LVI)To contribute to poverty reduction in a sustainable development framework in the Lake Victoria Region. This is an East African Community (EAC) project under implementation in the fi ve countries that share the Lake Victoria Basin: Burundi, Kenya, Rwanda, Tanzania and Uganda.

Government of Sweden

Lake Victoria Environment Management Programme (LVEMP) Aimed at generating information to guide policy decisions on sustainable management of the Lake Victoria Basin (LVB). It’s an East African Community (EAC) project under implementation in the fi ve countries that share the Lake Victoria Basin: Burundi, Kenya, Rwanda, Tanzania and Uganda.

World Bank Kenya Informal Settlements Improvement Project (KISIP)To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery ; and plan for urban growth

World Bank Water and Sanitation Services Improvement Project (WaSSIP)The project strives to (a) increase access to reliable, aff ordable and sustainable water supply and sanitation services; and (b) to improve the water and waste water services

World Bank Northern Corridor Transport Improvement Project (NCTIP)Rehabilitation of Northern corridor and emergency restoration of damaged public assets in order to enhance effi ciency and eff ectiveness of Kenya’s transport sector

World Bank National Urban Transport Improvement Project (NUTRIP)N/A

African Development Bank (AfDB)

Small Towns and Rural Water Supply and Sanitation ProjectSupport for institutional development, water supply and waste water infrastructure

African Development Bank (AfDB)

Power Transmission System Improvement ProgrammeConstruction of 153km Mwingi-Kitui-Wote-Sultan Hamud line

African Development Bank (AfDB)

Power Transmission System Improvement ProgrammeConstruction of 153km Mwingi-Kitui-Wote-Sultan Hamud line, extension of sub-station at Mwingi and construction of a new substation at Kitui

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP)To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development

Government of Sweden

Kenya Municipal Programme (KMP) To support the Government of Kenya through strengthening local governance and improving urban service delivery

Government of Sweden

Kenya Informal Settlements Improvement Project (KISIP) To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery; and planfor urban growth

World Bank Kenya Informal Settlements Improvement Project (KISIP)To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery ; and plan for urban growth

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

Government of Canada

Creating Safer SchoolsTo improve the safety and quality of school and community environments for 120,000 vulnerable boys and girls

Government of Japan

Mombasa Port Area Road Development Project Construction of bypass (Dongo Kundu)

World Bank Water and Sanitation Services Improvement Project (WaSSIP)The project strives to (a) increase access to reliable, aff ordable and sustainable water supply and sanitation services; and (b) to improve the water and waste water services

World Bank Water and Sanitation Services Improvement Project (WaSSIP)Rehabilitating and extending existing water supply facilities in Coast Water Service Board and new intake works

World Bank Rehabilitation of Bachuma Gate-Maji Ya Chumvi (A109)Rehabilitation of approximately 53km to provide access to economic and social services

Lamu Government of China

Rabai-Malindi-Garsen-Lamu Transmission Line320km 220Kv, 132/33Kv No23 MVA substations at Malindi, Garsen and Lamu to connect Lamu Port to the National grid and strengthen supply to the North Coast

World Bank Water and Sanitation Services Improvement Project (WaSSIP)hTe project strives to (a) increase access to reliable, aff ordable and sustainable water supply and sanitation services; and (b) to improve the water and waste water services

World Bank Kenya Urban Water and Sanitation OBA Fund for Low Income AreasProject aims to increase the number of people in low income areas with access to improved water supply and sanitation services.

World Bank Water and Sanitation Services Improvement Project (WaSSIP)Rehabilitating and extending existing water supply facilities in Coast Water Service Board and new intake works

African Development Bank (AfDB)

Power Transmission System Improvement ProgrammeConstruction of 79km Nanyuki-Nyahururu line, extension of sub-station at Nanyuki and construction of a new sub-station at Nyahururu

African Development Bank (AfDB)

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the Northern Water Services Boards (NWSB)

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

Government of Italy

Installation of High Mast Flood lighting structures High Mast Floodlighting structures distributed in slums

Government of Spain

Loiyangalani-Suswa Line430km 400Kv double circuit line and 400/220kV substations at Liyangalani and Suswa to evacuate 300MW from Lake Turkana Wind Plant

World Bank Northern Corridor Transport Improvement Project (NCTIP)Rehabilitation of Northern corridor and emergency restoration of damaged public assets in order to enhance effi ciency and eff ectiveness of Kenya’s transport sector

World Bank Kenya Urban Water and Sanitation OBA Fund for Low Income AreasDescription: Project aims to increase the number of people in low income areas with access to improved water supply and sanitation services.

Isiolo African Development Bank (AfDB)

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the Northern Water Services Boards (NWSB)

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development

United Nations International Children Education Fund (UNICEF)

NOKET (Girls Scholarships)Reduce the gender disparity especially in ASAL districts. Increase attendance retention and transition of girls especially in the ASAL areas

World Bank Northern Corridor Transport Improvement Project (NCTIP)Rehabilitation of Northern corridor and emergency restoration of damaged public assets in order to enhance effi ciency and eff ectiveness of Kenya’s transport sector

Kirinyaga African Development Bank (AfDB)

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

Machakos African Development Bank (AfDB)

Small Towns and Rural Water Supply and Sanitation ProjectSupport for institutional development, water supply and waste water infrastructure

African Development Bank (AfDB)

Reconstruction of Multinational Arusha-Namanga Athi River Road Lot K: Athi River Namanga sectionReconstruction of the existing bitumen surfaced road to an international trunk road standard with 7m wide shoulders on each side for a total length of 136km. The project includes 5.5km of service roads within the town of Athi River.

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

Government of Sweden

Kenya Municipal Programme (KMP) To support the Government of Kenya through strengthening local governance and improving urban service delivery

Government of Sweden

Kenya Informal Settlements Improvement Project (KISIP) To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery; and planfor urban growth

World Bank Kenya Informal Settlements Improvement Project (KISIP)To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery ; and plan for urban growth

World Bank Northern Corridor Transport Improvement Project (NCTIP)Rehabilitation of Northern corridor and emergency restoration of damaged public assets in order to enhance effi ciency and eff ectiveness of Kenya’s transport sector

Baringo

Kakamega

Kericho African Development

Community Empowerment and Institutional Support Project (CEISP)To help empower poor communities to access socio-economic services in order to reduce poverty and to

African Development Bank (AfDB)

Support To Enhancement of Quality and Relevance in Higher Education, Science and TechnologyThe overall objective of the project is to contribute to high quality education and training in STI.

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP)To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

European Development Fund (EDF)

Northern Corridor Rehabilitation Programme – Phase III (Eldoret-Webuye-Malaba)Rehabilitation of Eldoret-Webuye (59km) and Webuye-Malaba Road (61km) projects. Widening the shoulders from the current 1.5m to 2.0m. reconstruction of seriously deteriorated sections

Government of Sweden

Kenya Municipal Programme (KMP) To support the Government of Kenya through strengthening local governance and improving urban service delivery

Government of Sweden Initiatives

Kenya Informal Settlements Improvement Project (KISIP) To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery; and planfor urban growth

Government of Sweden

Lake Victoria Environment Management Programme (LVEMP) Aimed at generating information to guide policy decisions on sustainable management of the Lake Victoria Basin (LVB). It’s an East African Community (EAC) project under implementation in the fi ve countries that share the Lake Victoria Basin: Burundi, Kenya, Rwanda, Tanzania and Uganda.

World Bank Kenya Informal Settlements Improvement Project (KISIP)To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery ; and plan for urban growth

World Bank Water and Sanitation Services Improvement Project (WaSSIP)Rehabilitating and extending existing water supply facilities in Lake Victoria North Water Service Board (LVNESB) and the rehabilitation and expansion of Lumakanda Kipkaren Water Supply and new intake works

World Bank Western Kenya Community Driven Development and Flood Mitigation ProjectThe project comprises of community driven development. This will support community prioritized investment projects to improve livelihoods and build demand and capacity for local level development

World Bank Energy Sector Recovery Project (ESRP)Strengthening the energy sector regulator capacity to carry out an electricity tariff study and set power tariff s and prepare the secondary legislation

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP)To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

African Development Bank (AfDB)

Power Transmission System Improvement ProgrammeConstruction of 65km Lessos-Kabarnet line, extension of sub-station at Lessos and construction of a new sub-station at Kabarnet

German Development Bank KFW

Bogoria-Silali Geothermal Electricity ProjectDrilling of 20 wells

BometAfrican Development Bank (AfDB)

Power Transmission System Improvement ProgrammeConstruction of 33km Sotik-Bomet line, extension of sub-station at Sotik and construction of a new sub-station at Bomet

African Development Bank (AfDB)

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the Lake Victoria South Water Services Boards (LVSWSB)

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development

Government of Japan

Olkaria Lessos Kisumu Power Lines Construction Project Construction works for transmission lines, expansion of substations and consulting services

World Bank Water and Sanitation Services Improvement Project (WaSSIP)The project strives to (a) increase access to reliable, aff ordable and sustainable water supply and sanitation services; and (b) to improve the water and waste water services

Bungoma

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP)To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

European Development Fund (EDF)

Northern Corridor Rehabilitation Programme – Phase III (Eldoret-Webuye-Malaba)Rehabilitation of Eldoret-Webuye (59km) and Webuye-Malaba Road (61km) projects. Widening the shoulders from the current 1.5m to 2.0m. reconstruction of seriously deteriorated sections

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP)To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

European Development Fund (EDF)

Northern Corridor Rehabilitation Programme – Phase III (Eldoret-Webuye-Malaba)Rehabilitation of Eldoret-Webuye (59km) and Webuye-Malaba Road (61km) projects. Widening the shoulders from the current 1.5m to 2.0m. reconstruction of seriously deteriorated sections

Government of Italy

Installation of High Mast Flood lighting structures High Mast Floodlighting structures distributed in slums

Government of Sweden

Lake Victoria Environment Management Programme (LVEMP) Aimed at generating information to guide policy decisions on sustainable management of the Lake Victoria Basin (LVB). It’s an East African Community (EAC) project under implementation in the fi ve countries that share the Lake Victoria Basin: Burundi, Kenya, Rwanda, Tanzania and Uganda.

World Bank Western Kenya Community Driven Development and Flood Mitigation ProjectThe project comprises of community driven development. This will support community prioritized investment projects to improve livelihoods and build demand and capacity for local level development

World Bank Water and Sanitation Services Improvement Project (WaSSIP)Rehabilitating and extending existing water supply facilities in Lake Victoria North Water Service Board (LVNWSB) and new intake works

Kisumu African Development

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the

Community Empowerment and Institutional Support Project (CEISP)To help empower poor communities to access socio-economic services in order to reduce poverty and to

Development Partners Urban Initiatives

Kajiado African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

Arab Bank for Economic Development in Africa (BADEA)

Rehabilitation of Water Supply and Sewerage for Oloitoktok Town Rehabilitation of Water Supply and sanitation infrastructure for Oloitoktok Town and its environs

Kisii African Development Bank (AfDB)

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the Lake Victoria South Water Services Boards (LVSWSB)

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

Government of Germany (KFW GERMANY)

Development of Water and Sanitation SectorTo supply water to Kericho and Kisii to meet the demand for clean and safe water

Government of Netherlands

Kisii Water Supply and Sanitation Project (Bunyunyu Dam) Building of Bunyunyu Dam to increase water supply in Kisii and Nyamira Counties

Government of Sweden

Lake Victoria Environment Management Programme (LVEMP) Aimed at generating information to guide policy decisions on sustainable management of the Lake Victoria Basin (LVB). It’s an East African Community (EAC) project under implementation in the fi ve countries that share the Lake Victoria Basin: Burundi, Kenya, Rwanda, Tanzania and Uganda.

World Bank Water and Sanitation Services Improvement Project (WaSSIP)The project strives to (a) increase access to reliable, aff ordable and sustainable water supply and sanitation services; and (b) to improve the water and waste water services

Makueni African Development Bank (AfDB)

Power Transmission System Improvement Programme Construction of 153km Mwingi-Kitui-Wote-Sultan Hamud line and the construction of new substations at Wote and Sultan Hamud

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

World Bank Northern Corridor Transport Improvement Project (NCTIP)Rehabilitation of Northern corridor and emergency restoration of damaged public assets in order to enhance effi ciency and eff ectiveness of Kenya’s transport sector

Mandera African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

African Development Bank (AfDB)

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the Northern Water Services Boards (NWSB)

United Nations Development Programme (UNDP)

Economic Empowerment ProgrammeTo enhance and mainstream inclusiveness of the poor and vulnerable in the institutional and policy framework and private sector participation in job-rich and pro-poor growth; and to empower the poor and vulnerable

United Nations International Children Education Fund (UNICEF)

NOKET (Girls Scholarships)Reduce the gender disparity especially in ASAL districts. Increase attendance retention and transition of girls especially in the ASAL areas

Marsabit African Development Bank (AfDB)

Construction of Marsabit-Turbi Road (A2)Part of the Mombasa-Nairobi-Addis Ababa corridor development project with a total length of 121.5km.

