USAID/USEA/Ministry of PowerGreening The Grid (GTG) India Program
Battery Energy Storage Workshop
November 29, 2018
Vibhu KaushikDirector, Grid Technology & ModernizationSouthern California Edison
1
Southern California Edison in 2018
• 15 million residents in a 50,000 square mile area• 40% energy from carbon‐free sources• Joined open letter to support Paris Climate Accord• Utility Dive “2017 Utility of the Year” for our 2017 Clean Power and Electrification Vision Plan
• Procured close to 500 MW of storage
Supporting California’s 2030 greenhouse gas reduction goals
2
Goals To Improve
• California set a goal to reduce emissions 40% below 1990 levels by 2030, and 80% by 2050.
• SB 100 passed mandating 100% carbon free electric grid by 2045
If we want to get to zero emissions, eventually we have to replace many of the things we rely on today that require combustion.
3
Emissions contributors
• The largest contributor is transportation, followed by the electric sector.
Industrial, and commercial and residential sectors trail not too far behind.
• The most practical andeconomicalway to create real change is for sectors to work together to find an affordable alternative to fossil fuels.
4
SCE’s integrated solution
Clean the power grid. And electrify.
5
Role of the UtilitySCE’s vision: Enable the plug and play grid to enhance system reliability, support customer choice and use of clean energy technologies, to help California meet its clean energy goals.
Strengthen and Modernize the Grid
Modernize Distribution Planning
Influence Regulatory Outcomes that Benefit
Customers
Establish appropriate compensation for DERs
based on the value at the time and location of the
services they deliver
Integrate DERs in grid planning through more
transparent, multi-stakeholder processes,
tools, and analysis
Improve safety and reliability, and increased DER
integration
6
Forecast of DER Penetration at SCE
7
MW 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Energy Efficiency 180 341 546 791 1,034 1,369 1,690 2,007 2,319 2,634 2,948 3,258 3,568
Electric Vehicles 209 265 306 510 634 837 1,106 1,352 1,558 1,734 1,863 1,939 1,963
Solar PV 2,458 2,937 3,490 4,090 4,711 5,327 5,916 6,463 6,955 7,388 7,763 8,085 8,475
Demand Response 53 53 53 53 53 53 53 53 53 53 53 53 53
Energy Storage 68 104 143 186 232 282 337 395 458 525 596 674 756
7
SCE’s Energy Storage
SCE is positioned to respond to grid needs and strategically pursue innovative use cases for energy storage.
Procurement Activity
Contracted Transmission
Capacity (MW)
Contracted Distribution
Capacity (MW)
Contracted Customer
Capacity (MW)LCR RFO 100.5 0 160.5
2014 Energy Storage RFO 0 16.3 0PRP 2 RFO 0 60 20
2016 ACES RFO 0 22* 02016 ACES DBT RFP
(UOS)0 20* 0
Peaker EGT Projects(UOS)
20* 0 0
* Over 60 MW of contracted energy storage is already online2016 ACES RFO: Aliso Canyon Energy Storage Request for Offers2016 ACES DBT RFP: 2016 Aliso Canyon Energy Storage Design, Build & Transfer Request for Proposals Peaker EGT Projects: Peaker Enhanced Gas Turbine Projects
List of AcronymsLCR RFO: Local Capacity Requirement Request for Offers PRP 2 RFO: Preferred Resources Pilot 2nd Request for Offers
9
Energy Storage Overview at SCE
SCE’s Enhanced Gas Turbine (EGT) Installation
Southern California Edison10
11 Southern California Edison
EGT Concept
FUEL SAVINGS
MAINTENANCE
EMISSIONS
10MWLI BATTERY
1.25 MVA
INVERTERS
WATER CONSUMPTION
12 Southern California Edison
EGT Integration Diagram
Hybrid EGT Benefits
• Instant Response/Always Ready Technology
