+ All Categories
Home > Documents > U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX)...

U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX)...

Date post: 19-Jan-2016
Category:
Upload: morgan-benson
View: 219 times
Download: 3 times
Share this document with a friend
50
U.S. epartment of Energy’s Office f Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION on the review of the Daniel Lehman, Chair DOE/SC Review Committee August 17, 2007
Transcript
Page 1: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

U.S. Department of Energy’s

Office of Science

National CompactStellarator Experiment (NCSX)

Princeton Plasma Physics Laboratory (PPPL)

CLOSEOUT PRESENTATIONon the review of the

Daniel Lehman, Chair DOE/SC Review Committee August 17, 2007http://www.science.doe.gov/opa/

Page 2: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

2

Charge Memorandum

1. Is the project’s bottoms-up-estimate credible? Based on the funding guidance provided by the FES Program, is the cost and schedule estimate realistic for the remaining work? Is there an adequately mature design available on complex activities, such as machine assembly, to support the estimate?

2. Is the contingency supported by an consistent with an appropriate project-wide risk analysis? Is there adequate cost and schedule contingency in the new proposed baseline to achieve a high level of confidence in completing the project successfully?

3. Has the Project adequately incorporated developmental and fabrication experiences in the bottoms-up estimate as to increase the success of machine assembly and improve reliability during research operations?

4. Is the project being properly managed and organized at this point, and are future staffing plans at both PPPL and ORNL adequate? What is the level of confidence that the NCSX project team can complete the project within the proposed baseline? Is there adequate support from PPPL and ORNL management?

5. What is the planning level cost and schedule estimate that will be required for the NCSX project to perform Phase III (which includes implementation of all scope that was removed after CD-2) research activities?

Page 3: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

3

Review Committee Participants

Department of Energy

Daniel R. Lehman, DOE/SC, Chairperson

Kin Chao, DOE/SC

Jeff Hoy, DOE/SC

Stephen Meador, DOE/SC

Bruce Strauss, DOE/SC

Consultants

Dave Anderson, U. of Wisconsin

Ralph Brown, BNL

Patrick Hurh, Fermilab

Thomas McManamy, ORNL

Les Price, consultant

Russell Wells, LBNL

Observers

Ray Fonck, DOE/SC

Jeff Makiel, DOE/PAO

Greg Pitonak, DOE/PAO

Page 4: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

4

Report Outline/Writing Assignments

Executive Summary ................................................................................................................. Chao

1. Introduction.................................................................................................................... Sullivan

2. Accomplishments To Date............................................................................................. Sullivan

3. Remaining Technical Scope (Charge Questions 1, 2, 3, and 5)

3.1 Magnets............................................................................................ McManamy*/Strauss

3.1.1 Findings

3.2.1 Comments

3.3.3 Recommendations

3.2 Auxiliary ........................................................................................... Brown*/McManamy

3.3 Final Assembly ..............................................................................................Hurh*/Wells

3.4 Phase III and IV Scope ............................................................................Anderson*/Price

4. Cost Estimate (CQ 1, 2, 3, and 5) ........................................................................Meador*/Chao

5. Schedule and Funding (CQ 1, 2, 3,and 5)............................................................Meador*/Chao

6. Management (CQ 4 and 5)........................................................................Price*/Hoy/Anderson

*Lead

Page 5: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

5

Summary Assessment of the NCSX- 3.1 MagnetsAug 15-17, 2007

T. McManamy

B. Strauss

Page 6: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

6

NCSX- 3.1 Magnets

General Scope Modular Coils & Interface hardware Conventional Coils

PF Coils Central Solenoid TF Coils Trim Coils

Overall ACWP & Proposed Total EAC (M$) Modular Coils 34.2/40.4 Conventional Coils 3.2/6.7

Page 7: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

7

NCSX- 3.1 Magnets EIR Lines of Inquiry

Resource Loaded Schedule Satisfactory

Well developed for MC coils, TF coils. PF coils design, procurement and fab FY08-FY10 – overall schedule appears to have a good level of detail and reasonable durations

Key Project Cost and Schedule Assumptions Satisfactory- Good basis for ETC for majority of work, adequate schedule

contingency, some engineering delayed because of funding profile Critical Path

Satisfactory with comment – MC interface hardware design on critical path- appear to be on schedule for a Sep 07 FDR