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

African Development Bank (AfDB)

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the Northern Water Services Boards (NWSB)

European Development Fund (EDF)

Support to the Road Sector Policy: Regional Roads Component (Merille - Marsabit Road)Upgrading of the 122 km Merille River to Marsabit section of the 1,495km Nairobi - Addis Ababa highway (A2) from the existing gravel surface to paved international standard.

Government of Spain

Loiyangalani-Suswa Line430km 400Kv double circuit line at Liyangalani to evacuate 300MW from Lake Turkana Wind Plant

United Nations International Children Education Fund (UNICEF)

NOKET (Girls Scholarships)Reduce the gender disparity especially in ASAL districts. Increase attendance retention and transition of girls especially in the ASAL areas

KEYAfrican Development Bank (AfDB)

Arab Bank for Economic Development in Africa (BADEA)

Danish International Develop-ment Agency (DANIDA)

European Development Fund (EDF)

European Investment Bank (EIB)

German Development Bank (KFW)

Government of Belgium

Government of Canada

Government of China

United Kingdom

United Nations Development Programme (UNDP)United Nations International Children Education Fund (UNICEF)

WORLD BANK

Government of Finland (FINLAND)Government of France (AFD France)Government of Germany (KFW GERMANY)

Government of Italy

Government of Japan

Government of Netherlands (NETHERLANDS)

Government of Spain

Icelandic International Development Agency (ICEIDA)Nordic Development Fund (NDF)

Organization for Petroleum Exporting Countries (OPEC)

State of Kuwait

Government of Sweden

N/A ‘Data Not Available’

KakamegaKakamega African

Kajiado Government of Belgium

Ngong Hills Wind Power ProjectGreen energy generation for the national grid

Government of Spain

13.6Mw Ngong II Wind Energy ProjectInstallation of additional 13.6Mw wind farm in Ngong Forest by tapping the wind potential prevalent in Ngong area in order to provide additional power to the national grid and hence increase the national power generation

Government of Canada

Reading Kenya To improve primary school children’s reading and writing performance by drawing on Canadian expertise and leadership in literacy development and multilingual education

World Bank Northern Corridor Transport Improvement Project (NCTIP)Rehabilitation of Northern corridor and emergency restoration of damaged public assets in order to enhance effi ciency and eff ectiveness of Kenya’s transport sector

Page 11: Urbanisation in Kenyan Counties urbanisation and absolute ...symbiocitykenya.org/wp-content/uploads/2019/04/Urban-Maps-2015... · Urbanisation in Kenyan Counties This map shows the

Nairobi

Nyandarua

Samburu

Siaya

Taita Taveta

Tana River

Tharaka Nithi

Trans Nzoia

Turkana

Uasin Gishu

Vihiga

Wajir

West Pokot

Nandi

Meru

NairobiNairobi

African Development Bank (AfDB)

Small Towns and Rural Water Supply and Sanitation ProjectSupport for institutional development, water supply and waste water infrastructure

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

African Development Bank (AfDB)

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the Tana Water Services Boards (TWSB)

Government of Italy

Installation of High Mast Flood lighting structures High Mast Floodlighting structures distributed in slums

World Bank Kenya Urban Water and Sanitation OBA Fund for Low Income AreasProject aims to increase the number of people in low income areas with access to improved water supply and sanitation services. The project includes expansion f water treatment works, installation of new transmission and distribution lines and connections into un-served areas

Meru

Mombasa

Nandi

African Development Bank (AfDB)

Support To Enhancement Of Quality And Relevance In Higher Education, Science And TechnologyThe overall objective of the project is to contribute to high quality, education and training in STI.

Danish International Development Agency (DANIDA)

Mombasa Integrated Solid Waste Management Project Funding undertaking of the study

European Investment Bank (EIB)

Mombasa-Nairobi Transmission LineThe project consists of the construction of a 482km 400kv double-circuit transmission line between Rabai (Mombasa) and Embakasi (Nairobi); and the construction of the extension of the Rabai substations

European Development Fund

Maternal and child healthMaternal and child health, family planning and nutrition

Government of France

Water and SanitationFinances the upgrading and extension of drinking water supply and sanitation facilities by building the management and planning capacities of regional water agencies and local public water companies.

Government of France

Solid Waste Management Improvement ProjectN/A

Government of Germany (KFW GERMANY)

Primary and Secondary Education in Poor AreasThe project will assist children from poor areas to have access to formal education

Government of Germany (KFW GERMANY)

Programme development of the Health Sector Support to Health Financing Phase 3 & NbspFinancing of the vouchers for maternity care, family planning and related services within the framework of the output based approach

Government of Italy

Rehabilitation of Likoni Sub District HospitalConstruction of maternity wards and supply of medical equipment in Likoni Sub District Hospital

Government of Italy

Mariakani-Kaloleni Water Supply Project To provide clean and safe water

Government of Japan

Mombasa Port Development (Phase I)Expansion of the pport through development of a new container terminal

Government of Japan

Mombasa Port Area Road Development Project Construction of bypass (Dongo Kundu)

Government of Japan

Master Plan for the Development of Dongo Kundu, Mombasa Special Economic ZoneDevelopment of Master Plan for the Dongo Kundu, Mombasa Special Economic Zone

Government of Sweden

Kenya Municipal Programme (KMP) To support the Government of Kenya through strengthening local governance and improving urban service delivery

Government of Sweden

Kenya Informal Settlements Improvement Project (KISIP) To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery; and planfor urban growth

United Nations Development Programme (UNDP)

Economic Empowerment ProgrammeTo enhance and mainstream inclusiveness of the poor and vulnerable in the institutional and policy framework and private sector participation in job-rich and pro-poor growth; and to empower the poor and vulnerable

World Bank Kenya Informal Settlements Improvement Project (KISIP)To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery ; and plan for urban growth

World Bank Project Title: Water and Sanitation Services Improvement Project (WaSSIP)Description: the project strives to (a) increase access to reliable, aff ordable and sustainable water supply and sanitation services; and (b) to improve the water and waste water services

World Bank Water and Sanitation Services Improvement Project (WaSSIP)Rehabilitating and extending existing water supply facilities in Coast Water Service Board and new intake works

World Bank Kenya Municipal Program (KMP)To strengthen local governance and improve service delivery”

Nakuru

Government of Italy Korogocho Slum Upgrading Slum upgrading

German Development Bank KFW

Nairobi Water Distribution ProjectTo assure supply to under-served areas in Nairobi city

Government of Sweden Kenya Municipal Programme (KMP) To support the Government of Kenya through strengthening local governance and improving urban service delivery

Government of Sweden Kenya Informal Settlements Improvement Project (KISIP) To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery; and planfor urban growth

Government of Sweden Nairobi Metropolitan Services Improvement Programme (NAMSIP) The project aims to strengthen urban services andinfrastructure in the Nairobi Metropolitan Region

Organization of Petroleum Exporting Countries (OPEC)

Kenyatta National Hospital Upgrading Project Construction of new pediatric centre

United Nations Development Programme (UNDP)

Economic Empowerment ProgrammeTo enhance and mainstream inclusiveness of the poor and vulnerable in the institutional and policy framework and private sector participation in job-rich and pro-poor growth; and to empower the poor and vulnerable

World Bank Kenya Informal Settlements Improvement Project (KISIP)To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery ; and plan for urban growth

World Bank Fire Fighting Equipment for Nairobi MetropolitanFirefi ghting equipment consisting of trucks, land rovers and machinery inorder to reduce destruction of life/ property resulting from fi re outbreaks

World Bank Nairobi Metropolitan Services Improvement Project (NAMSIP)The project aims to strengthen urban services and infrastructure in the Nairobi Metropolitan Region

World Bank Water and Sanitation Services Improvement Project (WaSSIP)The project strives to (a) increase access to reliable, aff ordable and sustainable water supply and sanitation services; and (b) to improve the water and waste water services

World Bank Water and Sanitation Services Improvement Project (WaSSIP)Rehabilitating and extending existing water supply facilities in Athi Water Service Board and new intake works

World Bank Nairobi Sanitation ProjectN/A

Migori

African Support To Enhancement Of Quality And Relevance In Higher Education, Science And Technology

African Development Bank (AfDB)

Project Title: Water Services Boards Support ProjectDescription: to improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the Lake Victoria South Water Services Boards (LVSWSB)

African Development Bank (AfDB)

Project Title: Community Empowerment and Institutional Support Project (CEISP) Description: To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

Government of Canada

Project Title: Maternal Access and Infant Survival for Health Advancement Description: to reduce maternal mortality rates by increasing access to quality health care during pregnancy and delivery in Nyeri and Migori regions

Government of Sweden

Lake Victoria Environment Management Programme (LVEMP) Aimed at generating information to guide policy decisions on sustainable management of the Lake Victoria Basin (LVB). It’s an East African Community (EAC) project under implementation in the fi ve countries that share the Lake Victoria Basin: Burundi, Kenya, Rwanda, Tanzania and Uganda.

World Bank Project Title: Water and Sanitation Services Improvement Project (WaSSIP)Description: the project strives to (a) increase access to reliable, aff ordable and sustainable water supply and sanitation services; and (b) to improve the water and waste water services

African Development Bank (AfDB)

Power Transmission System Improvement ProgrammeConstruction of 68km Olkaria-Narok line

African Development Bank (AfDB)

Power Transmission System Improvement ProgrammeExtension of sub-station

African Development Bank (AfDB)

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the Lake Victoria South Water Services Boards (LVSWSB)

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

African Development Bank (AfDB)

Water Supply and SanitationTo support the improvement of water supply and sanitation service in urban, peri-urban and rural communities, under the Rift Valley Water Services Board’s jurisdiction.

European Investment Bank (EIB)

Menengai 400Mw Phase I Geothermal Development ProjectExploring, drilling and investor engagement to meet Kenya’s rapidly increasing demand for power while diversifying increasing sources of power supply by developing the country’s geothermal potential

European Investment Bank (EIB)

Olkaria I & IV Geothermal Extension ProjectOlkaria I & IV Geothermal Extension Project

European Investment Bank (EIB)

Nairobi Ring Energy ProjectMeant to provide an additional transmission capacity for extraction of power from the new Geothermal power plant at Olkaria

Government of China Olkaria IV Geothermal Field Production Drilling ProjectGeothermal well drilling to add 140Mw into the national grid

Government of France Geothermal Olkaria I Unit 4 and 5 and Olkaria IV Power PlantsOne of the projects in the greater Olkaria Geothermal Area (GOCA) located in the Rift Valley, near Lake Naivasha in the Hell’s Gate National ParkGeothermal Olkaria I Unit 4 and 5 and Olkaria IV Power Plants

Government of France Support of the development of Geothermal/Renewable EnergyPurchase of rigs for drilling geothermal wells, training if GDC technical staff and establishment of a power generation and transmission master plan

Government of France Upgrading of the Maai Mahiu-Narok roadReconstruction of the Maai Mahiu-Narok road (B3) on 89.3km and consulting services

Government of France Solid Waste Management Improvement N/A

Government of Japan Olkaria Lessos Kisumu Power Lines Construction Project Construction works for transmission lines, expansion of substations and consulting services

Government of Spain Loiyangalani-Suswa Line430km 400Kv double circuit line and 400/220kV substations at Liyangalani and Suswa to evacuate 300MW from Lake Turkana Wind Plant

Government of Sweden Kenya Municipal Programme (KMP) To support the Government of Kenya through strengthening local governance and improving urban service delivery

Government of Sweden Kenya Informal Settlements Improvement Project (KISIP) To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery; and planfor urban growth

World Bank Kenya Municipal Program (KMP)To strengthen local governance and improve service deliveryInternational Development Association (IDA - WORLD BANK)

World Bank Kenya Informal Settlements Improvement Project (KISIP)To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery ; and plan for urban growth