• 50MWs of Operating Reserve• Primary Frequency Response• -8 to +5 MVAR Voltage Support• 134 MW-Secs Inertia• Black Start Technology
Greenhouse Gas Free Attributes
With Fuel Consumption • 50 MWs Peaking Energy for Local
Contingency• 25 MWs of High Speed Frequency
Regulation• Demand Charge Management• Self Managed BESS SOC
ProvidesReduced System Costs & Increases Customer Value‒ Optimized System Dispatch‒ Lower System Fuel Use‒ Lower Maintenance Costs ‒ Lower System GHG Emissions‒ Renewable Energy Integration ‒ Increased Market Participation
Enables
10MW
200s(5-10mins)0
50MW
13
14 Southern California Edison
Purpose:Emergency
Proclamation→CPUCResolution E-4791 & Operational Flexibility
Location: Norwalk, CA
BESS Size: • 10 MW/4.3 MWh
Gas Turbine Size: • 50 MW
Commercial Operation:
Received CAISO confirmation on
12/30/16
Systems are bid into CAISO wholesale
generation market for spinning & non-
spinning reserve and regulation
CENTER EGT
15 Southern California Edison
CENTER BESS
Power Inverter AC to DC – (8) 1.25 MW
Medium Voltage Switchgear
13.8kV Interconnection
Step-Up or Down Transformers 13.8kV : 480V
Battery Enclosure 10MW – 4.3MWh
System Controller GE Mark-V
16 Southern California Edison
• Increase the catalyst cross-sectional area without increasing existing enclosure size
• Improve the SCR ammonia-injection and NOx water-injection tuning
• Increase ammonia concentration from 19% to 29%
• Upgrade sampling probes
Emissions Control System Enhancement
CENTER SCR
17 Southern California Edison
Purpose:Emergency
Proclamation→CPUCResolution E-4791 & Operational Flexibility
Location: Rancho Cucamonga,
CA
BESS Size: • 10 MW/4.3 MWh
Gas Turbine Size: • 50 MW
Commercial Operation:
Received CAISO confirmation on
12/30/16
Systems are bid into CAISO wholesale
generation market for spinning & non-
spinning reserve and regulation
GRAPELAND EGT
18 Southern California Edison
GRAPELAND EGTBattery Enclosure
10MW – 4.3MWh
Power Inverter AC to DC – (8) 1.25 MW
System Controller GE Mark-V
Step-Up or Down Transformers 13.8kV : 480V
Medium Voltage Switchgear
13.8kV Interconnection
Southern California Edison
Hybrid EGT Market Results Since Go-Live
19
Compared with SCE’s non-hybrid peakers over the same period:
• Higher capacity utilization• Lower fuel gas usage• Lower emissions• Higher market revenues
0
5
10
15
20
25
30
35
40
45
50
Hybrid EGT Peakers Non‐EGT Peakers
Average Da
y‐Ah
ead Ca
pacity Sales
(MW)
SCE Peakers Capacity Utilization
Energy Non‐Spin Reg‐Down Reg‐Up Spin
Southern California Edison
Hybrid EGT Recognition and Accolades
• “The SCE-GE project is a perfect example that distributed energy resources can be used in innovative ways and still fully participate in the wholesale energy market managed by the ISO.”
Steve BerberichPresident and CEOCalifornia Independent System Operator
• To date the Hybrid EGT has won four awards:• Edison Electric Institute (EEI) Edison Award• Energy Storage North America (ESNA) Innovation Award• South Coast Air Quality Management District (SCAQMD) Innovative Clean
Air Technology Award• Power Magazine’s Top Plant Award
20
21
Hybrid EGT Recognition and Accolades
“The SCE‐GE project is a perfect example that distributed energy resources can be used in innovative ways and still fully participate in the wholesale energy market managed by the ISO.”
Steve BerberichPresident and CEOCalifornia Independent System Operator
SCE’s Mira Loma Tesla Battery Energy Storage Installation
Southern California Edison22
23 Southern California Edison
Kevin Payne: “This project is part of our vision at Southern California Edison... California has been leading the way with aggressive goals.