Funding profile Satisfactory with comment – flat profile is required but not optimum

Basis of Design Satisfactory with comment – PDR for some systems considered low risk

not yet completed

Page 8: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

8

NCSX- 3.1 Magnets

Findings Modular Coils – 14 of 18 wound and 13 vacuum

impregnated – good basis for ETC TF Coil Procured under fixed price contract PF Coil design and procurement plan underway- Mar 08

Level 2 milestone for PDR Central Solenoid – spare NSTX coil to be used Engineering challenge with Modular Coil interface

hardware design and execution Recent progress on welded approach encouraging

Trim coil design deferred – FDR Dec 08 2 trim coils proposed

Page 9: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

9

NCSX- 3.1 Magnets

Comments There appears enough engineering support

now to eliminate or minimize concurrent engineering of the past

Cost estimates for the work to go appear to have a good basis

Adequate resources are being applied to solve the MC interface hardware design challenge

6 Trim coils would optimize physics

Page 10: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

10

NCSX- 3.1 Magnets

Recommendations Accelerate specific engineering efforts such

PF coil design Trim coil design

Perform cost/benefit analysis of installing additional trim coils

Page 11: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

11

NCSX Project Review

Section 3.2; Ancillary System

WBS: 2,3,4,5, & 6

R. Brown and T. McManamy

Page 12: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

12

WBS 2: Auxiliary Systems Findings:

Fueling and Vacuum Pumping systems were reduced in scope $194k by using a lower capacity existing turbo molecular vacuum pumping system that may meet pressure requirements at half the pumping speed.

EAC: $589k

Status: System design is planned for FY09 start.

Cost: The cost for this system is understood.

Recommendation: Move up PDR schedule.

Page 13: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

13

WBS 3: Diagnostics Findings:

Magnetic diagnostic loop increase in cost of $590k. Initial baseline design was inadequate and found to be more difficult than originally expected due to requirements for insulation and component protection. Increase in instrumentation scope.

Imaging and e-beam mapping decreased $62k due to equipment loans and collaboration arrangements.

EAC: $1,671k Status:

Magnetic Diagnostic System is 60% complete with many of the loops installed on vacuum vessels.

Cost: Well understood for these estimates.

Recommendation: Press on to meet schedule.

Page 14: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

14

WBS 4: Electrical Power Systems

Findings: AC, DC Power Systems, Controls and Protection Systems, Systems

Design and Integration was reduced in scope by $156k to meet minimum CD-4 requirements.

EAC: $3,145k

Status: Systems design is planned for an FY09 start.

Cost: The costs are well understood based on similar installation systems at

PPPL.

Recommendation: Move up PDR schedule.

Page 15: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

15

WBS 5: I & C Systems Findings:

Networking Infrastructure, Central Interface and Control Systems, DAQ and Facility Computing, Facility Timing and Synchronization Systems, Power Supply Control Systems, Safety Interlocks and System Integration has been reduced in scope by $881k to meet minimum requirement to satisfy CD-4 objectives.

EAC: $1,169K

Status: Systems design is planned for FY09 start.

Cost: Well understood from previous designs work.

Recommendation: Conduct safety systems design interface with ES&H.

Page 16: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

16

WBS 6: Facility Systems Findings:

Cryogenic Systems increased by $192k due to design experience on modular coil test facility system.

Vacuum Bake-out Systems has increased by $573k; original induction heating system design was scrapped and a 150 C gas bake-out system will be installed to achieve adequate CD-4 vacuum requirements.

EAC: $$1,403k Status:

Systems design planned for an FY09 start. Cost:

System cost well understood from similar designs. Recommendation:

Study cryogenic system design regulation for multiple parallel paths.

Page 17: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

17

EIR Lines of Inquiry

Resource loaded schedule: Satisfactory; complete and up to date.

Cost & Schedule: Costs understood (done before) Design starts in FY09 (consider earlier)

Critical Path: Off critical path.

Page 18: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

18

WBS 18 Field Period Assembly & WBS 7 Machine Assembly

Patrick Hurh (FNAL)

Russell Wells (LBNL)

NCSX Office of Science Review Close-out

(8-17-07)

3.3

Page 19: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

19

EIR Elements

Resource Loaded Schedule We agree with the project response for the FPA and

Machine Assembly portions of the project.