World Bank Project Title: Kenya Electricity Expansion Project (KEP)To enhance geothermal generation in order to increase the capacity, effi ciency and quality of electricity supply; and expand access to electricity in urban, peri-urban and rural areas

World Bank Lake Victoria Environmental Management Plan (LVEMP)To contribute to the EAC’s vision and strategy framework for management and development of the Lake Victoria Basin

World Bank Northern Corridor Transport Improvement Project (NCTIP)Rehabilitation of Northern corridor and emergency restoration of damaged public assets in order to enhance effi ciency and eff ectiveness of Kenya’s transport sector

World Bank Energy Sector Recovery Project (ESRP)Strengthening the energy sector regulator capacity to carry out an electricity tariff study and set power tariff s and prepare the secondary legislation

NandiAfrican Development Bank (AfDB)

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the Tana Water Services Boards (TWSB)

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

World Bank Kenya Urban Water and Sanitation OBA Fund for Low Income AreasProject aims to increase the number of people in low income areas with access to improved water supply and sanitation services. In Kambirwa and Mirira areas the project aims to supply potable water

World Bank Water and Sanitation Services Improvement Project (WaSSIP)The project strives to (a) increase access to reliable, aff ordable and sustainable water supply and sanitation services; and (b) to improve the water and waste water services

World Bank Water and Sanitation Services Improvement Project (WaSSIP)Rehabilitating and extending existing water supply facilities in Athi Water Service Board and new intake works

World Bank Northern Corridor Transport Improvement Project (NCTIP)Rehabilitation of Northern corridor and emergency restoration of damaged public assets in order to enhance effi ciency and eff ectiveness of Kenya’s transport sector

World Bank Energy Sector Recovery Project (ESRP)Strengthening the energy sector regulator capacity to carry out an electricity tariff study and set power tariff s and prepare the secondary legislation

MurangaAfrican Development Bank (AfDB)

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the Lake Victoria South Water Services Boards (LVSWSB)

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

World Bank Lake Victoria Environmental Management Plan (LVEMP)To contribute to the EAC’s vision and strategy framework for management and development of the Lake Victoria Basin

World Bank Water and Sanitation Services Improvement Project (WaSSIP)The project strives to (a) increase access to reliable, aff ordable and sustainable water supply and sanitation services; and (b) to improve the water and waste water services

World Bank Water and Sanitation Services Improvement Project (WaSSIP)Rehabilitating and extending existing water supply facilities in Lake Victoria North Water Service Board (LVNWSB) and new intake works

Narok African Development Bank (AfDB)

Power Transmission System Improvement ProgrammeConstruction of 68km Olkaria-Narok line and construction of a new sub-station at Narok

African Development Bank (AfDB)

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the Lake Victoria South Water Services Boards (LVSWSB)

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

Government of IcelandNordic Development Fund (NDF)

Suswa ProjectSuswa power generation project

Government of Japan

Narok Water ProjectDevelopment of detailed design for Narok County water supply

Government of Japan

Olkaria Lessos Kisumu Power Lines Construction Project Construction works for transmission lines, expansion of substations and consulting services

Government of Spain

Loiyangalani-Suswa Line400/220kV substation at Suswa to evacuate 300MW from Lake Turkana Wind Plant

World Bank Northern Corridor Transport Improvement Project (NCTIP)Rehabilitation of Northern corridor and emergency restoration of damaged public assets in order to enhance effi ciency and eff ectiveness of Kenya’s transport sector

World Bank Water and Sanitation Services Improvement Project (WaSSIP)The project strives to (a) increase access to reliable, aff ordable and sustainable water supply and sanitation services; and (b) to improve the water and waste water services

Nyamira African Development Bank (AfDB)

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the Lake Victoria South Water Services Boards (LVSWSB)

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

Government of Netherlands

Kisii Water Supply and Sanitation Project (Bunyunyu Dam)Building of Bunyunyu Dam to increase water supply in Kisii and Nyamira Counties

Government of Sweden Lake Victoria Environment Management Programme (LVEMP) Aimed at generating information to guide policy decisions on sustainable management of the Lake Victoria Basin (LVB). It’s an East African Community (EAC) project under implementation in the fi ve countries that share the Lake Victoria Basin: Burundi, Kenya, Rwanda, Tanzania and Uganda.

World Bank Water and Sanitation Services Improvement Project (WaSSIP)The project strives to (a) increase access to reliable, aff ordable and sustainable water supply and sanitation services; and (b) to improve the water and waste water services

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

African Development Bank (AfDB)

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the Northern Water Services Boards (NWSB)

Government of Germany (KFW GERMANY)

Water Services Trust Fund Phase 2 & NbspThe project was developed to ensure water and sanitation availability and access to the poor in the slums in both urban and rural areas

Government of Germany (KFW GERMANY)

Water Sector Development Support (Water Supply and Sanitation for the Urban Poor Programme)Developed to ensure water supply and sanitation availability and access to the poor in urban areas

World Bank Energy Sector Recovery Project (ESRP)Strengthening the energy sector regulator capacity to carry out an electricity tariff study and set power tariff s and prepare the secondary legislation

World Bank Northern Corridor Transport Improvement Project (NCTIP)Rehabilitation of Northern corridor and emergency restoration of damaged public assets in order to enhance effi ciency and eff ectiveness of Kenya’s transport sector

World Bank Kenya Health Sector Support Project (KHSSP)Setting up an eff ective and transparent implementation of KEPH and strengthening the governance and stewardship capacity of MOMS and MOPHS at the national, provincial and district levels

Nairobi

African Development Bank (AFDB)

Nairobi-Thika Highway Improvement ProjectNairobi-Thika Highway improvement works and construction of dual carriageway from Nairobi to Thika

African Development Bank (AfDB)

Nairobi Metropolitan StudiesNairobi Metropolitan Studies

African Development Bank (AfDB)

Nairobi River Basin Rehabilitation and Restoration Programme – Sewerage Improvement ProjectThe components of the project are waste infrastructure – covering rehabilitation and expansion of the sewerage network and treatment - sanitation, hygiene and social environment

African Development Bank (AfDB)

Jomo Kenyatta Airport Interim Terminal Construction Project (Thika Road Project/Education III Project)Project entails utilization of the loan savings from the Nairobi-Thika Highway Improvement project and Education III project to assist GoK to restore the levels pf service at JKIA which had deteriorated following a fi re accident

African Development Bank (AfDB)

Emergency Assistance to Address the damages and losses caused by the August 2013 inferno at JKIAAssistance to be provided to JKIA by improving the security checking system

African Development Bank (AfDB)

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the Athi Water Services Boards (AWSB)

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development

African Development Bank (AfDB)

Nairobi Outering Road Improvement Project Road construction civil works which involves improvement of the existing 13km single carriageway road to a 2-lane dual carriageway complete with service roads, pedestrian foot-over-bridges and walkways

Arab Bank for Economic Development in Africa (BADEA)

Kenyatta National Hospital Upgrading ProjectConstruction of new pediatric centre

Danish International Development Agency (DANIDA)

Promoting Urban Community Participation in Environmental Management Promoting Urban Community Participation in Environmental Management

European Development Fund (EDF)

Nairobi Missing Links Road and Non-motorized Transport FacilitiesProject contributes to implementation of the Japan Interntional Cooperation Agency’s (JICA) fi nanced “Study for the Master Plan for Urban Transport in Nairobi”

European Development Fund (EDF)

Nairobi Informal Settlement Water and Sanitation Improvement Programme (Niswsip)Construction of 4km of sewer systems in informal settlements in Nairobi

European Development Fund (EDF)

Maternal and child healthMaternal and child health, family planning and nutrition

European Development Fund (EDF)

Wezesha Jamii ProgrammePromoting livelihoods and Inclusion of vulnerable women domestic workers and women small scale traders in Kawangware, Korogocho, Kibera and Mukuru slums

European Investment Bank (EIB)

Mombasa-Nairobi Transmission LineThe project consists of the construction of a 482km 400kv double-circuit transmission line between Rabai (Mombasa) and Embakasi (Nairobi); and the construction of the extension of the Embakasi substations

Government of Canada Education for children with disabilitiesEducation for children with disabilities in Kenya targeting six primary schools in urban slums of Dandora and Kibera

Government of China Construction of Nairobi Eastern and Northern Bypasses Road ProjectSite clearance and top soil removal. Aimed at opening the outskirts of Nairobi

Government of China Nairobi-Thika Highway Improvement Project, & Nbsp; Lot 3: Kenyatta University - ThikaImprovement of Thika Road to a four lane carriageway to decongest Thika Road

Government of China Construction of Nairobi Southern bypassRoad decongestion

Government of China Nairobi 132Kv and 66Kv network upgrade and reinforcement Construction of Nairobi City Centre EHV Network upgrade and reinforcement project and Nairobi 66Kv Network upgrade and reinforcement (design, construction and erection of 22Kv underground cable from Embakasi)

Government of France Complementary Funding for Nairobi Water and Sewerage (Nwsepip)The project is meant to support the implementation of components as follows:(i) support the rehabilitation of rehabilitation of the damaged Sasumua Dam spillway and support the implementation of the dam’s safety monitoring instruments(ii) support the rehabilitation of both Ngethu and Sasumua water production plants including rehabilitation of the associated raw water mains(iii) support the rehabilitation of Ngethu-Gigiri-Kabete-Karen water transmission pipelines(iv) undertake the rehabilitation of Nairobi sewers and the Dandora waste water treatment plant(v) support the development and the improvement of water supply and sanitation services in Nairobi’s informal settlements(vi) undertake the preparation of the Nairobi water supply master plan in line WITH Vision 2030(vii) support activities towards the reduction of Non-Revenue Water (NRW) in Nairobi

Government of France Water and SanitationFinances the upgrading and extension of drinking water supply and sanitation facilities by building the management and planning capacities of regional water agencies and local public water companies.

Government of France Nairobi City Public Transport Lane ProjectProviding support for resolving the major congestion problem in Nairobi City, with a reserved lane public transport project

Government of Finland Juja Road Electricity Power Distribution Substation ProjectRenewal of the Juja Road electricity transmission substation

Government of Japan Construction of Nairobi Western Ring Roads (Detailed design)Construction of the Western Ring Roads in order to decongest the roads

Government of Japan Dualling of Nairobi – Dagoretti Corner Road phase IDualling of Nairobi – Dagoretti Corner Road onorder to decongest road

Samburu

Taita Taveta

African Development Bank (AfDB)

Small Towns and Rural Water Supply and Sanitation ProjectSupport for institutional development, water supply and waste water infrastructure

African Development Bank (AfDB)

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the Lake Victoria South Water Services Boards (LVSWSB)

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

Government of Sweden

Lake Victoria Environment Management Programme (LVEMP) Aimed at generating information to guide policy decisions on sustainable management of the Lake Victoria Basin (LVB). It’s an East African Community (EAC) project under implementation in the fi ve countries that share the Lake Victoria Basin: Burundi, Kenya, Rwanda, Tanzania and Uganda.