Southern California Edison embraces California's clean energy vision.”Source: http://www.latimes.com/business/la-fi-tesla-energy-storage-20170131-story.html
Purpose:Governor Brown’s
Emergency Proclamation→CPUC
Resolution E-4791
Location: Ontario, CA
Adjacent to SCE’s Mira Loma Peaker &
Substation
Size: • 20 MW/80 MWh• Energy for 15,000
homes for 4 hours
Commercial Operation:
Received CAISO confirmation on
12/30/16
Systems are bid into CAISO wholesale
generation market for day ahead and real
time dispatch
24 Southern California Edison
Construction:Facility was
constructed in 90 days through rain and
Holidays
Footprint: ~62,000 square feet
(under one and a half acres)
Components:• 398 Powerpacks• 48 Inverters
Connection: Each system
connected to 12kV circuit that feeds
customers
Considerations:Facility built between
66kV and 220kV transmission lines
Energy Storage Integration Pilots (ESIP)
Southern California Edison25
26
Energy Storage Integration Program (ESIP)
1. Optimize
Grid
3. Reduce
GHG
2. Integrate Renewabl
es
DESI
Deferral
High PV
ESIP Summary• Energy Storage Integration Program (ESIP) Strategy
Summary‒ The ESIP pilot approach is focused on learnings needed to
quantify benefit streams and build future Distributed Energy Resources (DER)/Distribution System Operator (DSO) capabilities
‒ 12 pilots are focused on program areas of:
• Project drivers: ‒ D. 13-10-040 established a 580 MW Energy Storage (ES)
procurement target for SCE (up to 290 MW of utility owned storage allowed)
‒ ESIP is aligned with CPUC goal of market transformation and ES guiding principles
27
1. DSP=distribution substation plan, TSP=transmission substation plan2. $10.3M approved by OU/2015 GRC for DESI 2 & 3, $5.6M approved by CRT for Horoscope (only $5.0M budgeted), $30.8M approved by FRM for 5 pilots
2 DESI Distribution Energy Storage Integration –grid optimization and reliability
3 DeferralTraditional Investment Deferral – identified through DSP and TSP1
3 High PV High PV Penetration –target circuits with >4MW connected PV
4 Strategic OpportunitiesStrategically address additional areas of learning, select with SIPP
APPROVED
Use Case/Benefit Summary (Identified Pilots)
28
Program Bucket
ProjectOnline Date1 Description
1-Optimize Grid 2-Integrate Renewables 3-Reduce
GHGDeferral Mkt-CAISO
Mkt-DSO RPF2 Voltage Depend
ability IC3
DESI DESI 2Q1 2018
Support grid operations for reliability purposes and incorporate advanced controls
TBD postIGP4
X TBD X TBD TBD
Deferral
Cadillac Q4 2018
Two systems % Narrows will defer the need to reconductor approximately 0.89 miles on the Mandalay-San Miguel 66kV line, solving a duct bank violation and N-1 condition.
X X TBD TBD X
YorktownQ4 2019 X X TBD TBD X
HoroscopeON HOLD
Defer a new duct bank and participate in the market as a dual-use system (re-evaluate need in 2018) X X TBD TBD X
High PV
PronghornQ1 2018
Address 11.5 MW of PV and minimize 8 MW back feed during the day from 15 NEM and 6 R21 systems X X X X X
InvaderQ1 2019
Address 5.3 MW of PV and reverse power flow issues from 10 NEM and 4 Rule 21 (R21) systems X X X X X
StealthQ1 2019
Address 4.3 MW of PV from 310 NEM and 2 R21 systems causing a high peak past 7 pm and eliminate back feed X X X X X
Strategic Opportunity
Demo EQ4 2018
Optimize the existing islanding capabilities at SCE’s 11MW Poole Hydro plant and help to facilitate a microgrid with DER controlled resources.