Key Project Cost and Schedule Assumptions We agree that the schedule estimates are reasonable.

The cost and schedule contingency are adequate given design maturity.

Critical Path We agree that the critical path is rational and

consistent with the RLS.

Page 20: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

20

Findings (1)

Together these make up roughly 42% of the full Project ETC contingency and are the 2 highest contingency values as well as the 2 highest individual ETC values.

Work extends until 1/10 (WBS 18) and until 7/10 (WBS 7).

WBSBaseline

(K$)

Re-Baseline

% Inc.

Spent(K$)

% Spent

ETC(K$)

Cont. (%ETC)

18 5,430 13,583 250% 3,479 26% 10,104 30%

7 4,412 8,914 202% 963 11% 7,951 38%

Page 21: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

21

Findings (2)

3.3.1.4--Increases in WBS 18 are attributed to underestimation of engineering and labor costs associated with assembly of complex, high tolerance, massive components including cost of extensive metrology and field engineering required to custom fit modular coils together.

3.3.1.10-- ….. Design Reviewers consist of PPPL and ORNL personnel, not necessarily external to NCSX project.

3.3.1.18 --Engineering resources at ORNL and PPPL were shown to be currently adequate for the re-baselined tasks. In addition, we found emphatic support at the Directorate level to add any necessary engineering effort.

Page 22: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

22

Comments (1)

3.3.2.1--The project staff should be congratulated on the significant engineering, design, and technical effort over the past months to overcome technical problems and develop detailed assembly plans and equipment. The engineering staff has developed engineering solutions for recent problems in FPA that have a high probability of success. We have not identified any other technical “show-stoppers” that threaten the completion of FPA or Final Assy.

3.3.2.4--…. overall we found the cost estimates and schedule estimates credible, including enough money to ensure success in a realistic environment. Contingency/risk assignment is consistent with the levels of design and status of assembly tasks. The work to develop the assembly plans is commendable and translating those into detailed procedures should be achievable.

Page 23: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

23

Comments (2)

3.3.2.3--Integration of design activities across WBS tasks is not ideal. (…) In addition, recent PDR’s and FDR’s do not seem to successfully integrate these designs and interface features. Management of engineering resources, integration of engineering design activities across WBS tasks, and design review scope and scheduling is considered to be crucial to the assembly tasks. Proper resources should be focused upon this task.

3.3.2.4--Vacuum vessel welding (in Station 6) seems to be underestimated in terms of technical risk. Distortion during these difficult welds needs to be assessed and mitigation efforts should be identified.

Page 24: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

24

Recommendations (1)

3.3.3.1--Scrub the RLS, WAF’s, and BOE’s for accuracy traceability and completeness.

3.3.3.2--Consider accelerating schedule of PDR’s and FDR’s to encourage early design activity and solidify estimates.

3.3.3.3--Include objective experts external to the project on design review teams.

3.3.3.4--Include all integration issues associated with related assembly tasks in design reviews.

Page 25: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

25

Recommendations (2)

3.3.3.4--Add vacuum vessel welding (in Station 6, Final Assy) to the Risk Registry and develop appropriate mitigation activities.

3.3.3.5--Continue to include dry-run fit-ups of the Final Assembly of Modular Coils in the RLS, and plan to perform these tasks even if metrology results appear to “close” properly.

3.3.3.6--Continue to look for opportunities to validate assembly design concepts early in the design process.

3.3.3.7--Ensure that engineering integration across WBS tasks occurs at a high level including interface design consistency, definition and scheduling of design reviews, and engineering resource management. This will require the focus of the responsible engineer as his/her primary activity.

Page 26: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

26

3.4--Phase 3 &Phase 4 Scope

Dave Anderson & Les Price

Page 27: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

27

3.4--Phase 3 &Phase 4 Scope

Findings:

• The project presented a prioritized list of experimental activities to be accomplished in the Phase III campaign for FY-13. These activities have been endorsed by their PAC.

• The goals represent important scientific achievements in understanding the potential of quasisymmetry on global confinement in hot-ion plasmas, initial investigations into the role of stellarator fields in disruption prevention, and obtaining knowledge of scrape-off layer characteristics necessary for upgrades required for Phase IV activities.

• The facility and diagnostic upgrades presented covered all necessary scope to accomplish these goals.

• The planning budget of $34.4M appears adequate to cover the needed costs.