World Bank Western Kenya Community Driven Development and Flood Mitigation ProjectThe project comprises of community driven development. This will support community prioritized investment projects to improve livelihoods and build demand and capacity for local level development

World Bank Water and Sanitation Services Improvement Project (WaSSIP)The project strives to (a) increase access to reliable, aff ordable and sustainable water supply and sanitation services; and (b) to improve the water and waste water services

Siaya

African Development Bank (AfDB)

Arusha-Holili/Taveta-Voi Road ProjectTo develop the road corridor between Arusha in Tanzania and Voi and to Mombasa Port in Kenya

Government of Canada

Meeting Critical Health Care and Nutritional Needs in KenyaTo contribute to a reduction in maternal, new born and child morbidity and mortality by using an integrated approach to address the health service and nutritional needs of vulnerable populations

United Kingdom

East Africa Transit Improvement Programme (Eatip)/ East Africa Trade Facilitation ProgrammeInfrastructure development at the Taveta and Busia border posts

World Bank Community Empowerment and Institutional Support Project (CEISP)To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

World Bank Water and Sanitation Services Improvement Project (WaSSIP)Rehabilitating and extending existing water supply facilities in Coast Water Service Board and new intake works

World Bank Water and Sanitation Services Improvement Project (WaSSIP)The project strives to (a) increase access to reliable, aff ordable and sustainable water supply and sanitation services; and (b) to improve the water and waste water services

Taita TavetaTaita Taveta

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP)To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

Government of China

Rabai-Malindi-Garsen-Lamu Transmission Line320km 220Kv, 132/33Kv No23 MVA substations at Malindi, Garsen and Lamu to connect Lamu Port to the National grid and strengthen supply to the North Coast

World Bank Water and Sanitation Services Improvement Project (WaSSIP)The project strives to (a) increase access to reliable, aff ordable and sustainable water supply and sanitation services; and (b) to improve the water and waste water services

World Bank Water and Sanitation Services Improvement Project (WaSSIP)Rehabilitating and extending existing water supply facilities in Coast Water Service Board and new intake works

Tana River

Tharaka

African Development Bank (AfDB)Government of China

World Bank

World Bank

African Development Bank (AfDB)

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the Tana Water Services Boards (TWSB)

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

United Nations International Children Education Fund (UNICEF)

East Africa Public Health Laboratory Network Project (EAPLHP)Rehabilitation, expansion and construction of 5 satellite laboratories to expand diagnostic services and develop capacity of laboratory personnel carrying out operational research and facilitate knowledge sharing

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) – Kang’atotha WardTo help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

World Bank Water and Sanitation Services Improvement Project (WaSSIP)Rehabilitating and extending existing water supply facilities in Lake Victoria North Water Service Board (LVNWSB) and new intake works

African Development Bank (AfDB)

NOKET (Girls Scholarships)Reduce the gender disparity especially in ASAL districts. Increase attendance retention and transition of girls especially in the ASAL areas

African Development Bank Group (AfDB)

Lake Turkana Wind FarmWill add 300Mw to power generation capacity in Kenya. It will be the largest wind power project in Africa

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

Government of Canada

Improving Access to Quality EducationTo increase the number of school going children, especially girls, and provide them with a better education

United Nations International Children Education Fund (UNICEF)

Extractive Industries For Sustainable Development In KenyaGoverning of the extractive sectors of Kenya’s economy in more participatory, equitable and sustainable ways to ensure that they contribute to peace and sustainable human development.

United Nations Development Programme (UNDP)

Nairobi Ring Energy ProjectMeant to provide an additional transmission capacity for extraction of power from the Lake Turkana Wind Power Plant

African Development Bank (AfDB)

Timboroa-Eldoret Road ProjectRehabilitation of 73km of the road to bituminous standard

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP)To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development

African Development Bank (AfDB)

Power Transmission System Improvement ProgrammeConstruction of 431km of 132kV lines, the extension of 6 sub-stations and the construction of 8 new sub-stations that will contribute to the capacity of Kenya to increase the number of new connections by 200,000 annually

European Development Fund (EDF)

Northern Corridor Rehabilitation Programme – Phase III (Eldoret-Webuye-Malaba)Rehabilitation of Eldoret-Webuye (59km) and Webuye-Malaba Road (61km) projects. Widening the shoulders from the current 1.5m to 2.0m. reconstruction of seriously deteriorated sections

European Investment Bank (EIB)

Moi Teaching And Referral Hospital : Academic Model Providing Access To Healthcare (AMPATH)Integrated program that coordinates a comprehensive HIV and Tuberculosis care in Western Kenya and providing support in the delivery of primary care at the community and facility levels including maternal child health, family planning and reproductive health

Government of Sweden

Kenya Municipal Programme (KMP) To support the Government of Kenya through strengthening local governance and improving urban service delivery

Government of Sweden

Kenya Informal Settlements Improvement Project (KISIP) To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery; and planfor urban growth

World Bank Kenya Informal Settlements Improvement Project (KISIP)To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery ; and plan for urban growth

World Bank Water and Sanitation Services Improvement Project (WaSSIP)Rehabilitating and extending existing water supply facilities in Lake Victoria North Water Service Board (LVNWSB) and new intake works

Nithi

Trans Nzoiaish

Turkana

African Timboroa-Eldoret Road ProjectUasin Gishu

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP)To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

Government of Sweden

Lake Victoria Environment Management Programme (LVEMP) Aimed at generating information to guide policy decisions on sustainable management of the Lake Victoria Basin (LVB). It’s an East African Community (EAC) project under implementation in the fi ve countries that share the Lake Victoria Basin: Burundi, Kenya, Rwanda, Tanzania and Uganda.

World Bank Water and Sanitation Services Improvement Project (WaSSIP)Rehabilitating and extending existing water supply facilities in Lake Victoria North Water Service Board (LVNWSB) and new intake works

World Bank Western Kenya Community Driven Development and Flood Mitigation ProjectThe project comprises of community driven development. This will support community prioritized investment projects to improve livelihoods and build demand and capacity for local level development

World Bank Energy Sector Recovery Project (ESRP)Strengthening the energy sector regulator capacity to carry out an electricity tariff study and set power tariff s and prepare the secondary legislationNyeri African Development

Bank (AfDB)Small Towns and Rural Water Supply and Sanitation ProjectSupport for institutional development, water supply and waste water infrastructure

African Development Bank (AFDB)

Power Transmission System Improvement ProgrammeConstruction of 33km Ishiara-Kieni line, extension of sub-station at Ishiara and construction of a new sub-station at Kieni

African Development Bank (AFDB)

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the Tana Water Services Boards (TWSB)

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP) To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

German Development Bank KFW

Kenya Municipal Water ProjectTo expand water treatment plants and water intake, and rehabilitate sewerage treatment works

Government of Canada Maternal Access and Infant Survival for Health Advancement To reduce maternal mortality rates by increasing access to quality health care during pregnancy and delivery in Nyeri and Migori regions

Government of Sweden Kenya Municipal Programme (KMP) To support the Government of Kenya through strengthening local governance and improving urban service delivery

Government of Sweden Kenya Informal Settlements Improvement Project (KISIP) To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery; and planfor urban growth

World Bank Kenya Informal Settlements Improvement Project (KISIP)To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery ; and plan for urban growth

World Bank Kenya Urban Water and Sanitation OBA Fund for Low Income AreasProject aims to increase the number of people in low income areas with access to improved water supply and sanitation services. In Mathira Constituency the project aims to improve water supply replacing the current dilapidated system and expansion to new areas without services

NyeriNyeri

African Development Bank (AfDB)

NOKET (Girls Scholarships)Reduce the gender disparity especially in ASAL districts. Increase attendance retention and transition of girls especially in the ASAL areas

African Development Bank (AfDB)

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the Northern Water Services Boards (NWSB)

State of Kuwait Wajir District Hospital ConstructionConstruction and extension of maternity unit

United Kingdom Wajir Integrated Development ProjectWater supply and sewerage system designated for Wajir Town, while water supply to be done to the towns along the river

United Nations International Children Education Fund (UNICEF)

East Africa Public Health Laboratory Network Project (EAPLHP)Rehabilitation, expansion and construction of 5 satellite laboratories to expand diagnostic services and develop capacity of laboratory personnel carrying out operational research and facilitate knowledge sharing

World Bank Community Empowerment and Institutional Support Project (CEISP)To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

African Development Bank (AfDB)

Additional Water WorksAdditional works related to previous unfi nished connections and other works

African Development Bank (AfDB)

Community Empowerment and Institutional Support Project (CEISP)To help empower poor communities to access socio-economic services in order to reduce poverty and to improve the management of local socio-economic development.

Government of Italy Scholarships For Students To extend scholarships to needy students

Government of Italy Capacity BuildingTo build the capacity of instructors

West Pokot

Wajir

Vihiga

Disclaimer:This series of urban mapsand info-graphics was produced by SymbioCity Kenya in 2015. Their purpose is to start a dialogue on urbanisation in Kenya. The maps are produced with fi nancial assistance from the Swedish International Development Agency (Sida). They are put together from available information from secondary sources and are not to be interpreted as a fl awless description of the actual situation. Any mistakes or oversights are unintentional and the responsibility of SymbioCity Kenya.You are welcome to copy, distribute and present the maps, pro-vided that you attribute the content to SymbioCity Kenya.

Page 12: Urbanisation in Kenyan Counties urbanisation and absolute ...symbiocitykenya.org/wp-content/uploads/2019/04/Urban-Maps-2015... · Urbanisation in Kenyan Counties This map shows the

Development Partners Urban Initiatives by Sector

EnErGy AfricAn DEvELopmEnT bAnk (AfDb)

Lake Turkana Wind Farm ProjectWill add 300Mw to power generation capacity in Kenya. It will be the largest wind power project in AfricaImplementing Agency: Ministry of Energy and Petroleum

Project duration: started working with

project developer from 2009

Total: Sh6.5 billion

AfricAn DEvELopmEnT bAnk Group (AfDb)

Power Transmission System Improvement ProgrammeConstruction of 431km of 132kV lines, the extension of 6 sub-stations and the construction of 8 new sub-stations that will contribute to the capacity of Kenya to increase the number of new connections by 200,000 annuallyImplementing Agency: Ministry of Energy and Petroleum

Project duration: August 2011 – March 2015

Total: KSh4.7 billion

EuropEAn invEsTmEnT bAnk (Eib)

220Kv Ring around Nairobi MetropolisConstruction of 180km, 220Kv double circuit ring around Nairobi and 6no. 22/66kV substations to transfer capacity and increase power reliabilityImplementing Agency: Ministry of Energy and Petroleum

Project duration: 2011-2015

Total: N/A

EuropEAn invEsTmEnT bAnk (Eib)

Menengai 400Mw Phase I Geothermal Development ProjectExploring, drilling and investor engagement to meet Kenya’s rapidly increasing demand for power while diversifying increasing sources of power supply by developing the country’s geothermal potentialImplementing Agency: Ministry of Energy and Petroleum

Project duration: September 2012 – June 2019

Total: Sh847 million

EuropEAn invEsTmEnT bAnk (Eib)

Mombasa-Nairobi Transmission LineThe project consists of the construction of a 482km 400kv double-circuit transmission line between Rabai (Mombasa) and Embakasi (Nairobi); and the construction of the extension of the Rabai and Embakasi substationsImplementing Agency: Ministry of Energy and Petroleum

Project duration: January 2010 - June 2014

Total: Sh19.5 billion

EuropEAn invEsTmEnT bAnk (Eib)

Nairobi Ring Energy ProjectMeant to provide an additional transmission capacity for extraction of power from the new Geothermal power plants at Olkaria and from Lake Turkana Wind Power PlantImplementing Agency: Ministry of Energy and Petroleum

Project duration: February 2012 – March 2017

Total: Sh2.2 billion

EuropEAn invEsTmEnT bAnk (Eib)

Olkaria I & IV Geothermal Extension Project

Olkaria I & IV Geothermal Extension ProjectImplementing Agency: Ministry of Energy and Petroleum

Project duration: to be completed on February

2011 - February 2017

Total: KSh1.107 billion

GErmAn DEvELopmEnT bAnk kfW

Bogoria-Silali Geothermal Electricity ProjectDrilling of 20 wellsImplementing Agency: Ministry of Energy and Petroleum

Project duration: N/A

Total: Sh8.9 billion

GovErnmEnT of bELGium

Ngong Hills Wind Power ProjectGreen energy generation for the national gridImplementing Agency: Ministry of Energy and Petroleum

Project duration: 33/4 years

Total: Sh1.7 billion

GovErnmEnT of bELGium

Thika-Gatundu West Power Line Reconstruction ProjectReconstruction of the Thika-Gatundu West 132Kv electrifi cation lineImplementing Agency: Ministry of Energy and Petroleum

Project duration: April 2009 – June 2014

Total: Sh1.3 billion

GovErnmEnT of cHinA

Nairobi 132Kv and 66Kv network upgrade and reinforcement Construction of Nairobi City Centre EHV Network upgrade and reinforcement project and Nairobi 66Kv Network upgrade and reinforcement (design, construction and erection of 22Kv underground cable from Embakasi)Implementing Agency: Ministry of Energy and Petroleum

Project duration: July 2014 – June 2017

Total: Sh11.6 billion

GovErnmEnT of cHinA

Olkaria IV Geothermal Field Production Drilling Project

Geothermal well drilling to add 140Mw into the national gridImplementing Agency: Ministry of Energy and Petroleum

Project duration: January 2011 – January 2016

Total: Sh23 billion

GovErnmEnT of cHinA

Rabai-Malindi-Garsen-Lamu Transmission LineConstruction of 320km 220Kv, 132/33Kv No23 MVA substations at Malindi, Garsen and Lamu to connect Lamu Port to the National grid and strengthen supply to the North CoastImplementing Agency: Ministry of Energy and Petroleum