The Strategic Opportunity projects will demonstrate unique applications and use cases targeting lessons
learned not covered by the other ESIP projects. Team is currently evaluating other potential projects
to be selected with SIPP.Ft. Irwin Army BaseQ4 2019
Support a microgrid to ensure continued operation of critical military loads and allow for voluntary islanding to serve national defense interests
DESIDeferralHigh PVStrategic
Need to quantifyTarget Use Case
Need to verify impact1Circuits are proposed, 2RPF=reverse power flow, 3IC=integration capacity, 4IGP=Integrated Grid Project
ESIP Pilot Locations
29
High PV-2019City: Palm SpringsCircuit: Invader
High PV-2019City: PalmdaleCircuit: Stealth
High PV-2018City: LancasterCircuit: Pronghorn
DESI 2-2018City: Santa AnaCircuit: Titanium
Deferral-TBDCity: TBDCircuit: TBD
Deferral-2018City: Pico RiveraCircuit: Cadillac
Strategic-2019City: Ft. IrwinCircuit: TBD
4 Other Projects TBD
Deferral-2019City: Pico RiveraCircuit: Yorktown
DESIDeferralHigh PVStrategic
Strategic-2018 (Demo E)City: BridgeportCircuit: Pickle Meadows
Strategic-TBDCity: TBDCircuit: TBD
Strategic-TBDCity: TBDCircuit: TBD
Strategic-TBDCity: TBDCircuit: TBD
8 Planned Projects
Earlier SCE Battery Installations
Southern California Edison30
Tehachapi Storage Project (TSP)
Southern California Edison31
Purpose:Evaluate capability of utility-scale battery technology to
improve grid performance & assist in integration of
variable energy resources
Location: Monolith
Substation in Tehachapi, CA
Partner/Funding Source:
US Department of Energy (DOE)
Size: 8 MW/32 MWh
Completed:July, 2014
Footprint:6,300 sq. ft.
building
The area is part of the Tehachapi Wind Resource Area, currently
capable of delivering over 2,000 MW of renewable
energy
At the time of commissioning, TSP was one of
the largest battery energy
storage systems in the world
Irvine Smart Grid Demonstration (ISGD)
Southern California Edison32
Purpose : Demonstrate feeder relief
Location: At and around
the University of CA, Irvine (UCI)
Partner/Site Host:
US DOE, UCI, University Staff
Size: 2MW/ 0.5MWh
Demonstration period: Completed
as of Q3 2015
Footprint:53 foot cargo
container
The ISGDproject was an
end-to-end study of smart grid
technologies with multiple energy storage systems
Three Primary Objectives:
1. Demonstrate next generation of distributed automation
2. Optimize voltage and VAR control
3. Demonstrate next generation substation automation *SCE’s distributed battery energy storage subproject
Distribution Energy Storage Integration (DESI)
Southern California Edison33
BESS Enclosure – houses batteries
Power Conversion System – converts DC to AC power
12 kV/480 V Transformer – steps voltage up or down
Switchgear –connects to
distribution system
Communications – supports data
transfers remotely
Purpose:Support the circuit during peak loads
Location: Orange, CA
Partner/Site Host:
National Oilwell Varco Facility
System Size: 2 MW/4 MWh
Footprint: ~1,600 sq. ft. (future
footprint slightly larger)
Battery energy storage systems
are comprised of 5 main components
Grid of the Future
Distribution Power Grid of the Future
One-Way Electricity Flow• System designed to distribute electricity
from large central generating plants• Increasing penetration of distributed
energy resources• Voltage centrally maintained• Limited situational awareness and
visualization tools for power grid operators
Renewable Generation Mandates
Subsidized Residential Solar
Limited Electric Vehicle Charging Infrastructure
Variable, Two-Way Electricity Flow• Distribution system at the center of the
power grid• System designed to manage fluctuating
resources and customer demand • Digital monitoring and control devices and
advanced communications systems to improve safety and reliability, and integrate DERs
• Improved data management and power grid operations with cyber mitigation
• Modernize utility distribution planning with distributed energy resources
Maximize Distributed Resources and Electric Vehicle Adoption• Distribution power grid infrastructure
design supports customer choice and greater resiliency
Past State Future State
35
36
Remote Intelligent Switch
Remote Fault Indicators
Smart Inverters
Field Area Network
Planning Tools
Grid Management System
Common Substation Platform
Wide Area Network
Substation Automation
Technologies Required to Improve Safety and Reliability, while Preparing the System for Distributed Energy ResourceIntegration and Managing Aging Infrastructure
Central Enabling Role of the Modern Grid
36
Imagine a world where the energy that powers our lives and propels us forward is provided by the Earth’s clean resources.
This is Our Clean Energy Future…