• The schedule appears reasonable providing the needed facilities at the appropriate time for Phase III activities, with a funding profile which takes into account longer lead time articles such as neutral beam refurbishment and Thomson scattering.

Page 28: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

28

3.4--Phase 3 &Phase 4 Scope

Comments:

• The cost and schedule estimate have been developed taking into account resource loading and a funding profile consistent with rolloff of the MIE, and which keeps total NCSX program costs level until FY13.

• The upgrade plans include capabilities in some elements which are required for progressing to Phase IV of the research (such as power systems), and $4.5M in FY13 for long lead items for the FY15 campaign, such as neutral beam units #3 and #4.

• A significant portion of the upgrades are refurbishments of existing equipment, duplication of previously produced systems, or routine in nature resulting in estimates which are on a very sound basis for a planning level. The development of a resource loaded schedule with detailed cost breakouts and a 30% overall contingency provide confidence in these estimates and schedules.

• Funds are planned to start becoming available in FY-10 for these activities. The project should reinvestigate the need, priorities, cost and schedule for the various planned upgrades as this period approaches, commensurate with research forums which will be occurring. Roughly 1/3 of the research is planned to be conducted through collaborations and this needs to be factored into the planning process.

Page 29: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

29

3.4--Phase 3 &Phase 4 Scope

Recommendations:

•Investigate the cost and benefit of inclusion of four additional trim coils into the upgrade plans. Present plans will augment the two coils in the MIE with two additional coils, so that n=1 and n=2 fields can be applied. The addition of two more would provide for control over natural (n=3) islands.

•Coordinate cost and schedule planning between NCSX and NSTX. In FY13, a $25M increase in the NCSX program total occurs as NCSX goes into Phase III operation and the two devices go to alternate year operations. The total available funds must be commensurate with NCSX operations and NSTX station-keeping and upgrade costs and the reverse in the alternate years and with OFES funding.

Page 30: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

30

4.0 Cost Estimate5.0 Schedule and Funding

Steve Meador, DOE/SC

Kin Chao, DOE/SC

Page 31: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

31

1. Resource Loaded Schedule

Committee Response:

The project has a detailed Resource Loaded Schedule using input (resources, activity durations, risk and uncertainty, etc.) from Job Managers and and the bottoms-up cost and schedule estimates.

Page 32: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

32

2. Key Project Cost & Schedule Assumptions

Committee Response:

The project’s cost and schedule assumptions appear to be reasonable.

Cost and schedule contingency have been developed that is supported by detailed analyses.

Additional work needed to more clearly define and document the bases of estimates prior to the EIR.

Page 33: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

33

3. Critical Path

Committee Response:

The project schedule is integrated and identifies activities that are on the critical path and near the critical path.

The Critical Path is reasonably defined with reasonable schedule durations.

Page 34: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

34

4. Funding Profile

Committee Response:

The funding profile is consistent with the Resource Loaded Schedule.

Page 35: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

35

5. Work Breakdown Structure

Committee Response:

The WBS is reasonable and captures all project work. The Resource Loaded Schedule is consistent with the project WBS.

Page 36: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

36

4.0 Cost Estimate - Findings

Completion of MIE Project

Completion of Project Upgrades to achieve Phase 3 Capability

MIE PROJECT TPC FOR CD-4 $142M Project Upgrades for Phase 3 $34.4M Total $176.4M

“To Go” Project costs to achieve Phase 3 Capability

ETC + Contingency + Project Upgrades = Total Cost

$50.9M + $14.4M + $34.4M = $99.7M

CURRENT PROPOSED TPC $101.2M $142M TEC $92.4M $132.4M Estimate to Complete (ETC) N/A $50.9M Cost Contingency N/A $14.4M (28% of ETC) CD-4 July 2009 December 2011 Schedule Contingency N/A 11 Months

Page 37: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

37

4.0 Cost Estimate - Findings

A new, bottoms-up estimate to complete was developed over the past several months

Contingency was estimated using a new probabilistic methodology

A new Resource Loaded Schedule was developed

Page 38: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

38

4.0 Cost Estimate - Comments

The project’s new bottoms-up Estimate to Complete, based on a well defined methodology involving all Job Managers and building on experience to date, adds credibility to the proposed baseline.

The project’s new probabilistic risk and uncertainty analyses is based on the new bottoms-up cost and schedule estimates. The resultant 28% cost contingency and 11 month schedule contingency appear reasonable.