Project duration: July 2010 – June 2017

GovErnmEnT of finLAnD

Juja Road Electricity Power Distribution Substation ProjectRenewal of the Juja Road electricity transmission substationImplementing Agency: Ministry of Energy and Petroleum

Project duration: January 2014 – June 2016

Total: Sh2.4 billion

GovErnmEnT of frAncE

220Kv Ring around Nairobi MetropolisConstruction of 180km, 220Kv double circuit ring around Nairobi and 6no. 22/66kV substations to transfer capacity and increase power reliabilityImplementing Agency: Ministry of Energy and Petroleum

Project duration: 2011-2015

Total: N/A

GovErnmEnT of frAncE

Geothermal Olkaria I Unit 4 and 5 and Olkaria IV Power PlantsOne of the projects in the greater Olkaria Geothermal Area (GOCA) located in the Rift Valley, near Lake Naivasha in the Hell’s Gate National ParkImplementing Agency: Ministry of Energy and Petroleum

Project duration: July 2011 – December 2015

Total: Sh15.3 billion

GovErnmEnT of frAncE

Support of the development of Geothermal/Renewable EnergyPurchase of rigs for drilling geothermal wells, training if GDC technical staff and establishment of a power generation and transmission master planImplementing Agency: Ministry of Energy and Petroleum

Project duration: May 2010 – January 2016

Total: Sh5.7 billion

GovErnmEnT of icELAnDnorDic DEvELopmEnT funD (nDf)

Suswa ProjectSuswa power generation projectImplementing Agency: Ministry of Energy and Petroleum

Project duration: March 2014 – June 2018

Total: Sh11.9 billion

GovErnmEnT of iTALy

Installation of High Mast Flood lighting structuresHigh Mast Floodlighting structures distributed to slums in various parts of the countryImplementing Agency: Ministry of Land Housing and Urban Development

Project duration: August 2012 – August 2013

GovErnmEnT of JApAn

Olkaria Lessos Kisumu Power Lines Construction ProjectConstruction works for transmission lines, expansion of substations and consulting services Implementing Agency: Ministry of Energy and Petroleum

Project duration: March 2013 - June 2018

Total: Sh13.9 billion

GovErnmEnT of spAin

13.6Mw Ngong II Wind Energy ProjectInstallation of additional 13.6Mw wind farm in Ngong Forest by tapping the wind potential prevalent in Ngong area in order to provide additional power to the national grid and hence increase the national power generationImplementing Agency: Ministry of Energy and Petroleum

Project duration: Approximately 5 years

Total: Sh1.9 billion

GovErnmEnT of spAin

Development of Solar Energy in KenyaTo facilitate development of solar energy in several ASAL Districts in the 47 countiesImplementing Agency: Ministry of Energy and Petroleum

Project duration: September 2011 – January

2015

Total: Sh1.3 billion

GovErnmEnT of spAin

Loiyangalani-Suswa LineConstruction of 430km 400Kv double circuit line and 400/220kV substations at Liyangalani and Suswa to evacuate 300MW from Lake Turkana Wind PlantImplementing Agency: Ministry of Energy and Petroleum

Project duration: 2010-2012

Total: N/A

WorLD bAnk

Energy Sector Recovery Project (ESRP)Strengthening the energy sector regulator capacity to carry out an electricity tariff study and set power tariff s and prepare the secondary legislationImplementing Agency: Ministry of Energy and Petroleum

Project duration: July 2009 – December 2013

Total: Sh12.2 billion

WorLD bAnkKenya Electricity Expansion Project (KEP)To enhance geothermal generation in order to increase the capacity, effi ciency and quality of electricity supply; and expand access to electricity in urban, peri-urban and rural areasImplementing Agency: Ministry of Energy and Petroleum

Project duration: May 2010 – May 2016

Total: KSh26.6 billion

WorLD bAnkKenya Electricity Modernization Project The project aims to increase access to electricity; improve reliability to electricity service; and to strengthen KPLCs fi nancial situationImplementing Agency: Ministry of Energy and Petroleum

Project duration: March 2015 – June 2020

Total: Sh5.8 billion

Total: Sh9.1 billion

Total: Sh69 million

GovErnmEnT of sWEDEn

Lake Victoria Environment Management Programme (LVEMP)Aimed at generating information to guide policy decisions on sustainable management of the Lake Victoria Basin (LVB). It’s an East African Community (EAC) project under implementation in the fi ve countries that share the Lake Victoria Basin: Burundi, Kenya, Rwanda, Tanzania and Uganda.Implementing Agency: Ministry of Environment, Water and Natural Resources

Project duration: N/A

Total: At least Sh3 billion

GovErnmEnT of sWEDEn

Lake Victoria Initiative (LVI)To contribute to poverty reduction in a sustainable development framework in the Lake Victoria Region. This is an East African Community (EAC) project under implementation in the fi ve countries that share the Lake Victoria Basin: Burundi, Kenya, Rwanda, Tanzania and Uganda.Implementing Agency: Ministry of Environment, Water and Natural Resources

Project duration: Approximately 20 years

Total: N/A

GovErnmEnT of sWEDEn

National Urban Development Policy (NUDP)Formulation of National Urban Development Policy (NUDP) in order to improve urban development training Implementing Agency: Ministry of Land Housing and Urban Development

Project duration: January 2010 – February 2016

Total: Sh13.998 billion

GovErnmEnT of sWEDEn

Kenya Informal Settlements Improvement Project (KISIP)To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery; and plan for urban growthImplementing Agency: Ministry of Land Housingand Urban Development

Total: Sh8.3 billion

Project duration: Approx. 6 years

GovErnmEnT of sWEDEn

Kenya Municipal Programme (KMP) To support the Government of Kenya through strengthening local governance and improving urban service delivery Implementing Agency: Ministry of Devolution and Planning

Project duration: April 2010 – May 2015

Total: Sh7.8 billion

urbAn DEvELopmEnT

EuropEAn DEvELopmEnT funD (EDf)

Nairobi Informal Settlement Water and Sanitation Improvement Programme (Niswsip)Construction of 4km of sewer systems in informal settlements in NairobiImplementing Agency: Ministry of Devolution and Planning

Project duration: January 2008 – June 2012

Total: Sh538 million

GovErnmEnT of frAncE

Kisumu Urban Project (KUP)To enhance the living conditions of Kisumu’s population by introducing a comprehensive urban programme. The project will fi nance needed public infrastructure and facilities, slum upgrading and local capacityImplementing Agency: Ministry of Devolution and Planning

Project duration: May 2010 – April 2014

Total: Sh1 billion

GovErnmEnT of iTALy

KKB Settlement Infrastructure Improvement Programme

To improve infrastructure in the slum areas of Kilifi Implementing Agency: Ministry of Devolution and Planning

Project duration: July 2012 – June 2018

Total: Sh60 million

GovErnmEnT of iTALy

Korogocho Slum Upgrading

Slum upgradingImplementing Agency: Ministry of Land Housing and Urban Development

Project duration: January 2009 – December

2013

Total: Sh340 million

GovErnmEnT of iTALy

Slum Upgrading in Kilifi

To upgrade the infrastructure of slums in Kilifi Implementing Agency: Ministry of Devolution and Planning

Project duration: Started on January 2013

Total: Sh60 million

GovErnmEnT of sWEDEn

Formulation of National Urban Development PolicyPreparation of a National Urban Development Policy (NUDP) in order to improve urban development and planning.Implementing Agency: Ministry of Land Housing and Urban Development

Project duration: January 2010 – February 2016

Total: Sh13.998 billion

GovErnmEnT of sWEDEn

Land Reform Support ProgrammeLand reform process as a catalyst for poverty reduction through improved access to land, security of tenure and improvement of livelihoods in informal settlementsImplementing Agency: Ministry of Land Housing and Urban Development

Project duration: December 2005 – January 2016

Total: Sh1 billion

un HAbiTAT

Kenya Slum Upgrading Project (KENSUP)Aimed at improving the livelihoods of people living and working in slums and informal settlement in the urban areas of Kenya through the provision of security of tenure and physical and social infrastructure as well as providing opportunities for housing improvement and income generationImplementing Agency: Ministry of Land Housing and Urban Development

Total: Sh884 billion

WorLD bAnk

Fire Fighting Equipment for Nairobi MetropolitanFirefi ghting equipment consisting of trucks, land rovers and machinery in order to reduce destruction of life/ property resulting from fi re outbreaksImplementing Agency: Ministry of Land Housing and Urban Development

Project duration: July 2014 – June 2015

Total: Sh612 million

WorLD bAnk

Kenya Informal Settlements Improvement Project (KISIP)To strengthen institutions and programme management; invest in security of tenure; invest in infrastructure and service delivery ; and plan for urban growthImplementing Agency: Ministry of Land Housing and Urban Development

Project duration: Approximately 6 years

Total: Sh8.3 billion

WorLD bAnk

Kenya Municipal Program (KMP)To strengthen local governance and improve service delivery in selected municipalitiesImplementing Agency: Ministry of Devolution and Planning

Project duration: April 2010 – May 2015

Total: Sh7.8 billion

WorLD bAnk

Nairobi Metropolitan Services Improvement Project (NAMSIP)The project aims to strengthen urban services and infrastructure in the Nairobi Metropolitan RegionImplementing Agency: Ministry of Land Housing and Urban Development

Project duration: May 2012 – June 2017

Total: Sh24.4 billion

WorLD bAnk

Western Kenya Community Driven Development and Flood Mitigation ProjectThe project comprises of community driven development. This will support community prioritized investment projects to improve livelihoods and build demand and capacity for local level development Implementing Agency: Ministry of Interior and Coordination of National Government; Ministry of Devolution and Planning

Project duration: June 2007 – August 2015

Total: Sh5.7 billion

WATEr AnD sAniTATion

AfricAn DEvELopmEnT bAnk (AfDb)

Nairobi River Basin Rehabilitation and Restoration Programme – Sewerage Improvement ProjectThe components of the project are waste infrastructure – covering rehabilitation and expansion of the sewerage network and treatment - sanitation, hygiene and social environmentImplementing Agency: Ministry of Environment Water and Natural Resources

Project duration: June 2011 -January 2016 Total: Sh3.5 billion

AfricAn DEvELopmEnT bAnk (AfDb)

Small Towns and Rural Water Supply and Sanitation ProjectSupport for institutional development, water supply and waste water infrastructureImplementing Agency: Ministry of Environment Water and Natural Resources

Project duration: Approximately 41/2 years Total: Sh9.7 billion

AfricAn DEvELopmEnT bAnk (AfDb)

Water Supply and SanitationTo support the improvement of water supply and sanitation service in urban, peri-urban and rural communities, under the Rift Valley Water Services Board’s jurisdictionImplementing Agency: Ministry of Environment Water and Natural Resources

Total: Sh2.8 billion

AfricAn DEvELopmEnT bAnk (AfDb)

Water Services Boards Support ProjectTo improve water supply and sanitation services in urban, peri-urban and rural communities within the service areas of the Athi, Lake Victoria South , Northern and Tana Water Services BoardsImplementing Agency: Ministry of Environment Water and Natural Resources

Project duration: Approximately 8 yearsTotal: Sh2.5 billion

ArAb bAnk for Economic DEvELopmEnT in AfricA (bADEA)

Garissa Sewerage ProjectSewerage project to cover Garissa and its environsImplementing Agency: Ministry of Environment Water and Natural Resources

Project duration: Approximately 10 years Total: Sh4 million

ArAb bAnk for Economic DEvELopmEnT in AfricA (bADEA)

Rehabilitation of Water Supply and Sewerage for Oloitokitok TownRehabilitation of water supply and sanitation infrastructure for Oloitokitok Town and its environsImplementing Agency: Ministry of Environment Water and Natural Resources

Project duration: May 2013 – September 2017Total: Sh167.9 million

DAnisH inTErnATionAL DEvELopmEnT AGEncy (DAniDA)

Mombasa Integrated Solid Waste Management ProjectFunding undertaking of the studyImplementing Agency: Ministry of Environment Water and Natural Resources

Project duration: N/A Total: Sh18.1 million

DAnisH inTErnATionAL DEvELopmEnT AGEncy (DAniDA)

Promoting Urban Community Participation in Environmental ManagementPromoting Urban Community Participation in Environmental Management Implementing Agency: Ministry of Environment Water and Natural Resources

Project duration: project was approved on December 9th 2008Total: Sh6.3 million

EuropEAn DEvELopmEnT funD (EDf)

