+ All Categories
Home > Documents > Uruguay - APR Energy · PDF fileUruguay could no longer rely on imports to meet domestic...

Uruguay - APR Energy · PDF fileUruguay could no longer rely on imports to meet domestic...

Date post: 18-Mar-2018
Category:
Upload: vanxuyen
View: 215 times
Download: 0 times
Share this document with a friend
1
additional 100 MW 200 MW in 45 days gas turbines Background The electricity sector of Uruguay is largely based on domestic hydropower, which leaves the country vulnerable to seasonal rainfall patterns. As a result, it is dependent on electricity imports from neighboring countries like Argentina and Brazil. However, given the economic growth and increasing electricity demand of these countries, Uruguay could no longer rely on imports to meet domestic consumption. Solution To add capacity to the national grid and alleviate seasonal and market shortages, APR Energy in 2012 provided a turnkey plant consisting of four high power density FT8 ® MOBILEPAC ® turbine generators. The plant, including the required substation and interconnection works, was completed in less than 45 days. To ensure optimal performance of our state-of-the-art dual-fuel gas turbine technology, we also installed a series of centrifuges to guarantee a clean supply of diesel-oil. Given the immediate need for power, we relied on an Antonov strategic airlift jet to deliver the first MOBILEPAC ® within days. Once in operation, this capacity added 100MW to the national electricity grid and helped provide a temporary solution to mitigate Uruguay’s supply/demand constraints during construction of a permanent generating facility. Outcome In 2012, UTE awarded APR Energy an additional contract to provide an incremental 200MW, bringing its total capacity to 300MW in the country. Extremely satisfied with the service it received, UTE renewed APR Energy’s contract multiple times to run into 2016. Uruguay Case Study Bridging Power Contact Information AMERICAS Jacksonville, USA +1 904 223 2278 Rio de Janeiro, Brazil +55 21 3957 9333 ASIA PACIFIC Singapore +65 6589 9140 EUROPE, MIDDLE EAST & AFRICA Dubai, UAE +971 800 2773 8224 e-mail: [email protected] www.aprenergy.com Twitter: @aprenergyplc | Linkedin: linkedin.com/company/apr-energy | Facebook: facebook.com/aprenergy | YouTube: youtube.com/aprenergy At a glance • 100MW ONLINE LESS THAN 45 DAYS • AIRFREIGHT FOR IMMEDIATE AVAILABILITY • SUPPLEMENT FOR SEASONAL HYDRO REDUCTIONS • REDUCED RELIANCE ON ELECTRICITY IMPORTS • PROJECT EXPANDED TO 300MW Challenges • NEED TO PROVIDE A 150KV SOLUTION WITH 50HZ GENERATING EQUIPMENT • UNCERTAIN QUALITY OF DIESEL OIL FOR DUAL-FUEL GAS TURBINES • AGGRESSIVE INSTALLATION AND COMMISSIONING SCHEDULE
Transcript

additional

100MW

200MW

in45 days

gas turbines

BackgroundThe electricity sector of Uruguay is largely based on domestic hydropower, which leaves the country vulnerable to seasonal rainfall patterns. As a result, it is dependent on electricity imports from neighboring countries like Argentina and Brazil. However, given the economic growth and increasing electricity demand of these countries, Uruguay could no longer rely on imports to meet domestic consumption.

SolutionTo add capacity to the national grid and alleviate seasonal and market shortages, APR Energy in 2012 provided a turnkey plant consisting of four high power density FT8® MOBILEPAC® turbine generators. The plant, including the required substation and interconnection works, was completed in less than 45 days. To ensure optimal performance of our state-of-the-art dual-fuel gas turbine technology, we also installed a series of centrifuges to guarantee a clean supply of diesel-oil. Given the immediate need for power, we relied on an Antonov strategic airlift jet to deliver the first MOBILEPAC® within days. Once in operation, this capacity added 100MW to the national electricity grid and helped provide a temporary solution to mitigate Uruguay’s supply/demand constraints during construction of a permanent generating facility.

OutcomeIn 2012, UTE awarded APR Energy an additional contract to provide an incremental 200MW, bringing its total capacity to 300MW in the country. Extremely satisfied with the service it received, UTE renewed APR Energy’s contract multiple times to run into 2016.

Uruguay

Case StudyBridging Power

Contact Information

AMERICAS

Jacksonville, USA +1 904 223 2278Rio de Janeiro, Brazil +55 21 3957 9333

ASIA PACIFICSingapore +65 6589 9140

EUROPE, MIDDLE EAST & AFRICADubai, UAE +971 800 2773 8224

e-mail: [email protected] www.aprenergy.com

Twitter: @aprenergyplc | Linkedin: linkedin.com/company/apr-energy | Facebook: facebook.com/aprenergy | YouTube: youtube.com/aprenergy

At a glance

• 100MW ONLINE LESS THAN 45 DAYS

• AIRFREIGHT FOR IMMEDIATE AVAILABILITY

• SUPPLEMENT FOR SEASONAL HYDRO REDUCTIONS

• REDUCED RELIANCE ON ELECTRICITY IMPORTS

• PROJECT EXPANDED TO 300MW

Challenges• NEED TO PROVIDE A 150KV SOLUTION WITH 50HZ GENERATING EQUIPMENT

• UNCERTAIN QUALITY OF DIESEL OIL FOR DUAL-FUEL GAS TURBINES

• AGGRESSIVE INSTALLATION AND COMMISSIONING SCHEDULE

Recommended