Common estimate formats will aid external reviews, but documentation and traceability will need additional work prior to EIR.

Page 39: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

39

4.0 Cost Estimate - Comments

Overall basis of estimate appears reasonable, but key assumptions need better definition - more detail or be more clearly associated with estimates at various levels within the WBS.

The Committee believes the project can be completed within the cost presented.

Page 40: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

40

4.0 Cost Estimate - Recommendations

1. Institutionalize the new cost and schedule methods and tools (ongoing)

2. Improve the basis of estimate - improved quality bases of estimates (well before the EIR)

3. Ensure the machine capabilities in the FY 2005 baseline and the new proposed baseline are consistent.

Page 41: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

41

5.0 Schedule and Funding - Findings

The project has developed a Resource Loaded Schedule based on detailed input (resources, duration, risks, uncertainties, etc.) from job managers

The schedule is developed at the WBS levels 4 or lower

A significant number of new Level 2 and 3 milestones have been identified to enhance identification of deliverables and management tracking

Page 42: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

42

5.0 Schedule and Funding - Findings

The current funding profile is shown below:

Prior FY

($K) FY2006

($K) FY2007

($K) FY2008

($K) FY2009

($K) FY2010

($K) FY2011

($K) TPC ($K)

Budget Authority $48,188 $19,073 $15,838 $14,483 $15,068 $12,581 $2,602 $127,833

Contingency $144 $2,205 $3,492 $4,450 $4,089 $14,380

Total $48,188 $19,073 $15,982 $16,688 $18,560 $17,031 $6,691 $142,213

Page 43: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

43

5.0 Schedule and Funding - Comments

The project has a good process for developing and updating the resource loaded schedule. However, documentation on some of the WBS elements (i.e., basis of estimates, assumptions, etc.) needs to be improved.

The Committee believes the project can be completed within the schedule presented.

Page 44: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

44

5.0 Schedule and Funding - Recommendations

1. Improve the basis of estimate - improved quality of bases of estimates (well before the EIR)

Page 45: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

45

6.0 Management

Les Price and Jeff Hoy

Page 46: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

46

Management – EIR LOI

6. Risk Management – Risks have been identified, classified, and reflected in contingency analysis

7. Basis of Design – Adequate for most of project. Some areas still lacking definitive designs

16. Integrated Project Team – In general, adequate staffing is available. Sufficient depth exists at PPPL and ORNL to handle additional needs.

Page 47: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

47

6.1 Management - Findings

Strong support from University, PPPL, ORNL, and PSO New, interim Project Manager on board; recruitment of permanent

underway Previously identified high risk items (VV, MCWFs) complete;

FPA/MA are remaining highest risk items Engineering resources needed are well below total available ORNL funding is provided directly from HQ Proposed baseline is constrained by flat funding ground rule – results

in higher cost, delayed schedule, and back-end loaded contingency Management relationship has been established with W-7X Considerable attention being paid to minimizing risks from FPA/MA

hoisting and rigging

Page 48: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

48

6.2 Management - Comments

Relationships among all project participants seem healthy New management already having positive impact – stronger project

management and physics integration; new processes being instituted PEP should be revised to reflect new management processes, e.g. requirement

for 6 month bottoms-up ETC Need to ensure additional University and PPPL oversight adds value and

doesn't hamper project decision-making Engineering resources generally appear adequate; however systems

engineering and integration needs strengthening Would be desirable to expedite design in high risk areas Risk mitigation steps to provide backup staff in key areas is commendable Optimized funding profile would minimize cost and schedule impacts For management flexibility, should consider consolidating funding through

PPPL in FY2008 Consider unofficial management tracking against provisional baseline,

pending results of planned additional DOE reviews

Page 49: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

49

Management -Recommendations

1. Develop an alternate cost/schedule baseline based on an “optimum” funding profile.

2. Provide strong leadership in the systems engineering and integration area.

Page 50: U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.

Office of Science

U.S. Department of Energy

50

Management – Charge Questions

4. Is the project being properly managed and organized at this point, and are future staffing plans at both PPPL and ORNL adequate?

YES

What is the level of confidence that the NCSX project team can complete the project within the proposed baseline?

HIGH

Is there adequate support from PPPL and ORNL management?

YES


Recommended