Improving Access to Water Supply and Basic Sanitation for the Urban PoorThe project aims to improve access to water supply and basic sanitation for the urban poorImplementing Agency: Ministry of Environment Water and Natural Resources

Project duration: Approximately 63/4 years Total: N/A

EuropEAn DEvELopmEnT funD (EDf)

Nairobi Informal Settlement Water and Sanitation Improvement Programme (Niswsip)Construction of 4km of sewer lines in informal settlements, construction of 5.8km waterlines in informal settlements and construction of 74 ablution blocks and 141 water kiosksImplementing Agency: Ministry of Environment Water and Natural Resources

Project duration: January 2008 – December 2013Total: Sh538.3 million

GovErnmEnT of frAncE

Coast Water and Sanitation ProgrammeThe project is meant to supply safe and clean water to the City of Mombasa and its environs through expansion and rehabilitation of water supply and sewerage systemsImplementing Agency: Ministry of Environment Water and Natural Resources

Project duration: project started on December 2008 – July 2015 Total: Sh900 million

The project is meant to support the implementation of components as follows:(i) support the rehabilitation of rehabilitation of the damaged Sasumua Dam spillway and support the implementation of the dam’s safety monitoring instruments(ii) support the rehabilitation of both Ngethu and Sasumua water production plants including rehabilitation of the associated raw water mains

(iii) support the rehabilitation of Ngethu-Gigiri-Kabete-Karen water transmission pipelines(iv) undertake the rehabilitation of Nairobi sewers and the Dandora waste water treatment plant(v) support the development and the improvement of water supply and sanitation services in Nairobi’s informal settlements (vi) undertake the preparation of the Nairobi water supply master plan in line WITH Vision 2030

(vii) support activities towards the reduction of Non-Revenue Water (NRW) in NairobiImplementing Agency: Ministry of Environment Water and Natural ResourcesProject duration: project was planned to start on

January 2009 – April 2015

GovErnmEnT of frAncE

Complementary Funding for Nairobi Water and Sewerage (Nwsepip)

GovErnmEnT of frAncE

Solid Waste Management Improvement ProjectImplementing Agency: Ministry of Environment Water and Natural Resources

Project duration: N/ATotal: N/A

GovErnmEnT of frAncE

Water and SanitationFinances the upgrading and extension of drinking water supply and sanitation facilities by building the management and planning capacities of regional water agencies and local public water companies.Implementing Agency: Ministry of Environment Water and Natural Resources

Project duration: 2012-2015Total: N/A

GovErnmEnT of GErmAny (GiZ GErmAny)

Water Sector Development Support (Water Supply and Sanitation for the Urban Poor Programme)Developed to ensure water supply and sanitation availability and access to the poor in urban areasImplementing Agency: Ministry of Environment Water and Natural ResourcesProject duration: project was started on January

2009 – May 2015Total: Sh1.3 billion

GovErnmEnT of GErmAny (kfW GErmAny)

Development of Water and Sanitation Sector (Lake Victoria South)To supply water to Kericho and Kisii to meet the demand for clean and safe waterImplementing Agency: Ministry of Environment Water and Natural Resources

Project duration: January 2012 – January 2016 Total: Sh3.6 billion

GovErnmEnT of GErmAny (kfW GErmAny)

Kenya Municipal Water ProjectTo expand water treatment plants and water intake, and rehabilitate sewerage treatment worksImplementing Agency: Ministry of Environment Water and Natural Resources

Project duration: N/ATotal: Sh1.1 billion

GovErnmEnT of GErmAny (kfW GErmAny)

Nairobi Water Distribution ProjectTo assure supply to under-served areas in Nairobi cityImplementing Agency: Ministry of Environment Water and Natural Resources

Project duration: N/A Total: Sh3.7 billion

GovErnmEnT of GErmAny (kfW GErmAny)

Water Sector Development Programme (Lake Victoria North)To supply clean and safe waterImplementing Agency: Ministry of Environment Water and Natural ResourcesProject duration: project was started on January 2009 – December 2014Total: Sh1.2 billion

GovErnmEnT of GErmAny (kfW GErmAny)

Water Sector ReformsSupporting the water ministry in sector reformImplementing Agency: Ministry of Environment Water and Natural ResourcesProject duration: planned start date was January 2006 January 2015 Total: Sh200 million

GovErnmEnT of GErmAny (kfW GErmAny)

Water Services Trust Fund Phase 2 & NbspThe project was developed to ensure water and sanitation availability and access to the poor in the slums in both urban and rural areasImplementing Agency: Ministry of Environment Water and Natural ResourcesProject duration: January 2011 – January 2015 Total: Sh97.4 billion

GovErnmEnT of iTALy

Additional Water Works

Additional works related to previous unfi nished connections and other worksImplementing Agency: State Department for Water and Regional Authorities.Project duration: February 2014 – June 2015Total: Sh49.5 million

GovErnmEnT of iTALy

Mariakani-Kaloleni Water Supply Project

To provide clean and safe water Implementing Agency: Ministry of Environment Water and Natural ResourcesProject duration: July 2012 – June 2016Total: Sh90 million

GovErnmEnT of JApAn

Narok Water Project

Development of detailed design for Narok County Water supplyImplementing Agency: Ministry of Environment Water and Natural ResourcesProject duration: project was approved on October 2012 – January 2016 Total: Sh1 billion

GovErnmEnT of nETHErLAnDs

Kisii Water Supply and Sanitation Project (Bunyunyu Dam)

Building of Bunyunyu Dam to increase water supply in Kisii and Nyamira Counties Implementing Agency: Ministry of Environment Water and Natural ResourcesProject duration: June 2014 –February 2016Total: Sh60 million

GovErnmEnT of sWEDEn

Kenya Water and Sanitation Programme

Programme in the water sector within the areas of water supply and sanitation, water resources management, support to water sector reform process and fl ood and drought mitigationImplementing Agency: Ministry of Environment Water and Natural ResourcesProject duration: planned start date was January 2005 – January 2017Total: Sh5 billion

orGAniZATion for pETroLEum ExporTinG counTriEs (opEc)

Garissa Sewerage Project

Sewerage project to cover Garissa and its environsImplementing Agency: Ministry of Environment Water and Natural ResourcesProject duration: Approximately 101/4 years

uniTED kinGDom

Wajir Integrated Development Project

Water supply and sewerage system designated for Wajir Town, while water supply to be done to the towns along the riverImplementing Agency: Ewaso Ngiro North Development Authority (ENNDA)Project duration: January 2011 – January 2021

uniTED nATions inTErnATionAL cHiLDrEn EDucATion funD (unicEf)

Water and Sanitation Services (WASH)

Improvement of hygiene among children in schoolsImplementing Agency: Ministry of EducationProject duration: planned start date was January 2008 - January 2016 Total: Sh575 million

WorLD bAnk

Kenya Urban Water and Sanitation OBA Fund for Low Income Areas

Project aims to increase the number of people in low income areas with access to improved water supply and sanitation servicesImplementing Agency: Ministry of Environment Water and Natural ResourcesProject duration: November 2014 – June 2018Total: Sh1.2 billion

WorLD bAnk

Lake Victoria Environmental Management Plan (LVEMP)

To contribute to the EAC’s vision and strategy framework for management and development of the Lake Victoria Basin Implementing Agency: Ministry of Environment Water and Natural ResourcesProject duration: January 2009 - June 2016Total: N/A

WorLD bAnk

Nairobi Sanitation Project

Project duration: December 2012 – June 2017Total: Sh7.4 million

WorLD bAnk

Water and Sanitation Services Improvement Project (WaSSIP)

Rehabilitating and extending existing water supply facilities in Athi Water Service Board, Coast Water Service Board and Lake Victoria North Water Service Board. Rehabilitation and expansion of Lumakanda Kipkaren Water Supply and new intake works Implementing Agency: Ministry of Environment Water and Natural ResourcesProject duration: April 2008 – December 2012Total: Sh9.8 billion

WorLD bAnk

Water and Sanitation Services Improvement Project (WaSSIP)

The project strives to (a) increase access to reliable, aff ordable and sustainable water supply and sanitation services; and (b) to improve the water and waste water servicesImplementing Agency: Ministry of Environment Water and Natural ResourcesProject duration: December 2007 - December 2017

Total: Sh3.1 billion

Total: Sh4 million

Total: Sh1.6 billionImplementing Agency: Ministry of EducationProject duration: planned start date was January 2008 - January 2016 Total: Sh575 millionTotal: Sh20.2 billion

GEnErAL Economic AnD commErciAL AffAirs

AfricAn DEvELopmEnT bAnk (AfDb)

Community Empowerment and Institutional Support Project (CEISP)

EuropEAn DEvELopmEnT funD (EDf)

Wezesha Jamii Programme

Promoting livelihoods and Inclusion of vulnerable women domestic workers and women small scale tradersImplementing Agency: N/A

Project duration: Project started on May 2015 Total: Sh247.6 million

GovErnmEnT of JApAn

Master Plan for the Development of Dongo Kundu, Mombasa Special Economic ZoneDevelopment of a Master Plan for the Dongo Kundu, Mombasa Special Economic ZoneImplementing Agency: Ministry of Industrialization and Enterprise Development

Project duration: November 2013 – August 2018 Total: Sh26 billion

uniTED nATions DEvELopmEnT proGrAmmE (unDp)

Economic Empowerment ProgrammeTo enhance and mainstream inclusiveness of the poor and vulnerable in the institutional and policy framework and private sector participation in job-rich and pro-poor growth; and to empower the poor and vulnerableImplementing Agency: Ministry of Devolution and Planning

Project duration: February 2013 – June 2018Total: Sh130.5 million

uniTED nATions DEvELopmEnT proGrAmmE (unDp)

Extractive Industries For Sustainable Development In KenyaGoverning of the extractive sectors of Kenya’s economy in more participatory, equitable and sustainable ways to ensure that they contribute to peace and sustainable human development.Implementing Agency: National Treasury; Ministry of Mining

Project duration: November 2013 – December 2015

Total: Sh5.7 billion

Comprises of the following two components:(a) capacity building which aims at developing the capacity of communities and other local level stakeholders to make better, more focused and equitable use of resources made available through devolved funds at the same time the project will support activities which assist in aggregating the voices of women and girls, and to

sensitize communities and local stakeholders towards their needs, abilities and potential(b) strengthening decentralized development planning and fi nance by facilitating eff ective people-centred decentralized development planning and management . Implementing Agency: Ministry of Devolution and PlanningProject duration: January 2010 – June 2016

Total: Sh2.8 million

Page 13: Urbanisation in Kenyan Counties urbanisation and absolute ...symbiocitykenya.org/wp-content/uploads/2019/04/Urban-Maps-2015... · Urbanisation in Kenyan Counties This map shows the

Development Partners Urban Initiatives by SectorHEALTH ArAb bAnk for

Economic DEvELopmEnT in AfricA (bADEA)

Kenyatta National Hospital Upgrading ProjectConstruction of new pediatric centreImplementing Agency: Ministry of Health

Project duration: January 2011 –March 2017 Total: Sh20.4 million

EuropEAn DEvELopmEnT funD (EDf)

Maternal and child healthMaternal and child health, family planning and nutritionImplementing Agency: Ministry of Health

Project duration: N/ATotal: N/A

GovErnmEnT of cAnADA

Maternal Access and Infant Survival for Health Advancement

To reduce maternal mortality rates by increasing access to quality health care during pregnancy and delivery in Nyeri and Migori regionsImplementing Agency: Ministry of Health

Project duration: September 2012 - December 2017Total: Sh1.7 billion

GovErnmEnT of cAnADA

Meeting Critical Health Care and Nutritional Needs in KenyaTo contribute to a reduction in maternal, new born and child morbidity and mortality by using an integrated approach to address the health service and nutritional needs of vulnerable populations Implementing Agency: Ministry of Health

Project duration: February 2012 – April 2015Total: Sh172.2 million

GovErnmEnT of cHinA

Kenyatta University Teaching and Referral Hospital ProjectConstruction and equipment of teaching and referral hospital at Kenyatta UniversityImplementing Agency: Ministry of Education

Project duration: February 2012 February 2016 Total: Sh3.4 billion

GovErnmEnT of GErmAny (GiZ GErmAny)

Development of the Health Sector (Health Swap)The project entails increasing accessibility and utilization of quality heath services; strengthening of processes and procedures of health support systems and facilitation of efficient and effective heath delivery systemImplementing Agency: Ministry of Health

Project duration: January 2006 – January 2015 Total: Sh200 million

GovErnmEnT of GErmAny (kfW GErmAny)

Development of the Health SectorTo assist the government in financing reproductive healthImplementing Agency: Ministry of Health

Project duration: January 2010 – January 2015Total: Sh825 million

GovErnmEnT of GErmAny (kfW GErmAny)

Programme development of the Health Sector Support to Health Financing Phase 3 & NbspFinancing of the vouchers for maternity care, family planning and related services within the framework of the output based approachImplementing Agency: Ministry of Health

Project duration: January 2012 – January 2015 Total: Sh2.5 billion

GovErnmEnT of GErmAny (kfW GErmAny)

Reproductive and Sexual HealthTo support the Government of Kenya in financing reproductive health including family planning to reduce the birth rateImplementing Agency: Ministry of Health

Project duration January 2012 – January 2016 Total: Sh880 million

GovErnmEnT of GErmAny (kfW GErmAny)

Reproductive Health – Output Based Approach (OBA) ProjectIncreased uptake of reproductive health services by poor and vulnerable womenImplementing Agency: Ministry of Health

Project duration: February 2011 February 2014Total: Sh1.6 billion

GovErnmEnT of iTALy

Rehabilitation of Likoni Sub District HospitalConstruction of maternity wards and supply of medical equipment in Likoni Sub District Hospital Implementing Agency: Ministry of Health

Project duration: July 2012 – August 2016Total: Sh18.96 million

orGAniZATion of pETroLEum ExporTinG counTriEs (opEc)

Kenyatta National Hospital Upgrading ProjectConstruction of new pediatric centreImplementing Agency: Ministry of Health

Project duration: January 2011 – March 2017 Total: Sh20.4 million

sTATE of kuWAiT

Wajir District Hospital ConstructionConstruction and extension of maternity unitImplementing Agency: Ministry of Health

Project duration: Approximately 7 yearsTotal: Sh800 million

uniTED kinGDomkEnyA HEALTH proGrAmmE

Support to NGO operations and research both local and international technical assistance and provision of commodities for malaria and family planningImplementing Agency: Ministry of Health

Project duration: January 200 – June 2014 Total: Sh13.8 billion

uniTED sTATEs AGEncy for inTErnATionAL DEvELopmEnT (usAiD)

Moi Teaching And Referral Hospital : Academic Model Providing Access To Healthcare (AMPATH)Integrated program that coordinates a comprehensive HIV and Tuberculosis care in Western Kenya and providing support in the delivery of primary care at the community and facility levels including maternal child health, family planning and reproductive healthImplementing Agency: Ministry of Health; Moi Teaching & Referral Hospital; State Department for Science and Technology

Project duration: March 2012 – June 2018 Total: Sh1.46 billion

WorLD bAnk

East Africa Public Health Laboratory Network Project (EAPLHP)Rehabilitation, expansion and construction of 5 satellite laboratories to expand diagnostic services and develop capacity of laboratory personel carrying out operational research and facilitate knowledge sharingImplementing Agency: Ministry of Health

Project duration: October 2010 – June 2015 Total: Sh1.9 billion

WorLD bAnk

Kenya Health Sector Support Project (KHSSP)Setting up an effective and transparent implementation of KEPH and strengthening the governance and stewardship capacity of MOMS and MOPHS at the national, provincial and district levelsImplementing Agency: Ministry of Health

Project duration: July 2010 - January 2017 Total: Sh8.1 billion

African Development bank (AfDb)Support for Technical, Industrial, Vocational and Entrepreneurship Training (TIVET)Construction of new TIVET institutions and upgrading the current ones; human capacity building and curriculum review and development; and the creation of centre of excellence and integration of ICTImplementing Agency: Ministry of Education

Project duration: Approximately 6 years

Total: Sh2.8 billion

AfricAn DEvELopmEnT bAnk (AfDb)

Support to Enhancement of Quality and Relevance in Higher Education, Science and TechnologyTo contribute to high quality education and training in STIImplementing Agency: Ministry of Education

Project duration: September 2013 – October 2018

Total: Sh3.8 billion

GovErnmEnT of cAnADA

Creating Safer SchoolsTo improve the safety and quality of school and community environments for 120,000 vulnerable boys and girlsImplementing Agency: Ministry of Education

Project duration: July 2014 -August 2019

Total: Sh1.2 billion

GovErnmEnT of cAnADA

Education for children with disabilitiesEducation for children with disabilities in Kenya targeting six primary schools in urban slums of Dandora and KiberaImplementing Agency: Ministry of Education

Project duration: N/A

Total: N/A

GovErnmEnT of cAnADA

Improving Access to Quality EducationTo increase the number of children, especially girls, attending schools in Garissa and Turkana Counties and provide them with a better educationImplementing Agency: Ministry of Education

Project duration: March 2013 -March 2016

Total: Sh712.1 million

GovErnmEnT of cAnADArEADinG kEnyA

To improve primary school children’s reading and writing performance by drawing on Canadian expertise and leadership in literacy development and multilingual educationImplementing Agency: Ministry of Education

Project duration: January 2014 - June 2018

Total: Sh308.2 million

GovErnmEnT of GErmAny (kfW GErmAny)

Primary and Secondary Education in Poor Areas The project will assist children from poor areas to have access to formal educationImplementing Agency: Ministry of Devolution and Planning

Project duration: Approximately 6 years

Total: Sh2.59 billion

GovErnmEnT of GErmAny (kfW GErmAny)

Primary Education in Poor Urban AreasThe project will assist children from poor urban areas to have access to formal educationImplementing Agency: Ministry of Devolution and Planning

Project duration: January 2007 – January 2015

Total: Sh 180 million

GovErnmEnT of iTALy

Capacity BuildingTo build the capacity of instructors Implementing Agency: State Department for Science and Technology

Project duration: February 2014 – June 2017

Total: Sh13.9 million

GovErnmEnT of iTALy

Scholarships for StudentsTo extend scholarships to needy studentsImplementing Agency: State Department for Science and Technology

Project duration: February 2014 – June 2017

Total: Sh9.3 million

uniTED nATions inTErnATionAL cHiLDrEn EDucATion funD (unicEf)

Early Childhood Development Interventions to improve quality of early childhood education especially in ASAL districts and informal settlements in major townsImplementing Agency: Ministry of Education

Project duration: Approximately 7 years

Total: Sh3.7 million

uniTED nATions inTErnATionAL cHiLDrEn EDucATion funD (unicEf)

NOKET – Northern Kenya Education Trust - (Girls Scholarships)Reduce the gender disparity especially in ASAL districts. Increase attendance retention and transition of girls especially in the ASAL areasImplementing Agency: Ministry of Devolution and Planning

Project duration: Approximately 7 years depending with county

Total: Sh39.1 million

TrAnsporT AfricAn DEvELopmEnT bAnk (AfDb)

Arusha-Holili/Taveta-Voi Road ProjectTo develop the road corridor between Arusha in Tanzania and Voi and to Mombasa Port in Kenya Implementing Agency: Ministry of Transport and InfrastructureProject duration: September 2013 – October 2018 Total: Sh9.6 billion

AfricAn DEvELopmEnT bAnk (AfDb)

Construction of Marsabit-Turbi Road (A2)Part of the Mombasa-Nairobi-Addis Ababa corridor development project with a total length of 121.5km.Implementing Agency: Ministry of Transport and Infrastructure Project duration: May 2011 – April 2014 Total: Sh13 billion

AfricAn DEvELopmEnT bAnk (AfDb)

Jomo Kenyatta Airport Interim Terminal Construction Project (Thika Road Project/Education III Project)Project entails utilization of the loan savings from the Nairobi-Thika Highway Improvement project and Education III project to assist GoK to restore the levels pf service at JKIA which had deteriorated following a fire accidentImplementing Agency: Ministry of Transport and InfrastructureProject duration: November 2013 – June 2015Total: Sh2.4 billion

AfricAn DEvELopmEnT bAnk (AfDb)

Nairobi Metropolitan StudiesNairobi Metropolitan StudiesImplementing Agency: Ministry of Transport and InfrastructureProject duration: January 2013 – January 2014 Total: Sh120 million

AfricAn DEvELopmEnT bAnk (AfDb)

Nairobi Outering Road Improvement ProjectRoad construction civil works which involves improvement of the existing 13km single carriageway road to a 2-lane dual carriageway complete with service roads, pedestrian foot-over-bridges and walkwaysImplementing Agency: Ministry of Transport and Infrastructure Project duration: March 2014 – December 2018Total: Sh9.9 billion

AfricAn DEvELopmEnT bAnk (AfDb)

Nairobi-Thika Highway Improvement ProjectNairobi-Thika Highway improvement works and construction of dual carriageway from Nairobi to ThikaImplementing Agency: Ministry of Transport and InfrastructureProject duration: April 2007 – May 2013Total: Sh30 million

AfricAn DEvELopmEnT bAnk (AfDb)

Reconstruction of Multinational Arusha-Namanga Athi River Road Lot K: Athi River Namanga sectionReconstruction of the existing bitumen surfaced road to an international trunk road standard with a 7m wide shoulders on each side for a total length of 136km. The project includes 5.5km of service roads within the towns of Athi River, Kitengela, Isinya, Ilbissis and Namanga.The works also include:- construction of junctions, accesses and bus lay bys- provision and erection of road furniture including road markings- 6 new bridges, 8 new box culverts, extending 9 existing box culverts and the construction of pipe culverts, drainage and all other works or things herein required to be done or which may be ordered by the engineer under the provision of the contractImplementing Agency: Ministry of Transport and InfrastructureProject duration: August 10th 2007 –September 2014

AfricAn DEvELopmEnT bAnk (AfDb)

Timboroa-Eldoret Road ProjectRehabilitation of 73km of the road to bituminous standardImplementing Agency: Ministry of Transport and InfrastructureProject duration: October 2011 – April 2016 Total: Sh3.5 billion

EuropEAn DEvELopmEnT funD (EDf)

Nairobi Missing Links Road and Non-motorized Transport Facilities Project contributes to implementation of the Japan Interntional Cooperation Agency’s (JICA) financed “Study for the Master Plan for Urban Transport in Nairobi”Implementing Agency: Ministry of Transport and InfrastructureProject duration: Approximately 7 yearsTotal: Sh4 billion

EuropEAn DEvELopmEnT funD (EDf)

Northern Corridor Rehabilitation Programme – Phase III (Eldoret-Webuye-Malaba)Rehabilitation of Eldoret-Webuye (59km) and Webuye-Malaba Road (61km) projects. Widening the shoulders from the current 1.5m to 2.0m. reconstruction of seriously deteriorated sectionsImplementing Agency: Ministry of Transport and InfrastructureProject duration: November 2007 – December 2016Total: N/A

EuropEAn DEvELopmEnT funD (EDf)

Support To The Road Sector Policy: Regional Roads Component (Merille - Marsabit Road)Upgrading of the 122 km Merille River to Marsabit section of the 1,495km Nairobi - Addis Ababa highway (A2) from the existing gravel surface to paved international standard.Implementing Agency: Ministry of Transport and Infrastructure; Kenya National Highway AuthorityProject duration: October 2012 - October 2017Total: Sh17.5 billion

GovErnmEnT of cHinA

Construction of Eastern and Northern Bypass (Mombasa Road/City Cabanas interchange and complimentary works)Consists of the Mombasa Road/City Cabanas interchange and complimentary worksImplementing Agency: Ministry of Transport and InfrastructureProject duration: March 2013 – March 2014Total: Sh2.5billion

GovErnmEnT of cHinA

Construction of Nairobi Eastern and Northern Bypasses Road ProjectSite clearance and top soil removal. Aimed at opening the outskirts of NairobiImplementing Agency: Ministry of Transport and InfrastructureProject duration: February 2009 – August 2015 Total: Sh12.1 billion

GovErnmEnT of cHinA

Construction of Nairobi Southern bypass Road decongestionImplementing Agency: Ministry of Transport and InfrastructureProject duration: February 2012 – August 2016 Total: Sh22.1 billion:

GovErnmEnT of cHinA

Development of Mombasa to Nairobi Standard Gauge railwayDevelopment of Mombasa to Nairobi Standard Gauge railwayImplementing Agency: Ministry of Transport and InfrastructureProject duration: July 2013 – June 2018Total: Sh6.7 billion

GovErnmEnT of cHinA

Nairobi-Thika Highway Improvement Project, & Nbsp; Lot 3: Kenyatta University – ThikaImprovement of Thika Road to a four lane carriageway to decongest Thika RoadImplementing Agency: Ministry of Transport and InfrastructureProject duration: July 2009 – December 2015 Total: Sh9.4billion

GovErnmEnT of frAncENairobi City Public Transport Lane ProjectProviding support for resolving the major congestion problem in Nairobi City, with a reserved lane public transport project.Implementing Agency: Ministry of Transport and InfrastructureProject duration: N/A Total: N/A

GovErnmEnT of frAncE

Upgrading of the Maai Mahiu-Narok roadReconstruction of the Maai Mahiu-Narok road (B3) on 89.3km and consulting servicesImplementing Agency: Ministry of Transport and InfrastructureProject duration: N/A Total: N/A

GovErnmEnT of JApAn

Construction of Nairobi Western Ring Roads (Detailed design)Construction of the Western Ring Roads in order to decongest the roads Implementing Agency: Ministry of Transport and InfrastructureProject duration: June 2011 – October 2015Total: Sh1.8 billion

GovErnmEnT of JApAn

Dualling of Nairobi – Dagoretti Corner Road phase IDualling of Nairobi – Dagoretti Corner Road onorder to decongest roadImplementing Agency: Ministry of Transport and InfrastructureProject duration: July 2014 – June 2016 Total: Sh1 billion

GovErnmEnT of JApAn

Mombasa Port Area Road Development ProjectConstruction of bypass (Dongo Kundu)Implementing Agency: Ministry of Transport and InfrastructureProject duration: July 2012 – June 2016 Total: Sh18.6 billion

GovErnmEnT of JApAn

Mombasa Port Development (Phase I)Expansion of the port through development of a new container terminal to enhance the container handing capacity at the port and to provide handling equipment Implementing Agency: Ministry of Transport and InfrastructureProject duration: July 2011 – July 2016Total: Sh22.99 billion

uniTED kinGDom

East Africa Transit Improvement Programme (Eatip)/ East Africa Trade Facilitation ProgrammeInfrastructure development at the Taveta and Busia border postsImplementing Agency: Ministry of Transport and InfrastructureProject duration: November 2012 – June 2014 Total: Sh1 billion

WorLD bAnk

Kenya Transport Sector Support Project (KTSSP)The project endeavors to:(a) increase the efficiency of road transport along the Northern corridor and the Tanzania-Kenya-Sudan road corridor(b) enhance aviation safety and security to meet international standards(c) improve the institutional arrangements and capacity in the transport sectorImplementing Agency: Ministry of Transport and InfrastructureProject duration: Approximately 51/4 years Total: KSh300 million

WorLD bAnk

National Urban Transport Improvement Project (NUTRIP)Implementing Agency: Ministry of Transport and InfrastructureProject duration: Approximately 5 years Total: Sh25 billion:

WorLD bAnk

Northern Corridor Transport Improvement Project (NCTIP)Rehabilitation of Northern corridor and emergency restoration of damaged public assets in order to enhance efficiency and effectiveness of Kenya’s transport sectorImplementing Agency: Ministry of Transport and Infrastructure Project duration: Approximately 11 yearsTotal: N/A

WorLD bAnk

Rehabilitation of Bachuma Gate-Maji Ya Chumvi (A109)Rehabilitation of approximately 53km to provide access to economic and social services Implementing Agency: Ministry of Transport and InfrastructureProject duration: January 2013 – July 2015 Total: Sh4.3 billion

EDucATion

Total: Sh6.2 billion

Disclaimer:This series of urban mapsand info-graphics was produced by SymbioCity Kenya in 2015. Their purpose is to start a dialogue on urbanisation in Kenya. The maps are produced with financial assistance from the Swedish International Development Agency (Sida). They are put together from available information from secondary sources and are not to be interpreted as a flawless description of the actual situation. Any mistakes or oversights are unintentional and the responsibility of SymbioCity Kenya.You are welcome to copy, distribute and present the maps, provided that you attribute the content to SymbioCity Kenya.

Page 14: Urbanisation in Kenyan Counties urbanisation and absolute ...symbiocitykenya.org/wp-content/uploads/2019/04/Urban-Maps-2015... · Urbanisation in Kenyan Counties This map shows the

County Urban Governance Tools

ish

ga

Mom-basa

Laikipia

Nyandarua

Nyeri

Muranga

Baringo

Garissa

Isiolo

Mandera

Marsabit

Samburu

Kirinyaga

Kitui

Tana River

Machakos

Kiambu

Nakuru

Nairobi

Nairobi

Meru

Tharaka Nithi

Elgeyo Marakwet

Uasin Gishu

Turkana

Wajir

Bungoma

Trans Nzoia

West Pokot

KakamegaKakamega

Nandi

Kericho

Busia

Busia

Siaya

Vihiga

Homa Bay

Migori

Kisumu

Kisii

Kisii

Nyamira

Nyamira

Bomet

Narok

Kajiado

Taita Taveta

Makueni

Kilifi

Lamu

Kwale

Embu

Mombasa

This map shows various governance and management

approaches counties are using in urban areas

KEY

County Budget and Economic Forums (CBEFs)They are meant to serve as the primary institution for ensuring public participation in public finances in order to im-prove accountability and public participation at the county level.Baringo County, Bomet County, Bungoma County, Busia County,Embu County, Elgeyo/ Marakwet County, Homabay County, Kajiado County, Kakamega County, Kericho Count, Kiambu County, Kilifi County, Kirin-yaga County, Kisii County, Kisumu County, Kitui County, Kwale County, Laikipia County, Machakos Coun-ty, Makueni County, Meru County, Mombasa County, Murang’a County, Nairobi County, Nakuru County, Nandi County, Nyandarua County, Nyeri County, Samburu County, Siaya County, TaitaTaveta County, TharakaNithi County, Trans Nzoia County, Uasin Gishu County

Youth Empowerment Programs in urban areas In collaboration with the national government, county governments unveiled these programs following Nairobi’s county success. This will see over 5,000 youth benefit from the projects.Kakamega, Vihiga, Bungoma, Busia, Siaya, Kisumu, Homabay, Migori, Kisii, Nyamira, Mombasa, Lamu, Kilifi, Tana River, Garissa, Wajir, Mandera, Marsabit, Meru, Tharaka Nithi, Embu, Kitui, Machakos, Makuie-ni, Nyandarua , Nyeri, Kirinyaga, Muranga, Kiambu, Turkana, West Pokot, Samburu, Trans Nzoia, Elgeyo Marakwet, Nandi, Baringo, Laikipia, Nakuru, Narok, Kajiado, Kericho

Electronic Revenue and Tax Collection ManagementTo help counties manage their revenue management systems. Started March 2014Nairobi, Bungoma, Kakamega

tax

tax

tax

tax

Online Governance Monitoring Tool Period: 2013 - 2016 Kisumu, Busia, Nyeri, Kwale and Tana River

Local Urban Forums (LUFs)Multi-stakeholder platforms for promoting constructive urban dialogue and consensus building on key urban is-sues relevant for sustainable local urban development as Kenya Nairobi, Kiambu, Mombasa, Kisumu, Nakuru, Uasin Gishu, Embu, Nyeri, Kilifi, Kakamega, Machakos, Garissa and Kitui

LUFs

LUFs

LUFs

LUFs

LUFsLUFs

LUFs

LUFs

LUFs

LUFs

LUFsLUFs

LUFs

LUFs

Urban Centers Governance and Management Counties have formed relevant ministries headed by Executive Secretaries to govern urban areas and related issues.. Many of the counties have decentralized the urban governance through all sub –counties and large towns to include town administrators and managers. All 47 counties

Public participation Counties that had passed the public participation Bill by June 2015 to meet the constitutional obligation for Baringo, Bom-et, Bungoma, Busia, Elgeyo Marakwet, Laikipia, Nakuru, Kericho, Kiambu, Nandi, Nairobi, Nyandarua, Machakos, Meru, Siaya, Turkana, West

Solid Waste Management Initiatives to control and regulate waste disposal, generation and management in urban centers Nakuru, Marsabit, Bomet, Mombasa, Kiambu, Lamu

Security chntrol Management Initiatives to control security and reduce crime related issues in urban areas though proper governance, street lighting, and formulation of laws.Kisii, Nairobi, Turkana Nyeri, Homa bay, Nyamira, Taita Taveta, Machakos, Murang’a, Mombasa, Siaya, Embu

Transport Management Initiatives to control and govern motor vehicle parking, access and related activities in urban areas Kisii, Uasin Gishu, Narok, Nyandarua,

Investment, trading and licensing control.Counties with plans on how to conduct business, acquire license and control investment in their jurisdiction. Bomet, Kakamega ElgeyoBusia , Nyandarua, Marakwet, Kitui, Machakos, Meru, Nairobi, Uasin Gishu, Mombasa, Nakuru, Vihiga, Baringo, , Kiambu, Taita Taveta, Marsabit, Nyamira, Makueni, Kajiado, Kericho, Samburu, West Pokot, Turkana, Murang’a,

P

P

P

P

P PP

P

P

P

P

P

P

P

P

P

P

P P

P

P

ITL

Disclaimer:This series of urban mapsand info-graphics was produced by SymbioCity Kenya in 2015. Their purpose is to start a dialogue on urbanisation in Kenya. The maps are produced with financial assistance from the Swedish International Development Agency (Sida). They are put together from available information from secondary sources and are not to be interpreted as a flawless description of the actual situation. Any mistakes or oversights are unintentional and the responsibility of SymbioCity Kenya.You are welcome to copy, distribute and present the maps, provided that you attribute the content to SymbioCity Kenya.

Page 15: Urbanisation in Kenyan Counties urbanisation and absolute ...symbiocitykenya.org/wp-content/uploads/2019/04/Urban-Maps-2015... · Urbanisation in Kenyan Counties This map shows the

11 COUNTIES

TELEVISION STATIONS

INFORMATION COMMUNICATION TECHNOLOGY CENTRES

COMMUNITY RADIO STATIONS

PUBLIC MEETINGS

TRADITIONAL MEDIA

10 COUNTIES

WEBSITES36 COUNTIES

28 COUNTIES

38 COUNTIES

30 COUNTIES

MEANS OF COMMUNICATION

USED BY COUNTIES

Public Participation in Urban AreasThis poster shows various approaches and mechanisms that are used in public participation and communication in urban areas in counties

PROPORTION OF COUNTIES THAT HAVE DEVELOPED STRUCTURES TO FACILITATE PARTICIPATION

Town hall meet-ings( structured meetings)

Budget preparation and validation fora

Establishment of citizen at county and decentralised units (also in section 22(1) of urban areasand cities Act, 2011)

Avenues for the participation of people’s representatives including but not limited to members of the national assembly and senate

Notice boards, announcing, appointments, procurements, awards and other important announcements of public interest

Information com-munication and technology based platforms Development

projects sites

Number of counties Percentage

Sector Counties

1 CIDP All counties2 Budgets All counties3 Fiscal Paper -4 County legislation -5 KMP, KISIP 126 Spatial planning All counties7 Education -8 Security -9 Tourism -10 Wind Power Generation Marsabit, Turkana, Nyandarua,

Isiolo, Machakos11 Agriculture -

PUBLIC PARTICIPATION TIMELINES GIVEN BY COUNTIES

PARTICIPATION BY SECTOR IN THE COUNTIES

1 Day

1 Week

2 Weeks75%

17%

8%

34

72%

32

68%

37

79%

40

85%

33

70%

35

75%

26

55%

The following counties (10 out of 47), which represents only 21% have prepared bills/acts on public participation in order to anchor the process in law.• BaringoCounty• WestPokot• Laikipia• Busiacounty• Kajiadocounty• MachakosCounty• Mombasacounty• Nakurucounty• Turkanacounty• TaitaTavetacounty

PUBLIC PARTICIPATION LEGISLATION

10 out of 47

21%

79%

This series of urban maps and info-graphics was produced by SymbioCity Kenya in 2015. Their purpose is to start a dialogue on urbanisation in Kenya. The maps are produced with financial assistance from the Swedish International Development Agency (Sida). They are put together from available information from secondary sources and are not to be interpreted as a flawless description of the actual situation. Any mistakes or oversights are unintentional and the responsibility of SymbioCity Kenya. You are welcome to copy, distribute and present the maps, provided that you attribute the content to SymbioCity Kenya.